municipal tax, transport undertaking, commercial law
0  19 May, 2023
Listen in 02:00 mins | Read in 33:00 mins
EN
HI

Tata Motors Limited Vs. The Brihan Mumbai Electric Supply & Transport Undertaking (Best) and Others

  Supreme Court Of India Civil Appeal /3897/2023
Link copied!

Case Background

As per the case facts, the High Court had set aside BEST's decision to accept a tender from EVEY. Tata Motors, another tenderer, was involved in the appeal. The appeals ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO.3897 OF 2023

(arising out of SLP(C) NO. 15708 OF 2022)

TATA MOTORS LIMITED ….APPELLANT(S)

VERSUS

THE BRIHAN MUMBAI ELECTRIC .…RESPONDENT(S)

SUPPLY & TRANSPORT

UNDERTAKING (BEST) AND OTHERS

WITH

CIVIL APPEAL NO. 3899 OF 2023

(arising out of SLP(C) No. 11871 OF 2022)

CIVIL APPEAL NO.3898 OF 2023

(arising out of SLP(C) No. 11933 OF 2022)

J U D G M E N T

J. B. PARDIWALA, J.:

1.Leave granted.

2.As the issues raised in all the captioned appeals are common and the

challenge is also to the self-same order passed by the High Court of Judicature

at Bombay dated 05.07.2022 in the Writ Petition (L) No. 15548 of 2022, those

1

were taken up for hearing analogously and are being disposed of by this

common judgment and order.

3.The Appeal arising out of SLP(C) No. 15708 of 2022 is at the instance

of TATA Motors Limited (for short, “TATA Motors”) (Original Writ Petitioner

before the High Court).

4.The Appeal arising out of SLP(C) No. 11871 of 2022 is at the instance

of EVEY Trans Pvt. Ltd. (for short, “EVEY”) (Original respondent No. 2

before the High Court).

5.The Appeal arising out of SLP(C) No. 11933 of 2022 is at the instance

of the Brihan Mumbai Electric Supply & Transport Undertaking (for short,

“BEST”) (Original respondent No. 1 before the High Court), a statutory

corporation operating under the provisions of the Mumbai Municipal

Corporation Act, 1888.

FACTUAL MATRIX

6.BEST floated a tender bearing No. DMM(T-II)/08/TCU/73169/2021-

2022/Advt. dated 26.02.2022 for the supply, operation and maintenance of

1400 (+50% variation) Single Decker AC Electric Buses with driver, for the

purpose of public transport service within the city of Mumbai along with other

civil infrastructure development at the BEST depots for a period of 12 years

(hereinafter referred to as, ‘the Tender’).

7.The Tender document provided for Technical specifications as

stipulated under Clause 3.5(e) and Clause 12 of Section 2 of Schedule IX,

under which the bidders were required to provide Single Decker Buses which

2

can run 200 Kms in single charge without interruption in actual conditions for

the relevant Gross Vehicle Weight (GVW) with air conditioning with not more

than 80% battery being consumed. Clause 3.5(e) and Clause 12 respectively

are reproduced hereunder:

“SCHEDULE IX

TECHNICAL SPECIFICATIONS

….

Section 2: Technical specifications of SD AC Electric Buses under Wet Lease

Scheme

….

Sr.

No.

DescriptionSpecifications

3.5Electric

Propulsion

System

Electric propulsion system motor rating/power

sufficient to provide:

(e)Minimum

Operation

Range per bus

per day

The minimum operating Km of the buses offered in

single charge will be 200 Km, for SD buses

respectively with (80% SoC). These offered buses

should run above mentioned minimum Km without

any interruption.

xxx xxx xxx

12Operating

range

Presently the BEST buses operate for around an

average of 200 km. per day (mostly uninterrupted).

Keeping the above in mind, the EV manufacturers

have to provide vehicles which can run 200 km. in

single charge for SD AC Buses in actual conditions

for the relevant GVW with Air Conditioning. The

Operating schedule shall be provided by BEST and

the successful bidder has to ensure the

uninterrupted operation of the schedules through

adequate spare buses.

In case the successful bidder is unable to maintain

3

uninterrupted operation of schedules for want of

charging, then BEST shall take suitable action by

levying additional penalty by non-payment towards

assured kms for that entire day per instance and if

the instance keeps on recurring for a long period of

time then the BEST may resort to even termination

of Contract.”

8. In all, eight market players participated in the Tender process, including

EVEY and TATA Motors. In the pre-bid meeting held on 11.03.2022, TATA

Motors submitted its pre-bid points, wherein under Point 1, it requested BEST

to consider its bid for 200 Kms per day with 75-minutes of opportunity

charging time during the day operations and range testing conditions as per

AIS 040/FAME II.

