mining law, administrative law
0  08 Jan, 2026
Listen in 2:00 mins | Read in 117:00 mins
EN
HI

M/S. Sri Kumaraswamy Silica Mines Vs. The Government Of India And Others

  Andhra Pradesh High Court W.P. Nos.31066 OF 2021
Link copied!

Case Background

As per case facts, the petitioner, a silica sand mining firm, challenged an Environmental Clearance (EC) granted by the Ministry of Environment, Forest and Climate Change. The 7th respondent appealed ...

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

1

THE HONOURABLE SRI JUSTICE RAVI NATH TILHARI

&

* THE HON’BLE SRI JUSTICE MAHESWARA RAO

KUNCHEAM

+W.P. Nos.31066 OF 2021

% 08.01.2026

# M/s. Sri Kumaraswamy Silica

Mines, Momidi Village, Chillakur

Mandal, SPSR Nellore District.

……Petitioner.

And:

$1. The Government of India, represented by its Director, Ministry

of Environment, Forest and Climate Change, Indira

Paryavaran Bhavan, Jorbagh Road, Aliganj, New Delhi and

others.

….Respondents.

!Counsel for the petitioner : Sri P. Veera Reddy, Sr.

Advocate assisted by

Sri B. Sarma.

^Counsel for the respondents : Sri G. Sai Narayana Rao, learned counsel for

the respondents 1 and 2

Ms. Anusha, Assistant

Government Pleader for Mines

and Geology for respondents 3

to 6,

Sri Ganta Rama Rao, learned

senior counsel assisted by Sri

Kambampati Ramesh Babu,

learned counsel for the 7

th

respondent.

<Gist:

>Head Note:

? Cases referred:

1.(2017) 9 SCC 499

2

2.2025 SCC OnLine SC 1139

3.(2022) 11 SCC 1

4.(2025) 5 SCC 786

5.(2013) 4 SCC 465

6.2022 SCC OnLine SC 639

7.2013 SCC OnLine NGT 31

8.(2023) 7 SCC 740

9.AIR 1976 SC 578

10.(2023) 6 SCC 615

11.2022 SCC OnLine SC 362

12.2022 SCC OnLine SC 1469

13.2021 SCC OnLine SC 897

14.AIROnline 2021 Bom 4360

15.SLP No. 4127/2021

16.(2012) 8 SCC 524

17.(2019) 18 SCC 494

18.(1998) 8 SCC 1

19.(1997) 3 SCC 261

20.2021 SCC OnLine SC 897

21.2021 SCCOnline SC 7

22.(2006) 11 SCC 356

23.(2004) 2 SCC 65

24.(1998) 7 SCC 66

25.(2006) 6 SCC 430

26.(2020) 16 SCC 446

27.(1991) 2 SCC 716

28. SCC OnLine SC 1789

29.2025 SCC OnLine SC 2474

30.2013 SCC OnLine All 6052

3

HIGH COURT OF ANDHRA PRADESH

* * * *

W.P. Nos.31066 OF 2021

DATE OF JUDGMENT PRONOUNCED: 08.01.2026

SUBMITTED FOR APPROVAL:

THE HON'BLE SRI JUSTICE RAVI NATH TILHARI

&

THE HON'BLE SRI JUSTICE MAHESWARA RAO KUNCHEAM

1. Whether Reporters of Local newspapers

may be allowed to see the Judgments?

Yes/No

2. Whether the copies of judgment may be

marked to Law Reporters/Journals

Yes/No

3. Whether Your Lordships wish to see the

fair copy of the Judgment?

Yes/No

____________________

RAVI NATH TILHARI, J

______________________________

MAHESWARA RAO KUNCHEAM ,J

4

THE HON’BLE SRI JUSTICE RAVI NATH TILHARI

&

THE HON’BLE SRI JUSTICE MAHESWARA RAO KUNCHEAM

W.P. Nos.31066 OF 2021

JUDGMENT: per the Hon‟ble Sri Justice Ravi Nath Tilhari:

1. Heard Sri P. Veera Reddy, learned senior counsel assisted

by Sri Bargava Sarma, learned counsel for the petitioner, Sri G.

Sai Narayana Rao, learned counsel for the respondents 1 and 2,

Ms.Anusha, learned Assistant Government Pleader for Mines and

Geology for respondents 3 to 6, Sri Ganta Rama Rao, learned

senior counsel assisted by Sri Kambampati Ramesh Babu,

learned counsel for the 7

th

respondent.

I. Facts:

(i) Petitioner’s case:

2. The petitioner Sri Kumaraswamy Silica Mines

Momidi Village, Chillakur Mandal SPSR Nellore District Andhra

Pradesh, represented by its Managing Partner, has filed the

present writ petition under Article 226 of the Constitution of India,

challenging the order passed by the National Green Tribunal,

South Zone (NGTSZ), Chennai, dated 15.11.2021, in Appeal

No.19 of 2020 (SZ) (B. Madan Kumar Reddy vs. Government of

India and others), filed under Section 16 of the National Green

5

Tribunal Act, 2010 (in short, the NGT Act) filed by the present 7

th

respondent, B.M. Reddy, Challenging the Environmental

Clearance (EC) granted, to the present petitioner -7

th

respondent

in the Appeal, by the 1

st

respondent-the Government of India

represented by its Director, Ministry of Environment Forest and

Climate Change, IA Division, New Delhi, vide proceedings

No.F.No.23-238/2018-IA.II(v) dated 16.04.2020.

3. The petitioner firm is a partnership firm carrying on

business of Silica sand mining. Mining lease was originally

granted in the name of V. Rama Chandra Reddy on 24.05.1975

for an extent of Ac.512.01 cents in Sy.No.695/22 and 696 of

Momidi Village, Chillakur Mandal SPSR Nellore District. The

mining lease was executed on 04.09.1975 for a period of 20

years. It was later on transferred in favour of the petitioner‟s firm

by executing, transfer of lease dated 01.07.1985. The lease

period expired on 03.09.1995, and was renewed by the

Government of Andhra Pradesh for another 20 years from

03.09.1995 but for a reduced area of 338.39 acres in

Sy.No.695/22 and 696.

4. The petitioner applied for E.C on 23.11.2013 to the 1

st

respondent as per EIA Notification 2006. The proposal was

6

examined by the Expert Appraisal Committee (EAC), but the

MOEF and CC 1

st

respondent vide letter dated 21.04.2014

directed the petitioner to stop mining activity as the proposal was

said to be in violation of EIA notification. The petitioner filed

W.P.No.4490 of 2014 challenging the order dated 21.04.2014

which was disposed of vide order dated 06.06.2014, observing

that the principles of natural justice were violated and no

opportunity of hearing was given to the petitioner, and so, it was

provided that, the petitioner shall submit a representation to

MOEF & CC, setting out the explanation and the 1

st

respondent

was directed to consider and pass appropriate orders. The

petitioner submitted the representation dated 03.07.2014 to the

1

st

respondent inter alia submitting that the petitioner did not

commit any violation of EIA notification and requested for

issuance of Term of Reference (ToR).

5. In the meantime one Mallikarjuna Reddy filed O.A.No.96 of

2015 before the NGT against 48 Mining Units including against

the petitioner raising the grievance that those units were

operating minings without E.C. The petitioner put in appearance

and took the stand that the petitioner had applied for the E.C

which was pending consideration. It was also the stand that the

7

mining of the petitioner was in operation since before the EIA

notification of 1994 came into force and so there was no legal

requirement to obtain the EC. The NGT vide common interim

order dated 08.07.2015 directed the respondent No.1 to pass

orders on the application for EC. The petitioner‟s further case is

that on the representation dated 13.07.2015 TOR, was issued by

the 1

st

respondent on 10.08.2015 and in the O.A.No.96 of 2015,

the NGT passed the final order dated 07.09.2015, issuing

directions to the 1

st

respondent to pass final orders on the

application for grant of EC. The public hearing was conducted by

the A.P.State Pollution Control Board (in short, the Board) on

29.04.2016. The petitioner made a representation to the EAC in

May, 2016 in respect of its Mining Project. The EAC

recommended issuance of EC subject to the final decision of the

1

st

respondent. The petitioner‟s further case is that the Regional

Director of MOEF & CC, Chennai inspected the minings on

08.07.2016 and gave a report dated 16.08.2016 in petitioner‟s

favour. A joint inspection was also made by the Revenue and

Forest Officials during May, 2016 and a report dated 24.01.2017

was also sent to the District Collector, Nellore observing that the

lease area was altered but the mining was in the leased area

8

only and there was no encroachment. Another joint inspection of

the mining area was conducted by the Forest and Revenue

officials on 14.03.2017 and 15.03.2017 and a report was sent to

the MOEF & CC, observing that the Sy.No.696 was never

classified as reserve forest and it was only Sy.No.692 which was

a reserve forest and no mining had taken place in the reserve

forest. Further, in Sy.No.696, measuring Ac.92.40 cents was

classified as forest reserve poromboke but was subsequently

changed as jungle poromboke. The same was presently treated

as „Adavi‟ (jungle) poromboke. Sy.No.696 to an extent of about

Ac.20.00 cents was classified as government dry land, during the

lease period which was surrendered. The lease of the petitioner

was renewed vide order dated 03.02.2017 up to 2035.

6. The petitioner‟s further case is that the 7

th

respondent filed

W.P.(PIL) No.22 of 2017 before the High Court for the State of

Telangana and Andhra Pradesh, alleging that Sy.No.696 was

classified as reserve forest and fell in the lease area of the

petitioner and therefore the lease should not be renewed. The

petitioner had also filed O.A.No.187 of 2017 against the 1

st

respondent, for not granting EC, which was disposed of by the

NGT directing the 1

st

respondent to pass appropriate orders in

9

accordance with law. The 1

st

respondent issued a letter dated

05.04.2018 that the petitioner would have to apply under violation

category. Though, the petitioner‟s case is that there was no

violation, still the petitioner submitted the application under the

violation category. The proposal of the petitioner was placed

before the EAC in April, 2019 which recommended for grant of

EC observing that the petitioner should furnish a bank guarantee

for a sum of Rs.63,50,000/- in order to satisfy the criteria in the

notification dated 14.03.2017. The 1

st

respondent thereafter

granted EC to the petitioner on 16.04.2020.

(ii). Challenge before National Green Tribunal:

7. The grant of EC dated 16.04.2020 was challenged by the

present 7

th

respondent by filing appeal before the NGT under

Section 16 of the N.G.T.Act.

8. Before the NGT, in response to the appeal filed by the

present 7

th

respondent, the petitioner herein, filed counter raising

the objections inter alia that the appeal was not maintainable. It

was also pleaded that after ensuring that all the requirements

were satisfied the 1

st

respondent granted the EC. The petitioner

already paid a fine of Rs.1,00,000/- in C.C.No.456 of 2018, for

carrying on mining operations without obtaining EC, as also after

10

issuance of additional ToR by the 1

st

respondent. The petitioner

had also furnished the bank guarantee, as was recommended by

the EAC for a sum of Rs.63,50,000/- in order to satisfy the criteria

of the violation category.

9. The NGT allowed the Appeal vide order dated 15.11.2021,

with detailed directions, which shall be referred shortly, and kept

the E.C dated 16.11.2020 in abeyance.

10. The petitioner has filed this Writ Petition challenging the

order of the National Green Tribunal dated 15.11.2021.

iii. Case of the respondents as per the Counter Affidavit:

11 Respondents 3 to 6 filed counter affidavit. The stand taken

is that the Director of Mines and Geology, Ibrahimpatnam vide

notice dated 03.02.2017 decided in principle to grant second

renewal of quarry lease for Silica Sand in favour of the petitioner

for a further period of 20 years with effect from 04.09.2015. It was

not correct to say that the lease was renewed upto the year 2035.

