As per case facts, the petitioner applied for a loan under the MKUY scheme for a layer farming project. A loan was sanctioned, and a go-ahead letter was issued. However, ...
WP(C) No.16506 of 2025 Page 1 of 18
ORISSA HIGH COURT : CUTTACK
WP(C) No.16506 of 2025
An application under Articles 226 & 227 of the Constitution of
India.
***
Ramesh Chandra Panda
… Petitioner.
-VERSUS-
State of Odisha & Others
… Opposite Parties.
Counsel appeared for the parties:
For the Petitioner : Mr. B. Jalli, Advocate
For the Opposite Parties : Mrs. U. Padhi, Addl. Standing Counsel.
Mr. K. Jena, Adv. (For O.P. No.6)
P R E S E N T:
HONOURABLE
MR. JUSTICE ANANDA CHANDRA BEHERA
WP(C) No.16506 of 2025 Page 2 of 18
Date of Hearing : 15.01.2026 :: Date of Judgment : 28.01.2026
JUDGMENT
ANANDA CHANDRA BEHERA, J.—
1. This writ petition under Articles 226 and 227 of the
Constitution of India, 1950 has been filed by the petitioner
praying for quashing the Letter/Order dated 16.04.2025
under Annexure-3 issued/passed by the Opp. Party No.6 (The
Managing Director Agriculture Promotion & Investment
Cooperation of Odisha i.e. APICOL) and to direct the Opp.
Parties including the Opp. Party No.6 for releasing the subsidy
of 40% of the project cost (fixed capital) limited to
Rs.50,00,000/- (rupees fifty lakhs only).
2. The factual backgrounds of this writ petition which
prompted the petitioner for filing of the same is that, on being
alured by the scheme/yojana of “Mukhyamantri Krushi
Udyog Yojana” (MKUY) published through the Notification of
the Government, Department of Agriculture & Farmers’
empowerment to ease of doing Agri-business with simple,
transparent, online and time bound implementation of the
said Yojana for the larger interest of the agri-entrepreneurs of
WP(C) No.16506 of 2025 Page 3 of 18
the State, the petitioner being an agriculturist applied for
establishing a layer farming of 30,000 bird capacity in his
landed properties in Mouza-Dimiria under Khalikote Police
Station in the District of Ganjam in the name of its project as
Maa Tarini Poultries Private Limited and made an application
for the sanction of loan for his such project as per MKUY
Scheme/Yojana and after considering his application and on
fulfilment of all the criterias of such Scheme/Yojana, a loan of
Rs.1,80,00,000/- was sanctioned by the Opp. Party No.3 (The
Chief District Veterinary Officer-Cum-Nodal Officer MKUY
(ARD), Ganjam) in favour of the petitioner towards the above
project cost of the petitioner and the Opp. Party No.3
requested Opp. Party No.7 (The Branch Manager, Indian
Bank, Berhampur, City High School Road, Berhampur) for
releasing the said loan amount in favour of the petitioner and
accordingly, a Go-Ahead Letter vide Annexure -4 was issued
on dated 25.05.2021 by the Opp. Party No.3 in favour of the
petitioner and the Opp. Party No.3 also issued a letter vide
Annexure-5 to the Opp. Party No.7 for extending cooperation
through necessary financial support to the petitioner for the
WP(C) No.16506 of 2025 Page 4 of 18
establishment of the project of the petitioner. During that
time, Covid-19 pandemic was continuing all over the country
and the same was at its peak stage. As the “Go-Ahead Letter”
vide Annexure-4 was issued during the time of continuation of
Covid-19 Pandemic, for which, the project works of the
petitioner could not be progressed effectively for the non-
availability of man powers. So, after lifting of the lockdown
and shut down measures of Covid-19 Pandemic, the project
works of the petitioner progressed slowly. Because, soon after
the lifting of the Covid-19 pandemic, required number of man
powers were not available only for the reason that, the
persons/labourers those were affected in Covid-19, they were
not physically fit to resume their works immediately. However,
the petitioner could able to complete his project work by the
end of March 2024 and intimated the same to the Opp.
