As per case facts, the Petitioner submitted a bid for a highway project, but its technical bid was deemed non-responsive by the Respondent. The main issue was the calculation of ...
W.P.(C) 3885/2026 Page 1 of 37
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 05.05.2026
Judgment pronounced on: 29.05.2026
Judgment Uploaded on: 29.05.2026
+ W.P.(C) 3885/2026, CM APPL. 19062/2026, CM APPL.
20206/2026, CM APPL. 21085/2026 & CM APPL. 24254/2026
S AND P INFRASTRUCTURE DEVELOPERS PVT LTD
.....Petitioner
Through: Mr. Gaurav Chopra, Sr. Adv.
along with Ms. Anusuya
Salwan, Mr. Jatin Bansal, Mr.
Divyam Suri, Mr. Afaq
Sherwani, Mr. Shantanu
Mishra, Mr. Jagrit Vyas and
Mr. Himanshu Bindal, Advs.
versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA
....Respondent
Through: Mr. Sanjay Jain Sr. Adv.Along
with Mr. Santosh Kumar,
Standing Counsel, Mr. Ritik
Dwivedi, Mr. Devansh
Malhotra, Mr. Adithya Ramani,
Mr. Nishank Tripathi, Ms.
Harshita Sukhija, Ms. Rishika
Agrawal and Ms. Priya Tyagi,
Advs. for R-1.
Mr. Dayan Krishnan, Sr. Adv.
along with Mr. Sanjeev K.
Kapoor, Mr. Dhritiman Roy,
Ms. Sania Abbasi and Mr.
Shreedhar Kale, Advs. for R-2.
CORAM:
HON'BLE MR. JUSTICE ANIL KSHETARPAL
HON'BLE MR. JUSTICE AMIT MAHAJAN
W.P.(C) 3885/2026 Page 2 of 37
J U D G M E N T
AMIT MAHAJAN, J.:
1. The present Petition has been filed under Article 226 of the
Constitution of India, seeking the following prayers:
a. Issue appropriate writ, order or directions in the nature of
certiorari quashing the order dated 23.03.2026 passed by the
Respondent rejecting the technical bid of the petitioner as non-
responsive.
b. Issue appropriate writ, order or direction in the nature of
Mandamus directing the Respondent to declare petitioner as
technically qualified, and
c. Issue appropriate writ, order or direction in the nature of
mandamus directing the Respondent to open and consider the
financial bid of the petitioner.
FACTUAL MATRIX
2. Respondent No.1, NHAI vide Request for Proposal (‘RFP’)
dated 12.12.2025 invited bids for the work of Upgradation of existing
highway to two lanes with paved shoulders from Parsarma to Araria
Section of NH-327E on Hybrid Annuity Mode in the state of Bihar on
design, build, operate and transfer basis.In terms of the RFP, the bid
was invited in a two-bid system for selection of the bidder for award
of the project. Under the process, eligibility and qualification of the
bidder was to be first examined based on the details submitted under
the first part (Technical Bid) with respect to the eligibility and
qualification criteria prescribed in the RFP. The financial bid under
the second part shall be opened for the bidders whose technical bids
are responsive to eligibility and qualification requirements as per the
RFP.
W.P.(C) 3885/2026 Page 3 of 37
3. The Petitioner submitted their bid document to Respondent
No.1 on 12.03.2026. In the said bid document, the Petitioner
submitted the Net Worth Certificate of its Associate (Ms. Krishna
Pandey) as on 27.12.2025, certified/authorised by its Statutory
Auditor.
4. Thereafter, on 17.03.2026, Respondent No.1 sent a letter to the
Petitioner seeking certain clarifications including a clarification
regarding the Net Worth of the Associate of the Petitioner, namely,
Ms. Krishna Pandey. Respondent No.1 asked for a clarification
regarding why the Net Worth of the Associate of the Petitioner had
been provided as on 27.12.2025 in the Petitioner’s bid, when the RFP
required the Petitioner to provide the same as on 31.03.2025. The
relevant extract of the said letter is reproduced herein below:
10. Net
Worth
The bidder has submitted the Net Worth of the
Ms. Krishna Pandey as on 27.12.2025 instead
of as on 31.03.2025. Bidder to clarify why the
Net Worth of the Associate has been provided as
on 27.12.2025 instead of 31.03.2025
5. Pursuant the same, the Petitioner submitted clarifications to
Respondent No. 1 on 19.03.2026. In reply to the clarification sought
pertaining to the Net Worth of the Associate of the Petitioner/ Ms.
Krishna Pandey the Petitioner submitted as under:
“The Authority is requested to refer page 108-110 of pdf file
named '3Technica1BidParsarmaArariaPart1' submitted with the
Bid documents. Wherein Net Worth Certificate of Ms. Krishna
Pandey have been issued by Statutory Auditor on 21.08.2025
based on (1) Market value of immovable properties has been
taken on the basis of valuation certificate issued by an Approved
Valuer /Chartered Engineer, and (2) investments in equity shares
W.P.(C) 3885/2026 Page 4 of 37
have been considered at book value of shares as per audited
financial statements as on 31.03.2024.
Therefore, the Net Worth certificate of the Ms. Krishna Pandey
have been issued as per procedures. The same Net Worth is
applicable as on 31.03.2025 as well as on Bid due date.”
6. On 23.03.2026, Respondent No.1 issued a communication
addressing all participating bidders, including the Petitioner, whereby
the technical bid of the Petitioner was held to be ‘non responsive’ on
the ground that the “Assessed Available Net Worth of the Petitioner at
the close of the preceding financial year (FY 2024-25) is less than the
minimum requirement of ₹152.25 Cr. as per clause 2.2.2 (BB) of the
RFP Document.”
7. The Petitioner filed a representation dated 24.03.2026 with
Respondent No.1 vide letter No. S&P/Tender/2025-26/342. The
Petitioner in its representation asserted that its Assessed Available Net
Worth was ₹244.38 Cr., which was well above the minimum
requirement of ₹152.25 Cr.
8. The Petitioner in the aforesaid representation also explained
why it had not earlier submitted the Net Worth of this Associate as on
31.03.2025, while also submitted that it was ready to provide the same
at that juncture, the reasons provided by the Petitioner are as under:
“It is to submit that, the concept of Assessed Available Net Worth
of the bidder was published by the Authority vide circular no.
11.68/2025 dated 6th August, 2025. Earlier there was no
requirement of the same. Therefore, viewing the situation the
Bidder started the practice of taking Net Worth of Associate in
account. However, this Net Worth was available with the Associate
from long time as also was available at close Financial Year 2024-
25. Therefore, the Net Worth of the Associate shall be taken in to
account. it is also to be submitted at Authority is requested to refer
clause 2.1. 18, wherein, nothing is written about the timing of
availability of Net Worth of the Associate. However, the valuation
W.P.(C) 3885/2026 Page 5 of 37
of the assets of the Associate were got conducted after Authority
circular no. 11.68/2025 dated 6th August, 2026. Therefore, the
valuation reports of the Assets of the Associate are also valid as on
close of preceding financial year (FY 2024-25). It is also to submit
that, if the Authority fee ls that, Net Worth of 31.03.2025, then we
are ready to provide the same at the direction of Authority.”
