electricity law
0  06 May, 2009
Listen in 2:00 mins | Read in 97:00 mins
EN
HI

Tata Power Company Ltd. Vs. Reliance Energy Limited and Others

  Supreme Court Of India Civil Appeal /3510/2008
Link copied!

Case Background

These statutory appeals under Section 125 of the Electricity Act, 2003​ are directed against a common judgment and order dated 6th May, 2008 passed by the Appellate Tribunal for Electricity, New ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

REPORTABLE

IN THE SUPREME COURT OF IDNIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NOS. 3510 - 3511 OF 2008

Tata Power Company Ltd. …. Appellant

Versus

Reliance Energy Limited and others … Respondents

WITH

CIVIL APPEAL NO. 4269 OF 2008

Tata Power Company Ltd. …. Appellant

Versus

Maharashtra Electricity Regulatory Commission

and others … Respondents

WITH

CIVIL APPEAL NO. 3593 OF 2008

Municipal Corporation of Greater Mumbai

BEST Undertaking …. Appellant

Versus

Reliance Energy Ltd. and others … Respondents

WITH

1

CIVIL APPEAL NO. 6098 OF 2008

Municipal Corporation of Greater Mumbai

BEST Undertaking …. Appellant

Versus

Maharashtra Electricity Regulatory Commission

and others … Respondents

AND

CIVIL APPEAL NO. 6099 OF 2008

Municipal Corporation of Greater Mumbai

BEST Undertaking …. Appellant

Versus

Maharashtra Electricity Regulatory Commission

and others … Respondents

J U D G M E N T

S.B. SINHA, J.

INTRODUCTION

These statutory appeals under Section 125 of the Electricity Act, 2003

(hereinafter called and referred to for the sake of brevity as ‘the 2003 Act’)

are directed against a common judgment and order dated 6

th

May, 2008

2

passed by the Appellate Tribunal for Electricity, New Delhi in Appeal

No.143 of 2007 and I.A. No.70 of 2008 whereby and whereunder a

judgment and order dated 6

th

November, 2007 passed by the Maharashtra

Electricity Regulatory Commission (MERC) was set aside.

THE PARTIES

Whereas Appellants, the Tata Power Company Ltd. (TPC) has two

divisions – ‘Generation’ [TPC (G)] and ‘Distribution’ [TPC (D)]; the Brihan

Mumbai Electricity and Transport Corporation (BEST) is a distribution

company; Respondent - Reliance Energy Ltd. now named as Reliance

Infrastructure Ltd. (RInfra) is a generating as well as a distributing company

within the meaning and provisions of the 2003 Act.

All of them have been operating in the city of Mumbai including

Suburban Mumbai of having approximately 384 sq. Km in area and the city

of Mumbai having approximately 60 sq. Km in area.

We may place on record that the aggregate capacity to generate

electricity of TPC is 1777 MW of power. The generation capacity of the

respondent RInfra is 500 MW, but it uses its power, as per its license, only

to serve its own consumers.

BACKGROUND FACTS

3

The following factual matrix relevant for proper appreciation of the

legal issues arising in the present case may be noticed.

Indisputably TPC has been generating and supplying electricity to

distribution licensees like RInfra and BEST for over a century. On or about

5

th

March, 1907 ; 3

rd

April, 1919 ; 15

th

November, 1921 and 19

th

November,

1953, the Bombay (Hydro-Electric) Licence ; the Andhra Valley (Hydro-

Electric) Licence, the Nila Mula Valley (Hydro-Electric) Licence and

Trombay Thermal Power Electric Licence respectively were granted to TPC

to generate and supply power in terms thereof.

Since 1907 consumers of electricity in Mumbai were served by

distribution lisensee, BEST (for the island city of Mumbai) and since 1926

onwards by RInfra (for suburban Mumbai). Indisputably demand of

electricity earlier was relatively low as compared to the demand post 1990s.

Nevertheless TPC progressively increased its capacity to meet the demand

of both RInfra and BEST. Issues of wrongful inter se allocation between the

various distribution licensee never really arose prior to the present scenario.

On or about 1

st

October, 1916 TPC and BEST (both Appellants

herein) entered into an agreement in terms whereof the former agreed to

4

supply and later agreed to buy power in bulk. This agreement was renewed

from time to time.

Subsequently a distribution licence was also issued to BSES,

predecessor in interest of respondent RInfra to supply power to the

consumers in the suburbs of Mumbai. Under the said license RInfra was

authorized to purchase electricity from the bulk Licensees. Accordingly it

began procuring bulk power from TPC generating stations according to its

requirements from time to time, based on its consumer load (TPC had been

the only bulk licensee for Mumbai). Indisputably, however, no agreement in

writing had ever been entered into by and between TPC and RInfra. It must

be noted in this regard that since its inception and till a very long time

RInfra continued to buy its entire requirement of power from TPC.

However in 1978 RInfra’s distribution license was amended to permit

it to put up a generation station to supply power only to its own consumers.

In or about 1995, RInfra commissioned its 500MW generating plant at

Dahanu, pursuant whereto the quantum of power purchased by it from TPC

was reduced by about 54%. Even then RInfra had been buying nearly 42%

of the energy generated by TPC. It had continued to purchase its remaining

requirements of power from TPC.

5

On or about 1998 a Committee on Review of Power demand in

Mumbai area commonly known as the ‘Kukde Committee’ was constituted

by the Government of Maharasthtra for the purpose of studying the techno

commercial feasibility of new power generation projects at Bhivpuri (500

MW) and Palghar (495 MW) proposed to be set up by TPC and RInfra

respectively.

It is accepted that before the said Committee, RInfra took the stand

that it wanted to supply to its existing consumers with the power generation

from its own proposed project instead of providing power from TPC. The

committee submitted its report on or about 26

th

May, 1998. In its report it

recommended for grant of approval for both the said projects. It was

furthermore recommended that the additional power generated from RInfra’s

project be used only to meet the future growth in demand arising from the

consumers of Mumbai. The Kukde Committee also recommended that first

the then existing generation facility of TPC be fully utilized to meet the

requirements of the current consumers of RInfra so as not to disturb the

existing technical and commercial arrangement between TPC and RInfra.

Subsequent thereto a ‘Principles of Agreement’ (POA) was executed

between TPC and RInfra on or about 31

st

January, 1998 inter alia providing

that there be a minimum power purchase (‘off-take’) on the basis of ‘pay or

6

take’ in each financial year by RInfra on the basis of its consumer demand

forecast. The POA also envisaged execution of a detailed Power Purchase

Agreement by the parties. However, no such agreement ever fructified.

Thereafter in 2000 the Maharashtra State Electricity Board [MSEB]

gave consent to the Saphale power project of RInfra. Approval however was

not granted to the Bhivpur project of TPC. Against the said order granting

approval in favour of RInfra, TPC filed a writ petition being No.916 of

2001 before the Bombay High Court on the premise that it had not approved

TPC’s proposal for the Bhivpuri power project despite it having been

submitted at an earlier point of time. It was alleged in the said petition that

the impugned decision of the MSEB was illegal and contrary to the 1948

Act, which forbade it from granting sanction to any other person to generate

electricity if the existing bulk licensee was able and willing to supply power.

A prayer inter alia was made therein that the recommendations of the Kukde

Committee should not be implemented.

In response to the said petition MSEB withdrew its approval to

RInfra’s Power project on the ground that TPC being the bulk licensee was

able and willing to supply power to it. On the withdrawal of the approval

TPC too withdrew its petition filed before the High Court

7

Thereafter the 2003 Act came into force with effect from 26

th

May,

2003. Under the new Act the ‘Generating Companies’ have been given

freedom of choice to sell power to any person or licensee. The Act also

introduced the concept of ‘open access’ which allows the distribution

licensee to source its power from any generating company. The distributors

accordingly under the changed law do not have to depend upon state based

generators to meet their needs.

PROCEEDING UNDER THE ACT

RInfra applied to Maharashtra Electricity Regulatory Commission

[MERC] for grant of ‘open access’ to bring in power from sources, outside

Mumbai, to supply electricity to its consumers.

On or about 11

th

June, 2004 TPC through its executive summary for

Annual Revenue Requirement (ARRA) filed before the MERC for the year

2003-04 insisted on having a PPA with RInfra as a condition for supply of

power to RInfra in the future. It, however, rejected the said demand on the

ground that there was no ‘legal justification’ or ‘tenable reason’ for entering

into such an agreement.

8

On or about 23

rd

August, 2005 the Commission made Regulations

known as MERC (Terms and Conditions of Tariff) Regulations, 2005,

Part-D whereof required all power purchase agreements/arrangements

entered into by the Distribution Licensees to be approved by MERC. The

regulation also provided that any amendment to such an agreement or

arrangement would require prior permission of the MERC irrespective of

whether such an agreement or arrangement was approved by the commission

or not.

MERC, on an application, filed by RInfra for direction to TPC to

provide additional outlets, agreed to the position that distribution licensees,

such as RInfra, can procure their power from any generating company in

India and because of the said flexibility in the 2003 Act also directed it to

enter into a PPA with TPC.

On or about 18

th

January, 2006, BEST executed a PPA with TPC for

purchase of 800 MW of power for a period of 10 years which was

subsequently revised in terms of the MERC’s order dated 7

th

July, 2006.

The said PPA was submitted for approval of MERC on 27

th

December, 2006

which was registered as Petition No.87 of 2006.

9

On or about 12

th

July, 2006 a Minutes of the Meeting (MoM) was

signed between TPC (G) and TPC (D) for allocation of power to TPC (D).

