As per case facts, plaintiffs filed a civil suit in 2003 against Gram Panchayat, Loharu, seeking an injunction for Plot Nos. 129 and 128, which was decreed in their favor ...
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --1--
112 IN THE HIGH COURT OF PUNJAB AND HARYANA AT
CHANDIGARH
(1) ESA No. 11 of 2024 (O&M)
State of Haryana Through SDO (Civil) Loharu ...... Appellant.
Versus
Neetu Dahiya ...... Respondent.
(2) ESA No. 12 of 2024 (O&M)
State of Haryana Through SDO (Civil) Loharu ....... Appellant.
Versus
Neetu Dahiya ...... Respondent.
1 The date when the judgment was reserved 03.07.2026
2 The date when the judgment is pronounced 10.09.2026
3 The date when the judgment is uploaded on the website 10.09.2026
4 Whether only operative part of the judgment is pronounced
or whether the full judgment is pronounced
Full
5 The delay, if any, of the pronouncement of full judgment,
and reasons thereof.
Not
applicable
CORAM: HON'BLE MR. JUSTICE HARKESH MANUJA
Present:Mr. Sharad Aggarwal, Additional Advocate General
for the appellant.
Mr. Govind Goel, Advocate for the respondent.
*****
HARKESH MANUJA J. (Oral)
[1] Vide this common order, aforementioned two Execution
Second Appeals shall stand disposed of as they involve common
question of law and fact. For the sake of brevity, the facts are being
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --2-
culled out from ESA-11 of 2024.
[2] By way of the present Execution Second Appeal, p rayer
has been made for setting aside of the orders dated 12.07.2023 and
29.09.2023 passed by the learned Courts below, whereby the
objections preferred at the instance of the appellant7State, claiming
itself to be a third party objector, to the execution of the decree dated
12.11.2005, have been dismissed.
FACTS
A. PRESENT LITIGATION
[3] Briefly stating, in the present case, plaintiffs (Decree
Holders/ Respondent’s predecessors) filed Civil Suit No. 74 of 2003
against Gram Panchayat, Loharu, seeking an injunction restraining
the Gram Panchayat from disturbing their possession of Plot No. 129,
measuring 1667 square yards, in village Loharu. Their claim rested
on a Kabala dated 04.04.1942, executed by the then Nawab of
Loharu, in favour of their predecessor, Bhikraj Jaipuria. The suit was
decreed on 12.11.2005 by the learned Additional Civil Judge (Senior
Division) holding that the plaintiffs' predecessor had purchased the
plot under the Kabala and that the plaintiffs, having inherited from
him, were owners in possession, the Gram Panchayat having
produced no document to support its own claim.
[3.1] The Gram Panchayat's first appeal, Civil Appeal No. 3 of
2006, was dismissed. The Gram Panchayat's further appeal, RSA
No. 1289 of 2007, was dismissed by this Court on 19.12.2007 and
the decree became final. A connected decree, over the adjoining Plot
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --3--
No. 128, was passed the same day in Civil Suit No. 76 of 2003 and
followed the same appellate course, the first appeal being dismissed
as Civil Appeal No. 1 of 2006 and the second appeal being dismissed
as RSA No. 2324 of 2007, also on 19.12.2007.
[3.2] The Decree Holders earlier initiated executio n
proceedings in 2008, which were withdrawn in 2014 as fully satisfied.
In those earlier proceedings, execution was pressed in respect of Plot
Nos. 126, 128 and 129, execution as to Plot No. 127 having been
separately withdrawn. The respondent in the present appeal7Neetu
Dahiya bought both properties relevant to the present appeal(s),
along with the other connected plots, under a registered sale deed
dated 14.03.2019 and on being substituted as Decree Holder,
continued the present Execution Petition No. 49/2017, seeking
warrants of possession.
[3.3] In support of its claim, the appellant State also relies
upon a demarcation report dated 10.04.2021, stated by it to have
been obtained pursuant to an order of the SDM, Loharu dated
05.04.2021. The Courts below found that this report was got
conducted by the SDO (Civil), Loharu on his own, through the Naib
Tehsildars, Loharu and Behal, without any order of the learned
Executing Court and without notice to the decree holder.