9. Thereafter, the Petitioner vide Letter No. S&P/Tender/2025-
26/343 dated 24.03.2026 submitted a certificate from the Statutory
Auditor of the Petitioner which provided the net worth of the associate
of the Petitioner (Ms. Krishna Pandey) as ₹192.36 Cr as on
31.03.2025.
10. The Petitioner approached this Court assailing the letter dated
23.03.2026 and this Court vide order dated 25.03.2026 directed
Respondent No.1 to not open the financial bids of the subject tender
till the representation of the Petitioner was decided.
11. Respondent No.1, while deciding the Petitioner’s representation
vide communication dated 27.03.2026, observed that although the
Petitioner had furnished valuation reports dated 18.08.2025 in respect
of the immovable properties of Ms. Krishna Pandey, the said reports
nowhere specified that the valuation had been undertaken as on
31.03.2025. Respondent No.1, therefore, treated the valuation as
pertaining to the date of issuance of the reports itself, namely
18.08.2025, and consequently excluded the immovable properties
from consideration while computing the net worth of the Associate.
Respondent No.1 also considered the subsequent Chartered
Accountant’s Certificate dated 24.03.2026, but declined to place
reliance upon the same observing that it was unsupported by any
W.P.(C) 3885/2026 Page 6 of 37
contemporaneous valuation documents establishing the value of the
immovable properties as on 31.03.2025.
12. Respondent No.1 in the aforesaid letter calculated the Assessed
Available Net worth of the Petitioner as ₹121.72 Cr., which was less
than the minimum requirement of Clause 2.2.2. (BB) of the RFP
Document, i.e. ₹152.25 Cr and accordingly decided the bid of the
Petitioner to be Technically Non-Responsive.
13. In response thereto, the Petitioner, vide email dated 28.03.2026,
disputed the computation of the balance value of ongoing PPP works
undertaken by Respondent No.1 and contended that Respondent No.1
had incorrectly assessed the value of completed work in respect of
Projects 1, 2 and 3 by considering only the amounts of MoRTH grant
certified and paid, while ignoring the actual physical and financial
progress already achieved in the projects. The Petitioner further
asserted that the EPC costs adopted by it for the respective projects
were in accordance with the financing documents and were exclusive
of escalation, GST, and other financing components, and therefore
maintained that the “B” value originally submitted by it was correct
and that the calculations undertaken by Respondent No.1 were
erroneous.
14. Thereafter, Respondent No.1, vide communication dated
28.03.2026 issued in response to the Petitioner’s objections regarding
computation of Component “B”, stated that the evaluation had been
undertaken strictly on the basis of the documents furnished along with
the bid and the financial progress reflected therein. Respondent No.1
clarified that, in terms of the MoRTH Circular dated 06.11.2025, the
W.P.(C) 3885/2026 Page 7 of 37
“Estimated Project Cost” included EPC cost, pre-operative expenses,
financing and legal costs, and interest during construction, and
accordingly recalculated the Petitioner’s existing commitments on the
basis of the financing agreements and bid documents on record.
Respondent No.1 further stated that even upon reconsidering the
Petitioner’s contention regarding the percentage of project progress,
the assessed available net worth of the Petitioner worked out to
₹148.812 crores, which remained below the minimum threshold of
₹152.25 crores prescribed under Clause 2.2.2(BB) of the RFP, and
consequently maintained the Petitioner’s status as “Technically Non-
Responsive”.
15. Respondent No.1 proceeded further with the subject tender and
awarded the letter of award dated 30.03.2026 to M/s Dineshchandra
R. Agrawal InfraconPvt. Ltd. This Court vide order dated 22.04.2026
allowed the impleadment application filed by the Petitioner and M/s
Dineshchandra R. Agrawal InfraconPvt. Ltd. was impleaded in the
present case as Respondent No.2. It was also noted in the said order
that the financial bid of the Petitioner was lower than the bid of M/s
Dineshchandra R. Agrawal InfraconPvt. Ltd.
SUBMISSIONS ON BEHALF OF THE PETITIONER
16. Learned Senior Counsel appearing for the Petitioner submitted
that the rejection of the Petitioner’s technical bid by Respondent No.1
was wholly arbitrary and based upon an erroneous determination that
the Petitioner failed to satisfy the minimum net worth requirement
under Clause 2.2.2 of the RFP, despite the Petitioner’s assessed
W.P.(C) 3885/2026 Page 8 of 37
available net worth being above the prescribed threshold of ₹152.25
crores.
17. He submitted that Respondent No.1 arbitrarily excluded 20
immovable properties of the Petitioner’s Associate, Ms. Krishna
Pandey, valued at ₹87.48 crores, solely on the ground that the
valuation reports and auditor’s certificates did not expressly mention
the date 31.03.2025. It was contended that Clause 2.2.2(B) merely
prescribes the reference date for assessing net worth and does not
mandate that the valuation report itself must be issued on that date.
18. He submitted that the Associate’s net worth as on 31.03.2025
stood duly certified by the statutory auditor vide certificate dated
27.12.2025 on the basis of valuation reports dated 18.08.2025 issued
by an approved valuer. Upon Respondent No.1 raising objections
regarding the valuation date, the statutory auditor issued a clarificatory
certificate dated 24.03.2026 reaffirming the net worth position as on
31.03.2025, and the approved valuer thereafter issued a clarification
dated 26.03.2026 specifically stating that the valuation had been
undertaken with reference to prevailing market rates as on 31.03.2025.
19. He further submitted that the RFP prescribed no separate
methodology for determination of the net worth of an Associate, and
therefore valuation of immovable properties by an approved valuer,
duly certified by the statutory auditor, constituted a valid method of
assessment. It was submitted that Respondent No.1 never disputed
either the existence or ownership of the immovable properties, all of
which had been acquired prior to 31.03.2025 through registered sale
deeds.
W.P.(C) 3885/2026 Page 9 of 37
20. It was contended that Respondent No.1 arbitrarily accepted only
the liquid assets of the Associate amounting to ₹16.63 crores while
excluding immovable assets worth ₹87.48 crores, despite the RFP
drawing no distinction between liquid and immovable assets for the
purpose of assessing net worth. Learned Senior Counsel submitted
that the subsequent certificates dated 24.03.2026 and 26.03.2026 did
not introduce any new assets, but merely clarified the valuation date of
the very same properties already disclosed in the original bid
documents.
21. He further submitted that the RFP itself contemplated post-bid
clarifications and updating of the assessed available net worth prior to
opening of financial bids, and therefore Respondent No.1 could not
reject the clarificatory documents on a hyper-technical basis. It was
submitted that the Petitioner’s detailed reply dated 19.03.2026 to
Respondent No.1’s query dated 17.03.2026 was never genuinely
considered, as the impugned rejection order dated 23.03.2026 neither
referred to the said clarifications nor disclosed any reasons or
calculations forming the basis of rejection.
22. Learned Senior Counsel further submitted that Respondent
No.1 repeatedly altered the Petitioner’s net worth assessment after
rejection of the technical bid, thereby exposing the arbitrary and
unreliable nature of the evaluation process. While the order dated
27.03.2026 reflected the Petitioner’s assessed available net worth as
₹121.72 crores, the same was revised within a day to ₹148.81 crores.
