As per case facts, the appellant, initially granted a Way Leave Permission for a water pipeline by Railways in 2007, sought its "revival" years after its expiry and during their ...
IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
(APPELLATE SIDE)
MAT 944 of 2024
With
CAN 1 of 2024
With
CAN 2 of 2024
Ramsarup Industries Ltd.
-Vs.-
Orissa Metaliks Pvt. Ltd. & Ors.
Before: The Hon’ble Justice Arijit Banerjee
&
The Hon’ble Justice Om Narayan Rai
For the Appellant : Mr. S. N. Mookherjee, Sr. Adv.,
Mr. Ratnanko Banerji, Sr. Adv.
Mr. Soumya Majumdar, Sr. Adv.
Mr. N.G. Khaitan, Adv.
Mr. Shounak Mitra, Adv.
Mr. Zulfiqar Ali Alquaderi, Adv.
Mr. Yash Singhi, Adv.
Ms. Akshita Bohra, Adv.
For the Respondent no. 1
:
Mr. Ranjan Bachhawat, Sr. Adv.,
Mr. Jishnu Chowdhury, Sr. Adv.
Mr. Raghunath Ghosh, Adv.
Mr. S. Mukherjee, Adv.
Mr. Debrup Bhattacharya, Adv.
Mr. B. Kumar, Adv.
Mr. Aayush Lakhotia, Adv.
2
For the Union of India : Mr. Ashok Bhowmik, Adv.,
Mr. Sourav Sengupta, Adv.
For Judgment on : 09.09.2026
Arijit Banerjee, J. :-
1. This appeal is directed against a judgment and order dated May 10,
2024, passed by a learned Judge of our Court disposing of a writ petition of
the respondent no. 1 herein, being WP No. 10441 of 2024. In the writ
petition, under challenge were letters dated April 3, 2024 and April 4, 2024,
whereby, the Railway Authorities had sanctioned revival of a Way Leave
Permission in favour of the respondent no. 6 in the writ petition being the
appellant herein, for constructing and running a water -pipeline under
railway property.
Appellant’s submission: -
2. Appearing for the appellant, Mr. S. N. Mookherjee, learned Senior
Advocate, submitted as follows: -
(i) On July 10, 2007, Ramsarup Lohh Udyog Ltd. was granted a
Way Leave Permission by the Railways, for construction of a water-
pipeline for usage at its plant in Kharagpur, West Bengal, for 10 years.
(ii) On June 30, 2008, Ramsarup Lohh Udyog Ltd. sto od
amalgamated with the appellant. All licenses, permissions etc. stood
transferred in the name of the appellant.
(iii) In June 2010, the appellant was shut down and all its plants
became non-operational.
3
(iv) On November 7, 2012, the appellant’s management made a
reference to the Board for Industrial and Financial Reconstruction (in
short, ‘BIFR’) under the Sick Industrial Companies Act, 1985 (in short,
‘SICA’), based on the company’s audited balance sheet for the year
2011-2012. The reference was registered as Case No. 67/2012.
(v) On February 19, 2014, upon hearing the appellant and its
secured financial creditors, the BIFR ordered abatement of the
reference in terms of the 3
rd
proviso to Section 15(1) of SICA.
(vi) The appellant challenged the order of BIFR before the Appellate
Authority for Industrial & Financial Reconstruction (in short, ‘AAIFR’)
which set aside the order of BIFR and remanded the matter back to
BIFR for reconsideration.
(vii) On November 25, 2016, SICA was repealed and all proceedings
before the BIFR/AAIFR stood abated with effect from December 1,
2016. However, any company whose reference was pending before the
BIFR/AAIFR at the time of repeal, was permitted to file an application
before the National Company Law Tribunal (in short, ‘NCLT’) within a
period of 180 days from the commencement of the Insolvency and
Bankruptcy Code, 2016 (in short, ‘IBC’).
(viii) On December 1, 2016, the IBC came into force.
(ix) On May 2, 2017, an application was made by the respondent
no. 1/ writ petitioner, Orissa Metaliks Private Limited (in short, ‘OMPL’)
to the Railways for Road Under Bridge permission.
4
(x) On May 18, 2017, a resolution was passed by the appellant’s
Board of Directors for filing an application under Section 10 of the IBC
before the NCLT. Such application was filed on May 25, 2017.
(xi) On June 8, 2018, the appellant was admitted to the Corporate
Insolvency Resolution Process (in short, ‘CIRP’) by NCLT.
(xii) On February 1,2019, OMPL obtained a Way Leave Permission
for construction of a Road Under Bridge (in short, ‘RUB’) under the
railway track between the stations Girimaidan and Gokulpur on
Kharagpur-Medinipur Section of Kharagpur Division, for transportation
of vehicles (Route 1).
(xiii) On February 27, 2019, an agreement in respect of Route 1 was
executed between the Railway Authorities and OMPL.
(xiv) On September 4, 2019, a resolution plan submitted by a
consortium for revival of the appellant herein, was approved by NCLT.
Clause 15.13 of the plan provided that all statutory rights, licenses,
agreements, registrations or other similar approvals will be valid and in
complete force. Clause 15.14 (ii) (b) provided that all consents, licenses,
approvals, rights, entitlements, benefits, privileges etc. granted in
favour of the appellant, which were in place on the shutdown date shall
be deemed to continue without disruption for the benefit of the
appellant for a period of 12 months from the completion date or until
renewal by the relevant authorities, whichever is later. Therefore, the
Way Leave Permission dated July 10, 2007, was still valid and
subsisting.
5
(xv) OMPL had also submitted a resolution plan. While approving
the resolution plan of the consortium, NCLT recorded that OMPL’s plan
stood rejected. OMPL was declared as the H -2 bidder/unsuccessful
Resolution Applicant.
(xvi) OMPL had tried to derail the implementation of the consortium’s
resolution plan by filing applications for liquidation of the appellant
company, which had been noted by the NCLAT. Su ch conduct of the
OMPL would show that it has not approached this Court with clean
hands.