[3.4] The appellant State was not a party to either of the 2003
suits. It objected under Order 21 Rule 99 CPC claiming that the land
is part of Khasra No. 735, owned by the State, that a Government
primary school has stood on part of it since 1918, that the decrees
were obtained by fraud since the Decree Holders were never in
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --4-
possession, that the 2021 demarcation report supports its claim.
[3.5] By order dated 12.07.2023, the learned Executing Court
dismissed the aforementioned objections, holding that the Decree
Holder was admittedly not in possession, a finding drawn from her
separate dispute with the named objectors/judgment debtors, who
were themselves found to be occupying the land as vegetable
vendors and further holding that Order 21 Rule 32(5) CPC permits
possession to be restored to a Decree Holder dispossessed after an
injunction decree, relying on a settled line of decisions of this Court.
The appeals against this order, together with the connected
objections of the Poddar Charity Trust, were dismissed by common
judgment dated 29.09.2023, which also directed that execution over
any part of the land within the Government school premises be
carried out in the presence of the District Elementary Education
Officer and the Tehsildar. Still aggrieved, the present Execution
Second Appeals came to be filed at the instance of State through
SDO (Civil) Loharu.
PREVIOUS LITIGATION
[4] Municipal Committee, Loharu, formerly Gram Panchayat,
Loharu, which had merged into it in 2006, filed third party objections
in the earlier execution in 2008 and a separate suit, claiming that the
land was part of Khasra No. 271. A Local Commissioner was
appointed by the Court to visit the spot. On 05.09.2011, after framing
issues and considering the evidence led by both sides, the learned
Executing Court dismissed the objections, holding that the land is not
part of Khasra No. 271. This finding was upheld in appeal on
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --5--
15.11.2013. Municipal Committee, Loharu also separately pursued its
Khasra No. 271 claim through Civil Suit No. 94 of 2009, dismissed on
26.02.2010, with the first appeal dismissed on 09.11.2010; a further
second appeal, RSA No. 806 of 2012, was allowed on 06.10.2016
and the suit remanded but Municipal Committee withdrew it on
22.02.2017/04.03.2017 rather than proceeding to a fresh trial.
[5] A separate application was moved in 2012 by ano ther
set of claimants, Suresh Kumar, Vicky and others, s eeking
demarcation of Khasra Nos. 734 and 735. This was dismissed by
order dated 16.08.2013, passed by Sh. Sunil Kumar, Additional Civil
Judge (Senior Division), Loharu, in the earlier execution proceedings,
the Court holding that it was for the applicants themselves to prove
where Khasra Nos. 734 and 735 lay and declining to order a fresh
demarcation to do that work for them. The same order also held that
the objectors, having claimed possession only through Municipal
Committee, could not agitate a claim that had already been finally
decided against Municipal Committee.
[6] In the present execution itself, a fresh set of objectors,
Pyare Lal and others, describing themselves as vegetable vendors on
the disputed land, which they described as falling in Khasra Nos. 734
and 735, raised objections and also moved an application seeking
demarcation of Khasra Nos. 734 and 735. By a composite order
dated 15.05.2019, Additional Civil Judge (Senior Division), Loharu,
dismissed both the objections and the demarcation application,
holding that the objectors were admittedly in possession only in the
character of vegetable vendors and directed them to vacate. Their
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --6-
first appeal, CA No. 209 of 2019, was dismissed on 15.02.2021 by
the Additional District Judge, Bhiwani, who held that the objectors,
claiming through Municipal Committee's earlier allotment, were bound
by the finding of the order dated 05.09.2011 by the principle of res
judicata. Their further appeals to this Court, ESA Nos. 6 to 9 of 2021,
were dismissed on 01.12.2021, this Court holding that the objectors
had shown no right or title in the property, that finding vacant land
and occupying it to sell vegetables conferred no valuable right and
that persons with no right or title in the property had no locus standi to
seek its demarcation. The SLP (Civil) Diary No. 10057 of 2022
against that order was dismissed as withdrawn on 01.11.2022.
