Ramachandra Reddy and Co. Vs. State of andhra Pradesh and Ors.

  Supreme Court Of India Civil Appeal /9405/1995
Link copied!

Case Background

As per case facts, a contractor undertook excavation work for the Srisailam Project. An arbitration award rejected some claims and partly allowed others, including interest. Dissatisfied with the rejection of ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7

CASE NO.:

Appeal (civil) 9405 of 1995.

PETITIONER:

RAMACHANDRA REDDY & CO.

Vs.

RESPONDENT:

STATE OF A.P. & ORS.

DATE OF JUDGMENT: 27/02/2001

BENCH:

U.C.Banerjee, Brijesh Kumar, G.B.Pattanaik

JUDGMENT:

PATTANAIK,J.

L.....I.........T.......T.......T.......T.......T.......T..J

Claimants are the appellants against the judgment of

the Andhra Pradesh High Court, arising out of an arbitration

proceeding. The North work excavation of approach channel

of Srisailam Project had been awarded to the claimants for

different amounts indicated in the contract. The contract

itself contained an arbitration clause. Dispute being

raised on different items of claim, those disputes had been

referred to a panel of arbitrators and the panel of

arbitrators, ultimately passed an award where-under claim

Items 1, 2 and 3 stood rejected. So far as claim item No.

4 is concerned, the same was allowed in part. Claim Item

No. 5 was claim of interest and the arbitrators allowed the

interest @ 12 per cent per annum over the amount awarded.

Claim Item No. 6 was the claim of cost and the arbitrators

directed that each party will bear its own cost. Against

the award of the arbitrators, rejecting claim item Nos. 1,

2 and 3, the claimants filed an objection in the Civil Court

and sought for remittance under Section 16 on the ground

that the arbitrators have left undetermined the claims of

the claimants on item No.1, 2 and 3 on an erroneous view of

the relevant clauses of the agreement. Claimants also filed

an application under Section 14 to make the award in

relation to claim allowed by the arbitrators as a rule of

Court. The State of Andhra Pradesh also filed a petition

under Section 30 of the Arbitration Act to set aside that

part of the award which allowed the claim of the contractor

to the extent of Rs.57,000/-. All these applications which

were registered as O.S. No. 1094/86, O.P.104/87 and

O.P.424/87 were disposed of by a common judgment of the

learned Vth Additional Judge, City Civil Court, Hyderabad.

The said learned Judge made the award in relation to claim

item No.4 a rule of Court. But he set aside the award in

relation to claim item Nos. 1,2,3 and 5and remitted the

same for reconsideration to the panel of arbitrators.

Against the aforesaid Judgment of the Additional Judge, City

Civil Court, remitting the disputes/claims in relation to

claim items 1, 2, 3 and 5 to the panel of arbitrators, the

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7

State of Andhra Pradesh preferred appeals under Section 39

of the Arbitration Act. The High Court by the impugned

judgment set aside the order of the Additional Judge, so far

it relates to remitting the claim item No. 1 to the panel

of arbitrators for reconsideration. So far as claim item

Nos. 2 and 3 are concerned, the High Court upheld the

direction of the Additional Judge, but, appointed a retired

Chief Justice of the Court as arbitrator to arbitrate the

claim items 2 and 3 and a part of claim item No. 5 relating

to interest. In this appeal filed by the claimants, we are

concerned only with claim item No.1. The legality of the

award in relation to claim items 2 and 3 are the subject

matter of an appeal, which is pending in this Court.