In compliance of the said notice dated 03.02.2017, the petitioner

had submitted approved mining scheme, environmental

clearance, concent for establishment and consent for operation,

and the renewal was under consideration. Their further stand is

that pursuant to the order of the N.G.T in Appeal No.19 of 2020

11

necessary directions have been issued to the concerned

authorities to take immediate necessary action. They have also

submitted that the technical staff conducted survey and

inspection of the subject quarry lease area of the petitioner,

initially on 19.12.2022 to 21.12.2022, which submitted the report.

Further in obedience of the order dated 15.11.2021, the mining

operations over the subject leased area of the petitioner were

stopped and the dispatch permits for transportation of Silica sand

were not being issued.

12. The respondent No.7 has also filed the counter affidavit.

The objection has been raised with respect to the maintainability

of the writ petition on the ground that there is statutory alternative

remedy under Section 22 of the N.G.T Act. The 7

th

respondent

has supported the impugned order of the N.G.T submitting that

the same was passed in a statutory appeal under Section 16 of

the N.G.T Act. The appeal was maintainable as the 7

th

respondent herein (the appellant before the N.G.T) was

aggrieved person being an affected person and had every right to

challenge the environmental clearance granted to the petitioner in

violation of the prescribed procedure, as also without complying

with the judgment of the Hon‟ble Apex Court in the Common

12

Cause vs. Union of India

1

. The further stand of the 7

th

respondent is that there is no violation of the principles of natural

justice in passing the order by the N.G.T before which the

petitioner had the ample opportunity of hearing and after hearing

the present petitioner, the order was passed by the N.G.T.

13. The 7

th

respondent has filed an additional counter affidavit

as well, raising the plea that the mining operations were

conducted by the petitioner without having environmental

clearance which was required under the provisions of the

notification of 1994-2006. He has referred to the report dated

24.01.2017 of the inspection of the mining sent to the District

Collector submitting that in the said report several adverse

observations were made against the petitioner including the one

that the mining activity was done without leaving safety zones

and the other that there shall be an acute scarcity of water both

for irrigation and drinking water due to extensive mining and

machinery.

14. On 23.04.2025, this Court passed the order inter alia

directing the counsel for the respondents 1 and 2 to get

instructions on the point “whether any decision has been taken by

1

(2017) 9 SCC 499

13

the Ministry of Environment, Forest and Climate Change

pursuant to the direction of the N.G.T”. The respondents 1 and 2

have filed the memo dated 20.06.2025 mentioning the action

taken by the respondents 1 and 2 pursuant to the direction of the

N.G.T in its judgment dated 15.11.2021. But, we find that those

correspondences mainly are of the date prior to the judgment of

the N.G.T. Another memo has been filed, in which, in substance,

what has been stated is that “at present, the process of

complying with the N.G.T judgment requires some more time.”

(II). Submissions of the learned counsels:

15. Sri P. Veera Reddy, learned senior counsel for the

petitioner submitted that the appeal by the present 7

th

respondent

before the NGT was not maintainable under Section 16 of the

NGT Act. The 7

th

respondent is not an aggrieved person within

the meaning of Section 16, so as to challenge the grant of EC by

the 1

st

respondent in favour of the petitioner. The appeal was not

maintainable and so the order passed thereon by the NGT is

without jurisdiction.

16. Learned senior counsel for the petitioner submitted that on

various points, the NGT recorded the finding in favour of the

petitioner, but still allowed the appeal of the 7

th

respondent. He

14

submitted that the grounds on which the EC has been kept in

abeyance and the matter has been remitted for fresh

consideration, were not even informed to the petitioner so,

against those grounds the petitioner was not afforded any

opportunity of hearing. The impugned order therefore, suffers

from violation of the principles of natural justice, and deserves to

be set aside.

17. Sri P. Veera Reddy, learned senior counsel for the

petitioner further submitted that the Project is for Silica Sand Mine

which is entirely different mineral to which the Sustainable Sand

Mining Management Guidelines, 2016 (in short SSMMG, 2016)

would not be applicable, which guidelines in his submission are

applicable only to recoveries of sand from the rivers.

18. Learned counsel for the petitioner further submitted that the

E.C was granted prior to the notification dated 07.07.2021 and

consequently notification of 2021 should not govern the

petitioner‟s case. He further submitted that the EC having been

granted under the notification of 2017, it was not open for the

Tribunal to have kept it in abeyance with the directions issued for

consideration on the points mentioned in the order of N.G.T. He

submitted that the E.C (s) granted upto the date of judgment in

15

Vanashakti vs Union of India

2

remained unaffected by and in terms of

the said judgment itself.

19. Learned counsel for the petitioner placed reliance on the

following judgments:-

1. Rajeev Suri vs Delhi Development Auhtority and others

3

2. Union of India vs Parashotam Das

4

3. Ayaaubkhan Noorkhan Pathan vs State of Maharashtra

5

4. Madhya Pradesh High Court Advocates Bar association vs

Union of India

6

5. Rana Sengupta vs Union of India

7

6. S. Narahari vs S. R. Kumar

8

7. JasbhaiMotibhai Desai vs Roshan Kumar

9

8. Electrosteel Steels ltd vs Union of India

10

9. Pahwa Plastics Pvt. Ltd. vs Dastak NGO

11

10. State of Uttar Pradesh vs Uday Education and Welfare Trust

12

ii) For the respondent No.7:

20. Sri Ganta Rama Rao, learned senior advocate assisted by

Sri Kambampati Ramesh Babu, learned counsel for the 7

th

2

2025 SCC OnLine SC 1139

3

(2022) 11 SCC 1

4

(2025) 5 SCC 786

5

(2013) 4 SCC 465

6

2022 SCC OnLine SC 639

7

2013 SCC OnLine NGT 31

8

(2023) 7 SCC 740

9

AIR 1976 SC 578

10

(2023) 6 SCC 615

11

2022 SCC OnLine SC 362

12

2022 SCC OnLine SC 1469

16

respondent raised a preliminary objection, that the order

impugned is subject to appeal before the Hon‟ble Apex Court.

There is alternative remedy under Section 22 of the NGT Act and

so the writ petition deserves not to be entertained.

21. Sri Ganta Rama Rao, learned senior counsel further

submitted that the NGT for the well recorded reasons viz. that,

various relevant aspects were not considered by the EAC

including no-detailed study conducted by the Project Proponent,

and that without ascertaining whether any District Survey was

conducted, the EC was recommended and granted which was in

violation of the SSMM Guidelines, 2016, kept the EC in abeyance

and remitted the matter for fresh consideration. So, there is no

illegality in the order of NGT, which calls for no interference in the

exercise of writ jurisdiction.

22. He further submitted that the respondent No.7 had the

locus being an aggrieved person within the meaning of Section

16 of the N.G.T Act, to maintain the appeal. So, the order of the

N.G.T is not without jurisdiction. He further submitted that in any

case the N.G.T has suo moto power to take note of the

environmental violations and threats and so even if the appeal be

17

not maintainable, the order of the N.G.T would be within

jurisdiction.

23. Learned counsel for the respondents submitted that the

procedure even under the notification of 2017 was not followed.

The expert committee did not act according to the procedure

prescribed in making the recommendations and therefore the

Tribunal having found the irregularities committed and the

necessary measures not having been adopted and the relevant

considerations not having been kept in view, the Tribunal was

right in passing the impugned order and keeping the E.C in

abeyance. So, the submission based on the no applicability of

the notification of 2021 is unsustainable.

24. Learned counsel for the respondents placed reliance on the

following judgments:-

1. Municipal Corporation of Greater Mumbai

13

2. Directorate of Mines and Geology vs Saidas

Khorjuvekar

14

3. Mehra Bal Chikitsalaya Evam NavjatShishu I.C.U. vs

Manoj Upadhyay

15

4. Cicily Kallarackal vs Vehicle Factory

16

13

2021 SCC OnLine SC 897

14

AIROnline 2021 Bom 4360

15

SLP No. 4127/2021

16

(2012) 8 SCC 524

18

5. Madhya Pradesh High Court Advocates Bar association

vs Union of India. (2022 SCC OnLine SC 639)

6. Mantri Techzone Pvt. Ltd. vs Forward Foundation

17

iii) Reply submissions:

25. In response, Sri P. Veera Reddy, learned senior counsel for

the petitioner submitted that the alternative remedy is no bar to

the maintainability or entertainability of the writ petition under

Article 226 of the Constitution of India. Further, the challenge to

the order of the NGT is on the ground of violation of the principles

of natural justice and being without jurisdiction. The writ petition

therefore deserves to be entertained.

26. He further submitted that the writ petition was filed in the

year 2021 and at this stage after four years, the petitioner

deserves not to be relegated to the alternative remedy of appeal.

III. Points for consideration:

27. The following points arise for our consideration and

determination:

(A) Whether the writ petition against the order of the

N.G.T is not maintainable? And if maintainable, it should or

should not be entertained?

17

(2019) 18 SCC 494

19

(B) Whether the impugned order of the N.G.T is without

jurisdiction on the argument that the appeal by 7

th

respondent was not maintainable under Section 16 of the

N.G.T Act?

(C) Whether the impugned order of the N.G.T violates

the principles of natural justice?

(D) Whether the order of the N.G.T calls for interference

in the exercise of the writ jurisdiction?

28. We have considered the aforesaid submissions and

perused the material on record.

IV. Analysis:

Point-A: Maintainability and entertainability of the writ

petition:

29. We would first consider the preliminary objection with

respect to the maintainability of the writ petition against the order

of the N.G.T, in the light of the submission advanced by the

learned counsel for the 7

th

respondent in view of the availability of

statutory remedy of appeal under Section 22 of the N.G.T.

30. Learned counsel for the 7

th

respondent placed reliance in

Directorate of Mines and Geology (supra). The Bombay High

Court held that the scheme of N.G.T Act should not be derailed by

taking recourse to proceed under Article 226 of the Constitution

20

of India and that the judicial prudence demands that the writ

Court refrains from exercising its jurisdiction. It was observed that

the appeal under Section 22 of the NGT Act is not a matter of right

and an appeal can be entertained on one or more of the grounds

mentioned in Section 100 of the Code of the Civil Procedure, but

that by itself would not warrant interdiction by a writ court. The

Bombay High Court declined to exercise the writ jurisdiction and

left the petitioners to avail the remedy of appeal before the Apex

Court or file the review before the Tribunal as provided by the

N.G.T Act in accordance with law. He contended that in view of

the remedy of appeal under Section 22 of the NGT Act, the writ

petition should not be entertained.

31. Learned counsel for the 7

th

respondent further placed

reliance in Cicily Kallarackal (supra), in which it was held that it

is not appropriate for the High Courts to entertain writ petitions

under Article 226 of the Constitution of India against the orders

passed by the Commission under the Consumer Protection Act,

1986, once the legislature had provided for a statutory appeal to

a higher court. It cannot be proper exercise of jurisdiction to

permit the parties to bypass the statutory appeal to a higher court

and entertain writ petitions under Article 226 of the Constitution of

21

India. Reliance was also placed reliance in Mehra Bal

Chikitsalaya Evam Navjat Shishu (supra), in which also, the

principle of law as laid down in Cicily Kallarackal (supra) was

restated and the writ petition was dismissed on the ground of

maintainability in the light of the availability of the statutory

alternative remedy.

32. So far as the maintainability of the writ petition against the

orders of the Tribunal is concerned, the law has been well settled

by the Hon‟ble Apex Court. The existence of the statutory

alternative remedy is no bar to the maintainability of the writ

petition under Article 226 of the Constitution of India. That does

not take away the jurisdiction of this Court though ordinarily, in

view of the statutory alternative remedy, this Court would be

reluctant in invoking the jurisdiction and would first require the

petitioner to avail the statutory alternative remedy. But, that is not

an absolute bar neither to the maintainability nor to the

entertainability of the writ petition. The exceptions to the doctrine

of exhaustion of alternative remedies are also well laid down,

inter alia, when the challenge is on the ground of the impugned

order being without jurisdiction; having been passed in violation

of the principles of natural justice, violation of fundamental rights;

22

utra vires, as laid down in the cases inter alia Whirlpool

Corporation vs. Registrar of Trade Marks, Mumbai

18

and other

various pronouncements of the Hon‟ble Apex Court.