TPC (D) indicated requirement of 500 MW power from TPC (G) in the said

MoM. A minor modification in the MoM was directed by MERC, pursuant

whereto, on or about 16

th

March, 2006, TPC (D) entered into a PPA with

TPC (G) for 477 MW power which was submitted for approval of MERC on

27

th

December, 2006 being Petition No.87 of 2006.

RInfra filed an application for intervention before the commission in

both the applications for approval of both the PPAs It subsequently also

filed its objections in the said proceedings.

It appears from the record that in the meanwhile TPC proposed to

enter into PPA with RInfra for its balance quantity after meeting the

contractual requirement of BEST for 800 MW and of TPC (D) for 477 MW

of electricity . The offer was made by TPC to RInfra for supply of 600 MW

which was not accepted. The later instead insisted on obtaining a much

higher quantum of power based on its consumer demand. TPC rejected the

said demand keeping in view its continuing obligation to its own consumers

and also those of BEST. No consensus was therefore reached with respect

to the said PPA between TPC-G and RInfra.

10

On or about 2

nd

April, 2007 MERC passed generation tariff order for

TPC (G) for the period 2006-2007. Commission, however, took the view

that since PPAs had not been approved, by way of an interim arrangement, it

would allocate available energy from TPC (G) on the basis of coincident

peak demand of the distribution licensees.

Aggrieved by and dissatisfied therewith BEST preferred an appeal

before the Electricity Appellate Tribunal on 26

th

April, 2007 which was

marked as Appeal No.41 of 2007. Similar appeal was filed by TPC against

the tariff order dated 2

nd

April, 2007 providing for allocation of TPC (G)

capacity on the basis of coincidence peak demand on 4

th

May, 2007, which

was marked as Appeal No.51 of 2007.

By an order dated 17

th

May, 2007 the Appellate Tribunal in Appeal

No.51 of 2007 filed by TPC directed MERC to decide BEST’s and TPC’s

petitions for approval of PPA and recorded the undertaking of all parties that

they would not claim equities on the basis of order of MERC dated 2

nd

April, 2007.

RInfra in the meantime initiated a proceeding under Section 86 of

2003 Act before MERC seeking direction against TPC (G) to allocate 762

11

MW to it and to enter into a PPA with RInfra on the said basis, which was

marked as Case No. 30 of 2007.

By reason of a judgment and order dated 6

th

November, 2007 the

Commission approved PPA between TPC (G) and BEST and the

arrangement between TPC (G) and TPC (D) for supply of 800 MW and 477

MW of power respectively with effect from 1

st

April, 2008. In relation to its

own jurisdiction it was, however, opined that it can issue direction upon the

generating companies in terms of Section 23 of 2003 Act.

RInfra preferred an appeal thereagainst which was marked as Appeal

No.143 of 2007.

Two separate appeals were preferred by BEST and TPC questioning

the interpretation of Section 23 of 2003 Act by the Commission which were

marked as Appeal No.159 of 2007 and Appeal No. 14 of 2008 respectively.

MERC while dealing with the application filed by RInfra for

continuing the tariff for financial year 2007-2008 even beyond 31

st

March,

2008 till the tariff year 2008-2009, by an order dated 1

st

April, 2008 clearly

indicated that for the purpose of fixing the distribution tariff of all the three

distribution licensees namely, BEST, TPC (D) and RInfra, based on the

share of generation capacity of TPC (G), it will be proceeding in the manner

12

as directed by the Commission in its order dated 6

th

November, 2007

approving the PPA entered into by and between TPC (G) and BEST and

TPC (G) and TPC (D).

Appellate Tribunal thereafter passed the impugned judgment on 7

th

April, 2008 in Appeal No.51 of 2007 filed by TPC against the tariff order

dated 2

nd

April, 2007 on the submission of appellant-TPC that it was not

pressing for the adjustment of any amount that may be payable by RInfra to

TPC for the period 2007-2008 in terms of the interim order of the Appelalte

Tribunal dated 17

th

May, 2007.

RInfra filed petition marked as Case No.6 of 2008 before MERC on

17

th

April, 2008 seeking equitable allocation of power generation from TPC

(G)’s generation facility under Section 23 of 2003 Act.

ORDER OF THE COMMISSION

The Commission passed a fairly detailed order. It took into

consideration the factual matrix ; the nature of agreements ; submissions of

BEST; its earlier orders ; contentions raised by BEST in its original

application as also revised petitions ; firm capacity and other details.

It noticed that a Technical Validation Session in case No. 87 of 2006

was held on 18

th

April, 2007 including justification for entering into a long

13

term contract for ten years taking into account the demand forecast during

peak and off-peak hours and analysis of other sources of power and

availability of transmission capacity in future. It also took into account the

basis for arriving at 10 paise/kwh surcharge payable by TPC (G) to BEST in

case the availability of generating stations of TPC (G) falls below 85%

alongwith supporting computations. It also noticed the mechanism for

assessing the amount of compensation payable in case of termination due to

events of default may be incorporated in the PPA. It furthermore noticed

that before it a public hearing was held on 17

th

July, 2007 wherein points

were raised by the participants and BEST’s response thereto.

We may also place on record that that RInfra did not make

submissions in the technical session but did so only at the public hearing.

The Commission took up Case No.88 of 2007 and noticed the details

of Technical Validation Session in regard to internal capacity allocation

from the generation division of TPC to its own distribution division

including RInfra’s intervention application. It also noticed the details in

regard to the public hearing in the aforementioned case which was held on

29

th

August, 2007. Similarly the application filed by RInfra which was

marked as Case No.30 of 2007 was considered in great details.

14

Submissions of learned counsel appearing for the parties were noticed.

Part IV of its judgment contains ‘the decision with reasons’. It took into

consideration the relevant provisions of law. It noticed its functions under

Section 86 of the 2003 Act as also various Regulations framed thereunder.

It placed on record that it had issued certain directives to the distribution

licensees from time to time. It opined that submission of Power Purchase

Agreements (PPA) for approval are imperative as the objective thereof is to

remove any uncertainty that may be faced by the consumers of a distribution

licensee who does not have any written terms and conditions. It opined that

RInfra’s recalcitrant attitude in seeking approval of the terms and conditions

of its power procurement deserved to be deprecated, whereupon a warning

was administered.

Submissions of BEST before the Commission were :-

(i)Ambit of approval process under Section 81(1)(b) of 2003 Act

was required to be restricted to the price and the Commission

had no power to reduce the quantum agreed by distribution

licensee and the generating company under the PPA submitted

for approval.

15

(ii)Insertion of the word “including” before the words “the price”

makes the intention of the legislature clear that the scope of the

power to regulate is extensive.

(iii)Power of a Regulatory Body is extensive under Section

86(1)(b) of the 2003 Act. Even the generator can be subject to

Regulations.

(iv)Section 86(1)(b) is required to be harmoniously read. For

invoking the provisions of Section 60 of the Act, the following

three situations must conclusively be shown to exist :

(a)any agreement has been entered into which is likely to

cause or causes an adverse effect on competition in

electricity industry; or

(b)dominant position has been abused which is likely to

cause or causes an adverse effect on competition in

electricity industry; or

(c)a combination has entered into which is likely to cause or

causes an adverse effect on competition in electricity

industry.

FINDINGS OF THE COMMISSION

16

The Commission discussed clause by clause of the PPAs entered into

by and between TPC-D and BEST and TPC (G) and TPC (D) in terms of the

MERC Regulations. It took into consideration each of the factors

enumerated in those PPAs to hold that they were justified for meeting the

requirements of BEST and TPC (D), stating :-

“Based on the above analysis, the Commission is

satisfied with the data and information submitted

by BEST and TPC substantiating the requirements

of Regulation 24 of the MERC (Terms and

Conditions of Tariff) Regulations, 2005”

In conclusion the Commission held that Section 86 (1) (b) of the 2003

Act would be applicable only when the PPA is produced before it for its

approval and not otherwise.

It also noted that it has the jurisdiction to go into the question with

regard to the quantity of supply of electrical energy in terms of the PPAs.

However, as the PPA took into consideration the demand of the licensee for

the next 10 years, the stipulations contained therein were held to be fair and

proper.

It was opined that the language of Section 60 of the Act being

restrictive, no cause had been made out for issuance of any direction

thereunder.

17

It furthermore noted that Section 23 of the 2003 Act brought within its

fold a generating company but no case had been made for issuance of any

direction thereunder while considering the question of grant of approval of a

long term PPA.

On the aforementioned findings the Commission approved the PPA of

BEST and TPC (D). It was directed :-

“(C)REL-D is directed to file long-term Power

Purchase Agreements for procurement of power

from generating Companies and other sources at

the earliest. Also, REL-D should submit Power

Purchase Arrangement for procurement of power

from its own generating unit REL-G, for the

Commission’s approval, within one month of the

issue of this Order.