Claim Item No. 1 relates to increase in quantity of

hard rock abnormally and on this head, the claimants had

claimed Rs.93, 76, 990/-. The claimants statement that was

filed before the arbitrator, makes out a vague claim on this

score without indicating the basis for the claim in

question. In respect of the aforesaid quantity of extra

excavation on hard rock, the State of Andhra Pradesh had

made the payment in terms of Clause 25 of Schedule C of

Section 2 of the agreement as per its letter dated 21st

October, 1981. Notwithstanding the said payment, the

claimants had made the extra claim on the ground that the

quantity of excavation of hard rock being abnormally high

and much beyond the anticipated quantity indicated in the

agreement and even much in excess of the so-called 25 per

cent of the work as per the GOMS No. 2289 dated 12.6.1968,

the claimants are entitled to a separate rate for such extra

excavation and the arbitrators failed to exercise their

jurisdiction in not granting the claim and on the other

hand, rejecting the same. The High Court in the impugned

judgment however, referring to clause 59 of the agreement,

which deals with delay and extension of time and in view of

the letters of the Superintending Engineer dated 15th July,

1980 and 19th May, 1983, came to hold that the

contractor-claimant will not be entitled to be paid at any

higher rate for such additional excavation work and

accordingly set aside the order of the learned trial Judge,

remitting the claim item No. 1 for being re-disposed of by

the arbitrator.

Mr. P.P.Rao, the learned senior counsel, appearing

for the appellant, contended that the High Court committed

serious error in referring to clause 59 as well as to the

letter dated 15th July, 1980 and 19th May, 1983, in coming

to the conclusion that the claimant-contractor will not be

entitled to be paid at any higher rate for the extra amount

of excavation made by him. Mr. Rao further submitted that

under GOMS No. 2289 dated 12.6.1968, a deviation limit upto

a maximum of 25 per cent being permissible, for any work in

excess of that limit, the contractor is entitled to claim a

higher rate and that being the position, the arbitrators had

committed an error apparent on the award in refusing the

claim and the High Court committed error in setting aside

the order of remittance passed by the Additional Judge. In

support of this contention, reliance was placed on the

judgment of this Court in the case of S. Harcharan Singh

vs. Union of India, 1990(4) SCC 647. Mr. Rao also further

urged that in view of the recommendations of the Executive

Engineer notwithstanding the continued objection of the

claimant, expressing inability to continue with the abnormal

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7

increase in the hard rock excavation, it must be held that

the payment at a higher rate for the additional or excess

quantity of excavation was implied and failure on the part

of the arbitrator to consider the same, constitutes an error

on the face of the award and as such the learned Additional

Judge was justified in remitting the matter for

reconsideration of the arbitrator. Mr. Rao lastly

submitted that for this excess of excavation work, the

contractor was entitled to be paid in accordance with Clause

63 of the agreement, which has not been noticed by the

arbitrator and adjudged from that stand point, the High

Court also committed error in setting aside the order of

remittance made by the learned Additional Judge.

