As per case facts, the petitioner, a partnership firm, was awarded a contract by the Central Railway for bridge construction. The work scope and completion period were extended due to ...
606-26-WP.odt
{1}
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO. 606 OF 2026
M/s. MVV Satyanarayan
A registered Partnership Firm,
Through its Authorized Signatory,
Mr. Niel S/o. Kakasaheb Patil,
Age: 42 years, Occu.: Project Manager,
R/o.C/o.6-1-136/3M, Flat No.101
Meher Ratna Complex, Balram Colony,
Padmarraonagar, Secunderabad-500025 … Petitioner
VERSYUS
1. The General Manager,
Central Railway, D.N. Road,
Mumbai CSMT - 400001
2. The Chief Administrative Officer (Const.),
Central Railway, New Administrative Building
6
th
Floor, D.N. Road,
Mumbai, CSMT – 400001.
3.The Chief Engineer/C/Central CSMT
Chief Administrative Officer (c)’s Office
Central Railway, New Administrative Building
6
th
Floor, D.N. Road,
Mumbai, CSMT -400001 … Respondents
…...
Mr. Prasadrao Vemulapalli, Advocate h/f Mr. A.A. Fulfagar,Advocate for
Petitioner
Mr. N.S. Salunke, Advocate for Respondents No.1 to 3
…...
CORAM : SMT. VIBHA KANKANWADI AND
HITEN S. VENEGAVKAR, JJ.
RESERVED ON : 13 MARCH, 2026
PRONOUNCED ON : 27 MARCH,2026 2026:BHC-AUG:13099-DB
606-26-WP.odt
{2}
JUDGMENT/ORDER [Per Hiten S. Venegavkar, J.] :-
1. Rule. Rule is made returnable forthwith. With the consent of the
parties, the petition is taken up for final disposal.
2. The present Writ Petition is filed under Article 226 of the
Constitution of India by a partnership firm, M/s. MVV Satyanarayan,
registered at Hyderabad, acting through its authorized signatory
(hereinafter referred to as 'the petitioner'), against Respondent No.1 –
the General Manager, Central Railway; Respondent No.2 – the Chief
Administrative Officer (Construction), Central Railway; and Respondent
No.3 – the Chief Engineer (Construction)/Central, Chhatrapati Shivaji
Maharaj Terminus, Mumbai (hereinafter collectively referred to as 'the
respondent railway authorities').
3. By way of the present petition, the petitioner challenges the
communication dated 13.11.2025 issued by Respondent No.3, whereby
a decision was taken to part terminate the contract/agreement dated
17.08.2024, and further challenges the termination notice dated
02.12.2025, on the grounds that the said actions are arbitrary, illegal,
and contrary to the principles of natural justice. The petitioner has also
prayed for a direction permitting it to complete the balance work as per
the petitioner's letter dated 6th December 2025 and for a further
direction to the respondents to release the payments for the work
executed by the petitioner till date.
606-26-WP.odt
{3}
4. The factual matrix as pleaded by the petitioner in its memo of
petition is as follows. The petitioner is a duly registered partnership firm
based at Hyderabad and has been carrying on business since
03.09.1984. The petitioner claims to have been engaged in the field of
civil contract works for Indian Railways, both Central and various State
Governments and their instrumentalities, for over four and a half
decades, with what it describes as an immaculate track record in
meeting exact specifications and completing work within targeted
timelines. In the process, it is stated that the petitioner has acquired
specialized skills in the construction of bridges and other works for
Indian Railways.
5. It is the case of the petitioner that Respondent No.2 had invited
tenders for the construction of balance minor and major bridges at
various places, construction of Road Under Bridges (RUBs) and drain
works in connection with the Ahmednagar–Beed–Parli Vaidyanath New
Broad Gauge Line Project, by issuing a Tender Notice dated 19.01.2024.