(D)In the past, in view of the prevailing supply

shortage situation, the Commission has invoked its

powers under Section 23 of the EA 2003, and has

directed the distribution licensees to share the

available generation capacity in a particular ratio,

based on the share of non-coincident peak demand

for FY 2006-07, and subsequently based on the

share of the coincident peak demand for FY 2007-

08, since the coincident peak demand data was

available by then. The situation in the previous

years was compounded by the fact that there were

no approved PPAs between the parties, and an

important aspect like power procurement cannot

operate in a vacuum. However, the Commission’s

powers to issue directions under Section 23 of the

EA 2003 are wide and if necessary and found

expedient, the Commission may issue such

directions in future also, despite the existence of

any or all the approved PPAs, in case of any

18

shortfall in contracted capacity, in order to protect

interests of consumers. During the transition

period, in case of shortage of supply of electricity

in the city of Mumbai, the Commission will assess

the situation at the time of conduct by the

Commission of Annual Performance Review in

terms of Regulation 17 of the MERC (Terms and

Conditions of Tariff) Regulations, 2005 and assess

whether any specific direction to the distribution

licensees is required to be issued, to ensure that the

consumers of all three distribution licensees in

Mumbai city are treated equitably and for

equitable distribution of electricity. It is clarified

that the supply in the form of generation capacity

does not necessarily have to be located within

Mumbai or even within Maharashtra, and the

supply availability referred to here is in the context

of firm long-term power purchase agreements

between the distribution licensees and power

suppliers. With the above observations, the

Commission disposes of Case No. 87 of 2006,

Case No. 88 of 2006 and Case No. 30 of 2007.”

APPELLATE TRIBUNAL

Four appeals were preferred by RInfra theregainst. Appellants also

preferred appeals in regard to the interpretation of Section 23 of 2003 Act.

The Tribunal by reason of its impugned judgment dated 6

th

May, 2008

disposed of the said appeals.

19

Therein apart from the factual matrix involved in each case, statutory

provisions and the submissions made by learned counsel for the parties were

duly noticed. The tribunal also extracted in details the averments made by

TPC in its writ petition before the High Court, which as noticed

hereinbefore, had ultimately been withdrawn.

The Tribunal in paragraph 93 of the judgment formulated the

questions for its consideration which read as under :-

“93. The main question in the set of these appeals

revolves around the approval of PPA between

TPC(G) and BEST and arrangement between

TPC(G) and TPC(D). These appeals raise the

question whether the Commission has the power to

disapprove the PPA and allocate the power of a

generating company amongst the distribution

licensees by regulating the supply in terms of

Section 23 of the Act?”

The Appellate Tribunal did not disturb the findings of the

Commission in regard to its interpretation of Section 60 as also Section 23

of the 2003 Act.

It, however, held that having regard to the purpose and object of the

Act, the Commission should have taken into consideration the need of the

first respondent in regard to the allocation of quantity of supply

20

Upon considering the provisions of the Act and the Regulations, the

Tribunal held :

“102. We note from the above regulations that the

Commission itself recognizes an agreement or an

arrangement for long-term power procurement by

a Distribution Licensee. Regulations require prior

approval of the Commission for any change to an

existing arrangement or agreement for long term

procurement. When an arrangement for power

procurement between TPC and BEST as also

between TPC and REL does exist, how the

Commission failed to consider the claim of REL.

103. We conclude from the aforementioned that

the Commission has wide powers to regulate the

quantity of energy that may be supplied by a

generating company to a distribution licensee

when both are under the jurisdiction of the same

Commission.

104. It is not in dispute that the claims of REL

have not been considered by the Commission

while approving the PPA between the TPC(G) and

BEST and arrangement between TPC(G) and

TPC(D). It is also not in dispute that the approval

of PPA and the arrangement has affected the

allocation of power to REL. The interests of REL

have been adversely affected by the Commission

in violation of the principle of natural justice. The

Commission ought to have considered the claim of

REL for allocation of power while considering the

approval of PPAs between TPC(G) and BEST and

arrangement between TPC(G) and TPC(D).

105. In the circumstances, appeal No. 143 of 2007

is allowed and order dated November 06, 2007 of

the MERC approving the PPA of TPC and BEST

and arrangement between TPC and TPC(D) with

reference to allocation of power to BEST and

21

TPC(D) is set aside. The Commission is directed

to consider the question of approval of PPA and

the arrangement afresh after taking into

consideration the claims of BEST, REL and

TPC(D). While considering the case of the parties

the Commission shall have regard to the fact that

the consumers of respective areas have been

bearing the Depreciation and Interest on Loan

elements of the Fixed Cost of tariff and also

consider all other submissions of the parties which

are permissible in the law.”

The Tribunal set aside the approval of PPA’s and remanded the matter

to MERC for its reconsideration.

The Tribunal, furthermore, did not interfere with the tariff order dated

2

nd

April,2007 while disposing of Appeal No. 41 of 2007 filed by BEST,

opining that the period for which allocation was made on the basis of

consistence peak demand had already expired

Both TPC as also BEST are before us questioning the legality and/or

validity of the final order passed by the Appellate Tribunal as also the orders

disposing of the interim applications.

SUBMISSIONS OF THE COUNSEL

Mr. Jaideep Gupta and Mr. Rohington Nariman, learned senior

counsel appearing on behalf of the appellants would submit :-

22

i)The Appellate Tribunal misdirected itself in passing the

impugned judgment in so far as it failed to take into

consideration that in terms of the provisions of the 2003 Act the

Commission had no jurisdiction to interfere with the functions

of the generating company and its jurisdiction was restricted to

regulate the terms of the agreement between a generating

company and a distribution company, particularly when no

fault with the approval of the PPA entered into by and between

TPC and BEST and TPC (G) and TPC (D) was found by it.

ii)RInfra also filed an application and the same having been

considered in great details, it has incorrectly been held by the

Appellate Tribunal that the principle of natural justice had not

been complied with.

iii)Direction of the Tribunal to the Commission to take into

consideration contribution towards depreciation and interest on

loan elements of fixed costs of TPC generation capacity while

considering the claim of RInfra is without any basis inasmuch

as :-

(a)Such direction of the Appellate Tribunal has the effect of

recognizing ownership of consumers over the generation

23

assets. The Act does not recognize any such right of

ownership of consumers over the generating assets.

(b)RInfra consumers have only paid towards costs of the

generation of the power consumed by them, which the

developer is entitled to recover as reasonable cost of

electricity and return of his investment.

If this argument is taken to its logical conclusion, every

consumer of electricity, whether domestic, industrial or

commercial, would claim ownership of generation plants for the

purpose of supply of power to their respective areas.

iv)2003 Act must be interpreted not only having regard to history

of legislation but also the purpose and object it seeks to achieve

wherefor the Commission and the Tribunal were not only

required to consider the chapter headings but also the marginal

notes.

v)Principles of harmonious construction of the provisions of the

statutes having not been resorted to either by the Commission

or by the Tribunal, they committed a serious error in opining

that Section 23 not only controls distribution of power but also

generation thereof.

24

Dr. A.M. Singhvi, learned senior counsel appearing on behalf of the

respondent, on the other hand, urged :-

(i)The factual matrix involved herein would clearly demonstrate a

long standing commercial relationship existing between TPC

(G) and RInfra and/or its predecessor-in-interest in regard to

supply of electrical energy for the consumers of suburb

Mumbai (approximately 384 sq. kms. area) being twenty five

lacs in number out of which eighteen lacs being small

individual and relatively economically weaker sections

consuming less than 300 units per month vis-à-vis the number

of consumers BEST serves, all of being in the town of Mumbai

being approximately of an area of 60 sq. kms. area who are

higher paying consumers and those of TPC (D) having 23846

consumers, the Commission must be held to have its

jurisdiction rightly to allocate supply of power to the licensees

in greater public interest.

(ii)2003 Act does not contemplate exclusion from the purview of

the Commission’s jurisdiction of all matters relating to

generation but also covers regulation of several aspects thereof

including tariff of generation companies, sale of electricity by

25

generators, maintaining efficient supply, securing the equitable

distribution of electricity, promotion competition, preventing

abuse of dominant position by generating companies,

preventing advese effect on competition in electricity industry

etc.

(iii)Regulation of tariff would bring within its fold inter alia the

quantity that a generator supplies to a distribution licensee or a

consumer and various interconnected and interrelated issues

which have a bearing on generation of electricity.

(iv)It is not that the 2003 Act merely empowers the Commission to

fix only the generating tariff and to otherwise adopt a hands off

attitude towards the generation company on the alleged ground

that the Commission did not have any other jurisdiction over

the generating companies.

(v)The principle of ‘purposive interpretation’ should be resorted to

for interpreting a statute regulating generation, distribution and

supply of electrical energy which is in short supply in the

country wherefor endeavour should be made to ascertain the

object and purport not only by reading one of the provisions of

the Act but the preamble thereof as also the other important

26

provisions, namely Sections 2(70) ; 7 ; 10 ; 11 ; 23 ; 60 ;

86(1)(b) and 86(1)(f) of the 2003 Act.

(vi)Only because the generation of electricity was taken outside the

purview of the licensing regime, the same would not mean that

a generator of an electrical energy would be entitled to free

wheel its entire supply to any person it likes and in any

quantity it likes.

(vii)The chapter heading and the marginal note of Section 23 of

2003 Act cannot be resorted to for its interpretation as it is well

settled that marginal notes do not control the meaning of the

section.

(viii)Chapter heading should not be treated to be containing

provisions dealing with a particular subject matter as rigid

compartment and it is not uncommon that a provision, rule or

regulation relatable to one chapter is in fact interpreted, applied

or related to other chapters of the same Act.

(ix)The term “supply” having been defined in Section 2(70) of the

2003 Act, in any event, the jurisdiction of the Commission

would clearly cover a situation where the power of regulation in

27

relation to supply and ensuring efficient thereof are required to

be regulated.

(x)Neither Section 23 nor Section 86(1)(b) of 2003 Act provides

‘any context to the contrary’ for the purpose of application/

interpretation of term “supply” as defined in Section 2(70).

Context of Section 86(1)(b) read with Section 23 and Section

2(70) of the Act if construed with the preamble thereof, upon

applying the principle of purposive interpretation, it would be

evident that the said provisions constitute an invisible seamless

web creating a context which, far from being to the contrary,

mutually reinforces each other and points only in one direction,

namely the necessity to regulate supply of electrical energy not

only at the hands of the licensees but also the generating

companies.