Ms. K. Amreswari, appearing for the respondent State

of Andhra Pradesh, on the other hand contended that the

power of interference of the Court under Sections 30 and 33

as well as under Section 16 is of a limited nature and the

Court would be justified in interfering with the reasoned

award of an arbitrator, if the award contains any apparent

error on the same. If the impugned award is examined from

the aforesaid stand point, the conclusion is irresistible

that it did not contain any error and, therefore, the

interference of the Court was not warranted. Ms. Amreswari

further contended that the claimants nowhere in the claim

petition had made out a case that for the additional

quantity of excavation work, they are entitled to the rate

as per clause 63 of the agreement which was urged for the

first time in this Court and, therefore, the said contention

should not be allowed to be raised. Ms. Amreswari further

urged that clause 63 will have no application for the extra

item of excavation made by the contractors since that clause

applies to any supplemental item, which are found essential,

incidental and inevitable during the execution of the work

and by no stretch of imagination, the additional excavation

which is the subject matter of claim in claim item No. 1

can be held to be supplemental item. Ms. Amreswari further

submitted that for this additional quantity of excavation

the claimant having been paid for in accordance with clause

25 of the agreement, the further claim of the contractor is

not arbitrable at all and, High Court therefore was fully

justified in setting aside the order of remittance made by

the Additional Judge. Ms. Amreswari further contended that

the claim for payment of higher rate for the work done

beyond the agreement is not at all sustainable in view of

the positive letter of the authorities dated 15th July, 1980

and 19th May, 1983, while allowing extension of time for

completion of the work, as has been held by this Court in

the case of Ch.Ramalinga Reddy vs. Superintending Engineer

and Anr. 1999(9) SCC 610, and, therefore, the High Court

was fully justified in interfering with the directions of

the sub- ordinate Judge in remitting the said claim item

No.1 for fresh arbitration. Mrs. Amreswari lastly

submitted that a bare scrutiny of the order of the Vth

Additional Judge, City Civil Court, Hyderabad, remitting

claim items Nos. 1, 2 and 3 for reconsideration would

indicate that no reasons had been given for such remittance

and on the face of it, the said judgment of the Civil Court

tantamounts to gross error of jurisdiction in interfering

with an award and transgressing the scope and limitation

provided under Sections 30 and 16 and, therefore, the High

Court was justified in correcting the said error in appeal.

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7

Under the Arbitration Act, Section 16 is the provision

under which the Court may remit the award for

reconsideration of an arbitration and necessity for

remitting the award arises when there are omissions and

defects in the award, which cannot be modified or corrected.

Remission of an award is in the discretion of the Court and

the powers of the Court are circumscribed by the provisions

of Section 16 itself. Ordinarily, therefore, a Court may be

justified in remitting the matter if the arbitrator leaves

any of the matters undetermined or a part of the matter

which had not been referred to and answered and that part

cannot be separated from the remaining part, without

affecting the decision on the matter, which was referred to

arbitration or the award is so indefinite as to incapable of

execution or that the award is erroneous on the face of it.

Discretion having been conferred on the Court, to remit an

award, the said discretion has to be judicially exercised

and an appellate Court would not be justified in interfering

with the exercise of discretion unless the discretion has

been misused. What is an error apparent on the face of an

award which requires to be corrected has always been a

subject matter of discussion. An error of law on the face

of the award would mean that one can find in the award or a

document actually incorporated thereto stating the reasons

for a judgment some legal propositions which is the basis of

the award and which can be said to be erroneous. Documents

not incorporated directly or indirectly into the award

cannot be looked into for the purpose of finding out any

alleged error. The courts are not to investigate beyond the

award of the arbitrators and the documents actually

incorporated therein and, therefore, when there would be no

patent error on the face of the award, it would not be open

for the court to go into the proceedings of the award. If

the application for remittance filed by the claimants

invoking jurisdiction of the court under Section 16 is

examined from the aforesaid stand point and if the order of

the learned Civil Court, remitting claim Item No. 1 is

tested in the light of the discussions made above, the

conclusion is irresistible that no case for remittance had

been made out and the learned trial Judge exercised his

discretion on the grounds which does not come within the

four-corners of the provisions of Section 16 of the

Arbitration Act. In fact no reasons had been ascribed for

interference with the award, rejecting claim Item No. 1 and

for remittance of the same. The High Court being the Court

of appeal, was therefore, fully justified in exercise of its

appellate power in correcting the error made by the Civil

Judge in remitting claim item No. 1.

Let us now examine the contentions of Mr. P.P.Rao,

the learned senior counsel, appearing for the appellant.

The learned counsels contention in fact centres round the

question as to whether for the additional quantity of

excavation work, the contractor would be entitled to at a

higher rate in accordance with Clause 63 of the agreement.

Mrs. Amreswari, appearing for the State was fully justified

in her submissions that this contention had never been

raised either before the arbitrator or before the

subordinate Judge or even before the High Court. In fact

the claim petition filed before the arbitrator is rather

cryptic and absolutely vague, not indicating on what basis

the additional claim is made, though the foundation for the

claim was there, namely there had been an increased amount

of excavation work beyond the agreement. It is in this

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7

connection, Mr. Rao had relied upon the two decisions of

this Court in the case of S.Harcharan Singh vs. Union of

India, 1990(4) SCC 647 and National Fertilizers vs. Puran

Chand Nangia 2000(8) SCC 343. But before examining the said

contention, it would be appropriate for us to extract Clause

63, which was the sheet anchor of the argument of Mr. Rao.