(xvii) In or around July, 2020, the construction of the RUB in
respect of Route 1 was completed by OMPL and the same was made
operational. The RUB was constructed by cutti ng through the
appellant’s existing water pipeline. It is pertinent to note that Clause
22 of the agreement dated February 27, 2019, executed by and between
OMPL and the Railways, obliges OMPL to make good any damage to or
loss of Railway/Third-Party property due to the presence of its facility.
Hence, OMPL cannot object to the restoration/revival of the appellant’s
water pipeline.
(xviii) By an order dated April 19, 2022, while dismissing all the
appeals filed against rejection of OMPL’s application for liquidation of
the appellant, the NCLAT observed the conduct of OMPL in trying to
acquire the appellant company, through ulterior modes, since it was
declared as an unsuccessful Resolution Applicant in the CIRP.
(xix) On June 1, 2022, OMPL obtained a Way Leave Permissio n for
construction of a RUB under the railway track between station
6
Gokulpur Outer Cabin and Gokulpur on KGP Division for
transportation of vehicles (“Route 2”).
(xx) On June 2, 2022, an agreement in respect of Route 2 was
executed between the Railway Authorities and OMPL.
(xxi) In August, 2022, the RUB in respect of Route 2 was constructed
and made operational by OMPL. Again, the said RUB was constructed
by cutting through the appellant’s existing water pipeline.
(xxii) On October 4, 2022, the Ministry of Railways (Railway Board)
issued a Master Circular on ‘Policy for Management of Railway Land’.
OMPL relies on Clauses 7.4 and 7.5.2 of the said Circular. However,
Clause 7.4 does not bar application for renewal of Way Leave
Permission which expired prior to issuance of the said circular.
Similarly, Clause 7.5.2 does not say that it would only apply to Way
Leave Permission subsisting as on the date of issuance.
(xxiii) OMPL relies on Clause 1033 (12) of the Indian Railway Code for
Engineering Department, alleging that overhead pip elines are not
permitted. However Clause 1033 (4) of that Code permits Way Leave
Permissions in genuine cases. Clause 1033 (12) permits overheads as
well as overhead pipelines so long as the Railway Authorities give
express permission for the same.
(xxiv) Further, more than 98% of the concerned pipeline of the
appellant is underground. The overhead structure has been
necessitated by reason of OMPL cutting through the appellant’s
pipeline which the appellant is now trying to restore.
7
(xxv) After approval of the resolution plan by NCLT, on March 27,
2023, the appellant applied for grant/revival of the Way Leave
Permission for a further period of 10 years or more to meet its water
requirements.
(xxvi) On April 27, 2023, the appellant submitted approved drawing to
the Railways.
(xxvii) On June 16, 2023, the Railways instructed ADE to visit the site
for joint inspection and to verify the drawings. On June 22, 2023, ADE,
Railways, wrote to four departments of the Railways for conducting a
joint inspection towards revival of Way Leave Permission to lay down
the pipeline. On June 24, 2023, joint inspection was conducted and
drawings were approved.
(xxviii) On July 11, 2023, further request was made by the appellant,
forwarding drawings and other technical details, to restore the Way
Leave Permission.
(xxix) On August 8, 2023, drawing was submitted for checking
technical viability. Between August 10 and August 22, 2023, technical
evaluation of the drawings was made by officers from five different
departments of the Railways.
(xxx) On December 11, 2023, technical viability check was forwarded
to various departments of the Railways for final signatures. On
December 21, 2023, technical viability check was made by all
departments. On December 22, 2023, DRM Engineering signed the
technical viability check.
8
(xxxi) Therefore, between August 10, 2023 and December 22, 2023, a
plan dated July 21, 2023, was prepared and approved by 7 Railways
officers/engineers over a period of four months after detailed scrutiny.
(xxxii) By a letter dated January 11, 2024, OMPL informed the
Railway Authorities that it had reasons to believe that the appellant’s
pipeline will compromise the safety of OMPLs RUBs and the boundary
wall of its industrial unit.
(xxxiii) On February 9, 2024, the appellant entered into an agreement
with Kharagpur Municipality, inter alia, for supply of a specified
quantity of water per day to its factory at Kharagpur.
(xxxiv) On March 18, 2024, the appellant, under protest, deposited a
sum of Rs 2,16,62,573/- towards Way Leave Permission fee for revival
of its water pipeline. On March 27, 2024, the appellant submitted a
Bank Guarantee for Rs 5,00,000/- valid for a period of one year as
required by the Railways.
(xxxv) On April 3, 2024, pursuant to Way Leave Permission, an
agreement was executed by and between the Railway Authorities and
the appellant for laying down a water pipeline at Section Kharagpur-
Medinipur through Railway land for a length of 2250 meters. The
agreement was to be valid for 10 years from the date of signing of the
agreement. On the same day, a letter was issued by DRM Engineering
to the appellant intimating Way Leave Permission for 10 years with
effect from 2017-18. Such permission stipulated that the work will have
to be undertaken as per drawing and design after completing all
formalities with the Railway departments and in the presence of
9
Railway Engineers. It further provided that the structural drawing and
design with respect to the construction at the subway location (OMPL’s
RUBs) should be approved by reputed organisations/engineers.
(xxxvi) On April 4, 2024, the Railway Authorities issued a
communication informing the concerned officers that an agency has
found some damage in the concerned pipeline from the Jharia
pumphouse to the appellant’s plant which needs repair work. On the
same date, the appellant informed the concerned Railway department
that the repair work on the damaged portions of the water pipeline
shall be undertaken in the presence of the Railway Engineers on April
9, 2024.
(xxxvii) By a letter dated April 5, 2024, the appellant sought the co-
operation and help of the District Magistrate, Paschim Medinipur, for
undertaking the repair work of its existing water pipeline.
