As per case facts, the Appellant Association challenged a single Bench judgment that partly allowed a writ petition but refused to order demolition of constructions on an alleged commercial plot. ...
1
IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
Present:
Hon’ble Justice Rajasekhar Mantha
And
Hon’ble Justice Anuj Singh
MAT 519 of 2024
With
I.A. No. CAN 2 of 2024
Rosedale Garden Apartment Owners Association
Vs.
The New Town Kolkata Development Authority and Ors.
For the Appellant: Mr. S. N. Mookherji, Ld. Sr. Adv,
Mr. Srijib Chakraborty,
Mr. Dhruv Chadha,
Mr. Aditya Mondal,
Ms. Shomrita Das,
Mr. Shomrik Das.
For the NKDA: Mr. Anirban Ray, Ld. Sr. Adv,
Ms. Munmun Ganguly,
Mr. SayanGanguly.
For the Respondent Nos.4 & 5: Mr. Ashok Kr. Banerjee, Ld. Sr. Adv,
Mr. Debabrata Banerjee,
Mr. Samir Kr. Chakraborty,
Mr. Hemanta Kumar Das.
For the Respondent No.6: Mr. Soumya Majumder, Ld. Sr. Adv,
Mr. Aritra Basu,
Ms. Madhusmita Senapati,
Ms. Swastika Roy.
2
For the Respondent Nos.7 to 9: Mr. Jayanta Kumar Mitra, Ld. Sr. Adv.
Mr. Rohit Das,
Mr. Indradip Das,
Ms. Kishwar Rahman,
Ms. Divya Tekriwal.
Joint Special Officer: Mr. Md. Farhaduddin, Adv.
Mr. Rajarshi Rai Chowdhury, Adv.
Hearing concluded on: 7
th
September, 2026
Judgment pronounced on: 14
th
September, 2026
RAJASEKHAR MANTHA, J:-
A. THE CHALLENGE
1. The Appellant Association has challenged the Judgment and order dated
February 23
rd
, 2024, by which the single Bench of this Court has partly
allowed and dismissed the writ petition WPA 302 of 2020 titled as
Rosedale Garden Apartment Owners Association Vs New Town,
Kolkata Development Authority & Ors .
2. The single Bench has set aside an order dated February 27
th, 2019
passed by the New Town Kolkata Development Authority (NKDA),
Respondent No. 1 therein. It was held that the sanction plan of 2009
issued by West Bengal Housing and Infrastructure Development
Corporation (HIDCO) was the actual sanction plan binding between the
parties. It, however, refused to order demolition of the constructions made
at the alleged commercial plot.
3. By the order dated February 27
th
, 2019, impugned in the said writ
petition, NKDA granted liberty to Rosedale developer Pvt Ltd (RDPL)
Respondent no. 6, to incorporate the deviations, recorded in the
inspection report of the NKDA dated November 28
th, 2018 (filed in WP No.
21146 of 2018, Vinay Chowdhury. Versus The New Town Kolkata
3
Development Authority & Ors.), in consultation with Rosedale Plaza (RP),
respondent nos. 7 -9, in a fresh sanction plan to be submitted to the
NKDA for final ratification, and obtain the consent of the flat owners, if
need be.
4. In the impugned judgement, the single Bench held that the plan dated
August 27
th
, 2009 (HIDCO plan), was valid, declaring the revised plan
dated April 26
th
, 2011 (NKDA revised plan), sanctioned by NKDA invalid,
inter-alia recording the following reasons :-
a) Two writ petitions were filed before this Court regarding the subject
bulk plot. The first writ petition was filed by a flat owner, Vinay
Chowdhury, seeking demolition of the constructions at the subject
bulk plots made in violation of the HIDCO plan. The second writ
petition was filed by RP (Respondent No. 7 to 9), praying for the
reconsideration of the completion certificate issued to the RDPL by
the NKDA without the consent of RP.
b) The NKDA inspection report dated November 28
th, 2018, recording
deviations in the constructions made by the RP from the NKDA
revised plan, should not be given any credence, given that the
HIDCO plan is the valid plan. No party has challenged the HIDCO
plan.
c) RP seeks to complete construction according to the HIDCO plan,
constructing the G+1 retail floor, and should be allowed to do so.
The NKDA revised plan is invalid because RP did not consent to it.
d) In a subsequent report dated October 7, 2020, the NKDA stated
that no illegal construction exists on the subject bulk plots.
4
Therefore, an order of demolition against the constructions made by
RP should not be passed.
5. The appellant Rosedale Garden Apartment Owners Association (RGAOA)
is aggrieved by the impugned order, inter alia, for refusal to order
demolition of the constructions made in deviation of the NKDA Sanction
plan dated 26
th
April 2011. They submit that the said NKDA plan
modified 26
th
April, 2011, superseded the original HIDCO plan of 27
th
August 2009. Hence, the instant appeal.
B. FACTS RELEVANT TO THE APPEAL
6. On February 24, 2006, a development agreement was executed
between HIDCO and RDPL, permitting the latter to construct
residential apartments including amenities for the residents and Retail
shopping area on the 16.32-acre plot (subject bulk plot) in Mouza
Patharghata (J.L. No. 36).
7. On July 24
th
, 2006, HIDCO Building Rules, 2006, and HIDCO Building
Regulations, 2006, were framed and promulgated, notifying HIDCO as
the ‘sanctioning authority’ for building permits.
8. In 2007, the Newtown Kolkata Development Authority Act, 2007
(NKDA Act, 2007) came in force with retrospective effect from
December 28
th, 2006. The schedule to the NKDA Act, 2007, included
the plots to which the said Act will apply. Serial Number 15 of the said
Schedule included a part of Patharghata, J.L. No. 36, under which
certain plots by their respective plot numbers were set out.
9. On August 27
th, 2009, HIDCO sanctioned a plan (HIDCO Plan) to the
RDPL for commencing construction of a residential multi-storied
residential towers and an ancillary retail area.
5
10. On April 20
th, 2010, the RDPL submitted a plan before the NKDA,
which modified the HIDCO plan. On April 26
th, 2011, NKDA sanctioned
the modified plan in favour of the RDPL. The modified plan was,
however, sanctioned by NKDA as per the Planning Area (Building
Operations) Rules, 2006, (HIDCO Building Rules, 2006), discussed
hereinafter.
11. On March 4
th
, 2014, the New Town Kolkata Planning Area Building
Rules, 2014 (Rules of 2014) was notified. By necessary implication,
the subject bulk plots were included under the said Rules of 2014,
discussed hereinafter.
12. On May 19
th
, 2014, a registered deed of conveyance was executed
between HIDCO, RDPL, and RP confirming the sale of 18,218 square
feet. In the conveyance, RP was directed to carry out construction as
per the HIDCO plan notwithstanding that on the date of the
conveyance, the RDPL has obtained the NKDA revised plan, and the
HIDCO plan was non-existent.
