As per case facts, the petitioner supplied ballastless track fastening sets. A variation order increased the total quantity, and for some curved tracks, required a 4-bolt system instead of a ...
O.M.P. (COMM) 414/2023 Page 1 of 16
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 12.05.2026
Judgment pronounced on: 20.05.2026
+ O.M.P. (COMM) 414/2023
PANDROL RAHEE TECHNOLOGIES PVT LTD THROUGH
AUTHORIZED REPRESENTATIV VARUN
BHOJAK .....Petitioner
Through: Mr. Naveen R. Nath, Sr. Adv
with Mr. Nishant Das, Mr. Atul
Kumar, Ms. Disha Gupta, Ms.
Aatrayi Das, Ms. Sakshi Nand,
Ms. Jyoti Jha and Mr. Aditya
Rana, Advs.
versus
IRCON INTERNATIONAL LTD THROUGH ITS
CHAIRMAN MR SUNIL KUMAR
CHAUDHURY .....Respondent
Through: Mr. Suman K. Doval, Mr.
Ramesh Wangnoo & Mr.
Lakshay Chaudhary, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
J U D G M E N T
1. The present petition is filed under Section 34 of the Arbitration
and Conciliation Act, 1996 (for short „the Act‟) against the arbitral
award dated 15.05.2023 (for brevity „the award‟).
2. The facts shorn of unnecessary detail are that the respondent on
21.04.2015, issued Notice Inviting Tender (for short „NIT‟) for
design, manufacture, supply, transportation and delivery of Ballastless
O.M.P. (COMM) 414/2023 Page 2 of 16
Track Fastening for standard gauge railway track (1435 mm) with 60
kg 1080 grade rail for installation of ballastless track in elevated and
underground sections of Mukundpur–Lajpat Nagar (excluding Line-7)
of Delhi MRTS Project Phase-III.
2.1 The petitioner was the successful bidder and the Letter of
Acceptance (LOA) dated 21.05.2015 was issued. On 09.10.2015, the
parties executed Contract CT-1A (for brevity „the contract‟). The
respondent by communication dated 04.08.2016 (hereinafter referred
to as „variation order‟) varied the quantity of the ballastless track
fastening sets (for short „sets‟) to be supplied under each of the
categories and the total quantity increased from 1,86,500 sets to
1,98,715 sets. The details of the change in quantities of sets pursuant
to the variation order are tabulated below:
Item
No
Description
of Item
Unit
BOQ
Qty.
Variation
Qty.
Total
Qty. after
variation
Percentage
Change %
1 Supply of
BLT fittings
1.1 Supply track
& curve
track up to
1750m
Sets
1,60,000
(-) 56,751
1,03,249 (-) 35.46%
1.2 For curved
track
a Radius
1750-1000m
Sets 1,500 (+) 13,522 15,022 (+) 901.46%
b Radius
1000m-
500m
Sets
4,500
(+) 20,558
25,058
(+) 456.84%
c Radius 500-
300m
Sets
19,000
(+) 28,804
47,804
(+) 151.60%
O.M.P. (COMM) 414/2023 Page 3 of 16
d Radius
<300m
Sets 1500 (+) 6,082 7,582 (+) 405.46%
Total 1,86,500 1,98,715
2.2 The dispute arose as according to the petitioner, the revised
quantities required supply of a 4-bolt fastening system in place of the
2-bolt fastening system for curved tracks above 500 metres. The
petitioner had to procure and supply additional components including
anchor, nut bolts, eccentric bush, collared washer and compression
springs for varied order and thereby the cost of execution increased.
2.3 The petitioner completed the supplies and completion certificate
dated 11.05.2017 was issued. The payment for the sets supplied was
released by the respondent. The claim of the petitioner for payment
over and above agreed price towards the additional components
supplied was denied by the respondent.
