As per case facts, the Petitioner, a private limited company, had an electrical connection which faced a breakdown due to a blast in its metering unit. After rectification, authorities conducted ...
2026 INSC 851 SLP (C) No.33179 of 2025 Page 1 of 32
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
SPECIAL LEAVE PETITION (CIVIL) NO(S). 33179 OF 2025
M/S. HIMADRI STEEL
PVT.LTD. … PETITIONER(S)
VERSUS
JHARKHAND URJA VIKAS NIGAM
LIMITED & ORS. … RESPONDENT (S)
J U D G M E N T
ARAVIND KUMAR, J.
CONSPECTUS
1. The Petitioner is a private limited company incorporated under
the relevant provisions of Companies Act, 1956. It was granted
electrical connection under HTSS (High Tension Special
Service) Tariff with contract demand of 3000 KVA which was
energized on 03.07.2006. On account of blast in the cubical
metering unit there was electricity breakdown in the
SLP (C) No.33179 of 2025 Page 2 of 32
petitioner’s premises which was rectified on 16.06.2017 by a
team of the Respondent Nigam’s officials and a report was
prepared. The report recorded that the metering unit chamber
was slightly damaged, K-Phase CT and all PT were found in
proper condition (written as OK), meter reading was correct
and there proper sealing, however, b-phase CT which was
totally cracked and damaged was replaced.
2. Authorities visited the petitioner’s premises on 26.09.2017 and
inspected the check meter installed by them and also inspected
the metering cubical installed. Further, they prepared an
inspection report dt. 26.09.2017.
3. On the strength of the written report of the Assistant Electrical
Engineer, Chakulia PS Case No. 30 / 2017 u/Ss. 379 / 420 / 353
IPC and u/Ss. 135 / 137 / 138 of the Electricity Act, 2003 was
lodged. The next day, the respondents disconnected the
electrical connection.
4. On 29.09.2017, the Respondents issued a Provisional
Assessment Order determining a liability of Rs. 3,23,71,524/-
towards loss caused due to theft of electricity as per Section
125 of the Act in accordance with the provisions of the
Electricity Act, 2003 and applicable regulations, based on the
inspection findings and relevant consumption data.
SLP (C) No.33179 of 2025 Page 3 of 32
5. The Petitioner ended up filing a Writ Petition (C) No. 6054 /
2017 before the High Court of Jharkhand, challenging the
Provisional Assessment Order and contending that the
Respondents had illegally disconnected the electrical
connection of the petitioner on 27.09.2017 on mere suspicion
of theft of electricity, in absolute contravention of the specific
provisions of the Electricity Act, 2003 as well as Clause 11.12
Jharkhand (Electricity Supply Code) Regulations, 2015
(hereinafter referred to as “the Regulations”) issued by the
Jharkhand State Electricity Regulatory Commission.
6. The said Writ Petition was allowed by the Ld. Single Judge
vide order dt. 05.09.2018 and the Provisional Assessment
Order was quashed. It was held that the inspection report did
not disclose conclusive evidence of theft of electricity.
7. Against the order of the Ld. Single Judge, the Respondents
filed LPA No. 648 / 2018 and in the said LPA, the Ld. Division
Bench allowed the LPA and set aside the order of the Single
Judge vide order dt. 08.08.2025, holding that the inspection
report disclosed sufficient material and that the statutory
mechanism under the Electricity Act is a complete code and
the Writ Petition was not maintainable in view of the
SLP (C) No.33179 of 2025 Page 4 of 32
alternative remedy available to the Petitioner. It is against this
order that the petitioners are before us.
SUBMISSIONS OF THE PETITIONER
8. The submissions of the Petitioner/ Electricity Consumer are as
follows:
a. That the inspection report dt. 26.09.2017 neither makes
any averment regarding the alleged “theft of electricity”,
nor does it record the satisfaction of the assessing officer
on “theft of electricity”.
b. The conclusion in the report that “further action will be
taken as per norms” is too vague and gives wide discretion
to respondents to twist the facts.
c. The inspection report does not allege “theft of electricity”
and the respondents are trying to build this claim as per
FIR.
d. During the detailed inspection by the authorities of the
petitioner’s premises, they found no irregularity or
disturbance in the check meter or the metering cubical
which may lead to evidence of theft. All the seals were
found intact and there had been no interference in any
manner with the entire metering arrangement.
SLP (C) No.33179 of 2025 Page 5 of 32
e. If at all there was any evidence of theft, they would have
mentioned that in the inspection report concluding that
there has been a theft of electricity and then they would
have mandatorily disconnected the electricity connection.
However, the inspecting team after the conclusion of
inspection restored the power supply and left the premises
saying that the metering cubicle is very old and it needs to
be replaced.
f. In the absence of direct evidence of theft of electricity, the
penalty cannot be imposed on the petitioner.
g. Subjective satisfaction of the officer based on evidence or
material collected during inspection is mandatory for
initiating proceedings for “suspected theft of electricity”,
or “unauthorized use of electricity” or “theft of
electricity”. In absence thereof, subsequent registration of
FIR or issuance of Provisional Assessment Order, which
is based on Inspection Report would be wholly without
jurisdiction.
