government contract, military engineering service, arbitration
0  09 May, 2023
Listen in 02:00 mins | Read in 40:00 mins
EN
HI

M/S. Shree Vishnu Constructions Vs. The Engineer In Chief Military Engineering Service & Ors.

  Supreme Court Of India Civil Appeal /3461/2023
Link copied!

Case Background

As per the case facts, an application for arbitrator appointment was dismissed by the High Court because the appellant had accepted final payment and issued a "no further claim certificate." ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 3461 OF 2023

(@ SLP (C) NO. 5306 OF 2022)

M/s. Shree Vishnu Constructions …Appellant(s)

Versus

The Engineer in Chief

Military Engineering Service & Ors. …Respondent(s)

J U D G M E N T

M.R. SHAH, J.

1.Feeling aggrieved and dissatisfied with the

impugned judgment and order passed by the High Court

for the State of Telangana at Hyderabad in ARBA No. 151

of 2016 by which the High Court has dismissed the said

application filed under Section 11 of the Arbitration Act,

1996 (hereinafter referred to as “Act, 1996”) and has

Civil Appeal No. 3461 of 2023

Page 1 of 42

refused to appoint an arbitrator on the ground that earlier

the appellant had accepted the amount as per the final bill

in full and final settlement and without raising any dispute

and also signed and issued “no further claim certificate”,

the original applicant has preferred the present appeal.

2.The facts leading to the present appeal in nutshell

are as under:-

2.1That the appellant herein and the respondents

entered into an agreement vide agreement dated

22.07.2010 for additions/alterations to Senior Non-

Commissioned Officers mess and repairs/renewals to

floors in tech area at Air Force Academy, Hyderabad. The

appellant raised a revised final bill for the aforesaid work

on 10.07.2012. The payment in respect of the final bill

was made to the appellant on 29.04.2013. The appellant

also issued “no further claim” certificate.

2.2The appellant sent a notice dated 20.12.2013

invoking the arbitration clause. The appellant preferred

an application under Section 11(6) of the Act, 1996 before

the High Court on 27.04.2016 and prayed to appoint an

arbitrator. The application was opposed by the

respondents inter alia on the ground that the entire

Civil Appeal No. 3461 of 2023

Page 2 of 42

amount due and payable under the final bill was paid as

far as back on 29.04.2013 and that even the appellant

issued the “no further claim” certificate and therefore, on

the ground of “accord and satisfaction”, the dispute is not

required to be sent for arbitration. However, it was the

case on behalf of the appellant that in view of the

Arbitration and Conciliation (Amendment) Act, 2015

(hereinafter referred to as “Amendment Act, 2015”) by

which Section 11(6A) came to be inserted, while deciding

the application under Section 11(6), the Court would have

a very limited jurisdiction and to consider only whether

there is an existence of the arbitration agreement or not

and no further inquiry is permissible at the stage of

deciding the application under Section 11(6) and the issue

with respect to the “accord and satisfaction” has to be left

to be decided by the arbitrator / arbitral tribunal.

Therefore, it was the case on behalf of the appellant that

the provisions of the Amendment Act, 2015 shall be

applicable.

2.3It was the case on behalf of the respondents that as

per Section 26 read with Section 21 of the Amendment

Act, 2015, Amendment Act, 2015 shall not be applicable in

a case where arbitration proceedings as per Section 21 of

Civil Appeal No. 3461 of 2023

Page 3 of 42

the Arbitration Act, has been commenced prior to the

Amendment Act, 2015.

2.4By the impugned judgment and order, the High

Court has dismissed the arbitration petition and has

refused to appoint the arbitrator / arbitral tribunal on the

ground that the Amendment Act, 2015 shall not be

applicable and the Act, pre-amendment, 2015, shall be

applicable. That thereafter, after holding that there was a

full and final settlement of the payment as per the final bill

as far as back on 29.04.2013 and even the appellant

issued the “no further claim” certificate and even the

application under Section 11(6) of the Act, 1996 was filed

after a period of approximately three years, the High Court

has dismissed the said arbitration application. The

impugned judgment and order passed by the High Court

is the subject matter of present appeal.

3.Shri K. Parameshwar, learned counsel has

appeared on behalf of the appellant.

3.1it is submitted by Shri Parameshwar, learned

counsel appearing on behalf of the appellant that the

issue that arises for consideration in the present appeal is

the interpretation of Section 26 of the Amendment Act,

Civil Appeal No. 3461 of 2023

Page 4 of 42

2015 insofar as the applicability of the amended

provisions, more specifically, insertion of Section 11(6A)

and its applicability to judicial proceedings initiated after

the Amendment Act, 2015 came into force w.e.f.

23.10.2015.

3.2Shri Parameshwar, learned counsel appearing on

behalf of the appellant has vehemently submitted that as

such the aforesaid issue is squarely covered by the

decision of this Court in the case of Board of Control for

Cricket in India (BCCI) Vs. Kochi Cricket Private

Limited and Ors., (2018) 6 SCC 287 (paras 37 and 39).

3.3 Relying upon the aforesaid decision, it is submitted

that in the said decision it is specifically observed and

held by this Court that the Amendment Act, 2015 shall be

applicable prospectively and that even in a case where

the arbitration proceedings were initiated as per Section

21 of the Act, prior to the Amendment Act, 2015, the

Amendment Act, 2015 shall be applicable.

3.4It is further submitted that this Court in BCCI

(supra) had the occasion to analyse and interpret Section

26 of the Amendment Act, 2015. The Court specifically

traced the legislative history and thereafter came to the

Civil Appeal No. 3461 of 2023

Page 5 of 42

conclusion that Section 26 is divided into two parts. The

first part applies to arbitral proceedings before the

arbitrator and the second part applies to the proceedings

in relation to arbitral proceedings, which means judicial

proceedings. The Court held as follows:

“38. That the expression “the arbitral

proceedings” refers to proceedings before an

Arbitral Tribunal is clear from the heading of

Chapter V of the 1996 Act, which reads as

follows:

“Conduct of arbitral proceedings”

The entire chapter consists of Sections

18 to 27 dealing with the conduct of arbitral

proceedings before an Arbitral Tribunal. What

is also important to notice is that these

proceedings alone are referred to, the

expression “to” as contrasted with the

expression “in relation to” making this clear.