Clause 63 reads as under:

Cl.63. Payment for additions and deductions for

omissions: (A) The contractor is bound to execute all

supplemental items that are found essential, incidental and

inevitable during the execution of the work, at the rates to

be worked out as detailed below: (a)For all items of work

in excess of the quantities shown in schedule A of the

tender the rates payable for such items shall be either the

tender rates or the standard schedule of rates for the items

plus or minus the overall tender percentage accepted by the

competent authority which ever is less. (b)For items

directly deducible from similar items in the agreement, the

rates shall be derived by adding to or substracting from the

agreement rate of such similar items, the cost of difference

in quantity of material or labour between the new items and

the similar items in the agreement, worked out with

reference to the Schedule of rates adopted in the sanctioned

estimate plus or minus the overall tender percentage.

(c)For new items which do not correspond to any items in the

agreement, the rates shall be standard schedule rate plus or

minus the over all tender percentage. The terms standard

schedule of rates used in the above subclauses (a), (b) &

(c) means the schedule of rates on which the sanctioned

estimate was prepared. (d)In the event of the Executive

Engineer and the Contractor failing to agree on a rate for

such additional work, the Executive Engineer may, at his

option either: (i)employ other parties to carry out the

additional work in the same manner as provided for under

clause 48, or (ii)the contractor shall execute the work upon

written orders from the Executive Engineer and the cost of

labour and materials plus 10 per cent thereon shall be

allowed therefor, provided that the vouchers for the labour

and materials employed shall have been delivered to the

Executive Engineer or his representative within seven days

after such work shall have been completed. If the Executive

Engineer considers that payment for such work on the basis

of the vouchers presented is unduly high, he shall make

payment in accordance with such valuation as he considers

fair and reasonable and his decision to the matter shall be

final, if the amount involved in additional payment is

Rs.1000 or less, for each occasion on which such additional

works shall have been authorised. If such amount exceeds

Rs.1000, the contractor shall have the right to submit the

matter to arbitration under the provisions of the

arbitration clause 73. (e)If, in the opinion of the

Executive Engineer a rate for the additional work is not

capable of being properly arrived at prior to execution of

work, or if the work is not capable of being properly

measured, then the cost and payment thereof shall be dealt

with as provided for in the preceding sub- clause (d)(ii).

