infrastructure contract, arbitration, ONGC
0  30 Aug, 2022
Listen in 01:59 mins | Read in 250:00 mins
EN
HI

Oil and Natural Gas Corporation Ltd Vs. Afcons Gunanusa Jv

  Supreme Court Of India Arbitration Petition /05/2022
Link copied!

Case Background

the petitioner, Oil and Natural Gas Corporation Limited1and the respondent, Afcons Gunanusa JV2, entered into a Lump Sum Turnkey

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

1

Reportable

IN THE SUPREME COURT OF INDIA

CIVIL ORIGINAL/APPELLATE JURISDICTION

Arbitration Petition (Civil) No. 0 5 of 2022

Oil and Natural Gas Corporation Ltd. .... Petitioner

Versus

Afcons Gunanusa JV .... Respondent

With

Civil Appeal No 5880 of 2022

With

Civil Appeal No 5879 of 2022

And With

Miscellaneous Application Nos. 1990-1991 of 2019 in Special Leave

Petition (Civil) Nos. 10021- 10022 of 2017

2

J U D G M E N T

Dr Dhananjaya Y Chandrachud, J

This judgment has been divided into sections to facilitate analysis. They are:

A Factual Background .................................................................................... 5

A.1 Facts of Petition for Arbitration (Civil) No 5 of 2022 .............................. 5

A.2 Facts of Special Leave Petition (Civil) No 13426 of 2021 ................... 13

A.3 Facts of Special Leave Petition (Civil) No 10358 of 2020 ................... 17

A.4 Facts of Miscellaneous Application Nos 1990-1991 of 2019 .............. 19

B Submissions of Counsel ............................................................................ 20

B.1 Submissions on behalf of the petitioners ............................................ 21

B.2 Submissions on behalf of the respondents ......................................... 28

B.3 Submissions on behalf of the amicus curiae ....................................... 31

C Determination of arbitrators’ fee ................................................................ 38

C.1 Comparative outlook ........................................................................... 38

C.1.1 Position of international organisations .......................................... 39

(i) United National Commission on International Trade ......................... 39

(ii) Permanent Court of Arbitration ......................................................... 42

(iii) London Court of International Arbitration ......................................... 43

(iv) International Centre for Dispute Resolution ..................................... 44

(v) International Chamber of Commerce ................................................ 44

(vi) Singapore International Arbitration Centre ....................................... 45

(vii) Hong Kong International Arbitration Centre .................................... 45

(viii) International Centre for Settlement of Investment Disputes ........... 46

3

(ix) Summary .......................................................................................... 46

C.1.2 Position in other national jurisdictions ........................................... 47

(i) England .............................................................................................. 48

(ii) Italy .................................................................................................... 50

(iii) Sweden ............................................................................................ 51

(iv) Germany .......................................................................................... 52

(v) Japan ................................................................................................ 54

(vi) Singapore ......................................................................................... 54

(vii) United States ................................................................................... 55

(viii) Summary ........................................................................................ 56

C.2 Statutory scheme on payment of fees to arbitrators in India............... 57

C.2.1 Party autonomy ............................................................................. 57

C.2.2 Fourth Schedule and regulation of arbitrators’ fees ...................... 59

C.2.3 Costs and fees: Two different paradigms ..................................... 70

C.2.4 Directives governing fees of arbitrators in ad hoc arbitrations ...... 92

D Interpretation of “sum in dispute” in the Fourth Schedule ......................... 97

D.1 Statutory Framework ........................................................................... 97

D.2 Definition of claim and counter-claim ................................................ 100

D.2.1 In re arbitration proceedings ....................................................... 100

(i) Statutory Framework of the Arbitration Act ................................. 100

(ii) Academic discourse .................................................................... 105

(iii) Judicial pronouncements ............................................................ 107

D.2.2 In re civil proceedings ................................................................. 109

(i) Statutory Framework of CPC ...................................................... 109

(ii) Academic discourse .................................................................... 112

4

(iii) Judicial pronouncements ............................................................ 114

D.3 Analysis ............................................................................................. 115

E Fee Ceiling in Fourth Schedule ............................................................... 119

E.1 Difference between the English and Hindi translations ..................... 121

E.2 Exception to literal interpretation ....................................................... 124

E.3 Interpretation based on legislative intent .......................................... 127

F Ceiling applicable to individual arbitrators ............................................... 130

G Conclusion ............................................................................................... 131

G.1 Findings ............................................................................................. 131

G.2 Directions .......................................................................................... 133

PART A

5

A Factual Background

A.1 Facts of Petition for Arbitration (Civil) No 5 of 2022

1 On 29 May 2009, the petitioner, Oil and Natural Gas Corporation Limited

1

,

and the respondent, Afcons Gunanusa JV

2

, entered into a Lump Sum Turnkey

Contract

3

for the construction of an ICP-R Platform. The ICP-R Platform is

alleged to have been completed on 31 October 2012.

2 Due to ongoing disputes and differences, Afcons invoked arbitration on 20

July 2015, in accordance with Clause 1.3 of the LSTK Contract. Afcons appointed

Justice Mukul Mudgal as their arbitrator.

3 The relevant parts of Clause 1.3 of the contract are extracted below:

“1.3 Laws/Arbitration

[…]

1.3.2 Arbitration

Except as otherwise provided elsewhere in the contract, if any

dispute, difference question or disagreement arises between

the parties hereto or their respective representatives or

assignees, in connection with construction, meaning,

operation, effect, Interpretation of the contract or breach

thereof which parties are unable to settle mutually, the same

shall be referred to Arbitration as provided hereunder:

1.3.2.1 A party wishing to commence arbitration proceeding

shall Invoke Arbitration Clause by giving 60 days notice to the

other party. The notice Invoking arbitration shall specify

all the points of disputes with details of the amount claimed

to be referred to arbitration at the time of Invocation of

arbitration and not thereafter. If the claim is in foreign

currency, the claimant shall indicate its value in Indian

Rupee for the purpose of constitution of the arbitral

tribunal.

1

“ONGC”

2

“Afcons”

3

“LSTK Contract”

PART A

6

1.3.2.2 The number of the arbitrators and the appointing

authority will be as under:

Claim amount

(excluding claim

for Interest and

counter claim, if

any)

Number

of

arbitrator

Appointing Authority

Upto Rs. 5 Crore Sole

Arbitrator

ONGC

Above Rs. 5

Crore

3

Arbitrators

One arbitrator by each

party and the 3rd

arbitrator, who shall be the

presiding arbitrator, by the

two arbitrators.

1.3.2.3 The parties agree that they shall appoint only

those persons as arbitrators who accept the conditions

of this arbitration clause. No person shall be appointed

as arbitrator or presiding arbitrator who does not accept

the conditions of this arbitration clause.

[…]

1.3.2.8 Arbitrators shall be paid fees at the following rates.

Amount of Claims

and Counter

Claims (excluding

interest)

Lump sum fees (Including fees for

study of pleadings, case material,

writing of the award, secretarial

charges etc.) payable to each

arbitrator (to be shared equally by the

parties)

Upto Rs. 50 lac Rs. 7,500 per meeting subject to a

ceiling of Rs. 75.000/-

Above Rs. 50 lac

to Rs. 1 crore

Rs. 90,000/- plus Rs. 1,200/- per lac

or a part there of subject to a cei ling

of Rs. 1,50,000/-

Above Rs. 1 Crore

and upto Rs. 5

Crores.

Rs. 1,50,000/- plus Rs. 22,500/- per

crore or a part there of subject to a

ceiling of Rs. 2,4 0,000/-

Above Rs. 5

Crores and upto

Rs. 10 Crores

Rs. 2,40,000/- plus Rs. 15,000/- per

crore or a part there of subject to a

ceiling of Rs. 3,15, 000/-

Above Rs. 10 Rs. 3,15,000/- plus Rs. 12,000/- per

PART A

7

Crores crore or a part there of subject to a

ceiling of Rs. 10,00,000/-

For the disputes above Rs. 50 lacs, the Arbitrators shall

be entitled to an additional amount @ 20% of the fee

payable as per the above fee structure.

1.3.2.9 lf after commencement of Arbitration pr oceedings, the

parties agree to settle the dispute mutually or refer the

dispute to conciliation, the arbitrators shall put the

proceedings in abeyance until such period as r equested by

the parties. Where the proceedings are put in abeyance o r

terminated on account of mutual settlement of dispute by the

parties, the fees payable to the arbitrators shall be

determined as under:

I) 25% of the fees if the claimant has not submitted statement

of claim.

II) 50% of the fees if the award is pending.

1.3.2.10 Each party shall pay its share of arbitrator’s fee in

stages as under:

(I) 25% of the fees on filing of reply to the statement of claims.

(II) 25% of the fees on the competition of evidence.

(III) Balance 50% at the time when award is given to the

parties.

[…]

1.3.2.14 Subject to aforesaid, provisions of the Arbitration and

Conciliation Act, 1 996 and any statutory modifications or re-

enactment thereof shall apply to the arbitration proceedings

under this clause.”

(emphasis supplied)

4 On 20 August 2015, ONGC responded by appointing Justice Gyan Sudha

Mishra as their a rbitrator. The arbitrators appointed Justice GN Ray as the

presiding arbitrator, and the a rbitral tribunal was constituted.

5 The arbitral tribunal held a preliminary meeting on 25 November 2015 at

which the members of the tribunal indicated their view that the fee schedule

PART A

8

prescribed in the contract seemed unrealistic. While Afcons was agreeable to a

revision in the fee, ONGC indicated that it may not be agreeable. The arbitral

tribunal directed ONGC to consider a revision of the arbitrators’ fee. In a letter

dated 28 January 2016 addressed to ONGC , the arbitral tribunal noted that the

Fourth Schedule to the Arbitration and Conciliation Act 1996

4

recommends the

fee for each arbitrator as Rs 30 lakhs, when the amount in dispute exceeds Rs 20

crore (in the present case, it was Rs 900 crores).

6 On 16 April 2016, the arbitral tribunal informed ONGC that it would no

longer bargain on the amount if ONGC was agreeable to the schedule provided

in the Fourth Schedule to the Arbitration Act, along with a reading fee of Rs 6

lakhs for each arbitrator. However, the letter stated that the ceiling of Rs 30 lakhs

provided in the Fourth Schedule was on the ‘ lower side’ for an arbitration with a

disputed amount of Rs 900 crores, and should be revised. The letter reads thus:

“If the appropriate authority of ONGC is inclined to accept the

ceiling referred to in the schedule of the amendment of

Arbitration and Conciliation Act and offer such remuneration,

the Arbitrators do not intend to enter into any bargaining. We

may only indicate that remuneration of Rs. 30 Lacs is in the

lower side and reasonably deserves upward revision in this

case. The arbitrators also expect that considering the

composition of the arbitral tribunal and huge claim involved

(about Rs. 1000 crore) and extraordinarily voluminous

documents to be taken into consideration it may be only

appropriate that as special case, a reasonable reading/

perusal fee to the tune of about 6 lacs for each arbitrator may

be considered. Such reading fee is prevalent in similar other

cases.”

7 By its letter dated 22 April 2016, ONGC informed the arbitral tribunal that

the proposal for the application of the Fourth Schedule of the Arbitration Act was

4

“Arbitration Act”

PART A

9

under consideration by them but since it did not provide for a reading fee, ONGC

could not agree to it.

8 At its second sitting on 4 August 2016, the arbitral tribunal passed a

procedural order directing the parties to deposit 25 per cent of the arbitrators’ fee,

which was recorded as Rs 30 lakhs. On 22 May 2018, the arbitral tribunal passed

another procedural order finalising its fee, stating that it had done so after taking

into account the pleadings submitted by the parties, the complexity of the issues

involved, high value of the claim (Rs 679 crores) and counter-claim (Rs 407

crores), and the voluminous nature of the documents. The tribunal fixed a fee of

Rs 1.5 lakhs for each arbitrator for every sitting of a three- hour duration. The

tribunal indicated that it may also charge a reading fee or conference fee (for

conferences between the members) , which would be indicated at a later stage.

The procedural order states as follows:

“The first sitting of this arbitration case was held in November,

2015. The remuneration of the members of the arbitral

tribunal could not be finally fixed. The claimant had agreed to

pay such remuneration in its share as would be directed by

the tribunal. But the respondent had requested the tribunal to

fix remuneration later on because appropriate authority was

to be considered. The arbitral tribunal was also not in a

position to assess the extent of claim and counter claim to be

raised by the parties and also the complexity of the arbitration

case at that stage. The respondent's representative, however,

had suggested for the ceiling fee at Rs. 30.00 lakhs for each

of the Arbitrators as mentioned in the fourth schedule of

amended Arbitration and Conciliation Act, 1996. It was

pointed out by the tribunal that the arbitration case arose prior

to amendment of the Act. Therefore, the ceiling fee referred to

in the amended Act was not attracted. It was also pointed out

to the respondent's representative that the Arbitral Tribunal

did not like to assert the remuneration of the members of the

tribunal and it would be only appropriate if fair, pragmatic and

reasonable remuneration would be fixed at the suggestion of

both the parties who were expected to take pragmatic and

realistic approach in suggesting the remuneration of the

PART A

10

arbitrators by taking into consideration of the amount of claim

and counter claim to be made by the parties, the composition

of the arbitral tribunal, the complexities of the issues requiring

adjudication and number of sittings likely to take for

concluding the arbitration case, in suggesting the

remuneration of the arbitrators. However, before finally fixing

the remuneration to be paid to the arbitrators by the parties,

25% of Rs. 30.00 lakhs were directed to be deposited by the

parties by sharing equally.

After pleadings have been filed by the parties by taking

substantially long time, presumably, in view of complex

technical issues involved and large number of documents

intended to be relied on by the parties, the members of the

arbitral tribunal have been able to have a fair idea about the

nature and complexities of the issues for determination and

the time likely to be required for completing the arbitration

case. The arbitral tribunal, therefore, holds that proper

remuneration payable to the members of the arbitral tribunal

should be indicated to the parties for compliance.

It may be indicated here that the claimant has claimed about

Rs. INR 6,79,20,52,999/- crores along with 18% interest per

annum on the said sum. The respondent has made a counter

claim of about Rs. INR 4,07,12,97,603/- crores and has also

claimed interest at 18% per annum on the said sum. Both the

parties have informed the arbitral tribunal that both the parties

will examine their respective witnesses including expert

witnesses. As a matter of fact, the claimant has filed affidavit

of evidence of three expert witnesses. Similarly, the

respondent also intends to examine witnesses including

expert witness. Till date 20 sittings have been held and

examination of first witness of the claimant is estimated to be

completed by holding 26 sittings.

It is, therefore, quite evident that the hearing of this arbitration

case will take fairly long time. Along with the pleadings, both

the parties have filed volumes of documents in support of

their respective case. By now the claimant has filed 68

volumes of their document. Similarly, the respondent has also

filed 24 volumes as its document to be relied on. It is not

unlikely that further documents may be relied on by the

parties in the hearing process.

Considering the amounts of claim and counter claim, the

voluminous documents to be taken into consideration and a

very long hearing to conclude the arbitration case and the

complex technical issues required to be taken into

consideration, the arbitral tribunal has decided that it will be

only appropriate, fair and reasonable to fix remuneration of

each of the arbitrators at Rs. 1.50 lakhs (Rupees one lakh

PART A

11

and fifty thousand) per sitting, each sitting confined to three

hours or part thereof. Perusal fee and inter se conference

amongst the members of the tribunal, may not be indicated

now. Such fee may be indicated later or after the case

proceeds further thereby enabling the tribunal to assess the

extent of exercise called for.”

9 On 22 June 2018, ONGC filed an application before the arbitral tribunal for

modifying the procedural order dated 22 May 2018 increasing the fee. The

arbitral tribunal issued a procedural order dated 25 July 2019 rejecting ONGC’s

application. The tribunal observed that:

(i) At the first sitting, the tribunal indicated that the fee specified in the

contract (Rs 12 lakhs per arbitrator) was unrealistic. While Afcons agreed

to a revision of the fee, ONGC was not agreeable. The tribunal granted an

opportunity to ONGC to propose a ‘ reasonable and pragmatic’ fee

schedule;

(ii) While awaiting ONGC’s response, the tribu nal proposed the fee schedule

in the Fourth Schedule to the Arbitration Act “as an example” while noting

that the ceiling of Rs 30 lakhs was also “too low”. Since ONGC seemed

agreeable, the tribunal directed the parties to deposit the first tranche of

fee based on Rs 30 lakhs in the interim;

(iii) Since ONGC did not propose a revised fee schedule, the tribunal, after

considering the complexity of the issues involved, the quantum of the

amount in dispute and the voluminous nature of the documents, fixed its

fee by a procedural order dated 22 May 2018;

(iv) ONGC has not refuted the reasons provided by the tribunal for fixing its

fee. It has only contested the revision on the ground that the fee schedule

PART A

12

in the contract was binding. Since ONGC had shown its willingness earlier

to accept the schedule of fees in the Fourth Schedule, ONGC’s submission

was rejected; and

(v) The ceiling of Rs 30 lakhs in the Fourth Schedule is not applicable to the

present dispute since it arose before the amendment which added the

Schedule.

The tribunal held that the fee was set on the basis of the amount being paid in

arbitrations of such nature. However, it agreed to reduc e the fee of each

arbitrator to Rs 1 lakh per sitting. It noted that the reading fee was kept open, and

would be decided at a later stage.

10 By its letter dated 21 August 2020, ONGC informed the arbitral tribunal

that the revised fee was not approved by its ‘higher’ management. Thereafter,

ONGC filed a petition

5

under Section 14 read with Section 15 of the Arbitration

Act before the Bombay High Court for the termination of the mandate of the

arbitral tribunal and the substitution of a fresh set of arbitrators. By its order dated

7 October 2021, th e petition was dismissed by the Bombay High Court on the

ground of a lack of jurisdiction since the arbitration was an international

commercial arbitration within the meaning of Section 2(f) of the Arbitration Act.

However, ONGC was granted liberty to approach this Court and all its

contentions were kept open. ONGC then filed the present arbitration petition.

5

Commercial Arbitration Petition (Lodging) No 9590 of 2020

PART A

13

A.2 Facts of Special Leave Petition (Civil) No 13426 of 2021

11 This appeal arises from a final judgement and order dated 6 August 2021

of the High Court of Delhi, by which it dismissed the petition

6

filed by the

petitioner, NTPC Limited

7

.

12 NTPC and the respondent, Afcons-Shetty and Company Private Limited-

JV

8

, entered into a contract for the construction of a “ desilting arrangement

package for Koldam Hydro Electric Power (Package- 3) Project”. When disputes

arose between the parties, Afcons-Shetty invoked arbitration for a claim of about

Rs 37 crores. An arbitral tribunal was to be constituted in terms of Clause 67.3 of

the contract. Both parties nominated their arbitrators – NTPC nominated Shri

Krishna Mohan Singh and Afcons-Shetty nominated Shri Santanu Basu Rai

Chaudhuri. When the nominated arbitrators failed to appoint a presiding

arbitrator, Afcons-Shetty approached the Delhi High Court under Section 11 of

the Arbitration Act

9

, which then appointed Justice Manmohan Sarin as the

presiding arbitrator on 21 May 2018 with the consent of parties.

13 The arbitral tribunal held its first sitting on 12 July 2018, where it decided

that the fees payable to the tribunal shall be in terms of the Fourth Schedule to

the Arbitration Act. The Fourth Schedule was subsequently amended on 12

November 2018.

14 NTPC filed its counter-claim of approximately Rs 19 crores. By a

procedural order dated 13 July 2019, the arbitral tribunal fixed a separate fee for

6

OMP (T) (COMM) 37 of 2021

7

“NTPC”

8

“Afcons-Shetty”

9

Arbitration Petition No 375 of 2018

PART A

14

the claim (Rs 28,64,520 per arbitrator) and counter-claim (Rs 19,13,615 per

arbitrator), aggregating to a total fee of Rs 47,78,135 per arbitrator. In support of

its position, the tribunal placed reliance upon the proviso to Section 38(1) of the

Arbitration Act.

15 On 21 September 2019, NTPC filed an application seeking a modification

of the procedural order dated 13 July 2019. By its reply dated 18 October 2019,

Afcons-Shetty opposed the application. By its order dated 8 November 2019, the

arbitral tribunal dismissed NTPC’s application noting that:

“4. There is merit in Mr. Mukhopadhyay's submission that

claims and counter claims being independent of each other

for which separate fee is to be fixed the same cannot be

combined for purpose of ceiling. Moreover, it cannot also be

lost sight of that the Fourth Schedule of the Act can only

serve as a guiding principle in the absence any rules being

framed by the High Court. In view of the foregoing

discussions the order passed by us does not call for any

modifications or review. The application is accordingly

dismissed.”

16 On 15 October 2020, NTPC sought a modification of the tribunal’s orders

dated 13 July 2019 and 8 November 2019, so that the fee fixed in terms of the

Fourth Schedule should include the fee payable for NTPC’s counter-claim. By its

reply dated 30 October 2020, Afcons -Shetty opposed the application.

17 By its order dated 14 January 2021, the t ribunal rejected NTPC’s position

that the claim and counter-claim have to be cumulated to arrive at the “sum in

dispute” for the purposes of the Fourth Schedule. The tribunal held that:

(i) Section 31(8) of the Arbitration Act allows a tribunal to provide for the costs

of arbitration. The regime for costs is provided under Section 31A. The

PART A

15

explanation to Section 31A(1) provides that costs include those relating to

the fees and expenses of the arbitrators;

(ii) The proviso to Section 38(1) stipulates that separate costs are to be fixed

for claims and counter-claims. The position under proviso to Rule 3 of the

DIAC (Administrative Cost & Arbitrators’ Fees) Rules 2018

10

is also similar;

and

(iii) Nothing in the Fourth Schedul e or the DIAC Rules imposes a restriction on

separate costs (and thus fees) being fixed for claims and counter-claims by

the tribunal.

18 Subsequently, by its order dated 19 March 2021, the tribunal held that in

case NTPC does not comply with its directions contained in the order dated 14

January 2021 for payment of Rs 2 lakhs per arbitrator, the tribunal would

consider whether NTPC’s counter-claim should be suspended.

19 NTPC filed a petition under Sections 9 and 14 read with Section 31(8)

before the Delhi High Court, seeking a direction that the tribunal charge a

combined fee under the Fourth Schedule for adjudicating both the claim and the

counter-claim or, in the alternate, for the termination of the mandate of the

tribunal. The petition was opposed by Afcons -Shetty.

20 By a judgment dated 6 August 2021, a Single Judge of the Delhi High

Court dismissed NTPC’s petition. The Single Judge held that the proviso to

Section 38(1), Section 31(8) and Section 31A are inextricably linked and on a

10

“DIAC Rules”

PART A

16

combined reading, a tribunal would have the power to fix a separate fee for

claims and counter-claims. The Single Judge of the Delhi High Court held thus:

“43. …the scheme of 1996 Act is such that the provisions of

Section 38(1), 31(8) and 31A are inextricably interlinked.

These provisions cannot be read in isolation. The proviso to

Section 38(1) clearly states that, where there are claims and

counter-claims before the arbitral tribunal, the Arbitral

Tribunal may fix separate amount of deposits for the claim

and counter-claim. Section 38(1) clarifies that the “amount of

deposit” is to be directed “as an advance for the costs

referred to in sub- section (8) of Section 31”. Sub- section (8)

of Section 31 requires the Arbitral Tribunal to fix the costs of

arbitration in accordance with Section 31A. The explanation

to Section 31A(1) clearly states that, for the purposes of

Section 31A(1) the expression “costs” means reasonable

costs relating to, inter alia, “the fees and expenses of the

arbitrators”.

[…]

48. The position becomes clear when we view the proviso to

Section 38(1), Section 31(8) and the Explanation to Section

31A(1) in juxtaposition. Section 31(8) mandates that the

arbitral tribunal fix the costs of arbitration, in accordance with

Section 31A. Clause (i) of the Explanation to Section 31A(1)

specifically includes the fees and expenses of the arbitrators

as an integral part of the “costs”. Clearly, therefore, the

arbitrator has to fix the fees payable to the arbitral tribunal,

with, needless to say, consent of parties. Section 38(1)

provides for advance, for such “costs” fixed, by way of

“deposit”. The expressions “deposit”, “costs” and “fees” are,

therefore, intertwined by statute, and, as the interpreter

thereof, the Court can hardly extricate them from each other.

The proviso to Section 38(1) provides that, where the arbitral

tribunal is seized of claims and counter-claims, it may fix

separate amount of deposit for each. No doubt, the use of the

word “may” does involve an element of discretion; but, if the

arbitral tribunal does fix separate fees for the claims and

counter-claims, it cannot be held that it has acted irregularly,

or contrary to the statutory mandate. ”

PART A

17

A.3 Facts of Special Leave Petition (Civil) No 10358 of 2020

21 The appeal arises from a final judgement and order dated 10 July 2020 by

which the High Court of Delhi dismissed the petition

11

filed by the petitioner, Rail

Vikas Nigam Limited

12

.

22 On 28 December 2010, RVNL awarded a contract for the “ construction of a

viaduct and related works for a length of 4.748 kms in the Joka- BBD Bag Corridor

of Kolkata Metro Railway Line” to the respondent, Simpex Infrastructures

Limited

13

. Disputes having arisen between the parties, Simpex invoked arbitration

by its letter dated 26 December 2017.

23 The parties could not agree upon the appointment of arbitrators. While

Simpex nominated its arbitrator, RVNL contended that Simpex had to nominate

its arbitrator from a panel of five names recommended by RVNL. Since RVNL

refused to nominate their arbitrator, Simpex approached the Delhi High Court

under Section 11 of the Arbitration Act

14

. The High Court, by its order dated 11

December 2018, nominated an arbitrator on behalf of RVNL and ordered that “the

Arbitrator[s] shall be paid fee as per Fourth Schedule to the [Arbitration] Act”.

RVNL’s special leave petition

15

against the order of the Delhi High Court was

dismissed by this Court on 12 April 2019.

24 Meantime, the arbitrators nominated by the parties appointed a presiding

arbitrator. The arbitral tribunal held its preliminary sitting on 15 January 2019,

where it recorded that its fee shall be in accordance with the Fourth Schedule to

11

OMP (T) (COMM) 38 of 2020

12

“RVNL”

13

“Simpex”

14

ARB P 519 of 2018

15

SLP

PART A

18

the Arbitration Act. By its order dated 9 January 2020, the arbitral tribunal

recorded that, in accordance with Fourth Schedule, the fee of each arbitrator

would be Rs 49,87,500.

25 RVNL then filed an application on 27 February 2020 for the recall of the

tribunal’s order dated 9 January 2020 on the ground that the ceiling on fees for

each arbitrator under the Fourth Schedule is Rs 30,00,000.

