As per case facts, a dispute arose between M/S Ramacivil India Construction Pvt Ltd and Central Public Works Department regarding a construction project for IIM Jammu, leading the Petitioner to ...
ARB.P. 1787/2025 & connected matters Page 1 of 52
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 24.04.2026
Judgment pronounced on: 29.05.2026
+ ARB.P. 1787/2025, I.A. 30458/2025 (U/O 1 Rule 10), I.A.
8810/2026 (Delay of 1 day in filing of the chamber appeal),
O.A. 42/2026 (Seeking setting aside of the order dt.
23.01.2026 passed by the Ld. Joint Registrar (Judicial) &
REVIEW PET. 187/2026 (Filed on behalf of the R-2, Seeking
review of the order dt. 02.04.2026)
M/S RAMACIVIL INDIA CONSTRUCTION PVT LTD
THROUGH ITS AUTHORIZED REPRESENTATIVE
DIRECTOR SH R N GUPTA .....Petitioner
Through: Mr. Anurag Ahluwalia, Senior
Advocate along with Mr.
Avinash Trivedi, Mr. Dipanshu
Gaba, Ms. Ritika Trivedi, Mr.
Rahul Aggarwal, Mr. Anurag
Kaushik, Mr. Jatin Arora, Mr.
Rhythem Nagpal, Mr. Rishank
Gola and Mr. Aryan Sangwan,
Advocates.
versus
CENTRAL PUBLIC WORKS DEPARTMENT THROUGH
ITS ADDL DIRECTOR GENERAL .....Respondent
Through: Mr. Vikram Jetly, CGSC along
with Ms. Laavanya Kaushik,
GP, Ms. Shreya Jetly and Ms.
Khyaati Bansal, Advocates for
Respondent No. 1.
Mr. Rajshekhar Rao, Senior
Advocate along with Mr.
Praveen Kumar Jain, Ms.
Rashmi Kumari, Mr. Yash
Chauhan, Mr. Aditya Rathi, Mr.
Harshil Wason, Advocates
ARB.P. 1787/2025 & connected matters Page 2 of 52
along with Cmdr. Kesavan
Baskkaran (CAO, IIM Jammu)
for Respondent No. 2.
+ O.M.P.(I) (COMM.) 35/2025
RAMA CIVIL INDIA CONSTRUCTION PRIVATE LTD
THROUGH AUTHORIZED REPRESENTATIVE MR R N
GUPTA DIRECTOR .....Petitioner
Through: Mr. Vivek Narayan Sharma,
Ms. Mahima Bhardwaj
Kalucha, Mr. Akash Singh, Ms.
Palak Kaushik and Ms. Annika
Khurana, Advocates.
versus
CENTRAL PUBLIC WORKS DEPARTMENT JAMMU (J
AND K) REPRESENTED THROUGH THE EXECUTIVE
ENGINEER AND SENIOR MANAGER IIM JAMMU
PROJECT DIVISION & ANR. .....Respondents
Through: Mr. Vikram Jetly, CGSC along
with Ms. Laavanya Kaushik,
GP, Ms. Shreya Jetly and Ms.
Khyaati Bansal, Advocates for
Respondent No. 1.
+ O.M.P.(I) (COMM.) 447/2025, I.A. 26536/2025 (Dir.), I.A.
27193/2025 (Dir.), I.A. 30390/2025 (U/O 1 Rule 10), I.A.
8915/2026 (Delay of 1 day in filing of the chamber appeal),
O.A. 41/2026 (Seeking setting aside of the order dt.
23.01.2026 passed by the Ld. Joint Registrar (Judicial) &
REVIEW PET.190/2026 (U/S 114 R/W order XLVII and
Section 151 of the CPC Order dt. 02.04.2026)
M/S RAMACIVIL INDIA CONSTRUCTION PVT LTD
THROUGH ITS AUTHORIZED REPRESENTATIVE
DIRECTOR SH R N GUPTA .....Petitioner
Through: Mr. Anurag Ahluwalia, Senior
Advocate along with Mr.
Avinash Trivedi, Mr. Dipanshu
Gaba, Ms. Ritika Trivedi, Mr.
ARB.P. 1787/2025 & connected matters Page 3 of 52
Rahul Aggarwal, Mr. Anurag
Kaushik, Mr. Jatin Arora, Mr.
Rhythem Nagpal, Mr. Rishank
Gola and Mr. Aryan Sangwan,
Advocates.
versus
CENTRAL PUBLIC WORKS DEPARTMENT THROUGH
ITS ADDL DIRECTOR GENERAL .....Respondent
Through: Mr. Vikram Jetly, CGSC along
with Ms. Laavanya Kaushik,
GP, Ms. Shreya Jetly and Ms.
Khyaati Bansal, Advocates for
Respondent No. 1.
Mr. Rajshekhar Rao, Senior
Advocate along with Mr.
Praveen Kumar Jain, Ms.
Rashmi Kumari, Mr. Yash
Chauhan, Mr. Aditya Rathi, Mr.
Harshil Wason, Advocates
along with Cmdr. Kesavan
Baskkaran (CAO, IIM Jammu)
for Respondent No. 2.
+ O.M.P.(I) (COMM.) 484/2025, I.A. 29299/2025 (Stay), I.A.
29796/2025 (U/O 1 Rule 10), I.A. 29997/2025 (U/O 1 Rule 10),
I.A. 8914/2026 (Delay of 1 day in filing of the chamber
appeal), O.A. 40/2026 (Seeking setting aside of the order
dt. 23.01.2026 passed by the Ld. Joint Registrar
(Judicial) & REVIEW PET. 188/2026 (Filed on behalf of the
R-2, Seeking review of the order dt. 02.04.2026)
M/S RAMACIVIL INDIA CONSTRUCTION PVT. LTD
.....Petitioner
Through: Mr. Avinash Trivedi, Ms.
Ritika Trivedi, Mr. Rahul
Aggarwal, Mr. Anurag
Kaushik, Mr. Jatin Arora, Mr.
Rhythem Nagpal, Mr. Rishank
Gola and Mr. Aryan Sangwan,
Advocates.
ARB.P. 1787/2025 & connected matters Page 4 of 52
versus
CENTRAL PUBLIC WORKS DEPARTMENT .....Respondent
Through: Mr. Vikram Jetly, CGSC along
with Ms. Laavanya Kaushik,
GP, Ms. Shreya Jetly and Ms.
Khyaati Bansal, Advocates for
Respondent No. 1.
Mr. Rajshekhar Rao, Senior
Advocate along with Mr.
Praveen Kumar Jain, Ms.
Rashmi Kumari, Mr. Yash
Chauhan, Mr. Aditya Rathi, Mr.
Harshil Wason, Advocates
along with Cmdr. Kesavan
Baskkaran (CAO, IIM Jammu)
for Respondent No. 2.
CORAM:
HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
SHANKAR
J U D G M E N T
HARISH VAIDYANATHAN SHANKAR, J.
1. All four Petitions have been instituted by the same Petitioner,
namely, Ramacivil India Construction Pvt. Ltd., against the same
Respondent, namely, Central Public Works Department. Since the
Petitions arise out of the same factual background and emanate from a
common set of facts involving interconnected issues and overlapping
reliefs, with the consent of the parties, they were heard together and
are being disposed of by way of this common judgment.
ARB.P. 1787/2025 & connected matters Page 5 of 52
2. ARB.P. 1787/2025 has been filed, on 27.10.2025, under Section
11 of the Arbitration and Conciliation Act, 1996
1
, seeking the
following reliefs:
“(a) Reject the respondent’s nominee as appointed vide letter dated
24.10.2025 and appoint the Nominee Arbitrator on behalf of the
respondent strictly in accordance with the mandatory qualification
prescribed in Clause 25 of the GCC to adjudicate the dispute
between the parties arising out - of letter of- acceptance dated
16.10.2020 and agreement bearing no. 01/EE/CE cum
ED/IIM/2020-21 in favour of the petitioner and against the
respondent and in the interest of justice; And / Or;
(b) Direct the two nominee arbitrators to appoint the presiding
arbitrator within 30 days; And /Or;
(c) Cost of this petition may be allowed in favour of the petitioner and
against the respondents; And /Or;
…”
3. O.M.P.(I)(COMM.) 35/2025 has been filed, on 03.02.2025,
under Section 9 of the A&C Act, seeking the following reliefs:
“….
(a) Pass an ad-interim stay on the operation and execution of the
tender issued by the Respondent under NIT No. 02/NIT/CE
cum ED/JPZ/IIM/2024-25 (Recall) with tender opening date as
14.01.2025, pending the resolution of the disputes between the
parties through Arbitration;
(b) Pass an ad-interim Order appointing an independent 3
rd
body of
expert(s) or any other technical person as a court commissioner
to assess and verify:
i) the scope and extent of the works done by the
petitioner under its original EPC Contract and to
ascertain fresh NIT (Recall) was within Petitioner's
scope or is it an additional work that Respondent
wants to get executed;
ii) the inventory lying at the site and not included in
the recent inventory prepared pursuant to the joint
inspection conducted on 23
rd
January 2025, and
iii) the unauthorized use of the LV facilities erected by
the petitioner under the contract without any
corresponding payment, till the respondent issues
the taking over /completion certificate to the
petitioner and make the due payment.
1
A&C Act
ARB.P. 1787/2025 & connected matters Page 6 of 52
(c) Pass an ad-interim stay directing the Respondents to stop using
the LV facilities erected by the Petitioner under the contract,
till the respondent issues the taking over /completion certificate
to the Petitioner and making due payment;
(d) Pass an ad-interim stay thereby restraining the Respondents
from altering, modifying, adding, or removing any equipment,
device, software, or any other component in the already
designed and operational system executed by the Petitioner,
which may affect or disturb its operations, efficiency, or
efficacy till the adjudication of the present Application.
(e) Any other relief that this Hon'ble Court may deem fit and
proper in the facts and circumstances of the present case and in
the interest of justice.”
4. O.M.P.(I)(COMM.) 447/2025 has been filed, on 27.10.2025,
under Section 9 of the A&C Act, seeking the following reliefs:
“….
a) Pass an ex-parte order thereby restraining the Respondent from
passing any order in pursuance to the show cause dated
09.10.2025 (Document No. 77) consequently not to levy any
compensation under Clause 2 of the GCC since time has not
remained essence of contract during the pendency of the
arbitration proceedings; And/Or;
b) In-1alternative to Prayer (a) above, the Respondent be
restrained from enforcing any order if passed in pursuance to
show cause dated 09.10.2025 during the pendency of the
arbitration proceedings; And /Or;
c) Pass an order thereby restraining the respondent from taking
any further coercive action against the petitioner for the project
in question; And/Or;
d) Pass an order thereby directing the respondent to record
completion of the already completed/handed over buildings of
the project in terms of Clause 8 of the GCC as requested vide
letter dated 07.08.2024 (Document No. 26) of the petitioner;
And/ Or;
e) Pass an order thereby directing the Respondent to provide
documents as requested by the petitioner in Para 11.6 of the
reply dated 16.10.2025 to the show cause notice dated
09.10.2025 for filing of a complete reply by the petitioner;
And/Or;
f) Pass any other and further order(s) as are deemed fit and proper
in the facts and circumstances of the case and to meet the end
of justice in favour of the petitioner and against the
Respondent.”