Likewise, the “B” value was altered from ₹1082.95 crores to ₹947.49
crores, with Respondent No.1 itself admitting in its Counter Affidavit
W.P.(C) 3885/2026 Page 10 of 37
that certain errors in the earlier computation had “inadvertently” gone
undetected. It was submitted that no material or calculation supporting
the original rejection dated 23.03.2026 had been placed on record, and
the subsequent re-evaluation itself rendered the impugned decision
unsustainable.
23. It was further submitted that no objection regarding the
Petitioner’s computation of the “B” value or Estimated Project Cost
had been raised during the original evaluation process and that the
same was introduced only subsequently during the pendency of the
present proceedings.
24. It was contended that Respondent No.1 acted contrary to Clause
2.2.2(BB) of the RFP by relying upon the MoRTH Circular dated
06.11.2025, despite the same never having been incorporated into the
RFP through any corrigendum. Learned Senior Counsel submitted that
under the RFP, the “Estimated Project Cost” referred only to the EPC
cost reflected in the approved financing documents and did not
include financing costs, interest during construction, or pre-operative
expenses.
25. He submitted that Respondent No.1, by relying upon the
aforesaid circular, altered the methodology for computation of
Component “B” by including financing liabilities and other additional
costs within the Estimated Project Cost, thereby artificially inflating
the “B” component and correspondingly reducing the Petitioner’s
assessed available net worth below the prescribed threshold. It was
submitted that the revised methodology was never disclosed in the
W.P.(C) 3885/2026 Page 11 of 37
tender conditions and was introduced subsequently only to justify the
Petitioner’s disqualification.
26. It was further submitted that even on the basis of Respondent
No.1’s revised computation of Component “B”, the Petitioner would
satisfy the prescribed threshold once the correct value of Component
“A” was considered. Applying the formula prescribed under the RFP,
the Petitioner’s assessed available net worth would amount to ₹237.23
crores, which is substantially above the minimum requirement of
₹152.25 crores.
27. Lastly, it was submitted that during the pendency of the present
petition, Respondent No.1 proceeded with undue haste to issue the
Letter of Award dated 30.03.2026 in favour of the sole remaining
bidder, M/s Dineshchandra R. Agrawal InfraconPvt. Ltd.,
immediately after opening of the financial bids, with the apparent
intent of creating a fait accompli and frustrating the Petitioner’s right
to an effective remedy. It was submitted that only two bidders had
participated in the tender process and the arbitrary disqualification of
the Petitioner defeated the doctrine of a level playing field, thereby
rendering the process violative of Article 14 of the Constitution of
India.
SUBMISSIONS ON BEHALF OF THE RESPONDENT
28. The learned Senior Counsel appearing on behalf of Respondent
No.1 submitted that the present petition is devoid of merit and liable
to be dismissed. He submitted that under Clause 2.2.2(B) of the RFP,
the Petitioner was required to demonstrate a minimum assessed
W.P.(C) 3885/2026 Page 12 of 37
available net worth of ₹152.25 crores as on 31.03.2025. He submitted
that Clause 2.2.2(BB) prescribed the formula for determining assessed
available net worth as “A – (20% of B)”, where Component “A”
represented the net worth of the bidder as on 31.03.2025 and
Component “B” represented the aggregate value of existing PPP
commitments secured by the bidder.
29. In relation to the computation of Component “A”, learned
Senior Counsel submitted that Respondent No.1, vide communication
dated 17.03.2026, had specifically sought clarification from the
Petitioner regarding the valuation of the immovable properties of Ms.
Krishna Pandey, associate of the Petitioner, since the Chartered
Accountant’s certificate forming part of the bid was dated 27.12.2025
whereas the RFP required the net worth to be assessed as on
31.03.2025. It was submitted that the Petitioner, in its response dated
19.03.2026, merely stated that the Chartered Accountant’s certificate
was based upon a valuation undertaken by an approved valuer,
without producing any material to establish that the valuation itself
had been carried out as on 31.03.2025. Learned Senior Counsel
submitted that the valuation reports relied upon by the Petitioner were
admittedly dated 18.08.2025 and did not specify the effective date of
valuation of the properties. Consequently, in the absence of any
indication that the valuation had been undertaken as on 31.03.2025,
Respondent No.1 rightly treated the valuation as pertaining to the date
of the report itself and excluded the said immovable properties while
computing the Petitioner’s net worth.
W.P.(C) 3885/2026 Page 13 of 37
30. He submitted that only such assets of Ms. Krishna Pandey as
were demonstrably reflected as on 31.03.2025, namely cash and bank
balances and loans and advances aggregating to ₹16.63 crores, were
added to the admitted net worth of the Petitioner company amounting
to ₹321.68 crores for the purpose of computing Component “A”.
31. Learned Senior Counsel further submitted that there was no
scope under the tender conditions to cure defects or supplement
deficiencies by placing additional documents on record after expiry of
the bid submission deadline on 12.03.2026. In this regard, reliance
was placed upon Clause 2.14.3.1 of the RFP as well as the decision in
M/s Hazoor Multi Projects Limited v. Union of India, W.P.(C)
3434/2026, to contend that fresh material cannot be introduced after
the bid due date. It was submitted that the subsequent Chartered
Accountant’s certificate dated 24.03.2026 and valuation clarification
dated 26.03.2026 were rightly disregarded by Respondent No.1, as the
same had been furnished belatedly after the technical evaluation and
were intended only to cure defects in the original bid documents.
32. Insofar as computation of Component “B” was concerned,
learned Senior Counsel submitted that the estimated project cost for
existing PPP commitments necessarily included not only the EPC or
civil construction cost, but also pre-operative expenses, financing and
legal costs, and interest during construction. He submitted that the
said interpretation was consistent with the MoRTH Circular dated
06.11.2025. According to Respondent No.1, the Petitioner, while
calculating Component “B”, had considered only the civil
construction cost and excluded other relevant components of the
W.P.(C) 3885/2026 Page 14 of 37
estimated project cost, thereby understating its existing commitments.
It was submitted that the said discrepancy was specifically
communicated to the Petitioner vide letter dated 28.03.2026.
33. Learned Senior Counsel further submitted that the Petitioner
had wrongly sought to attribute mala fides to Respondent No.1 on
account of the revised calculations communicated on 28.03.2026. He
submitted that the subsequent calculation in fact gave greater benefit
to the Petitioner by enhancing its assessed available net worth from
₹121.72 crores to ₹148.812 crores after rectification of certain
arithmetical errors in the earlier computation. It was submitted that
Respondent No.1 had additionally granted benefit to the Petitioner by
including amounts that had become due under milestone charts, even
if not actually received, resulting in an increase of ₹290.23 crores
while computing Component “B”. However, despite such benefit, the
Petitioner’s assessed available net worth still remained below the
prescribed threshold of ₹152.25 crores and therefore the Petitioner
was rightly declared technically non-responsive.
34. Learned Senior Counsel appearing for Respondent No.2
submitted that the Petitioner had admittedly failed to satisfy the
minimum net worth requirement prescribed under Clause 2.2.2 of the
RFP, inasmuch as the assessed available net worth of the Petitioner, as
determined by NHAI, was ₹148.812 crores, which fell below the
prescribed threshold. He submitted that the decision of NHAI to
exclude the immovable properties of Ms. Krishna Pandey while
assessing the Petitioner’s net worth was justified and consistent with
the framework of the RFP.