33. In Madhya Pradesh High Court Advocates Bar Association

(supra), one of the issues was:

“A. Whether the NGT seized the High Court‟s jurisdiction

under Section 14 & 22 of the NGT Act.”

34. The Hon‟ble Apex Court referring to the judgment in L.Chandra

Kumar vs. Union of India

19

, reiterated that the NGT like any other

Tribunal is within the jurisdiction of the High Court (s) under Article 226

and 227 of the Constitution of India but it further observed that while

exercising such jurisdiction the courts necessarily exercise due

discretion on whether to entertain or to reject the petition as per the

test broadly laid down in Whirlpool Corporation (supra). The Hon‟ble

Apex Court further held that there is nothing contained in the N.G.T

Act, either impliedly or explicitly which seized the jurisdiction of the

High Court under Article 226 and 227 of the Constitution of India. The

power of judicial review remains intact and uneffected by the NGT Act.

35. Paras 18 to 22 and 45 of Madhya Pradesh High Court

Advocates Bar Association (supra) read as under:

18

(1998) 8 SCC 1

19

(1997) 3 SCC 261

23

“18. With the above prefatory contexts in mind, we may now look

at the challenge.

ISSUE WISE DISCUSSION

A. Whether the NGT ousts the High Court's jurisdiction under

Sections 14 & 22 of the NGT Act?

19. Insofar as the contention of the petitioners that there is ouster

of jurisdiction of the High Courts under Article 226 and 227 of the

Constitution because of Sections 14 & 22 of the NGT Act, it must

be recalled that in L. Chandra Kumar v. Union of India [supra], it

has been categorically declared that the power of judicial review

under Articles 226, 227, and 32 are part of the basic structure of

our constitution and the same is inviolable. The following pertinent

opinion rendered by the 7 Judges' bench of this Court must be

remembered on this aspect:—

“78..........We, therefore, hold that the power of judicial review over

legislative action vested in the High Courts under Article 226 and

in this Court under Article 32 of the Constitution is an integral and

essential feature of the Constitution, constituting part of its basic

structure. Ordinarily, therefore, the power of High Courts and the

Supreme Court to test the constitutional validity of legislations can

never be ousted or excluded.

79. We also hold that the power vested in the High Courts to

exercise judicial superintendence over the decisions of all courts

and tribunals within their respective jurisdictions is also part of the

basic structure of the Constitution. This is because a situation

where the High Courts are divested of all other judicial functions

apart from that of constitutional interpretation, is equally to be

avoided.”

20. Apart from the clear enunciation on legal position to the effect

that the NGT is within the purview of Article 226 and 227

jurisdiction of the High Courts, the learned Attorney General on

24

behalf of the Union of India has also made submissions consistent

with L. Chandra Kumar [supra] and conceded the legal position.

21. It can further be noted that in terms of the above ratio in L.

Chandra Kumar* [supra], the High Courts have been entertaining

petitions under Article 226 and 227 of the Constitution against

orders of the NGT. While exercising such jurisdiction, the Courts

necessarily exercise due discretion on whether to entertain or to

reject the petition, as per the test broadly laid down in Whirlpool

Corpn. v. Registrar of Trade Marks, Mumbai;

14. The power to issue prerogative writs under Article 226 of the

Constitution is plenary in nature and is not limited by any other

provision of the Constitution. This power can be exercised by the

High Court not only for issuing writs in the nature of habeas

corpus, mandamus, prohibition, quo warranto and certiorari for the

enforcement of any of the Fundamental Rights contained in Part

III of the Constitution but also for “any other purpose”.

15. Under Article 226 of the Constitution, the High Court, having

regard to the facts of the case, has a discretion to entertain or not

to entertain a writ petition. But the High Court has imposed upon

itself certain restrictions one of which is that if an effective and

efficacious remedy is available, the High Court would not normally

exercise its jurisdiction. But the alternative remedy has been

consistently held by this Court not to operate as a bar in at least

three contingencies, namely, where the writ petition has been filed

for the enforcement of any of the Fundamental Rights or where

there has been a violation of the principle of natural justice or

where the order or proceedings are wholly without jurisdiction or

the vires of an Act is challenged. There is a plethora of case-law

on this point but to cut down this circle of forensic whirlpool, we

would rely on some old decisions of the evolutionary era of the

constitutional law as they still hold the field.”

25

22. It is also noteworthy that nothing contained in the NGT Act

either impliedly or explicitly, ousts the jurisdiction of the High

Courts under Article 226 and 227 and the power of judicial review

remains intact and unaffected by the NGT Act. The prerogative of

writ jurisdiction of High Courts is neither taken away nor it can be

ousted, as without any doubt, it is definitely a part of the basic

structure of the Constitution. The High Court's exercise their

discretion in tandem with the law depending on the facts of each

particular case. Since the High Court's jurisdiction remain

unaffected, the first question is answered in the negative, against

the petitioners.

45. In consequence of the above analysis, our conclusions

are,

A. The National Green Tribunal under Sections 14 & 22 of

the NGT Act does not oust the High Court‟s jurisdiction under

Article 226 & 227 as the same is a part of the basic structure of

the Constitution.”

36. In Parashotam Dass (supra), one of the issues was with

respect to the power of High Court under Article 226 of the

Constitution of India with respect to the order of the Armed

Forces Tribunal, against which the remedy of appeal was

provided to the Supreme Court under the Armed Forces Tribunal

Act, 2007. The Hon‟ble Apex Court reiterated that the power of

High Court under Article 226 of the Constitution of India is not

inhibited.

26

37. Paras 25 and 26 of Parashotam Dass (supra) read as

under:

“25. While we agree with the aforesaid principle, we are unable

to appreciate the observations in the case of Major General Shri

Kant Sharma & Anr. (supra), which sought to put an embargo

on the exercise of jurisdiction under Article 226 of the

Constitution, diluting a very significant provision of the

Constitution which also forms the part of basic structure. The

principles of basic structure have withstood the test of time and

are emphasized in many judicial pronouncements as an

ultimate test. This is not something that can be doubted. That

being the position, the self-restraint of the High Court under

Article 226 of the Constitution is distinct from putting an

embargo on the High Court in exercising this jurisdiction under

Article 226 of the Constitution while judicially reviewing a

decision arising from an order of the Tribunal.

26. On the legislature introducing the concept of

"Tribunalisation" (one may say that this concept has seen many

question marks vis-a-vis different tribunals, though it has also

produced some successes), the same was tested in L. Chandra

Kumar (supra) case before a Bench of seven Judges of this

Court. Thus, while upholding the principles of "Tribunalisation"

under Article 323A or Article 323B, the Benc h was

unequivocally of the view that decisions of Tribunals would be

subject to the jurisdiction of the High Court under Article 226 of

the Constitution, and would not be restricted by the 42nd

Constitutional Amendment which introduced the aforesaid two

Articles. In our view, this should have put the matter to rest, and

no Bench of less than seven Judges could have doubted the

proposition. The need for the observations in the five-Judges'

Bench in Rojer Mathew (supra) case qua the Armed Forces

27

Tribunal really arose because of the observations made in

Major General Shri Kant Sharma & Anr. (supra) Thus, it is,

reiterated and clarified that the power of the High Court under

Article 226 of the Constitution is not inhibited, and

superintendence and control under Article 227 of the

Constitution are somewhat distinct from the powers of judicial

review under Article 226 of the Constitution.”

38. We thus hold that the writ petition is maintainable. Further,

as the challenge is on the grounds of order being without

jurisdiction and in violation of the principles of natural justice, and

further as the writ petition is pending since 2021 with the affidavit

exchanged, we entertain the writ petition as well.

Point-B( Order if without jurisdiction):

39. The submission of the learned counsel for the petitioner is

that the 7

th

respondent herein does not fall under the expression

„person aggrieved by‟ so as to maintain the appeal under Section

16 of the N.G.T Act and so, the order passed by the N.G.T in the

appeal of 7

th

respondent is without jurisdiction.

40. Section 16 of the N.G.T Act read as under:

Section 16. Tribunal to have appellate jurisdiction.

Any person aggrieved by,--

(a) an order or decision, made, on or after the

commencement of the National Green Tribunal Act, 2010, by the

appellate authority under section 28 of the Water (Prevention

and Control of Pollution) Act, 1974 (6 of 1974);

28

(b) an order passed, on or after the commencement of

the National Green Tribunal Act, 2010, by the State Government

under section 29 of the Water (Prevention and Control of

Pollution) Act, 1974 (6 of 1974);

(c) directions issued, on or after the commencement of

the National Green Tribunal Act, 2010, by a Board, under

section 33A of the Water (Prevention and Control of Pollution)

Act, 1974 (6 of 1974);

(d) an order or decision made, on or after the

commencement of the National Green Tribunal Act, 2010, by the

appellate authority under section 13 of the Water (Prevention

and Control of Pollution) Cess Act, 1977 (36 of 1977);

(e) an order or decision made, on or after the

commencement of the National Green Tribunal Act, 2010, by the

State Government or other authority under section 2 of the

Forest (Conservation) Act, 1980 (69 of 1980);

(f) an order or decision, made, on or after the

commencement of the National Green Tribunal Act, 2010, by the

Appellate Authority under section 31 of the Air (Prevention and

Control of Pollution) Act, 1981 (14 of 1981);

(g) any direction issued, on or after the commencement

of the National Green Tribunal Act, 2010, under section 5 of the

Environment (Protection) Act, 1986 (29 of 1986);

(h) an order made, on or after the commencement of the

National Green Tribunal Act, 2010, granting environmental

clearance in the area in which any industries, operations or

processes or class of industries, operations and processes shall

not be carried out or shall be carried out subject to certain

safeguards under the Environment (Protection) Act, 1986 (29 of

1986);

(i) an order made, on or after the commencement of the

National Green Tribunal Act, 2010, refusing to grant

environmental clearance for carrying out any activity or

29

operation or process under the Environment (Protection) Act,

1986 (29 of 1986);

(j) any determination of benefit sharing or order made, on

or after the commencement of the National Green Tribunal Act,

2010, by the National Biodiversity Authority or a State

Biodiversity Board under the provisions of the Biological

Diversity Act, 2002 (18 of 2003), may, within a period of thirty

days from the date on which the order or decision or direction or

determination is communicated to him, prefer an appeal to the

Tribunal:

Provided that the Tribunal may, if it is satisfied that the

appellant was prevented by sufficient cause from filing the

appeal within the said period, allow it to be filed under this

section within a further period not exceeding sixty days.”

41. Section 16 of the N.G.T Act thus provides that „any person

aggrieved by‟ an order, decision, direction etc. under Clauses (a)

to (j), prefer an appeal to the Tribunal.

42. In Jasbhai Motibhai Desai (supra), on the point of locus

standi, the Hon‟ble Apex held that an applicant may ordinarily fall

in any of these categories; i) persons aggrieved; (ii) strangers;

and (iii) busybodies/meddlesome interlopers. The Hon‟ble Apex

Court observed that there is a distinction between the first and

second categories of applicants, though real, is not always well-

demarcated. The Hon‟ble Apex Court laid down some broad

tests, to determine whether the applicant is a person aggrieved,

30

observing that those tests were not absolute or ultimate

paragraphs 36 to 38 read as under:

36. It will be seen that in the context of locus standi to apply for a

writ of certiorari, an applicant may ordinarily fall in any of these

categories:

(i) “person aggrieved”; (ii) “stranger”; (iii) busybody or meddlesome

interloper. Persons in the last category are easily distinguishable

from those coming under the first two categories. Such persons

interfere in things which do not concern them. They masquerade

as crusaders for justice. They pretend to act in the name of pro

bono publico, though they have no interest of the public or even of

their own to protect. They indulge in the pastime of meddling with

the judicial process either by force of habit or from improper

motives. Often, they are actuated by a desire to win notoriety or

cheap popularity; while the ulterior intent of some applicants in this

category, may be no more than spoking the wheels of

administration. The High Court should do well to reject the

applications of such busybodies at the threshold.