SUBMISSIONS OF THE RESPONDENTS
9. The submissions of the Respondents / Jharkhand Urja Vikas
Nigam Ltd. are as follows:
SLP (C) No.33179 of 2025 Page 6 of 32
a. That the SLP ought to be dismissed at the threshold as the
petitioner has consciously bypassed the remedy u/Ss. 126
and 127 of the Electricity Act which provide a complete
and self - contained mechanism for assessment,
adjudication, filing of objections and appeal and in such a
case, no Writ Petition should have been entertained.
b. Under the Electricity Act, an inspection report is only
required to disclose prima facie material indicating
unauthorized use or theft of electricity, and there is no
requirement that such report must record a conclusive
finding at the stage of inspection.
c. Proceedings u/S. 126 of the Electricity Act, 2003 are civil
in nature and operate independently of criminal
prosecution under S. 135 and it is well-settled that
assessment for unauthorized use and criminal liability for
theft are distinct and can proceed simultaneously. In the
present case, clear jurisdictional facts existed in asmuch
as the inspection report dt. 26.09.2017 disclosed material
irregularities in the metering system enabling
unauthorized abstraction of electricity, thereby validly
conferring jurisdiction upon the Respondents to initiate
proceedings.
SLP (C) No.33179 of 2025 Page 7 of 32
LEGAL POSITION
10. We have heard the parties and thoroughly perused the record.
Before proceeding with the case, we would like to discuss the
Electricity Act, 2003 first.
11. As the Title of the Act states, it is an act to consolidate the laws
relating to generation, transmission, distribution, trading and
use of electricity and generally for taking measures conducive
to development of electricity industry, promoting competition
therein, protecting interest of consumers and supply of
electricity to all areas, rationalisation of electricity tariff,
ensuring transparent policies regarding subsidies, promotion of
efficient and environmentally benign policies, constitution of
Central Electricity Authority, Regulatory Commissions and
establishment of Appellate Tribunal and for matters connected
therewith or incidental thereto.
12. Before this Act, the Electricity Act, 1910, the Electricity
(Supply) Act, 1948 and the Electricity Regulatory
Commissions Act, 1998 held the ground. With an intent to
encourage the private sector participation in generation,
transmission and distribution of the electricity, the Electricity
Act, 2003 was introduced.
SLP (C) No.33179 of 2025 Page 8 of 32
13. In the present case, we are dealing with terms such as
“unauthorised use of electricity” which features u/S. 126 and
127 of the Act and “theft of electricity” which features u/S. 135
of the Act.
14. Sections 126 and 127 fall in Part XII of the Act which relates
to Investigation and Enforcement and form a complete code
unto themselves. Section 135 falls under Part XIV of the Act
which deals with “Offences and Penalties”. For quick
reference, Sections 126, 127 and 135 of the Electricity Act,
2003 have been reproduced below:
“126. Assessment. — (1) If on an inspection of any place
or premises or after inspection of the equipments, gadgets,
machines, devices found connected or used, or after
inspection of records maintained by any person, the
assessing officer comes to the conclusion that such person
is indulging in unauthorised use of electricity, he shall
provisionally assess to the best of his judgment the
electricity charges payable by such person or by any other
person benefited by such use.
(2) The order of provisional assessment shall be served
upon the person in occupation or possession or in charge of
the place or premises in such manner as may be prescribed.
(3) The person, on whom an order has been served under
sub-section (2), shall be entitled to file objections, if any,
against the provisional assessment before the assessing
officer, who shall, after affording a reasonable opportunity
of hearing to such person, pass a final order of assessment
within thirty days from the date of service of such order of
provisional assessment, of the electricity charges payable
by such person.
SLP (C) No.33179 of 2025 Page 9 of 32
(4) Any person served with the order of provisional
assessment may, accept such assessment and deposit the
assessed amount with the licensee within seven days of
service of such provisional assessment order upon him:
* * * * *
(5) If the assessing officer reaches to the conclusion that
unauthorised use of electricity has taken place, the
assessment shall be made for the entire period during which
such unauthorised use of electricity has taken place and if,
however, the period during which such unauthorised use of
electricity has taken place cannot be ascertained, such
period shall be limited to a period of twelve months
immediately preceding the date of inspection.
(6) The assessment under this section shall be made at a rate
equal to twice the tariff applicable for the relevant category
of services specified in sub-section (5).
Explanation.
—For the purposes of this section, —
(a) “assessing officer” means an officer of a State
Government or Board or licensee, as the case may be,
designated as such by the State Government;
(b) “unauthorised use of electricity” means the usage of
electricity—
(i) by any artificial means; or
(ii) by a means not authorised by the concerned
person or authority or licensee; or
(iii) through a tampered meter; or
(iv) for the purpose other than for which the usage of
electricity was authorised; or
(v) for the premises or areas other than those for
which the supply of electricity was authorised.
127. Appeal to Appellate Authority. — (1) Any person
aggrieved by the final order made under section 126 may,
within thirty days of the said order, prefer an appeal in such
form, verified in such manner and be accompanied by such
fee as may be specified by the State Commission, to an
appellate authority as may be prescribed.
