2025 INSC 217 Page 1 of 21
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO S. 2027-2028 OF 2012
PUJA FERRO ALLOYS P LTD. … APPELLANT
VS.
STATE OF GOA AND ORS. … RESPONDENTS
WITH
CIVIL APPEAL NO. 4556 OF 2012
M/S KARTHIK ALLOYS LTD . … APPELLANT
VS.
STATE OF GOA AND ANR. … RESPONDENTS
AND
CIVIL APPEAL NO S.2033-2034 OF 2012
KARTHIK INDUCTIONS LTD. … APPELLANT
VS.
STATE OF GOA AND ORS. … RESPONDENTS
Page 2 of 21
AND
CIVIL APPEAL NO S.2031-2032 OF 2012
GLOBAL ISPAT LTD. … APPELLANT
VS.
STATE OF GOA AND ORS. … RESPONDENTS
AND
CIVIL APPEAL NO S.2035-2036 OF 2012
SUNRISE ELECTROMELT LTD. … APPELLANT
VS.
STATE OF GOA AND ORS. … RESPONDENTS
J U D G M E N T
DIPANKAR DATTA, J.
THE APPEAL
1. In all but one of the civil appeals under consideration, the appellant-
companies call in question the common impugned judgment and order
dated 08.07.2011 of the High Court
1
in a batch of writ petitions
2
and a
common order dated 21.10.2011 on a batch of civil review applications.
By the impugned judgment and order, the High Court declined to grant
the relief of rebate of 25% on the electricity tariff in terms of the
1
High Court of Bombay, at Goa
2
W.P. Nos. 157-160/2011
Page 3 of 21
notification dated 30.09.1991 to the appellants. The subsequent order
dismissed the review applications.
2. Civil Appeal No. 4556/2012 [M/s Karthik Alloys Ltd. v. The State of Goa
and Another] is a connected appeal, which challenges the judgment and
order dated 08.07.2011 of the High Court dismissing the writ petition
3
filed by M/s Karthik Alloys Ltd. on similar grounds.
RESUME OF FACTS
3. This is the third round of litigation before this Court regarding the issue
of grant of relief of rebate, but not between the same parties.
4. Civil Appeal No. 2027-28 of 2012 [Puja Ferro Alloys P Ltd. v. The State
of Goa and Another] is the lead appeal. Considering the commonality of
the issues of facts and law in all the connected appeals, we proceed to
note the facts of the lead appeal to the extent the same are relevant for
a decision on these appeals.
i. Vide Notification dated 27.06.1988, the first respondent-State of Goa
4
determined tariff applicable to electricity bills issued from
01.07.1988.
ii. Vide Notification dated 30.09.1991 issued under Section 23 read with
Section 51-A of the Indian Electricity Act, 1910
5
, the SoG determined
tariff whereby industrial units which applied for availing High-Tension
or Low-Tension power supply for bona fide industrial activities were
held entitled to a rebate of 25% on the tariff chargeable under the
3
WP No. 179/2011
4
SoG
5
1910 Act
Page 4 of 21
notification dated 27.06.1988 for a period of five years from the date
on which the electricity supply was made available.
iii. The appellant-companies then applied for power from the SoG and
entered into respective power supply agreements. The details are
tabulated hereunder
6
:
Appellant-
Company
Application
for Power
Power Supply
Agreement
Date of
Power
Connection
Puja Ferro
Alloys Pvt. Ltd.
15.09.1992 05.08.1993 16.05.1995
Karthik Alloys
Ltd.
26.11.1992 - 17.11.1993
Karthik
Inductions Ltd.
- - 28.07.1995
Global Ispat
Pvt. Ltd.
21.02.1994 10.02.1995 29.04.1995
Sunrise
Electromelt
Ltd.
01.02.1994 08.02.1995 10.02.1995
iv. Vide Notification dated 31.03.1995, issued under Section 23 read with
Section 51-A of the 1910 Act as well as Section 21 of the General
Clauses Act, 1897, the previous notification dated 30.09.1991 was
rescinded w.e.f. 01.04.1995. In terms thereof, the scheme of rebate
was stopped and any new industrial unit applying for power after
31.03.1995 would not get the benefit of the notification dated
30.09.1991.
v. On 15.05.1996, the notification dated 30.09.1991 was amended to
include another consumer category of “Extra High-Tension”.