The petitioner's tender was accepted by Respondent No.3, who issued a
Letter of Acceptance dated 30.04.2024. Thereafter, an agreement came
to be executed between Respondent No.2 and the petitioner on
17.08.2024. As per the terms of the Letter of Acceptance, the initial
value of the work was Rs.3,74,65,7193/- (Rupees Thirty Seven Crores
606-26-WP.odt
{4}
Forty Six Lakhs Fifty Seven Thousand One Hundred and Ninety Three
only). The work was to be completed within twelve calendar months
from the date of the Letter of Acceptance, making the completion date
on or before 29.04.2025. Upon completion of the work, the petitioner
was also obligated to provide a maintenance period of twelve calendar
months, including through the monsoon season, under the defect
liability clause.
6. The petitioner further states that in terms of the Letter of
Acceptance, the Earnest Money Deposit (EMD) of Rs.20,66,500/-
submitted by the petitioner along with the tender document was to be
retained by the respondents as part payment of security deposit until
the liability period was over. In addition, the respondents were entitled
to deduct and recover an amount equivalent to 6% of each running bill
until the amount so deducted and recovered reached 5% of the contract
value towards the balance security deposit. The petitioner contends
that, as a consequence of these deductions, the respondents hold a sum
of approximately Rs.2.66 crores belonging to the petitioner. The
petitioner has also furnished a Bank Guarantee towards a Performance
Guarantee for an amount of Rs.1,87,32,859.67 issued by the Bank of
Maharashtra, the validity of which, according to the respondents, has
been extended up to 25.06.2026.
606-26-WP.odt
{5}
7. The petitioner submits that upon receipt of the Letter of
Acceptance, it mobilized and deployed the necessary men, machinery,
and material to the site and commenced work with due earnestness so
as to complete it within the agreement period. It is further submitted
that during the execution of the work, due to prevailing site conditions,
certain additional quantities and extra items became necessary, on
account of which two supplemental agreements were entered into
between the parties, whereby the value of the work was increased to
Rs.54,85,03,233.53/- (Rupees Fifty Four Crores Eighty Five Lakhs Three
Thousand Two Hundred and Thirty Three and paise Fifty Three),
representing an increase of approximately 46 to 50% over the original
contract value. Consequent upon the increase in quantities and the
change in the scope of work, coupled with prevailing site conditions, the
completion period was also extended from time to time without the
imposition of any penalty, and the agreement was stated to be valid
through 31.03.2026. The petitioner contends that the extension of time
without any penalty is itself indicative of the fact that the delay in
completion of work was not attributable to the petitioner but was on
account of factors beyond its control.
8. As per the case of the petitioner, work to the tune of
approximately Rs.46 crores has been executed, out of which the
606-26-WP.odt
{6}
petitioner has been paid an amount of Rs.38,95,69,185/- and that work
valued at approximately Rs.7.5 crores is yet to be measured, recorded
and paid for. The petitioner further contends that during the execution
of work, without the consent of the petitioner and without any formal
amendment to the agreement, certain works forming part of the scope
of work under the agreement dated 17.08.2024 were awarded by the
respondents to other agencies. Some of these offloaded works,
according to the petitioner, were crucial for the completion of the
petitioner's own scope, including the laying of the deck slab on the
major bridge. While the work was in progress, the petitioner alleges
that for extraneous reasons, Respondent No.3 issued a series of show-
cause and adverse notices in order to arm-twist and compel the
petitioner not to raise complaints about the unauthorized offloading of
works to what the petitioner describes as 'blue-eyed boys', without
entering into formal agreements with those agencies.
9. It is the case of the petitioner that without regard to the
prevailing site conditions and the progress of work, a communication
dated 13.11.2025 was issued by Respondent No.3 through which the
administration took a decision to 'part terminate' the work awarded to
the petitioner, which the petitioner describes as unheard of in the annals
of contract management. A Seven Days' Notice was issued on
606-26-WP.odt
{7}
19.11.2025, followed by a 48-Hours' notice on 27.11.2025, and finally
the agreement was terminated by way of a Termination Notice dated
02.12.2025. The petitioner submits that the managing partner was out
of the country at the relevant time and returned only on 29.11.2025,
which is stated to be one of the reasons for not replying to the show-
cause notices. Feeling aggrieved by what it terms an illegal termination,
the petitioner has approached this Court invoking its jurisdiction under
Article 226 of the Constitution of India.
