Heard Ms. Shristi Sinha, Advocate and Mr. Vikash Kumar,Advocate appearing on behalf of the appellants.
1
IN THE HIGH COURT OF JHARKHAND AT RANCHI
Arbitration Appeal No. 12 of 2016
1. The State of Jharkhand, Minor Irrigation Division at present through
Secretary, Water Resources Department, having its office at Nepal
House, P.O. and P.S. Doranda, District Ranchi
2. The Chief Engineer, Jamshedpur, Swarnrekha Multipurpose Project
Icha Galudih Complex, P.O. and P.S. Adityapur, Jamshedpur at
present Chief Engineer, Swarnrekha Multipurpose Project, Chandil
Complex, Chandil, P.O. and P.S. Adityapur, Jamshedpur
3. The Executive Engineer, Minor Distribution Division No. 9, Ghatshila
Camp, Galudih, District East Singhbhum at present Executive
Engineer, Minor Distribution Division No. 12, Mango, Jamshedpur
4. The Superintending Engineer, Kharkhai Dam Circle Icha Chaliyama,
District East Singhbhum at present Superintending Engineer, Chandil
Dam Circle, Chandil, District Saraikela-Kharsawan
… … … Plaintiff/Applicants/Appellants
Versus
M/s. Shahi Construction, having its local office at Devi Mandap Road,
Hesal, P.O. and P.S. Sukhdeonagar, District Ranchi and site office at
Kumharpara, New Baradwari, Jamshedpur at present C/o Shri Sheo
Narayan Prasad (Kabijee) Vir Kunwar Singh Colony, Airport Road,
Hinoo, Ranchi-834002 … … Defendant/Respondent
---
CORAM: HON'BLE MRS. JUSTICE ANUBHA RAWAT CHOUDHARY
---
For the Appellants : Ms. Shristi Sinha, Advocate
Mr. Vikash Kumar, Advocate
For the Respondents : Mr. Deepak Sinha, Advocate
---
14/18.01.2019
1. Heard Ms. Shristi Sinha, Advocate and Mr. Vikash Kumar,
Advocate appearing on behalf of the appellants.
2. Heard Mr. Deepak Sinha, Advocate appearing on behalf of the
respondent assisted by Mr. Tarun Kumar, Advocate.
3. Instant Arbitration Appeal has been filed for setting aside the
judgment dated 15.06.2016, passed in Misc. Case No. 2/2012 by
learned Civil Judge, Sr. Division-I, Ghatshila, East Singhbhum,
whereby award dated 24.12.2011, passed by the learned Arbitrator
has been affirmed and the petition under Section 34 of the
Arbitration and Conciliation Act, 1996 filed by the appellants has
been dismissed.
Arguments of the appellants
4. The brief facts and submissions by the counsel appearing on behalf
2
of the appellants are as under:-
a. In the year 2004, the appellants had come up with two Notice
Inviting Tenders bearing No. 2/2003-04 and No. 3/2003-04
for total value of Rs. 30,48,228.85 and Rs. 78,06,649.80
respectively. The period of completion of work was 12
months and 6 months respectively from the date of
agreement. Counsel submits that the work related to earth
work, lining and construction of structure in Minor
Distribution Division No. 2, Ghatsila Camp, Galudih under
Irrigation Department, State of Jharkhand. The respondent
herein issued work order dated 29.01.2004 and 25.03.2004
respectively against which the respondent deposited security
amount and entered into agreement dated 10.02.2004 and
04.08.2004. The specific case of the appellants is that both the
agreements were executed at the office of Minor Distribution
Division No. 2, Ghatsila Camp, Galudih , within the
jurisdiction of the learned court and the agreement was
executed on behalf of the State by the then Executive
Engineer, Minor Distribution Division No. 9, Ghatsila Camp,
Galudih, who was authorize to Act on behalf of the State of
Jharkhand.
b. He submits that in the notice inviting tender it was indicated
that clause-23 of the F 2 agreement was excluded and all
other terms contained therein would remain as it is. He
further submits that in view of such clear cut exclusion of
clause-23 of the F 2 agreement in the notice inviting tender
itself, there was no arbitration clause in the agreement and
accordingly the matter could not have been referred to the
Arbitrator.
c. He further submits that the respondent herein had filed an
application being Arbitration Application No. 6/2010
annexing the copy of the F 2 agreement, where clause-23 was
not struck off and the matter was referred to the Arbitrator
vide order dated 10.12.2010 passed in Arbitration Case No.
6/2010. He submits that specific condition/terms of the
notice inviting tender was not brought to the notice of this
3
Hon’ble Court at the time of hearing of Arbitration
Application No. 6/2010 and the lawyer who represented the
appellant, without instruction of the concerned department,
consented for appointment of the Arbitrator and the matter
was referred to Arbitrator vide order dated 10.12.2010 passed
in Arbitration Application No. 6/2010.
d. He further submits that on receipt of notice from the learned
sole Arbitrator, Sri Sanat Kumar Chattopadhyay, former
Judge, Jharkhand High Court, the appellants along with
officers of the Division appeared before the learned
Arbitrator and prayed for time for want of approval.
e. He further submits that since the respondent without
disclosing the terms of notice inviting tender obtained order
dated 10.12.2010 passed in Arbitration Application No.
6/2010, the appellants herein filed Special Leave Petition
against the aforesaid order dated 10.12.2010 which was S.L.P.