W.P.(C) 3885/2026 Page 15 of 37
35. He further submitted that Respondent No.1 was barred under
Clause 2.14.3.1 of the RFP from accepting any additional documents
after the Bid Due Date, and therefore the subsequent documents
sought to be relied upon by the Petitioner could not have been
considered. Learned Senior Counsel submitted that after the Petitioner
had already been declared technically non-responsive, it sought to rely
upon a fresh Chartered Accountant’s certificate dated 24.03.2026
certifying the net worth of Ms. Krishna Pandey as on 31.03.2025. It
was submitted that unlike the earlier certificate forming part of the bid
documents, the said certificate was not based upon any valuation
report, but had been issued merely on the request of Ms. Krishna
Pandey and was unsupported by any contemporaneous material. He
submitted that Respondent No.1, while rejecting the Petitioner’s
representation on 27.03.2026, had specifically declined to consider the
said certificate on the ground that it was unsupported by relevant
valuation documents.
36. He submitted that the subsequent valuation certificate dated
26.03.2026 issued by the same valuer was also a self-serving
document created after rejection of the technical bid solely to cure
deficiencies in the original bid documents. It was submitted that the
said certificate, for the first time, stated that the earlier valuation
report dated 18.08.2025 had assessed the properties as on 31.03.2025,
despite there being no such indication either in the original valuation
report or in the earlier Chartered Accountant’s certificates.
37. He submitted that Respondent No. 1 has elaboratively explained
the entire calculation of component A and B undertaken by
W.P.(C) 3885/2026 Page 16 of 37
Respondent No. 1 and the same does not involve any arbitrariness or
discrimination. He submitted that in such circumstances, no ground to
interfere has been made out, and the present petition is consequently
liable to be dismissed.
ANALYSIS
38. Before this Court embarks on the journey to delve into the
examination of the merits of the case, at the outset, it is apposite to
briefly note the scope of judicial review in matters pertaining to public
auction/tender. It is not in doubt that the terms concerning the
invitation to tender and its consequential evaluation thereof primarily
falls within the domain of executive discretion. The Tender Evaluation
Committee, more often than not, comprises a body of experts who are
best suited to determine the financial and technical merits of the bids
received. This Court therefore does not sit as a Court of appeal but
merely reviews the manner in which the decision was made. For this
reason, plausible decisions ought not to be interfered with and latitude
also ought to be granted to the State to exercise its executive power.
At the same time, it is pertinent to note that the circumspection
involved in exercise of jurisdiction does not tantamount to mean that
the actions of the State or its instrumentalities are beyond scrutiny.
Pertinently, the scope of judicial review in matters relating to tender
has been navigated by the Hon’ble Apex Court in several judgments
and it has consistently been emphasised that accusations of illegality,
irrationality and procedural impropriety would suffice for Courts to
assume jurisdiction to remedy such defects. In the case of State of
W.P.(C) 3885/2026 Page 17 of 37
Punjab v. Mehar Din
1
, the Hon’ble Apex Court while considering the
principles pertaining to the exercise of judicial interference as evolved
over time, observed as follows:
21. In Tata Cellular v. Union of India [Tata Cellular v. Union of
India, (1994) 6 SCC 651] it was held that judicial review of
government contracts is permissible in order to prevent arbitrariness
or favouritism. It was fearlessly opined in this case as under : (SCC
pp. 687-88, para 94)
“94. The principles deducible from the above are:
(1) The modern trend points to judicial restraint in
administrative action.
(2) The court does not sit as a court of appeal but merely
reviews the manner in which the decision was made.
(3) The court does not have the expertise to correct the
administrative decision. If a review of the administrative
decision is permitted it will be substituting its own
decision, without the necessary expertise which itself may
be fallible.
(4) The terms of the invitation to tender cannot be open to
judicial scrutiny because the invitation to tender is in the
realm of contract. Normally speaking, the decision to
accept the tender or award the contract is reached by
process of negotiations through several tiers. More often
than not, such decisions are made qualitatively by experts.
(5) The Government must have freedom of contract. In
other words, a fair play in the joints is a necessary
concomitant for an administrative body functioning in an
administrative sphere or quasi-administrative sphere.
However, the decision must not only be tested by the
application of Wednesbury principle of reasonableness
(including its other facts pointed out above) but must be
free from arbitrariness not affected by bias or actuated by
mala fides.
(6) Quashing decisions may impose heavy administrative
burden on the administration and lead to increased and
unbudgeted expenditure.”
22. The exposition of law on the subject has been consistently
followed by this Court even in the later decisions holding that
superior courts should not interfere in the matters of tenders, unless
1
(2022) 5 SCC 648
W.P.(C) 3885/2026 Page 18 of 37
substantial public interest was involved or the transaction was mala
fide. It was consistently stressed by this Court that the need for
overwhelming public interest should always be kept in mind to
justify judicial intervention in contracts involving the State and its
instrumentalities and while exercising power of judicial review in
relation to contracts, the courts should consider primarily the
question whether there has been any infirmity in the decision-
making process.
23. This view has been further considered by this Court in Jagdish
Mandal v. State of Orissa [Jagdish Mandal v. State of Orissa, (2007)
14 SCC 517] , wherein it was observed as under : (SCC p. 531, para
22)
“22. Judicial review of administrative action is intended
to prevent arbitrariness, irrationality, unreasonableness,
bias and mala fides. Its purpose is to check whether choice
or decision is made “lawfully” and not to check whether
choice or decision is “sound”. When the power of judicial
review is invoked in matters relating to tenders or award
of contracts, certain special features should be borne in
mind. A contract is a commercial transaction. Evaluating
tenders and awarding contracts are essentially
commercial functions. Principles of equity and natural
justice stay at a distance. If the decision relating to award
of contract is bona fide and is in public interest, courts
will not, in exercise of power of judicial review, interfere
even if a procedural aberration or error in assessment or
prejudice to a tenderer, is made out. The power of judicial
review will not be permitted to be invoked to protect
private interest at the cost of public interest, or to decide
contractual disputes. The tenderer or contractor with a
grievance can always seek damages in a civil court.
Attempts by unsuccessful tenderers with imaginary
grievances, wounded pride and business rivalry, to make
mountains out of molehills of some technical/procedural
violation or some prejudice to self, and persuade courts to
interfere by exercising power of judicial review, should be
resisted. Such interferences, either interim or final, may
hold up public works for years, or delay relief and succour
to thousands and millions and may increase the project
cost manifold.”
xxxxx xxxxx xxxxx xxxxx xxxxx
25. The law on the subject is settled that the courts being the
custodian of fundamental rights are under an obligation to interfere
where there is arbitrariness, irrationality, unreasonableness, mala
fides and bias, if any, but at the same time, the courts should
W.P.(C) 3885/2026 Page 19 of 37
exercise the power of judicial review with a lot of restraint,
particularly in contractual and commercial matters.
(Emphasis Supplied)
39. From a reading of the judgment as quoted supra, it materialises
that while there are inherent limitations to the exercise of judicial
review, the power may be invoked to obviate favouritism,
arbitrariness, irrationality, unreasonableness and public interest.
40. In the present case, the technical bid submitted by the Petitioner
was held to be ‘non responsive’, by Respondent No.1, on the ground
that the “Assessed Available Net Worth of the Petitioner at the close of
the preceding financial year (FY 2024-25) is less than the minimum
requirement of Rs. 152.25 Cr. as per clause 2.2.2 (BB) of the RFP
Document.” The controversy in the present petition, therefore,
primarily pertains to the manner in which the Respondent computed
the Petitioner’s “Assessed Available Net Worth” under the terms of
the RFP.