37. The distinction between the first and second categories of

applicants, though real, is not always well-demarcated. The first

category has, as it were, two concentric zones; a solid central zone

of certainty, and a grey outer circle of lessening certainty in a

sliding centrifugal scale, with an outermost nebulous fringe of

uncertainty. Applicants falling within the central zone are those

whose legal rights have been infringed. Such applicants

undoubtedly stand in the category of “persons aggrieved”. In the

grey outer circle the bounds which separate the first category from

the second, intermix, interfuse and overlap increasingly in a

centrifugal direction. All persons in this outer zone may not be

“persons aggrieved”.

31

38. To distinguish such applicants from “strangers”, among them,

some broad tests may be deduced from the conspectus made

above. These tests are not absolute and ultimate. Their efficacy

varies according to the circumstances of the case, including the

statutory context in which the matter falls to be considered. These

are: Whether the applicant is a person whose legal right has been

infringed? Has he suffered a legal wrong or injury, in the sense,

that his interest, recognised by law, has been prejudicially and

directly affected by the act or omission of the authority, complained

of? Is he a person who has suffered a legal grievance, a person

“against whom a decision has been pronounced which has

wrongfully deprived him of something or wrongfully refused him

something, or wrongfully affected his title to something?”

Has he a special and substantial grievance of his own beyond

some grievance or inconvenience suffered by him in common with

the rest of the public? Was he entitled to object and be heard by

the authority before it took the impugned action? If so, was he

prejudicially affected in the exercise of that right by the act of

usurpation of jurisdiction on the part of the authority? Is the

statute, in the context of which the scope of the words “person

aggrieved” is being considered, a social welfare measure

designed to lay down ethical or professional standards of conduct

for the community? Or is it a statute dealing with private rights of

particular individuals?”

43. In Ayaaubkhan Noorkhan Pathan (supra), the Hon‟ble

Apex Court held that only a person who has suffered or suffers

from a legal injury can challenge the act/action/order, etc in a

court of law. It was held that a person who suffers the grievance

must show how he has suffered legal injury.

32

44. Paras 9 to 17 Ayaaubkhan Noorkhan Pathan

(supra) read as under:

Person aggrieved:

“9. It is a settled legal proposition that a stranger cannot be

permitted to mediate or to prosecute or to defend, or to argue

or to file an appeal or a petition within the category of

aggrieved persons. Only a person who has suffered, or

suffers from legal injury can challenge the act/action/order,

etc. in a court of law. A legal right is an interest which the law

protects-an interest enjoyment of which the law protects. It

must be a legally enforceable claim right available for

enforcement, on the basis of which writ jurisdiction is

exercised. The cause of action must, therefore, be germane

to the statutory duty by a public body, using its writ jurisdiction

at the behest of a person, complaining of a wrong and the

court can also go into the question of his on such

performance. The existence of such right is a condition

precedent for invoking the writ jurisdiction of the Court. It is

open to a person to seek such extraordinary jurisdiction that

the relief prayed for must be one to promote a cause and he

must be a person who is or is to be, prejudicially affected by

the exercise of the said jurisdiction by the Court. The legal

right that can be enforced must ordinarily be the right of the

person complaining of the infraction of infraction of such right

and approaches the Court for relief as regards the State,

1999) 7 SCC 725, 746, paras 46 & 47; *M.S. Jayaraj v.

Commissioner of U.P., Calcutta Gas Co. (Proprietary) Ltd. v.

State of W.B., Rajendra v. State of A.P., 2008) 13 SCC 128,

33

143, paras 33 & 34 and Ravi Yashwant Assn. v. SCC

Sekhar).

10. A "legal right" means an entitlement arising out of legal

rules. Thus, it may be defined as an advantage, or a benefit

conferred upon a person by the rule of law. The existence of

some tangible interest is a sine qua non for any person, be it

a psychological or an pecuniary injury, to be an aggrieved

must, therefore, necessarily be one whose right or interest

has been adversely affected or jeopardised. (See: Kumaun

Mandal Vikas Nigam Ltd. v. Home Insurance Co. of New York

and State of Rajasthan v. Union of India.)

11. In Anand Sharadchandra Oka v. University of

Mumbai, (AIR 2008 SC 1289), a similar view was taken by

this Court, observing that, if a person claiming relief is not a

legally aggrieved person, he is not entitled to be a person

aggrieved regarding the selection or the election of other

persons.

12. In A. Subhash Babu v. State of A. P., (AIR 2011 SC

3031), this Court held:

"25. ... The expression 'person aggrieved' cannot be

confined to any elusive concept. It cannot be confined

within the bounds of a rigid, exact and comprehensive

definition. Its scope and meaning depends on diverse,

variable factors such as the content and intent of the

statute of which the infringement is alleged, the nature

of the breach or the wrong done, nature and extent of

the interest of the informant and the nature and the

extent of the prejudice suffered by the

informant/complainant."

34

13. This Court, even as regards the filing of a habeas corpus

petition, has explained that the petition has to be filed by the

person who is in illegal stranger. Such a petition cannot be

filed by one who is a complete stranger to the person who is

in alleged illegal custody. (Vide Charanjit v. Delhi University

v. Union of India, Sunil Batra v. Delhi Admn. v. Nirmal

Choudhary v. State of Bihar, Simranjit Singh Mann v. Union

of India, Karamjeet Singh v. Union of India, and Rishu v.

State of U.P.)

14. This Court has consistently cautioned the courts against

entertaining public interest litigation filed by “meddlesome

persons” or “busy-bodies who do not hesitate to abuse the

process of court. The right of effective access to justice,

which has emerged with the new social justice regime, must

be used to serve basic human rights, which purport to

guarantee legal rights and, therefore, a necessary connect

within the framework of the judicial system must be provided.

Whenever any public interest is involved, the court must

examine the case to ensure that there is, in fact, genuine

public interest involved. The court must restrain strict

vigilance to ensure that there is no abuse of the process of

court and that, “outlandish meddlesome bystanders are not

granted a visa”. Many are legal disputants, others new

prophets of non-redressed grievances, but the court should

make an earnest endeavour to take the broad facts of where

the subjective purpose of the litigant lies. The court must

(Vide P.S.R. Sadhanantham v. Arunachalam, Dalip Singh v.

State of U.P.,State of Uttaranchal v. Balwant Singh Chaufal

and Amar Singh v. Union of India.)

35

15. Even as regards the filing of a public interest litigation,

this Court has consistently held that such a course of action is

not permissible so far as service matters are concerned.

(Vide Duryodhan Sahu v. Jitendra Kumar Mishra, Dattaraj

Natthuji Thaware v. State of Maharashtra and Neetu v.

State of Punjab (2007) 10 SCC 614.)

16. In Ghulam Qadir v. Special Tribunal, this Court

considered a similar issue and observed as under: (SCC p.

54, para 38)

"38. There is no dispute regarding the legal

proposition that the rights under Article 226 of the

Constitution of India can be enforced only by an

aggrieved person except in the case where the writ

prayed for is for habeas corpus or quo warranto.

Another exception to the general rule is the filing of a

writ petition in public interest. The existence of the

legal right of the petitioner which is alleged to have

been violated is the foundation for invoking the

jurisdiction of the High Court under the aforesaid

article. The orthodox rule of interpretation regarding

the locus standi of a person is receding, inter alia,

because of the change which the development of

constitutional law, as our country and the

constitutional courts are, now adopting a liberal

approach in dealing with the cases or dislodging the

claim of a litigant merely on hypertechnical grounds.

In other words, if the person is found to be an offerer,

a stranger having no right whatsoever to any post or

property, he cannot be non-suited on the ground of

his not having the locus standi." (emphasis added).

36

45. In Thammanna (supra), the Hon‟ble Apex Court held that

the expression „person aggrieved‟ may vary according to the

context of the statute at the facts of the case, nevertheless

normally, a „person aggrieved‟ must be a man who has suffered a

legal grievance, a man against whom a decision has been

pronounced which has wrongfully deprived him of something or

wrongfully refused him something, or wrongfully affected his title

to something. Para 16 of Thammanna (supra) reads as under:

“16. Although the meaning of the expression „person

aggrieved‟ may vary according to the context of the

statute at the facts of the case, nevertheless normally,

“a „person aggrieved‟ must be a man who has suffered

a legal grievance, a man against whom a decision has

been pronounced which has wrongfully deprived him of

something or wrongfully refused him something, or

wrongfully affected his title to something.”

46. In Rana Sengupta (supra), the NGT, New Delhi,

considered the meaning of the „aggrieved person‟ and the „locus

standi‟ to prefer the appeal before the N.G.T under Section 16 of

the N.G.T Act was considered. It was held that the expression

“person aggrieved by” imply some or other reason which might

have demonstrated that such person is directly or indirectly

37

concerned with the adverse environmental impact which is likely

to be caused due to granting of EC by the competent authority.

47. In view of the above, the law on the said point can be

summarised to the effect that a person who claims to

intervene, must show how he has suffered legal injury.

Generally, a stranger having no right whatsoever to any post

or property cannot be permitted to intervene in the affairs of

others.

48. The 7

th

respondent in his appeal filed before the

Tribunal specifically stated in para 1 thereof that he was resident

of the concerned village. The 7

th

respondent being the resident of

the village concerned, if for any mining activity, the EC was

issued and violating norms such person will certainly be a person

aggrieved within the meaning of Section 16 of the N.G.T Act. The

7

th

respondent cannot be said to be a stranger. It can also not be

said that he has no legal right. Right to air, water, free of pollution

is a fundamental right of a person enshrined under Article 21 of

the Constitution of India. In case of any infringement thereof or

likely to be infringed, such person shall certainly have a right to

challenge the action and would have the locus standi being

„aggrieved person‟ within the meaning of Section 16 of the N.G.T

38

Act. In Thammanna (supra), it was observed that the meaning of

the expression „person aggrieved‟ may follow according to the

context of the statute at the facts of the case. In the context of

the environmental matter, the resident of the particular place

would have certainly the right to file the appeal under Section 16

of the N.G.T Act. In Pranav Kumar vs. State of U.P and 4

others

20

, it was held as under:

“It cannot be said that the petitioner who is resident of

same village where mining operations are going on, effecting

the pollution and environment, has no right to raise any voice.

As noted above, the petitioner has made a complaint and on

his complaint, the mining operation of the respondent No.5

was stopped…………”

In the said case, it was further held that “…………..as

noted above, the present is a case where operation by the

respondent No.5 in the village where the petitioner is residing

has a direct impact on the environment and pollution. The

petitioner who is affected by environmental degradation and

increases in pollution cannot be said to be a person who has

no interest in the subject matter…………………….”

So, it cannot be said that the impugned order passed by

the N.G.T on the appeal filed by the 7

th

respondent was without

jurisdiction.

20

2013 SCC OnLine All 6052

39

Point-C violation of principles of natural justice and Point-D

order of the N.G.T:

49. The submission of the learned counsel for the petitioner is

that there is violation of the principles of natural justice. The

submission proceeds on the ground that the Tribunal had passed

the order taking into consideration various aspects, which were

not made known to the petitioner. The petitioner had no

opportunity with respect to those aspects which violates the

principles of natural justice of opportunity of hearing. Connected

to the above submissions are the other submissions to challenge

the impugned order. We shall consider those submissions

together under those heads.

50. We shall consider the order on merits for which we refer to the

points framed; the reasons/findings, and the justification recorded by

the NGT in its order.

