As per case facts, the petitioner, M/s. Precision Infratech Private Limited, challenged a tender process for barrage repair and replacement works. They argued that new eligibility conditions introduced via Corrigendum-3 ...
1
APHC010143272026
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
[3332]
FRIDAY, THE EIGHTH DAY OF MAY
TWO THOUSAND AND TWENTY SIX
PRESENT
THE HONOURABLE SRI JUSTICE RAVI CHEEMALAPATI
WRIT PETITION NOs: 7552 and 13218 of 2026
Between:
M/s., Precision Infratech Private Limited., ...PETITIONER
AND
State Of Andhra Pradesh and Others ...RESPONDENT(S)
Counsel for the Petitioner:
1. SRICHARAN TELAPROLU
Counsel for the Respondent(S):
1. UNNAM AKHIL CHOWDARY
2. GP FOR IRRI AND CAD
RESERVED ON: 05.05.2026
PRONOUNCED ON: 08.05.2026
UPLOADED ON: 08.05.2026
The Court made the following common order:
The case of the petitioner is that, pursuant to the G.O.Rt.No.339 dated
30.06.2025, the Superintending Engineer (3
rd
respondent) issued a Tender
Document E-Procurement Notice Inviting Tender NIT No.19/2025-26, dated
09.01.2026 inviting bids for execution of "Repairs, Servicing and replacement
2
of Mechanical and Electrical Components on four arms and embankments of
Sir Arthur Cotton Barrage", and the eligibility criteria relates to experience in
executing similar works, minimum financial turnover and Technical capacity.
2. In the said tender, it was mentioned that the tender schedule download
closing date as 27-01-2026 at 4.30 pm, Bid Submission closing date as 27-01-
2026 at 4.30 pm; Technical Bid Opening Date as 27-01-2026 at 4.31 PM and
Price Bid Opening date as 29-01-2026 at 11 am. Later, for the reasons best
known to the Respondents 1 to 3, the tender was made invisible in the portal
before the Bid Submission ending date, as such, the petitioner addressed an
email on 27-01-2026 at 12-45 PM to the notified email ID informing the
difficulty and requesting an extension of the bid submission date. Thereafter,
the same tender document was again uploaded on 27.01.2026, changing the
tender schedule download closing date to 10-02-2026 at 2.00 pm; Bid
Submission closing date to 10-02-2026 at 4.00 pm; Technical Bid Opening
Date to 10-02-2026 at 4.30 PM; and Price Bid Opening Date to 12-02-2026 at
11 am.
3. The petitioner along with its JV Partner M/s. Swapna Projects Private
Limited, being fully qualified as per the original tender conditions, submitted its
bid within the stipulated time i.e., on 04-02-2026.
4. While so, the Superintending Engineer-3
rd
respondent, issued
Corrigendum-1 on 04-02-2026 notifying the details of designated stacking
yard for stacking of dismantled components and payment details ;
Corrigendum-2 on 09-02-2026 again extending the timelines prescribing the
3
tender schedule download closing date as 20-02-2026 at 11.00 AM; Bid
Submission closing date as 20-02-2026 at 4.00 pm; Technical Bid (PQ Stage)
Opening Date as 20-02-2026 at 4.30 PM and Price Bid (Commercial Stage)
Opening date as 23-02-2026 at 11 am; Corrigendum-3 on 14-02-2026,
introducing new eligibility conditions, namely requirement of workshop within
500 km from the project site and local Class-I contractor (Electrical)
registration in the State of Andhra Pradesh during the tender process.
5. It is the case of the petitioner that, there is no issue with regard to
Corrigendum-1 & 2 but the Corrigendum-3 was issued with new eligibility
conditions on 14.02.2026, after the petitioner submitted its bid on 04-02-2026.