SLP (C) No.33179 of 2025 Page 10 of 32
(2) No appeal against an order of assessment under sub-
section (1) shall be entertained unless an amount equal to
half of the assessed amount is deposited in cash or by way
of bank draft with the licensee and documentary evidence
of such deposit has been enclosed along with the appeal.
(3) The appellate authority referred to in sub-section (1)
shall dispose of the appeal after hearing the parties and pass
appropriate order and send a copy of the order to the
assessing officer and the petitioner.
(4) The order of the appellate authority referred to in sub-
section (1) passed under sub-section (3) shall be final.
(5) No appeal shall lie to the appellate authority referred to
in sub-section (1) against the final order made with the
consent of the parties.
(6) When a person defaults in making payment of assessed
amount, he, in addition to the assessed amount shall be
liable to pay, on the expiry of thirty days from the date of
order of assessment, an amount of interest at the rate of
sixteen per cent. per annum compounded every six months.
135. Theft of electricity. —
(1) Whoever, dishonestly, —
(a) taps, makes or causes to be made any connection with
overhead, underground or under water lines or cables, or
service wires, or service facilities of a licensee or
supplier, as the case may be; or
(b) tampers a meter, installs or uses a tampered meter,
current reversing transformer, loop connection or any
other device or method which interferes with accurate or
proper registration, calibration or metering of electric
current or otherwise results in a manner whereby
electricity is stolen or wasted; or
(c) damages or destroys an electric meter, apparatus,
equipment, or wire or causes or allows any of them to be
so damaged or destroyed as to interfere with the proper
or accurate metering of electricity; or
(d) uses electricity through a tampered meter; or
(e) uses electricity for the purpose other than for which
the usage of electricity was authorised, so as to abstract
SLP (C) No.33179 of 2025 Page 11 of 32
or consume or use electricity shall be punishable with
imprisonment for a term which
may extend to three years or with fine or with both:
Provided that in a case where the load abstracted,
consumed, or used or attempted abstraction or attempted
consumption or attempted use—
(i) does not exceed 10 kilowatt, the fine imposed on
first conviction shall not be less than three times the
financial gain on account of such theft of electricity
and in the event of second or subsequent conviction
the fine imposed shall not be less than six times the
financial gain on account of such theft of electricity;
(ii) exceeds 10 kilowatt, the fine imposed on first
conviction shall not be less than three times the
financial gain on account of such theft of electricity
and in the event of second or subsequent conviction,
the sentence shall be imprisonment for a term not less
than six months, but which may extend to five years
and with fine not less than six times the financial gain
on account of such theft of electricity:
Provided further that in the event of second and
subsequent conviction of a person where the load
abstracted, consumed, or used or attempted abstraction
or attempted consumption or attempted use exceeds 10
kilowatt, such person shall also be debarred from getting
any supply of electricity for a period which shall not be
less than three months but may extend to two years and
shall also be debarred from getting supply of electricity
for that period from any other source or generating
station:
Provided also that if it is proved that any artificial means
or means not authorised by the Board or licensee or
supplier, as the case may be, exist for the abstraction,
consumption or use of electricity by the consumer, it
shall be presumed, until the contrary is proved, that any
abstraction, consumption or use of electricity has been
dishonestly caused by such consumer.
SLP (C) No.33179 of 2025 Page 12 of 32
(1A) Without prejudice to the provisions of this Act, the
licensee or supplier, as the case may be, may, upon
detection of such theft of electricity, immediately
disconnect the supply of electricity:
Provided that only such officer of the licensee or
supplier, as authorised for the purpose by the
Appropriate Commission or any other officer of the
licensee or supplier, as the case may be, of the rank
higher than the rank so authorised shall disconnect the
supply line of electricity:
Provided further that such officer of the licensee or
supplier, as the case may be, shall lodge a complaint in
writing relating to the commission of such offence in
police station having jurisdiction within twenty-four
hours from the time of such disconnection:
Provided also that the licensee or supplier, as the case
may be, on deposit or payment of the assessed amount
or electricity charges in accordance with the provisions
of this Act, shall, without prejudice to the obligation to
lodge the complaint as referred to in the second proviso
to this clause, restore the supply line of electricity within
forty-eight hours of such deposit or payment.
(2) Any officer of the licensee or supplier as the case may
be, authorised in this behalf by the State Government
may—
(a) enter, inspect, break open and search any place or
premises in which he has reason to believe that
electricity has been or is being used unauthorisedly;
(b) search, seize and remove all such devices,
instruments, wires and any other facilitator or
article which has been, or is being used for unauthorised
use of electricity;
(c) examine or seize any books of account or documents
which in his opinion shall be useful for or relevant to,
any proceedings in respect of the offence under sub-
section (1) and allow the person from whose custody
SLP (C) No.33179 of 2025 Page 13 of 32
such books of account or documents are seized to make
copies thereof or take extracts therefrom in his presence.