ARB.P. 1787/2025 & connected matters Page 7 of 52
5. O.M.P.(I)(COMM.) 484/2025 has been filed, on 22.11.2025,
under Section 9 of the A&C Act, seeking the following reliefs:
“….
a) Pass an ex-parte order thereby restraining the Respondent from
passing any order in pursuance to the show cause notices dated
10.10.2025 (Document No. 87) and 17.11.2025 (Document No.
132) consequently not to terminate the contract without
complying with the provision of Clause l(v) of the GCC during
the pendency of the arbitration proceedings; And/Or;
b) In alternative to Prayer (a) above, the respondent be restrained
from enforcing any order if passed in pursuance to show cause
notices dated 10.10.2025 (Document No. 87) and 17.11.2025
(Document No. 132) without complying with the provision of
Clause l(v) of the GCC during the pendency of the arbitration
proceedings without complying with the provision of Clause
l(v) of the GCC during the pendency of the arbitration
proceedings; And/Or;
c) Pass an order thereby directing the respondent to conduct a
joint verification of the defects rectified by the petitioner in the
presence of an independent expert/local commissioner before
passing any final order pursuant to show cause notice dated
10.10.2025 and 17.11.2025; And/Or;
d) Pass an order thereby permitting the Petitioner to rectify the
defects if any within 60 days of the joint verification; And/or
e) Pass any other and further order(s) as are deemed fit and proper
in the facts and circumstances of the case and to meet the end
of justice in favour of the petitioner and against the
Respondent.”
BRIEF FACTS LEADING TO THE PRESENT
ADJUDICATION:
6. Shorn of unnecessary details, before proceeding to adjudicate
upon the issues involved in the present Petitions, the brief factual
background germane to the institution thereof may be summarised as
follows:
(a) The Petitioner herein is a company duly incorporated under the
Companies Act, 2013, and is an enlisted contractor in various
Government Departments, including the Respondent/CPWD.
ARB.P. 1787/2025 & connected matters Page 8 of 52
(b) The Petitioner was declared the successful bidder by CPWD for
the work of Construction of Permanent campus under Phase-
1 for IIM Jammu at Jagti Jammu, containing the work of
various nature
2
vide letter of acceptance dated 16.10.2020
3
.
(c) Upon the submission of a Bank Guarantee by the Petitioner, the
parties herein entered into an Agreement bearing No.
01/EE/CE-cum-ED/IIM/2020-21.
(d) Material on record indicates that the Agreement contains a
Dispute Resolution Clause, being Clause 25 of the GCC, which
stipulates the reference of disputes firstly to the Dispute
Redressal Committee
4
.
(e) It is stated that during the course of execution of the Project,
certain disputes arose between the Petitioner and the CPWD
concerning execution of the works, pending dues, delays,
defects, rectification works and contractual obligations under
the agreement.
(f) It is further stated that substantial portions of the project,
including academic, residential and infrastructure facilities,
were progressively handed over between July 2023 and June
2024 and the project campus was inaugurated on 20.02.2024.
(g) Material placed on record reflects that CPWD issued show
cause notices to the Petitioner in October-November, 2025
concerning alleged defects and deficiencies in the execution of
the works.
2
Project
3
Letter of Acceptance
4
DRC
ARB.P. 1787/2025 & connected matters Page 9 of 52
(h) Pursuant to the disputes that had arisen inter se the parties, the
Petitioner invoked Clause 25 of the GCC and initiated the
contractual dispute resolution mechanism.
(i) It is stated that following the failure to initiate the proceedings
before the DRC, disagreements arose between the parties
regarding the constitution of the learned Arbitral Tribunal,
including objections concerning the appointment and eligibility
of the nominee Arbitrators and the Presiding Arbitrator.
(j) Consequently, the Petitioner instituted ARB.P. 1787/2025 under
Section 11 of the A&C Act before this Court, seeking
appropriate reliefs in relation to the constitution of the Arbitral
Tribunal in terms of Clause 25 of the Agreement.
(k) In addition, the Petitioner also instituted, from time to time,
various proceedings under Section 9 of the A&C Act, being
OMP(I)(COMM.) 35/2025, OMP(I)(COMM.) 447/2025 and
OMP(I)(COMM.) 484/2025, seeking interim protection against
alleged coercive measures initiated by the CPWD.
(l) In the interregnum, and during the pendency of the aforenoted
Petitions, IIM Jammu moved applications under Order 1 Rule
10 read with Section 151 of the Code of Civil Procedure,
1908
5
, being I.A. 30458/2025, I.A. 30390/2025, and I.A. No.
29997/2025
6
, seeking impleadment as a respondent in the
petitions, being ARB.P. 1787/2025, O.M.P.(I)(COMM.)
447/2025 and O.M.P.(I)(COMM.) 484/2025, on the grounds,
inter alia, that IIM Jammu was the ultimate beneficiary of the
project, having funded the project works through CPWD and
5
CPC
6
Impleadment Applications
ARB.P. 1787/2025 & connected matters Page 10 of 52
having participated in review meetings and correspondence
concerning the execution of the project.
(m) The said Impleadment Applications came to be listed before the
learned Joint Registrar of this Court and came to be finally
allowed vide Order dated 23.01.2026
7
, thereby IIM Jammu
came to be impleaded as Respondent No. 2 in the said petitions.
(n) Aggrieved by the aforesaid Impleadment Orders passed by the
learned Joint Registrar, the Petitioner herein preferred the
Chamber Appeals before this Court, in the respective petitions,
assailing the legality and correctness thereof.
(o) The said Chamber Appeals preferred by the Petitioner came to
be allowed by this Court vide common Judgment dated
23.01.2026, whereby the Impugned Impleadment Orders passed
by the learned Joint Registrar were set aside and thereby IIM,
Jammu, was removed from the array of the parties.
(p) Being dissatisfied with the aforesaid common Judgment, IIM
Jammu preferred Appeals before the Division Bench of this
Court. The Division Bench, however, without entering into or
expressing any opinion on the merits of the rival contentions,
disposed of the said Appeals, vide Order dated 24.03.2026, in
the following terms:
“….
FAO(OS) 32/2026, FAO(OS) (COMM) 62/2026 &
FAO(OS) (COMM) 63/2026
3. The present appeals have been preferred under Section
10 of the Delhi High Court Act, 1966, impugning the
common Order dated 19.02.2026 passed by the learned
Single Judge in O.A. No. 42/2025, O.A. No. 41/2025 and
O.A. No. 40/2025, filed by Respondent No.1 in ARB.P.
7
Impleadment Order
ARB.P. 1787/2025 & connected matters Page 11 of 52
No. 1787/2025, OMP (I) (COMM.) No. 447/2025 and
OMP (I) (COMM.) No. 484/2025, respectively.
4. Learned counsel appearing for the appellant submits
that the appeals preferred before the learned Single Judge
impugns the Separate Orders passed by the learned Joint
Registrar on 23.01.2026. In terms of the applicable Delhi
High Court Rules, such appeals were required to be filed
within 15 days, i.e., on or before 04:00 PM on 07.02.2026.
However, the same came to be filed only at 10:47 PM on
the said date, resulting in a delay of at least 01 day. It is
contended that no application seeking condonation of
delay accompanied the said appeals, and yet, without
condoning the delay, the learned Single Judge proceeded
to allow the said appeals.
5. Per Contra, learned counsel for the respondents raises a
preliminary objection with regard to the maintainability of
present appeals.
6. At this stage, after advancing some arguments, learned
counsel for the parties agree that, without going into the
merits of the matter, or adjudicating upon the issue of
maintainability, the ends of justice would be met if the
matter is remanded back to the learned Single Judge. It is
agreed that the Respondent No.1 shall move an
appropriate application seeking condonation of delay in
support of the said appeals preferred before the learned
Single Judge against the Separate Orders dated
23.01.2026.
7. It is further agreed that the learned counsel for the
appellant shall be at liberty to file a reply to the said
application in the shortest possible time. Thereafter, the
learned Single Judge may decide the applications for
condonation of delay and the said appeals, in accordance
with the law.
8. In view of the aforesaid consensus and without
expressing any opinion on the merits of the case or the
issue of maintainability, the Impugned Orders dated
19.02.2026 are set aside, with the aforesaid directions.
9. The present appeals stand disposed of in the above
terms and the said appeals are restored before the learned
Single Judge to their original number.”
(emphasis supplied)
(q) Pursuant to the restoration of the Chamber Appeals in terms of
the order passed by the Division Bench, the Petitioner filed
ARB.P. 1787/2025 & connected matters Page 12 of 52
appropriate applications in the said Chamber Appeals seeking
condonation of the delay of one day in their institution.
(r) In view thereof, and as a necessary sequitur, this Court is first
required to adjudicate upon the applications seeking
condonation of delay in filing the Chamber Appeals. Only upon
such delay being condoned, if permissible in law, would this
Court proceed to examine the merits of the Chamber Appeals in
the abovementioned three Petitions.
(s) The ultimate adjudication upon the merits of the present four
petitions would thereafter necessarily depend upon and follow
the outcome rendered in those Chamber Appeals.
(t) Since subsequently elaborate submissions were addressed
before this Court not only in relation to the applications seeking
condonation of delay and the merits of the Chamber Appeals,
but also with respect to the substantive issues arising in the
present four petitions, this Court considers it appropriate to
examine and adjudicate all such issues comprehensively in this
common order in the sequence noted hereinabove.
I.A. 8810/2026 (Delay of 1 day in filing of the Chamber Appeal) in
O.A. 42/2026 in ARB.P. 1787/2025
I.A. 8915/2026 (Delay of 1 day in filing of the Chamber Appeal) in
O.A. 41/2026 in O.M.P.(I) (COMM.) 447/2025
I.A. 8914/2026 (Delay of 1 day in filing of the Chamber Appeal) in
O.A. 40/2026 in O.M.P.(I)(COMM.) 484/2025
7. The Chamber Appeals, being O.A. 42/2026, O.A. 41/2026 and
O.A. 40/2026, under Rule 5, Chapter II of the Delhi High Court
ARB.P. 1787/2025 & connected matters Page 13 of 52
(Original Side) Rules, 2018
8
, read with Section 151 of the CPC, have
been filed seeking to challenge the Impleadment Orders passed by the
learned Joint Registrar in the respective petitions.
8. Pursuant to the Order dated 24.03.2026 passed by the Division
Bench of this Court in FAO(OS) 32/2026, FAO(OS) (COMM)
62/2026 & FAO(OS) (COMM) 63/2026, the Applications, being I.A.