The petitioner sent an email to the designated email-ID on 16-02-2026 raising
objection to the new eligibility conditions and requested for review. Despite
the same, the technical bids were opened on 20-02-2026 wherein only the 5
th
respondent was said to have qualified in view of the new conditions under
Corrigendum-3 and the price bid was confirmed in favour of the 5
th
respondent. It is the further case that, the said issue was discussed in the
meeting held on 09-03-2026 before the State Level Technical committee and
the contract agreement is yet to be entered with the 5
th
respondent.
6. Challenging the new conditions prescribed in the Corrigendum-3 dated
14.02.2026, the petitioner filed W.P.No.7552 of 2026.
7. In the said writ petition, the 3
rd
respondent filed counter affidavit and
vacate stay petition and also filed a memo dated 01.05.2026 communicating
4
the minutes of State Level Technical Committee dated 09.03.2026 which
contains the reasons for rejecting the petitioner‟s technical bid. On noticing
the said minutes, the petitioner filed W.P.No.13218 of 2026 questioning the
same.
8. Inasmuch as both the writ petitions are connected and the parties are
one and the same, they are heard together and disposed of under this
common order.
9. Heard Sri Sricharan Telaprolu, learned counsel for the petitioner, Sri
Somaraju Yelisetti, learned Government Pleader for Irrigation, Sri Unnam
Muralidhar, learned senior counsel assisted by Sri Unnam Akhil Chowdary,
learned counsel for the 5
th
respondent.
10 (a). Learned counsel for the petitioner in elaboration to what has been
stated in the affidavit contended that, by issuing Corrigendum-3 dated
14.02.2026, the respondent authorities have inserted entirely new eligibility
conditions which are tailor made, completely altering the eligibility criteria,
after the commencement of the tender process, which is impermissible under
law. He further submitted that, the prescription of new condition of having
work shop within 500 km from the work site would render the clause
impractical since 500 km from the work site would cross the State of A.P., and
the other condition of having A.P. Electrical Class-I registration would also
become impractical since it would be impossible for the bidders, who does not
5
possess, to obtain the same within 5 days from the issuance of the said
Corrigendum-3.
(b) He further submitted that, the subject tender relates to Fabrication work,
for which, the bidder is required to be registered as a Special Class contractor
(Fabrication and Erection of Structural Steel) with the Government of Andhra
Pradesh (1st Respondent) which was prescribed in the original tender
document and the petitioner already possess the same. However, the 3
rd
respondent has issued Corrigendum-3 with new prescriptions of having a local
registration as Class-l contractor (Electrical) only to favour the Respondent
No.5 who alone has the said local registration as Class-l contractor (Electrical)
and the workshop within 500 km and thus disqualified the petitioner and
declared the 5
th
respondent as successful bidder. He further submitted that,
the 3
rd
respondent in the counter, on one hand stated that there are no
bidders as such the timeline was extended twice and to the contrary, issued
Corrigendum-3, to eliminate bidders by prescribing new conditions. If the
Corrigendum-3 is not issued there is a possibility of more bidder participation
and many of the bidders might have turned back in view of Corrigendum-3.
Thus the entire decision making process as well as the process of conducting
the tender is wholly illegal and arbitrary and made only to facilitate the 5
th
respondent. He further submitted that, the Respondents 1 to 3, being the
State authorities, are bound to act in conformity with the equality principle in
as much as the State instrumentalities cannot act arbitrarily in awarding
6
contracts and the impugned Corrigendum-3 is in clear violation of the equality
principle.