(xi)The basic and overriding purpose of 2003 Act being ensuring

generation of electricity and efficient equitable distribution

thereof with the interest of the consumers in mind the

generating companies cannot be permitted to act outside the

purview of Regulations of a Regulatory Commission and

consequently it must be held that the Commission has full

jurisdiction not only to regulate tariff and price issues but also

28

distribution of quantum of electricity and other necessary

concomitance thereto.

(xii)The word “regulate” reflects a statutory mandate of all

encompassing jurisdiction.

(xiii)TPC being in a public utility service, it is required to act fairly,

equitably and not in an arbitrary fashion.

(xiv)The principle of harmonious construction may be resorted to

only in a case where there exists any contradiction or

overlapping as in this case the provisions of Sections 11 and 23

apply in different fields, there is absolutely no necessity to take

recourse to the said principle.

(xv)As TPC (G)’s acts and omission, despite its status as

commercial entity, constitutes an abuse of its dominant

position, which cannot be permitted to take rccourse to “cherry

picking” of RInfra’s high end consumers.

ISSUES ARISING HEREIN

Although before us a large number of contentions had been raised, the

core questions, which arise for our consideration, are :-

29

(A)Whether recourse to Section 23 of the Act can be taken for

issuance of any direction to the generating company?

(B)Whether the Commission while applying the provisions of

Section 86(1)(b) of the Act could also take recourse to Sections

23 and 60 thereof?

(C)Whether equitable allocation of power generated by a

generating company is permissible?

LEGISLATIVE HISTORY

1910 ACT

The earliest statute relating to control of generation of supply,

distribution of electrical energy which governed the field was Indian

Electricity Act, 1910 (1910 Act). Part-II of the said Act provided for supply

of energy. Section 3 thereof provided for grant of licence to any person to

supply energy in any specified area and also to lay down or place electric

supply-lines for the conveyance and transmission of energy.

However, after coming into force the 1948 Act, such licences could be

granted only upon consulting the State Electricity Boards constituted and

incorporated under Sections 5 and 12 thereof. Section 22-B in the 1910 Act,

30

which was inserted by Act 32 of 1959, provided for power to control the

distribution and consumption of energy stating :-

“Section 22B - Power to control the distribution

and consumption of energy

(1) If the State Government is of opinion that it is

necessary or expedient so to do, for maintaining

the supply and securing the equitable distribution

of energy, it may by order provide for regulating

the supply, distribution, consumption or use

thereof.

(2) Without prejudice to the generality of the

powers conferred by sub-section (1) an order made

thereunder may direct the licensee not to comply,

except with the permission of the State

Government, with—

(i) the provisions of any contract, agreement or

requisition whether made before or after the

commencement of the Indian Electricity

(Amendment) Act, 1959, for the supply (other

than the resumption of a supply) or an increase

in the Supply of energy to any person, or

(ii) any requisition for the resumption of supply

of energy to a consumer after a period of six

months, from the date of its discontinuance, or

(iii) any requisition for the resumption of

supply of energy made within six months of its

discontinuance, where the requisitioning

consumer was not himself the consumer of the

supply at the time of its discontinuance.”

1948 ACT

31

The 1948 Act was enacted to provide for the rationalization of the

production and supply of electricity and generally for taking measures

conducive to electrical development. Section 43 conferred power on the

Board to enter into arrangements for purchase or sale of electricity under

certain conditions. Section 43-A provided for terms, conditions and tariff for

the sale of electricity generated by it to any other person with the consent of

the competent government or governments.

Section 44 of 1948 Act also placed restrictions on establishment of

new generating stations or major additions or replacement of plant in

generating stations except with the previous consent in writing of the Board,

to establish or acquire a new generating station or to extend or replace any

major unit of plant or works pertaining to the generation of electricity in a

generating station.

1998 ACT

The Parliament enacted Electricity Regulatory Commissions Act,

1998 (for short, “the 1998 Act”) to provide for the establishment of a Central

Electricity Regulatory Commission and State Electricity Regulatory

Commissions, rationalization of electricity tariff, transparent policies

regarding subsidies, promotion of efficient and environmentally benign

policies and for matters connected therewith and incidental thereto.

32

In terms of the 1998 Act, the Regulatory Commission was conferred

with the power to determine tariff for all sales by a generating company in

terms of Section 22(1)(c) thereof. It further required in line with the

provisions of the 1910 Act as also the 1948 Act, for the State Commission

constituted thereunder to regulate investment approval for generation,

transmission, distribution and supply of electricity to require the licensees to

formulate prospective plans and schemes for the promotion of generation,

transmission, distribution and supply of electricity and to devise proper

power purchase and procurement process, and to regulate the assets and

properties related to the electricity industry, etc. The 1998 Act did not

envisage de-licensing of generating companies as in terms thereof the

following requirements were to be complied with on the establishment and

operations of a generating station:

(a)Setting up a generating station requires approval of a Board (u/s

44 of Electricity Supply Act, 1948)

(b)Sale of Power by a generating company of any person requires

approval of the competent government (u/s 43A of Electricity

Supply Act, 1948)

(c)Investment approval for generating was regulated by the

ERCA.

33

(d)The tariff for all supply of power by a generating company was

determined by the Regulatory Commission.

(e)The generating company was also regulated from the

perspective of transmission grid stability and operation, which

is necessary on the technical side.

Section 22(1)(c) of the 1998 Act reads :-

“Section 22 - Functions of State Commission

(1) Subject to the provisions of Chapter III, the

State Commission shall discharge the following

functions, namely:--

(c) to regulate power purchase and procurement

process of the transmission utilities and

distribution utilities including the price at which

the power shall be procured from the generating

companies, generating stations or from other

sources for transmission, sale, distribution and

supply in the State;”

2003 ACT

The 2003 Act was enacted to consolidate the laws relating to

generation, transmission, distribution, trading and use of electricity.

Before noticing the relevant provisions of the 2003 Act, we may place

on record the statement of objects and reasons for enactment thereof, the

relevant portion whereof reads as under :-

34

“3.With the policy of encouraging private

sector participation in generation, transmission and

distribution and the objective of distancing the

regulatory responsibilities from the Government to

the Regulatory Commissions, the need for

harmonizing and rationalizing the provisions in the

Indian Electricity Act, 1910, the Electricity

(Supply) Act, 1948 and the Electricity Regulatory

Commissions Act, 1998 in a new self contained

comprehensive legislation arose. Accordingly, it

became necessary to enact a new legislation for

regulating the electricity supply industry in the

country which would replace the existing laws,

preserve its core features other than those relating

to the mandatory existence of the State Electricity

Board and the responsibilities of the State

Government and the State Electricity Board with

respect to regulating licensees. There is also need

to provide for newer concepts like power trading

and open access. There is also need to obviate the

requirement of each State Government to pass its

own Reforms Act. The Bill has progressive

features and endeavours to strike the right balance

given the current realities of the power sector in

India. It gives the State enough flexibility to

develop their power sector in the manner they

consider appropriate. The Electricity Bill, 2001

has been finalized after extensive discussions and

consultations with the States and all other stake

holders and experts.

4.The main features of the Bill are as follows:-

(i)Generation is being delicensed and

captive generation is being freely permitted. Hydro

projects would, however, need approval of the

State Government and clearance from the Central

Electricity Authority which would go into the

issues of dam safety and optimal utilization of

water resources.

35

(ii)There would be a Transmission

Utility at the Central as well as State level, which

would be a Government company and have the

responsibility of ensuring that the transmission

network is developed in a planned and coordinated

manner to meet the requirements of the sector.

The load dispatch function could be kept with the

Transmission Utility or separated. In the case of

separation the load dispatch function would have

to remain with a State Government

organization/company.”

Section 2 is the interpretation section.

Section 2(4) defines “appropriate Commission” to mean the Central

Regulatory Commission referred to in sub-section (1) of section 76 or the

State Regulatory Commission referred to in section 82 or the Joint

Commission referred to in section 83, as the case may be.

“Consumer” has been defined in section 2(15) to mean any person

who is supplied with electricity for his own use by a licensee or the

Government or by any other person engaged in the business of supplying

electricity to the public under this Act or any other law for the time being in

force and includes any person whose premises are for the time being

connected for the purpose of receiving electricity with the works of a

licensee, the Government or such other person, as the case may be;

36

Section 2(17) defines “distribution licensee” to mean :-

(17) "distribution licensee" means a licensee

authorised to operate and maintain a distribution

system for supplying electricity to the consumers in

his area of supply;

(23) "electricity" means electrical energy--

(a) generated, transmitted, supplied or traded for

any purpose; or

(b) used for any purpose except the transmission of

a message;

(28) "generating company" means any company or

body corporate or association or body of individuals,

whether incorporated or not, or artificial juridical

person, which owns or operates or maintains a

generating station;

(38) "licence" means a licence granted under section

14;

(39) "licensee" means a person who has been granted

a licence under section 14;

(50) "power system" means all aspects of generation,

transmission, distribution and supply of electricity and

includes one or more of the following, namely:--

(a) generating stations;

(b) transmission or main transmission lines;

(c) sub-stations;

(d) tie-lines;

(e) load despatch activities;

(f) mains or distribution mains;

37

(g) electric supply-lines;

(h) overhead lines;

(i) service lines;

(j) works;

(57) "regulations" means regulations made under this

Act;

(71) "trading" means purchase of electricity for resale

thereof and the expression "trade" shall be construed

accordingly

Section 3 provides for the National Electricity Policy and Plan

enabling the Central Government to prepare the National Electrcity Policy

and tariff policy, in consultation with the State Government and the

Authority for development of the power system based on optimal utilization

of resources such as coal, natural gas, nuclear substances or materials, hydro

and renewable sources of energy.

