As per case facts, the Petitioner filed a Contempt Petition alleging violation of a previous order where the State had undertaken to supply approved drawings from a meeting. The Petitioner ...
COCP-1774-2025 (O&M) - 1 -
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
205 COCP-1774-2025- (O&M)
Date of decision: 12.12.2025
Sarb Alliance Hospitality Pvt. Ltd. ...Petitioner(s)
Vs.
Gurpreet Kaur Sapra ...Respondent(s)
CORAM: HON’BLE MS. JUSTICE NIDHI GUPTA
Present:-Mr. Sanjay Kaushal, Senior Advocate with
Mr. R.Kartikeya, Advocate
for the petitioner.
Mr. Saurav Verma, Addl.A.G., Punjab and
Mr. Manmeet Singh Teji, A.A.G., Punjab.
NIDHI GUPTA, J.
The present contempt petition has been filed alleging
violation of order dated 20.09.2024 (Annexure P-1) passed in CWP-27996-
2023 titled as "Sarb Alliance Hospitality Pvt. Ltd. vs. State of Punjab and
others”.
2. In compliance of last order dated 13.11.2025, respondent is
present in person in Court today.
3. The relevant extract of the order dated 01.10.2025 passed by
this Court in the present Contempt Petition, is as under: -
“The present contempt petition has been filed alleging
violation of order dated 20.09.2024 (Annexure P-1) passed by a
co-ordinate Bench of this Court in CWP-27996-2023 titled as
“Sarb Alliance Hospitality Pvt. Ltd. vs. State of Punjab and
COCP-1774-2025 (O&M) - 2 -
others” whereby the writ petition was “disposed of as not
pressed” for the following reasons:-
‘xxx xxx xxx
Learned Sr. Counsel for the petitioner confines his
prayer and draws the attention of this Court towards the
minutes of the meeting (Annexure R-3) held on
07.05.2024 for development-cum-completion, operation
and maintenance of the Circuit House, Amritsar under
Public Private Partnership (PPP) mode. He contends that
in the said meeting held through video conferencing, the
Committee has approved the proposed drawings on the
basis of the conditions put forth by the Senior Architect
(North) Office of Architecture Department, Punjab vide
letter dated 25.08.2023 and subject to certain additional
conditions. He contends that notwithstanding the
approval of the drawings, the respondents have issued
the stamped copy of the old unapproved drawings
submitted by him instead of handing over the drawings
furnished subsequently and already approved. He thus
prays that the corrected and the subsequent drawings
submitted by him and as approved in the meeting held
on 07.05.2024 be delivered to him, duly stamped by the
Competent Authority and in a time bound manner.
Learned State Counsel, on instructions from Mr.
Manwar, Senior Assistant, Hospitality Department,
Punjab submits that the requisite approved drawings as
per the decision taken in the meeting held on 07.05.2024
shall be supplied to the petitioner positively within a
period of ten days from today.
In view of the above statement made by learned
State Counsel on instructions from Mr. Manwar, Senior
Assistant, Hospitality Department, Punjab, learned
Senior Counsel for the petitioner does not press the
instant petition any further.
The respondent-State shall, however, remain
bound to ensure that delivery of the drawings as
approved in the meeting held on 07.05.2024, are
supplied to the petitioner within the aforesaid period.
Disposed of as not pressed.
All other misc, application(s), if any, also stand(s)
disposed of accordingly.’
COCP-1774-2025 (O&M) - 3 -
It is submitted by learned Senior Counsel for the
petitioner that despite the above undertaking given on behalf
of the respondent-State, the said approved drawings have still
not been supplied to the petitioner. It is clarified that initially
the petitioner had submitted the plans dated 02.1.2022 for
approval, in which certain corrections were made by the
respondents, pursuant to which revised plans dated 08.2.2022
were submitted by the petitioner. It is submitted that the said
plans were approved by the Chief Architect, Punjab vide
order/letter dated 26.4.2022 (Annexure P-9); and further
approved in the meeting held on 7.5.2024. The building of the
Circuit House, Amritsar has been constructed as per the said
approved drawings. The Chief Minister, and Ministers of the
State of Punjab now regularly stay there. However, even
though the project stands completed, the formal approval of
the plans dated 08.2.2022 submitted by the petitioner has not
yet been received.