(3) The occupant of the place of search or any person on his
behalf shall remain present during the search and a list of
all things seized in the course of such search shall be
prepared and delivered to such occupant or person who
shall sign the list:
Provided that no inspection, search and seizure of any
domestic places or domestic premises shall be carried out
between sunset and sunrise except in the presence of an
adult male member occupying such premises.
(4) The provisions of the Code of Criminal Procedure, 1973
(2 of 1974), relating to search and seizure shall apply, as far
as may be, to searches and seizure under this Act.”
ISSUES
15. In the instant case, it emerges that on the basis of the Inspection
Report dated 26.09.2017, a provisional assessment order was
passed by the Respondent / Jharkhand Bijli Vitran Nigam Ltd.
for payment of loss of amount of Rs. 3,23,71,524/- under
Section 135 of the Electricity Act, 2003 r/w Clause 11 of the
Electricity Supply Code Regulation, 2015.
16. In the light of this fact, the following questions emerge for
consideration:
SLP (C) No.33179 of 2025 Page 14 of 32
a. Whether the remedy of Writ Petition was
available to the Petitioner when statutory
remedies are available under the Act?
b. Whether the Petitioner is liable to be held
accountable under Section 135 of the
Electricity Act, 2003? In other words, are the
ingredients of Section 135 satisfied in the
present case?
17. We now proceed to analysis.
Whether the remedy of Writ Petition was available to the Petitioner
when statutory remedies are available under the Act?
18. The General law is that if the statutory remedies are available,
then the aggrieved party will not ordinarily move the High
Court. However, the said position of law is not free of
exceptions. Availability of a statutory remedy does not oust the
jurisdiction of the High Court to entertain a matter under A.226
of the Constitution. In the case of Southern Electricity Supply
Co. of Orissa Ltd. v. Sri Seetaram Rice Mill
1
, it was
expounded as follows.
“80. It is a settled canon of law that the High Court would
not normally interfere in exercise of its jurisdiction under
1
(2012) 2 SCC 108
SLP (C) No.33179 of 2025 Page 15 of 32
Article 226 of the Constitution of India where statutory
alternative remedy is available. It is equally settled that this
canon of law is not free of exceptions. The courts, including
this Court, have taken the view that the statutory remedy, if
provided under a specific law, would impliedly oust the
jurisdiction of the civil courts. The High Court in exercise
of its extraordinary jurisdiction under Article 226 of the
Constitution of India can entertain writ or appropriate
proceedings despite availability of an alternative remedy.
This jurisdiction, the High Court would exercise with some
circumspection in exceptional cases, particularly, where the
cases involve a pure question of law or vires of an Act are
challenged. This class of cases we are mentioning by way
of illustration and should not be understood to be an
exhaustive exposition of law which, in our opinion, is
neither practical nor possible to state with precision. The
availability of alternative statutory or other remedy by itself
may not operate as an absolute bar for exercise of
jurisdiction by the courts. It will normally depend upon the
facts and circumstances of a given case. The further
question that would inevitably come up for consideration
before the Court even in such cases would be as to what
extent the jurisdiction has to be exercised.
81. Should the courts determine on merits of the case or
should they preferably answer the preliminary issue or
jurisdictional issue arising in the facts of the case and remit
the matter for consideration on merits by the competent
authority? Again, it is somewhat difficult to state with
absolute clarity any principle governing such exercise of
jurisdiction. It always will depend upon the facts of a given
case. We are of the considered view that interest of
administration of justice shall be better subserved if the
cases of the present kind are heard by the courts only where
they involve primary questions of jurisdiction or the matters
which go to the very root of jurisdiction and where the
authorities have acted beyond the provisions of the Act.
However, it should only be for the specialised tribunal or
SLP (C) No.33179 of 2025 Page 16 of 32
the appellate authorities to examine the merits of
assessment or even the factual matrix of the case.
xxx
87…
3. In view of the language of Section 127 of the 2003
Act, only a final order of assessment passed under
Section 126(3) is an order appealable under Section
127 and a notice-cum-provisional assessment made
under Section 126(2) is not appealable.
4. Thus, the High Court should normally decline to
interfere in a final order of assessment passed by the
assessing officer in terms of Section 126(3) of the
2003 Act in exercise of its jurisdiction under Article
226 of the Constitution of India.”
19. The concept of “provisional order of assessment” and “final
order” find their place under Section 127 of the Act which
governs the cases falling squarely under Section 126 of the Act.
Section 135 does not have a separate procedure. Even then, the
procedure applicable under Section 127 is applicable on cases
falling under Section 126 simply for the reason that all acts of
unauthorised use of electricity are not theft, but all cases of
“theft of electricity” fall under the unauthorised use of
electricity. Hence, if we were to make a Venn Diagram, it will
look somewhat like this:
SLP (C) No.33179 of 2025 Page 17 of 32
20. Our assessment also finds precedence in the case of W.B. State
Electricity Distribution Co. Ltd. v. Orion Metal (P) Ltd.