10.The learned Advocate appearing on behalf of the petitioner has
advanced the following arguments in support of the petition. It is firstly
argued that the reasons assigned in the communications dated
13.11.2025 and 02.12.2025 are absolutely contrary to the actual site
conditions and hence cannot be sustained. It is further argued that as on
13.11.2025, the petitioner still had more than 140 days remaining to
complete the balance work, and even as on the date of issuance of the
final termination notice on 02.12.2025, there were more than 100 days
remaining, which made the action of part termination and eventual
termination completely unwarranted and deserving of interference by
this Court. It is also submitted that since certain works were offloaded
by the respondents to other agencies without the consent of the
petitioner, the failure of those other agencies to complete the offloaded
work cannot be fastened as a liability upon the petitioner.
606-26-WP.odt
{8}
11.The learned Advocate for the petitioner further argues that the
allegations made in the letters dated 13.11.2025 and 02.12.2025 are
trivial in nature and that most of the works were actually in progress at
the relevant point of time, and hence did not warrant either part
termination or full termination. He argues with vehemence that both
the communications dated 13.11.2025 and 02.12.2025 were issued in
gross violation of the principles of natural justice as the petitioner was
never afforded an adequate opportunity of being heard before the
impugned decisions were taken. He contends that the petitioner had
sufficient time remaining to complete the contracted work within the
extended period of validity of the agreement, namely, 31.03.2026, and
therefore the impugned communications are bad in law. He further
argues that some of the works offloaded to third agencies were a pre-
condition for the petitioner to take up and complete its allotted work,
and therefore, the non-completion of the offloaded work by those third
agencies cannot be attributed to the petitioner, nor can the petitioner be
held liable for any resultant delay. He submits that even at the time of
filing of the present petition, sufficient time remained for the balance
contract work to be completed, and if permitted by this Court, the
petitioner is ready and willing to complete the work within the balance
days. In support of this submission, he draws the attention of this Court
to the letter dated 06.12.2025 addressed by the petitioner to the
606-26-WP.odt
{9}
respondent authorities expressing its desire to complete the work within
the balance period.
12.On the question of maintainability of the writ petition, the
learned Advocate for the petitioner acknowledges that the contract
agreement contains an arbitration clause but argues that the reliefs
sought in the present petition are declaratory and consequential in
nature, and if relegated to arbitration, it would consume substantial
time, during which the material already present at the site would get
damaged and rendered unusable, thereby causing irreparable harm to
the petitioner. He also argues that the primary challenge in the present
petition is to the termination order on the grounds of violation of the
principles of natural justice, which is a public law remedy and is
cognizable by this Court under Article 226 of the Constitution. In
support of the maintainability of the writ petition, the learned Advocate
places heavy reliance on the judgment of the Hon'ble Supreme Court of
India in the case of Union of India & Ors. v. Tantia Construction Pvt.
Ltd., (2011) 5 SCC 697, which is also a railway contract case, wherein
the Hon'ble Apex Court has held that an alternative remedy, including
the existence of an arbitration clause in a contract, is not an absolute
bar to the invocation of the writ jurisdiction of the High Court or the
Supreme Court, and that such a petition is maintainable.
606-26-WP.odt
{10}
13.The learned Advocate appearing for the respondent railway
authorities has advanced arguments in support of the action taken and
in support of the impugned orders. He submits that the termination
order dated 02.12.2025 has been issued strictly in accordance with the
terms and conditions of the contract agreement and after duly following
the process of law as contemplated therein. He states that the
respondents had invited tenders for the completion of the subject work
and, after accepting the tender of the petitioner, issued a Letter of
Acceptance as per standard procedure and thereafter executed the
contract agreement in accordance with the General Conditions of
Contract (GCC). The completion period, maintenance period, retention
of EMD amount, deduction of security deposit, and the performance
guarantee are all strictly in terms of the contract agreement and the
Letter of Acceptance dated 30.04.2024. He further states that the
validity of the performance guarantee in the form of a Bank Guarantee
of the Bank of Maharashtra has been extended up to 25.06.2026.