Learned counsel for the respondent has submitted that
the plans dated 08.2.2022 submitted by the petitioner could
not be approved by the Design Approval Committee as the
Chief Architect, Punjab vide letter dated 04.10.2024 (Annexure
R-2) had forwarded the original plans of 02.1.2022 for
approval, and not the plans dated 08.2.2022. However, it is
admitted that the said contention of learned counsel for the
respondent does not find mention in the Short reply dated
12.5.2025 filed by way of affidavit of Smt. Gauri Parasher Joshi,
Secretary to Government of Punjab, Department of General
Administration.
It is further submitted by learned counsel for the
respondent that the petitioner has constructed the building of
the Circuit House, Amritsar, which is at variance even with the
COCP-1774-2025 (O&M) - 4 -
allegedly approved designs of 08.2.2022. However, again the
said contention is not borne out from the abovesaid Short reply
filed by the State.
It is also submitted by learned counsel for the
respondents that the Annual Concession Fee (ACF) has not
been paid by the petitioner.
This assertion of the respondents is strongly
controverted by learned Senior Counsel for the petitioner, who
submits that the ACF amount of Rs.One crore and five lacs
already stands paid in August 2023, in respect of which
compliance certificate has still not been given by the
respondents.
It is also pointed out by learned Senior Counsel for the
petitioner that the variations allegedly incorporated in the
building constructed by the petitioner were not mentioned by
the respondents before the Writ Court while suffering the order
dated 20.09.2024 (Annexure P-1).
In this view of the situation, at the oral request of
learned Senior Counsel for the petitioner, the Chief Architect,
Punjab is made party to the present contempt petition.
Let notice of this contempt petition be issued to the Chief
Architect, Punjab.
Mr. Manmeet Singh Teji, AAG Punjab accepts notice of
this contempt petition on behalf of newly impleaded
respondent-the Chief Architect, Punjab.
The Registry is directed to carry out necessary
incorporation in the Memo of Parties at appropriate place.
Learned counsel for the respondents further prays for
some time to file better reply in the matter.
At his request, adjourned to 13.11.2025.”
COCP-1774-2025 (O&M) - 5 -
4. Ld. Senior Counsel for the petitioner submits that in flagrant
violation of the undertaking given by the respondents before the Writ
Court, till date the said revised plans have not been supplied to the
petitioner. It is submitted that in fact, the case of the petitioner has been
admitted in the short reply dated 26/27.11.2025 by way of Affidavit of
Chief Architect, Punjab, wherein, in para 11 it has been mentioned as
follows: -
“11.That in response to the above said letter dated
11.03.2022, the present Petitioner submitted fresh design of
the Circuit House, Amritsar on 14.03.2022 annexed as
Annexure R-2/7, which was received by the Respondent Office
on 18.04.2022. The design sent by the present Petitioner on
dated 14.03.2022 were discussed and approved. The
approval of the same was sent by answering respondent to
the Petitioner, Sarb Alliance Hospitality Private Limited, vide
Memo No. CA2022/1145, dated 26.04.2022 is being annexed
as Annexure R-2/8.
12. That in response to Annexure P-6, the layout plan duly
approved by this office included a 6-metre clear driveway
around the building to facilitate fire tender movement and
provided adequate building setbacks from the boundary wall,
as shown in Annexure R-2/9. It is respectfully submitted that
the petitioner has been repeatedly mis-stating the facts by
submitting different and altered layout plans to various
authorities at different points of time through multiple email
IDs. However those designs have never been approved/vetted
by the Office of the Chief Architect, Punjab, as they do not
comply with the applicable building norms and standards.”
