banking recovery, loan default, corporate finance, banking law
0  18 Dec, 2019
Listen in 01:59 mins | Read in 24:00 mins
EN
HI

Standard Chartered Bank Vs. Heavy Engineering Corporation Ltd. & Anr.

  Supreme Court Of India Civil Appeal /9288/2019
Link copied!

Case Background

The appeal challenges the High Court of Calcutta's decision which overturned the Single Bench's ruling from thereby validating the plaintiff's entitlement to bank guarantees amounting to Rs. 1,10,33,207.00, plus 8% ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

                       REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

    CIVIL APPEAL NO(S).9288 OF 2019

(ARISING OUT OF SLP(CIVIL) NO(s). 23430 OF 2019)

STANDARD CHARTERED BANK ….APPELLANT(S)

VERSUS

HEAVY ENGINEERING 

CORPORATION LTD. & ANR.  …RESPONDENT(S)

J U D G M E N T

Rastogi, J.

1.Leave granted.

2.The instant appeal is being preferred against the judgment

and order dated 8

th

 May, 2019 passed by the Division Bench of the

High   Court   of   Calcutta   setting   aside   the   judgment   dated   16

th

October, 2015 of the Single Bench and accepting claim of the 1

st

respondent­plaintiff holding that the bank guarantees were properly

invoked in law and accordingly the decree came to be passed for Rs.

1

1,10,33,207.00/­ as claimed in paragraph 18 of the plaint with

interest at the rate of 8 per cent per annum from the date of

institution of the suit until payment.

3.Although both the Judges of the Division Bench has delivered

their separate judgment but have expressed a concurring view on

the subject.

4.The   dispute   primarily   arose   with   regard   to   two   bank

guarantees amounting to Rs. 71,35,100/­ and Rs. 20,32,500/­ in

terms of the letters of intent, HEC­CS­1502­81 dated 19

th

  May,

1981 and HEC­CS­1502­81 dated 19

th

  May, 1981 furnished on

behalf of the 2

nd

 defendant by the appellant Bank(1

st

 defendant) in

favour of the 1

st

 respondent­plaintiff “as advance against supply of

plant  and  equipment”  by the  1

st

  respondent­plaintiff to the  2

nd

respondent (defendant no. 2).   The two bank guarantees are on

identical terms and the only difference is the date and the amount

which are reproduced as under:­

Bank   Guarantee   No.   1001/03/100G   dated   16   

th

February, 1983

“We,   GRINDLAYS  BANK   P.L.C.,   19   Netaji   Subhas

Road, Calcutta 700001 undertake the Indemnity and

keep the CORPORATION indemnified to the extent of

2

Rs.   71,35,100/­(Rupees   SEVENTY   ONE   LAKHS

THIRTY FIVE THOUSAND AND ONE HUNDRED ONLY)

against any loss or damage caused to or suffered by

the CORPORATION by reason or any breach or failure

by   the   said   SUPPLIER,   in   due   performance   of   the

aforesaid contract,  we shall forthwith on demand pay

to the CORPORATION any sum or sums not exceeding

Rs.   71,35,100/­(RUPEES   SEVENTY   ONE   LAKHS

THIRTY FIVE THOUSAND AND ONE HUNDRED ONLY)

without   making   any   prior   reference   to   the   said

SUPPLIER with and exclusion of any action in Court by

SUPPLIER.”

Bank   Guarantee   No.   G/1001/84/608   dated   29   

th

August, 1984

“We, GRINDLAYS BANK P.L.C., 19 Netaji Subhas Road,

Calcutta 700001 do hereby undertake the Indemnity

and keep the CORPORATION indemnified to the extent

of Rs. 20,32,500(Rupees TWENTY LAKHS THIRTY TWO

THOUSAND FIVE HUNDRED ONLY)   against any loss

or damage caused to or suffered by the CORPORATION

by   reason   or   any   breach   or   failure   by   the   said

SUPPLIER,   in   due   performance   of   the   aforesaid

contract,   we   shall   forthwith   on   demand   pay   to   the

CORPORATION any sum or sums not exceeding Rs.

20,32,500/­(RUPEES   TWENTY   LAKHS   THIRTY   TWO

THOUSAND FIVE HUNDRED ONLY) without  making

any   prior   reference  to  the  said  SUPPLIER  with  and

exclusion of any action in Court by SUPPLIER.”