2.4 The petitioner on 23.08.2019, invoked arbitration by issuing
notice under Section 21 of the Act. Vide court order dated 25.10.2021,
the sole arbitrator was appointed and the proceedings culminated in
the impugned award dated 15.05.2023. The claims of the petitioner
were rejected and hence, the present petition.
3. Learned senior counsel for the petitioner submits that the sets
were accepted by the respondent and the contract was fully executed.
The petitioner had to supply 4-bolt system instead of the 2-bolt system
for the curved tracks above 500 metres. The contention is that the
arbitrator failed to appreciate that the cost of supplies increased due to
the variation order.
O.M.P. (COMM) 414/2023 Page 4 of 16
3.1 Reliance is on the decisions of the Supreme Court in Patel
Engineering Ltd. v. North Eastern Electric Power Corporation Ltd.,
(2020) 7 SCC 167, Associate Builders v. Delhi Development
Authority, (2015) 3 SCC 49, Dyna Technologies Pvt. Ltd. v.
Crompton Greaves Ltd., (2019) 20 SCC 1 and Ssangyong
Engineering & Construction Co. Ltd. v. National Highways
Authority of India, (2019) 15 SCC 131 to contend that interpretation
of a contract in a manner which no reasonable person would have
arrived at, constitutes patent illegality. An arbitrator must consider the
evidence on record and take a plausible view.
3.2 The submission is that the findings of the arbitrator are perverse
and are beyond the terms of the contract. It is contended that the
award is contrary to the evidence on record and is liable to be set
aside.
3.3 The argument is that the contract is not a fixed value contract
and under Clause 27 of the General Conditions of Contract (for short
„GCC‟) the quantities under the Bill of Quantities (for short „BOQ‟)
were subject to variation and in the event the variation of individual
items exceeding twenty-five percent, fresh rates were to be negotiated.
3.4 It is emphasised that Clause 2.8 of the LOA does not deal with
payment for supply of additional components. The interpretation of
Clause 2.8 of the LOA by the arbitrator is not plausible and warrants
interference under Section 34 of the Act.
4. Per contra, the terms of the contract obligated that before
commencement of supplies the petitioner had to obtain approval of the
O.M.P. (COMM) 414/2023 Page 5 of 16
design of sets from Delhi Metro Rail Corporation (for short „DMRC‟)
but the petitioner made supplies before getting the approval. Reliance
is on Clause 27 of GCC, Clauses 2.5 and 2.8 of the LOA and
Stipulation No. 6 of the Technical Specifications (for short „TS‟) to
argue that only agreed price is to be paid for additional supplies.
4.1 The argument is that on 07.04.2017 the final bill was paid as per
the rates agreed between the parties. The petitioner accepted the
payment without any protest and now cannot raise further bills on
account of additional costs incurred.
4.2 It is submitted that Clause 27 of the GCC permits negotiation of
fresh rates for increased quantities only when variation in individual
items exceeds (+) or (-) 25% and in the present case the variation of
sets is (+) 6.55% and only the agreed price is to be paid. Further,
Clause 2.8 of the LOA stipulates that Clause 27 of the GCC is not
applicable to the variation of individual items. Submission is that as
per Clause 1 of the Special Conditions of Contract (for short „SCC‟)
the LOA is at priority over the GCC.
4.3 Lastly, it is argued that the scope of interference under Section
34 of the Act is limited. There cannot be interference with a plausible
view of the arbitrator and the evidence cannot be re-appreciated. The
interpretation of the clauses of the contract falls within the domain of
the arbitrator and unless the interpretation is perverse no interference
is to be made on the ground that another view is possible.
5. Heard learned counsel for the parties at length. No other
arguments apart from those noted above were pressed.
O.M.P. (COMM) 414/2023 Page 6 of 16
6. Before proceeding further, it would be apposite to quote Clause
27 of the GCC, Clauses 2.5 and 2.8 of the LOA, Clause 1 of the SCC
and Stipulation No. 6 of the TS.