9.On 15.03.2022, BEST published the minutes of the pre-bid meeting.

BEST revised certain specifications, however, the modifications as requested

by TATA Motors were rejected. BEST opted for a specific reference to “in

actual conditions” and excluded any reference to “AIS 040” or “Standard

Conditions” in the Tender specifications. It is pertinent to note that the AIS

040 certification would be upon standard testing conditions and not on the

actual road conditions, which would account for passenger load, temperature,

traffic conditions, etc.

10. On 27.04.2022, BEST issued Corrigendum No. 8 specifying the end of

submission of bids for the Tender as 02.05.2022 and the date of opening the

technical bid as 04.05.2022.

11.TATA Motors submitted its bid on 25.04.2022, wherein it guaranteed

operating range of 200 Kms with 80% State of Charge, “SoC” (i.e. 20%

reserve left upon running 200 Kms in single charge), however, the same was

4

achieved “in standard test conditions as per AIS 040”. This was a deviation

from the Tender specifications.

12.EVEY submitted its bid on 02.05.2022, claiming that the same was

submitted without any deviation from the Tender conditions including the

condition of minimum operating range of 200 Kms in a single charge. EVEY

claimed that the TATA Motors was the only bidder which, referenced

“standard test conditions” instead of “actual road conditions”, while stating

that it complied with the Tender requirement of minimum operating range.

13.Under Clause 5.1.1 of the Schedule II (Definitions and Instructions to

Bidders) of the Tender, the mode and manner of submission of the bid

proposal has been provided. The said clause also provided for certain

annexures to be submitted along with the bid. Pertinently, Annexure Y, which

is an undertaking to be given by the Operational Equipment Manufacturer

(OEM) for the operating range of the buses, was not required to be submitted

along with the bid but was only required to be submitted by the successful

bidder. The purpose of the undertakings under Clause 3.5 (e) and Clause 12 of

Section 2 of Schedule IX (Technical Specifications) and Annexure Y is to

confirm that the requirement of meeting the 200 Kms range in single charge is

satisfied.

14.EVEY along with its bid dated 02.05.2022 submitted Annexure Y,

wherein the OEM gave an undertaking for the operating range which included

a table that mentioned that the operating range for a single decker bus would

be 200 Kms with the opportunity charging time of 1 hour. The same was done

in accordance with the specifications of the earlier tender dated 20.08.2021,

which allowed for an opportunity time of 60 minutes.

5

15.EVEY vide email dated 06.05.2022, provided a revised Annexure Y as

per the Single Charge Requirements mentioned in the Tender along with an

explanation for the same holding it to be a mere “clerical error”.

16.The Tender bids were opened on 04.05.2022 and the technical

suitability evaluation was announced on 06.05.2022. BEST in its technical

suitability evaluation dated 06.05.2022, held TATA Motors along with four

other bidders, to be “technically non-responsive”. TATA Motor’s bid was

rejected on account of technical deviation with respect to the operating range

in its Annexure F and Annexure Y, respectively. The bid offered by EVEY in

the said report was deemed to be “technically responsive”.

17.Thereafter, on 06.05.2022, the price bids of the eligible bidders were

opened, and EVEY was declared to be the L1 bidder. The price bid of TATA

Motors was not opened in accordance with Sr. No. 7 of the Schedule I

(Invitation for Proposal) and Sr. No. 15 of the Schedule II (Definitions and

Instructions to Tenderers) of the Tender document. Sr. No. 7 of Schedule I

reads as under:

“7. The Bidders/Tenderers who meet the mandatory technical

and commercial eligibility criteria as mentioned in Schedule III

of Tender Document shall only be held eligible for opening of

price bids.”

18. Sr. No. 15 of Schedule II (Definitions and Instructions to Tenderers) of

the Tender document, reads as under:

“15. The Bidders shall accept unconditionally BEST's

'Conditions of Tender & Conditions of Supply' in TOTO, failing

which their financial bids shall not be considered for ·opening.

Bidders are requested to go through the same carefully.”

6

19.Aggrieved by the technical suitability evaluation issued by BEST by

which it rejected the bid of TATA Motors, the latter approached the High

Court of Judicature at Bombay by way of a writ petition bearing WP(L) No.

15548 of 2022 dated 10.05.2022. TATA Motors prayed for the following

reliefs:

“18. The Petitioners therefore pray that this Hon'ble Court may be

pleased to:

(a) Issue a writ of Certiorari or any other writ, order or direction

in the nature of Certiorari to call for the records of the case and

quash and set aside the decision dated 06.05.2022 taken by the

Respondent No. 1 declaring the bid submitted by the Petitioner No.

