0  31 Aug, 2024
Listen in 49:00 mins | Read in 90:00 mins
EN
HI

M/S. Usha Martin Ltd. Vs. Jharkhand Urja Vikas Nigam Ltd.

  Jharkhand High Court L.P.A. No.305 of 2015
Link copied!

Case Background

he challenge in these batch of appeals is to the common judgment passed by the writ court in batch of writ petitions by Order dated 08.05.2015; wherein the Writ Petition ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

1

IN THE HIGH COURT OF JHARKHAND AT RANCHI

L.P.A. No.305 of 2015

……..

M/S. USHA MARTIN LTD. (Earlier known as M/s. Usha

Beltron Ltd.), A Company incorporated under the provisions

of Companies Act, 1956, having its Registered Office at 2A,

Shakespeare Sarani, Kolkata, P.O. Shakespeare Sarani,

P.S. Shakespeare Sarani, District Kolkata, West Bengal

through its General Manager (Commercial) Sri N.K. Patodia,

son of Late R.D. Patodia, Resident of Deputy Para, P.O.

GPO, P.S. Kotwali, District Ranchi. ..… Appellant

Versus

1. JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman-cum-Managing Director,

Engineers' Bhawan, H.E.C., P.O. & P.S. Dhurwa, District

Ranchi.

2. Bihar State Electricity Board, a body constituted under

the Indian Electricity Act, 1910, having its Head Office at

Bailey Road, Patna, through its Chairman, P.O & P.S.

Fraser (Dak Bunglow).

3.The Chief Engineer (Commercial and T.A.), Bihar State

Electricity Board, Bailey Road, Patna, P.O & P.S. Fraser

(Dak Bunglow).

4. The Financial Controller (Rev.), Bihar State Electricity

Board, Bailey Road, Patna. P.O & P.S. Fraser (Dak Buglow).

5. General Manager-cum-Chief Engineer, Ranchi Area

Electricity Supply (Earlier known as South Bihar and

Chhotanagpur Area Electricity Board), Kusai Colony,

Doranda, P.O & P.S:- Doranda Ranchi.

6.General Manager-cum-Chief Engineer, Jharkhand Urja

Sancharan Nigam Limited (Earlier Jharkhand State

Electricity Board), Transmission Zone JR, Gamharia, P.O. &

P.S. Gamharia, District- Seraikella Kharsawan.

7. The Electrical Superintending Engineer, Ranchi

Electrical Circle, Kusai Colony, Doranda, P.O. and P.S.

Doranda, District Ranchi.

8. The Electrical Superintending Engineer, Electric Supply

Circle, having its office at Vikash Bhawan, Adityapur, P.O.

and P.S. Adityapur, District Seraikella Kharsawan.

2

9.The Electrical Executive Engineer (Commercial &

Revenue), Office of the Electrical Superintending Engineer,

Ranchi Electrical Circle, Kusai Colony, Doranda, P.O.&.S:-

Doranda,Ranchi.

10.The Electrical Executive Engineer (Commercial and

Revenue), Office of the Electrical Superintending Engineer,

Electric Supply Circle, VikashBhawan, Adityapur, P.O. and

P.S. Adityapur, District –SeraikellaKharsawan.

.....Respondents

With

L.P.A. No.410 of 2015

……..

Ramakant Vishwakarma, son of Late Udaybhan

Vishwakarma, Resident of Dimna Chowk P.O. and P.S.

Mango, Town-Jamshedpur, District-Singhbhum East.

..… Appellant

Versus

1. Jharkhand State Electricity Board(Now Jharkhand State

Vijli Vitran Nigam Ltd.) through its Chairman, Engineering

Bhawan, Dhurwa, P.O. Dhurwa P.S. Jagannathpur,

District-Ranchi.

2.General Manager Cum Chief Engineer, Singhbhum

Division, Jharkhand State Electricity Board(Now

Jharkhand State VijliVitran Nigam Ltd.), Co-operative

Building, Bistupur, P.O. and P.S. Bistupur, Town-

Jamshedpur, District-Singhbhum East.

3. Electrical Executive Engineer, Electric Supply Division,

Jamshedpur, P.O. and P.S. Bistupur, District- Singhbhum

East. ....Respondents

W ith

L.P.A. No. 431 of 2015

……..

M/s. La Opala (R.G.), Ltd., at Madhupur, District- Deoghar,

a Company incorporated under the Indian Companies Act,

having its factories at Madhupur through its Vice President

and Secretary Alok Pandey, Son of Late Bal Krishna

Pandey, Resident of 1/C, Heysham Road, P.O. LalaLaljpat

Rai Sarani Road, P.S. Bhawanipur Town and District-

Kolkata, West Bengal-700020. ..… Appellant

3

Versus

1.Jharkhand URJA VIKAS NIGAM LIMITED (Earlier known

as Jharkhand State Electricity Board), having its office at

Engineers Bhawan, HEC, Dhurwa, Ranchi through its

Chairman, Project Bhawan, H.E.C, P.O. & P.S. Dhurwa,

District-Ranchi.

2.Bihar State Electricity Board, Vidyut Bhawan, Bailey

Road, P.O., G.P.O & P.S. Kotwali, Patna through its

Chairman.

3.The Chief Engineer (Commercial & T.A.), Manager, Bihar

State Electivity Board, Bailey Road, P.O., G.P.O & P.S.

Kotwali, Patna.

4.The Financial Controller (Rev.), Bihar State Electricity

Board, Bailey Road, P.O., G.P.O, & P.S.-Kotwali.

5.The General Manager-cum-Chief Engineer, Chotanagpur

Area, Electricity Board, Doranda, Ranchi, P.O. & P.S.

Doranda, Ranchi.

6.Electrical Superintending Engineer, Electric Supply

Circle, Deoghar, P.O. and P.S. Deoghar, District-Deoghar.

7.Electrical Executive Engineer (C& R), Electrical Circle,

Deoghar, P.O. and P.S. Deoghar, District-Deogahr.

.....Respondents

W ith

L.P.A. No. 444 of 2015

……..

URANIUM CORPORATION Of INDIA LIMITED,A

Government Company, registered under section 617 of

the Companies Act, 1956, having its registered and Head

Office at Jadugora Mines, PO and PS Jadugoda District-

East Singhbum, through Its G M (Personnel-IR) Shri C H

Sharma, son of- Late L P Sharma resident of- E- 2 Ucil

Colony PO and PS Jadugora District-Singhbum East.

..… Appellant

Versus

1.JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

Known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, H E C, Dhurwa,

Ranchi through its Chairman, Engineers Bhawan, HEC,

P.O. and P.S. Dhurwa, District-Ranchi.

4

2. Bihar State Electricity Board, Vidyut Bhawan Bailey

Road , P.O. & P.S. Patna, District-Patna Through Its

Chairman.

3. The Electrical Executive Engineer, (Commercial &

Revenue), Jharkhand State Electricity Board, Singhbhum

Supply Circle Jamshedpur PO and PS Adityapur,

Jamshedpur, (Singhum East).

4.The Financial Controller (Rev ), Jharkhand State

Electricity Board, Engineers Bhawan H E C P.O and P.S

Dhurwa District- Ranchi .....Respondents

W ith

L.P.A. No. 448 of 2015

……..

URANIUM CORPORATION Of INDIA LIMITED, A

Government Company, registered under section 617 of

the Companies Act, 1956, having its registered and Head

Office at Jadugora Mines, PO and PS Jadugoda District-

East Singhbum, through Its G M (Personnel- IR) Shri C H

Sharma, son of- Late L P Sharma resident of- E- 2 Ucil

Colony P.O and P.S Jadugora District- Singhbum East

..… Appellant

Versus

1.JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

Known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, H E C, Dhurwa,

Ranchi through its Chairman, Engineers Bhawan, HEC,

P.O. and P.S. Dhurwa, District-Ranchi.

2. Bihar State Electricity Board, VidyutBhawan Bailey

Road , P.O. & P.S. Patna, District-Patna Through Its

Chairman.

3.The Chief Engineer, (Commercial and T A) Bihar State

Electricity Board, Bailey Road, P.O & P.S. Patna, Bihar.

4. The Electrical Executive Engineer, Commercial &

Revenue), Bihar State Electricity Board, Singhbhum

Supply Circle, Jamshedpur, P.O. and P.S. Adityapur.

5.The Financial Controller (Rev), Bihar State Electricity

Board, Bailey Road, P.O. & P.S. Patna, Bihar.

6.The Secretary, Bihar State Electricity Board, Baily

Road, P.O. & P.S. Patna, Bihar. .....Respondents

5

With

L.P.A. No. 449 of 2015

……..

URANIUM CORPORATION OF INDIA LIMITED, A

Government Company, Registered under Section 617 of the

Companies Act, 1956 having its registered and Head Office

at Jadugora Mines, P.O. and P.S. Jadugoda, District - East

Singhbhum through its G.M. (Personnel IR) Shri C.H.

Sharma, son of Late L.P. Sharma, Resident of E-2, UCIL

Colony, P.O, and P.S. Jadugora, District Singhbhum East.

..… Appellant

Versus

1. JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman, Engineers Bhawan, H.E.C.,

P.O. & P.S. Dhurwa, District – Ranchi.

2. Secretary, Bihar State Electricity Board, Bailey Road,

P.O., P.S. and District-Patna.

3. The Chief Engineer (Commercial and T.A.), Bihar State

Electricity Board, Bailey Road, P.O., P.S. and District-

Patna.

4. The Electrical Executive Engineer (Commercial &

Revenue), Bihar State Electricity Board, Bailey Road, P.O.,

P.S. and District-Patna.

5. The Financial Controller (Rev.), Bihar State Electricity

Board, Bailey Road, P.O., P.S. and District-Patna.

.....Respondents

With

L.P.A. No. 454 of 2 015

……..

URANIUM CORPORATION OF INDIA LIMITED, A

Government Company, Registered under Section 617 of the

Companies Act, 1956 having its registered and Head Office

at Jadugora Mines, P.O. and P.S. Jadugoda, District - East

Singhbhum through its G.M. (Personnel IR) Shri C.H.

Sharma, son of Late L.P. Sharma, Resident of E-2, UCIL

Colony, P.O, and P.S. Jadugora, District Singhbhum East.

6

..… Appellant

Versus

1. JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman, Engineers Bhawan, H.E.C.,

P.O. & P.S. Dhurwa, District – Ranchi

2. The Chairman, JHVNL, Engineers Bhawan, H.Е.С., Р.О.

& P.S. Dhurwa, District Ranchi.

3. The Chief Engineer (Commercial and T.A.) J.S.E.B,

Engineers Bhawan, HEC, P.O. & P.S.-Dhurwa, District-

Ranchi

4. The Electrical Executive Engineer (Commercial &

Revenue), J.S.E.B, Singhbhum Supply Circle, Jamshedpur,

P.O. and P.S. –Adityapur District-Jamshedpur.

5. The Financial Controller (Rev.), J.S.E.B, Engineers'

Bhawan, H.E.C., P.O. and P.S. Dhurwa, District Ranchi.

.....Respondents

With

L.P.A. No. 463 of 2015

……..

URANIUM CORPORATION OF INDIA LIMITED, A

Government Company, Registered under Section 617 of the

Companies Act, 1956 having its registered and Head Office

at Jadugora Mines, P.O. and P.S. Jadugoda, District East

Singhbhum through its G.M. (Personnel-IR) Shri C.H.

Sharma, son of Late L.P. Sharma, Resident of E-2, UCIL

Colony, P.O. and P.S. Jadugora, District - Singhbhum East.

..… Appellant

Versus

1. JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman, Engineers Bhawan, H.E.C.,

P.O. & P.S. Dhurwa, District – Ranchi.

2.Secretary, Jharkhand State Electricity Board, Doranda,

P.O. & P.S. Doranda, District-Ranchi.

3. The Chief Engineer (Commercial and T.A.), J.S.E.B ,

Engineers Bhawan, HEC, Dhurwa, P.O. & P.S. Dhurwa,

7

District-Ranchi.

4. The Electrical Executive Engineer (Commercial &

Revenue), JUVNL, Singhbhum Supply Circle, Jamshedpur,

P.O. and P.S.Adityapur.

5. The Financial Controller (Rev.), J.S.E.B., Doranda, P.O.

and P.S.-Doranda, Ranchi .....Respondents

With

L.P.A. No. 465 of 2015

……..

MAHALAKSHMI FIBERS & INDUSTRIES LIMITED, a

company duly registered under the Companies Act, 1956

having its Registered Office at 5, Synagogue Street, P.O.,

P.S. & District Kolkata and its manufacturing unit and

works at Ormanjhi, P.S. Ormanjhi, District Ranchi, through

its Commercial Manager and duly constituted Attorney Shri

Jawahar Bhan, Son of Late, P.S. Bhan, Resident of P.O.

Ormanhji, P.S. Ormanjhi, District Ranchi. ..… Appellant

Versus

1.JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as Jharkhand State Electricity Board), having its

office at Engineers Bhawan, HEC, Dhurwa, Ranchi through

its Chairman-Cum-Managing Director, Engineers' Bhawan,

H.E.C. P.O. & P.S. Dhurwa, District. Ranchi.

2. Bihar State Electricity Board, a body constituted under

the Indian Electricity Act, 1910, having its Head Office at

Baily Road P.O. & P.S. Baily Road, District- Patna, through

its Chairman.