   (emphasis supplied)

5.The  said  two bank   guarantees  were furnished  for  and  on

behalf of 2

nd

 respondent towards the sum insured “against any loss

or damage caused to or suffered by the Corporation by reason or

any breach or failure by the said supplier, in due performance of

the aforesaid contract.”  

3

Brief facts of the case :

6.By a letter of intent dated 19

th

  May, 1981, 1

st

  respondent

placed an order on 2

nd

 respondent(Simon Carves India Ltd. ‘SCIL’)

for the complete design, supply of both indigenous and imported

equipments,   erection   and   commissioning   of   requisite   civil   and

construction works of the Dankuni Coal Complex at a total price of

Rs. 21.10 crores.  The letter of intent dated 19

th

 May, 1981 after

describing 4 sections of the LTC plant at Dankuni stated as under:­

“The above price covers the complete design, supply of

both indigenous and imported equipment, erection and

commissioning   with   requisite   civil   and   structural

works complete in all respects except land filling upto

4.00 M level, railways siding, roads & outside drawing

and perphorial lighting which will only be outside your

scope or work.

The break up of the total price of Rs. 21.10 crores for

purpose of billing is enclosed.

We have noted the terms of payment proposed by you

in your letter dated 18.05.81.   As we have indicated

about the terms of payment agreed to by us, it will not

be possible to consider your proposal for relaxation of

the same.  However, attempts will be made to consider

some softening of payment terms later depending our

own cash flows on this project.

Kindly   let   us   have   your   detailed   technical

specifications etc to enable us to draw up a detailed

contract for the work.

Kindly communicate your acceptance of this letter of

intent and furnish us a bank guarantee on approved

4

proforma to release the initial advance of Rs. 15.64

lakhs to you. 

In   pursuance   of   the   letter   of   intent   two   bank

guarantees have been furnished by the defendant no. 1

on behalf of the defendant no. 2 “as advance against

the supply of plant and equipment.”

      (emphasis supplied)

7.Pursuant to the letter of intent, a formal Memorandum of

Agreement dated 8

th

  August, 1985 was executed by and between

SCIL.   Thereafter, the 1

st

  respondent (plaintiff) from time to time

advanced   for   the   said   work   against   several   bank   guarantees

furnished by SCIL.   It may be noticed that the instant dispute

pertains to two bank guarantees dated 16

th

 February, 1983 and 29

th

August, 1984, which were advanced to SCIL, the details of which

have been indicated above.  The said guarantees furnished by the

appellant bank were extended from time to time and revalidated.  

8.In  due   course   of  time,  in  breach  of  contract  with the  1

st

respondent­plaintiff, SCIL failed to duly complete the supply of

equipment and the other conditions of the letter of intent and

further defective equipments.  It is alleged that the work had to be

abandoned due to which 1

st

  respondent suffered huge losses and

damages.  Ultimately, a sum of Rs. 139.90 lakhs, was deducted by

5

the 1

st

 respondent from final bill which pertained to the apportioned

work handed over to SCIL.

9.In view of the letter dated 6

th

 November, 1998, 1

st

 respondent­

plaintiff demanded encashment of both the said guarantees which

were refused by the bank to honour and diverse correspondence

was exchanged by and between the 1

st

 respondent ­plaintiff and the

appellant­defendant bank.   1

st

  respondent in continuation made

subsequent demands for encashment of the guarantees by letter

dated 19

th

 December, 1998 which is reproduced hereunder:­

“No.HDC/Proj/Fin/98­343

     Dated the 19

th

 December, 1998

To

The Chief Manager

Corporate Banking

ANZ Grindlays Bank

19, Netaji Subhas Road

Post Box No.2645

Calcutta – 700001

Dear Sir,

With reference to your St. Relationship Manager’s

letter   dtd.   7.12.98   regarding   encashment   of   B.Gs

issued by you on behalf of M/s. SCIL for a total value

of Rs.91.68 lakhs you are very much aware that M/s.