[7] During the pendency of the execution, a warrant of
possession issued for the decretal land came back unexecuted, the
Bailiff reporting that a portion of approximately seven feet of Plot No.
129 fell under a Government primary school.
[8] Separately, the appellant State filed suits to set aside the
2005 decrees, pleading that the decretal land formed part of Khasra
No. 735: Civil Suit No. 347 of 2013 concerning Plot No. 129 and Civil
Suit No. 342 of 2013 concerning Plot No. 128, both instituted on
24.10.2013. The suit concerning Plot No. 128 was dismissed on
10.08.2017, the learned Additional Civil Judge (Senior Division),
Loharu holding that the State had failed to prove that the land forms
part of Khasra No. 735 and that the decree dated 12.11.2005, resting
on the 1942 Kabala, was valid. The first appeal was dismissed on
19.04.2018. The second appeal, RSA No. 373 of 2022, was
dismissed by this Court on 14.02.2022, holding that no substantial
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --7--
question of law arose and further, that the appeal was liable to be
dismissed on the independent ground of an unexplained delay of 682
days in filing it. The SLP (Civil) Diary No. 24915 of 2022, was
dismissed by the Hon'ble Supreme Court on 03.07.2023. The suit
concerning Plot No. 129 followed the same course.
CONTENTIONS
ON BEHALF OF THE APPELLANT
[9] Learned counsel for the State argued that a dec ree of
permanent injunction cannot be enforced through a warrant of
possession and that the learned Executing Court went beyond what
the decrees allowed. He argued that the land is part of Khasra No.
735, owned by the State, with a Government primary school standing
on part of it since 1918. He argued that the decrees were obtained by
fraud, since the Decree Holders were never actually in possession.
He argued that the State was denied a fair chance to prove its case,
since no issues were framed and no evidence was allowed and that
the demarcation report the State obtained in 2021 supports its claim
and should have been considered.
ON BEHALF OF THE RESPONDENT
[10]
Learned counsel for the respondent argued that the
question of mode of execution was already raised before and answered
by, the learned Executing Court and does not in any event help the
State, since the finding of non7possession came from a
separate
dispute to which the State was never a party. He argued that the
State itself pursued the identical claim, that the land is Khasra No.
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --8-
735, in its own suits against these Decree Holders, over both plots
and lost in each, carrying the matter through every tier up to the
Hon'ble Supreme Court, so that the present objections are barred by
res judicata. He argued that the fraud plea gives no particulars as
required by law, that the 2021 demarcation report was made without
any order of the learned Executing Court and without notice to the
decree holder and that the order refusing to frame issues has long
become final, since it was never appealed.
DISCUSSION AND REASONING
[11] I have heard learned counsel for the parties and gone
through the paper7book and records of the case.
[12] The following questions arise for determination in these
appeals:
(i) Whether, in the absence of any independent right, title or
possession established by the appellant7State, the correctness of
the mode of execution adopted, namely restoration of possession
under Order 21 Rule 32(5) CPC upon a decree of perm anent
injunction, gives rise to any substantial question of law requiring
determination in these appeals?
(ii) Whether the appellant7State, having litigated the identical claim
that the decretal land forms part of Khasra No. 735 in its own suits to
set aside the very decrees now sought to be executed and having
failed to discharge the burden that lies upon a third party objector
under Order 21 Rules 97 to 99 CPC, can reagitate that claim through
the present objections or whether such objections are barred and
disclose no substantial question of law warranting interference with
the concurrent findings of the Courts below?
[13] The contention raised that an injunction decree cannot
be enforced by a warrant of possession is not new here. The learned
Executing Court dealt with this exact question in its order dated
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --9--
12.07.2023, relying on settled authority that allows possession to be
restored where a Decree Holder is shown to have lost possession
after the decree. This Court need not decide whether that view is
correct because the point does not help the State's case either way.
