As per case facts, a dispute arose from a development agreement concerning unutilized FSI and TDR benefits, leading to an arbitration where a majority award directed petitioners to pay compensation. ...
wp 1298 of 2026.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO.1298 OF 2026
M/s. Gagan Ace Developers and Anr. ...Petitioners
versus
M/s. Choice and Ors. … Respondents
Mr. G.S.Godbole, Sr. Advocate with Mr. Sitesh Sharma i/by Mr. Vijay
Upadhyay, for Petitioners.
Mr. Sandesh Shukla with Dr. Milind Hartalkar i/by Mr. Tejas P. Hartalkar, for
Respondent Nos.1 and 2.
CORAM: N.J.JAMADAR, J.
RESERVED ON : 4 MARCH 2026
PRONOUNCED ON : 18 MARCH 2026
JUDGMENT :
1.Rule. Rule made returnable forthwith, and, with the consent of the
learned Counsel for the parties, heard finally.
2.By this Petition under Article 227 of the Constitution of India, the
Petitioners take exception to an order dated 25 September 2025 passed by
the learned District Judge, Pune, whereby the application for stay to the
execution and operation of the award under Section 36 of the Arbitration and
Conciliation Act, 1996 (the Act, 1996) came to be partly allowed, subject to the
Petitioners – Applicants in the application under section 34 of the Act, 1996
depositing the entire award amount along with interest accrued thereon, till
the date of the deposit.
3.The background facts necessary for the determination of this Petition,
SSP 1/20 2026:BHC-AS:13526
wp 1298 of 2026.doc
can be summerized as under :
2.1The Bombay Society of Franciscan Sister of Marry (R3) – a trust
registered under the Maharashtra Public Trusts Act, 1950, was the original
owner of the large parcel of land bearing final plot No.153, situated at Village
Ghorpadi, within the limits of Pune Municipal Corporation. Respondent No.3
divided the larger land into 16 sub-plots. On 26 January 1980, Respondent
No.3 entered into a development agreement with M/s. Choice (R1), a
partnership firm, of which Atul Mahadeo Bhagat (R2) is a partner. Under the
said Development Agreement, Respondent No.1 was to construct buildings
on sub-plot Nos.13 to 15 and deliver the same to Respondent No.3 for its use
and occupation, and, thereafter, develop and construct buildings on sub-plot
Nos.1 to 8 and sell/transfer the same.
2.2Eventually, sub-plot Nos.2 and 3 and 4 to 8 were permitted to be
amalgamated. The Government of Maharashtra passed an order directing
transfer of 30% of the constructed area - residual self-contained units, to the
Government under the provisions of the Urban Lands (Ceiling and
Regulation) Act, 1976.
2.3Development commenced on amalgamated sub-plot Nos.4 to 8.
However, the development could not be completed. Further Joint Venture
Agreements and Development Agreements were entered into by Respondent
No.1 with the third parties, who are impleaded as Respondent Nos.4 to 8.
SSP 2/20
wp 1298 of 2026.doc
Despite the involvement of Respondent Nos.4 to 8 at various stages, further
development of sub-plot Nos.4 to 8 on a portion of land by consuming
unutilized FSI of about 9150 sq.ft. and the available TDR could not be carried
out. The Respondents, thus, decided to entrust the future development in
respect of the said project to the purchaser/developer interested to undertake
the same.
2.4Thus, the Respondents agreed to sell/assign unutilized potential
residual FSI of 9150 sq.ft. to be used on Plot No.5 together with entire present
and future TDR benefits accruing and arising for the entire aggregate area of
the sanctioned layout plot Nos.4 to 8 having total area 5876.4 sq. mtrs., other
benefits and residual accruals available to the said plot Nos.4 to 8 to be used
and utilized on the plot No.5 thereof, in favour of the Petitioners. Accordingly,
agreements for sale cum transfer of rights to use TDR came to be executed
between the Petitioners and the Respondents, on 17 November 2015. Under
the terms of the said agreement, the Petitioners were to develop the subject
property to the fullest extent permissible, including right to utilize TDR therein,
in accordance with the DCR and agreed to pay aggregate consideration of
Rs.15 Crores to the Respondent No.1 and Respondent Nos.4 to 8
apportionable as per their specific directions and requirements.
2.5A Deed of Confirmation came to be executed on 4 May 2017.