3. The Chief Engineer (Commercial and T.A.), Bihar State

Electricity Board, Baily Road, P.O. & P.S. Bailey Road,

District-Patna, Bihar

4. The Financial Controller (Rev.), Bihar State Electricity

Board, Bailey Road, Patna. P.O. & P.S. Baily Rood, District-

Patna, Bihar.

5. General Manager-cum-Chief Engineer, Ranchi Area

Electricity Supply (Earlier known as South Bihar and

Chhotanagpur Area Electricity Board),Kusai Colony,

Doranda, Ranchi. P.O. & P.S. Doranda

6. The Electrical Superintending Engineer, Ranchi

Electrical Circle, Kusai Colony, Doranda, P.O. and P.S.

8

Doranda, District-Ranchi.

7. The Electrical Executive Engineer (Commercial and

Revenue Electric Supply sub. Division, JCEB), office of the

Ranchi Electrical Circle Kusai Colony, Doranda, P.O. & P.S.

Doranda, Ranchi. ....Respondents

With

L.P.A. No. 470 of 2015

……..

M/s. Auto Profiles Ltd. (Unit-1), A company registered

under the provisions of Indian Companies Act having is

works at Plot Nos.33 - 34, 4th Phase, Gamharia, P.O. and

P.S. Gamharia, District-SeraikellaKharsawan, through its

Managing Director Sri Bikash Mukherjee, son of Late P

Mukherjee, resident of 457, G-Road, West Layout, P.O. and

P.S. Sonari, Town-Jamshedpur, District- Singhbhum East.

..… Appellant

Versus

1. JHARKHAND BIJLI VITRAN NIGAM LIMITED, having its

Head Office at Engineering Bhawan, Dhurwa, P.O. & P.S.

Dhurwa, District-Ranchi, through its Managing Director.

2.The Secretary, Jharkhand State Electricity Board, Kusai

Colony, Doranda P.O. & P.S. Doranda, District-Ranchi.

3. The Finance Controller (Revenue), Jharkhand State

Electricity Board, Kusai Colony, P.O. & P.S. Doranda,

District-Ranchi.

4. General Manager-Cum-Chief Engineer, Jharkhand

BijliVitran Nigam Limited, Jamshedpur Division, Co-

operative Building, Bistupur, P.O. and P.S. Bistupur, Town-

Jamshedpur, District-East Singhbhum

5. Electrical Executive Engineer, (Commercial & Revenue),

Electric Supply Circle, Adityapur, Vikash Bhawan,

Adityapur, P.O.and P.S. Adityapur, District- Seraikella

Kharsawan. .....Respondents

With

L.P.A. No. 481 of 2015

……..

M/S. Maithan Ceramics Ltd., a Company incorporated

under the provisions of Companies Act, 1956, having its

Factory at Chirkunda, P.O. and P.S. Chirkunda, District

9

Dhanbad, through one of its Director Binod Kumar

Agarwal, son of Late Raghunath Agarwal, Resident of

Chirkunda, P.O. and P.S. Chirkunda, District - Dhanbad.

..… Appellant

Versus

1. JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman cum - Managing Director,

Engineers' Bhawan, H.E.C., P.O. & P.S. Dhurwa, District -

Ranchi.

2. Bihar State Electricity Board, a body constituted under

the Indian Electricity Act, 1910, having its Head Office at

Bailey Road, Patna, P.O. G.P.O., P.S. Kotwali, District -

Patna, through its Chairman.

3.The Financial Controller (Rev.), Bihar State Electricity

Board, having its Head Office at Bailey Road, Patna, P.O.

G.P.O., P.S. Kotwali, District - Patna.

4. Chief Engineer (Commercial and T.A.), Bihar State

Electricity Board, having its Head Office at Bailey Road,

Patna, P.O. G.P.O., P.S. Kotwali, District - Patna.

5.General Manager-cum-Chief Engineer, Dhanbad Area

Electricity Board, JUVNL, having its office at Combined

Building, P.O. and P.S. - Dhanbad, District - Dhanbad.

6.The Electrical Executive Engineer (Commercial and

Revenue), JUVNL, Electrical Supply Circle, P.O. and P.S. -

Dhanbad, District - Dhanbad.

7. The Superintending Engineer, Dhanbad.

.....Respondents

W ith

L.P.A. No. 482 of 2015

……..

M/S. Maithan Coal Co Pvt Ltd., a Company incorporated

under the provisions of Companies Act, 1956, having its

Factory at Tetulia,, P.O. and P.S. Nirsha, District Dhanbad,

through one of its Directors Shri Shiv Kumar Sharma,, son

of R.S. Sharma, Resident of Chirkunda, P.O. and P.S.

Chirkunda, District - Dhanbad. ..… Appellant

Versus

10

1. JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman cum - Managing Director,

Engineers' Bhawan, H.E.C., P.O. & P.S. Dhurwa, District -

Ranchi.

2. Bihar State Electricity Board, a body constituted under

the Indian Electricity Act, 1910, having its Head Office at

Bailey Road, Patna, P.O. G.P.O., P.S. Kotwali, District -

Patna, through its Chairman.

3.The Financial Controller (Rev.), Bihar State Electricity

Board, having its Head Office at Bailey Road, Patna, P.O.

G.P.O., P.S. Kotwali, District - Patna.

4. Chief Engineer (Commercial and T.A.), Bihar State

Electricity Board, having its Head Office at Bailey Road,

Patna, P.O. G.P.O., P.S. Kotwali, District - Patna.

5.General Manager-cum-Chief Engineer, Dhanbad Area

Electricity Board, JUVNL, having its office at Combined

Building, P.O. and P.S. - Dhanbad, District - Dhanbad.

6.The Electrical Executive Engineer (Commercial and

Revenue), JUVNL, Electrical Supply Circle, P.O. and P.S. -

Dhanbad, District - Dhanbad.

7. The Superintending Engineer, Dhanbad.

.....Respondents

With

L.P.A. No. 483 of 2015

……..

1. M/S. Mugma Coke Oven Pvt ltd a company

incorporated under the Companies Act, 1956 having its

factory at Mugma, P.O. Mugma, P.S. Nirsha, district-

Dhanbad through one of its Directors Sri Shri

JalajChowdhary son of Shri Krishna MurariChowdhary ,

resident of Chirkunda, P.O. & P. S - Chirkunda, District -

Dhanbad, Jharkhand.

2. M/s Shree Dwarka Bee Hive Plant PvtLtd., a company

incorporated under the Companies Act, 1956 having its

factory at Egarpore, P.O. Egarpore, P.S. Chirkunda,

district- Dhanbad Jharkhand through one of its present

Director, Sri Shiv Kumar Sharma, Son of Shri Radhey

Shyam Sharma, resident of Hariyana Colony, Upper Bazar

11

G.T. Road, P.O. & P.S. Chirkuna, Dhanbad, Jharkhand

..… Appellants

Versus

1. JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman cum Managing Director,

Engineers' Bhawan, H.E.C., P.O. & P.S. Dhurwa, District -

Ranchi.

2.Bihar State Electricity Board, through its Chairman a

body constituted under the Indian Electricity Act, 1910,

having its Head Office at Bailey Road, Patna, P.Ο. G.P.O.,

P.S. Kotwali, District - Patna,

3. The Financial Controller (Rev.), Bihar State Electricity

Board, having its Head Office at Bailey Road, Patna, P.O.

G.P.O., P.S. Kotwali, District – Patna

4. Chief Engineer (Commercial and T.A.), Bihar State

Electricity Board, having its Head Office at Bailey Road,

Patna, P.O, G.P.O., P.S. Kotwali, District - Patna.

5.General Manager- cum- Chief Engineer, Dhanbad Area

Electricity Board, JUVNL, having its office at Combined

Building, P.O, and P.S, Dhanbad, District Dhanbad.

6. The Electrical Executive Engineer (Commercial and

Revenue), JUVNL, Electrical Supply Circle, P.O, and P.S. -

Dhanbad, District Dhanbad.

7. Electrical Executive Engineer, Commercial & Revenue,

Electric Supply Circle, P.O, and P.S. Dhanbad, District

Dhanbad.

8.The Electrical Executive Engineer, Electric Supply Circle,

Dhanbad. .....Respondents

With

L.P.A. No. 484 of 2015

……..

1. M/S. Arun Refractories, a partnership firm, having its

factory at Chirkunda, P.O. & P.S. Chirkunda , District,

Dhanbad through one of its partners Sri, SUSHIL Kumar

Gadhyan son of Late Rajkumar Gadhyan, resident of

Chirkunda, P.O. & P. S Chirkunda, Distric t - Dhanbad,

Jharkhand.

12

2. M/s Sharad Refractories Pvt Ltd. a company

incorporated under the Companies Act, 1956 having its

factory at Chirkunda, P.O. & P.S. Chirkunda, District ,

Dhanbad through one of its Directors Sri Arun Agarwal son

of Late Bihari Agarwal, resident of Chirkunda P.O. & P. S -

Chirkunda, District Dhanbad, Jharkhand.

3. M/s Associated Ceramics Ltd., a company incorporated

under the Companies Act, 1956 having its factory at

Chirkunda, P.O. & P.S. Chirkunda District, Dhanbad

through one of its Directors Sri Arun Agarwal , son of Late

Bihari Agarwal, resident of Chirkunda P.O. & P. S -

Chirkunda, District Jharkhand. ..… Appellants

Versus

1. JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman cum Managing Director,

Engineers' Bhawan, H.E.C., P.O. & P.S. Dhurwa, District -

Ranchi.

2. Bihar State Electricity Board, a body constituted under

the Indian Electricity Act, 1910, having its Head Office at

Bailey Road, Patna, P.O. G.P.O., P.S. District Patna,

through its Chairman.

3. The Financial Controller (Rev.), Bihar State Electricity

Board, having its Head Office at Bailey Road, Patna, P.O.

G.P.O., P.S. Kotwali, District Patna.

4. Chief Engineer (Commercial and T.A.), Bihar State

Electricity Board, having its Head Office at Bailey Road,

Patna, P.O. G.P.O., P.S. Kotwali, District - Patna.

5. General Manager cum Chief Engineer, Dhanbad Area

Electricity Board, JUVNL, having its office at Combined

Building, P.O. and P.S. Dhanbad, District - Dhanbad.

6.The Electrical Executive Engineer (Commercial and

Revenue), JUVNL, Electrical Supply Circle, P.O. and P.S. + -

Dhanbad, District - Dhanbad.

7. The superintending Engineer, Dhanbad.

.....Respondents

With

L.P.A. No. 485 of 2015

13

……..

M/S. SRI DURGA CEMENT COMPANY LIMITED, a

company incorporated under the provisions of the

Companies Act, 1956, having its unit at Hesla, Argada

Road, Ramgarh Cantonment through one its Executive

Director Sri Naresh Kumar Iyangar son of Late A.K. Iyangar

resident of Bharechnagar, Ramgarh Cantonment, P.O.

Bharechnagar& P.S. Kujju, Dist. Ramgarh. ..… Appellant

Versus

1.JHARKHAND URJA VITARAN NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman, Project Bhawan, H.E.C., P.O.

& P.S. Dhurwa, District – Ranchi

2. BIHAR STATE ELECTRICITY BOARD, Vidyut Bhawan,

Bailey Road, P.O. & P.S.- Bailley Road, District -Patna

through its Chairman.

3. The Chief Engineer (Commercial & T.A.), Manager, Bihar

State Electricity Board, Bailey Road, P.O. & P.S.- Bailley

Road, District - Patna.

4. The Financial Controller (Rev.), Bihar State Electricity

Board, Bailey Road, P.O. & P.S.- Bailley Road, District

Patna.

5. The General Manager cum Chief Engineer, Jharkhand

UrjaVitaran Nigam Limited (earlier Dhanbad) now

Hazaribagh Electric Supply Area, P.O. and P.S. Hazaribagh.

Hazaribagh, Town & District

6. Electrical Superintending Engineer, Electric Hazaribagh.

P.O. and P.S. Hazaribagh, Town & District - Hazaribagh.

7. Electrical Executive Engineer (C & R), Electrical Circle,

Hazaribagh, P.O. and P.S. Hazaribagh, Town & District -

Hazaribagh .....Respondents

With

L.P.A. No. 498 of 2015

……..

M/s. R. K. Industries, a company incorporated under the

Companies Act, 1956 having its Head Office at 144, Sakchi

Market, P.O. & P.S. Sakchi, Town-Jamshedpur, District-

Singhbhum East and works at 11 & 12, Phase-IV,

Adityapur Industrial Area, P.O, & P.S. Gamharia, District-

14

SeraikelaKharsawan through its PatnerBalkrishna

Choudhary, Son of Late Lal Chand Choudhary, resident of

144, Sakchi Market, P.O. & P. S. Sakchi, Town-

Jamshedpur, District-Singhbhum East. ..… Appellant

Versus

1.JharkhandState Electricity Board, now Jharkhand Bijli

Vitran Nigam Limited, Engineering Bhawan, P.O. and P.S.

Dhurwa, District-Ranchi through its Chairman.

2. General Manager-Cum-Chief Chief Engineer, Singhbhum

Area, Cooperative Building, Bistupur, PO. and P.S.

Bistupur, Town- Jamshedur, District-Singhbhum East.

