construction law, contract dispute, housing authority
0  12 Aug, 2005
Listen in 00:55 mins | Read in 22:00 mins
EN
HI

Rajendra Construction Company Vs. Maharashtra Housing and Area Development Authority and Ors.

  Supreme Court Of India Civil Appeal /5045-5046/2005
Link copied!

Case Background

This appeal is brought before the Supreme Court of India by Rajendra Construction Company against the Maharashtra Housing and Area Development Authority and others. The case arises from a dispute ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8

CASE NO.:

Appeal (civil) 5045-5046 of 2005

PETITIONER:

Rajendra Construction Company

RESPONDENT:

Maharashtra Housing & Area Development Authority & Ors.

DATE OF JUDGMENT: 12/08/2005

BENCH:

C.K. Thakker & P.K.Balasubramanyan

JUDGMENT:

J U D G M E N T

(Arising out of S.L.P (c) Nos. 10963-10964 of 2003)

C.K. Thakker, J.

Leave granted.

The present appeals are directed against the judgment and order dated

June 4, 2003 passed by the Division Bench of the High Court of Bombay

(Aurangabad Bench) in First Appeal Nos. 528 and 529 of 1996. By the said

judgment, the High Court allowed the appeals filed by the Maharashtra

Housing & Area Development Authority and set aside decrees dated August

25, 1996, passed by the Court of Civil Judge, (Senior Division), Aurangabad

in Special Civil Suit Nos. 265 and 266 of 1991.

The relevant facts leading to these appeals may now be stated in brief;

Appellant Rajendra Construction Company ('RCC' for short) is a

partnership firm doing business in construction work. Maharashtra Housing

& Area Development Authority ('MHADA' for short) issued a Tender

Notice No. 4/87-88 calling offers from registered contractors for the

construction of 444 tenements under the Low Income Group Scheme

(LIGs), near Scot Grini, Garkheda, Aurangabad and 192 tenements under

Middle Income Group Scheme (MIGs), near Griha Nirman Bhavan,

Aurangabad.

In November, 1987, work orders were issued in favour of RCC for an

amount of Rs. 50,38,068/- in respect of the first work and for an amount of

Rs. 74,56,972/- in respect of the second work. According to the appellant,

the time limit within which the construction was to be completed was

eighteen months for the first scheme and twelve months for the second

scheme. However, the execution of construction work was delayed on

account of variation in the existing and agreed items as also certain extra

work as per the instructions of MHADA. Requests were, therefore, made by

RCC for extension of time which was granted and within that extended

period, the work was completed to the satisfaction of MHADA. MHADA,

however, took no steps to prepare final bill on one pretext or the other and

no payment was made to RCC. It was the case of RCC that its claim was

not properly worked out. Still, however, RCC accepted the payment made

by MHADA 'under protest'.

RCC then issued notice to MHADA on April 17, 1991 demanding

additional amount of Rs. 19,01,600 for construction work in the first scheme

and Rs. 21,08,100/- for the work in the second scheme. MHADA, however,

refused to make payment. RCC filed two appeals before MHADA Board on

May 06, 1991 under Clause 30 of the agreement claiming the above amounts

with interest at the rate of 18 per cent per annum. On June 14, 1991, RCC

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8

requested the Board to decide its claim. On June 29, 1991, RCC issued

notice to MHADA under Section 173 of Maharashtra Housing & Area

Development Act, 1976 to settle the claim within a period of sixty days. As

the claim was not settled, and payment was not made, RCC filed two suits in

the Court of Civil Judge, (Senior Division); Aurangabad being Special Civil

Suit No. 265 of 1991 for Rs. 19,01,100/- with running interest of 18 per cent

per annum from the date of the suit till realization of the amount and Special

Civil Suit No. 266 of 1991 for Rs. 21,08,100/- with running interest of 18

per cent per annum for the second scheme. The Civil Judge, (Senior

Division), Aurangabad issued summons to MHADA. MHADA filed written

statements in the suits. On September 3, 1993, the Court framed issues in

Special Civil Suit No. 266 of 1991 and on October 27, 1993 in Special Civil

Suit No. 265 of 1991. On January 5, 1995, RCC filed an application (Ex.

