As per case facts, a company petitioned the court to extend the time limit for an arbitrator to finish proceedings and pass an award. The delay was caused by the ...
O.M.P. (MISC) (COMM) 592/2025 Page 1 of 17
$~J
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment reserved on: 10.10.2025
Judgment pronounced on: 14.01.2026
+ O.M.P. (MISC.) (COMM.) 592/2025
NCC LIMITED ...Petitioner
Through: Dr. Amit George,
Mr. Adhishwar Suri,
Mr. Dusyant Kishan Kaul,
Ms. Ibansara Syiemlieh,
Ms. Rupam Jha, Advocates.
versus
INDIAN OIL CORPORATION LIMITED ...Respondent
Through: Mr. VN Koura,
Ms.Paramjeet Benipal,
Advocates.
CORAM:
HON'BLE MR. JUSTICE JASMEET SINGH
J U D G M E N T
1. This is a petition filed under section 29A(4) read with 29A(5) of the
Arbitration and Conciliation Act, 1996 (“the Act”), seeking extension of
the mandate of the Sole Arbitrator for a period of one year for
concluding the arbitral proceedings and passing the arbitral award.
FACTUAL MATRIX AS PER THE PETITIONER
O.M.P. (MISC) (COMM) 592/2025 Page 2 of 17
2. The petitioner, namely NCC Limited, is a company having its registered
office at Survey No. 64, Corporate Office, Madhapur, Hyderabad
(500081), Telangana.
3. The respondent, namely Indian Oil Corporation Limited, is a
Government of India undertaking having its registered office at G-9, Ali
Yavar Jung Marg, Bandra (East), Mumbai (400050), Maharashtra.
4. The respondent floated a tender for “Civil, Structural & Associated UG
piping works of VGO-HDT, DHDT & HCDS Units (EPCM-2)” for the
Paradip Refinery Project (“the project”). The petitioner was declared as
the successful bidder for the project and consequently, the parties entered
into a formal Agreement dated 28.04.2010.
5. The Agreement between the party clearly designated the commencement
date for the project as 03.03.2010 with scheduled completion date as
02.10.2011. However, the project was ultimately completed with delays
on 28.12.2015. Subsequently, disputes arose regarding payments due
under the terms of the contract.
6. The petitioner invoked the arbitration Agreement vide communication
dated 01.07.2017. Upon failure of the parties to mutually agree on the
constitution of the Arbitral Tribunal, the petitioner approached this
Hon’ble Court by filing a petition under Section 11 of the Act.
7. This Court in a petition under Section 11 of the Act, vide judgment dated
08.02.2019 in NCC Limited v. Indian Oil Corporation Limited
1
,
rejected the objections raised by the respondent and appointed the Sole
Arbitrator to adjudicate the disputes between the parties. The Sole
1
(Arb.Pet.115/2018).
O.M.P. (MISC) (COMM) 592/2025 Page 3 of 17
Arbitrator entered reference and held its first hearing on 05.03.2019,
directing completion of pleadings by 01.07.2019.
8. The respondent challenged the appointment of the Sole Arbitrator before
the Hon’ble Supreme Court by way of a Special Leave Petition S.L.P.
(C.) 13161/2019. Consequently, the Hon’ble Supreme Court vide orders
dated 03.07.2019 and 18.07.2019, stayed further arbitral proceedings.
9. The respondent also preferred an Application under Section 16 of the
Act challenging the jurisdiction of the Sole Arbitrator. The Hon’ble
Supreme Court, vide judgment dated 20.07.2022 decided the Civil
Appeal no. 341 of 2022 arising out of the aforesaid SLP, and dismissed
the respondent’s appeal but directed the Sole Arbitrator to first
adjudicate the pending Section 16 Application regarding “accord and
satisfaction” and arbitrability of the disputes within 3 months from the
date of first sitting.
10. In pursuance of the aforesaid directions, the arbitral proceedings were
resumed on 15.12.2022, wherein the Sole Arbitrator directed the parties
to complete the pleadings with regards to the Section 16 Application by
15.02.2023. However, the timeline for deciding the Section 16
Application was extended with the consent of parties by 5 months vide
Procedural Order No. 3, and the said Application was ultimately
dismissed vide Procedural Order No. 7 dated 16.08.2023. The respondent
thereafter delayed filing its Statement of Defence (“SOD”) and
ultimately filed the same on 30.04.2024, subject to costs.