Also, the reference to Section 21 of the 1996

Act, which appears in Chapter V, and which

speaks of the arbitral proceedings

commencing on the date on which a request

for a dispute to be referred to arbitration is

received by the respondent, would also make

it clear that it is these proceedings, and no

others, that form the subject-matter of the first

part of Section 26. Also, since the conduct of

arbitral proceedings is largely procedural in

nature, parties may “otherwise agree” and

apply the Amendment Act to arbitral

proceedings that have commenced before the

Civil Appeal No. 3461 of 2023

Page 6 of 42

Amendment Act came into force. [ Section 29-

A of the Amend (sic Amended) Act provides

for time-limits within which an arbitral award is

to be made. In Hitendra Vishnu

Thakur v. State of Maharashtra, (1994) 4 SCC

602 at p. 633 : 1994 SCC (Cri) 1087, this

Court stated: (SCC p. 633, para 26)“26. … (iii)

Every litigant has a vested right in substantive

law but no such right exists in procedural law.

(iv) A procedural statute should not generally

speaking be applied retrospectively where the

result would be to create new disabilities or

obligations or to impose new duties in respect

of transactions already accomplished.(v) A

statute which not only changes the procedure

but also creates new rights and liabilities shall

be construed to be prospective in operation,

unless otherwise provided, either expressly or

by necessary implication.” It is, inter alia,

because timelines for the making of an arbitral

award have been laid down for the first time in

Section 29-A of the Amendment

(sic Amended) Act that parties were given the

option to adopt such timelines which, though

procedural in nature, create new obligations in

respect of a proceeding already begun under

the unamended Act. This is, of course, only

one example of why parties may otherwise

agree and apply the new procedure laid down

by the Amendment Act to arbitral proceedings

that have commenced before it came into

force.] In stark contrast to the first part of

Section 26 is the second part, where the

Amendment Act is made applicable “in relation

to” arbitral proceedings which commenced on

or after the date of commencement of the

Civil Appeal No. 3461 of 2023

Page 7 of 42

Amendment Act. What is conspicuous by its

absence in the second part is any reference to

Section 21 of the 1996 Act. Whereas the first

part refers only to arbitral proceedings before

an Arbitral Tribunal, the second part refers to

court proceedings “in relation to” arbitral

proceedings, and it is the commencement of

these court proceedings that is referred to in

the second part of Section 26, as the words

“in relation to the arbitral proceedings” in the

second part are not controlled by the

application of Section 21 of the 1996 Act.

39. Section 26, therefore, bifurcates

proceedings, as has been stated above, with

a great degree of clarity, into two sets of

proceedings — arbitral proceedings

themselves, and court proceedings in relation

thereto. The reason why the first part of

Section 26 is couched in negative form is only

to state that the Amendment Act will apply

even to arbitral proceedings commenced

before the amendment if parties otherwise

agree. If the first part of Section 26 were

couched in positive language (like the second

part), it would have been necessary to add a

proviso stating that the Amendment Act would

apply even to arbitral proceedings

commenced before the amendment if the

parties agree. In either case, the intention of

the legislature remains the same, the negative

form conveying exactly what could have been

stated positively, with the necessary proviso.

Obviously, “arbitral proceedings” having been

subsumed in the first part cannot re-appear in

the second part, and the expression “in

Civil Appeal No. 3461 of 2023

Page 8 of 42

relation to arbitral proceedings” would,

therefore, apply only to court proceedings

which relate to the arbitral proceedings. The

scheme of Section 26 is thus clear : that the

Amendment Act is prospective in nature, and

will apply to those arbitral proceedings that

are commenced, as understood by Section 21

of the principal Act, on or after the Amendment

Act, and to court proceedings which have

commenced on or after the Amendment Act

came into force.”

3.5It is further submitted that it is specifically held that

the phrase ‘in relation to arbitral proceedings’ appearing in

the second part of Section 26 refers to commencement of

court proceedings and are not controlled by Section 21 of

the principal Act. It is submitted that in such

circumstances, the relevant date so far as the applicability

of Section 11(6A) is concerned, is not the date of

invocation of arbitration but the date of commencement of

judicial proceedings before a court under Section 11. It is

submitted that therefore viewed in this light, the finding of

the High Court that Section 11(6A) shall not be applicable

in the present case is clearly erroneous.

3.6It is submitted that in the case of Union of India Vs.

Parmar Construction Company, (2019) 15 SCC 682

(Two Judge Bench) (paras 25-27), without noticing the

judgment in BCCI (supra), a coordinate Bench has held,

Civil Appeal No. 3461 of 2023

Page 9 of 42

relying on Section 21, that, the relevant date for

applicability of Section 26 of the Amendment Act, 2015 is

the date when request for appointment of arbitrator was

made. It is further submitted that this has been followed in

the judgment in the case of Union of India Vs. Pradeep

Vinod Construction Company, (2020) 2 SCC 464

(Three Judge Bench), which also did not refer to the case

of BCCI (supra) but has only followed the judgment in

Parmar Construction Company (supra).

3.7It is submitted that the judgment in BCCI (supra)

was rendered in the context of Section 36 of the Act and

not in the context of Section 11. Both Pradeep Vinod

Construction Company (supra) and Parmar

Construction Company (supra) were cases relating to

Section 11. However, neither of the case distinguished the

second part of Section 26 of the Amendment Act, 2015 as

relating to judicial proceedings. It is further submitted that,

in Parmar Construction Company (supra), reliance was

placed on Aravali Power Company Private Limited Vs.

Era Infra Engineering Limited, (2017) 15 SCC 32 (Para

22), to examine the effect of Section 21 of the principal

Act read with Section 26 of the Amendment Act, 2015. It is

submitted that the reliance placed on Aravali Power

Company Private Limited (supra) in the case of Parmar

Civil Appeal No. 3461 of 2023

Page 10 of 42

Construction Company (supra) is completely

misplaced. Firstly, neither Section 21 of the principal Act

nor Section 26 of the Amendment Act, 2015 were

discussed in Aravali Power Company Private Limited

(supra). Secondly, the decision in Aravali Power

Company Private Limited (supra) did not concern

judicial proceedings but applications filed before the

arbitrator challenging his qualification under Sections 12

and 13. It is submitted that therefore, the second part of

Section 26 did not come for consideration at all.