8810/2026, I.A. 8915/2026 and I.A. 8914/2026, have been filed, in the
respective Chamber Appeals, under Section 5 of the Limitation Act,
1963
9
read with Section 151 of the CPC, seeking the condonation of
the delay of one day in filing those Chamber Appeals.
9. At the very outset, this Court considers it appropriate to first
adjudicate upon the applications seeking condonation of the delay of
one day in filing the present Chamber Appeals. Before proceeding to
examine the merits of the said applications, this Court shall record and
consider the rival submissions advanced on behalf of the respective
parties in relation thereto, hereinafter.
Submissions on behalf of the Parties:
10. Learned Senior Counsel appearing on behalf of IIM Jammu
raises a preliminary objection on the Applications seeking
condonation of delay.
11. He would seek to challenge the maintainability of the
Applications on the ground that, firstly, the Impleadment Order that
came to be passed by the learned Joint Registrar was done while
exercising its power that came to be delegated by this Court. It would
be submitted that since the learned Joint Registrar was acting upon the
powers delegated by this Court, the Impleadment Orders have to be
8
Original Side Rules
9
Limitation Act
ARB.P. 1787/2025 & connected matters Page 14 of 52
construed as orders that have come to be passed by this Court itself,
and therefore, this Court cannot sit in appeal over such Orders that
essentially, as per the learned Senior Counsel for IIM Jammu, are
passed by this Court itself.
12. The second ground that the learned Senior Counsel for IIM
Jammu would seek to canvass is that the Original Side Rules do not
expressly provide for condonation of delay in filing the Chamber
Appeal, nor does it expressly provide that the Limitation Act would be
applicable to the Original Side Rules.
13. It would be contended that the Original Side Rules constitute a
complete and self-contained procedural code governing proceedings
on the Original Side of this Court and, therefore, the applicability of
the provisions of the Limitation Act stands excluded either expressly
or by necessary implication.
14. It would further be argued that where the Rules prescribe a
specific procedure, timeline, or remedy, the same must be strictly
adhered to and cannot be supplemented by recourse to the general
provisions of the Limitation Act.
15. In essence, the submission would be that the Original Side
Rules, being a special procedural framework framed in exercise of
statutory powers, prevail over the general law of limitation, and
consequently, provisions such as Section 5 of the Limitation Act
would not stand attracted unless specifically incorporated.
16. The learned Senior Counsel would further argue that the
Chamber Appeals under Chapter II Rule 5 of the Original Side Rules
is not an ordinary statutory appeal. It is a sui generis internal appellate
ARB.P. 1787/2025 & connected matters Page 15 of 52
mechanism, created by the said Rules, against specified procedural
orders of the learned Registrar passed under Chapter II Rule 3.
17. He would submit that if such a remedy is permitted to be filed
at any indefinite future point through Section 5 of the Limitation Act,
or by resort to any of the inherent powers conferred upon this Court,
the inevitable consequence would be that every order passed by the
learned Registrar would remain vulnerable to challenge ad infinitum,
without there being a definitive bar to preferring the same.
18. It would further be argued that a perusal of the Original Side
Rules would indicate that the intent of the said Rules to provide for
“flexibility” is expressed equivocally wherever the lawmakers
intended to do so.
19. A comparison would be sought to be made with Chapter VII
Rule 4, where the right to file a Written Statement stands closed
within the time prescribed, being 30 days and upon showing sufficient
cause, the same can be extended up to 90 days, but not thereafter.
This, as would be submitted by the learned Senior Counsel, clearly
shows that, if intended, the flexibility has been granted within the
Original Side Rules itself and since Chapter II Rule 5 only provides
for a period of 15 days, it indicates that the statute does not provide
for such a flexibility to be extended to the litigant who chose to sleep
over its rights within the time prescribed to prefer a Chamber Appeal
as per the provisions therein.
20. To further buttress his argument, he would seek to rely upon the
judgments of this Court passed by the Division Bench in Ram Sarup
ARB.P. 1787/2025 & connected matters Page 16 of 52
Lugani v Nirmal Lugani
10
and CM Corps Ltd. v Rani Kapoor and
Others
11
.
21. Learned Senior Counsel for IIM Jammu would also seek to
place reliance upon the judgement of the Hon’ble Supreme Court in
CCE & Customs v. Hongo India (P) Ltd.
12
to contend that the ratio
laid down in the said judgement squarely applies to the present case
and that the Original Side Rules create the remedy, prescribe the
limitation, and consciously do not confer the power to condone the
delay under Chapter II Rule 5, and therefore, Section 5 of the
Limitation stands excluded by necessary implication.
22. On a demurrer, learned Senior Counsel would also submit that
the said Chamber Appeals, which have been filed belatedly, cannot be
salvaged by invoking the inherent powers under Chapter I Rule 16 of
the Original Side Rules or under Section 151 of the CPC. He would
submit that it is well settled that inherent powers may supplement
procedure where there is a genuine vacuum. They cannot be used to
defeat the structure of rules or to override a deliberate omission.
23. It would therefore be argued that once Section 5 of the
Limitation Act stands excluded and no independent power of
condonation exists under the Original Side Rules, this Court cannot
inquire into the sufficiency of the cause shown. The defect is not
merely procedural; it would be submitted that it is jurisdictional.
Therefore, it would be contended that the said Chamber Appeals,
having been instituted beyond the prescribed period of fifteen days,
10
2020 SCC OnLine Del 1353
11
2025 SCC OnLine Del 9838
12
(2009) 5 SCC 791
ARB.P. 1787/2025 & connected matters Page 17 of 52
are not maintainable and are liable to be dismissed in limine at the
threshold.
24. Per contra, learned Senior Counsel appearing on behalf of the
Applicant would submit that the objections sought to be raised by the
non-applicant proceed on a fundamentally misconceived
understanding of the nature of the jurisdiction exercised by the learned
Joint Registrar as well as the scope and operation of the Original Side
Rules.
25. It would be submitted that the contention that the present
Chamber Appeals are not maintainable since the learned Joint
Registrar exercises powers delegated by this Court is wholly
untenable.
26. Learned Senior Counsel would contend that the very existence
of Chapter II Rule 5 of the Original Side Rules itself demolishes the
said submission, inasmuch as the Rules expressly contemplate a
remedy by way of Chamber Appeal against specified orders passed by
the learned Joint Registrar. Once the Rules themselves create a
statutory intra-court remedy against such orders, it is not open for the
non-applicant to contend that this Court cannot examine the
correctness of the same.
27. It would further be submitted that the learned Joint Registrar,
though exercising powers delegated by this Court, nevertheless
functions as a distinct procedural authority under the scheme of the
Original Side Rules, and the Chamber Appeal is nothing but a
continuation of the supervisory jurisdiction expressly preserved under
the Rules themselves.
ARB.P. 1787/2025 & connected matters Page 18 of 52
28. Learned Senior Counsel for the Applicants would further
submit that the argument seeking exclusion of Section 5 of the
Limitation Act is equally devoid of merit. It would be contended that
exclusion of the provisions of the Limitation Act cannot be readily
inferred and must either be expressly provided or flow by necessary
implication from the statutory framework.
29. According to the learned Senior Counsel, neither the Original
Side Rules nor the Delhi High Court Act, 1966, contains any
provision expressly barring the applicability of Section 5 of the
Limitation Act to Chamber Appeals preferred under Chapter II Rule 5.
To further buttress his argument, he would seek to rely upon the
judgment of the Hon’ble Supreme Court in State of Maharashtra v.
Borse Bros. Engineers & Contractors (P) Ltd.
13
.
30. It would further be argued that the Original Side Rules are
merely procedural rules framed by this Court in exercise of delegated
rule-making powers and do not constitute a self-contained code so as
to completely oust the operation of the general law of limitation.
31. The Rules, it would be submitted, regulate procedure and
practice on the Original Side; however, they do not create substantive
rights in derogation of statutory enactments such as the Limitation
Act. In the absence of an express exclusionary clause, the provisions
of the Limitation Act would continue to apply, particularly where the
consequence sought to be imposed is the extinguishment of a vested
remedy of appeal.
32. Learned Senior Counsel would submit that the reliance placed
by IIM Jammu upon the judgment in Hongo India (supra) is
13
(2021) 6 SCC 460
ARB.P. 1787/2025 & connected matters Page 19 of 52
misplaced and wholly distinguishable. It would be argued that the said
judgment arose in the context of a special fiscal statute where the
legislature itself had prescribed a rigid and peremptory limitation
regime and consciously excluded the applicability of Section 5 of the
Limitation Act. In contradistinction, the Original Side Rules are not a
parliamentary enactment creating a special statutory tribunal with
restricted jurisdiction. Rather, they are procedural rules framed for
regulating the internal administration and procedure of this Court. It
would therefore be submitted that the ratio of Hongo India (supra)
cannot be mechanically imported into the present case.
33. Learned Senior Counsel would further contend that the mere
prescription of a limitation period under Chapter II Rule 5 does not,
ipso facto, amount to exclusion of Section 5 of the Limitation Act. It
would be submitted that Section 5 itself employs language of the
widest possible amplitude by providing that “any appeal” or “any
application”, other than those specifically excluded, may be admitted
after the prescribed period upon sufficient cause being shown.
34. According to the learned Senior Counsel, the legislature
consciously employed the expression “any appeal” without restricting
the same only to appeals arising under specific parliamentary
enactments. In the present case, the Chamber Appeal contemplated
under Chapter II Rule 5 is unquestionably an appellate remedy created
under the Rules against orders passed by the learned Registrar and
therefore squarely falls within the ambit of the expression “any
appeal” occurring under Section 5 of the Limitation Act.
35. It would be argued that once the lawmakers have neither
expressly excluded the applicability of Section 5 nor employed any
ARB.P. 1787/2025 & connected matters Page 20 of 52
prohibitory language restricting the power of condonation, the
ordinary operation of Section 5 must necessarily continue to apply.
36. Learned Senior Counsel would also submit that any
interpretation seeking to curtail the scope of the expression “any
appeal” would amount to judicially reading limitations into the statute
which the legislature itself has consciously refrained from imposing.
37. It would further be submitted that if the lawmakers intended to
completely prohibit condonation of delay, the Rules would have
expressly employed language indicating a peremptory embargo, as has
been done in several statutory schemes where the legislature
consciously restricts the power of extension beyond a prescribed
period.
38. The absence of such restrictive language, according to the
learned Senior Counsel, is significant and indicative of the fact that
the Rules never intended to exclude the general discretionary
jurisdiction of this Court to condone marginal delays upon sufficient
cause being shown.