COCP-1774-2025 (O&M) - 6 -
5. It is accordingly prayed that necessary action be taken against
the respondents under the Act.
6. Learned counsel for the respondents vehemently opposes
submissions on behalf of the petitioner. It is submitted that in fact in the
meeting dated 7.5.2024, glaring discrepancies in the execution of the
project by the petitioner were discussed and recorded. In this regard,
Learned counsel refers to the short reply dated 12.05.2025 by way of
Affidavit of Gauri Parasher Joshi, Secretary to the Government of Punjab,
Department of General Administration; in specific to the Proceeding
Report of the meeting of Design Approval Committee dated 07.05.2024
(Annexure R-1/T) in regard to Development, Completion, Operation &
Maintenance of Circuit House, at Amritsar. It is submitted that from the
perusal of para 2(i) of the said Proceeding Report (Annexure R-1/T), it is
clearly mentioned that as per the Agreement in question, the petitioner
had been asked to construct 70 rooms however, the
Concessionaire/petitioner has constructed 89 rooms, which is beyond the
terms of the Agreement and without the consent of
respondents/Authority. Therefore, as the petitioner had failed to adhere
to the terms and conditions of the Concession Agreement, the Building
Plans were approved while imposing several conditions including that all
the additional construction in excess of the provisions of the Concession
Agreement shall vest in the Government for all intents and purposes.
Furthermore, petitioner had also not completed the project within the
stipulated time. Even ACF was paid after a delay of 132 days. Accordingly,
COCP-1774-2025 (O&M) - 7 -
petitioner was asked to deposit the interest amount within 7 days.
Furthermore, petitioner was also asked to remove all discrepancies within
30 days and failure to comply would invite penalty of Rs.30,000/- i.e. 0.2%
of the Performance Security for each day’s delay.
7. It is further submitted that in any event, drawings approved
in the meeting held on 07.05.2024 were duly forwarded to the petitioner
firstly, on 14.5.2024; and then in compliance of the Writ Court order dated
20.9.2024, the approved drawings were again supplied to the petitioner
vide letter dated 04.10.2024 (Annexure R-1/4).
8. Ld. counsel also refers to the reply/ Affidavit dated
28.11.2025 of Ms.Gauri Parashar Joshi, Secretary to the Government of
Punjab, Department of General Administration; wherein it is mentioned as
under:-
“7. That it is apposite to mention here that the Petitioner is
misstating the facts before this Hon'ble Court. The true facts
of the case are that the Petitioner had vide its letter dated
14.03.2022, submitted the designs/drawings to the office of
Chief Architect Punjab. Pursuant to the said letter, the office
of Chief Architect, vide letter dated 26.04.2022 (Annexure P-
6) had granted approval to the design sent by the Petitioner,
subject to some conditions. Thereafter, the said approved
designs were sent by the office of Chief Architect Punjab vide
its letter dated 25.08.2023 to the Office of Director
Hospitality. The copy of the same is annexed as Annexure
R1/1 (COLLY). It is further humbly submitted that these same
designs were presented before the Design Approval
Committee in its meeting dated 07.05.2024 and approved by
the Committee subject to the conditions mentioned therein
COCP-1774-2025 (O&M) - 8 -
such as payment of the penalty for depositing the ACF after
due date, the penalty for delay in constructions etc.
8. That it is humbly submitted that vide letter dated
14.05.2024 the Answering Department supplied the
Petitioner with the proceedings of the meeting dated
07.05.2024, stating that the designs so sent by the office of
Chief Architect on 25.08.2023 (Annexure R1/1) were
approved by the Design Approval Committee. The copy of the
same is annexed as Annexure R1/2. It is further humbly
submitted that the Petitioner had duly acknowledged the
receipt and had agreed with the conditions so levied in the
meeting dated 07.05.2024, vide its email/letter dated
13.06.2024. The copy of the email/letter of acknowledgement
is attached herewith as Annexure R1/3.