1 as "technically non-responsive";

(b) Issue a writ of mandamus or writ in the nature of mandamus or

any appropriate writ, order or direction under Article 226 of the

Constitution of India directing Respondent No. 1 to reconsider the

bid submitted by the Petitioner No. 1 for the purposes of the

Tender;

(c) In the alternative to prayer (b) issue a writ of mandamus or

writ in the nature of mandamus or any appropriate writ, order or

direction under Article 226 of the Constitution of India directing

Respondent Nos. 1 to cancel the Tender and float a fresh tender;

(d) During the pendency of the Petition, restrain Respondent No. 1

from taking any steps towards award of contract under the Tender;

(e) ad-interim reliefs in terms of prayers in clause (d) above;

(f) Cost of the present Petition; and

(g) such further and other reliefs as the nature and the

circumstances of the case may require be granted to the

Petitioner.”

20. During the pendency of the aforesaid writ petition BEST awarded the

Tender in favour of EVEY with the Letter of Acceptance dated 20.05.2022.

EVEY accordingly submitted the required Performance Bank Guarantee on

23.05.2022. An agreement for operation of Stage Carriage Services for public

transport of Single Decker AC Electric Buses with Driver in the city of

7

Mumbai and its extended suburbs on Gross Contract Cost (GCC) model for 12

years was entered into between the EVEY and BEST on 26.05.2022.

21.A subsidy bank guarantee dated 02.06.2022 was submitted by EVEY

and BEST released the requisite amount to the EVEY’s account towards

subsidy on 10.06.2022. The EVEY even provided the BEST with 8 buses

between 04.07.2022 and 05.07.2022.

22.The High Court vide its impugned order and judgment dated

05.07.2022, took the view that the requirement for the operating range to be

more than 200 Kms in a single charge in “actual conditions” was

unambiguous. Accordingly, the High Court upheld the disqualification of

TATA Motors and rejected their claim from being considered as an eligible

bidder as they failed to comply with the technical requirements of the Tender.

The High Court in paragraphs 9 and 13 respectively of the impugned order

observed thus:

“9. Reading the aforesaid, it is unambiguous that operating range

provided in the tender document is that the electric vehicles

manufacturers have to provide the vehicles which can run 200 kms

in single charge for SD air conditioning buses in actual conditions

for relevant GVW air conditioning. The prima donna requirement

of the tender document it appears is that the electric vehicle

offered should run 200 Kms in a single charge for Single Decker

air conditioning bus in actual conditions with 80% SoC without

any interruption.

Xxx xxx xxx

13. Petitioner No.1 did not submit its bid for 200 Kms@ 80% SoC

in single charge on actual condition but at standard test conditions

as per AIS 040. As per the tender condition if a person to whom

the contract is awarded i.e. lessee does not comply with the

condition of achieving range of 200 Kms at 80% SoC in single

charge then he is penalized for the same. Meaning thereby,

8

Respondent No.1 was conscious that the standard test conditions

as per AIS 040 is different than the actual condition. The tender of

the Petitioner certainly was not compliant with the said clause.

The Petitioner has deviated from the material and the substantial

term of the tender. The Petitioner, as such, is rightly disqualified

for deviating from the material requirements stipulated in the

tender.”

(Emphasis supplied)

23. The High Court, after holding as above proceeded further to discuss as

to why the bid of EVEY also should have been rejected. The High Court noted

EVEY’s contention that Annexure Y submitted along with the technical bid

was an incidental document, however, rejected such contention. The High

Court while referring to Clause 16 of Schedule I held that once the final date

for the submission of the bid expires, there can be no additions/corrections/

submissions of documents by the bidders. Clause 16 of Schedule I of the

Tender is produced hereinbelow:

“SCHEDULE I

Invitation for Proposal

16. Interested Bidders are advised to study this Tender

document carefully before submitting their proposal in

response to this Tender document. Submission of a

proposal in response to this tender shall be deemed to

have been after careful study and examination of this

document with full understanding of its terms,

conditions and implications. No addition / correction,

submission of documents will be allowed after opening

of technical bid”

9

24.The High Court as a result, held that the email dated 06.05.2022 ought

not to have been entertained, and the technical bid evaluation, which was

released on the same day did not depict fairness in the actions of BEST. The

High Court in paragraphs 20 – 22 respectively held as under:

“20. It has been contended by Respondent No.1 that letter issued

by Respondent No.2 on 6th morning did not influence the

decision to hold the bid of Respondent No.2 responsive in the

afternoon of 6th May 2022. The same is not borne-out from the

facts and circumstances of the case. Clause-16, as stated above

specifically and categorically prohibits additions / corrections /

submission of documents after opening of technical bid.