41. Under Clause 2.2.2 of the RFP, a bidder was required to fulfil
the following condition of eligibility in terms of the Financial
Capacity of the Bidder:
2.2.2(B)Financial Capacity: The Bidder shall have a minimum
available Net Worth (the“Financial Capacity”)ofRs. 152.25 crore
(Rs. One hundred Fifty Two Crore and Twenty Five Lakh only) at
the close of the preceding financial year
§
.
In case of a Consortium, the combined technical capability and net
worth of thoseMembers, who have and shall continue to have an
equity share of at least 26%(twenty six per cent) each in the SPV,
should satisfy the above conditions of eligibility; provided that each
such Member shall, for a period of 06 (six) months from the date of
commercial operation of the Project, hold equity share capital not less
than: (i) 26% (twenty six per cent) of the subscribed and paid up
equity of theSPV; and (ii) 5% (five per cent) of the Total Project Cost
specified in theConcession Agreement
£
.
W.P.(C) 3885/2026 Page 20 of 37
Provided further that each member of the Consortium shall have a
minimum available Net Worth of 10% of Estimated Project Cost in the
immediately preceding financial year
§€
.
2.2.2. (BB) Bidders who inter-alia meet the minimum qualification
criteria will be qualified only if their available Net Worth is more than
or equal to the requiredNet Worth value (value as per Clause
2.2.2(B)). The available Net Worth will be assessed as per following,
based on information mentioned at Annexure-VIII ofAppendix-IA:
Assessed Available Net Worth = (A-B*20%), Where A = Net Worth of
theBidder.
B = Balance value of existing commitments of PPP works for which
the bidder has emerged as the winner of the bids or on-going works to
be completed during the period of completion of the works for which
BID is invited. For the avoidance of doubt, it is clarified that works
for which bidder has emerged as the winner of the bids but LOA has
not been issued as on the day before opening the financial bids shall
also be considered while calculating value of B.
The status of Assessed Available Net Worth of the bidder to be
updated as on the date before opening the financial bids.”
42. Further, Clause 2.1.18 of the RFP specifically provides that for
the purpose of determining Net Worth under Clause 2.2.2, the Net
Worth of an Associate of the Bidder would also be eligible for
consideration.
43. As is evident from the above, Clause 2.2.2(BB) of the RFP
prescribes the following formula for determination of the “Assessed
Available Net Worth” of a bidder:
Assessed Available Net Worth = (A-B*20%),
Where:
A = Net Worth of the Bidder.
B = Balance value of existing commitments of PPP works for which
the bidder has emerged as the winner of the bids or on-going works to
W.P.(C) 3885/2026 Page 21 of 37
be completed during the period of completion of the works for which
BID is invited.
44. The challenge laid by the Petitioner essentially proceeds on two
principal grounds concerning the computation adopted by Respondent
No.1 while assessing the aforesaid components.
i. Respondent No.1 excluded the immovable properties of
the Petitioner’s Associate, namely Ms. Krishna Pandey, worth
approximately ₹87 crore, while computing Component “A”,
thereby substantially reducing the net worth attributable to the
Petitioner.
ii. Respondent No.1, while computing Component “B”,
relied upon the MoRTH Circular dated 06.11.2025 and included
financing costs, pre-operative expenses, and interest during
construction within the “Estimated Project Cost”, thereby
inflating the Petitioner’s existing commitments.
Component “A” of the Assessed Available Net Worth
45. At the outset, this Court is conscious of the settled position that
the tendering authority is well within its jurisdiction to prescribe
eligibility conditions, including financial thresholds and cut-off dates
for determination of net worth of bidders, and ordinarily, such
conditions are not liable to be interfered with in exercise of judicial
review unless found to be arbitrary, discriminatory, or actuated by
mala fides. The requirement of assessing the financial position of a
bidder as on a particular date serves a legitimate commercial purpose,
namely, to ensure that only financially stable and established entities
W.P.(C) 3885/2026 Page 22 of 37
possessing the requisite economic capacity are permitted to participate
in public projects of substantial value.
46. However, the rationale underlying such a requirement would
stand on a somewhat different footing in the case of an Associate
whose net worth is permitted to be considered along with that of the
bidder under Clause 2.1.18 of the RFP. The purpose of permitting
inclusion of the Associate’s net worth is evidently to assess the overall
financial capacity available to the bidder for execution of the project.
Viewed from that perspective, the financial capability of the Associate
at the stage of bid evaluation and award of the contract may arguably
assume greater significance than its precise financial position as on the
close of the preceding financial year.
47. Nevertheless, since the Petitioner has participated in the tender
process without assailing the validity of the tender conditions, the
controversy in the present case does not pertain to the validity of the
eligibility criteria prescribed under the RFP itself, but to the legality,
reasonableness, and manner in which Respondent No.1 interpreted
and applied the said conditions while evaluating the Petitioner’s bid.
48. Clause 2.2.4(ii) of the RFP required bidders to furnish
certificates from their Statutory Auditors specifying the net worth of
the bidder as at the close of the preceding financial year. In
compliance thereof, the Petitioner submitted a Net Worth Certificate
dated 27.12.2025 certifying the net worth of its Associate, Ms.
Krishna Pandey, at ₹192.36 crores. The said certificate was based
upon the Net Worth Certificate dated 21.08.2025 and valuation reports
dated 18.08.2025 relating to various immovable properties valued at
W.P.(C) 3885/2026 Page 23 of 37
approximately ₹87 crores. Since the valuation reports did not
expressly recite that the valuation had been undertaken as on
31.03.2025, Respondent No.1 proceeded to seek further clarification
from the Petitioner despite the fact that the RFP itself did not
prescribe any specific format, language, or separate valuation
documentation requirement in which such valuation was required to
be expressed.
49. Pursuant thereto, the Petitioner, vide reply dated 19.03.2026,
clarified that the said net worth was equally applicable as on
31.03.2025. Thereafter, by way of a representation dated 24.03.2026,
the Petitioner also furnished a fresh Chartered Accountant’s
Certificate certifying the net worth of Ms. Krishna Pandey as on
31.03.2025.
50. Respondent No.1 decided the representation of the Petitioner
vide letter dated 27.03.2026. Respondent No.1 considering the
submissions of the Petitioner regarding net worth of the Associate of
the Petitioner(Ms. Krishna Pandey), decided as under:
“Considering the Net Worth of the Associate: The bidder in its 4th,
5th and 6th para of its representation vide letter no. 341 dated
24.03.2026 has submitted regarding net worth of the Associate of the
bidder. As per clause 2.2.2(B) of the RFP Document, it is evident that
the bidder is required to submit its Net Worth at the close of the
preceding financial year (31.03.2025). Accordingly, the Net Worth of
Associate is to be taken at the close of the preceding financial year
which in the instant case is 31st March 2025. However, the bidder has
submitted the certificate dated 27.12.2025 from its Statutory Auditor
certifying that the Net Worth has been computed on the basis of
Audited financial statements of the Company as on 31 .03.2025;
Relevant books of accounts and supporting schedules up to
27.12.2025; and Net worth position of Ms. Krishna Pandey as per
records and declarations made available to Statutory Auditor.