11. The petitioner filed its rejoinder on 17.06.2024, and on this date i.e.
17.06.2024, the pleadings were completed. Consequently, the statutory
O.M.P. (MISC) (COMM) 592/2025 Page 4 of 17
period of twelve months under Section 29A(1) of the Act commenced
from 17.06.2024 and expired on 17.06.2025.
12. The arbitral proceedings are presently at an advanced stage as the Cross-
examination of the respondent’s sole witness is also completed.
13. Hence, through the present petition, the petitioner has approached this
Court seeking extension of the mandate of the Sole Arbitrator under
Section 29A of the Act.
SUBMISSIONS ON BEHALF OF THE PETITIONER
14. Dr. Amit George, Ld. Counsel for the petitioner, contends that the
commencement of the 12 month statutory period is calculated from the
date of completion of pleadings, and relying on the judgment of this
Hon’ble Court in Emco Limited v. Delhi Transco Limited
2
, it is
submitted that when a rejoinder is permitted to be filed by the Arbitral
Tribunal, pleadings stand completed on the date of filing of the rejoinder
which in the present case is 17.06.2024. Thus, the mandate of the Sole
Arbitrator continued for a period of 12 months from 17.06.2024 to
17.06.2025, and the present petition filed on 21.07.2025 is maintainable
even after the expiry of the said period.
15. Dr. George, also submits that the petitioner filed its Statement of Claim
(“SOC”) on 18.04.2019 in accordance with timeline fixed by the
Procedural Order. However, the respondent filed Special Leave Petition
(C) No. 13161/2019 before the Hon’ble Supreme Court challenging the
judgment dated 08.02.2019 of this Court, thereby keeping the arbitral
proceedings in abeyance. Further, the Sole Arbitrator resumed its
proceedings on 15.12.2022 and subsequently by Procedural Order No. 3
on mutual consent, the timeline for deciding the Section 16 Application
2
2024 SCC Online Del 6306.
O.M.P. (MISC) (COMM) 592/2025 Page 5 of 17
was extended by five months, which was sought by the respondent itself
after completion of pleadings in the Application so as to file additional
documents. The Sole Arbitrator disposed of the respondent’s Section 16
Application holding that the settlement of disputes, subject to final
determination after evidence, was not genuine and the “accord and
satisfaction” were conditional, and the arbitration Agreement therefore
survived the purported settlement and the disputes are arbitrable. Further,
the respondent delayed the filing of its SOD by 6 months, which was
ultimately filed on 30.04.2024 and taken on record with costs.
16. Dr. George, further submits that the principal cause for the delay in the
arbitral proceedings is the lackadaisical approach of the respondent,
while at the same time the petitioner has consistently complied with the
timelines for filing of its pleadings before the Sole Arbitrator. The
process of recording oral evidence stands completed as on 26.09.2025.
Thus, non-extension of the mandate at this juncture would result in
severe prejudice to both the parties and would lead to wastage of all the
time and resources invested, and would also defeat the very purpose of
the arbitration.
17. Further he also states, that the contentions raised by the respondent
regarding alleged loss of confidence in the Sole Arbitrator and alleged
misconduct in the conduct of proceedings are wholly misplaced in the
context of a petition under Section 29A of the Act. Relying on decisions
in the case of Poonam Mittal v. Created Pvt. Ltd.
3
and Anay Kumar
Gupta v. Jagmeet Singh Bhatia
4
, it is submitted that the courts while
deciding a petition under Section 29A of the Act should restrict
themselves as to whether the Arbitral Tribunal has proceeded with due
3
2024 SCC Online Del 6621.
4
2023 SCC Online Del 3939.
O.M.P. (MISC) (COMM) 592/2025 Page 6 of 17
expedition and does not permit a review of the conduct or the judicial
determinations made by the Arbitral Tribunal. Thus, the said contention
of the respondent and other grievances cannot be the subject matter of
the proceedings under Section 29A petition.
18. In light of the aforesaid submissions, the Ld. Counsel for the petitioner,
submits that there are sufficient grounds to justify the extension of the
mandate.