The finding of non7possession came from the Decree Holders'
dispute with their own judgment debtors, found to be occupying the
land as vegetable vendors. That dispute was decided against them
by the learned Additional Civil Judge (Senior Division), Loharu, by
order dated 15.05.2019 and their appeal, CA No. 209 of 2019, was
dismissed by the Additional District Judge, Bhiwani, on 15.02.2021,
holding that the objectors, claiming through a party already bound by
an earlier finding, could not take a different stand. Their further
appeals to this Court, ESA Nos. 6 to 9 of 2021, were also dismissed
on 01.12.2021, by this Court independently, holding that the objectors
had shown no right or title in the property and that occupying vacant
land to sell vegetables conferred no valuable right upon them. The
State was never one of those objectors/judgment debtors and does
not claim through them. It claims a wholly separate title, as owner in
its own right. Where such an independent claim is made by someone
who is a stranger to the decree, the real question is not the mode of
execution as between the Decree Holder and her objectors/judgment
debtors but whether the objector has itself proved a right, title or
possession strong enough to defeat the Decree Holder's claim. That
is what the second question answers.
[14] On the second question, the State's case encou nters a
difficulty that goes to substance and not merely to procedure. It is
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --10-
necessary to notice that the finding dated 05.09.2011 of the learned
Executing Court, on which the Courts below have pla ced
considerable reliance, addressed a single question, namely whether
the decretal land forms part of Khasra No. 271 and answered it in the
negative. Khasra No. 735 was never in issue before that Court. That
finding cannot, therefore, be read as an affirmative determination that
the decretal land either is or is not part of Khasra No. 735. The claim
that the land instead falls within Khasra Nos. 734 and 735 has, in
fact, been raised no fewer than three times: first in 2012, resulting in
the order dated 16.08.2013 dismissing the demarcation application
for want of proof; again in 2019, resulting in the order dated
15.05.2019, upheld in CA No. 209 of 2019 decided on 15.02.2021
and in ESA Nos. 6 to 9 of 2021 decided by this Court on 01.12.2021;
and once more through the demarcation report dated 10.04.2021,
which was got conducted without any order of the learned Executing
Court authorising it. On each occasion, the claim was either rejected
for want of proof by the person asserting it or in the case of the 2021
report, never even tested. None of these attempts settles the
question either way; what they establish is only that no claimant
asserting these Khasra numbers has ever discharged the burden of
proving them.
[14.1] What the State cannot escape, however, is it s own
conduct. The State has itself pursued, through its own suits rather
than mere objections, the identical claim it now presses in respect of
both plots, that the decretal land is part of Khasra No. 735. Its suit
concerning Plot No. 128, Civil Suit No. 342 of 2013, was dismissed
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --11--
on 10.08.2017, the first appeal was dismissed on 19.04.2018 and the
second appeal, RSA No. 373 of 2022, was dismissed by this Court on
14.02.2022, both on merits and independently on the ground of an
unexplained delay of 682 days. Its suit concerning Plot No. 129, Civil
Suit No. 347 of 2013, rests on the same pleadings and pressed the
same claim. Both suits were fought out on evidence, with witnesses
examined on both sides and were dismissed on a specific finding that
the State had failed to prove the connection between the decretal
land and Khasra No. 735. This is a decision on the merits in the
fullest sense and Section 11 CPC squarely bars the State from
raising that same question again, whether by suit or by objection,
against the same Decree Holders.
[14.2] A recent decision of the Hon'ble Supreme Court, though
turning on somewhat different facts, reached the same result on a
footing considerably weaker than the present one. In Sharada
Sanghi v. Asha Agarwal, 2026 INSC 292 , the party seeking to
reopen at the execution stage a question already put before a Court
was the Decree Holder rather than the objector but the principle
applied was the same. There, the appellants had, while their specific
performance suit was pending, separately sued to cancel the very
sale deeds under which the respondents claimed a rival title. Those
suits were allowed to be dismissed for default, without any decision
on the merits. When the appellants later sought to execute their
decree so as to dispossess the respondents, it was held that
dismissal for default could not attract Section 11 CPC, since that
Section requires the matter to have been “heard and finally decided.”