3.8It is submitted that similarly, the reliance placed in

Parmar Construction Company (supra) on S.P. Singla

Constructions Private Limited Vs. State of Himachal

Pradesh and Anr., (2019) 2 SCC 488 (Para 16) is again

misplaced because in S.P. Singla Constructions Private

Limited (supra) issue also involved was disqualifications

of an arbitrator under Section 12 and consequent filing of

Section 11 petitions prior to coming into force of the

Amendment Act, 2015.

3.9It is submitted that on the other hand, this Court in

Ssangyong Engineering and Construction Company

Limited Vs. National Highways Authority of India

(NHAI), (2019) 15 SCC 131 (Para 19), has held that,

Civil Appeal No. 3461 of 2023

Page 11 of 42

Section 34 as amended in 2015, will apply only to Section

34 applications that have been made to the Court on or

after 23.10.2015, irrespective of the fact that the

arbitration proceedings may have commenced prior to

that date and while doing so, this Court followed the

judgment in BCCI (supra).

3.10It is submitted that in order to get over the judgment

in BCCI (supra), the Parliament omitted Section 26 of the

Amendment Act, 2015 w.e.f. 23.10.2015 by way of

Section 15 of the Arbitration and Conciliation

(Amendment) Act, 2019, which was notified on

30.08.2019. It is further submitted that the validity of

Section 15 was inter alia challenged in Hindustan

Construction Company Limited and Anr. Vs. Union of

India and Ors., (2020) 17 SCC 324 (Three Judge Bench).

It is submitted that this Court held that, though the basis

for the judgment in BCCI (supra) was removed, but still

found that Section 15 of the Amendment Act, 2019 was

unconstitutional as being manifestly arbitrary. What is

noteworthy is that despite having noticed that the Justice

Srikrishna committee report held that the Amendment Act,

2015 must apply to arbitrations, which commenced on or

after 23.10.2015 and related court proceedings, the Court

Civil Appeal No. 3461 of 2023

Page 12 of 42

struck down the amendment and resurrected the law as

stated in BCCI (supra). The Court emphatically held that,

“66. The result is that Kochi Cricket [BCCI v.

Kochi Cricket (P) Ltd., (2018) 6 SCC]

judgment will therefore continue to apply so as

to make applicable the salutary amendments

made by the 2015 Amendment Act to all court

proceedings initiated after 23-10-2015.”

3.11It is further submitted that the judgment in BCCI

(supra), so far as it differentiated between arbitral

proceedings and court proceedings, was followed in

Government of India Vs. Vedanta Limited, (2020) 10

SCC 1 (Three Judge Bench), and the Court emphasized

that the Amendment Act, 2015 would be applicable to

court proceedings arising out of arbitration proceedings,

irrespective of whether such arbitration proceedings

commenced prior to or after the Amendment Act, 2015.

3.12It is further submitted that the judgment in BCCI

(supra) has also been followed in Patel Engineering

Limited Vs. North Eastern Electric Power Corporation

Limited, (2020) 7 SCC 167 (Para 15) (Three Judge

Bench).

3.13In light of this brief conspectus of the aforesaid

decisions, it is submitted that, the decision in BCCI

Civil Appeal No. 3461 of 2023

Page 13 of 42

(supra), regarding judicial proceedings referred to in

Section 26 not being controlled by Section 21 of the

principal Act, has been followed by a coordinate bench of

this Hon’ble Court in Ssangyong Engineering and

Construction Company Limited (supra) and the three-

judge benches in Hindustan Construction Company

Limited and Anr. (supra), Vedanta Limited (supra) and

Patel Engineering Limited (supra). It is further

submitted that on the other hand, the decision by the

coordinate bench in Parmar Construction Company

(supra) was rendered in ignorance of the decision in

BCCI (supra). Further, the coordinate bench in Parmar

Construction Company (supra) placed reliance on the

decisions in Aravali Power Company Private Limited

(supra) and S.P. Singla Constructions Private Limited

(supra), neither of which concerned judicial proceedings

as they were rendered on the issue of qualification or

disqualification of the arbitrator. It is further submitted that

the decision in the case of Parmar Construction

Company (supra) was followed by the three-judge bench

in Pradeep Vinod Construction Company (supra)

without any reference to BCCI (supra).

3.14It is therefore, the submission on behalf of the

appellant that the decision of this Court in the case of

Civil Appeal No. 3461 of 2023

Page 14 of 42

BCCI (supra) was binding on the coordinate bench which

rendered the decision in the case of Parmar

Construction Company (supra), this Court has not

noticed the said decision and therefore, the decision in the

case of Parmar Construction Company (supra) can be

said to be per incuriam and/or sub silentio. It is submitted

that therefore, the decision in the case of Parmar

Construction Company (supra) being per incuriam, the

larger Bench, which rendered the decision in the case of

Pradeep Vinod Construction Company (supra) ought

not to have placed reliance on Parmar Construction

Company (supra) . Therefore, relying upon the decision

of this Court in the case of BCCI (supra), which has been

subsequently followed in other decisions referred to

hereinabove, it is prayed to allow the present appeal.

4.Present appeal is vehemently opposed by Shri

Padmesh Mishra, learned counsel appearing on behalf of

the respondents.

4.1It is vehemently submitted by the learned counsel

appearing on behalf of the respondents that as such the

Hon’ble High Court has rightly dismissed the Section

11(6) application by observing and holding that the pre-

amendment Arbitration Act, 2015 shall be applicable.

Civil Appeal No. 3461 of 2023

Page 15 of 42

4.2It is submitted that in the present case, admittedly

the notice invoking the arbitration was issued on

20.12.2013, i.e., much prior to the Amendment Act, 2015.

It is further submitted that admittedly the application under

Section 11(6) of the Act, 1996 was preferred and filed on

27.04.2016, i.e., much after the Amendment Act, 2015

came into force. It is submitted that therefore, taking into

consideration section 26 of the Amendment Act, 2015 and

when the notice invoking the arbitration was issued much

prior to the Amendment Act, 2015, therefore, the

arbitration proceedings can be said to have commenced

on 20.12.2013 and therefore, pre-Amendment Act, 2015

shall be applicable and not the Amendment Act, 2015.