2
,
wherein it came to be held as under: -
“12. A perusal of the aforesaid provisions and on giving a
conjoint reading of the same, it appears to us that after an
inspection of any place or any premises of any consumer,
when the assessing officer comes to a conclusion that the
2
(2020) 18 SCC 588
SLP (C) No.33179 of 2025 Page 18 of 32
consumer is indulging in unauthorised use of electricity, the
provisional assessment to the best of his judgment is to be
made in accordance with Section 126(1) of the Act and such
provisional assessment shall be served upon the person in
occupation of the premises. After giving an opportunity to
file objections to the provisional assessment, the assessing
officer is empowered to pass a final order of the assessment
assessing the loss of energy, on account of unauthorised use
of energy. The unauthorised use of electricity is defined
under Section 126(6)(b) of the Act. It is clear from the
aforesaid definition that unauthorised use of electricity
means, the usage of electricity by any artificial means or by
a means not authorised by the person or authority or
licensee concerned; or through a tampered meter; or for the
purpose other than for which the usage of electricity was
authorised; or for the premises or areas other than those for
which the supply of electricity was authorised.
13. It is clear from the reading of Section 126(6)(b)(iii) of
the Act that instances of use of energy through a tampered
meter is included in the definition of unauthorised use of
electricity. If that is so, there is no reason, for excluding the
power of the authorities for making assessment under
Section 126(1) of the Act to assess the loss of energy, where
electricity is used through a tampered meter. All instances
of unauthorised use of energy may not amount to theft of
electricity within the meaning of Section 135 of the Act, but
at the same time, the theft of electricity which is covered by
Section 135 of the Act, will fall within the definition of
unauthorised use of electricity. As per Section 135(1-A) of
the Act, without prejudice to the other provisions of the Act,
the licensee or supplier, as the case may be, upon detection
of theft of electricity, is empowered to disconnect the power
supply immediately. Further, as per the third proviso to
Section 135(1-A) of the Act, the licensee or supplier, as the
case may be, on deposit or payment of assessed amount or
electricity charges, without prejudice to the obligation to
lodge a complaint, can restore the power supply electricity
within forty-eight (48) hours of deposit/payment of such
SLP (C) No.33179 of 2025 Page 19 of 32
amount. Thus, it is clear that the authorities under the Act
are empowered to make a provisional and final assessment
by invoking power under Section 126(1) of the Act, even in
cases where electricity is unauthorisedly used by way of
theft. When a consumer deposits the assessed amount, the
licensee or the supplier has to restore the power supply. The
assessed amount referred to in the aforesaid proviso, relates
to assessment which is contemplated under Section 126(1)
of the Act only. There is apparent distinction between
Section 126 and Section 135 of the Act. Section 126 forms
part of the scheme which authorises electricity supplier to
ascertain loss in terms of revenue caused to it by the
consumer by his act of “unauthorised use of electricity”
whereas Section 135 deals with offence of theft if he is
found to have indulged himself in the acts mentioned in
clauses (a) to (e) of sub-section (1) of Section 135 of the
Electricity Act. Further, it is also clear from Section 154 of
the Act, which prescribes procedure and power of the
Special Court, that the Special Court is empowered to
convict the consumer and impose a sentence of
imprisonment. The Special Court, in cases, where a
criminal complaint is lodged, is also empowered to
determine civil liability under Section 154(5) of the Act. As
per Section 154(6) of the Act, in case civil liability so
determined by the Special Court is less than the amount
deposited by the consumer or the person, the excess amount
so deposited by the consumer or the person, shall be
refunded by the licensee or the person concerned, as the
case may be. Merely because the Special Court is
empowered to determine civil liability under Section 154(5)
of the Act, in cases where a complaint is lodged, it cannot
be said that there is no power conferred on authorities to
make provisional assessment/final assessment under
Section 126 of the Act.”
SLP (C) No.33179 of 2025 Page 20 of 32
21. It stands established that though not explicitly mentioned,
Section 127 applies as much to Section 135 as it does to Section
126. It is clear as daylight that the provision for statutory appeal
under Section 127 of the Electricity Act is only with regards to
a final order of assessment and not a provisional order. Since
the Act does not provide for a statutory appeal against a
Provisional Assessment Order, the Writ Petition against the
same is maintainable.
Whether the Petitioner is liable to be held accountable under
Section 135 of the Electricity Act, 2003? In other words, are the
ingredients of Section 135 satisfied in the present case?
22. The Provisional Assessment Order was issued under Section
135 of the Electricity Act, 2003, which exhaustively defines
“theft of electricity” as including acts such as interference with
the meter, tapping of electricity, making or causing to be made
any connection with overhead, underground or underwater
lines or cables, or service wires, installation or use of tampered
meter etc. This Court has illuminatingly explained the features
of Section 135 and also expounded upon the procedure
mentioned under Sections 126 and 127 in the case of Southern
SLP (C) No.33179 of 2025 Page 21 of 32
Electricity Supply Co. of Orissa Ltd. v. Sri Seetaram Rice
Mill
3
, thus:
“25. Section 135 of the 2003 Act falls under Part XIV
relating to “offences and penalties” and title of the section
is “theft of electricity”. The section opens with the words
“whoever, dishonestly” does any or all of the acts specified
under clauses (a) to (e) of sub-section (1) of Section 135 of
the 2003 Act so as to abstract or consume or use electricity
shall be punishable for imprisonment for a term which may
extend to three years or with fine or with both. Besides
imposition of punishment as specified under these
provisions or the proviso thereto, sub-section (1-A) of
Section 135 of the 2003 Act provides that without prejudice
to the provisions of the 2003 Act, the licensee or supplier,
as the case may be, through officer of rank authorised in this
behalf by the appropriate commission, may immediately
disconnect the supply of electricity and even take other
measures enumerated under sub-sections (2) to (4) of the
said section. The fine which may be imposed under Section
135 of the 2003 Act is directly proportional to the number
of convictions and is also dependent on the extent of load
abstracted.