2.6Disputes arose between the Respondent No.1 and the Petitioners over
SSP 3/20
wp 1298 of 2026.doc
the performance of the terms of the contract between the parties, especially in
regard to the construction of Building B out of the sanctioned plan.
Respondent Nos.1 and 2 – claimants, asserted that the Petitioners carried out
construction over the lands beyond the rights granted to the Petitioners under
the Agreement dated 17 November 2015. The Petitioners erected
constructions over a portion of Plot No.6 in breach of the terms of the
Agreement dated 17 November 2015. Secondly, the claimants asserted,
Petitioners failed to comply with the conditions of the ULC order passed by
the Government of Maharashtra, and, instead, obtained a waiver by payment
of premium, and, thereby, enriched themselves at the cost of the claimants.
2.7Eventually, arbitration was invoked by the claimants. A three-member
Arbitral Tribunal came to be appointed. The Arbitral Tribunal, after appraisal
of the evidence and material, gave a split award. Hon’ble Shri Justice
S.R.Sathe (Retd.), the Presiding Arbitrator, gave a minority award, dismissing
the claim of the claimants. Mr. R.R.Deshmukh and Mr. Anurag M. Jain, Co-
Arbitrators, gave a majority award and allowed the claim of the claimants.
2.8The Petitioners (Respondent Nos.1 to 3 before the Arbitral Tribunal),
were directed to pay to the claimants an amount of Rs.7,81,18,000/- together
with interest @ 18% p.a from the date of filing of the claim till the realization.
The majority award proceeded on the premise that, by erecting constructions
over some portion of sub-plot No.6, the Petitioners committed breach of the
SSP 4/20
wp 1298 of 2026.doc
terms of the Development Agreement dated 17 November 2015. Thus, the
claimants were entitled for compensation. Placing reliance on the report of
the Architect - Commissioner, the Arbitral Tribunal recorded a finding that the
excess construction over sub-plot No.6 was to the extent of 1396.70 sq.mtrs.,
and, thus, applying the ready reckoner rate, 40% share of the claimants in the
said construction was computed at Rs.2,92,35,724/-.
2.9Secondly, the Arbitral Tribunal held, the Petitioners had no right under
the Development Agreement or the Deed of Confirmation to obtain waiver of
the conditions contemplated under the ULC order, and, thus, computed the
net value of the flats, which became available to the Petitioners for sale in the
open market, after deducting the amount of premium paid by the Petitioners
to the Government. The Arbitral Tribunal assessed 40% share of the
claimants therein at Rs.4,68,82,000/-.
2.10In addition, under the terms of the Development Agreement, the
claimants were entitled to a sum of Rs.20 Lakhs. Resultantly, the Arbitral
Tribunal proceeded to pass the award, in the aggregate sum, as noted above.
2.11The Petitioners preferred an application to set aside the award under
Section 34 of the Act, 1996, before the District Court at Pune. In the said
application, the Petitioners sought stay to the execution and operation of the
award impugned therein, by filing an application (Exh.5) under Section 36 of
the Act, 1996.
SSP 5/20
wp 1298 of 2026.doc
2.12By the impugned order, the learned District Judge was persuaded to
grant stay to the execution and operation of the award, subject to the deposit
of the entire award amount along with interest accrued thereon.
2.13Being aggrieved, the Petitioners have invoked the writ jurisdiction.
4.I have heard Mr. G.S.Godbole, learned Senior Advocate for the
Petitioners, and Mr. Shukla, learned Counsel for Respondent Nos.1 and 2, at
some length. With the assistance of the learned Counsel for the parties, I
have perused the material on record, including the arbitral award and the
impugned order.
5.Mr. Godbole, learned Senior Advocate for the Petitioners, submitted
that the learned District Judge has imposed a condition of deposit of the entire
award amount along with interest accrued thereon, in a rather mechanical
manner. Glaring infirmities in the majority award were not all adverted to by
the learned District Judge. Under no circumstances, the arbitral Tribunal
could have passed the impugned award as the claim was in the nature of
damages without proof of actual loss. The Arbitral Tribunal ventured into the
exercise of hazardous guesswork to arrive at the compensation, to which the
claimants were found entitled to. In such circumstances, the execution and
operation of the impugned award deserves to be stayed unconditionally.
6.Taking the Court through the recitals in the Development Agreement
dated 17 November 2015 and the pleadings before the Arbitral Tribunal, Mr.