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --12-
Even so, the appellants were not permitted to obtain through
execution what their own abandoned suits had failed to secure,
applying the wider principle, drawn from K.K. Modi v. K.N. Modi,
(1998) 3 SCC 573, that relitigating an issue already raised and lost is
an abuse of the process of the Court, whether or not the strict
requirements of res judicata are met. The nexus between an
independent suit raising a question that goes to the decree and a
later attempt to have that same question determined in execution, is
thus squarely established; and it operates with equal force whether
the party attempting it is the Decree Holder, as there or the objector,
as here. The relevant portion of Sharada’s case (supra) is
reproduced herein:7
“45. In the case of Greenhalgh v. Mallard [(1947) 2 All ER
255] the Court had to consider different proceedings on the same
cause of action for conspiracy, but supported by different averments.
The Court held that if the plaintiff has chosen to put his case in one
way, he cannot thereafter bring the same transaction before the
Court, put his case in another way and say that he is relying on a
new cause of action. In such circumstances he can be met with the
plea of res judicata or the statement or plaint may be struck out on
the ground that the action is frivolous and vexatious and an abuse of
the process of the court.
46. In Mcllkenny v. Chief Constable of West Midlands Police Force
[(1980) 2 All ER 227] the court of appeal in England struck out the
pleading on the ground that the action was an abuse of the process
of the court since it raised an issue identical to that which had been
finally determined at the plaintiffs' earlier criminal trial. The Court
said even when it is not possible to strike out the plaint on the
ground of issue estoppel, the action can be struck out as an abuse
of the process of the court because it is an abuse for a party to re7
litigate a question or issue which has already been decided against
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --13--
him even though the other party cannot satisfy the strict rule of res
judicata or the requirement of issue estoppel. (emphasis ours)
48. In the exercise of equitable jurisdiction, this Court cannot ignore
such conduct where a party plays fast and loose with the court.
Allowing proceedings touching upon title to be dismissed for default,
while continuing to pursue relief in another proceeding concerning
the same property, raises concerns as to procedural fairness. Equity
frowns upon selective prosecution. A party cannot act recklessly with
the judicial process, invoking it as per his convenience and
abandoning it when inconvenient, only to resurrect advantage in
execution.”
[14.3] The present case stands on an even better fo oting
because the very thing missing, a hearing and a final decision on the
merits, is squarely present here. The State's suits were not dismissed
for default. They went to trial, evidence was led by both sides and a
clear finding was returned against the State. If the Hon’ble Apex
Court refused to allow relitigation even where the earlier suits had
never been tried on the merits, then the State cannot be allowed to
relitigate a claim that was actually tried, evidenced, and lost.
Sharada Sanghi’s case (supra) , therefore, only fortifies a
conclusion that Section 11 CPC compels on its own terms. The
burden of proof points the same way. In an objection of this kind, it is
for the objector to establish its right, title or possession and the State
has already had one full opportunity, with its own pleadings and its
own evidence, to discharge that burden and failed.
[15] The State's difficulty deepens further when the history of
this very execution is considered. The claim that the land is part of
Khasra Nos. 734 and 735 was pursued by a different set of objectors,
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --14-
Pyare Lal and others, under a different name, through the learned
Executing Court, by order dated 15.05.2019, the first appellate Court,
in CA No. 209 of 2019 decided on 15.02.2021 and this Court, in ESA
Nos. 6 to 9 of 2021 decided on 01.12.2021 and failed at every stage;
a Special Leave Petition against this Court's order was dismissed as
withdrawn on 01.11.2022. That outcome does not itself bind the
State, which did not claim through those objectors. But it confirms
that this specific numerical claim has already been tested to finality
once before and rejected, within this very execution.