39. Insofar as the comparison sought to be drawn with Chapter VII
Rule 4 is concerned, learned Senior Counsel would submit that the
same, in fact, militates against the case sought to be set up by IIM
Jammu. It would be argued that Chapter VII Rule 4 pertains to the
filing of Written Statements in commercial causes, where strict
timelines have been statutorily engrafted pursuant to the amendments
introduced under the Commercial Courts Act, 2015, and the CPC. The
same operate in a wholly distinct field and derive their rigidity from a
statutory mandate. The absence of similar restrictive language under
Chapter II Rule 5 would therefore clearly demonstrate that no absolute
ARB.P. 1787/2025 & connected matters Page 21 of 52
embargo upon condonation was intended in respect of Chamber
Appeals.
40. It would further be submitted that the power of this Court to
condone delay also inheres in its plenary procedural jurisdiction
preserved under Section 151 of the CPC as well as Chapter I Rule 16
of the Original Side Rules.
41. Learned Senior Counsel would submit that procedural rules are
handmaidens of justice and cannot be interpreted in a manner that
defeats substantive adjudication, particularly where the delay involved
is merely of one day and no prejudice whatsoever is demonstrated to
have been caused to the non-applicant.
42. Learned Senior Counsel for the Applicant would also submit
that the objection raised by the non-applicant is hyper-technical and
seeks to elevate procedure above substance. It would be contended
that the Chamber Appeals had, in fact, already been entertained and
adjudicated upon by this Court earlier and the Division Bench, while
remanding the matter, never held that the delay was incapable of being
condoned. On the contrary, the Division Bench merely directed that
appropriate applications seeking condonation be filed and adjudicated
first. It would therefore be submitted that the very remand order
proceeds on the implicit recognition that this Court possesses the
jurisdiction to examine and condone the delay, if sufficient cause
exists.
43. It would also be submitted that the present Applications
disclose sufficient cause within the meaning of Section 5 of the
Limitation Act; that the delay is minimal, bona fide, and wholly
ARB.P. 1787/2025 & connected matters Page 22 of 52
unintentional; and that refusal to condone the delay would result in
grave prejudice by shutting out adjudication on merits.
44. Lastly, it would also be submitted by the learned Senior
Counsel for the Applicant that even though the Impleadment Order
came to be passed by the learned Registrar on 23.01.2026, it only
came to be signed and uploaded on the website of this Court on
24.01.2026, where the complete order came to be made available to
the parties. Seen from the date of signing and uploading of the said
Order, the Chamber Appeals, filed on 07.02.2026, are within the
prescribed period of 15 days and therefore are not filed belatedly.
Analysis:
45. This Court has heard the learned Senior Counsel appearing on
behalf of the parties and, with their able assistance, perused the record.
46. The controversy that arises for consideration in the present
Applications is narrow and lies within a limited compass, namely,
whether the delay of one day in filing the present Chamber Appeals
under Chapter II Rule 5 of the Original Side Rules is capable of being
condoned by this Court.
47. The preliminary objection raised by IIM Jammu proceeds on
two broad limbs: firstly, that the Chamber Appeals themselves are not
maintainable since the order impugned therein is an order passed by
the learned Joint Registrar while exercising delegated powers of this
Court; and secondly, that the Original Side Rules constitute a self-
contained procedural code which excludes, either expressly or by
necessary implication, the applicability of Section 5 of the Limitation
Act.
ARB.P. 1787/2025 & connected matters Page 23 of 52
48. Insofar as the first objection is concerned, this Court finds itself
wholly unable to accept the same. Chapter II Rule 5 of the Original
Side Rules expressly contemplates and preserves a remedy by way of
Chamber Appeal against specified orders passed by the Registrar/Joint
Registrar. The very existence of such a provision is indicative of the
intent that orders passed by the learned Registrar or Joint Registrar are
not intended to attain unquestionable finality and remain amenable to
judicial scrutiny by the Court. Once the Rules themselves create an
appellate or supervisory mechanism against such orders, it would be
wholly impermissible to contend that this Court lacks the authority to
examine the correctness thereof.
49. The submission of the non-applicant proceeds upon an incorrect
conflation between the delegation of power and the identity of the
forum. Merely because the learned Joint Registrar exercises powers
delegated by this Court does not mean that every order passed by the
learned Joint Registrar assumes the character of a judicial
determination rendered by the Court itself. Delegation of procedural
powers is an administrative and functional device intended to facilitate
the efficient conduct of proceedings and streamline judicial
administration. However, the authority exercised by the learned Joint
Registrar remains circumscribed by the framework of delegation and
continues to be subject to the supervisory and corrective jurisdiction
expressly retained by this Court under the Rules.
50. If the submission canvassed by IIM Jammu were to be
accepted, the inevitable consequence would be that Chapter II Rule 5
itself would stand rendered otiose and nugatory.
ARB.P. 1787/2025 & connected matters Page 24 of 52
51. A settled principle of interpretation requires that a statutory
provision or rule must be construed in a manner that gives meaningful
effect to it and not in a manner that renders it redundant or
superfluous. The Court cannot adopt an interpretation which
effectively nullifies an express remedy consciously created under the
Rules themselves.
52. The Chamber Appeal mechanism under Chapter II Rule 5 is not
an ornamental or illusory remedy. It constitutes an integral part of the
procedural architecture of the Original Side Rules whereby judicial
oversight over procedural and interlocutory determinations made by
the Registrar/Joint Registrar is preserved. The said mechanism ensures
that parties aggrieved by orders passed in exercise of delegated
authority are not left remediless and that procedural determinations
remain subject to scrutiny by the Court. Therefore, the argument that
this Court cannot “sit in appeal” over an order passed by the learned
Joint Registrar fundamentally misunderstands the very nature and
purpose of the appellate framework expressly embedded in the Rules.
53. Further, the use of the expression “appeal” under Chapter II
Rule 5 itself carries significance. The draftspersons were fully
conscious that the orders impugned therein would emanate from the
exercise of delegated powers of the Court and yet consciously created
a remedy permitting an appellate remedy. Thus, the jurisdiction
exercised by this Court in a Chamber Appeal is not an exercise of
sitting in appeal over its own order, but rather an exercise of
jurisdiction expressly preserved against determinations rendered by a
delegate functioning under the procedural scheme of the Rules.
ARB.P. 1787/2025 & connected matters Page 25 of 52
54. Therefore, this Court finds no merit in the preliminary objection
raised by IIM Jammu. The contention, if accepted, would not only
defeat the plain language of Chapter II Rule 5 but would also denude
litigants of a remedy specifically conferred upon them under the
Original Side Rules. Such an interpretation cannot be countenanced
either on principle or on a plain reading of the Rules.
55. At this point, this Court also take note of the fact that the Rule
is not under challenge and the submissions advanced would
encompass and be subsumed in a challenge to the Rules itself and this
Court, in the exercise of its jurisdiction under the Rules, cannot
conduct the exercise of a determination of what, in essence, is a
substantive challenge to the Rule while exercising the jurisdiction
conferred under the Rule.
56. This Court also finds no merit in the submission that the
provisions of Section 5 of the Limitation Act stand excluded in
relation to Chamber Appeals preferred under Chapter II Rule 5.
57. It is a settled principle of law that exclusion of the Limitation
Act is not to be readily inferred. Such exclusion must either be express
or arise by necessary implication from the statutory framework. Mere
prescription of a period of limitation does not, by itself, amount to
exclusion of the power to condone delay.
58. A careful perusal of the Original Side Rules reveals no
provision expressly barring the applicability of Section 5 of the
Limitation Act. Equally, this Court is unable to discern any necessary
implication flowing from the scheme of the Rules so as to conclude
that the lawmakers intended to altogether exclude the discretionary
jurisdiction of this Court to condone delay in appropriate cases.
ARB.P. 1787/2025 & connected matters Page 26 of 52
59. The submission that the Original Side Rules constitute a
complete and self-contained code also does not commend acceptance.
The said Rules are procedural in character and have been framed to
regulate practice and procedure on the Original Side of this Court.
They do not possess the status of a special parliamentary enactment
creating substantive rights coupled with rigid exclusionary limitation
provisions. In the absence of an express legislative bar, the general
principles embodied under the Limitation Act cannot be held to stand
displaced merely by implication.
60. The reliance placed by the non-applicant upon the judgment of
Hongo India (supra) is misconceived. The said decision arose in the
context of a special fiscal statute where the legislature had consciously
enacted a strict and exhaustive limitation regime. The observations
made therein cannot be mechanically extended to procedural rules
framed by this Court for internal administration and regulation of
proceedings on the Original Side.
61. This Court also finds substance in the submission advanced on
behalf of the Applicant that the comparison sought to be drawn with
Chapter VII Rule 4 of the Original Side Rules, in fact, undermines the
case of the non-applicant itself. Wherever the lawmakers intended to
impose a rigid and inflexible embargo, the same has been expressly
articulated in clear language. No such restrictive or prohibitory
language finds place under Chapter II Rule 5. The absence thereof
assumes significance and militates against the contention that the
power of condonation stands excluded.
62. Insofar as the reliance placed by the learned Senior Counsel for
IIM Jammu upon the judgment of the Division Bench of this Court in
ARB.P. 1787/2025 & connected matters Page 27 of 52
Ram Sarup Lugani (supra) is concerned, this Court finds the same to
be clearly distinguishable and inapplicable to the facts of the present
case.
63. The decision in Ram Sarup Lugani (supra) turned upon the
interpretation of a provision which itself employed express
exclusionary language by stipulating that the prescribed period could
be extended “but not thereafter”. It was in the backdrop of such
peremptory and prohibitory language that the Division Bench came to
hold that the power to condone delay beyond the statutorily prescribed
outer limit stood excluded.
64. The present case stands on an entirely different footing. Chapter
II Rule 5 of the Original Side Rules merely prescribes a period of
limitation of fifteen days for filing a Chamber Appeal. Significantly,
the said provision does not contain any restrictive expression akin to
“but not thereafter”, nor does it prescribe any absolute outer limit
beyond which the delay becomes incurable. The absence of such
exclusionary phraseology assumes considerable significance. It is a
settled principle that where the legislature or the rule-making authority
intended to place an absolute embargo upon extension of time, it has
consciously done so in express terms.
65. Thus, the very foundation upon which the judgment in Ram
Sarup Lugani (supra) proceeded is absent in the present case. The
reliance placed thereupon by IIM Jammu is therefore misconceived.
Rather, the omission of any restrictive phrase such as “but not
thereafter” under Chapter II Rule 5 militates against the contention
that the applicability of Section 5 of the Limitation Act stands
excluded by necessary implication. In the absence of any such express
ARB.P. 1787/2025 & connected matters Page 28 of 52
or implied prohibition, this Court finds no reason to deny recourse to
the beneficial and enabling provisions of Section 5 of the Limitation
Act, particularly where the delay involved is merely of one day.
66. This Court cannot lose sight of the fact that the delay involved
in the present matter is merely of one day. The law relating to
condonation of delay is founded upon advancement of substantial
justice and not upon punishing litigants for marginal procedural
lapses. Unless gross negligence, deliberate inaction, or mala fides are
demonstrated, Courts ought to lean in favour of adjudication on merits
rather than shutting the doors of justice on technical considerations.