3. Bihar State Electricity Board, Vidyut Bhawan,

Serpantine Road, Patna through its Chairman, Bihar State

Electricity Board, Bailey Road, Patna. .....Respondents

with

L.P.A. No. 499 of 2015

……..

M/s. JMT Auto Ltd., a company incorporated under the

Companies Act, 1956 having its accounts and project office

at C-19/20, 7th Phase, Adityapur Industrial Area, P.O. and

P.S. Adityapur, District-SeraikellaKharswan, through its

Company Secretary, Mona Bahadur, daughter of Ravindra

Bhadur, Resident of Bijaya Heritage P.O. and P.S. Sonari,

Town Jamshedpur, District-Singhbhum East.

..… Appellant

Versus

1.Jharkhand State Electricity Board, Now Jharkhand Bijli

Vitran Nigam Limited, Engineering Bhawan, P.O. and P.S.

Dhurwa, District-Ranchi.

2. General Manager-Cum-Chief Engineer, Singhbhum Area,

Cooperative Building, Bistupur, PO. and P.S. Bistupur,

Town- Jamshedur, District-Singhbhum East.

3. Bihar State Electricity Board, Vidyut Bhawan,

Serpantine Road, Patna through its Chairman, Bihar State

Electricity Board, Bailey Road, Patna

.....Respondents

With

L.P.A. No. 505 of 2015

15

……..

M/s. JMT Auto Ltd.(Unit-2), a company incorporated under

the Companies Act, 1956 having its accounts and project

office at C-19/20, 7th Phase, Adityapur Industrial Area,

P.O. and P.S. Adityapur, District-SeraikellaKharswan,

through its Company Secretary, Mona Bahadur, daughter

of Ravindra Bhadur, Resident of Bijaya Heritage P.O.

and P.S. Sonari, Town Jamshedpur, District-Singhbhum

East. ..… Appellant

Versus

1. Jharkhand State Electricity Board, Now Jharkhand Bijli

Vitran Nigam Limited, Engineering Bhawan, P.O. and P.S.

Dhurwa, District-Ranchi.

2. General Manager-Cum-Chief Engineer, Singhbhum Area,

Cooperative Building, Bistupur, PO. and P.S. Bistupur,

Town- Jamshedur, District-Singhbhum East.

3. Bihar State Electricity Board, Vidyut Bhawan,

Serpantine Road, Patna through its Chairman, Bihar State

Electricity Board, Bailey Road, Patna.

.....Respondents

With

L.P.A. No. 508 of 2015

……..

M/s. Bihar Caustics & Chemicals Ltd. (now known as M/s.

Aditya Birla Chemicals (India) Ltd.), having its Factory and

Registered Office at village - Rehla, P.S. Garhwa Road,

District Palamau, through its Legal Officer and authorized

signatory Shri Shailendra Panday, son of Shri H.N. Pandey,

Resident of-293 K, Lake Avenue, P.O. and P.S. Gonda,

Kanke, District - Ranchi, Jharkhand, 834008.

..… Appellant

Versus

1. The Jharkhand State Electricity Board,KusaiColony,

Ranchi, through its Chairman, NOW JHARKHAND URJA

VIKAS NIGAM LIMITED (Earlier known as JHARKHAND

STATE ELECTRICITY BOARD), having its office at

Engineers Bhawan, HEC, Dhurwa, Ranchi through its

Chairman, Project Bhawan, H.E.C., P.O. & P.S. Dhurwa,

District – Ranchi.

2. Bihar State Electricity Board, Vidyut Bhawan, PO.-G.PO.

16

P.S. Kotwali, District-Patna, Bailey Road, Patna through its

Chairman.

3. The Chief Engineer (Commercial & T.A.), Manager, Bihar

State Electricity Board PO.-G.PO. P.S. Kotwali, District-

Patna, Bailey Road, Patna.

4. The Financial Controller (Rev.), Bihar State Electricity

Board, P.O., P.S.-Kotwali, District-Patna, Bailey Road,

Patna.

5. The General Manager- cum-Chief Engineer,

ChhotanagpurArea Electricity Board, Doranda, Ranchi, now

The General Manager - cum - Chief Engineer, Daltonganj,

P.O. and P.S. -Daltonganj, Town Daltonganj, District -

Palamau.

6. The Electrical Superintending Engineer, transmission

Circle, Kusai Colony, Doranda Ranchi, Now Electrical

Superintending Engineer, Supply Circle, Daltonganj, P.O.

and P.S.-Daltonganj, District - Palamau.

7. Assistant Executive Engineer, Supply Sub-Station,

Garhwa Grid, Garhwa Road, P.O. and P.S. - Garhwa Road,

District - Palamau. .....Respondents

With

L.P.A. No. 542 of 2015

……..

M/S. USHA MARTIN LTD. (Earlier known as M/s. Usha

Beltron Ltd.), A Company incorporated under the provisions

of Companies Act, 1956, having its Registered Office at 2A,

Shakespeare Sarani, Kolkata, P.O. Shakespeare Sarani,

P.S. Shakespeare Sarani, District Kolkata, West Bengal

through its General Manager (Commercial) Sri N.K. Patodia,

son of Late R.D. Patodia, Resident of Deputy Para, P.O.

GPO, P.S. Kotwali, District - Ranchi. ..… Appellant

Versus

1.JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman, Project Bhawan, H.E.C., P.O.

& P.S. Dhurwa, District - Ranchi.

2. Bihar State Electricity Board, a body constituted under

the Indian Electricity Act, 1910, through its Chairman,

17

having its Head Office at Bailey Road, P.O G.P.O., P.S.

Kotwali, Patna.

3. The Chief Engineer (Commercial and T.A.), Bihar State

Electricity Board, Bailey Road, P.O G.P.O., P.S.-Kotwali

Patna.

4. The Financial Controller (Rev.), Bihar State Electricity

Board, Bailey Road, P.O - G.P.O., P.S.- Kotwali Patna.

5.General Manager cum Chief Engineer, Ranchi Area

Electricity Supply (Earlier known as South Bihar and

Chhotanagpur Area Electricity Board), Kusai Colony,

Doranda, P.O. & P.S.- Doranda, Ranchi, R.Np.5 as per the

certified copy: The General Manager Cum Chief Engineer,

Singhbhum Area Electricity Board , Bistupur, P.O, P.S.

Bistupur, District-Jamshedpur.

6. The Electricity Superintending Engineer, Ranchi

Electrical Circle, Kusai Colony, Doranda, P.O. and P.S. -

Doranda, District - Ranchi.

7. The Electrical Superintending Engineer, Electric Supply

Circle, having its office at Jamshedpur Vikash Bhawan,

Adityapur, P.O. and P.S. Adityapur, District-Seraikella

Kharsawan, R.No.7 as per C.C: The Electrical

Superintending Engineer, Electric Supply Circle,

Jamshedpur.

8. The Electrical Executive Engineer (Commercial &

Revenue), Office of the Electrical Superintending Engineer,

Ranchi Electrical Circle, Kusai Colony, P.O. & P.S.-

Doranda Ranchi. R.No8 as per C.C.: The office of the

Electrical Executive Engineer (Commercial & Revenue) ,

office of the Electrical Superintending Engineer, Ranchi,

Electrical Circle, at Kusai Colony, P.O. & P.S. Doranda,

Ranchi.

9. The Electrical Executive Engineer (Commercial &

Revenue) Office of the Electrical Superintending Engineer,

Electric Supply Circle, Vikas Bhawan, Adityapur, P.O. and

P.S. Adityapur, District-Seraikella Kharsawan, West

Singhbhum R. No.9, as per CC: The Electrical Executive

Engineer (Commercial and Revenue), Office of the Electrical

Superintending Engineer, Electric Supply Circle,

Jamshedpur. .....Respondents

With

18

L.P.A. No. 581 of 2015

……..

M/s UBL INDUSTRIES & INVESTMENT LIMITED, (WIRE

MILL DIVISION) (Now known as Usha Martin Ltd. (Bar and

Wire Mills Division Unit-I & II), a Company incorporated

under the provisions of Companies Act, 1956, having its

Registered Office at 8, Chittaranjan Avenue, P.O. & P.S.

Chittaranjan Avenue, District Kolkata and its works at Plot

No. 34, Phase-IV, Adityapur Industrial Area, Gamharia,

P.O. & P.S. Adityapur, Jamshedpur, District East

Singhbhum, through its General Manager (Works) Sri I.

Mitra, Son of A.K.Mitra, Resident of Adityapur Industrial

Area, Gamharia, P.O. & P.S. Adityapur, Jamshedpur,

District East Singhbhum. ..… Appellant

Versus

1.JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman-cum-Managing Director,

Engineers Bhawan, H.E.C., P.O. & P.S. Dhurwa, District

Ranchi.

2. Bihar State Electricity Board, a body constituted under

the Indian Electricity Act, 1910, having its Head Office at

Bailey Road, P.O. & P.S. Baily Road, District Patna, through

its Chairman.

3. The Chief Engineer (Commercial and T.A.), Bihar State

Electricity Board, Bailey Road, P.O. & P.S. Baily Road,

District Patna.

4. The Financial Controller (Rev.), Bihar State Electricity

Board, Bailey Road, P.O. & P.S. Baily Road, District Patna.

5. General Manager cum Chief Engineer, Singhbhum Area ,

Electricity Board, Bistupur, Jamshedpur

6.The Electrical Superintending Engineer, Electric Supply

Circle Jamshedpur.

7. The Electrical Executive Engineer (Commercial &

Revenue), office of the Electrical Superintending Engineer,

Electric Supply Circle, Jamshedpur. .....Respondents

With

L.P.A. No. 585 of 2015

……..

19

M/s UBL INDUSTRIES & INVESTMENT LIMITED, (WIRE

MILL DIVISION) (Now known as Usha Martin Ltd. (Bar and

Wire Mills Division Unit-I & II), a Company incorporated

under the provisions of Companies Act, 1956, having its

Registered Office at 8, Chittaranjan Avenue, P.O. & P.S.

Chittaranjan Avenue, District Kolkata and its works at Plot

No. 34, Phase-IV, Adityapur Industrial Area, Gamharia,

P.O. & P.S. Adityapur, Jamshedpur, District East

Singhbhum, through its General Manager (Works) Sri I.

Mitra, Son of A.K.Mitra, Resident of Adityapur Industrial

Area, Gamharia, P.O. & P.S. Adityapur, Jamshedpur,

District East Singhbhum. ..… Appellant

Versus

1. JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman-cum-Managing Director,

Engineers Bhawan, H.E.C., P.O. & P.S. Dhurwa, District

Ranchi.

2. Bihar State Electricity Board, a body constituted under

the Indian Electricity Act, 1910, having its Head Office at

Bailey Road, P.O. & P.S. Baily Road, District Patna, through

its Chairman.

3. The Chief Engineer (Commercial and T.A.), Bihar State

Electricity Board, Bailey Road, P.O. & P.S. Baily Road,

District Patna.

4. The Financial Controller (Rev.), Bihar State Electricity

Board, Bailey Road, P.O. & P.S. Baily Road, District Patna.

5. General Manager cum Chief Engineer, Singhbhum Area ,

Electricity Board, Bistupur, Jamshedpur

6. The Electrical Superintending Engineer, Electric Supply

Circle Jamshedpur.

7. The Electrical Executive Engineer (Commercial &

Revenue), office of the Electrical Superintending Engineer,

Electric Supply Circle, Jamshedpur. .....Respondents

W ith

L.P.A. No. 597 of 2015

20

……..

M/S. BIHAR EXTRUSIONS LTD, A Company incorporated

under the provisions of Companies Act, 1956, having its

factory at Industrial area, Gamharia, District Singhbhum

(East) through its authorized signatory Sri Rahul Tantia,

son of Ishwari Prasad Tantia, resident of 96, Narkeldanga

Main Road, P.O.- Kankurgachi and P.S. Phoolbagan,

District- West Bengal, Kolkata. ..… Appellant

Versus

1.Earlier Known as “ Bihar State Electricity Board having it

office at Baily Road, Patna through its Chairman” in the

matter; M/s Bihar Extrusions Ltd. having its factory at

Industrial Area, Gambharia, District-Singhbhum (East),

through its authorized Signatory, Now known as,

JHARKHAND URJA VIKAS NIGAM LIMITED" (Earlier known

as) " Jharkhand State Electricity Board having it office at

Engineers Bhawan, H.E.C Dhurwa, Ranchi, through its

Chairman, Project Bhawan, H.E.C., P.O. and P.S. Dhurwa,

District-Ranchi.

2. Bihar State Electricity Board, a body constituted under

the Indian Electricity Act, 1910, through its Chairman

having its Head Office at Bailey Road, P.O. G.P.O, P.S.-

Kotwali Patna.

3. The Secretary Bihar State Electricity Board, having its

Head Office at Bailey Road, P.O. G.P.O, P.S. Kotwali Patna,

4. The State of Bihar through its Secretary (Energy) Energy

Department, Government of Bihar 8 DarogaRai Path Patna-

800001, Bihar, P.O.-GPO and P.S. Kotwali.

5.The Chief Engineer (Commercial and T.A.), Bihar State

Electricity Board, Bailey Road, P.O. G.P.O, P.S.- Kotwali

Patna.