4.3Now, insofar as the reliance placed upon the

decision of this Court in the case of BCCI (supra) relied

upon on behalf of the appellant is concerned, it is

submitted that the decision in the case of BCCI (supra)

and the subsequent decisions following the BCCI (supra)

are all with respect to the proceedings under Sections 34

and 36 of the Act, 1996. It is submitted that therefore,

considering Sections 34 and 36 proceedings as

judicial/court proceedings, this Hon’ble Court has

interpreted Section 26, bifurcating Section 26 into two

Civil Appeal No. 3461 of 2023

Page 16 of 42

parts and to that it is observed and held that with respect

to judicial proceedings under Sections 34 and 36, the

Amendment Act, 2015 shall be applicable. It is submitted

that, however, on the other hand, there is a direct decision

of this Hon’ble Court in the case of Parmar Construction

Company (supra) dealing with the very issue of

application under Section 11(6) of the Act, 1996 and in the

said decision it is specifically observed and held that so

far as the application under Section 11(6) of the Act, 1996

is concerned, in case the notice invoking the arbitration is

invoked prior to the Amendment Act, 2015, pre

Amendment Act, 2015 shall be applicable. It is submitted

that as such the decision of this Court in the case of

Parmar Construction Company (supra), which is a Two

Judge Bench decision has been subsequently considered

and followed by a Three Judge Bench in the case of

Pradeep Vinod Construction Company (supra).

4.4It is further submitted that in the case of BCCI

(supra), this Court has unequivocally held that from the

scheme contained in Section 26 of the Amendment Act, it

is clear that the Amendment Act is prospective in nature

and will only apply to those arbitral proceedings that

commence in terms of Section 21 of the Act, on or after

the Amendment Act, and to Court proceedings, which

Civil Appeal No. 3461 of 2023

Page 17 of 42

have commenced on or after the Amendment Act came

into force. It is submitted that it necessarily follows that in

such cases, where the arbitration proceedings have been

initiated prior to 23.10.2015, it will continue to be

governed by the legal position as it existed prior to the

coming into force of the Amendment Act, 2015.

4.5It is submitted that as submitted hereinabove, the

judgments in Parmar Construction Company (supra)

and Pradeep Vinod Construction Company (supra) are

with respect to the applications under Section 11(6) and

the decision of this Court in the case of BCCI (supra) is

with respect to the proceedings under Sections 34 and 36

and even the observations made in paragraphs 37 to 39

are with respect to the “court proceedings” and therefore,

the aforesaid two decisions cannot be said to be in conflict

with the judgment in the case of BCCI (supra).

4.6It is submitted that the reliance by the appellant on

the expression “court proceedings in relation thereto” as it

occurs in Section 26 of the Amendment Act, 2015 to

contend that applications under Section 11 of the Act,

1996 would fall in such category is misplaced. It is

submitted that it must be borne in mind that this Hon’ble

Court was called upon to interpret Section 26 of the

Civil Appeal No. 3461 of 2023

Page 18 of 42

Amendment Act, 2015, to answer as to whether

applications under Section 36, which was amended by the

Amendment Act, 2015 would apply in its amended form in

respect of Section 34/36 proceedings initiated before the

commencement of the Amendment Act, 2015. It is

submitted that, thus, any observation in BCCI (supra)

ought to be understood in the context in which the issue

arose therein and the same cannot be said to have laid

down the law as regards applicability of the Amendment

Act, 2015 to Section 11 applications.

4.7It is submitted that the judgment in Parmar

Construction Company (supra) follows the judgment of

this Hon’ble Court in S.P. Singla Constructions Private

Limited (supra) in order to conclude that Section 11

petitions in respect of proceedings initiated prior to the

commencement of the Amendment Act, 2015, would be

governed by the pre-amended legal position. It is

submitted that the said judgment in S.P. Singla

Constructions Private Limited (supra) in turn follows

the observations of this Hon’ble Court in BCCI (supra).

4.8It is further submitted that the issue as to whether

the Amendment Act, 2015 would apply to proceedings

under Section 11, with respect to arbitration commenced

Civil Appeal No. 3461 of 2023

Page 19 of 42

prior to 23.10.2015 (the date on which the Amendment

Act, 2015 came into force) has been elaborately dealt with

by a Three Judge Bench in the case of S.P. Singla

Constructions Private Limited (supra), after analysing

threadbare the judgment in BCCI (supra) to conclude as

under:-

“16. Considering the facts and circumstances

of the present case, we are not inclined to go

into the merits of this contention of the

appellant nor examine the correctness or

otherwise of the above view taken by the

Delhi High Court in Ratna Infrastructure

Projects case [Ratna Infrastructure Projects

(P) Ltd. v. Meja Urja Nigam (P) Ltd., 2017

SCC OnLine Del 7808]; suffice it to note that

as per Section 26 of the Arbitration and

Conciliation (Amendment) Act, 2015, the

provisions of the amended 2015 Act shall not

apply to the arbitral proceedings commenced

in accordance with the provisions of Section

21 of the principal Act before the

commencement of the Amendment Act unless

the parties otherwise agree. In the facts and

circumstances of the present case, the

proviso in Clause (65) of the general

conditions of the contract cannot be taken to

be the agreement between the parties so as

to apply the provisions of the amended Act. As

per Section 26 of the Act, the provisions of the

Amendment Act, 2015 shall apply in relation to

Civil Appeal No. 3461 of 2023

Page 20 of 42

arbitral proceedings commenced on or after

the date of commencement of the Amendment

Act, 2015 (w.e.f. 23-10-2015). In the present

case, arbitration proceedings commenced

way back in 2013, much prior to coming into

force of the amended Act and therefore,

provisions of the amended Act cannot be

invoked.

17. In BCCI v. Kochi Cricket (P) Ltd. [(2018) 6

SCC 287], this Court has held that the

provisions of the Amendment Act, 2015 (with

effect from 23-10-2015) cannot have

retrospective operation in the arbitral

proceedings already commenced unless the

parties otherwise agree and held as under :

…………………………..”