26 By its order dated 3 March 2020, the arbitral tribunal rejected RVNL’s

application. It noted that that the limitation of Rs 30,00,000 in the entry at Serial

No 6 of the Fourth Schedule does not encompass the entire fee, comprising of

the base component of Rs 19,87,500 and the variable component (0.5 per cent of

the claim amount above Rs 20 crores) but was only limited to the variable

component. Hence, the ceiling on fee according to the tribunal, is Rs 49,87,500,

and not Rs 30,00,000.

27 RVNL then filed a petition under Section 14 of the Arbitration Act before

the Delhi High Court, praying for the termination of the mandate of the arbitral

tribunal.

28 By a judgment dated 10 July 2020, a Single Judge of the Delhi High Court

rejected RVNL’s petition. The Single Judge held that the ceiling of Rs 30,00,000

is applicable only to the variable component of the entry at Serial No 6 of the

Fourth Schedule. It has been held that the use the disjunctive, namely, ‘plus’

between the fixed base component and the variable component indicates that the

ceiling of Rs 30,00,000 applies only to the latter. According to the judgment, such

an interpretation arises not only from the English version of the Arbitration Act,

PART A

19

but also its Hindi version. Finally, the court held that while this interpretation was

based on the text of the entry at Serial No 6 of the Fourth Schedule, it is also

supported by the 246

th

Report of the Law Commission (which recommended the

changes to the Fourth Schedule) and the DIAC Rules Model Fee (on the basis of

which the Schedule Four was crafted).

A.4 Facts of Miscellaneous Application Nos 1990-1991 of 2019

29 The miscellaneous application has been filed by the respondent, RV NL, in

relation to an order dated 16 January 2018 of a two-Judge Bench of this Court in

the main SLP. By its order dated 16 January 2018, this Court appointed Justice

Vikramjit Sen as the sole arbitrator with the consent of the parties, to decide their

disputes. The order of this C ourt recognised that “[t]he learned Arbitrator is at

liberty to fix his remuneration”.

30 By a procedural order dated 24 February 2018, the sole arbitrator, with the

consent of the parties, decided that arbitral fee shall be payable in accordance

with the Fourth Schedule to the Arbitration Act. On 25 March 2019, the sole

arbitrator raised separate invoices for the payment of fee for claims and counter-

claims.

31 RVNL filed an application on 18 May 2019 raising an objection to the sole

arbitrator raising separate invoices for payment of a fee for claims and counter

PART B

20

claims. By an email dated 20 May 2019, the petitioner HCIL-Adhikarya- Arss

(JV)

16

, agreed to RVNL’s application and for it to be allowed.

32 The sole arbitrator dismissed RVNL’s application on 20 May 2019, holding

that in terms of the proviso to Section 38(1) of the Arbitration Act and Order VIII

Rule 6A of the Civil Procedure Code 1908

17

, claims and counter-claims have to

be treated separately. Further, the sole arbitrator noted that since he had been

appointed by this Court in an ad hoc arbitration with liberty to fix his own fee, a

separate fee could be charged for the claim (Rs 325,89,48,831) and counter -

claim (Rs 21,59,56,092).

33 RVNL has filed a miscellaneous application before this Court, seeking a

determination of whether a fee can be charged separately by the arbitral tribunal

for the claim and counter-claim and whether the tribunal was justified in doing so

after fixing its fee in terms of the Fourth schedule.

B Submissions of Counsel

34 We have heard Mr KK Venugopal the learned Attorney General, and Mr

Tushar Mehta, learned Solicitor General, on behalf of the petitioners. Dr Abhishek

Manu Singhvi led the arguments on behalf of the respondents and Mr Manu

Sheshadri for the respondent in SLP (C) No. 13426 of 2021. Mr K. Parmeshwar

addressed the court for the intervenors. Mr Huzefa Ahmadi, has rendered

objective assistance to this Court as amicus curiae.

16

“HCIL”

17

“CPC”

PART B

21

B.1 Submissions on behalf of the petitioners

35 On behalf of the various public sector undertakings that have instituted

proceedings before this Court, the following submissions have been made by the

Attorney General and the Solicitor General:

(i) The arbitration clause of a contract is binding on the parties and the

arbitrators. Once the fee payable to the arbitrators has been specified in

the agreement between the parties, the arbitrators must either accept their

appointment on the terms agreed in the contract between the parties or

refuse the arbitration if they are not agreeable to accept the assignment on

the fee which has been fixed by parties in their agreement. In NHAI v.

Gayatri Jhansi Roadways Ltd.

18

, this Court has held that the fee fixed in

the agreement is binding. In Russell on Arbitration

19

(24

th

Edition) it has

been noted that the appointment of arbitrators is a matter of contract

subject to the mandatory provisions of the governing law. Arbitrators

cannot increase their fees and expenses unless their agreement with the

parties entitles them to do so. Gary Born in his treatise titled International

Commercial Arbitration

20

has observed that arbitrators, in principle, should

not be permitted to unilaterally determine their own fee in the absence of

any agreement between the parties since that violates the principle that

one cannot be the judge of their own cause;

(ii) If either one party or both parties are not willing to pay the fees desired by

the arbitrators or if the arbitrators deviate from the fees stipulated under

18

(2020) 17 SCC 626 (“Gayatri Jhansi Roadways Ltd”)

19

David St John Sutton, Judith Gill and Matthew Gearing, Russell on Arbitration (24

th

edition, 2015) (“Russell on

Arbitration”)

20

Gary B Born, International Commercial Arbitration (2

nd

edition, 2014)

PART B

22

the agreement, the mandate of the arbitral tribunal would have to be

terminated in its entirety;

(iii) Section 11(14) of the Arbitration Act provides that the “High Court may

frame such rules [for determination of fees] as may be necessary, after

taking into consideration the rate specified in the Fourth Schedule”.

Therefore, the Fourth Schedule should serve as a template or a guide for

the High Courts in fixing fees for the arbitrators;

(iv) Sub-Section (3A) of Section 11, inserted by the Arbitration and Conciliation

(Amendment) Act 2019

21

, also stipulates that the arbitrator appointed by a

party shall be entitled to the fees at the rates specified in the Fourth

Schedule;

(v) Conflicting views have emerged from the High Courts as regards the

nature of the Fourth Schedule to the Arbitration Act. Typically, it is

considered suggestive in cases where arbitrators are appointed by parties

and mandatory when arbitrators are appointed by the court;

(vi) The entry at Serial No 6 of the Fourth Schedule to the Arbitration Act

provides a cap on the fees payable to the arbitral tribunal. There is an

apparent mismatch between the English and Hindi versions, since a

comma which is present in the Hindi version is absent in the English

version, before the phrase “with a ceiling of Rs 30,00,000”. The comma

disjoins the phrase "with a ceiling of Rs.30,00,000” from the words

preceding the comma, "Rs. 19,87,500 plus 0.5 % of the claim amount over

and above Rs. 20 Cr." The use of the comma in the Hindi version suggests

21

“Arbitration Amendment Act 2019”

PART B

23

that the ceiling is applicable to the entire clause. Thus, the total fees

payable to the arbitrators cannot exceed Rs 30,00,000;

(vii) The omission of the comma in the English version is an inadvertent

grammatical mistake. Commas have a crucial role to play in interpretation

and due regard must be given to it when multiple interpretations are

possible;

(viii) If the comma is not given its due effect, the upper limit on the fees can be

interpreted to mean Rs 49,87,500 [19, 87,500 + 30,00,000]. Such an

interpretation would be contrary to the legislative intent of making

arbitration cost-effective and economical;

(ix) The Fourth Schedule is based on the D elhi International Arbitration

Centre

22

fees’ schedule which contains a comma like the Hindi version,

which disjoints the applicable fees and establishes a ceiling of Rs

30,00,000 towards arbitrators’ fees. This ceiling applies to the aggregate

amount of the claim and counter-claim;

(x) Section 2(9) of the Arbitration Act provides that wherever Part - I of the

Arbitration Act refers to a claim, it shall be applicable to a counter-claim

and where it refers to defence, it shall include a reference to the defence of

a counter-claim;

(xi) The legislative intent behind using the phrase “sum in dispute” in the

Fourth Schedule of the Arbitration Act was to refer to the cumulative sum

of the claim and counter-claim. If the legislative intent was to charge

22

“DIAC”

PART B

24

separate fees for both the claim and counter-claim, it would have been

explicitly stated;

(xii) The plain English meaning of the term “sum” means aggregate and of the

term “dispute” means the totality of all the claims and counter-claims. The

term “sum” or “dispute” cannot be bifurcated through legal interpretation to

refer to claims and counter-claims as separate concepts;

(xiii) The rules of various institutions in India and abroad that conduct

arbitration proceedings also fortify the position that the “sum in dispute”

includes the claim and counter-claim;

(xiv) In Union of India v. Singh Builders

23

and Sanjeev Kumar Jain v. RS

Charitable Trust

24

, this Court observed that arbitrators are charging

exorbitant fees, without any ceilings. The Law Commission of India in its

246

th

Report

25

identified the above mischief and recommended the

introduction of the Fourth Schedule to address this issue;

(xv) It is evident from the LCI 246

th

Report (supra) that the Fourth Schedule

was introduced to make arbitration a cost-effective solution for dispute

resolution domestically by providing some mechanism to rationalise the fee

structure for arbitration. The Law Commission stated that the model

schedule of fees recommended by it is based on the fee set by DIAC. The

fee schedule set by DIAC specifically provides that the “sum in dispute”

includes the counter-claim made by any party. Thus, the interpretation that

the “sum in dispute” includes the counter-claim would be in tandem with

23

(2009) 4 SCC 523 (“Singh Builders”)

24

(2012) 1 SCC 455

25

Law Commission of India, ‘Amendments to the Arbitration and Conciliation Act 1996’ (246

th

Report, August

2014) available at <https://lawcommissionofindia.nic.in/reports/report246.pdf> accessed on 29 June 2022 (“ LCI

246

th

Report”)

PART B

25

the legislative intent and the object that was sought to be achieved with the

introduction of the Fourth Schedule;

(xvi) The proviso to Section 38(1) of the Arbitration Act, providing for a

separate “deposit” for claim and counter-claim as an advance for the costs

referred to in Section 31(8), cannot be construed to include arbitrators’

fees because that would negate the requirement of the Fourth Schedule

framed either under Section 11(14) or Section 11(3A) of the Arbitration Act,

as the case may be. This can be harmoniously reconciled by excluding

“fees” from the ambit of “costs”;

(xvii) Fees and costs are completely distinct. Fees are a return or

consideration for professional services rendered, where there is an

element of quid pro quo. Fees can be fixed by agreement between the

parties in an ad hoc arbitration or by rules in an institutional arbitration. On

the other hand, costs are expenses incurred in the facilitation of the

arbitration, which include expenses for the venue of arbitration,

transportations costs and secretarial expenses;

(xviii) Section 31(8) of the Arbitration Act states that the cost of arbitration is

fixed by the arbitral tribunal in accordance with Section 31A. There is no

involvement of party autonomy in the determination of costs, unlike the

concept of fees which is based on party autonomy;

(xix) Sub-Sections (3) and (4) of Section 31A of the Arbitration Act enumerate

the circumstances which may be taken into account by the arbitral tribunal

to determine costs. None of these circumstances make any references to

PART B

26

arbitrators’ fees but refer to expenses incurred in the process of facilitating

the arbitration proceedings;

(xx) In Gayatri Jhansi Roadways Ltd (supra), this Court held that while

arbitrators’ fees may be a component of costs to be paid but it is a far cry

to state that Section 31(8) and 31A would directly govern contracts in

which the fee structure has already been laid down. Section 31(8) read

with Section 31A deals with costs generally but not with arbitrator(s) fees;

(xxi) The Explanation to Section 31A(1) of the Arbitration Act states for the

purpose of this sub- Section, “costs” means reasonable costs relating to the

“fees” and expenses of the arbitrator. The Explanation takes away the

effect of the legislative intent enshrined in Sections 11(14) read with the

Fourth Schedule and Section 38(1) of the Arbitration Act. In Dattatraya

Govind Mahajan v. State of Maharashtra

26

, this Court has held that the

intention of the legislature is paramount;

(xxii) Further, the Explanation to Section 31A(1) which provides that costs

include the “fees and expenses of arbitrators, Courts and witnesses” has to

be read in conjunction with Section 31A(1)(a) which provides that the

arbitral tribunal has the discretion to determine “whether costs are payable

by one party to another”. The implication of the above is that when costs

are awarded to the successful party, it would recoup the entirety of the

amount that has been spent on arbitration, including fees and expenses of

the arbitrators, court and witnesses as compensation for the arbitration

which has failed against it. This does not refer to a new determination of

26

(1977) 2 SCC 54

PART B

27

fees by the arbitrators; they are only entitled to what the agreement states.

It would be extraordinary to state that the arbitrators can stipulate a new

fee at the final stage of determining costs under Section 31A;

(xxiii) The Fourth Schedule uses the phrase “sum in dispute” and there is no

mention of this phrase in the Arbitration Act. On the other hand, Section 38

pertains to deposits and that too at a preliminary stage as an advance for

costs as referred to in Section 31(8). These provisions cannot be used to

interpret the term “sum in dispute”. If the language of the enacting part is

ambiguous, then the Schedule should be referred to for understanding the

intent of the legislature. Thus, the Fourth Schedule would supersede the

provisions of Section 38 on the basis of which, it can be concluded that

arbitral fee refers to a cumulative amount of claim and counter-claim;

(xxiv) The Fourth Schedule was introduced by the Arbitration and Conciliation

(Amendment) Act 2015

27

. The legislature was aware of the terminology

used in Section 38(1) and could have used the terms “costs” or “deposits”

but yet it still chose to use the term “sum in dispute”; and

(xxv) Public sector undertakings, unlike private companies, cannot afford the

high fees that are charged by the arbitrators. A failure to pay the hefty fees

being charged by arbitrators could lead to a situation where the arbitral

tribunal forms a bias against such public sector undertakings.

27

“Arbitration Amendment Act 2015”

PART B

28

B.2 Submissions on behalf of the respondents

36 On behalf of the respondents, the following submissions have been urged

by Dr Abhishek Manu Singhvi, S enior Counsel:

(i) If the parties have prescribed a fee schedule and the arbitral tribunal

agrees to be bound by it unconditionally, without any caveat, then the

agreed schedule would apply. However, there is nothing in the Arbitration

Act to indicate what is to be done in a circumstance where the parties are

unable to agree to a fee schedule. The question then arises if the arbitral

tribunal can fix its own fees;

(ii) The issue of fee fixation is dealt with as a part of “costs” under Section

31(8) (prior to the Arbitration Amendment Act 2015) or Section 31(8) read

with Section 31A (after the Arbitration Amendment Act 2015);

(iii) Sections 31(8) and 31A are part of Chapter VI titled “Making of Arbitral

Award and Termination of Proceedings”, which implies that the issue of

fees remains open to determination till the award is made. A similar

practice is followed under the English Arbitration Act 1996, UNICITRAL

Rules and International Chamber of Commerce Rules. Therefore, if there

is no agreement between the parties regarding the fees of the arbitrators

and the arbitration has proceeded, the arbitral tribunal would be entitled to

its right to remuneration, which is crystallized as a part of “reasonable

costs” as provided under the Explanation to Section 31A(1);

(iv) It has been suggested that this Court may provide guidelines where three

case management hearings can be conducted at the initial stage of

PART B

29

arbitration leading to the fixation of the fee of the arbitrators, which shall

not be changed except under extraordinary circumstances;

(v) Arbitrator(s) may demand an increase in fees if there is an undue delay in

the completion of the arbitration proceedings;

(vi) The right to remuneration of the arbitrator(s) is secured by empowering the

arbitral tribunal to fix an amount of deposit or supplementary deposit in

advance under Section 38(1) of the Arbitration Act, which is a part of final

accounting upon the termination of arbitral proceedings under Section

38(3). The enforcement of this right is ensured by empowering the arbitral

tribunal to exercise a lien on the award under Section 39(1);

(vii) Section 39(1) of the Arbitration Act permits a party to approach the court

to resolve the issue of costs (including fees) as the court “may consider

reasonable”. The arbitral tribunal’s right to fix reasonable costs (including

its final determination of fee) is judicially reviewable under Section 39 read

with Section 31A of the Arbitration Act;

(viii) Section 31(8) of the Arbitration Act provides that the costs of arbitration

shall be fixed in terms of Section 31A of the Act. The Explanation to

Section 31A(1) provides that “costs” shall mean reasonable costs relating

to the fees and expenses of arbitrators;

(ix) The proviso to Section 38(1) of the Arbitration Act in clear and

unambiguous terms provides that a separate amount may be fixed for

deposit towards the claim and the counter-claim, if any counter-claim is

preferred apart from the claim;

PART B

30

(x) The fees of arbitrators are an integral part of the costs to be fixed by the

arbitral tribunal under Section 31(8) towards deposits, for which the arbitral

tribunal is empowered to fix separate amounts for claims and counter-

claims;

(xi) The phrase “sum in dispute” mentioned in the Fourth Schedule has to be

interpreted in the above context;

(xii) Any reliance on the inconsistency between the Hindi and English versions

of the Arbitration Act with respect to the entry at Serial 6 of the table in the

Fourth Schedule is in the teeth of Article 348(1)(b)(ii) of the Constitution,

which provides that the Act passed by Parliament in the English language

shall be the authoritative text. Further, Article 348(1) begins with a non-

obstante clause which has an overriding effect over other provisions;

(xiii) If the legislature wanted to indicate that the maximum cap on fees

payable to an arbitrator is Rs 30 ,00,000, it would have simply stated so.

There was no need to provide in the entry at Serial 6 that the fixed amount

of Rs 19,87,500% + 0.5% of the claim amount over and above Rs

20,00,00,000 with a ceiling of Rs 30,00,000 would be the upper ceiling;

(xiv) Counter-claims arise from a distinct dispute, separate from the dispute

pertaining to the claim and mostly in regard to an independent cause of

action. Even if the main suit fails, a counter-claim may survive and

continue. Thus, a separate court fee (where a suit is filed in a court) is

required to be paid on the amount of counter-claim. A counter-claim is

different from a set-off, which arises from the same dispute and can be

PART B

31

claimed as an adjustment in the main suit, without requiring the payment of

court fees;

(xv) The Arbitration Act refers to claims and counter- claims distinctly in

various provisions such as Section 2 (9), Section 23 (2A), Section 31A and

Section 38;

(xvi) Section 2(9) of the Arbitration Act, which states any reference to a claim

in Part - I also applies to a counter-claim, has to be read in tandem with the

proviso to Section 38(1), Section 31A and Section 31(8); and

(xvii) Bias is not an appropriate ground to challenge the increase in fees of

arbitrators.

B.3 Submissions on behalf of the amicus curiae

37 Mr Huzefa Ahmadi, learned Senior Counsel, assisting this Court as amicus

curiae made the following submissions:

(i) Party autonomy is the overarching principle of arbitration and is crystallised

in Section 2(6) of the Arbitration Act. It allows parties to determine the

relevant law and procedure that will govern the arbitration and limits court

intervention. The principle of party autonomy extends to parties’ freedom to

decide the fees payable to the arbitrator(s);

(ii) Prior to the amendment of the Arbitration Act in 2015, the issue of

arbitrators’ fees would have been a subject of agreement between the

parties and the arbitrators. However, this Court in Singh Builders (supra)

noted that the arbitrators have been unilaterally, arbitrarily and

disproportionately fixing their fees. This observation was made in the

PART B

32

context of court-appointed arbitrators where this Court was concerned with

the fact that parties were being sent for arbitration by courts and were

being forced to pay the fees fixed by such arbitrators. This Court noted that

institutional arbitration has already remedied this problem since the arbitral

institution fixes the fees and not the arbitrators in terms of the rules of the

institution;

(iii) In the above backdrop, the Law Commission recognised that the issue of

arbitrator fees in ad hoc arbitration must be resolved by the introduction of

a mechanism to rationalise the fee structure. A model schedule of fees, the

Fourth Schedule, was added to the Arbitration Act through the Arbitration

Amendment Act 2015, which was to serve as a guide for High Courts to

frame rules governing the fixation of fees payable to the arbitrators. This

model schedule of fees was based on the schedule of fees developed by

DIAC and was suitably revised;

(iv) The Fourth Schedule is to be read along with provisions for appointment of

arbitrators under Section 11. It does not apply to international commercial

arbitration and is not applicable when the parties have agreed to the fees

in terms of the rules of an arbitral institution;

(v) The High Courts have been slow in framing rules for the determination of

fees payable to arbitrator(s);

(vi) Some High Courts have been of the view that the Fourth Schedule is

merely suggestive and not mandatory, while others have held that it is

mandatory. Thus, there is an uncertainty regarding the nature of the Fourth

Schedule. In Gayatri Jhansi Roadways Ltd (supra), this Court held that if

PART B

33

the fee schedule is fixed by the parties in an agreement, they would not be

bound by the Fourth Schedule. Pursuant to this decision, many High

Courts have proceeded to hold that the Fourth Schedule is only applicable

to court-appointed arbitrators if stated expressly or if the parties and

arbitrators have agreed to its applicability;

(vii) Section 11 has been further amended by the Arbitration Amendment Act

2019. Sub- Section (14) of Section 11 now reads that “[t]he arbitral

institution shall determine the fees of the arbitral tribunal and the manner of

its payment to the arbitral tribunal subject to the rates specified in the

Fourth Schedule”. The amended Section 11 has not been brought into

force and is subject to two exceptions. Crucially, once the amendment

comes into force, the fee of the arbitral tribunal would be fixed by the

arbitral institution appointing the arbitrator. This Court’s interpretation

regarding the nature of the Fourth Schedule would also have an impact on

the amended Section 11 when it is brought into force;

(viii) To determine if the term “sum in dispute” refers to both the claim and

counter-claim, it has to be considered whether a counter=claim can be

treated as an independent claim for which a legal proceeding may be

instituted. Section 23 of the Arbitration Act provides the basis on which a

counter-claim is to be adjudicated. Section 23 does not stipulate that the

counter-claim must be linked or related to the claim; rather it only states

that the counter-claim must come within the scope of the arbitration

agreement;

PART B

34

(ix) The independent nature of the counter-claim is recognised under Sections

38(1) and 38(2) of the Arbitration Act in the following terms, where the

arbitral tribunal is empowered to:

(a) Determine separate amount of deposits on a claim and counter-claim;

and

(b) Suspend or terminate the proceedings in respect of the claim or

counter-claim, in the event, the deposit directed to be paid by the

tribunal is not paid by the parties;

(x) Claims and counter-claims are treated separately under the analogous

provisions of Order VIII of the CPC ;

(xi) Proceedings relating to a counter -claim can survive even if the

proceedings relating to a claim are terminated;

(xii) Section 2(9) only provides that provisions of the Arbitration Act relating to

a claim would mutatis mutandis apply to a counter-claim. It is not a

definition clause but it is intended to apply to only procedural aspects. In

fact, it fortifies the argument that the “claim amount” under the Fourth

Schedule would mutatis mutandis apply to counter-claims and is not an

aggregate of claims and counter-claims;

(xiii) An arbitral tribunal is not restrained from deciding its fees under the

Fourth Schedule for claims and counter-claims separately;

(xiv) The Fourth Schedule does not explicitly state that the “ sum in dispute”

includes a counter-claim;

(xv) Until the amendment to Section 11 is notified, the court appointing

arbitrators should ensure that the parties are made aware of the terms on

PART B

35

which the appointment is made and specifically whether or not the Fourth

Schedule is applicable. The court should also ensure that the parties have

clarity on the fees and expenses payable to the arbitrator(s);

(xvi) This Court may recommend that either prior to or at the time of notifying

the amendments to Section 11, the rates specified in the Fourth Schedule

may be revised to reflect the rates that are realistic in present times;

(xvii) None of the provisions of the Arbitration Act entitle the arbitrators to fix

their own fees. The scheme of the Act indicates that the arbitral tribunal is

only empowered to apportion costs (including the arbitrators’ fee) incurred

during the arbitration as between the parties at the time of passing the

award;

(xviii) Remuneration of arbitrators is subject to direct negotiation and

agreement between the arbitrators and the parties and ought to be

determined at the inception of the proceedings. The fee that has been

agreed upon between the parties and the arbitrators is apportioned as a

part of the costs at the time when the award is passed. This view is

supported by the decision of this Court in Gayatri Jhansi Roadways Ltd

(supra), where it was observed that “…it is true that the arbitrator’s fees

may be a component of costs to be paid but it is a far cry thereafter to state

that section 31(8) and 31A would directly govern contracts in which a fee

structure has already been laid down”;

(xix) Section 39 of the Arbitration Act also empowers the arbitral tribunal to

only hold the award from the parties for any unpaid costs of arbitration.

PART B

36

These unpaid costs could include arbitrators’ fees previously agreed upon

between the parties and not paid;

(xx) Any deviation from the fees agreed between the parties and the

arbitrator(s) would require the consent of the parties. It would be

unreasonable and unfair to the parties if the arbitral tribunal is allowed to

alter its fees at a later stage of the arbitration proceedings. At an advanced

stage, parties may be apprehensive to disagree with the arbitral tribunal

and may agree to an unreasonable and arbitrary fee sought by it;

(xxi) The fee payable under the Fourth Schedule would be applicable to each

member of the arbitral tribunal. It cannot be considered as a lump sum to

be split among the members. The Note to the Fourth Schedule provides

that where the tribunal consists of a sole arbitrator, they would be entitled

to 25 per cent over and above the fee payable under the Fourth Schedule.

It would be absurd if the sole arbitrator would be entitled to 25 per cent

over and above the stipulated sum under the Fourth Schedule but in the

case of an arbitral tribunal consisting of three or more members, the entire

fee would have to split;

(xxii) Under Section 10 of the Arbitration Act, parties are free to determine the

number of arbitrators. If there is no agreement, then the default rule is of

appointing a sole arbitrator. Parties can always appoint a sole arbitrator,

but if there are unwilling to derogate from the agreement which provides

for appointment of three or more arbitrators, then they would have to bear

the costs accordingly;

PART B

37

(xxiii) The ceiling of Rs 30,00,000 in the Fourth Schedule is only applicable to

the sum of 0.5% of the claim amount over and above Rs 20 crores. The

expression “+” that appears after Rs 19,87,500 is disjunctive; and

(xxiv) The Fourth Schedule was introduced in English while the Hindi version

was the translation. Thus, precedence must be given to the English

version. A comma is not conclusive for determining the meaning of a

statutory provision.