9. That it is further humbly submitted that in compliance of
the Order dated 20.09.2024 passed by the Hon'ble High Court
in CWP No. 27996 of 2023, the Answering Department had
again sent the designs duly signed and stamped as approved
by the Design Approval Committee in its meeting dated
07.05.2024. The copy of the letter dated 04.10.2024 of the
same is annexed as Annexure R1/4. It is humbly submitted
that the Answering Department has already complied with
the Order dated 20.09.2024 passed by this Hon'ble High
Court.
10. That it is further humbly submitted that on 01.10.2025,
the Petitioner had made wrong submission that the Petitioner
had submitted the plan/designs dated 02.01.2022 for
approval, on which certain conditions were imposed, and in
pursuance to which the Petitioner had submitted revised
plan/designs dated 08.02.2022 and the said plans were
approved by Chief Architect vide letter dated 26.04.2022. In
fact, no such designs/drawings as alleged by the Petitioner
COCP-1774-2025 (O&M) - 9 -
dated 02.01.2022 and 08.02.2022 were ever received by the
Answering Department. It is humbly submitted that the
Petitioner had submitted the designs vide its letter dated
14.03.2022, which were duly approved, with conditions, by
the office of Chief Architect vide letter dated 26.04.2022
(Annexure P-6) and were further approved by the Design
Approval Committee in its meeting held on 07.05.2024.
Annexure R1/2 and R1/4).”
9. It is submitted that in actual fact, the petitioner is attempting
to convert this Contempt Petition into a Civil Suit. Ld. State Counsel also
submits that any alleged loss of revenue being suffered by the petitioner
on account of non-grant of certain statutory permissions is not the
consequence of any post-writ inaction. It is pointed out that the State has
processed and conveyed approvals, subject to contractual conditions and
regulatory compliances. Ld. Counsel reiterates that the record also shows
that the petitioner:
a)has constructed 89 rooms as against 70 rooms permitted under
the Concession Agreement, leading the Committee to stipulate that
any construction in excess of the agreement shall vest in the
Government;
b)has not yet fulfilled all Conditions Precedent, including execution
of the Escrow account and submission of the Safety Plan and
Procedures, exposing it to contractual penalties; and
COCP-1774-2025 (O&M) - 10 -
c)has defaulted in payment of ACF for subsequent years 2024-25
and 2025-26, despite having paid ACF for 2023-24 after issuance of
notice.
10. It is submitted that in this background, the petitioner is
misusing the present contempt petition which is being aggressively
pressed not to ensure compliance with a limited direction (which has
already been complied), but to arm-twist the State into:
a)recognising the petitioner’s preferred revised drawings dated
08.02.2022, irrespective of what the Committee actually
approved;
b)ignoring deviations and contractual breaches; and
c)effectively diluting conditions imposed by the Design Approval
Committee and other statutory authorities.
11. It is contended that the petitioner is, in substance, seeking
to reopen and rewrite the Concession Agreement and the Committee’s
decision, rather than invoking proper remedies. It is prayed that the
contempt jurisdiction of this Court under Article 215 and Sections 10–12
of the Contempt of Courts Act may not be converted into a forum for
adjudicating complex PPP disputes. It is accordingly prayed that the
present Contempt Petition be dismissed.
12. At this stage, it is submitted by learned Senior Counsel for the
petitioner that the drawings Annexure R-2/11 given to the petitioner by
the respondent did not bear proper stamp or dates et cetera; and
COCP-1774-2025 (O&M) - 11 -
therefore, the respondents be held accountable under the Act. It is
contended that the proper plans are not being released to the petitioner
only because of the EGO of the respondent.
13. No other argument is raised on behalf of the parties. I have
heard learned counsel for the parties and perused the case file in detail.