6
Data taken from GR Ispat Ltd. v. Chief Electrical Engineer, 1999 (1) Goa L.T. 218
Page 5 of 21
vi. The notification dated 30.09.1991 was once again amended on
01.08.1996 so as to extend the benefit of rebate to all the industrial
units who apply or avail extra high-tension power supply. The rebate
of 25% was given on the prevailing tariff in force.
vii. Power began to be supplied to the appellant-companies as mentioned
in the table above. However, the 25% rebate was given only from
01.01.1997. The accumulated arrears of rebate were sought to be
disbursed in 60 equated monthly instalments.
viii. Vide Circular dated 31.03.1998, the SoG suspended the rebate
entitlement. However, the said circular does not mention whether the
suspension of the rebate was of the rebate given under the
notification dated 30.09.1991 or the amending notifications of
15.05.1996 and 01.08.1996.
ix. On 24.07.1998, the amending notification dated 01.08.1996 was
rescinded.
x. A batch of writ petitions challenging the circular dated 31.03.1998
and the notification dated 24.07.1998 came to be presented before
the High Court.
xi. The High Court vide judgment and order dated 21.01.1999 in W.P.
No. 239 of 1998 [GR Ispat Ltd. v. Chief Electrical Engineer
7
] held
that rescission of the notification dated 30.09.1991 by the notification
dated 31.03.1995 would only mean that the scheme providing rebate
was given up from 01.04.1995 and that the new industrial units could
7
1999 (1) Goa L.T. 218
Page 6 of 21
not apply after 01.04.1995 to obtain the benefit of rebate. The High
Court also held that the amendment of the notification after its
rescission clearly indicates that the notification dated 30.09.1991 was
in existence and operation for those industrial units who had already
become entitled to get the benefit of rebate under it. Therefore, the
suspension of the release of rebate was invalid and inoperative. The
High Court concluded that the notification dated 24.07.1998 is legal,
valid and operative and that the petitioning companies therein were
entitled to 25% rebate in power tariff till 24.07.1998.
xii. When the decision was challenged in this Court in CA No. 3206 -
3217/1999, interference was declined vide order dated 13.02.2001
as the High Court had taken a balanced view in the matter.
xiii. A writ petition also came to be filed in the High Court challenging the
notifications dated 15.05.1996 and 01.08.1996 wherein prayer was
made to declare the same as null and void. The High Court allowed
the said writ petition [Manohar Parrikar v. State of Goa
8
] owing to
brazen non-compliance with the Rules of Business framed under
Article 166(3) of the Constitution. The impugned notifications were
held to be non-est and void ab initio and the consequential acts based
on such notifications were also to be considered null and void.
xiv. Meanwhile in 2002, the SoG enacted the Goa (Prohibition of Further
Payments and Recovery of Rebate Benefits) Act, 2002
9
. Section 3 of
2002 Act specified that any person or industrial consumer in the SoG
8
2001 SCC OnLine Bom 350
9
2002 Act
Page 7 of 21
who has already availed of the benefits of 25% rebate in pursuance
of the Government notifications dated 15.05.1996 and 01.08.1996
would be liable to refund the amount to the third respondent herein
– the Chief Electrical Engineer, Electricity Department, Government
of Goa.
xv. A batch of civil appeals challenging the judgment and order in
Manohar Parrikar (supra) was dismissed by this Court in MRF
Limited v. Manohar Parrikar & Ors.
10
.
xvi. Moreover, this Court in Goa Glass Fibre Limited v. State of Goa &
Anr.
11
categorically held that the object of the 2002 Act is not to undo
or reverse the judgments of the Supreme Court or the High Court but
it merely seeks to recover and extinguish all liabilities of the SoG that
accrue or arise from the notifications dated 15.05.1996 and
01.08.1996.
xvii. Vide demand notice dated 21.02.2011, the respondents sought
recovery from Puja Ferro [the lead appellant-company], under
Section 3 of the 2002 Act, an amount of Rs. 1,36,30,072/-. Aggrieved
by the impugned demand notice, the appellant-company preferred a
writ petition
12
before the High Court. Similar demand notices were
served on the other appellant-companies leading them too to file their
respective writ petitions before the High Court.