38) for appointment of sole arbitrator under Section 21 of Arbitration Act,

1940 for settling of the disputes/claims in the light of Clause 30 of contract

giving the names of five officers. A copy was served on defendant MHADA

immediately and the court passed the order "Call say other side". On March

10, 1995, MHADA filed application (Ex. 45) thereby giving no objection for

appointment of sole arbitrator but suggested three different names. On April

3, 1995, RCC, vide its application (Ex. 47) agreed to the appointment of Mr.

S.R. Wadekar as sole arbitrator as suggested by MHADA and to refer the

dispute to the said arbitrator. In pursuance of the above agreement, the

learned Civil Judge, (Senior Division), Aurangabad passed an order on April

6, 1995 vide ex. 48 and on April 7, 1995 vide Ex. 51. The order Ex. 47

reads as under :

ORDER PASSED BELOW EXH. NO. 47

"Shri S.R. Wadekar, Ex. Chief Engineer is appointed as

Sole Arbitrator who shall settle the terms of the agreement

along with the record if any, relevant and necessary. The sole

Arbitrator shall also collect the record from the Court and

shall report and shall write the award within 60 days from the

date of passing of this order, and without any further delay."

The Court then stated;

"You are therefore hereby appointed as Sole Arbitrator in

the matter. Accordingly the disputes and claims between the

parties are referred to you for Arbitration.

You are required to complete the proceedings as per

provisions of Arbitration Act, 1940 and file your award in

this Court within the time fixed by this Court.

You may fix up terms of fees and expenses with the

parties after entering on this reference. (Rs.2,000/- deposited

in Court).

Please notify the parties at the earliest.

Please acknowledge receipt of this order."

On the same day, the Court communicated the decision to sole

Arbitrator Mr. Wadekar. Mr. Wadekar sent his acceptance vide letter dated

April 10, 1995. The Arbitrator then conducted the proceedings, called for

record of the Civil Court and examined it. He also visited the site of

construction. After going through all the documents, terms and conditions of

tender agreement and other relevant records and after hearing the parties, he

passed awards on August 17, 1995. He considered the claims under

different heads and awarded an amount of Rs. 14,36,708.00 in respect of

Scheme No.1 and an amount of Rs.11,80,935.00 in respect of Scheme No.2.

The sole Arbitrator also awarded interest at the rate of 18 per cent per annum

on the principal amount of the award from the date of the suit till the date of

the awards as also from the date of the awards to the date of payment or the

date of decrees, 'whichever is earlier'.

The Arbitrator issued notice to both the parties intimating them about

passing of the awards. The Arbitrator also filed awards in the court. On 16th

September, 1995, sealed envelope of award was opened in the court.

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8

MHADA raised objection against the awards under Section 30 of the Act,

vide objections (Ex. 62 and 66) on October 13, 1995. RCC filed its

objections (Ex. 63 and 67) on October 16, 1995 to the applications of

MHADA. On the same day, RCC filed applications (Exs. 64 and 68) under

Section 17 of the Act for making awards of the Arbitrator as rule of the court

by pronouncing judgment. By final order dated April 25, 1996, the Civil

Judge, (Senior Division), Aurangabad made Arbitrator's awards as "rule of

court". He also passed an order to draw up decrees accordingly.

Against the above judgment of the Civil Court, MHADA filed two

First Appeals. The Division Bench of the High Court, by the judgment

impugned in the present appeals, allowed those appeals, set aside the order

passed by the trial court and remitted arbitration proceedings to the sole

arbitrator to pass fresh awards. According to the High Court, the awards

passed by the sole Arbitrator were not speaking awards and, therefore, could

not be said to be in accordance with law. The High Court concluded that the

awards were vitiated under Section 30 of the Act.