(c) Learned counsel for the petitioner further submitted that, after filing the
writ petition questioning the Corrigendum-3, the 3
rd
respondent has furnished
the minutes of the meeting dated 09.03.2026 by way of memo dated
01.05.2026 wherein the reasons for rejecting the petitioner‟s technical bid
were shown. The reasons stated by the 3
rd
respondent are that the JV
member has produced contractor registration of Telangana state, the
petitioner has produced GST registration of Gujarat State and that the prime
quantities requirement is not satisfied as per eligibility criteria stipulated in the
bid document. He further submitted that, the said reasons are unsustainable
because the petitioner, being the lead partner has the contractor registration
of State of Andhra Pradesh which would satisfy the requirements and; the
tender notice itself prescribes that, if not already having AP GST registration,
an undertaking to obtain the same before entering into LOA to be given, which
was already submitted by the petitioner. He further submitted that, as per the
bid documents the minimum quantity required for supply of Fabrication and
Erection is 872.28 MT during any one year in the last 10 years whereas the
petitioner and the JV partner have executed more than the minimum quantity
required. Hence, the rejection of the technical bid of the petitioner for the
stated reasons is unsustainable and is totally without application of mind. As
such, prayed to set aside the entire tender process by allowing both the writ
petitions.
7
11 (a). On the other hand, learned Senior counsel for the 5
th
respondent
contended that, Corrigendum-3 is not the reason for petitioner‟s
disqualification or for the acceptance of 5
th
respondents‟ bid. In the counter
filed by the 2
nd
respondent, it was mentioned that petitioner‟s disqualification
was primarily based on the reason that all the bidders were supposed to have
undertaken at least 872.28 MT of Supply, Fabrication and Erection works in at
least one year within last 10 years and the petitioner does not possess the
required experience. He further submitted that, as per special conditions of
the initial notice inviting tender (at para 38(27)) the experience certificates, to
prove the same, have to be signed by the relevant Executive Engineer and
Counter signed by a Superintending Engineer or any other superior officer but
the documents submitted by the petitioner in that regard are not signed by the
authority, as such they cannot be relied upon. The other reason for the
disqualification of the petitioner bid is that the JV partner of the petitioner‟s
company is a registered contractor in the State of Telangana but not in the
State of A.P. as per required conditions. The subject contract is a highly
technical work and since the petitioner company has not having the technical
qualification as required, their bid was rightly rejected by the authority.
(b) The learned Senior counsel further submitted that, the Corrigendum-3 is
issued on 14.02.2026, which are not a mandatory conditions and the petitioner
has questioned the said corrigendum-3 only on 16.03.2026 as an afterthought
after being unsuccessful in the tender process, without any legal grounds,
nearly after one month. He further submitted that, the petitioner having
8
submitted the bid as a Joint venture along with JV partner, filed the writ
petitions in individual capacity without arraying the JV partner as a party to the
lis, as such, the writ petition is liable to be dismissed on the said ground as
well. He further submitted that, on 09.03.2026, Letter of Acceptance (LOA)
was issued to 5
th
respondent and the 5
th
respondent has accepted the same
and complied with all the required tender formalities on 17.03.2026 except
agreement and the petitioner has not questioned the same. He further
submitted that, once an LOA has been executed, it becomes a binding
contract as held in Jawahar LalBurman Vs UOI
1
. As such, the petitioner
company has not made out any points warranting the interference of this court
with the tender process and accordingly prayed to dismiss the writ petition
being meritless. In support of his contentions, the learned standing counsel
relied on nearly 18 judgments and emphasized particularly on Tata Motors
Limited Vs Brihan Mumbai Electric Supply and Transport Undertaking &
Others
2
, Afcons Infrastructure Vs Nagpur Metro
3
, M/s.N.G.Projects
Limited Vs M/s Vinod Kumar Jain & others
4
.
12 (a). Learned Government Pleader for Irrigation on counter submitted that,
since the authorities have found „Stock Yard‟ within the limits of Barrage
where the dismantled components could be stacked, they have issued
Corrigendum-1 and as no bids were received within the prescribed time, the
respondents contemplated to extend the Bid Submission date further by
1
(1962) 3 SCR 769
2
(2023) 19 Supreme Court Cases 1
3
(2016) 16 SCC 818
4
2022 AIR (SC) 1531
9
issuing a Corrigendum-2 and due to a technical glitch, the uploaded document
remained invisible.