4.9It is submitted that it is a settled law that arbitration

commences upon invocation of the notice as per Section

21 of the Act, 1996. It is submitted that therefore, in a

case where the notice invoking the arbitration has been

issued prior to the Amendment Act, 2015, on true

interpretation of Section 26 read with Section 21 of the

Amendment Act, 2015, the Amendment Act, 2015 shall

not be applicable and the arbitration would be governed

by the unamended provision.

Civil Appeal No. 3461 of 2023

Page 21 of 42

4.10Making above submissions and relying upon the

decisions of this Court in the case of Parmar

Construction Company (supra); Pradeep Vinod

Construction Company (supra) and S.P. Singla

Constructions Private Limited (supra), it is prayed to

dismiss the present appeal.

5.We have heard learned counsel for the respective

parties at length.

The short question which is posed for the

consideration of this Court is, in relation to the arbitration

proceedings, in a case where the notice invoking

arbitration is issued prior to the Amendment Act, 2015, the

old Act shall be applicable (pre-amendment 2015) or the

new Act?

6.While considering the aforesaid issue the relevant

provisions of the Amendment Act, 2015 are required to be

referred to, namely, Sections 11(6A), 21 and 26, which

are as under:

“(6A) The Supreme Court or, as the case may

be, the High Court, while considering any

application under sub-section (4) or sub-

section (5) or sub-section (6), shall,

notwithstanding any judgment, decree or

order of any Court, confine to the examination

of the existence of an arbitration agreement.

Civil Appeal No. 3461 of 2023

Page 22 of 42

21.Commencement of arbitral proceedings

– Unless otherwise agreed by the parties, the

arbitral proceedings in respect of a particular

dispute commence on the date on which a

request for that dispute to be referred to

arbitration is received by the respondent.

26.Act not to apply to pending arbitral

proceedings – Nothing contained in this Act

shall apply to the arbitral proceedings

commenced, in accordance with the

provisions of Section 21 of the principal Act,

before the commencement of this Act unless

the parties otherwise agree but this Act shall

apply in relation to arbitral proceedings

commenced on or after the date of

commencement of this Act.”

6.1Section 11(6A) has been inserted by Amendment

Act, 2015, by which the powers of the Court dealing with

an application under Section 11(6) of the Act are

restricted and as per section 11(6A), the powers of the

Court while deciding application under Section 11(6) of

the Act are confined to the examination of the existence of

an arbitration agreement, which powers were not

restricted in the pre-amendment Act, 2015. However,

Section 26 of the Amendment Act, 2015 provides that

nothing contained in this Act shall apply to the arbitral

proceedings commenced, in accordance with the

provisions of Section 21 of the principal Act, before the

Civil Appeal No. 3461 of 2023

Page 23 of 42

commencement of this Act unless the parties otherwise

agree. At this stage, it is required to be noted that as per

Section 21 of the principal Act, unless otherwise agreed

by the parties, the arbitral proceedings in respect of a

particular dispute commence on the date on which a

request for that dispute to be referred to the arbitration is

received by the respondent. Therefore, as per section 21

of the principal Act, the arbitral proceedings can be said to

have commenced on the date on which a request for the

dispute to be referred to the arbitration is received by the

respondent. Therefore, as per section 21 of the principal

Act the arbitral proceedings can be said to have

commenced on the date on which a request for the

dispute to be referred to the arbitration is received by the

respondent. At this stage, it is required to be noted that

by Amendment Act, 2015, Sections 34 and 36 of the

Arbitration Act also came to be amended and the

interference of the Court in challenge to the award has

been restricted and/or narrowed down.

7.The question of applicability of the Arbitration

Amendment Act, 2015 fell for consideration before this

Court in catena of decisions, few of them are as under:

Civil Appeal No. 3461 of 2023

Page 24 of 42

i)In the case of Mayawati Trading v. Pradyut

Debbarman, (2019) 8 SCC 714, it is observed and

held that the position of law that prevails after insertion

of section 11(6A) is that Supreme Court or, as the case

may be, the High Court, while considering any

application under Sections 11(4) to 11(6) is to confine

itself to examination of existence of arbitration

agreement, nothing more, nothing less, and leave all

other preliminary issues to be decided by arbitrator;

ii)In the case of BCCI (supra), while interpreting

section 26 of the Amended Act, 2015, this Court has

observed in paragraphs 37 to 39 as under:

“37. What will be noticed, so far as the first

part is concerned, which states—

“26. Act not to apply to pending

arbitral proceedings. — Nothing

contained in this Act shall apply to

the arbitral proceedings

commenced, in accordance with

the provisions of Section 21 of the

principal Act, before the

commencement of this Act unless

the parties otherwise agree.…”

is that: (1) “the arbitral proceedings” and their

commencement is mentioned in the context of

Section 21 of the principal Act; (2) the

expression used is “to” and not “in relation to”;

Civil Appeal No. 3461 of 2023

Page 25 of 42

and (3) parties may otherwise agree. So far as

the second part of Section 26 is concerned,

namely, the part which reads, “… but this Act

shall apply in relation to arbitral proceedings

commenced on or after the date of

commencement of this Act” makes it clear that

the expression “in relation to” is used; and the

expression “the” arbitral proceedings and “in

accordance with the provisions of Section 21

of the principal Act” is conspicuous by its

absence.

38. That the expression “the arbitral

proceedings” refers to proceedings before an

Arbitral Tribunal is clear from the heading of

Chapter V of the 1996 Act, which reads as

follows:

“Conduct of arbitral proceedings”

The entire chapter consists of Sections 18 to

27 dealing with the conduct of arbitral

proceedings before an Arbitral Tribunal. What

is also important to notice is that these

proceedings alone are referred to, the

expression “to” as contrasted with the

expression “in relation to” making this clear.

Also, the reference to Section 21 of the 1996

Act, which appears in Chapter V, and which

speaks of the arbitral proceedings

commencing on the date on which a request

for a dispute to be referred to arbitration is

received by the respondent, would also make

it clear that it is these proceedings, and no

others, that form the subject-matter of the first

Civil Appeal No. 3461 of 2023

Page 26 of 42

part of Section 26. Also, since the conduct of

arbitral proceedings is largely procedural in

nature, parties may “otherwise agree” and

apply the Amendment Act to arbitral

proceedings that have commenced before the

Amendment Act came into force. [ Section 29-

A of the Amend (sic Amended) Act provides

for time-limits within which an arbitral award is

to be made. In Hitendra Vishnu

Thakur v. State of Maharashtra, (1994) 4 SCC

602 at p. 633 : 1994 SCC (Cri) 1087, this

Court stated: (SCC p. 633, para 26)“26. … (iii)

Every litigant has a vested right in substantive

law but no such right exists in procedural law.