14.The learned Advocate for the respondents further submits that it
was the sole and primary responsibility of the petitioner to deploy the
requisite manpower, machinery, and material at the site for
commencement and continuous progress of the work. He contends that
the respondents wrote to the petitioner on several occasions pointing
606-26-WP.odt
{11}
out the slow progress of work and the non-deployment of requisite
manpower at the site. Regular meetings were held with the petitioner,
and the minutes of meetings dated 06.01.2025 and 13.06.2025 record
that target dates for completion of various works were provided to the
petitioner, but the same were never adhered to or achieved. Owing to
site conditions, additional quantities and additional items were
incorporated into the existing scope of work in agreement with the
petitioner, and variations were processed accordingly, for which the
petitioner also submitted numbered claim certificates. The first
extension of time was granted to the petitioner up to 30.09.2025, at the
request of the petitioner vide its communication dated 28.04.2025. A
second extension was thereafter granted up to 31.03.2026, again on the
specific request of the petitioner. Thus, according to the respondents,
the original timeline of twelve months has been extended by a further
eleven months, representing an extension of approximately 91% of the
original completion period, while the variation in the original contract
amount is approximately 46%.
15.The learned Advocate for the respondents submits that even
after the grant of extensions, the petitioner was unable to complete the
work, and after reviewing the progress, it was found that there was no
activity at the site for the casting of the deck slab. Accordingly, a Seven
606-26-WP.odt
{12}
Days' Notice was issued to the petitioner on 19.11.2025. Even after the
said notice, the petitioner failed to mobilise the necessary resources. A
48-Hours' Notice was therefore issued on 27.11.2025, but there was still
no improvement. The part termination notice dated 13th November
2025 was issued in accordance with Annexure XIII of the contract
agreement, due to the urgency of completing the work before a
scheduled inspection by the Commissioner of Railway Safety (CRS), and
the poor performance and planning on the part of the petitioner had
resulted in the delay of the CRS inspection by four months. The
termination of the agreement on 02.12.2025 was accordingly a
culmination of a long process during which the petitioner was given
ample opportunity but repeatedly failed to comply.
16.With regard to the payments claimed by the petitioner, the
learned Advocate for the respondents submits that the amounts claimed
in the petition are incorrect, as the petitioner has not submitted the
details of measurements along with the technical site registers duly
signed by the railway officials in respect of the balance work.
Measurements for the balance work have not been initiated by the
petitioner till date, and therefore the payments in respect of such work
remain outstanding solely on that account. He further submits that the
action taken by the respondents is in strict accordance with the terms
606-26-WP.odt
{13}
and conditions of the contract, which expressly reserves the right of the
railway to alter, omit, or get executed any part of the work through
other agencies.
17.On the question of maintainability of the writ petition, the
learned Advocate for the respondents strongly argues that, in view of
Clauses 63 and 64 of the General Conditions of Contract, all disputes
between the parties are required to be resolved by way of arbitration.
He submits that once the parties have consciously adopted an
arbitration mechanism for resolution of disputes arising out of the
contract, there is no warrant for invoking the extraordinary jurisdiction
of this Court under Article 226 of the Constitution of India. He further
submits that the issues raised by the petitioner are essentially disputed
questions of fact, requiring the recording of evidence and proof, which
is a function that cannot be performed in a writ petition but can only be
adjudicated before an arbitrator. In support of his contentions, he relies
upon the judgment of the Hon'ble Supreme Court in (i) State of U.P. &
Ors. v. Bridge & Roof Co. (India) Ltd., (1996) 6 SCC 22, (ii) Kerala
State Electricity Board & Anr. v. Kurien E. Kalathil & Ors., (2000) 6 SCC
293 and (iii) Joshi Technologies International Inc. v. Union of India &
Ors., (2015) 7 SCC 728.