Technical bids have been opened on 4th May 2022. Thereafter no

such letter could have been entertained. The proximity of the

time i.e. 6th May at 11.35 am. the letter issued by Respondent

No. 2 along with the modified Annexure-Y and after two hours,

the bid of Respondent No.2 held responsive, does not support the

contention of Respondent No.1 that the said revised Annexure-Y

and the letter written on 6th May morning did not weigh in

holding Respondent No.2's bid responsive. First of all, accepting

the letter from Respondent No.2 by Respondent No.1 on 6 May

morning itself was against the specific terms of the tender

(clause 16). It is further the case of Respondent No.1 that on 6

th

morning revised Annexure-Y forwarded by Respondent No.2 was

sou motu and not at the instance of Respondent No.1, may not be

relevant here. The fact remains that Respondent No.2 was

allowed to submit the letter and revised Annexure-Y after two

days of the opening of technical bids. It is also the fact that on

28th April Respondent No.2 had submitted the bid and on 2nd

May it had submitted the revised bid, however, with the same

Annexure-Y clearly stating that it would require opportunity

charging tune of one hour. The same would not be in tune with

the tender conditions.

21. From the aforesaid facts, it is clear that; (i) the tender

documents submitted by the Petitioner contained deviation in

Annexure-Y i.e. the undertaking from OEM stating that one

hour charging time would be required for achieving operating

range of 200 Kms.; and (ii) Respondent No.2 submitted the

10

revised Annexure-Y on 6th morning i.e. two days after the

opening of technical bids and after acceptance of revised

Annexure-Y on 6tb May morning, the technical bid of

Respondent No.2 was accepted in the afternoon of the same

day.

22. The aforesaid does not depict fair play in action. The facts

create doubt about, whether the decision was a fair one or was

the decision reached fairly? The same does not appear to be so

in view of the facts discussed above while accepting the bid of

Respondent No.2 as responsive.”

(Emphasis supplied)

25.In view of the aforesaid, the High Court thought fit to declare EVEY

also as an unsuccessful bidder. The High Court in paragraphs 23 and 24

respectively held as under:

“23. We are aware that the principle of equity and natural justice

stay at a distance and no judicial interference is warranted in

case of an error in assessment. However, the same holds good, if

the decision is bona fide. We are also aware that interference of

the Court would lead to some delay. It would be seen that earlier

also the tenders were issued. However, because of non-sanction

of subsidy, the earlier tender process was scrapped and fresh

tender process was issued. For accepting the bid of Respondent

No.2, 90 days’ time is provided to it for getting the prototype

vehicle. The said period is not over. It is not even one month. The

Respondent No.2's tender is accepted. The Courts upon coming

to the conclusion that the decision making process was not fair.

The same lacked fair play in action and arbitrary, will have to

step in.

24. In the light of the above, we set aside the decision of the

Respondents of acceptance of tender of Respondent No.2.

Respondent No.1, if it so desires, may proceed with a fresh tender

process.”

(Emphasis supplied)

11

26.In such circumstances referred to above, all the three parties are here

before this Court with their respective petitions.

27.It is pertinent to note that during the pendency of the proceedings

before the High Court and after submitting the subsidy guarantee, EVEY had

already supplied total 8 buses between 04.07.2022 to 05.07.2022. However,

this Court by an interim order dated 14.07.2022 granted an interim stay of the

impugned judgment insofar as EVEY is concerned. This Court observed that,

the supply of the buses, if any, by EVEY would be subject to the result of

these petitions and EVEY shall not claim any equity at a later stage.

SUBMISSIONS ON BEHALF OF THE “EVEY”

28.Mr. Rohatgi, the learned Senior counsel appearing for EVEY placed

strong reliance on the decision of this Court in W.B. State Electricity Board v.

Patel Engineering Co. Ltd. & Ors., reported in (2001) 2 SCC 451 to submit

that the equitable relief can be granted to the bidder where it has made a

material mistake of fact in the bid and upon discovery of that mistake he has

acted promptly and rectified his mistake. He submitted that, Clause 16 of

Schedule I of the Tender would not apply to a document, like Annexure Y,

which was originally required to be submitted by the "Successful Bidder'' after

the evaluation of the bid. Furthermore, the learned Senior counsel proceeded

to submit that, even in the original Annexure Y as submitted on 02.05.2022,

his client had mentioned that, “These offered buses will run above mentioned

minimum Kms without any interruption”.