SCIL owes to H.E.C. Rs.139.90 lakhs due to defective

supply of Plant & Equipment as well as non­supply of

Plant   &   Equipment   and   also   other   contractual

deficiencies which has caused loss as reflected in the

6

handing over/taking over report of the DCC Project by

CIL.  You are also aware that HEC has gone out of the

way   in   supporting   SCIL   and   getting   the   Plant

completed with minimum damage.  It is within HEC’s

full rights to invoke the BG as per Clause No.2 of the

BG’s   which   is   reproduced   below;   (BG

No.G1001/83/1084 dt. 16.8.83 for Rs. 71,35,100.00

and   BG   No.G1001/84/608   dt.   29.8.84   for   Rs.

20,32,500.00).

WE GRINDLAYS BANK PLC 19, Netaji Subhas Road,

Calcutta – 700001 do hereby undertake the Indemnity

of Rs.               (Rupees ____________) against any loss

or damage caused to or suffered by the CORPORATION

by   reason   or   any   breach   or   failure   by   the   said

SUPPLIER,   in   due   performance   of   the   aforesaid

contract,   we   shall   forthwith   on   demand   pay   to   the

CORPORATION any sum or sums not exceeding Rs.

(RUPEES                          without making any prior

reference to the said SUPPLIER with an exclusion of

any action in court by SUPPLIER.

The failure of M/s. SCIL in fulfilling the contractual

obligation which includes performance Guarantees of

Plant & Equipment are very well documented by HEC

& CIL.   In fact, the unadjusted advance of SCIL on

account of Plant & Equipment is far in excess of the

loss suffered by HEC.   The same has been brought

down   to   Rs.139.90   lakhs   after   allowing   credit   for

contractual settlement.

 Although as per terms of BG we are not bound to

explain you all these things but the above details are

furnished so that good sense will prevail and we expect

you   to   live   up   to   your   reputation   and   honour   the

beneficiaries claim for encashment.

    Thanking you,

                            Yours faithfully,

   T.L.N. SOURI

   GENERAL MANAGER (PROJECTS & MNTG)

  (emphasis supplied)”

7

10.This was followed by the letter dated 28

th

  December, 1998

which is also reproduced hereunder:­

“No.GGM(CM)/    /98

                      28

th

 December,

1998

To

The Chief Manager

ANZ Grindlays Bank

CALCUTTA.

(Atten: Shri Vasudeo Kundu)

   Fax No.033­2211196

Sub: Encashment of two Bank Guarantees Nos.

1)G/1001/83/108G for Rs.71,35,100/­

2)G/1001/88/608 for Rs.20,32,500/­

Ref: Our letter dated 19.11.1998.

Dear Sir,

We have intimated vide our above letter to encash

the   above   two   Bank   Guarantees   issued   by   you   on

behalf of SCIL India Ltd., to HEC.

You   are   requested   to   encash   the   above   Bank

Guarantees   and   send   the   proceeds   amounting   to

Rs.91,67,600/­ within 3 days time.   Kindly treat this

as most urgent and failing on the part of the Bank to

honour   the   beneficiaries   demand   will   be   viewed

seriously.

Thanking you,

                  Yours faithfully,

   (L.M. Prasad)”

   

8

11.A further complaint was made by way of a letter dated 22

nd

February, 1999 to the Banking Ombudsman, Calcutta.  Ultimately,

1

st

 respondent­plaintiff was constrained to institute a suit before the

High Court of Calcutta for decree of Rs. 1,10,33,207.07/­ along

with interest being the aggregate sum of both the said guarantees.

12.The appellant Bank filed its written statement and primarily

took objection that the invocation of the bank guarantees was not

in accordance with either of the said guarantees and contrary to the

terms thereof and accordingly the appellant Bank was not liable to

make payment to the 1

st

  respondent­plaintiff under either of the

said guarantees.   In support of its defence, the appellant Bank

referred   to   the   diverse   correspondence   exchanged   between   the

appellant and 1

st

 respondent.  In brief, the defence of the appellant

Bank was that the invocation of the said bank guarantees was

contrary to the terms or not in terms thereof.