Part III of the Act provides for generation of electricity. Section 7

enables a generating company to establish, operate and maintain a

generating station without obtaining a licence if it complies with the

technical standards relating to connectivity with the grid referred to in clause

(b) of Section 73.

38

Section 8, however, provides that a generating company intending to

set up a hydro-generating station shall prepare and submit to the Authority

for its concurrence, a scheme estimated to involve a capital expenditure

exceeding such sum, as may be fixed by the Central Government from time

to time by Notification.

Section 9 provides for captive generation. Section 10 lays down

duties of generating companies, sub-sections (1) and 2 whereof reads as

under :-

“10 - Duties of generating companies

(1) Subject to the provisions of this Act, the duties

of generating company shall be to establish,

operate and maintain generating stations, tie-lines,

sub-stations and dedicated transmission lines

connected therewith in accordance with the

provisions of this Act or the rules or regulations

made thereunder.

(2) A generating company may supply electricity

to any licensee in accordance with this Act and the

rules and regulations made thereunder and may,

subject to the regulations made under sub-section

(2) of section 42, supply electricity to any

consumer.”

The power to issue directions to the generating companies by the

Appropriate Government and appropriate Commissions are laid down in

sub-section (1) of Section 11 of the 2003 Act stating :-

39

“Section 11 - Directions to generating companies

(1) The Appropriate Government may specify that

a generating company shall, in extraordinary

circumstances operate and maintain any generating

station in accordance with the directions of that

Government.

Explanation:--For the purposes of this section,

the expression "extraordinary circumstances"

means circumstances arising out of threat to

security of the State, public order or a natural

calamity or such other circumstances arising in

the public interest.”

Part IV of the 2003 Act provides for licensing.

Section 12 prohibits any person to transmit electricity, or distribute

electricity; or undertake trading in electricity, unless authorized to do so by a

licence issued under Section 14 or exempt under Section 13 of the 2003 Act.

Section 14 provides for grant of licence by the Appropriate Commission to

any person – (a) to transmit electricity as a transmission licensee ; or (b) to

distribute electricity as a distribution licensee; or (c) to undertake trading in

electricity as an electricity trader in any area as may be specified in the

licence.

40

Section 15 of the 2003 Act provides for procedure for grant of licence.

Section 16 provides for conditions of licence. Section 15 mandates the

licensee not to do certain things. The provisions for amendment of licence is

contained in Section 18 thereof. Section 19 provides for revocation of

licence. Section 20 provides for sale of utilities of licensees. Section 21

provides for vesting of utility in purchaser.

Section 23, which is relevant for our purpose, reads as under :-

“23 - Directions to licensees

If the Appropriate Commission is of the opinion

that it is necessary or expedient so to do for

maintaining the efficient supply, securing the

equitable distribution of electricity and promoting

competition, it may, by order, provide for

regulating supply, distribution, consumption or use

thereof.”

Section 24 provides for suspension of distribution licence and sale of

utility.

Part V deals with transmission of electricity.

Section 60 provides for market domination. It reads :-

“The Appropriate Commission may issue such

directions as it considers appropriate to a licensee

or a generating company if such licensee or

generating company enters into any agreement or

41

abuses its dominant position or enters into a

combination which is likely to cause or causes an

adverse effect on competition in electricity

industry.”

Section 86 provides for functions of State Commission, clauses (a),

(b) and (f) of sub-section (1) whereof, read as under :-

“Section 86 - Functions of State Commission

(1) The State Commission shall discharge the

following functions, namely:--

(a) determine the tariff for generation, supply,

transmission and wheeling of electricity,

wholesale, bulk or retail, as the case may be,

within the State:

PROVIDED that where open access has

been permitted to a category of consumers

under section 42, the State Commission

shall determine only the wheeling charges

and surcharge thereon, if any, for the said

category of consumers;

(b) regulate electricity purchase and

procurement process of distribution licensees

including the price at which electricity shall be

procured from the generating companies or

licensees or from other sources through

agreements for purchase of power for

distribution and supply within the State;

.. … …

(f) adjudicate upon the disputes between the

licensees and generating companies and to refer

any dispute for arbitration;

42

Section 181 of 2003 Act empowers the State Commissions to make

regulations, consistent with the provisions of the Act and the rules generally

to carry out the provisions of the Act.

Pursuant to or in furtherance of the aforementioned regulations

making powers, the Commission has made regulations known as MERC

(Terms and Conditions of Tariff) Regulations, 2005.

Regulation 7 deals with determination of generation tariff.

Regulation 22 provides for Power procurement guidelines to the

following terms :

“22.1 A Distribution Licensee shall follow the

guidelines contained in this Part with respect to:

(a) Procurement of power under any arrangement

or agreement with a term or duration exceeding

one year (i.e. long-term power procurement); and

(b) Procurement of power under any arrangement

or agreement with a term or duration less than or

equal to one year (i.e. short-term power

procurement).”

Regulation 23 mandates the distribution of licenses to prepare long

term power procurement plan which should fulfill the requirements specified

thereunder.

43

We may now notice that Regulation 24 provides for approval of

power purchase agreement/arrangement.

PRELIMINARY OBSERVATIONS

Before adverting to the rival contentions of the parties we may

observe :

The Tribunal committed a factual error in so far as it failed to notice

that no long term PPA exists between TPC (G) and RInfra. It furthermore

was not correct in opining that the Commission had not considered the claim

of RInfra while approving the arrangements between TPC (G) and TPC (D),

despite the fact that REL (RInfra) not only filed objections to the application

for grant of approval of PPA filed by the parties herein, it also filed

independent application; took part in the deliberations and all its contentions

had been considered. On what basis the Tribunal opined that the decision of

the Commission is in violation of the principle of natural justice is beyond

anybody’s comprehension. It furthermore took into consideration an

irrelevant fact, namely that the Commission in determining the issue

between the parties should have regard to the fact that the consumers of

respective areas have been bearing the ‘depreciation’ and interest on loan

44

elements of the Fixed Cost of tariff. It furthermore without assigning any

reason dismissed the appeals being Nos. 159 of 2007 and 14 of 2008.

INTERPRETATION OF THE STATUTORY PROVISIONS

A statute, as is well known, must be construed having regard to

Parliamentary intent. For the said purpose it is open to a court not only to

take into consideration the history of the legislation including the mischief

sought to be remedied but also the objects and purpose it seeks to achieve.

The 1910 Act provided for licensing of all the operators who were

engaged not only in transmission and distribution of electricity but also

generation thereof. Indisputably ‘electricity’ comes within the purview of

the public utility service. It, in the modern context, is a necessary item for

the purpose of better living of the citizens. After India became independent

and with the advent of industrialization as also for other reasons, the benefit

of availing consumption of electrical energy not only remained with the

urban areas but also extended to rural areas. With growth in

industrialization as also trade and commerce in the country, its requirements

increased many fold. With a view to provide for effective control and

regulation of generation, distribution and supply of electrical energy each

45

State was separately required to set up Electricity Boards wherefor the

Parliament enacted 1948 Act. For all intent and purport the Boards

constituted under the 1948 Act were to exercise monopoly power. The 1910

Act also made provisions for purchase of electricity undertakings by the

State.

Section 3 of 1910 Act, as amended in 1959, and Sections 43-A and 44

of 1948 Act clearly go to show that the private generating companies were

brought under an extensive control as not only for extension of its existing

plants but also for setting up or acquiring new plants, the previous consent of

the concerned State and the Board became necessary.

The private generating companies, in terms of the provisions of the

statutes governing the field were, thus, subjected to an extensive control by

the States. As the years rolled by, the activities of the Boards grew by leaps

and bounds. The Boards, for all intent and purpose, acquired monopoly

status. In terms of Sections 46 and 49 of the 1948 Act, they were entitled to

fix grid tariff and to make provisions for earning reasonable profits.

It was, however, noticed that in the absence of any competition from

the private operators, the Boards were not in a position to provide for the

desired optional results. It was in the aforementioned premise and

46

particularly having regard to the liberalized economic policy of the Central

Government since 1991 necessities were felt for providing greater room for

the private generating companies. For the aforementioned purposes, the

Central Government as also the State Governments adopted liberalized

polices. They invited private operators to generate electrical energy not only

through conventional modes, namely, Hydro Electric Power and Thermal

Power but also generation of power by using other raw-materials, for

example gas, naptha etc.

The 1998 Act, as notice hereinbefore, did not envisage delicensing of

generating companies. It provided for approval by the Board therefor. It

provided for imposition of other conditions for generation of electricity.

The Parliament by making 2003 Act clearly acknowledged the

necessity of providing a greater room for generation of electrical energy so

as to enable the country to meet its requirements. It is only in that view of

the matter, the liberalization policy of the State provided for de-licensing of

the generating companies.

In terms of the said provision, the activities of the erstwhile licensees

of power generation on the one hand and those of transmission and

distribution in electricity on the other were separated. The concept of

47

trading was brought thereunder for the first time. Trading activities are

permitted subject to grant of licenses. Distribution of electricity was defined

as licensed activity in terms whereof a holder of a license can supply power

to a person for his own use. A licensee for the activity of transmission could

own the wires/transmission lines constituting the part of their grid but it

could not engage itself in the activity of buying or selling the electrical

energy.