26. In contradistinction to these provisions, Section 126 of
the 2003 Act would be applicable to the cases where there
is no theft of electricity but the electricity is being
consumed in violation of the terms and conditions of supply
leading to malpractices which may squarely fall within the
expression “unauthorised use of electricity”. This
assessment/proceedings would commence with the
inspection of the premises by an assessing officer and
recording of a finding that such consumer is indulging in an
“unauthorised use of electricity”. Then the assessing officer
shall provisionally assess, to the best of his judgment, the
electricity charges payable by such consumer, as well as
3
(2012) 2 SCC 108
SLP (C) No.33179 of 2025 Page 22 of 32
pass a provisional assessment order in terms of Section
126(2) of the 2003 Act.
27. The officer is also under obligation to serve a notice in
terms of Section 126(3) of the 2003 Act upon any such
consumer requiring him to file his objections, if any, against
the provisional assessment before a final order of
assessment is passed within thirty days from the date of
service of such order of provisional assessment. Thereafter,
any person served with the order of provisional assessment
may accept such assessment and deposit the amount with
the licensee within seven days of service of such provisional
assessment order upon him or prefer an appeal against the
resultant final order under Section 127 of the 2003 Act. The
order of assessment under Section 126 and the period for
which such order would be passed has to be in terms of sub-
sections (5) and (6) of Section 126 of the 2003 Act. The
Explanation to Section 126 is of some significance, which
we shall deal with shortly hereinafter. Section 126 of the
2003 Act falls under Part XII and relates to investigation
and enforcement and empowers the assessing officer to pass
an order of assessment.
28. Section 135 of the 2003 Act deals with an offence of
theft of electricity and the penalty that can be imposed for
such theft. This squarely falls within the dimensions of
criminal jurisprudence and mens rea is one of the relevant
factors for finding a case of theft. On the contrary, Section
126 of the 2003 Act does not speak of any criminal
intendment and is primarily an action and remedy available
under the civil law. It does not have features or elements
which are traceable to the criminal concept of mens rea.
29. Thus, it would be clear that the expression
“unauthorised use of electricity” under Section 126 of the
2003 Act deals with cases of unauthorised use, even in the
absence of intention. These cases would certainly be
different from cases where there is dishonest abstraction of
electricity by any of the methods enlisted under Section 135
of the 2003 Act. A clear example would be, where a
SLP (C) No.33179 of 2025 Page 23 of 32
consumer has used excessive load as against the installed
load simpliciter and there is violation of the terms and
conditions of supply, then, the case would fall under
Section 126 of the 2003 Act. On the other hand, where a
consumer, by any of the means and methods as specified
under Sections 135(a) to 135(e) of the 2003 Act, has
abstracted energy with dishonest intention and without
authorisation, like providing for a direct connection
bypassing the installed meter, the case would fall under
Section 135 of the Act.
30. Therefore, there is a clear distinction between the cases
that would fall under Section 126 of the 2003 Act on the
one hand and Section 135 of the 2003 Act on the other.
There is no commonality between them in law. They
operate in different and distinct fields. The assessing officer
has been vested with the powers to pass provisional and
final order of assessment in cases of unauthorised use of
electricity and cases of consumption of electricity beyond
contracted load will squarely fall under such power. The
legislative intention is to cover the cases of malpractices
and unauthorised use of electricity and then theft which is
governed by the provisions of Section 135 of the 2003 Act.”
23. Reference must also be made to the case of Kerala SEB v.
Thomas Joseph
4
, which laid down broad principles of law
pertaining to Sections 126 and 127; the same are as follows:
“60.1. The provisions of Section 126, read with Section 127
of the 2003 Act become a code in themselves. It specifically
provides the method of computation of the amount that a
consumer would be liable to pay for excessive consumption
of electricity and for the manner of conducting assessment
proceeding. Section 126 of the 2003 Act has been enacted
4
(2023) 11 SCC 700
SLP (C) No.33179 of 2025 Page 24 of 32
with a purpose to achieve i.e. to put an implied restriction
on such unauthorised consumption of electricity.
60.2. The purpose of Section 126 of the 2003 Act is to
provide safeguards to check the misuse of powers by
unscrupulous elements. The provisions of Section 126 of
the 2003 Act are self-explanatory. They are intended to
cover situations, other than, the situations specifically
covered under Section 135 of the 2003 Act. In such
circumstances, the Court should adopt an interpretation
which should help in attaining the legislative intent.