51. The NGT framed the following points for consideration:

“i) Whether the Environmental Clearance (EC)

granted in favour of 7

th

respondent is liable to be set aside for

any of the reasons stated in the Appeal memorandum and the

submission made by the counsel for the appellant?

(ii) Whether there is any procedural irregularities

committed by MoEF&CC in considering the application as a

violation case as per the procedure provided in the notification

40

issued in this regard on 14.03.2017, if so, what is the nature of

further directions to be issued by this Tribunal in this regard?

(iii) Whether the MoEF&CC was justified in relegating

the power of calculating the compensation amount as directed

by the Hon'ble Apex Court in Common Cause Case to the

Mining Authority without exercising that power by themselves?

(iv) Relief and costs.”

52. On the aforesaid points 1 to 4, the NGT recorded findings

to state briefly, to the following effect:

01. So, the contention that still the appellant‟s land is

included in the lease area appears to be not correct (vide para

100).

02. So, the averments in the memorandum of appeal that

there was suppression of material facts, appears to be not correct

(para 101)

03. So, it cannot be said that on a ground of alleged

suppression of material fact, proper appraisal could not be done

by the EAC and the same is not correct (Para 102).

04. So, on the ground that there was no public hearing

conducted for the violation category and thereby EC granted, is

vitiated, cannot be accepted, as there was earlier public hearing

on the petitioner‟s previous application and also the material

collected on the basis of the compliance filed after getting reports,

will be sufficient and there is no necessity to conduct any further

public hearing as it cannot be said to be a new application but

only a conversion of the original application to violation category

and it can only be said as continuation of earlier application and

as such non conduct of further public hearing is not fatal and on

41

that ground the EC need not be set aside or to be sent for further

public hearing to get further opinion on these subjects (para 103).

53. With respect to the contentions of the petitioner herein (7

th

respondent before the NGT), the N.G.T observed and held as

under to be stated briefly, as in the judgment of the NGT:

01. So, the MOEI was perfectly justified in treating this as

a violation category and having obtained the EC under the

violation category by filing an application and want to enjoy the

benefit of EC, the 7

th

respondent (the present petitioner) is

stopped from contending that he will not fall under the violation

category and such contention raised by the 7

th

respondent is

unsustainable and the same is rejected. (Para 104).

02. The submission of the 7

th

respondent (petitioner

herein) that the common cause case is not applicable and it

applies to the State of Orissa alone and till the EAC was

appointed by the Government in terms of the common cause

case judgment and the recommendations of such committee-7

th

respondent was not liable to comply with the same, was not

acceptable, as also the contention that the dictum laid down in

the common cause case was modified in Alembic

Pharmaceuticals case by the Hon‟ble Apex Court. (Para

No.105). The NGT observed that the 7

th

respondent (petitioner

herein) could not avoid the liability fixed under the common cause

case.

03. The observations made by the NGT in previous

O.A.No.96 of 2015, that the mining and mineral was included in

42

the EIA notification with effect from 01.12.2009 and from that date

onwards the liability to obtain the EC was mandatory, and only

from that date onwards it could be said to have been violated the

EC condition, was also not accepted by the NGT in the present

Appeal No.19 of 2020 (S2).

04. The contention of the 7

th

respondent (petitioner

herein) that it was not liable to pay any compensation and if at all

liable only from 01.12.2009, was rejected by the NGT (Para

No.106).

54. The NGT also recorded in detail, in its judgment the further

relevant aspects/proceedings as under:-

01. That there was lethargic attitude on the part of the

Mining Department in directing the natural resources against over

exploitation and even after the order/recommendation dated

23.01.2017, against the order imposing penalty of Rs.55,28,293/-

by the Government and the matter remitted to the authority

concerned for fresh consideration, no action was taken for

considerable period to adjudicate the aspect of penalty payable

by the present petitioner. The petitioner deposited the amounts

only under protest and not by accepting the liability.

43

02. That the excess mining if any, could not be assessed

by the Mining Department within a reasonable time and unless

that amount was also paid, no Mining Operation could be

permitted. The Expert Appraisal Committee should have

assessed this amount also, instead of relegating the work to the

State Department without providing any supervisory mechanism

as to whether that amount has been paid or not, as a condition in

the EC, will go to the root of the EC itself which also showed the

non-application of mind of that aspect by the EAC as also by the

MoEF&CC.

03. That no compensation was assessed for the loss

occurred due to cutting of 1607 cashew trees. Instead of re-

planting cashew trees, they accepted the mining plan of planting

casuarina trees in that place without considering as to whether it

will be substitute for ecological loss to environmental and

whether it will have any impact on the ground water level and

affect the spring channel that is being available in that area, as

also the liability to pay compensation for the trees apart from the

undertaking to replant the same as an afforestation process

applying the decision of the Hon‟ble Apex Court in T.N.

Godhavarman Thirumalpad (2008) 7 SCC 126 (Para 115).

44

04. That the EAC did not consider the impact of Silica

Mines in that area in a right perspective though the mining plant

proceeds by the Project Proponent showed that, it was a unique

eco sensitive area and certain flora and fauna had to be

protected, under the head, Geology, Hydrology, Demography,

Ecology of Coastal Dunes, Formation of Dunes and Eco Systems.

05. That the EAC did not ascertain as to whether any

District Survey had been conducted by the authorities as per the

guidelines provided under the Sustainable Sand Mining

Management Guidelines, 2020, and the Enforcement and

Monitoring Guidelines for Sand Mining, 2020.

06. That the impact of the large scale mining being

undertaken in that area for the last 40 years had not been

properly considered and no proper study had been conducted in

that regard.

07. That the EAC as well as the Mining Department had

only relied on the study conducted by the Project Proponent

themselves. The aspect of, there being progressive increase of

permissible quantity to be undertaken by the lessee and

ultimately by virtue of the mining lease and EC, the project

proponent was permitted to mine 3,40,000 Silica Sand from the

45

Unique Eco Sensitive Area, around ten times of original quantity.

This aspect was also not properly considered by the EAC or by

MOEF and CC.

08. That the aspect that mechanized mining was not

permissible, was not considered by the EAC which also did not

consider as to whether so much quantity of sand could be mined,

mainly using small escalation policy during the mining period.

55. The N.G.T concluded that the Expert Appraisal Committee

as well as the MOEF and CC had not even considered their own

Sustainable Sand Mining Management Guidelines, 2016; the

directions issued by the NGT in similar nature of sand mining

leases, regarding the responsibility of the authorities to conduct

district survey of the sand available, the rate of depletion and

replenishment of sand in that area so as to ascertain the quantity

available for mining and how much quantity could be permitted for

mining in such areas, before permitting a particular quantity of

sand to be mined from the mining area. The N.G.T observed that

the expert body, is an expert body intended to protect the

environment, which ought to have but did not properly consider

the various aspects and recommended accepting the

Environmental Management Plan submitted by the Project

46

Proponent without properly examining the reports of various

District Collectors. The N.G.T concluded that under the

circumstances a detailed study had to be conducted by the

Project Proponent, which had to appraise the EAC as well as the

MOEF and CC, before ascertaining for allowing such type of

mining of huge quantity.

56. The NGT therefore allowed the appeal in part and kept the

EC dated 16.04.2020 in abeyance as follows:

“130. In the result, the appeal is allowed in part and disposed

of as follows:-

(i) The Environmental Clearance (EC) granted by the 1

respondent vide Order No. F.No.23-238/2018-IA.II(V)

dated 16.04.2020 in favour of the 7th respondent is

directed to be kept in abeyance for a period of 6 (Six)

months or such period till the Ministry of Environment,

Forests & Climate Change (MoEF&CC) or take further

decision after completion of the enquiry as directed by

this Tribunal and compliance with the direction as

directed by the Ministry of Environment, Forests &

Climate Change (MoEF&CC) and the additional

conditions to be imposed whichever is later

(ii) The Ministry of Environment, Forests & Climate Change

(MoEF&CC) is directed to revisit the question of

assessing the compensation for illegal mining without

obtaining Environmental Clearance (EC) as directed by

the Hon'ble Apex Court in Common Cause case on the

basis of the admitted quantity of minerals extracted and

47

transported during that period and impose a condition

that without paying this amount, the Environmental

Clearance (EC) will not come into effect and that too only

on satisfaction of the Regional Office of the Ministry of

Environment, Forests & Climate Change (MoEF&CC)

that the amount has been paid as directed. With further

direction to the Mining Department, State of Andhra

Pradesh to ascertain as to whether any excess mining

has been done in violation of the mining lease and also

under the Metalliferous Mines Regulation Rules, 1961

and if so, recover the amount also from the project

proponent before permitting them to carry out the mining

operation on the basis of the Environmental Clearance

(EC) to be granted after imposing additional conditions.

(iii) The Ministry of Environment, Forests & Climate

Change (MoEF&CC) is also directed to revisit on the

question of imposing compensation for cutting of 1607

cashew trees, apart from fixing the amount for

Environment Management plan and implementation of

the same and also ascertain as to whether planting of

Casuarina Trees in the place of cashew trees will be a

substitute for such ecological loss, after ascertaining the

impact on the ground water level and its impact on the

spring channel available in that area and thereafter,

reassess the amount of Bank Guarantee to be furnished

for implementation of the Environment Management

Plan. But that should not include the NPV (Net Present

Value) of the cashew trees that have been cut and also

ascertain as to whether this has been cut from Sy.No.696

of that village which was identified as the Adavi

48

Poramboke and later included in the revenue records and

omitted from the mining lease applying the principles laid

down by the Apex Court in T.N Godhavarman

Thirumnalpad case taking this as a deemed forest, so as

to apply the Forest (Conservation) Act, 1980.

(iv) The MoEF&CC is directed to issue further direction to

get the details regarding the district survey conducted by

the authorities in that area regarding the availability of

sand as has been directed by the MoEF&CC in the

Sustainable Sand Mining Management Guidelines, 2016

and also by the Principal Bench of National Green

Tribunal, New Delhi in several cases of this nature.

(v) After obtaining the same, they are directed to conduct a

further study as to how much sand will be available for

mining considering the nature of replenishment and

without affecting the unique Dunal wetland ecosystem

available in that area.

(vi) The MoEF&CC is also directed to consider the question

as to whether in an area like this, mechanized mining can

be permissible, as over exploitation of natural resources

of such nature available in that area will have adverse

impact on the Dunal wetland ecosystem.

(vii)After considering these aspects, the MoEF&CC is

directed to form an opinion as to whether the sand mining

could be possible in that area to such a larger extent and

if not, to what extent it can be permissible and the

methodology to be adopted for conducting mining and if

mechanized process is permissible, what are all the

additional conditions to be imposed for that purpose,

taking into account the number of vehicles that are likely

49

to be used for the purpose of transporting the same and

consequential noise as well as air pollution that is likely to

be caused on account of the same and the mitigating

circumstances to be imposed, if it is permissible applying

the "Precautionary Principle and then fix the quantity of

mining that could be permissible which is safe for the

purpose of protecting environment and the unique Dunal

wetland ecosystem as has been admitted by the project

proponent themselves in The Environment Management

Plan. The Corporate Environment Responsibility project

should also be reexamined to incorporate activities for

sustainability of the Dunal wetland ecosystem.