6. The Financial Controller (Rev.), Bihar State Electricity

Board, Bailey Road, P.O. G.P.O, P.S. Kotwali Patna.

7. General Manager cum Chief Engineer, Jamshedpur Area

Electricity Board, Bistupur, PO & P.S. Bistupur, Town

Jamshedpur

8. The Electrical Executive Engineer (Commercial and

Revenue) Office of the Electrical Superintending Engineer,

Electric Supply Circle, Vikash Bhawan, Adityapur, P.O. and

P.S. Adityapur, District-Seraikella Kharsawan, as per CC,

21

the Electrical Sup./Executive Engineer (Commercial and

Rev), BSEB, Electric Supply Circle Jamshedpur.

.....Respondents

With

L.P.A. No. 599 of 2015

……..

M/S TATA STEEL LIMITED (previously known as M/S. Tata

Iron & Steel Co. Ltd.,) a Company incorporated under the

Companies Act, 1956, having its Registered Office at 24,

Homi Mody Street, Fort, Bombay and works at Jamshedpur

in the State of Jharkhand through its Legal Head, Mrs

Meena Lall wife Sri Behari Lall and Chief Legal, (Corporate

Services), Tata Steel limited, Jamshedpur, resident of R/o

B-228, G. K. -1 P.O and P.S-G.K-1, New- Delhi - 49.

..… Appellant

Versus

1. Bihar State Electricity Board, a body constituted under

the Indian Electricity Act, 1910, having its Head Office at

Bailey Road, Patna, P.O,G.P.O., P.S. Kotwali, District Patna,

through its Chairman having his office at Bailey Road,

Patna, P.O. Kotwall, District - Patna. G.P.O., P.S.Kotwali,

District-Patna.

2. The Chief Engineer (Commercial and T.A.), Bihar State

Electricity Board, having its Head Office at Bailey Road,

Patna, P.O. G.P.O., P.S. Kotwali, District Patna.

3. The Financial Controller (Rev.), Bihar State Electricity

Board, having its Head Office at Bailey Road, Patna, P.O.

G.P.O., P.S. - Kotwali, District - Patna.

4. General Manager- cum- Chief Engineer, Singhbhum Area

Electricity Board, P.O AND P.S Bistupur, Jamshedpur

District Singhbhum (east) PIN 831001 (previously under

General Manager cum Chief Engineer, South Bihar and

Chhotanagpur Area Electricity Board, Kusai Colony,

Doranda, Ranchi).

5. The Electrical Superintending Engineer, Jamshedpur

Electric Circle, Jharkhand Urja Vikash Nigam Limited

(Earlier Bihar State Electricity Board) having its office at

Vikash Bhawan, Adityapur, P.O, and P.S. Adityapur,

Jamshedpur District - Singhbhum (East)

6. The Electrical Executive Engineer (Commercial and

22

Revenue), Electric Supply Sub-Division, Jharkhand Urja

Vikash Nigam Limited (Earlier Bihar State Electricity Board)

Vikash Bhawan, Adityapur, P.O. and P.S. - Adityapur,

District - Singhbhum (East).

7.JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD

which is successor of erstwhile Bihar State Electricity

Board), having its office at Engineers Bhawan, HEC,

Dhurwa, Ranchi through its Chairman, Project Bhawan,

H.E.C., P.O. & P.S. Dhurwa, District - Ranchi.

.....Respondents

With

L.P.A. No. 610 of 2015

……..

MECON LIMITED. (formerly known as Metallurgical &

Engineering Consultants (India) Ltd.), a Company

incorporated under the Companies Act, 1956 and a

Government of India Undertaking having its Registered

Office at Doranda, Ranchi through its DGM 1/c TA&CD, Sri

Vijay Khanna, son of Late G.D.Khanna, resident of Flat no.

204, Ishwar Enclave, P.P Compound, Ranchi -834001, P. O.

Hindpiri and P.S. Hindpiri, Ranchi, Jharkhand.

..… Appellant

Versus

1. JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman cum Managing Director,

Engineers' Bhawan, H.E.C., P.O. & P.S. Dhurwa, District -

Ranchi.

2. Bihar State Electricity Board, a body constituted under

Indian Electricity Act, 1910, through its Chairman, having

its Head Office at Bailey Road, Patna, P.O. G.P.O., P.S.

District - Patna

3. The Chief Engineer (Commercial & T.A.), Bihar State

Electricity Board, Bailey Road, having its Head Office at

Bailey Road, Patna, P.O. G.P.O., P.S. Kotwali, District -

Patna.

4.The Financial Controller (Rev.), Bihar State Electricity

Board, having its Head Office at Bailey Road, Patna, P.O.

23

G.P.O., P.S. Kotwali, District Patna.

5. General Manager cum Chief Engineer, JHARKHAND

URJA VIKAS NIGAM LIMITED, Kusai colony Doranda,

Ranchi. P.O and P.S- Doranda, District- Ranchi.

6. The Electrical Superintending Engineer, Ranchi

Electrical Circle 'Kusai colony Doranda, Ranchi. P.O and

P.S- Doranda, District- Ranchi.

7. The Electrical Executive Engineer (Commercial and

Revenue), JUVNL, Electrical Supply Circle, P.O. and P.S. -

Dhanbad, District - Dhanbad. .....Respondents

With

L.P.A. No. 613 of 2015

……..

M/s. Gajanan Minerals Private Limited, a Company

incorporated under the provisions of Indian Companies Act,

1956 having its Works and Office at Plot No.B047 and B-

29,1st Phase, Industrial Area, Adityapur, P.O. & P.S.

Adityapur, District-SeraikellaKharsawan through its

Director Kaushal Singhal, Son of Sri Kailash Chandra

Singhal resident of B-47, 1st Phase, Industrial Area,

Adityapur, P.O. & P. S. Adityapur, District-Seraikella

Kharsawan. ..… Appellant

Versus

1. Jharkhand Bijli Vitran Nigam Limited, having its Head

Office at Engineering Bhawan, Dhurwa, P.O. and P. S.

Dhurwa, District-Ranchi through its Managing Director.

2. Bihar State Electricity Board, having its office at Vidhut

Bhawan, Patna, through its Chairman, P.O. G.P.O., P.S.

Kotwali, Patna, District-Patna.

3. The Finance Controller (Revenue), Jharkhand State

Electricity Board, Kusai Colony, P.O. and P.S. Doranda,

District-Ranchi.

4. General Manager cum Chief Engineer, Jharkhand Bijli

Vitran Nigam Limited, Jamshedpur Division, Co-operative

Building, P.O. and P.S. Bistupur, Town-Jamshedpur,

District-Singhbhum East.

5. Electrical Executive Engineer (Commercial & Revenue),

Electric Supply Circle, Jharkhand Bijali Vitran Nigam Ltd.

24

Adityapur, P.O. and P.S. Adityapur, District-Seraikella,

Kharsawan.

6. Chief Engineer (Commercial), Bihar State Electricity

Board, Fraser Road, P.O., G.P.O, P.s. Kotwali, District-

Patna. .....Respondents

With

L.P.A. No. 616 of 2015

……..

M/S. B.M.C. Metal Cast Ltd., A Company incorporated

under the provisions of Companies Act, 1956, having its

factory at A-1819, 2nd Phase, Industrial Area, Adityapur,

P.O. and P.S. Adityapur, District SeraikellaKharsawan-

832109, through its Executive Director Shri Deepak

Dokania, Son of Shri Mahaveer Ram, Resident of - 7,

Circuit House Area (North West), Sonari, P.O. and P.S.

Sonari Town Jamshedpur, District - Singhbhum East.

..… Appellant

Versus

1.JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD).

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman, Project Bhawan, H.E.C., P.O.

& P.S. Dhurwa, District - Ranchi.

2. Bihar State Electricity Board, a body constituted under

the Indian Electricity Act, 1910, through its Chairman

having its Head Office at Bailey Road, P.O.- G.P.O, P.S.-

Kotwali Patna,.

3. The Secretary, Bihar State Electricity Board, having its

Head Office at Bailey Road, P.O.- G.P.O, P.S.-

KotwaliPatna,.

4. General Manager cum Chief Engineer, Jamshedpur Area

Electricity Board, Bistupur, P.O & P.S.- Bistupur, Town

Jamshedpur

5. The Electrical Executive Engineer (Commercial and

Revenue), Office of the Electrical Superintending Engineer,

Electric Supply Circle, Vikash Bhawan, Adityapur, P.O. and

P.S. Adityapur, District –Seraikella Kharsawan.

.....Respondents

With

25

L.P.A. No. 43 of 2016

……..

M/S. Tetuliya Coke Plant Pvt. Ltd., A Company

incorporated under the provisions of Companies Act, 1956,

having its factory at Govindpur, P.O. and P.S. - Govindpur,

District - Dhanbad, Jharkhand through one of its Directors

Shri ShaileshAgarwala, son of Late Birendra Kumar

Agarwala, Resident of - SukhiNiwas, P.O. and P.S. -

Govindpur, District - Dhanbad, Jharkhand.

..… Appellant

Versus

1.JHARKHAND URJA VIKAS NIGAM LIMITED (Earlier

known as JHARKHAND STATE ELECTRICITY BOARD),

having its office at Engineers Bhawan, HEC, Dhurwa,

Ranchi through its Chairman, Project Bhawan, H.E.C., P.O.

& P.S. Dhurwa, District - Ranchi.

2.Bihar State Electricity Board, a body constituted under

the Indian Electricity Act, 1910, through its Chairman

having its Head Office at Bailey Road, P.O.- G.P.O, P.S.-

Kotwali Patna.

3. The Secretary, Bihar State Electricity Board, having its

Head Office at Bailey Road, P.O.- G.P.O, P.S.- Kotwali

Patna.

4.General Manager cum Chief Engineer, Dhanbad Area

Electricity Board, Combined Building, P.O & P.S.-

Dhanbad, Town Dhanbad.

5. The Electrical Executive Engineer (Commercial and

Revenue), Electrical Supply Circle, Dhanbad, Combined

Building, P.O & P.S.-Dhanbad, Town - Dhanbad.

.....Respondents

---------

CORAM: HON’BLE MR. JUSTICE RONGONMUKHOPADHYAY

HON’BLE MR. JUSTICE DEEPAK ROSHAN

---------

For the Appellants : Mr. Navniti Prasad Singh, Sr. Adv.

Mr. M.S.Mittal, Sr. Adv.

Mr. Indrajit Sinha, Adv.

Mr. Salona Mittal, Adv.

[in L.P.A. Nos. 305/15, 431/15, 444/15, 448/15,

449/15, 454/15, 463/15, 481/15, 482/15,

483/15, 484/15, 508/15, 542/15, 597/15,

26

610/15, 616/15, & 63/16]

Mr. BirenPoddar, Sr. Adv.

Mr. PiyushPoddar, Adv

(in LPA No. 465/2015, 581/2015 & 585/20150

M/S. Shankar Lal Agarwal, Adv.

(In LPA No. 410/2015, 470/2015, 498/ 2015,

498/2015, 505/2015 & 613/2015

Mr. Dhananjay Kr. Pathak, Adv.

(In LPA No. 508 of 2015)

Mr. M.B.Lal, Advocate

[ in L.P.A Nos. 444/15, 448/15, 449/15, 454/15 &

463/15]

Ms. Monika Kumari

[ in L.P.A. No. 508/15]

For the JUVNL/JSEB :Mr. Shri Venkatesh, Advocate

Mr. Rahul Saboo, G.P.II

For the JUVNL : Mr. Manish Kumar, Adv.

For the BSEB : Mr. Manoj Tandon, Adv

---------

CAV on:-21.06.2024 Pronounced on:-31/08/2024

Per Deepak Roshan J.

Heard learned counsel for the parties.

2. The challenge in these batch of appeals is to the

common judgment passed by the writ court in batch of writ

petitions by Order dated 08.05.2015; wherein the Writ

Petition filed by the respective petitioner-consumer was

dismissed.

3. The brief fact of the case is that the erstwhile Bihar

State Electricity Board (hereinafter to be referred as BSEB)

had notified a new power tariff dated 21.06.1993 which was

made effective from 01.07.1993.

In the said tariff clause 16.10deals with operational

charges-

i. “Operational charges” contains two elements i.e.

“other operational charge” and “fuel surcharge”.

ii. Other operational charge was struck down by the

Hon’ble High Court in the case of Bihar 440 Vidyut

Upbhokta Sangh Vs. B.S.E.B. (1994) 2 PLJR 103 and

affirmed by the Hon’ble Supreme Court as reported

in (1997) 11 SCC 380).

27

iii. Clause 16.10.1 specifies the categories of the

consumers which were required to pay the

operational surcharge at the rate to be determined

every year in accordance with the formula.

iv. Clause 16.10.3 of the tariff specifies of the formula

for calculation in increase in the rate of fuel

surcharge.

v. Clause 17 of the tariff specifies that the entire rate of

fuel surcharge amounting to 32 paise per unit had

been merged with the tariff rates.

4. From time- to-time various circulars were issued by the

Board fixing various rates of fuel surcharge. Finally, for the

consumers this final rate of fuel surcharge was raised much

after the actual accounting period, resulting in the fact that

after completion of books of accounts of the year, huge

liability accrued upon the consumers which could not be

recovered by them from their customers resulting in huge

losses and ultimate closure of various industries.