The Court observed :

"We are, therefore, of the view that the award of

the sole arbitrator which has been made rule of the court

by the trial court is unsustainable on the ground that it

suffers from errors apparent on the face of the record

and the sole arbitrator misdirected the proceedings, in as

much as, he was required to adjudicate upon the issues

framed by the trial court and give reasons thereof in

respect of the claims allowed by him. In addition, the

directions to pay interest at 18% per annum for the post-

pendente lite period are not supported by any reasons,

howsoever short they may be, and therefore, the said

directions are also unsustainable. We, therefore, deem it

appropriate to remit the arbitration proceedings to the

sole arbitrator for fresh award and thereupon the trial

court would examine the same for its decision under

Section 21 of the Act.

In the result, the appeals are allowed and the

decrees passed by the trial court in Special Civil Suit Nos.

265 and 266 of 1991 are hereby quashed and set aside.

The arbitration proceedings initiated pursuant to the order

passed by the trial court are restored to the sole arbitrator

Shri S.R. Wadekar. He shall pass a fresh award within a

period of 60 days from the date of appearance of the

parties before him. The parties shall appear before the

sole arbitrator on1 16.6.2003. No order as to costs."

The above judgment is challenged by RCC in the present appeals.

We have heard learned counsel for the parties.

The learned counsel for RCC submitted that the High Court has

committed an error of law in interfering with the order passed by the trial

court and in setting aside the award made by the sole Arbitrator on the

ground that the awards were not 'speaking' awards. The learned counsel

submitted that the High Court was wrong in holding that an award passed by

the Arbitrator must be a reasoned one. According to the counsel, under the

Arbitration Act, 1940 (hereinafter referred to as 'the old Act'), there was no

obligation on the Arbitrator to record reasons. He further submitted that

admittedly the proceedings were governed by the old Act and the Arbitration

and Conciliation Act, 1996, (hereinafter referred to as 'the new Act'), has no

application and the provisions of the new Act could not be pressed into

service by MHADA. Since it was not necessary for the Arbitrator to record

reasons under the old Act and as there was no agreement between the parties

nor the contract provided for recording of reasons by the Arbitrator, he was

under no obligation to make reasoned awards. Setting aside of award by the

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8

High Court, therefore, was contrary to law. It was submitted that the

Arbitrator followed the requisite procedure under the old Act. He conducted

the proceedings by calling the parties and by affording opportunity of

hearing to them. He also visited the construction-site. He perused the

material documents, pleadings of the parties, relevant record and having

applied his mind, passed awards which were in conformity with law. The

counsel also submitted that the trial court before which the awards were

produced to make them rule of the court, again considered the objections

raised by MHADA. It negatived the objections and by detailed judgment,

the awards were made rule of the court. The Court also ordered to draw

decrees in terms of awards. In the circumstances, there was no reason for

the High Court to interfere with the awards passed by the sole Arbitrator as

also the judgment and order passed by the trial court. The order passed by

the High Court, therefore, deserves to be quashed and set aside.

The learned counsel for the respondent MHADA, on the other hand,

supported the order passed by the High Court. He submitted that since there

was dispute between the parties, RCC had approached Civil Court by filing

two civil suits. In those suits, written statements were filed by MHADA

raising several objections against maintainability of the claim and also the

amount demanded by RCC. On the basis of pleadings of the parties, issues

were framed and thereafter an application was made by RCC to refer the

matter to sole Arbitrator. In the light of the facts and attending

circumstances, it was clear that the Arbitrator was a "substituted forum". It

was, therefore, incumbent on him to apply his mind to the rival contentions

of the parties, to consider the issues framed by the trial court and to record

findings on those issues supported by reasons and to make awards. Since

the Arbitrator had totally overlooked those aspects and the facts and

circumstances in which the matters were referred to him, the awards suffer

from non-application of mind and the trial court was wrong in making such

awards rule of the court and by directing to draw up decrees on the basis of

the awards. The High Court was fully justified in setting aside such awards

and also the judgment and order of the trial court by remitting the matter to

the sole Arbitrator to decide the same in accordance with law. It was also

submitted that even if there was no clause in the contract or agreement

providing for recording of reasons, since the Arbitrator was to decide the

question and to adjudicate the matter, he ought to have recorded reasons in

support of such decision, finding and adjudication. The counsel, therefore,

submitted that no case for interference with the order passed by the High

Court has been made out and the appeals deserve to be dismissed.