(iv) A procedural statute should not generally

speaking be applied retrospectively where the

result would be to create new disabilities or

obligations or to impose new duties in respect

of transactions already accomplished.(v) A

statute which not only changes the procedure

but also creates new rights and liabilities shall

be construed to be prospective in operation,

unless otherwise provided, either expressly or

by necessary implication.” It is, inter alia,

because timelines for the making of an arbitral

award have been laid down for the first time in

Section 29-A of the Amendment

(sic Amended) Act that parties were given the

option to adopt such timelines which, though

procedural in nature, create new obligations in

respect of a proceeding already begun under

the unamended Act. This is, of course, only

one example of why parties may otherwise

agree and apply the new procedure laid down

by the Amendment Act to arbitral proceedings

that have commenced before it came into

Civil Appeal No. 3461 of 2023

Page 27 of 42

force.] In stark contrast to the first part of

Section 26 is the second part, where the

Amendment Act is made applicable “in relation

to” arbitral proceedings which commenced on

or after the date of commencement of the

Amendment Act. What is conspicuous by its

absence in the second part is any reference to

Section 21 of the 1996 Act. Whereas the first

part refers only to arbitral proceedings before

an Arbitral Tribunal, the second part refers to

court proceedings “in relation to” arbitral

proceedings, and it is the commencement of

these court proceedings that is referred to in

the second part of Section 26, as the words

“in relation to the arbitral proceedings” in the

second part are not controlled by the

application of Section 21 of the 1996 Act.

39. Section 26, therefore, bifurcates

proceedings, as has been stated above, with

a great degree of clarity, into two sets of

proceedings — arbitral proceedings

themselves, and court proceedings in relation

thereto. The reason why the first part of

Section 26 is couched in negative form is only

to state that the Amendment Act will apply

even to arbitral proceedings commenced

before the amendment if parties otherwise

agree. If the first part of Section 26 were

couched in positive language (like the second

part), it would have been necessary to add a

proviso stating that the Amendment Act would

apply even to arbitral proceedings

commenced before the amendment if the

parties agree. In either case, the intention of

the legislature remains the same, the negative

Civil Appeal No. 3461 of 2023

Page 28 of 42

form conveying exactly what could have been

stated positively, with the necessary proviso.

Obviously, “arbitral proceedings” having been

subsumed in the first part cannot re-appear in

the second part, and the expression “in

relation to arbitral proceedings” would,

therefore, apply only to court proceedings

which relate to the arbitral proceedings. The

scheme of Section 26 is thus clear: that the

Amendment Act is prospective in nature, and

will apply to those arbitral proceedings that

are commenced, as understood by Section 21

of the principal Act, on or after the Amendment

Act, and to court proceedings which have

commenced on or after the Amendment Act

came into force.”

Thus, in the case of BCCI (supra), it is observed

and held that the Amendment Act, 2015 is prospective

in nature. However, it is required to be noted that in

the case of BCCI (supra), this Court was considering

the proceedings under sections 34 and 36 of the

Amendment Act, 2015 and to that while interpreting

section 26, it is observed that the Amendment Act is

prospective in nature, and will apply even to those

arbitral proceedings that are commenced, as

understood by section 21 of the principal Act, prior to

the Amendment Act, and to Court proceedings which

have commenced on or after the Amendment Act came

into force.

Civil Appeal No. 3461 of 2023

Page 29 of 42

iii)In the case of Parmar Construction Company

(supra), in relation to application under section 11(6)

of the Act, in a case where notice for arbitration is

received/invoked prior to the Amendment Act, 2015,

but the application under section 11(6) of the Act is

filed post Amendment Act, 2015, it is observed in

paragraphs 25 to 28 as under:

“25. As on 1-1-2016, the 2015 Amendment

Act was gazetted and according to Section

1(2) of the 2015 Amendment Act, it was

deemed to have come into force on 23-10-

2015. Section 21 of the 1996 Act clearly

envisages that unless otherwise agreed by the

parties, the arbitral proceedings in respect of a

dispute shall commence from the date on

which a request for that dispute to be referred

to arbitration is received by the respondent

and the plain reading of Section 26 of the

2015 Amendment Act is self-explicit, leaves no

room for interpretation. Sections 21 and 26 of

the 1996 Act/the 2015 Amendment Act

relevant for the purpose are extracted

hereunder:

“21. Commencement of arbitral

proceedings.—Unless otherwise

agreed by the parties, the arbitral

proceedings in respect of a particular

dispute commence on the date on which

a request for that dispute to be referred

Civil Appeal No. 3461 of 2023

Page 30 of 42

to arbitration is received by the

respondent.

***

26. Act not to apply to pending

arbitral proceedings .—Nothing

contained in this Act shall apply to the

arbitral proceedings commenced, in

accordance with the provisions of

Section 21 of the principal Act, before

the commencement of this Act unless

the parties otherwise agree but this Act

shall apply in relation to arbitral

proceedings commenced on or after the

date of commencement of this Act.”

26. The conjoint reading of Section 21 read

with Section 26 leaves no manner of doubt

that the provisions of the 2015 Amendment

Act shall not apply to such of the arbitral

proceedings which have commenced in terms

of the provisions of Section 21 of the principal

Act unless the parties otherwise agree. The

effect of Section 21 read with Section 26 of

the 2015 Amendment Act has been examined

by this Court in Aravali Power Co. (P)

Ltd. v. Era Infra Engg. Ltd. [Aravali Power Co.

(P) Ltd. v. Era Infra Engg. Ltd., (2017) 15 SCC

32 : (2018) 2 SCC (Civ) 642] and taking note

of Section 26 of the 2015 Amendment Act laid

down the broad principles as under : (SCC p.