Further, the bidder has submitted the certificate dated 21.08.2025
W.P.(C) 3885/2026 Page 24 of 37
from its Statutory Auditor certifying the Net Worth of its Associate i.e.,
Ms. Krishna Pandey on the basis of information and explanations
furnished to Statutory Auditor, wherein the details of assets and
liabilities considered for the Net worth of Ms. Krishna Pandey are as
under: -
a. Immoveable Properties (As per Valuation Report issued by
Approved Valuer)- Submitted Valuer's certificates were issued on
18.08.2025, but nowhere in the Valuer's Certificates it is mentioned
that the valuation of the immovable properties has been done as on
31.03.2025, therefore, the date of valuation has been considered as on
the date of issuance of the said certificates i.e., 18.08.2025. Since, the
valuation of immovable properties are not certified as on 31 .03.2025,
hence, the immovable properties have not been considered as part of
the Net worth of the Associates as on 31.03.2025 as per clause
2.2.2(B) of RFP.
b. Investment in Equity Shares (basis Valuation of shares as on
31.03.2024)- Since, the same amount is deducted by the bidder as
crossholding investments, hence, the same has been agreed to.
c. Investment in current Assets (Jewellery at cost declared, Furniture
& Fixtures at cost as declared, Investment in Public Provident Fund,
Cash ft. Bank Balance as on 31.03.2025, Loan ft Advances given up to
31.03.2025)- Cash & Bank Balance as on 31.03.2025, i.e., Rs 14.78
Cr. and Loan & Advances given up to 31.03.2025 i.e., Rs 1.85 Cr.
were considered for evaluation as the same are given as on
31.03.2025. Assets for which valuation as on 31.03.2025 were not
certified, have not been considered for evaluation.
Earlier, the bidder was given an opportunity to clarify why the Net
Worth of the Associate has been provided as on 27.12.2025 instead of
31.03 .2025. However, the reply furnished by the bidder vide its letter
dated 19.03.2026 was not found satisfactory as bidder in its letter
dated 19.03.2025 has submitted that the same Net Worth of the
Associate, namely, Ms. Krishna Pandey as per bid documents is
applicable as on 31.03.2025 without any supplementary evidence. In
light of the above, the assessed Net Worth of Ms. Krishna Pandey
comes as Rs 16.63 Cr., considering the following items which have
been valued as on 31.03.2025 in the Statutory Auditors' Certificate:
1. Cash & Bank Balance as on 31.03.2025, i.e., Rs 14.78 Cr.;
2. Loan & Advances given up to 31.03.2025 i.e., Rs 1.85 Cr.
Accordingly, the Assessed Available Net Worth of the bidder comes
out to be less than the minimum requirement of Cl. 2.2.2. (BB) of the
RFP Document, i.e., Rs 152.25 Cr. and the bidder was treated as
"Technically Non-Responsive" as per Cl. 2.2.2.(BB) of the RFP
Document'.
W.P.(C) 3885/2026 Page 25 of 37
It is pertinent to inform that the bidder in its supplementary
representation vide letter no. 343 dated 24.03.2026 has submitted
another Statutory Auditors' certificate dated 24.03.2026.
Notwithstanding, this is an additional document, the merit of this
document has been evaluated. In this certificate the same value of Net
Worth of the Associate has been shown as was submitted in the bid but
now as on 31 st March 2025 excluding the words, "As per Valuation
Report issued by Approved Valuer" after the words "Details of
immovable Properties at Market Value". No supporting documents
confirming the value of Immovable properties and other claimed
assets (except Cash & Bank Balance as on 31.03.2025, Loan &
Advances given up to 31.03.2025) as on 31st March 2025 has been
submitted by the bidder in the representation vide letter no. 343 dated
24.03 .2026. Hence, the same may not be considered as part of the Net
Worth of the Associate as on 31.03.2025.”
51. At this stage, it is apposite to note the Clause 1 of the
Instructions contained in Annexure-3 relating to “Financial Capacity
of the Bidder”, which read as under:
“Instructions:
1. The Bidder/ its constituent Consortium Members shall attach copies
of the balancesheets, financial statements and Annual Reports for 5
(five) years preceding the Bid Due Date. The financial statements
shall:
(a) reflect the financial situation of the Bidder or Consortium
Members and its/ their Associates where the Bidder is relying on its
Associate’s financials;
(b) be audited by a statutory auditor;
(c) be complete, including all notes to the financial statements; and
(d) correspond to accounting periods already completed and audited
(no statements for partial periods shall be requested or accepted).”
52. A plain reading of the aforesaid clause demonstrates that the
RFP nowhere mandated submission of any separate valuation
certificate or independent Statutory Auditor’s certificate of the
Associate in any particular format as a pre-condition for consideration
of the Associate’s net worth. In the present case, the Petitioner had
furnished a consolidated Statutory Auditor’s certificate concerning
both the Petitioner company and its Associate, wherein the relevant
financial information was compiled in tabular form and the net worth
W.P.(C) 3885/2026 Page 26 of 37
of Ms. Krishna Pandey as on 31.03.2025 was specifically reflected as
₹192.36 crores. Prima facie, therefore, the requirement under the
tender conditions stood satisfied. Significantly, even while seeking
clarification vide communication dated 17.03.2026, Respondent No.1
neither questioned the methodology adopted by the Statutory Auditor
nor undertook any independent assessment disputing the correctness
of the valuation reflected in the certificate.
53. It is also pertinent to note that while furnishing the net worth
details of the Associate, the Petitioner had specifically disclosed
details of approximately 20 immovable properties situated in New
Delhi under the signatures of the Statutory Auditor itself. Note-1
appended to the certificate expressly clarified that the market value of
the immovable properties had been taken on the basis of valuation
certificates issued by an approved valuer. In addition thereto,
valuation reports issued by Chartered Engineers and Designers in
respect of each of the said immovable properties were also furnished
along with the bid documents. The said valuation reports were
admittedly issued on 18.08.2025, i.e., prior to submission of the bid
itself. In such circumstances, exclusion of the entirety of the
immovable assets from consideration while computing the Associate’s
net worth merely because the valuation reports did not expressly
mention the date “31.03.2025” was wholly inappropriate and
arbitrary, particularly when the ownership and existence of the
properties prior to the relevant date was never disputed by Respondent
No.1.
W.P.(C) 3885/2026 Page 27 of 37
54. As is evident from the above, Respondent No.1 did not reject
the subsequent Statutory Auditor’s Certificate on the ground that the
assets were non-existent, ineligible, or incorrectly disclosed. The
dispute throughout remained confined only to the absence of express
reference to the valuation date in the supporting valuation material,
despite the substantive financial particulars of the Associate having
already been disclosed in the original bid documents.
55. Subsequently, vide email dated 28.03.2026, the Petitioner
furnished a further clarification issued by the Approved Valuer stating
that the valuation of the immovable properties had in fact been
undertaken with reference to prevailing market rates as on 31.03.2025
and that the issuance date of the reports, i.e., 18.08.2025, had no
bearing on the assessment date. Respondent No.1 has contended that
the said clarification could not be considered since it was furnished
after the Bid Due Date and after completion of the technical
evaluation process. However, the aforesaid clarification neither
introduced any new asset nor altered the financial position already
disclosed in the original bid documents. The clarification merely
explained the reference date and basis of valuation of the very same
immovable properties which already formed part of the bid documents
and whose existence and ownership were never disputed by
Respondent No.1.