606-26-WP.odt
{14}
18.We have heard the learned Advocates for both the parties at
length and have carefully perused the material on record, including the
documents annexed to the petition and the reply filed by the
respondents, and have given our earnest consideration to the citations
relied upon by both sides. We are now called upon to adjudicate upon
the maintainability of the present writ petition and the merits of the
challenge mounted by the petitioner against the impugned orders.
19.Before we advert to the facts of the case, it would be apposite to
set out the legal framework governing the invocation of writ jurisdiction
by a High Court under Article 226 of the Constitution in matters arising
out of contractual disputes between a contractor and a State or its
instrumentality. The law on this aspect is well-settled through a catena
of pronouncements of the Hon'ble Supreme Court of India, and the
principles emerging therefrom may be briefly summarised. The power
of this Court under Article 226 of the Constitution is undoubtedly
plenary and wide. It is also well settled that the existence of an
alternative remedy, including an arbitration clause in a contract, does
not absolutely and invariably foreclose the exercise of writ jurisdiction
by a High Court. At the same time, however, it is equally well settled
that writ jurisdiction under Article 226 is discretionary in nature, and
the exercise of such extraordinary jurisdiction has to be calibrated with
606-26-WP.odt
{15}
care and caution, having regard to the nature of the dispute, the
availability of an efficacious alternative remedy, and the question of
whether the dispute essentially involves contested questions of fact that
cannot be adjudicated in writ proceedings.
20.The Hon'ble Supreme Court, in State of U.P. & Ors. v. Bridge &
Roof Co. (India) Ltd. (supra), laid down the foundational principles
governing this field in clear and emphatic terms. In that case, the Apex
Court held that a contract between the parties is in the realm of private
law and is governed by the provisions of the Contract Act. Any dispute
relating to the interpretation of the terms and conditions of such a
contract cannot be agitated, and could not have been agitated, in a writ
petition; that is a matter either for arbitration, as provided by the
contract, or for the civil court, as the case may be. The Court further
held that where the contract itself contains a clause providing for
settlement of disputes by reference to arbitration, there is no reason
why the parties should not follow and adopt that remedy, and that the
existence of an effective alternative remedy, in such case provided in the
contract itself, is a good ground for the Court to decline to exercise its
extraordinary jurisdiction under Article 226 of the Constitution of India.
The Hon’ble Apex Court pointedly observed that Article 226 of the
Constitution of India was not meant to supplant the existing remedies
606-26-WP.odt
{16}
at law but only to supplement them in certain well-recognized
situations.
21.The principle enunciated in Bridge & Roof Co. (supra) was
affirmed and elaborated by the Hon'ble Supreme Court in Kerala State
Electricity Board & Anr. v. Kurien E. Kalathil & Ors. (supra), wherein the
Apex Court, speaking through a Bench of two learned Judges, reiterated
with clarity that every act of a statutory body need not necessarily
involve an exercise of statutory power, and that statutory bodies, like
private parties, have the power to contract or deal with property, and
such activities may not raise any issue of public law. The Court held that
the contract between the parties therein was in the realm of private law
and not a statutory contract, and that disputes relating to the
interpretation of the terms and conditions of such a contract could not
have been agitated in a petition under Article 226 of the Constitution. It
was further held that whether any amount is due to the contractor and,
if so, how much, and whether the refusal of the authority to pay it is
justified or not, are not matters which could have been agitated and
decided in a writ petition. The Court emphasized that the proper forum
for such adjudication is a civil court or, where the contract provides for
it, arbitration.
606-26-WP.odt
{17}
22.The Hon'ble Supreme Court in Joshi Technologies International
Inc. v. Union of India & Ors., reported in (2015) 7 SCC 728, further
clarified the position by holding that the law has developed through a
catena of judgments, and from a reading of those judgments it emerges
that in pure contractual matters, the extraordinary remedy of writ
under Article 226 or Article 32 of the Constitution cannot be invoked.
The Court held that such a remedy is available only in a limited sphere,
namely, when the non-Government contracting party is able to
demonstrate that it is a public law remedy which it seeks to invoke, as
contra-distinguished from the private law remedy simpliciter available
under the contract. This principle constitutes a clear and authoritative
statement of the law on the interface between writ jurisdiction and
contractual disputes.