5. A batch of writ petitions were filed before the Patna

High Court, with the lead case being that of M/s Pulak

Enterprises being CWJC No. 5542 of 1999.The Patna High

Court delivered its judgment dated 26.06.2000 (Ann – 1). In

the said judgment the High Court held that –

(i) “Purchase of electricity from TVNL cannot be made a

component of H-3”; and as such purchase of

electricity from TVNL has to be deleted as competent

of H-3 (Refer Paras 34 & 35).

(ii) There could not be two rates of supply of electricity

by DVC, i.e., Supply by DVC to TISCO and supply by

DVC to BSEB, and as such for the component of D-3

there can only be one rate as the source is one. (Refer

Para-36).

(iii) The High Court also dealt with the issue of Rs. 100

Crore paid by the Coal Companies to the Board, but

no specific direction was issued on that (Refer para -

40).

6. Pursuant to said Judgment of Patna High Court, both

the BSEB as well as consumers approached the Supreme

28

Court of India. BSEB challenged findings of the Division

Bench of Patna High Court so far as TVNL issue and deemed

supply by DVC (and consequently the dual rate for D3) are

concerned. The consumers filed their Appeals on the issue of

Rs. 100 Crores, wherein though the issue was referred in the

judgment, but no specific direction was given.

Since, no stay was granted by the Hon’ble Apex Court

and in order to collect fuel surcharge, the BSEB, pursuant to

direction of the Patna High Court in Pulak Enterprises case,

issued various Circulars of fuel surcharge which were claimed

to be in gross contravention of the Patna High Court

Judgment and these circulars were challenged in the batch of

writ petitions by the consumers, being CWJC No. 2758 of

2000(R) and analogous cases. It is the order passed in these

batch of cases which has been impugned in the present

Appeals.

In the meantime, all the appeals were disposed of by

the Hon’ble Apex Court vide its judgment dated 15.4.2009.

7. As a matter of fact, the BSEB was getting

reimbursement of increased cost of power from the certain

categories of consumers on quarterly / yearly basis since

long. In the year 1999 when they issued circulars for fuel

surcharge, consumers challenged the validity of calculation

before the Patna High Court bench, later on Jharkhand High

Court and Hon'ble Supreme Court of India as well.

8. Present issue is also related to the method of

calculation of fuel surcharge which was calculated against the

order of Patna High Court as well as Supreme Court of India,

although BSEB/JSEB claiming that they have calculated the

rate of fuel surcharge in line with the order of High Court and

Supreme Court of India. This is the reason, so many

petitioners challenged the calculation by filing various writ

petitions and later on Appeal before this Court. With consent

of the parties; leading case has been considered for hearing

29

purpose is LPA No. 305 of 2015which has been filed by Usha

Martin.

9. In this LPA, Usha Martin challenged the validity of the

bills amounting to Rs.107.73 crores (For principal amount

Rs.23.85 crores and DPS Rs.83.88 crores). Hon'ble Supreme

Court of India stayed the DPS of Rs.83.88 crores and directed

Usha Martin to pay Principal amount of Rs.23.85 crores

which Usha Martin has paid.

10. In all these LPAs, what can be culled out from the

argument by the learned senior counsel / counsel of the

appellants is that largely on five issues plus on charging of

DPS has affected the rate of fuel surcharge drastically for the

year 1996-97 to 2000-01 which was valid up to 31.03.2003.

The same are discussed hereunder under:

(i) TVNL issue: TVNL came into existence in the year 1996-97

whereas base year for calculation of fuel surcharge is 1991-

92, as such, Division bench of Patna High Court and Hon’ble

Supreme Court of India both has directed Electricity Board

not to consider the increase in cost on account of TVNL as

TVNL was not existence in the year 1991-92 i.e. base year.

Year As per

calculation of

the Board

(paise KWH)

As per the Consumers

Calculation should have been as

per UML (Paise KWH)

1996-97

1997-98

1998-99

1999-2000

2000-01 to

31.03.2003

86.25

137.20

164.83

204.4

244.01

79.58

115.76

140.54

186.36

Data not available for

calculation.

II) Providing credit of Rs.100 crores while calculating

the rate of fuel surcharge on account of credit receivable by

BSEB from CCL. A/c. due to the inferior quality of coal supply

in the year 1996-97.It has been submitted that after hearing

the argument of Board, Patna High Court as well as Hon'ble

30

Apex Court has directed to consider credit of Rs.100 crores in

the year 1998-99 instead of 1997-98.

iii) Higher amount of increased cost of fuel considered

in Calculation of Fuel Surcharge Rate in the matter of

DVC.

(a) Deemed supply to TISCO: TISCO is in outside

command area of DVC, as such, to avail DVC Power, they

have entered into a tripartite agreement with BSEB/ DVC

wherein it was decided that DVC will bill to TISCO at BSEB

Rate but will charge to BSEB at DVC Rate. Differential

amount will be adjusted by DVC against the power supply to

BSEB. It has been submitted that while calculating the fuel

surcharge rate, Board considered increase in DVC charge at

two rates i.e. one for direct supply to DVC and another one to

BSEB. Hon'ble Courts passed order that there cannot be two

rates for the source being one; as such, directed BSEB to

charge the rate at which DVC supplied the power to BSEB.

(b) In addition, DVC tariff from the year 1991-92 to

1996-97 increased every year but BSEB has considered this

increase only from 01.05.1997. While making the calculation

of Fuel Surcharge, BSEB considered increased rate of DVC

tariff.

iv) Charging of fuel surcharge on unconsumed units of

LTIS, CS 2 and CS 3 categories of consumers who are

entitled to pay for minimum guarantee unit.

It has been submitted that while issuing the fuel

surcharge circular, BSEB has considered only actual

consumed units by these categories of consumers; whereas

BSEB has charged fuel surcharge on unconsumed units also.

The issue has been raised before the court that these

unconsumed units are also being considered for arriving at

the rate of fuel surcharge as Board has already collected the

money from these categories of consumers.

31

(v) Recalculation of fuel surcharge after the bifurcation

of Jharkhand State Electricity Board (JSEB) from Bihar

State Electricity Board (BSEB) with effect from

01.04.2001.

This issue was raised for the first time before the writ

court stating therein that JSEB has bifurcated from BSEB

and have started functioning independently of their own.

Ratio of power consumption is different after the bifurcation.

As per lump sum calculation it was observed that earlier

almost 30-35% power was being consumed by bifurcated

BSEB and 65% to 70% power was being used by the

consumer of JSEB. In addition, major industrial consumers

i.e. Fuel Surcharge payable consumers are in the area of

JSEB, as such, recalculation of fuel surcharge rate from

01.04.2001 to 31.12.2003 is necessary based on the actual

figure of JSEB keeping the formula intact.

(vi) DPS:

(a) In this regard, it has been submitted that BSEB has

issued a circular reducing therein the rate of fuel surcharge

by 6.04 paise/kwh considering only Rs.23.22 crores in

calculation of fuel surcharge for the year 1998-99; whereas

they were required to consider Rs.100 crores; if considered

Rs.100 crores, expected reduction in the rate of fuel

surcharge will be about 26 paise per/kwh.It has been

contended that the Board has not given effect of this circular

while issuing the fuel surcharge bill as such, they will have to

issue new bills. Once the new bills are issued, DPS has to go.

b) On this issue, it has been further contended by the

appellants that there are various orders of various High

Courts and Hon'ble Supreme Court of India ordering therein

that once the bills are revised; DPS has to be set aside. In the

present case Board has already issued revised circular for the

year 1998-99 reducing therein the rate of fuel surcharge by

6.04 paise/KWH only considering Rs.23.22 crores in

32

calculation, with regards to inferior quality of coal. Effect of

this circular was not given by the Board in the fuel surcharge

bills which are under challenge.

11. At the outset, Mr. Navniti Prasad Singh, senior

Counsel and Mr. Indrajit Sinha, Advocate appearing for

respective appellants have submitted the following formula in

order to appreciate the issue of fuel surcharge involved in this

case. He referred the judgment rendered in the case of

Rohtas Industries Ltd. v. Bihar SEB, 1984 Supp SCC 161,

and contended that the Hon’ble Apex Court has held that

“Though the nomenclature given to the levy is “fuel surcharge”

it is really a surcharge levied to meet the increased cost of

generation and purchase of electricity”. In this background,

the formula of Fuel Surcharge in the 1993 Tariff is

reproduced herein below

33

12. From the impugned order it transpires that during the

course of hearing, the writ Court culled out five issues which

were for consideration before the Court. The same are as

follows:[Refer: Para 17].

I. Whether the deletion of TVNL component from H1 & H2

along with H3 is against the mandates of the Hon’ble Patna

High Court in M/s. Pulak Enterprises case and if so, on that

ground the impugned Circulars are liable to be quashed?

II. Whether while recalculating the rates of fuel surcharge, as

per the decision of M/s Pulak Enterprises case, it was

imperative for the Board to exclude the power supply by the

DVC to the TISCO from the arena of consultation?

III. Whether the Board can be directed to recalculate the rates of

fuel surcharge after taking into account the unconsumed

units of CS and LT consumers on which the Board levied

fuel surcharge?

IV. Whether the Board could be directed to recalculate the rates

of fuel surcharge after adjusting Rs. 100 crores receivable by

the Boards from the Coal Companies?

V. Whether after the creation of the State of Jharkhand, the

formula prescribed for calculation of the rates of fuel

surcharge is required to be reformulated and consequently

rates be reworked out ?

13. Learned senior counsel representing the

appellants had advanced his argument on the issues involved

in this batch of appeals; which are summarized herein below:

 For the purpose of calculation of fuel surcharge in

terms of the 1993 tariff, the base year taken by the B.S.E.B.

to calculate the proportionate increase in rate of purchase

from external sources, was 1991-92.

 Accordingly, since TVNL came into existence only in

1996 – 97, there could have been no increase from the base

year of 1991-92 as TVNL did not exist during the base year.

 The Patna High Court in Pulak Enterprises has dealt

with the Issue No.1 at para -34 &Para-35, Para 43and para

44.

 The Division Bench of Patna High Court clearly stated

that that “In my view, on the admitted facts, it is not possible

34

to allow the Board to include purchase of electricity as a

component of H3 without suitably amending the formula in

accordance with law.”

 Accordingly, the Division Bench directed the Board to

re-work out the rate of fuel surcharge in the year 1996-97

after deleting the purchase of electricity from TVNL as

component of H3.

 Though the Patna High Court directed the Board to

delete TVNL from H3, it is discernible from a reading of the

entire finding on this issue was that purchase from TVNL was

not to be taken into consideration altogether, i.e., from the

numerator side of the formula – both H1 and H3. This is

because if the TVNL component in H3 is taken as ‘0’, then the

TVNL component in ‘H1’ would also become ‘0’. Thus ,

purchases from TVNL would be excluded altogether.

 This is further evident from the fact that the counsel

for BSEB had specifically contended before the Patna High

Court that if TVNL is not to be included in H3, then

consequence will that units purchased from TVNL would have

to be kept out. However, the Court negated the same by

saying that it will create a different base year and that

purchase from TVNL cannot be included unless the BSEB

changes it formula, which it has admittedly not done.

 When the matter went to Hon’ble Supreme Court, the

Hon’ble Court in its judgment dealt with this issue at para 61

to 62 and confirmed the findings of Patna High Court.

 It is also important to mention that H1 contains

purchase from other sources ‘respectively’ meaning thereby

that H1 also includes other sources apart from TVNL. Same is

the position for H3. Thus, H1 and H3 are not just TVNL.

 He relied upon the judgments of Hon’ble Apex Court in

Canara Bank v. Debasis Das , (2003) 4 SCC 557, wherein it

has been held that “The expression “respectively” means

35

belonging or relating separately to each of several people. It is

a word of severance.”

 Therefore, it has been contended by the Sr. Counsel

that essentially the BSEB had to take from H3, the TVNL

component as ‘0’ and multiply it with the TVNL component in

H1, which would result in excluding the purchase of

electricity from TVNL altogether, as was the mandate of Pulak

Enterprises by the Patna High Court and that of the Hon’ble

Supreme Court. An illustration of the following formula has

been tendered during the course of hearing; for brevity, the

same is extracted herein below:

Illustration

Other Sources (H): For eg., NTPC and TVNL

Units Purchased

Purchase Rate

Originally

Others 1000 Rs. 0.50

TVNL 500 Rs. 0.10

Thus, increased cost = (1000 x 0.5) + (500 x 0.10)

= 500 + 50

= 550

I) As per HC direction

Others 1000 Rs. 0.50

TVNL 500 Rs. 0.00

Thus, increased cost = (1000 x 0.5) + (500 x 0.0)

= 500 + 0

= 500

II) Mischief by BSEB

Others 1000 Rs. 0.50

TVNL 500 -

Thus, increased cost = (1000 + 500) x 0.50

= 1500 x 0.50

= 750

 It has been further submitted that the BSEB in

purported compliance of the directions in Pulak Enterprises

however, excluded TVNL from H1 and H2 also. They did this,

in order to show that deleting all three components from ‘H’,

would result in lower rate of Fuel Surcharge. Annexure-L to

the additional counter affidavit dated 15.2.2001 was relied in

this regard.