(viii) After considering all these aspects, the Expert

Appraisal Committee (EAC) as well as the Ministry of

Environment, Forests & Climate Change (MoEF&CC) are

directed to impose additional stringent conditions that till

these amounts are paid, the Environmental Clearance

(EC) will not come into effect and the project proponent

has to satisfy the Regional Office, Ministry of

Environment, Forests & Climate Change (MoEF&CC) at

Vijayawada which is having jurisdiction over the State of

Andhra Pradesh before permitting the project proponent

to carry out the mining operation on the basis of the

Environmental Clearance (EC) granted

(ix) The Director of Mines and Geology, State of Andhra

Pradesh is also directed to expedite the process of

assessing the excess mining done as early as possible at

any rate within a period of 6 (Six) months and to assess

the compensation payable for such illegal mining, apart

from payment of royalty and penalty payable under the

50

mining laws applicable to that State and take steps to

recover the amount from the 7 respondent after giving

them an opportunity of hearing as per the Rules and only

on payment of that amount as well, they will have to be

permitted to continue with the mining operation if eligible

as per Rules in vogue

(x) The Andhra Pradesh Pollution Control Board is also

directed to assess compensation for violation of

operating the unit without obtaining Consent to Operate

under the Water (Prevention and Control of Pollution)

Act, 1974 and Air (Prevention and Control of Pollution)

Act, 1981 as it is seen from the counter statement field by

the 7th respondent that they had obtained Consent to

Establish and Consent to Operate only during 2016 and

prior to that, they were operating the same without

obtaining Consent to Establish and Consent to Operate,

as has been held by the Principal Bench in O.A. No.593

of 2017 (Paryavaran Suraksha Samiti & Anr. Vs. Union of

India & Ors.) and followed by this Bench also in several

cases of this nature and recover the amount from the 7th

respondent in accordance with law and till then, they

should not be permitted to operate on the basis of the

Environmental Clearance (EC) granted or the Consent to

Establish and Consent to Operate granted earlier

(xi) Considering the circumstances, the parties are

directed to bear their respective cost in the appeal.

(xii) The Registry is directed to communicate this order to

the Ministry of Environment, Forests & Climate Change

(MoEF&CC), New Delhi, Regional Office, Ministry of

Environment, Forests & Climate Change (MoEF&CC),

51

Vijayawada, the Chief Secretary for State of Andhra

Pradesh, Director of Mines and Geology State of Andhra

Pradesh and Andhra Pradesh Pollution Control Board

immediately by e-mail for their information and

compliance of the direction.

(xiii) The Ministry of Environment, Forests & Climate

Change (MoEF&CC) is directed to take back the file

relating to issuance of Environmental Clearance (EC)

produced before this Tribunal.

131. With the above observations and directions, this

appeal is allowed in part and disposed of accordingly.”

57. In our view, the findings arrived at by the Tribunal, are

raised on consideration of the material on record before it and

therefore the directions issued by the Tribunal keeping the EC in

abeyance till the consideration of the matter by the competent

authorities is not unsustainable nor it suffers from any perversity.

58. The issue before the Tribunal essentially related to

environment ecology. The Tribunal is also having suo moto

power under Sections 14 and 15 of the N.G.T Act to consider all

the relevant aspects, which caused or are likely to cause threat to

the environment.

52

Suo Moto Power of N.G.T:

59. At this stage, Sections 14 of the NGT Act deserves

reference which reads as under:

“Section 14. Tribunal to settle disputes.

(1) The Tribunal shall have the jurisdiction over all civil

cases where a substantial question relating to environment

(including enforcement of any legal right relating to

environment), is involved and such question arises out of the

implementation of the enactments specified in Schedule I.

(2) The Tribunal shall hear the disputes arising from the

questions referred to in sub-section (1) and settle such disputes

and pass order thereon.

(3) No application for adjudication of dispute under this

section shall be entertained by the Tribunal unless it is made

within a period of six months from the date on which the cause

of action for such dispute first arose:

Provided that the Tribunal may, if it is satisfied that the

applicant was prevented by sufficient cause from filing the

application within the said period, allow it to be filed within a

further period not exceeding sixty days.”

60. In Uday Education and Welfare Trust (supra), the Hon‟ble

Apex Court referring to Municipal Corporation of Greater Mumbai

v. Ankita Sinha

21

held that the NGT is empowered to take suo

motu cognizance and that, taking into consideration the nature of

functions of the NGT, it cannot be equated with other Tribunals. In

environmental matters, it will also have a power to take suo motu

21

2021 SCC OnLine SC 897

53

cognizance. Paras 96 and 98 of Uday Education and Welfare

Trust (supra) read as under:

“96. Another aspect that needs consideration is that a serious issue

was raised before the learned NGT by the appellants herein with

regard to the credentials and bonafides of the original applicants.

98. Shri Dhruv Mehta, learned Senior Counsel has rightly relied on the

judgment of this Court in the case of Ankita Sinha and Others (supra)

to submit that the learned NGT is empowered to take suo motu

cognizance. This Court has held that, taking into consideration the

nature of functions of the learned NGT, it cannot be equated with other

Tribunals and in environmental matters, it will also have a power to

take suo motu cognizance. However, when the credentials and

bonafides of a litigant approaching the learned NGT are seriously

raised, the same cannot be ignored.

61. In Mantri Techzone Private Limited (supra), it was held

that the N.G.T Act being a beneficial legislation, the power

bestowed upon the Tribunal would not be read narrowly. An

interpretation which furthers the interests of environment must be

given a broader reading on the scope of the jurisdiction under

Sections 14 and 15 of the Act with the Tribunal. Paras 41 to 46

read as under:

“41. The jurisdiction of the Tribunal is provided under Sections 14, 15 and 16 of the

Act. Section 14 provides the jurisdiction over all civil cases where a substantial

question relating to environment (including enforcement of any legal right relating to

environment) is involved. However, such question should arise out of implementation

of the enactments specified in Schedule I.

42. The Tribunal has also jurisdiction under Section 15(1)(a) of the Act to provide

relief and compensation to the victims of pollution and other environmental damage

54

arising under the enactments specified in Schedule I. Further, under Section 15(1)(b)

and 15(1)(c) the Tribunal can provide for restitution of property damaged and for

restitution of the environment for such area or areas as the Tribunal may think fit. It is

noteworthy that Section 15(1)(b) & (c) have not been made relatable to Schedule I

enactments of the Act. Rightly so, this grants a glimpse into the wide range of powers

that the Tribunal has been cloaked with respect to restoration of the environment.

43. Section 15(1)(c) of the Act is an entire island of power and jurisdiction read with

Section 20 of the Act. The principles of sustainable development, precautionary

principle and polluter pays, propounded by this Court by way of multiple judicial

pronouncements, have now been embedded as a bedrock of environmental

jurisprudence under the NGT Act. Therefore, wherever the environment and ecology

are being compromised and jeopardized, the Tribunal can apply Section 20 for taking

restorative measures in the interest of the environment.

44. The NGT Act being a beneficial legislation, the power bestowed upon the

Tribunal would not be read narrowly. An interpretation which furthers the interests of

environment must be given a broader reading. (See Kishsore Lal v. Chairman,

Employees’ State Insurance Corpn. (2007) 4 SCC 579, para 17). The existence of

the Tribunal without its broad restorative powers under Section 15(1)(c) read with

Section 20 of the Act, would render it ineffective and toothless, and shall betray the

legislative intent in setting up a specialized Tribunal specifically to address

environmental concerns. The Tribunal, specially constituted with Judicial Members as

well as with Experts in the field of environment, has a legal obligation to provide for

preventive and restorative measures in the interest of the environment.

45. Section 15 of the Act provides power & jurisdiction, independent of Section 14

thereof. Further, Section 14(3) juxtaposed with Section 15(3) of the Act, are separate

provisions for filing distinct applications before the Tribunal with distinct periods of

limitation, thereby amply demonstrating that jurisdiction of the Tribunal flows from

these Sections (i.e. Sections 14 and 15 of the Act) independently. The limitation

provided in Section 14 is a period of 6 months from the date on which the cause of

action first arose and whereas in Section 15 it is 5 years. Therefore, the legislative

intent is clear to keep Section 14 and 15 as self contained jurisdictions.

46. Further, Section 18 of the Act recognizes the right to file applications each under

Sections 14 as well as 15. Therefore, it cannot be argued that Section 14 provides

jurisdiction to the Tribunal while Section 15 merely supplements the same with

powers. As stated supra, the typical nature of the Tribunal, its breadth of powers as

provided under the statutory provisions of the Act as well as the Scheduled

enactments, cumulatively, leaves no manner of doubt that the only tenable

55

interpretation to these provisions would be to read the provisions broadly in favour of

cloaking the Tribunal with effective authority. An interpretation that is in favour of

conferring jurisdiction should be preferred rather than one taking away jurisdiction.”

62. In Ankita Sinha (supra), the Hon‟ble Apex Court on the

exercise of suo moto power by the National Green Tribunal held

that the role of the NGT was not simply adjudicatory in the nature

of a lis but to perform equally vital roles which are preventative,

ameliorative or remedial in nature. The functional capacity of the

NGT was intended to leverage wide powers to do full justice in its

environmental mandate. The Hon‟ble Apex Court referred to its

judgment in Rajeev Suri vs. DDA

22

. This consideration on

exercise of the suo moto power by the NGT, under paras 51 to 58

of the judgment is re-produced as under:

“51. In addition to the grounds urged in W.P. (C) 510/2020,

the petitioners herein submit that the CVC was functioning under

the chairmanship of ADG (Works) who is not an architect or town

planner and thereby lacks the requisite skills/knowledge required

for considering the said proposal. The argument is supplemented in

the written submissions where it is stated that the nature of duties

entrusted to CVC requires the head of the Committee to be a

professional architect or town planner so as to consider the

proposal in a nuanced manner. To buttress this submission, the

petitioners contend that the meeting was called despite absence of

external experts and it was a deliberate step to avoid professional

scrutiny of the professional, thereby rendering the said no objection

as arbitrary and illegal.

52. The petitioners have also pressed the argument of non-

application of mind, akin to that taken in W.P. (C) 510/2020, on the

ground that no assessment was made by the respondents to consider

22

2021 SCCOnline SC 7

56

the viability and need of a new Parliament building and the entire

process was carried in undue haste. To buttress this argument,

reliance has been placed upon Inderpreet Singh Kahlon & Ors. v.

State of Punjab & Ors.

23

and Bahadursinh Lakhubhai Gohil v.

Jagdishbhai M. Kamalia & Ors.

24

to urge that an action taken in

undue haste could be declared as bad in law.

53. It is further submitted that CVC disregarded the legal

framework for dealing with heritage structures. The petitioners

seek support from clause 7.26 read with Annexure-II of Building

Byelaws to contend that minimum changes are permissible on

Grade-I heritage buildings/precincts and the Committee failed to

take that into consideration. The said no objection is also assailed

on the alleged failure of the Committee to take into consideration

various factors concerning environmental impacts, traffic

assessment etc.

54. During the hearing, Mr. Hegde, appearing for the petitioners,

submitted that CVC, though originally conceived as an advisory

body, has assumed a statutory character owing to its long

functioning and is expected to discharge pivotal role in

development of such projects. In “Supplementary Note on the Role

of Central Vista Committee” submitted by the petitioners, reference

is made to the notice inviting bids and clause 6.4.3 of ZDP for

Zone-D to support the view that CVC was envisaged as a statutory

committee.

55. Alternatively, it is urged that the statutory mandate of CVC is

in line with the doctrine of legitimate expectations in administrative

matters. The petitioners have relied upon National Buildings

Construction Corporation v. S. Raghunathan & Ors.

25

to contend

that this doctrine is premised on the ground of reasonableness and

natural justice, and has now become a source of substantive as well

as procedural rights.

56. In addition to cases noted above, the petitioners have placed

reliance upon R.S. Garg v. State of U.P. & Ors.

26

, Council of

Architecture v. Mukesh Goyal & Ors.

27

and Maharashtra State

23

(2006) 11 SCC 356

24

(2004) 2 SCC 65

25

(1998) 7 SCC 66

26

(2006) 6 SCC 430

27

(2020) 16 SCC 446

57

Board of Secondary and Higher Secondary Education v. K.S.

Gandhi & Ors.

28

57. The argument regarding the statutory character of CVC has

been countered by learned Solicitor General. He would urge that it

is merely an advisory body with a limited mandate to advise the

Government on a proposal submitted for its consideration. It has no

authority to grant approvals or take decisions. Further, merely

because a body has been referred to in the ZDP (Zone-D) or has

been working for a prolonged period, it will not assume a statutory

character on its own until it is so provided by a statute.