56. In the opinion of this Court, the approach adopted by
Respondent No.1 while excluding the immovable properties of the
Petitioner’s Associate from consideration for computation of
Component “A” was manifestly arbitrary and founded upon an unduly
W.P.(C) 3885/2026 Page 28 of 37
hyper-technical interpretation of the tender conditions. Significantly,
Respondent No.1 has nowhere disputed the existence, ownership, or
antecedent acquisition of the immovable properties in question.Vide
letter dated 17.03.2026, the Petitioner was never called upon to
furnish ownership documents pertaining to Mrs. Krishna Pandey, the
Petitioner’s Associate. In these circumstances, it is reasonable to infer
that the Respondent did not, at any stage, dispute the Associate’s
ownership of the 20 immovable properties as on 31.03.2025. The sole
basis for exclusion of assets worth approximately ₹87 crores was that
the valuation reports dated 18.08.2025 did not expressly state in so
many words that the valuation was being reflected as on 31.03.2025.
Thus, the rejection was not founded on absence of assets, absence of
ownership, or falsity of disclosure, but merely on the form in which
the supporting valuation material was expressed.
57. In view of the foregoing it is essential to examine Clause
2.2.4(ii) of the RFP which mandates bidders to submit Certificates
from its Statutory Auditor specifying the net worth of the Bidder, as at
the close of the preceding financial year. The said clause is reproduced
herein below:
“2.2.4 The Bidders shall enclose with its bid, to be submitted as per
the format at Appendix-IA, complete with its Annexes, the following:
(i) Certificate(s) from its statutory auditors or the concerned client(s)
stating the payments made/ received or works commissioned, as the
case may be, during the past 5 years in respect of the projects
specified in paragraph 2.2.2 (A) above. In case a particular job/
contract has been jointly executed by the Bidder (as part of a
Consortium), it should further support its claim for the share in work
done for that particular job/ contract by producing a certificate from
its statutory auditor or the client; and
(ii) Certificate(s) from its statutory auditors specifying the net worth
of the Bidder, as at the close of the preceding financial year, and also
W.P.(C) 3885/2026 Page 29 of 37
specifying that the methodology adopted for calculating such net
worth conforms to the provisions of this Clause 2.2.4 (ii). For the
purposes of this RFP, net worth (the “Net Worth”) shall mean the
aggregate value of the paid-up share capital and all reserves created
out of the profits and securities premium account, after deducting the
aggregate value of the accumulated loses, deferred expenditure and
miscellaneous expenditure not written off, as per the audited balance
sheet, but does not include reserves created out of revaluation of
assets, write back of depreciation and amalgamation.”
(Emphasis Supplied)
58. A conjoint reading of Clause 2.2.4(ii) and the Instructions
contained in Annexure-3 makes it abundantly clear that the RFP
principally required submission of audited financial statements and a
certificate from the Statutory Auditor specifying the net worth of the
bidder as at the close of the preceding financial year. The RFP did not
prescribe any separate mandatory format of valuation certification nor
require independent valuation reports in any particular form as a
condition precedent for consideration of the Associate’s net worth.
59. In fact, the valuation reports relied upon by the Petitioner were
additional supporting material voluntarily furnished along with the bid
documents. Respondent No.1, however, proceeded to treat the absence
of an express recital regarding the valuation date in the valuation
reports as fatal to the bid itself, despite such a requirement being
absent from the tender conditions. It is well settled that a tendering
authority cannot introduce, during evaluation, eligibility conditions or
documentary requirements not contemplated under the terms of the
RFP itself.
60. Furthermore, the approach adopted by Respondent No.1
becomes wholly inappropriate when examined in the factual context
of the present case. The immovable properties excluded from
W.P.(C) 3885/2026 Page 30 of 37
consideration were valued at approximately ₹87.48 crores, whereas
the shortfall ultimately attributed to the Petitioner, even on the
Respondent’s own revised calculations, was only approximately ₹3.44
crores. Thus, exclusion of even a small fraction of the value of the
said immovable properties would have been sufficient to render the
Petitioner technically qualified. Once the existence and ownership of
the assets prior to 31.03.2025 was undisputed, rejection of the entire
value of the immovable properties merely because the valuation
reports did not expressly mention the valuation date was clearly
arbitrary, irrational, and disproportionate to the object sought to be
achieved under the tender conditions.
61. It is also pertinent to note that Respondent No.1 itself proceeded
to examine the subsequent Chartered Accountant’s Certificate dated
24.03.2026 on merits while deciding the Petitioner’s representation.
Once Respondent No.1 chose to evaluate the said document
substantively, it cannot simultaneously contend that no post-bid
clarificatory material whatsoever could be looked into under the
tender conditions. The stand adopted by Respondent No.1 is therefore
internally inconsistent. The subsequent documents furnished by the
Petitioner did not introduce any new asset, alter the financial position
of the bidder, or improve the bid in any substantive manner, but
merely clarified the valuation date of already disclosed assets forming
part of the original bid documents.
62. It is well settled that the chief objective of a tender process is
maximization of public value through a fair, transparent and
competitive bidding process. Since public procurement involves
W.P.(C) 3885/2026 Page 31 of 37
expenditure of public funds, tender conditions are required to be
interpreted and applied in a manner that promotes genuine
competition and secures the most beneficial outcome for the public
exchequer. Reference in this regard is drawn to the judgment in
Shanti Construction (P) Ltd. v. State of Odisha and Others
2
, where
the Hon’ble Apex Court held as under:
“10. A public tender is not a private bargain. It is instrument of
governance, a mechanism through which the State discharges its
solemn duty as trustee of public wealth. Its purpose is not merely
procedural compliance, but maximisation of public value
through a process i.e. fair, transparent and competitive. The
obligation of the Tendering Authority is therefore twofold, namely,
to interpret its own terms with consistency and to ensure that such
interpretation advances, not defeats, the object of tender. The court
must intervene in a case of demonstrable misconstruction of a
tender condition or irrationality which affects the public interest.
When an interpretation of a tender condition narrows competition
and excludes the highest bidder on a ground unsupported by law,
the decision making process is vitiated. The interpretation of the
terms of tender must, therefore, serve the object and purpose of the
tender mainly to maximise the revenue to the State, when it deals
with a natural resource.”
(Emphasis Supplied)
63. Bearing the aforesaid principles in mind, this Court is of the
considered view that the decision-making process adopted by
Respondent No.1 in relation to Component “A” stood vitiated by an
excessively technical interpretation of the tender conditions which had
the effect of excluding an otherwise financially eligible bidder from
the zone of consideration. Public procurement norms are intended to
secure genuine competition and protect public interest, and not to
eliminate bidders on procedural technicalities having no bearing on
substantive eligibility. Particularly in a case where only two bidders
2
2025 SCC OnLine SC 2368
W.P.(C) 3885/2026 Page 32 of 37
participated in the tender process and where, during the course of
hearing, the Petitioner has contended that its financial bid is lower
than that of Respondent No.2, the approach adopted by Respondent
No.1 had the direct consequence of restricting competition and
adversely affecting public interest.
