As per the case facts, a power project sought benefits under a government policy from the date the policy was announced. However, lower courts determined that benefits should only apply ...
2024 INSC 833 1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 8478 OF 2014
NABHA POWER LIMITED & ANR. …Appellant (s)
Versus
PUNJAB STATE POWER
COROPORATION LIMITED & ANR. ...Respondent(s)
J U D G M E N T
K.V. Viswanathan, J.
1. The present appeal arises from the judgment dated 30.06.2014
of the Appellate Tribunal for Electricity (for short the “APTEL”) in
Appeal No. 29 of 2013. By the said judgement, the APTEL
dismissed the appeal of the appellant and confirmed the order dated
12.11.2012 of the Punjab State Electricity Regulatory Commission
(for short the “State Commission”), insofar as issue no. 1 discussed
therein was concerned. That issue concerned the aspect of Mega
2
Power Policy and the effect of the Press Release of 01.10.2009. We
are only concerned with the said issue in this Appeal.
FACTS OF THE CASE: -
A) Customs Notification No. 21/2002 dated 01.03.2002.
2. To appreciate the issues involved, certain background facts
need to be set out. Goods imported for setting up a Mega Power
Project had, under a notification issued under Section 25 of the
Customs Act dated 01.03.2002, been granted certain exemptions
from customs duty. It will be useful to set out the relevant part of the
01.03.2002 notification.
“Exemption and effective rates of basic and additional duty
for specified goods of Chapters 1 to 99. - In exercise of the
powers conferred by sub-section (1) of section 25 of the
Customs Act, 1962 (52 of 1962) and in supersession of the
notification of the Government of India in the Ministry of
Finance (Department
of Revenue), No. 17 /2001- Customs, dated the 1st March, 2001
[G.S.R. 116(E), dated the 1st March, 2001], the Central
Government, being satisfied that it is necessary in the public
interest so to do, hereby exempts the goods of the description
specified in column (3) of the Table below or column (3) of the
said Table read with the relevant List appended hereto, as the
case may be, and falling within the Chapter, heading or sub-
heading of the First Schedule to the Customs Tariff Act, 1975
(51 of 1975) as are specified in the corresponding entry in
column (2) of the said Table, when imported into India, -
3
(a) from so much of the duty of customs leviable thereon under
the said First Schedule as is in excess of the amount calculated
at the rate specified in the corresponding entry in column (4) of
the said Table;
(b) from so much of the additional duty leviable thereon under
sub-section (1) of section 3 of the said Customs Tariff Act, as
is in excess of the rate specified in the corresponding entry in
column (5) of the said Table,
Subject to any of the conditions, specified in the Annexure to
this notification, the condition No. of which is mentioned in the
corresponding entry in column (6) of the said Table :
S.No. Chapter or
Heading
No. or sub-
heading
No.
Description of
goods
Standard
rate
Additional
dduty rate
Condition
no.
400 98.01 Goods required
for setting up of
any Mega
Power Project
specified in List
42, if such
Mega Power
Project is –
(a) an inter-
State thermal
power plant of a
capacity of
1000 MW or
more; or
(b) an inter-
State hydel
power plant of a
capacity of 500
MW or more, as
Nil Nil 86
4
certified by an
officer not
below the rank
of a Joint
Secretary to the
Government of
India in the
Ministry of
Power
86. (a) If an officer not below the rank of a Joint Secretary to
the Government of India in the Ministry of Power certifies that-
(i) the power purchasing State has constituted the Regulatory
Commission with full powers to fix tariffs; ·
(ii) the power purchasing State undertakes, in principle, to
privatise distribution in all cities, in that State, each of which
has a population of more than one million, within a period to be
fixed by the Ministry of Power; and
(iii) the power purchasing State has agreed to provide recourse
to that State’s share of Central Plan allocations and other
devolutions towards discharge of any outstanding payment in
respect of purchase of power;
(b) In the case of imports by a Central Public Sector
Undertaking, the quantity, total value, description and
specifications of the imported goods are certified by the
Chairman and Managing Director of the said Central Public
Sector Undertaking; and
(c) In the case of imports by a Private Sector Project, the
quantity, total value, description and specifications of the
imported goods are certified by the Chief Executive Officer of
such project.”
B) Mega Power Policy of 2006
3. On 10.06.2009, when competitive bidding was initiated by the
respondent, what was in vogue was the Mega Power Policy, 2006. If
5
a thermal plant was covered as a Mega Power Project under the Mega
Power Policy of 2006, it was entitled to the benefit of certain
exemptions under the customs notification dated 01.03.2002
extracted hereinabove.
4. The Mega Power Policy, 2006 prescribed the following
conditions to be fulfilled by the developer for grant of mega power
status:-
“MEGA POWER PROJECTS: REVISED POLICY
GUIDELINES
The following conditions are required to be fulfilled by the
developer for grant of mega project status:-
(a) an inter-state thermal power plant of a capacity of 700 MW
or more, located in the States of Jammu and Kashmir, Sikkim,
Arunachal Pradesh, Assam, Meghalaya, Manipur, Mizoram,
Nagaland and Tripura; or
(b) an inter-state thermal power plant of a capacity of 1000 MW
or more, located in States other than those specified in clause
(a) above; or
(c) an inter-state hydel power plant of a capacity of 350 MW or
more, located in the States of Jammu and Kashmir, Sikkim,
Arunachal Pradesh, Assam, Meghalaya, Manipur, Mizoram,
Nagaland and Tripura; or
(d) an inter-state hydel power plant of a capacity of 500 MW or
more, located in States other than those specified in clause (a)
above.
Fiscal concessions/benefits available to the Mega Power
Projects
Zero Customs Duty: In terms of the notification of the
Government of India in the Ministry of Finance (Department of
Revenue) No.21/2002-Customs dated 1st March, 2002 read
6
together with No.49/2006-Customs dated 26th May, 2006, the
import of capital equipment would be free of customs duty for
these projects.
Deemed Export Benefits: Under Chapter 8(f) of the Foreign
Trade Policy, Deemed Export Benefits is available to domestic
bidders for projects both under public and private sector on
following the stipulations prescribed therein.
Pre-conditions for availing the benefits: Goods required for
setting up of any mega power project, qualify for the above
fiscal benefits after it is certified by an officer not below the
rank of a Joint Secretary to the Govt. of India in the Ministry of
Power that-
(i) the power purchasing States have constituted the Regulatory
Commissions with full powers to fix tariffs;
(ii) the power purchasing States undertakes, in principle, to
privatize distribution in all cities, in that State, each of which
has a population of more than one million, within a period to be
fixed by the Ministry of Power.
Price preference to domestic PSUs bidders: In order to ensure
that domestic bidders are not adversely affected, price
preference of 15% would be given for the projects under public
sector. The domestic bidders would be allowed to quote in US
Dollars or any other foreign currency of their choice.
Income Tax benefits: In addition, the income-tax holiday
regime as per Section 80-IA of the Income Tax Act 1961 can
also be availed.”
What is important is the phrase “Inter-State Thermal Power Plant”
employed in the policy.
C) Request For Proposal
5. It was when this legal regime was in force that on
10.06.2009, the erstwhile Punjab State Electricity Board [now
7
after unbundling-the distribution being known as Punjab State
Power Corporation Limited (PSPCL)] through its then wholly
owned subsidiary and a special purpose vehicle, appellant no. 1-
Nabha Power Limited issued a Request For Proposal (RFP). The
RFP was for selection of developers through tariff-based bidding
process under Section 63 of the Electricity Act 2003, for
procurement of power on long-term basis from the power station
to be set up at village Nalash, near Rajpura, District Patiala,
Punjab. This was as per the Guidelines for Determination of
Tariff by Bidding Process for Procurement of Power by
Distribution Licencees issued by the Ministry of Power,
Government of India. In terms of RFP, the bidders were required
to quote the Capacity Charge (i.e. capital cost component) and
Station Heat Rate (i.e. amount of heat required by the plant to
generate one unit of electrical energy/efficiency of the plant) to
convert the heat energy for the project and based on these
components, a levelized tariff for each bidder was to be worked
out. The bidder with the lowest levelized tariff was to be selected
for the development of the project.