(xxxviii) By a letter dated April 8, 2024, addressed to the Railway
Authorities, OMPL alleged that due to low quality of the pipeline
material used by the appellant and the sub -standard
installation/operational process, there may be accidental damage to the
RUBs of OMPL. On that ground, OMPL called for re-examination of the
alignment of the proposed water pipeline.
(xxxix) On April 9, 2024, a joint survey report was prepared and issued
by the concerned Railway Authorities/ Engineers. The appellant was
granted permission to execute only repair work on the said pipeline
except the subway part. OMPL filed the present writ petition on April
10
10, 2024, inter alia, seeking cancellation of the appellant’s Way Leave
Permission dated April 3/4, 2024.
(xl) On April 17, 2024, the appellant submitted drawing through a
reputed consultant. On April 18, 2024, the drawing was re-submitted
with modification. On April 23, 2024, structural drawings with
certification by qualified engineers were submitted by the appellant. On
the same day i.e., April 23, 2024, final permission was granted by the
Railways to the appellant to carry out repair works in respect of its
pipeline.
(xli) The writ petition was disposed of by a judgement and order
dated May 10, 2024 setting aside the appellant’s Way Leave Permission
dated April 3/4, 2024 and quashing all consequent steps taken in
pursuance thereof.
(xlii) On May 13, 2024, the present appeal was filed. By an interim
order, a Division Bench called for a report from the Railways. On
August 19, 2024, the Railways filed a report. OMPL filed its Exception
to that report on September 2, 2024. On September 24, 2024, the
Railways filed an affidavit in response to the Exception of OMPL. OMPL
filed its rejoinder on November 12, 2024.
3. Learned Senior Counsel for the appellant relied on the following
decisions: -
(i) Gujarat Urja Vikas Nigam Ltd. v. Ami t Gupta & Ors., reported at
(2021) 7 SCC 209. Paragraph 74.
11
(ii) Municipal Corporation of Greater Mumbai & Ors. v. Rafiqunnisa M.
Khalifa (Deceased) Through His Legal Heir Mohd. Muqueen Qureshi &
Anr. reported at (2019) 5 SCC 119. Para 26.
(iii) Union of India v. M/S. Chaturbhai M. Patel & Co., reported at
(1976) 1 SCC 747. Para 7.
Submission on behalf of the respondent no. 1:-
4. On the factual score, apart from what has been noted above, learned
Senior Counsel for the respondent no. 1 added the following: -
(i) On July 9, 2017, the Way Leave Permission granted to the appellant
expired since the license expired and no money was paid for renewal thereof.
The pipeline had not been in use for 7 years.
(ii) On February 1, 2019, OMPL was granted permission for construction of
the first RUB. At this stage, the Railways obviously treated the appellant’s
license as non-existent and, therefore, gave permission to OMPL.
Accordingly the agreement dated February 27, 2019 was entered into an
agreement between OMPL and the Railways in respect of the first RUB.
(iii) The Resolution Plan of the appellant that was approved by the NCLT on
September 4, 2019, could not and did not create any right in the appellant’s
pipeline. The permission of the appellant had already expired/lapsed pre-
CIRP. A Resolution Plan cannot create a new right. Such right could only
have been granted by the Railways or by the Civil Court in an appropriate
proceeding.
(iv) An agreement dated June 2, 2022, was executed between the Railways
and OMPL with respect to the second RUB. At that stage also, evidently the
Railways treated the appellant’s license as being non-existent.
12
(v) The agreement dated April 3, 2024, that was entered into by and between
the appellant and the Railways purporting to renew Way Leave Permission
with retrospective effect, was executed behind the back of OMPL, in an
extremely hurried manner and without giving an opportunity of hearing to
OMPL, despite valuable rights having accrued in favour of OMPL in the
meantime.
(vi) It is clear from the Report filed by the Railways that the safety aspects
relating to the RUBs of OMPL were never considered at all.
(vii) No technical assessment was made pre -revival. Post-revival, only
drawings were approved. It will appear from the drawings disclosed that
pillars of the appellant’s pipeline are dangerously close to OMPL’s RUB (less
than 1 meter) and the entire area up to OMPLs RUB was excavated despite
OMPL’s objection.
(viii) Fresh permission for over ground pipeline was granted to the appellant
despite the prohibition in Clause 14 (b) under para 1033 of the Indian
Railways Engineering Code, which reads as follows: -
“14. (b) Way leave permission in respect of open drainage and
surface/overhead pipelines should be allowed only in unavoidable
cases. In any case, fresh permission for this in favour of private
parties should not be given. All efforts may also be made to have
the existing open drainage and surface/overhead pipelines
replaced by underground installations at the earliest.
(ix) It was submitted that no unavoidable case has been made out by the
appellant justifying grant of permission in respect of overhead pipelines.
13
Other organizations like Tata Steel, etc., were denied such permission. Such
organizations have arranged water supply from river Kangsabati.
5. Learned Senior Counsel for OMPL relied on the following decisions: -
(i) Gujarat Urja Vikas Nigam Ltd. v. Amit Gupta & Ors. (Supra)
(ii) Hardesh Ores (P) Ltd. v. Hede & Company, reported at
(2007) 5 SCC 614.
(iii) Corporation of Kochi v. Elamkulam Village Cooperative
Society Ltd. & Anr., reported at (2006) 7 SCC 708.
(iv) General Manager , Electrical Rengali Hydro Electric
Project, Orissa & Ors. v. Giridhari Sahu & Ors. , reported at
(2019) 10 SCC 695.
(v) B. Subramanyam & Anr. v. B.M. Chandra Gowda & Anr.,
reported at (2017) SCC OnLine Kar 6985 .
Judgement and Order of Learned Single Judge: -
6. Learned Single Judge framed the issue as to whether the grant of
renewal of the Way Leave Permission to respondent no. 6 (present appellant)
which had expired in the year 2017, is valid in the eye of law and/or
interdicts the rights conferred in the meantime on the petitioner (present
respondent no.1) in any manner.