10
(2010) 11 SCC 374
11
(2010) 6 SCC 499
12
W.P. No.160/2011
Page 8 of 21
xviii. By the common impugned judgment and order, referred to at the
beginning of this judgment, the Division Bench of the High Court
dismissed the batch of writ petitions filed by the appellant-companies
and thereby, upheld the demand notices. Review applications filed
against the impugned judgment and order were also dismissed by the
High Court holding that no error apparent on the face of the record
was shown to exist.
IMPUGNED JUDGMENTS
5. Before the High Court, the appellant-companies assailed the demand
notices on the ground that the rebate was offered for the purpose of
increasing investment and industries in the SoG. Based on the promise
that incentives in the form of rebate would be given, the appellant-
companies set up industries in the SoG, obtaining loans from banks and
financial institutions as well as on plots of land on lease from the
Industrial Development Corporation. They urged that the SoG was bound
to provide the rebate as per the notifications providing such rebate and
the subsequent power supply agreement entered int o by and between
the appellant-companies and the authorities. Moreover, the High Court
had previously decided that the amendment of the rescinded notification
would imply that the rebate entitlement was still available to existing
consumers and that only new consumers were not eligible for the 25%
rebate. This was carried up to this Court which upheld the said order of
the Division Bench of the High Court. They further contended that the
decision of the High Court in Manohar Parrikar (supra) does not affect
Page 9 of 21
the claim of the appellant-companies as it was a judgment in personam.
It was also urged that the SoG under the guise of recovery of rebate was
actually recovering the rebate benefit granted under the notification
dated 30.09.1991.
6. The respondents defended the impugned demand notice s before the
High Court on the ground that the appellant-companies had claimed that
they availed the benefits of 25% rebate on the power tariff pursuant to
the notification dated 30.09.1991; however, their case cannot be
accepted because the notification dated 30.09.1991 was rescinded with
effect from 01.04.1995 vide notification date 31.03.1995. It was further
urged that the previous order of the High Court in Manohar Parrikar
(supra), which was subsequently challenged before this Court, binds the
appellant-companies as it has clearly held that the rebate benefit will not
be available to the appellant-companies after the unexpired period of
five years.
7. The High Court concluded that the appellant-companies are not those
who are claiming benefit of rebate under the notification dated
30.09.1991, as this notification was rescinded by the notification dated
31.03.1995. The High Court, based on the reply affidavit filed by the
respondents, proceeded on the basis that the appellant-companies have
availed the power supply only after 31.03.1995. The High Court held that
the previous decisions have clarified that the 2002 Act is valid and
constitutional and that the demand notice s had been issued under
Section 3 of the 2002 Act. Moreover, it was held that the appellant-
Page 10 of 21
companies cannot rest their claims on the basis of the notifications dated
15.05.1996 and 01.08.1996 as these decisions were held not to be
Government decisions, and the notification dated 30.09.1991 was
rescinded on 31.03.1995 with effect from 01.04.1995.
8. The High Court observed that the appellant-companies have been
supplied power only from 10.05.1995, 29.04.1995, 28.07.1995 and
16.05.1995 and, therefore, none of the appellants before the High Court
could lay a valid claim to be covered by the notification dated
30.09.1991. Consequently, all the writ petitions came to be dismissed.
9. Aggrieved by the said judgment and order of the High Court, various civil
review applications were filed seeking a review thereof. The Division
Bench dismissed the same holding that there was no error apparent on
the face of the record that would necessitate any review of the judgment
and order under review.