13. On October 14
th, 2015, NKDA issued the final occupancy certificate
for the subject bulk plots on an application filed by the RDPL. The
inspection report dated November 28
th
, 2018 filed in WP No. 21146
of 2018 titled Vinay Chowdhury v. New Town Kolkata Development
Authority and Others, preferred by one of the flat owners, recorded
deviations in the constructions at the retail area from the serial nos.
34, 35, and 36 of such a final occupancy. Serial nos. 34, 35, and 36
(supra) are set out below:-
Serial no Construction not found in accordance with
the NKDA revised plan upon spot inspection
6
34. Ground Floor Plan & East Elevation (Retail
Building)
35. Roof Plan (Retail Building)
36. Sections, Elevation-North (Retail Building)
14. On September 9
th
, 2018, WP No. 21146 of 2018 (Vinay Chowdhury v.
New Town Kolkata Development Authority and Others) was filed by
a flat owner, praying for restoring the nature and character of the
Rosedale Garden Complex (residential complex) as depicted in the
original HIDCO plan of 27
th August 2009.
15. On November 2
nd, 2018, RP, purchaser of the alleged commercial plot,
approached NKDA by a letter in writing for an extension of time to
complete the construction at the alleged commercial plot in terms of
the NKDA revised plan dated 26
th April 2011. RP was informed by
NKDA that the final occupancy certificate has already been issued on
October 14
th
, 2015, based on the notice of completion submitted by the
RDPL. RP, which functioned under the name and style of ‘Ramji
Constructions’ till then, was thereafter reconstituted to a partnership
firm called M/s Rosedale Plaza (RP) with the respondents Nos. 7 & 8 as
its partners.
16. RP challenged the final occupancy certificate in a writ petition WP No.
24454 of 2018 titled as Rosedale Plaza v. New Town Kolkata
Development Authority and Others), seeking recall of the
observations of NKDA at serial nos. 34, 35, and 36 of the final
occupation completion certificate, which dealt with the constructions
at the retail plots.
7
17. By an order dated November 15
th, 2018, passed in WPA 21146 of
2018 Vinay Chowdhury (supra) , NKDA was directed to conduct a site
inspection and file a report before the Court. An inspection was
conducted on November 28
th, 2018, by the Chief Architect of the New
Town Kolkata Development Authority. The spot inspection revealed
several existing commercial constructions which violate the completion
drawings submitted by the RDPL to the NKDA. They are as follows: -
A) Unsanctioned Security Structure: A security post (gumti) is
found which is not reflected in the completion drawings.
B) Unauthorized Commercial Outlets: Erection of commercial
establishments, "Momo", "Noodle Story", and a large structure
named "Hola" on the alleged commercial plot. These were not
included in the completion drawings.
C) Unsanctioned Fencing & Encroachment: Installation of a
boundary fence separating the residential complex from the
alleged commercial plot. The said partition was not shown in the
completion drawings.
D) Roadway Contravention: Construction of a toilet block and gas
bank in the northwest corner, directly obstructing and
contravening the internal road network.
E) Illegal Roof Access & Additions: Construction of a stair block
to lay out a roof access from the commercial structures.
Ongoing construction of overhead structures on the roof.
Construction of a U-shaped additional space alongside the stair
headroom. These were not shown in the completion drawings.
8
F) Hazardous Utility Placement: Installation of additional gas
banks within the residential area beyond the scope of the
sanctioned completion drawings.
G) Relocation & Boundary Alterations: Relocation of the tennis
and badminton courts to the front of the club-house,
accompanied by the installation of high fencing. This was not
included in the completion drawings.
18. By Order dated December 4
th
, 2018, WP 21146 of 2018 was
disposed by a single bench of this Court, with a direction to the NKDA
to start demolition proceedings under Section 81 and 82 of the NKDA
Act, 2007 based on the report of the Chief Architect dated
28
thNovember, 2018.
19. By Order dated December 6
th, 2018, WP No. 24454 of 2018 ,
preferred by RP was disposed off, granting liberty to RP to demonstrate
the incorrectness of Serial Nos. 34, 35, and 36, of the final completion
certificate dated October 14
th, 2015, in the aforesaid demolition
proceedings before the NKDA. The NKDA was also to ‘reconsider’ the
issuance of the completion certificate since it was issued without
consent of the owner of alleged commercial plot, RP.
20. By Order dated February 27, 2019 passed in the aforesaid
demolition proceedings, NKDA directed RDPL to file a fresh plan in
consultation with RP including all the changes in the construction and
also obtain the no-objection of the other flat owners, if need be.
21. On April 17
th, 2019, Manoj Kumar Sharma, a flat owner/constituted
attorney of the appellant Apartment Owners’ Association filed a Title
Suit no. 286 of 2019 before Ld. 1
st Civil Judge (Senior division) at
9
Barasat, titled as Sri Monoj Kumar Sharma & Ors v. Rosedale Plaza
and Orspraying for a declaration that RP has no right, title, and
interest in the alleged commercial plot and that the construction
thereat has transgressed to the common area of the residential towers.
The suit appears to have been abandoned.
22. An injunction application filed therein was rejected. The Appeal no.
63 of 2018 before Ld. District Judge, Barasat, was preferred against
the order rejecting the injunction. The prayer for ex-parte ad-interim
injunction was refused in the said appeal. Subsequently, the said
appeal was dismissed for default.
23. On January 6
th
, 2020, WPA 302 of 2020 was filed by the appellant
Association through its constituent attorney/vice-president, Manoj
Kumar Sharma, challenging the order dated February 27
th,
2019(supra) as stated above.
24. By order dated January 10, 2020, The National Consumer Disputes
Redressal Commission in Consumer Case No. 1270 of 2017 titled as
Sanjay Agarwal v. Rosedale Developer Private Limited recorded
material alterations from the original HIDCO plan in the NKDA revised
plan. The NKDA revised plan was held contrary to the provisions of
Section 8(1) of the West Bengal Promoters Act. It was however held that
the NKDA Act and the Rules of NKDA were also valid and applicable to
the project.
25. By judgment dated February 23
rd
, 2024, WPA No. 302 of 2020 was
partly allowed by a single bench of this Court, as already discussed in
para no. 4 hereinabove.
10
26. The instant appeal was thereafter filed challenging the judgement
and order dated 23
rd February 2024(Supra).
27. This Court has heard detailed arguments advanced by Mr. S.N.
Mookherji, Sr Adv, for the appellant, Mr. Jayanta Kumar Mitra, Sr Adv
for the Respondent RP, Mr Ashok Kumar Bannerjee, Sr Adv for HIDCO,
Mr. Soumya Mazumdar, Sr Adv for RDPL and Mr. Anirban Ray Sr Adv
for NKDA.