60.3. The purpose sought to be achieved with the aid of the
provisions of Section 126 of the 2003 Act is to ensure
stoppage of misuse/unauthorised use of the electricity as
well as to ensure prevention of revenue loss.
60.4. The overdrawal of electricity is prejudicial to the
public at large, as it is likely to throw out of gear the entire
supply system, undermining its efficiency, efficacy and
even — increasing voltage fluctuations.
60.5. The expression “unauthorised use of electricity”
means as it appears in Section 126 of the 2003 Act. It is an
expression of wider connotation and principle construed
purposively in contrast to contextual interpretation, while
keeping in mind the object and purpose of the 2003 Act.”
24. Section 135 is a criminal remedy as it falls under Part XIV
which pertains to Offences and Penalties under the Act. In
order to invoke this remedy, the State must firstly satisfy the
twin tests of actus reus and mens rea and further, the State must
prove the offence beyond reasonable doubt. Hence, the
threshold for proof is high. Section 135 is a distinct provision
from Section 126 which talks about “unauthorised use of
electricity”. The former is a criminal remedy and the latter is a
SLP (C) No.33179 of 2025 Page 25 of 32
civil remedy. The cases covered under Section 126 are those in
which electricity was consumed in variation of the terms and
conditions of supply leading to malpractises and mens rea is
not a vital element of the same.
25. However, on the contrary, Section 135 starts with the word
“whoever dishonestly” which indicates that there must be
presence of mens rea for invoking the said provision. The word
“dishonestly” has been defined u/S. 24 of Indian Penal Code,
1860 as well as S.2(7) of the Bhartiya Nyaya Sanhita, 2023 as
doing anything with the intention of causing wrongful gain to
one person or wrongful loss to another person. The actus reus
in this provision is tapping the connection or cables, or
tampering a meter, or damaging the electrical meter or
apparatus, or using electricity through a tampered meter or
using it for a purpose other than the one which was prescribed.
26. Section 135 (1A) of the Act confers powers on the authorized
officer to disconnect the electricity connection provided that he
is satisfied that theft of electricity has occurred, but the starting
point to take such a decision is an inspection.
27. As per Clause 11.3 of the Regulations, an authorised officer
upon reliable information shall promptly conduct inspection of
the premises. As per Clause 11.8, in case sufficient evidence is
SLP (C) No.33179 of 2025 Page 26 of 32
found to establish direct theft of electricity, licensee or Supplier
as per Section 135 sub-clause (1A) of the Act shall disconnect
the supply and seize all material evidence including
wires/cables, meter, service line etc., from the premises and
shall lodge a complaint in writing relating to the commission
of such offence in police station having jurisdiction within 24
hours from the time of such disconnection. Clause 11.10 says
that an assessment order has to be prepared by the Authorised
Officer. As per Clause 11.12, in case of suspected theft, the
Authorised Officer shall remove the old meter under a seizure
memo and seal it in the presence of the consumer or his
authorised representative. The Distribution Licensee or
supplier shall continue the supply to the consumer with a new
meter.
28. Further, Clause 11.14 provides that after the detailed
examination of the evidence and the consumption pattern of the
consumer, if the Distribution Licensee or supplier is convinced
that a prima-facie case is made out for the abstraction,
consumption or use of electricity dishonestly against the
consumer, the Distribution Licensee or supplier shall, within 7
days of inspection, serve a provisional assessment order
assessed as per clause 11.24 of these Regulations along with
SLP (C) No.33179 of 2025 Page 27 of 32
show cause notice to the consumer, giving reasons, as to why
a case of theft should not be booked against such consumer
giving full details for arriving at such decision and points on
which reply has to be submitted. As per Clause 11.17, the
person, on whom an order has been served under clauses 11.14
and 11.15 of these Regulations, shall be entitled to file
objections, if any, against the provisional assessment before the
Authorised Officer, who shall, after affording a reasonable
opportunity of hearing to such person, pass a final order of
assessment. Clause 11.28 says that the Distribution Licensee or
supplier, as the case may be, on deposit or payment of the
assessed amount or electricity charges in accordance with the
provision of these regulations, shall, without prejudice to the
obligation to lodge the complaint as referred to in the second
proviso to the clause (1A) of Section 135 of the Electricity
(Amendment) Act, 2007, restore the supply line of electricity
within forty eight hours of such deposit or payment.
29. In other words, the following procedure emerges on a
consonant reading of Section 135 of Electricity Act and
Regulations, 2015.
a. Inspection of Theft.
SLP (C) No.33179 of 2025 Page 28 of 32
b. Disconnection of Electricity in case sufficient evidence is
found to establish direct theft of electricity.
c. Removal and seizure of meter.
d. Preparation of Provisional Assessment Order.
e. Objections, if any, to be filed.
f. Final Assessment Order to be passed.
g. If the consumer deposits the assessed amount then the
electricity supply shall be restored within 48 hours.
30. At this juncture, it is pertinent to refer to the Inspection Report
dt. 26.09.2017 relied upon by the 1
st
Respondent Nigam which
reads as follows:
“As directed by GM cum CE surprise inspection has been
carried out by MRT officials alongwith supply officials.