23.We have given careful consideration to the judgment of the
Hon'ble Apex Court in Union of India & Ors. v. Tantia Construction Pvt.
Ltd. (supra), upon which the learned Advocate for the petitioner has
placed heavy reliance. The Hon’ble Apex Court, in that case, upheld the
maintainability of the writ petition filed by a railway contractor
challenging an order requiring it to execute enlarged and altered work
at the same rates as originally tendered, and held that the existence of
an arbitration clause in the agreement does not absolutely bar the
606-26-WP.odt
{18}
parties from invoking the writ jurisdiction of the High Court or the
Supreme Court. The Court reiterated the rule that the exclusion of writ
jurisdiction on account of an alternative remedy is a rule of discretion
and not one of compulsion. We have no quarrel with the aforesaid legal
proposition. However, the Tantia Construction judgment must be read
in its correct context. In that case, the dispute was not merely a factual
dispute regarding slow progress or breach of contractual obligations;
rather, it involved a fundamental question of whether the Railway was
entitled to require the contractor to execute a substantially and
qualitatively altered scope of work, amounting in substance to a new
project, at the rates originally tendered, which raised a significant
public law issue pertaining to the exercise of contractual power
arbitrarily and beyond the four corners of the agreement. The factual
matrix of the present case is materially different, as we shall presently
demonstrate.
24.Before examining whether the disputes in the present case are
essentially factual in nature, we must address the principal ground
urged by the petitioner, namely, the alleged violation of the principles of
natural justice. The petitioner's learned Advocate has vehemently
contended that the impugned communications dated 13.11.2025 and
02.12.2025 were issued without affording the petitioner any
606-26-WP.odt
{19}
opportunity of being heard. We find this submission to be factually
unsustainable in the present case. From the record before us, it is
evident that the respondent railway authorities had issued multiple
show-cause notices and adverse progress reports to the petitioner over a
prolonged period, spanning several months prior to the issuance of the
part termination notice. The minutes of meetings held on 06.01.2025
and 13.06.2025, and the communications between the parties, establish
beyond any doubt that the petitioner was made fully aware of the
concerns of the respondents regarding the slow progress of the work
and the non-deployment of adequate manpower and machinery at the
site. The petitioner was not only present at those meetings but was also
given specific target dates for completion of various items of work.
Seven Days' Notices were issued to the petitioner on at least five
separate occasions and 48-Hours' Notices were also issued repeatedly,
all of which were received by the petitioner.
25.In this background, The work assigned to the petitioner was of
national importance, and therefore completion of the said project
within time was absolutely necessary for the public at large and also for
the nation. The respondents, being public authorities involved in
essential services like Railways, have a primary duty towards the
citizens of this nation, and therefore the targeted completion of the
606-26-WP.odt
{20}
work was not only necessary but rather mandatory. The record shows
that the respondent authorities have constantly raised their concern
with the petitioner regarding the slow progress of the work and have,
from time to time, issued instructions and directions to the petitioner to
expedite the work and complete the same within the allotted time as
well as the extended time. It will, therefore, be incorrect to characterize
the impugned action as one taken behind the back of the petitioner
without any opportunity of being heard. The communication dated
13.11.2025 and the subsequent termination notice dated 02.12.2025
were not the first communications from the respondents; they were the
culmination of a long chain of notices, meetings, and communications,
all of which afforded the petitioner more than adequate opportunity to
explain its position, mobilize resources, and remedy the defaults
complained of. The submission of the petitioner that its managing
partner was abroad and therefore could not respond is, in our
considered view, an afterthought that cannot be elevated to the level of
a valid legal ground of natural justice violation. The petitioner is a
partnership firm, capable in law of acting through its authorized
representative or any other partner, and the absence of the managing
partner from the country does not create a legal vacuum that would
nullify the actions taken by the respondents after following the due
contractual process. The principles of natural justice do not require the
606-26-WP.odt
{21}
respondents to wait indefinitely for a response or to maintain the status
quo until such time as it suits a contracting party to engage with the
notices issued to it.
