As per case facts, a construction contract awarded to the appellant was terminated, leading to a writ petition challenging the termination. The Single Judge dismissed the petition, noting no irregularity ...
2026 INSC 976 1
[REPORTABLE ]
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. OF 2026
(@ SPECIAL LEAVE PETITION (CIVIL) NO. 7338 OF 2026)
M/s. GVV Constructions
Private Limited … Appellant
Versus
The Union of India & Ors. … Respondents
J U D G M E N T
Alok Aradhe, J.
1. Leave granted.
2. This appeal takes exception to the judgment dated 16.12.2025
passed by the Division Bench of the High Court for the State of
Telangana at Hyderabad.
FACTS
3. The facts leading to the filing of the present appeal may be stated
briefly. The appellant is a private limited company and is engaged
in construction and infrastructure works. On 21.02.2017, South
Central Railway namely, respondent no. 2 invited tenders for the
work of “Doubling of track between Guntur-Guntakal Section-
Earthwork in formation including blanketing to GE: 0014
2
specifications, construction of bridges, RUBs for LCs and other
miscellaneous works….” (‘Work’). In response to the aforesaid
tender, the appellant submitted its bid. The appellant’s bid was
accepted, and on 30.11.2017, a formal Contract Agreement was
executed stipulating the due date of completion of the Work as
23.10.2018.
4. On 10.06.2022, the said contract was terminated under Clause
62 of Indian Railways Standard General Conditions of Contract
(‘GCC’) and the performance guarantee and security furnished
by the appellant were also forfeited. Further, the appellant was
held to be disentitled to any compensation for any loss.
5. The appellant sought quashing of the aforesaid order of
termination in a writ petition inter alia on the ground that the
same is in contravention of the procedure laid down under GCC
and sought a consequential direction to respondents to follow
Clause 17 of the GCC. The learned Single Judge by an order
dated 18.10.2022, dismissed the writ petition inter alia on the
ground that serious and complicated questions of fact were not
amenable to adjudication under Article 226 of the Constitution
of India. In paragraph 35 of the order, the learned Single Judge
further held that since the appellant had already invoked the
3
arbitration clause by filing an arbitration petition it could take
all its defences before the Arbitral Tribunal. However, it was also
recorded as a finding that there existed no irregularity in the
order of termination of contract.
6. Being aggrieved, the appellant preferred an appeal. The Division
Bench of the High Court vide its judgment dated 16.12.2025,
held that the finding recorded by the learned Single Judge that
the contract of the appellant had been validly terminated, was
without assigning any reason. It was further held that if the
validity of the order of termination of contract is upheld, there
would be no scope left for the Arbitral Tribunal or any other
forum to decide the dispute in favour of the appellant. The
Division Bench accordingly set aside the finding contained in
paragraph 35 of the order of the learned Single Judge which
stated that there exists no irregularity in termination of the
contract of the appellant. The appellant was granted the liberty
to raise all its claims before the Arbitral Tribunal, which in turn
was granted the liberty to decide the claims of the appellant
strictly in accordance with the terms of the contract agreed upon
between the parties. The Division Bench clarified that the
Arbitral Tribunal shall take a decision in accordance with law
4
without being influenced by the observations made either by it
or by the learned Single Judge.
7. In pursuance of the order passed by the Division Bench of the
High Court, a former judge of this Court was appointed as the
Sole Arbitrator and arbitration proceedings commenced on
20.01.2026. The Arbitral Tribunal framed twelve issues
including the issue of the validity of the order of termination
dated 10.06.2022 and the question whether any claims are
barred by limitation or fall under “excepted matters” or are not
otherwise arbitrable.
SUBMISSIONS
8. Mr. Gaurav Agarwal, learned senior counsel for the appellant
submitted that the reasons for delay in completion of the Work
were not attributable to the appellant. It was contended that the
contract was illegally terminated. It was pointed out that
respondents themselves admitted in paragraph 1 of the counter
affidavit filed in the writ petition, that the same is not
maintainable, as appellant has an effective and alternative
remedy of arbitration. Therefore, the respondents cannot now
turn around and dispute that the issue of termination of contract
cannot be decided by the Arbitral Tribunal. It was urged that the
5
only grievance of the appellant in the present appeal pertains to
the direction issued by the Division Bench to the Arbitra l
Tribunal to decide all claims of the appellant in accordance with
the terms of the contract agreed upon by the parties. It was
contended that the issue of the illegal termination of the contract
is directly and intrinsically linked with all other issues pending
before the Arbitral Tribunal and, therefore, it should be permitted
to decide the issue of termination of contract as well. It was
submitted that the impugned direction is contrary to the decision
of this Court in ABS Marine Services v. Andaman and Nicobar
Administration
1
.