During inspection cubical metering arrangement was found
raising two compartments one is meter chamber and other
is CT, PT chamber. This cubical metering arrangement
installed under metal sheet room and wall. This
arrangement makes easily approach to the CT/DT of
metering cubical. It has been absorbed that the nut in which
GPC seal is used to affix is found welded at mid point. This
welding enables the removal of the seal to start the CT
terminal point without disturbing seal. Two holes found in
meter chambers. The cover of meter chamber was opened
very easily without breaking the glass. The check metering
unit secondary box control cable came out through given
slot but more space between cable and slot. Further action
will be as per norms.
SLP (C) No.33179 of 2025 Page 29 of 32
Remarks: (i) There is no welding on the nut, (ii) earlier also
there had been blast in the cubical metering, which is very
old, and was twice repaired, (iii) door cannot be opened
without opening plastic seal, (iv) all plastic seals (paper
seal) were found correct, plastic seal may be checked, and
(v) joint inspection be made by the officer of Board and the
office bearer of Chamber.”
31. To this inspection report, the petitioners have two objections,
firstly that the Cubical Metering Unit was installed by the
respondents themselves in open space since it is a huge device.
The petitioners had simply covered the same with a Metallic
Sheet with a purpose to secure the same from direct sunlight
and rain. The premises were inspected by the authorities
periodically and not even once did they object to the sheet and
the seals on the meter were found intact at all times. Secondly,
when this inspection was conducted, nothing was seized as per
the seizure report and hence the 2015 Regulations were not
followed.
32. There is merit in what the petitioner says. The inspection report
does not have even a whiff of allegation of theft of electricity,
much less the evidence. At best, there was a suspicion and only
on the basis of the said suspicion an FIR was registered. The
Ld. Single Judge was right to record that as a matter of practice,
many people cover their metering unit to protect it from
depreciation. The minor discrepancy alleged by the inspecting
SLP (C) No.33179 of 2025 Page 30 of 32
team is not enough to prove the case of theft of electricity,
which has to adhere to the strict standards of criminal law.
33. Suspicion, no matter how strong, cannot take the place of strict
proof. After a thorough perusal of record, we find that not even
a single shred of evidence has been produced by the State
which would allow us to come to the conclusion that the
discrepancies that the State alleges can be elevated to the level
of an offence.
34. It is essential that in order to hold a person or a legal entity
responsible for the theft of electricity, the theft has to be first
detected in the course of inspection. The inspection report must
reveal that theft was detected and the details of such evidence
must also be recorded therein. As noted above, in the present
inspection report, no details or evidence of theft of electricity
were noted. Further, there was no subjective satisfaction of the
authorized officer either. Only if the inspection report records
a finding on the theft of electricity and gives details of the
evidence collected during the inspection which unerringly
disclose theft of electricity, the provisional assessment order
can be sustained. Such a finding of theft must be apparent on a
bare reading of the report. If the report is of such a nature that
upon bare reading of the same, one cannot construe the basis
SLP (C) No.33179 of 2025 Page 31 of 32
of theft, then in such a thorough investigation would be
required to ascertain whether theft took place or not and the
inspection officer will not be allowed to visit penalties upon
the consumer in the name of theft only on the basis of such a
provisional report that has no legs to stand on.
35. In the instant matter, as the Ld. Single Judge has rightly
recorded, upon a bare reading of the report, one cannot arrive
at the conclusion that a theft of electricity has taken place. The
inspection reported that the door cannot be opened without
opening a plastic seal and that all plastic seals were found
correct, intact and further reported that the meter chamber was
easily accessible, however, that by itself does not prove mens
rea.
36. Further, there is also a violation of Regulation 11.8 as per
which all material evidence including wires, cables and meters,
service lines are to be seized. Neither the inspection report nor
the written report has disclosed that any material from premises
of the consumer have been seized.
37. Lastly, the respondents have tried making a case that the
provisional assessment order was issued and electricity
connection was disconnected in order to protect the revenue of
the State. This argument has to be rejected at the threshold
SLP (C) No.33179 of 2025 Page 32 of 32
because if protection of revenue is accepted as an argument,
then that will open floodgates of cases where the inspecting
authority will be get arbitrary powers to disconnect electricity
of the consumers on the basis of vague reports that do not
satisfy the essentials of Section 135, turning this provision into
an abuse of process of law.
38. The Ld. Division Bench was in error in setting aside the well-
reasoned order of the Ld. Single Judge and same cannot be
sustained. For the aforesaid reasons, the Order of Division
Bench rendered in L.P.A. No. 648 of 2018 is set aside and the
Order of the Single Judge dated 05.09.2018 passed in W.P. (C)
No. 6054 of 2017 is restored by allowing this Appeal with no
order as to costs. Pending applications, if any, stand disposed
of.
...........................................................J.
[ARAVIND KUMAR ]
............................................................J.
[VIPUL M. PANCHOLI]
NEW DELHI;
AUGUST 12
th
, 2026.
Legal Notes
Add a Note....