67. Insofar as the contention advanced on behalf of IIM Jammu is
concerned, namely that permitting such Chamber Appeals to be
entertained beyond the prescribed period of limitation, in the absence
of any express enabling provision for condonation of delay, would
open the floodgates for parties to file appeals at any point of time after
a prolonged delay and thereby render the orders passed by the learned
Joint Registrar perpetually vulnerable, this Court is of the considered
opinion that the said contention is wholly misconceived.
68. The power of condonation of delay under Section 5 of the
Limitation Act is neither unbridled nor automatic. The benefit thereof
can be availed only by a party that is able to satisfactorily establish the
existence of “sufficient cause” preventing it from approaching the
Court within the prescribed period of limitation. The principles
governing the interpretation and application of the expression
“sufficient cause” are no longer res integra and have been consistently
settled through judicial pronouncements, which require the Court to
ARB.P. 1787/2025 & connected matters Page 29 of 52
examine the facts and circumstances of each case with due regard to
bona fides, diligence and absence of deliberate inaction.
69. Therefore, the apprehension expressed by IIM Jammu that
recognition of the power to condone delay would permit filing of
appeals at any indefinite stage, irrespective of the length or nature of
delay, is unfounded and contrary to the settled legal position.
Consequently, this Court finds no merit in the said submission.
Conclusion:
70. In view of the aforesaid discussion, this Court is satisfied that
sufficient cause has been shown by the Applicants for condonation of
the delay of one day in filing the Chamber Appeals in the respective
Petitions. The present Applications are accordingly allowed, and the
delay in filing the Chamber Appeals stands condoned.
71. The Applications are disposed of in the aforesaid terms.
O.A. 42/2026 in ARB.P. 1787/2025
O.A. 41/2026 in O.M.P.(I) (COMM.) 447/2025
O.A. 40/2026 in O.M.P.(I) (COMM.) 484/2025
72. Since this Court has found the delay in filing the present
Chamber Appeals to be liable to be condoned, this Court now
proceeds to adjudicate upon the Chamber Appeals on their merits,
which have been preferred assailing the Impugned Impleadment
Orders passed by the learned Joint Registrar.
73. This Court notes that the reliefs sought in the aforesaid
Chamber Appeals are identically framed and essentially challenge the
separate Orders dated 23.01.2025 passed by the learned Joint
Registrar (Judicial) of this Court, whereby I.A. 30458/2025, I.A.
ARB.P. 1787/2025 & connected matters Page 30 of 52
30390/2025 and I.A. 29997/2025 were allowed, leading to the
impleadment of IIM Jammu/Applicant therein, as a party to the
proceedings instituted under Sections 9 and 11 of the A&C Act.
74. It is not in dispute that the reasoning adopted by the learned
Joint Registrar in the respective Impugned Orders, while allowing the
aforesaid applications, is materially identical.
75. In view of the fact that the present set of matters arises from
Orders of a similar character and involves common questions for
determination, this Court, for the purposes of convenience, brevity
and consistency, proposes to refer to the facts of O.A. 42/2026, which
is filed in ARB.P. 1787/2025, save and except where the context may
otherwise require.
76. The principal challenge raised by the Appellant before this
Court proceeds on the assertion that there exists no privity of contract
between the Petitioner and IIM Jammu.
77. Learned Senior Counsel appearing for the Petitioner would
submit that although IIM Jammu may be the principal beneficiary of
the project, the tender in question was floated by the CPWD, pursuant
to which the agreement came to be executed exclusively between the
Petitioner and CPWD. It would, thus, be contended that there exists
no contractual relationship between the Petitioner and IIM Jammu so
as to justify its impleadment in the present proceedings.
78. Per contra, learned Senior Counsel appearing on behalf of the
impleaded party, being IIM Jammu, would submit that IIM Jammu is
both a necessary and proper party to the present proceedings. It would
be contended that IIM Jammu is the principal entity for whose benefit
the project is being executed and that all financial disbursements
ARB.P. 1787/2025 & connected matters Page 31 of 52
towards the works carried out by the Petitioner emanate from IIM
Jammu.
79. Learned Senior Counsel for IIM Jammu would further submit
that the institution is the ultimate beneficiary of the works executed
and has played a substantive role in the overall decision-making
process relating to the execution of the project. To further buttress this
argument, he would seek to rely upon the minutes of various
meetings, which reveal that the same were chaired by the Director of
IIM Jammu, thereby indicating the dominant role allegedly played by
IIM Jammu in the execution and supervision of the project and
consequently, justifying its impleadment.
80. Reliance would also be placed upon a communication dated
19.11.2025 to contend that the Petitioner itself had approached IIM
Jammu seeking intervention and assistance in relation to disputes that
had arisen between the Petitioner and CPWD.
81. This Court has heard learned Senior Counsel appearing on
behalf of the parties and, with their able assistance, carefully
examined the material placed on record.
82. The sum and substance of the issue that arises for consideration
before this Court concerns the contours and permissibility of arbitral
participation by entities that are admittedly non-signatories to the
underlying Agreement and seek participation primarily on the basis
that they are the ultimate beneficiaries.
83. Upon a comprehensive consideration of the factual matrix, this
Court is of the considered opinion that IIM Jammu remains a non-
signatory to the agreement which forms the substratum of the present
ARB.P. 1787/2025 & connected matters Page 32 of 52
disputes. The contracts giving rise to the present lis stand executed
exclusively between the Petitioner and CPWD.
84. Acceptance of the submissions advanced on behalf of IIM
Jammu would result in far-reaching consequences. If the mere status
of being a principal entity or beneficiary of a project were held
sufficient to justify impleadment, then in every arbitration arising
from layered or delegated governmental projects, principal institutions
at multiple levels would necessarily have to be impleaded, thereby
disturbing the settled principle of party autonomy which forms the
bedrock of the A&C Act.
85. It is a matter of common commercial practice, particularly in
governmental projects, that principal institutions entrust execution to
specialised agencies such as CPWD, which alone undertake the
tendering process and execute agreements with contractors.
Contractors, in turn, perform works and raise bills strictly within the
contractual framework entered into with the tendering authority. The
legal relationship is thus defined by the instrument executed and not
by the identity of the ultimate institutional beneficiary.
86. In the present case, IIM Jammu had entered into a
Memorandum of Understanding dated 09.03.2019 with CPWD for the
execution of construction works pertaining to its proposed campus.
87. Pursuant thereto, CPWD issued a tender acceptance letter dated
16.10.2020 for the construction and maintenance of the academic
block of the proposed campus of IIM Jammu.
88. The disputes that have arisen emanate solely from the
agreement subsequently executed between the Petitioner and the
ARB.P. 1787/2025 & connected matters Page 33 of 52
CPWD, and the arbitration clause invoked in the present proceedings
is traceable only to the said agreement.
89. At the outset, it is pertinent to note that the scheme of the A&C
Act proceeds on the premise that every arbitration agreement operates
within the confines of the particular contract and the parties thereto.
Even where disputes may appear factually interconnected, the Court,
while exercising jurisdiction under Section 11 of the A&C Act, is
required to independently examine the existence of an arbitration
agreement in respect of each distinct contract.
90. The statutory framework does not contemplate a composite or
omnibus arbitral reference merely because multiple transactions may
be interlinked. The legal position in this regard has been succinctly
explained by this Court in Arunachalam Chandrasekharan and Ors
v. Concept Capital Infra Project Pvt. Ltd and Anr
14
, which reads as
under:
“8. At the outset, it is apposite to note that the Hon’ble Supreme
Court in Duro Felguera, S.A. v. Gangavaram Port Ltd. has
categorically held that where parties have entered into multiple
independent contracts, each containing a separate arbitration
clause, a single arbitral tribunal cannot be constituted to adjudicate
disputes arising out of all such contracts. The Apex Court, while
considering the provisions of the Act, held that the Court’s
jurisdiction at the stage of appointment of an arbitrator is confined
to examining the existence of an arbitration agreement.
9. In that case, which concerned five separate contracts, each
dealing with distinct subject matters and containing independent
arbitration clauses, the Hon’ble Supreme Court held that there
could not be a “composite reference” or the constitution of a single
arbitral tribunal to adjudicate disputes arising under all such
contracts, notwithstanding any interconnection between them. The
relevant portion of Duro Felguera (supra) is extracted herein
under:
“22. On behalf of GPL, it was repeatedly urged that the
works are intrinsically connected, inseparable, integrated,
interlinked and that they are one composite contract and
14
2026:DHC:1364
ARB.P. 1787/2025 & connected matters Page 34 of 52
that they were split up only on the request and
representations given by Duro Felguera and FGI. As
discussed earlier, as per amended provision Section 11(6-
A), the power of the Supreme Court or the High Court is
only to examine the existence of an arbitration agreement.
From the record, all that we could see are five separate
letters of award; five separate contracts; separate subject-
matters; separate and distinct work; each containing
separate arbitration clause signed by the respective parties
to the contract.
23. All the above five contracts awarded to Duro Felguera
and FGI have independent arbitration clauses. Mr Sunil
Gupta and Mr A.M. Singhvi, learned Senior Counsel have
taken us through the contract agreements in New Package
No. 4 awarded to M/s Duro Felguera and Package No. 6
(for sample) awarded to FGI and submitted that all the
five different contracts have independent arbitration
clauses (in sub-clause 20.6). In the contract New Package
No. 4 there is a header “Supply of bulk material handling
equipments and parts on F.O.B. basis”. Likewise, contract
agreement for Package No. 6 contains the header “Design,
manufacture, supply, installation, erection, testing
commissioning of bulk material handling equipments and
all other activities related therewith”. Various clauses in
the Original Package No. 4 TD were suitably modified
and incorporated in the split-up contract agreements. Sub-
clause 20.6 dealing with arbitration in the Original
Package No. 4 TD has been reproduced in New Package
No. 4 and other Packages Nos. 6 to 9. The contract for
New Package No. 4 which was entered into between M/s
Duro Felguera and GPL, also contains an arbitration
clause, which reads as under:
“Sub-clause 20.6—Arbitration
Any dispute in respect of which amicable
settlement has not been reached within the
period stated in sub-clause 20.5, shall be
finally and conclusively settled by arbitration
under the Arbitration and Conciliation Act,
1996 by appointing two arbitrators one by
each party and a presiding arbitrator to be
appointed by the said arbitrators. Any such
arbitration proceeding shall be within the
exclusive jurisdiction of court of law at
Hyderabad, India. The place of arbitration
shall be Hyderabad and the language of
arbitration shall be English. The contractor
shall continue to attend to discharge all his
ARB.P. 1787/2025 & connected matters Page 35 of 52
obligations under the contract during pendency
of the arbitration proceedings.”