14. Needless to say, the issues being raised by the parties are
disputed questions of fact; and enquiry into the same cannot be
conducted by this Court in contempt jurisdiction. Nonetheless, the facts
that emerge from the record are as under: -
14.03.2022: Petitioner vide its letter dated 14.03.2022 submitted the
Designs/Drawings to office of Chief Architect Punjab.
26.04.2022: Office of Chief Architect had granted approval to the Design
sent by petitioner subject to some conditions.
25.08.2023: Approved Designs were sent by office of Chief Architect to
the office of Director Hospitality (Annexure R1/1 colly).
07.05.2024: Same Designs were presented before Design Approval
Committee/DAC and approved by the Committee subject to the
conditions mentioned therein. The Design Approval Committee held its
meeting on 07.05.2024 under the Chairmanship of Secretary, General
Administration Department. The minutes record that the Committee
approved the drawings vetted by the Senior Architect (North),
Department of Architecture, Punjab, vide letter No. C.A.(N)-2023/1474
dated 25.08.2023, subject to certain conditions regarding: (i) additional
rooms constructed beyond 70, (ii) delay in construction completion, (iii)
COCP-1774-2025 (O&M) - 12 -
delay in payment of Annual Concession Fee (ACF), and (iv) non- fulfilment
of Conditions Precedent. These minutes are (Annexure R- 1/T.)
14.05.2024: On 14.05.2024, immediately after the meeting, the
Government of Punjab, Department of General Administration (Protocol
Branch), issued memo”No. GAD-POLORESE/39/2020-RVA POL-1-
Part(2)/E450998/624 (Annexure R1/2) to the petitioner conveying that
the drawings vetted and forwarded by the Senior Architect (North) under
letter dated 25.08.2023 stand approved by the Design Approval
Committee, and setting out the above conditions in detail. The memo
expressly directs the petitioner to comply with these conditions and to
deposit the stipulated penalty and interest. (Annexure R-2/11 Chief
Architect affidavit).
13.06.2024: Vide its own Email/letter dated 13.6.2024 (Annexure R1/3)
addressed to the Principal Secretary, General Administration, the
petitioner not only acknowledged the receipt of plans, but it
“acknowledged and expressed gratitude” for the approval of drawings,
referring specifically to the approval letter No. 625 dated 16.05.2024 and
confirming deposit of the demanded amount.
1.10.2024: Thereafter, on 01.10.2024, the Additional Chief Architect,
Punjab, vide memo No. C.A.-2024/4667(Annexure R-2/T - along with short
reply dated 12.05.2025), informed the Director, Hospitality Department,
that the drawings approved by the Senior Architect (North) vide letter
dated 25.08.2023 were being forwarded after verification “for further
necessary action”.
COCP-1774-2025 (O&M) - 13 -
04.10.2024: In compliance with the Writ Court order dated 20.9.2024
(Annexure P1) in CWP-27996-2023, the Director, Hospitality Department,
Punjab, vide letter/ memo No. 5795 dated 4.10.2024 (Annexure R1/4),
issued to the petitioner again forwarded the approved drawings of the
project dated 25.08.2023 as approved by DAC in its Meeting on
07.05.2024 (Annexures R-3/T and R-4/T along with short reply dated
12.05.2025), both by email and by hard copy. The short reply affidavit
dated 12.05.2025 clearly states that the drawings, duly stamped and
approved, were sent to the petitioner on 04.10.2024. These were duly
received by Sh Angadeep Singh, one of the partners of petitioner firm on
the same date, i.e. 04.10.2024.
10.03.2025: Present COCP-1774-2025 is filed by the petitioner against.
02.08.2025: Rejoinder to the short reply of respondent is filed by the
petitioner by way of CM-15385-2025 stating that:
a) respondent projected wrong and incomplete facts. Only a part of order
has been referred in the Affidavit filed by respondent while concealing
earlier part.
b) Old unapproved Drawing have been supplied to allege that order stands
complied with.
c) Maps appended with the said email, are in complete contradistinction
to the maps appended with the present Affidavit.