Having given anxious and thoughtful consideration to the rival

contentions of the parties, in our opinion, the appeals deserve to be allowed

partly. The main question, according to us, is as to whether the sole

Arbitrator was required to record reasons in support of the awards made by

him. If that was the duty on the part of the Arbitrator, the contention of

MHADA must be upheld by holding that the order passed by the High Court

was in accordance with law and no fault can be found against the decision.

If, on the other hand, there was no such requirement of law and Arbitrator

was not bound to record reasons in support of the awards, they could not

have been set aside 'merely' on the ground of non-recording of reasons and

the High Court ought not to have interfered with the said awards and set

them aside reversing the judgment and order passed by the trial court.

The learned counsel for RCC drew our attention to the relevant case

law on the point. We would refer to only few of them. Raipur Development

Authority & Others vs. M/s. Chokhamal Contractors & others, (1989) 2

SCC 721 is indeed the leading decision of this Court on the point. A

Constitution Bench of this Court was called upon to consider an identical

issue which has been raised before us, i.e. whether an award passed under

the (old) Act was liable to be set aside under Section 30 or to be remitted

under Section 16 of the Act "merely" on the ground that no reasons had been

recorded by the Arbitrator in support of the award.

After considering the relevant provisions of law, legal position in

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8

England, America and Australia and after referring to leading decisions on

the point, this Court held that an award passed under the (old) Act was not

liable to be set aside or remitted only on the ground that no reasons had been

recorded in support of such award. The Court also referred to the Hand Book

of Arbitration Practice by Ronald Bernstein wherein it was stated' "The

absence of reasons does not invalidate an award. In many arbitrations the

parties want a speedy decision from a tribunal whose standing and integrity

they respect, and they are content to have an answer Yes or No; or a figure

of X. Such an award is wholly effective; indeed, in that it cannot be

appealed as being wrong in law it may be said to be more effective than a

reasoned award." (emphasis supplied)

The Court then proceeded to state;

"It is now well settled that an award can neither be

remitted nor set aside merely on the ground that it

does not contain reasons in support of the conclusion

or decisions reached in it except where the

arbitration agreement or the deed of submission

requires him to give reasons. The arbitrator or

umpire is under no obligation to give reasons in

support of the decision reached by him unless under

the arbitration agreement or in the deed of

submission he is required to give such reasons and if

the arbitrator or umpire chooses to give reasons in

support of his decision it is open to the court to set

aside the award if it finds that an error of law has

been committed by the arbitrator or umpire on the

face of the record on going through such reasons.

The arbitrator or umpire shall have to give reasons

also where the court has directed in any order such

as the one made under Section 20 or Section 21 or

Section 34 of the Act that reasons should be given or

where the statute which governs an arbitration

requires him to do so."

In the opinion of this Court, it could not be disputed that in India, it

has been 'firmly established' that it was not obligatory on the Arbitrator or

Umpire to record reasons in support of the award when "neither any

arbitration agreement nor any deed of submission" required reasons to be

recorded. In that case also, it was urged, as has been done in the instant

case, that if no reasons are disclosed by the Arbitrator, it would not be

possible for the court to find out whether the award passed is in accordance

with law. The Court, however, negatived the contention observing that if the

parties wanted reasons to be recorded in support of the award to be passed

by Arbitrator or Umpire it was open to them to make a provision in the

agreement/contract itself to that effect. But in the absence of any stipulation

in the contract, the court could not say that Arbitrator was duty bound to

record reasons and if reasons are not recorded in support of the award, the

award was vulnerable and liable to be set aside or should be remitted to the

Arbitrator. According to this court, such an order would amount to virtually

introducing by judicial verdict an amendment to the Act. No doubt, if the

reasons are recorded by the Arbitrator or Umpire in support of the award,

they can be considered by the court and if those reasons disclose an error

apparent on the face of the record, the award can be set aside by a competent

court of law. But in the absence of such requirement under the agreement

itself, the party could not insist for reasons in support of the award nor a

court of law can interfere with non speaking award.