(b) He further submitted that, since the Barrage safely discharges over
3000 TMC of flood water from July to September, mandating a 500 km
workshop radius was a direct, legally binding compliance with the World
Bank's mandate to mitigate catastrophic flood risks, the introduction of the
preference for a 500 km workshop radius and Electrical Class-I registration
through Corrigendum-3 is a bonafide technical requirement. He further
submitted that the conditions introduced in Corrigendum No.3 are only
preferred conditions but not mandatory for evaluation of bids submitted by
various bidders.
(c) He further submitted that, having agreed to execute the work in the
proportion of 60:40 by the petitioner and M/s. Swapna Projects Private Limited
(JV partner), both the contractors have to produce the contractor registration
certificate and GST Registration certificate of Andhra Pradesh, but the
petitioner has not produced GST registration certificate of A.P. and the JV
partner did not produced contractor registration certificate of A.P., as such,
they have not satisfied the eligibility criteria mentioned in the tender document.
He further submitted the most important and crucial requirement is that the JV
partner should have executed a minimum quantity of 872.28 MT of supply,
fabrication & erection and also should have executed 34,840.43 Sq.mts of
painting of embedded metal parts and all types of gates, stop logs etc, on
sand blasted surfaces in a year during last ten financial years whereas the
10
petitioner and JV partner, either individually or collectively have not met this
prime requirement as per the eligibility criteria stipulated in the bid document.
Hence, the petitioner‟s bid was rejected.
(d) He further submitted that, the respondents have acted in a fair
transparent, bona fide and lawful manner and provided equitable treatment to
all Bidders, by strictly adhering to the conditions of the NIT and purely based
on the certificates/documents uploaded in the e-procurement system by
various bidders and accordingly approved the bid submitted by 5
th
respondent,
being the lowest bidder and issued Letter of Acceptance (LOA) bearing
No.SE/IC/DWM/DB/ATO.4/584M dated 13-03-2026. Therefore, there is no
procedural infirmity on the part of the respondent authorities, as such prayed
to dismiss the writ petition.
13. In reply, learned counsel for the petitioner submitted that, the very
purpose of entering into joint venture is to ensure that one of the partners
would possess the required eligibilities while both will collectively meet the
eligibility criteria. He further submitted that, without there being any such
prescription in the tender notice, disqualifying the bid document on the ground
that both the JV partners need to submit the required registration in the state
of Andhra Pradesh is irrational. He further submitted that the counter affidavit
of the 3
rd
respondent is not clear as to the parameters under which the bid
documents of the bidders are considered and disqualified and the evaluation
reports of the bids are also not enclosed. He further submitted that, earlier,
though the JV partner of the petitioner is not a registered contractor in A.P.,
11
the State of A.P., has given contract to it and the same was executed by it
successfully. Having allotted the contract to its JV partner without having a
registration in A.P. earlier, the respondent authorities cannot now raise the
ground that the JV partner has not produced a contractor certificate registered
in the State of A.P. As such prayed to pass appropriate orders in that regard.
14. Perused the record and considered the submissions of respective
learned counsel.
15. The petitioner has mainly questioned the issuance of the Corrigendum-
3 dated 14.02.2026 in W.P.No.7552/2026 and later filed W.P.No.13218/2026
questioning the reasons incorporated in the minutes of State Level Technical
Committee dated 09.03.2026 which was filed by the learned Government
pleader for Irrigation after filing of W.P.No.7552 of 2026. It is the contention of
the petitioner that, while the eligibility criteria of the subject tender, which
relates to Fabrication work, is to be registered as a Special Class (Fabrication
and Erection of Structural Steel) with the Government of Andhra Pradesh (1st
Respondent) which the petitioner already possess, the 3
rd
respondent has
issued Corrigendum-3 with a new prescriptions of having a local registration
as Class-l contractor (Electrical) and 500 Kms workshop radius preference,
after the bids have been submitted by various bidders including petitioner,
only to favour the Respondent No.5 who alone has the said local registration
as Class-l contractor (Electrical) and workshop and thus disqualified the
petitioner and declared the 5
th
respondent as successful bidder. The 2
nd
respondent has taken a stand that, since the Barrage safely discharges over
12
3000 TMC of flood water from July to September, mandating a 500 km
workshop radius was a direct, legally binding compliance with the World
Bank's mandate to mitigate catastrophic flood risks, the introduction of the
preference for a 500 km workshop radius and Electrical Class-I registration
through Corrigendum-3 is a bonafide technical requirement. It was also stated
that the said conditions are only preferential conditions but not mandatory.