8
6. The term- “Successful Bidder or Selected Bidder” was to mean
that the bidder selected pursuant to the RFP to set up the project and
supply electrical output therefrom to the Procurer through the Seller
as per the terms of the power purchase agreement (PPA) and other
RFP project documents. Under Clause 2.7.2.1 and 2.7.2.2, the bidder
was to make an independent enquiry and satisfy itself with respect to
all the required information, inputs, conditions and circumstances
and factors that may have any effect on the bid. Under the said
clauses, it was deemed that while submitting the bid, the bidder was
to have inspected and examined the site conditions, the laws and
regulations in force. The bidder was to acknowledge that on being
selected as the successful bidder and on acquisition of the special
purpose vehicle (the seller) the seller shall not be relieved from any
of its obligations under the RFP project documents nor shall the seller
be entitled for any extension of time or financial compensation by
reason of the unsuitability of the site. Clauses 2.7.2.1 and 2.7.2.2 read
as under.
“2.7.2.1 The Bidder shall make independent enquiry and
satisfy itself with respect to all the required information, inputs,
conditions and circumstances and factors that may have any
effect on his Bid. While submitting the Bid the Bidder shall be
9
deemed to have inspected and examined the site conditions
(including but not limited to its surroundings, its geological
condition, the adequacy of the road and rail links to the Site and
the availability of adequate supplies of water), examined the
laws and regulations in force in India, the transportation
facilities available in India, the grid conditions, the conditions
of roads, bridges, ports, etc. for unloading and/or transporting
heavy pieces of material and has based fts design, equipment
size and fixed its price taking into account all such relevant
conditions and also the risks, contingencies and other
circumstances which may influence or affect the supply of
power. Accordingly, the Bidder acknowledges that, on being
selected as Successful Bidder and on acquisition of the Seller,
the Seller shall not be relieved from any of its obligations under
the RFP Project Documents nor shall the Seller be entitled to
any extension of time or financial compensation by reason of
the unsuitability of the Site for whatever reason.
2.7.2.2 In their own interest, the Bidders are requested to
familiarize themselves with the Electricity Act, 2003, the
Income Tax Act 1961, the Companies Act, 1956, the Customs
Act, the Foreign Exchange Management Act, IEGC, the
regulations framed by regulatory commissions and all other
related acts, laws, rules and regulations prevalent in India. The
Procurer/Authorised Representative shall not entertain any
request for clarifications from the Bidders regarding the same.
Non-awareness of these laws or such information shall not be a
reason for the Bidder to request for extension of the Bid
Deadline. The Bidder undertakes and agrees that before
submission of its Bid all such factors, as generally brought out
above, have been fully investigated and considered while
submitting the Bid.”
Press Release of 1.10.2009
7. When the matter stood thus, a Press Release was issued by the
Press Information Bureau, Government of India under the heading
“Modification of Mega Power Policy”. It will be safer to extract the
10
entire Press Release as this is the fulcrum on which the entire case of
the appellant revolves. The Press Release with certain portions
emphasized by us, is extracted hereinbelow:
“PRESS INFORMATION BUREAU
GOVERNMENT OF INDIA
Press Release
Thursday, October 01,2009
Modification of Mega Power Policy
The Union Cabinet today approved modifications in the
existing mega power policy. This would encourage setting up
of mega power plants to take advantage of economies of scale
and improve their viability. It will simplify the procedure for
grant of mega certificate and encourage capacity addition. It
will also encourage technology transfer and indigenous
manufacturing in the field of super critical power equipments.
The mega Power Policy was introduced in November 1995 for
providing impetus to development of large size power projects
in the country and derive benefit from economies of scale.
These guidelines were modified in 1998 and 2002 and was last
amended in April 2006 to encourage power development in
Jammu & Kashmir and the North Eastern region.
In order to rationalize the Mega Power Policy and bring it in
consonance with the National Electricity Policy 2005 and Tariff
Policy 2006, the following modifications of the existing Mega
Power Policy have been envisaged:
(i) The existing condition of privatization of distribution by
power purchasing states would be replaced by the condition
that power purchasing states shall undertake to carry out
distribution reforms as laid down by the Ministry of Power.
(ii) The conditions requiring inter-state sale of power for
getting mega power status would be removed.
(iii) The present dispensation of 15% price preference available
to the domestic bidders in case of cost plus projects of PSUs
11
would continue. However, the price preference will not apply
to tariff based competitively bid projects of PSUs. A Committee
would be set up under the Planning Commission, with DHI,
MoP and DoR as members which would suggest options and
modalities to take care of the disadvantages suffered by the
domestic industry related to power sector keeping all factors in
view.
(iv) The benefits of Mega Power Policy will also be extended
to supercritical projects to be awarded through ICB with the
mandatory condition of setting up indigenous manufacturing
facility provided they meet the eligibility criteria.
(v) The requirement of undertaking international competitive
bidding (ICB) by the developers for procurement of equipment
for mega power projects would not be mandatory, if the
requisite quantum of power has been tied up through tariff
based competitive bidding or the project has been awarded
through tariff based competitive bidding.
(vi) A basic custom duty of 2.5% only would be applicable on
brown field expansion of existing mega projects. All other
benefits under mega power policy available to Greenfield
projects would also be available to expansion unit(s)
(Brownfield projects) even if the total capacity of expansion
unit(s) is less than the threshold qualifying capacity, provided
the size of the unit(s) is not less than that provided in the earlier
phase of the project granted mega power project certificate. All
other conditions for grant to the mega power status shall remain
the same.
(vii) Mega Power Projects would be required to tie up power
supply to the distribution companies/utilities through long term
PPA(s) and may also sell power outside long term PPA(s) in
accordance with the National Electricity Policy 2005 and Tariff
Policy 2006, as amended from time to time, of Government of
India.”
(Emphasis supplied)
12
The Cabinet decision, as such, is not on record and admittedly what
is available is the Press Release issued by the Press Information
Bureau.
8. The final bidding date was on 09.10.2009 and as per clause 13.1
from the Format-1 Annexure-3 annexed to the RFP, 02.10.2009 was
the cutoff date for consideration of change in law. Equally, under
clause 2.5.3, 25.09.2009 was the last date for seeking clarification.
Law is defined in Clause 1.1.
D) BID RESULTS
9. The second appellant L&T Power Development Limited
emerged as the successful bidder and a Letter of Intent was issued on
19.11.2009 and the L&T Power Development Limited acquired the
first appellant. The appellant contends that on 02.10.2009, the second
appellant had addressed a letter to Nabha (then owned by the
respondent) requesting an extension of the bid deadline to enable
them to go through the changes pursuant to the Press Release of
01.10.2009 and ascertain the impact of the bid. It was followed up
with a letter of 06.10.2009 setting out that the appellant had taken
into consideration the benefits associated with the mega power status
13
in evaluation of their project. According to the appellant, it was
forced to withdraw the letter before submitting the bid. According to
the respondent that letters were extraneous to the bid and were not
entertained.
E) Developments in December, 2009
10. Certain rapid developments happened in December, 2009. On
3
rd
December, 2009, the Government of India in the Ministry of
Power addressed a letter to all the Principal Secretary/Secretary
Energy of all the States/Union Territories under the subject
“Distribution reforms under the modified Mega Power Policy”. It
was set out in the letter that in order to further liberalize the Mega
Power Policy as issued on 2
nd
August, 2006 and also remove such
provisions which had lost relevance, Government has made
modifications in the Mega Power Policy and the revised policy
guideline was being issued separately. It set out that one of the
decisions taken in this regard was that the existing condition of
privatization of distribution by power purchasing States would be
replaced by the condition that power purchasing States were to
undertake to carry out distribution reforms as laid down by the
14
Ministry of Power. The letter proceeded to State that in this regard
the matter was examined in the Ministry of Power and a follow up
meeting was held on 28
th
October, 2009 with the representatives of
State Power Departments. It was set out that in the said meeting
various measures for distribution reforms that could be taken up by
the State Governments were discussed in detail and the letter
annexed the summary of the minutes of the meeting of 28.10.2009.
An undertaking was to be taken from the States in a prescribed format
and the operative portion of the letter, which is crucial, is extracted
hereinbelow:
“Accordingly, in pursuance of the Cabinet decision dated 1
st
October 2009 on the modification to the Mega Power Policy,
following four distribution reform measures hereby laid down
by the Ministry of Power required to be undertaken by the states
purchasing power from the mega power projects:
a) Timely release of subsidy as per Section 65 of Electricity Act
2003.
b) Ensure that Discoms approach SERC for approval of annual
revenue requirement/tariff determination in time according to
the SERC regulations.
c) Setting up special courts as provided in the Electricity Act
2003 to tackle related cases.
d) Ring fencing of SLDCs.
An undertaking in the enclosed format (Annexure- II) may
be given to the Ministry of Power. The said undertaking needs
to be given at least, once and would be considered in all the
cases where the concerned State Distribution Utility ties up
15
procurement of power from a power project considered for
grant of mega power state.
Receipt of this communication may please be acknowledged
and the undertaking in the enclosed format may be sent to this
Ministry at the earliest to facilitate processing of the Mega
Power Policy case(s).”