C. ANALYSIS OF THIS COURT
28. A peculiar situation has emerged in this appeal. All sides have as per
their convenience approbated and reprobated. The first writ petition WP
No. 21146 of 2018 titled Vinay Chowdhury v. New Town Kolkata
Development Authority and Others was filed by one of the flat owners,
praying for the restoration of the construction according to the HIDCO
plan. However, the appellant association of the flat owners now seeks
enforcement of the NKDA revised plan dated April 26, 2011.
29. RP filed the second writ petition WP No. 24454 of 2018 (supra) ,
challenging the completion certificate issued by the NKDA to the RDPL.
The writ petition was filed after the NKDA refused to grant an extension of
the NKDA revised plan to complete the construction at the retail area. RP
now seeks to complete construction at the retail area, according to the
HIDCO plan.
30. The NKDA in the inspection report dated November 28
th, 2018, filed in
the writ petitionof Vinay Chowdhury (supra) carried out a spot
inspection and compared the existing construction thereat with the NKDA
revised plan. It found several deviations and illegalities committed by the
Respondent No.7-9 However, the NKDA allowed the RDPL and RP to apply
11
for regularization of deviations to the Re-sanctioned plan dated 26-04-
2011. The NKDA thereafter permitted RP to seek regularization of such
changes, based on the HIDCO plan.
31. Ld. Sr. Counsel for the NKDA submits that NKDA took over the
jurisdiction of the bulk plots from HIDCO. However, NKDA modified
HIDCO's August 27, 2009 plan with a revised plan dated April 26, 2011,
under the HIDCO Building Rules, 2006. The NKDA Building Rules, 2009
had been in force since August 10, 2010. The NKDA, however, chose the
HIDCO 2006 rules over the NKDA Building Rules 2009 while modifying
the HIDCO plan on April 26
th
, 2011.
32. Before the single Bench, RP averred on affidavit that RP’s unit was
commercial and distinct and separate unit from Rosedale Garden which
is the residential part and a separate and independent unit. Ld. Sr.
Counsel for the RP before this Court has submitted that the
Retail/Commercial part of the plot was a single unit with that of Rosedale
Garden.
33. RP submitted an application along with a majority of the residents
under Section 2 read with Section 10 of the WB Apartments Ownership
Act of 1993 declaring that it was a member of the Appellant Association
having an area of 18,218 Square feet.
34. While the Development agreement prescribed that the plots cannot be
subdivided, RDPL executed a conveyance in favour of RP transferring
exclusively the ownership of the Retail area of the plot.
35. HIDCO sanctioned the plan on August 27, 2009. The NKDA was
constituted in 2007. The NKDA Building Rules came into force on August
10, 2009. Thus, NKDA was empowered to sanction plans for the bulk plot
12
as on August 27, 2009. However, it did not. The reasons therefor are
discussed below.
36. There are several other contradictions in the stand of the each of the
parties in these proceedings. Hence this Court is compelled to address the
following issues to set at rest all controversies between the parties.
A. What is the object and purpose of the development
agreement executed between HIDCO and RDPL?
B. What is the legal status of HIDCO plan dated August 27th,
2009?
C. What is legal status of the NKDA revised plan dated April
26th, 2011?
D. What are the rights of RP, Respondents No. 7 to 9, in the
subject bulk plot?
I) Object and Purpose of the Development Agreement and
its Legal Status
37. The development agreement dated February 24
th
, 2006,
executed between HIDCO and RDPL, conceived a residential project
on the subject bulk plot. Some clauses of the said development
agreement are set out below:-
E. Under the said Memo No. 4146/HIDCO/Admn-681/2004 dated
22
nd
, October, 2005, it was inter alia specified that:-
i) The Developer shall act as a developer of HIDCO with
regard to the development of the said plot by construction of
the said Housing Complex and sale and allotment of the
constructed dwelling units to NRIs and Resident Indians.
In this Agreement, unless there be something contrary or repugnant
to the subject or context:
(ii) "HOUSING COMPLEX" shall mean the said plot and the
new buildings to be constructed thereon in accordance with
the sanction plan thereof comprising of approximately 900
13
(nine hundred) residential units, car parking spaces, internal
roads and all other constructed areas or spaces needed for
use and enjoyment of the Housing Complex and shall
include such other common facilities and/or amenities
that may be required, installed and/or provided therein or
therefor for more better enjoyment of such units/flats, car
parking spaces other entertainments, commercial hubs,
worship place, golf course, swimming pool as are admissible
under relevant building rules and/or other constructed areas
or spaces by the owners thereof
(ix) "SANCTION PLAN" shall mean the plan for construction of
the new buildings at the said plot, to be prepared by the
Architect and caused to be sanctioned by the Developer from
the HIDCO and shall include modifications, alterations
additions and/or amendments thereof of thereto male or
caused by the Developer with the approval of HIDCO
(xv) "PROJECT" shall mean and include the project of the,
development of the Housing Complex and construction of the
new buildings at the said plot for allotment of at least 75% of
the total units, car parking spaces and other constructed
areas or spaces comprised therein to Non-Resident Indians
(NRIs) and the balance to Resident Indians;
ARTICLES-VII
RIGHTS OF THE PARTIES
7.1 It is clarified that this agreement is not an agreement for sale
and/or otherwise transfer of the said plot or any part thereof to the
Developer, but is merely an agreement allotting the said plot to the
Developer and authorising the Developer to develop the said plot by
constructing and completing the said Housing Complex consisting
of a number of new buildings and allotment of the several
independent and self-contained flats, units, car parking spaces,
other entertainment, commercial hubs, worship place, golf
course, swimming pool as are admissible under relevant building
rules and other constructed areas or spaces therein to the intending
buyers thereof.
8.5 The said plot shall be used exclusively for residential
purposes only with such other use as is absolutely related for a
residential complex and as permissible under law.
Emphasis Applied
38. The said development agreement directed RDPL to develop and
construct a ‘housing complex’ on the subject bulk plot. All
14
construction thereon should therefore be in harmony with a housing
residential project.
39. Clause no. 2 thereof defined "Housing Complex" which includes
commercial hubs. The phrase commercial hub is preceded by terms
"better enjoyment," "other entertainments", and "common facilities".
The commercial hubs were therefore conceptualized as common
facilities for the residents.
40. Clause 7.1 mandates that residential units must be "self-
contained,”. Thus the retail/commercial facilities thereat are in aid
of the residential project. They are not independent of the
residential units.
41. Clause 8.5 thereof explicitly states that the bulk plot must be used
exclusively for residential purposes. Any ancillary use should strictly
be limited to the benefit of residents.
42. The development agreement conferred the right to develop a
residential project on RDPL. The agreement authorized RDPL only to
sub-delegate the development work and nothing further.
43. RDPL was authorized to sell the residential units and other non-
residential facilities to buyers. The agreement did not confer any
right of title and ownership on RDPL. Therefore, RDPL could not
have sold any vacant land before developing it.
44. HIDCO continued to own the subject bulk plots. However, HIDCO
restricted its right to sell vacant land thereat by appointing RDPL to
develop the subject bulk plots and sell only constructed units.