[16] The fraud plea does not hold up either. A decr ee
obtained by fraud gives no right to the person who obtained it,
however, it is well7settled that allegations of fraud must be
substantiated with specific evidence and cannot rely solely on general
pleadings. Absence of evidence to support pleadings of fraud renders
the claim untenable. In Bishundeo Narain v. Seogeni Rai, 1951
AIR Supreme Court 280 the Hon’ble Apex Court observed:7
"
25. It is also to be observed that no proper particulars have
been furnished. Now if there is one rule which is better
established than any other, it is that in cases of fraud, undue
influence and coercion, the parties pleading it must set forth
full particulars and the case can only be decided on the
particulars as laid. There can be no departure from them in
evidence. General allegations are insufficient even to amount
to an averment of fraud of which any Ct. ought to take notice,
however, strong the language in which they are couched may
be and the same applies to undue influence and coercion. See
Order 6, Rule 4, Civil Procedure Code.”
[16.1] The present objections say no more than that the Decree
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --15--
Holders were never in possession, which falls short of a proper plea
of fraud and is harder still to accept once it is recalled that the State's
own claim on the same question has already been hea rd and
rejected, over both plots. It may also be noted that in the State's own
suits, its pleadings describe a Government Primary School as lying
on the eastern boundary of Khasra No. 735, rather than within it, a
description that sits uneasily with the present claim that a school has
stood on Khasra No. 735 itself since 1918. The 2021 demarcation
report fares no better. As already noticed, it was got conducted by the
SDO (Civil), Loharu on his own, without any order of the learned
Executing Court and without notice to the decree holder, who had no
chance to take part in the exercise or to question its findings. It
cannot be used against her, particularly against the background of
the earlier, fully contested proceedings that reached a different
conclusion.
[17] The complaint that the State was denied a chan ce to
lead evidence cannot be entertained here. The appellant State,
through the learned Government Pleader, moved its own separate
application on 13.12.2022 for framing of issues. Replies were filed on
behalf of the decree holder and the application was dismissed by the
learned Executing Court by order dated 17.01.2023, nearly six
months before the objections themselves came to be decided on
12.07.2023. That order was appealable and the State, which lost no
time in appealing the order dated 12.07.2023, chose not to assail it. It
has long attained finality, binds the parties on that question and
cannot be reopened collaterally at this stage.
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --16-
[18] Moreover, it is difficult to overlook what this Decree
Holder has had to go through merely to obtain what a Court granted
her predecessors in 2005. The Hon'ble Supreme Court , in
Satyawati v. Rajinder Singh, (2013) 9 SCC 491 , made the
following observations:7
“13. It is really agonizing to learn that the appellant 7 Decree
Holder is unable to enjoy the fruits of her success even today
i.e. in 2013 though the appellant7 plaintiff had finally
succeeded in January, 1996. As stated hereinabove, the Privy
Council in the case of The General Manager of the Raj
Durbhnga under the Court of Wards v. Maharajah Coomar
Ramaput Sing had observed that the difficulties of a litigant in
India begin when he has obtained a Decree. Even in 1925,
while quoting the aforestated judgment of the Privy Council in
the case of Kuer Jang Bahadur v. Bank of Upper India
Ltd., Lucknow, [AIR 1925 Oudh 448] , the Court was
constrained to observe that " Courts in India have to be
careful to see that process of the Court and law of procedure
are not abused by the judgment7debtors in such a way as to
make Courts of law instrumental in defrauding creditors, who
have obtained decrees in accordance with their rights. "
14. In spite of the aforestated observation made in 1925,
this Court was again constrained to observe in Babu Lal
v. M/s. Hazari Lal Kishori Lal & Ors., [(1982)1 SCC 525] in
para 29 that " Procedure is meant to advance the cause of
justice and not to retard it. The difficulty of the Decree Holder
starts in getting possession in pursuance of the decree
obtained by him. The judgment debtor tries to thwart the
execution by all possible objections... "
15. This Court, again in the case of Marshall Sons & Co. (I)
Ltd. v. Sahi Oretrans (P) Ltd. & Anr., [(1999)2 SCC
325] was constrained to observe in para 4 of the said
judgment that " ..it appears to us, prima facie, that a decree in
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --17--
favour of the appellant is not being executed for some reason
or the other, we do not think it proper at this stage to direct
the respondent to deliver the possession to the appellant since
the suit filed by the respondent is still pending. It is true that
proceedings are dragged for a long time on one count or the
other and on occasion, become highly technical accompanied
by unending prolixity at every stage providing a legal trap to
the unwary. Because of the delay, unscrupulous parties to the
proceedings take undue advantage and person who is in
wrongful possession draws delight in delay in disposal of the
cases by taking undue advantage of procedural complications.