F) Amendment to the Customs Notification dated 11.12.2009
11. Thereafter, on 11.12.2009, an amendment to the customs
notification no. 21 of 2002 dated 01.03.2002 was issued. The
notification is extracted hereinbelow.
“In exercise of the powers conferred by sub-section (1) of section
25 of the Customs Act 1962 (52 of 1962), the Central
Government, on being satisfied that it is necessary in the public
interest so to do, hereby makes the following further amendments
in the notification of the Government of India in the Ministry of
Finance (Department of Revenue) No. 21/2002-Customs, dated
the 1
st
March, 2002, which was published in the Gazette of India,
Extraordinary vide number G.S.R. 118(E), dated the 1
st
March,
2002, namely:-
In the said notification, -
A. in the Table,
(i) against S.No. 400, for the entry in column (3), the following
entry shall be substituted namely:-
“Goods required for setting up of any Mega Power Project, so
certified by an officer not below the rank of a Joint Secretary to
the Government of India in the Ministry of Power, that is to say -
(a) a thermal power plant of a capacity of 700 MW or more,
located in the States of Jammu and Kashmir, Sikkim, Arunachal
Pradesh, Assam, Meghalaya, Manipur, Mizoram, Nagaland and
Tripura: or
16
(b) a thermal power plant of a capacity of 1000 MWor more,
located in States other than those specified in clause (a) above; or
(c) a hydel power plant of a capacity of 350MW or more, located
in the States of Jammu and Kashmir, Sikkim, Arunachal Pradesh,
Assam, Meghalaya, Manipur, Mizoram, Nagaland and Tripura; or
(d) a hydel power plant of a capacity of 500MW or more, located
in States other than those specified in clause (c) above":
(ii) after S.No. 400 and the entries relating thereto, the following
S.No. and entries shall be inserted, namely :-
1 2 3 4 5 6
400A. 980
1
Goods required for the
expansion of any existing
Mega Power Project so
certified by an officer not
below the rank of a Joint
Secretary to the
Government of India in the
Ministry of Power.
Explanation: for the
purposes of this
exemption, Mega Power
project means a project as
defined in S. No. 400
above.
2.5% Nil 86
B. in the Annexure, in Condition No. 86, for sub-clause (ii) of
clause (a), the following shall be substituted namely:
(ii) the power purchasing states shall undertake to carry out
distribution reforms as laid down by Ministry of Power.”
(Emphasis supplied)
17
12. It will be noticed that entry 400 from the notification of 2002
was substituted and in the substituted clause there is no reference to
the thermal plant being an inter-State thermal plant.
Mega Power Policy of 14.12.2009
13. Close on the heels, on 14.12.2009, the Government of India and
the Ministry of Power issued an office memorandum under the
subject “revised Mega Power Policy”, which reads as under:-
“No. A-118/2003-IPC
Government of India
Ministry of Power
Shram Shakti Bhavan, New Delhi
Dated 14
th
December, 2009
OFFICE MEMORANDUM
Subject : Revised mega power project policy.
Policy guidelines for setting up of mega power projects
were last revised and issued vide this Ministry's letter of even
number dated 2
nd
August, 2006. The Government of India has
modified the Mega Power Policy to smoothen the Procedures
further. The modified Mega Power Policy is as follows:
(i) The power projects with the following threshold capacity shall
be eligible for the benefit of mega power policy:
(a) A thermal power plant of capacity 1000 MW or more; or
(b) A thermal power plant of capacity of 700MW or more, located
in the States of J & K, Sikkim, Arunachal· Pradesh, Assam,
Meghalaya, Manipur, Mizoram, Nagaland and Tripura; or
(c) A hydel power plant of capacity of 500 MW or more; or
(d) A hydel power plant of a capacity of 350 MW or more, located
in the States of J&K, Sikkim, Arunachal Pradesh, Assam,
Meghalaya, Manipur, Mizoram, Nagaland and Tripura;
18
(e) Government has decided to extend mega policy benefits to
brownfield (expansion) projects also. In case of the brownfield
(expansion) phase of the existing mega project, size of the
expansion units would not be not less than that provided in the
earlier phase of the project granted mega power project certificate.
(ii) Mandatory condition of Inter-State sale of power for getting
mega power status has been removed.
(iii) Goods required for setting up a mega power project, would
qualify for the fiscal benefits after it is certified by an officer not
below the rank of a Joint Secretary to the Govt. of India in the
Ministry of Power that (i) the power purchasing States have
constituted the Regulatory Commissions with full powers to fix
tariffs and (ii) power purchasing states shall undertake to carry out
distribution reforms as laid down by Ministry of Power.
(iv) Mega Power Projects would be required to tie up power
supply to the distribution companies/utilities through long term
PPA(s) in accordance with the National Electricity Policy 2005
and Tariff Policy 2006, as amended from time to time, of
Government of India.
(v) There shall be no further requirement of ICB for procurement
of equipment for mega projects if the requisite quantum of power
has been tied up or the project has been awarded through tariff
based competitive bidding as the requirements of ICB for the
purpose of availing deemed export benefits under Chapter 8 of the
Foreign Trade Policy would· be presumed to have been satisfied.
In all other cases, ICB for equipments shall be mandatory.
(vi) The present dispensation of 15% price preference available to
the domestic bidders in case of cost-plus projects of PSUs would
continue. However, the price preference will not apply to tariff
based competitively bid projects of PSUs.
3. This issues with the approval of Secretary (Power).
Sd/-
(Puneet K Goel)
To
Principal Sectary/Secretary/ Energy of all States/UTs.
19
Copy to:
(i) Chairman, CEA,
(ii) CMDs of all PSUs of MOP
Copy for information to :-
PS to MOP/PS to MOS(P) / PS to Secretary(P) Sr. PPS to
AS(AK)/ PPS to AS(GBP)/ All Joint Secretaries/ Directors in the
Ministry of Power, Dir (PIB), MOP.
Copy also to Cabinet Secretariat, New Delhi
Copy for putting on website of Ministry of Power to NIC, MOP.
Sd/-
(Puneet K Goel)
Director (IPC)”
(Emphasis Supplied)
14. It will be noticed that the mandatory conditions of inter-State
sale of power for getting mega power status was removed; it was
decided that goods required for setting up a Mega Power Project
would qualify for the fiscal benefits after it is certified by an officer
not below the rank of a Joint Secretary to the Government of India in
the Ministry of Power that (i) the Power purchasing States have
constituted the Regulatory Commissions with full powers to fix
tariffs and (ii) Power purchasing States shall undertake to carry out
distribution reforms as laid down by Ministry of Power apart from
certain other conditions.
20
Events Leading to the Dispute
15. The appellant no. 1 Nabha Power Limited, which was now
owned by appellant no. 2, entered into a Power Purchase Agreement
on 18.01.2010 with the respondent PSPCL.
16. According to the appellant, thereafter a series of correspondence
ensued between appellant no. 1 and the respondent with regard to the
issuance of Essentiality Certificate so that the customs authorities
allow import at the concessional duty in terms of the amended entry
400, in the Notification of 11.12.2009. The appellant has a case that
apart from the other documents the respondent asked for an affidavit
indemnifying the respondent against adverse consequences arising
out of wrong claim of benefits by the appellant and also an affidavit
stating that the benefits of mega power status granted to the appellant
project will be passed on to the respondent as per clause 13.3 of the
PPA.
17. The appellant claims that while it furnished the other documents,
with regard to the affidavit for passing on the benefits of the mega
power status, it wrote to the respondent on 17.02.2011 stating that it
had already factored in the benefits available in view of the Cabinet
21
decision dated 01.10.2009 and thereafter there is no basis for
submission of the affidavit as called for.
18. The respondent replied by its letter of 04.03.2011 and insisted
on the affidavit as sought for by setting out the following reasons:
“(i) at the time of submission of bid, the Mega Policy 2006
was in vogue and therefore, the Project could not have
qualified as a MPP;
(ii) the Mega Policy 2009 was notified on 14.12.2009, post
submission of the bids and therefore, the benefits could have
only accrued post such notification;
(iii) the mega power status is granted to a project subject to
(a) project getting certified as a MPP from an officer not
below the rank of Joint Secretary to the Ministry of Power;
(b) the power purchasing States having constituted the
Regulatory Commissions with full power to fix tariffs; (c)
power purchasing States undertaking to carry out
distribution reforms as laid down by the Ministry of Power;
(iv) the distribution reforms took place in Punjab in April,
2010 and hence, the bidders could not have considered
benefits available under the Mega Policy 2009 prior to the
submission of the bid; and
(v) in relation to the Project, the Petitioner No.1 had applied
to the Ministry of Power for grant of mega power status to
the Project on 11.05.2010 and the Ministry of Power had
granted the said status vide its letter dated 30.07.2010.”