38. The submission of GPL is that since reference to
Original Package No. 4 TD is made in MoU, the
arbitration clause is incorporated in the MoU and there has
to be a “composite reference” for settling the disputes
under different contracts by constitution of single Arbitral
Tribunal for dealing with the international commercial
arbitration. As discussed earlier, as per the amended
provision of sub-section (6-A) of Section 11, the power of
the court is only to examine the existence of arbitration
agreement. When there are five separate contracts each
having independent existence with separate arbitration
clauses, that is, New Package No. 4 (with foreign
company Duro Felguera) and Packages Nos. 6, 7, 8 and 9
[with Indian subsidiary (FGI)] based on MoU and
Corporate Guarantee, there cannot be a single Arbitral
Tribunal for “international commercial arbitration”.
(emphasis added)
10. The aforesaid proposition is not only judicially recognized but
is also embedded in the statutory framework of the Act.
11. This Court also takes note of Section 2(8) of the Act, which
contemplates a party to a specific arbitration agreement, as is
evident from the repeated reference to “an arbitration agreement”.
The statutory language makes it clear that the Act proceeds on the
basis of identifiable parties to a particular agreement. Section 2(8)
of the Act reads as follows:
“2. Definitions.-
****
(8) Where this Part-
(a) refers to the fact that the parties have agreed or that
they may agree, or
(b) in any other way refers to an agreement of the parties,”
….”
12. Further, Section 7 of the Act defines an “arbitration agreement”
as an agreement between the parties to submit to arbitration
disputes that have arisen or may arise between them in respect of a
defined legal relationship. It also mandates that such an agreement
must be in writing and may either be in the form of an arbitration
clause in a contract or a separate agreement. The emphasis
throughout the provision is on “an agreement” between specific
parties concerning a defined legal relationship. Section 7 of the Act
is reproduced hereunder:
“7. Arbitration agreement.- (1) In this Part, “arbitration
agreement” means an agreement by the parties to submit
to arbitration all or certain disputes which have arisen or
which may arise between them in respect of a defined
legal relationship, whether contractual or not.
ARB.P. 1787/2025 & connected matters Page 36 of 52
(2) An arbitration agreement may be in the form of an
arbitration clause in a contract or in the form of a separate
agreement.
(3) An arbitration agreement shall be in writing.
(4) An arbitration agreement is in writing if it is contained
in—
(a) a document signed by the parties;
(b) an exchange of letters, telex, telegrams or other means
of telecommunication which provide a record of the
agreement; or
(c) an exchange of statements of claim and defence in
which the existence of the agreement is alleged by one
party and not denied by the other. (5) The reference in a
contract to a document containing an arbitration clause
constitutes an arbitration agreement if the contract is in
writing and the reference is such as to make that
arbitration clause part of the contract. ”
(emphasis supplied)
13. A plain reading of Section 7(1) of the Act makes it abundantly
clear that the statute contemplates “an agreement” between “the
parties” to that particular agreement to submit disputes to
arbitration. The expression necessarily refers to the parties of a
particular agreement governing a defined legal relationship. Such
parties are bound in respect of that agreement alone. The provision
does not envisage the consolidation of numerous independent
agreements executed by different parties into a single arbitral
reference. However, the manner in which the present Petition has
been instituted, by clubbing together disputes arising out of
multiple, distinct agreements, effectively seeks to create a form of
class-action proceeding, which is alien to the scheme of Section 11
of the Act.
14. This Court also takes note of Section 11(6A) of the Act, which
mandates that while considering an application for appointment of
an arbitrator, the Supreme Court or the High Court shall confine
itself to the examination of the existence of “an arbitration
agreement”. Section 11(6A) of the Act reads as follows:
“11. Appointment of arbitrators.-
****
(6A) The Supreme Court or, as the case may be, the High
Court, while considering any application under sub-
section (4) or sub-section (5) or sub-section (6), shall,
notwithstanding any judgment, decree or order of any
Court, confine to the examination of the existence of an
arbitration agreement.
…. ”
(emphasis supplied)
15. A careful perusal of Section 11(6A) indicates that the
legislative intent is to restrict the Court’s scrutiny to the existence
ARB.P. 1787/2025 & connected matters Page 37 of 52
of “an arbitration agreement” between “the parties” to that
particular agreement before it. The use of the singular expression
reinforces the position that the Court must examine each arbitration
agreement independently. This statutory limitation effectively
undermines the Petitioners’ contention that a composite petition,
founded upon multiple separate agreements, is maintainable.”
(emphasis supplied)
91. In the present case, therefore, the adjudicatory exercise must
remain confined to the specific agreement which binds the parties to
arbitration and cannot be expanded so as to include entities or
arrangements falling beyond the scope of that defined legal
relationship.
92. The Impugned Impleadment Orders passed by the learned Joint
Registrar proceed on the premise that IIM Jammu, being the ultimate
beneficiary and funding authority, deserves to be impleaded. The
relevant extracts of the Impugned Orders are reproduced herein
below:
“28. On perusal of law laid down in aforesaid judgments and on
applying the same to the facts and circumstances of the case in
hand, I am of the considered view that applicant/IIM Jammu is
entitled of being impleaded as a party in the present matter as the
premises in question have been constructed for applicant/IIM
Jammu. Applicant/IIM Jammu is beneficiary of the premises in
question and all the payment for construction of premises has been
made/is to be made by IIM/Jammu. Applicant/IIM Jammu is the
ultimate beneficiary/sufferer of all the acts/omissions of petitioner.
Applicant/IIM Jammu has supervised the entire construction
process and has been involved in day-to-day affairs/decisions with
respect to construction of premises in question. Para/Clause 36.0
(page no. 115) of Notice inviting tender gives applicant/IIM
Jammu the power to do so. Applicant/IIM Jammu had played
active role in performance of the Contract/Agreement in question.
29. It is also a matter of record that the petitioner itself had written
letter to Director as well as other Board Members of IIM Jammu to
intervene and mediate when disputes arose between petitioner and
respondent.
30. Respondent/CPWD was acting as an agent of applicant/IIM
Jammu and presence of applicant/IIM Jammu is very much
essential and required for the complete and effective adjudication
ARB.P. 1787/2025 & connected matters Page 38 of 52
of the dispute between parties. Though IIM Jammu is not signatory
to the Arbitration Agreement but the positive, direct and
substantial involvement of applicant/IIM Jammu in fulfilling the
terms and conditions of notice inviting tender etc. establishes its
role as necessary party to the dispute.”
93. As is evident from the reasoning adopted by the learned Joint
Registrar, impleadment has primarily been permitted on the ground
that IIM Jammu stands to benefit from the project and has supervised
certain aspects of its execution.
94. This Court is unable to accept that the status of an “ultimate
beneficiary” can constitute the governing test for impleadment in
arbitral proceedings. Arbitration, being fundamentally consensual in
nature, cannot be enlarged to include entities merely because they
derive a benefit or possess an institutional interest in the project. The
law in this regard has been succinctly laid down by the Hon’ble
Supreme Court in Hindustan Petroleum Corporation Ltd. v. BCL
Secure Premises Pvt. Ltd.
15
, which reads as under:
“24. The scope of jurisdiction of the referral court hearing a
Section 11-Petition when faced with an issue of joinder of a non-
signatory to the arbitration agreement has been lucidly set out by
the five-judge Bench of this Court in Cox and Kings
Limited v. Sap India Private Limited
1
. Though said in the context
of considering the Group of Companies doctrine, the said judgment
has a great bearing for the present case. This Court, speaking
through Chief Justice D.Y. Chandrachud, held as under:—
“84. It is presumed that the formal signatories to an
arbitration agreement are parties who will be bound by it.
However, in exceptional cases persons or entities who
have not signed or formally assented to a written
arbitration agreement or the underlying contract
containing the arbitration agreement may be held to be
bound by such agreement. As mentioned in the preceding
paragraphs, the doctrine of privity limits the imposition of
rights and liabilities on third parties to a contract.
Generally, only the parties to an arbitration agreement can
be subject to the full effects of the agreement in terms of
15
2025 SCC OnLine SC 2746
ARB.P. 1787/2025 & connected matters Page 39 of 52
the reliefs and remedies because they consented to be
bound by the arbitration agreement. Therefore, the
decisive question before the Courts or tribunals is whether
a non-signatory consented to be bound by the arbitration
agreement. To determine whether a non-signatory is
bound by an arbitration agreement, the Courts and
tribunals apply typical principles of contract law and
corporate law. The legal doctrines provide a framework
for evaluating the specific contractual language and the
factual settings to determine the intentions of the parties to
be bound by the arbitration agreement. [Gary
Born, International Arbitration Law and Practice,
(3
rd
Edn., 2021) at p. 1531.]
101. A formalistic construction of an arbitration
agreement would suggest that the decision of a party to
not sign an arbitration agreement should be construed to
mean that the mutual intention of the parties was to
exclude that party from the ambit of the arbitration
agreement. Indeed, corporate entities have the commercial
and contractual freedom to structure their businesses in a
manner to limit their liability. However, there have been
situations where a corporate entity deliberately made an
effort to be not bound by the underlying contract
containing the arbitration agreement, but was actively
involved in the negotiation and performance of the
contract. The level of the non-signatory party's
involvement was to the extent of making the other
party believe that it was a veritable party to the
contract, and the arbitration agreement contained
under it. Therefore, the Group of Companies doctrine
is applied to ascertain the intentions of the parties by
analysing the factual circumstances surrounding the
contractual arrangements. [Gary Born, International
Arbitration Law and Practice, (3
rd
Edn., 2021) at p. 1568.]
126. Evaluating the involvement of the non-signatory
party in the negotiation, performance, or termination of a
contract is an important factor for a number of
reasons. First, by being actively involved in the
performance of a contract, a non-signatory may create
an appearance that it is a veritable party to the
contract containing the arbitration agreement; second,
the conduct of the non-signatory may be in harmony
with the conduct of the other members of the group,
leading the other party to legitimately believe that the
non-signatory was a veritable party to the contract;
and third, the other party has legitimate reasons to
rely on the appearance created by the non-signatory
party so as to bind it to the arbitration agreement.
ARB.P. 1787/2025 & connected matters Page 40 of 52
169. In case of joinder of non-signatory parties to an
arbitration agreement, the following two scenarios will
prominently emerge: first, where a signatory party to an
arbitration agreement seeks joinder of a non-signatory
party to the arbitration agreement; and second, where a
non-signatory party itself seeks invocation of an
arbitration agreement. In both the scenarios, the referral
court will be required to prima facie rule on the
existence of the arbitration agreement and whether the
non-signatory is a veritable party to the arbitration
agreement. In view of the complexity of such a
determination, the referral court should leave it for the
Arbitral Tribunal to decide whether the non-signatory
party is indeed a party to the arbitration agreement on
the basis of the factual evidence and application of
legal doctrine. The Tribunal can delve into the factual,
circumstantial, and legal aspects of the matter to decide
whether its jurisdiction extends to the non-signatory party.