It is also a known fact that after obtaining a decree for
possession of immovable property, its execution takes long
time.. "
16. Once again in the case of Shub Karan Bubna alias
Shub Karan Prasad Bubna v. Sita Saran Bubna and Ors.,
[2009(4) RCR (Civil) 303 : 2009(5) Recent Apex
Judgments (R.A.J.) 534 : (2009)9 SCC 689] at para 27 this
Court observed as under :
" In the present system, when preliminary decree for
partition is passed, there is no guarantee that the
plaintiff will see the fruits of the decree. The proverbial
observation by the Privy Council is that the difficulties of
a litigant begin when he obtains a decree. It is
necessary to remember that success in a suit means
nothing to a party unless he gets the relief. Therefore, to
be really meaningful and efficient, the scheme of the
Code should enable a party not only to get a decree
quickly, but also to get the relief quickly. This requires a
conceptual change regarding civil litigation, so that the
emphasis is not only on disposal of suits, but also on
securing relief to the litigant. "”
[18.1.] In the present case, in the twenty years since the decree
was passed in 2005, this land has been contested by Gram
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --18-
Panchayat, then by Municipal Committee under its new name, then
by a fresh set of claimants asserting Khasra Nos. 734 and 735, then
by another set of claimants doing the same in this very execution and
now by the State itself, twice over, first through a suit to set aside the
decree and now through these very objections. Each challenge has
run its own course, through trial, appeal and often second appeal and
each has failed. A Decree Holder is entitled to the fruits of her decree
within a reasonable time and a repeated succession of objections,
each raising a variant of the same claim after the last one has failed,
cannot be allowed to become a substitute for a right of appeal that
was never successfully exercised. The finality of a decree would
mean little if it could be indefinitely deferred by the simple device of a
new objector appearing each time an earlier one is turned away.
[19] At this stage, it is made clear that this Court is not
inclined to order a fresh demarcation. The claim that the land falls
within Khasra Nos. 734 and 735 has already been raised three times,
in 2012, in 2019 and again through the State's own report dated
10.04.2021 and has failed on each occasion. When that claim was
last pressed, by a different set of objectors, it was rejected at every
tier up to this Court, which held that a person with no right or title in
the property has no locus standi to ask for its demarcation.
Reopening that question now would simply repeat what has already
been settled three times over. The only concrete public7interest
concern disclosed by this record is the seven7foot portion of Plot No.
129 which the Bailiff, on visiting the spot in 2021, found to fall under
the Government primary school. That is a narrow and specific matter,
ESA-11-2024 (O&M) & ESA-12-2024(O&M) --19--
quite distinct from the sweeping claim of title that has been raised and
rejected. It is already addressed by the direction contained in the
impugned judgment, that execution be carried out in the presence of
the District Elementary Education Officer and the Tehsildar, Bhiwani,
which shall continue to operate. Nothing further is required.
CONCLUSION
[20] In view of the discussion made hereinabove, no
substantial question of law arises and the impugned orders call for no
interference. Consequently, the present appeal(s), being devoid of
merits, are hereby dismissed.
[21] Since the main appeal itself stands dismissed, no order
is required to be passed on the application for condonation of delay in
either appeal. The applications for stay and any other pending
miscellaneous applications, shall stand disposed of.
[22] A copy of this order be placed on the file of the
connected appeal.
[23] Pending applications, if any, also stand disposed of.
10.09.2026 (HARKESH MANUJA)
sonika JUDGE
(i) Whether speaking/reasoned: Yes
(ii) Whether reportable: Yes
Legal Notes
Add a Note....