SUBMISSIONS ON BEHALF OF THE RESPONDENT
19. Mr. V.N. Koura, Ld. Counsel for the respondent, vehemently opposes
the present petition seeking extension of the mandate of the Sole
Arbitrator and submits that no sufficient cause has been shown for the
grant of such extension under Section 29A(5) of the Act. The mandate of
the Sole Arbitrator terminated on 30.04.2025, as the period of 12 months
contemplated under Section 29A(1) of the Act commences from the date
of completion of pleadings and which is understood as the filing of the
SOD when read with Section 23(4) of the Act and not the rejoinder. In
the present case, the respondent filed its SOD on 30.04.2024, and
consequently the statutory period of one year ended on 30.04.2025, with
the mandate of the Sole Arbitrator terminating on that date.
20. Mr. Koura, further submits that the present arbitration arises out of the
judgment of the Hon’ble Supreme Court in Indian Oil Corporation
Limited (Supra), wherein the Hon’ble Supreme Court provided explicit
and binding directions in clear terms that the Sole Arbitrator shall first
decide the issue of “accord and satisfaction” and the arbitrability of the
disputes by deciding the pending Section 16 Application within a period
of three months from the date of the first sitting held after the judgment.
O.M.P. (MISC) (COMM) 592/2025 Page 7 of 17
21. It is further submitted that the Sole Arbitrator has completely
disregarded the binding directions of the Hon’ble Supreme Court and has
failed to decide the issues of “accord and satisfaction” and arbitrability
of the disputes. Instead, by Procedural Order No. 7, the Sole Arbitrator
dismissed the respondent’s Section 16 Application without deciding the
core issues raised therein. The Sole Arbitrator merely observed that the
issues of “accord and satisfaction” and whether claims are “Notified
Claims”, were “matters of evidence” to be decided at a later stage and
proceeded to direct the respondent to file its SOD on merits.
22. The Ld. Counsel further submits that the respondent thereafter filed
another Application under Section 16 of the Act, raising the objection
that the agreed procedure under Clause 9.0.2.0 of the GCC, requires that
the General Manager first decide whether the petitioner’s claims were
“Notified Claims” included in the Final Bill in accordance with Clause
6.6.3.0 of the GCC, and that the arbitration could not proceed unless
such decision was first rendered. The Sole Arbitrator dismissed this
Application vide Procedural Order No. 8 dated 01.12.2023 and directed
the respondent to file its SOD on merits, thereby disregarding the agreed
contractual procedure binding upon the Sole Arbitrator under Section
19(2) of the Act.
23. The Ld. Counsel emphasizes that the delay in the arbitral proceedings
has occurred solely due to the misconduct of the Sole Arbitrator in
disregarding the Hon’ble Supreme Court’s directions and the agreed
procedure between the parties. The Sole Arbitrator proceeded to record
evidence and conduct substantive proceedings on the merits without first
complying with the directions or the agreed procedure. Such
disobedience of binding directions of the Hon’ble Supreme Court and
O.M.P. (MISC) (COMM) 592/2025 Page 8 of 17
disregard of the agreed procedure amounts to misconduct on the part of
the Sole Arbitrator.
24. Mr. Koura, also submits that in light of the principles explained by the
Hon’ble Supreme Court in Rohan Builders (India) Ltd. v. Berger Paints
India Ltd.
5
, the Court must exercise its judicial discretion under Section
29A(5) only where sufficient cause for extension is clearly show, and
such extension should not be granted mechanically. The misconduct of
the Sole Arbitrator in disregarding the Hon’ble Supreme Court’s
directions and the agreed contractual arbitration procedure constitutes a
ground to refuse extension and to terminate the mandate of the Sole
Arbitrator and to further appoint a substituted arbitrator.
ANALYSIS AND FINDINGS
25. I have heard the learned counsel for the parties and perused the material
and documents placed on record.
26. It is the case of the respondent that the extension under Section 29A of
the Act should not be granted because of the misconduct of the arbitrator
in not deciding the Application which was directed by the Hon’ble Apex
Court in Indian Oil Corporation Limited (Supra), and to arrogate itself
with jurisdiction in clear violation of the terms of the Contract. The
respondent further opposes extension of the mandate and seeks
substitution of the Sole Arbitrator.
27. It will be pertinent to mention the few relevant dates:
Date Event
28.04.2010 The petitioner and the respondent entered
into a formal Agreement.