53, para 22)

“22. The principles which emerge from

the decisions referred to above are:

Civil Appeal No. 3461 of 2023

Page 31 of 42

22.1. In cases governed by the 1996 Act

as it stood before the Amendment Act

came into force:

22.1.1. The fact that the named

arbitrator is an employee of one of the

parties is not ipso facto a ground to

raise a presumption of bias or partiality

or lack of independence on his part.

There can however be a justifiable

apprehension about the independence

or impartiality of an employee arbitrator,

if such person was the controlling or

dealing authority in regard to the subject

contract or if he is a direct subordinate

to the officer whose decision is the

subject-matter of the dispute.

22.1.2. Unless the cause of action for

invoking jurisdiction under clauses (a),

(b) or (c) of sub-section (6) of Section 11

of the 1996 Act arises, there is no

question of the Chief Justice or his

designate exercising power under sub-

section (6) of Section 11.

22.1.3. The Chief Justice or his

designate while exercising power under

sub-section (6) of Section 11 shall

endeavour to give effect to the

appointment procedure prescribed in the

arbitration clause.

22.1.4. While exercising such power

under sub-section (6) of Section 11, if

Civil Appeal No. 3461 of 2023

Page 32 of 42

circumstances exist, giving rise to

justifiable doubts as to the

independence and impartiality of the

person nominated, or if other

circumstances warrant appointment of

an independent arbitrator by ignoring

the procedure prescribed, the Chief

Justice or his designate may, for

reasons to be recorded ignore the

designated arbitrator and appoint

someone else.

22.2. In cases governed by the 1996 Act

after the Amendment Act has come into

force : If the arbitration clause finds foul

with the amended provisions, the

appointment of the arbitrator even if

apparently in conformity with the

arbitration clause in the agreement,

would be illegal and thus the court

would be within its powers to appoint

such arbitrator(s) as may be

permissible.”

which has been further considered in S.P.

Singla Constructions (P) Ltd. case [S.P.

Singla Constructions (P) Ltd. v. State of H.P.,

(2019) 2 SCC 488 : (2019) 1 SCC (Civ) 748] :

(SCC p. 495, para 16)

“16. Considering the facts and

circumstances of the present case, we

are not inclined to go into the merits of

this contention of the appellant nor

examine the correctness or otherwise of

Civil Appeal No. 3461 of 2023

Page 33 of 42

the above view taken by the Delhi High

Court in Ratna Infrastructure Projects

case [Ratna Infrastructure Projects (P)

Ltd. v. Meja Urja Nigam (P) Ltd., 2017

SCC OnLine Del 7808] ; suffice it to note

that as per Section 26 of the Arbitration

and Conciliation (Amendment) Act,

2015, the provisions of the amended

2015 Act shall not apply to the arbitral

proceedings commenced in accordance

with the provisions of Section 21 of the

principal Act before the commencement

of the Amendment Act unless the parties

otherwise agree. In the facts and

circumstances of the present case, the

proviso in Clause (65) of the general

conditions of the contract cannot be

taken to be the agreement between the

parties so as to apply the provisions of

the amended Act. As per Section 26 of

the Act, the provisions of the 2015

Amendment Act shall apply in relation to

arbitral proceedings commenced on or

after the date of commencement of the

2015 Amendment Act (w.e.f. 23-10-

2015). In the present case, arbitration

proceedings commenced way back in

2013, much prior to coming into force of

the amended Act and therefore,

provisions of the amended Act cannot

be invoked.”

27. We are also of the view that the 2015

Amendment Act which came into force i.e. on

23-10-2015, shall not apply to the arbitral

proceedings which have commenced in

Civil Appeal No. 3461 of 2023

Page 34 of 42

accordance with the provisions of Section 21

of the principal Act, 1996 before the coming

into force of the 2015 Amendment Act, unless

the parties otherwise agree.

28. In the instant case, the request was made

and received by the appellants in the appeal

concerned much before the 2015 Amendment

Act came into force. Whether the application

was pending for appointment of an arbitrator

or in the case of rejection because of no claim

as in the instant case for appointment of an

arbitrator including change/substitution of

arbitrator, would not be of any legal effect for

invoking the provisions of the 2015

Amendment Act in terms of Section 21 of the

principal Act, 1996. In our considered view,

the applications/requests made by the

respondent contractors deserve to be

examined in accordance with the principal Act,

1996 without taking resort to the 2015

Amendment Act which came into force from

23-10-2015.”

In the case of Parmar Construction Company

(supra), this Court heavily relied upon para 16 of the

decision in the case of S.P. Singla Constructions

Private Limited (supra).

iv)Then comes the decision of this Court in the case of

Pradeep Vinod Construction Company (supra). In

the said case, a three Judge Bench of this Court has

Civil Appeal No. 3461 of 2023

Page 35 of 42

followed the decision in the case of Parmar

Construction Company (supra) and in the said

decision it is specifically observed that unamended

1996 Act, i.e., prior to Amendment Act, 2015 for

appointment of arbitrator shall be applicable where the

request to refer the dispute to arbitration was made

before 2015 amendment came into effect.

v)In the case of Ssangyong Engg. & Construction

Co. Ltd. (supra), in which the decision in the case of

BCCI (supra) was followed, it is observed and held

that section 34, as amended, will apply to only section

34 applications that have been made to the Court on or

after 23.10.2015 irrespective of the fact that the

arbitration proceedings may have commenced prior to

that date. (See para 19). However, it is required to be

noted that in the case of Ssangyong Engg. &

Construction Co. Ltd. (supra), this Court has

followed the decision in the case of BCCI (supra) (See

para 17).