36

 However, reliance on the said annexure is a mere

eyewash. It is evident that for the year 1996-1997, the total

units purchased from other sources was 737.82 Mkwh (H1)

and the average rate of purchase was 60.57 (H3). Thus, the

total cost of increase came to Rs. 4468.98 Lakhs (H1 x H3).

As per the direction of High Court, purchases from TVNL were

to be excluded altogether; however, in the column showing

compliance of the High Court, a higher figure has been

shown, i.e., Rs. 4872.56 Lakhs which cannot be possible if

purchase from TVNL is altogether excluded. This has arisen

due to the fact that BSEB has not reduced units purchased

from TVNL from H1, which it ought to have done.

 Furthermore, it can be seen that in 1996-97, the BSEB

has tried to show that by deleting H1, H2, and H3, the rate

had come to 86.25 paise; whereas by deleting only H3, the

rate was 88.06 paise. However, in the subsequent year, i.e.,

1997-98, by deleting all three components, the rate comes to

137.20 paise; whereas by only deleting H3, the rate comes to

131.11paise. Thus, it was clear that the BSEB misinterpreted

the judgment and/or was flouting the judgment of the Patna

High Court in Pulak Enterprises.

 However, in the impugned judgment, the Ld. Single

Judge while dealing with this issue at para 18 to 26 has failed

to apply the findings of the Patna High Court and the

Supreme Court Judgments and has held at para 26 of the

judgment that deletion of TVNL component from H1and H2 is

against the decision of the Division Bench Judgment of Patna

High Court in Pulak Enterprises; however, by the aforesaid

action of the Board, rate of fuel surcharge had not increased;

rather the same has decreased. Therefore, the Court did not

interfere with the said issue.

 It has been contended that the writ Court was duty

bound to follow the Judgment of the Hon’ble Supreme Court.

37

In fact, reliance on annexure – L by the Ld. Single Judge was

also totally misplaced as shown hereinabove.

 Further, the finding that if H3 is taken as 0, then

entire component on the numerator side will become 0 and

will result in excluding other sources apart from TVNL also,

was patently incorrect. As stated above, H1 and H3 contains

multiple other sources ‘respectively’. TVNL can certainly be

severed from H1 and H3 and excluded from the numerator

side. It was never the contention of the petitioners that all

other sources will also have to be excluded.

 The Judgment of Patna High Court and the Supreme

Court never gave any permission to the Board to delete H2 in

entirety; as the unit sold from energy purchased from TVNL is

one of the sources of H2 and particularly because since the

units purchased from TVNL were being sold by the Board. By

deletion of sold units from denominator, obviously the rate of

fuel surcharge would increase. Therefore, the Impugned

Judgment so far TVNL issue is concerned is absolutely

erroneous and is liable to be set aside.

 No party, defying the order of a High Court can take

recourse to the fact that substantial injustice has not been

done. The High Court has the power to reach injustice

wherever it is found (Refer:U.P. State Sugar Corpn .

Ltd. v. Kamal Swaroop Tondon , (2008) 2 SCC 41 – Para

35) and it cannot on the basis of certain erroneous

calculations refuse to enforce the directions of the previous

Division Bench or of the Hon’ble Supreme Court. Reference in

this regard is also made to the judgment of the Hon’ble

Supreme Court in State of Bihar v. Kalika Kuer, (2003) 5

SCC 448 wherein it was held that “The earlier judgment may

seem to be not correct yet it will have the binding effect on the

later Bench of coordinate jurisdiction”. Relying upon the above,

Ld. Sr. Counsel contended that on this issue, the order

passed by the writ Court requires interference.

38

14. In respect of TVNL issue, the Respondents primarily

submitted the following:

(I) On a holistic and complete reading of the Judgment

passed in Pulak Enterprises; it is evident that the entire

component of TVNL had to be excluded all together, meaning

thereby that even from H2, the TVNL component had to be

excluded.

(II) Reliance was placed on Annexure-L to the Counter

Affidavit filed in the Writ proceedings. It was submitted that

by excluding all three components, a lower rate of fuel

surcharge was being computed and hence deletion of TVNL

from H1, H2 & H3 would inure to the benefit of the

consumers.

(III) Reference was made to para 19 of the Impugned Order

to submit that if the Petitioner’s argument is accepted, then

the entire component of H1 i.e., purchases from other sources

would become zero.

15. Having heard learned counsel for the rival parties and

after going through the documents available before us it

appears that a complete reading of the Judgment in Pulak

Enterprises would make it evident that the Patna High Court

only directed that purchases from TVNL ought to be excluded

i.e. only on the numerator side of the formula.

There is no direction that the TVNL component from

H2 (denominator / units sold) also has to be deleted. As a

matter of fact, para 18 of the Impugned Order records that

deletion from H2 is against the Judgment of Pulak

Enterprises. Therefore, there can be no quarrel that deletion

of TVNL component from H2 was not contemplated by the

Judgment in Pulak Enterprises.

Reference in this regard is also made to the Judgment

of the Hon’ble Supreme Court in Ashwani Kumar Singh v.

U.P. Public Service Commission, reported in (2003) 11 SCC

584;whereinit was held that –

39

“10. …Observations of courts are not to be read as Euclid's

theorems nor as provisions of the statute. These observations

must be read in the context in which they appear. Judgments of

courts are not to be construed as statutes. To interpret words,

phrases and provisions of a statute, it may become necessary for

Judges to embark upon lengthy discussions, but the discussion

is meant to explain and not to define. Judges interpret statutes,

they do not interpret judgments. They interpret words of statutes;

their words are not to be interpreted as statutes.”

Therefore, the question of deducing something from a

judgment which is not expressly stated therein does not arise.

Moreover, such an argument made by the Respondents is

clearly oblivious to the formula of fuel surcharge; more

particularly that of H2. H2 has been defined to mean units

sold from purchases made from other sources on which fuel

surcharge is leviable.

Therefore, the units sold by which fuel surcharge

leviable was had to be included in H2 i.e. on the denominator

side. There is no dispute regarding the fact that units

purchased from TVNL were sold by the Board and fuel

surcharge was collected thereon. Therefore, TVNL cannot be

excluded from H2 by any reason whatsoever.

As far as reliance on Annexure-L is concerned; the

same can also not be countenanced for the following reasons:

(a) Firstly, while demonstrating compliance with the High

Court Order, the Board has not deducted TVNL

component from H1. This is contrary to the dictum of

Pulak Enterprises, which required the Board to

exclude purchases from TVNL. If TVNL component in

H3 is taken as zero and multiplied by the TVNL

component in H1, it would result in excluding

purchases from TVNL all together i.e. on the

numerator side.

(b) Even if it is assumed that calculation by the Board

with respect to compliance of the High Court Order

was correct, the benefit of deleting TVNL from H1, H2

40

& H3 was available only in 1996-97. However, a

reference to the working for the year 1997-98 would

show that deleting all three components would have

resulted in a higher rate. Therefore, the mischief

perpetrated by the Board was that it only showed

figures of one year.

Reliance on para 19 of the Impugned Judgment

was also inapposite. The Petitioner’s argument was

never that the entire component of H3 should be zero.

H3 contains of many sources and only TVNL

thereunder would have become zero. The remaining

component would still be there. H1 and H3 are not

just TVNL and only excluding TVNL component woul d

not result in making H1 as zero.

16. For issue No. 2 which relates to DVC; Ld. Sr.

Counsel contended that it relates to taking into consideration,

the sale of supply by DVC to Tata Steel and thereby taking

two rates of purchase i.e., one to BSEB by DVC and another

to Tata Steel by DVC was not permissible. However, the issue

has been erroneously framed by Ld. Single Judge in the

Impugned Judgment. It was never the contention of the

Petitioner that “deemed supply” was to be “excluded”. He

advanced following argument:

 DVC was selling electricity to Tata Steel, which was not

in its command area and a Tripartite Agreement had

been entered among DVC, Tata Steel and BSEB

allowing sale of electricity by DVC to Tata Steel, at the

BSEB rate. It was admitted that the BSEB rate was

much higher than that of DVC. The arrangement was

that whatsoever extra that DVC was realising from Tata

Steel, was to be offset from the purchases made by

BSEB from DVC.

41

 For an example, if rate of BSEB was Rs. 1.50 per unit

and the rate of DVC was Rs. 1/- per unit, DVC realised

the charges from Tata Steel @ Rs. 1.50 per unit which

was the rate of JSEB, and difference of rate between

BSEB and DVC i.e. 50 paise per unit was offset /

credited from supplies made from DVC to BSEB.

 However, while making calculation of the formula for

fuel surcharge, both the rates of sale by DVC to Tata

Steel as well as sale by DVC to BSEB was taken, which

the Patna High Court held to be illegal.

 The Division Bench of Patna High Court had dealt with

this issue of dual rate of DVC at para 36,para 37,and

gave findings at para 43 and 44. It was held that source

being one, i.e., DVC, two rates cannot be taken for the

purpose of computing D3.

 The Hon’ble Supreme Court dealt with this issue of

“deemed supply” at para 51 and 521and approved the

Judgment of Patna High Court and Court in para 62

the Supreme Court held that they are in agreement

with conclusion of the High Court and Appeal filed by

the Board was accordingly dismissed.

 However, while issuing the circulars in purported

compliance of the directions in Pulak Enterprises, it was

evident that the BSEB had deliberately misread the

judgment of the Hon’ble Court. The same is evident

from the calculations provide by the Board itself at

Annexure – D to the Counter Affidavit filed on

17.10.2000.

 From the calculation chart it is evident that the BSEB

had taken the average rate for purchase by BSEB from

DVC and TISCO from DVC, which was not in

accordance with the judgment. The BSEB was to take

original rate of DVC and not the weighted average.

There was no such direction.

42

 Another issue was that despite the fact DVC increased

its tariff on a few occasions after 1993, but the BSEB

continued to pay at the tariff prevailing at 1993 to DVC

and as a matter of fact, BSEB started paying at the

current rate of DVC only from 1997-98. The said fact is

also evident from Annexure - H to the additional

counter affidavit filed by the Board on 15.2.2001,

wherein the Board itself has stated that BSEB

“continued to admit the bill of DVC” at the tariff of 1991

“till 30.4.1997”.

 The Ld. Single Judge dealt with this issue at para 27 of

the Impugned Judgment and held that “I find that the

Board had substantially complied the direction given in

M/s. Pulak Enterprises case”.

 In this regard, the directions have to be fully complied

with and not substantially complied. The BSEB was not

allowed to take the weighted average, it had to be the

rate of tariff of DVC as recognized by the BSEB. In fact,

rather than “substantial compliance”, there has been

“no compliance” by BSEB. The requirement of taking

one rate for D3 as recognised by the Board, was a

mandatory direction and not merely directory, thus the

principle of substantial compliance would not apply at

all in the present case.

 In this regard, reference is made to the judgment of

the Hon’ble Supreme Court in CCE v. Hari Chand Shri

Gopal, (2011) 1 SCC 236, wherein it was held that –

32. The doctrine of substantial compliance is a judicial invention,

equitable in nature, designed to avoid hardship in cases where a

party does all that can reasonably be expected of it, but failed or

faulted in some minor or inconsequent aspects which cannot be

described as the “essence” or the “substance” of the requirements.

Like the concept of “reasonableness”, the acceptance or otherwise of

a plea of “substantial compliance” depends upon the facts and

circumstances of each case and the purpose and object to be

achieved and the context of the prerequisites which are essential to

achieve the object and purpose of the rule or the regulation. Such a

defence cannot be pleaded if a clear statutory prerequisite

which effectuates the object and the purpose of the statute

has not been met . Certainly, it means that the Court should

43

determine whether the statute has been followed sufficiently so as to

carry out the intent for which the statute was enacted and not a

mirror image type of strict compliance. Substantial compliance means

“actual compliance in respect to the substance essential to every

reasonable objective of the statute” and the Court should determine

whether the statute has been followed sufficiently so as to carry out

the intent of the statute and accomplish the reasonable objectives for

which it was passed.

 On this ground, Ld. Sr. Counsel contended that this

issue of dual rate of DVC has also to be set aside.

17. With respect to DVC, the Respondents sought to argue

that -

(I) The Petitioner’s argument that sale by DVC to TISCO

was to be excluded all together was against the

decision of Pulak Enterprises, and such argument

could not have been made by the Petitioner.

(II) A single rate has been taken for calculating D3 and as

such there is no deviation from the direction given by

the Hon’ble Patna High Court in Pulak Enterprises

and the Board has not taken an average rate.

18. On this issue, we are of the view that it was never

the argument of the Petitioner-Appellant that deemed

supplies have to be excluded all together. A wrong framing of

question has led to an incorrect answer. Reference in this

regard is made to the judgment of the Hon’ble Supreme Court

in the case of Cholan Roadways Ltd. v. G.

Thirugnanasambandam, reported in(2005) 3 SCC 241

wherein it was held that –

“34. This decision also has no application to the facts of the present

case. In the instant case, the Presiding Officer, Industrial

Tribunal as also the learned Single Judge and the Division

Bench of the High Court misdirected themselves in law insofar

as they failed to pose unto themselves correct questions. It is

now well settled that a quasi-judicial authority must pose unto

itself a correct question so as to arrive at a correct finding of

fact. A wrong question posed leads to a wrong answer.”

As a matter of fact; the Petitioner’s casethroughout was

that a single rate has to be taken for the purchases from DVC

i.e. the rate at which BSEB purchases electricity from DVC.