9. Mr. Vikramjit Banerjee, learned Additional Solicitor General,
submitted that appellant by seeking to submit the issue of
validity of termination of contract to arbitration is acting in direct
violation of Clause 63 of GCC which was signed and accepted by
both the parties. It was further submitted that exclusion of
validity of termination of the contract from the scope of
arbitration does not prevent the appellant from approaching the
civil court which is the designated forum for “excepted matters”.
It was contended that the reliance placed on the decision of this
1
2026 SCC OnLine SC 460.
6
Court in ABS Marine Services (supra), is misplaced as the
clauses in GCC are different from the Clause struck down by this
Court in the said decision. It was urged that the Arbitral Tribunal
has no jurisdiction over “excepted matters” under the GCC and
the impugned judgment does not call for any interference in this
appeal. In support of the aforesaid submissions, reliance has
been placed on the decisions of this Court in General Manager,
Northern Railway and Another
2
v. Sarvesh Chopra and
Harsha Constructions v. Union of India and Others
3
.
ANALYSIS
10. We have carefully considered the rival submissions advanced by
the learned counsel for the respective parties and have perused
the record.
ISSUE
11. The solitary issue which arises for consideration in this appeal is
whether the observation of the Division Bench that “the
Arbitrator is at liberty to decide the claim of the appellant strictly
in accordance with the terms of the contract agreed upon
between the parties”, travels beyond the scope of the jurisdiction
of a court exercising power of judicial review under Article 226 of
2
(2002) 4 SCC 45.
3
(2014) 9 SCC 246.
7
the Constitution of India and impinges upon the jurisdiction of
the Arbitral Tribunal under Section 16 of the Arbitration and
Conciliation Act, 1996 (‘Act’).
RELEVANT CLAUSES OF THE AGREEMENT
12. Before proceeding to deal with the issue, it is apposite to take
note of Clause 63 and relevant parts of Clause 64 of the GCC :-
“63. Matters Finally Determined By The
Railway: All disputes and differences of any kind
whatsoever arising out of or in connection with
the contract, whether during the progress of the
work or after its completion and whether before
or after the determination of the contract, shall
be referred by the contractor to the GM and the
GM shall, within 120 days after receipt of the
contractor’s representation, make and notify
decisions on all matters referred to by the
contractor in writing provided that matters for
which provision has been made in Clauses 8,
18, 22(5), 39, 43(2), 45(a), 55, 55-A(5), 57,
57A, 61(1), 61(2) and 62(1) to (xiii)(B) of
Standard General Conditions of Contract or
in any Clause of the Special Conditions of the
Contract shall be deemed as ‘excepted
matters’ (matters not arbit rable) and
decisions of the Railway authority, thereon
shall be final and binding on the contractor;
provided further that ‘excepted matters’
shall stand specifically excluded from the
purview of the Arbitration Clause.
64.(1) Demand for Arbitration
8
64.(1)(i) In the event of any dispute or difference
between the parties hereto as to the
construction or operation of this contract, or the
respective rights and liability of the parties on
any matter in question, dispute or difference on
any account or as to the withholding by the
Railway of any certificate to which the
contractor may claim to be entitled to, or if the
Railway fails to make a decision within 120
days, then and in any such case, but except in
any of the “excepted matters” referred to in
Clause 63 of these conditions, the contractor,
after 120 days but within 180 days of his
presenting his final claim on disputed matters
shall demand in writing that the dispute or
difference be referred to arbitration.
64.(1)(ii) The demand for arbitration shall
specify the matters which are in question, or
subject of the dispute or difference as also the
amount of claim item-wise. Only such dispute(s)
or difference(s) in respect of which the demand
has been made, together with counter claims or
set off, given by the Railway, shall be referred to
arbitration and other matters shall not be
including in the reference.”
Thus, a conjoint reading of Clause 63 and relevant part of Clause
64 of the GCC, makes it clear that Clause 63 only excludes the
excepted matters from the purview of the Arbitration Clause but
does not exclude the jurisdiction of the Court of Law to examine
the validity of the decision taken in respect of excepted matters.
THE ARBITRATION AND CONCILIATION ACT, 1996
13. The Act is modelled on the UNCITRAL Model Law and is intended
to bring the domestic as well as International Commercial
9
Arbitration in consonance with the UNCITRAL Model, the New
York Convention and the Geneva Convention, as has been held
by a three-Judge Bench of this Court in Chloro Controls India
Pvt. Ltd. v. Severn Trent Water Purification Inc. & Ors.