5
(2025)10 SCC 802.
O.M.P. (MISC) (COMM) 592/2025 Page 9 of 17
28.12.2015 The Project was actually completed by the
petitioner.
01.07.2017 Disputes arose between the parties,
regarding payments due to the petitioner
and the arbitration was invoked by the
petitioner vide letter dated 01.07.2017.
05.03.2019 The Sole Arbitrator held its First Hearing.
18.04.2019 The claimant/petitioner filed its SOC
03.07.2019
&
18.07.2019
The Hon’ble Supreme Court stayed further
proceedings before the Sole Arbitrator.
20.07.2022 The Hon’ble Supreme Court dismissed the
appeal filed by the respondent, while
directing the Sole Arbitrator to firstly
decide the pending Section 16 application.
16.08.2023 The Sole Arbitrator disposed of the
respondent’s Section 16 Application vide
Procedural Order No. 7.
30.04.2024 After multiple opportunities, the respondent
filed its SOD on 30.04.2024.
17.06.2024 The petitioner filed its rejoinder to the
respondent’s SOD.
28. In the present case, the Sole Arbitrator vide Procedural Order No. 10
dated 01.05.2024 allowed the filing of a rejoinder to the SOD. In cases,
when a rejoinder is allowed to be filed by the tribunal and is actually
filed, the pleadings are deemed complete on the date of filing of the
rejoinder and not on the date of filing of the SOD. This position is
O.M.P. (MISC) (COMM) 592/2025 Page 10 of 17
clearly supported by the judgment of this Court in Emco Limited v.
Delhi Transco Limited
6
and the Hon’ble Supreme Court’s order dated
29.04.2024, while dismissing the SLP in Buoyant Technology
Constellations Pvt. Ltd. v. Manyata Infrastructure Developers Pvt.
Ltd.
7
, relevant paragraph of Buoyant (Supra) reads as under:
“We are in agreement with the findings recorded in the
impugned judgment that in case a rejoinder or sur-rejoinder
are filed and taken on record, the pleadings for the purpose
of Section 29A of the Arbitration and Conciliation Act,
1996, shall concluded on the date the last pleading is filed.
We also agree that the period during which there was a stay
of arbitration proceedings has to be excluded.”
29. Further, the present petition seeking extension was filed on 21.07.2025
and the Hon’ble Supreme Court in Rohan Builders (Supra) has
unambiguously held that an Application for extension of mandate under
Section 29A(4) read with 29A(5) is maintainable even after the expiry of
the 12 month or 6 month extended period. The statute also provides that
the Court may extend the time “either prior to or after the expiry of the
period so specified
8
”, the relevant paragraphs of Rohan Builders
(Supra) read as under:
“22. While interpreting a statute, we must strive to give
meaningful life to an enactment or rule and avoid cadaveric
consequences that result in unworkable or impracticable
scenarios. An interpretation which produces an
unreasonable result is not to be imputed to a statute if there
is some other equally possible construction which is
6
2024 SCC Online Del 6306.
7
SLP (C) No. 9331/2024.
8
Section 29A(4), Arbitration and Conciliation Act, 1996.
O.M.P. (MISC) (COMM) 592/2025 Page 11 of 17
acceptable, practical and pragmatic.
23. In view of the above discussion, we hold that an
application for extension of the time period for passing an
arbitral award under Section 29A(4) read with Section
29A(5) is maintainable even after the expiry of the twelve-
month or the extended six-month period, as the case may be.
The court while adjudicating such extension applications
will be guided by the principle of sufficient cause and our
observations in paragraph 19 of the judgment.”
30. In view of the aforesaid position, it is clear that in the present case the
rejoinder was actually filed on 17.06.2024 and thus pleadings were
completed on that date. Accordingly, the 12 month statutory period
commenced from 17.06.2024 and expired on 17.06.2025.
CONDUCT OF THE ARBITRATOR
31. The respondent has raised allegations that the Sole Arbitrator
has disregarded the Hon’ble Supreme Court’s directions in Indian Oil
Corporation Limited (Supra), and violated the agreed contractual
procedure.