In the case of S. Harcharan Singh vs. Union of

India, 1990(4) SCC 647, on which Mr. Rao had strongly

relied upon, this Court had quoted clause 12 of the

agreement in paragraph 8 of the judgment and referring to

the standard form of contract of the Central Public Works

Department, specifically permitting for a limit of variation

called deviation limit up to a maximum of 20 per cent, it

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7

was held that the contractor has to carry out the work at

the rate stipulated in the contract upto such limit but for

work in excess of that limit he has to be paid at the rates

to be determined in accordance with clause 12A, under which

the Engineer in-charge can revise the rates, having regard

to the prevailing market rates. The Court also referred to

the letters of the Executive Engineers, the Superintending

Engineer and the Additional Chief Engineer recommending that

the additional work may be confined to 20 per cent and for

the extra quantity of additional work, he may be paid

remuneration at the increased rate taking into account the

increased cost of the execution of work on account of

peculiar nature of the work. We fail to understand how the

aforesaid decision will be of any assistance to the claimant

in the present case, where there is no clause like Clause

12A nor is there any letter from the competent authority

agreeing to payment at a higher rate for the additional work

beyond the limit of 25 per cent as provided under the GOMS

No.2289 dated 12.6.1968. Arbitrator being a creature of the

agreement, unless agreement either specifically or

inferentially provides for a higher rate to be awarded for

any additional or excess work done by the contractor, it

would not be permissible for the arbitrator to award for the

so-called additional work at a higher rate. In the case in

hand, not only there is no letter from the competent

authority, namely the Superintending Engineer that the

contractor would be paid at any higher rate for the

additional excavation of rock, though the Executive Engineer

had indicated that he has recommended to the Superintending

Engineer. But such recommendation of the Executive

Engineer, who was not competent to decide the question of

awarding a higher rate for the excess quantity of excavation

will not clothe any jurisdiction on the arbitrator to award

the contractor at a higher rate nor would it entitle the

contractor to get a higher rate for the claim in question on

the basis of agreement. Now coming to the very clause, upon

which Mr. Rao relied upon, we find that the said clause

relates to supplemental item, which have been found

essential, incidental and inevitable during the execution of

the work. The excavation of hard rock cannot be held to be

a supplemental item and on the other hand, is an item of

work tendered and accepted, and as such clause 63 will have

no application to the claim item No.1. Mr. Rao had also

relied upon the decision of this Court in National

Fertilizers vs. Puran Chand Nangia, 2000(8) SCC 343,

wherein this Court had held that an interpretation of a

particular clause of the agreement must be such, so as to

balance the rights of both parties and when a variation

clause permits the employer to make variation in the work

upto a specified limit, beyond the said limit, the claimant

could be paid at a higher rate. The Court in the aforesaid

case was examining the principle of integrity of the

contract and refused to interfere with the award merely

because arbitrator had granted an escalation. In the

aforesaid case, the Court was examining whether it would be

permissible for interfering with an award which was a

non-speaking one merely because the arbitrator had awarded

the claim at an escalated rate for the excess quantity of

work and since the award itself was a non-speaking award,

the court held that it is not permissible to probe into the

mental process of the arbitrator and then interfered with

the same. Then again the question of granting a higher rate

for any extra quantity of work executed by the contractor

would at all arise only when the contract provides for such

escalated rate either expressly or by implication as in the

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7

case of S. Harcharan Singh 1990(4) SCC 647, where the

competent authority had agreed for the same by

correspondence. But in the case in hand, when there is no

such acceptance by the competent authority, and there is no

provision in the contract, permitting such escalated rate

for the additional quantity of excavation made and in view

of our rejecting the contention raised on the basis of

clause 63, the conclusion is irresistible that the

contractor will not be entitled to a higher rate for the

additional excavation work and as such the High Court was

fully justified in setting aside the direction of the trial

judge, remitting the claim item No. 1 for reconsideration

and we see no infirmity with the said direction of the High

Court to be interfered with. We also find sufficient force

in the submission of Mrs. Amreswari, relying upon the

letters of the competent authority, specifically intimating

that the grant of extension of time will not in any way make

the contractor eligible for any extra claim due to

escalation in rates of labour and materials or due to any

other reasons under any circumstances and the decision of

this Court in Ramalinga Reddy, 1999(9) SCC 610 supports the

aforesaid contention. In the aforesaid premises, we do not

find any merits in this appeal, requiring our interference

with the impugned judgment of the High Court. The appeal

fails and is

dismissed but in the circumstances there will be no

order as to costs.

Reference cases

Description

Legal Notes

Add a Note....

Advance Search Tool

💡 How to Get the Best Legal Answers:

1. Keep it simple: Frame your question in plain language.

2. Add scope: Tag @ a court, judge, year, or act section for accurate results.

3. Attach files: Upload a PDF only if you are using a private document.

🌍 Ask in your language: English • Hindi • Assamese • Bangla • Gujarati • Kannada • Malayalam • Marathi • Odia • Punjabi • Tamil • Telugu • Urdu


💡 New Advocate? Don’t worry! Working without senior support today? Turn on Client Advisory to get instant legal strategies, practical angles, and precedent-backed options for your client.

Add research context Type to filter