SSP 6/20
wp 1298 of 2026.doc
Godbole made a strenuous effort to demonstrate that the parties fully
understood that the development of building B in accordance with the
sanctioned building plan was not possible on Plot No.5 only. The parties were
fully cognizant of the fact that a portion of Plot No.6 was required to be utilized
to exploit the full developmental potential of Plot No.4 to 8 collectively.
7.It was further submitted that, under the Development Agreement, the
claimants were not entitled to claim any share in regard to the saleable
portion which would become available for the Petitioners. As the Petitioners
had got waiver of condition to surrender units, upon payment of premium to
the State Government, and the claimants were completely divested of any
interest in the development potential of the subject property, the claimants
were not entitled to claim any share in the flats which became available to the
Petitioners, upon payment of premium to the Government.
8.In opposition to this, Mr. Shukla, learned Counsel for Respondent Nos.1
and 2 submitted that the impugned order passed by the learned District Judge
does not suffer from such legal infirmity or perversity as would warrant
interference in exercise of the supervisory jurisdiction under Article 227 of the
Constitution. The learned District Judge has dealt with the contentions raised
on behalf of the Petitioners, rather elaborately, and has recorded a justifiable
finding. Thus, the Petition does not deserve to be entertained against an
interim order which grants stay to the award subject to the condition of deposit
SSP 7/20
wp 1298 of 2026.doc
of the award amount.
9.Mr. Shukla submitted that, it is fairly well settled that, where the award
is in monetary terms, if the stay is granted to the execution and operation of
the award under Section 36 of the Act, 1996, the award-debtor shall be
required to deposit 100% of the award amount. In the case at hand, Mr.
Shukla would urge, the Petitioners have failed to make out any ‘exceptional
case’ for extending the benefit of unconditional stay to the execution and
operation of the award. Neither the award passed by the Arbitral Tribunal can
be said to be perverse, nor riddled with patent illegalities, nor ex-facie
untenable. On the contrary, Mr. Shukla would urge, all the contentions which
were sought to be urged before this court, were canvassed before the Arbitral
Tribunal and have been repelled by the Arbitral Tribunal by ascribing
sustainable reasons. To buttress these submissions, Mr. Shukla placed
reliance on an order passed by the Supreme Court in the case of Popular
Caterers V/s. Ameet Mehta and Ors.
1
.
10.At the outset, it is necessary to note that, from a bare perusal of the
material on record and the award passed by the Arbitral Tribunal, there does
not seem much controversy over the fact that the Petitioners have carried out
construction over a portion of Plot No.6. The arbitral tribunal has in terms
recorded that the Petitioners did concede that they had carried out
12025 LiveLaw (SC) 1144
SSP 8/20
wp 1298 of 2026.doc
construction over a portion of plot No.6.
11.Mr. Godbole, learned Senior Advocate for the Petitioners, submitted
that, even if the court were to proceed on the premise that the Petitioners
have carried out construction over a portion of Plot No.6, yet, that, by itself,
would not sustain the impugned award. A valiant attempt was made by Mr.
Godbole to drive home the point that the construction over a portion of Plot
No.6 was squarely in the contemplation of the parties.
12.It would be contextually relevant to note that, an endeavour was made
before the arbitral tribunal to show that the Development Agreement dated 17
November 2015 and the Deed of Confirmation dated 4 May 2017 did not
reflect the real intent of the parties. It was also sought to be contended that
there was an inadvertence error in recording the terms of the contract in the
said instruments.
13.It is well recognized that the intent of the parties to a commercial
contract is required to be ascertained from the words employed by the parties
in the agreement and the express terms thereof. It is impermissible for the
Courts to construe or make a new contract for the parties. Therefore, the
submission that the terms of the bargain between the parties as incorporated
in the Development Agreement dated 17 November 2015 and the Deed of
Confirmation dated 4 May 2017, did not reflect the real intent of the parties,
cannot be readily acceded to.
SSP 9/20
wp 1298 of 2026.doc
14.Schedule II to the Development Agreement dated 17 November 2015
makes it abundantly clear that the said agreement was in respect of unutilized
potential residual FSI of 9150 sq.ft. usable on plot No.5 together with TDR
benefits accuring upon the sanctioned layout plot Nos.4 to 8 having total area
as per Property Card admeasuring 5876.4 sq. mtrs.