38 Mr Ahmadi also urged the court to issue certain directives for governing ad

hoc arbitrations in India. These are reproduced below:

“1. In cases where the arbitrator(s) are appointed by

parties in the manner set out in the arbitration agreement,

upon constitution of the arbitral tribunal, the parties and the

arbitral tribunal shall hold a preliminary hearing amongst

themselves to finalise the terms of reference (the “Terms of

Reference”) of the arbitral tribunal. The arbitral tribunal must

set out the components of its fee in the Terms of Reference

which would serve as a tripartite agreement between the

parties and the arbitral tribunal. Once the Terms of Reference

have been finalised and issued, it would not be open for the

arbitral tribunal to vary either the fee fixed or the heads under

which the fee may be charged.

2. The parties and the arbitral tribunal may make a carve

out in the Terms of Reference that the fee fixed therein may

be analysed upon completion of pleadings. The parties and

the arbitral tribunal may hold another meeting to ascertain the

number of sittings that may be required for the final

adjudication of the dispute which number may then be

incorporated the Terms of Reference as an additional term.

3. In cases where the arbitrator(s) are appointed by the

Court, the order of the Court should ideally expressly stipulate

the fee that arbitral tribunal would be entitled to charge.

However, where the Court leaves this determination to the

arbitral tribunal in its appointment order, the arbitral tribunal

and the parties should agree upon the Terms of Reference as

specified in the manner set out in draft practice direction (1)

above.

PART C

38

4. There can be no unilateral deviation from the Terms

of Reference. The Terms of Reference being a tripartite

agreement between the parties and the arbitral tribunal, any

amendments, revisions, additions or modifications may only

be made to it with the consent of the parties.

5. All High Courts shall frame the rules for arbitrator fee

for the purposes of Section 11(14) of the Arbitration and

Conciliation Act, 1996.”

39 On the basis of these submissions, this Court has now been called to

determine the following issues in relation to the arbitrators’ fees:

(i) Whether the arbitrator(s) are entitled to unilaterally determine their own

fees;

(ii) Whether the term “sum in dispute” in the Fourth Schedule to the Arbitration

Act means the cumulative total of the amounts of the claim and counter -

claim;

(iii) Whether the ceiling of Rs 30,00,000 in the entry at Serial No 6 of the

Fourth Schedule of the Arbitration Act is applicable only to the variable

amount of the fee or the entire fee amount; and

(iv) Whether the ceiling of Rs 30,00,000 applies as a cumulative fee payable to

the arbitral tribunal or it represents the fee payable to each arbitrator.

C Determination of arbitrators’ fee

C.1 Comparative outlook

40 The issue whether the remuneration of arbitrators has to be decided by the

parties or by the arbitrator(s) on their own has not been exhaustively addressed

PART C

39

in India. People and businesses across the world have increasingly become

interconnected with the advent of globalisation. Hence, it will be useful to look at

the practices adopted by international organisations and in national jurisdictions

on the determination of arbitrators’ fees. We must at the outset distinguish

between arbitrations administered by institutions and ad hoc arbitrations.

Typically, when an arbitration is conducted under the aegis of an arbitral

institution, the fees payable to the arbitrators is fixed by the institution, sometimes

independently or in consultation with the sole or presiding arbitrator. The parties

are not involved in negotiations with the arbitrator(s) to decide the fees. However,

in ad hoc arbitrations, parties enter into their own arrangements with the

arbitrators regarding their remuneration

28

.

C.1.1 Position of international organisations

(i) United National Commission on International Trade

29

41 The UNCITRAL adopted a model law on International Commercial

Arbitration on 21 June 1985. It was hoped that states would give due

consideration to the model law while framing their own domestic legisla tion. The

Arbitration Act has also been enacted taking into account the UNCITRAL Model

Law. The Preamble to the Act states:

“WHEREAS the United Nations Commission on International

Trade Law (UNCITRAL) has adopted the UNCITRAL Model

Law on International commercial Arbitration in 1985:

28

Nigel Blackaby, Constantine Partasides, Alan Redfern and Martin Hunter, Redfern and Hunter on International

Arbitration (6th Edition, 2015), Chapter 4, Paragraph 4.203 (“Redfern and Hunter on International Arbitration”)

29

“UNCITRAL”

PART C

40

AND WHEREAS the General Assembly of the United Nations

has recommended that all countries give due consideration to

the said Model Law, in view of the desirability of uniformity of

the law of arbitral procedures and the specific needs of

international commercial arbitration practice;

AND WHEREAS the UNCITRAL has adopted the UNCITRAL

Conciliation Rules in 1980;

AND WHEREAS the General Assembly of the United Nations

has recommended the use of the said Rules in cases where a

dispute arises in the context of international commercial

relations and the parties seek an amicable settlement of that

dispute by recourse to conciliation;

AND WHEREAS the said Model Law and Rules make

significant contribution to the establishment of a unified legal

framework for the fair and efficient settlement of disputes

arising in international commercial relations;

AND WHEREAS it is expedient to make law respecting

arbitration and conciliation, taking into account the aforesaid

Model Law and Rules;

BE it enacted by Parliament in the forty-seventh Year of the

Republic of India as follows:-”

42 The UNCITRAL Model Law does not explicitly recognise the right of

remuneration of arbitrator(s). However, arbitrators must be compensated for their

services. This flows from the contractual relationship between the parties and the

arbitrator and customary practice

30

.

43 The original UNCITRAL Rules introduced in 1976 could be used to govern

ad hoc arbitrations as well as arbitrations where an arbitral institution was

involved. The 1976 Rules allowed the arbitrator(s) to determine their own fees,

which were to be reasonable taking into account the sum in dispute and the

complexity of the dispute

31

. The UNCITRAL rules also required the arbitrator(s) to

30

Gary B Born, International Commercial Arbitration (3

nd

edition, 2021), Chapter 13 (“Gary Born on

Arbitration”)

31

Article 38(a) read with Article 39(1), UNCITRAL Rules 1976

PART C

41

take into account the schedule of fees that has been issued or provided by an

appointing authority, if designated by the parties

32

. In the absence of such a fee

schedule, the arbitral tribunal could fix its fees only after consulting with the

appointing authority if a party has requested the appointing authority to furnish a

statement for determining the fees and the appointing authority has consented to

providing such a statement

33

. However, the appointing authority did not have the

power to alter the decision of the tribunal regarding remuneration payable to

arbitrators. The arbitrators had the final authority to determine their

remuneration

34

. Commentators have noted that this was an “unusual approach”

for establishing the fees of arbitrators and was subject to criticism because it

granted arbitrator(s) undue authority to determine their compensation

35

.

44 The UNCITRAL Rules were revised in 2010. The Rules continue to grant a

substantial role to the arbitrators in deciding their own fees but the appointing

authorities, if designated by the parties, or the Permanent Court of Arbitration

36

,

have greater control over such determination. Article 40(2)(a) read with Article 41

of the UNCITRAL Rules 2010 empowers the arbitral tribunal to fix their fees

subject to the same reasonableness requirement and the other criteria prescribed

under the 1976 Rules

37

. The arbitral tribunal is required to inform the parties as to

“how it proposes to determine its fees and expenses, including any rates it

intends to apply” promptly after its constitution

38

. It is noted that this makes the

32

Article 39(2)-(3), UNCITRAL Rules 1976

33

Article 39(3)-(4), UNCITRAL Rules 1976

34

D Caron and L Caplan, The UNCITRAL Arbitration Rules: A Commentary (2

nd

edition, 2013), page 863

35

Supra at note 30

36

“PCA”

37

Article 41(1) reads: “The fees and expenses of the arbitrators shall be reasonable in amount, taking into

account the amount in dispute, the complexity of the subject matter, the time spent by the arbitrators and any

other relevant circumstances of the case.”

38

Article 41(3), UNCITRAL Rules 2010

PART C

42

process of determining fees more transparent

39

. The fees set by the arbitrators

can be reviewed they are not reasonable. Under Articles 41(3)

40

and 41(4)(b)

41

of

the UNCITRAL Rules 2010, within 15 days of receiving the arbitral tribunal’s

determination of fees, the parties can refer the fees determined by the arbitral

tribunal to the appointing authority for review and if no such authority has been

designated, then the review will be undertaken by the Secretary-General of the

PCA. If the Secretary-General of the PCA or the appointing authority (if

designated) finds that the fee proposed to be charged is excessive, then it can

make necessary adjustments in terms of Article 41(4)(c)

42

. The fees so revised

are binding on the tribunal

43

.

(ii) Permanent Court of Arbitration

45 The PCA Rules have been formulated on the basis of the UNCITRAL

Rules 2010. A mandatory automatic review of the fees and expenses determined

by the arbitral tribunal is carried out by Secretary General of the PCA (as the

appointing authority under the PCA Rules) at the conclusion of each case

44

. The

process of review of fees set by the arbitral tribunal is not automatic under the

39

Supra at note 34

40

Article 41(3) reads: “Within 15 days of receiving that proposal, any party may refer the proposal to the

appointing authority for review. If, within 45 days of receipt of such a referral, the appointing authority finds that

the proposal of the arbitral tribunal is inconsistent with paragraph 1, it shall make any necessary adjustments

thereto, which shall be binding upon the arbitral tribunal.”

41

Article 41(4)(b) reads: “Within 15 days of receiving the arbitral tribunal’s determination of fees and expenses,

any party may refer for review such determination to the appointing authority. If no appointing authority has been

agreed upon or designated, or if the appointing authority fails to act within the time specified in these Rules, then

the review shall be made by the Secretary -General of the PCA;”

42

Article 41(4)(c) reads: “If the appointing authority or the Secretary-General of the PCA finds that the arbitral

tribunal’s determination is inconsistent with the arbitral tribunal’s proposal (and any adjustment thereto) under

paragraph 3 or is otherwise manifestly excessive, it shall, within 45 days of receiving such a referral, make any

adjustments to the arbitral tribunal’s determination that are necessary to satisfy the criteria in paragraph 1. Any

such adjustments shall be binding upon the arbitral tribunal;”

43

Articles 41(3), UNCITRAL Rules 2010

44

Article 41(3)(a), PCA Rules 2010

PART C

43

UNCITRAL Rules 2010. Parties may hesitate to invoke the provisions of review in

the fear of upsetting the tribunal or they may raise unjustified requests for review

if they are dissatisfied with the award. The PCA Rules avoid these pitfalls. The

PCA is also empowered to manage the advances of costs incurred by the

arbitrators. Every time a payment is made to an arbitrator out of the deposit, it is

subject to review

45

. The PCA rules become relevant since India has signed a

Host Country Agreement with the PCA and a PCA facility is in the process of

being set up in India.

(iii) London Court of International Arbitration

46

46 The LCIA’s Schedule of Costs of arbitrations governs the fees payable to

the arbitrator(s). The arbitral tribunal is required to agree in writing to the rates

specified in the schedule. The tribunal’s fees are calculated on the basis of the

work done by the arbitrator(s) in connection with the arbitration, the complexity of

the case and requirements relating to the qualification of the arbitrator(s). The

fees are charged on an hourly basis not exceeding £500 unless there are

exceptional circumstances

47

. The role of the arbitrator(s) thus is limited to

reporting the hours worked which forms the basis of the fees to be paid.

45

Article 43 of the PCA Rules reads: “[t]he [PCA] shall ensure that any disbursements of arbitral tribunal fees and

expenses made prior to the fixing of the costs of arbitration pursuant to article 40 are consistent with the criteria in

article 41, paragraph 1 and with the arbitral tribunal’s proposal (and any adjustments thereto)…”

46

“LCIA”

47

Schedule of Arbitration Fees and Costs, LCIA Rules 2020

PART C

44

(iv) International Centre for Dispute Resolution

48

47 The ICDR case administrator fixes the daily or hourly rate for

arbitrator(s)

49

. The determination of fees may involve an element of negotiation

between the parties and the arbitrator(s)

50

. Article 38 of the ICDR Rules 2021

provides that the “[t]he fees and expenses of the arbitrators shall be reasonable

in amount, taking into account the time spent by the arbitrators, the size and

complexity of the case, and any other relevant circumstances”.

(v) International Chamber of Commerce

51

48 The ICC Rules 2021 stipulate that the ICC Court will determine the

arbitrators’ fee

52

according to the fee scale based on the sum in dispute, or where

the sum is not stated, based on its discretion

53

. The ICC Court while setting the

fees of the arbitrator(s) has to consider various factors like “the diligence and

efficiency of the arbitrator, the time spent, the rapidity of the proceedings, the

complexity of the dispute and the timeliness of the submission of the draft

award”

54

. The ICC Court is empowered to increase the fees if the arbitration has

48

“ICDR”

49

Article 38(2), ICDR Rules 2021

50

Article 38(2) of ICDR Rules 2021 provides: “As soon as practicable after the commencement of the arbitration,

the Administrator shall designate an appropriate daily or hourly rate of compensation in consultation with the

parties and all arbitrators, taking into account the arbitrators’ stated rate of compensation and the size and

complexity of the case”.

51

“ICC”

52

Article 38(1) of the ICC Rules 2021 provides: “The costs of the arbitration shall include the fees and expenses

of the arbitrators and the ICC administrative expenses fixed by the Court, in accordance with the scale in force at

the time of the commencement of the arbitration, as well as the fees and expenses of any experts appointed by

the arbitral tribunal and the reasonable legal and other costs incurred by the parties for the arbitration.” Article

38(2) provides: “The Court may fix the fees of the arbitrators at a figure higher or lower than that which would

result from the application of the relevant scale should this be deemed necessary due to the exceptional

circumstances of the case”.

53

Articles 2(1), Appendix III (Arbitration Costs and Fees), ICC Rules 2021

54

Article 2(2), Appendix III (Arbitration Costs and Fees), ICC Rules 2021

PART C

45

been conducted expeditiously and reduce the fees if there has been a delay in

pronouncing the award

55

.

(vi) Singapore International Arbitration Centre

56

49 The fees are fixed by the Registrar in accordance with the Schedule of

Fees on basis of the amount in dispute

57

. The time spent on the matter and the

complexity of the dispute are considered for the determination of fees

58

. The

parties have the discretion to provide an alternative method of determining the

fees prior to the constitution of the arbitral tribunal

59

.

(vii) Hong Kong International Arbitration Centre

60

50 The parties determine the arbitrators’ fees based on either the sum in

dispute or at an hourly rate

61

. If the fees are decided based on the sum in

dispute, then the fees will be fixed on the basis of the guidelines and fee table

55

Paragraphs 118- 22, Note to Parties and Arbitral Tribunals on the Conduct of the Arbitration Under the ICC

Rules of Arbitration (2019)

56

“SIAC”

57

Rule 36(1) of SIAC Rules 2016 provides: The fees of the Tribunal shall be fixed by the Registrar in accordance

with the applicable Schedule of Fees or, if applicable, with the method agreed by the parties pursuant to Rule

34.1, and the stage of the proceedings at which the arbitration concluded. In exceptional circumstances, the

Registrar may determine that an additional fee over that prescribed in the applicable Schedule of Fees shall be

paid”.

58

Supra at note 30

59

Rule 34(1) of SIAC Rules 2016 provides: “The Tribunal’s fees and SIAC’s fees shall be ascertained in

accordance with the Schedule of Fees in force at the time of commencement of the arbitration. The parties may

agree to alternative methods of determining the Tribunal’s fees prior to the constitution of the Tribunal” .

60

“HKIAC”

61

Article 10.1 of HKIAC Rules 2018 provides: “The fees and expenses of the arbitral tribunal shall be determined

according to either:

(a) an hourly rate in accordance with Schedule 2; or

(b) the schedule of fees based on the sum in dispute in accordance with Schedule 3.

The parties shall agree the method for determining the fees and expenses of the arbitral tribunal, and shall inform

HKIAC of the applicable method within 30 days of the date on which the Respondent receives the Notice of

Arbitration. If the parties fail to agree on the applicable method, the arbitral tribunal's fees and expenses shall be

determined in accordance with Schedule 2”.

PART C

46

provided in the Rules. If the fees are to be determined at hourly rates, then a co-

arbitrator will negotiate and agree on their f ees with the nominating party, and a

sole or presiding arbitrator will negotiate with parties jointly

62

.

(viii) International Centre for Settlement of Investment Disputes

63

51 The Secretary General, with the approval of the Chair (Chairman of the

Administrative Council), would determine and publish the fee and per diem

allowance payable to each arbitrator(s) in terms of the Regulation 14 of the ICSID

Administrative and Financial Regulations 2022

64

. The older 2006 version of the

Regulations allowed the parties to contract out of the fee structure prescribed by

ICSID

65

.

(ix) Summary

52 Typically, when an arbitration is conducted under the auspices of an

arbitral institution, the fees payable to the arbitrator(s) are fixed by the institution

62

Article 10.2 of HKIAC Rules 2018 provides: “Where the fees of the arbitral tribunal are to be determined in

accordance with Schedule 2,

(a) the applicable rate for each co-arbitrator shall be the rate agreed between that co- arbitrator and the

designating party;

(b) the applicable rate for a sole or presiding arbitrator designated by the parties or the co-arbitrators, as

applicable, shall be the rate agreed between that arbitrator and the parties, subject to paragraphs 9.3 to 9.5 of

Schedule 2. Where the rate of an arbitrator is not agreed in accordance with Article 10.2(a) or (b), or where

HKIAC appoints an arbitrator, HKIAC shall determine the rate of that arbitrator”.

63

“ICSID”

64

Regulation 14 (2) states: “The Secretary-General, with the approval of the Chair, shall determine and publish

the amount of the fee and the per diem allowance referred to in paragraph (1)(a) and (c). Any request by a

member for a higher amount shall be made in writing through the Secretary-General, and not directly to the

parties. Such a request must be made before the constitution of the Commission, Tribunal or Committee and

shall justify the increase requested”.

65

Regulation 14 states: “(1) Unless otherwise agreed pursuant to Article 60(2) of the Convention, and in addition

to receiving reimbursement for any direct expenses reasonably incurred, each member of a Commission, a

Tribunal or an ad hoc Committee appointed from the Panel of Arbitrators pursuant to Article 52(3) of the

Convention (hereinafter referred to as “Committee”) shall receive…”

PART C

47

itself. However, some arbitral institutions like ICDR, SIAC and HKIAC allow a

certain level of negotiations between the parties and arbitrator(s) for the

determination of fees payable to the arbitrators, upholding the principle of party

autonomy. ICDR allows determination of compensation by the Administrator in

consultation with the arbitrator(s) and the parties. SIAC allows the parties to

propose an alternative method of calculating fees prior to the constitution of the

tribunal. HKIAC enables the parties to choose between remuneration based on

the sum in dispute or hourly rates. Interestingly, UNCITRAL Rules 2013 allow

greater control to the arbitrator(s) in determining their fees. However, the

designated appointing authority or the Secretary General of the PCA can make

adjustments to the fees proposed by the arbitrator(s). Thus, none of the

international bodies (including arbitral institutions) confer an absolute or unilateral

power to the arbitrator(s) to decide their own fees. G ary Born in his treatise on

international commercial arbitration has noted that, “[a] number of other

institutional rules also minimize the role of arbitrators in fixing the tribunal’s fees.

These rules typically fix the amount of the arbitrator’s fees by reference to the

amount in dispute”

66

.

C.1.2 Position in other national jurisdictions

53 While it will not be possible to undertake a comprehensive review of all the

foreign jurisdictions in respect of the legal regime governing the payment of

remuneration to arbitrators, we have discussed a few jurisdictions that either

66

Supra at note 30

PART C

48

have explicitly recognised an arbitrators’ entitlement to remuneration and/or have

dealt with the issue of arbitrators’ power of fixing their own remuneration.

(i) England

54 The English courts have held that the arbitrator’s rights and duties result

from a conjunction of contract and status

67

. Upon accepting the appointment, the

arbitrator becomes a party to the arbitration agreement, giving rise to a trilateral

contract between the parties and the arbitrator

68

. However, the English courts

acknowledge that certain aspects of the relationship between the arbitrator and

parties are also influenced by the quasi-judicial status of the arbitrator, which

requires the arbitrator to be independent of the parties

69

.

55 Section 28 of the English Arbitration Act 1996

70

recognises the entitlement

of an arbitrator to remuneration. This is a mandatory provision which cannot be

derogated from

71

. Section 28(1) codifies the common law position

72

that parties

are jointly and severally liable to pay reasonable fees and expenses to the

arbitrator(s) as is appropriate in the circumstances. In terms of Section 28(5), the

arbitrator(s) are entitled to be paid the fees and expenses agreed by them with

the parties

73

. However, if there is no such agreement, the arbitral tribunal can

67

KS Norjarl AS v. Hyundai Heavy Indus. Co., [1992] 1 QB 863, 884

68

Compagnie Européenne de Céréales SA v. Tradax Exp. SA, [1986] 2 Lloyd’s Rep. 301 (QB)

69

Jivraj v. Hashwani, [2011] UKSC 40

70

“English Arbitration Act”

71

Section 4(1) and Schedule 1 of the English Arbitration Act

72

Loukas A Mistelis (ed), Concise International Arbitration (2

nd

edition, 2015), Chapter 23 (“Mistelis on

Arbitration”)

73

Section 28(5) provides: “Nothing in this section affects any liability of a party to any other party to pay all or any

of the costs of the arbitration (see sections 59 to 65) or any contractual right of an arbitrator to payment of his

fees and expenses.”

PART C

49

seek payment of such fees and expenses from one, some or all the parties

74

. The

parties’ liability to pay fees and expenses may be determined by courts. The

court may consider factors like the standard fee s of the arbitrator(s), the time

invested, complexity of the dispute, and whether the procedures adopted by the

tribunal were suitable

75

.Section 33(1)(b) stipulates that it is the duty of the arbitral

tribunal to adopt procedures that are suitable to the circumstances of the case

and to avoid unnecessary delays or expenses, to provide a fair means for the

resolution of the dispute. The court is also entitled to review the fees

76

determined by the arbitrator(s) or arbitral institution, which has not been

contractually agreed to by the parties

77

. However, if the agreement with an

arbitrator(s) or an arbitral institution is not clear regarding the terms of the

payment , the court can intervene to review the fees, in order to examine if they

are reasonable

78

. It is also important to note that where only one party has

agreed to the fees and the fees have been held to be unreasonable, then the

other party is only jointly and severally liable to pay the amount that the court has

determined to be reasonable, but the first party may be liable contractually to pay

the contractually agreed amount

79

.

74

Supra at note 72

75

ibid

76

Section 28(2) provides: “Any party may apply to the court (upon notice to the other parties and to the

arbitrators) which may order that the amount of the arbitrators’ fees and expenses shall be considered and

adjusted by such means and upon such terms as it may direct.”

77

Hussmann (Europe) Ltd v. Al Ameen Development & Trade, [2000] 2 Lloyd's Rep. 83. Queen’s Bench

Division (Commercial Court)), paragraphs 71- 72

78

ibid

79

Supra at note 72

PART C

50

(ii) Italy

56 Article 814 of the Italian Code of Civil Procedure provides that the

arbitrators have a right to expenses and the fees for the work done, unless they

have waived this right at the time of acceptance or through a subsequent written

statement. Article 814 also provides that the parties are jointly and severally liable

for paying the fees and expenses of the arbitral proceedings, irrespective of how

the arbitration costs are apportioned between them. If one party has made all the

payments of the fees and expenses payable to the arbitrator(s), they are entitled

to recover this amount from the other party subject to the limits set out in the

award.

57 Article 814 also recognises that arbitrator(s) determine their own fees in

the award and allocate the responsibility of the payment of such fees. However,

such a determination is not binding unless the parties approve the fees proposed

by the arbitrator(s). If the fees have not been paid, the arbitrator(s) can approach

the President of the court in the district where the arbitration is seated for the

determination of the fees. This order is enforceable against the parties

80

. The

schedule of fees is provided in the Ministerial Decree issued by the Italian

Ministry of Justice for domestic ad hoc arbitrations

81

.

80

CMS Expert Guides, “International Arbitration Law and Rules in Italy ”, available at

<https://cms.law/en/int/expert- guides/cms-expert-guide-to -international-arbitration/italy> accessed on 29 June

2022; See also, Italian Code of Civil Procedure, available at <https://www.international-arbitration-

attorney.com/wp-content/uploads/2013/07/Italy -Arbitration-Law.pdf> accessed on 29 June 2022

81

Cecilia Carrara, Stefano Parlatore, Daniele Geronzi et.al, Arbitration Procedures and Practice in Italy, available

at <https://uk.practicallaw.thomsonreuters.com/6-383 -

9187?transitionType=Default&contextData=(sc.Default)&firstPage=true#co_anchor_a719112> accessed on 29

June 2022

PART C

51

(iii) Sweden

58 The arbitral tribunal is empowered to set its own fees unless there is an

agreement between the parties

82

. Section 37(1) of the Swedish Arbitration Act

83

provides that the parties are jointly and severally liable to pay reasonable

compensation to the arbitrator(s) for work and expenses. The Swedish Supreme

Court has interpreted the words “reasonable compensation” to mean an

assessment of time spent by the arbitrator (s) and the qualification of the

arbitrator(s)

84

. The Swedish Supreme Court has also noted that a

disproportionately high cost of arbitration compared to the value of sum in dispute

does not necessarily require a reduction in the compensation

85

.

59 Section 37 of the Swedish Arbitration Act is applicable “unless otherwise

jointly decided by the parties in a manner that is binding upon the arbitrators”.

Commentators have thus noted that Section 37 is non -mandatory and can be

altered or waived off by the parties

86

. However, it is understood that if the

arbitrator(s) are not parties to an agreement with respect to their compensation, it

becomes binding on the arbitrator(s) only if they are aware and understand the

agreement when they accept the appointment

87

. Section 39 of the Swedish

Arbitration Act further provides that an agreement regarding compensation to the

arbitrator(s) which is not entered jointly by the parties is void.

82

Annette Magnusson, Jakob Ragnwaldh and Martin Wallin (eds), International Arbitration in Sweden: A

Practitioner's Guide (2

nd

edition, 2021), Chapter 9

83

The Swedish Arbitration Act (SFS 1999:116), available at <https://sccinstitute.se/media/1773096/the-swedish -

arbitration- act_1march2019_eng-2.pdf > accessed on 29 June 2022

84

Supra at note 82

85

NEMU Mitt i Sverige AB v. Jan H, Gunnar B and Bo N (the arbitrators), the Supreme Court, 22 October

1998, NJA 1998 p. 574 (T 105-98)

86

Supra at note 82

87

ibid

PART C

52

60 Section 41 enables a party or an arbitrator to file an application before the

District Court regarding the amendment of the award with respect to the payment

of compensation to the arbitrator(s). The District Court is empowered to reduce

the compensation of the arbitrator(s). The national courts also have the power to

revise the fees set by arbitral institutions, if the seat of the arbitration is in

Sweden

88

. This is an unusual exception since typically rules of arbitral institutions

setting the fees are never subject to judicial review

89

.