19. Ultimately, after a lengthy exchange of correspondence with
each party sticking to their respective position, the appellant no. 1
submitted an undertaking in the specified format (the factum of the
22
undertaking being under protest and without prejudice as claimed by
the appellant is disputed by the respondent) in order to avoid further
delay in the issuance of the Essentiality Certificate. The respondent
replied by stating that the non-escalable capacity charge would stand
reduced in terms of the Article 13 of PPA in proportion to the
concession in custom duty on the consignment value of the imported
goods. Ultimately, the appellant obtained the Essentiality Certificate
on 16.06.2011. Similar affidavits were furnished for the further
imports and the respondent granted Essentiality Certificate only on
the condition that it would have the right to seek appropriate
reduction in tariff on account of decrease in capital cost of the
project.
20. On 22.05.2012, the appellants filed a Petition bearing Petition
no. 30 of 2012 before the Punjab State Electricity Regulatory
Commission, Chandigarh under Section 86(1)(f) of the Electricity
Act, 2003, contending that appellant no. 2 had considered and
factored the benefits available to the project under the Mega Power
Policy of 2009, on 09.10.2009 when they submitted the bid and had
passed on such benefits to the respondent by way of the tariff it
23
quoted. The appellant contended that no change in law occurred in
view of the notification of 11.12.2009 and 14.12.2009 and whatever
change was there, happened on 01.10.2009 itself with the press
release of the Cabinet decision. The following prayers were made in
the claim petition:
“In light of the facts and circumstances as stated above, the
Petitioners are respectfully praying before this Hon'ble
Commission:
(a) to declare that the Union Cabinet's decision dated
01.10.2009 modifying the Mega Policy 2006 reported vide
Press Information Bureau on the same date does not
amount to 'Change in Law' under Article 13 of the PPA;
(b) following the declaratory relief sought by the
Petitioners, to hold that consequential relief as set out under
Article 13.2 of the PPA has not triggered and no
consequential benefits under Article 13 have to be passed
on to the Respondent by the Petitioner under the PPA on
account of Union Cabinet's decision to change the Mega
Policy 2006 dated 01.10.2009;
(c) in alternative, if reliefs sought under para (a) and (b)
above are not granted, then to direct and allow that the
Petitioners shall be entitled to claim 'Change in Law'
against the Respondent's claim on the basis of withdrawal
of fiscal benefits which were available to the Project under
the FTP on the date of bidding on standalone basis, without
considering Mega Policy, 2009;
(d) award cost in favour of the Petitioners;
(e) pass such other and further orders / directions as the
Hon'ble Commission may deem appropriate in the facts and
circumstances of the case.”
24
Though the prayer are not happily worded, the issue raised with
regard to the Mega Power Policy issue, as understood by both parties,
is whether the legal regime was altered on 01.10.2009 or on
11.12.2009 and 14.12.2009 respectively.
21. The appellant’s claim before the Commission was founded on
twin basis. The main relief was on the aspect of the Mega Power
Policy, the contention of the appellant being that the legal regime was
altered on 01.10.2009, with the Cabinet Decision, as noticed in the
Press Release of 01.10.2009. The alternative plea was based on the
Foreign Trade Policy (in short ‘FTP’) and the appellants contention
was that in the alternative, the appellant was entitled to claim change
in law against the respondent on the basis of withdrawal of fiscal
benefits which were available to the project under the Foreign Trade
Policy on the date of bidding, on a standalone basis without
considering the Mega Power Policy of 2009.
Order of the State Commission
22. By its Order of 12.11.2012, the State Commission rejected both
the prayers. The State Commission held that the mega power status
was made available to a project only when the State in which the
25
project is being setup had undertaken the reforms mentioned in the
Ministry of Power’s letter dated 03.12.2009; that these reforms were
undertaken by the Government of Punjab only on 16.04.2010 and
intimated to the Central Government vide letter dated 30.04.2012;
that the detailing in respect of the modified policy was not available
in the press release dated 01.10.2009; that the same was covered only
in the letter dated 03.12.2009 of the Ministry of Power addressed to
the States and in the notification of the Ministry of Power dated
14.12.2009. The Commission further held that the benefit of mega
power status cannot be granted with effect from 01.10.2009
considering the fact that it was only after a gazette notification that
the public at large were informed of the decisions of the Government
and which gazette notification was issued only in December, 2009.
That the press release itself provided a disclaimer that though all
efforts have been made to ensure the accuracy and the currency and
the content of the website of the Press Information Bureau, the same
should not be construed as a statement of law or used for any legal
purpose. On the FTP issue, it was held that the benefits under the
FTP were never available to the appellant and if identical benefits
26
were indeed available to them under the FTP, there was no need for
them to claim the same benefit under the modified Mega Power
Policy. It was further held that even if it was assumed for the sake of
argument that the FTP benefits were available before the cutoff date,
they have forfeited their right to these benefits by claiming similar
benefits under the new Mega Power Policy.
Proceedings before APTEL
23. After the Order of the State Commission, the appellant filed
Appeal No. 29 of 2013 in the APTEL. The APTEL in the impugned
judgment denied benefits under the Mega Power Policy and
confirmed the order of the State Commission on the said issue.
Insofar as the FTP aspect was concerned, the issue was remanded to
the Commission. According to the APTEL, the State Commission in
the order impugned before it had not analyzed the question as to
whether the benefits under the FTP were available to the appellant as
on the cutoff date of 02.10.2009 and whether the subsequent
withdrawal by the Government of India would amount to change in
law.
27
24. Pursuant to the remand, the Commission revived petition No.
30 of 2012 and issued notice for rehearing on the appellant’s
alternative claim based on FTP. By its judgment of 16.12.2014, the
Commission rejected the claim of the appellant based on the FTP by
a majority order.
25. Aggrieved by the same, the appellants filed Appeal No. 47 of
2015 before APTEL. By a judgment of 04.07.2017, the APTEL
dismissed the Appeal No. 47 of 2015 of the appellant. Against the
said judgment of APTEL dated 04.07.2017, appellant has filed Civil
Appeal No. 8694 of 2017. We have in this judgment not touched
upon the issues in Civil Appeal No. 8694 of 2017.
26. Coming back to the order of the APTEL dated 30.06.2014, the
APTEL while dismissing the appeal insofar as the first issue of the
Mega Power Policy discussed therein was concerned held that the
press release did not indicate the terms and conditions on which the
Mega Power Status could be made available; that the press release
cannot be construed as a statement of law in view of the disclaimer;
that the notification dated 11.12.2009 modifying the customs duty
and specifying the terms and conditions for Mega Power is what is
28
law under the definition in the power purchase agreement and that
the Mega Power Status was received only on 30.07.2010. Certain
other findings have also been recorded which are not directly
germane in view of the decision that we have ultimately taken in this
Appeal.
27. Aggrieved by the judgment of the APTEL on the issue of the
Mega Power Policy, the appellants have filed Civil Appeal No. 8478
of 2014.
Contentions:
28. In support of the appeal, we have heard Mr. C.S. Vaidyanathan,
learned Senior Advocate and in opposition thereof we have heard Mr.
M.G. Ramachandran, learned Senior Advocate for the respondent
no.1.
Submissions of the Appellant
29. Learned Senior Counsel for the appellant contends that the effect
of the Cabinet Decision must be seen with respect to the contours of
the definition of law in the Power Purchase Agreement; that the
definition includes “any order” of any Indian Government
instrumentality and hence it cannot be said that the decision of the
29
highest constitutionally entrusted body for formulating binding
national policy is not law for the purpose of the PPA; that the
appellant could not be expected to ignore the decision of the Cabinet
dated 01.10.2009 announced through the press release being a
prudent bidder/businessmen; that even the respondent concedes that
the Cabinet Decision could lead to promissory estoppel against the
Government; that clause 2.7.2.1 of the RFP deems that the bidders
have factored in all “Required information/factors that may have any
effect on the bid” and that the Cabinet Decision is at least an
information/factor for bidding purposes.
30. Learned senior counsel contended that the appellant factored in
the fiscal benefits accruing from the Mega Policy in view of the
Cabinet Decision of 01.10.2009; that the appellant informed PSPCL
by way of letters dated 02.10.2009 and 06.10.2009 about the
factoring in of the benefits; that the Mega Power Policy 2006
amendments stood approved on 01.10.2009 and hence the same
amounted to law; that the implementing actions that followed the
Cabinet Decision also accord the same understanding as would be
clear from the Ministry of Power letter dated 03.12.2009, the Minutes
30
of meeting dated 28.10.2009 annexed to the letter dated 03.12.2009,
the Memorandum dated 14.12.2009 and the fact that each department
was bound to carry out the policy in pursuance of the Cabinet
Decision dated 01.10.2009.