29.He submitted that, Annexure F specifies that “If the variations specified

herein, are found to be in nature of contradiction to BEST’s

requirements/specifications then such Bids will be treated as Non-responsive”

12

and therefore, the bidder would have to essentially comply with the

specifications mentioned in Annexure F otherwise the bid would be treated as

“technically non-responsive”. He submitted that Annexure F can be rightly

termed as an essential condition of Tender. He placed strong reliance on the

decision of this Court in the case of Kanhaiya Lal Agrawal v. Union of India

and Others, reported in (2002) 6 SCC 315, to submit that whether a condition

is essential, or collateral could be ascertained by reference to the consequence

of non-compliance thereto. It was submitted that if non-fulfilment of the

requirement results in rejection of the tender, then it would be an essential part

of the tender otherwise it is only a collateral term. He further submitted that,

non-compliance of the conditions mentioned in Annexure Y would lead to

levy of penalty and if the instance keeps on recurring, it may lead to

termination of contract and therefore, Annexure Y should be treated as a

collateral term of the Tender. Under Clause 5.1.1 of Schedule II (Definitions

and Instructions to Bidders) of the Tender document Annexure Y was not

required to be submitted along with the bid documents but the same was to be

submitted by the "Successful Bidder''.

30.He submitted that, in view of the decision of this Court in, N.G.

Projects Limited v. Vinod Kumar Jain and Others, reported in (2022) 6 SCC

127, the writ court should refrain itself from imposing its decision over the

decision of the employer as to whether to accept the bid of a tenderer and that

contract of public service should not be interfered with lightly. The injunction

or interference in the Tender leads to additional costs on the State and is also

against public interest.

31.He submitted that the allegations of favouritism levelled by TATA

Motors by pointing towards the fact that apart from EVEY, there were two

more parties who were technically qualified and were L2 and L3 viz., Switch

13

Mobility Automotive Limited and PMI Electro Mobility Solutions Private

Limited respectively, EVEY was declared L1 and awarded the Tender only

after opening of the price bids at a later stage are reckless and baseless.

32.Relying on the decisions of this Court in Raunaq International Ltd. v.

I.V.R. Construction Ltd. and Others reported in (1999) 1 SCC 492 and S.S.

& Company v. Orrisa Mining Corporation Limited reported in (2008) 5 SCC

772, he submitted that once the High Court found TATA Motors to be

technically non-compliant, it ought not to have entertained a challenge to the

tendering process at the instance of an unsuccessful party. The writ petition

was filed against the technical evaluation, whereas, the contract is now well

underway at the stage of performance. He submitted that interfering with the

technical evaluation at this stage would make the contract redundant and

cause loss of exchequer’s money.

33.In the last, the learned Senior counsel submitted that till date EVEY has

supplied 20 tailor-made buses and the civil infrastructure for these buses has

also been put in place.

SUBMISSIONS ON BEHALF OF THE “TATA MOTORS”

34. Dr. Abhishek Manu Singhvi, the learned Senior counsel, appearing for

TATA Motors vehemently submitted that the contract awarded by BEST to

EVEY is per se illegal. The learned Senior counsel argued that the acceptance

of the EVEY’s revised Annexure Y after the expiry of the bid submission end

date and technical bid opening date is contrary to the Tender conditions.

Clause 16 of Schedule I (Invitation for Proposal) of the Tender prohibits any

addition, correction or submission of document after the technical bid

opening. However, the same was not followed and by allowing a bidder to

14

correct errors at a later stage may lead to unequal treatment of bidders. The

decisions of this Court in Poddar Steel Corporation v. Ganesh Engineering

Works and Others, reported in (1991) 3 SCC 273 (Para 6); W.B. State

Electricity Board (supra) (Paras 27 and 28), were relied upon to substantiate

the aforesaid contention.

35.He submitted that the actions of BEST could be termed as arbitrary,

discriminatory, unfair, and that his client has locus to challenge the same as no

legitimacy should be granted to tender processes tainted with malice. The

learned Senior counsel relied upon the decision of this Court in Monarch

Infrastructure (P) Ltd v. Commissioner, Ulhasnagar Municipal Corporation

and Others, reported in (2000) 5 SCC 287 (Paras 10 and 14); Meerut

Development Authority v. Association of Management Studies and Another,

reported in (2009) 6 SCC 171 (Paras 27, 28, 45 and 76); Maa Binda Express

Carrier and Another v. North-East Frontier Railway and Others, reported in

(2014) 3 SCC 760 (Paras 8, 9 and 12) to fortify the submission.

36.He argued that the High Court in paragraph 19 of the impugned

judgment has rightly observed that the battery range guarantee can be given

only by the OEM from whom the bidder is purchasing the battery, and in such

circumstances, the same cannot be said to be incidental. The same was

considered as an important part of the technical evaluation by BEST.

37.He vociferously submitted that Annexure Y was a part of the bid

document and once submitted, could not have been permitted to be altered

after the bid submission end date i.e., 02.05.2022. The argument that

Annexure Y was optional and not required at the time of submission of the bid

is an afterthought, and the same being a question of fact or at the most a

mixed question of fact and law cannot be raised for the first time in a Special

Leave Petition. He relied on the decision of this Court in Jagannath Behera

15

& Ors. v. Raja Harihar Singh Mardaraj Bhramarbara Roy, reported in 1958

SCR 1067 (Paras 17 and 19); Karanpura Development Co. Ltd v. Raja

Kamakshya Narain Singh Etc., reported in 1956 SCR 325 (Para 24);

Vasantkumar Radhakisan Vora v. Board of Trustees of Port of Bombay,

reported in (1991) 1 SCC 761 (Para 24); Steel Authority of India Ltd v.