4
Section 5 of the Act prescribes the extent of judicial intervention
and begins with a non-obstante clause and mandates that “no
judicial authority shall intervene except where so provided in this
part”. Section 16(1) of the Act empowers the Arbitral Tribunal to
rule on its jurisdiction “including ruling on any objections with
respect to existence or validity of the arbitration agreement”.
Section 16 incorporates the principle of kompetenz-kompetenz,
which lies at the foundation of the Act and makes a decisive
departure from the preceding statutory regime contained in the
Arbitration Act, 1940.
PERMISSIBLE EXTENT OF JUDICIAL SCRUTINY PRIOR OR
AT THE STAGE OF REFERENCE OF DISPUTE
14. The extent of judicial scrutiny permissible even at the stage
anterior to appointment of an Arbitrator or at the stage of
appointment of an Arbitrator under Section 11 of the Act has
travelled through four distinct phases each marking a
4
(2013) 1 SCC 641.
10
progressively narrower conception of the Court’s role,
culminating in the position that holds the field today. In Konkan
Railway Corpn. Ltd. & Ors. v. Mehul Construction Co .
5
,
reaffirmed by a Constitution Bench in Konkan Railway Corpn.
Ltd. v. Rani Construction (P) Ltd.
6
, this Court characterised the
power of appointment under Section 11(6) as purely
administrative, leaving every contested question, including the
existence of the agreement and arbitrability, to the Arbitral
Tribunal under Section 16. The aforesaid view was overruled by
a seven-Judge Bench in SBP & Co. v. Patel Engineering. Ltd.
and Another
7
, wherein it was held the power to be judicial,
requiring the court, at the referral stage, to decide, amongst other
things, the existence of a valid arbitration agreement. This view
was refined in National Insurance Co. Ltd. v. Boghara Polyfab
(P) Ltd.
8
, which classified the issues arising on a Section 11
application into three categories, of which “Category III” issues,
namely whether the claim made falls within the arbitration
clause, illustratively including “a matter which is reserved for the
final decision of a departmental authority and excepted or
5
(2000) 7 SCC 201.
6
(2002) 2 SCC 388.
7
(2005) 8 SCC 618.
8
(2009) 1 SCC 267.
11
excluded from arbitration”, were held to be decided by the
Arbitral Tribunal alone, and not by the referral court.
15. The Arbitration and Conciliation (Amendment) Act, 2015, on the
basis of the recommendations contained in the 246
th Report of
the Law Commission of India, inserted Section 11(6A)
9
in the Act,
by which the scope of examination by the Court,
“notwithstanding any judgment, decree or order of any Court”, is
confined, at the stage of appointment, to the existence of the
arbitration agreement. In Duro Felguera, S.A. v. Gangavaram
Port Ltd.
10
, this Court applied the amended provision literally,
holding that the referral court is only required to examine “if an
arbitration agreement exists, nothing more, nothing less”. A
three-Judge Bench of this Court in Mayavati Trading (P) Ltd. v.
Pradyuat Deb Burman
11
, held that Section 11(6A) legislatively
overruled the wider scrutiny contemplated by SBP & Co. and
Boghara Polyfab (supra).
16. Another three-Judge Bench of this Court in Vidya Drolia and
Others v. Durga Trading Corp oration
12
, harmonised the
standard of review under Sections 8 and 11 of the Act and held
9
Sub-section (6A) omitted by Act 33 of 2019, sec 3(v) [Date of enforcement yet to be notified.]
10
(2017) 9 SCC 729.
11
(2019) 8 SCC 714.
12
(2021) 2 SCC 1.
12
that a court should decline reference only where it is manifestly
and ex facie certain that the arbitration agreement is non-
existent, invalid, or that the dispute is non-arbitrable; short of
that, the governing maxim is “when in doubt, do refer.” This “eye
of the needle” standard has since been applied consistently, in
subsequent decisions by this Court in Uttarakhand Purv Sainik
Kalyan Nigam Ltd. v. Northern Coal Field Ltd.
13
(holding that
limitation, being a mixed question of fact and law bound up with
the Tribunal’s Section 16 jurisdiction, is ordinarily for the
Arbitral Tribunal) and in In Re: Interplay Between Arbitration
Agreements and the Indian Stamp Act, 1899
14
(holding by a
seven-Judge Bench, that even insufficiency of stamping is a
curable, evidentiary question for the Tribunal, and thus
overruling N.N. Global Mercantile (P) Ltd. v. Indo Unique
Flame Ltd.)