In the process, the Tribunal should comply with the
requirements of principles of natural justice such as giving
opportunity to the non-signatory to raise objections with
regard to the jurisdiction of the Arbitral Tribunal. This
interpretation also gives true effect to the doctrine of
competence-competence by leaving the issue of
determination of true parties to an arbitration agreement to
be decided by the Arbitral Tribunal under Section 16.
170.12. At the referral stage, the referral court should
leave it for the Arbitral Tribunal to decide whether the
non-signatory is bound by the arbitration agreement.”
(Emphasis supplied)
25. A careful reading of the above passage reveals that the referral
court should be prima facie satisfied that there exists an arbitration
agreement and as to whether the non-signatory is a veritable party.
It further holds that even if the referral court prima facie arrives at
the satisfaction that the non-signatory is a veritable party, the
Arbitral Tribunal is not denuded of its jurisdiction to decide
whether the non-signatory is indeed a party to the arbitration
agreement on the basis of factual evidence and application of legal
doctrine. The Court further reinforces this proposition by holding
that as to whether the non-signatory is bound would be for the
Arbitral Tribunal to decide.
*****
39. It will be apt to refer to the judgment of this Court in Khardah
Company Limited v. Raymon & Co.
6
wherein this Court held as
under:—
“The law of the subject is well settled and might be
stated in simple terms. An assignment of a contract might
result by transfer either of the rights or of the obligations
ARB.P. 1787/2025 & connected matters Page 41 of 52
thereunder. But there is a well-recognised distinction
between these two classes of assignments. As a rule
obligations under a contract cannot be assigned except
with the consent of the promise, and when such consent is
given, it is really a novation resulting in substitution of
liabilities. On the other hand rights under a contract are
assignable unless the contract is personal in its nature the
rights are incapable of assignment either under the law or
under an agreement between the parties.”
(emphasis supplied)
95. This Court is of the considered view that the reasoning adopted
by the learned Joint Registrar would lead to anomalous consequences.
Large infrastructure projects often involve several institutional
stakeholders at different levels. If every beneficiary were to be
regarded as a necessary party, arbitral proceedings would cease to
retain their consensual character and instead be converted into
sprawling multi-party disputes detached from the contractual
foundation of arbitration law.
96. The Impugned Impleadment Orders also place reliance upon the
supervisory role allegedly exercised by IIM Jammu and its alleged
involvement in day-to-day decision-making processes. In support
thereof, reliance has been placed upon Clause 36 of Part B (Civil
Works) of the Notice Inviting Tender No. 02/NIT/CE cum
ED/JPZ/2020-21, which reads as under:
“36.0 Quality Assurance: Quality of work is of paramount
importance. Contractor will be required to engage well-
experienced supervisors, engineers, skilled labour and deploy
modern T&P and other equipments to execute the work in a time
bound manner. Many items like exposed finish form work,
specialized flooring work, factory made door- window shutters,
proper slope maintaining in toilet units, sanitary- water supply
installation, textured finishing, aluminium and glass work and
water proofing treatment will specially require engagement of
skilled workers having experience particularly in execution of such
items.
ARB.P. 1787/2025 & connected matters Page 42 of 52
The contractor shall ensure quality construction in a planned and
time bound manner. Any substandard material / work beyond set
out tolerance limit shall be summarily rejected by the Engineer-in-
Charge & contractor shall be bound to replace / remove such sub-
standard / defective work immediately. If any material, even
though approved by Engineer -in-Charge is found defective or not
conforming to specifications shall be replaced / removed by the
contractor at his own risk & cost.
In addition to the supervision of work by CPWD engineers, the
Consultants / third party quality assurance representatives / Quality
Assurance of CPWD and IIM Jammu representatives shall also be
carrying out regular and periodic inspections of the on-going
activities in the work and deficiencies, shortcomings, inferior
workmanship pointed out by them shall be communicated by
CPWD engineers to the contractor. Upon receipt of instructions
from Engineer -in-Charge these are also to be made good by
necessary improvement, rectification, replacement upto his
complete satisfaction. Special attention shall be paid towards line
and level of internal and external plastering, exposed smooth
surface of RCC members by providing fresh shuttering plates,
rubberized linings to all the shuttering joints, accurate joinery work
in wooden doors and windows, thinnest joints in stone/ tiling /
cladding work, non-hollowness in floor and dado tiles work,
protection of scratches over flooring by impounding layer of
Plaster of Paris, water tight pipe linings, absence of hollow vertical
joints in brick masonry, proper compaction of filled up earth and
up keeping of quality assurance shall be of paramount importance.
It is proposed to have monthly meeting having CPWD officers,
IIM officials, Third party consultant of CPWD/IIM, consultant of
EPC contractor etc. for progress review. The progress of the work
shall be captured using Drone mounted camera. The entire battery
limit and path to be constructed along the boundary wall shall be
video graphed and still pictures captured for the purpose of
progress review on monthly basis after the planning period of
Three months is over. The approvals required for drone operation,
if any, shall be obtained by the EPC contractor from the concerned
department(s).”
(emphasis supplied)
97. A careful reading of Clause 36 demonstrates that although
representatives of IIM Jammu were entitled to participate in quality
assurance inspections, any observations made by them were
necessarily required to be communicated through CPWD engineers.
ARB.P. 1787/2025 & connected matters Page 43 of 52
The clause, therefore, preserves a clear distinction between the
executing authority and the principal institution.
98. The contractual framework thus recognises CPWD as the nodal
authority responsible for supervision, communication and contractual
enforcement vis-à-vis the contractor. The role assigned to IIM Jammu
remains merely advisory and supervisory to a limited extent and does
not translate into contractual control or privity.
99. Acceptance of the reasoning adopted in the Impugned
Impleadment Orders would effectively amount to rewriting the
contractual architecture by permitting IIM Jammu to assume a direct
contractual and supervisory role contrary to the express terms of the
agreement itself. Such an interpretation cannot be sustained in law.
Effectively, thereby, IIM Jammu would stand transposed as the
primary contestant instead of the contractual parties themselves.
100. Insofar as reliance placed upon the communication dated
19.11.2025 addressed by the Petitioner to the Director of IIM Jammu
is concerned, this Court finds that the said communication merely
indicates an attempt on the part of the Petitioner to seek institutional
assistance in resolving disputes with CPWD. The said letter, to the
mind of this Court, only evinces a request for facilitation or
intervention and cannot be construed as conferring upon IIM Jammu
the status of a contracting party or a party to the arbitration agreement.
101. Further, although the Impugned Impleadment Orders record a
finding regarding the “positive, direct and substantial involvement” of
IIM Jammu, the reasoning supporting such a conclusion is
conspicuously absent. The finding appears to rest upon broad
ARB.P. 1787/2025 & connected matters Page 44 of 52
generalisations rather than any demonstrable analysis of contractual
rights and obligations.
102. In view of the aforesaid discussion, this Court is of the
considered opinion that the Impugned Orders passed by the learned
Joint Registrar in all three Chamber Appeals suffer from fundamental
infirmities. The reasoning adopted therein overlooks the settled
principle that arbitration is founded upon consent and that a party can
be subjected to arbitral proceedings only where it is bound by the
arbitration agreement. In the absence of privity of contract between
the Petitioner and IIM Jammu, and there being no material to
demonstrate that IIM Jammu is either a signatory to, or otherwise
bound by, the arbitration agreement, its impleadment is legally
unsustainable.
103. Accordingly, all three Chamber Appeals are allowed and the
separate Impugned Impleadment Orders dated 23.01.2025, passed in
I.A. 30458/2025, I.A. 30390/2025 and I.A. 29997/2025 are set aside.
ARB.P. 1787/2025
104. This Petition has been filed seeking the reference of the
disputes that have arisen between the parties to arbitration. The
Petition, inter alia, seeks directions to CPWD to abide by the
requisites as stated in the dispute resolution clause in terms of
nomination of the learned arbitrator on its behalf. The relevant clause,
being clause 25 of the GCC, reads as follows:
“Clause 25: Settlement of Disputes & Arbitration
Except where otherwise provided in the contract, all questions and
disputes relating to the meaning of the specifications, design,
drawings and instructions here-in before mentioned and as to the
quality of workmanship or materials used on the work or as to any
other question, claim, right, matter or thing whatsoever in any way
ARB.P. 1787/2025 & connected matters Page 45 of 52
arising out of or relating to the contract, designs, drawings,
specifications, estimates, instructions, orders or these conditions or
otherwise concerning the works or the execution or failure to
execute the same whether arising during the progress of the work
or after the cancellation, termination, completion or abandonment
thereof shall be dealt with as mentioned hereinafter:
(i) If the contractor considers any work demanded of him to be
outside the requirements of the contract, or disputes any
drawings, record or decision given in writing by the Engineer-
in-Charge or if the Engineer in Charge considers any act or
decision of the contractor on any matter in connection with or
arising out of the contract or carrying out of the work, to be
unacceptable and is disputed, such party shall promptly within
15 days of the arising of the disputes request the Chief
Engineer/ CPM, or where there is no Chief Engineer/CPM,
request the Additional Director General/Special Director
General ,who shall refer the disputes to Dispute Reressal
Committee (DRC) within 15 days along with a list of disputes
with amounts claimed if any in respect of each such dispute.
The Dispute Redressal Committee (DRC) give its decision
within a period of 60 days extendable by 30 days by consent of
both the parties from the receipt of reference from
CE/CPM/ADG/SDG. The constitution of Dispute Redressal
Committee (DRC) shall be as indicated in Schedule 'F'.
Provided that no party shall be represented before the Dispute
Redressal Committee by an advocate/legal counsel etc.
The DRC will submit its decision to the concerned ADG/SDG
for acceptance. ADG/ SDG in a time limit of 30 days from
receipt of DRC decision will convey acceptance or otherwise on
the said decision .If the Dispute Redressal Committee (DRC)
fails to give its decision within the aforesaid period or the
ADG/SDG fails to give his decision in the aforesaid time limit
or any party is dissatisfied with the decision of Dispute
Redressal Committee (DRC)/ ADG/ SDG the neither party may
within a period of 30 days from the receipt of the decision of
Dispute Redressal Committee (DRC)/ ADG/ SDG or on expiry
of aforesaid the time limits available to DRC/ ADG/SDG ,may
give notice to the Chief Engineer/CPM, CPWD, in charge of the
work or if there be no Chief Engineer/ CPM,, the Additional
Director General /Special Director General concerned or if there
be no Additional Director General/ Special Director General, the
Director General, CPWD for appointment of arbitrator on
prescribed proforma as per Appendix XVII under intimation to
the other party.
It is a term of contract that each party invoking arbitration must
exhaust the aforesaid mechanism of settlement of
claims/disputes prior to invoking arbitration.