15.The following recitals in the Development Agreement also deserve to
be noted :
“AND WHEREAS pursuant to mutual negotiations,
the owners, erstwhile Developers / Stakeholder and
the Consenting Party have now agreed to sell /
assign the unutilized potential residual FSI of 9150
sq. ft. to be used on Plot No.5 together with entire
present and future TDR benefits accruing and arising
for the entire aggregate area of the sanctioned layout
plot Nos.4 to 8 having total area 5876.4 sq. mtrs.
Other benefits and residual accruals available to the
said plot Nos.4 to 8 to be used and utilized on the plot
No.5 thereof and more particularly described in
Schedule II hereunder and hereinafter referred to as
the “said Property.
………..
AND WHEREAS, the Purchaser / developer further
represented that if shall comply with the orders of the
ULC and shall allot and grant the balance unallotted
flats as per list above remained to be allotted under
SSP 10/20
wp 1298 of 2026.doc
the said ULC order.”
16.The intent of the parties, as is evincible from the description of the
property in Schedule II and the aforesaid recitals, prima facie, appears to be
that, the Development Agreement was confined to Plot No.5, though TDR
benefits accruing upon the sanctioned layout Plot Nos.4 to 8 were also to be
utilized on the said Plot No.5. The Deed of Confirmation dated 4 May 2017,
in a sense, seals the issue. The relevant covenant in the said Deed of
Confirmation reads as under :
“It is made absolutely clear that this Deed does not
confer upon the Purchasers / Developers any right to
make any construction of any nature whatsoever on
any plot other than Plot No.5 on which, however, the
Owners / Developers can exploit and use the entire
residual potential & TDR of Plot Nos.4 to 8 in terms of
the Agreement dated 17 November 2015.”
17. Keeping in view the aforesaid contractual stipulations and rather
incontrovertible position that the Petitioners have erected construction over a
portion of Plot No.6, the justifiability of the impugned order granting stay to the
execution and operation of the award of the Arbitral Tribunal, deserves to be
decided. The provisions contained in Section 36 of the Act, 1996, on the
touchstone of which the legality and correctness of the impugned order
deserve to be evaluated, read as under :
SSP 11/20
wp 1298 of 2026.doc
“36.Enforcement – (1)……..
(2)Where an application to set aside the arbitral award
has been filed in the Court under section 34, the filing of
such an application shall not by itself render that award
unenforceable, unless the Court grants an order of stay of
the operation of the said arbitral award in accordance with
the provisions of sub-section (3), on a separate application
made for that purpose.
(3)Upon filing of an application under sub-section (2) for
stay of the operation of the arbitral award, the Court may,
subject to such conditions as it may deem fit, grant stay of
the operation of such award for reasons to be recorded in
writing :
Provided that the Court shall, while considering the
application for grant of stay in the case of an arbitral award
for payment of money, have due regard to the provisions of
grant of stay of a money decree under the provisions of the
Code of Civil Procedure, 1908.
Provided further that where the Court is satisfied that
a prima facie case is made out that, -
(a)the arbitration agreement or contract which is
the basis of the award; or
(b)the making of the award,
was induced or effected by fraud or corruption, it shall
stay the award unconditionally pending disposal of the
challenge under section 34 to the award.”
18.A plain reading of the aforesaid provisions would indicate that the filing
of an application under section 34 of the Act, 1996 shall not, by itself, operate
SSP 12/20
wp 1298 of 2026.doc
as a stay to the enforcement of the arbitral award. In the event, an application
for stay to the award is filed, in such an application under Section 34 of the
Act, 1996 the Court has discretion to grant stay, which may be subject to such
conditions as it may deem fit. However, while granting stay to the arbitral
award, the Court shall have “due regard to the provisions of the Code of Civil
Procedure, 1908” for grant of stay of money decree. If a case falls within the
ambit of the second proviso to sub-section (3) of Section 36, it is mandatory
for the court to say the award unconditionally. For that, the Court has to
record a prima facie satisfaction that, either arbitral agreement or contract
which is the basis of the award, or the making of the award was induced or
effected by fraud or corruption. If that is not the ground of challenge to the
arbitral award, the case would fall within the ambit of the first proviso and then
the Court is expected to have due regard to the provisions of the Code, for
grant of stay of money decree.