Parties. For which, on 06.05.2024, the project of the petitioner
was inspected physically by the Engineer of Indian Bank and
a report about the completion of project of the petitioner was
given on dated 07.05.2024 vide Annexure-7.
WP(C) No.16506 of 2025 Page 5 of 18
As per the guidelines of “Mukhyamantri Krushi Udyog
Yojana” (MKUY) and as per Annexure-4, the petitioner was
entitled for the subsidy of 40% of the project cost (fixed
capital) limited to Rs.50,00,000/- on completion of his above
project, but, when in spite of approach of the petitioner, the
Opp. Party No.6 did not release his subsidy of 40% amount of
the project cost (Fixed Capital) limited to Rs.50,00,000/- in
conformity with the guidelines of MKUY scheme, then, the
petitioner approached this Court by filing a writ petition vide
WP(C) No.3624 of 2025 praying for directing the Opp. Parties
including the Opp. Party No.6 (M.D of APICOL) for releasing
subsidy of 40% of the project cost (fixed capital) limited to
Rs.50,00,000/- (in words, fifty lakhs only) in favour of the
petitioner.
3. As per the final order dated 06.03.2025 passed in WP(C)
No.3624 of 2025, by this Court, liberty was granted to the
petitioner to approach the Opp. Party No.6 (M.D. of APICOL)
ventilating his all grievances through a representation for the
sanction of the above subsidy and to dispose of the said
representation of the petitioner within 2 weeks, clarifying that,
WP(C) No.16506 of 2025 Page 6 of 18
if the petitioner’s claim is found to be genuine and admissible,
necessary benefits be disbursed in his favour without any
further delay.
Accordingly, the petitioner made a representation on
dated 17.03.2025 (Annexure-2) in due time before the Opp.
Party No.6 (M.D. of APICOL) praying for releasing the subsidy
of 40% of the project cost (fixed capital) limited to
Rs.50,00,000/- stating everything in detail in his
representation.
After considering the representation dated 17.03.2025
(Annexure-2) of the petitioner, the Opp. Party No.6, as per
Order dated 16.04.2025 (Annexure-3) rejected to his
representation dated 17.03.2025 (Annexure-2) assigning the
reasons that,
“According to the Go-Ahead Letter dated 25.05.2021
(Annexure-4), the project works of the petitioner should have
been completed by 25.05.2023, but, as per the physical
verification report dated 06.05.2024, his project works have
been completed on 07.05.2024 and as his project works were
not completed within 25.05.2023 i.e. within the time period
WP(C) No.16506 of 2025 Page 7 of 18
indicated in Annexure-4, he (petitioner) is not entitled for the
subsidy of 40% of the project cost (fixed capital) limited to
Rs.50,00,000/- as per MKUY scheme as claimed by him.
The Opp. Party No.6, communicated his aforesaid order
dated 16.04.2025 (Annexure-3) to the petitioner through Letter
No.391 dated 16.04.2025.”
4. On being dissatisfied with the said order/letter dated
16.04.2025 (Annexure-3) issued/passed by the Opp. Party
No.6, the petitioner challenged the same by filing this Writ
Petition under Articles 226 and 227 of the Constitution of
India, 1950 against the Opp. Parties praying for quashing the
Letter/Order No.391 dated 16.04.2025 (Annexure-3) of the
Opp. Party No.6 and to direct the Opp. Parties including the
Opp. Party No.6 for releasing subsidy of 40% of the project
cost (fixed capital) limited to Rs.50,00,000/- in favour of the
petitioner and to pass such other writs/orders as this Court
may deem fit and proper stating in the writ petition that, due
to continuation of Covid-19 pandemic, there was some delay
in completion of the project works of the petitioner within
25.05.2023 for the non-availability of man powers
WP(C) No.16506 of 2025 Page 8 of 18
during such Covid-19 Pandemic period and the completion of
project works by the petitioner within 25.05.2023 was beyond
the control of the petitioner due to the continuation of Covid-
19 Pandemic. For which, the subsidy of 40% of the project
cost, which was declared by the Government as an incentive
for the promotion of MKUY Scheme cannot be denied
defeating the main object/purpose of such scheme
discouraging the agricultural entrepreneurs like the petitioner
causing ultimate loss and harassment to the petitioner as well
Jeopardizing/creating obstacle in the nation’s progress.