Gupta Brother Steel Tubes Ltd, reported in (2009) 10 SCC 63 (Paras 32 and

34).

38.He submitted that the High Court was justified in saying that a fresh

tender in the present matter is warranted more particularly in view of the

arbitrary tender process and delay in supply of the buses as per the timeline

prescribed under the Tender. He submitted that a fresh tender would be in

public interest as there has been a breach of delivery timeline by EVEY as

prescribed under the Tender. It is alleged that there is a deficit in the supply of

1,030 buses till date. BEST has failed to take necessary steps against EVEY

for the delay, and the same showcases that the two contracting parties have

colluded with each other. The fresh tender would allow for more competitive

price bids and there would not be any financial burden on BEST in the event

of termination, as the Tender provides for forfeiture of Earnest Money Deposit

(EMD) and encashment of performance guarantee.

39.In the last, the learned Senior counsel submitted that the High Court

while upholding the disqualification of his client on the sole basis that it

guaranteed the operating range in ‘standard test conditions as per AIS 040’

committed an error. It was submitted that TATA Motors had complied with the

essential conditions and certain departures under the Tender were permissible.

SUBMISSIONS ON BEHALF OF THE “BEST”

16

40.Mr. Tushar Mehta, the learned Solicitor General, appearing for BEST

submitted that the Tender document provided for mandatory eligibility

conditions for being declared as a qualified bidder at the stage of technical

bid, and the said eligibility conditions were stipulated in sub – clauses (iv) and

(v) of Clause 5.1.1 respectively of the Tender Document.

41.He further submitted that Clause 5.1.1 (v), providing for Annexure F

was a mandatory condition for being qualified as a bidder at the Technical

Bidding stage. The mandatory requirement reads as under:

“5.1.1The Proposal should be submitted in the following

manner:

Bid 1: Technical Submissions, which would include:

i) Schedule of Guaranteed Performance & Other

Technical Particulars as shown in the prescribed

format in Annexure-A incorporated in the Tender

document (in case of a consortium that of a lead

member),

ii) Schedule of Performance of the Bidder (in case of

consortium experience of any member) as in Annexure

C,

iii) Proforma for certification for Minimum Average

Annual Turnover (“MAAT”) from Chartered

Accountant as in Annexure D. (in case of consortium

for lead member and in case of Aggregator, Networth

certificate or Investible fund certificate),

iv) Aggregator have to submit back-to-back agreement

17

with OEM for complete contract period for the

maintenance of buses. Aggregator have also to submit

Manufacturer Authorization Form (if aggregator is a

sole bidder or lead bidder then such bidder shall

submit Manufacturer Authorization Form) from OEM,

v) Schedule of Departures from technical

specification as in Annexure F,

vi) General details of Bidder with registration proof

and credentials (in case of Consortium, this would

need to be provided by the lead members) as in

Annexure G & H,

vii) Bid Security/EMD as in Annexure I,

viii) The Annexure-L. (undertaking of the Bidder not

being involved/engaged in any corrupt or fraudulent

malpractices or not being black-listed with any

Government or Public Sector Units in India or outside

India)

ix) In case of Consortium, proforma of Consortium

Agreement to be entered into between members as in

Annexure N,

x) Covering Letter cum Project Undertaking as per

Annexure Q stating the Proposal Validity Period,

xi) Power of Attorney for Signing of the Proposal (in

case of Consortium, this would need to be provided by

all the members) as in Annexure R.”

18

42.He submitted that TATA Motors deviated from the mandatory

requirement while filing the said Annexure F. He highlighted the portion of

the Annexure which states that if variations are found contradicting BEST’s

requirements then such bids would be treated as non-responsive. The non-

compliant deviation was as under:

“Shall meet the operating range requirement of 200 KMS @

80% SOC in single charge as certified per AIS 040.”

43.He submitted that none of the bidders including EVEY (successful

bidder) deviated from this mandatory condition. Hence, TATA Motors was

declared a non-responsive bidder at the technical stage itself. On 06.05.2022,

BEST undertook the technical evaluation and took a decision that of all the

bidders found eligible and responsive, EVEY had quoted the lowest rates and

accordingly the contract was awarded in its favour.

44.The learned SG further submitted that the successful bidder was

required to fill up Annexure Y. However, Annexure Y was neither a condition

precedent for being a responsive bidder nor a mandatory condition for

awarding the contract.