The core question which, therefore, arises for consideration is as to

whether despite the Parliamentary intent of giving a go-bye to its licensing

policy to generating companies, whether through imposing stringent

regulatory measures the same purpose should be allowed to be achieved?

The Act is a consolidating statute. It brings within its purview

generation, transmission, distribution, trade and use of electricity. Whereas

generation of electricity has been brought outside the purview of the

licensing regime, the transmission, distribution and trading are subject to

grant of licence are kept within the regulatory regime.

The statute provides for measures to be taken which would be

conducive to development of electricity industry. Measures are also

required to be taken for promoting competition which would also mean the

48

development of electricity industry. It, indisputably, provides for measures

relating to the protection of interest of consumers and supply of electricity to

all areas. The generating companies, however, despite de-licensing, do not

enjoy the monopoly status. They are subject to rationalization of electricity

tariff. The preamble envisages ensuring transparent policies, policies

regarding subsidies, promotion of efficient and environmentally benign

policies, constitution of Central Electricity Authority Regulatory

Commissions and establishment of Appellate Tribunal and for matters

connected therewith or incidental thereto.

Electricity is not an essential commodity within the meaning of the

provisions of the Essential Commodities Act, 1955 or any other statute. It

is, however, in short supply. As the number of consumers as also the nature

of consumption have increased many fold, the necessity of more and more

generation of electrical energy must be given due importance.

The preamble of the 2003 Act, although speaks of development of

electricity industry and promotion of competition, it does not speak of

equitable distribution of electrical energy. The statutes governing essential

and other commodities in respect whereof the State intends to exercise

complete control, provide for equitable distribution thereof amongst the

consumers.

49

For the purpose of deciphering the object and purport of the Act, it is

well known, the Court can look to the statement of objects and reasons

thereof. One of the principal purposes which had been taken note of for

enactment of 2003 Act by the Parliament is the poor performance of the

State Electricity Boards. The Government intended to have an independent

body for determining the tariff which was required to be carried on in a

professional and independent manner. It was felt that cross-subsidies have

reached to unsustainable levels. The enactment provides for establishment

of the Electricity Regulatory Commissions.

Encouraging private sector participation, generation, transmission and

the distribution of electricity became the statutory policy. The Parliament

felt the need of harmonizing and rationalizing the provisions of the Act. De-

licensing of generation as also grant of free permission of captive generation

is one of the main features of the 2003 Act. It is clearly provided that only

hydro-generating projects would need the approval of the State Commission

and the Central Electricity Regulatory Authority. It recognized the need of

prohibiting transmission licensees. It also for the first time provided for

open access in transmission from the outset. It even provides where the

distribution licensee proposes to undertake distribution of electricity for a

50

specified area within the area of supply through another person, that person

shall not be required to obtain separate licence.

In terms of Section 7 of the 2003 Act, all persons are permitted to

establish, operate and maintain a generating station. It can, in terms of

Section 62(1)(a) of the 2003 Act, supply electricity to any licensee i.e.

distribution licensee or trading licensee. The 2003 Act permits the

generating company to supply the electricity directly to a trader or a

consumer. In terms of Section 42(2) of the 2003 Act even for the said

purpose no tariff is required to be determined.

The primary object, therefore, was to free the generating companies

from the shackles of licensing regime. The 2003 Act encourages free

generation and more and more competition amongst the generating

companies and the other licensees so as to achieve customer satisfaction and

equitable distribution of electricity.

The generation company, thus, exercises freedom in respect of choice

of site and investment of the generation unit; choice of counter-party buyer;

freedom from tariff regulation when the generating company supplies to a

trader or directly to the consumer.

51

If de-licensing of the generation is the prime object of the Act, the

courts while interpreting the provisions of the statute must guard itself from

doing so in such a manner which would defeat the purpose thereof. It must

bear in mind that licensing provisions are not brought back through the side

door of Regulations.

DIRECTION TO GENERATING COMPANIES

This brings us to the interpretation of Section 11 of the 2003 Act. In

terms of 1910 Act the State Government was the licensing authority. It

alone, therefore, in the said capacity was entitled to issue directions. Sub-

section (1) of Section 11 of 2003 Act empowers the Appropriate

Government to issue directions but such direction can be issued only in

extraordinary circumstances as stated in the explanation appended thereto

i.e. arising out of threat to security of the State, public order or a natural

calamity or such other circumstances arising in the public interest.

Interpretation clause contained in Section 2 of the Act prefixes the

words “unless the context otherwise requires”. The word “supply” has

separately been used even for generation and distribution. Thus, although a

broad meaning may be assigned to the said term but the same must be held

to be ‘subject to the context’. The word “supply” used in Section 23 of 2003

52

Act for bringing in efficient supply would mean regulate and

consequentially licensing in respect of the generating company.

For the aforementioned purpose it cannot be given a general or

popular meaning denoting supplier and receiver. Once it is held that by

reason thereof the Parliament aimed at ensuring the supply, the purported

object it sought to achieve by enacting Section 7 would lose its purpose. It,

however, does not mean that Section 23 itself becomes unworkable as it

would not be possible to secure equitable distribution and supply. The

agreement of distribution (PPA) being subject to approval, indisputably the

Commission would have the public interest in mind. It has power to

approve a MOU which subserves the public interest. It, while granting such

approval may also take into consideration the question as to whether the

terms to be agreed are fair and just.

SECTION 23 – DIRECTION BY THE COMMISSION

Could a generating company, despite Section 11 be subjected to any

direction by the Commission in terms of Section 23 of the 2003 Act?

Whether chapter headings and marginal notes should be taken into

consideration for the purpose of interpretation of the main provision are the

questions?

53

Chapter headings and the marginal note are parts of the statute. They

have also been enacted by the Parliament. There cannot, thus, be any doubt

that it can be used in aid of the construction. It is, however, well settled that

if the wordings of the statutory provision are clear and unambiguous,

construction of the statute with the aid of ‘chapter heading’ and ‘marginal

note’ may not arise. It may be that heading and marginal note, however, are

of a very limited use in interpretation because of its necessarily brief and

inaccurate nature. They are, however, not irrelevant. They certainly cannot

be taken into consideration if they differ from the material they describe.

We may notice some authorities on the subject at the outset.

In Bennion on Statutory Interpretation, Fifth edition, Section 255, it is

stated : “where general words are preceded by a heading indicating a

narrower scope it is legitimate to treat the general words as cut down by the

heading.”,

Section 256 of the said treatise deals with “sidenote, heading or title”,

wherein it is stated :-

“Use in interpretation – Like anything else in what

Parliament puts out as its Acts, a sidenote or

heading is part of the Act, despite dicta to the

contrary. It may therefore be used by the

54

interpreter. ‘No judge can be expected to treat

something which is before his eyes as though it

were not there. However, the sidenote or section

heading is of very limited use in interpretation

because of its necessarily brief and therefore

possibly inaccurate nature.”

It was commented :-

“If the sidenote contradicts the text this puts the

interpreter on inquiry; but the answer may be that

the drafter chose an inadequate signpost, or

neglected to alter it to match an amendment made

to the clause during the passage of the Bill. Such

facts are outside the knowledge of the interpreter,

who must therefore adopt a rule not depending on

them.

… ….. …..

Modern judges believe it proper to consider

sidenotes or headings to sections, and gather what

guidance they can from them. Thus Vinelott J said

that the sidenote to the Income and Corporation

Taxes Act, 1970 s 488 (repealed) was a

permissible and useful guide that threw a light on

the mischief at which the section was aimed.

Upjohn LJ gave a precisely accurate indication of

the role of the sidenote when he said :

‘While the marginal note to a section cannot

control the language used in the section , it

is at least permissible to approach a

consideration of its general purpose and the

mischief at which it is aimed with the note

in mind.’

The italicised words accurately show the

relationship of this component to the informed

interpretation rule. Earlier inconsistent dicta, a

55

selection of which are now considered, must be

treated as erroneous.”

In Interpretation of Statutes, Fourth Edition, by Vepa P. Sarathi at

page 347 it is stated :-

‘The heading of a chapter may be referred to in

order to determine the sense of any doubtful

expression in a section ranged under it. But it

cannot control unambiguous expressions.

It is true that a heading cannot control the

interpretation of a clause if its meaning is

otherwise plain and unambiguous, but it can

certainly be referred to as indicating the general

drift of the clause and affording a key to a better

understanding of its meaning.”

Similarly in Principles of Statutory Interpretation by Justice G.P.

Singh, upon noticing the conflicting opinion, the learned Author states:-

“The view is now settled that the Headings or

Titles prefixed to section or group of sections can

be referred to in construing an Act of the

Legislature.”

Chapter heading, therefore, is a permitted tool of interpretation. It is

considered to be a preamble of that section to which it pertains. It may be

taken recourse to where an ambiguity exists. However, where there does not

56

exist any ambiguity, it cannot be resorted to. Chapter heading and marginal

note, however, can be resorted to for the purpose of resolving the doubts.

It furthermore appears that there is a drift from the old value in recent

times.

We may notice that the English decisions whereupon reliance had

been placed by this Court in various judgments and in particular Chandler v.

DPP, [ (1962) All ER 142 ], str considered to be a no longer a good law in

the country of origin, as stated in Bennion on Statutory Interpretation Fifth

Edition at page 748 :-

“ Superseded dicta Phillimore LJ referred to a

‘general rule of law’ to the effect that marginal

notes must be disregarded ‘upon the principle that

those notes are inserted not by Parliament nor

under the authority of Parliament, but by

irresponsible persons’. In fact, with occasional

triffling exceptions, the marginal notes in an Act

are not inserted by parliamentary clerks - or even

drafters – but are contained either in the Bill as

introduced or in new clauses added by amendment.