A specific ground in this regard has been raised as

44

ground ‘XX’ of the LPA. In fact, reading of para 51 to 55 of the

Judgment of the Hon’ble Supreme Court in Pulak Enterprises

(Annexure-11) would show that it was never the case of any of

the consumers that deemed supply to TISCO by DVC was to

be excluded altogether.

Further, the argument that BSEB has taken a single

rate for D3 is also not born out from the Respondents’ own

records. A perusal to Annexure-D of the Counter Affidavit filed

in the Writ proceedings would show that BSEB has taken the

weighted average of sale by DVC to BSEB & TISCO. In doing

so, they have taken into account two rates which was not as

per ratio laid down by Pulak Enterprises and as such was in

direct conflict with the judgment.

Further, the Petitioner had also tendered separately

Annexure-H to the Respondents’ Counter Affidavit to show

that DVC’s increase in tariff had only been recognized by

BSEB from 30.04.1997. Thus, in the year 1996-97 BSEB

ought to have calculated D3 at the rate by which it was

paying DVC irrespective of tariff rate.

Having regards to the above; the finding of the Writ

Court on this issue cannot survive.

19. On the Issue No.III of Rs. 100 Crores, it has been

contended by the appellants that the Board was supposed to

consider credit of Rs. 100 Crores as agreed by the coal

companies against the claim of BSEB towards slippage, short

supply and supply of stone etc., to consider while calculating

the rate of fuel surcharge for the year 1998-99. He further

made following submissions:

 The High Court has at para 40,has dealt with issue of

accounting of Rs. 100 Crores paid by the Coal

Company to the Board. The Division Bench referred to

Affidavit of Board that “as against the total claim of Rs.

356.20 Crores, on account of loss due to grade slippage,

45

short supply of coal, supply of stones etc., the coal

companies have agreed to pay Rs. 100 Crores in full and

final settlement of the claim, but though such decision

was taken on 30.08.1998”, but the actual payment had

not been made till date. The Court further observed “it

was pointed out payment of the amount would be

relevant consideration while calculating the rate of fuel

surcharge for the year 1998-99 and not 1997-98”.

 This issue was confirmed by Hon’ble Supreme Court at

para 63 and 64of its judgment; wherein the Hon’ble

Supreme Court has given specific direction that actuals

will be worked out within 3 months from the date of

Judgment and adjustment of Rs. 100 Crores are to be

worked out accordingly.

 It has been further submitted that against this

direction, the Board filed an I.A. Application before the

Hon’ble Apex Court and the Order of which is annexed

as Annexure-12; it is evident that time completion for

adjustment of Rs.100 Crores has been extended for a

period of four months from the date of the Order i.e.,

25.01.2010.

 The Board thereafter issued an office Order at

Annexure-13,on 22.10.2010, that in terms of the

Judgment passed in Civil Appeal and also Civil I.A., the

Board has decided to make an adjustment in the rate of

fuel surcharge for the F.Y. 1998-99 by incorporating

amount of Rs. 100 Crores receivable from Coal India

Ltd. with regard to coal supplies including quality,

quantity, all types of claims and damages up to

31.03.1997. However, rider was added that such

adjustment was to be made effective as soon as the

amount of Rs. 100 Crores is received, although no such

direction was given by the Hon’ble Supreme Court.

46

 Ld. Sr. Counsel further contended that the Board

further played fraud upon its consumers by issuing one

Office Order dated 01.12.2010, (Annex-14) wherein it

revised the rate of fuel surcharge for the year 1998-99

from which existing rate of fuel surcharge of 164.83

paisa per unit was revised to 158.79 paisa per unit. It

was stated that the Board computed and modified the

rate of fuel surcharge for the F.Y. 1998-99 by making

adjustment of Rs. 100 Crores receivable from CIL and

the said modified rate and unpaid accrued amount

from them to the consumers shall be effective as soon

as Rs. 100 Crores is received from M/s. CIL.

 The calculation was appended to such Office Order and

from the perusal of calculation given as per para (b) is

concerned, it would be evident that the Board had

taken only Rs. 23.22 Crores which is related to “Fuel

Related Loss” in the Chart.At column 4, it has been

stated that amount of Rs. 23.22 Crores only has been

taken which is benefit of fuel related loss to be passed

to the fuel surcharge leviable consumers from Rs. 100

Crores receivable from CIL. This was again contrary to

the direction of the Hon’ble Supreme Court.

 The Board does not actually receive money from the

coal companies; rather a system of adjustment is

followed vis-à-vis coal supplied by the coal companies

and energy supplied by the Board.

The Board follows a mercantile system of

accounting and not cash system. In mercantile system,

since the amount become receivable, it becomes the

part of the accounts and therefore, the stand of the

Board that adjustment shall be given after the amount

is received goes to show the misleading attitude of the

Board.

47

 He contended that it is a fact that Board will never

receive this amount directly from the coal companies

since only adjustment are being made in the books and

differential taken is being made on the basis of balance

outstanding.

 Relying upon the above, Mr. Singh contended that:

(i) There was specific direction of the Supreme Court

giving benefit of Rs. 100 Crores, without waiting for

the money having been received or not.

(ii) Board on its own could not have reduced the benefit

of Rs. 100 Crores for the purpose of adjustment for

only Rs. 23.22 Crores which is against the specific

direction of the Hon’ble Supreme Court.

 Ld. Sr. Counsel pointed out that the Impugned

Judgment was reserved after completion of hearing on

20.04.2015 and the Judgment was pronounced on

08.05.2015, but by then JSEB had already received a

sum of Rs. 100 Crores from CIL (as a successor of and

on behalf of BSEB) which was not disclosed by JSEB

during course of hearing.

 This is evident from the Judgment passed by the Patna

High Court in the case of M/s. Pulak Enterprises

reported in 2015 SCC OnLine Pat 2652 after remand

from the Supreme Court and the said Judgment is

dated 23

rd March 2015, wherein the Patna High Court

took cognizance of an Affidavit filed by BSEB wherein it

was stated “16. It is stated that since Rs. 100 Crores

paid by CCL is lying with JSEB, the Board has filed

Review Application before the Hon’ble Supreme Court for

review of the Order”.

 Therefore, from the above, it is evident that JSEB had

already received Rs. 100 Crores from CIL, even before

the hearing before the Ld. Single Judge had started,

48

but the JSEB did not apprise about the same to the

Court.

 Therefore, immediately Board should be directed to

calculate benefit based on the entire 100 Crores it has

received and if the calculation on the basis of Rs. 23.22

Crores has been worked out from 164.83 per unit to

158.79 per unit, there is difference of about 6 paise,

then if the entire 100 Crores is taken into

consideration, the difference would be at least 25 paise

per unit.

 This benefit has to be given to all the consumers which

will result a downward revision of the bills and

consequently deletion of the entire amount of Delayed

Payment s surcharge.

 The Ld. Single Judge had dealt with this issue in the

Impugned Judgment at para 32 of the Judgment

wherein the Ld. Single Judge has held that because the

Circular has not been challenged in these writ

petitions, therefore the said grievance cannot be

entertained and the Court refused to adjudicate on the

said issue.

 It has been submitted that when the direction of Rs.

100 Crores was given by the Hon’ble Supreme Court,

then it may not have been necessary to challenge to

follow up Order and Appellant can show that the follow-

up Order was in contravention of the Supreme Court

Judgment. As a matter of fact, actions of the

Respondent Board, is absolutely contemptuous.

 In this regard, reliance is placed by him on the

judgment of the Hon’ble Supreme Court in the case of

Shree Bhagwati Steel Rolling Mills v. CCE , reported

in (2016) 3 SCC 643, wherein it was held that –

“29.Rules or regulations which are in the nature of

subordinate legislation which are ultra vires are

bound to be ignored by the courts when the

49

question of their enforcement arises and the

mere fact that there is no specific relief sought

for to strike down or declare them ultra vires

would not stand in the court's way of not

enforcing them. We also feel that since this is a

question of the very jurisdiction to levy interest

and is otherwise covered by a Constitution

Bench decision of this Court, it would be a

travesty of justice if we would not allow Shri

Aggarwal to make this submission”

 A circular which is completely against the law declared

by the Hon’ble Supreme Court would certainly be ultra

vires and hence the Ld. Single Judge ought to have

considered the submissions in this regard. The

judgment of the Hon’ble Supreme Court Shree

Bhagwati Steel Rolling Mills was also specifically

followed by the Hon’bleDelhi High Court in the context

of an office order in Unaided Recognized Private

Schools v. DDA, (2020) 1 HCC (Del) 447.

 Furthermore, the Circular itself stated that the benefit

of 100 Crores will be given when the money is actually

received. Till date, the Board has not given effect to

such circular by reducing the rates. Therefore, when

the Board has not even implemented the Circular, then

there stood no occasion to challenge it.

 He lastly submits that even otherwise, in one of the

cases before the Ld. Single judge, i.e., M/s. Auto Profiles

Ltd., the said circular was categorically challenged.

20. In response to the same, it has been argued by the

Respondents that no relief or direction was given by the

Hon’ble Patna High Court in Pulak Enterprises regarding this

issue. Further, the ground that the Mercantile System of

Accounting is to be used was never argued by the Petitioners.

21. Thus, we see that the Respondents have practically did

not denied any of the contention of the appellants rather;

made simple objection that no relief or direction was given by

50

the Hon’ble Patna High Court in Pulak Enterprises regarding

this issue and the ground of Accountancy has been raised for

the first time.

The above submissions are also incorrect for the

reasons that since no specific direction was given by the

Patna High Court in Pulak Enterprises on this issue; the

consumers had approached the Hon’ble Supreme Court and a

clear direction was given by the Hon’ble Supreme Court in

para 64 of the Judgment that an adjustment of Rs. 100

Crores should be worked out within three months. Therefore,

a direction is certainly there. In fact, the Board had also

published an Office Order dated 22.10.2010 and 01.02.2010

for implementing of the Supreme Court direction.

Further, even assuming that Mercantile System of

Accounting cannot be taken into consideration, still the Board

has actually received Rs. 100 Crores and ought to have given

effect to the Judgment of the Hon’ble Supreme Court and re-

calculate rates of fuel surcharge.

It must also be noted that there was no response by

the Respondent as to the following issues –

(i) Actual receipt of Rs. 100 crores by JSEB.

(ii) Reducing benefit of Rs. 100 Crores to only Rs. 23

Crores (approx.) when there was no direction in this

regard.

22. On the Issue No. IV - Unconsumed units; Ld. Sr.

Counsel made following submissions:

 Board has issued a circular dated 17.09.1999 (Annex-

3,to the writ petition) by which it has been decided to

levy fuel surcharge on unconsumed units on two

categories of consumers namely CS and LT. A

retrospective effect has also been given to this circular.

 By issuance of this circular the respondents have

basically amended the formula of fuel surcharge. Since

the present petitioner was a High-Tension consumer, it

51

had nothing to do with the circular as it dealt with

Commercial Service consumers and Low-Tension

consumers. Nor did the Board place the circular before

the Patna High Court and subsequently there is no

finding or direction for the same either in the High

Court or in the Supreme Court’s judgment. The

Appellant has dealt with this issue in paragraph 90 to

92 of the Appeal.

 After proper effect is given to the circular, the effect

would be lowering of rates of the fuel surcharge

because the denominator consists only of the unit sold

but if fuel surcharge is levied on unconsumed units,

then those units have to be added to the denominator.

 An example would be if Rs. 100 is the cost of generation

and Rs. 100 is the cost of purchase and 100 units are

sold which would be worked out to Rs. 2 per unit, but if

unconsumed units, for example say 100 units, are also

added to the denominator then the cost of fuel

surcharge would work out to Rs. 1. i.e., Rs. 100 (cost of

generation) + Rs. 100 (cost of purchase) = Rs. 200

divided by 200 units sold.

 The formula of fuel surcharge is clear, inasmuch as,

Denominator has to be the same number of units on

which the fuel surcharge is being levied. In the present

case, the Board has not considered the unconsumed

unit while arriving at the denominator, hence the Board

has to work out the rates of fuel surcharge by adding

the unconsumed unit in the denominator.

 This issue was not raised before the Patna High Court

and consequently also not before the Supreme Court,

because at that time the consumers were not aware of

the existence of that circular, since it was an internal

circular. But however, before the Ld. Single Judge, this

issue was raised by the Petitioner / consumers. It was

52

contended that since numerator consisted of the units

purchased and units generated sold to fuel surcharge

paying consumers, therefore, unconsumed units on

which the Board is also levying fuel surcharge from the

category of commercial service consumers and LTIS

(Low Tension Industrial Services) also has to be added

to the denominator. This would result in increasing the

denominator and the moment the denominator

increases, the rate of fuel surcharge will automatically

decrease.

 However, the Ld. Single Judge in the Impugned

judgment has held that the Petitioner at this stage is

prevented from raising issue on the principle of res

judicata and as such the Court was not inclined to

interfere this ground attack and accordingly the same

was rejected.

 The approach of the Ld. Single Judge on this issue was

absolutely erroneous. The Hon’ble Single Judge fallen

into error, as the Petitioner was prevented to raise

ground of effect of unconsumed units on the principle

of res judicata when there was neither any arguments

made on this issue earlier. This issue also deserves to

be decided in favour of the consumers because, it is

directly co-related to the rate of fuel surcharge.