CONTENTIONS
10. Mr. Santosh Paul, learned senior advocate for the appellant-companies,
orally as well as through the written notes of arguments assailed the
impugned judgment and order by contending that:
i. The appellant-companies are covered by the notification dated
30.09.1991 and not by the notification dated 01.08.1996.
ii. The High Court has not appreciated that the rights of the appellant-
companies crystallized upon making the application for power while
the notification dated 30.09.1991 was in force and hence, irrespective
Page 11 of 21
of when the power was actually supplied, the appellant-companies
are entitled to the benefit of rebate.
iii. Referring to the decision in Pawan Alloys & Casting (P) Ltd. v. UP
SEB
13
, it was urged that the new industries were attracted to the
region relying upon the promise of the SoG to grant rebate and that
without the lure of rebate, the appellant-companies would not have
set up industries in the SoG.
iv. A notification cannot be rescinded with retrospective effect and only
with prospective effect and that the decision in GR Ispat Ltd. (supra)
clearly lays down that the appellant-companies cannot be denied the
rebate.
v. The impugned demand notice s are illegal, arbitrary, and ultra vires
the provisions of the 2002 Act.
vi. The appellant-companies became aware of a certain letter of the
Electricity Department of the SoG which has a direct bearing on the
matter and discovery of such new material is sufficient to exercise the
power of review, as decided in Inderchand Jain v. Motilal
14
.
vii. The appellant-companies have been treated rather unfairly and to set
things right, the impugned demand notices ought to be quashed and
the deposits made by them, in pursuance of the order issuing notice
dated 10.02.2012, may be directed to be refunded.
11. Mr. Abhay Anil Anturkar, learned Standing Counsel for the respondents,
has assiduously contended that the impugned judgment and order not
13
(1997) 7 SCC 251
14
(2009) 14 SCC 663
Page 12 of 21
suffering from any infirmity, the civil appeals deserve outright dismissal.
It was further contended that:
I. The impugned demand notice s have been issued in consonance
with the 2002 Act. The challenge to the constitutionality of the
2002 Act has been upheld by this Court.
II. The High Court has rightly concluded that the said notification
dated 30.09.1991 does not cover the case of the appellant -
companies and hence, they are not entitled to any rebate.
III. The appellant-companies have received the benefits from the
notifications dated 15.05.1996 and 01.08.1996, however, the case
that has been made out before this Court is that they received
benefit from the notification dated 30.09.1991.
THE QUESTION
12. The short question arising for decision in all the connected appeals is,
whether the appellant-companies are covered by the notification dated
30.09.1991 for the purpose of availing 25% rebate on the tariff
chargeable for availing power supply.
ANALYSIS AND REASONS
13. At the outset, we record our sense of surprise having noticed that the
notification dated 30.09.1991, which was rescinded by notification dated
31.03.1995, was amended twice vide notifications dated 15.05.1996 and
01.08.1996. However, the High Court in GR Ispat (supra) clarified the
position and such clarification having been accepted by this Court, we
refrain from expressing any further view.
Page 13 of 21
14. Moving ahead to determine the question as to which of the notifications
would apply in the case of the appellant-companies before us, we have
perused the series of notifications published by the SoG along with the
impugned demand notices and the impugned judgment and order.
15. The impugned demand notice s were issued under the 2002 Act and
seeks to recover the rebate granted to the appellant-companies by the
SoG. This Court has previously held in Goa Glass Fibre (supra) that the
2002 Act is legal and valid. This enactment provides for recovery of
rebate granted under the notifications dated 15.05.1996 and
01.08.1996. The appellant-companies have primarily urged before this
Court that since their claim is governed by the notification dated
30.09.1991, Section 3 of the 2002 Act does not apply to them and that
the SoG does not have the power to recover the rebate granted to these
companies.
16. While at first blush this argument seems to be attractive, upon a closer
examination of the facts, it must be rejected for the reasons that follow.
17. In the case of GR Ispat (supra), the High Court decided that the
rescission of the notification dated 30.09.1991 was limited to new
industrial units and that it was very much in existence and operative for
those industrial units who had already become entitled to the rebate
benefit under the said notification. Therefore, the High Court concluded
that the grant of 25% rebate was operative till it was suspended vide
notification dated 31.03.1998. The High Court ruled that only one of the
petitioners before it, i.e., the Marmagao Steel Company is entitled to the
Page 14 of 21
benefit of rebate under the notification dated 30.09.1991 or the second
notification dated 01.08.1996. The High Court ruled that the companies
could have applied before 01.10.1991 but the supply of electricity must
be availed from a date subsequent to 01.10.1991 for being entitled to
the rebate. This ruling is admittedly in favour of the appellant -
companies. However, the further discussion of the High Court from
paragraph 35 onwards merits consideration. The High Court specifically
held that the challenge against the rescission on the grounds of
promissory estoppel against the SoG is unsustainable as it must yield to
the principle of public equity. Therefore, it was held that the Government
has a justifiable ground of supervening public interest to withdraw the
grant of rebate in power tariff which was promised in the two
notifications dated 30.09.1991 and 01.08.1996. The High Court further
noted that many of the companies did not complete their respective
period of five years to get the rebate on 27.07.1998; therefore, they will
have to forgo their claim of rebate for the unexpired period in view of
the overriding public interest arising due to financial crunch. The High
Court also clearly laid down the period of entitlement of rebate up to
27.07.1998 for the respective appellant-companies in paragraph 56 of
the judgment. When challenged before this Court, it was dismissed on
the ground that the High Court has taken a balanced view of the matter.