6.1 Clause 27 of the GCC:
“27.0 VARIATION IN QUANTITY OF ITEMS
COVERED BY THE BILL OF QUANTITIES
27.1 The quantities of items shown in the Bill of
Quantities are approximate, and liable to vary during the
actual execution of the supplies. The Supplier shall be
bound to carry out and complete the stipulated work,
irrespective of the variations in individual items, specified
in the Bill of Quantities
(ii) Such variations in quantities shall be paid for in the
manner laid down below:
(a) The accepted rates for various individual shall remain
firm for variation upto (+) or (-) 25%
(b) In case the variations in individual items is more than
(+) or (-) 25% the rate for the increased quantities beyond
(+) or (-) 25% shall be negotiated between the Engineer
and the Supplier.”
6.2 Clauses 2.5 and 2.8 of the LOA:
“2.5 Approval of the Design of system/various
component from the client
The supplier is required to submit detailed design
calculations of the fastening system for various types of
fastenings (straight track and for track on curves of
various radia) as provided in the Bill of Quantities. The
supplier shall be primarily responsible for obtaining the
approval for the above designs from the Client and
various components shall be supplied only as per the
designs/drawing approved by the Client.
*** *** ***
O.M.P. (COMM) 414/2023 Page 7 of 16
2.8 Quantity Variation
Clause 27.0 of General Conditions of Contract shall be
applicable for the total quantity of fastening sets of
various types contained in Bill of Quantity i.e. sum total
of item no (i) to (vi) i.e. for total quantity of 1,86,500 sets
and will not be applicable for the variation of individual
items of each type.”
6.3 Clause 1 of the SCC:
“ORDER OF PRIORITY OF CONTRACT
DOCUMENTS:
Where there is any conflict between the various
documents in the contract, the following order of priority
shall be followed i.e. a document appearing earlier shall
override the document appearing subsequently:
1) Agreement
2) Letter of Acceptance of Tender
3) Notice Inviting Tender
4) Instructions to the Tenderers
5) Appendix to Tender
6) Form of Bid
7) Special Conditions of the Contract
8) General Conditions of Contract
9) Technical Specifications
10) Relevant codes and Standards
11) Bill of Quantities”
6.4 Stipulation No. 6 of the TS:
“6. The Bill of Quantities provides for the supply of set of
fastening system (imported and Indian components) for
straight track and for curve track for various range of
radius. The supplier shall be responsible for obtaining
O.M.P. (COMM) 414/2023 Page 8 of 16
approval of the Client for the design of fastenings sets for
various types as regards the nos. of anchor bolts with
associated components per set (Bolt calculations). The
accepted rates shall remain unchanged irrespective of the
design of fastening system approved by the Client as
regards nos. of anchor bolts for various range of radius.
No claim on this account shall be accepted.”
7. The petitioner was the successful bidder and was issued LOA
for supply of 1,86,500 sets. The quantity of the sets to be supplied
increased to 1,98,715. For the additional sets supplied, the petitioner
was paid at the agreed rate.
8. The surviving dispute is that due to the variation in quantity the
petitioner had to supply additional components for which payment is
claimed over and above the agreed price of the sets.
9. The NIT invited bids for supply of a total of 1,86,500 sets,
comprising of both Indian and imported components. The bid was for
a price per set as is evident from the contract documents including the
NIT, LOA and BOQ and held by the arbitrator. The LOA dated
21.05.2015, was for the total cost of work to be undertaken and
bifurcated the amount into Indian Rupees (hereinafter referred to as
„INR‟) and US Dollars, the price was inclusive of taxes, levy, cess,
etc.