8.It is the case on behalf of the appellant that

therefore in the case of BCCI (supra), the decision which

has been subsequently followed in the case of

Ssangyong Engg. & Construction Co. Ltd. (supra) and

Civil Appeal No. 3461 of 2023

Page 36 of 42

other decisions, it has been specifically observed and

held that the Amendment Act, 2015 is prospective in

nature. It is the case on behalf of the appellant that while

taking a contrary view in the cases of Parmar

Constructions Company (supra) and Pardeep Vinod

Construction Company (supra), this Court had not

noticed and/or considered the binding decision of this

Court in the case of BCCI (supra) and therefore the

decisions of this Court in the cases of Parmar

Constructions Company (supra) and Pardeep Vinod

Construction Company (supra) are per incuriam. It is

also the case on behalf of the appellant that so far as the

decision in the case of Aravali Power Company Private

Limited (supra), which was considered by this Court in

the case of Parmar Constructions Company (supra) is

concerned, in the said decision also, there is no reference

to the decision in the case of BCCI (supra). It is also the

case on behalf of the appellant that though in the case of

S.P. Singla Constrictions Private Limited (supra), there

is a reference to the decision in the case of BCCI

(supra), but in the said decision paragraphs 38 and 39

are not referred to and/or considered and except

reproduction of para 37, there is no further discussion in

the case of BCCI (supra). Therefore, it is the specific

Civil Appeal No. 3461 of 2023

Page 37 of 42

case on behalf of the appellant that as the decisions in

the cases of Parmar Constructions Company (supra)

and Pardeep Vinod Construction Company (supra) are

per incuriam, we must hold that in the present case

Amendment Act, 2015 shall be applicable and therefore

the High Court has committed a very serious error in

opining on accord and satisfaction which is not

permissible as per the Amendment Act, 2015, i.e., Section

11(6A).

9.Submission on behalf of the appellant, as above,

seems to be attractive but has no substance. This Court

is required to consider whether the decision in the cases

of Parmar Constructions Company (supra) and

Pardeep Vinod Construction Company (supra) can be

said to be per incuriam as the decision of this Court in the

case of BCCI (supra) has not been considered by this

Court in the said decisions. However, on a fair reading of

the decisions in the case of BCCI (supra) and the

observations made in paragraphs 37 to 39 and on a fair

reading of decisions in the cases of Parmar

Constructions Company (supra) and Pardeep Vinod

Construction Company (supra), we are of the opinion

that this Court in the case of BCCI (supra) has held that

the Arbitration Amendment Act, 2015 is prospective in

Civil Appeal No. 3461 of 2023

Page 38 of 42

nature insofar as the proceedings under sections 34 & 36

are concerned. It is required to be noted that in the case

of BCCI (supra), application under section 11(6) was not

the subject matter and there was no issue before the

Court that even in a case where the notice invoking the

arbitration is issued prior to the Amendment Act, 2015, but

the application under section 11(6) is filed post

Amendment Act, 2015, what will be the position and

whether the old Act will be applicable or the amended Act.

On the other hand, the decisions in the case of Parmar

Constructions Company (supra) is directly on the point,

namely, the application under section 11(6) of the Act. In

the case of Parmar Constructions Company (supra), it

is specifically observed and held that in a case where

notice invoking arbitration is issued prior to Amendment

Act, 2015 and the application under section 11(6) is filed

post amendment, as per section 21 of the principal Act,

the date of issuance of the notice invoking arbitration shall

be considered as commencement of the arbitration

proceedings and therefore as per section 26 of the

Amendment Act, 2015, the Amended Act, 2015 shall not

be applicable and the parties shall be governed by the

pre-amendment Act, 2015.

Civil Appeal No. 3461 of 2023

Page 39 of 42

9.1The submission on behalf of the appellant, as

above, cannot be accepted for the simple reason that this

Court in the case of BCCI (supra) was considering the

court proceedings under sections 34 and 36. To that, this

Court interpreted section 26 in paragraphs 37 to 39,

reproduced hereinabove, and held that the Amendment

Act is prospective in nature, and will apply to those

arbitral proceedings that are commenced as understood

by section 21 of the principal Act, on or after the

Amendment Act, 2015 and to court proceedings which

have commenced on or after the Amendment Act, 2015

came into force. Therefore, any observations made by

this Court in paragraphs 37 to 39 in the case of BCCI

(supra) shall be understood and construed with respect

to court proceedings which have commenced on or after

the Amendment Act coming into force, namely, the

proceedings under sections 34 & 36. Therefore, the

decisions of this Court in the cases of Parmar

Constructions Company (supra) and Pardeep Vinod

Construction Company (supra) cannot be said to be

per incuriam and/or in conflict with the decision of this

Court in the case of BCCI (supra). As observed

hereinabove, in the case of Parmar Constructions

Company (supra) which is directly on the point, it is

Civil Appeal No. 3461 of 2023

Page 40 of 42

specifically observed and held that the 2015 Amendment

Act, which came into force w.e.f. 23.10.2015 shall not

apply to the arbitral proceedings which are commenced in

accordance with the provisions of section 21 of the

principal Act, 1996 before the coming into force the 2015

Amendment Act, unless parties otherwise agree (para

27). Similar view has been expressed in the case of S.P.

Singla Constructions Private Limited (supra).

10.Applying the law laid down by this Court in the

cases of Parmar Constructions Company (supra) and

Pardeep Vinod Construction Company (supra) and

S.P. Singla Constructions Private Limited (supra) to

the facts of the case on hand as in the present case the

notice invoking arbitration clause was issued on

26.12.2013, i.e., much prior to the Amendment Act, 2015

and the application under Section 11(6) of the Act has

been preferred/filed on 27.04.2016, i.e., much after the

amendment Act came into force, the law prevailing prior

to the Amendment Act, 2015 shall be applicable and

therefore the High Court has rightly entered into the

question of accord and satisfaction and has rightly

dismissed the application under section 11(6) of the Act

applying the principal Act, namely, the Arbitration and

Conciliation Act, 1996, prevailing prior to the Amendment

Civil Appeal No. 3461 of 2023

Page 41 of 42

Act, 2015. We are in complete agreement with the view

taken by the High Court. It is observed and held that in a

case where the notice invoking arbitration is issued prior

to the Amendment Act, 2015 and the application under

Section 11 for appointment of an arbitrator is made post

Amendment Act, 2015, the provisions of pre-Amendment

Act, 2015 shall be applicable and not the Amendment Act,

2015.

11.In view of the above and for the reasons stated

above, the present appeal fails and the same deserves to

be dismissed and is accordingly dismissed. However, in

the facts and circumstances of the case, there shall be no

order as to costs.

………………………………..J.

[M.R. SHAH]

……………………………….J.

[C.T. RAVIKUMAR]

NEW DELHI;

MAY 09, 2023.

Civil Appeal No. 3461 of 2023

Page 42 of 42

Description

Legal Notes

Add a Note....