45. In Chairman, Indore Vikas Pradhikaran v. Pure Industrial
Coke & Chemicals Ltd. & Ors., reported in (2007) 8 SCC 705, it
15
was held that a Town Planning Act regulates the development of the
land as follows:-
57. The Act being regulatory in nature as by reason thereof the right of
an owner of property to use and develop stands restricted, requires
strict construction. …………..Restrictions are made in larger public
interest. Such restrictions, indisputably must be reasonable ones . (See
Balram Kumawat v. Union of India10; Krishi Utpadan Mandi Samiti v.
Pilibhit Pantnagar Beej Ltd.11 and Union of India v. West Coast Paper Mills
Ltd.12)
Emphasis Applied
46. In State of Gujarat v. Shantilal Mangaldas & Ors., reported in
(1969) 1 SCC 509, it was held that when a town planning scheme is
declared under the Town Planning Act, the right to develop the bulk
plots, governed by the town planning scheme, stands restricted.
Paragraph no. 55 of Shantilal decision ( supra) is set out below :-
55. ……Once the draft town-planning scheme is sanctioned, the
land becomes subject to the provisions of the Town Planning
Act, and on the final town-planning scheme being sanctioned,
by statutory operation the title of the various owners is
readjusted and the lands needed for a public purpose vest in the
local authority.
Emphasis Applied
47. The development agreement has specified the nature and scope of the
project. RDPL, therefore, could not travel beyond the scope of the
development agreement. HIDCO is equally bound by the mandate of
the development that the subject bulk plot should be developed as a
residential project so also RDPL.
48. Any existing partition of the bulk plot for residential and commercial
sections is therefore liable to be demolished. The parties are ad idem
to the demolition of any such partition.
i) The concept of residential cum retail construction
49. The concept of the residential-cum-retail construction was
addressed in Vasundhara Vyapar Mandal v. U.P. Avas Evam Vikas
16
Parishad, reported in (2004) SCC OnLine All 2067. The division
Bench, presided over by Justice Markandey Katju, addressed the
concept of ‘convenient shopping’ in a residential project as follows :-
46. We have perused the relevant extract of the master plan which is
Annexure II to the writ petition. Under the said master plan certain
convenience shops are permitted in residential areas . The term
convenience shops have not been defined, but obviously it means
shops where items of daily use e.g. bread, milk, vegetables, fruits,
etc. may be available to the residents in the area.
47. However, as stated in para 8 of the counter-affidavit, the Vasundhara
Scheme has already provided for convenience shops in certain places in
the residential scheme. Some of the shops have been built by the
Parishad, while certain vacant plots have been allotted for raising
commercial constructions to permit business activities to satisfy
the daily needs of the residents. Details have been given in para 8 of
the counter-affidavit. It follows that no other commercial activities can be
permitted in any other place other than those earmarked in the
Vasundhara Scheme. It is not the petitioner's case that its members are
carrying on commercial activities at the places earmarked for this
purpose in the Vasundhara Scheme.
48. In fact a perusal of Annexure CA-2, which are the photographs of the
various shops and commercial establishments, shows that the entire
residential Vasundhara Scheme has been disrupted by such shops
and commercial establishments which have been set up by the
members of the petitioner's Society. This is clearly illegal as held in
the decisions referred to above. Hence we find no infirmity in the
impugned order dated 23-1-2004.
49. We are also of the opinion that there can be no compounding
which permits change of the land user. Compounding may be
possible (provided it satisfies the relevant prescribed criteria) to
regularise the construction of additional residential room or storey
in an existing residential house, but not by changing the land use.
Emphasis Applied
50. A division Bench of the Delhi High Court in P.V. Kapur v. Union of
India, reported in 2020 SCC OnLine Del 3054, has also explained
the concept of residential-cum-commercial construction in a
residential project to meet the economic realities of the 21
st century
as follows:-
80. One other scholar G.B.K. Rao in an article titled “Issues in
Controlling Urban Building Activities” in “Control of Urban
17
Building Activities” (edited by D.D. Malhotra) JITPA noted, in the
context of Indian cities in general as under:
“…there is horizontal and vertical mixing of uses primarily
between residential, commercial and industrial use, e.g.
commerce on ground floor and residence in the rear and
on upper floors; and industry, at times in the rear. Often,
traditional industry of the household type flourishes in the
older parts of the city and invariably specific industry type is
found to be associated with specific caste, ethnic or religious
group. In a sense, the mixed pattern or landuses in the older
parts of the cities is very much a gradual evolution of the
pattern established in the past when the urban settlement
was still nourishing its rural moorings. The mixing of
landuses grows with the organic growth of settlements
over a period of time, …. In fact, the central areas of
older cities bustle with life and vitality, during the day
and major part of the night due to such conglomeration
of uses which is sadly lacking in more recent
developments.
82. In preparation of the Perspective Development Plan for Delhi
(1981-2001), the DDA conducted a study, which revealed certain facts
about the extent of mixed use in residential areas as under:
“(1) Instances of mixed land uses were correlated with
the age of development, i.e. higher percentage of
dwelling units used for more than one activities in
areas developed before 1962 as compared to those
after that year.
(2) In case of low-income communities, the instances
of mixing of uses was in respect of retail commercial
activities within residential premises. But in Case of
higher income group communities, non-residential
uses that were penetrating into residential areas were
mostly professional consultancy offices and other
office uses, banks and guest houses.
(3) More than 90% of instances of mixed uses were
confined to ground floors of buildings and upper floor
generally used extensively for residential purposes. In case
of commercial and residential mix use areas, commercial
development spreads linearly along the roads occupying
front portions or whole of the ground floors.”
89. The legal position in relation to the permissibility of commercial
activities in a residential zone was summarised thus:
“i) there cannot be a commercial activity in
residential zone and thus chemists shops are not
permitted.
ii) the area in question does not fall in the mixed-use.
18
iii) the DDA & MCD are required to take action under the
respective laws against these violators running chemists
shops in the residential zone, viz in a building allowed to
be used for the purpose of residence only by the
competent authority.”
Emphasis applied
51. In Vasundhara Vyapar Mandal decision (supra) , it was held that
convenient shopping provided within a residential complex cannot be
converted for commercial exploitation. It is for exclusively serving the
residents of the said project.
52. In P.V. Kapur decision (supra), it was held that commercial
exploitation of a residential unit or a residential area is not permissible.
The concept of convenient shopping under the bracket residential-cum -
retail project is as follows:-
a) Residents gain immediate walking-distance access to gyms,
grocery stores, restaurants, offices, healthcare, childcare,
banking, parks, and recreational facilities, simplifying daily life
and freeing up time.
b) Mixed-use occupancy cuts down long commutes and vehicular
emissions by encouraging walking and cycling thereby reducing
our carbon footprint.
c) Developments feature everything from cozy cafes and boutique
stores to high-end restaurants and supermarkets, attracting a
broad customer base.