31. Learned Senior Counsel further contended that to claim change
in law (restitution), three essential ingredients are necessary namely
(a) The event must be after the cutoff date (b) it must be an event
stipulated in Article 13.1.1 (1 to 4) of the PPA and (c) it must result
in change in cost of or revenue from the business of selling electricity
under the PPA.
32. Learned Senior Counsel contends that the respondent to claim
relief under, ‘change in law’ must establish with documentary proof
that consequent to change in law there has been a decrease in capital
cost and since the appellant in its bid submitted on 09.10.2009 had
factored in the benefit derived from the Cabinet Decision in relation
to Mega projects, it received no economic benefit and there was no
change in the cost or revenue from the business of selling electricity
under the PPA in view of the issuance of the notification on
11.12.2009.
31
33. Learned senior counsel contended that there was no notice for
change in law issued by the respondent under Article 13.3.2; no proof
of reduction in capital cost and no issuance of supplementary bill.
Further, learned senior counsel contended that no petition claiming
change in law or any counter claim to the same effect was filed by
the respondent and it was the appellant which approached the State
Commission contending that the Cabinet Decision dated 01.10.2009
is law as on the cutoff date and thus, there was no change in law event
enuring to the advantage of the respondent. It is further contended
for the appellant that the Mega Power Policy issued in 2006 was
issued by way of an executive decision and that the present Cabinet
Decision is also issued under Article 77 of the Constitution of India;
that the requirement to place the Cabinet Decision before the
President is only for information and on this aspect no Presidential
assent is a prerequisite. Lastly, it is contended that as per Rule 50(13)
of the Central Secretariat, Manual of Office Procedure, the Press
Communique/Note is the approved formal procedure of
communication. Learned senior counsel relied on a large number of
precedents in support of his submissions.
32
Submission of the Respondent
34. While stoutly defending the orders of the fora below, learned
senior counsel for the respondent contends that change in law for the
purpose of customs duty insofar as the appellant is concerned was
brought into force only on 11.12.2009 with the issuance of customs
notification under Section 25 of the Customs Act 1962; that Section
25(1) of the said Act provides for exemption from the payment of
customs duty to be by notification; that Sub-Section 4 of Section 25
inter alia provides that every notification unless otherwise provided
shall come into force on the date of its issue by the Central
Government for publication in the Official Gazette and that Cabinet
Decision by itself cannot therefore effect such a change without a
notification under Section 25 since if something is specified to be
done in a particular manner it needs to be done in that manner and in
no other. In view thereof, it was contended that it was the customs
notification dated 11.12.2009 which brought into force the ‘change
in law’.
35. Learned senior counsel for the respondent contended that
without prejudice to the above submissions, the Cabinet Decision
33
dated 01.10.2009 was only the intent or proposal to implement
something in future and not to give effect to something on
01.10.2009 itself ; the Cabinet Decision does not also provide that
the benefits therefrom will be effective from 01.10.2009; that the
Cabinet Decision/Press release by no means can be said to be a
regulation, notification, Code, Rule, or order having a force of law as
specified in the definition of the term “Law” in the PPA; that under
the Rules of Business of the Central Government, the decision taken
in the Cabinet ought to get implemented in the manner provided or
under the relevant statute such as by Notification, Rule, Regulation
or Code in the case of the plenary legislation, such as the Customs
Act; in the absence of any plenary legislation, the manner of
implementation is provided under Article 77 by the issuance of an
authenticated instrument in the manner provided thereon; that the
definition of the term “Law” in the PPA and the expression
“Decision” is limited only with regard to the decision by the
Appropriate Commission and not an Indian Governmental
instrumentality. Learned senior counsel contends that there is no
scope for the argument of the promissory estoppel in inter-partes
34
disputes between the appellant and the respondent since the Union of
India is not a party and the present proceeding is not a proceeding
where a promise is sought to be enforced by a Court of law, against
the promisor.
36. The learned senior counsel contends that the appellant under
Clauses 2.7.2.1 and 2.7.2.2 ought to have considered only the
applicable law. It is further contended that the Cabinet Decision of
01.10.2009 did not decide all the aspects of the distribution reforms
to be undertaken by the concerned State Government to entitle the
intra-state power projects in the State to be eligible for Mega Power
benefits. To illustrate, it is contended that the Cabinet Decision stated
that “Power Purchasing States” shall undertake to carry out
distribution reforms as laid down by the Ministry of Power. Learned
senior counsel contends that Ministry of Power laid down the
conditions on 03.12.2009 including an undertaking to be given by the
State Government to the Government of India as a pre-condition. In
view of this, learned senior counsel contends that the Cabinet
Decision was not in complete form and it was only after the
conditions were laid down by the Ministry of Power on 03.12.2009
35
that the notification dated 11.12.2009 and office memorandum of
14.12.2009 was issued by the Central Government providing for
exemption to Mega Power Projects specifically stating that “The
Power Purchasing State shall undertake to carry out distribution
reforms as laid down by the Ministry of Power”. Learned senior
counsel contends that the Mega Power Policy was issued only on
14.12.2009 with further additions. In view of the same, learned
senior counsel for the respondents contend that there is no scope for
interference with the concurrent judgments of the Courts below.
Question for consideration:
37. In the above background, the question that arises for
consideration is: Whether the press release of 01.10.2009
announcing the decision of the Union Cabinet about approval of
certain modifications envisaged in the then existing mega power
policy, is covered within the meaning of the expression “law as
defined in Clause 1.1 of the RFP/PPA and if so did the extant legal
regime as on 01.10.2009 undergo a change from the said date”?
36
Analysis and reasons:
38. The appellant’s case, as set out above, is that with the press
release on 01.10.2009, a new legal regime commences and on that
basis, it is contended that the appellant in its bid of 09.10.2009
factored the altered position including the fiscal benefits due to
customs duty exemptions. The respondent’s case is that the press
release of 01.10.2009 only sets out the proposal for modification and
the real modification happened on 11.12.2009 and 14.12.2009
(preceded by the letter of 03.12.2009). According to them, since the
change of law having happened on 11.12.2009/14.12.2009 the
benefits that have accrued to the appellant ought to be passed on. This
is the simple issue to be resolved.
39. To answer this question, certain clauses from RFP needs to be
set out. The RFP carried the format of the power purchase agreement
as Format 1 Annexure 3. There is no dispute that the same clauses
occurred in the power purchase agreement executed on 18.01.2010.
Clause 1.1 defines law as under :
“Law: means, in relation to this Agreement, all laws including
Electricity Laws in force in India and any statute, ordinance,
regulation, notification or code, rule, or any interpretation of any
of them by an Indian Governmental Instrumentality and having
37
force of law and shall further include all applicable rules,
regulations, orders notifications by an Indian Governmental
Instrumentality pursuant to or under any of them and shall include
all rules, regulations, decisions and orders of the Appropriate
Commission.”
40. The relevant Clauses read as under:-
“13 ARTICLE 1.3 Change in Law
13.1 Definitions
In this Article 13, the following terms shall have the following
meanings.
13.1.1 “ Change in Law” means the occurrence of any of the
following events after the date, which is seven (7) days prior to
the Bid Deadline;
(i) the enactment, bringing into effect, adoption, promulgation,
amendment, modification or repeal, of any law or (ii) a change
in interpretation of any law by a competent court of law,
tribunal or Indian Governmental instrumentality provided such
Court of law, tribunal or Indian Governmental Instrumentality
is final authority under law for such interpretation or (iii)
change in any consents approvals or licenses available or
obtained for the project, otherwise than for default of the seller,
which results in any change in any cost of or revenue from the
business of selling electricity by the seller to the procurer under
the terms of this agreement or (iv) any change in the (a) declared
price of land for the project or (b) the cost of implementation of
the resettlement and rehabilitation package of the land for the
project mentioned in the RFP or (c) the cost of implementing
environmental management plan for the power station (d)
deleted.
but shall not include (i) any change in any withholding tax on
income or dividends distributed to the shareholders of the
Seller, or (ii) change in respect of UI Charges or frequency
intervals by an Appropriate Commission.
38
13.1.2 “Competent Court” means:
The Supreme Court or any High Court, or any tribunal or any
similar judicial or quasi-judicial body in India that has
jurisdiction to adjudicate upon issues relating to the Project.