13.On the pleadings of the parties, the suit in the first instance

came to the dismissed vide judgment & decree dated 16

th

 October,

2015 which came to be challenged by the 1

st

 respondent in appeal

before the Division Bench of the High Court of Calcutta.   In a

9

concurring judgment while setting aside the judgment of the Single

Judge   of   the   High   Court,   it   was   finally   held   that   the   bank

guarantees were properly invoked in law by the 1

st

  respondent­

plaintiff and accordingly passed a decree of Rs. 1,10,33,207.00/­

together with interest at the rate of 8% per annum on and from the

date of institution of the suit until payment.

14.Learned senior counsel for the appellant Bank, Shri Amit Sibal

submits that the said bank guarantees only covered losses arising

out of supply of plant & equipment and according to the pleadings

on record, the plant stood installed in October, 1990 and this is the

case where the appellant Bank in its independent capacity, refused

the claim for it being clearly false to its knowledge and also not in

accordance with the terms of the guarantee, i.e. beyond the purview

of   the   bank   guarantees   and   failing   to   apportion   those   losses

suffered on account of claims which would be within the terms of

the bank guarantees.

15.Learned counsel further submits that the bank guarantees are

in reference to two category of losses (i) non­supply/defective supply

of plant & equipment (ii) “other contractual deficiencies” and by the

10

invocation vide letter dated 19

th  

December, 1998 claims caused by

“non­supply/defective   supply   of   plant   &   equipment  and   other

contractual   deficiencies”   is   outside   the   purview   of   the   bank

guarantee.  Further, assuming the correctness of the claim, the 1

st

respondent if suffered loss for both (i) non­supply/defective supply

of plant and equipment (ii) “other contractual deficiencies”, it is

difficult to determine the apportionment between the two categories,

because the invocation does not state how they are apportioned.

The invocation is thus inchoate and incomplete and this according

to the appellant does not constitute a valid invocation at all and it

has not been properly appreciated by the Division Bench of the

High Court in the impugned judgment and has to be interfered by

this Court.

16.In  support   of  his   submission,   learned  counsel   has   placed

reliance on the judgment of this Court in Hindustan Construction

Co. Ltd. Vs. State of Bihar & Others   

1

  and Gangotri Enterprises

Ltd. Vs. Union of India and Others   

2

.

1 1999(8) SCC 436

2 2016(11) SCC 720

11

17.Per contra, Ms. Madhavi Diwan, learned ASG appearing on

behalf  of the 1

st

 respondent, while supporting the finding recorded

by the High Court in the impugned judgment submits that as per

precedents laid down by this Court, the question of law is no more

res   integra   and   is   well   settled   that   the   bank   guarantee   is   an

independent contract between the bank and the beneficiary and the

bank is always obliged to honour its guarantee as long as it is an

unconditional and irrevocable one.  At the same time, the dispute

between the beneficiary and the party at whose instance the bank

has given the guarantee is immaterial and is of no consequence and

two exceptions to the rule have been carved out.  The first is when

there is a fraud of which the Bank has notice and a fraud of the

beneficiary from which it seeks to benefit.  The second exception to

the   general   rule   of   non­intervention   is   such   when   there   is   a

‘irretrievable injury’ or ‘irretrievable injustice’ that would occur to

the Bank.

18.We have heard learned counsel for the parties and with their

assistance perused the material available on record.

12

19.The law relating to invocation of bank guarantees with the

consistent line of precedents of this Court is well settled and a

three­Judge Bench of this Court in  Ansal Engineering Projects

Ltd.  Vs.  Tehri   Hydro   Development   Corporation   Ltd.   and

Another   

3

 held thus:­

“4. It   is   settled   law   that   bank   guarantee   is   an

independent and distinct contract between the bank

and   the   beneficiary   and   is   not   qualified   by   the

underlying transaction and the validity of the primary

contract   between   the   person   at   whose   instance   the

bank guarantee was given and the beneficiary. Unless

fraud or special equity exists, is pleaded and prima

facie established by strong evidence as a triable issue,

the beneficiary cannot be restrained from encashing

the   bank   guarantee   even   if   dispute   between   the

beneficiary and the person at whose instance the bank

guarantee   was   given   by   the   bank,   had   arisen   in

performance of the contract or execution of the works

undertaken   in   furtherance   thereof.   The   bank

unconditionally and irrevocably promised to pay, on

demand,   the   amount   of   liability   undertaken   in   the

guarantee without any demur or dispute in terms of

the bank guarantee. The object behind is to inculcate

respect for free flow of commerce and trade and faith in

the   commercial   banking   transactions   unhedged   by

pending   disputes   between   the   beneficiary   and   the

contractor.