(iv) Germany

61 The German arbitration law is governed by the Tenth Book of the Code of

Civil Procedure (Zivilprozessordnung)

90

. In the absence of an agreement in ad

hoc arbitrations, the ZPO does not contain any provision regulating the fees

payable to arbitrator(s). Fees are then to be charged in terms of the rules of the

German Civil Code (Bürgerliches Gesetzbuch)

91

depending on whether the

contract between the parties is to be classified as a service contract or contract

for work. The provisions of the BGB provide that remuneration for such contracts

is deemed to be the fees of the arbitrator(s) in absence of an agreement between

the parties

92

.

62 However, in Germany, the arbitrator(s) are prohibited from determining

their own fees in the absence of an agreement under the doctrine of prohibition of

88

Soyak Int’l Constr. & Inv. Inc. v. Hobér, Kraus & Melis, Case No. O 4227-06 (Swedish S.Ct. 2008)

89

Supra at note 30

90

“ZPO”

91

“BGB”

92

K. Bockstiegel, Stefan Kröll and Patricia Nacimiento (eds), Arbitration in Germany: The Model Law in Practice

(2

nd

edition, 2015), Chapter VI

PART C

53

in rem suam decisions, i.e., arbitrators cannot be a judge of their own cause

93

.

Earlier, even a decision regarding the sum in dispute by the arbitral tribunal was

seen as indirectly determining the amount of fees when fees are calculated as a

percentage of the amount at stake and thus, was considered to be a violation of

the above doctrine

94

. However, recently, the Federal Court of Justice

(Bundesgerichtshof)

95

held that a decision of the tribunal regarding the sum in

dispute, even if it influences the fees payable to the arbitrator(s), does not violate

the doctrine of prohibition of in rem suam decisions

96

. The BGH observed that

since the ZPO obligates the arbitral tribunal to render a determination on costs,

which often includes a determination regarding the sum in dispute, such a

determination, even if it indirectly includes a decision on the fees, would not

become a decision in rem suam

97

. The BGH further noted that while a

determination of the sum in dispute only binds the parties, it is not actually a

decision in rem suam from the arbitrators’ perspective

98

. In any event, an indirect

determination by the arbitrator(s) as to their own fees only forms the basis of an

arbitrator’s claim against a party and can be enforced only through court action if

the party fails to pay the amount. In terms of the BGB, the courts can review such

a claim to decide if it’s equitable. Thus, the arbitrator(s) cannot determine their

fees arbitrarily

99

.

93

ibid

94

ibid

95

“BGH”

96

BGH 28.03.2012, SchiedsVZ 2012, 154 cited in supra at note 30; See also, supra at note 92

97

ibid

98

ibid

99

ibid

PART C

54

(v) Japan

63 Under Article 47(1) of the Japanese Arbitration Law

100

, the fees payable to

the arbitrator(s) are to be governed by the agreement between the parties. If

there is no agreement, then in terms of Article 47(2), the arbitral tribunal has the

power to determine the remuneration of the arbitrator(s). In such cases, the

remuneration has to be of an appropriate amount.

(vi) Singapore

64 Section 40(1) of the Arbitration Act 2001

101

provides that the parties are

jointly and severally liable to pay reasonable fees and expenses to the

arbitrator(s) that are appropriate to the circumstances. Section 40(2) provides

that in the absence of a written agreement between the parties as to the fees

payable to the arbitrator(s), any party can approach the Registrar of the Supreme

Court within the meaning of the Supreme Court of Judicature Act 1969 for the

assessment of fees. While Section 41(1) of the Singapore Arbitration Act

empowers the arbitral tribunal to refuse to deliver an award if the parties have not

made full payment of their fees and expenses, Section 41(2) allows a party to

apply to the court to review the fees

102

. This has been understood as the right of

the parties to challenge unreasonable fees

103

.

100

Law No 138 of 2003, available at < https://japan.kantei.go.jp/policy/sihou/arbitrationlaw.pdf> accessed on 29

June 2022

101

Available at

<https://sso.agc.gov.sg/Act/AA2001#:~:text=1.,is%20the%20Arbitration%20Act%202001.&text=the%20arbitral%

20tribunal%20as%20authorised,and%20all%20the%20relevant%20circumstances> accessed on 29 June 2022

(“Singapore Arbitration Act”)

102

Section 41(2) reads: “(2) Where subsection (1) applies, a party to the arbitral proceedings may, upon notice to

the other parties and the arbitral tribunal, apply to the Court, which may order that —

PART C

55

(vii) United States

65 The United States Federal Arbitration Act 1925

104

does not explicitly make

a reference to the rights or duties of the arbitrator(s). The Uniform Arbitration Act,

enacted in 1955, is also of relevance. It functions as a model arbitration statute to

enable each state to adopt a uniform arbitration law. It was revised in 2000.

Section 21(d) of the revised version of the Act provides that “an arbitrator’s

expenses and fees, together with other expenses, must be paid as provided in

the award.” The comment to this Section under the Act provides that “Section

21(d)… allows arbitrators, unless the agreement provides to the contrary, to

determine in the award payment of expenses, including the arbitrator’s expenses

and fees”

105

. In the United States, it has been held that it is a violation of public

policy if the arbitrator(s) attempt to renegotiate the fees at a later stage once they

are appointed, owing to the concern that the parties may be compelled to accede

to the demand fearing adverse consequences

106

.

(a) the arbitral tribunal must deliver the award upon payment into Court by the applicant of the fees and

expenses demanded, or any lesser amount that the Court may specify;

(b) the amount of the fees and expenses demanded are to be assessed by the Registrar of the Supreme

Court; and

(c) out of the money paid into Court, the arbitral tribunal must be paid the fees and expenses that may be

found to be properly payable and the balance of the money (if any) must be paid out to the applicant”.

103

Bernard Hanotiau and Alexis Mourre (eds), Players Interaction in International Arbitration (ICC, 2012),

Chapter 12

104

“FAA”

105

Uniform Arbitration Act (Last Revisions Completed Year 2000), available at

<https://www.uniformlaws.org/HigherLogic/System/DownloadDocumentFile.ashx?DocumentFileKey=8fff228f-

9517-f310-36a1- 989efa4a826e&forceDialog=0> accessed on 29 June 2022

106

Double-M Construction Corp. v. Central School District No 1 Town of Highlands Orange County, (1978)

402 NYS 2d 442 cited in Jeffrey Waincymer, Procedure and Evidence in International Arbitration (Walters Kluwer,

2012)

PART C

56

(viii) Summary

66 Although there are jurisdictional differences, the following broad principles

emerge from our discussion above:

(i) Typically, the fees payable to arbitrator(s) are determined through an

agreement between the parties (of which the arbitrator(s) become aware of

when they take up the assignment) or a separate agreement of the parties

with the arbitrator (s). The arbitrator (s) then become bound by such

contractually agreed fees; and

(ii) Certain arbitration legislations give the arbitrator(s) effective power to

determine their own fees, typically when there is an absence of agreement

between the parties on the subject. However, such determination of fees is

subject to review by the courts who can reduce the fees if they are not

reasonable.

67 Thus, arbitrator(s) do not possess an absolute or unilateral power to

determine their own fees. Parties are involved in determining the fees of the

arbitrator(s) in some form. It could be by: (i) determining the fees at the threshold

in the arbitration agreement; or (ii) negotiating with the arbitrators when the

dispute arises regarding the fees that are payable; or (iii) by challenging the fees

determined by the tribunal before a court.

PART C

57

C.2 Statutory scheme on payment of fees to arbitrators in India

C.2.1 Party autonomy

68 Party autonomy is a cardinal principle of arbitration. The arbitration

agreement constitutes the foundation of the arbitral process. The arbitral tribunal

is required to conduct the arbitration according to the procedure agreed by the

parties. The procedure may stipulate adherence to institutional rules or ad hoc

rules or a combination of both. Redfern and Hunter on International

Commercial Arbitration (supra) compares arbitration to a ship, highlighting the

extent of control parties exercise over arbitral proceedings:

“In some respects, an international arbitration is like a ship.

An arbitration may be said to be ‘owned’ by the parties, just

as a ship is owned by shipowners. But the ship is under the

day-to-day command of the captain, to whom the owners

hand control. The owners may dismiss the captain if they

wish and hire a replacement, but there will always be

someone on board who is in command (5) —and, behind the

captain, there will always be someone with ultimate control.”

The leading treatise on international commercial arbitration further notes that the

principle of party autonomy is entrenched in the international and national

regimes on arbitration:

“Party autonomy is the guiding principle in determining the

procedure to be followed in an international arbitration. It is a

principle that is endorsed not only in national laws, but also by

international arbitral institutions worldwide, as well as by

international instruments such as the New York Convention

and the Model Law. The legislative history of the Model Law

shows that the principle was adopted without

opposition, (7) and Article 19(1) of the Model Law itself

provides that: ‘Subject to the provisions of this Law, the

parties are free to agree on the procedure to be followed by

the arbitral tribunal in conducting the proceedings.’ This

principle follows Article 2 of the 1923 Geneva Protocol, which

provides that ‘[t]he arbitral procedure, including the

PART C

58

constitution of the arbitral tribunal, shall be governed by the

will of the parties …’, and Article V(1)(d) of the New York

Convention, under which recognition and enforcement of a

foreign arbitral award may be refused if ‘the arbitral procedure

was not in accordance with the agreement of the parties’.”

69 The Arbitration Act recognises the principle of party autonomy in various

provisions. It allows the parties to derogate from the provisions of the Act on

certain matters. Several provisions of the Arbitration Act explicitly embody the

principle of party autonomy. Section 2(6)

107

of the Arbitration Act provides that

parties have the freedom to authorise any person, including an arbitral institution,

to determine the issue between them. Section 19(2)

108

provides that the parties

are free to choose the procedure to be followed for the conduct of arbitral

proceedings. Section 11(2)

109

provides that parties are free to decide on the

procedure for the appointment of arbitrators. In Bharat Aluminium Co. v. Kaiser

Aluminium Technical Services

110

, this Court observed that party autonomy is

the “brooding and guiding spirit” of arbitration. In Centrotrade Minerals & Metal

Inc. v. Hindustan Copper Ltd

111

, this Court referred to party autonomy as the

backbone of arbitration.

70 Having spelt out party autonomy as the cardinal principle of arbitration in

India, in the sections which follow we analyse how provisions relating to the

payment of fees to arbitrators have to be interpreted in light of this principle.

107

Section 2 (6) of the Arbitration Act states: “Where this Part, except section 28, leaves the parties free to

determine a certain issue, that freedom shall include the right of the parties to authorise any person including an

institution, to determine that issue”.

108

Section 19(2) of the Arbitration Act states: “Subject to this Part, the parties are free to agree on the procedure

to be followed by the arbitral tribunal in conducting its proceedings”.

109

Section 11(2) of the Arbitration Act states: “Subject to sub-section (6), the parties are free to agree on a

procedure for appointing the arbitrator or arbitrators”.

110

(2016) 4 SCC 126, paragraph 5

111

(2017) 2 SCC 228, paragraph 38

PART C

59

C.2.2 Fourth Schedule and regulation of arbitrators’ fees

71 Appointment of arbitrator(s) in India may take place either through an

agreement between parties or by taking recourse to courts under Sections 11(3)

and 11(6) of the Arbitration Act. Prior to the amendment of the Arbitration Act by

the Arbitration Amendment Act 2015, a practice emerged, especially in cases of

ad hoc arbitrations, where arbitrators would unilaterally, and in some cases

arbitrarily, fix excessive fees for themselves. In Singh Builders (supra), this

Court noted that such arbitrary fixation of fees by the arbitrators, specifically

court-appointed arbitrators, has made arbitration an expensive proposition,

bringing it into disrepute. The Court suggested some possible solutions. This

Court observed:

“22. When an arbitrator is appointed by a court without

indicating fees, either both parties or at least one party is at a

disadvantage. Firstly, the parties feel constrained to agree to

whatever fees is suggested by the arbitrator, even if it is high

or beyond their capacity. Secondly, if a high fee is claimed by

the arbitrator and one party agrees to pay such fee, the other

party, which is unable to afford such fee or reluctant to pay

such high fee, is put to an embarrassing position. He will not

be in a position to express his reservation or objection to the

high fee, owing to an apprehension that refusal by him to

agree for the fee suggested by the arbitrator, may prejudice

his case or create a bias in favour of the other party which

readily agreed to pay the high fee.

23. It is necessary to find an urgent solution for this problem

to save arbitration from the arbitration cost. Institutional

arbitration has provided a solution as the arbitrators' fees is

not fixed by the arbitrators themselves on case- to-case basis,

but is governed by a uniform rate prescribed by the institution

under whose aegis the arbitration is held. Another solution is

for the court to fix the fees at the time of appointing the

arbitrator, with the consent of parties, if necessary in

consultation with the arbitrator concerned. Third is for the

retired Judges offering to serve as arbitrators, to indicate their

fee structure to the Registry of the respective High Court so

that the parties will have the choice of selecting an arbitrator

PART C

60

whose fees are in their “range” having regard to the stakes

involved.

24. What is found to be objectionable is parties being forced

to go to an arbitrator appointed by the court and then being

forced to agree for a fee fixed by such arbitrator. It is

unfortunate that delays, high costs, frequent and sometimes

unwarranted judicial interruptions at different stages are

seriously hampering the growth of arbitration as an effective

dispute resolution process. Delay and high costs are two

areas where the arbitrators by self-regulation can bring about

marked improvement.”

72 In Sanjeev Kumar Jain v. Raghubir Saran Charitable Trust and Ors.

112

,

this Court in a similar vein observed that arbitrators in ad hoc arbitrations in India

are charging disproportionately high fees. While interpreting Section 11 of the

Arbitration Act, this Court held that the word “appointment” does not merely refer

to nominating or designating a person to act as an arbitrator, but it includes the

court’s power to stipulate the fees that can be charged by an arbitrator appointed

by the court. The fees should be stipulated after hearing the parties and, if

required, after ascertaining the fees structure from prospective arbitrators. This

will avoid a situation where parties have to negotiate the terms of the fees of the

arbitrators, after their appointment. Referring to Singh Builders (supra), this

Court acknowledged the increased complaints against disproportionate fees

being charged by the arbitrators and made certain suggestions for the healthy

development of arbitration in India. One such remedy suggested by this Court

was disclosure of the fee structure prior to the appointment of arbitrators to

enable any party to express their unwillingness to bear such expenses . This

Court observed thus:

112

(2012) 1 SCC 455

PART C

61

“41. There is a general feeling among the consumers of

arbitration (parties settling disputes by arbitration) that ad hoc

arbitrations in India—either international or domestic, are time

consuming and disproportionately expensive. Frequent

complaints are made about two sessions in a day being

treated as two hearings for the purpose of charging fee; or

about a session of two hours being treated as full session for

purposes of fee; or about non- productive sittings being

treated as fully chargeable hearings. It is pointed out that if

there is an Arbitral Tribunal with three arbitrators and if the

arbitrators are from different cities and the arbitrations are to

be held and the arbitrators are accommodated in five star

hotels, the cost per hearing (arbitrator's fee, lawyer's fee, cost

of travel, cost of accommodation, etc.) may easily run into

rupees one million to one- and-half million per sitting. Where

the stakes are very high, that kind of expenditure is not

commented upon. But if the number of hearings become too

many, the cost factor and efficiency/effectiveness factor is

commented. That is why this Court in Singh Builders

Syndicate [(2009) 4 SCC 523 : (2009) 2 SCC (Civ) 246]

observed that the arbitration will have to be saved from the

arbitration cost.

42. Though what is stated above about arbitrations in India,

may appear rather harsh, or as a universalisation of stray

aberrations, we have ventured to refer to these aspects in the

interest of ensuring that arbitration survives in India as an

effective alternative forum for disputes resolution in India.

Examples are not wanting where arbitrations are being shifted

to neighbouring Singapore, Kuala Lumpur, etc. on the ground

that more professionalised or institutionalised arbitrations,

which get concluded expeditiously at a lesser cost, are

available there. The remedy for healthy development of

arbitration in India is to disclose the fees structure before the

appointment of arbitrators so that any party who is unwilling to

bear such expenses can express his unwillingness. Another

remedy is institutional arbitration where the arbitrator's fee is

prefixed. The third is for each High Court to have a scale of

arbitrator's fee suitably calibrated with reference to the

amount involved in the dispute. This will also avoid different

designates prescribing different fee structures. By these

methods, there may be a reasonable check on the fees and

the cost of arbitration, thereby making arbitration, both

national and international, attractive to the litigant

public. Reasonableness and certainty about total costs are

the key to the development of arbitration. Be that as it may.”

PART C

62

73 It was in the above context that the LCI 246

th

Report (supra) proposed

reforms for regulating arbitrators’ fees in ad hoc arbitrations. The Commission

recommended that a model schedule of fees should be inserted into the

Arbitration Act, which was to serve as a guide for High Courts to frame their own

rules governing the fixation of arbitrators’ fees. The Commission accepted that

different values and standard of fees may be adopted in international commercial

arbitrations, which led to the exclusion of the applicability of the Fourth Schedule

to the Arbitration Act to international commercial arbitrations. The Commission

adversely commented on the practice of charging fees on “per sitting” basis in ad

hoc arbitrations where sometimes there are 2- 3 sittings in a day in the same

matter between the same parties. The Commission also noted that costs are

further increased by continuation of proceedings for years since dates are given

with significant gaps, resulting in the denial of timely delivery of justice to the

aggrieved party.

74 The Arbitration Amendment Act 2015 introduced the Fourth Schedule to

the Arbitration Act as a model schedule of fees in terms of the recommendations

of the LCI 246

th

Report (supra). The Fourth Schedule came into effect on 23

October 2015. Section 11 of the Arbitration Act was also accordingly amended to

add sub-Section (14) to Section 11, which reads as follows:

“Section 11. Appointment of arbitrators

[…]

(14) For the purpose of determination of the fees of the

arbitral tribunal and the manner of its payment to the arbitral

tribunal, the High Court may frame such rules as may be

necessary, after taking into consideration the rates specified

in the Fourth Schedule.

PART C

63

Explanation: For the removal of doubts, it is hereby clarified

that this subsection shall not apply to international

commercial arbitration and in arbitrations (other than

international commercial arbitration) in case where parties

have agreed for determination of fees as per the rules of an

arbitral institution.”

The Fourth Schedule has to be read along with the provisions of sub- Section (14)

of Section 11. In terms of the Explanation to Section 11(14), the Fourth Schedule

will not be applicable to international commercial arbitrations. Further, the Fourth

Schedule will not be applicable where parties have agreed to the determination of

the arbitrators’ fees according to the rules of an arbitral institution. The Fourth

Schedule was to serve as a guide for different High Courts to frame rules for

determining the fees of arbitrators. The High Courts have been slow, if not tardy,

in framing these rules. Apart from the High Courts of Rajasthan, Kerala and

Bombay, other High Courts have not framed rules under Section 11 (14) of the

Arbitration Act for the determination of fees. Further the rules framed by High

Courts of Bombay and Rajasthan only govern arbitrators appointed by the courts.

Thus, the purpose of Section 11(14) for regulating fees in ad hoc arbitrations

remains unrealised.

75 A dispute arose before the Delhi High Court regarding the applicability of

the Fourth Schedule to the arbitration agreement in a situation where the fee

payable to the arbitrator(s) has already been stipulated in the arbitration

agreement. In Gammon Engineers and Contractors Pvt. Ltd. v. NHAI

113

, the

fee schedule was fixed by the parties in accordance with a policy decision of the

National Highways Authority of India dated 31 May 2004. However, the arbitral

113

2018 SCC OnLine Del 10183 (“Gammon”)

PART C

64

tribunal decided that its fees will be regulated in terms of the Fourth Schedule

introduced through the Arbitration Amendment Act 2015 by observing that the

latest provisions in the amended Act empower it to unilaterally determine its own

fees, irrespective of the agreement between the parties. NHAI moved an

application under Section 14 of the Arbitration Act to terminate the mandate of

the arbitral tribunal since it had wilfully rejected the agreement between the

parties. A Single Judge of the Delhi High Court held that since there was an

agreement between the parties regarding the fixation of fees, the Fourth

Schedule will not be applicable. The Single Judge further held that while Section

31A of the Arbitration Act discusses different aspects of “costs” to be fixed by the

arbitral tribunal while passing an award, it is only one of the aspects to be

considered by the tribunal for determining costs payable by one party to another.

The words “unless otherwise agreed by the parties” were omitted from Section

31(8) of the Arbitration Act (as amended by the Arbitration Amendment Act 2015)

to ensure that parties cannot contract out of paying costs and denude the ability

of the tribunal to award costs in favour of the successful party. The Single Judge,

thus, terminated the mandate of the arbitral tribunal since it wilfully ignored the

agreement between the parties. In doing so, the Single Judge disagreed with the

view of another Single Judge of the Delhi High Court in NHAI v. Gayatri Jhansi

Roadways Ltd.

114

.

76 In Gayatri Jhansi (Delhi High Court) (supra), it was held that Section

31(8) and Section 31A of the Arbitration Act govern the determination of fees and

since the expression “unless otherwise agreed by the parties” has been removed

114

2017 SCC OnLine Del 10285 (“Gayatri Jhansi (Delhi High Court)”)

PART C

65

from Section 31(8) by the Arbitration Amendment Act 2015, the power of the

parties to fix the arbitrators’ fees has been specifically taken away except in

international commercial arbitrations and arbitrations where parties have agreed

that the fees will be fixed under the rules of an arbitral institution. Thus, in Gayatri

Jhansi (Delhi High Court) (supra), the arbitral tribunal was allowed to fix its fees

according to the Fourth Schedule dehors the agreement between the parties.

77 The appeals against both the judgements of the Delhi High Court were

heard by this Court in Gayatri Jhansi Roadways Ltd (supra), where a two-

Judge Bench of this Court was called upon to determine the applicability of the

Fourth Schedule when the arbitrators’ fee has been fixed by an agreement

between the parties. This Court held that Section 31(8) read with Section 31A will

not be applicable if the fees of the arbitrator(s) have been fixed by an agreement.

This Court upheld the observations of the Single Judge of the Delhi High Court in

Gammon (supra) in this regard. Justice Rohinton F Nariman, speaking for the

Bench, observed as follows:

“14. However, the learned Single Judge's conclusion that the

change in language of Section 31(8) read with Section 31- A

which deals only with the costs generally and not with

arbitrator's fees is correct in law. It is true that the arbitrator's

fees may be a component of costs to be paid but it is a far cry

thereafter to state that Sections 31(8) and 31-A would directly

govern contracts in which a fee structure has already been

laid down. To this extent, the learned Single Judge is correct.

We may also state that the declaration of law by the learned

Single Judge in Gayatri Jhansi Roadways Ltd. [NHAI v.

Gayatri Jhansi Roadways Ltd., 2017 SCC OnLine Del 10285]

is not a correct view of the law.”

However, this Court observed that the fee schedule contained in NHAI’s circular

dated 1 June 2017 would substitute the earlier schedule and the arbitrators would

PART C

66

be entitled to charge their fees in accordance with the updated fee schedule, but

not in terms of the Fourth Schedule to the Arbitration Act. This Court further

observed that the mandate of the arbitral tribunal in Gammon (supra) should not

be terminated since the arbitrator(s) had merely followed the law which had been

laid down in Gayatri Jhansi (Delhi High Court) (supra).

78 The Arbitration Amendment Act 2019 was introduced on the basis of the

report of High Level Committee dated 30 July 2017 for promoting institutional

arbitration. Sub-Section 11(14) has been subsequently amended by the

Arbitration Amendment Act 2019. The amended sub- Section (14) to Section 11

provides thus:

“Section 11. Appointment of arbitrators

[…]

(14) The arbitral institution shall determine the fees of the

arbitral tribunal and the manner of its payment to the arbitral

tribunal subject to the rates specified in the Fourth Schedule.

Explanation: For the removal of doubts, it is hereby clarified

that this sub- section shall not apply to international

commercial arbitration and in arbitrations (other than

international commercial arbitration) in case where parties

have agreed for determination of fees as per the rules of an

arbitral institution.”

Further, sub- Section (3A) has been introduced to Section 11, which stipulates

thus:

“Section 11. Appointment of arbitrators

[…]

(3A) The Supreme Court and the High Court shall have the

power to designate, arbitral institutions, from time to time,

which have been graded by the Council under section 43- I,

for the purposes of this Act:

PART C

67

Provided that in respect of those High Court jurisdictions,

where no graded arbitral institution are available, then, the

Chief Justice of the concerned High Court may maintain a

panel of arbitrators for discharging the functions and duties of

arbitral institution and any reference to the arbitrator shall be

deemed to be an arbitral institution for the purposes of this

section and the arbitrator appointed by a party shall be

entitled to such fee at the rate as specified in the Fourth

Schedule:

Provided further that the Chief Justice of the concerned High

Court may, from time to time, review the panel of arbitrators.”

The amendments introduced to Section 11 by the Arbitration Amendment Act

2019 came into force on 30 August 2019. However, even after a lapse of three

years, the Arbitration Council has not been established in accordance with Part

IA of the Arbitration Amendment Act 2019. In the absence of the Arbitration

Council of India, graded arbitral institutions for the purpose of implementing

amendments to Section 11 are yet to come into existence. While several High

Courts have taken concerted steps to establish and refer matters to court adjunct

arbitration centres, ad hoc arbitrations continue to hold the field since the

amendments made by the Arbitration Amendment Act 2019 have been non-

starters. . However, the amendments indicate the legislative intent that going

forward, the fixation of fees of arbitrator(s) would be carried out by an arbitral

institution designated for such purpose in terms of sub- Section (14) of Section 11.

Further, there is one notable difference between the sub- Section (14) as it stood

before the amendment and after, in terms of the applicability of the Fourth

Schedule. Earlier, the rates specified in the Fourth Schedule were only to be

taken into consideration by the High Court while framing the rules relating to the

fixation of fees. However, now the provision reads that, “[t]he arbitral institution

PART C

68

shall determine the fees of the arbitral tribunal and the manner of its payment to

the arbitral tribunal subject to the rates specified in the Fourth Schedule”. There

are two exceptions to this – Section 11(14) is not applicable to international

commercial arbitrations and to a situation where the parties have agreed to

determine fees in terms of the rules of an arbitral institution as stipulated in the

Explanation to Section 11(14). It is important to note that the newly introduced

Section 11(3A) provides that the Supreme Court and the High Courts shall have

the power to designate arbitral institutions from time to time, which have been

graded by the Arbitration Council of India under Section 43(1) of the Arbitration

Act. The first proviso to sub- Section (3A) to Section 11 provides that in those

jurisdictions of High Courts where there are no graded arbitral institutions

available, the Chief Justice of the High Court may maintain a panel of arbitrators

for discharging the functions and duties of an arbitral instit ution. In terms of the

first proviso, the reference to such an arbitrator would be deemed to be reference

to an arbitral institution for the purpose of Section 11 and arbitrator appointed by

a party is entitled to such fee at the rate as specified in the Fourth Schedule. A

harmonious reading of the first proviso to sub- Section (3A) of Section 11 and

sub-Section (14) of Section 11 indicate that the Fourth Schedule shall have a

mandatory effect on the stipulation of fees for arbitrator(s) appointed by arbitral

institutions designated for such purpose in terms of Section 11 of the Arbitration

Act in the absence of an arbitration agreement governing the fee structure.