It was, however, urged that recording of reasons in support of the

order is part and parcel of 'natural justice' and on that count also,

unreasoned award should be treated as null and void and ineffective. We are

unable to uphold the argument. A similar contention was raised in

Chokhamal and negatived by this Court observing that the

said doctrine applies to Administrative Law field. In the decisions

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8

pertaining to Administrative Law, this Court has always insisted

for recording of reasons in support of the order or decision.

The Court observed that it would apply to "public law" field and not to

"private law" field like Arbitration agreement.

The Court stated:

"It is no doubt true that in the decisions pertaining to

Administrative Law, this Court in some cases has observed

that the giving of reasons in an administrative decision is

rule of natural justice by an extension of the prevailing rule.

It would be in the interest of the world of commerce that the

said rule is confined to the area of Administrative Law. We

do not appreciate the contention, urged on behalf of the

parties who contend that it should be made obligatory on the

part of the arbitrator to give reasons for the award, that there

is no justification to leave the small area covered by the law

of arbitration out of the general rule that the decision of every

judicial and quasi-judicial body should be supported by

reasons. But at the same time it has to be borne in mind that

what applies generally to settlement of disputes by

authorities governed by public law need not be extended to

all cases arising under private law such as those arising

under the law of arbitration which is intended for settlement

of private disputes." (emphasis supplied)

This Court noted that a consistent view has been taken by all courts

that an award was not liable to be set aside merely because reasons were not

given except where the arbitration agreement or the deed of submission or

an order made by the court under Sections 20, 21 or 34 of the Act or the

statute governing the arbitration required the Arbitrator or Umpire to give

reasons for the award.

In our opinion, the ratio in Chokhamal applies to the case on hand.

The law laid down in that case has been reiterated by this Court in many

cases. [See T.N. Electricity Board v. Bridge Tunnel Construction & Others,

(1997) 4 SCC 121, Kundale & Associates v. Konkan Hotels (P) Ltd., (1999)

3 SCC 533, Build India Construction System v. Union of India, (2002) 5

SCC 433].

In T.N. Electricity Board, this Court considered the old Act as well as

new Act and particularly sub-section (3) of Section 31 of the new Act which

provides for recording of reasons by Arbitrator in support of the award

unless (a) the parties have agreed that no reasons are to be given, or (b) the

award is an arbitral award on agreed terms under Section 30. The Court

noted that Parliament had expressed the legislative judgment that the award

must state reasons upon which it is passed unless the parties have agreed

otherwise or the award is on agreed terms.

The present awards are not under the new Act but under the old Act.

It is, therefore, obvious that they could not have been set aside by the High

Court on the ground that they were not supported by reasons and were not

speaking awards.

The learned counsel for the respondent invited our attention to a

decision of this Court in State of Punjab vs. Bhag Singh, (2004) 1 SCC 547

and contended that this Court has held that reasons must be recorded in

support of the order. That was a case wherein the High Court dismissed an

appeal against an order of acquittal without recording reasons. The State

approached this Court. Reversing the order passed by the High Court, this

Court held that in an appeal against acquittal recorded by the Sessions Court,

the High Court must record reasons as the High Court was obliged to

undertake the exercise by application of mind and coming to the conclusion

that an order of acquittal recorded by the trial court was or was not in

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8

accordance with law. The ratio laid down in Bhag Singh, in our opinion,

does not apply to the facts of the present case.

The counsel relied upon the observations of Lord Denning, M.R. in

Breen v. Amalagamated Engineering Union, (1971) 1 All ER 1148. There

His Lordship observed; "The giving of reasons is one of the fundamentals of

good administration". Reference was also made to Alexander Machinery

(Dedley) Ltd. v. Crabtree, 1974 ICR 120, wherein it was indicated that

failure to give reasons amounts to denial of justice. Reasons are live links

between the mind of the decision maker to the controversy in question and

the decision or conclusion arrived at by him. Reasons substitute subjectivity

by objectivity. The emphasis on recording reasons is that if the decision

reveals the inscrutable face of the sphinx, it can by its silence render it

virtually impossible for the courts to perform their appellate function or

exercise the power of judicial review in adjudging the validity of the

decision.