32. The Sole Arbitrator decided the Section 16 Application vide Procedural
Order No. 7 dated 16.08.2023, the relevant excerpts from the Procedural
Order No.7, read as under:
“29. The further case of learned counsel is that no
arbitrable disputes have arisen in view of Clause 9.0.2.0,
particularly sub-clauses (ii) and (iii) thereof. It is submitted
that the claims raised by the Claimant are not notified
claims. As far as the submission with regard to Clause
9.0.2.0 is concerned, it is really a matter that will need to be
O.M.P. (MISC) (COMM) 592/2025 Page 12 of 17
decided in the event it is held that arbitrable disputes have
been raised by the Claimant. It is not necessary to decide
this issue at this stage, and this was not disputed by learned
counsel for the Respondent.
xxxx
31. A bare perusal of the italicized portion of this clause
makes it clear that notified claims are not covered by the
prohibition regarding arbitrability. There is no dispute that
the Claimant had raised some disputes which it says are
notified claims. The position accepted by learned counsel
for the Respondent is that the question whether the claims
are indeed notified claims is a matter that will have to be
considered by this Tribunal after the disposal of the
application under Section 16 of the act. If that be so, it may
be assumed for the time being and without prejudice, that
the claims raised by the Claimant in its communication
dated 5th August, 2016 are in fact notified claims. These
claims, in view of a plain reading of Clause 6.7.1.0 of the
GCC, are exempted and are not discharged or extinguished,
with the arbitration clause surviving as far as these claims
are concerned.
xxxx
36. Insofar as the present case is concerned, it is quite clear
that there were disputes between the parties, and one of
them, that is, the Claimant succumbed to what it claims to
be economic coercion. The settlement of disputes under the
circumstances was not a genuine settlement, assuming the
Claimant is able to prove its case of economic coercion. It
O.M.P. (MISC) (COMM) 592/2025 Page 13 of 17
must be held that the accord and satisfaction of the disputes
was conditional as far as the Claimant is concerned. This is
evident from the communications sent by the Claimant. As
such, arbitrable disputes do arise and survive. Under the
circumstances, it must be held that the arbitration clause
would survive the contract in terms of the law clearly
exposited by the Hon’ble Supreme Court (and followed in
subsequent decisions). That being so, the arbitration clause
in the contract survives, and the disputes being arbitrable,
reference to arbitration would be justified.”
33. From a conspectus of the determination of the aforesaid Application by
the Sole Arbitrator, it seems that the Sole Arbitrator has substantially
complied with the directions of the Hon’ble Supreme Court in Indian
Oil Corporation Limited (Supra). Be that as it may, it is not for this
court to decide this issue in detail in the present petition, as that would be
the subject matter of a petition under Section 34 or Section 37 of the Act,
as and when filed by the respondent. It is a settled position of law that
while exercising jurisdiction under Section 29A(4), the Court is only
required to see if sufficient cause exists for the extension of mandate of
the Arbitrator.
SUFFICIENT CAUSE
34. In the present petition, the core issue is whether the petitioner has shown
sufficient cause for extension of the mandate of the Sole Arbitrator. The
relevant factors to be considered for the same are at the judicial
discretion of the court
9
.
9
Paragraph 19, Rohan Builders (Supra).
O.M.P. (MISC) (COMM) 592/2025 Page 14 of 17
35. The disputes in this case emanate from a substantial commercial contract
concerning civil, structural and associated works undertaken at a refinery
project and the project also included issues of delays exceeding four
years. The examination and cross-examination of the witnesses
continued after filing of the rejoinder and additionally, there was also a
Section 16 application which was directed to be decided by the Hon’ble
Supreme Court prior to proceeding further with the arbitration. All of the
aforesaid consumed substantial time and the proceedings presently are at
the stage of addressing final arguments.
36. In Rohan Builders (Supra), the Hon’ble Supreme Court has enunciated
some observations which will guide the adjudication of Applications for
extension filed under Section 29A(4) read with Section 29A(5), the
relevant paragraphs of the judgment read as under:
“19.Rohan Builders [Rohan Builders (India) (P)
Ltd. v. Berger Paints India Ltd., 2023 SCC OnLine Cal
2645] highlights that an interpretation allowing an
extension application post the expiry period would
encourage rogue litigants and render the timeline for
making the award inconsequential. However, it is apposite
to note that under Section 29-A(5), the power of the court to
extend the time is to be exercised only in cases where there
is sufficient cause for such extension. Such extension is not
granted mechanically on filing of the application. The
judicial discretion of the court in terms of the enactment
acts as a deterrent against any party abusing the process of
law or espousing a frivolous or vexatious application.