7. Learned Judge held that when the petitioner was granted such
permission there was no existing Way Leave Permission operating in favour
of OMPL. Such permission having expired almost two years prior thereto,
was in no manner subsisting at the juncture when the petitioner’s rights
were created.
14
8. In so far as the document dated April 3, 2024, is concerned, learned
Judge held that the description of a fresh Way Leave Permission as ‘renewal’
was a fraud practiced upon the writ petitioner in collusion between the
Railway Authorities and the present appellant as well as fraud on the
applicable Laws and Regulations. A license that stood expired by efflux of
time long time back, could not be renewed. Only a fresh license could be
granted. Learned Judge then held that in the communications emanating
from the Railways including the letter dated April 4, 2024, as well as in the
agreement dated April 3, 2024, entered into by and between the present
appellant and Railways, an impression has been sought to be given that
permission was being given for reviving an underground water pipeline. The
said attempt is evidently to bypass the effect of sub-clause (12) of clause
1033 of the Railway Engineering Code, which provides that in all cases of
Way Leave facilities (except ROBs/RUBs and underground pipelines), no
construction (whether permanent, quasi-permanent or temporary) other
than a Kuchcha or Pucca road in cases the facility is expressly given for the
same, is to be permitted on Railway land. If any such construction comes up
subsequently, the same should be immediately removed as soon as noticed
and the Way Leave facility discontinued with.
9. Learned Judge also observed that the efforts on the part of the
Railway Authority and the present appellant reeks of surreptitious and mala
fide effort to bypass the Railway Engineering Code as well as the Master
Circular operating in respect of Railway lands, which comprise a policy
decision taken by the Railway Authorities and have the status of statutory
guidelines.
15
10. Learned Judge further held that the structure shown in the map
submitted by the appellant contemplates an overhead construction over the
Railway property. Such attempt is barred firstly, because Clause 1033, sub-
clause (12) of the Railway Engineering Code debars any such overhead
construction; secondly, the Way Leave Permission sought to be given is a
fresh Way Leave Permission in the garb of a ‘renewal’, which cannot now be
given in view of the intervening underpass of the writ petitioner, regarding
which two sets of Way Leaves and agreements subsist between the writ
petitioner and the Railways; and thirdly, the effect of the impugned grant of
permission cannot be ‘renewal’ as described in the permission since the
tenure of the previous Way Leave Permission expired long seven years back
in 2017 and there was never any application for renewal filed or pending at
any point of time.
11. The learned Judge negated the argument advanced on behalf of the
present appellant that the writ petitioner was trying to frustrate the
Resolution Plan which has been approved in connection with the CIRP
initiated by the present appellant. His Lordship held that the Resolution
Process commenced on January 8, 2018, whereas the Way Leave Permission
of the present appellant for its previous pipeline had expired in July, 2017.
Hence, even at the inception of the CIRP, there was no ‘subsisting’
permission or license in favour of the present appellant. The Resolution Plan
was approved much later and as such, the already expired W ay Leave
Permission of the present appellant could not come within the purview of
such ‘subsisting’ approvals/licenses/permissions. Further, it was held that
no new rights could be created in favour of the present appellant merely by
16
virtue of approval of the Resolution Plan. In this connection, learned Judge
referred to the Supreme Court decision in the case of Embassy Property
Developments Pvt Ltd. v. State of Karnataka and Ors, reported at
(2020) 13 SCC 308.
12. It was observed that the failure of the writ petitioner in the Resolution
Process has no bearing on the present dispute and as such, mala fides
cannot be read into the resistance of the writ petitioner to an illegal attempt
by the respondent no.6 (present appellant) to create rights where there do
not exist any. The very attempt to package the unlawful grant of new Way
Leave Permission directly in derogation of the rights already conferred on
the writ petitioner by the Railways, as a ‘renewal’, is itself mala fide and
fraudulent, being contrary to the Engineering Code of the Railway itself and
the Master Circular.
13. Regarding the argument of the present appellant that the structure of
the appellant would not in any manner affect the rights of the writ
petitioner, the learned Judge came to the conclusion that the Railways did
not conduct a proper safety audit prior to granting the impugned permission
to the present appellant. It was not considered as to whether or not the new
construction which the Railways were permitting the appellant to make
would adversely affect the underpass constructed by OMPL pursuant to
permission granted by the Railways. Learned Judge finally observed that the
action of public authorities of the stature of the Railways has to be
transparent and above board and cannot be actuated b y petty profit-
motives, giving a go-bye to safety standards and violating existing valid
agreements with third parties. Accordingly, the learned Judge set aside the
17
Way Leave Permission granted to the present appellant by the letters dated
April 3, 2024 and April 4, 2024. All consequential steps taken in terms of
such permission, were also quashed. The respondents in the writ petition
were directed to take immediate steps to reverse any action taken pursuant
to the quashed Way Leave and ‘revival’ permission. The present appellant
was directed to restore, at its own cost, the property adjoining the location
underneath which the writ petitioner’s underpass runs, which has been dug
up and/or on which full or partial construction has been made by the
present appellant. It was directed that the site shall be restored to its
original position as it stood before the commencement of construction and
allied work by the present appellant and its agents.
14. Being aggrieved, the respondent no.6 in the writ petition is before us
by way of this appeal.
Court’s view
15. The material facts of the case, as noted above, are not in dispute. To
avoid undue prolixity, I do not reiterate the same.
16. The main points urged by the appellant are as follows: -
(i) OMPL has no locus standi to challenge the permission granted
by the Railways to the appellant since no legal right of OMPL has
been infringed thereby.
(ii) The permission was granted by the Railways after carrying out
necessary groundwork, scrupulously examining the construction
plans submitted by the appellant and after complying with all
procedural formalities as were necessary. The permission has
18
not been granted in violation of any law or in derogation of any
clause of the Railway Engineering Code.