04.08.2025: Petitioner submitted before this Court that meeting of
concerned authorities was held on 18.07.2025 in which petitioner had
also participated and prayed that State be directed to get instruction with
COCP-1774-2025 (O&M) - 14 -
regard to revised drawings whether the designs as approved by
Department were given to petitioner.
15. From the above sequence of facts, it is clear that the
drawings approved by the respondent in the meeting dated 7.5.2024 have
been supplied to the petitioner firstly on 14.5.2024 (Annexure R-1/2), and
then again on 4.10.2024 (Annexure R-1/4. (Annexures R-3/T and R-4/T)).
This fact has also not been denied by the petitioner. Even the email dated
13.6.2024, written by the petitioner to the respondent acknowledging
receipt of the plans and expressing gratitude for approval of the plans, is
not denied. The contention of the petitioner that the drawings Annexure
R-2/11 do not bear proper stamps and dates, et cetera are misleading as
the said Contractual disputes about which drawings ought to have been
approved, the correctness of conditions imposed by the Committee, or
alleged monetary claims under the Concession Agreement, are all outside
the four corners of the original Writ Court order.
16. At the risk of repetition, it is reiterated that the writ petition
was disposed of as “not pressed” after recording the limited statement of
the State that approved drawings, as per the decision of the Design
Approval Committee meeting dated 07.05.2024, will be supplied to the
petitioner within ten days. There is no other operative direction in the writ
order. In the present contempt proceedings, therefore, the only justiciable
issue is a narrow and objective one as to whether the drawings “as
approved in the meeting held on 07.05.2024” have been supplied to the
COCP-1774-2025 (O&M) - 15 -
petitioner. From the facts recorded above, it is clear that even before the
present contempt petition was filed (10.03.2025), the State had:
(a)convened the Design Approval Committee meeting;
(b)approved the drawings as per the Committee’s decision;
and
(c)communicated the approval of the drawings to the petitioner by
memo dated 14.05.2024 Annexure R-1/2 and forwarded the
stamped plans on 04.10.2024 Annexure R-1/4. (Annexures R-3/T and
R-4/T).
17. In addition, the respondent has filed a detailed affidavit dated
28.11.2025, explaining the entire factual matrix and clarifying that the
only drawings ever vetted and approved are those transmitted by the
Senior Architect (North) on 25.08.2023 (Annexure R-2/11) and
subsequently stamped and dispatched on 14.5.2024/04.10.2024, and
reiterating that therefore, the order dated 20.09.2024 stands fully
complied with. The Writ Court had not directed the State to approve any
particular set of drawings (for example, the drawings dated 08.02.2022),
nor did it adjudicate upon the contractual legality of the conditions
imposed by the Design Approval Committee. The Writ Court only directed
that whatever drawings were approved in the meeting of 07.05.2024
should be supplied to the petitioner. It would appear that the grievance of
the petitioner in the present Contempt Petition is that:
COCP-1774-2025 (O&M) - 16 -
a)drawings dated 08.02.2022, allegedly revised and final, have not been
“stamped and delivered”; and
b)the Design Approval Committee ought to have approved those
drawings instead of the earlier set. This is, in substance, a challenge
to the correctness of the decision taken by the Committee, and not to
the compliance of the order passed by Writ Court. The Writ order
does not entitle the petitioner to insist that its preferred drawings
must be treated as approved in law; it merely secures delivery of the
drawings actually approved by the Committee.
18. However, as the State has shown that the drawings which the
Committee in fact approved have been sent to the petitioner, the remit of
contempt ends. If the petitioner is aggrieved by which drawings were
approved, by the conditions attached (penalties, vesting of additional
rooms, insistence on ACF and Conditions Precedent), or by the refusal to
approve its later revised drawings, the proper remedy is an independent
writ or appropriate contractual proceeding, but not a contempt petition.