Further, the court can impose terms and conditions while
O.M.P. (MISC) (COMM) 592/2025 Page 15 of 17
granting an extension. Delay, even on the part of the
Arbitral Tribunal, is not countenanced. [H.P.
Singh v. Northern Railways, 2023 SCC OnLine J&K 1255]
The first proviso to Section 29-A(4) permits a fee reduction
of up to five per cent for each month of delay attributable to
the Arbitral Tribunal.
xxxx
23. In view of the above discussion, we hold that an
application for extension of the time period for passing an
arbitral award under Section 29-A(4) read with Section 29-
A(5) is maintainable even after the expiry of the twelve-
month or the extended six-month period, as the case may be.
The court while adjudicating such extension applications
will be guided by the principle of sufficient cause and our
observations in para 19 of the judgment.”
37. In RCC Infraventures Ltd. & Ors. v. DMI Finance Pvt. Ltd. & Ors.
10
,
this Court while relying on Rohan Builders (Supra) held that the
foundational precept of the Arbitration and Conciliation Act, 1996, is a
litigant centric approach to reduce the cost of litigation and expedite
disposal of cases. From a conspectus of the said decision, it is clear that
the termination of the mandate of the Arbitral Tribunal results in wastage
of time and resources for the parties. This principle applies with greater
force when the proceedings are at an advance stage, the relevant
paragraphs of RCC Infraventures Ltd. (Supra) read as under:
“27. The Hon’ble Supreme Court in the aforesaid judgment
has relied upon the 176th Report of the Law Commission of
India, wherein it was held that the termination of the
10
2024 SCC Online Delhi 8961.
O.M.P. (MISC) (COMM) 592/2025 Page 16 of 17
mandate of the Arbitral Tribunal results in waste of time,
resources and money for the parties. The same is predicated
on the fact that the parties and the Arbitral Tribunal have
invested a lot of time, effort and energy in the arbitral
proceedings. The essence of the A&C Act is a litigant-
centric process to expedite the disposal of cases and
reducing the cost of litigation.
28. In the present case, the mandate of the Sole Arbitrator
terminated on 31.08.2023 and the present petition was filed
on 12.01.2024 i.e. after a period of four and a half months.
29. To my mind, the said delay of four and a half months in
filing the present petition is not an inordinate delay to direct
that the mandate of the Sole Arbitrator should not be
extended or a substitute arbitrator should be appointed.
30. The pleadings in the arbitral proceedings have already
been completed and the Claimants i.e. the petitioners have
started its evidence. In this regard, my attention has been
drawn to order dated 19.09.2023, whereby CW-1 is being
examined. Further, the entire computed fees of the learned
sole arbitrator with respect to the claims has been paid by
the petitioners.”
38. Further, the petitioner has consistently complied with all timelines fixed
by the Sole Arbitrator for SOC dated 18.04.2019 and also for the
rejoinder dated 17.06.2024. However, despite multiple opportunities the
respondent delayed filing of its SOD and the same was only taken on
record subject to costs vide Procedural Order No. 10.
39. It is for the reasons as enumerated above, the petitioner has shown
sufficient cause for seeking extension under Section 29A of the Act. The
O.M.P. (MISC) (COMM) 592/2025 Page 17 of 17
delay in concluding the arbitral proceedings is neither inordinate nor
unexplainable. Further, the termination of mandate would result in
wastage of substantial time and resources already incurred by both
parties and the Sole Arbitrator.
CONCLUSION
40. Having considered all the material issues, I am of the view that sufficient
cause exists under Section 29A of the Act for granting extension of the
mandate of the Sole Arbitrator.
41. For the aforesaid reasons and discussion, the petition is allowed and the
mandate of the Sole Arbitrator is extended by a period of 1 year from the
date of this judgment.
42. The Sole Arbitrator shall conduct the remaining proceedings
expeditiously.
43. The period from 18.06.2025 till today stands regularised.
44. The petition is disposed of accordingly.
JASMEET SINGH, J
JANUARY 14
th
, 2026 / SS
Legal Notes
Add a Note....