13.2 Application and Principles for computing impact of
Change in Law
While determining the consequence of Change in Law under
this Article 13, the Parties shall have due regard to the principle
that the purpose of compensating the Party affected by such
Change in Law, is to restore through Monthly Tariff payments,
to the extent contemplated in this Article 13, the affected Party
to the same economic position as if such Change in Law has not
occurred.
a) Construction Period
As a result of any Change in Law, the impact of
increase/decrease of Capital Cost of the Project in the Tariff
shall be governed by the formula given below:
For every cumulative increase/decrease of each Rupees
16,50,00,000/-
(Rupees Sixteen crore fifty lakhs) in the Capital Cost over the
term of this Agreement, the increase/decrease in Non Escalable
Capacity Charges shall be an amount equal to 0.267%
(percentage zero point two six seven) of the Non Escalable
Capacity Charges. Provided that the Seller provides to the
Procurer documentary proof of such increase/decrease in
Capital Cost for establishing the impact of such Change in Law.
In case of Dispute, Article 17 shall apply:
It is clarified that the above mentioned compensation shall be
payable to either Party, only with effect from the date on which
the total increase/decrease exceeds amount of Rupees
16,50,00,000/- (Rupees Sixteen crore fifty lakhs).
b) Operation Period
39
As a result of Change in Law, the compensation for any
increase/decrease in revenues or cost to the Seller shall be
determined and effective from such date, as decided by the
Appropriate Commission whose decision shall be final and
binding on both the Parties, subject to rights of appeal provided
under applicable Law.
Provided that the above mentioned compensation shall be
payable only if and for increase/decrease in revenues or cost to
the Seller is in excess of an amount equivalent to 1% of the
Letter of Credit in aggregate for a Contract Year.
13.3 Notification of Change in Law
13.3.1 If the Seller is affected by a Change in Law in accordance
with Article 13.2 and wishes to claim a Change in Law under
this Article, it shall give notice to the procurer of such Change
in Law as soon as reasonably practicable after becoming aware
of the same or should reasonably have known of the Change in
Law.
13.3.2 Notwithstanding Article 13.3.1, the Seller shall be
obliged to serve a notice to the Procurer under this Article
13.3.2 if it is beneficially affected by a Change in Law. Without
prejudice to the factor of materiality or other provisions
contained in this Agreement, the obligation to inform the
Procurer contained herein shall be material.
Provided that in case the Seller has not provided such notice,
the Procurer shall have the right to issue such notice to the
Seller.
13.3.3 Any notice served pursuant to this Article 13.3.2 shall
provide, amongst other things, precise details of:
(a) the Change in Law; and
(b) the effects on the Seller of the matters referred to in Article
13.2.
40
13.4. Tariff Adjustment Payment on account of Change in
Law
13.4.1 Subject to Article 13.2., the adjustment in Monthly Tariff
Payment shall be effective from:
(i) the date of adoption, promulgation, amendment,
re-enactment or repeal of the Law or Change in Law; or
(ii) the date of order/judgment of the Competent Court or
tribunal of Indian Governmental Instrumentality, if the Change
in Law is on account of a change in interpretation of Law.
13.4.2 The payment for Changes in Law shall be through
Supplementary Bill as mentioned in Article 11.8. However, in
case of any change in Tariff by reason of Change in Law, as
determined in accordance with this Agreement, the Monthly
Invoice to be raised by the Seller after such change in Tariff
shall appropriately reflect the changed Tariff.”
41. The golden rule of interpretation is that the words of a contract
should be construed in their grammatical and ordinary sense, except
to the extent that some modification is necessary in order to avoid
absurdity, inconsistency or repugnancy. (See para 5.01 Kim
Lewison, The interpretation of Contracts, 3
rd
Edition). Similarly,
any invocation of the business efficacy test as canvassed would arise
only if the terms of the contract are not explicit and clear. The
business efficacy test cannot contradict any express term of the
contract and is invoked only if by a plain and literal interpretation of
the term in the agreement or the contract, it is not possible to achieve
41
the result or the consequence intended by the parties acting as
prudent businessmen. [See Nabha Power Limited (NPL) vs. Punjab
State Power Corporation Limited (PSPCL) and Another, (2018) 11
SCC 508, (para 49) and Adani Power (Mundra) Limited vs. Gujarat
Electricity Regulatory Commission and Others, (2019) 19 SCC 9
(para 24).
42. The law as defined in Clause 1.1 was validly promulgated vide
the notification of 01.03.2002 and the policy document dated
07.08.2006. The appellant seeks to contend that the press release of
01.10.2009 announcing the Cabinet decision approving the modified
Mega Power Policy as envisaged tantamounts to “law” as defined in
Clause 1.1 of the Request For Proposal. The appellant contends that
qua the Power Purchase Agreement (PPA), the press release of
01.10.2009 would be an order and covered by the phrase “and shall
include all applicable rules, regulations, orders, notifications by an
Indian Governmental Instrumentality”. We are unable to accept this
submission. First of all, the commonly understood meaning of the
word “order” as defined in Black’s Law Dictionary is as follows:-
42
“Order – A command, direction or instruction.
See MANDATE (1) 2. a written direction or command
delivered by a government official, esp. a court or judge.”
43. The press release of 01.10.2009 certainly does not fulfil the
meaning of the word “order” as understood in legal parlance. As
explained earlier, the Press Release with all its future eventualities
and conditionalities is only a proposal and it is only after the
undertakings were agreed to be given by the State Government that
a final shape was given in the form of a Section 25 customs
notification on 11.12.2009 and by the policy document of
14.12.2009. The press release announcing the cabinet approval of
certain modifications envisaged in the existing Mega Power Policy
is not law as defined in Clause 1.1 of the PPA. Further, the press
release does not enact, adopt, promulgate, amend, modify or repeal
any existing law or bring into effect any law. This aspect has been
elaborated hereinbelow. Hence, the appellant’s would fail on the
ground that the press release of 01.10.2009 is not law and as of
01.10.2009, the continuing legal regime was as per the notification
of 01.03.2002 issued under Section 25 of the Customs Act and the
Mega Power Policy of 07.08.2006 and there was no alteration of that
43
legal regime on 01.10.2009. The change in law occurred only on
11.12.2009/14.12.2009, and the respondent no. 1 has rightly been
held by the fora below to be entitled to the benefits, which ultimately
will go to the consumers.
44. The argument feebly advanced by the appellant that no notice
of change of law was issued by the respondent under Clause 13.3.1
and 13.3.2 does not impress us. The said clause expressly deals only
with a seller having to issue the notice if it is beneficially affected by
the change of law. In this case, PSPCL is the buyer. Further, post
the change in law on 11.12.2009/14.12.2009 there is a change in cost
with the reduction of customs duty which will enure to the benefit
the appellant-seller and under 13.1.1. the benefit ought to be passed
on to the respondent.
45. The words of clause 13.1.1 read with the definition of law in
Clause 1.1 are plain and clear. For a change in law to occur, the
following events ought to have happened seven days prior to the bid
deadline that is on 02.10.2009 in our case; (i) the enactment brining
into effect, adoption, promulgation, amendment, modification or
repeal of any law or (ii) a change in interpretation of any law by a
44
competent court of law, Tribunal or Indian Governmental
instrumentality provided such court of law, Tribunal or Indian
Governmental instrumentality is the final authority under law for
such interpretation or (iii) change in any consents, approvals or
licences available or obtained for the project, otherwise than for
default of the seller, which results in any change in any cost or
revenue from the business of selling electricity by the seller to the
procurer under the terms of this agreement or (iv) any change in the
(a) declared price of land for the project or (b) the cost of
implementation of the resettlement and rehabilitation package of the
land for the project mentioned in RFP or (c) the cost of implementing
environmental management plan for the power station but shall not
include (i) any change in any withholding tax on income or dividends
distributed to the shareholders of the Seller, or (ii) change in respect
of UI Charges or frequency intervals by an Appropriate Commission.
46. Considering the facts of the case and the arguments, we are
very clear that the case of the parties is not based on any change in
interpretation or change in consent, approval or licence so these sub
clauses of the opening part of 13.1.1 is ruled out. Equally, the latter
45
part dealing with price of land for the project and cost of
implementation and rehabilitation package of land or cost of
implementing environmental management plan is also not attracted.
47. The question that remains is the applicability of sub clause (i)
of clause 13.1.1 namely, when did the change in law happen? For
13.1.1. (i) to be attracted there has to be an enactment, bringing into
effect, adoption, promulgation, amendment, modification or repeal
of any law. Further, if there was a change in law the question would
be, did it result in any change in any cost or revenue from the
business of selling electricity by the seller to the procurer under the
terms of the agreement.