79 Based on the above discussion, w e summarise the position as follows:

(i) In terms of the decision of this Court in Gayatri Jhansi Roadways Ltd

(supra) and the cardinal principle of party autonomy, the Fourth Schedule

PART C

69

is not mandatory and it is open to parties by their agreement to specify the

fees payable to the arbitrator(s) or the modalities for determination of

arbitrators’ fees; and

(ii) Since most High Courts have not framed rules for determining arbitrators’

fees, taking into consideration Fourth Schedule of the Arbitration Act, the

Fourth Schedule is by itself not mandatory on court-appointed arbitrators in

the absence of rules framed by the concerned High Court. Moreover, the

Fourth Schedule is not applicable to international commercial arbitrations

and arbitrations where the parties have agreed that the fees are to be

determined in accordance with rules of arbitral institutions. The failure of

many High Courts to notify the rules has led to a situation where the

purpose of introducing the Fourth Schedule and sub- Section (14) to

Section 11 has been rendered nugatory, and the court-appointed

arbitrator(s) are continuing to impose unilateral and arbitrary fees on

parties. As we have discussed in Section C.2. 1, such a unilateral fixation

of fees goes against the principle of party autonomy which is central to the

resolution of disputes through arbitration. Further, there is no enabling

provision under the Arbitration Act empowering the arbitrator(s) to

unilaterally issue a binding or enforceable order regarding their fees. This

is discussed in S ection C.2.3 of this judgement. Hence, this Court would

be issuing certain directives for fixing of fees in ad hoc arbitrations where

arbitrators are appointed by courts in Section C.2 .4 of this judgement.

PART C

70

C.2.3 Costs and fees : Two different paradigms

80 Prior to the Arbitration Amendment Act 2015, Section 31(8) governing the

determination of costs of arbitration by the arbitral tribunal read thus:

“Section 31. Form and contents of arbitral award

[…]

(8) Unless otherwise agreed by the parties:-

(a) the costs of an arbitration shall be fixed by the arbitral

tribunal;

(b) the arbitral tribunal shall specify--

(i) the party entitled to costs,

(ii) the party who shall pay the costs,

(iii) the amount of costs or method of determining that

amount, and

(iv) the manner in which the costs shall be paid.

Explanation.---For the purpose of clause (a), "costs" means

reasonable costs relating to-

(i) the fees and expenses of the arbitrators and witnesses,

(ii) legal fees and expenses,

(iii) any administration fees of the institution supervising the

arbitration, and

(iv) any other expenses incurred in connection with the

arbitral proceedings and the arbitral award.”

The unamended sub- Section (8) of Section 31 enabled the arbitral tribunal to fix

the costs, unless otherwise agreed by the parties. The term “ costs” meant

“reasonable costs” relating inter alia to the fees and expenses payable to the

arbitrators and witnesses, in terms of the Explanation to Section 31(8). The LCI

246

th

Report (supra) had recommended the recognition of th e “loser pays”

principle for costs to reflect the relative success and failure of the parties. The

PART C

71

Law Commission noted that the “loser pays” principle serves as a deterrent

against frivolous invocation of disputes and incentivises contractual compliance.

81 Pursuant to the LCI 246

th

Report (supra), the Arbitration Amendment Act

2015 deleted the phrase “unless otherwise agreed by the parties” from sub-

Section 31(8) and the arbitral tribunal was given the power to fix costs in terms of

Section 31A of the A rbitration Act. The amended Section 31(8) reads thus:

“Section 31. Form and contents of arbitral award

[...]

(8) The costs of an arbitration shall be fixed by the arbitral

tribunal in accordance with section 31A.”

Section 31A of the Arbitration Act stipulates thus:

“31A. Regime for costs

(1) In relation to any arbitration proceeding or a proceeding

under any of the provisions of this Act pertaining to the

arbitration, the Court or arbitral tribunal, notwithstanding

anything contained in the Code of Civil Procedure, 1908 (5 of

1908), shall have the discretion to determine--

(a) whether costs are payable by one party to another;

(b) the amount of such costs; and

(c) when such costs are to be paid.

Explanation.--For the purpose of this sub- section, "costs"

means reasonable costs relating to--

(i) the fees and expenses of the arbitrators, Courts and

witnesses;

(ii) legal fees and expenses;

(iii) any administration fees of the institution supervising the

arbitration; and

(iv) any other expenses incurred in connection with the

arbitral or Court proceedings and the arbitral award.

PART C

72

(2) If the Court or arbitral tribunal decides to make an order as

to payment of costs,--

(a) the general rule is that the unsuccessful party shall be

ordered to pay the costs of the successful party; or

(b) the Court or arbitral tribunal may make a different order for

reasons to be recorded in writing.

(3) In determining the costs, the Court or arbitral tribunal shall

have regard to all the circumstances, including--

(a) the conduct of all the parties;

(b) whether a party has succeeded partly in the case;

(c) whether the party had made a frivolous counter claim

leading to delay in the disposal of the arbitral proceedings;

and

(d) whether any reasonable offer to settle the dispute is made

by a party and refused by the other party.

(4) The Court or arbitral tribunal may make any order under

this section including the order that a party shall pay--

(a) a proportion of another party's costs;

(b) a stated amount in respect of another party's costs;

(c) costs from or until a certain date only;

(d) costs incurred before proceedings have begun;

(e) costs relating to particular steps taken in the proceedings;

(f) costs relating only to a distinct part of the proceedings;

and

(g) interest on costs from or until a certain date.

(5) An agreement which has the effect that a party is to pay

the whole or part of the costs of the arbitration in any event

shall be only valid if such agreement is made after the dispute

in question has arisen.”

Section 31A provides that the arbitral tribunal or the court has the discretion to

determine costs of arbitration which includes, inter alia, reasonable costs relating

to the fees and expenses of the arbitrators, courts and witnesses. Sub-Section

(5) of Section 31A specifies that an agreement between parties apportioning

PART C

73

costs is only valid if it is made after the dispute has arisen. The provision has an

effect of limiting party autonomy when an agreement regarding apportioning of

costs can be entered between the parties. However, it does not completely efface

the principle of party autonomy.

82 Section 38 of the Arbitration Act also becomes relevant since it enables the

arbitral tribunal to demand an advance for costs in the form of deposits. The

provision reads thus:

“Section 38 - Deposits

(1) The arbitral tribunal may fix the amount of the deposit or

supplementary deposit, as the case may be, as an advance

for the costs referred to in sub- section (8) of section 31, which

it expects will be incurred in respect of the claim submitted to

it:

Provided that where, apart from the claim, a counter -claim

has been submitted to the arbitral tribunal, it may fix separate

amount of deposit for the claim and counter-claim.

(2) The deposit referred to in sub- section(1) shall be payable

in equal shares by the parties:

Provided that where one party fails to pay his share of the

deposit, the other party may pay that share:

Provided further that where the other party also does not pay

the aforesaid share in respect of the claim or the counter-

claim, the arbitral tribunal may suspend or terminate the

arbitral proceedings in respect of such claim or counter-claim,

as the case may be.

(3) Upon termination of the arbitral proceedings, the arbitral

tribunal shall render an accounting to the parties of the

deposits received and shall return any unexpended balance

to the party or parties, as the case may be.”

Section 38(1) of the Arbitration Act empowers the arbitral tribunal to determine

the deposit that is payable as advance on costs based on its own assessment of

what may be incurred as costs for adjudicating the claim and counter-claim (if

PART C

74

any) before it. Section 38(2) also empowers the arbitral tribunal to suspend or

terminate the proceedings if the parties fail to pay the deposit.

83 Additionally, Section 39(1) enables the arbitral tribunal to hold a lien on an

arbitral award if there are any unpaid costs of arbitration. Section 39 of the

Arbitration Act provides thus:

“Section 39 - Lien on arbitral award and deposits as to

costs

(1) Subject to the provisions of sub- section (2) and to any

provision to the contrary in the arbitration, agreement, the

arbitral tribunal shall have a lien on the arbitral award for any

unpaid costs of the arbitration.

(2) If in any case an arbitral tribunal refuses to deliver its

award except on payment of the costs demanded by it, the

Court may, on an application in this behalf, order that the

arbitral tribunal shall deliver the arbitral award to the applicant

on payment into Court by the applicant of the costs

demanded, and shall, after such inquiry, in any, as it thinks,

fit, further order that out of the money so paid into Court there

shall be paid to the arbitral tribunal by way of costs such sum

as the Court may consider reasonable and that the balance of

the money, if any, shall be refunded to the applicant.

(3) An application under sub- section (2) may be made by any

party unless the fees demanded have been fixed by written

agreement between him and the arbitral tribunal, and the

arbitral tribunal shall be entitled to appear and be heard on

any such application.

(4) The Court may make such orders as it thinks fit respecting

the costs of the arbitration where any question arises

respecting such costs and the arbitral award contains no

sufficient provision concerning them.”

84 The legal regime on costs under the Arbitration Act has been set out in

some detail above because it has been argued on behalf of the respondents that

the arbitral tribunal’s power to fix costs under Section 31(8) read with 31A entails

the power to fix arbitrators’ fees, which are also a component of the costs in

PART C

75

terms of the Explanation to Section 31A. According to the respondents, this

position is bolstered by the fact that the arbitral tribunal has the power to fix the

amount of deposit that is payable as an advance on costs and it can also hold a

lien on the arbitral award if such costs remain unpaid.

85 In Gayatri Jhansi Roadways Ltd (supra), this Court held:

“14. However, the learned Single Judge’s conclusion that the

change in language of section 31(8) read with Section 31A

which deals only with the costs generally and not with

arbitrator’s fees is correct in law. It is true that the arbitrator’s

fees may be a component of costs to be paid but it is a far cry

thereafter to state that section 31(8) and 31A would directly

govern contracts in which a fee structure has already

been laid down…”

86 The above interpretation of this Court is in harmony with the observations

of the Law Commission in the LC I 246

th

Report (supra) where it had

recommended changes to the regime of costs only to provide a statutory

recognition to the “loser pays” principle. The Report contained the following

observations:

“70. Arbitration, much like traditional adversarial dispute

resolution, can be an expensive proposition. The savings of a

party in avoiding payment of court fee, is usually offset by the

other costs of arbitration – which include arbitrator’s fees and

expenses, institutional fees and expenses, fees and

expenses in relation to lawyers, witnesses, venue, hearings

etc. The potential for racking up significant costs justify a

need for predictability and clarity in the rules relating to

apportionment and recovery of such costs. The Commission

believes that, as a rule, it is just to allocate costs in a manner

which reflects the parties’ relative success and failure in the

arbitration, unless special circumstances warrant an

exception or the parties otherwise agree (only after the

dispute has arisen between them).

71.The loser-pays rule logically follows, as a matter of law,

from the very basis of deciding the underlying dispute in a

PART C

76

particular manner; and as a matter of economic policy,

provides economically efficient deterrence against frivolous

conduct and furthers compliance with contractual obligations.”

The Law Commission was seeking to regulate how costs are apportioned and

recovered between parties by suggesting amendments to the legal framework on

costs. The same LCI 246th Report (supra) dealt with redressing the issue of

exorbitant fees being charged by arbitrators and recommended the introduction

of a model schedule of fees, based on which High Courts could frame rules on

fixing fees, to decrease the control arbitrators have over fixing their own fees.

Hence, it is evident that the Law Commission understood that the issue of

arbitrators’ fees is independent of the issue of allocation of costs. The LCI 246th

Report (supra) was attempting to address the concern of arbitrary and unilateral

fixation of fees by the arbitrators. The interpretation suggested by the

respondents, that while allocating costs the arbitral tribunal can enter into a fresh

and unilateral determination of fees, would be contrary to what the Law

Commission sought to achieve by recommending the regulation of fees charged

by arbitrators.

87 The concepts of costs and fees in arbitration must be distinguished. Fees

constitute compensation or remuneration payable to the arbitrators for their

service. Arbitrators are entitle d to “financial remuneration by the parties in return

for performance of his or her mandate”

115

. While the national laws governing

arbitration give a quasi-judicial status to arbitrators where they have to be

impartial adjudicators, many aspects of the relationship between the parties and

115

Supra at note 30

PART C

77

arbitrators are contractual in nature

116

. Without acknowledging the contractual

nature of the relationship, there is no satisfactory explanation for the parties’ right

to appoint arbitrator(s) (and the corresponding right of the arbitrator(s) to decline

such appointment), arbitrators’ remuneration, arbitrators’ duty to conduct

arbitration in terms of the arbitration agreement (independently of the requirement

of fairness and equality) and the parties’ right to jointly remove arbitrator (s)

117

. In

Voestalpine Schienen GmbH v. Delhi Metro Rail Corpn. Ltd.

118

, this Court,

while holding that the arbitrator has to act impartially and independently,

recognised the contractual nature of the relationship between the parties and

arbitrator(s) in the following extract:

“20. Independence and impartiality of the arbitrator are the

hallmarks of any arbitration proceedings. Rule against bias is

one of the fundamental principles of natural justice which

applied to all judicial and quasi-judicial proceedings. It is for

this reason that notwithstanding the fact that relationship

between the parties to the arbitration and the arbitrators

themselves are contractual in nature and the source of

an arbitrator's appointment is deduced from the

agreement entered into between the parties,

notwithstanding the same non- independence and non-

impartiality of such arbitrator (though contractually

agreed upon) would render him ineligible to conduct the

arbitration. The genesis behind this rational is that even

when an arbitrator is appointed in terms of contract and

by the parties to the contract, he is independent of the

parties. Functions and duties require him to rise above the

partisan interest of the parties and not to act in, or so as to

further, the particular interest of either parties. After all, the

arbitrator has adjudicatory role to perform and, therefore, he

must be independent of parties as well as impartial. The

United Kingdom Supreme Court has beautifully highlighted

this aspect in Hashwani v. Jivraj [Hashwani v. Jivraj, (2011) 1

WLR 1872 : 2011 UKSC 40] in the following words : (WLR p.

1889, para 45)

116

ibid

117

ibid

118

(2017) 4 SCC 665

PART C

78

“45. … the dominant purpose of appointing an arbitrator or

arbitrators is the impartial resolution of the dispute between

the parties in accordance with the terms of the agreement

and, although the contract between the parties and the

arbitrators would be a contract for the provision of personal

services, they were not personal services under the direction

of the parties.”

(emphasis supplied)

88 The relationship between parties and arbitrator(s) is contractual in nature.

Upon that relationship, the law superimposes a duty upon the arbitrator(s) to act

as an impartial and independent adjudicator. The principle of party autonomy

plays a substantial role in the determination of arbitrators’ fees. We have noted in

Section C.1 of this judgement that party autonomy plays a central role in the

determination of arbitrators’ fees in the rules of international arbitral institutions

and domestic legislation of other countries. Aside from institutional arbitration,

arbitrators’ fees in ad hoc arbitration are arrived at through negotiations between

the parties and the arbitrator(s)

119

. The primacy of parties’ agreement in

determination of arbitrators’ fees was also reaffirmed by this Court in Gayatri

Jhansi Roadways Ltd (supra). However, there may be instances where the

parties have not entered into any agreement with respect to the fees. In ad hoc

arbitrations this leads to a peculiar situation where it has to be determined who

will fix the fees in such circumstances. While certain foreign jurisdictions enable

the arbitral tribunal to fix the fees typically subject to review by courts, there are

jurisdictions which continue to give value to parties’ consent in determining

renumeration for arbitrators. As discussed above in Section C.1 , in certain

jurisdictions like Germany, arbitrators are prohibited from unilaterally fixing their

119

Supra at note 28

PART C

79

fees because it violates the doctrine of the prohibition of in rem suam decisions,

i.e., arbitrators cannot give an enforceable ruling on their own fees. Austria and

Switzerland also do not allow arbitrators to issue binding and enforceable orders

regarding fixation of their own fees

120

. In Italy, while the arbitrators can determine

fees in absence of an agreement between parties, such fees become binding

only once the parties’ consent to it. In Singapore, in absence of a written

agreement, a party may approach the Registrar of the Supreme Court within the

meaning of the Supreme Court of Judicature Act 1969 for the assessment of

fees.

89 In contrast, costs are typically compensation payable by the losing party to

the winning party for the expenses the latter incurred by participating in the

proceedings

121

. In Salem Advocate Bar Assn. (II) v. Union of India

122

, this

Court has defined costs in a similar manner in the context of litigation:

“37. Judicial notice can be taken of the fact that many

unscrupulous parties take advantage of the fact that either the

costs are not awarded or nominal costs are awarded against

the unsuccessful party. Unfortunately, it has become a

practice to direct parties to bear their own costs. In a large

number of cases, such an order is passed despite Section

35(2) of the Code. Such a practice also encourages the filing

of frivolous suits. It also leads to the taking up of frivolous

defences. Further, wherever costs are awarded, ordinarily the

same are not realistic and are nominal. When Section 35(2)

provides for cost to follow the event, it is implicit that the

costs have to be those which are reasonably incurred by

a successful party except in those cases where the court

in its discretion may direct otherwise by recording

120

Michael Wietzorek, “Chapter II: The Arbitrator and the Arbitration Procedure: May Arbitrators Determine their

own Fees?” in Christian Klausegger, Peter Klein, et al (eds), Austrian Yearbook on International Arbitration 2012,

Austrian Yearbook on International Arbitration, Volume 2012 (Manz’sche Verlags- und Universitätsbuchhandlung;

Manz’sche Verlags- und Universitätsbuchhandlung , 2012).

121

John Y. Gotanda, “Part I: International Commercial Arbitration, Chapter 7: Bringing Efficiency to the Awarding

of Fees and Costs in International Arbitrations”, in Stefan M. Kröll, Loukas A. Mistelis, et al. (eds), International

Arbitration and International Commercial Law: Synergy, Convergence and Evolution (Kluwer Law International,

2011)

122

(2005) 6 SCC 344

PART C

80

reasons therefore. The costs have to be actual

reasonable costs including the cost of the time spent by

the successful party, the transportation and lodging, if

any, or any other incidental costs besides the payment of

the court fee, lawyer's fee, typing and other costs in

relation to the litigation. It is for the High Courts to examine

these aspects and wherever necessary make requisite rules,

regulations or practice direction so as to provide appropriate

guidelines for the subordinate courts to follow.”

(emphasis supplied)

90 The principle of the payment of “costs” remains the same in litigation and

arbitration even though the form of expenses may vary. Redfern and Hunter on

International Commercial Arbitration (supra) has classified the various

components of costs under the following headings

123

:

“•‘costs of the tribunal’ (including the charges for

administration of the arbitration by any arbitral institution);

•‘costs of the arbitration’ (including hiring the hearing rooms,

interpreters, transcript preparation, among other things); and

•‘costs of the parties’ (including the costs of legal

representation, expert witnesses, witness and other travel-

related expenditure, among other things).”

The first category of “costs of the tribunal” includes the fees, travel-related and

other expenses, payable to the arbitrators. However, this category also includes

fees and expenses relating to the experts appointed by the tribunal,

administrative secretary or registrar and other incidental expenses incurred by

the tribunal in respect of the case

124

. Fees of arbitrators constitute a component

of the diverse elements which make up the costs that are payable by one party to

another. The purpose of awarding costs is to “indemnify the winning party”. The

123

Supra at note 28 , Chapter 9

124

ibid

PART C

81

“loser pays” principle apportions the costs between the parties through the cost s

follow the event

125

method. The primary purpose of the CFE method is to “make

the claimant whole”

126

. The CFE method has been statutorily recognised in some

national legislations. The English Arbitration Act provides that “unless the parties

otherwise agree, the tribunal shall award costs on the general principle that costs

should follow the event except where it appears to the tribunal that this principle

is not appropriate in relation to whole or part of the costs”

127

. Since costs are

typically awarded at the conclusion of the proceedings on the basis of the relative

success or failure of parties, an award of costs forms a part of the final award.

However, interim awards or rulings on costs may also be issued. M ost

international arbitral institutions give arbitral tribunals the discretion to allocate

costs unless there is an agreement between the parties regarding the

apportionment of costs. It has been noted that the “loser pays” principle is a

common approach

128

followed for awarding costs

129

. The UNCITRAL Rules, while

providing that costs of arbitration shall be “borne by the unsuccessful party” as a

general principle, allow the arbitral tribunal to take the ultimate decision

130

. The

LCIA Rules allow the arbitral tribunal to depart from the general principle “in

circumstances (in which) the application of such a general principle would be

inappropriate”

131

. The Arbitration Act also provides statutory recognition to the

125

“CFE”

126

Supra at note 12 1

127

Section 61(2), English Arbitration Act

128

There are some institution rules which do not prescribe a general rule and leave the apportionment of the

costs to the arbitral tribunal. The ICDR (Art. 34) and HKIAC (34.3) require the tribunal to carry out a reasonable

apportionment of costs. The ICC Rules (Art. 38(5) and SIAC Rules (Art. 35) leave the apportionment of costs

upto the discretion of the tribunal.

129

Arif Hyder Ali, Jane Wessel, et al. (eds), The International Arbitration Rulebook: A Guide to Arbitral Regimes

(Kluwer Law International, 2019), Chapter 8

130

Article 42(1), UNCITRAL Rules

131

Article 28(4), LCIA Rules

PART C

82

principle of “loser pays” in Section 31A (2)

132

as the general principle of allocating

costs, which can be derogated from at the discretion of the tribunal provided it

records its reasons in writing. Further, the Arbitration Act seeks to limit the ability

of parties to contractually allocate fees by specifying in Section 31A(5) that such

an agreement will only be valid “if such agreement is made after the dispute in

question has arisen”. The intention of the legislature to limit party autonomy in

allocation of costs is also evident from the deletion of the phrase “unless

otherwise agreed by the parties” from Section 31(8) through the Amendment Act

2015.

91 We can see that the functional role of costs and fees is different. While

fees represent the payment of remuneration to the arbitrators, costs refer to all

the expenses incurred in relation to arbitration that are to be allocated between

the parties upon the assessment of certain parameters by the arbitral tribunal or

the court. Section 31A(3) provides that an arbitral tribunal or the court has to take

into account the following factors for determining costs:

“(a) the conduct of all the parties;

(b) whether a party has succeeded partly in the case;

(c) whether the party had made a frivolous counter claim

leading to delay in the disposal of the arbitral proceedings;

and

(d) whether any reasonable offer to settle the dispute is made

by a party and refused by the other party.”

132

Section 31A(2) provides:

“(2) If the Court or arbitral tribunal decides to make an order as to payment of costs,--

(a) the general rule is that the unsuccessful party shall be ordered to pay the costs of the successful party; or

(b) the Court or arbitral tribunal may make a different order for reasons to be recorded in writing.”

PART C

83

This is accompanied by the general rule under Section 31A(2) that the

unsuccessful party has to bear the costs of arbitration.

92 Another way to understand the difference between costs and fees is to

distinguish between the nature of the claim that both reflect. Redfern and Hunter

on International Commercial Arbitration (supra) discusses costs in Chapter 9,

titled “Awards”. It states that “[a] claim in respect of the costs incurred by a party

in connection with an international arbitration is, in principle, no different from any

other claim, except that it usually cannot be quantified until the end of the arbitral

proceedings”

133

. The decision of an arbitral tribunal ordering one party to pay

arbitration costs is considered as an “award” within the meaning of the New York

Convention and UNCITRAL Model Law since the decision resolves a claim one

party has towards another in respect to the entitlement of being repaid by the

other party for expenses incurred during arbitration

134

. Gary Born on Arbitration

(supra) specifically notes the difference between costs and fees, and states that

any decision of the arbitral tribunal relating to payment of fees to the members of

the tribunal is not considered an award since it does not resolve a claim between

the parties; rather it resolves a claim between the arbitrator(s) against the

parties

135

. The Swiss Federal Tribunal has observed in this context that

136

:

“[A]ccording to the majority of legal writing the arbitral tribunal

has no authority to issue an enforceable decision as to the

fees it may derive from the arbitration agreement (receptum

arbitri). This is because claims resulting from the relationship

between the arbitral tribunal and the parties do not fall within

the arbitration clause; also because this would be an

unacceptable decision in one’s own case. The decision on

133

Supra at note 12 3

134

Supra at note 3 0, Chapter 23

135

ibid

136

Judgment of 10 November 2010, DFT 136 III 597, 603 cited in i bid

PART C

84

costs in an arbitral award is therefore nothing else as a

rendering of account which does not bind the parties or a

circumscription of the arbitrators’ private law claim based on

the arbitration agreement on which in case of dispute the

State Court will have to decide.”

The German arbitration law also takes the above position, where a portion of the

award relating to costs of arbitration was denied enforcement as arbitrators are

prohibited from fixing their own fees and costs, except when there is an

agreement between the parties and arbitrators

137

.

93 Since fees of the arbitrators are not a claim that needs to be quantified at

the end of the proceedings based, inter alia , on the conduct of parties and

outcome of the proceedings, they can be determined at the stage when the

arbitral tribunal is being constituted. Redfern and Hunter on International

Commercial Arbitration (supra) discusses the concept of fees of arbitrators in

Chapter 4, titled “Establishment and Organisation of an Arbitral Tribunal”,

indicating that fees have to be determined much earlier at the inception of the

proceedings. In fact, the commentary states that in ad hoc arbitrations, “it is

necessary for the parties to make their own arrangements with the arbitrators as

to their fees. The arbitrators should do this at an early stage in the proceedings,

in order to avoid misunderstandings later”

138

.

94 It has been argued on behalf of the respondents that the power of

arbitrator(s) under Section 38(1) of the Arbitration Act to demand a deposit as an

advance on costs “which it expects will be incurred” in relation to the claim and

137

Judgment of 24 October 2008, XXXIV Y.B. Comm. Arb. 533 (Oberlandesgericht Frankfurt) (2009) cited in

supra at note 12 3

138

Supra at note 28

PART C

85

counterclaim (if any) indicates that the tribunal is entitled to determine its own

fees. If such a deposit is not paid, the tribunal can suspend or terminate the

proceedings under Section 38(2) of the Arbitration Act. It can also hold a lien on

the award if the costs of arbitration remain unpaid under Section 39(1) of the

Arbitration Act.