(iii) As on the date of filing of the application under Section 10 of
the IBC before the NCLT, i.e., May 18, 2017, the Way Leave
Permission dated July 10, 2007, was still subsisting. On
January 8, 2018, the appellant was admitted to CIRP by NCLT.
Such order of admission related back to the date of filling of the
application under Section 10 of the IBC thereby, preserving the
Way Leave Permission. Hence, there was no irregularity in the
Railways renewing such permission on a later date.
(iv) The writ petition filed by OMPL is a mala fide effort on its part to
render nugatory the Resolution Plan passed by NCLT for revival
of the appellant company. Such mala fide act has been prompted
by the fact that OMPL’s Resolution Plan was not accepted by
NCLT.
(v) No case of fraud was pleaded or argued by the OMPL. Therefore,
the finding of collusion and fraud on the part of the appellant’s
officers and the concerned Railway officials is completely
unwarranted.
17. Insofar as the point of locus standi is concerned, I find no merit
therein. At a point of time when the Way Leave Permission that had been
granted to the appellant stood expired by efflux of time, the Railways
granted permission to OMPL to construct two underpasses at the concerned
location. Pursuant to such permission, OMPL constructed such
underpasses and made the same operational. The contention of the OMPL is
19
that the permission that has been granted by the Railways to the appellant,
ostensibly for revival of the water pipeline entails new construction which
would have serious adverse impact on the underpasses constructed by
OMPL. Two agreements were entered into between OMPL and the Railways
on February 27, 2019 and June 2, 2022 respectively, regarding construction
of two Railway RUBs by OMPL. The apprehension of OMPL that revival of
the water pipeline passing over the RUBs constructed by OMPL will
compromise the safety of that area in many ways and have immediate
adverse effect on the RUBS and the industrial boundary wall of OMPL’s
industry unit, was communicated by OMPL by its letter dated January 11,
2024 to the Divisional Railway Manager (Engineering), South Eastern
Railway, Kharagpur. The reasons for such apprehension would appear from
the said letter which is extracted hereunder: -
“Dear Sir,
Apropos to the above subject matter it may be noted that M/s
Ramswarup Loha Udhyog Limited (RLUL) is trying to revive an old
underground water pipe which is running parallel to the track and also
alongside the boundary wall of OMPL plant, and it is cutting across the
RUB constructed by the Company. We have reasons to believe that this
pipeline will compromise the safety of this area in many ways including
immediate adverse effect on the RUB and the boundary wall of our
industrial unit. Moreover, the Railway Main line may also get impacted
by the waterline passing parallel to the track. The reasons for the
objection can be summarized as under:
20
a) Potential risk of boundary wall collapsing as the pipeline
installation is being carried out just adjacent to the boundary
wall of our plant unit, under at an estimated depth of 6-7
Meters.
b) If an eventuality of pipeline burst occurs and leakage of water
towards the adjacent Railway track, it would endanger the
Railway Safety, due to subsidence, and slips of embankment.
c) Orissa Metaliks Private Limited is built up in the year 2016
when the existence of such pipe line was ineffective since RLUL
was locked down, since declared bankrupt and whereabouts
were not known. Subsequently, we have our plant alongside this
concealed pipeline of RLUL. Now, we strongly appeal against the
work of pipeline restoration, as it will cause grave impact on
OMPL’s infrastructure. Our sophisticated electrical equipment is
susceptible and prone to the dangers of water logging. In such
case, factory operations will collapse and production gets
impacted. This is a cause of concern foreseeing the pecuniary
losses to the company and also adverse impact on Ra ilway
traffic.
d) Had we known the existence of such big pipe line in the
vicinity of the Railway track, we would have taken necessary
safety precautions in the past with proper planning and design
of our steel factory. Therefore, we express our deep concern,
with dismay that due to lack of prior knowledge of the
21
underground water filled pipeline which is now unearthed by
Railway administration, now we are at the risk for an imminent
Industrial disaster.
e) It is needless to emphasize that such pipe parallel to track of
long length laid under the policy of ‘way leave permission’
adjacent to track is not in accordance with the Railways policy.
We would like to bring it to your knowledge the contents the
KGP division's letter (Copy enclosed), where in the proposal
laying of water pipeline along the track beside railway boundary
from Kansaboti river was not accepted on the grounds as there
is no existing policy.
f) We cite the reference of the letter (Copy enclosed) given by our
company, on the objection raised when an attempt is made to
carry out the work on the said pipeline, without any ‘authority
to work’ duly issued by the Division. We would like to state that
had if not be for our timely intervention, the JCB employed by of
RLUL working at the vicinity, would have damaged the RUB.
g) The water pipeline is stated to be originating from water
source of Kharagpur Municipality, and we find that there is an
attempt to revive the water supply by M/s RLUL from same
source. We came to know, through a copy of RTI letter
addressed to Shri Rajkumar Das by Kharagpur Municipality
(Copy enclosed), where in it is mentioned that they have no
agreement at present with M/s RLUL for supply of water due to
22
scarcity. In the prevailing situation, the revival of the said
pipeline doesn’t have proper sanctity and justification.
We therefore request you good self to look into the matter and order
immediate action, so that it doesn ’t become problematic to our
company as well as to the Railways.
Enclosed: As above
Your Faithfully,
(RN Yadav)
Director (Projects)
For Orissa Metallks Private Limited”
18. By another letter dated April 8, 2024, OMPL requested the Divisional
Railway Manager (Engineering), South Eastern Railway, Kharagpur to re -
examine the permission granted to the appellant herein for renewal of Way
Leave Permission for revival of water pipeline. The reasons prompting OMPL
to write that letter would appear from the letter itself which is extracted
hereunder: -
“Sir,
Sub: Re-examination of the permission granted to M/s. Ramsarup
Industries Limited for renewal of way leave permission for revival of
water pipe line
1.0 Came to know through a reliable source that permission is being
granted to M/s. Ramsarup Industries Limited for renewal of way leave
permission for revival of water pipe line of 500 mm dia beside the
railway track line connecting Gokulpur and Kharagpur.