19.In the case of Pam Developments Pvt. Ltd. V/s. State of West
Bengal
2
, the Supreme Court has clarified that the phrase ‘have due regard to
the provisions for grant of stay to the money decree’ under the provisions of
the Code, 1908, does not imply that the court is enjoined to determine an
application for stay of an arbitral award for payment of money ‘in accordance
with the provisions of the Code’. The said expression, therefore, does not
2(2019) 8 SCC 112
SSP 13/20
wp 1298 of 2026.doc
partake the character of a legislative edict, but operates as a guiding principle.
The observations of the Supreme Court in paragraph No.20 are instructive,
and, hence, extracted below :
“20.In our view, in the present context, the phrase used is
‘having regard to’ the provisions of CPC and not ‘in
accordance with” the provisions of CPC. In the latter case, it
would have been mandatory, but in the form as mentioned in
Rule 36(3) of the Arbitration Act, it would only be directory or
as a guiding factor. Mere reference to CPC in the said
Section 36 cannot be construed in such a manner that it
takes away the power conferred in the main statute (i.e.
Arbitration Act) itself. It is to be taken as a general guideline,
which will not make the main provision of the Arbitration Act
inapplicable. The provisions of CPC are to be followed as a
guidance, whereas the provisions of the Arbitration Act are
essentially to be first applied. Since, the Arbitration Act is a
self-contained Act, the provisions of the CPC will apply only
insofar as the same are not inconsistent with the spirit and
provisions of the Arbitration Act.” (emphasis supplied)
20. If the Courts under Section 34 of the Act, 1996 were to have due
regard to the provisions of the Code in regard to the grant of stay of a money
decree, the three-pod requirements under the provisions of Order XVI Rule
5(3) need to be kept in view, namely, (i) whether the applicant would suffer
substantial loss, if stay is declined; (ii) whether the application suffers from
unreasonable delay; (iii) whether security has been furnished by the applicant
SSP 14/20
wp 1298 of 2026.doc
to satisfy the decree.
21.A profitable reference in this context can be made to a judgment of the
Supreme Court in the case of Lifestyle Equities C.V. and Anr. V/s. Amazon
Technologies Inc.
3
, wherein after an elaborate analysis of the provisions and
the precedents, including the implication of the provisions contained in
Section 36 of the Act, 1996, though the said case did not arise out of an
arbitral award, the Supreme Court culled out the principles in paragraph
No.134. The relevant propositions read as under :
“134…..
(VIII)For the grant of benefit of an unconditional stay of
execution of a decree, an exceptional case has to be made
out before the appellate court. This discretion of the
appellate court to grant an unconditional stay of execution of
decree must not be exercised arbitrarily. It must be
exercised sparingly and only if an exceptional case is made
out for such stay in view of the peculiar facts and attending
circumstances of the case before it.
(IX) A lodestar for bringing a case within the purview of
“exceptional case” for the purpose of granting benefit of
unconditional stay of the execution of money decree by the
appellate court would be, if the money decree in question: -
(i) is egregiously perverse;
(ii) is riddled with patent illegalities;
(iii) is facially untenable; and/or
(iv) such other exceptional causes similar in nature.
(X) For the purpose of the grant or refusal of stay of
32025 SCC Online SC 2153
SSP 15/20
wp 1298 of 2026.doc
execution of the decree under Rule 5 of Order XLI, it is
immaterial whether the decree is a money decree or any
other decree. The language couched in the said provision is
very clear. Order XLI, Rule 5 of the makes no distinction
between a money decree and other decrees, and the said
provision applies with full rigour in both instances. Yet as a
rule of prudence and established practice evolved over a
period of time, no stay of execution of a money decree
should be granted, except on the condition that the decretal
amount be deposited in the court. However, such condition
for deposit cannot be said to be mandatory and non-
prescription thereof does not operate as a bar to staying the
execution of a money decree.”(emphasis supplied)
22.In the case of Popular Caterers (supra), on which reliance was placed
by Mr. Shukla, the Supreme Court has again emphasised that, while granting
unconditional stay to the execution of the arbitral award, the High Court
should have posed unto itself a question, whether the award-debtors could be
said to have made out an exceptional case, for the purpose of granting benefit
of unconditional stay of the execution of the award, which is in the form of a
money-decree. A reference was made to the propositions enunciated in
Lifestyle Equities (supra).