No. 16942/2011 and later on the said S.L.P. was withdrawn
with a view to move before the Hon’ble High Court for
review of the order dated 10.12.2010.
f. He also submits that aforesaid order of the Special Leave
Petition was communicated to the learned Arbitrator vide
letter dated 23.12.2011 with a prayer to defer and adjourn the
pronouncement of award for at least two months, but in spite
of service of said letter, the learned Arbitrator passed the
award on 24.12.2011.
g. In such circumstances, the appellants challenged the award
dated 24.12.2011 under Section 34 of the Arbitration and
Conciliation Act, 1996, as after passing of the award, there
was no question of filing any review application in
Arbitration Application Case No. 6/2010.
h. He submits that award was challenged before the learned
court below on the following grounds:-
(i) For that the appointment of sole learned Arbitrator by the
Hon’ble Chief Justice is beyond the purview of the
Agreement, as after detection of exclusion of Clause 23 of the
Agreement, the Opp. Party had no occasion to move before
the Hon’ble Court for appointment of Arbitrator and thus on
4
the basis of order dated 10.02.2010 all the arbitration
proceeding adopted by the learned Arbitrator is vitiated and
not sustainable.
(ii) For that the learned Arbitrator at least should have given
opportunity to the applicants to move before the Hon’ble
High Court for reviewing the order dated 10.02.2010.
(iii) For that the findings of the learned Arbitrator to the
effect that applicant/authorities have committed breach of
contract is highly erroneous and contrary to materials
available.
(iv) For that the findings of the learned Arbitrator below to
the effect that concerned opp. party committed gross error
and illegality in signing the agreements before acquisition of
the land for which claimant is entitled for compensation and
order of termination is also illegal and arbitrary are contrary
to fact.
(v) For that the findings of the learned Arbitrator that Suptd.
Engineer ought to have appointed arbitrator for redressal of
the grievances is beyond the purview of terms of Agreement
as NIT is the part of Agreement, which clearly speaks of
exclusion of arbitration Clause 23 of the agreement.
(vi) For that while the learned Arbitrator opined and
observed that claim of the Claimant with regard to claim No.
1 was not genuine and is doubtful even though a sum of Rs.
2,00,000/- awarded being advanced made by the claimant to
works using of J.C.B. Machine, Dumper etc.
(vii) For that the award of claim No. 2 allowed by the learned
sole Arbitrator amounting to Rs. 3,00,000/- based on mere
possibility and presumption of the learned Arbitrator which
would be evident from the observations and findings of the
learned Arbitrator that the Opp. party is unable to give
reasonable explanation for this claim.
(viii) For that the award of Rs. 1,40,000/- of claim No. 3
allowed by the learned Arbitrator is baseless and unfounded
which is based on mere opinion which would be crystal clear
from the opinion of the learned Arbitrator that claim in this
regard is also vague to be considered it seems to be
deliberately and intentionally manufactured.
5
(ix) For that the award of Rs. 5,00,000/- of claim No. 4 on
account of loss or profit is beyond the terms of agreement.
(x) For that since there was no arbitration clause in the
Agreements and thus the applicants should not have been
saddled with the legal expenses and remuneration and
Secretarial Charges as allowed in Claim No. 7 by the learned
Arbitrator.
(xi) For that all the amounts awarded by the learned
Arbitrator beyond the terms of agreement and based on mere
conjecture and surmises and also against a wrong person.
(xii) For that the award is in conflict with the public interest.
(xiii) For that the Award is otherwise invalid and bas been
improperly procured by the Opp. Party.
(xiv) For that the applicants reserve their right to file
additional ground in support of this objection if so require in
course of time.
i. Counsel submits that notices were issued pursuant to the
petition filed under Section 34 of Arbitration and Conciliation
Act, 1996. The case was instituted before the learned court
below as Misc. Case No. 2/2012.
j. Learned court below while rejecting the application for
setting aside the award under Section 34 of the Arbitration
and Conciliation Act, 1996 held that clause-23 of the F 2
agreement is an arbitration clause and was not deleted at the
time of signing of the agreement. Moreover, at the time of
referring the matter to the learned Arbitrator, in the High
Court, said fact was not raised and also before the Arbitral
Tribunal it was not raised by the appellants and the
appellants intentionally and deliberately remained absent
from arbitration proceeding. The learned court held that no
ground of challenge was sustainable and accordingly vide
order dated 15.06.2016 rejected the petition filed by the
appellant for setting aside the award under Section 34 of the
Arbitration and Conciliation Act, 1996.
k. Counsel for the appellants while advancing the argument
submits that there was no arbitration clause in existence
pursuant to the agreement between the parties and
6
accordingly the learned Arbitrator wrongly assumed
jurisdiction. He submits that the various clauses of the notice
inviting tender were required to be read into the agreement
and therefore clause 23 of the agreement was not applicable
and accordingly there was no arbitration clause between the
parties.
l. He further submits that even if clause 23 of the agreement is
assumed to be there, the same cannot be termed as arbitration
agreement.
m. Counsel has referred to the judgment passed by the Hon’ble
Supreme Court reported in 2018 SCC On line SC 327 (Lion
Engineering Consultants vs. State of M.P.) paragraph no. 5
and 6 to submit that the plea of jurisdiction by way of
objection under Section 34 of the Act can be raised, even if it
was not raised under Section 16 of the Act. Accordingly, he
submits that it has been held by the Hon’ble Supreme Court
that as per the scheme of the Act, all objections to jurisdiction
of whatever nature must be taken at the stage of the
submission of the statement of defence and must be dealt
with under Section 16 of the Arbitration Act, 1996 and further
once the parties seeks to contend that the subject matter of the
dispute is such as cannot be dealt with by arbitration, it may
be dealt under Section 34 of the Act by the Court.