23
2.0 It is found and observed that the pipeline is passing above the
underpass constructed by M/s. Orissa Metaliks Private Limited
(hereinafter referred as 'company' or 'us' or 'we') for movement of
materials between one plant to another plant of the company. However,
the pipeline above the underpass will have the following implications on
the company:
Since the said pipeline will be in close vicinity of the company’s
boundary wall. there will be safety hazards for our plant &
machinery and other equipments due to low qual ity of pipeline
material, substandard installation and operation process and
hydraulic pressure from unsteady flow of water etc.
Any accidental damage to the pipeline of M/s. Ramsarup
Industries Limited will cause flood inside the underpass as well as
the plant area and hence will compromise with the security of the
lives of various workers and assets of the company.
This will also impact future expansion plan of the company as
the pipeline will become a major bottleneck for us.
This will cause hindrance at the time of laying pipeline to bring
water from Kansai River to the plant which will be constructed
keeping in mind all the safety and future implications.
3.0 In view of the above, Railways may please re-examine the alignment
of proposed waterline for M/s. Ramsarup Inudustries Limited. It is also
pertinent to mention that neither M/s. Ramsarup Industries Limited
24
nor Railways discussed the revival of the captioned pipeline with the
representatives of the company before granting such approval.
4.0 We shall be ever grateful for your kind indulgence and due
consideration of our prayer in this regard in the interest of justice.
Yours faithfully,
for M/s. Orissa Metaliks Private Limited
(Authorised Signatory)
Copy to:
1) The Division Railway Manager, South Eastern Railway, Kharagpur
2) The Chief Transport Planning Manager, South Eastern Railway
(GRC)
3) The Principal Chief Operating Manager, South Eastern Railway
(GRC)
4) The Principal Chief Engineer, South Eastern Railway (GRC)”
19. From the above, it appears that OMPL expressed apprehension of its
interests being adversely affected by the renewal of the Way Leave
Permission granted in favour of the appellant herein. It does not appear from
the records that the Railway Authorities responded to the aforesaid two
letters of OMPL. The Authorities did not deem it necessary to discuss the
matter even once with OMPL. No opportunity of hearing was afforded to
OMPL. Whether or not renewal of the Way Leave Permission in favour of the
appellant and permitting the appellant to carry out necessary
construction/re-construction/repairing work would have adverse impact on
OMPL’s RUBs, was not at all considered by the Railway Authorities.
20. Prima facie, it appears that the apprehension of the OMPL is no t
completely baseless or fanciful. When an order or an act of an Authority is
25
likely to or has the possibility of affecting a person by way of adverse civil
consequences, however remote such possibility be, the person likely to be
affected would surely have the standing to challenge such act or order of the
Authority before a competent court of law. The rule of locus standi has been
developed by the courts to weed out frivolous litigations at the instance of
busybodies who have no real interest in such litigations. However, in the
present case, it does not appear to us that OMPL can be said to be such a
busybody having absolutely no stake in the matter. Hence, I reject the
appellant’s argument that OMPL did not have the locus standi to maintain
the writ petition.
21. In this connection the appellant relied on the decision of the Hon’ble
Supreme Court in Municipal Corporation of Greater Mumbai & Ors. v.
Rafiqunnisa M. Khalifa (Deceased) Through His Legal Heir Mohd.
Muqueen Qureshi & Anr., (Supra) in support of the contention that a writ
of mandamus under Article 226 of the Constitution of India is issued only
when there is a right, contractual or otherwise, in favour of the writ
petitioner and correspondently there is a legal duty to perform. The
argument was that there is no legal or contractual right in favour of OMPL
and therefore the writ petition was not maintainable at its instance.
We are unable to accept the above argument. OMPL having constructed
the RUBs pursuant to agreements entered into with the Railway Authorities,
it is the duty of the Railway Authorities to ensure that any permission
granted to anybody for any fresh construction or making an old construction
operational, does not have any adverse impact on the RUBs constructed by
26
OMPL. OMPL is surely entitled to approach the Writ Court praying for
appropriate writs of mandamus, certiorari or prohibition.
22. When the appeal was admitted by a Co-ordinate Bench by its order
dated May 21, 2024, while staying the operation of the impugned order to
the extent the same directed demolition of constructions made by the
appellant, the Bench had called for a report from the Railways. Paragraphs 4
and 5 of the said order read as follows: -
“4. It appears that the writ petition was disposed of without calling
for affidavits, more particularly, the stand taken by the railway
administration was not put in writing. The qu estion would be
whether a permission, which stood lapsed in 2017 could have been
revived by the railway administration retrospectively and if so,
what would be the position of the persons, who had acquired
certain rights in the interregnum. Apart from that, the Court
should be informed as to whether there was any technical
assessment done by the railway administration before revival of
permission to take the pipeline above the railway underpass,
which has been permitted to be constructed by the writ petitioner
when the permission for the pipeline was not in vogue.
5. Let a report be filed in the form of an affidavit by the highest
competent authority of the railway administration duly supported
with documents.”
23. Such a report by way of affidavit affirmed on July 5, 2024, by the
Divisional Engineer (West), South Eastern Railway, Kharagpur , who was
27
also the Divisional Railway Manager (Engineering), was filed. Various
documents have been annexed to such report. Such report along with its
annexures have been brought on record by OMPL by filing an exception to
the report in the form of an application registered as CAN 2 of 2024.
24. From the documents annexed to the said report, it does not appear
that due safety audit was undertaken by the Railway Authorities prior to
granting the impugned permission to the appellant. The safety I have in
mind is not only as regards any adverse impact on the RUBs constructed by
OMPL but in general, safety of the entire industrial area. If the
apprehensions expressed by OMPL in its two letters dated January 11, 2024
and April 8, 2024, addressed to the Railway Authorities, are correct even if
to some extent, the possibility of accidents involving loss of life and limbs
apart from property, would loom large. In our view, a comprehensive and
exhaustive safety audit was absolutely essential prior to granting the
impugned permission to the appellant, especially, in view of the contents of
OMPL’s aforesaid two letters.