58. As regards the argument of non-application of mind, it is

submitted that CVC is not supposed to supply reasons for its

approval in a manner akin to judicial/quasi-judicial bodies and the

fact that CVC, in its decision, had asked the project

proponent/CPWD to ensure that the project is in sync with the

character of Central Vista reveals due application of mind. It is

urged that application of mind must be revealed from a substantial

compliance perspective. The respondents have urged that the

present case is a sui generis one and must be treated accordingly

keeping in mind larger national interest. For brevity, other

submissions of the respondents to this prayer are not being repeated

here.”

63. In Ankita Sinha (supra) the Hon‟ble Apex Court also

considered the role of the N.G.T and held that the N.G.T is a

Tribunal with sui generis characteristic, with the special and all-

encompassing jurisdiction to protect the environment. Besides its

adjudicatory role as an appellate authority, it is also conferred

with the responsibility to discharge role of supervisory body and

to decide substantial questions relating to the environment. The

necessity of having a specialized body, with the expertise to

handle multi- dimensional environmental issues allows for an all-

28

(1991) 2 SCC 716

58

encompassing framework for environmental justice. The technical

expertise that may be required to address evolving environmental

concerns would definitely require a flexible institutional

mechanism for its effective exercise. Paras 63 to 67 of Ankita

Sinha (supra) read as under:

“63. The NGT being one of its own kind of forum,

commends us to consider the concept of a sui generis

role, for the institution. The structure of Sui generis

institutions was explained in Paramjit Kaur Vs. State of

Punjab20, wherein Justice S. Saghir Ahmad spoke thus

for a Division Bench, “14. The concept of sui generis is

applied quite often with reference to resolution of

disputes in the context of international law. When the

conventions formulated by compacting nations do not

cover any area territorially or any subject topically, then

the body to which such power to arbiter is entrusted acts

sui generis, that is, on its own and not under any law.”

64. In D G NHAI vs. Aam Aadmi Lokmanch (2020

SCCOnline SC 572), Justice S. Ravindra Bhat

commenting on the sui generis role of the NGT, so

appropriately stated as follows:-

“38. A conjoint reading of Sections 14, 15 and the

Schedules would lead one to infer that the NGT has

circumscribed jurisdiction to deal with, adjudicate, and

wherever needed, direct measures such as payment of

compensation, or make restitutionary directions in cases

where the violation (i.e. harm caused due to pollution or

exposure to hazards, etc.) are the result of infraction of

any enactment listed in the first schedule. Yet, that,

interpretation, in the opinion of this court, is not

warranted.

**** **** **** ****

**** **** **** ****

76. The power and jurisdiction of the NGT under

Sections 15(1)(b) and (c) are not restitutionary, in the

sense of restoring the environment to the position it was

before the practise impugned, or before the incident

occurred. The NGT's jurisdiction in one sense is a

59

remedial one, based on a reflexive exercise of its

powers. In another sense, based on the nature of the

abusive practice, its powers can also be preventive.

77. As a quasi-judicial body exercising both appellate

jurisdiction over regulatory bodies' orders and directions

(under Section 16) and its original jurisdiction under

Sections 14, 15 and 17 of the NGT Act, the tribunal,

based on the cases and applications made before it, is

an expert regulatory body. Its personnel include

technically qualified and experienced members. The

powers it exercises and directions it can potentially issue,

impact not merely those before it, but also state agencies

and state departments whose views are heard, after

which general directions to prevent the future

occurrence of incidents that impact the environment, are

issued.”

65. In that case, this Court repelled the argument for a

restricted jurisdiction for the NGT, and fittingly observed

in paragraph 76 that the powers conferred on the NGT

are both reflexive and preventive and the role of the NGT

was recognized in paragraph 77 as “an expert regulatory

body”, which can issue general directions also albeit

within the statutory framework.

66. The above discussion would advise us to say that

the NGT was conceived as a specialized forum not only

as a like substitute for a civil court but more importantly

to take over all the environment related cases from the

High Courts and the Supreme Court. Many of those

cases transferred to the NGT, emanated in the superior

courts and it would be appropriate thus to assume that

similar power to initiate suo motu proceedings should

also be available with the NGT.

67. The NGT is a Tribunal with sui generis

characteristic, with the special and all-encompassing

jurisdiction to protect the environment. Besides its

adjudicatory role as an appellate authority, it is also

conferred with the responsibility to discharge role of

supervisory body and to decide substantial questions

relating to the environment. The necessity of having a

specialized body, with the expertise to handle multi-

dimensional environmental issues allows for an all-

encompassing framework for environmental justice. The

technical expertise that may be required to address

evolving environmental concerns would definitely require

60

a flexible institutional mechanism for its effective

exercise.”

64. It is further apt to refer the conclusions in Ankita Sinha

(supra), in paras 97 to 102 as under:

“97. It would be procedural hairsplitting to argue (as it has been)

that the NGT could act upon a letter being written to it, but learning

about an environmental exigency through any other means cannot

trigger the NGT into action. To endorse such an approach would

surely be rendering the forum procedurally shackled or

incapacitated.

98. When the Registry of the NGT does indeed receive a

communication or letter, including matters published in media, it

may cause to initiate suo motu action by inviting attention of NGT to

such matters in the form of office report. Such circumstances would

however require a notice to be given to the sender of the

communication or author of the news item, as the case may be, to

assist the NGT in the course of hearing and to substantiate the

factual matters. It must also be said that the exercise of suo motu

jurisdiction does not mean eschewing with the principles of natural

justice and fair play. In other words, the party likely to be affected

should be afforded due opportunity to present their side, before

suffering adverse orders.

99. One could admit to the argument of danger of suo motu

jurisdiction, if the NGT was acting outside its domain. But when it is

legitimately working within the contours of its statutory mandate and

with procedurals safeguards clarified above in play, the nature of the

trigger itself viz. a letter or a „suo motu‟ initiation, cannot be the

basis to curtail the role and responsibility of the specialized forum.

100. Institutions which are often addressing urgent concerns

gain little from procedural nitpicking, which are unwarranted in the

face of both the statutory spirit and the evolving nature of

61

environmental degradation. Not merely should a procedure exist but

it must be meaningfully effective to address such concerns. The role

of such an institution cannot be mechanical or ornamental. We must

therefore adopt an interpretation which sustains the spirit of public

good and not render the environmental watchdog of our country

toothless and ineffective.

101. Let us now hark back to the dialogues of the two

protagonists, in Waiting for Godot, the play written by Samuel

Beckett with which, we started this judgment. At the end of the

deliberations, we find ourselves saying that the National Green

Tribunal must act, if the exigencies so demand, without indefinitely

waiting for the metaphorical Godot to knock on its portal. The

preceding discussion advises us to answer the pointed question in

the affirmative. It is accordingly declared that the NGT is vested with

suo motu power in discharge of its functions under the NGT Act.

102. Having answered the common legal issue involved in

all these cases regarding the suo motu jurisdiction of NGT, we direct

delinking of these cases for now being heard separately on merits.

Indeed, if the cases(s) emanate from same/common order of NGT,

such case(s) be heard together. Registry may do the needful and

post the matters on 25.10.2021 for direction and fixing date of

hearing, before the Bench presided over by one of us (Justice A.M.

Khanwilkar). For the purpose of further hearing, the respective

cases shall not be treated as part-heard before this Bench.”

65. From the aforesaid judgments, the law is well settled that

the N.G.T Act is a beneficial legislation. The power vested upon

the N.G.T would not be read narrowly and any interpretation

which furthers the interest of the environmental concerns must

be preferred. The N.G.T has the legal obligation to provide for

preventing and restorative measures. The role of the N.G.T is not

62

simply adjudicatory but is also preventive and remedial. It has

the suo moto power as well to take cognizance of various aspects

and factors consequently in discharge of its functions under the

N.G.T Act, it cannot be said that the N.G.T ought to have

confined only to the objections raised in the appeal. We are of the

view that the N.G.T did not commit any error of law or of

jurisdiction, in keeping in view, the broader aspects, relevant to

the protection and preservation of the environment, to ensure that

there is no environmental degradation and the grant or the

procedure for grant of E.C must be in consonance with the

prescribed procedure and following the laws.

66. We refer to the recent pronouncement of Hon‟ble the Apex

Court in Union Territory of J&K (Previously State of Jammu &

Kashmir) and Another vs. Raja Muzaffar Bhat and others

29

.

67. The Hon‟ble Apex Court held that the absence of a

replenishment study renders a District Survey Report

fundamentally defective. The Hon‟ble Apex Court considered the

Guidelines, 2016 and the Enforcement Monitoring Guidelines for

Sand Mining-2020 and held that without a proper study of the

existing position of the river bed and its sustainability for further

29

2025 SCC OnLine SC 1789

63

sand mining grant of environmental clearances would be

detrimental for the ecology.

68. In the present case, the N.G.T has mentioned about the

lack of a proper study of ecology and the impact of the large scale

mining in that area for last 40 years, as one of the grounds for its

order. Paras 29 to 33 of Raja Muzaffar Bhat (supra) read as

under:

“29. From the foregoing analysis, it is apparent that in light of

Guidelines, 2016 and the Guidelines, 2020, the absence of a

replenishment study renders a DSR fundamentally defective.

These guidelines categorically require that any assessment

of mineable mineral quantity must be premised on scientific

estimation of replenishment rates, failing which the DSR

lacks the foundational data necessary to determine

sustainable extraction limits.

30. Over the past two decades, environmental statutory and

regulatory law in India has undergone significant evolution,

particularly in response to the challenges posed by

unregulated and unsustainable sand mining. Recognizing

the adverse ecological impacts of such activities, successive

legal and policy frameworks have progressively tightened the

requirements for environmental compliance. In order to

appreciate the present controversy, it was necessary to

retrace the legal trajectory. Recently, this Court has

discussed, in detail, the legal regime surrounding the

preparation, nature, scope and importance of DSR in Gaurav

Kumar (supra). However, the focal point for present

64

discussion is the value that must be appended to

replenishment study before EC is granted to mining

operations.

31. Demand for construction-grade sand is growing at a

tremendous rate and it is said that the world is expected to

run out of this resource by 2050. Construction-grade sand,

can be found in aquatic environments, such as rivers and is

a provisioning ecosystem service. Even under controlled

circumstances, the practice of extracting sand from the

riverbed and banks impacts the environment. In the physical

environment, the primary effects are riverbed widening and

lowering. In the biological environment, the overarching

effect is a reduced biodiversity and stretches from the

aquatic and shoreline flora and fauna to the whole floodplain

area. Due to easy access, river sand and gravel have been

used extensively in construction projects. Depending on the

mining operation method as well as morphologic and

hydraulic characteristics of the river, sand mining may cause

bed and bank erosion or other negative consequences for

the river eco-system. It is, therefore, necessary to conduct

appropriate studies, including that of replenishment to

explore sustainable and cost-effective methods for river

mining.

32. Without a proper study of the existing position of the

riverbed and its sustainability for further sand mining, grant

of environmental clearances would be detrimental for the

ecology. It has therefore been held that a detailed study

leading to a preparation of the replenishment report is an

integral part of the DSR. If the DSR becomes the foundation

for consideration of an application for environmental

clearance, then it is compelling to ensure replenishment

65

studies are undertaken in advance and the report forms an

integral part of the DSR.

33. In view of the existing legal regime that mandates

preparation of replenishment report in a scientific manner

and such a report forming an integral part of the District

Survey Report, we hold that a District Survey Report without

a proper replenishment study is equally untenable.”

69. We do not find any jurisdictional error or any improper

exercise of the jurisdiction by the N.G.T, so as to call for our

interference in the exercise of the writ jurisdiction.