26.Turning now to the crux of the matter, we are of the considered
view that the disputes sought to be agitated in the present writ petition
are essentially and overwhelmingly disputes involving contested
questions of fact. The petitioner alleges, on one hand, that the works
were in progress and that the extension of time without penalty is
indicative of the absence of any default on its part. The respondents, on
the other hand, have specifically averred that the progress of work was
consistently unsatisfactory, that the petitioner repeatedly failed to
adhere to contractual milestones, that no activity was observed at the
site for the casting of the deck slab despite repeated notices, and that
the Commissioner of Railway Safety's inspection was delayed by four
months on account of the petitioner's poor performance and planning.
The petitioner has alleged that certain works were offloaded to other
agencies without its consent, which prevented it from completing its
own work. The respondents have denied that such offloading was
improper or beyond the scope of the contractual power reserved to the
railway. The petitioner has claimed that a sum of approximately Rs.7.5
crores is yet to be paid for work already executed, while the
606-26-WP.odt
{22}
respondents have submitted that the measurements and technical
documentation required to process payment for the balance work have
not been submitted by the petitioner.
27.It is manifest that each and every one of these contentions raises
a disputed question of fact that cannot be examined, evaluated, or
adjudicated in a proceeding under Article 226 of the Constitution. A
writ court does not record evidence, examine witnesses, or scrutinize
technical specifications and site records. The determination of whether
the work was progressing satisfactorily or not, whether the offloading of
certain works was in accordance with or contrary to the terms of the
contract, whether the petitioner is entitled to additional time for
completion, whether any amount is due and payable to the petitioner,
whether the default in completion is attributable to the petitioner or to
other agencies appointed by the respondents, and whether the
termination was for bona fide reasons related to public interest and the
operational requirements of the railway — all of these are questions
that can only be resolved through a detailed examination of evidence,
including technical site records, minutes of meetings, correspondence
between the parties, measurement books, and the opinions of experts, if
any. The appropriate forum for such an exercise is the Arbitral Tribunal
as specifically agreed upon by the parties under Clauses 63 and 64 of
the General Conditions of Contract.
606-26-WP.odt
{23}
28.We are also of the view that the petitioner has failed to
demonstrate the existence of any element of public law that would
justify the exercise of the extraordinary jurisdiction of this Court under
Article 226 of the Constitution. The rights sought to be enforced by the
petitioner are purely contractual rights arising from the agreement
dated 17.08.2024. The petitioner's grievance, at its core, is that the
respondent authorities terminated the contract before the expiry of the
extended completion period, and that the reasons given for termination
are factually incorrect or insufficient. This is a private law dispute
arising in the realm of contract and is not a matter involving the
violation of any fundamental right or any statutory right that requires
the intervention of this Court under Article 226. As the Hon'ble
Supreme Court observed in Kerala State Electricity Board v. Kurien E.
Kalathil (supra), not every action of a statutory body or instrumentality
of the State raises a public law issue, and where the dispute is purely in
the domain of private law, the appropriate remedy is before a civil court
or an arbitrator, as the case may be.
29.We have also considered the submission of the petitioner's
learned Advocate that if the petitioner is relegated to arbitration, the
material at the site would get damaged and become unusable, thus
causing irreparable harm. While we are sensitive to this concern, we
606-26-WP.odt
{24}
find that this submission does not, by itself, create a ground for
invoking the writ jurisdiction of this Court. The Arbitration and
Conciliation Act, 1996 itself provides adequate mechanisms for
obtaining interim relief, including under Section 9 of the Act, where a
party may approach the competent court for interim measures of
protection pending arbitration proceedings. The petitioner is at liberty
to avail of those statutory remedies. The availability of interim relief
through the arbitration framework further reinforces our conclusion
that the present writ petition is not the appropriate vehicle for the
adjudication of the petitioner's grievances.