 In this regard, reference is made by the Ld. Sr. Counsel

to the judgment of the Hon’ble Supreme Court in the

case of Rural Litigation and Entitlement Kendra v.

State of U.P., reported in1989 Supp (1) SCC 504,

wherein the Hon’ble Supreme Court has held that –

“16. … At the same time it has to be remembered that every

technicality in the procedural law is not available as a

defence when a matter of grave public importance is

for consideration before the court. Even if it is said

that there was a final order, in a dispute of this type it

would be difficult to entertain the plea of res judicata.

As we have already pointed out when the order of 12-

3-1985, was made, no reference to the Forest

53

(Conservation) Act of 1980 had been done. We are of

the view that leaving the question open for

examination in future would lead to unnecessary

multiplicity of proceedings and would be against the

interests of society. It is meet and proper as also in

the interest of the parties that the entire question is

taken into account at this stage.”

 The issue regarding rate of fuel surcharge is a far

reaching one as it impacts all the industrial (HT and LT)

and Commercial category of consumers and hence

merely on a technical plea of constructive res judicata,

this issue cannot be brushed aside.

23. In response to the aforesaid arguments, the

Respondent made following submissions:

(I) The Petitioner’s apprehension that unconsumed units

had not been taken into account was unfounded as the

rate of fuel surcharge actually took into account the

same.

(II) Secondly, it was argued that this contention of the

Petitioner regarding un-consumed units had never been

raised in the first round of litigation and thus cannot be

raised now.

24. In respect of the above, we are of the considered

opinion that the argument of the Board that un-consumed

units had been taken into account is absolutely incorrect.

Reference is made to Annexure-5 of the LPA in which the

Appellant-Petitioner has annexed calculations at Page-128,

129 and 130 (which are based on the Board’s own figures) to

show that unconsumed units had in fact not taken into

consideration.

Once such statement was made, onus lay on the

Respondents. It is now well settled principles of law that,

when a point which is ostensibly a point of law is required to

be substantiated by facts, the party raising the point, if he is

the writ petitioner, must plead and prove such facts by

54

evidence which must appear from the writ petition and if he is

the respondent, from the counter-affidavit. If the facts are not

pleaded or the evidence in support of such facts is not

annexed to the writ petition or to the counter-affidavit, as the

case may be, the court will not entertain the point. In this

context, it will not be out of place to point out that in this

regard there is a distinction between a pleading under the

Code of Civil Procedure and a writ petition or a counter-

affidavit. While in a pleading, that is, a plaint or a written

statement, the facts and not evidence are required to be

pleaded, in a writ petition or in the counter-affidavit not only

the facts but also the evidence in proof of such facts have to

be pleaded and annexed to it.

In the case at hand, the appellant has given a

calculation at Page-128, 129 and 130; which are based on the

Board’s own figures to show that unconsumed units had in

fact not taken into consideration

Further, the Circular regarding taking into account of

unconsumed units was issued only on 14.09.1999 and thus;

consideration of unconsumed units on the denominator side

of the formula, prior to such date cannot arise at all.

It is also pertinent to mention here that, the issue of

unconsumed units was never raised in the first round of

litigation and hence would not operate as res-judicata in the

present proceedings. Further, it is trite law that the State

cannot harp on technicalities and defeat the legitimate claims

of the Petitioner. Reference is made to the Judgment of the

Hon’ble Supreme Court in Hindustan Sugar Mills v. State

of Rajasthan, (1980) 1 SCC 599, wherein it was held that –

We hopefully expect that the Central Government

will not try to shirk its legal obligation by

resorting to any legal technicalities, for we

maintain that in a democratic society governed

by the rule of law, it is the duty of the State to do

what is fair and just to the citizen, and the State

should not seek to defeat the legitimate claim of

55

the citizen by adopting a legalistic attitude but

should do what, fairness and justice demand.

The Respondent Board ought to have addressed on this

issue on merits; rather than taking such technical pleas. It

has recently been held by the Hon’ble Supreme Court in the

case of State (NCT of Delhi) v. BSK Realtors LLP, reported

in2024 SCC OnLine SC 1092 that res-judicata is in the

realm of procedural law which cannot be pressed as a defense

which public interest is involved (Para 25).

In the present case, the rate of fuel surcharge or any

enhancement or decrease thereof would affect all the

consumers in the State of Jharkhand. Therefore, this issue

would certainly affect the public interest. Therefore, a

technical plea of res-judicata ought not to have deterred on

Learned Single Judge in deciding this issue.

Moreover, as stated herein above; the Circular dated

14.09.1999 was an internal Circular, and the consumers

never had an opportunity to address the same in the first

round of litigation.

25. The next issue argued by the Appellants, before the Ld.

Single Judge was that the State was bifurcated as on

15.11.2000 and Jharkhand State Electricity Board came into

existence on 01.04.2001. Though Jharkhand State Electricity

Board adopted tariff of Bihar State Electricity Board till

31.12.2003, but the formula of fuel surcharge being based

upon generation and purchase and as well as sale of units

have to be worked out after bifurcation of the State and more

so, after 01.04.2001, when JSEB came into existence.

On the issue of bifurcation of State and its impact; Ld.

Sr. Counsel further contended that in terms of the formula,

the generating station of Baruni and Muzzafarpur and

purchases made by Bihar State Electricity Board ought to

have been deleted from the numerator and so far as

56

Jharkhand is concerned, and only inclusion in the numerator

should be that of Patratu Thermal Power Station and

purchase of electricity by Jharkhand State Electricity Board.

The denominator ought to have been only the sale of units of

the fuel surcharge paying consumers in the State of

Jharkhand and not in the entire State of Bihar.

This calculation in the formula will have resulted in

great decrease of the fuel surcharge as almost 70% of the

consumption of electricity of the unified State of Bihar was

after the bifurcation in the new State of Jharkhand.

This aspect of the matter were legal issues which have

not been considered by the writ Court, but in Para 36 of the

Impugned Judgment, the Court discarded the contention of

the Appellant consumers and wrongly observed that fuel

surcharge circulars are operative in the State of Jharkhand

before the date on which JSEB was created, ignoring the fact

that the formula ought to have changed from 01.04.2001 till

31.12.2003, as energy generated in the Power Stations

became only one instead of three, and also the purchase of

energy by JSEB only should have been taken for

consideration for calculations. Accordingly, the calculation of

the fuel surcharge had to be changed on and from

01.04.2001.

26. Learned counsel for the respondent submitted that

since JSEB’s tariff only came into existence on 01.01.2004,

therefore, fuel surcharges ought to be continued till

31.12.2003.

27. In this regard, we are of the view that the JSEB had

already came into existence on 1.4.2001. The Books of

Accounts for both JSEB and BSEB were maintained

separately. Therefore, effect of bifurcation of the State must

be taken into consideration while calculating fuel surcharge

for consumers in the State of Jharkhand. The power

generated by the power plants in Bihar and the power

57

purchased from other sources by BSEB as well as the units

sold to consumers in Bihar could not have been taken into

consideration while calculating the rate of fuel surcharge in

the State of Jharkhand.

28. On the issue of “Delayed Payment Surcharge” it has

been submitted that after the Judgment was delivered, all

consumers were served with the bills based upon the

circulars issued after Judgment in the case of M/s. Pulak

Enterprises at Patna. However, almost all consumers had

challenged those circulars and interim Orders were passed in

favour of the consumers.

However, after the impugned judgment, the Board

raised balance amount of bills and levied a phenomenal

amount of interest which in almost all the cases was about

four times of the balance principal amount. All the consumers

had continued to make payment of fuel surcharge in terms of

the interim orders and as a matter of fact, after the

Judgment, the consumers also paid balance amount of

principal amount of fuel surcharge. However, despite there

being no direction in the Impugned Judgment, the Board

levied interest for almost 16-17 years each from the F.Y.

1996-97 upon all consumers.

When the bills were raised after the impugned

judgment, certain consumers approached the Hon’ble

Supreme Court, and the Hon’ble Supreme Court was pleased

to direct that DPS shall not be levied and the consumers were

only required to the principal amount at this stage.

Learned senior counsel , lastly submitted that it is

evident that working of the fuel surcharge by the Board was

absolutely erroneous and was in gross contravention of the

directions of the Hon’ble Supreme Court and all the five

issues of the rates of fuel surcharge are to be answered in

favor of the Petitioner consumers.

58

It is evident that the bills issued after the impugned

judgment are unworkable and will have to be revised in light

of the fact that even one of the issues being decided in favor of

the consumers.

So far as the levy of delayed payment surcharge is

concerned, there are a series of Judgments in respect of the

issue that when electricity bills revised and found to be

erroneous then in that event Delayed Payment surcharge has

to be set aside. He relied upon the following judgments in this

regard –

(i) M/s. Hotel Woodlands v. JSEB, LPA No. 274 of 2004 – Para 5

(ii) M/s. Raj laxmi factories and Ceramic Works v. BSEB & Ors .,

(1999) 2 BLJR 508 – Paras 15 to 18

(iii) M/s. Gaya Roller Flour Mills Pvt. Ltd. v. BSEB, (1995) 2 PLJR

715 – Paras 9 and 10

(iv) M/s. Incore Metal ndCmement (P) Ltd. v. State of Jharkhand,

WP(C) 6587 of 2009 – Paras 12 to 14

(v) ManvinderNarain Agarwal v. BSEB &Ors., (2002) 3 PLJR 510 –

Para 10

(vi) Subodh Kumar Poddar v. BSEB &Ors ., (2002) 3 PLJR 532 –

Paras 2, 3 and 9

(vii) Kusumam Hotels Pvt. Ltd. v. KSEB &Ors., (2008) 13 SCC 213 –

Para 45

On the strength of the above referred judgments and

the factual background of this case, Ld. Sr. Counsel

contended that the fact that bills have to be revised is evident

from BSEB ‘s own Circular dated 01.12.2010 (Annexure-13

dated 22.10.2010, Annexure-14 dated 01.12.2010) wherein

BSEB has stated that benefit of Rs. 100 Crores will be given

to the consumers, once the amount is received from Coal

Companies which would result in an alleged reduction of 6.04

P/KWh in the rates of fuel surcharge for the year 1998-99.

It has been further submitted that even ignoring the

fact that BSEB’s Circulars only gave benefit of reduction of

Rs. 23.22 crores out of Rs. 100 crores, then also as per their

59

own admission, bills ought to have been revised by reducing

6.04 P/KWh for the year 1998-99.

Hence refund has to be done in any event. Once the

revision is done, the question of DPS does not arise. In fact, at

the time of raising of the bill after Impugned Order 2015,

JSEB has already received Rs. 100 Crores and should have

reduced rate for the year 1998-99 and thus no DPS ought to

have levied at all.

29. On this last issue with respect to D.P.S., the Board

contended that it would be equitable for D.P.S. to be levied as

Board was deprived of fuel surcharge during the disposal of

the Writ petition. Reference was also made to the Judgment

rendered in (2003) 8 SCC 648.

30. In this regard, we are of the view that Board was never

deprived of fuel surcharge. The consumers kept paying at old

rate as per direction of this Court. Moreover, in the impugned

judgment, there was no direction that bills should be raised

along with DPS.

Further, the decision relied on by the Respondents is

also inaccurate as this would not be a case where there is no

change in the rate of fuel surcharge calculated by the Board.

Only if there was any interference / no reduction in the

calculation of fuel surcharge made by the Board, it would be

justified in levying D.P.S. However, as per the Board’s own

case, the benefit of Rs. 100 Crores has to be given which

would result in downward revision of fuel surcharge.

Further, from discussions made hereinabove, it can be

seen that calculation of fuel surcharge is totally inaccurate;

accordingly, we hold that the same needs to be revised. Once

the rates are revised, the original bill will be deemed to be

incorrect and there can be no question of levy of interest/DPS

thereupon.

31. Hence, we deem it proper to allow the present batch of

appeals. Accordingly, the impugned order passed by the writ

60

court is quashed. Consequently, all the bills which has been

impugned in the respective writ applications, are hereby,

quashed.

It is ordered that the Bills is to be rework out and the

rates of Fuel Surcharge be revised strictly in the line of what

has been held by the Patna High Court and the Hon’ble Apex

Court and also the finding given by us hereinabove on each

and every issue; keeping in mind the fact of Bifurcation of

Boards i.e. BSEB and JSEB, amount of Rs.100 Crore received

from coal Company and the observation given by us on DPS.

32. For making the revised calculations, we hereby appoint

three men committee headed by Hon’ble Mr. Justice Amitabh

Kumar Gupta (Retd.), Jharkhand High Court along with two

chartered accountants to be nominated by the Chairman of

the committee from the names given by both the parties i.e.

Board and the Consumers; to examine the calculations.

The committee after coming to the conclusion shall

send the calculation to the Board which shall issue fresh Bills

to the Consumers for its payment.

The professional fees of the Committee shall be decided

by its Chairman and the same will be borne by the appellants.

33. Consequently, all these appeals are disposed of in

the manner indicated herein above.

34. Pending I.A.s, in respective appeals, if any, are

also closed.

(Rongon Mukhopadhyay, J.)

(Deepak Roshan, J.)

Jharkhand High Court at Ranchi

Dated:-31/08/2024

Amardeep/

AFR/

Reference cases

Description

Legal Notes

Add a Note....