53. Mr Jayanta Mitra, Ld. Sr. Counsel for Respondents No. 7 to 9,
contended that the HIDCO Planning Area 2006 Rules permit mixed
occupancy for diverse non-residential purposes, such as IT hubs meant
for the general public, not just residents. Both HIDCO and NKDA relied
19
on these mixed-occupancy provisions to sanction. NKDA subsequently
revised the HIDCO plan of 2009 in April 2011. He argues that these
provisions entitle RP to allow outsiders to access non-residential facilities
within a residential project. He argues that 10 % of the bulk plot can be
used for Mercantile (Retail) purposes and all other commercial purposes
as defined in Rule no. 3 of the Planning Area (Building Operations)
Regulations, 2006. This argument cannot be accepted.
54. While the township planning rules outline various ‘land uses’, the
planning authority holds the final discretion to conceive plans and
choose land use. In the development agreement (supra), HIDCO
permitted limited non-residential construction over the bulk plots, that
too in aid of the Residents.
55. The definition of ‘housing complex’ in the development agreement
(supra) has not included IT and other non-residential facilities. It, inter
alia, included facilities such as club house, swimming pool, golf course,
place of worship, etc. These are, therefore, facilities aimed to serve the
residents living thereat. The phrase "better enjoyment and common
facilities" in the ‘housing complex’ definition ensures that every non-
residential facility thereat must ultimately serve the residents.
56. Thus, the development agreement did not provide for the access of
outside public to the non-residential facilities. This is reaffirmed in
Clause no. 8.5 of the development agreement.
20
II. The Legal Status of the HIDCO Plan dated August 27
th
,
2009.
57. HIDCO has been constituted under the West Bengal Town and
Country (Planning and Development) Act, 1979 (Act of 1979). It
carried the mandate to develop a residential project in the subject bulk
plot. Section 13 of the Act of 1979 sets out the power of the ‘planning
authority’ as follows:-
Section 13 Powers and functions of Planning Authority and
Development Authority.
(1) Subject to the provisions of this Act, and the rules made
thereunder and any direction which the State Government
may give from time to time -
(i) a Planning Authority shall have the following powers and
functions :-
(a) to prepare Land Use Map;
(b) to prepare and enforce [a Land Use and
Development Control Plan;]
(c) to prepare and enforce a Detailed
Development Plan;]]
(d) to prescribe use of land within its area;
(e) to perform any other function which is
supplemental, incidental or consequential to
any of the functions aforesaid or which may be
prescribe
Emphasis Applied
58. HIDCO prepared a development plan namely, the development
agreement executed with the RDPL herein. It prescribes the use of land
to be developed namely, a residential project herein. Section 46 of the
Act of 1979, enables a developer to apply for permission before the
planning authority to develop a planning area, namely, the RDPL herein
and subject bulk plot. Section 46(1) and (2) of the Act of 1979, are set
out below:-
Section 46- Permission for development .
(1) Any person or body (excluding a department of the Central or the
State Government or any local authority) intending to [carrying out
21
any development or township project on any land] for carrying out
any development on any land.] shall make an application in
writing to the Planning Authority or Development Authority for
permission in such form and containing such particulars and
accompanied by such documents and plans as may be
prescribed.
(2) On such application having been duly made, and on payment
of the development charge as may be assessed under Chapter IX. -
(a) The Planning Authority or the Development
Authority may pass an order, -
(i) granting permission unconditionally; or
(ii) granting permission subject to such conditions as
it may think fit; or
(iii) refusing permission,
Emphasis Applied
59. HIDCO was declared as the ‘planning authority’ for the entire Mouza
Patharghata, JL Number 36. All subject bulk plot fall within the
jurisdiction of Mouza Patharghata, JL Number 36.
60. The Act of 1979 is a non-municipal legislation. Thus, in exercise of
powers under the Act, 1979, the ‘Planning Area Building Operation
Rules, 2006’ and ‘the Building Regulations of 2006’, were notified. Under
the said rules of 2006, HIDCO was empowered to sanction building
plans, grant occupation certificates, and address unauthorized
constructions.
61. The aforesaid executive notifications and the rules referred to
hereinabove have never been withdrawn in exercise of powers under
Section 10 of the Act of 1979, which is set out below:-
10. Power to withdraw Planning Area from the operations of this
Act.
(1)The State Government may, by notification, withdraw
from the application of this Act any Planning Area or
part thereof.
(2)When a notification is issued under sub-section (1) in
respect of any Planning Area or part thereof
(i)this Act and all notifications, rules, regulations,
orders, directions and powers issued, made or
22
conferred under this Act shall cease to apply to
the said area or part thereof;
Emphasis applied
62. These executive notifications were, in fact, regularized by and under The
New Town Kolkata Planning Area Building Rules, 2014. It has
recognized that in the New Town Area, HIDCO and NKDA will share power
of regulating building operations over plots of land. Both NKDA and
HIDCO thus continued to have jurisdiction in the new town area, where
the bulk plot are situated. The rival parties do not contest the power of
NKDA to grant the revised plan dated April 26
th
, 2011. RP, however,
objects to the modifications made in the NKDA revised plan from HIDCO
plan dated August 27
th, 2009.
63. The development agreement entrusted the RDPL to develop the entire
16.32 acres of land. It did not draw up the boundaries within the 16.32
acres. The HIDCO sanction plan specified the quantity of land for
constructing 6 residential towers, clubs, commercial hubs and etc. The
particulars of the HIDCO sanction plan are set out below:-
Nature of Construction Extent of Area allotted
1. TOTAL AREA OF
TOWER 1, 2,3,4, & 6-
1,03,481.30 Square meter
2. TOTAL AREA OF
TOWER 5
19,888.88 Square meter
3. TOTAL AREA OF
SENIOR RESIDENCE.
- 3891.83 Square meter
4. TOTAL AREA OF
SERVANT QUARTER
1020.05 Square meter
5. TOTAL AREA OF CLUB
BUILDING
1706.70 Square meter
6. TOTAL AREA OF
RETAIL BUILDING
3898.52 Square meter
7. TOTAL AREA OF ESS
ROOMS
1,529.50 square meter
8. TOTAL AREA OF
CONSTRUCTION
SANCTIONED
24,952.68 SQM.
23
64. The primordial object of the HIDCO therefore was to develop the subject
bulk plot into residential units. This is evident from the major part of the
land allotted was for constructing 6 residential towers. HIDCO has also
sanctioned land for construction of units for senior residents and quarters
for servants. The areas allotted for Retail and other constructions,
therefore, were essentially in aid of residents living thereat. The WBHIDCO
plan is in harmony with the development agreement (supra).
III) The Legal Status of the NKDA revised plan
65. Ld Counsel for the NKDA has submitted that the subject plot is under
his client’s jurisdiction. By reason of amendment to Section 10 of the
NKDA Act in the year 2010, it had the power to consider modifications to
existing plans including that of HIDCO.