16. As could be seen from the minutes of State Level Technical Committee
(SLTC) dated 09.03.2026, it was mentioned that, the technical bids were
opened on 20.02.2026 by the Superintending Engineer through online in the
office of the Superintending Engineer, Irrigation Circle, Dowlaiswaram wherein
four (4 Nos.) bidders have participated in the said bid including petitioner‟s
company and the 5
th
respondent. The Chief Engineer reported that the
documents uploaded by the bidders were downloaded and evaluated by the
Superintending Engineer, Irrigation Circle, Dowlaiswaram. It was further
reported that the bidder M/s Swapna Projects Pvt. Ltd., Hyderabad, one of the
JV members of the petitioner (M/s Precision Infratech Pvt. Ltd., Ahmedabad,
Gujarat) has produced contractor registration of Telangana State and is
therefore not eligible as per the tender document. Further, the petitioner
company has produced GST Registration of Gujarat State, and the prime
quantities requirement is not satisfied as per the eligibility criteria stipulated in
the bid document. Hence, the petitioner‟s bid was not qualified. It can be
further seen that the other bidders are also not qualified as they have not met
the eligibility criteria as mentioned in the tender document. Since the 5
th
13
respondent only has satisfied the Technical criteria prescribed in the bid
document, the Chief Engineer, GDS accorded permission for opening of the
price bid and recommended to award the subject work to the 5
th
respondent
herein and placed before the SLTC for approval.
17. No doubt, the rules or conditions cannot be changed once the tender
process has commenced, even otherwise, as mentioned, they are not
mandatory conditions to reject the petitioners‟ bid. Therefore, the issuance of
Corrigendum-3 should not affect the petitioner‟s bid. However, a close reading
of the minutes of the SLTC dated 09.03.2026 would go to show that the
petitioner‟s bid was not rejected based on the conditions imposed in the
Corrigendum-3 but as they did not meet the eligibility criteria with regard to
submission of certificates and prime quantities requirement, their bid was
rejected.
18. The Technical requirement of the subject tender dated 09.01.2026 is
that the contractor should have executed a minimum quantity of 872.28 MT of
supply, fabrication & erection and also should have executed 34,840.43
Sqmts of painting of embedded metal parts and all types of gates, stop logs
etc, on sand blasted surfaces in a year during last ten financial years (2015-16
to 2024-25). The Special condition of the subject tender includes:
“In case of Projects executed in Government departments/Government
undertakings, the experience certificates should be certified by the
Executive Engineer or equivalent and counter signed by the
Superintending Engineer or equivalent and copies may be uploaded
along with tender duly self attested.”
14
19. A perusal of the evaluation of the Technical requirement pertaining to
the supply, fabrication and erection in MT submitted by the 3
rd
respondent
would indicate that the certificates submitted by petitioner company with
regard to completed works is signed only by the Engineer-in-Charge but not
countersigned by the Superintending Engineer or an officer superior to the
equivalent and Engineer-in-Charge, as required under the special conditions of
the bid and hence they are not considered. Further, it shows that the total
quantity of work executed by the petitioner and its JV partner company
together is only 730.97MT but not 872.28 MT, as required under the technical
qualification of the bid. Therefore, it can be said that the petitioner has not met
the eligibility criteria mentioned in the tender document irrespective of the
Corrigendum-3 issued by the 3
rd
respondent.