45.EVEY rectified its mistake, explaining that the Annexure Y submitted

by it was inadvertently placed after doing a cut-and-paste job from the

previous tender. EVEY filed a revised/fresh Annexure Y strictly in accordance

with the Tender.

46.The learned SG vehemently submitted that to ask BEST to issue a fresh

tender notice would be against public interest. In the contract given to EVEY

in May 2022, BEST was to pay Rs. 46.81/KM to EVEY. BEST examined the

possibility of re-tendering and found that in the recent past, one similar tender

19

was issued by the Convergency Energy Services Limited (CESL), a

Government of India undertaking. As per the recent contract awarded by

CESL, it ended up paying Rs. 1,200 Crore more than the present rate at which

“BEST” awarded the instant contract. Therefore, it would be commercially

imprudent to opt for re-tendering.

ANALYSIS

47.Having heard the learned counsel appearing for the parties and having

gone through the materials on record, the only question that falls for our

consideration is : Whether the High Court after upholding the disqualification

of TATA Motors from the Tender was justified in undertaking further exercise

to ascertain whether EVEY also stood disqualified and that BEST in its

discretion may undertake a fresh tender process?

48.This Court being the guardian of fundamental rights is duty-bound to

interfere when there is arbitrariness, irrationality, mala fides and bias.

However, this Court has cautioned time and again that courts should exercise

a lot of restraint while exercising their powers of judicial review in contractual

or commercial matters. This Court is normally loathe to interfere in

contractual matters unless a clear-cut case of arbitrariness or mala fides or bias

or irrationality is made out. One must remember that today many public sector

undertakings compete with the private industry. The contracts entered into

between private parties are not subject to scrutiny under writ jurisdiction. No

doubt, the bodies which are State within the meaning of Article 12 of the

Constitution are bound to act fairly and are amenable to the writ jurisdiction

of superior courts but this discretionary power must be exercised with a great

deal of restraint and caution. The courts must realise their limitations and the

20

havoc which needless interference in commercial matters can cause. In

contracts involving technical issues the courts should be even more reluctant

because most of us in Judges' robes do not have the necessary expertise to

adjudicate upon technical issues beyond our domain. The courts should not

use a magnifying glass while scanning the tenders and make every small

mistake appear like a big blunder. In fact, the courts must give “fair play in the

joints” to the government and public sector undertakings in matters of

contract. Courts must also not interfere where such interference will cause

unnecessary loss to the public exchequer. (See: Silppi Constructions

Contractors v. Union of India, (2020) 16 SCC 489)

49.It is not in dispute that the first and the foremost requirement of the

Tender was the prescribed operating range of the single decker buses which

would operate for around and average of 200 Kms in a single charge in

“actual conditions” with 80% SoC without any interruption. Then materials

on record would indicate that the TATA Motors in its bid deviated from this

requirement and had informed BEST that it could carry the operating range in

the “standard test conditions” which was not in accordance with the Tender

conditions. The High Court has rightly observed in its impugned judgment

that the bid of the TATA Motors failed to comply with the said clause. TATA

Motors deviated from the material and the essential term of the Tender. It may

not be out of place to state at this stage that it is only TATA Motors who

deviated from the condition referred to above. However, we are of the view

that the High Court having once declared TATA Motors as “non-responsive”

and having stood disqualified from the Tender process should not have entered

into the fray of investigating into the decision of BEST to declare EVEY as

the eligible bidder. We are saying so because the High Court was not

exercising its writ jurisdiction in public interest. The High Court looked into a

petition filed by a party trying to assert its own rights. As held by this Court in

21

Raunaq International Ltd. (supra), that grant of judicial relief at the instance

of a party which does not fulfil the requisite criteria is something which could

be termed as misplaced. In Raunaq International Ltd. (supra), this Court

observed as under:

“27. In the present case, however, the relaxation was

permissible under the terms of the tender. The relaxation which

the Board has granted to M/s Raunaq International Ltd. is on

valid principles looking to the expertise of the tenderer and his

past experience although it does not exactly tally with the

prescribed criteria. What is more relevant, M/s I.V.R.

Construction Ltd. who have challenged this award of tender

themselves do not fulfil the requisite criteria. They do not

possess the prescribed experience qualification. Therefore,

any judicial relief at the instance of a party which does not

fulfil the requisite criteria seems to be misplaced . Even if the

criteria can be relaxed both for M/s Raunaq International Ltd.

and M/s I.V.R. Construction Ltd., it is clear that the offer of

M/s Raunaq International Ltd. is lower and it is on this ground

that the Board has accepted the offer of M/s Raunaq

International Ltd. We fail to see how the award of tender can

be stayed at the instance of a party which does not fulfil the

requisite criteria itself and whose offer is higher than the offer

which has been accepted. It is also obvious that by stopping

the performance of the contract so awarded, there is a major

detriment to the public because the construction of two

thermal power units, each of 210 MW, is held up on account of

this dispute. Shortages of power have become notorious. They

also seriously affect industrial development and the resulting

job opportunities for a large number of people. In the present

case, there is no overwhelming public interest in stopping the

project. There is no allegation whatsoever of any mala fides or

collateral reasons for granting the contract to M/s. Raunaq

International Ltd.”