10. The arbitrator after considering the terms and clauses of the
tender and the LOA concluded that the supply of sets was at a fixed
cost and the agreement dated 09.10.2015, executed between the
parties was to that effect. The challenge to the finding of a fixed value
O.M.P. (COMM) 414/2023 Page 9 of 16
contract by learned counsel for the petitioner by relying upon Clause
27 of the GCC and the BOQ, lacks merit. Clause 27 of the GCC
specifies that the quantities mentioned in the BOQ may vary and the
supplier would be bound to complete the work despite variation. The
price for additional supplies consequent to variation are dealt with in
two categories: first, where the variation is upto (+) or (-) 25% , the
supplies are to be made at the accepted rates and second, where the
variation exceeds (+) or (-) 25%, the rates for the increased quantities
had to be negotiated. The clause does not deal with the rate fixed for
the supply of 2-bolt and 4-bolt sets or with additional components
supplied. The rates specified in clause 27 of GCC in case there is
variation in quantities does not alter the position that sets were to be
supplied on fixed price. The BOQ gives the split of price for imported
components, Indian components, transportation costs, taxes, amount
payable in USD and the amount payable in INR but does not support
the case of the petitioner that the contract was for the supply of
individual components and not complete sets. The conclusion of the
arbitrator is a plausible one.
11. The component wise price break-up in annexure to the LOA
was specified to be for taxes and transportation only and was
considered accordingly by the arbitrator. The price break-up would
not affect the tender awarded for total cost of the work i.e., the cost for
supply of the sets of various categories.
12. It is an admitted fact that consequent to variation order the
petitioner was paid the agreed price for the supply of additional sets
O.M.P. (COMM) 414/2023 Page 10 of 16
but the grievance is that consequent to variation the petitioner ended
up supplying additional components. Stipulation No. 6 of the TS
forms part of the contract and obligated the petitioner to get approval
from DMRC of the designs for various types of sets and the number of
anchor bolts with associated components per set. It provides that the
accepted rates shall remain the same irrespective of design of the
fastening system approved by DMRC and no claim shall be accepted
on this account. The claim of the petitioner for payment of additional
components over and above the agreed price of the sets is barred by
stipulation no. 6 of the TS.
13. The issue as to the type of sets to be used for the curved track
above 500 metres was pending and the insistence of the petitioner on
use of 2-bolt system instead of a 4-bolt system was not accepted by
DMRC. The petitioner in violation of Stipulation No. 6 of the TS
made the supplies prior to obtaining approval from DMRC. The
petitioner raised a claim that due to the supply of additional
components, the procurement cost increased and petitioner is entitled
to additional payment over and above the agreed price. It is important
to note that Stipulation No. 6 of the TS provided that the accepted
rates shall not change upon approval of the design by DMRC. The
arbitrator rightly noted that the bolt calculation was dependent upon
approval of the design by DMRC and this was also evident from the
email communication of the petitioner dated 07.08.2015.
14. The arbitrator was right in holding that Clause 27 of the GCC
and Stipulation No. 6 of the TS deal with different situations and there
O.M.P. (COMM) 414/2023 Page 11 of 16
was no need to go into the priority ranking inter se the two clauses.
The case set up by the petitioner for getting out of the rigours of
Stipulation No. 6 of the TS by contending that acceptance of the
supplies by the respondent tantamounted to acceptance of the design
was contrary to Stipulation No. 6 of the TS. The design was to be
approved by DMRC and not by IRCON ltd., the executing agency.
15. It would be relevant to note that as per Clause 2.8 of the LOA,
Clause 27 of the GCC was applicable for variation of the sets of
various types contained in the BOQ i.e. for sum total of Item no. (i) to
(vi) mentioned in the BOQ and not for the variation of individual
items. The contention of learned counsel for the petitioner that Clause
2.8 of the LOA dealt with individual items and not additional
components is ill-founded. If the argument if taken to logical end
would mean that upon variation, the contract would change from a set-
based to a component-based contract, which the parties never
contemplated. The total quantity in the BOQ mentioned in Clause 2.8
relates to the quantity of sets to be supplied and the clause cannot be
read to mean that in case of variation of quantity of sets, the nature of
the tender would change and the varied quantity is to be supplied
item-wise and not on complete set basis as the original quantity was
being supplied.