66. Even if one considers the argument to the contrary advanced by
Counsel for RP, this court notices as follows. By legislative notification
No. 1088-L, dated June 27
th
, 2008, the Newtown Kolkata
Development Authority Act, 2007 was gazetted and notified with
retrospective effect from December 28
th
, 2006. The NKDA Building Rules,
2009 came in force from August 10
th
, 2009.
67. HIDCO sanctioned the building plan on August 27
th, 2009, i.e. after
the NKDA came to be constituted. The Developer, therefore, could have
approached NKDA for a sanction on August 27
th, 2009. It, however, chose
to apply before the HIDCO. Therefore, HIDCO acted as the sanctioning
authority for building operations at the bulk plots, as did the RDPL.
68. The role and presence of New Town Kolkata Development Authority
(NKDA) in the day to day life of the residents of the Rosedale project
24
assumes immense importance. A separate and independent legislation
namely, the New Town Kolkata Development Authority Act, 2007 was
enacted to grant sanction plans and deal with unauthorized constructions
and completion certificates. NKDA has also set up a municipal mechanism
for providing essential services such as water supply and other utilities.
69. NKDA employs competent engineers and architects who possess the
expertise to understand the structural firmness and architectural value of
buildings. NKDA has the expertise to analyse and potentially modify the
HIDCO plan or grant sanction for subject plots. It lacked the territorial
jurisdiction over the subject plots, which continues to lie with HIDCO. The
NKDA authority however did not lack inherent jurisdiction over the
subject matter.
70. While want of inherent jurisdiction renders an order a nullity, an order
passed without territorial jurisdiction, however, is merely irregular. In
Hira Lal Patni v. Kali Nath [Hira Lal Patni v. Kali Nath, reported in
AIR 1962 SC 199, it was held as follows:-
The objection to its [Bombay High Court] territorial jurisdiction is one which
does not go to the competence of the court and can, therefore, be waived .
In the instant case, when the plaintiff obtained the leave of the Bombay High
Court on the original side, under Clause 12 of the Letters Patent, the
correctness of the procedure or of the order granting the leave could be
questioned by the defendant or the objection could be waived by him. When he
agreed to refer the matter to arbitration through court, he would be deemed to
have waived his objection to the territorial jurisdiction of the court, raised by
him in his written statement. It is well settled that the objection as to local
jurisdiction of a court does not stand on the same footing as an objection to the
competence of a court to try a case.
Competence of a court to try a case goes to the very root of the
jurisdiction, and where it is lacking, it is a case of inherent lack of
jurisdiction. On the other hand, an objection as to the local jurisdiction of a
court can be waived and this principle has been given a statutory recognition
by enactments like Section 21 of the Code of Civil Procedure."
Emphasis applied
25
71. In Hasham Abbas Sayyad v. Usman Abbas Sayyad, reported in
(2007) 2 SCC 355, it was held as follows:-
"24. We may, however, hasten to add that a distinction must be made
between a decree passed by a court which has no territorial or pecuniary
jurisdiction in the light of Section 21 of the Code of Civil Procedure, and a
decree passed by a court having no jurisdiction in regard to the
subject-matter of the suit.Whereas in the former case, the appellate
court may not interfere with the decree unless prejudice is
shown,ordinarily the second category of the cases would be interfered
with."
Emphasis Applied
72. In M/S Aarsuday Projects & Infrastructure (P) Ltd v. Jogen
Chowdhury & Ors., reported in 2026 INSC 93, it was held lack of
territorial jurisdiction of the sanctioning authority is a curable
irregularity when the construction is done honestly as follows:-
36. Likewise, even if it is assumed that the Gram Panchayat was not the
competent authority to accord approval to the building plan and that such
authority vested exclusively in the Panchayat Samiti, the same would
constitute, at best, a procedural irregularity. Such an irregularity, especially
where the building plan had been duly vetted by the higher forum, i.e., the
ZillaParishad and construction was undertaken in a bona fide manner, was
clearly curable in nature. In the absence of any tangible evidence of
fraud, misrepresentation, or deliberate circumvention of statutory
requirements, such a procedural lapse, even if assumed to exist, for
arguments sake, could not render the construction per se illegal, nor could it
justify the issuance of a direction for demolition, which is an extremely
draconian consequence reserved for cases of blatant and substantive
illegalities and violation.
Emphasis Applied
73. The salient features of the NKDA revised plan are set out below
Nature of
Construction
Extent of area
(Sanctioned earlier
in the WBHICO
building plan)
Extent of area (proposed
for sanction in the NKDA
revised plan)
1. Total area of
Tower nos. 1, 2,
3, and 6
82, 785.04 square
meter
83, 030. 96 square meter
2. Total area of
Tower no.4
20.696.26 square
meter
20, 693. 69 square meter
26
3. Total area of
Tower no. 5
19.888.88 square
meter
19, 979 square meter
4. Total area of
Senior
residence
3891.83 square meter 2580.10 square meter
5. Total area of
club building
1706.70 square meter 1712.17 square meter
6. Total area of
retail building
with ESS
3,898.52 square meter 2156.81 square meter
7. Total area of
Executive
apartment
New Building Proposed 6517.33 square meter
74. NKDA modified the HIDCO plan to include an executive apartment. This
is in furtherance of the development agreement's core motto of serving
residents without violating the said agreement. The introduction of an
executive apartment is just one more facility added to the bucket of
facilities for the residents. The NKDA was therefore well within its authority
to introduce an executive apartment in the Revised Plan dated 26
th April
2011. The HIDCO plan dated 27
th August 2009 has been superseded by the
NKDA re-sanction dated 26
th April 2011.
75. The conduct of the parties also demonstrates that the NKDA revised plan
of 26
th April 2011 was accepted and acted upon by them:-
a) In the inspection conducted by NKDA on 28
th Nov 2018 pursuant
to order dated 15
th
November 2018 passed in WP 21146 of 2018,
violation of the NKDA Sanction plan of 26
th
April 2011 was found.
b) RP in its writ petition WP.24454 of 2018 asked for extension of re-
sanction of the NKDA plan of 26-04-2011.
c) RP admitted that the NKDA re sanction dated 26-04-2011 was
the basis of the conveyance between RDPL and RP dated 19
th
May 2014.