95 Gary Born on Arbitration (supra) explains the concept of an advance on

costs or deposits in the following terms

139

:

“Once the arbitral tribunal is in place, the parties are generally

required to provide security for the fees and costs of the

arbitrators. Most institutional arbitration rules contain express

provisions for payment by the parties of an advance on costs

(or deposit), and arbitrators often have the power under

national law to require payment of an advance even absent

express provision to that effect in either the arbitration

agreement or institutional rules.

The amount of the advance on costs is based upon the

expected total amount of fees and expenses of the arbitrators

and institutional administrative costs. If the parties do not pay

the advance, the arbitration will not go forward; if one party

fails to make payment, the other may do so on its behalf, so

that the arbitration will proceed, hopefully to conclude with a

decision in its favor, in which the prevailing party will be

awarded (among other things) reimbursement of the amounts

it advanced on behalf of its counter-party.”

The above extract and Section 38

140

of the Arbitration Act indicate that the

purpose of demanding a deposit is to simply secure the future expenses or the

139

Supra at note 30 , Chapter 15

140

“Section 38 - Deposits

(1) The arbitral tribunal may fix the amount of the deposit or supplementary deposit, as the case may be, as an

advance for the costs referred to in sub- section (8) of section 31, which it expects will be incurred in respect of

the claim submitted to it:

Provided that where, apart from the claim, a counter-claim has been submitted to the arbitral tribunal, it may fix

separate amount of deposit for the claim and counter-claim.

(2) The deposit referred to in sub-section(1) shall be payable in equal shares by the parties:

Provided that where one party fails to pay his share of the deposit, the other party may pay that share:

Provided further that where the other party also does not pay the aforesaid share in respect of the claim or the

counter-claim, the arbitral tribunal may suspend or terminate the arbitral proceedings in respect of such claim or

counter-claim, as the case may be.

PART C

86

“costs” relating to the arbitration, including arbitrators’ fees. The arbitrator(s) may

resign or cease their work until such payment is made. This principle cannot be

extended to establish that the arbitrator(s) have a unilateral power to fix their own

fees while demanding a deposit. The arbitral tribunal can also ask for a

supplementary deposit, which indicates that the amount fixed in the deposit is

provisional in nature. Upon the termination of the mandate of the arbitral tribunal,

it is required to provide an account of the deposits and if the deposits exceed the

total amount of costs, the tribunal is required to return the balance. This indicates

that the order on deposits is not a binding determination as to costs (including

arbitrators’ fees). It is a procedural order issued for the purpose of sec uring

payment of future expenses.

96 While the arbitral tribunal can exercise a lien over the arbitral award for

any unpaid costs of arbitration under Section 39(1) of the Arbitration Act, a party

can also approach the court for the release of the award and the court on inquiry

can assess whether the costs demanded are reasonable under Section 39(2).

These costs would include the arbitrators’ fees that have been previously agreed

upon. However, even if there is no agreement between the parties and the

arbitrator(s) regarding the fees payable to the arbitrator(s), any determination of

costs relating to arbitrators’ fees by the tribunal is a non- binding demand that has

been raised by the tribunal. As has been discussed above, while costs, in

general, are to be decided at the discretion of the tribunal or the court because

they involve a claim that one party has against the another relating to resolution

of a dispute arising from the arbitration agreement, fees of the arbitrators are not

(3) Upon termination of the arbitral proceedings, the arbitral tribunal shall render an accounting to the parties of

the deposits received and shall return any unexpended balance to the party or parties, as the case may be.”

PART C

87

a claim to be decided between the parties . Rather, it is an independent claim that

the arbitrator(s) have against the parties

141

. It will be for the court to decide

whether the claim of the arbitrator(s) regarding their remuneration is reasonable.

This also becomes clear from sub- Sections (2) and (3) of Section 39, which

provide:

“Section 39 - Lien on arbitral award and deposits as to

costs

[…]

(2) If in any case an arbitral tribunal refuses to deliver its

award except on payment of the costs demanded by it, the

Court may, on an application in this behalf, order that the

arbitral tribunal shall deliver the arbitral award to the applicant

on payment into Court by the applicant of the costs

demanded, and shall, after such inquiry, in any, as it thinks,

fit, further order that out of the money so paid into Court there

shall be paid to the arbitral tribunal by way of costs such sum

as the Court may consider reasonable and that the balance of

the money, if any, shall be refunded to the applicant.

(3) An application under sub- section (2) may be made by any

party unless the fees demanded have been fixed by written

agreement between him and the arbitral tribunal, and the

arbitral tribunal shall be entitled to appear and be heard on

any such application.

[…]”

(emphasis supplied)

Sub-Section (2) provides that an application can be made to the court if the

arbitral tribunal is refusing to deliver the award, except on payment of costs

demanded by it. The court can then order the arbitral tribunal to deliver the award

to the applicant on payment of the costs demanded by the tribunal to the court.

Crucially, the court can conduct an inquiry to determine if the costs are

reasonable and out of the money paid to the court, it can direct the payment of

141

Paragraphs 91-92 of this judgement

PART C

88

reasonable costs to the tribunal and the balance (if any) to be refunded to the

applicant. Sub-Section (3) provides that an application under sub- Section (2) for

the delivery of an award withheld by the arbitral tribunal exercising a lien over it,

can only be made if the fees demanded have not been fixed by a written

agreement by the party and the arbitral tribunal. Section 39 of the Arbitration Act

is similar to Section 38 of the now repealed Arbitration Act 1940. Section 38 of

the erstwhile legislation provided thus:

“38. Disputes as to arbitrator's remuneration or costs:

(1) If in any case an arbitrator or umpire refuses to deliver his

award except on payment of the fees demanded by him, the

Court may. on an application in this behalf, order that the

arbitrator or umpire shall deliver the award to the applicant on

payment into Court by the applicant of the fees demanded,

and shall, after such inquiry, if any, as it thinks fit, further

order that out of the money so paid into Court there shall be

paid to the arbitrator or umpire by way of fees such sum as

the Court may consider reasonable and that the balance of

the money, if any, shall be refunded to the applicant.

(2) An application under Sub- section (1) may be made by any

party to the reference unless the fees demanded have been

fixed by written agreement between him and the arbitrator or

umpire, and the arbitrator or umpire shall be entitled to

appear and be heard on any such application.

(3) The Court may make such orders as it thinks fit respecting

the costs of an arbitration where any question arises

respecting such costs and the award contains no sufficient

provision concerning them.”

Section 38(1) of the Arbitration Act 1940 enabled an arbitrator or umpire to refuse

delivery of an award if the payment of fees demanded by them remained unpaid,

and in such cases the court could direct the arbitrator or the umpire to deliver the

award upon payment of such fees to the court by the applicant. Thereafter, it

could assess the propriety of the fees demanded and out of the amount

PART C

89

deposited in court, it could direct payment to the tribunal and the balance (if any)

to be refunded to the applicant. The difference between Section 38(1) of the

Arbitration Act 1940 and Section 39(1) of the Arbitration Act is that the former

specifically refers to the payment of the arbitrators’ fee, while the latter refers to

costs demanded by the tribunal. Section 39(1) seems to be wider in scope.

However, since the costs under Section 39 are to be payable to the arbitral

tribunal, these would typically reflect costs relating to fees of the members of the

tribunal and other out-of-pocket expenses payable to the arbitrators that are

necessary for the conduct of arbitral proceedings like expenses relating to travel,

accommodation and any other allowances.

97 This interpretation of costs under Section 39 as only limited to the costs

owed to the arbitral tribunal is also in consonance with the purpose of Section 39,

which is that it enables the arbitral tribunal to exercise a lien over the arbitral

award. In Triveni Shankar Saxena v. State of UP & Ors.

142

, this Court defined

lien as follows:

“17…The word 'lien' originally means "binding" from the Latin

ligamen. Its lexical meaning is "right to retain". The word 'lien'

is now variously described and used under different contexts

such as 'contractual lien', 'equitable lien', 'specific lien',

'general lien', 'partners lien', etc. etc. in Halsbury's Laws of

England, Fourth Edition, Volume 28 at page 221, para 502 it

is stated:

“In its primary or legal sense "lien" means a right at common

law in one man to retain that which is rightfully and

continuously in his possession belonging to another until the

present and accrued claims are satisfied.””

142

1992 Suppl. 1 SCC 524

PART C

90

“Lien” has been defined in P Ramanatha Aiyar: The Major Law Lexicon as

143

:

““Lien” defined. A right by which a person in possession of the

property holds and retains it against the other in satisfaction

of a demand due to the party retaining it. [O. VIII, R. 6(2),

CPC (5 of 1908)and S. 47, margin, (3 of 1930)].

Right of one person to satisfy a claim against another by

holding or retaining possession of that other ’s

assets/property. (Finance)

The right to possession of property until such time that an

outstanding liability has been repaid. A banker’ s lien gives a

bank the right to retain or sell the property of a debtor in

lieu of payment. (Banking; Insurance & International

Accounting).”

The arbitral tribunal can exercise a lien over the arbitral award and refuse to

deliver it if there are outstanding payments yet to be made to the tribunal. T he

principle behind allowing the arbitral tribunal to exercise a lien over the arbitral

award is to ensure that the tribunal is not left in the lurch without its expenses

being met, while the beneficiary of the award reaps the benefits of it. In Assam

State Weaving and Manufacturing Co. Ltd. v. Vinny Engineering Enterprises

(P) Ltd.

144

, the Calcutta High Court observed that:

“Section 39 of the 1996 Act, much like Section 38 of the old

Act, recognises an arbitral tribunal's lien over the award. The

section conceives of a situation where there may be a dispute

between the arbitral tribunal and one or more parties to the

reference as to the costs of the arbitration. Upon an arbitral

tribunal refusing to deliver its award unless its demand for

payment of costs were met by a party, an application may be

carried to court for directing the tribunal to deliver the award

to the applicant. Sub- section (2) contemplates an applicant

thereunder to put into court the costs demanded by the

arbitral tribunal. Upon such costs being deposited the court

may order the tribunal to deliver the award to the applicant.

The court can thereafter inquire into the propriety of the costs

demanded and deal with the matter following the inquiry.

143

P Ramanatha Aiyar: The Major Law Lexicon (LexisNexis, 4

th

edition)

144

AIR 2010 Cal 52

PART C

91

Sub-section (3) of Section 39 permits an application under

sub-section (2) to be carried by any party to the reference

only on condition that the fees demanded were not as fixed

by written agreement between the applicant and the arbitral

tribunal. The sub- section does not limit an application to be

made under sub- section (2) only by a party who has been

refused the delivery of the award. The delivery that Section

39 speaks of is the physical delivery of the document

embodying the award and not merely the pronouncement of

the award. For, it is the physical receipt of the document that

would entitle a party to apply for setting aside the award or for

implementing it.”

98 Hence, sub- Section (2) and (3) of Section 39, read together, govern a

situation where the fees and other expenses payable to the arbitrators have not

been decided through a written agreement between the party and the arbitral

tribunal. While ideally, the parties and the arbitrators should arrive at an

arrangement regarding the remuneration of arbitrators, the arbitral tribunal may

raise a non- binding invoice regarding the arbitration costs (i.e., fees and

expenses payable to arbitrator(s)) and may refuse to deliver the award unless the

outstanding payments have been made. The parties are not obligated to pay

such costs if they believe that such costs are unreasonable. In such a case, it is

the court that determines whether the fees and other expenses demanded by the

tribunal are reasonable in terms of Section 39(2).

99 To conclude, the arbitral tribunal while deciding the allocation of costs

under Sections 31(8) read with 31A or advance of costs under Section 38 cannot

issue any binding or enforceable orders regarding their own remuneration. This

would violate the principle of party autonomy and the doctrine of prohibition of in

rem suam decisions

145

, which postulates that the arbitrators cannot be the judge

145

Supra at note 120

PART C

92

of their own claim against parties’ regarding their remuneration. The principles of

party autonomy and the doctrine of prohibition of in rem suam decisions do not

restrict the arbitral tribunal from apportioning costs between the parties (including

the arbitrator(s) remuneration) since this is merely a reimbursement of the

expenses that the successful party has incurred in participating in the arbitral

proceedings. Likewise, the arbitral tribunal can also demand deposits and

supplementary deposits since these advances on costs are merely provisional in

nature. If while fixing costs or deposits, the arbitral tribunal makes any finding

relating to arbitrators’ fees (in the absence of an agreement), it cannot be

enforced in favour of the arbitrators . The party can approach the court to review

the fees demanded by the arbitrators.

100 Ideally, in ad hoc arbitrations, the fees payable to the arbitrator (s) should

be decided through an arrangement between the parties and the arbitrator (s). In

the next section, we are issuing certain directives to govern the process of how

fees payable to the arbitrator(s) have to be fixed in ad hoc arbitrations.

C.2.4 Directives governing fees of arbitrators in ad hoc arbitrations

101 Preliminary meetings in arbitration proceedings entail a meeting convened

by the arbitral tribunal with the parties to arrive at a common understanding about

how the arbitration is to be conducted. It generally takes place at an early stage

of the dispute re solution process, prior to the “written phase of the proceedings”.

Rules of certain international arbitral institutions provide for convening a

PART C

93

preliminary meeting

146

or case-management conference

147

. The fees and

expenses are typically addressed at this stage

148

. We propose that this stage of

having a preliminary hearing should be adopted in the process of conducting ad

hoc arbitrations in India as it will provide much needed clarity on how arbitrators

are to be paid and reduce conflicts and litigation on this issue.

102 These preliminary hearings should also be conducted when the fees are

specified in the arbitration agreement. The arbitration agreement may have been

entered into at an earlier point in time, even several years earlier. It is possible

that at the time when the disputes between the parties arise, the fees stipulated

in the arbitration agreement may have become an unrealistic estimate of the

remuneration that is to be offered for the services of the arbitrator due to the

passage of time. In the preliminary hearings, if all the parties and the arbitral

tribunal agree to a revised fee, then that fee would be payable to the arbitrator(s).

However, if any of the parties raises an objection to the fee being demanded by

the arbitrator(s) and no consensus can be arrived at between such a party and

the tribunal or a member of the tribunal, then the tribunal or the member of the

tribunal should decline the assignment. Since the relationship between the

parties and arbitrator(s) is contractual in nature, specifically with respect to the

payment of remuneration, there must be a consensus on the fees to be paid.

103 It is possible that during the preliminary hearings, the parties and the

arbitral tribunal may be unsure about the extent of time that needs to be invested

by the arbitrator(s) and the complexity of the dispute. It is also possible that the

146

Rule 19.3, SIAC Rules

147

Article 24, ICC Rules

148

Supra at note 28

PART C

94

arbitral proceedings may continue for much longer time than was expected. In

order to anticipate such contingencies, during the preliminary hearings, the

parties and the arbitrator (s) should stipulate that after a certain number of sittings,

the fee would stand revised at a specified rate. The number of sittings after which

the revision would take place and the quantum of revision must be clearly

discussed and determined during the preliminary hearings through the process of

negotiation between the parties and the arbitrator(s). There is no unilateral power

reserved to the arbitrator(s) to revise the fees on their own terms if they believe

that an additional number of sittings would be required to settle the dispute. The

fees payable to the arbitral tribunal in an ad hoc arbitration must be settled

between the arbitral tribunal and the parties at the threshold during the course of

the preliminary hearings. Resolution of the fees payable to the arbitral tribunal by

mutual agreement during the preliminary hearings is necessa ry. Failing such an

agreement, the arbitrator(s) who decline to accept the fee suggested by the

parties (or any of them) are at liberty to decline the assignment. The fixation of

arbitral fees at the threshold will obviate the grievance that the arbitrator(s) are

arm-twisting parties at an advanced stage of the dispute resolution process. In

such a situation, a party who is not agreeable to a unilateral revision of fees

demanded by the arbitral tribunal in the midst of the proceedings has a real

apprehension that its refusal may result in embarrassing consequences bearing

on the substance of the dispute.

104 We believe that the directives proposed by the amicus curiae, with suitable

modifications, would be useful in structuring how these preliminary hearings are

to be conducted. Exercising our powers conferred under Article 142 of the

PART C

95

Constitution, we direct the adoption of the following guidelines for the conduct of

ad hoc arbitrations in India:

“1. Upon the constitution of the arbitral tribunal, the

parties and the arbitral tribunal shall hold preliminary hearings

with a maximum cap of four hearings amongst themselves to

finalise the terms of reference (the “Terms of Reference”) of

the arbitral tribunal. The arbitral tribunal must set out the

components of its fee in the Terms of Reference which would

serve as a tripartite agreement between the parties and the

arbitral tribunal.

2. In cases where the arbitrator(s) are appointed by

parties in the manner set out in the arbitration agreement, the

fees payable to the arbitrators would be in accordance with

the arbitration agreement. However, if the arbitral tribunal

considers that the fee stipulated in the arbitration agreement

is unacceptable, the fee proposed by the arbitral tribunal must

be indicated with clarity in the course of the preliminary

hearings in accordance with these directives. In the

preliminary hearings, if all the parties and the arbitral tribunal

agree to a revised fee, then that fee would be payable to the

arbitrator(s). However, if any of the parties raises an objection

to the fee proposed by the arbitrator(s) and no consensus can

be arrived at between such a party and the tribunal or a

member of the tribunal, then the tribunal or the member of the

tribunal should decline the assignment.

3. Once the Terms of Reference have been finalised

and issued, it would not be open for the arbitral tribunal to

vary either the fee fixed or the heads under which the fee may

be charged.

4. The parties and the arbitral tribunal may make a carve

out in the Terms of Reference during the preliminary hearings

that the fee fixed therein may be revised upon completion of a

specific number of sittings. The quantum of revision and the

stage at which such revision would take place must be clearly

specified. The parties and the arbitral tribunal may hold

another meeting at the stage specified for revision to

ascertain the additional number of sittings that may be

required for the final adjudication of the dispute which number

may then be incorporated in the Terms of Reference as an

additional term.

5. In cases where the arbitrator(s) are appointed by the

Court, the order of the Court should expressly stipulate the

fee that arbitral tribunal would be entitled to charge. However,

where the Court leaves this determination to the arbitral

PART C

96

tribunal in its appointment order, the arbitral tribunal and the

parties should agree upon the Terms of Reference as

specified in the manner set out in draft practice direction (1)

above.

6. There can be no unilateral deviation from the Terms

of Reference. The Terms of Reference being a tripartite

agreement between the parties and the arbitral tribunal, any

amendments, revisions, additions or modifications may only

be made to them with the consent of the parties.

7. All High Courts shall frame the rules governing

arbitrators' fees for the purposes of Section 11(14) of the

Arbitration and Conciliation Act, 1996.

8. The Fourth Schedule was lastly revised in the year

2016. The fee structure contained in the Fourth Schedule

cannot be static and deserves to be revised periodically. We,

therefore, direct the Union of India to suitably modify the fee

structure contained in the Fourth Schedule and continue to do

so at least once in a period of three years.”

105 Conscious and aware as we are that (i) Arbitration proceedings must be

conducted expeditiously; (ii) Court interference should be minimal; and (iii) Some

litigants would object to even a just and fair arbitration fee, we would like to

effectuate the object and purpose behind enacting the model fee schedule. When

one or both parties, or the parties and the arbitral tribunal are unable to reach a

consensus, it is open to the arbitral tribunal to charge the fee as stipulated in the

Fourth Schedule, which we would observe is the model fee schedule and can be

treated as binding on all. Consequently, when an arbitral tribunal fixes the fee in

terms of the Fourth Schedule, the parties should not be permitted to object the

fee fixation. It is the default fee, which can be changed by mutual consensus and

not otherwise.

PART D

97

D Interpretation of “sum in dispute” in the Fourth Schedule

D.1 Statutory Framework

106 We must begin by looking at the statutory framework of the Arbitration Act.

In order to understand the genesis of the competing interpretations, it is important

to first consider Sections 31(8), the Explanation to Section 31A(1) and Section

38(1).

107 Section 31(8) of the Arbitration Act reads thus:

“31. Form and contents of arbitral award.—

[…]

(8) The costs of an arbitration shall be fixed by the arbitral

tribunal in accordance with Section 31- A.”

Sub-Section (8) of Section 31 was amended by the Arbitration Amendment Act

2015, which also added Section 31A to the Arbitration Act.

108 Section 31A(1) is in the following terms:

“31-A. Regime for costs.—(1) In relation to any arbitration

proceeding or a proceeding under any of the provisions of this

Act pertaining to the arbitration, the court or arbitral tribunal,

notwithstanding anything contained in the Code of Civil

Procedure, 1908 (5 of 1908), shall have the discretion to

determine—

(a) whether costs are payable by one party to another;

(b) the amount of such costs; and

(c) when such costs are to be paid.

Explanation.—For the purpose of this sub- section,

“costs” means reasonable costs relating to—

PART D

98

(i) the fees and expenses of the arbitrators, courts and

witnesses;

(ii) legal fees and expenses;

(iii) any administration fees of the institution supervising the

arbitration; and

(iv) any other expenses incurred in connection with the

arbitral or court proceedings and the arbitral award.

[…]”

(emphasis supplied)

Sub-Section (1) of Section 31A provides the court or the arbitral tribunal with the

power to determine the following in regard to costs: (i) whether they are payable

by one party to the other; (ii) their amount; and (iii) when they are payable. The

Explanation to Section 31A(1) defines “costs” to include four components, the

first of which is “the fees and expenses of the arbitrators, courts and witnesses”.

109 Section 31(8) is also linked to Section 38(1) , which is as follows:

“38. Deposits.—(1) The arbitral tribunal may fix the amount

of the deposit or supplementary deposit, as the case may be,

as an advance for the costs referred to in sub- section (8) of

Section 31, which it expects will be incurred in respect of the

claim submitted to it:

Provided that where, apart from the claim, a counter-

claim has been submitted to the arbitral tribunal, it may

fix separate amount of deposit for the claim and counter-

claim.”

(emphasis supplied)

According to sub- Section (1) of Section 38 of the Arbitration Act, the arbitral

tribunal can direct the parties to make a deposit, as an advance, for the costs

referred to in Section 31(8). As noted earlier, Section 31(8) states that such costs

are to be determined in accordance with Section 31A. Crucially, the proviso to

PART D

99

Section 38(1) provides that the arbitral tribunal may fix a separate amount of

deposit for the claim and counter-claim, in an arbitration where a counter-claim

has been filed.

110 The inter-connection between Section 31(8), Section 31A and Section

38(1) bears directly on the interpretation of the Fourth Schedule of the Arbitration

Act. The Fourth Schedule is extracted below:

“THE FOURTH SCHEDULE

See Section 11(3- A)

Sl. No. Sum in dispute Model fee

(1) (2) (3)

1. Up to Rs 5,00,000 Rs 45,000

2. Above Rs 5,00,000 and up to Rs

20,00,000

Rs 45,000 plus 3.5 per cent of

the claim amount over and above

Rs 5,00,000.

3. Above Rs 20,00,000 and up to

Rs 1,00,00,000

Rs 97,500 plus 3 per cent of the

claim amount over and above Rs

20,00,000.

4. Above Rs 1,00,00,000 and up to

Rs 10,00,00,000

Rs 3,37,500 plus 1 per cent of

the claim amount over and above

Rs 1,00,00,000.

5. Above Rs 10,00,00,000 and up

to Rs 20,00,00,000

Rs 12,37,500 plus 0.75 per cent

of the claim amount over and

above Rs 10,00,00,000.

6. Above Rs 20,00,00,000 Rs 19,87,500 plus 0.5 per cent of

the claim amount over and above

Rs 20,00,00,000 with a ceiling of

Rs 30,00,000.

Note: In the event the arbitral tribunal is a sole arbitrator, he shall be entitled to

an additional amount of twenty-five per cent on the fee payable as per the

above.”

PART D

100

The issue before this Court turns on the interpretation of the term “sum in

dispute”, which is the header of the second column of the Fourth Schedule. This

column provides the different categories of the amounts, corresponding to which

the third column provides the relevant fee which the arbitrators can charge for

that category.

111 On the one hand, it has been argued before us that the expression “sum in

dispute” should be the cumulative sum of the claim and counter-claim raised by

the parties. If such a position is adopted, the arbitrators will charge one common

fee for hearing both the claim and counter-claim, and the ceiling prescribed in the

Fourth Schedule will apply to their cumulati ve total. On the other hand, it is

submitted that “sum in dispute” refers to the individual sums in dispute in the

claim and counter-claim. The consequence of adopting this position would be that

the arbitrators will charge different sets of fee s for the claim and counter-claim,

and hence, separate fee ceilings will apply to both.

D.2 Definition of claim and counter-claim

D.2.1 In re a rbitration proceedings

(i) Statutory Framework of the Arbitration Act

112 The Arbitration Act does not specifically define either the expression

“claim” or “counter-claim”. However, these expressions are referred to in

numerous instances, which we shall now outline.

PART D

101

113 Part I of the Arbitration Act is titled “Arbitration”. Section 2 is the definitions

clause for Part I. Section 2(1) defines the various terms used throughout Part I .

Sections 2(2) to 2(5) clarify the scope of the disputes which will be covered by

Part I. Section 2(6) notes that where Part I allows parties to determine any issue,

it also provides them a right to let any other person or institution determine the

issue for them. Section 2(7) notes that awards passed under Part I shall be

domestic awards. S ection 28(1) clarifies that any reference to an agreement

made by the parties (or which may be made), will also include a reference to any

arbitration rules referred to in the agreement. Crucially, Section 2(9) states that

“[w]here [Part I], other than clause (a) of Section 25 or clause (a) of sub- section

(2) of Section 32, refers to a claim, it shall also apply to a counter-claim, and

where it refers to a defence, it shall also apply to a defence to that counter-claim”.

This corresponds to Article 2(f)

149

of the UNCITRAL Model Law, on which the

Arbitration Act is based. Section 25(a) notes that if the claimant fails to

communicate his statement of claim in accordance with sub- section (1) of Section

23, the arbitral tribunal shall terminate the proceedings, while Section 32(2)(a)

provides that the arbitral tribunal shall issue an order for termination of arbitration

proceedings where the claimant withdraws his claim, unless the respondent

objects to the order and the arbitral tribunal recognises a legitimate interest on his

part in obtaining a final settlement of the dispute. Hence, as is evident, other than

these specific provisions which refer to only a claim filed by the claimant, the

Arbitration Act treats claims and counter-claims at par.

149

Article 2(f) provides: “(f)where a provision of this Law, other than in Article 25(a) and 32(2)(a), refers to a

claim, it also applies to a counter-claim, and where it refers to a defence, it also applies to a defence to such

counter-claim”.

PART D

102

114 Another reference is then made to counter -claims in sub-Section (2- A) of

the Section 23, which provides as follows:

“23. Statements of claim and defence.