(Emphasis supplied)

22

50.We take notice of the fact that Annexure Y was originally required to be

submitted by the “Successful Bidder” after the evaluation of the bid and the

same did not figure in the list of documents and annexures to be included in

the technical submissions, as provided under Clause 5.1.1 of Schedule II of

the Tender. Further the format provided for Annexure Y in the Tender

documents in its heading states that the “Successful Bidders shall upload a

Letter of Undertaking on their letter head as below”. Therefore, we are of the

view that the restriction on revision of documents under Clause 16 of

Schedule I, which states, “No addition/correction, submission of documents

will be allowed after opening of technical bid,” is only limited to the

documents necessary to be included in the technical bid and would not be

applicable to any such document which does not form a part of the technical

bid.

51.We are of the view that the High Court should have been a bit slow and

circumspect in reversing the action of BEST permitting EVEY to submit a

revised Annexure Y. We are of the view that the BEST committed no error or

cannot be held guilty of favoritism, etc. in allowing EVEY to submit a revised

Annexure Y as the earlier one was incorrect on account of a clerical error. This

exercise itself was not sufficient to declare the entire bid offered by EVEY as

unlawful or illegal.

52.Ordinarily, a writ court should refrain itself from imposing its decision

over the decision of the employer as to whether or not to accept the bid of a

tenderer unless something very gross or palpable is pointed out. The court

ordinarily should not interfere in matters relating to tender or contract. To set

at naught the entire tender process at the stage when the contract is well

underway, would not be in public interest. Initiating a fresh tender process at

this stage may consume lot of time and also loss to the public exchequer to the

23

tune of crores of rupees. The financial burden/implications on the public

exchequer that the State may have to meet with if the Court directs issue of a

fresh tender notice, should be one of the guiding factors that the Court should

keep in mind. This is evident from a three-Judge Bench decision of this Court

in Association of Registration Plates v. Union of India and Others, reported

in (2005) 1 SCC 679.

53.The law relating to award of contract by the State and public sector

corporations was reviewed in Air India Ltd. v. Cochin International Airport

Ltd., reported in (2000) 2 SCC 617 and it was held that the award of a

contract, whether by a private party or by a State, is essentially a commercial

transaction. It can choose its own method to arrive at a decision and it is free

to grant any relaxation for bona fide reasons, if the tender conditions permit

such a relaxation. It was further held that the State, its corporations,

instrumentalities and agencies have the public duty to be fair to all concerned.

Even when some defect is found in the decision-making process, the court

must exercise its discretionary powers under Article 226 with great caution

and should exercise it only in furtherance of public interest and not merely on

the making out of a legal point. The court should always keep the larger public

interest in mind in order to decide whether its intervention is called for or not.

Only when it comes to a conclusion that overwhelming public interest

requires interference, the court should interfere.

54.As observed by this Court in Jagdish Mandal v. State of Orissa and

Others, reported in (2007) 14 SCC 517, that while invoking power of judicial

review in matters as to tenders or award of contracts, certain special features

should be borne in mind that evaluations of tenders and awarding of contracts

are essentially commercial functions and principles of equity and natural

justice stay at a distance in such matters. If the decision relating to award of

24

contract is bona fide and is in public interest, courts will not interfere by

exercising powers of judicial review even if a procedural aberration or error in

assessment or prejudice to a tenderer, is made out. Power of judicial review

will not be invoked to protect private interest at the cost of public interest, or

to decide contractual disputes.

55.In such circumstances referred to above, we set aside that part of the

judgment and order passed by the High Court by which the decision of BEST

to accept the tender of EVEY was set aside and it was left to the discretion of

BEST to undertake a fresh tender process.

56.The Appeal filed by TATA Motors accordingly fails and is hereby

dismissed. Whereas the Appeals filed by EVEY and BEST are allowed to the

aforesaid extent.

57.There shall be no order as to costs.

58.Pending application, if any, stands disposed of accordingly.

..…………….……………….CJI.

[Dr. Dhananjaya Y. Chandrachud]

……………..………………….J.

[Pamidighantam Sri Narasimha]

……….…………..…………….J.

[J. B. Pardiwala]

New Delhi;

May 19, 2023

25

Reference cases

Description

Legal Notes

Add a Note....