5. I have already heard from the learned counsel for the
petitioner, the learned Addl. Standing Counsel for the State
and the learned Counsel for the Opp. Party No.6.
6. The project of the petitioner i.e. M/s. Maa Tarini
Poultries Private Limited at Dimiria is a layer poultry farming
of 30,000 bird capacity, which is purely an agricultural
project.
On this aspect, the propositions of law has already been
clarified in the ratio of the following decisions:
(I) In cases between Commissioner of Income Tax,
Bangalore Vs. Venkateswara Hatcheries (P) Ltd.
WP(C) No.16506 of 2025 Page 9 of 18
and Ors. reported in (1999) 3 SCC 632 & The
Executive Engineer (Electrical) NESCO, Baripada
Electrical Division Vs. OMBUDSMAN-II,
(Electricity) and Ors. reported in 2013 (I) OLR 250
that, hatchery comes under poultry farming covered
under allied agricultural activities.
7. Here in this matter at hand, when the loan for the
project of the petitioner i.e. M/s. Maa Tarini Poultries Private
Limited was sanctioned under MKUY Agricultural Scheme of
the Government and when the petitioner is an entrepreneur of
the said agricultural scheme, then, as per the guidelines of
the MKUY scheme, it is held that, the petitioner is an
agricultural entrepreneur of the State under the MKUY
scheme.
As per the MKUY scheme, all the agri-entrepreneurs of
MKUY scheme like the petitioner shall be entitled to the
subsidy of 40% of the project cost (fixed capital) limited to
Rs.50,00,000/- but, as per Letter/Order No.391 dated
16.04.2025 vide Annexure-3, the Opp. Party No.6 has
disentitled/denied the petitioner to get the same on the
ground of non-completion of his project works within
25.05.2023.
WP(C) No.16506 of 2025 Page 10 of 18
The petitioner has specifically stated in his
representation dated 17.03.2025 vide Annexure-2 (which was
submitted on the basis of the final order dated 06.03.2025
passed by this Court in WP(C) No.3624 of 2025) that, due to
the continuation of Covid-19 pandemic, there was little delay
in completion of the project works and the project works were
completed by the end of April 2024. The aforesaid little delay
in completion of the project works by the petitioner was
neither intentional nor deliberate, but the said delay was
natural and obvious on account of Covid-19 Pandemic, which
was beyond his control.
Considering the restrictions in the movements of the
citizens all over the country during Covid-19 Pandemic, the
stipulation/limitation/target for completion of all the project
works were extended by the Supreme Court excluding the
Covid-19 Pandemic Period clarifying about the same in the
ratio of the following decisions:
(I) In Re: Cognizance for Extension Of
Limitation In Suo Motu Writ Petition (C) No.
3 Of 2020 decided in 23.03.2020 reported in
2020 (1) CLR SC 660 that, on account of
Covid-19 variant resultant difficulties that may
WP(C) No.16506 of 2025 Page 11 of 18
be faced by the litigants across the country,
period of limitation in all proceedings
irrespective of limitation prescribed under the
General Law or Special Law whether
condonable or not shall stand extended w.e.f.
from 15.03.2020 till further orders to be passed
in the present proceedings and further declared
that, the order is binding on all the
Courts/Tribunals and authorities within the
meaning of Article 141 of the Constitution of
India, 1950. In the said case i.e. In Re:
Cognizance for Extension Of Limitation In
Suo Motu Writ Petition (C) No. 3 Of 2020
decided on 10.01.2022 reported in 2022 (1)
Civ.C.C. 317 (SC) that, due to second surge in
Covid Cases, the period of extension which was
granted since 15.03.2020, the same is granted
from 15.03.2020 to till 28.02.2022 and the
period of limitation expires during such period
shall stand excluded in computing the period
of limitation.