15
.
17. A three-Judge Bench of this Court in SBI General Insurance
Company Ltd. v. Krish Spinning
16
, in paragraph 114 held as
follows,
“The use of the term “examination” under Section 11(6-
A) as distinguished from the use of the term “rule”
13
(2020) 2 SCC 455.
14
(2024) 6 SCC 1.
15
(2023) 7 SCC 1 (overruled).
16
(2024) 12 SCC 1.
13
under Section 16 implies that the scope of enquiry
under Section 11(6-A) is limited to a prima facie
scrutiny of the existence of the arbitration agreement,
and does not include a contested or laborious enquiry,
which is left for the Arbitral Tribunal to “rule” under
Section 16. The prima facie view on existence of the
arbitration agreement taken by the Referral Court does
not bind either the Arbitral Tribunal or the Court
enforcing the arbitral award.”
This view was reiterated by a two-Judge Bench of this Court in
Office for Alternative Architecture v. Ircon Infrastructure
and Services Ltd.
17
18. What emerges from the foregoing survey is that, under the Act,
the question whether a particular claim is covered by, or falls
outside, an “excepted matters” clause of a works contract is a
matter squarely within the competence of the Arbitral Tribunal
under Section 16, and not a question for a court exercising even
the wider, appointment-stage jurisdiction under Section 11,
much less for a court exercising the discretionary jurisdiction of
judicial review under Article 226 of the Constitution, whose very
engagement with the merits of the dispute, in the present case,
was declined on the ground that it involved complicated
questions of fact.
17
2025 SCC OnLine SC 1098.
14
19. If a court exercising the power of appointment under Section
11(6A) has no jurisdiction to enter upon, still less to pre-
determine, the touchstone by reference to which the Arbitral
Tribunal is to adjudicate a claim said to fall within an “excepted
matters” clause, a writ appellate court, whose task was confined
to testing the correctness of the learned Single Judge’s disposal
of a writ petition impugning a termination notice, had, by parity
of reasoning and a fortiori, no such jurisdiction. The direction
that the Arbitrator “is at liberty to decide the claim of the
appellant strictly in accordance with the terms of the contract
agreed upon between the parties”, whatever the intention behind
it, has the inevitable effect of circumscribing the width of the
Arbitrator’s enquiry, including his authority under Section 16 to
rule upon the scope of his own jurisdiction over the dispute
relating to termination.
20. Whether the dispute regarding termination is, in whole or in part,
an “excepted matter” outside the Arbitrator's jurisdiction, and, if
so, what remedy survives to the appellant in that behalf, are
questions that Section 16 of the Act commits to the Arbitrator in
the first instance. It was not open to the Division Bench, in the
exercise of its writ appellate jurisdiction, to prescribe in advance
15
the manner of, or to place constraints upon, that adjudication.
For yet another reason, the Division Bench ought not to have
made such an observation as the issue of arbitrability of
termination of agreement was not an issue before it. Accordingly,
the issue is answered.
21. Insofar as reliance placed by the appellant on ABS Marine
Services (supra) is concerned, suffice it to say that same has no
application to the fact situation of the case, as Clauses 3.20 of
the said case and 63 of GCC in the instant case are differently
worded. Clause 3.20 in ABS Marine Services (supra) ousts the
jurisdiction of any court of law and prohibits arbitration
proceedings as well, whereas in the instant case, Clause 63 does
not bar the jurisdiction of the court but only puts the excepted
matters beyond the scope of arbitration. As far as the reliance
placed by the respondents on General Manager Northern
Railway (supra) is concerned, same is of no assistance to them
in the facts of the present case for the reason, that in the said
case, this Court dealt with Section 20 of the Arbitration Act, 1940
and the provisions of the Act make a decisive departure from the
previous statutory regime.
16
CONCLUSION
22. For the foregoing reasons, it is clarified that the direction issued
by the Division Bench to the Arbitrator to decide all claims of the
appellant strictly in accordance with the terms of the contract
agreed upon between the parties shall not be construed to
impinge upon the jurisdiction of the Arbitral Tribunal, to
adjudicate the dispute with regard to termination of contract. It
is clarified that this Court has not expressed any opinion on the
merits of the case.
23. In the result, the appeal is disposed of. There shall be no order
as to costs.
24. Pending applications, if any, shall stand disposed of.
……………..……………………………….J.
[PAMIDIGHANTAM SRI NARASIMHA]
…….…………………………………………J.
[ALOK ARADHE]
NEW DELHI;
SEPTEMBER 08, 2026.
Legal Notes
Add a Note....