19. The order dated 01.10.2025 passed in the present COCP
notes the petitioner’s argument that drawings dated 08.02.2022 allegedly
approved by the Chief Architect on 26.04.2022, have not yet been
formally approved or supplied, and also records submissions from the
State’s side regarding the petitioner’s construction being at variance with
the approved plans and about non-payment of ACF. In this regard it is
clarified from the record that the Petitioner is relying upon letter dated
26.04.2022 by Chief Architect Punjab (Annexure R2/8). However, in this
COCP-1774-2025 (O&M) - 17 -
letter itself the Chief Architect had referred to letter dated 14.03.2022
written by the petitioner to the Chief Architect (Annexure R-2/7); whereby
the petitioner had sent the revised designs to the Chief Architect vide said
letter dated 14.03.2022; and not on 08.02.2022 as alleged by him. Further,
in terms of the order dated 1.10.2025 passed by this Court, the
respondent has furnished a fuller, factual and satisfactory explanation by
way of the detailed affidavit dated 28.11.2025, clarifying that:
a)the petitioner’s revised drawings dated 08.02.2022 were never
finally vetted;
b)The only drawings ever approved are those transmitted by the
Senior Architect (North) on 25.8.2023 and approved in the meeting
dated 7.5.2024;
c)Vide memo dated 14.05.2024 the Committee’s approval and the
memo dated 04.10.2024 the stamped drawings were forwarded to
the petitioner; and
d)sets out the petitioner’s own letter of gratitude dated 13.06.2024
(Annexure R1/3) acknowledging approval.
20. In these circumstances, reference may be made to the law as
laid down by the Hon’ble Supreme Court to the effect that:
1)Contempt is not a substitute for execution or appeal. In
Niaz Mohammad v. State of Haryana, (1994) 6 SCC 332,
the Hon’ble Apex Court held that where the directions of
a judgment have been substantially complied with, any
COCP-1774-2025 (O&M) - 18 -
residual grievance must be worked out in appropriate
proceedings; contempt jurisdiction is not meant for
“enforcement of monetary or other civil rights” when
there is bona fide compliance.
2)Wilful and deliberate disobedience must be clearly
proved. In Kapildeo Prasad Sah v. State of Bihar, (1999) 7
SCC 569, the Hon’ble Court explained that for civil
contempt it must be shown that the disobedience is not
merely accidental or due to inability or misunderstanding;
if there is any genuine doubt about the scope of the order
or if compliance is reasonably arguable, contempt will
not lie.
3)Contempt cannot enlarge or vary the original order. In
Jhareswar Prasad Paul v. Tarak Nath Ganguly, (2002) 5
SCC 352, and Anil Ratan Sarkar v. Hirak Ghosh, (2002) 4
SCC 21, it has been repeatedly emphasised that the
Hon’ble Court, in contempt, may not read into the original
order rights or directions which are not expressly granted;
a party cannot, under the guise of contempt, obtain
substantive relief which it failed to secure in the
main proceeding.
4)Standard of proof akin to criminal proceedings. In Ashok
Paper Kamgar Union v. Dharam Godha, (2003) 11 SCC 1,
the Hon’ble Supreme Court described contempt as a
COCP-1774-2025 (O&M) - 19 -
quasi-criminal jurisdiction where findings of guilt must
rest on clear, cogent and unimpeachable evidence of
wilful disobedience.
21. Thus, keeping in view the above noted factual and legal
aspect, present Contempt Petition is hereby dismissed.
22. Rule stands discharged.
23. Pending applications, if any, stand disposed of.
12.12.2025 (NIDHI GUPTA)
Divyanshi JUDGE
Whether speaking/reasoned: Yes/No
Whether reportable: Yes/No
Legal Notes
Add a Note....