30.Having regard to the foregoing analysis, we are of the
considered view that the present writ petition is not maintainable for
the following principal reasons. First, the disputes raised in the petition
are essentially disputes involving contested questions of fact arising out
of the execution of a works contract, which are incapable of
adjudication in a writ proceeding and must be resolved through the
mechanism of arbitration as contractually agreed upon between the
parties. Second, the petitioner has failed to make out any case of
violation of the principles of natural justice, inasmuch as the respondent
railway authorities had issued multiple notices, held numerous
meetings, and provided the petitioner with ample and repeated
606-26-WP.odt
{25}
opportunities over a prolonged period to respond, mobilize resources,
and remedy the alleged defaults before issuing the impugned
communications. Third, the petitioner has not demonstrated the
infringement of any fundamental right or statutory right that would
attract the extraordinary jurisdiction of this Court under Article 226 of
the Constitution. Fourth, both parties, having agreed to the mechanism
of arbitration under Clauses 63 and 64 of the General Conditions of
Contract for the resolution of all disputes arising out of the contract, it
would be wholly inappropriate for this Court to permit a party to bypass
the agreed dispute resolution mechanism and invoke the extraordinary
jurisdiction of the writ court to adjudicate upon essentially contractual
grievances. Fifth, the law laid down by the Hon'ble Supreme Court in
State of U.P. v. Bridge & Roof Co. (India) Ltd. (supra), and Kerala State
Electricity Board v. Kurien E. Kalathil (supra), read together with the
principles enunciated in Joshi Technologies International Inc. v. Union
of India (supra), fully supports the conclusion that this Court ought to
exercise its discretion to decline to entertain the petition and to relegate
the parties to the arbitral forum agreed upon by them.
31.The judgment in Union of India v. Tantia Construction Pvt. Ltd.
(supra) does not assist the petitioner in the facts of the present case. As
we have already observed, the factual matrix of Tantia Construction
606-26-WP.odt
{26}
involved a qualitatively different and more fundamental challenge,
namely, the question of the railway's entitlement to alter the entire
design of a project and compel the contractor to execute a substantially
new and different project at the original tendered rates, which raised a
pure public law issue of arbitrary exercise of statutory power. In the
present case, in contrast, the petitioner's challenge is to the termination
of a contract on the ground of slow progress and non-completion, which
is a matter squarely within the domain of contract law and is subject to
the arbitration clause agreed upon by the parties. The principle laid
down in Tantia Construction (supra) that an alternative remedy is not
an absolute bar to the exercise of writ jurisdiction is a rule of discretion,
and in the exercise of that discretion, having regard to the nature of the
dispute, the adequacy of the alternative remedy, and the essentially
factual character of the controversy, we decline to entertain this
petition.
32.Before parting with this order, we deem it appropriate to record
that by dismissing the present writ petition, we have not adjudicated
upon the merits of the dispute between the parties, and our
observations on the facts contained in this judgment are solely for the
purpose of determining the maintainability of the petition and shall not
prejudice either party in any future proceedings. The petitioner shall be
at liberty to raise all its claims and contentions, including the legality of
606-26-WP.odt
{27}
the termination, the question of payments due, the alleged offloading of
works without consent, and any other grievance, before the Arbitral
Tribunal constituted in accordance with the provisions of the General
Conditions of Contract. It is further clarified that the security deposit,
the EMD amount retained by the respondents, and the Bank Guarantee
submitted by the petitioner shall continue to be maintained and shall
not be forfeited, encashed, or acted upon by the respondents pending
the initiation and conclusion of the arbitration proceedings, for a period
of twelve weeks from today, to enable the petitioner to initiate
arbitration proceedings.
33.In view of the above, the Writ Petition stands dismissed. Rule
discharged. There shall be no order as to costs.
34.The observations made herein above shall not prejudice the
rights of either party before the Arbitral Tribunal.
35.The protection granted by way of interim order, if any, subsisting
as on date shall stand vacated subject to the aforesaid direction with
respect to the security deposit, EMD, and Bank Guarantee.
[ HITEN S. VENEGAVKAR ] [ SMT. VIBHA KANKANWADI ]
JUDGE JUDGE
S P Rane
Legal Notes
Add a Note....