Furthermore, the clerks are not ‘irresponsible

persons’, but are subject to the authority of

Parliament. Avory J. said that ‘marginal notes

form no part of a statute’. He added : ‘They are

not voted on or passed by Parliament, but are

inserted after the Bill has become law’. This is not

the case however. The entire Act is passed by

Parliament and is entered, or deemed to be entered,

in the Parliament Roll with all non-amendable

components included. These components mostly

57

remain unchanged throughout the passage of the

Bill. They are certainly not inserted after the Bill

has become law. Willes J. after asserting that the

marginal notes and other ‘appendages’ are not part

of an Act, said of any Act, passed after the practice

of actually engrossing Acts on the Parliament Roll

ceased in 1849: ‘The Act, when passed, must be

looked at just as if it were still entered upon a roll,

which it may be again if Parliament should be

pleased so to order; in which case it would be

without these appendages…’”

It is, however, evident from the decision of this Court in Indian

Aluminium Company v. Kerala State Electricity Board, [ AIR 1975 SC

1967 ], that the modern trend is to take into consideration the marginal note.

It could be used, as has been held, in R.S. Joshi, Sales Tax Officer, Gujarat

and Ors. v. Ajit Mills Limited and Anr., [ (1977) 4 SCC 98 ]. Relevance of

marginal note was also taken note of in Ramesh Chand and Ors. v. State of

U.P. and Ors., [ (1979) 4 SCC 776 ].

In Bombay Dyeing and Mfg. Co. Ltd. v. Bombay Environmental

Action Group and Ors., [ (2006) 3 SCC 434 ], marginal note has been taken

into consideration as an intrinsic part of the Section. In Deewan Singh and

Ors. v. Rajendra Pd. Ardevi and Ors., [ 2007 (1) SCALE 32 ] it has been

held that the marginal note may be taken into consideration for the purpose

of proper construction of the provision although there is no ambiguity.

58

Sarabjit Rick Singh v. Union of India (UOI), [ (2008) 2 SCC 417 ] follows

Deewan Singh (supra).

SUPPLY – CONTEXTUAL MEANING

It was submitted by the respondents that in any event the word

‘supply’ as used in Section 23 should be given the same meaning as is given

to it in Section 2(70) of the Act i.e. the sale of electricity to a licensee or

consumer. Accordingly by its very nature, supply would have a supplier and

a receiver and any direction which is aimed at ensuring or regulating supply

by its very nature would have to be directed to both the supplier and the

receiver.

However, when the question arises as to the meaning of a certain

provision in a statute, it is not only legitimate but proper to read that

provision in its context.

The legal principle is that all statutory definitions have to be read

subject to the qualification variously expressed in the definition clause

which created them and it may be that even where the definition is

exhaustive inasmuch as the word defined is said to mean a certain thing, it is

possible for the word to have some what different meaning in different

sections of the Act depending upon the subject or context. That is why all

59

definitions in statutes generally begin with the qualifying words ‘unless

there is anything repugnant to the subject or context’. [See Whirlpool

Crporation v. Registrar of Trade Marks, Mumbai and others, { (1998) 8

SCC 1 ; Garhwal Mandal Vikas Nigam Ltd. v. Krishna Travel Agency,{

(2008) 6 SCC 732 } and National Insurance Co. Ltd. v. Deepa Devi,

[ (2008) 1 SCC 414 } ].

Accordingly the word ‘supply’ cotnained in Section 23 refer to

‘supply to consumers only’ in the context of Section 23 and not to supply to

licensees. On the other hand, in Section 86(1)(a) ‘supply’ refers to both

consumers and licensees. In Section 10(2) the word ‘supply’ is used in two

parts of the said Section to mean two different things. In the first part it

means ‘supply to a licensee only’ and in the second part ‘supply to a

consumer only’. Further in first proviso to Section 14, the word ‘supply’ has

been used specifically to mean ‘distribution of electricity’. In Section 62(2)

the word ‘supply’ has been used to refer to ‘supply of electricity by a trader’.

To assign the same meaning to the word “supply” in Section 23 of the

Act, as is assigned in the interpretation section, it is, in our opinion,

necessary to take recourse to the doctrine of harmonious construction and

read the statute as a whole. Interpretation of Section indisputably must be

premised on the scheme of the statute. For the purpose of construction of a

60

statute and in particular for ascertaining the purpose thereof, the entire Act

has to be read as a whole and then chapter by chapter, section by section and

word by word.

{See Reserve Bank of India, v. Peerless General Finance and

Investment Co. Ltd, [ (1987) 1 SCC 424 ] ; Peerless General Finance and

Investment Co. Ltd. v. Reserve Bank of India, [ (1992) 2 SCC 343 ] and

National Insurance Co. Ltd. v. Swaran Singh, [ (2004) 3 SCC 297 ]. }

Thus, in a case where interpretation of a Section vis-à-vis the scheme

of the Act, the purport and object of the legislation, particularly having

regard o the mischief it seeks to remedy; the chapter heading as also the

marginal note, in our opinion, are relevant.

PURPOSIVE CONSTRUCTION

Legislation has an aim, it seeks to obviate some mischief, to supply an

inadequacy, to effect a change of policy, to formulate a plan of government.

That aim, that policy is not drawn like nitrogen, out of air ; it is evidenced in

the language of the statute, as read in the light of other external

manifestations of purpose. [See Justice Frankfurtir, Some Reflextions on the

reading of Statutes, 47 Columbia LR 527, at page 538 (1947) ; Union of

61

India v. Ranbaxy Laboratories Ltd. and others ; { (2008) 7 SACC 502 }and

D. Purushotam Reddy and another vs. K. Sateesh, {(2008) 11 SCALE 73}].

ANALYSIS

In this case the relevance of chapter heading is more for the purpose

of arriving at a conclusion as to whether the arrangement and scheme of the

statute is such it can be said be relatable to different types of licensees on the

one hand and a generating company which does not require a licence on the

other. If by reason of a provision of a statute the generating companies are

excluded from the licensing provisions, one of the principal tool of

interpretation is that the mischief which was sought to be remedied may not

be brought back by a side door. It has to be borne in mind that if the licence

raj is brought back through the side door or regulations seeking to achieve

the same purpose which the Parliament intended to avoid, there would be a

possibility of mis-interpretation and mis-application of statute.

For the said purpose even the history of the Act may be noticed. It is

from this point of view that the ambiguity, if any, must be found out.

If the marginal note in this case is given effect to it would come

within the scheme. If it is not given effect to and plain meaning is resorted

62

to it will produce anomaly with the purpose and object of the Act. Chapter

IV in which Section 23 occurs deals with a particular category of licensees.

Almost all the sections preceding Section 23 as also Section 24 refer to the

licensees and the licensees alone. None of the sections in the said chapter

refers to generating companies.

Furthermore in the scheme of the Act wherever regulation of

generating companies is necessary the same has been provided for. Section

11 and Section 60 provide for adequate indication in this behalf. They deal

with extra ordinary situations.

Transmission of electrical energy does not come within the purview of

section 23. Trading therein also does not per say come within the purview

thereof.

It has to be construed harmoniously with other powers. Had the

power of the Commission to issue direction in regard to supply of electrical

energy was so pervasive, Section 23 could have been appropriately worded..

It could have been placed in an appropriate chapter and not in the chapter

dealing with licensing. There was also no necessity to bring out

transmission of electricity from the purview thereof as the same would also

come within the purview of supply of electricity. If transmission of

63

electricity can be kept outside the purview of direction by the Commission,

there is no reason why generation thereof would not be.

We, therefore, of the opinion that Section 23 of the 2003 Act does not

contemplate issuance of any direction by the Commission.

SECTION 86 – FUNCTION OF THE COMMISSION

Section 86 provides for the functions of the Sate Commission, clause

(a) of sub-section (1) whereof empowers it to determine the tariff for

generation, supply, transmission and wheeling of electricity. Clause (b)

empowers it to regulate electricity purchase and procurement process of

distribution licensees. Inevitably it speaks of PPA. PPA may provide for

short term plan, a mid term plan or a long term plan. Depending upon the

tenure of the plan, the requirement of the distribution licensee vis-à-vis its

consumers ; the nature of supply and all other relevant considerations,

approval thereof can be granted or refused.

While exercising the said function necessarily the provisions of

Section 23 may not be brought within its purview. While even exercising

the said power the State Commission must be aware of the limitations thereo

as also the purport and object of the 2003 Act. It has to take into

consideration that PPA will have to be dealt with only in the manner

64

provided therefor. The scheme of the Act, namely the generation of

electricity is outside the licensing purview and subject to fulfillment of the

conditions laid down under Section 42 of the Act a generating company may

also supply directly to consumer wherefor no licence would be required,

must be given due consideration. The said provision has to be read with

Regulation 24. In regard to the grant of approval of PPA the procedures laid

down in Regulation 24 are required to be followed. While exercising its

power of ‘Regulation’ in relation to purchase of electricity and procurement

process of distribution, it is not permissible for the Commission to direct

allocation of electricity to different licensees keeping in view their own

need. Section 86(1)(b) read with Section 23 if interpreted differently would

empower the Commission to issue direction to the generating company to

supply electricity to a licensee who had not entered into any PPA with it.