Therefore, this judgment has attained finality.
18. Now turning to the impugned judgment and order of the High Court, the
appellant-companies on a similar challenge argued that the demand
Page 15 of 21
notices seek to recover the benefit that has already been protected by
the Division Bench earlier in GR Ispat (supra). The High Court spurned
this argument by highlighting that the previous decision was restricted
to those claims which actually accrued and were admissible in terms of
the notification dated 30.09.1991. However, if the power supply itself
has not been availed of within the period during which the notification
dated 30.09.1991 was in force, the foundation for the challenge itself is
shaky and without any legal basis.
19. First, the notification dated 30.09.1991 made the rebate available for
five (5) years from the date on which electric supply was effected to the
appellant-companies. As seen in the table above, supply of electricity
was effected to all the appellant-companies, except M/s Karthik Alloys,
on varying dates beyond 31.03.1995 ; however, the notification dated
30.09.1991 had life till 31.03.1995 whereafter it stood rescinded, leaving
no option but to decline acceptance of their pleas.
20. Secondly, reliance placed on the notifications dated 15.05.1996 and
01.08.1996 is wholly misconceived as they must be deemed not to have
existed at all because of the declaration in Manohar Parrikar (supra),
that they were non-est and void ab initio. The appellant-companies
herein were seeking benefit of these subsequent notifications before the
High Court in GR Ispat (supra), which was not accepted by the High
Court. Considering the ruling by the High Court that they are covered
under the notification dated 30.09.1991, they now seek to protect their
benefits under the guise of this notification which, in any event, stood
Page 16 of 21
rescinded with effect from 01.04.1995 whereas the supply was effected
therafter. Despite the redundancy, we stress that the appellant -
companies, except M/s Karthik Alloys, received power connection
beyond 01.04.1995; thus these claims cannot be sustained.
21. Thirdly, we do not have any doubt that the Division Bench is correct in
holding that the challenge is without any legal basis as the question is
squarely covered by the previous decision of the High Court in GR Ispat
(supra).
22. For the principle of res judicata to be applied in the subsequent
proceeding, it must be between the same parties and the cause of action
of the subsequent proceeding must be the same as in the previous
proceeding. The Supreme Court in the case of Satyadhyan Ghosal v.
Deorajin Debi
15
has succinctly noted that the principle of res judicata
is essential in giving a finality to judicial decisions by observing as under:
“The principle of res judicata is based on the need of giving a finality to
judicial decisions. What it says is that once a res is judicata, it shall not
be adjudged again. Primarily it applies as between past litigation and
future litigation. When a matter — whether on a question of fact or a
question of law — has been decided between two parties in one suit or
proceeding and the decision is final, either because no appeal was taken
to a higher court or because the appeal was dismissed, or no appeal lies,
neither party will be allowed in a future suit or proceeding between the
same parties to canvass the matter again. This principle of res judicata
is embodied in relation to suits in Section 11 of the Code of Civil
Procedure; but even where Section 11 does not apply, the principle of
res judicata has been applied by courts for the purpose of achieving
finality in litigation. The result of this is that the original court as well as
any higher court must in any future litigation proceed on the basis that
the previous decision was correct.