n. He further refers to the judgment passed by the Hon’ble
Supreme Court reported in (2018) 4 SCC 793 and refers to
paragraph no. 35 and 36 to submit that it has been held by the
Hon’ble Supreme Court that in the absence of arbitration
agreement the court can refer the matter to the Arbitrator
only with written consent of the parties by way of joint
application, more so, when Government or statutory body
like the appellants are involved. He submits that the matter
could not have been referred to Arbitrator on oral consent
between the parties as has been done in the instant case in
Arbitration Application No. 6 of 2010.
o. He has also referred to the judgment passed by the Hon’ble
Supreme Court reported in (2014) 1 SCC 516 (Vishnu
7
(DEAD) By LRS. Versus State of Maharashtra and Others)
at paragraph no. 11 to submit that similar clause as that of
clause 23 of F-2 Agreement was subject matter of
interpretation by the Hon’ble Supreme Court and it was held
that such clause is not an arbitration agreement. Accordingly,
he submits that even if it is assumed that parties would be
governed by clause 23 of the agreement the same cannot be
termed as arbitration agreement. He further submits that the
issues involved in this case are pure question of law which
could have been agitated before the learned court below
which has a bearing upon the very jurisdiction of the learned
Arbitrator who passed the award.
Arguments of the respondent
5. Counsel appearing on behalf of the respondent, on the other hand,
submits as under:-
A. The dispute was referred to learned Arbitrator by
virtue of order dated 10.12.2010 by this Court in
Arbitration Application No. 6 of 2010. He further refers
to the order of this Court to submit that the matter was
referred to the Arbitrator with the consent of the
parties.
B. He submits that admittedly learned Arbitrator served
notice upon the appellants and they had appeared
before the learned Arbitrator, but in spite of that
appellants did not object to the arbitration proceeding
conducted by the learned Arbitrator, rather they
prayed for time for seeking certain approval from their
department.
C. He submits that from perusal of the award passed by
the learned Arbitrator, it is apparent that the learned
Arbitrator had taken all pain to ensure appearance of
the appellants and has recorded such steps in
paragraph no. 9 of the award and had no option but to
proceed in the matter of arbitration in absence of the
appellants. He further submits that the appellant herein
had taken a chance by not appearing before the learned
8
arbitrator and after having lost before the learned
Arbitrator have challenged the award by taking a plea
that the Arbitrator had no jurisdiction.
D. Counsel further submits that in the notice inviting
tender, clause 23 of the F 2 agreement was indicated to
be excluded, but the fact remains that at the time of
signing of the agreement, clause 23 of the agreement
was existing and the agreement was duly signed by the
parties. Clause 27 of the agreement clearly indicates
that parties had read contents of the agreement. He
submits that there is no indication in the petition filed
for setting aside the arbitration award by the appellants
as to why and under what circumstances clause 23 of
the agreement was retained in the agreement.
Accordingly, the parties had agreed to be governed by
clause 23 of the agreement. He also submits that every
page of the agreement were signed by both the parties.
He further submits that even if there was exclusion of
clause 23 of F 2 Agreement in notice inviting tender,
there was no legal bar in entering into the agreement
containing clause 23. He further submits that objection
in regard to existence of clause 23 is not a pure question
of law and it requires evidence as the appellants were
required to explain as to why and how clause 23 of the
agreement was retained. He submits that there is no
doubt that the point regarding the jurisdiction could
also have been raised before the learned Arbitrator, but
the same was required to be raised by the appellants
before the learned Arbitrator. Having not done so,
there was no occasion for the learned Arbitrator to go
into the issue as to whether clause 23 of the agreement
was existing or not particularly when the same was not
challenged and the matter was referred to arbitrator by
the order passed by this Court in Arbitration
Application No. 6/2010. He further submits that at the
stage of referring matter to arbitrator under Section 11
9
of the Arbitration & Conciliation Act, 1996, the Court is
under obligation to at least prima facie examine the
existence of arbitration agreement. He submits that the
appellants having chosen not to file any objection
before the learned arbitrator it was not open to the
appellant to raise such question before the learned
court below under Section 34 of the Arbitration &
Conciliation Act, 1996.
E. He further submits that no element of public policy is
involved in this case and such argument of the
appellants has been rejected by the learned court
below. Counsel also submits that the learned arbitrator
was careful enough even to look into the said
communication issued by the appellants as contained
in letter dated 10.02.2010 and contained in Annexure-7
to the claim petition wherein the Superintending
Engineer had rejected the application of the respondent
to refer the matter to the arbitrator on two grounds:-
(i) prayer for payment of compensation
was rejected by the court below the same
could not be allowed.
(ii) with effect from 18.11.1992 clause 23 i.e
arbitration clause has been deleted in
relation to F-2 Agreement.
6. He further submits that specific issue of point no. 4 was framed by
the learned arbitrator and the contention of the appellants as
contained in letter dated 10.02.2010 was also rejected, although the
appellants never filed any written statement before the learned
Arbitrator. He submits that the order of the learned Arbitrator on
this aspect is a well reasoned order and rightly not called for any
interference by the court below.
7. So far as interpretation of clause 23 is concerned, he submits that
judgment which has been relied upon by the appellants reported in
(2014) 1 SCC 516, in the said judgment, term dispute was totally
missing in the so-called arbitration clause. He further submits that
clause 29 and 30 of the agreement involved in the said case has been
10
quoted in the said judgment at paragraph no. 11 and there is no
clear indication for referring the dispute to the Arbitrator.