As already observed by us, all these principles apply to

Administrative Law and in the public law field. They would not get

attracted in the field of private law. The court, in such matters, does not

exercise appellate jurisdiction and cannot substitute its decision for the

decision of the Arbitrator. Those principles, therefore, have no place when

one is considering the legality of an award made by an Arbitrator with the

consent of parties, which is otherwise legal and valid.

The learned counsel also placed reliance on a decision of this Court in

Gora Lal v. Union of India, (2003) 12 SCC 459. The Court in that case held

that when the Arbitrator was to give his findings, it was obligatory on him to

record reasons. In Gora Mal, the relevant clause of arbitration was as

under;

"The arbitrator shall be deemed to have entered on the

reference on the date he issues notice to both the parties,

asking them to submit to him their statement of case and

pleadings in defence.

The arbitrator may, from time to time, with the consent

of the parties, enlarge the time up to but not exceeding one

year from the date of his entering on the reference, for

making and publishing the award.

The arbitrator shall give his award within a period of six

months from the date of his entering on the reference or

within the extended time as the case may be on all matters

referred to him and shall indicate his findings, along with the

sums awarded, separately on each individual item of the

dispute."

Observing that the word 'findings' denotes 'reasons' in support of the

conclusion 'on each item of dispute', the Court held that the Arbitrator was

required to record reasons in support of his findings. The Court, however,

added; "We make it clear that this order is confined to the facts of this case

and our interpretation is confined to clause 70 of the arbitration agreement in

this case". Gora Lal thus was decided in the fact-situation before the Court

and the relevant clause in the agreement and the ratio of that case cannot

make the awards in the present case illegal or unlawful in absence of a

similar clause.

For the foregoing reasons, the awards passed by the sole Arbitrator

cannot be held illegal or unlawful. In making such awards the rule of the

court, the Court of Civil Judge, (Senior Division), Aurangabad had not

committed any illegality which vitiated the awards and the High Court could

not have set aside them.

The question then remains as to interest. The appellant had claimed

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8

interest in the suits. The Arbitrator awarded interest at the rate of 18 per

cent per annum on the principal amount from the date of the suits to the date

of awards and also from the date of the awards to the date of payment or up

to the date of decrees, 'whichever is earlier'. This Court has dealt with the

power of Arbitrator to award interest for (i) pre-reference period [Executive

Engineer, Dhenkanal Minor Irrigation Division & Others v. N.C. Budhraj

(Deceased) by LRs & Others (2001) 2 SCC 721]; (ii) pendente lite

[Secretary, Irrigation Department, Government of Orissa & Others v. G.C.

Roy (1992) 1 SCC 508]; and (iii) post-award period [Hindustan

Construction Co. Ltd. v. State of Jammu & Kashmir, (1992) 4 SCC 217]. In

Bhagwati Oxygen Ltd. v. Hindustan Copper Ltd., AIR 2005 SC 2071 : JT

(2005) 4 SC 73, one of us (C.K. Thakker, J.) had an occasion to consider the

relevant decisions on the power of Arbitrator to award interest at all the three

stages. It was held that the arbitrator had power to award interest. Keeping

in view the facts and circumstances of the present case that the contract was

entered into in 1987, the work was completed in 1990 after extension

granted by MHADA and the Arbitrator passed awards in 1995, it would be

proper, equitable and in the interest of justice if we reduce the rate of interest

to 10 per cent per annum.

For the foregoing reasons, in our opinion, the order passed by the

High Court deserves to be interfered with by partly allowing the appeals.

We, therefore, allow the appeals in part confirming the awards made by the

Arbitrator. We, however, direct the respondent MHADA to pay interest at

the rate of 10 per cent per annum instead of 18 per cent per annum as

awarded by the Arbitrator. The other directions in the awards are hereby

confirmed. The appeals are allowed to the extent indicated above. There

shall be no order as to costs.

Reference cases

Description

Legal Notes

Add a Note....