23.Whether the Petitioners have succeeded in making out an exceptional
case of the nature, illustratively expounded in the case of Lifestyle Equities
(supra), is the moot question ? As noted above, there is not much
SSP 16/20
wp 1298 of 2026.doc
controversy over the first component of the claim, namely, the erection of
construction over the portion of Plot No.6. On the second component of the
claim premised on the availability of the flats, which were to be surrendered to
the Government by the Petitioners, upon obtaining a waiver of the said
condition, the facts that such waiver has been obtained, albeit upon payment
of premium, and, those flats became available for free sale, are also not much
in contest.
24.In the Development Agreement (extracted above), the Petitioners had
specifically represented that the Petitioners shall comply with the orders of
ULC and shall allot and grant the balance unallotted flats under the said ULC
order. Recitals in the development agreement further record that the
Petitioners had a right to sell – transfer the units to be developed on the
subject properties (excluding the units allocable under the order of exemption
under ULC). In this backdrop, the Arbitral Tribunal has recorded a finding
that, neither under the Development Agreement nor under the Deed of
Confirmation, the Petitioners were given a right and option to obtain a waiver
of the condition under ULC order and, thus, the said action of the Petitioners
was beyond the scope of the Development Agreement.
25.Prima facie, the aforesaid finding is borne out by the contractual
instruments between the parties. The legality and validity of the award based
on the aforesaid findings would be examined by the District Court on the well
SSP 17/20
wp 1298 of 2026.doc
recognized parameters for setting aside the arbitral award. However, it cannot
be said that the arbitral award is egregiously perverse on the said count.
26.The thrust of the submission of Mr. Godbole was that the arbitral award
suffers from the patent illegality as it awards a claim for damages without
actual proof of loss. Reliance was placed on an order of this Court in the
case of Alkem Laboratories Ltd. V/s. Issar Pharmaceuticals Pvt. Ltd.
4
,
wherein a prima facie view was recorded that the arbitral award in the said
case suffered from perversity as well as patent illegalities as the learned
Arbitrator therein had ignored the settled law that in regard to the claim for
damages actual loss was required to be proved.
27.I have perused the arbitral award to ascertain, albeit prima facie,
whether the arbitral award suffers from patent illegality and perversity which
stares in the face. The fulcrum of the Petitioners’ contention is that the
compensation was awarded by the Arbitral Tribunal sans evidence of actual
loss. Primarily, two pieces of material were considered by the arbitral tribunal.
First, the report of Architect – Commissioner indicating the area of excess
construction and, second, the value of the construction as per the ready
reckoner rate. First is rather an objective fact. The second is in public
domain.
28.At this stage, while the challenge to the arbitral award awaits
4IA 377 of 2024 in Comm. Arb. Petition No.389 of 2023 dt. 5 Feb. 2024
SSP 18/20
wp 1298 of 2026.doc
determination by the District court, this Court does not consider it appropriate
to delve more on this aspect of the matter. Suffice to note that the
consideration of the aforesaid material, prima facie, does not appear to be an
exercise riddled with patent illegality or perversity.
29.The conspectus of aforesaid consideration is that the Petitioners cannot
be said to have succeeded in making out an exceptional case. Nor could it be
demonstrated that the Petitioners would suffer a substantial loss if the
execution of the award is not stayed. The fact that the Petitioners have
suffered an arbitral award, which directs payment, by itself, cannot be
construed as a substantial loss. Nor there is material to show that the
Petitioners have given adequate security for the due performance of the
arbitral award. Thus, viewed from any perspective, no case for grant of
unconditional stay was made out. Resultantly, the learned District Judge
cannot be said to have committed any error in the exercise of discretion in
granting stay to the execution of the award upon deposit of the award amount.
The Writ Petition, therefore, deserves to be dismissed.
30.Hence, the following order :
ORDER
(i)The Writ Petition stands dismissed.
(ii)Rule discharged.
(iii)By way of abundant caution, it is clarified that the consideration is
SSP 19/20
wp 1298 of 2026.doc
confined to test the legality, propriety and correctness of the impugned order
and this court may not be understood to have expressed any opinion on the
merits of the application under Section 34 of the Arbitration Act, 1996 and the
District Court shall decide the same on its own merits and in accordance with
law, without being influenced by any of the aforesaid observations.
(iv)No costs.
( N.J.JAMADAR, J. )
SSP 20/20
Legal Notes
Add a Note....