48. It is important to keep in mind the definition of law which has
been defined to mean in relation to this Agreement, all laws including
Electricity Laws in force in India and any statute, ordinance,
regulation, notification or code, rule or any interpretation of any of
them by an Indian Governmental instrumentality and having force of
law and shall further include all applicable rules, regulations, orders,
notification by an Indian Governmental instrumentality pursuant to
or under any of them and shall include all rules, regulations,
46
decisions and orders of the Appropriate Commission. We are
convinced that the words “shall include all rules, regulations,
decisions and orders of the Appropriate Commission”, only refer to
the rules, regulations, decisions and orders of the Appropriate
Commission.
49. It is important to bear in mind that ‘law’ is one thing and
‘change in law’ is another, in the sense that the two are two different
concepts. For the case in question, we need to understand what the
extant law was on 01.10.2009 and then decide whether there was a
legal regime alteration as defined under 13.1.1 on the said date.
50. The law, as it stood prior to the press release of 01.10.2009
insofar as the financial implications for the matter is concerned, was
the notification under Section 25 of the Customs Act issued on
01.03.2002 and entry 400 thereof, extracted in the earlier part of this
judgment. That notification, subject to the conditions mentioned
thereon in entry 400 granted exemption from customs duty for import
of goods required for setting up of any Mega Power project if such
Mega Power project was an inter-State power plant and if it fulfilled
the other conditions mentioned in the notification. Section 25(1) of
47
the Customs Act under which the notification is issued reads as
under:
“25. Power to grant exemption from duty.- (1) If the Central
Government is satisfied that it is necessary in the public interest
so to do, it may, by notification in the Official Gazette, exempt
generally either absolutely or subject to such conditions (to be
fulfilled before or after clearance), as may be specified in the
notification goods of any specified description from the whole
or any part of duty of customs leviable thereon.”
51. It will be very clear that for an exemption under the Customs
Act to operate thereon there has to be a notification issued in the
manner provided by the Customs Act and duly published in the
official gazette. It is so well settled that if a certain thing has to be
done in a certain manner, it shall be done in that manner or not at all.
[See Babu Verghese and Others vs. Bar Council of Kerala and
Others, (1999) 3 SCC 422, relying on Taylor vs. Taylor, (1875) 1 C
h D 426 and Nazir Ahmad vs. King Emperor, AIR 1936 PC 253].
Further, Section 21 of the General Clauses Act, 1897 clearly
prescribes as under:-
“21. Power to issue, to include power to add to, amend, vary
or rescind, notifications, orders, rules or bye-laws.—Where,
by any Central Act or Regulation, a power to issue notifications,
orders, rules, or bye-laws is conferred, then that power includes
a power, exercisable in the like manner and subject to the like
48
sanction and conditions (if any) to add to, amend, vary or rescind
any notifications, orders, rules or bye-laws so issued.”
(Emphasis Supplied)
There was no duly constituted amendment notification as on
01.10.2009.
52. The exemption notification has to be read with the then extant
policy of 07.08.2006 under which Mega Power Policy, to obtain a
Mega Power Status, the plant had to be an inter-State power plant of
the prescribed dimensions and if it were so, certain financial
concessions/benefits were to be available to it under the policy
document. Admittedly, that policy of 07.08.2006 was duly
promulgated by the Government of India through Ministry of Power
and there is no dispute on this score.
53. What the appellant contends is that with the press release on
01.10.2009 and they having received no positive response to the
letters of 02.10.2009 and 06.10.2009 (since withdrawn), they in their
bid of 09.10.2009 factored in the benefits that would be available in
view of the Cabinet decision as announced in the press release of
01.10.2009. According to the appellants, as such, when the
notifications for amendment were issued on 11.12.2009 and when
49
the policy document was amended on 14.12.2009, there was no
change in law because the legal regime stood altered on 01.10.2009
with the press release. Respondents contended that any clarification
for the bid ought to have been sought before 25.09.2009 and
independent of that they also contend that press release of 01.10.2009
does not tantamount to law and that the change in law happened only
on 11.12.2009/14.12.2009.
54. The scenario that emerges is that there was a legal regime
operating, which continued to have force since there was no repeal
of the notification of 01.03.2002 or the supersession of the Mega
Power Policy document of 07.08.2006 on 01.10.2009. The press
release clearly mentioned as to what was envisaged and the
conditions that were to be replaced and removed.
55. In our considered opinion, the press release did not
alter/amend/repeal the existing law as on 01.10.2009. It was at best
the announcement of a proposal approved by the Cabinet which had
to be given shape after fulfilment of the conditions mentioned
therein. Some of the conditions were that the power purchasing
States were to undertake to carry out distribution reforms as laid
50
down by the Ministry of Power and admittedly in that regard there
was a meeting held on 28.10.2009; an undertaking was sought from
the States in the prescribed formats and the four distribution reform
measures required to be undertaken were part of the undertaking.
Those four measures are (a) timely release of subsidy as per Section
65 of the Electricity Act, 2003 (b) Ensure that discoms will approach
SERC for approval of annual revenue requirement/tariff
determination in time according to SERC regulations (c) Setting up
of Special Courts as provided in the Electricity Act, 2003 to tackle
the related cases and (d) ring fencing of SLDCs.
56. It was thereafter on 11.12.2009 in due compliance with the
provisions of Section 25 of the Customs Act that the amendment
notifications were issued which expressly specified the condition that
the power purchasing States ought to have undertaken to carryout
distribution reforms as laid out by the Ministry of Power. It is only
with the promulgation of the 11.12.2009 notification that entry 400
of the 01.03.2002 notification issued earlier in 2002 was substituted
to cover goods required for setting up of any Mega Power Project (as
now defined and set out in the notification of 11.12.2009 and
51
elaborated in the policy document of 14.12.2009) did the ‘change in
law’ happen.
57. Could the appellant has assumed that the Press Release of
01.10.2009 ordained a new legal regime? We think not and we hold
accordingly. The press release is a summary of the Cabinet decision.
Even the press release makes it clear that it was a proposal that was
envisaged and which was to come into force in future.
58. Certainty is the hallmark of law. It is one of its essential
attributes. It is an integral component of the rule of law. What was
certain on 01.10.2009 in the context of our case was only the
prevalent customs notification of 01.03.2002 issued under section 25,
duly notified and gazetted as well as the Mega Power Policy
document admittedly promulgated on 07.08.2006.
59. The press release summarizing the Cabinet decision and beset
with several conditions created no vested rights on any party to the
power purchase agreement vis-a-vis the other party on 01.10.2009.
In fact, the press release itself contemplated certain contingencies. A
right vests when all the facts have occurred which must by law occur
in order for the person in question to have the right (see Salmond on
52
Jurisprudence, Twelfth Edition P.J. Fitzgeral page 245). It is
only when the right vests will there be a corelative duty on the other
as far as nature of the right involved in the present case is concerned.
60. Accepting the argument would also create tremendous
uncertainties in the law. In the absence of any repeal of 01.03.2002
notification and the 07.08.2006 Mega Power Policy, between
01.10.2009 and 11.12.2009/14.12.2009 there will be two legal
regime operating.
61. Lord Bingham of Cornhill in his locus classicus ‘The Rule
of Law’ rightly identifies as one of the facets of rule of law, the
following – “the law must be accessible and so far as possible
intelligible, clear and predictable.” The second and third reason given
to support the principle makes for fascinating reading and are
reproduced hereinbelow.
“The second reason is rather similar, but not tied to the criminal
law. If we are to claim the rights which the civil (that is, non-
criminal) law gives us, or to perform the obligations which it
imposes on us, it is important to know what our rights or
obligations are. Otherwise we cannot claim the rights or
perform the obligations. It is not much use being entitled to, for
example, a winter fuel allowance if you cannot reasonably
easily discover your entitlement, and how you set about
claiming it. Equally, you can only perform a duty to recycle
53
different kinds of rubbish in different bags if you know what
you are meant to do.
The third reason is rather less obvious, but extremely
compelling. It is that the successful conduct of trade, investment
and business generally is promoted by a body of accessible legal
rules governing commercial rights and obligations. No one
would choose to do business, perhaps involving large sums of
money, in a country where the parties' rights and obligations
were vague or undecided. This was a point recognized by Lord
Mansfield, generally regarded as the father of English
commercial law, around 250 years ago when he said: The daily
negotiations and property of merchants ought not to depend
upon subtleties and niceties; but upon rules easily learned and
easily retained, because they are the dictates of common sense,
drawn from the truth of the case.”