8. As per the dictum of the Apex Court in the ratio of the
aforesaid decisions, the time period stipulated in the
Annexure-4 for starting the project works of the petitioner
since 25.05.2021, as per Go-Ahead Letter dated 25.05.2021
was extended automatically as per law up to 29.02.2022 on
the ground of restrictions in the movements of the people for
WP(C) No.16506 of 2025 Page 12 of 18
any work during that period due to natural non-availability of
man powers for Covid-19 pandemic up to 28.02.2022.
When in view of the above dictum of the Apex Court, the
project works of the petitioner should have been completed
within its two years since 29.02.2022, but, instead of which,
the project works of the petitioner have been completed by the
end of April 2024 i.e. only in delay of two months on account
of the affect of large number of persons in Covid-19 due to the
slow progress of their physical fitness to join in the works,
then, in such a situation, the slow progress of the project
work due to lack of adequate man powers soon after the over
of Covid-19 Pandemic was natural and obvious due to lack of
physical ability of the persons/labourers to work physically
soon after their recovery from Covid-19. For which, above two
months delay in completion of the project work by the
petitioner cannot be treated as his deliberate and intentional
delay in completion of the same.
9. The conclusions drawn above finds support from the
ratio of the following decisions:
(I) In cases between Naihati Jute Mills Limited Vs.
Khyalinam Jagannath reported in AIR 1968 (SC) 522 &
WP(C) No.16506 of 2025 Page 13 of 18
Satyabrata Ghosh Vs. Mugneeram Bangur & Co.
reported in AIR 1954 (SC) 44 that, impossibility of
performance may also arise where without any default of
either party, when the contractual obligation had become
incapable/impracticable of being performed, because the
circumstances in which performance was called for was
radically different from that undertaken by the contract, the
Court can take the note of the said impossibility of
performance.
(II) In a case between Syed Khursed Ali Vs. State of
Orissa & Another reported in 2006 (I) CLR 400 (Para
No.12) that, when performance of the contract on the part
of the petitioner became an impossibility and such
impossibility can be brought within the fold of “force
majeure”, because it applies to a subsequent unforeseen
event or contingency, for which, neither of the parties is
responsible.
(III) In a case between Alopi Parshad & Sons Ltd. Vs.
Union of India reported in AIR 1960 (SC) 588 that, in
India, in the codified law of contracts, there is nothing
which justifies the view that, a change of circumstances,
“completely outside the contemplation of parties”, at the
time when the contract was entered into, will justify a
Court, while holding the parties bound by the Contract, in
departing from the express terms thereof.
10. Subsidy means, the subsidy is a monetary help provided
to the loanee by the Government.
WP(C) No.16506 of 2025 Page 14 of 18
The object and intention of the Government for the
introduction of the Subsidy Scheme is to attract more
entrepreneurs in respect of the projects under that scheme.
The law relating to the object of the subsidy has already been
clarified in the ratio of the following decisions:
(I) In a case between Vasu Coco Private Limited Vs.
State of Kerala & Others reported in 2023 Livelaw
(Ker.) 27 (decided on 10.01.2023) that, the intention
of the Government for the introduction of the subsidy
scheme is to attract the persons like that of the
petitioner as entrepreneur giving benefit through
subsidy.
(II) In a case between Indian Oil Corporation &
Others Vs. Kerala Road Transport Corporation &
Others reported in (2018) 12 SCC 518 that, grant of
subsidy by the Government is a matter of privilege, to be
extended by the Government.
11. From the ratio of the aforesaid decisions as well as from
the scheme of MKUY, it is clear that, the declaration was
made by the Government for the payment of the subsidy in
order to attract more entrepreneurs for that agricultural
MKUY Scheme/Yojana.