27
d) Prayer C of WP 24454 of 2018 was for extension of re-sanction
dated 26-11-2011.
e) The said revised sanction of NKDA, removed the first floor from
the Retail area. It reduced the Senior Citizens building from
Ground plus II to Ground Plus I, and omitted the Servants
quarters to accommodate an Executive Tower of Ground plus IX
floors.
f) The removal of servants' quarters and reduction in the height of
the senior citizens quarters done to facilitate the construction of
the executive apartments was within the original FAR under the
HIDCO as well as the NKDA plans, for the whole project. There
is no alteration in the nature of user of the modified
construction in the project i.e. residential. The modified sanction
dated 26
th April 2011 by NKDA rightly approved and re-
sanctioned the same.
g) The conveyance of the year 2014 between RDPL HIDCO and RP
only transferred 18,218 Square feet comprising in a Ground
Floor, Ramp etc. This was the retail area in the re-sanctioned
plan dated 26
th
April 2011. They have purchased only 18,218
square feet out of entire reduce retail area of 27,000 odd square
feet. RP thus cannot maintain a claim to construct the entire
G+1 retail floor sanctioned in HIDCO plan for the entire retail
area.
h) The reduction of the retail area to increase the residential area
is lawful and in harmony with the original development
28
agreement between RDPL and HIDCO of the year 2009, of the
project being a Residential one.
i) The clauses in the conveyance dated 19
th May 2014 restricting
the rights of the parties not to construct on the roof of the
ground floor of the Retail area are in furtherance of the revised
sanction dated 26
th
April 2011.
j) RP and the appellants jointly submitted an application under
Section 10 of the WB Apartment Ownership Act 1972, referring
to the retail area to be restricted to 18,218 Sq Ft in terms of the
re-sanctioned building plan dated 26
th
April 2011.
k) The residential owners would require grocery shops, and etc.
and hence the commercial hubs. These commercial/retail hubs
must be aligned with the development agreement.
l) A deemed consent thus flows from the conduct of both the
residential flat owners and RP to the NKDA Revised Plan dated
26
th April 2011.
ii. The propriety of NKDA to grant a re-sanction on April 26
th, 2011
under the HIDCO building Rules and Regulations, 2006
76. NKDA sanctioned the revised plan under the HIDCO Building Rules
and Regulations, 2006. The reason therefor flows from Rule 4A of the
NKDA Building Rules, 2009, which is set out below:-
4A. Provision of Re-Sanctioning of existing building plan : (1)
Notwithstanding anything contained in these rules —
(a)********
(b)*********
(2) where construction has been commenced and the previous
sanction of the building plan has been obtained in violation of
the provisions of these rules, the re-sanction of the building
29
plan shall be made under the provision of this rule on the
request of the applicant:
Provided that if the building is already constructed, in part
or in full, on the basis of such building plan which has
been obtained in violation of the any provisions of these
rules, shall be seized to exist unless the contradiction is
removed and if the contradiction has not been removed,
the re-sanction may be processed as per the provisions
of respective rule under which the original plan has
been sanctioned unless the applicant opts for sanction of
building plan under these rules.
Emphasis Applied
77. Sub-rule 2 of Rule 4A governs the NKDA revised plan dated April
26th, 2011. Sub-rule 2 applies when construction is made according to
a Plan, sanctioned under different rules by another authority. In the
instant case, the original plan was sanctioned by HIDCO in 2009 under
the HIDCO Building Rules and Building Regulations, 2006.
78. Under sub-rule 2, ordinarily, the re-sanction of such constructions at
the first instance should be attempted to be done under the NKDA
Building Rules, 2009. The proviso to sub-rule 2, however, clarifies that
at the time of re-sanction, if NKDA finds that the existing construction
contradicts the Rules of 2009, NKDA may either remove such
contradiction. If it cannot be removed, NKDA may re-sanction the
revised plan as per the rules under which the Original Plan was
sanctioned.
79. In the present case, the HIDCO plan was sanctioned under the
HIDCO Building Rules, 2006. The proposal to introduce the executive
apartment amounted to a change in the said HIDCO plan. This could
be in violation of NKDA Building Rules, 2009. NKDA thus re-sanctioned
the executive apartment in line with the object of the development
30
agreement, under the HIDCO Building rules of 2006, in terms of the
proviso to sub rule 2 of Rule 4A.
IV) The Right of RP on the Subject Bulk Plots
80. The conveyance dated May 19
th
, 2014 executed in favour of Rp
and/or its predecessor-in interest needs to be examined in light of
development agreement. The relevant clauses from the said
conveyance are set out below:-
ii. PREMISES shall mean Commercial building for the time being
consisting of entire space of 18643 sqft (SBA)constructed by the
Developer at the said plot to be used as self-contained
apartments, shops, show rooms, offices and other constructed
spaces in the Building capable of being exclusively held or
occupied by a person, morefully and particularly mentioned and
described in the SECOND SCHEDULE hereunder.
ix. SUPER BUILT-UP AREA shall where the context refers to the
said Unit (the entire Retail cum Commercial building of
18643 sq.ft S.B.A. little more or less) mean and include (a)
the super built up area of the said Unit, (b) proportionate
share of the area of the Common Areas and Installations
and open areas including top roof of the Premises.
xi. SAID UNIT shall mean the entire Retail cum Commercial
building of 18643 sq.ft S.B.A. little more or less to be
constructed &finished in parity with the morefully and
particularly shown in the brochure complex and as mentioned
and described in the SECOND SCHEDULE hereunder written
TOGETHER WITH the Purchaser's proportionate undivided
share in the common areas and Installations attributable to the
said Unit TOGETHER ALSO WITH the right to use the open
spaces on the top roof of the Premises and wherever the context
so permits shall include the right of parking motor car at the car
parking space at the said premises if so specifically and as
expressly mentioned and described in the within stated
SECOND SCHEDULE and wherever the context so intends or
permits shall also include the said share in the said premises.
xiii. PURPOSE OF USE shall mean usage of the space for
Retail commercial purpose including provision for ATM
facility. Grocery Stores, Utility shop, Pharmacy, & others.
SALE OF PROPERTY AND CONSIDERATION: The Developer
agrees to sell and transfer ALL THAT the said Unit being the entire
Retail cum Commercial building 18218 sqft more or less (15325
31
sqft Builtup area approx. + 1500 sqft. approx. of passage + 1393
sqft. stair, ramp, platform etc.
THE SECOND SCHEDULE ABOVE REFERRED TO:
ALL THAT of entire 18218 sqft more or less (15325 sqft Built up area
approx. + 1500 sqft. approx of passage + 1393 sqft. stair. ramp,
platform etc.) of the Retail cum Commercial building to be constructed
&finished in parity with the complex and as shown in the brochure.
The space to be given an bare shell with brick work & plaster with
provision for for six to ten toilets at north-west corner as shown in the
plan annexed
81. HIDCO’s sole mandate was to develop land or have it developed through
a designated developer. The original development agreement with the
RDPL permitted RDPL to sub-delegate the construction work, but not
transfer of land title. The execution of the conveyance date May 19
th
, 2014
conferring exclusive rights and title of a portion of the bulk plot to RP,
thus, violates the development agreement. RP could at best have been sub-
developer.
82. The said conveyance between RP, HIDCO, and RDPL initially covered
15,000 square feet, which was later increased to 18,218 square feet
handed over as a bare shell. HIDCO’s approved sanction plan dated
August 27, 2009 allocated a total area of 3,898.52 square meters
(equivalent to 41,963.32 square feet) for the retail building.