Accordingly, the said judgement relied upon by the appellants is
clearly distinguishable and does not apply to the facts and
circumstances of this case.
8. He further submits that clause 23 of the F-2 Agreement has been
duly interpreted by this Hon’ble Court in judgement reported in
Sharda Construction vs. State of Jharkhand reported in (2004)
Online Jhar 587 . He submits that in the said judgment the issue
involved was consequence of deleting clause 23 of the F-2
Agreement by way of gazette notification dated 18.11.1992 and it
was held that in spite of deleting the said clause by way of gazette
notification, the clause was not deleted from the agreement.
Accordingly, it was held that various questions regarding existence
of validity of agreement was required to be adjudicated only by the
Arbitration Tribunal and the matter was referred to the then
Arbitrator. It was also held that clause 23 of the agreement, which
was existing in the contract between the parties and the said
contract was not a statutory contract and was signed by both the
parties , the same cannot be said to have been deleted merely on
account of an executive order issued by the government by
notification. Similar view was taken by this Court in the judgment
passed in the case of Madan Prasad vs. State of Jharkhand reported
in (2016) 3 JLJR 169. He further refers to another judgment passed
by this Court decided on 22.11.2018 in Arbitration Application No.
32 of 2017 wherein by relying upon clause 23 of the agreement, the
matter was referred for arbitration.
Arguments of the appellants by way of rejoinder
9. In response, counsel for the appellants submits that clause 23,
which has been quoted in the judgment relied upon by the
respondents, had specific indication that the arbitration can be
invoked under the Arbitration & Conciliation Act, 1996. In the
instant case, clause 23 of the agreement did not indicate about
Arbitration & Conciliation Act, 1996 and therefore it cannot be said
that clause 23 of the instant agreement was the arbitration
agreement. It is submitted that on this ground the judgments which
11
has been relied upon by the respondents are clearly distinguishable.
Findings of this court
10. After hearing counsel for the parties and after considering the
materials on record this Court finds that admittedly two notice
inviting tenders were floated bearing no. 2 and 3 of 2003-04 for
earth working lining and construction of structures by the Irrigation
Department of the state and the time for completion of work was 12
months and 6 months respectively from the date of agreement.
Further, the value of the work was Rs. 30,48,228.85 and Rs.
78,06,649.80 respectively. Accordingly, the work order dated
29.01.2004 and 25.03.2004 were issued in connection with aforesaid
two notice inviting tenders. After the respondent herein was
declared as successful, the respondent deposited the security
money against both the work orders and entered into an agreement
with the appellant for the purposes of execution of work vide
agreement dated 10.02.2004 and 04.08.2004 respectively. However,
in the notice inviting tender it was clearly indicated that the
agreement will be entered into in Form F 2 as per its terms and
conditions except clause 23. This Court also finds that as per the
notice inviting tender, the N.I.T. was an integral part of the
agreement. This Court further finds that in spite of aforesaid
stipulation in the N.I.T., the authorized representative of the
appellants and the respondent herein had executed the agreement
containing clause 23 which reads as follows:-
Clause-23 : “In case any dispute or difference shall
arise between the parties or either of there upon any
question relating to the meaning of the specifications,
designs, drawings and instructions hereinbefore
mentioned or as to the quality of workmanship or
materials used on the work, or as to the quality of
workmanship or materials used on the work, or as be
the construction of any of the conditions or any clause
or thins there is contained, or as to any question,
claim, rights on liabilities of the parties, or any clause
or thing whatsoever, in my way arising out of, or
relating to the contract, designs drawing,
specification, estimates, instructions order, or these
12
conditions, or otherwise concerning the work, or the
execution, or failure to execute the same whether
arising during the progress of the work, or as to the
breach or this contract, then either party shall
forthwith give to the other notice of such dispute or
difference and such dispute or difference shall be
referred to the Superintending Engineer of the circle
and his decision thereon shall be final conclusive and
binding on all the parties.”
11. This Court finds that the some dispute arose between the parties
and accordingly the respondent herein filed application for
appointment of arbitrator under Section 11 of the Arbitration &
Conciliation Act, 1996 which was numbered as A.A Case No. 6/
2010. The said arbitration was disposed of vide order dated
10.12.2010 and with the consent of the parties and Hon’ble retired
judge of this Court was appointed as Arbitrator in the matter. The
order dated 10.12.2010 passed in Arbitration Application No. 6 of
2010 is quoted hereinbelow for ready reference:-
“This case comes up before this Court for appointment of
an arbitrator as provided in the arbitration agreement.
Both the parties agreed that Justice S.K. Chattopadhaya, a
retired High Court Judge be appointed as an arbitrator,
Since the appointment of arbitrator is on the agreed
submission of the parties, this Court feels inclined to
appoint Justice S.K. Chattopadhaya, a retired High Court
Judge. On being noticed, the parties will appear before him.
The arbitration application, accordingly, stands disposed
of.”