The principle of res judicata applies also as between two stages in the
same litigation to this extent that a court, whether the trial court or a
higher court having at an earlier stage decided a matter in one way will
not allow the parties to re-agitate the matter again at a subsequent stage
of the same proceedings. …”
15
[1960] 3 SCR 590
Page 17 of 21
23. A three-judge bench of this Court in the case of Hope Plantations Ltd.
v. Taluk Land Board
16
, has elucidated the applicability of the principles
of res judicata and estoppel in the Indian context and held that:
“26. It is settled law that the principles of estoppel and res judicata are
based on public policy and justice. Doctrine of res judicata is often
treated as a branch of the law of estoppel though these two doctrines
differ in some essential particulars. Rule of res judicata prevents the
parties to a judicial determination from litigating the same question over
again even though the determination may even be demonstratedly
wrong. When the proceedings have attained finality, parties are bound
by the judgment and are estopped from questioning it. They cannot
litigate again on the same cause of action nor can they litigate any issue
which was necessary for decision in the earlier litigation. These two
aspects are ‘cause of action estoppel’ and ‘issue estoppel’. These two
terms are of common law origin. Again, once an issue has been finally
determined, parties cannot subsequently in the same suit advance
arguments or adduce further evidence directed to showing that the issue
was wrongly determined. Their only remedy is to approach the higher
forum if available. The determination of the issue between the parties
gives rise to, as noted above, an issue estoppel. It operates in any
subsequent proceedings in the same suit in which the issue had been
determined. It also operates in subsequent suits between the same
parties in which the same issue arises. Section 11 of the Code of Civil
Procedure contains provisions of res judicata but these are not
exhaustive of the general doctrine of res judicata. Legal principles of
estoppel and res judicata are equally applicable in proceedings before
administrative authorities as they are based on public policy and justice.
………
31. Law on res judicata and estoppel is well understood in India and
there are ample authoritative pronouncements by various courts on
these subjects. As noted above, the plea of res judicata, though
technical, is based on public policy in order to put an end to litigation. It
is, however, different if an issue which had been decided in an earlier
litigation again arises for determination between the same parties in a
suit based on a fresh cause of action or where there is continuous cause
of action. The parties then may not be bound by the determination made
earlier if in the meanwhile, law has changed or has been interpreted
differently by a higher forum. But that situation does not exist here.
Principles of constructive res judicata apply with full force. It is the
subsequent stage of the same proceedings. If we refer to Order XLVII of
the Code (Explanation to Rule 1) review is not permissible on the ground
‘that the decision on a question of law on which the judgment of the
Court is based has been reversed or modified by the subsequent decision
of a superior court in any other case, shall not be a ground for the review
of such judgment’.”
16
(1999) 5 SCC 590
Page 18 of 21
24. It is now well settled that the principle of res judicata applies even to
petitions arising for decision in the writ jurisdiction under Article 226 of
the Constitution. If any authority is required one may profitably refer to
the decision in T.P. Moideen Koya v. State of Kerala
17
.
25. In the instant case, we are convinced that the writ petitions before the
High Court were hit by res judicata in view of its previous decision in GR
Ispat (supra) which, when challenged before this Court, was upheld with
the further observation that a balanced view of the matter had been
taken and no interference was called for. The appellant-companies were
all parties and are bound by the decision in GR Ispat (supra). Having
failed up to this Court, the appellant-companies could not have adopted
a stand different from the one taken in the first round of litigation. They
sought to challenge the demand notices by re-opening the litigation and
arguing that they are entitled to the benefit for five years, which they
would have been entitled to had they availed the supply of power within
the time that the notification dated 30.09.1991 was in force.
26. Though we have emphatically held against the appellant -companies
hereinabove, we wish to also deal with the final contention that since the
appellant-companies have invested in the SoG on the basis of the rebate
granted to them, the State is now estopped from resiling and
withdrawing this benefit, which has crystallised. Reliance has been
placed on the decision in Pawan Alloys (supra), where this Court
ruled:
17
(2004) 8 SCC 106
Page 19 of 21
“24. Consequently it cannot be held on the clear recitals found in the
aforesaid three notifications issued by the Board that no representation
whatsoever guaranteeing 10% rebate on electricity consumption bills
could be culled out from these notifications. We, therefore, agree with
the finding of the High Court on Issue No. 1 that by these notifications
the Board had clearly held out a promise to these new industries and as
these new industries had admittedly got established in the region where
the Board was operating, acting on such promise, the same in equity
would bind the Board. Such a promise was not contrary to any statutory
provision but on the contrary was in compliance with the directions
issued under Section 78-A of the Act. These new industries which got
attracted to this region relying upon the promise had altered their
position irretrievably. They had spent large amounts of money for
establishing the infrastructure, had entered into agreements with the
Board for supply of electricity and, therefore, had necessarily altered
their position relying on these representations thinking that they would
be assured of at least three years' period guaranteeing rebate of 10%
on the total bill of electricity to be consumed by them as infancy benefit
so that they could effectively compete with the old industries operating
in the field and their products could effectively compete with their
products. On these well-established facts the Board can certainly be
pinned down to its promise on the doctrine of promissory estoppel.”