[…]

(2-A) The respondent, in support of his case, may also submit

a counter claim or plead a set-off, which shall be adjudicated

upon by the arbitral tribunal, if such counter claim or set-off

falls within the scope of the arbitration agreement.”

Section 23(2- A) clarifies that an arbitral tribunal is under an obligation to also

adjudicate upon a counter-claim or set-off filed by a party in an arbitration

proceeding, with the limitation that they should fall within the scope of the

arbitration agreement. This is in line with the requirements under the UNCITRAL

Model Law

150

. If a party files a frivolous counter-claim which leads to a delay in

the arbitration proceedings, the arbitral tribunal can take that into account while

determining costs in accordance with Section 31A(3)(c).

115 Section 23(2- A) was introduced by the Arbitration Amendment Act 2015,

bearing in view the recommendations in the LCI 246

th

Report (supra). The

Report had recommended the addition of an explanation to Section 23(1)

(instead of a different sub- Section) along with the following comment:

“Amendment of Section 23

13.In section 23, after sub-section (1) and before sub- section

(2), add the words “Explanation: In his defence the

respondent may also submit a counter claim or plead a set

off, which shall be treated as being within the scope of

reference and be adjudicated upon by the arbitral tribunal

notwithstanding that it may not fall within the scope of the

150

Howard M Holtzmann and Joseph E Neuhaus, A Guide to the UNCITRAL Model Law on International

Commercial Arbitration: Legislative History and Commentary (Walter Kluwers, 1989), page 649

PART D

103

initial reference to arbitration, but provided it falls within the

scope of the arbitration agreement.”

[NOTE: This explanation is in order to ensure that counter

claims and set off can be adjudicated upon by an arbitrator

without seeking a separate/new reference by the respondent

so long as it falls within the scope of the arbitration

agreement, in order to ensure final settlement of disputes

between parties and prevent multiplicity of litigation.]”

Thus, the object of taking up a counter-claim along with the claim in the same

proceeding is not because the counter-claim arises due to the claim (which it may

not) but in order to prevent a multiplicity of proceedings.

116 We have already noted Section 38(1) earlier in this judgment, where the

proviso provides the arbitral tribunal with the power to fix a separate amount of

deposits (of costs determined under Section 31(8)) in instances where a claim

and counter-claim have both been filed in an arbitration proceeding. We must

also take note of Section 38(2) of the Arbitration Act, which provides:

“(2) The deposit referred to in sub- section (1) shall be payable

in equal shares by the parties:

Provided that where one party fails to pay his share of the

deposit, the other party may pay that share:

Provided further that where the other party also does not pay

the aforesaid share in respect of the claim or the counter-

claim, the arbitral tribunal may suspend or terminate the

arbitral proceedings in respect of such claim or counter -claim,

as the case may be.”

As a general rule, sub- Section (2) of Section 38 provides that the deposits

determined under Section 38(1) have to be shared by both parties. The first

proviso notes that if one party fails to pay their share, the other party may step in

and pay it. Further, the second proviso notes that if the other party also does not

PART D

104

pay that share, the arbitral tribunal can suspend proceedings. Importantly, it

provides that it may terminate proceedings in relation to either the claim or

counter-claim or both, depending upon whether the appropriate deposits have

been made for one of them or neither of them.

117 Consequently, on the basis of the above analysis, the following principles

emerge:

(i) The Arbitration Act treats claims and counter-claims at par, and holds them

subject to the same procedural timelines and requirements;

(ii) The Arbitration Act allows the arbitral tribunal to fix a deposit of costs for

claims and counter-claims separately, recognizing that they are distinct

proceedings since: (a) the proceeding for adjudicating on the claim is

independent of the proceeding for deciding the counter -claim; (b) distinct

issues may arise before the tribunal while adjudicating on the claim and

counter-claim; (c) the evidence led in support of the claim may not be

dispositive of the material which would be relied on to decide the counter-

claim; and (d) the decision on the claim does not necessarily conclude the

adjudication of the counter -claim; and

(iii) The Arbitration Act considers claims and counter-claims to be independent

proceedings since the latter is not contingent upon the former. Rather, it

protects the right of any respondent to raise a counter-claim in an

arbitration proceeding, provided it arises from the arbitration agreement

under dispute. Further, in the event of a default in the payment of a deposit

either for the claim or counter-claim, it specifically notes that the

PART D

105

proceedings will be terminated only in respect of the claim, or as the case

may be, the counter-claim in respect of which the default has occurred;

(iv) Though a counter-claim may arise from similar facts as a claim, the

counter-claim is not a set off and is not in the nature of a defence to the

claim; and

(v) A counter-claim will survive for independent adjudication even if the claim

is dismissed or withdrawn and the respondent to a claim would be entitled

to pursue their counter-claim regardless of the pursuit of or the decision on

the claim.

(ii) Academic discourse

118 In Justice R S Bachawat’s seminal treatise on Law of Arbitration &

Conciliation, it has been noted that an arbitral tribunal has the jurisdiction to

decide any claim and counter-claim arising out of a dispute referred to it, and not

deciding the latter would be a ground to set aside the award

151

:

“[s 7.44.3] Counter-claim

When disputes in a pending suit are referred to arbitration,

the arbitrator has jurisdiction to decide both the claim and the

counterclaim…An award allowing the claim without deciding

the counterclaim is liable to be set aside. Where the

arbitration agreement permitted reference of all disputes to

arbitration, it could not be said that by entertaining a

counterclaim, the arbitrator exceeded his jurisdiction.”

151

Anirudh Wadha and Anirudh Krishnan, Justice R S Bachawat’s Law of Arbitration & Conciliation (6

th

edition,

2017)

PART D

106

119 Similarly, CR Dutta’s treatise on Law of Arbitration & Conciliation supports

the proposition that the Arbitration Act treats a claim and counter-claim as two

separate and independent proceedings

152

:

“4. To be paid equally

The cost amount to be deposited will be in respect of the

claim and separately in respect of the counter -claim by the

parties in equal shares. If a party does not pay the other party

may be asked to pay the shares of both the parties. If the

amount directed to be deposited in respect of the claim is not

made, then the proceedings in respect of the claim may be

suspended or terminated but the proceedings in respect of

counter-claim can proceed if the amount in respect thereof

has been deposited. For the purposes of deposit of costs and

expenses, the claim and counter-claim have been treated as

two separate independent proceedings.”

120 Gary Born on Arbitration (supra) notes that a party is generally not

bound by any restriction in regards to its counter-claim, except that it must fall

within the scope of the arbitration agreement

153

:

“In general, there are no limits under national law on the

subject matter of a respondent’s counterclaims, beyond

whatever restrictions may be contained in the parties’

arbitration agreement: the respondent may assert any

counterclaim that falls within the scope of the arbitration

agreement. This general freedom may be limited by the

parties’ arbitration agreement or applicable institutional rules

(which, however, usually do not impose further limits).”

121 Finally, in Procedure and Evidence in International Arbitration , a counter-

claim is differentiated from a set-off by noting that it is a claim brought by the

defendant and is not a defence to the claimant’s claim

154

:

152

CR Dutta’s Law Of Arbitration And Conciliation (LexisNexis)

153

Supra at note 30

154

Jeffrey Waincymer, Procedure and Evidence in International Arbitration (Walters Kluwer, 2012)

PART D

107

“4.4. A counterclaim is usually seen as a claim brought by a

respondent in a civil suit against the claimant that is

independent of the primary claim although it may be linked to

the same facts. The term is used in contradistinction to a set-

off that is seen as a defence to the primary claim, albeit one

invariably related to different facts. Because it is not simply a

defence, a counterclaim leads to a separate judgment that

may be in excess of the judgment under the primary claim.

Furthermore, the counterclaim remains alive even if the initial

claim is withdrawn. Thus, it is truly a reverse claim and not a

defence as such.”

122 These academic writings a support the conclusion that claims and counter-

claims within an arbitration proceeding are distinct and independent proceedings

in themselves.

(iii) Judicial pronouncements

123 Even before the introduction of Section 23(2-A) through the Arbitration

Amendment Act 2015, counter-claims were raised by parties in arbitration

proceedings. In Indian Oil Corpn. Ltd. v. Amritsar Gas Service

155

, this Court

had to decide on the validity of an award under the Arbitration Act 1940 where

the appellant’s counter-claim had been dismissed by the arbitrator since it was

not part of the reference. Speaking for the three- Judge Bench, Justice J S Verma

held that when all disputes under an arbitration agreement are referred to

arbitration, a party can file its counter-claim before the arbitral tribunal:

“15. The appellant's grievance regarding non- consideration of

its counter-claim for the reason given in the award does

appear to have some merit. In view of the fact that reference

to arbitrator was made by this Court in an appeal arising out

of refusal to stay the suit under Section 34 of the Arbitration

Act and the reference was made of all disputes between the

parties in the suit, the occasion to make a counter-claim in the

written statement could arise only after the order of reference.

155

(1991) 1 SCC 533 (“Amritsar Gas Service”)

PART D

108

The pleadings of the parties were filed before the arbitrator,

and the reference covered all disputes between the parties in

the suit. Accordingly, the counter-claim could not be made at

any earlier stage. Refusal to consider the counter-claim for

the only reason given in the award does, therefore, disclose

an error of law apparent on the face of the award. However,

in the present case, the counter-claim not being pressed at

this stage by learned counsel for the appellant, it is

unnecessary to examine this matter any further.”

124 In State of Goa v. Praveen Enterprises

156

, a two-Judge Bench followed

the principle enunciated in Amritsar Gas Service (supra) in a case arising under

the Arbitration Act. Speaking for the two -Judge Bench, Justice R V Raveendran,

in the course of an erudite exposition of the law, highlighted that a respondent to

a claim could well seek independent recourse to arbitration for deciding the

counter-claim, but raising a counter-claim obviates a multiplicity of litigation:

“32. A counterclaim by a respondent presupposes the

pendency of proceedings relating to the disputes raised by

the claimant. The respondent could no doubt raise a dispute

(in respect of the subject-matter of the counterclaim) by

issuing a notice seeking reference to arbitration and follow it

by an application under Section 11 of the Act for appointment

of arbitrator, instead of raising a counterclaim in the pending

arbitration proceedings. The object of providing for

counterclaims is to avoid multiplicity of proceedings and to

avoid divergent findings. The position of a respondent in an

arbitration proceeding being similar to that of a defendant in a

suit, he has the choice of raising the dispute by issuing a

notice to the claimant calling upon him to agree for reference

of his dispute to arbitration and then resort to an independent

arbitration proceeding or raise the dispute by way of a

counterclaim, in the pending arbitration proceedings.”

156

(2012) 12 SCC 581 (“Praveen Enterprises”)

PART D

109

Subsequently, in Voltas Ltd. v. Rolta India Ltd.

157

, another two- Judge Bench of

this Court followed the reasoning in Praveen Enterprises (supra), that counter-

claims were independent claim proceedings by the respondent. The C ourt held

that the limitation for a counter-claim would be determined with reference to the

date it was instituted before the arbitral tribunal. However, it carved out an

exception to this general rule for instances where the respondent had earlier

raised the counter-claim as a claim in a notice for arbitration sent to the claimant,

but did not subsequently file an application under Section 11 of the Arbitration

and raised it directly as a counter-claim. In such instances, the date of limitation

would, it was observed, begin from when the notice of arbitration was first

received by the claimant.

D.2.2 In re c ivil proceedings

(i) Statutory Framework of CPC

125 Order VIII of the CPC contains provisions pertaining to written statements,

set-offs and counter-claims by the defendant. Rule 6 elucidates the particulars of

a set-off to be given in a written statement:

“6. Particulars of set-off to be given in written

statement.—(1) Where in a suit for the recovery of money

the defendant claims to set-off against the plaintiff's demand

any ascertained sum of money legally recoverable by him

from the plaintiff, not exceeding the pecuniary limits of the

jurisdiction of the Court, and both parties fill the same

character as they fill in the plaintiff's suit, the defendant may,

at the first hearing of the suit, but not afterwards unless

permitted by the Court, present a written statement containing

the particulars of the debt sought to be set-off.

157

(2014) 4 SCC 516

PART D

110

(2) Effect of set- off.—The written statement shall have the

same effect as a plaint in a cross-suit so as to enable the

Court to pronounce a final judgment in respect both of the

original claim and of the set-off, but this shall not affect the

lien, upon the amount decreed, of any pleader in respect of

the costs payable to him under the decree.

(3) The rules relating to a written statement by a defendant

apply to a written statement in answer to a claim of set-off.”

Rule 6(1) specifies that while filing their written statement, a defendant may

mention the particulars of an ascertained sum l egally recoverable from the

plaintiff. Rule 6(2) notes that the effect of pleading a set-off in a written statement

is the same as filing a plaint in a cross-suit. Rule 6(3) then notes that the

plaintiff’s written statement in respondent to the defendant’s set-off claim shall

follow the same rules as the defendant’s written statement in response to the

plaintiff’s plaint.

126 On the other hand, a distinct provision is made for a counter -claim under

Rule 6-A of Order VIII of the CPC :

“6-A. Counter-claim by defendant.—(1) A defendant in a

suit may, in addition to his right of pleading a set-off under

Rule 6, set up, by way of counter-claim against the claim of

the plaintiff, any right or claim in respect of a cause of action

accruing to the defendant against the plaintiff either before or

after the filing of the suit but before the defendant has

delivered his defence or before the time limited for delivering

his defence has expired, whether such counter-claim is in the

nature of a claim for damages or not:

Provided that such counter -claim shall not exceed the

pecuniary limits of the jurisdiction of the Court.

(2) Such counter-claim shall have the same effect as a cross-

suit so as to enable the Court to pronounce a final judgment

in the same suit, both on the original claim and on the

counter-claim.

PART D

111

(3) The plaintiff shall be at liberty to file a written statement in

answer to the counter-claim of the defendant within such

period as may be fixed by the Court.

(4) The counter-claim shall be treated as a plaint and

governed by the rules applicable to plaints.”

Rule 6-A(1) provides that the defendant’s counter-claim is in addition to a claim

for set-off under Rule 6. It provides that the defendant may file a counter-claim

based on a cause of action accruing to them against the plaintiff either before or

after the filing of the suit but before the defendant has delivered his defence or

before the time limited for delivering his defence has expired. The proviso notes

that the value of the counter-claim cannot exceed the pecuniary jurisdiction of the

court where it is being filed. Rule 6-A(2) provides that the counter-claim has the

same effect as a cross-suit. Rule 6-A(3) permits a plaintiff to file a written

statement against the defendant’s counter-claim. Finally, Rule 6-A(4) notes that

the counter-claim shall be treated as a plaint and the rules governing plaints will

be applicable to it.

127 Rule 6-D of Order VIII is of particular importance, and it provides thus:

“6-D. Effect of discontinuance of suit.—If in any case in

which the defendant sets up a counter-claim, the suit of the

plaintiff is stayed, discontinued or dismissed, and counter-

claim may nevertheless be proceeded with.”

Rule 6-D clarifies, in no uncertain terms, that even if the suit which has been

instituted by the plaintiff is stayed, discontinued or dismissed, it would not affect

the defendant’s counter-claim. This highlights, once again, that counter-claims

are distinct and independent from claims. The defendant’s counter-claim is

equivalent to a plaint. The counter-claim is not being filed as an independent suit

PART D

112

but as a counter-claim within a pre- existing suit so as to avoid a multiplicity of

litigation. However, it is not dependant on the outcome of the original suit and is

an independent proceeding.

(ii) Academic discourse

128 Mulla’s treatise on the Code of Civil Procedure notes that a counter-claim

is an independent suit which exists within another pre- existing suit, in order to

enable the court to pronounce final judgment on the claim and the counter-claim

together

158

:

“The very object of Rule 6A is to treat a counterclaim as an

independent suit to be heard together with the plaintiff’s suit

to enable the court to pronounce final judgement. ”

129 Sarkar’s Code of Civil Procedure notes that a counter-claim is an

independent action and not a defence to the plaintiff’s original claim

159

:

“The provisions of Rule 6A(1) are in substance similar to

those of RSC, 1965 [Rules of the Supreme Court of UK,

1965], Order 15, Rule 2(1). Cf Rule 6(2) with Order 8, Rule

6(2) of the Code and Rule 6A(4) with RSC 1965, Order 18,

Rule 18. The effect of this rule is from the point of view of

pleading to assimilate a counter-claim with a plaint in a suit

and is therefore governed by the same rules of pleading as a

plaint. A counter-claim is substantially a cross- action, not

merely a defence to the plaintiff’s claim. It must be of such

a nature that the court would have jurisdiction to entertain it

as a separate action. ”

(emphasis supplied)

158

Mulla, The Code of Civil Procedure, (Volume 2, 18

th

edition) page 1925

159

Sudipto Sarkar and Aditya Swarup, Sarkar’s Code of Civil Procedure (LexisNexis, 13

th

edition) (“Sarkar”)

PART D

113

Sarkar (supra) further notes that this understanding is crystallised in Order VIII

Rule 6-D, where the dismissal of a frivolous action by the plaintiff would not affect

the defendant’s counter-claim:

“[Rule 6- D] further illustrates the principle that a counter-claim

is to be treated as a cross action, and is not affected by

anything which relates solely to the plaintiff’s claim. Thus,

where the plaintiff discontinues action the counter-claim has

been served, he cannot prevent the defendant from enforcing

against him the causes of action contained in the counter-

claim. So if an action is dismissed being frivolous, the

counter-claim is not affected and the defendant may be

granted the relief which he seeks thereby.”

130 The above exposition of a counter-claim is elaborated in Halsbury’s Laws

of India (Civil Procedure)

160

:

“A “counter-claim” is a claim made by a defendant in a suit

against a plaintiff. It is a claim, independent of and

separable from the plaintiff’s claim, which can be

enforced by a cross- action. It is a cause of action in favour

of the defendant against the plaintiff…”

(emphasis supplied)

131 Zuckerman’s treatise on Civil Procedure, Principles of Practice also

observes that counter-claims are an independent proceeding

161

:

“4.52. A counterclaim is independent of the main claim. It may

relate to the same transaction, as where the claimant claims

for the price of goods and the defendant counterclaims

damages for late delivery or for defects. Equally, a

counterclaim can be wholly separate from the claim, as where

the defendant sues in respect of entirely different events from

those that are raised in the claimant’s claim.”

160

Halsbury’s Laws of India (Civil Procedure) (2

nd

edition)

161

Zuckermann on Civil Procedure (Sweet & Maxwell, 4

th

edition)

PART D

114

(iii) Judicial pronouncements

132 In Jag Mohan Chawla v. Dera Radha Swami Satsang

162

, a two-Judge

Bench of this Court had to decide whether, under the CPC, a counter-claim can

be made on a cause of action different from the primary claim. Speaking for the

two-Judge Bench, Justice K Ramaswamy held:

“5…In sub- rule (1) of Rule 6-A, the language is so couched

with words of wide width as to enable the parties to bring

his own independent cause of action in respect of any

claim that would be the subject-matter of an independent

suit. Thereby, it is no longer confined to money claim or to

cause of action of the same nature as original action of the

plaintiff. It need not relate to or be connected with the original

cause of action or matter pleaded by the plaintiff. The words

“any right or claim in respect of a cause of action accruing

with the defendant” would show that the cause of action from

which the counter-claim arises need not necessarily arise

from or have any nexus with the cause of action of the plaintiff

that occasioned to lay the suit…The counter-claim

expressly is treated as a cross- suit with all the indicia of

pleadings as a plaint including the duty to aver his cause

of action and also payment of the requisite court fee

thereon. Instead of relegating the defendant to an

independent suit, to avert multiplicity of the proceeding

and needless protection (sic protraction), the legislature

intended to try both the suit and the counter-claim in the

same suit as suit and cross- suit and have them disposed

of in the same trial. In other words, a defendant can claim

any right by way of a counter-claim in respect of any cause of

action that has accrued to him even though it is independent

of the cause of action averred by the plaintiff and have the

same cause of action adjudicated without relegating the

defendant to file a separate suit…”

(emphasis supplied)

Hence, it was held that since the counter-claim was effectively an entirely

independent suit from the claim, it could arise out of any unrelated cause of

action.

162

(1996) 4 SCC 699

PART D

115

133 In Rajni Rani v. Khairati Lal

163

, Justice Dipak Misra (as t he learned Chief

Justice then was), speaking for a two- Judge Bench of this Court, analysed the

provisions of Order VIII and held:

“9.6…a counterclaim preferred by the defendant in a suit

is in the nature of a cross- suit and by a statutory

command even if the suit is dismissed, counterclaim

shall remain alive for adjudication. For making a

counterclaim entertainable by the court, the defendant is

required to pay the requisite court fee on the valuation of the

counterclaim. The plaintiff is obliged to file a written statement

and in case there is default the court can pronounce the

judgment against the plaintiff in relation to the counterclaim

put forth by the defendant as it has an independent status.

The purpose of the scheme relating to counterclaim is to

avoid multiplicity of the proceedings. When a counterclaim

is dismissed on being adjudicated on merits it forecloses the

rights of the defendant. As per Rule 6- A(2) the court is

required to pronounce a final judgment in the same suit both

on the original claim and also on the counterclaim.

The...purpose is to avoid piecemeal adjudication…”

134 In Thomas Mathew v. KLDC Ltd., another two- Judge Bench of this Court

held that a counter-claim is an independent suit and consequently, the period of

limitation would be three years from the date of accrual of the cause of action

164

.

D.3 Analysis

135 On our analysis of the statutory framework of the Arbitration Act and the

CPC, related academic discourse and judicial pronouncements, the following

conclusions emerge:

(i) Claims and counter-claims are independent and distinct proceedings;

163

(2015) 2 SCC 682

164

(2018) 12 SCC 560

PART D

116

(ii) A counter-claim is not a defence to a claim and its outcome is not

contingent on the outcome of the claim;

(iii) Counter-claims are independent claims which could have been raised in

separate proceedings but are permitted to be raised in the same

proceeding as a claim to avoid a multiplicity of proceedings; and

(iv) The dismissal of proceedings in relation to the original claim does not

affect the proceedings in relation to the counter-claim.

136 We must now consider these principles in the context of the inter-

connection between Section 31(8), Section 31A and Section 38(1) and the Fourth

Schedule of the Arbitration Act. On a combined reading of Section 31(8), Section

31A and Section 38(1), it is clear that: (i) separate deposits are to be made for a

claim and counter-claim in an arbitration proceeding; and (ii) these deposits are in

relation to the costs of arbitration, which includes the fee of the arbitrators.

Therefore, prima facie, the determination of the fee under the Fourth Schedule

should also be calculated separately for a claim and counter-claim – i.e., the term

“sum in dispute” refers to independent claim amounts for the claim and counter-

claim. Such an interpretation is also supported by the definition of claim and

counter-claim, and by the fact that the latter constitutes proceedings independent

and distinct from the former.

137 If this interpretation were to be discarded in favor of construing “sum in

dispute” as a cumulation of the claim amount for the claim and counter-claim, it

would have far-reaching consequences in terms of procedural fairness. First ,

under the proviso to Section 38(1), the arbitral tribunal can direct separate

deposits for a claim and counter-claim. These are based on the cost of arbitration

PART D

117

defined by a conjoint reading of Sections 31(8) and 31A, which includes the

arbitrators’ fee. Hence, if the arbitrators were to charge a common fee for both

the claim and counter-claim, they would have to then equitably divide that fee

while calculating individual deposits for the purpose of the proviso to Section

38(1). Second, the second proviso to Section 38(2) provides that if the deposit is

not made by both the parties, the arbitral tribunal can dismiss the claim and/or

counter-claim, as the case may be. If the claim was to be dismissed in such a

manner, it would lead to an absurd situation where the arbitrators’ fee would have

to be revised in the middle of the arbitration proceedings solely on the basis of

the amount of the counter -claim. Third, under Section 23(2- A), the only

requirement of a counter-claim is that it should arise out of the same arbitration

agreement as the claim. However, the cause of action of a counter-claim may be

entirely different from the claim and possibly far more complex. Therefore,

determining the arbitrators’ fee on a combined basis for both the claim and

counter-claim would thus not match up to the separate effort they would have to

put in for each individual dispute in the claim and counter-claim.

138 In support of the proposition that “sum in dispute” in the Fourth Schedule

includes the cumulation of the sums of the claim and counter-claim, we have also

been referred to the LCI 246

th

Report (supra). It has been argued that the Law

Commission highlighted the problem of arbitrators charging an excessive fee in

ad hoc arbitrations, which is what led to the introduction of the Fourth Schedule

by the Arbitration Amendment Act 2015. Thus, it has been urged that “sum in

dispute” in the Fourth Schedule should be interpreted keeping in mind the

purpose with which it was introduced. However, we must reject the argument

PART D

118

since it would militate against the statutory framework of the Arbitration Act as it

stands today. If Parliament intended that a common fee be charged for a claim

and counter-claim, it would have amended the rest of the Arbitration Act as well

or introduced a specific clause in the Fourth Schedule. Parliament may in its

legislative wisdom still do so. In Aphali Pharmaceuticals Ltd. v. State of

Maharashtra

165

, speaking for a two- Judge Bench of this Court, Justice K N

Saikia held:

“31. A Schedule in an Act of Parliament is a mere question of

drafting…The Schedule may be used in construing provisions

in the body of the Act. It is as much an act of legislature as

the Act itself and it must be read together with the Act for all

purposes of construction. Expressions in the Schedule

cannot control or prevail against the express enactment

and in case of any inconsistency between the Schedule

and the enactment, the enactment is to prevail and if any

part of the Schedule cannot be made to correspond it

must yield to the Act.”

(emphasis supplied)

139 In a final attempt, we have also been referred to the rules of numerous

arbitral institutions which provide for the calculation of arbitrators’ fees on the

cumulation of the sum of the claim and counter-claim – such as the DIAC

166

,

Mumbai Centre for International Arbitration

167

, Indian Council of Arbitration

168

,

Construction Industry Arbitration Council

169

, SIAC, HKIAC

170

, Stockholm.

165

(1989) 4 SCC 378

166

Rule 3(ii) of the DIAC Rules provides: “3. Arbitrators' Fees - (ii)The fee shall be determined and assessed on

the aggregate amount of the claim(s) and counter claim(s)”.

167

Based on its online Fee Calculator available at <https://mcia.org.in/mcia- schedule- of-fees/calculate_fees/#>

accessed on 29 June 2022

168

Rule 31(2) of Rules of Domestic Commercial Arbitration and Conciliation

169

Schedule of Fees available at <http://www.ciac.in/fee_arbitrator.html> accessed on 29 June 2022

170

Article 6.3 of Schedule III of HKIAC Administered Arbitration Rules 2013 provides: “6.3 Claims and

counterclaims are added for the determination of the amount in dispute. The same rule applies to any set-off

defence, unless the arbitral tribunal, after consulting with the parties, concludes that such set-off defence will not

require significant additional work”.