12. S.L.P. was filed against aforesaid order dated 10.12.2010 on the
ground that the dispute has been wrongly referred to the learned
Arbitrator and that there was no arbitration clause in existence in
view of the stipulation in the N.I.T. regarding non-applicability of
the clause 23 of Form F-2 and that it was only the counsel for the
appellants appearing in Arbitration Application No. 6 of 2010 who
had consented for reference to Arbitration by retired judge of this
Hon’ble Court without any instruction in the matter. Admittedly,
the S.L.P. No. 16942 of 2011 was withdrawn by the appellants vide
order dated 21.10.2011. It has been recorded in the order of
withdrawal passed by Hon’ble Supreme Court that the appellants
intended to move the High Court seeking “view” of the impugned
13
order. At this stage of dictation of the judgement in the court, the
counsel for the appellants submits that the word ‘view’ has been
wrongly mentioned in the order passed by the Hon’ble Supreme
court although the same ought to have been “review” and there
appears to be a typographical error in the order passed by the
Hon’ble Supreme Court to this effect. This court is not inclined to
read the order passed by the Hon’ble Supreme Court by
substitution the word “review” for the word “view”. If there was
any typographical mistake, it was for the appellants to move
appropriate petition before the Hon’ble Supreme Court which
admittedly has not been done. The order dated 21.10.2011 passed
by the Hon’ble Supreme Court in the aforesaid S.L.P. is quoted as
under :-
“ Learned counsel for the petitioners seeks withdrawal of
the special leave petition as the petitioners intend to move
the High Court seeking view of the impugned order.
Special leave petition is dismissed as withdrawn.”
13. Admittedly, in the meantime, the learned Arbitrator had
commenced the arbitration proceeding pursuant to the order dated
10.12.2010 passed in Arbitration Application No. 6/2010 and the
learned Arbitrator had issued notice to the appellants and the
appellants had appeared before the learned Arbitrator and had
prayed for time on the ground that certain approvals were required.
Thereafter, the appellants did not participate in the proceeding
before the learned Arbitrator which ultimately led to passing of the
award on 24.12.2011. It is the specific case of the appellants that the
order dated 21.10.2011 passed in aforesaid S.L.P. was duly
communicated to the office of learned Arbitrator on 23.12.2011,
with a prayer to adjourn the matter for two months so as to enable
them to take appropriate steps in the High Court, but in spite of
this, the learned Arbitrator had pronounced the award on
24.12.2011. The fact about filing of letter before the learned
Arbitrator on 23.12.2011 is not reflected from the award and
admittedly the appellants did not take any steps for more than two
months after order of withdrawal of the S.L.P. filed before the
Hon’ble Supreme Court. This court is of the considered view that
otherwise also, order of withdrawal of the S.L.P could not have
14
prevented the learned arbitrator from pronouncing the award
particularly when the appellants had refused to participate in the
arbitral proceedings.
14. From perusal of the award passed by the learned Arbitrator, this
court finds that the learned Arbitrator had mentioned about non
appearance of the appellants in paragraph no. 9 of the award which
clearly indicates that the learned Arbitrator had taken pain to
ensure that the appellants should appear in the proceeding.
However, in spite of best of efforts, the appellants did not
participate in the arbitration proceeding in spite of service of notice
and accordingly did not raise any objection in connection with the
existence of arbitration clause and/or on the interpretation of
clause-23 of the agreement which was never struck off by the
parties to the agreement. For ready reference, paragraph no. 9 of the
award passed by the learned Arbitrator is quoted below:-
“On being noticed, the claimant appeared but surprisingly
except one Mr. P.C. Jha, Executive Engineer, Minor
Distribution Division No. 9 (respondent no. 3) along with Mr.
M.K. Jha, S.D.O. Minor Distribution Division No. 9 appeared
on the date fixed i.e. on 27.01.2011 but no other respondents
appeared. However, the Chief Engineer (respondent no. 2) and
the Superintending Engineer (respondent no. 4) informed Mr.
Jha of their inability to appear on the date fixed as they could
only receive the notices on the said date. They assured Mr.
Jha that they would be present on 28.01.2011 and as such the
case was adjourned for 28.01.2011 though Mr. Tarun Kumar,
Advocate, appeared on behalf of the claimant and Mr. P.C.
Jha (respondent no. 3) along with Mr. M.K. Jha, appeared but
respondent no. 2 and 4 did not appear. When enquired by me,
Mr. Jha submitted that unless and until approval is given by
the concerned Department it was not possible for either
respondent no. 2 or 4 to appear before the Tribunal in spite of
receiving the notices. He prayed for three months time for
taking necessary approval from the Department so that on
the next date other two respondents could appear before me.
Prayer was allowed and the case was adjourned for three
months.
15
On 29.04.2011, that is after three months, when the matter
was again placed before me, none of the respondents
including Mr. Jha appeared before the Tribunal. On the same
date Tribunal observed that it will have no option but to
hear the claimant exparte on the next date and to pass an
exparte Award without hearing any of the respondents above
named. In order to facilitate the respondents to appear before
me on the next date positively and in order to avoid passing
of an exparte Award, I adjourned the matter to 12.05.2011.
Mr. Tarun Kumar on behalf of the claimant even could not
serve the copy of the claim petition to the respective
respondents due to non-appearance of the respondents. The
case was ordered to be listed on 12.05.2011 and the copies of
this order along with order dated 28.01.2011 were sent to
respondent nos. 1 to 4 by Speed-Post. It was expected that at
least respondent no. 1, the Secretary, Minor Irrigation
Division, would take steps in proper adjudication of the
disputes but all my efforts went in vain as even on 12.05.2011
nobody appeared on behalf of the respondents and having
found no other alternative the case was listed for hearing
exparte. On the prayer made by Mr. Deepak Sinha, learned
counsel on behalf of the claimant next date of hearing was
fixed on 03.06.2011 and the argument was advanced in part.”
15. This court further finds that Arbitrator had framed following issues
(I) Whether the respondents committed a breach of contract by
failing to allot lands free from all encumbrances to the
claimant for executing the allotted work?
(II) Whether respondent department was obliged to provide
encumbrances free land to the contractor for executing the
work allotted to him?
(III) Whether termination of contract for no fault of the claimant
and forfeiting security amount was an arbitrary and
malafide action on part of the Respondents?