5. …..The court exercising its power cannot interfere

with enforcement of bank guarantee/letters of credit

except only in cases where fraud or special equity is

prima facie made out in the case as triable issue by

strong evidence so as to prevent irretrievable injustice

to the parties.” 

                                                       (emphasis supplied)

3 1996(5) SCC 450

13

20.A bank guarantee constitutes an independent contract.   In

Hindustan   Construction   Co.   Ltd.  Vs.  State   of   Bihar   and

Others(supra), a two Judge Bench of this Court formulated the

condition upon which the invocation of the bank guarantee depends

in the following terms:­

“9. What   is   important,   therefore,   is   that   the   bank

guarantee   should   be   in   unequivocal   terms,

unconditional  and   recite   that   the   amount   would   be

paid without demur or objection and irrespective of any

dispute   that   might   have   cropped   up   or   might   have

been pending between the beneficiary under the bank

guarantee or the person on whose behalf the guarantee

was furnished. The terms of the bank guarantee are,

therefore,   extremely   material.   Since   the   bank

guarantee represents an independent contract between

the bank and the beneficiary, both the parties would

be   bound   by   the   terms   thereof.   The   invocation,

therefore, will have to be in accordance with the terms

of the bank guarantee, or else, the invocation itself

would be bad.”

21.The same principle was followed in State Bank of India and

Another Vs. Mula Sahakari Sakhar Karkhana Ltd.   

4

 wherein a

two­Judge Bench held thus:­

4 2006(6) SCC 293

14

“33. It is beyond any cavil that a bank guarantee must

be construed on its own terms. It is considered to be a

separate transaction.

34. If   a   construction,   as   was   suggested   by   Mr

Naphade, is to be accepted, it would also be open to a

banker   to   put   forward   a   case   that   absolute   and

unequivocal   bank   guarantee   should   be   read   as   a

conditional   one   having   regard   to   circumstances

attending thereto. It is, to our mind, impermissible in

law.”

22.Taking note of the exposition of law on the subject in Himadri

Chemicals Industries Limited Vs. Coal Tar Refining Co.   

5

, a two­

Judge Bench of this Court in Gujarat Maritime Board Vs. Larsen

&   Toubro  Infrastructure Development  Projects  Limited  and

Another   

6

  has laid  down the  principles for grant  or refusal  for

invocation of bank guarantee or a letter of credit.   The relevant

paragraph is as under:­

“ From the discussions made hereinabove relating to

the principles for grant or refusal to grant of injunction

to restrain enforcement of a bank guarantee or a letter

of credit, we find that the following principles should

be noted in the matter of injunction to restrain the

encashment of a bank guarantee or a letter of credit:

(i)   While   dealing   with   an   application   for

injunction   in   the   course   of   commercial

5 2007(8) SCC 110

6 2016(10) SCC 46

15

dealings, and  when  an unconditional  bank

guarantee   or   letter   of   credit   is   given   or

accepted, the beneficiary is entitled to realise

such a bank guarantee or a letter of credit in

terms   thereof   irrespective   of   any   pending

disputes relating to the terms of the contract.

(ii) The bank giving such guarantee is bound

to honour it as per its terms irrespective of

any dispute raised by its customer.

(iii) The courts should be slow in granting an

order of injunction to restrain the realisation

of a bank guarantee or a letter of credit.

(iv)   Since   a   bank   guarantee   or   a   letter   of

credit   is   an   independent   and   a   separate

contract   and   is   absolute   in   nature,   the

existence of any dispute between the parties

to the contract is not a ground for issuing an

order of injunction to restrain enforcement of

bank guarantees or letters of credit.

(v) Fraud of an egregious nature which would

vitiate the very foundation of such a bank

guarantee   or   letter   of   credit   and   the

beneficiary   seeks   to   take   advantage   of   the

situation.

(vi) Allowing encashment of an unconditional

bank  guarantee  or   a  letter   of  credit  would

result in irretrievable harm or injustice to one

of the parties concerned.”