25. Further, the overhead structure that the Railways have permitted the
appellant to construct in aid of revival of the concerned pipeline appears to
be contrary to Clause 1033 (12) of the Railway Engineering Code as has
been rightly noted by the learned Single Judge.
26. As regards the third contention of the appellant, we do not find any
merit in that also. The Way Leave Permission was granted on July 10, 2007.
It expired by efflux of time on July 9, 2017. On May 25, 2017, the appellant
filed an application for CIRP under Section 10 of the IBC before the NCLT.
On January 8, 2018, the appellant was admitted to the CIRP by the NCLT.
28
As on that date there was no subsisting Way Leave Permission in favour of
the appellant, the same having expired on July 9, 2017. Hence, the question
of the Way Leave Permission continuing to be in force by operation of law,
cannot and does not arise.
27. In any event, it is beyond the jurisdiction of NCLT to revive or renew
the Way Leave Permission that was granted by the Railways in 2007. While
approving the Resolution Plan on September 4, 2019, NCLT could not have
renewed a Way Leave Permission which stood expired on July 9, 2017. A
permission which has expired cannot be renewed as has been extensively
discussed by the learned Single Judge. Only a fresh permission can be
granted. It was not within the NCLT’s power to grant such permission nor
did it do so.
28. The decision of the Hon’ble Supreme Court in Gujarat Urja Vikas
Nigam Ltd. v. Amit Gupta & Ors., (Supra) relied upon by the appellant
does not advance its case to any extent. The appellant relied on paragraph
74 of the reported judgement which reads as follows: -
“74. Therefore, we hold that the RP can approach NCLT for
adjudication of disputes that are related to the insolvency
resolution process. However, for adjudication of disputes that arise
dehors the insolvency of the corporate debtor, the RP must
approach the relevant competent authority. For instance, if the
dispute in the present matter related to the non -supply of
electricity, the RP would not have been entitled to invoke the
jurisdiction of NCLT under IBC. However, since the dispute in the
present case has arisen solely on the ground of the insolvency of
29
the corporate debtor, NCLT is empowered to adjudicate this
dispute under Section 60(5)(c) of IBC.”
29. As I read the said observations, the same go against the appellant’s
contention. The issue of Way Leave Permission in connection with Railway
land cannot be said to be a dispute related to the Insolvency Resolution
Process. It is a dispute dehors such process just like non -supply of
electricity as observed by the Hon’ble Supreme Court. Therefore, NCLT
would have no jurisdiction to renew or revive or preserve the Way Leave
Permission granted by the Railways in 2007 which stood expired on July 9,
2017.
30. As regards the fourth point urged before us by the appellant, we are
not impressed that any case of the writ petition being a mala fide, has been
made out by the appellant. The learned Single Judge has observed that
renewal of the Way Leave Permission in 2024, with retrospective effect from
2017 was illegal. Mala fides cannot be read into the writ petiti oner’s
resistance to an illegal attempt by the present appellant to create rights
where none exists. The mere fact that OMPL failed to take over the appellant
company in the CIRP cannot be the ground or reason to presume or infer
that the instant writ petition is mala fide.
31. As regards the fifth point of the learned Judge having come to a
finding of fraud and collusion between the officers of Railways and the
appellant, the appellant relied upon a decision of the Hon’ble Supreme
Court in the case of Union of India v. M/S. Chaturbhai M. Patel & Co.,
(Supra), in support of the contention that fraud like any other charge of a
criminal offence, whether made in civil or criminal proceedings, must be
30
established beyond reasonable doubt. However suspicious may be th e
circumstances, however strange the coincidence is and however grave the
doubt, suspicion alone can never take the place of proof.
32. We agree with the learned Senior Counsel for the appellant that it may
not have been necessary for the learned Single Judge to hold that renewal of
the concerned Way Leave Permission was a result of collusion between the
appellant and the Railways or amounts to fraud on the statute or on Court
or on the relevant Rules or Regulations of the Railways. A verdict of fraud
having been practised cannot be returned lightly. Fraud is a criminal charge
and so is fraudulent collusion. Such charges must be established on proper
material and beyond reasonable doubt in contradistinction to balance of
probabilities which is the standard appl icable in civil cases. The
observations of the learned Single Judge regarding fraud on the part of the
appellant and the Railways and collusion between them, stand expunged
from the judgment and order of the learned Single Judge.
33. We, therefore, substantially agree with the learned Single Judge that
‘renewal’ of the concerned Way Leave Permission 7 years after expiry of such
permission, without conducting due safety audit and completely oblivious of
the adverse civil consequences that the same may have for OMPL, was not
only irregular but also illegal. The least that the Railways could have done
was to carry out due safety audit and give opportunity of hearing to OMPL,
prior to granting the impugned permission to the appellant. The Railway
Authorities completely ignored the two letters dated January 11, 2024 and
April 8, 2024, addressed by OMPL to them ventilating their apprehension
regarding revival of the concerned Way Leave Permission in favour of the
31
appellant. This does raise a doubt in my mind as to whether the Railway
Authorities acted fairly, honestly and impartially, but I stop at that.
34. In the result, we affirm the judgment and order under appeal except to
the extent of expunging certain observations therefrom, as indicated above.
The judgment is a well-reasoned one and we do not find any such error
therein as would persuade us to interfere. The view of the learned Single
Judge is an eminently plausible one. It is settled law that if a learned Single
Judge’s view is a possible view, then, in an intra-court appeal, the Division
Bench will not interfere only because it may have a different view.
Interference is warranted only when the order of the learned Single Judge,
in the opinion of the Appeal Court, is ‘clearly wrong’ or palpably perverse.