1
In the same vein he said: 'In
all mercantile transactions the great object should be certainty:
and therefore, it is of more consequence that a rule should be
certain, than whether the rule is established one way or the
other. Because speculators [meaning investors and
businessmen] then know what ground to go upon.”
2
62. Explaining felicitously the said principle, O. Chinnappa Reddy,
J. speaking for this Court in B.K. Srinivasan and Others vs. State of
Karnataka and Others, (1987) 1 SCC 658 ruled:-
“15. There can be no doubt about the proposition that where a law,
whether parliamentary or subordinate, demands compliance, those
that are governed must be notified directly and reliably of the law
and all changes and additions made to it by various processes.
Whether law is viewed from the standpoint of the “conscientious
good man” seeking to abide by the law or from the standpoint of
Justice Holmes's “unconscientious bad man” seeking to avoid the
law, law must be known, that is to say, it must be so made that it
1
Hamilton vs. Mendes (1761) 3 Burr 1198, 1214
2
Vallejo vs. Wheeler (1774) 1 Cowp 143, 153
54
can be known. We know that delegated or subordinate legislation
is all-pervasive and that there is hardly any field of activity where
governance by delegated or subordinate legislative powers is not
as important if not more important, than governance by parliamen-
tary legislation. But unlike parliamentary legislation which is pub-
licly made, delegated or subordinate legislation is often made un-
obtrusively in the chambers of a Minister, a Secretary to the Gov-
ernment or other official dignitary. It is, therefore, necessary that
subordinate legislation, in order to take effect, must be published
or promulgated in some suitable manner, whether such publication
or promulgation is prescribed by the parent statute or not. It will
then take effect from the date of such publication or promulgation.
Where the parent statute prescribes the mode of publication or
promulgation that mode must be followed.…”
(Emphasis supplied)
63. The appellant has relied upon RFP to contend that the Press
release of 01.10.2009 could not have been ignored by them. We do
not find merit in this submission. Those clauses in the RFP obligate
the bidder to satisfy itself about the extant legal regime and those
clauses cannot operate as a crutch to elevate the press release of
01.10.2009 to the status of law under Clause 1.1. of the PPA.
64. We have also found that the terms of the contract to be clear
and hence there is no scope for applying any business efficacy test to
interpret the contract as was sought to be contended for the appellant.
65. One of the arguments advanced by the learned senior counsel
for the appellants is based on the doctrine of promissory estoppel.
The argument need not detain us since the respondent PSPCL which
55
is the party to power purchase agreement is not the promisor, even if
we assume the press release of 01.10.2009 as holding out the
promise. The Union of India has not been arrayed in any duly
constituted litigation to enforce the promise. The argument also
belies the primary contention of the appellant since even according
to their understanding, it was at best a promise by the Union of India
and not any alteration of the law proprio vigore (by its own force).
In any case, no steps have been taken to enforce the so-called promise
and there is no order of any court of law enforcing the promise as on
02.10.2009. The appellant contends that since the promise was duly
complied with, there was no need to enforce the promise. This is
also an argument which cuts at the root of appellants main
submission. The notifications constituting change in law happened
on 11.12.2009 and 14.12.2009 and hence there is no basis in the
contention that on 01.10.2009 the old legal regime had given way.
66. The judgments cited by learned Senior Counsel for the
appellant also do not in any manner support the case of the appellant.
In GMR Warora Energy Limited vs. Central Electricity Regulatory
Commission [CERC] and Others, (2023) 10 SCC 401, this Court
56
found that busy season surcharge, development surcharge, and port
congestion surcharge were increased by circular/notifications issued
by the Ministry of Railways by virtue of the powers vested in them
which were enforceable commands proprio vigore. Similarly, the
letters carrying the decisions of Coal India on the aspect of charges
for linkage coal and the direction to use beneficiated coal were held
to be statutory documents having the force of law. The press release
of 01.10.2009 does not enjoy the same legal characteristics for the
reasons already set out hereinabove.
67. Equally, for the same reason, the judgment in Energy
Watchdog vs. Central Electricity Regulatory Commission and
Others, (2017) 14 SCC 80 will also not help the appellant. The
appellant’s main reliance has been on Lloyd Electric and
Engineering Limited vs. State of Himachal Pradesh and Others,
(2016) 1 SCC 560. In Lloyd Electric (supra), the appellant therein
was already enjoying the concessional rate in CST @ 1% up to
31.03.2009. Not only this, after the Cabinet note, a policy decision
was taken to extend the period of concession up to 31.03.2013 or till
CST was phased out. The Department of Industries had issued a
57
notification extending concessions from 01.04.2009 to 31.03.2013 or
till the time CST is phased out. The dispute arose because the Excise
and Taxation Department issued a notification of 18.06.2009
granting benefit with immediate effect for the period ending
31.03.2013. It was in that context that this Court held that the State
Government cannot speak in two voices and gave effect to the
notification of the Industries Department so as to maintain continuity
in exemption from 01.04.2009 and set aside the judgment of the High
Court which denied exemption from 01.04.2009 till 18.06.2009
which was the date on which the Excise Department issued the
notification. Unlike in Lloyd Electric (supra), in this case, there is
only one voice of the government which has given the customs duty
exemption for goods imported for use in thermal power plants,
(without the requirement of the plant being an interstate power plant)
with effect from 11.12.2009. The policy document also came on
14.12.2009. The press release of 01.10.2009 could not have been the
basis for the appellant to have assumed that the notification of
01.03.2002 would stand amended and they would have the benefit
from 01.10.2009 itself.
58
68. In Uttar Haryana Bijli Vitran Nigam Limited and Another vs.
Adani Power (Mundra) Limited and Another, (2023) 7 SCC 623,
this Court held that the communication of 19.06.2013 in that case
effected a modification to the mutual Fuel Supply Agreement and by
force of the communication, transfer of coal, which was not allowed
till then, was allowed between power plants. This Court held that the
communication reflected the decision of the Coal India Limited
which was an instrumentality of the Government of India. The said
case has no application to the facts of the present case.
69. The judgment in Burn Standard Company Limited Vs.
McDermott International INC and Anr., (1991) 2 SCC 669 also
does not advance the case of the appellant. That case dealt with
permission granted to an individual entity and whether on the facts
of that case there existed a valid permission by the Reserve Bank of
India. The issue involved in the present case is vastly different and
we find the judgment in Burn Standard (Supra) of no relevance to
this case.
70. The judgment closer to our facts is Maharashtra State
Electricity Distribution Company Limited vs. Adani Power
59
Maharashtra Limited and Others, (2023) 7 SCC 401. In the said
case, neither the decision of the Cabinet Committee on Economic
Affairs dated 06.02.2013 nor the Press Release of 21.06.2013 was
considered as the relevant date for change in law and only 26.07.2013
which was the date on which the Office Memorandum was issued
providing further instructions regarding the implementation of the
New Coal Distributional Policy [NCDP] was considered as the
change in law event. Pursuant to the Office Memorandum of
26.07.2013, the Ministry of Power issued a communication of
31.07.2013 setting out the decision taken. This case clearly supports
the case of the respondent that the press release of 01.10.2009 on the
facts herein could not have been the basis for the appellant to assume
that a new legal regime had commenced in with effect from that date.
71. Though several judgments were cited, including Bachhittar
Singh vs. The State of Punjab, [1962] Supp. 3 SCR 713, to contend
that the press release of 01.10.2009 was not an “order”, we do not
propose to examine them as we are otherwise convinced for the
reason set out above that the 01.10.2009 Press Release is not law
under Clause 1.1. Equally, for that reason, we have not discussed the
60
cases on Article 77 of the Constitution of India, dealing with
authentication of orders.
72. The State Commission while rejecting the contention of the
appellant has rightly recorded the following operative findings:-
“In view of the above findings, the Commission holds that
since the Mega Power Status was granted to the Project under
the Mega Power Policy by the Ministry of Power on
30.07.2010 on the application dated 11.05.2010 filed by the
respondent no.1, having become eligible on 16.04.2010, the
benefits, if any, accruing thereunder to the Project would be
applicable only from 30.07.2010 and not from any prior date,
notwithstanding that the decision for granting the Mega Power
Status was taken/announced on 01.10.2009 or the notifications
in respect of the said decision of the Union Cabinet were
issued by the concerned Ministries of the Government of India
on 11.12.2009 and14.12.2009.”
73. For the reasons set out hereinabove, we find no reason to
interfere with the concurrent judgments of the courts below. The
Civil Appeal is dismissed. No order as to costs.
……….………………J.
(B.R. Gavai)
.…...…………………J.
(Prashant Kumar Mishra)
.…...…………………J.
(K.V. Viswanathan)
New Delhi;
5
th
November, 2024.
Legal Notes
Add a Note....