We do not think that such a contingency was contemplated by the

Parliament. A generating company, if the liberalization and privatization

policy is to be given effect to, must be held to be free to enter into an

agreement and in particular long term agreement with the distribution

agency, terms and conditions of such an agreement, however, are not

unregulated. Such an agreement is subject to grant of approval by the

Commission. The Commission has a duty to check if the allocation of

power is reasonable. If the terms and conditions relating to quantity, price,

65

mode of supply the need of the distributing agency vis-à-vis the consumer,

keeping in view its long term need are not found to be reasonable, approval

may not be granted. A generating company has to make a huge investment

and assurances given to it that subject to the provisions of the Act he would

be free to generate electricity and supply the same to those who intend to

enter into an agreement with it. Only in terms of the said statutory policy,

he makes huge investment. If all his activities are subject to regulatory

regime, he may not be interested in making investment. The business in

regard to allocation of electricity at the hands of the generating company

was the subject matter of the licensing regime. While interpreting the statute

it must be borne in mind that such a mechanism should not come back.

That, however, would not mean that the generating company is

absolutely free from all regulations. Such regulations are permissible under

the 2003 Act ; , one of them being fair dealing with the distributor. Thus,

other types of regulations should not be brought in which were not

contemplated under the statutory scheme. If he is exercising his dominant

position, Section 60 would come into play. It is only in a situation where a

generator may abuse or misuse his position the Commission would be

entitled to issue a direction. The regulatory regime of the Commission, thus,

can be enforced against a generating company if the condition precedent

therefor becomes applicable.

66

INTERRETATION OF SECTION 86

Section 86(1)(b) provides for regulation of electricity purchase and

procurement process of distribution licensees. In respect of generation its

function is to determine, the tariff for generation as also in relation to

supply; transmission and wheeling of electricity. Clause (b) of sub-section

(1) of Section 86 provides to regulate electricity purchase and procurement

process of distribution licensees including the price at which the electricity

shall be procured from the generating companies or licenses or from other

sources through agreements. As a part of the regulation it can also

adjudicate upon disputes between the licensees and generating companies in

regard to the implementation, application or interpretation of the provisions

of the said agreement.

There are some provisions which provide for regulation etc. of

generation and/or generating companies, namely –

(i)Section 10(3)

(ii)Section 11(2)

(iii)Section 23

(iv)Section 33(2)

(v)Section 55(2) and (3)

67

(vi)Section 60

(vii)Section 62(1), (2) and (95)

(viii)Section 81(1)(a), (b), (e), (f) and sub-section (2)

(ix)Section 128(1), (6), (7) and (8)

(x)Section 129

(xi)Section 181

The Parliament thought it necessary to provide for specific provisions

for the purpose of regulating the functions of the generating companies,

those provisions are special provisions vis-à-vis the other general provisions

which take within its abridge the function of the distributor, transmitter and

trader.

In U.P. Power Corporation Ltd. v. NTPC and others, [2009 (3)

SCALE 620] this Court opined :

“There cannot be any doubt whatsoever that the

word ‘regulation’ in some quarters is considered to

the unruly horse.”

[See also Bank of New South Wales v. Commonwealth {(1948) 76

CLR 1} and Prasar Bharti and others v. Amarjeet Singh and others, { 2007

(2) SCALE 486 } ].

68

We may notice a comparative chart of the provisions of Section

22(1)(c) of 1998 Act and Section 86(1)(b) of the 2003 Act.

Section 22(1)(c) of the 1998 Act Section 86(1)(b) of the 2003 Act

to regulate power purchase and

procurement process of the

transmission utilities and

distribution utilities including the

price at which the power shall be

procured from the generating

companies, generating stations or

from other sources for

transmission, sale, distribution

and supply in the State;

regulate electricity purchase and

procurement process of distribution

licensees including the price at

which electricity shall be procured

from the generating companies or

licensees or from other sources

through agreements for purchase of

power for distribution and supply

within the State;

A critical comparison of the said provisions would show that the

agreements for purchase of power referred to therein is directly linked with

the procurement process of distribution license either from the generating

companies or licensees or from other sources. Regulation of transmission

has been taken out of the regulatory provision. The words ‘through

agreements for purchase of power’ inserted in Section 86(1)(b) of the 2003

Act bring about a significance distinction. It is neither irrelevant nor

immaterial as contended by Dr. Singhvi.

A PPA may be a long term one or a short term one. Regulations have

been made by the Commission by making MERC (Terms and Conditions of

Tariff) Regulations, 2005.

69

Short term power procurement refers to an agreement for procurement

of power for a period of less than one year. Regulation 23.1 requires the

distribution licensee to prepare a five year plan inter alia upon taking into

consideration the sources for procurement thereof. Regulation 24.1

mandates obtaining of prior approval of the Commission therefor. Approval

by Commission is granted upon examining the process of procurement

having regard to the factors specified in Regulation 24.2. It is in the

aforementioned context grant of approval of the PPA by and between TPC

(G) on the one hand and BEST and TPC (D), on the other hand, necessitated.

The proposal of TPC (G) that RInfra should enter with it a long term

agreement assumes significance.

RE: HARDSHIP OF RIinfra

For the purpose of interpretation and/or application of a statute, this

Court cannot base its decision on any hypothesis. Construction of a statute,

save and except some exceptional cases, cannot be premised on the hardship

of a party which may be suffered by one of the licensees. Enabling

provisions are made for entering into a free contract.

A company incorporated under the Companies Act being not a citizen

of India does not have any fundamental right to carry on business in terms of

70

Article 19(1)(g) of the Constitution of India; its shareholders and directors

have. Even otherwise in a free market economy right to enter into contract

by and between two private parties are not to be discouraged in absence of

any statute or statutory regulation. The intendment of Parliament in making

statute is clear and unambiguous. Requirements of a licensee and/or sheer

number of its consumers, in our opinion, would be wholly irrelevant for the

purpose of the construction of a statute.

RELEVANCE OF SECTION 60

It is, in the facts and circumstances of this case, not necessary for us to

consider an extraordinary situation where the Commission may exercise its

jurisdiction both under Section 86(1)(b) and Section 60 simultaneously. We

are also not concerned with any extra ordinary situation. Assuming that

such a contingency may take place and having regard to Sections 23 & 60

of the Act while issuing direction to the licensee company the right of a

generating company may also be affected., but we are not concerned with

such a situation. The Commission which is an expert body has not found

that any such case has been made out for exercise of its jurisdiction in that

behalf.

71

The 2003 Act even permits the generating company to supply

electricity to a consumer directly. For the said purpose what is necessary is

to comply with the provisions of the Act , Rules and the Regulations.

Section 14 of the Act categorically provides for grant of licnece to any

person who is transmitting electricity or distributing supply or undertaking

trading therein, indisputably, however, the generator of an electrical energy,

although is not subject to the grant of licence but while supplying electrical

energy to a distributing agency, in turn would be subject to approval and

directions of the Commission.

CONCLUSION

1)Activities of a generating company are beyond the purview of

the licensing provisions.

2)The Parliament therefor did not think it necessary to provide for

any regulation or issuance of directions except that which have

expressly been stated in the Act.

3)Section 21 occurs in the chapter of “licensing” under which the

generating companies would not be governed.

4)As almost all the sections preceding Section 23 as also Section

24 talk about licensee and licensee alone, the word “supply” if

72

given its statutorily defined meaning as contained in Section

2(70) of the Act would lead to an anomalous situation as by

reason thereof supply of electrical energy by the generating

company to the consumers directly in terms of Section 12(2) of

the Act as also by the transmission companies to the consumers

would also come within its purview.

5)In a case of this nature the principle of exclusion of the

definition of Section by resorting to “unless the context

otherwise requires” should be resorted to.

6)Section 86(1)(a) of the 2003 Act clearly shows the para meters

of supply for the purpose of Regulation, viz. supply of

electricity by the distribution company to the consumer.

7)If regulatory clause is sought to be applied in relation to

allocation of power, the same would defeat the de-licensing

provisions. Generating companies have the freedom to enter

into contract and in particular long term contracts with a

distribution company subject to the regulatory provisions

contained in the 2003 Act. .

8)PPA for a long term is essential for increasing and decreasing

the capacity of generation of electricity by the generating

73

company, which purpose by the 2003 Act must be allowed to

be achieved.

9)Duration of the contract in regard to supply of electricity by and

between TPC (G) and RInfra prior to coming into force of the

contract is of no consequence, particularly when no written

long term or short term contract had been entered into by and

between them.

10)Fairness or otherwise of the supply of electricity to different

distribution companies being outside the jurisdiction of the

Commission, the same by itself cannot be a ground for bringing

back the licence raj, which is not contemplated by the Act.

11)For true and correct construction of the Act, the principle of

harmonious construction is required to be resorted to.

12)Recourse to the principle of purposive construction does not

militate against the conclusion reached by us and as indicated

hereinbefore in fact in terms of the said doctrine the purpose

and object of the Parliament must prevail over a narrow and/or

literal interpretation, which would defeat the purpose and object

of the Act.

74

13)Section 86(1)(b) of the 2003 Act clearly shows that the

generating company indirectly comes within the purview of

regulatory jurisdiction as and when directions are issued to the

distributing companies by the appropriate Commission but the

same would not mean that while exercising the said

jurisdiction, the Commission will bring within its umbrage the

generating company also for the purpose of issuance separate

direction.

For the aforementioned reasons, the impugned judgment of the

Tribunal cannot be sustained. It is set aside accordingly. The appeals are

allowed with costs. Counsel’s fee Rs. 1,00,000/- (Rupees one lakh) in each

appeal.

……….……………………J.

[ S.B. Sinha ]

……………..………………J.

[Dr. Mukundakam Sharma ]

New Delhi

May 06, 2009

75

Reference cases

Description

Legal Notes

Add a Note....