Sustainable Sand Mining Management Guidelines, 2016:

70. The next submission of the learned counsel for the

petitioner that Sustainable Sand Mining Management Guidelines,

2016 are not applicable, deserves rejection. The submission was

that those guidelines relate to the sand mining from the river and

since the E.C granted to the petitioner is for sand mining not from

the river those Guidelines, had no application.

71. Learned counsel for the petitioner referred to the objectives

of the Guidelines to emphasise that it relates to the sand mining

from the river. He also referred to the effect of sand river mining

for the same purpose.

66

72. We are not convinced. A perusal of the Guidelines, 2016

clearly show that they apply to the sand mining from the river and

also from other sand sources. The Guidelines have been framed

with the objective to ensure Sustainable Sand Mining

Management Guidelines, 2016 and environment friendly

management tracks, in order to restore and maintain the ecology

of river and other sand sources. A perusal of the „objectives‟, „the

effect of sand and gravel mining‟ does not show that these

guidelines of 2016 are for the sand mining from the river only.

We need not reproduce those guidelines as from perusal it is

evident that they are not confined to the sand mining from the

river but, as a whole to ensure control of the un-control sand

mining and with an objective to protect the environment and the

right of the population to live in clean and safe surroundings.

Violation of the principles of natural justice:

73. Another submission of the learned counsel for the petitioner

that the N.G.T reordered findings on Points 1 to 4 (briefly

narrated in para 52 supra) were recorded in petitioner‟s favour

still the impugned order was passed against the petitioner does

not impress upon us for the reason that the N.G.T has assigned

67

reasons for passing the impugned order which have been briefly

noted by us in paras 53,54 and 55 hereinabove.

74. We are of the view that the Tribunal being an authority

vested with the powers, the jurisdiction and the duty to ensure the

environmental protection, if different aspects come before it, or

are brought to its notice, it has to take into consideration those

various aspects while deciding the lis. Even if it be taken that the

petitioner had no opportunity on certain aspects mentioned in the

order, even then, considering that the Tribunal has not set aside

the EC granted but has only kept it in abeyance while remitting

the matter for fresh consideration, the petitioner cannot succeed

on the ground of alleged violation of the principles of natural

justice, in as much as, while considering the matter by the

competent authority, pursuant to the direction issued by the

Tribunal, the petitioner may avail the opportunity of hearing

before the respondent authorities with respect to those aspects.

E.C granted prior to 2021:

75. The next submission of the learned counsel that the EC

granted was prior to 2021 and as such the N.G.T ought not to

have interfered with the same. The E.C (s) granted even prior to

2021 must confirm the then existing rules, regulations and the

68

notifications, which could not be granted dehors the rules. The

N.G.T has elaborately discussed the illegalities and irregularities

committed in grant of E.C to the petitioner. In view thereof no

immunity can be claimed from interference by the N.G.T on the

well assigned reasons.

Ex-post Facto grant of EC:

76. Learned counsel for the petitioner next submitted that Ex-

post facto EC could be granted. He emphasized in Electrosteel

Steels Limited (supra) to contend that the grant of ex post facto

environmental clearance is not prohibited in appropriate cases,

where the projects are in compliance with, or can be made to

comply with the environment norms.

77. The Hon‟ble Apex Court in Electrosteel Steels Limited

(supra) held that the need to comply with the requirement to

obtain environment clearance is non-negotiable. A project can be

set up or allowed to expand subject to compliance of the requisite

norms. Environmental clearance is granted on condition of the

suitability of the site to set up the project from the environmental

angle, and existence of necessary infrastructural facilities and

69

equipment for compliance of environmental norms. To protect

future generations, it is imperative that pollution laws be strictly

enforced. Under no circumstances, can industries which pollute

be allowed to operate unchecked and degrade the environment.

78. In Electrosteel Steels Limited (supra), considering the

office memorandum of 2021 and the subsequent follow up

proceedings for identification enabled of violation case under

2006 EIA notification, it was observed that in terms of the SOP,

the proposal for grant of EC in case of violations were to be

considered on merits with prospective effect, applying the

principles of proportionally and the principle that the Polluter Pays

Principle and liable for costs of remedial measures. The Hon‟ble

Apex Court, in Electrosteel Steels Limited (supra) observed that

ex post facto EC clearance should not however be granted

routinely but in exclusive circumstances taking into consideration

relevant environmental factors. Whe re the adverse

consequences of ex post facto approval outweigh the

consequences of regularization of operation of an industry by

grant of ex post facto approval and the industry or establishment

concerned otherwise conforms to the requisite pollution norms,

ex- post facto approval should be given in accordance with law, in

70

strict conformity with the applicable rules, regulations and/or

notifications. Ex post facto approval should not be withheld only

as a penal measure. The deviant industry may be penalized by

an imposition of heavy penalty on the principle of “polluter pays”

and the cost of restoration of environment may be recovered.

79. In Pahwa Plastics Pvt Limited (supra) the Hon‟ble Apex

Court observed that the Ex- Post facto Environmental Clearance

should not ordinarily be granted and certainly not for the asking.

80. In Uday Education and Welfare Trust (supra), the

Hon‟ble Apex Court considered the principles of sustainable

development, the precautionary principle and the polluter pays

principle. It was observed that it cannot be disputed that Section

20 of the NGT Act itself directs the learned Tribunal to apply the

principles of sustainable development, the precautionary principle

and the polluter pays principle. Undisputedly, it is the duty of the

State as well as its citizens to safeguard the forest of the country.

The resources of the present are to be preserved for the future

generations. However, one principle cannot be applied in isolation

of the other. It is necessary that, while protecting the

environment, the need for sustainable development has also to

71

be taken into consideration and a proper balance between the

two has to be struck.

81. Learned counsel for the petitioner referred to the judgment

of the Apex Court in Union of India vs. Vanshakti (supra) along

with, Confederation of Real Estate Developers of India

(CREDAI) vs. Vanashakti and another

30

, to contend that the

E.Cs already granted till date under the 2017 notification and the

2021 OM remained unaffected. He contended that the Ex-post

Facto EC can be granted in exceptional circumstances. There is

no absolute bar in grant of Ex-post Facto EC. He submitted that

the EC already granted to the petitioner was prior to notification of

2021. In Vanashakti (supra-2), the E.C (s) granted til the date of

judgment in Vanashakti (supra-2) were saved. So, it was not

open to the N.G.T to interfere with the E.C granted to the

petitioner.

82. In Vanshakti (supra-2), the Hon‟ble Apex Court held that

ex-post facto grant of EC under the notification of 2017 was not

permitted for the projects and activities which were commenced

or continued after 14.03.2017. The provision for grant of ex-post

facto was made only in relation to projects or activities which were

30

2025 SCC OnLine SC 2474

72

in violation as of 14.03.2017. The window which was initially for a

period of six months was eventually extended till completion of 30

days from 14.03.2018. The Hon‟ble Apex Court observed that in

environmental matters, the Courts must take a very strict view of

the violations of the laws relating to the environment. The Hon‟ble

Apex Court further observed that Once there is a violation of the

EIA notification, the project proponent has to compensate,

following the Polluter Pays Principle. Even if, EC is not granted to

him he has to pay for remedial plan to remedy the damage done

to the environment. He has also to pay the penalty. In Vanashkti

(supra-2), the Hon‟ble Apex Court saved the ECs already granted

till date of that judgment by providing that those ECs shall remain

unaffected.

83. The aforesaid judgment in Vanashkti (supra-2) has been

reviewed vide judgment reported in 2025 SCC OnLine SC 2474

(supra).

84. So far as the contention with respect to the Ex- Post facto

grant of EC is concerned, we are of the view that while

considering the matter in terms of the order of the Tribunal,

keeping in view the directions issued, the question of the grant of

EC whether Ex- Post facto, prospective or with retrospective

73

effect, in the light of the various factors, can be taken due care of

by the respondent authorities also keeping in view the latest

position in law in the case of Vanashkti (in Review Petition (C)

No.200 of 2025 Diary No.41929 of 2024 reported in 2025 SCC

OnLine SC 2474. So, at this stage of the writ petition against the

order of the NGT, we are not required to make any observation

on that aspect. It is upon the decision, when taken, by the

authorities, it may be open to the aggrieved party/person to raise

such an issue if so open under law in appropriate proceedings

before appropriate Forum.

V. Conclusions:

85. Thus, considered our conclusions on the points of

determination are as follows:

Point-A:

(i) The writ petition under Article 226 of the Constitution of

India is maintainable against the order of the National

Green Tribunal. The alternative remedy under Section 22

of the N.G.T Act is not an absolute bar.

(ii) We also entertain the writ petition, as the challenge is

on the ground of (a), the order being without jurisdiction,

(b) in Violation of the principles of natural justice and (c)

74

The petition is pending since 2021 and the affidavits have

been exchanged.

Point-B:

The 7

th

respondent (appellant before the N.G.T) is a

„person aggrieved‟ under Section 16 of the N.G.T.Act. The order

passed by the N.G.T in the appeal filed by the 7

th

respondent, is

not without jurisdiction.

Points C & D:

(i) There is no violation of the principles of natural justice,

so as to interfere with the order of the N.G.T.

(ii) Though on some aspects, finding has been recorded

in petitioner‟s favour but merely on that count, it cannot be said

that the N.G.T ought not ot have passed the impugned order.

The N.G.T has for the well assigned reasons, on justifiable

grounds rightly interfered with the grant of the E.C.

(iii) The N.G.T has also the suo moto power. Its role is

not simply adjudicatory in the nature of a lis, but it has also to

perform the vital roles which are preventive and remedial in

nature to save the environment from the degradation.

(iv) The N.G.T rightly took the cognizance of various

aspects in discharge of its statutory function. Its power and

75

jurisdiction while deciding a lis cannot be confined only to the

grounds raised in the appeal before it.

(v) Sustainable Sand Mining Management Guidelines,

2016 are applicable to the sand mining from the river as also from

the other sources. It is not confined only to the mining of sand

from the river only.

(vi) The E.C granted, even prior to 2021 notification has

to be in conformity with the then existing rules, regulations,

notification and the guidelines. Any EC issued in violation, cannot

claim immunity from interference merely because the grant was

prior to 2021 notificaotion.

(vii) Grant of Ex-post Facto E.C, is matter which lies in

the domain of the respondent authorities, for consideration, in

accordance with law, keeping in view the latest pronouncement of

the Hon‟ble Apex Court in the case of Confederation of Real

Estate Developers of India (CREDAI) vs. Vanashakti and

another (2025) SCC OnLine SC 2474).

(viii) No interference is called with the order of the N.G.T,

in the exercise of the writ jurisdiction.

VI. Result:

86. In the result:

76

(a) Writ Petition is dismissed,

(b) The respondent Nos.1 to 6 shall pursuant to the order

dated 15.11.2021, passed by the National Green Tribunal, South

Zone (NGTSZ), Chennai in Appeal No.19 of 2020 (SZ)

(B. Madan Kumar Reddy vs. Government of India and others)

proceed to consider the grant of EC, in accordance with law

keeping in view the directions issued by the N.G.T.

(c) While considering the matter the respondent

authority shall also take into account the latest pronouncement of

the Hon‟ble the Apex Court in Confederation of Real Estate

Developers of India (CREDAI) vs. Vanashakti and another

(2025 SCC OnLine SC 2474).

(d) The petitioner as also the 7

th

respondent shall be

provided with the opportunity of hearing.

87. No order as to costs.

77

Consequently, miscellaneous application if any pending

shall also stand closed.

________________________

RAVI NATH TILHARI,J

______________________________

MAHESWARA RAO KUNCHEAM,J

Date:08.01.2026.

Note:

L.R copy to be marked.

B/o.Gk.

78

THE HON’BLE SRI JUSTICE RAVI NATH TILHARI

&

THE HON’BLE SRI JUSTICE MAHESWARA RAO KUNCHEAM

W.P. No.31066 OF 2021

Date:08.01.2026.

Gk.

Description

Legal Notes

Add a Note....