(IV) Whether deletion of Clause 23 of the Agreement regarding
arbitration with effect from 18.11.1992 will have any
bearing on the arbitration clause incorporated in the
Agreements entered into in this case?
(V) Whether the Respondent No. 4 deliberately misinterpreted
16
the findings of the Hon’ble High Court while refusing to
appoint an Arbitrator for resolving the disputes?
(VI) Whether due to failure of the respondents, in allotting lands
free from all encumbrances to the claimant, the claimant
had to suffer a financial loss for sitting idle along with its
men and machineries, equipments and materials for almost
one year?
(VII) Whether the claimant is entitled to get the amount of
compensation as claimed by him?
16. Clause-23 of the agreement was subject matter of consideration
under issue no. 4. In spite of non appearance of the appellants
before the learned Arbitrator and their non participation, the
learned Arbitrator took note of the letter dated 10.02.2010 as
contained in Annexure-17 to the claim petition and which was
issued by the appellants wherein request for appointment of
Arbitrator was turned down by the appellant by specifying
following two grounds.
(i) As the prayer for payment of compensation was rejected by
the High court the same could not be allowed.
(ii) With effect from 18.11.1992, clause-23 (i.e. Arbitration Clause)
has been deleted in relation to F 2 agreement.
17. The learned Arbitrator while discussing issue no. 4 recorded his
findings as under:-
“It appears from letter dated 10.02.2010, as contained in
Annexure-17 to the claim petition, that when after the High
Court’s order the claimant filed an application before the
Superintending Engineer requesting him to appoint as
Arbitrator so that loss and damages suffered by him could
be ascertained and he may be compensated accordingly, the
Superintending Engineer by his aforesaid letter rejected the
said application on two grounds, namely (i) as the prayer
for payment of compensation was rejected by the High
Court, the same could not be allowed and (ii) with effect
from 18.11.1992. Clause-23 (i.e. Arbitration Clause) has been
deleted in relation to Agreement F-2.
The second reason assigned by the Superintending
Engineer, in my view, cannot be sustained in law as much
17
as in the present case, deletion of the said clause cannot be
hold good. The reason for my conclusion is that so far the
present case is concerned, the first Agreement was executed
on 10.02.2004 and period expires on 09.02.2005. The
Agreement Nos. 2F -2/2003-04 and 4F-2/2004-05 are
Annexures-3 & 4 to the claim petition. A bare perusal of
conditions of contract of both the Agreements will show
that Arbitration Clause, namely Clause 23, is very much in
existence n both the Agreements. Therefore, in my view if
the Arbitration Clause 23 would have been deleted from the
Conditions of Contract w.e.f. 18.01.1992, this Clause would
not have been mentioned in the Agreements executed much
after the deletion of the said clause, Moreover, the
Superintending Engineer has not annexed any notification
of the State Government by and under which Clause-23 was
deleted with effect from 18.11.1992 as claimed by him. This
shows that the Superintending Engineer in order to
frustrate the claim of the claimant has refused to refer the
matter to Arbitration by taking a non-existent ground of
deletion of Clause 23 from the Agreement. Another
important aspect of the matter is that when the claimant
filed Arbitration Application No. 6 of 2010 before the
Jharkahnd High Court, J.C. to G.P. –I appeared for
respondents and he also did not take this plea by indicating
to the High Court that Arbitration Clause has been deleted
with effect from 18.11.1992. On the other hand he also
agreed along with the claimant’s counsel that an Arbitrator
may be appointed. The order of the High court dated
10.12.2010 appointing me as the Arbitrator is Annexure-18 to
the claim petition.
Thus in my view, it is too late for the Superintending
Engineer to suggest that Clause 23 has been deleted and
therefore the matter could not be referred for Arbitration. I
am of the view that this fact also indicates that the
Superintending Engineer also trying to avoid illegalities
committed by concerned authority/authorities in signing
the Agreements before acquisition of land. In my opinion,
in all fairness the Superintending Engineer ought to have
18
appointed as arbitrator for redressal of the grievances of the
claimant.”
18. This court finds that the award of the learned Arbitrator was
challenged before the learned Civil Judge, Sr. Division at Ghatshila
under Section 34 of the Arbitration and Conciliation Act, 1996
which was numbered as Misc. Case No. 2/2012 and the ground of
challenge have been quoted above.
19. This court finds from perusal of the petition filed under Section 34
of the Arbitration and Conciliation Act, 1996, there is no
explanation on behalf of the appellants as to why and under what
circumstance, clause-23 of the agreement was not struck off at the
time of signing of the agreement by their authorised officer and also
their contention that the parties are governed by the conditions of
notice inviting tender read with the agreement and accordingly
clause-23 stood excluded by virtue of terms of the notice inviting
tender. Counsel for the appellants has referred to the judgment
passed by the Hon’ble Supreme Court reported in (2018) 16 SCC
758 and in also (2018) SCC Online 327 (Lion Engineering
Consultants v. State of M.P.) has referred to paragraph no. 5 and 6
of the said judgment. However , it would be useful to refer to para
4 to 6 of the said judgement which reads as follows:-
“4. Learned Advocate General for the State of M.P. submitted that
the amendment sought is formal. Legal plea arising on undisputed
facts is not precluded by Section 34 (2) (b) of the Act. Even if an
objection to jurisdiction is not raised under Section 16 of the Act, the
same can be raised under Section 34 of the Act. It is not even
necessary to consider the application for amendment as it is a legal
plea, on admitted facts, which can be raised in any case. He thus
submits the amendment being unnecessary is not pressed. Learned
Advocate General also submitted that observations in MSP
Infrastructure Ltd. (supra), particularly in Paragraphs 16 and 17 do
not laid down correct law.