16. The argument of learned counsel for the petitioner that the
arbitrator has re-written the terms and conditions agreed between the
parties is noted to be rejected. The arbitrator took into consideration
O.M.P. (COMM) 414/2023 Page 12 of 16
the terms of the tender, TS and the clauses of the LOA and has given a
plausible interpretation.
17. The scope of interference under Section 34 of the Act is well
settled. The award cannot be interfered for another possible view. The
interpretation of the clauses of the contract falls within the exclusive
domain of the arbitrator. The award cannot be interfered with for
every legal or factual error unless it is vitiated by perversity.
Reference in this regard may be made to the following decisions of the
Supreme Court:
17.1 In Prakash Atlanta (JV) v. National Highways Authority of
India, 2026 INSC 76 it was held as under:-
“59. (vi) If an arbitral tribunal‟s view is found to be a
possible and plausible one, it cannot be substituted
merely because an alternate view is possible.
Construction and interpretation of a contract and its terms
is a matter for the arbitral tribunal to determine. Unless
the same is found to be one that no fair-minded or
reasonable person would arrive at, it cannot be interfered
with. If there are two plausible interpretations of the
terms of a contract, then no fault can be found if the
arbitrator accepts one such interpretation as against the
other. To be in conflict with the public policy of India,
the award must contravene the fundamental policy of
Indian law, which makes it narrower in its application.”
17.2 In Ramesh Kumar Jain v. Bharat Aluminium Company
Limited (BALCO), 2025 INSC 1457 it was held as under:-
“28. The bare perusal of section 34 mandates a narrow
lens of supervisory jurisdiction to set aside the arbitral
award strictly on the grounds and parameters enumerated
in sub-section (2) & (3) thereof. The interference is
O.M.P. (COMM) 414/2023 Page 13 of 16
permitted where the award is found to be in contravention
to public policy of India; is contrary to the fundamental
policy of Indian Law; or offends the most basic notions of
morality or justice. Hence, a plain and purposive reading
of the section 34 makes it abundantly clear that the scope
of interference by a judicial body is extremely narrow. It
is a settled proposition of law as has been constantly
observed by this court and we reiterate, the courts
exercising jurisdiction under section 34 do not sit in
appeal over the arbitral award hence they are not
expected to examine the legality, reasonableness or
correctness of findings on facts or law unless they come
under any of grounds mandated in the said provision. In
ONGC Limited. v. Saw Pipes Limited
14
, this court held
that an award can be set aside under Section 34 on the
following grounds: “(a) contravention of fundamental
policy of Indian law; or (b) the interest of India; or (c)
justice or morality, or (d) in addition, if it is patently
illegal.”
17.3 In Consolidated Construction Consortium Limited v. Software
Technology Parks of India, (2025) 7 SCC 757 it was held as under:
“46. Scope of Section 34 of the 1996 Act is now well
crystallized by a plethora of judgments of this Court.
Section 34 is not in the nature of an appellate provision. It
provides for setting aside an arbitral award that too only
on very limited grounds i.e. as those contained in Sub-
sections (2) and (2-A) of Section 34. It is the only remedy
for setting aside an arbitral award. An arbitral award is
not liable to be interfered with only on the ground that the
award is illegal or is erroneous in law which would
require re-appraisal of the evidence adduced before the
arbitral tribunal. If two views are possible, there is no
scope for the court to re-appraise the evidence and to take
the view other than the one taken by the arbitrator. The
view taken by the arbitral tribunal is ordinarily to be
accepted and allowed to prevail. Thus, the scope of
O.M.P. (COMM) 414/2023 Page 14 of 16
interference in arbitral matters is only confined to the
extent envisaged Under Section 34 of the Act. The court
exercising powers Under Section 34 has perforce to limit
its jurisdiction within the four corners of Section 34. It
cannot travel beyond Section 34. Thus, proceedings
Under Section 34 are summary in nature and not like a
full-fledged civil suit or a civil appeal. The award as such
cannot be touched unless it is contrary to the substantive
provisions of law or Section 34 of the 1996 Act or the
terms of the agreement.”