12. APICOL i.e. Agricultural Promotion Investment of Odisha
Limited is a wholly owned corporation of Government of
Odisha. The sole objective of the APICOL is to promote agri-
WP(C) No.16506 of 2025 Page 15 of 18
based industries, food processing industries including
commercial agriculture, horticulture, animal husbandry and
fisheries. APICOL is a Government of Odisha undertaking,
coming up as a promotional organization for providing
assistance to agricultural enterprises in the State of Odisha.
So, APICOL is a sector of the Government. Therefore,
Government is the principal of the APICOL.
13. Here in this matter at hand, none of the Opp. Parties
including the Government (which is the Principal of the Opp.
Party No.6) except the Opp. Party No.6(M.D of APICOL) has
opposed/objected to the entitlement to the subsidy of 40% of
the project cost (fixed capital) limited to Rs.50,00,000/-
submitting any counter against the prayer of the petitioner
and when subsidy will be paid by the Government as per the
declaration made in the MUKY Scheme and when the
Government (who is the Principal of the Opp. Party No.6) is
not disagree for the payment of the declared subsidy as per
the MUKY Scheme to the petitioner and when the completion
of the project works within 25.05.2023 as per Annexure-4 by
the petitioner was impossible/ impracticable on account of
WP(C) No.16506 of 2025 Page 16 of 18
continuation of Covid-19 pandemic till 28.02.2022
commencing prior to 25.05.2021 and when for such Covid-19
Pandemic, neither of the parties is responsible for delay in
completion of the project works and when supervision of the
project works of the petitioner were made by the Opp. Parties
after 25.05.2023 without raising any objection about the non-
completion of the project work within 25.05.2023, as they
were aware that, for Covid-19 pandemic, it was not possible to
complete the project works within 25.05.2023
forgiving/abandoning their right of any objection, then, at
this juncture, the rejection to the claim of the petitioner for
the grant of subsidy of 40% of the project cost (fixed capital)
limited to Rs.50,00,000/- as per the impugned Letter/Order
dated 16.04.2025 (Annexure-3) by the Opp. Party No.6 (The
Managing Director Agriculture Promotion & Investment
Cooperation of Odisha i.e. APICOL) only on the ground of
non-completion of such project works within 25.05.2023 is
not justified under law. Because, the completion of project
works within 25.05.2023 by the petitioner was impossible and
WP(C) No.16506 of 2025 Page 17 of 18
the same was beyond his control for the reasons assigned
above.
For which, the impugned Letter/Order dated 16.04.2025
(Annexure-3) issued/ passed by the Opp. Party No.6 cannot
be sustainable under law. The same is liable to be quashed.
14. Therefore, there is merit in the writ petition filed by the
petitioner. The same is to be allowed.
15. In result, the writ petition filed by the petitioner is
allowed on contest.
16. The impugned Letter/Order dated 16.04.2025
(Annexure-3) passed/issued by the Opp. Party No.6 is
quashed.
All the Opp. Parties including the Opp. Party No.6 (The
Managing Director Agriculture Promotion & Investment
Cooperation of Odisha i.e. APICOL) are jointly and severally
liable for the disbursement of the subsidy of 40% of the
project cost (fixed capital) limited to Rs.50,00,000/- as per
“Mukhyamantri Krushi Udyog Yojana (MKUY)” in favour of the
petitioner within a period of 15 days from the date of this
Judgment, failing which, the petitioner is entitled to get 9%
WP(C) No.16506 of 2025 Page 18 of 18
interest per annum thereon since 14.02.2026 till its full and
final payment to the petitioner.
17. Registry is directed to communicate the copy of this
Judgment to all the Opp. Parties immediately for proper
implementation of the directions made in this Judgment.
18. As such, this writ petition filed by the petitioner is
disposed of finally.
(ANANDA CHANDRA BEHERA )
JUDGE
High Court of Orissa, Cuttack
The 28 .01. 2026// Rati Ranjan Nayak
Sr. Stenographer
Legal Notes
Add a Note....