5. We find merit in the contentions raised on behalf of the State. We
proceed on the footing that the amendment being beyond limitation is
not to be allowed as the amendment is not pressed.
6. We do not see any bar to plea of jurisdiction being raised by way of
an objection under Section 34 of the Act even if no such objection was
19
raised under Section 16.”
20. This court is of the considered view that the aforesaid judgement
does not apply to the facts and circumstances of this case
particularly in view of the fact that the point regarding jurisdiction
in the instant case is not a pure question of law but is a mixed
question of fact and law. Here admittedly the clause 23 of the
agreement was existing in the agreement which was ultimately
signed, although as per the case of the appellants, the said clause
was to be excluded. It was certainly for the respondents to lead
evidence on this point and satisfy the learned arbitrator as to under
what circumstances the clause 23 of the agreement was not struck
off from the agreement while signing the same. There is no bar for
the parties to enter into arbitration agreement at a subsequent stage
of signing the agreement even if it was mentioned in the tender that
the clause regarding agreement is to be excluded. This court further
finds that in the instant case, at the initial stage when the appellants
refused to refer the matter for arbitration vide letter dated
10.02.2010, it was mentioned that the dispute cannot be referred to
arbitration as clause 23 was deleted with effect from 18.11.1992 by
virtue of one notification and no such plea was taken that as per the
tender conditions the clause 23 was to be excluded. This court finds
that the appellants have consciously chosen not to participate in the
arbitration proceedings and accordingly did not raise their point of
jurisdiction before the learned arbitrator in-spite of repeated
opportunities granted by the learned arbitrator. This court is of a
considered view that it was not open to the appellant to raise such
point of jurisdiction involving mixed questions of fact and law for
the first time in petition under section 34 of Arbitration and
Conciliation Act, 1996.
21. This court finds that the appellants having appeared before the
learned Arbitrator at one point of time prayed for time and
subsequently they abandoned the proceedings and allowed the
learned Arbitrator to proceed in the matter and did not file any
written statement to dispute the claim. This court also finds that the
learned Arbitrator was careful enough to take into consideration
objection of the State in connection with existence of arbitration
clause on the basis of whatever was available on record including
20
letter dated 10.02.2010, which was filed by the respondent before
the learned Arbitrator, this court finds that the appellants allowed
the learned Arbitrator to proceed in the matter and when the
Arbitrator was scheduled to pronounce the judgment on 24
th
December, 2011, they claimed to have filed a petition in the office of
the learned Arbitrator regarding dismissal of S.L.P. therefore
proposed petition to be filed before the High Court that too after
expiry of two months from the date of dismissal of the S.L.P. which
was dismissed vide order dated 21.10.2011. Even as per the
appellants request to adjourn the case was filed in the office of the
learned Arbitrator only on 23.12.2011. From perusal of the lower
court records this court finds that receiving copy of the letter dated
23.12.2011 has been filed by the appellants which appears to have
been signed by one clerk and there is nothing on record to suggest
that the same was brought to the notice of the learned Arbitrator.
Even final award which has been passed does not indicate the filing
of any such letter before the learned Arbitrator. This court further
finds that even if it is assumed that the said letter was brought to
the notice of the learned Arbitrator, then also, merely because the
party is going to file a petition cannot be a ground for not
pronouncing the award.
22. The counsel for the appellant has submitted that objection to
jurisdiction can be taken under Section 34 of the Arbitration and
Conciliation Act, 1996. He has referred to Para 35 and 36 of another
judgment reported in (2018) 4 SCC 793 (Kerela State Electricity
Board and Another vs. Kurien E. Kalathil and Another) Paragraph
no. 35 and 36 of the said judgment reads as follows:-
35. “After pointing out the disputed claims of additional work (Ext. P-59)
and on the oral consent of the counsel for the appellant, the High Court has
referred the parties to arbitration appointing Justice K.A. Nayar as the
arbitrator. Arbitrator/Tribunal is a creature of the contract between the
parties. There was no arbitration agreement between the parties. The
question falling for consideration is whether the High Court was right in
referring the parties to arbitration on the oral consent given by the counsel
without written instruction from the party.
36. Jurisdictional precondition for reference to arbitration under Section 7
21
of the Arbitration and Conciliation Act is that the parties should seek a
reference or submission to arbitration. So far as reference of a dispute to
arbitration under Section 89 CPC is concerned, the same can be done only
when parties agree for settlement of their dispute through arbitration in
contradistinction to other methods of alternative dispute resolution
mechanism stipulated in Section 89 CPC. In so far reference of the parties
to arbitration, oral consent given by the counsel without a written memo
of instructions does not fulfil the requirement under Section 89 CPC.
Since referring the parties to arbitration has serious consequences of taking
them away from the stream of civil courts and subject them to the rigour of
arbitration proceedings, in the absence of arbitration agreement, the court
can refer them to arbitration only with written consent of parties either by
way of joint memo or joint application; more so, when Government or
statutory body like the appellant Board is involved.”
23. This court is of the considered view that the aforesaid judgement
does not help the appellants in any manner and is clearly
distinguishable on facts. In the instant case the reference to learned
arbitrator is based on a written agreement containing clause 23 and
is not merely on account of consent during disposal of Arbitration
Application No. 6/2010. In the aforesaid judgment the reference to
arbitrator was solely on the basis of oral consent of counsels.