PART E

119

140 Chamber of Commerce

171

and European Court of Arbitration

172

. This will,

however, have no bearing on our judgment. As noted earlier in this judgment,

parties have the freedom to opt for institutional arbitration and be bound by the

rules of the institution. However, the judgment is currently dealing with instances

of ad hoc arbitrations where the Fourth Schedule has been made applicable for

the calculation of the arbitrators’ fee. In such cases, we hold that the “sum in

dispute” in the Fourth Schedule of the Arbitration Act shall be considered

separately for the claim amount in dispute in the claim and counter-claim.

Consequently, the arbitrators’ fee will be calculated separately for the claim and

counter-claim, and the ceiling on the fee will also be applicable separately to

both.

E Fee Ceiling in Fourth Schedule

141 This issue revolves around the interpretation of the sixth entry of the

Fourth Schedule. For convenience of the reader, the Fourth Schedule is being

extracted again:

“THE FOURTH SCHEDULE

See Section 11(3- A)

Sl. No. Sum in dispute Model fee

(1) (2) (3)

1. Up to Rs 5,00,000 Rs 45,000

171

Article 2 of Appendix IV of 2017 Arbitration Rules provides: “(3) The amount in dispute shall be the aggregate

value of all claims, counterclaims and set-offs. Where the amount in dispute cannot be ascertained, the Board

shall determine the Fees of the Arbitral Tribunal having regard to all relevant circumstances.”.

172

Appendix 3 of the Arbitration Rules of the European Court of Arbitration – 2021 provides: “For the purposes of

the application of the scale range the amount to be taken into account to apply this scale will be the total of the

claims made by the parties, i.e. of the claims and counterclaims.”.

PART E

120

2. Above Rs 5,00,000 and up to Rs

20,00,000

Rs 45,000 plus 3.5 per cent of

the claim amount over and above

Rs 5,00,000.

3. Above Rs 20,00,000 and up to

Rs 1,00,00,000

Rs 97,500 plus 3 per cent of the

claim amount over and above Rs

20,00,000.

4. Above Rs 1,00,00,000 and up to

Rs 10,00,00,000

Rs 3,37,500 plus 1 per cent of

the claim amount over and above

Rs 1,00,00,000.

5. Above Rs 10,00,00,000 and up

to Rs 20,00,00,000

Rs 12,37,500 plus 0.75 per cent

of the claim amount over and

above Rs 10,00,00,000.

6. Above Rs 20,00,00,000 Rs 19,87,500 plus 0.5 per cent

of the claim amount over and

above Rs 20,00,00,000 with a

ceiling of Rs 30,00,000.

Note: In the event the arbitral tribunal is a sole arbitrator, he shall be entitled to

an additional amount of twenty-five per cent on the fee payable as per the

above.”

(emphasis supplied)

142 The choice before this Court is between two competing interpretations of

the Model Fee where the sum in dispute is above Rs 20,00,00,000. Before we

explain the competing interpretations, it is important to note that there is an

agreement on the following:

(i) For an arbitration with the sum in dispute is Rs 20,00,00,000, the fee would

be Rs 19,87,500. This will be referred to as the base amount;

(ii) For any increase in the sum in dispute over and above Rs 20,00,00,000,

0.5 per cent of the amount above Rs 20,00,00,000 will be added to the fee.

This will be referred to as the variable amount. For instance, if the sum in

PART E

121

dispute was Rs 21,00,00,000, the amount above Rs 20,00,00,000 is Rs

1,00,00,000. Hence, 0.5 per cent of Rs 1,00,00,000 will be added as the

variable amount; and

(iii) There is a ceiling of Rs 30,00,000.

The controversy before this Court is in relation to the third point, namely, to what

does the ceiling apply. There are two possible interpretations:

(i) First, the ceiling is for the sum of the base amount and the variable

amount. If this interpretation were to be accepted, the highest possible fee

would be Rs 30,00,000; or

(ii) Second, the ceiling is for the variable amount only. If this interpretation

were to be accepted, the highest possible fee would be Rs 49,87,500.

E.1 Difference between the English and Hindi translations

143 The first submission before us is that there is a difference between the

English and Hindi translation of the relevant text. For ready reference, the two

versions are being extracted below:

Rs.19,87,500 plus 0.5 per cent of the claim

amount over and above Rs.20,00,00,000 with

a ceiling of Rs.30,00,000.

19,87,500 �पए + 20,00,00,000 �पए से अिधक

की दावा रकम का 0.5 प्रितशत, 30,00,000 �पए

की अिधकतम सीमा सिहत।

(emphasis supplied)

PART E

122

The difference between the two is the presence of a comma (“,”) in the Hindi

translation, which is absent in the English version. It has been submitted that the

comma was inadvertently missed from the English version, and hence the Hindi

translation should be given preference. In support of this proposition, reliance is

also placed upon Article 343(1) of the Constitution which provides that “[t]he

official language of the Union shall be Hindi in Devanagari script”.

144 We must reject this submission at the threshold since it is in teeth of Article

348(1)(b)(ii) of the Constitution, which reads thus:

“348. Language to be used in the Supreme Court and in

the High Courts and for Acts, Bills, etc. —(1)

Notwithstanding anything in the foregoing provisions of this

Part, until Parliament by law otherwise provides—

[…]

(b) the authoritative texts—

(i) of all Bills to be introduced or amendments thereto to be

moved in either House of Parliament or in the House or either

House of the Legislature of a State,

[…]

shall be in the English language.”

Article 348 begins with a non- obstante clause, which clarifies that it shall have

precedence over other Articles in Part XVII, including Article 343(1).

145 In Nityanand Sharma v. State of Bihar

173

, a three- Judge Bench of this

Court had to decide whether the ‘Lohar’ community would be construed as a

Scheduled Tribe since their name appeared in the Schedule in the Hindi

173

(1996) 3 SCC 576

PART E

123

translation while the English original had the community “Lohra”. Speaking for the

Bench, Justice K Ramaswamy held:

“19. Article 348(1)(b) of the Constitution provides that

notwithstanding anything in Part II (in Chapter II Articles

346 and 347 relate to regional languages) the

authoritative text of all Bills to be introduced and

amendments thereto to be moved in either House of

Parliament … of all ordinances promulgated by the

President… and all orders, rules, regulations and bye-

laws issued under the Constitution or under any law

made by Parliament, shall be in the English language. By

operation of sub- article (3) thereof with a non obstante

clause, where the Legislature of a State has prescribed any

language other than the English language for use in Bills

introduced in, or Acts passed by, the Legislature of the State

or in Ordinances promulgated by the Governor of the State or

in any order, rule, regulation or bye- law referred to in

paragraph (iii) of that sub- clause, a translation of the same in

the English language published under the authority of the

Governor of the State in the Official Gazette of that State shall

be deemed to be the authoritative text thereof in the English

language under this article. Therefore, the Act and the

Schedule thereto are part of the Act, as enacted by

Parliament in English language. It is the authoritative

text. When the Schedules were translated into Hindi, the

translator wrongly translated Lohara as Lohar omitting the

letter ‘a’ while Lohra is written as mentioned in English

version. It is also clear when we compare Part XVI of the

Second Schedule relating to the State of West Bengal, the

word Lohar both in English as well as in the Hindi version was

not mentioned. Court would take judicial notice of Acts of

Parliament and would interpret the Schedule in the light of the

English version being an authoritative text of the Act and the

Second Schedule. ”

(emphasis supplied)

Similarly, in the present case, this Court shall be governed by article 348 (1)(b)(i)

while interpreting the entry at S erial No 6 of the Fourth Schedule.

PART E

124

E.2 Exception to literal interpretation

146 There is no comma in the English version of the sixth entry of the Fourth

schedule. Hence, there is nothing to suggest conclusively (unlike the Hindi

translation) that the ceiling of Rs 30,00,000 applies cumulatively to the sum of the

base amount and variable amount.

147 The absence of a comma may be one indicator of the meaning of a

provision. However, in his seminal treatise on Principles of Statutory

Interpretation, Justice GP Singh has observed

174

:

“In England, before 1850, there was no punctuation in the

manuscript copy of any Act which received the Royal assent;

therefore, the courts cannot have any regard to punctuation

for construing the older Acts. Even as regards more modern

Acts, it is very doubtful if punctuation can be looked at for

purposes of construction. The opinion on Indian statutes is

not very much different.”

148 Similarly, Bennion in his treatise on Statutory Interpretation notes

175

:

“16.8. Punctuation is a part of an Act and may be considered

in construing a provision. It is usually of little weight, however,

since the sense of an Act should be the same with or without

its punctuation…Although punctuation may be considered, it

will generally be of little use since the sense of an Act should

be the same with or without it. Punctuation is a device not for

making meaning, but for making meaning plain. Its purpose is

to denote the steps that ought to be made in oral reading and

to point out the sense. The meaning of a well-crafted

legislative proposition should not turn on the presence or

absence of a punctuation mark.”

149 In Aswini Kumar Ghose v. Arabinda Bose

176

, a Constitution Bench of

this Court had to interpret provisions of the Bar Councils Act 1926. A key

174

Justice GP Singh, Principles of Statutory Interpretation (14

th

edition, LexisNexis)

175

Diggory Bailey and Luke Norbury, Bennion on Statutory Interpretation (7

th

edition, LexisNexis)

PART E

125

submission was in reference to the presence of a comma before the word “or” in

the non- obstante provision. Justice B K Mukherjea in his judgment observed:

“56…Punctuation is after all a minor element in the

construction of a statute, and very little attention is paid to it

by English courts. Cockburn, C.J. said in Stephenson v.

Taylor [(1861) 1 B & S p. 101] : “On the Parliament Roll there

is no punctuation and we therefore are not bound by that in

the printed copies”. It seems, however, that in the Vellum

copies printed since 1850 there are some cases of

punctuation, and when they occur they can be looked upon

as a sort of contemporanea exposition [See Craies on Statute

Law, p. 185]. When a statute is carefully punctuated and

there is doubt about its meaning, a weight should

undoubtedly be given to the punctuation [Vide Crawford on

Statutory Construction, p. 343]. I need not deny that

punctuation may have its uses in some cases, but it cannot

certainly be regarded as a controlling element and cannot be

allowed to control the plain meaning of a text [Ibid].”

Thus, Justice Mukherjea chose a middle- path where t he learned Judge admitted

to the use of punctuation but held that it still cannot be a controlling element in

interpreting a provision.

150 Another Constitution Bench of this Court in Indore Development

Authority (LAPSE-5 J.) v. Manoharlal

177

, has noted its support of the use of

punctuation as a tool of interpretation and cited with approval the following extract

from Taylor v. Caribou

178

:

“We are aware that it has been repeatedly asserted by courts

and jurists that punctuation is no part of a statute, and that it

ought not to be regarded in construction. This rule in its origin

was founded upon common sense, for in England until 1849

statutes were entrolled upon parchment and enacted without

punctuation…Such a rule is not applicable to conditions

where, as in this State, a Bill is printed and is on the desk of

176

1953 SCR 1

177

(2020) 8 SCC 129

178

102 Me 401 : 67 A 2 (1907)

PART E

126

every Member of the Legislature, punctuation and all, before

its final passage. There is no reason why punctuation, which

is intended to and does assist in making clear and plain the

meaning of all things else in the English language, should be

rejected in the case of the interpretation of statutes.

“Cessante ratione legis cessat ipso lex”. Accordingly we find

that it has been said that in interpreting a statute punctuation

may be resorted to when other means fail…; that it may aid

its construction…; that by it the meaning may often be

determined; that it is one of the means of discovering the

legislative intent…; that it may be of material assistance in

determining the legislative intention…”

Indeed, in Mohd. Shabir v. State of Maharashtra, a two-Judge Bench of this

Court held that mere stocking was not an offence under Section 27 of Drugs and

Cosmetics Act 1940 due to the absence of a comma after the word “stock”

179

.

151 In the present case, the English version of the entry at Serial No 6 of the

Fourth Schedule does not have any comma. Due to its absence, it can be

construed that the literal meaning of the provision is that the ceiling should only

apply to the variable amount. However, Maxwell on The Interpretation of Statutes

notes that the literal meaning of a provision must be rejected when it goes

manifestly against the legislative intent behind the enactment

180

:

“WHERE the language of a statute, in its ordinary meaning

and grammatical construction, leads to a manifest

contradiction of the apparent purpose of the enactment, or to

some inconvenience or absurdity which can hardly have been

intended, a construction may be put upon it which modifies

the meaning of the words and even the structure of the

sentence. This may be done by departing from the rules of

grammar, by giving an unusual meaning to particular words,

or by rejecting them altogether, on the ground that the

legislature could not possibly have intended what its words

signify, and that the modifications made are mere corrections

of careless language and really give the true meaning. Where

the main object and intention of a statute are clear, it must not

179

(1979) 1 SCC 568

180

P St J Langan, Maxwell on The Interpretation of Statutes (N M Tripathi Private Ltd, 1976)

PART E

127

be reduced to a nullity by the draftsman's unskilfulness or

ignorance of the law, except in a case of necessity, or the

absolute intractability of the language used.”

Hence, in the present case, we must aim to ascertain the legislative intent behind

the Fourth Schedule.

E.3 Interpretation based on legislative intent

152 The Fourth Schedule was added to the Arbitration Act pursuant to the

Arbitration Amendment Act 2015, which in itself was based upon the

recommendations in the LCI 246

th

Report (supra). The R eport referred to the

judgment in Singh Builders (supra), which raised the issue of arbitrators

charging exorbitant fees:

“20. Another aspect referred to by the appellant, however

requires serious consideration. When the arbitration is by a

tribunal consisting of serving officers, the cost of arbitration is

very low. On the other hand, the cost of arbitration can be

high if the Arbitral Tribunal consists of retired Judge(s).

21. When a retired Judge is appointed as arbitrator in place of

serving officers, the Government is forced to bear the high

cost of arbitration by way of private arbitrator’s fee even

though it had not consented for the appointment of such non-

technical non- serving persons as arbitrator(s). There is no

doubt a prevalent opinion that the cost of arbitration becomes

very high in many cases where retired Judge(s) are

arbitrators. The large number of sittings and charging of very

high fees per sitting, with several add- ons, without any ceiling,

have many a time resulted in the cost of arbitration

approaching or even exceeding the amount involved in the

dispute or the amount of the award.

22. When an arbitrator is appointed by a court without

indicating fees, either both parties or at least one party is at a

disadvantage. Firstly, the parties feel constrained to agree to

whatever fees is suggested by the arbitrator, even if it is high

PART E

128

or beyond their capacity. Secondly, if a high fee is claimed by

the arbitrator and one party agrees to pay such fee, the other

party, which is unable to afford such fee or reluctant to pay

such high fee, is put to an embarrassing position. He will not

be in a position to express his reservation or objection to the

high fee, owing to an apprehension that refusal by him to

agree for the fee suggested by the arbitrator, may prejudice

his case or create a bias in favour of the other party which

readily agreed to pay the high fee.

23. It is necessary to find an urgent solution for this problem

to save arbitration from the arbitration cost. Institutional

arbitration has provided a solution as the arbitrators’ fees is

not fixed by the arbitrators themselves on case- to-case basis,

but is governed by a uniform rate prescribed by the institution

under whose aegis the arbitration is held. Another solution is

for the court to fix the fees at the time of appointing the

arbitrator, with the consent of parties, if necessary in

consultation with the arbitrator concerned. Third is for the

retired Judges offering to serve as arbitrators, to indicate their

fee structure to the Registry of the respective High Court so

that the parties will have the choice of selecting an arbitrator

whose fees are in their “range” having regard to the stakes

involved.”

153 After noting the judgment in Singh Builders (supra), the LCI 246

th

Report

(supra) stated as follows:

“11. In order to provide a workable solution to this problem,

the Commission has recommended a model schedule of fees

and has empowered the High Court to frame appropriate

rules for fixation of fees for arbitrators and for which purpose

it may take the said model schedule of fees into account. The

model schedule of fees are based on the fee schedule set by

the Delhi High Court International Arbitration Centre, which

are over 5 years old, and which have been suitably revised.

The schedule of fees would require regular updating, and

must be reviewed every 3- 4 years to ensure that they

continue to stay realistic.

12.The Commission notes that International Commercial

arbitrations involve foreign parties who might have different

values and standards for fees for arbitrators; similarly,

institutional rules might have their own schedule of fees; and

in both cases greater deference must be accorded to party

autonomy. The Commission has, therefore, expressly

PART E

129

restricted its recommendations in the context of purely

domestic, ad hoc, arbitrations.”

As a means of controlling the rising fees of arbitrators, the Law Commission

proposed a model fee schedule based on the one used by the DIAC. Schedule B

of the DIAC Rules provides that when the sum in dispute is above Rs

20,00,00,000, the fees shall be “Rs.19,87,500/- + 0.5% of the claim amount over

and above Rs.20 crores , with a ceiling of Rs.30,00,000/ -”. Evidently, the DIAC

Rules have a comma, which would mean that the ceiling would have been

applicable to the base amount and the variable amount.

154 In Mithilesh Kumari v. Prem Behari Khare

181

, a two-Judge Bench of this

Court held that, depending on the facts and circumstances of each case, law

commission reports preceding enactments of statutes can be relied on as an aid

in interpretation. Speaking for the Bench, Justice K N Saikia held:

“15…where a particular enactment or amendment is the

result of recommendation of the Law Commission of India, it

may be permissible to refer to the relevant report as in this

case. What importance can be given to it will depend on the

facts and circumstances of each case.”

155 The LCI 246

th

Report (supra), indicates that the legislative intent behind

the introduction of the Fourth Schedule was to put an end to the practise of

arbitrators charging exorbitant fees from the parties taking their services in ad

hoc arbitrations. Consequently, when we have the option of setting the ceiling of

the fees in the Fourth Schedule at either Rs 30,00,000 or Rs 49,87,500, we

believe that it would be appropriate to choose the lower amount since it would be

181

(1989) 2 SCC 95

PART F

130

in keeping with legislative intent. The 2015 Arbitration A mendment Act was

clearly enacted with the intent to give effect to the recommendation of the LCI

246th Report on the point. Thus, we hold that the ceiling of Rs 30,00,000 in entry

at Serial No 6 of the Fourth Schedule is applicable to the sum of base amount

and the variable amount, and not just the variable amount.

F Ceiling applicable to individual arbitrators

156 The final submission made before this Court was that the ceiling of Rs

30,00,000 prescribed in the entry at S erial No 6 of the Fourth Schedule will be

applicable to the cumulative fee paid to the entire arbitral tribunal, i.e., in a three-

member tribunal, each individual arbitrator would receive a fee of Rs 10,00,000.

157 Such a submission is erroneous , and hence we must reject it. First, there

is nothing in the language of the Fourth Schedule to support such an

interpretation. The header of the third column states “Model Fee” and does not

specify it to be in respect of the whole tribunal. Second , if such an interpretation

were to be adopted, it would lead to absurd consequences. For instance, in an

arbitration where the sum in dispute is large enough to trigger the ceiling of Rs

30,00,000 and it were to be adjudicated by a three- member tribunal, the

maximum fee would have to be divided amongst the three arbitrators. On the

other hand, if the same dispute were to be adjudicated by a sole arbitrator, the

sole arbitrator would then receive the whole amount of the maximum fee, i.e.,

triple of what each individual arbitrator would have received in a three- member

tribunal. Such a disparity is inconceivable, regardless of the extra work a sole

PART G

131

arbitrator may have to put in. This is further bolstered by the Note to the Fourth

Schedule, which states that “[i]n the event the arbitral tribunal is a sole arbitrator,

he shall be entitled to an additional amount of twenty-five per cent on the fee

payable as per the above”. Consequently , the sole arbitrator would not only

receive Rs 30,00,000, but an additional 25 per cent over and above it. Indeed, it

is clear that the Note was added to the Fourth Schedule to fairly compensate sole

arbitrators who arguably would have to do more work than as a member of a

larger tribunal; which is why they are allowed payment of 25 per cent of the fee

over and above what they would be paid pursuant to the table given in the Fourth

Schedule. The corollary of this is that the fee provided in Fourth Schedule is for

each individual arbitrator, regardless of whether they are a member of a multi-

member tribunal or a sole arbitrator. Finally, this interpretation of the Fourth

Schedule, that the fee provided therein is applicable for each individual arbitrator

and not the whole arbitral tribunal, has also been fairly conceded before this

Court by the learned Attorney General.

G Conclusion

G.1 Findings

158 We answer the issues raised in this batch of cases in the following terms:

(i) Arbitrators do not have the power to unilaterally issue binding and

enforceable orders determining their own fees. A unilateral determination

of fees violates the principles of party autonomy and the doctrine of the

prohibition of in rem suam decisions, i.e., the arbitrators cannot be a judge

PART G

132

of their own private claim against the parties regarding their remuneration.

However, the arbitral tribunal has the discretion to apportion the costs

(including arbitrators’ fee and expenses) between the parties in terms of

Section 31(8) and Section 31A of the Arbitration Act and also demand a

deposit (advance on costs) in accordance with Section 38 of the Arbitration

Act. If while fixing costs or deposits, the arbitral tribunal makes any finding

relating to arbitrators’ fees (in the absence of an agreement between the

parties and arbitrators), it cannot be enforced in favour of the arbitrators.

The arbitral tribunal can only exercise a lien over the delivery of arbitral

award if the payment to it remains outstanding under Section 39(1). The

party can approach the court to review the fees demanded by the

arbitrators if it believes the fees are unreasonable under Section 39(2);

(ii) Since this judgment holds that the fees of the arbitrators must be fixed at

the inception to avoid unnecessary litigation and conflicts between the

parties and the arbitrators at a later stage, this Court has issued certain

directives to govern proceedings in ad hoc arbitrations in Section C.2.4;

(iii) The term “sum in dispute” in the Fourth Schedule of the Arbitration Act

refers to the sum in dispute in a claim and counter -claim separately, and

not cumulatively. Consequently, arbitrators shall be entitled to charge a

separate fee for the claim and the counter-claim in an ad hoc arbitration

proceeding, and the fee ceiling contained in the Fourth Schedule will

separately apply to both, when the fee structure of the Fourth schedule has

been made applicable to the ad hoc arbitration;

PART G

133

(iv) The ceiling of Rs 30,00,000 in the entry at S erial No 6 of the Fourth

Schedule is applicable to the sum of the base amount (of Rs 19,87,500)

and the variable amount over and above it. Consequently, the highest fee

payable shall be Rs 30,00,000; and

(v) This ceiling is applicable to each individual arbitrator, and not the arbitral

tribunal as a whole, where it consists of three or more arbitrators. Of

course, a sole arbitrator shall be paid 25 per cent over and above this

amount in accordance with the Note to the Fourth Schedule.

G.2 Directions

159 We issue the following directions in each of the cases before this Court:

(i) In respect of Arbitration Petition (Civil) No 5 of 2022, a fee schedule for the

arbitrators was already prescribed in the LSTK contract. However, during

the preliminary meeting on 25 November 2015, the arbitral tribunal

observed that the fee schedule in the LSTK contract was unrealistic. While

Afcons agreed to revise the fees, ONGC expressed its disagreement. The

tribunal directed ONGC to consider revising the fees. On 16 April 2016, the

arbitral tribunal informed ONGC that it would no longer bargain on the

amount of fees if ONGC was agreeable to the fee provided in the Fourth

Schedule to the Arbitration Act, along with a reading fee of Rs 6 lakhs for

each arbitrator. By its letter dated 22 April 2016, ONGC indicated that it

was agreeable to revising the fees in terms of the Fourth Schedule. It only

objected to the reading fee. Subsequently, the arbitral tribunal passed a

PART G

134

procedural order dated 4 August 2016 directing the parties to deposit 25

per cent of the arbitrators’ fee, which was recorded as Rs 30 lakhs. It

seems a ceiling of Rs 30 lakhs was determined following the Fourth

Schedule to the Arbitration Act. However, the arbitral tribunal then

unilaterally decided to revise the fees and passed a procedural order fixing

a fee of Rs 1.5 lakhs for each arbitrator for every sitting of a three- hour

duration. The tribunal also indicated it may also charge a reading or

conference fee, which would be decided at a later stage. By an order dated

25 July 2019, the arbitral tribunal adjusted its fees to Rs 1 lakh per sitting.

Around 54 sittings have been held in terms of the arbitral tribunal’s order

dated 25 July 2019. In this background, it is evident that there was no

consensus between the parties and the arbitrators regarding the fee that is

to be paid to the members of the arbitral tribunal. Allowing the continuance

of the arbitral tribunal would mean foisting a fee upon the parties and the

arbitral tribunal to which they are not agreeable. In view of our directives in

Section C.2.4 and the facts noted earlier, we exercise our powers under

Article 142 of the Constitution of India and direct the constitution of a new

arbitral tribunal in accordance with the arbitration agreement. For this

purpose, Arbitration Petition (C) No. 5 of 2022 would be listed for directions

before this Court on 21 September 2022. The above directions should not

be construed as a finding on the conduct of the arbitration proceedings.

These directions are an attempt to ensure that the arbitral proceedings are

conducted without rancour which may derail the proceedings. In

consonance with our findings, the fee payable to the earlier arbitral tribunal

PART G

135

would be the fee payable in terms of the Fourth Schedule of the Arbitration

Act. Though the Fourth Schedule is per se not applicable to an

international commercial arbitration, since ONGC had indicated (following

the suggestion of the arbitral tribunal) that it would be agreeable to pay the

fee payable in terms of Schedule, it cannot now take recourse to the

arbitration agreement between the parties to pay a lesser fee. We further

clarify that if the fee in excess of the amount payable under the Fourth

Schedule has been paid to the members of the arbitral tribunal, such

amount will not be recovered from them;

(ii) The civil appeal arising out of Special Leave Petition (Civil) No 13426 of

2021 is dismissed and the judgment of the Single Judge of the Delhi High

Court dated 6 August 2021 is upheld;

(iii) The civil appeal arising out of Special Leave Petition (Civil) No 10358 of

2020 is allowed and the judgment of the Single Judge of the Delhi High

Court dated 10 July 2020 is set aside; and

(iv) Miscellaneous Application Nos 1990- 1991 of 2019 are dismissed.

PART G

136

160 Before parting, we would like to place on record our sincere appreciation

for the submissions made by the amicus curiae, Mr Huzefa Ahmadi who was ably

assisted by Ms Anushka Shah.

161 Pending applications, if any, stand disposed of.

….......…...….......………………........J.

[Dr Dhananjaya Y Chandrachud]

….....…...….......………………........J.

[Surya Kant]

New Delhi;

August 30, 2022

Reference cases

Description

Legal Notes

Add a Note....