23.The settled position in law that emerges from the precedents of

this Court is that the bank guarantee is an independent contract

between bank and the beneficiary and the bank is always obliged to

honour   its   guarantee   as   long   as   it   is   an   unconditional   and

16

irrevocable one.  The dispute between the beneficiary and the party

at whose instance the bank has given the guarantee is immaterial

and is of no consequence.  There are, however, exceptions to this

Rule when there is a clear case of fraud, irretrievable injustice or

special equities.  The Court ordinarily should not interfere with the

invocation or encashment of the bank guarantee so long as the

invocation is in terms of the bank guarantee.

24.The   guarantees   in   the   instant   case   were   unconditional,

specific   in   nature   and   limited   in   amount.     The   terms   of   the

guarantee categorically covered money which the 1

st

  respondent

had advanced against supply of the plant and equipment by SCIL.

The said guarantees covered any loss and damage caused to or

suffered by the 1

st

  respondent­plaintiff in due performance of the

contract   for   supply   of   plant   and   equipment.     The   guarantee

documents dated 16

th

 February, 1983 and 29

th

 August, 1984, as a

whole and clause 2 of the guarantee document in particular cover

the advance which had been paid by the 1

st

 respondent­plaintiff by

reason of any breach or failure by SCIL in due performance of the

17

aforesaid contracts i.e. against the contract for supply of plant and

equipment.

25.From the correspondence that has been exchanged by and

between them pertaining to invocation of the said guarantees, it

clearly manifests that the initial letter of invocation written by the

1

st

 respondent­plaintiff dated 6

th

 November, 1998 indeed was per se

inadequate and did not enumerate any condition for invocation of

said   guarantees   save   and   except   a   reference   to   “a   substantial

amount   to   be   recovered   from   SCIL”.   However,   in   the   later

correspondence   exchanged   between   the   parties   dated   19

th

December, 1998 followed by a letter dated 28

th

 December, 1998, 1

st

respondent   informed   the   appellant   Bank   that   due   to   defective

supply of plant and equipment as well as non­supply of plant and

equipment and also other contractual deficiencies of SCIL, losses

had been suffered by the 1

st

 respondent and it was duly informed to

the appellant Bank that the losses had been incurred both on

account   of   supply   of   plant   and   equipment   and   on   account   of

performance of the supply of plant and equipment.  On reading of

letters exchanged by and between 1

st

 respondent and the appellant

18

Bank pertaining to invocation of the guarantees, the condition of

the guarantees had been duly complied with.

26.In our considered view, once the demand was made in due

compliance of bank guarantees, it was not open for the appellant

Bank   to   determine   as   to   whether   the   invocation   of   the   bank

guarantee was justified so long as the invocation was in terms of

the bank guarantee.  The demand once made would oblige the bank

to pay under the terms of the bank guarantee and it is not the case

of the appellant Bank that its defence falls in any of the exception to

the rule of case of fraud, irretrievable injustice and special equities.

In absence thereof, it is not even open for the Court to interfere with

the invocation and encashment of the bank guarantee so long as

the invocation was in terms of the bank guarantee and this what

has been observed by the Division Bench of the High Court in the

impugned judgment and that reflected the correct legal position.

27.It is informed by the learned counsel for the appellant that the

Standard Chartered Bank’s predecessor in interest, ANZ Grindlay’s

Bank had opened a fixed deposit of Rs. 91,67,600/­ on 18

th

 May,

2001,   which   was   lien   marked   to   HEC(Heavy   Engineering

19

Corporation Ltd.) and is being held under the control of the Registry

of the High Court of Calcutta and the current fixed deposit is valued

at Rs. 2,32,69,129.71/­ and the total liability under the impugned

order as on date will be Rs. 2,78,03,681.64/­.  The Registry of the

High Court of Calcutta may release the money lying in the account

in   favour   of   the   1

st

  respondent   and   it   is   for   the   appellant

Bank(judgment debtor) to settle and satisfy the decree which is

impugned in the instant proceedings.

28.We   do   not   find   any   merit   in   the   appeal   which   is   hereby

dismissed.  No costs.

29.Pending application(s), if any, stands disposed of.

…………………………….J.

(L. NAGESWARA RAO)

…………………………….J.

(AJAY RASTOGI)

NEW DELHI

December 18, 2019

20

Reference cases

Description

Legal Notes

Add a Note....