ARB.P. 1787/2025 & connected matters Page 46 of 52
The CE/ADG/ SDG shall in such case appoint the sole arbitrator
or one of the three arbitrators as the case may be within 30 days
of receipt of such a request and refer such disputes to
arbitration. Wherever the Arbitral Tribunal consists of three
Arbitrators, the contractor shall appoint one arbitrator within 30
days of making request for arbitration or of receipt of request by
Engineer-in-charge to CE/ADG/ SDG /DG for appointment of
arbitrator, as the case may be, and two appointed arbitrators
shall appoint the third arbitrator who shall act as the Presiding
Arbitrator.
In the event of
(a) A party fails to appoint the second Arbitrator, or
(b) The two appointed Arbitrators fail to appoint the Presiding
Arbitrator, then the Director General, CPWD shall appoint
the second or Presiding Arbitrator as the case may be.
(ii) Disputes or difference shall be referred for adjudication through
arbitration by a Tribunal having sole arbitrator where claimed
amount is Rs. 20 Crore or less. Where claimed Value is more
than Rs. 20 Crore, Tribunal shall consist of three Arbitrators as
above. The requirements of the Arbitration and Conciliation Act,
1996 (26 of 1996) and any further statutory modification or re-
enactment thereof and the rules made there under and for the
time being in force shall be applicable.
It is a term of this contract that the party invoking arbitration shall
give a list of disputes with amounts claimed, if any, in respect of
each such dispute along with the notice for appointment of
arbitrator and giving reference to the decision of the ADG/ SDG on
the finding / recommendation of DRC.
It is also a term of this contract that member(s) of the Arbitration
Tribunal shall be a Graduate Engineer with experience in handling
public works engineering contracts, and further he shall have
earlier worked at a level not lower than Chief Engineer/ equivalent
(i.e. Joint Secretary level of Government of India). This shall be
treated as a mandatory qualification to be appointed as arbitrator.
Parties, before or at the time of appointment of Arbitral Tribunal
may agree in writing for fast track arbitration as per the Arbitration
and Conciliation Act, 1996 (26 of 1996) as amended in 2015.
Subject to provision in the Arbitration and Conciliation Act, 1996
(26 of 1996) as amended in 2015 whereby the counter claims if
any can be directly filed before the arbitrator without any
requirement of reference by the appointing authority. The arbitrator
shall adjudicate on only such disputes as are referred to him by the
appointing authority and give separate award against each dispute
and claim referred to him and in all cases where the total amount of
the claims by any party exceeds Rs. 1,00,000/-, the arbitrator shall
give reasons for the award.
ARB.P. 1787/2025 & connected matters Page 47 of 52
It is also a term of the contract that fees payable to arbitral tribunal
shall be as approved by DG, CPWD, OM issued vide
no.2/2006/SE(TLC)/CSQ /137 dated 19-11-2019 (or its latest
amendment as approved by DG, CPWD). This fee shall be shared
equally by parties.
The place of arbitration shall be as mentioned in Schedule F. In
case there is no mention of place of arbitration, the arbitral tribunal
shall determine the place of arbitration.
The venue of the arbitration shall be such place as may be fixed by
the Arbitral Tribunal in consultation with both the parties. Failing
any such agreement, then the Arbitral Tribunal shall decide the
venue.”
(emphasis supplied)
105. It is stated that Petitioner was constrained to prefer the present
Petition owing to the following disputes that had arisen as between the
parties while attempting to constitute the learned Arbitral Tribunal in
terms of the Dispute Resolution Clause as noted herein above.
106. It is stated that, through various correspondences exchanged
between the parties, a consensus had been reached for referring the
disputes to arbitration. Pursuant thereto, vide letter dated 04.07.2025,
the Petitioner informed CPWD of its nomination of Shri Vinod Kumar
Malik, Former Special Director General, CPWD, as its nominee
arbitrator, and simultaneously called upon CPWD to appoint its
nominee arbitrator in terms of the arbitration agreement. Thereafter,
vide communication dated 30.07.2025, CPWD informed the Petitioner
that it had nominated Shri Vineet Kumar Jayaswal, Retired Director
General, CPWD, as its nominee arbitrator.
107. Thereafter, the nominee arbitrators appointed by the respective
parties jointly appointed Shri Sudhir Kumar, Former Additional
Director General, CPWD, as the Presiding Arbitrator. Pursuant to his
appointment, the learned Presiding Arbitrator furnished the disclosure
ARB.P. 1787/2025 & connected matters Page 48 of 52
contemplated under Section 12(1) of the A&C Act, vide
communication dated 09.08.2025.
108. However, it is stated that CPWD raised allegations regarding
the disclosure made by the learned presiding arbitrator, which was in
violation of CPWD’s OM dated 13.06.2025 and requested the learned
nominee arbitrators to propose someone else as the presiding
arbitrator. It is stated that another letter dated 26.08.2025 came to be
addressed by CPWD to the nominee arbitrators, raising allegations
including influence and bias of the learned presiding arbitrator.
109. Consequent thereof, the learned presiding arbitrator vide his
letter dated 23.09.2025 withdrew from the post of the presiding
arbitrator. As a result, Sh. Vineet Kumar Jayaswal, CPWD’s nominee
arbitrator, also withdrew from the office as a member of the learned
Arbitral Tribunal vide his letter dated 01.10.2025.
110. The Petitioner, vide letter dated 04.10.2025, requested CPWD
to nominate a substitute arbitrator in place of Sh. Vineet Kumar
Jayaswal.
111. CPWD vide letter dated 24.10.2025 confirmed the appointment
of Sh. Vinod Kumar Malik as the Petitioner’s nominee and further
informed about the nomination of Hon’ble Mr. Justice J.R. Midha,
Former Judge of this Court, as their nominee, which is stated to be
violative of the clear and binding stipulation under Clause 25 of the
GCC, which provides for the qualification of the arbitrator to
adjudicate the disputes arising out of the agreement entered into
between the parties.
112. It is stated that, in these factual backdrops, the Petitioner was
constrained to file the present Petition.
ARB.P. 1787/2025 & connected matters Page 49 of 52
113. It would be argued by the learned Senior Counsel for the
Petitioner that the said act of CPWD is violative of the agreed terms as
between the parties.
114. This Court is also of the considered view that the intent and
objective of the A&C Act, namely, party autonomy and equal
participation, would be rendered otiose if the parties were permitted to
step back from the agreed terms of their agreement.
115. Upon a pointed query, the learned CGSC appearing for CPWD,
on instructions, fairly submits that CPWD shall appoint its nominee
arbitrator in accordance with the Dispute Resolution Clause of the
GCC as agreed by the parties.
116. In view thereof, and since disputes have arisen inter se the
parties, this Court finds no impediment to referring the same to
arbitration. Accordingly, this Petition is allowed.
117. Since the Petitioner has already nominated its learned nominee
arbitrator, CPWD is directed to communicate to the Petitioner its
learned nominee arbitrator within 15 days from the receipt of this
Order.
118. Thereafter, the learned nominee arbitrators so appointed shall,
within a period of 15 days thereafter, appoint the presiding arbitrator
and thereafter proceed with the arbitration proceedings expeditiously
in accordance with the law.
119. All rights and contentions of the parties in relation to the
claims/counter-claims are kept open, to be decided by the learned
Tribunal on their merits, in accordance with law.
ARB.P. 1787/2025 & connected matters Page 50 of 52
120. Needless to say, nothing in this Order shall be construed as an
expression of opinion of this Court on the merits of the controversy
between the parties.
121. Accordingly, ARB.P. 1787/2025, along with pending
application(s), if any, stands disposed of in the aforesaid terms.
O.M.P.(I) (COMM.) 35/2025
O.M.P.(I) (COMM.) 447/2025
O.M.P.(I) (COMM.) 484/2025
122. As a necessary corollary, and upon the consent of the parties
herein, the captioned Petitions under Section 9 of the A&C Act shall
be treated as Applications under Section 17 of the A&C Act, instead
of being adjudicated on merits by this Court.
123. The learned Arbitral Tribunal so appointed is requested to take
up the captioned applications for hearing as expeditiously as possible
upon entering into the reference.
124. All rights and contentions of the parties in relation to the
claims/counter-claims are kept open, to be decided by the learned
Tribunal on their merits, in accordance with law.
125. Needless to say, nothing in this Order shall be construed as an
expression of opinion of this Court on the merits of the controversy
between the parties.
CONSOLIDATED SUMMARY:
126. Brevitatis causa, the final conclusions in relation to the
Applications, Chamber Appeals, and the captioned Petitions
considered herein above may be summarised hereunder:
ARB.P. 1787/2025 & connected matters Page 51 of 52
S.
No.
Particulars Summary of the
conclusions
1. I.A. 8810/2026 (Delay of 1
day in filing of the Chamber
Appeal) in O.A. 42/2026 in
ARB.P. 1787/2025
I.A. 8915/2026 (Delay of 1
day in filing of the Chamber
Appeal) in O.A. 41/2026 in
O.M.P.(I) (COMM.)
447/2025
I.A. 8914/2026 (Delay of 1
day in filing of the Chamber
Appeal) in O.A. 40/2026 in
O.M.P.(I)(COMM.) 484/2025
Applications seeking condonation
of delay of one day in filing of the
Chamber Appeals are allowed,
and therefore, the said delay
stands condoned.
2. O.A. 42/2026 in ARB.P.
1787/2025
O.A. 41/2026 in O.M.P.(I)
(COMM.) 447/2025
O.A. 40/2026 in O.M.P.(I)
(COMM.) 484/2025
The Chamber Appeals are
allowed. Consequently, the
Impleadment Applications filed
by IIM Jammu, which had been
allowed by the learned Joint
Registrar vide Orders dated
23.01.2026, stand set aside.
3. ARB.P. 1787/2025
The Petition under Section 11 of
the A&C Act is allowed. CPWD
is directed to communicate to the
Petitioner the name of its
nominee Arbitrator within a
period of 15 days from the date of
ARB.P. 1787/2025 & connected matters Page 52 of 52
receipt of this Order.
Upon such nomination, the
nominee Arbitrators appointed by
the respective parties shall, within
a further period of 15 days,
appoint the Presiding Arbitrator,
thereby constituting the Arbitral
Tribunal.
The Arbitral Tribunal so
constituted shall thereafter
proceed to adjudicate the disputes
between the parties in accordance
with law.
4. O.M.P.(I)(COMM.) 35/2025
O.M.P.(I)(COMM.) 447/2025
O.M.P.(I)(COMM.) 484/2025
In view of the constitution of the
Arbitral Tribunal, the Petitions
under Section 9 of the A&C Act
stand disposed of. The petitions
shall be treated as Applications
under Section 17 of the A&C Act
and shall be taken up by the
learned Arbitral Tribunal for
consideration on their merits, in
accordance with law.
127. These Petitions as well as all pending Applications stand
disposed of in the above terms.
HARISH VAIDYANATHAN SHANKAR, J.
JULY 29, 2026/va
Legal Notes
Add a Note....