20. However, in Tata Motors Limited (supra 2), the Apex court has held
that, ordinarily, a writ court should refrain itself from imposing its decision over
the decision of the employer as to whether or not to accept the bid of a
tenderer unless something very gross or palpable is pointed out. The court
ordinarily should not interfere in matters relating to tender or contract. To set at
naught the entire tender process at the stage when the contract is well
underway, would not be in public interest. Initiating a fresh tender process at
this stage may consume lot of time and also loss to the public exchequer to
the tune of crores of rupees. The financial burden/implications on the public
exchequer that the State may have to meet with if the Court directs issue of a
15
fresh tender notice, should be one of the guiding factors that the Court should
keep in mind.
21. In Afcons Infrastructure (supra 3), the Apex Court has held thus:
“11. Recently, in Central Coalfields Ltd. vs SLL-SML (Joint Venture Consortium)
5
it
was held by this Court, relying on a host of decisions that the decision-making
process of the employer or owner of the project in accepting or rejecting the bid of a
tenderer should not be interfered with. Interference is permissible only if the
decision-making process is mala fide or is intended to favour someone. Similarly,
the decision should not be interfered with unless the decision is so arbitrary or
irrational that the Court could say that the decision is one which no responsible
authority acting reasonably and in accordance with law could have reached, In other
words, the decision-making process or the decision should be perverse and not
merely faulty or incorrect or erroneous. No such extreme case was made out by
GYT-TPL JV in the High Court or before us.
13. In other words, a mere disagreement with the decision-making process or the
decision of the administrative authority is no reason for a constitutional court to
interfere. The threshold of mala fides, intention to favour someone or court
interferes with the decision-making process or the decision”.
22. In M/s.N.G.Projects Limited (supra 4), the Apex court has held that
writ court should refrain itself from imposing its decision over the decision of
the employer as to whether or not to accept the bid of a tenderer. The Court
does not have the expertise to examine the terms and conditions of the
present day economic activities of the State and this limitation should be kept
in view. Courts should be even more reluctant in interfering with the contracts
involving technical issues as there is a requirement of the necessary expertise
to adjudicate upon such issues. The approach of the court should be not to
find fault with magnifying glass in its hands, rather the court should examine as
to whether the decision-making process is after complying with the procedure
contemplated by the tender conditions. If the court finds that there is total
5
(2016) 8 SCC 622
16
arbitrariness or that the tender has been granted in a malafide manner, still the
court should refrain from interfering in the grant of tender but instead relegate
the parties to seek damages for the wrongful exclusion rather than to injunct
the execution of the contract.
23. Since the subject work is a highly technical work, the required work to
execute the Project is exclusively within the technical competence and
discretion of the concerned Departmental Engineers and the Department is at
absolute liberty to specify the terms, conditions and eligibility criteria when
inviting tenders in such matters.
24. It is the contention of the petitioner that, earlier, the State of A.P., has
given contract to the JV partner of the petitioner, though it is not a registered
contractor in A.P. Each tender has unique terms and conditions. Since, the
petitioner‟s JV partner did not meet the terms and conditions prescribed in the
subject tender document, their bid was rejected and it has nothing to do with
the previous tender. Therefore, their contention is untenable. Admittedly, the
LOA was already issued to the 5
th
respondent and the same was not
questioned by the petitioner. At this length of time, interfering with the same,
would affect the Public Exchequer and the public interest will be affected.
Further, it is settled law that in such highly technical matters, especially tender
matters, writ courts refrain from interfering and the tender author has absolute
discretion to set the tender terms to address the technical needs.
17
25. In view of the decisions made supra, this court finds no reason to
interfere with the impugned Corrigendum-3 and the minutes of State Level
Technical Committee dated 09.03.2026, as such both the writ petitions are
devoid of merits and liable to be dismissed.
Accordingly, both the writ petitions are dismissed. No costs.
Miscellaneous applications, pending if any, shall stand closed.
___________________________
JUSTICE RAVI CHEEMALAPATI
BRS
Legal Notes
Add a Note....