17.4 In Sepco Electric Power Construction Corporation v. GMR
Kamalanga Energy Ltd., 2025 INSC 1171 it was held as under:
“97……..Therefore, it appears that even if the arbitrator‟s
legal or factual reasoning is faulty, the courts ought to
ideally refrain from interfering with an award until an
error of law is evident from the award itself or in a
document that forms an integral component thereof.”
17.5 In Parsa Kente Collieries Limited. v. Rajasthan Rajya Vidyut
Utpadan Nigam Limited, (2019) 7 SCC 236 held as under:-
“9.1. In Associate Builders [Associate Builders v. DDA,
(2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , this Court
had an occasion to consider in detail the jurisdiction of
the Court to interfere with the award passed by the
Arbitrator in exercise of powers under Section 34 of the
Arbitration Act. In the aforesaid decision, this Court has
considered the limits of power of the Court to interfere
with the arbitral award. It is observed and held that only
when the award is in conflict with the public policy in
India, the Court would be justified in interfering with the
arbitral award. In the aforesaid decision, this Court
considered different heads of “public policy in India”
which, inter alia, includes patent illegality. After referring
Section 28(3) of the Arbitration Act and after considering
the decisions of this Court in McDermott International
Inc. v. Burn Standard Co. Ltd. [McDermott International
O.M.P. (COMM) 414/2023 Page 15 of 16
Inc. v. Burn Standard Co. Ltd., (2006) 11 SCC 181] ,
SCC paras 112-113 and Rashtriya Ispat Nigam Ltd. v.
Dewan Chand Ram Saran [Rashtriya Ispat Nigam Ltd. v.
Dewan Chand Ram Saran, (2012) 5 SCC 306] , SCC
paras 43-45, it is observed and held that an Arbitral
Tribunal must decide in accordance with the terms of the
contract, but if an Arbitrator construes a term of the
contract in a reasonable manner, it will not mean that the
award can be set aside on this ground. It is further
observed and held that construction of the terms of a
contract is primarily for an Arbitrator to decide unless the
Arbitrator construes the contract in such a way that it
could be said to be something that no fair-minded or
reasonable person could do. It is further observed by this
Court in the aforesaid decision in para 33 that when a
court is applying the “public policy” test to an arbitration
award, it does not act as a court of appeal and
consequently errors of fact cannot be corrected. A
possible view by the Arbitrator on facts has necessarily to
pass muster as the Arbitrator is the ultimate master of the
quantity and quality of evidence to be relied upon when
he delivers his arbitral award. It is further observed that
thus an award based on little evidence or on evidence
which does not measure up in quality to a trained legal
mind would not be held to be invalid on this score.”
(Emphasis supplied)
18. The conclusions of the tribunal: (i) that the petitioner started the
supplies before the design was approved on 19.11.2015 and thereby
violated Stipulation No. 6 of the TS; (ii) there was no modification of
the contract and only the number of sets of various kinds to be
supplied were varied; (iii) the payment for additional sets supplied
was to be made at the agreed price; and (iv) rejecting the claim of the
petitioner seeking payment over and above the agreed price, for
O.M.P. (COMM) 414/2023 Page 16 of 16
additional components supplied consequent to variation order, suffers
from no legal or factual error much less perversity and the view is
plausible, neither against public policy and nor is patently illegal.
19. No case is made out for interference under Section 34 of the
Act. The impugned award is upheld.
AVNEESH JHINGAN, J
MAY 20, 2026
‘ha’
Reportable:- Yes
Legal Notes
Add a Note....