83. Out of the total 41,963.32 square feet, only 18,218 square feet was
transferred to RP, leaving 23,320.32 square feet un-transferred. The non-
transfer of the entire retail area in favour of RP, clearly implies that HIDCO
and RDPL engaged in a private sale of the 18,218 square feet plot to RP.
Any transfer could at best have been for development of the retail area. No
undeveloped part or portion of the bulk plot of 16. 32 acres could have
been transferred to RP by RDPL and HIDCO.
32
84. Clause 13 of the conveyance confirms that the commercial structures
were meant to serve residents through amenities like ATM facilities,
grocery stores, utility shops, and pharmacies. Such facilities could only be
exploited by RP to the extent of 18, 218 that too ‘ ordinarily and
primarily’ for the benefit of the residents. Clause no. 13 should govern
the constructions made by RP. This aligns the purported conveyance in
favour of RP with the development agreement (supra).
85. Hence the absolute transfer of the 18,218 square feet to RP by RDPL is
illegal. In light of the development agreement (supra),RP can at best be
accepted as the entity to construct and manage the retail area for the
exclusive benefit of the Residents. Any construction made beyond 18, 218
Square feet or beyond the sanction plan dated 26
th April 2011 issued by
NKDA is illegal and is liable to be demolished and removed.
86. The learned Single Judge erred by holding that RP’s right to construct
over the entire retail area stems from the HIDCO plan. RP’s sale deed
explicitly restricted its construction rights to 18,218 odd square feet out of
the broader retail pool. RP is bound by the NKDA revised plan dated 26th
April 2011 that reduced the area of retail construction to 27,000 odd
square feet, of which it has received rights only in respect of 18,218 Sq ft.
RP is therefore strictly prohibited from effecting construction under the
HIDCO plan of August 2009, which has been superseded by the NKDA
revised plan dated April 26
th
, 2011.
87. Ld. Counsels and Sr. Counsel for the RP have conceded that RP’s right
over the retail area does not extend beyond 18, 218 square feet, purchased
by it from RDPL. This would also imply that RP cannot question the NKDA
revised plan. The NKDA revised plan reduced the area of construction for
33
the retail area to 27,000 odd square feet. RP enjoys a lesser area of 18,218
square feet therefrom.
88. The aforesaid concession of counsel for RP implies, as a logical corollary,
that it cannot claim to construct a G+1 structure at the retail area as the
revised sanction plan of NKDA has modified the retail structure to mean
ground plus roof, stairway and ramp etc. The reason is that RP was
transferred 18,218 square feet. The rest of the retail area sanctioned in
both plans was not transferred to it.
89. With the reduction of the retail area in the NKDA revised plan, the
height and breadth of the structure to be built thereon would equally
reduce. The reduction from G+1 to Ground floor and Roof in the NKDA
revised plan was thus an obvious consequence of the reduction of the
retail area from 41, 000 odd square feet to 27, 000 odd square feet.
90. RP cannot claim a right to construct the entire ground floor plus roof
sanctioned in the NKDA revised plan dated April 26th, 2011 since the
same was sanctioned for the entire retail area of 27,000-odd square
feet, of which only 18,218 square feet was purchased by RP. The right
of the RP to make constructions in the retail area, therefore, should be
proportionate to the 18,218 square feet.
D. CONCLUSIONS
91. The Rosedale Garden and RP are a part and parcel of a singular
residential housing project comprising in about 16.32 acres. The Entire
project is under the New Town Kolkata Development Authority. The only
valid sanction plan in respect of the retail and residential areas is dated
26
th
April 2011.
34
92. The retail part of the housing project comprising in about 18,218
square feet purchased by RP, is meant primarily for the use and benefit
of the residents and members of the Appellant.
93. The rights of the respondent RP in respect of the retail part of the
project is restricted to making construction and running of the retail area
to the extent of 18, 218 Square Feet, strictly in terms of the NKDA
sanction Plan dated 26
th
April 2011.
94. The MOU dated 27
th
November 2009, agreements dated 7
th
April 2010
and 30
th
April 2011 and the Conveyance dated 19
th
May 2014, cannot be
invoked to sub-divide the plot of 16.32 Acres into commercial and
residential use. The counsels including the Ld. Sr. Counsel for RP,
respondent nos. 7-9 has agreed and admitted to the same.
95. The Conveyance dated 19
th May 2014, is a contract of sub-agency
permitting RP to construct, run, exploit and manage the retail area in
terms of the NKDA plan of 26
th April 2011.
96. All gates installed at the subject bulk plots are declared an integral
part of and provide access to, the residential-cum-retail area. Such gates
shall not be construed as separating the retail area from the residential
area. This direction aligns the subject bulk plots with the development
agreement under the Town Planning Act, 1979.
97. The order of NKDA dated February 27
th
, 2019 is set aside. The NKDA
RTI reply cum report dated October 7
th
, 2020, absolving RP of any un-
authorized construction is set aside.
35
E. DIRECTIONS
98. The NKDA shall ensure that existing constructions at RP, including
residential towers and retail shops, comply with the development agreement
dated 24
th
February 2006 between HIDCO and RDPL, and the re-sanctioned
plan of NKDA dated 26
th
April 2011.
99. Respondent Nos. 7 to 9, are not entitled to make constructions exceeding
18,218 sq. ft. of the total retail area of 27, 000 odd square feet. The retail
area outside the aforesaid 18, 218 square feet shall not be used by RP. The
NKDA shall demolish all and any construction made by Respondents Nos.7-9
and/or M/s RP beyond the 18,218 square feet, in the retail area demarcated
in the NKDA plan dated 26
th April 2011, within two months from date.
100. NKDA shall further demolish the existing partition by fence, separating the
residential complex from the commercial complex. For the said purpose the
NKDA shall depute appropriate engineers and officers to ascertain the extent
of illegal construction made by respondents Nos.7-9 and M/s RP over the
subject bulk plot and take steps as directed hereinabove. The costs of
demolition shall be recovered from RP.
101. The RP shall be at liberty to cordon off 18,218 square feet of the 16.32
acres of land together with limited access area as per the NKDA Act and
Rules framed thereunder to demarcate the length and breadth of its right
over the subject plots. This is to ensure the privacy of the residents of bulk
plot.
36
102. MAT 519 of 2024 is disposed of. Consequently all connected applications,
if any, are disposed of in terms of this judgement. The impugned judgement
is set aside to the extent that it is inconsistent with the above.
103. There shall be no orders as to costs.
(Rajasekhar Mantha, J.)
I Agree
(Anuj Singh, J.)
Later:
After the judgment is pronounced in open Court, the Joint Special Officer
appointed by the Coordinate Bench in this appeal, shall stand discharged. The
remuneration already paid shall constitute final remuneration to the Special
Officer.
(Rajasekhar Mantha, J.)
I Agree
(Anuj Singh, J.)
Legal Notes
Add a Note....