However, the appellant -companies have failed to consider the
discussion in paragraph 31:
“31. In the light of this settled legal position we, therefore, hold that
even though the appellants have succeeded in convincing us that the
earlier three notifications dated 29-10-1982, 13-7-1984 and 28-1-1986
did contain a clear promise and representation by the Board to the
prospective new industrialists that once they established their industries
in the region within the territorial limits of the operation of the Board,
they would be assured 10% rebate on the total bills regarding
consumption of electricity by their industries for a period of three years
from the initial supply of electric power to their concerns, the appellants
will not be able to enforce the equity by way of promissory estoppel
against the Board if it is shown by the Board that public interest required
it to withdraw this incentive rebate even prior to the expiry of three years
as available to the appellants concerned. It has also to be held that even
if such withdrawal of development rebate prior to three years is not
based on any overriding public interest, if it is shown that by such
premature withdrawal the appellant-promisees would be restored to
status quo ante and would be placed in the same position in which they
were prior to the grant of such rebate by earlier notifications th e
appellants would not be entitled to succeed……”
(emphasis supplied)
Page 20 of 21
27. In our opinion, public interest is what turns the tide against the
appellant-companies. The SoG before the High Court in GR Ispat
(supra) had specifically taken the stand that the policy of rebate was
unviable resulting from financial crunch and was overriding public
interest. This, the High Court accepted, unlike in the case of Pawan
Alloys (supra). This too would apply as res judicata against the
appellant-companies.
28. Applying these principles to the instant case, we have no doubt in our
minds that the High Court was right in holding that the appellant -
companies before it are not entitled to the rebate and the impugned
demand notices do not suffer from any vice including that of illegality.
29. Regarding Civil Appeal No. 4556 of 2012 (M/s Karthik Alloys Ltd. v. The
State of Goa and Another), the matter has not been argued before us as
Mr. Paul, representing the concerned appellant -company earlier,
submitted not having received any instructions to proceed.
30. Turning to the challenge laid to the common order dismissing the review
applications, we hold bearing in mind Order XLVII Rule 7 of the Code of
Civil Procedure that no appeal lies against an order of rejection of a
petition for review. The Civil Appeals in this behalf are misconceived.
31. Even otherwise, we have considered such appeals on merit. The
additional minor issue raised by the appellant-companies, as is revealed
from the common order on the review applications, is that review was
sought on two counts: first, that the rights of the applicants had
crystallised upon making the application for power and secondly, a new
Page 21 of 21
document had been unearthed by the applicants which proves that the
High Court had committed a mistake/error apparent on the face of the
record. As the first question has already been answered against the
appellant-companies, it is clear that this is not a ground for reviewing
the judgment. On the second count also, the argument of discovery does
not at all impress us. The document being a letter dated 06.04.1999 has
been perused. It does not aid the review applicants. We are, thus, in
agreement with the High Court in its determination that the document
does not in any way advance the case of the appellant-companies.
CONCLUSION
32. Bearing in mind the aforesaid discussion, civil appeals nos.2027-
2028/2012, 2033-2034/2012, 2031-2032/2012, and 2035-2036/2012
are dismissed. Civil appeal no.4556/2012 is dismissed as not pressed.
33. No order as to costs.
……………………………J .
(DIPANKAR DATTA)
……………………………J .
(SANDEEP MEHTA )
NEW DELHI ;
14
th
FEBRUARY, 2025.
Legal Notes
Add a Note....