35. The appeal is accordingly disposed of along with the connected
applications. The interim order that is subsisting, stands vacated.
36. Urgent Photostat certified copies of this judgement and order, if
applied for, be supplied to the parties on compliance of all necessary
formalities.
I agree.
(Om Narayan Rai, J.) (Arijit Banerjee, J.)
In a significant decision addressing the complexities of expired Way Leave Permissions and the scope of NCLT's jurisdiction in non-insolvency matters, the High Court at Calcutta, Civil Appellate Jurisdiction (Appellate Side), recently upheld a single judge's order. This ruling, emanating from MAT 944 of 2024 with connected applications CAN 1 of 2024 and CAN 2 of 2024, involves Ramsarup Industries Ltd. (Appellant) and Orissa Metaliks Pvt. Ltd. & Ors. (Respondent No. 1, OMPL). The judgment, delivered by the Hon'ble Justice Arijit Banerjee and the Hon'ble Justice Om Narayan Rai, provides crucial clarity for legal professionals navigating administrative law, corporate insolvency, and regulatory compliance. Detailed analyses of such pivotal rulings are made easily accessible on CaseOn, ensuring legal practitioners and students remain updated on judicial precedents.
The dispute centers around a 'Way Leave Permission' granted by the Railways to Ramsarup Industries Ltd. in 2007 for a water pipeline, which was to last for 10 years, expiring on July 9, 2017. Ramsarup, having undergone corporate insolvency proceedings (CIRP) under the IBC and secured an NCLT-approved resolution plan in September 2019, sought to 'revive' this expired permission in 2023. Crucially, in the interim (2019 and 2022), Orissa Metaliks Pvt. Ltd. (OMPL) had obtained its own Way Leave Permissions from the Railways to construct two Road Under Bridges (RUBs) at the same location, cutting through Ramsarup’s existing, albeit non-operational, pipeline.
OMPL objected strongly to Ramsarup's proposed revival, citing safety concerns for its RUBs, industrial unit, and the railway line itself. Despite these objections, the Railways granted Ramsarup a 'renewal' of permission in April 2024, with retrospective effect from 2017-18. This decision led OMPL to challenge the 'renewal' before a single judge of the High Court, who set aside the permission, deeming it a 'fraud' and 'mala fide' attempt to bypass regulations.
The core issues before the appellate bench were:
The High Court's decision was guided by several key legal principles and statutes:
The appellant, Ramsarup, argued that OMPL lacked locus standi to challenge the permission. The Division Bench firmly rejected this, stating that OMPL had entered into agreements with the Railways for its RUBs and that the revival of Ramsarup’s pipeline could have serious adverse impacts on OMPL’s infrastructure and safety. OMPL was not a 'busybody' but a directly affected party with legitimate concerns. The Railways, having granted permissions to OMPL, had a duty to ensure no new or revived permissions adversely affected OMPL's existing facilities.
Ramsarup contended that its resolution plan, approved by NCLT, implied the continuation or revival of its Way Leave Permission. The court, echoing the single judge, clarified that NCLT's jurisdiction under the IBC does not extend to reviving or renewing statutory permissions that expired before the CIRP commenced and are not intrinsically linked to the insolvency process. Citing Gujarat Urja Vikas Nigam Ltd., the court reiterated that Way Leave Permissions are matters 'dehors' the insolvency process, much like a dispute over electricity supply.
While the single judge had found fraud and collusion between Ramsarup and the Railways, the appellate bench took a more nuanced stance. Acknowledging that fraud is a severe charge requiring a high standard of proof ('beyond reasonable doubt'), the Division Bench expunged these specific observations from the single judge’s order. However, this expungement did not alter the core finding of illegality. The court still found the Railways' actions 'not only irregular but also illegal' due to the retrospective nature of the 'renewal' seven years after expiry, and the lack of a proper safety audit or consultation with OMPL.
A critical aspect of the court's analysis was the absence of a comprehensive and exhaustive safety audit by the Railway Authorities before granting the permission to Ramsarup. OMPL had clearly articulated its apprehensions regarding potential boundary wall collapse, pipeline bursts affecting railway safety, and waterlogging impacting its electrical equipment. The court underscored that public authorities like the Railways must act transparently, prioritize safety standards, and honor existing agreements, rather than being driven by 'petty profit-motives.'
For legal professionals seeking swift comprehension of such detailed judicial reasoning, CaseOn.in's 2-minute audio briefs offer an invaluable resource, distilling complex rulings into easily digestible summaries that pinpoint the critical legal arguments and their implications.
The court also agreed with the single judge that the proposed overhead structure by Ramsarup appeared contrary to Clause 1033(12) of the Indian Railway Engineering Code, which generally restricts such constructions unless specific and unavoidable circumstances are proven.
The Division Bench of the Calcutta High Court largely affirmed the judgment and order of the single judge. It found no 'clear error' or 'palpable perversity' in the single judge's reasoning. While the specific findings of 'fraud' and 'collusion' were expunged due to the high standard of proof required, the appellate court maintained that the Railways' action of 'renewing' an expired Way Leave Permission retrospectively, without a proper safety audit or hearing OMPL's legitimate concerns, was 'irregular' and 'illegal.' Consequently, the Way Leave Permission granted to Ramsarup Industries Ltd. on April 3/4, 2024, and all subsequent steps, stand quashed. The interim order staying demolition was vacated, and Ramsarup was directed to restore the site at its own cost.
This judgment serves as a pivotal reference for several areas of law:
For legal professionals, this case emphasizes the need for meticulous due diligence in assessing the status of permissions during insolvency proceedings and underscores the robust oversight courts maintain over administrative actions to prevent arbitrary or unfair outcomes. For students, it's a practical example of how different legal domains intersect in complex commercial disputes.
All information provided in this article is for informational purposes only and does not constitute legal advice. It is recommended to consult with a qualified legal professional for advice pertaining to any specific legal issue.
Legal Notes
Add a Note....