64. In the facts of the present case, this Court is therefore unable to
sustain the exclusion of the immovable properties of the Petitioner’s
Associate while computing Component “A” of the Assessed Available
Net Worth. Once the statutory auditor’s certificate stood furnished in
terms of Clause 2.2.4(ii), the assets themselves were undisputed,
Respondent No.1 could not have rejected the Petitioner’s bid merely
because the accompanying valuation reports did not expressly specify
the valuation date in a particular format. Such an approach amounts to
elevating form over substance and results in defeating the very object
of competitive public procurement.
65. Permitting Respondent No.1 to reject the Petitioner’s bid in the
aforesaid circumstances would effectively amount to permitting
disqualification of an otherwise eligible bidder on the basis of a
deficiency which neither affected the substance of the bid nor caused
any prejudice to competing bidders. The law relating to public
procurement consistently distinguishes between essential conditions
affecting eligibility and ancillary procedural requirements relating to
the mode of proof. In the present case, the substantive requirement of
financial capacity stood fulfilled, while the alleged defect pertained
only to the manner in which the supporting valuation material was
expressed.
W.P.(C) 3885/2026 Page 33 of 37
Component “B” of the Assessed Available Net Worth.
66. As regards the assessment of Component “B”, the controversy
in the present case is confined to the question whether Respondent
No.1 was justified in relying upon the MoRTH Circular dated
06.11.2025 while computing the “Estimated Project Cost” for the
purposes of Clause 2.2.2(BB) of the RFP, and consequently including
components such as pre-operative expenses, financing and legal costs,
and interest during construction within the computation of Component
“B”.
67. The MoRTH Circular dated 06.11.2025 clarifies that the
“Estimated Project Cost” for HAM projects would include not merely
the EPC/civil construction cost, but also pre-operative expenses,
financing and legal costs, and interest during construction.
Respondent No.1 has relied upon the said circular while assessing the
balance value of the Petitioner’s ongoing commitments for the
purposes of computation of Component “B”.
68. It is pertinent to note that Clause 2.1.24 of the RFP specifically
provides that all orders issued by the Ministry of Finance, DPIIT, or
any other Government agencies, as applicable and prevalent on the
date of issuance of the LOA, shall apply to the tender process. The
said clause reads as under:
“2.1.24 All Orders of Ministry of Finance/DPIIT/any other
Government agencies, as applicable and prevalent on the date of
LOA, shall be applicable.”
69. The Ministry of Road Transport & Highways (MoRTH), being
the nodal ministry governing the subject project and the issuing
W.P.(C) 3885/2026 Page 34 of 37
authority of the circular dated 06.11.2025, would clearly fall within
the ambit of “other Government agencies” contemplated under Clause
2.1.24 of the RFP. Consequently, the contention of the Petitioner that
the said circular could not have been relied upon merely because it
was not separately incorporated through a corrigendum to the RFP
cannot be accepted. At the same time, even accepting the
methodology adopted by Respondent No.1 for computation of
Component “B” on the basis of the aforesaid circular, the Petitioner
would still satisfy the prescribed threshold of Assessed Available Net
Worth once Component “A” is computed by taking into consideration
the immovable properties of the Associate which already formed part
of the original bid documents. The controversy in the present case,
therefore, essentially does not arise on account of the methodology
adopted for computation of Component “B”, but on account of the
exclusion of the immovable properties while assessing Component
“A” on an unduly hyper-technical basis.
70. In the aforesaid circumstances, this Court finds no arbitrariness
or illegality in the methodology adopted by Respondent No.1 while
computing Component “B” of the Assessed Available Net Worth, and
consequently no fault can be found with the reliance placed upon the
MoRTH Circular dated 06.11.2025 for the said purpose.
71. It has also been contended by the Petitioner that Respondent
No.1 repeatedly altered the assessment of the Petitioner’s Assessed
Available Net Worth and the computation of Component “B” even
after rejection of the technical bid. It was submitted that while the
communication dated 27.03.2026 reflected the Petitioner’s Assessed
W.P.(C) 3885/2026 Page 35 of 37
Available Net Worth as ₹121.72 crores, the same was subsequently
revised to ₹148.81 crores. Similarly, the computation of Component
“B” was revised from ₹1082.95 crores to ₹947.49 crores. Although
the aforesaid circumstances do raise certain concerns regarding the
manner in which the evaluation exercise was undertaken by the
tendering authority, Respondent No.1 has explained the same as
inadvertent computational errors on the part of the concerned officials.
Be that as it may, the repeated revisions undertaken by Respondent
No.1 itself demonstrate that the evaluation process was neither treated
as immutable nor incapable of correction. In such circumstances,
Respondent No.1 could not have simultaneously adopted a rigid and
hyper-technical approach while considering the clarificatory material
furnished by the Petitioner in relation to Component “A”, particularly
when the same neither introduced any new asset nor altered the
substantive financial position already disclosed in the original bid
documents.
CONCLUSION
72. In view of the foregoing discussion, this Court finds no
infirmity in the methodology adopted by Respondent No.1 while
computing Component “B” of the Assessed Available Net Worth.
However, insofar as Component “A” is concerned, this Court is of the
considered opinion that Respondent No.1 acted arbitrarily and adopted
an unduly hyper-technical approach in excluding the immovable
properties of the Petitioner’s Associate from consideration.
73. The rejection of the Petitioner’s bid was not founded upon any
dispute regarding the existence, ownership, or antecedent acquisition
W.P.(C) 3885/2026 Page 36 of 37
of the assets in question, nor upon any finding that the Petitioner
lacked substantive financial capacity. The disqualification arose solely
because the valuation reports accompanying the Statutory Auditor’s
Certificate did not expressly state that the valuation was as on
31.03.2025, despite no such specific requirement being prescribed
under the RFP. The tender conditions merely required submission of a
Statutory Auditor’s Certificate specifying the net worth as at the close
of the preceding financial year, which requirement stood duly
complied with by the Petitioner. Respondent No.1, in effect,
introduced an additional documentary condition during the course of
evaluation which was never stipulated in the RFP.
74. This Court is also unable to overlook that the shortfall attributed
to the Petitioner by Respondent No.1 was itself marginal, being
approximately ₹3.44 crores even on the revised calculations of
Respondent No.1, whereas the value of immovable properties
excluded from consideration was approximately ₹87.48 crores. In
such circumstances, wholesale exclusion of the said assets on a purely
technical basis was wholly inappropriate and contrary to the principles
governing fair and competitive public procurement.
75. Significantly, Respondent No.1 has never contended that
consideration of the immovable properties of the Associate would
prejudice any competing bidder or alter the level playing field. On the
contrary, the properties in question formed part of the original bid
documents themselves. The present case, therefore, is not one
involving supplementation or improvement of a bid after submission,
but merely one concerning clarification of already disclosed material.
W.P.(C) 3885/2026 Page 37 of 37
76. Accordingly, the impugned decision declaring the Petitioner as
“Technically Non-Responsive” insofar as it excludes the immovable
properties of the Petitioner’s Associate while computing Component
“A” is set aside. Respondent No.1 is directed to recompute the
Petitioner’s Assessed Available Net Worth by taking into
consideration the said immovable properties forming part of the
original bid documents and thereafter proceed consequentially in
accordance with law.
77. The present petition is disposed of in the aforesaid terms.
Pending applications also stand disposed of.
AMIT MAHAJAN, J.
ANIL KSHETARPAL, J.
MAY 29, 2026
s.godara/vv/shah
Legal Notes
Add a Note....