24. This court further finds that contract herein is not a statutory
contract and no element of public policy is involved in this case.
25. So far as contention of the appellants that clause-23 by itself cannot
be said to be an arbitration clause is concerned, they have relied
upon the judgment passed by the Hon’ble Supreme Court reported
in (2014) 1 SCC 516 ( Vishnu versus State of Maharashtra)
paragraph no. 11,12,13 which reads as follows:-
11. We have considered the respective arguments.
Clauses 29 and 30 of the B-1 Agreements entered into
between the parties read as under:
“29. All works to be executed under the contract shall
be executed under the direction and subject to the
approval in all respects of the Superintending Engineer
of the Circle for the time being, who shall be entitled to
direct at what point or points and in what manner they
are to be commenced, and from time to time carried on.
22
30. Except where otherwise specified in the contract
and subject to the powers delegated to him by the
Government under the Code Rules then in force the
decision of the Superintending Engineer of the Circle for
the time being shall be final, conclusive, and binding on
all parties to the contract upon all questions, relating
to the meaning of the specifications, designs, drawings,
and instructions hereinbefore mentioned and as to the
quality of workmanship, or materials used on the
work, or as to any other question, claim, right, matter,
or thing whatsoever, if any way arising, out of, or
relating to the contract designs , drawings,
specifications, estimates, instructions, orders, or these
conditions or otherwise concerning the works, or the
execution, or failure to execute the same, whether
arising, during the progress of the work, or after the
completion or abandonment thereof.”
12. Para 224 of the Maharashtra Public Works Manual,
as amended by Government C.M. No. C.M. No. CAT-
1070/460-DSK.2, dated 09.05.1977, reads as under:
“224. Clause 30 of B-1 and B-2 Agreement forms lays
down that the decision of the Superintending Engineer
in certain matters relating to the contract would be
final. The Superintending Engineer’s decision taken
under this clause should be considered as that taken as
an arbitrator and this should be considered as the
decision taken under that Arbitration Act. The
decisions taken by the Superintending Engineer under
the other clauses should be considered different from
his decision taken under Clause-30 of B-1 and B-2
tender agreements as an arbitrator.”
13.We shall first consider the question whether Clause
30 of the B-1 Agreements can be construed as an
arbitration clause:
13.1 A conjoint reading of Clauses 29 and 30 of B-1
Agreements entered into between the parties shows
that the appellant had to execute all works subject to
the approval in all respects of the Superintending
23
Engineer of the Circle, who could issue directions from
time to time about the manner in which work was to
commence and be executed. By virtue of Clause 30, the
decision of the Superintending Engineer of the Circle
was made final, conclusive and binding on all the
parties in respect of all questions relating to the
meaning of the specifications, designs, drawings,
quality of workmanship or materials used on the work
or any other question relating to claim, right, matter or
things arising out of or relating to the contract designs,
drawings, specifications, estimates, instructions,
orders etc.
13.2 These two clauses by which the Superintending
Engineer was given overall supervisory control were
incorporated for smooth execution of the works in
accordance with the approved designs and
specifications and also to ensure that the quality of
work is not compromised. The power conferred upon
the Superintending Engineer of the Circle was in the
nature of a departmental dispute resolution mechanism
and was meant for expeditious sorting out of problems
which could crop up during execution of the work.
13.3 Since the Superintending Engineer was made
overall in-charge of all works to be executed under the
contract, he was considered by the parties to be the
best person who could provide immediate resolution of
any controversy relating to specifications, designs,
drawings, quality of workmanship or material used
etc. It was felt that if all this was left to be decided by
the regular civil courts, the object of expeditious
execution of work of the project would be frustrated.
This is the primary reason why the Superintending
Engineer of the Circle was entrusted with the task of
taking decision on various matters.
13.4 However, there is nothing in the language of
Clause-30 from which it can be inferred that the parties
had agreed to confer the role of arbitrator upon the
Superintending Engineer of the Circle.”
24
26. This court finds that the Hon’ble Supreme Court in paragraph no.
19 has referred to the judgement passed in the case of K.K. Modi
versus K.N. Modi reported in (1998) 3 SCC 573 wherein the
attributes of an arbitration agreement has been culled out. Further
vide para 30 and 31 the judgement passed in the case of Punjab
State versus Dina Nath has been referred and quoted. Para 30 and
31, of the said judgement reported (2014) 1 SCC 516 is quoted as
follows:-
31. After noticing the judgment in K.K. Modi v. K.N. Modi, the
Court observed(Dina Nath case, SCC pp. 33-34, paras 12 & 14)
“12. Keeping the ingredients as indicated by this Court
in K.K. Modi in mind for holding a particular
agreement as an arbitration agreement, we now
proceed to examine the aforesaid ingredients in the
context of the present case :
(a) Clause 4 of the Work Order categorically states
that the decision of the Superintending Engineer shall
be binding on the parties.
(b) The jurisdiction of the Superintending Engineer
to decide the rights of the parties has also been derived
from the consent of the parties to the Work Order.
(c) The Agreement contemplates that the
Superintending Engineer shall determine substantive
rights of parties as the Clause encompasses all
varieties of disputes that may arise between the parties
and does not restrict the jurisdiction of the
Superintending Engineer to specify issues only.
(d) That the agreement of the parties to refer their
disputes to the decision of the Superintending Engineer
is intended to be enforceable in law as it is binding in
nature.
* * *
14. The words ‘any dispute appears in Clause 4 of
the Work Order. Therefore, only on the basis of the
materials produced by the parties in support of their
respective claims a decision can be arrived at in
resolving the dispute between the parties. The use of
25
the words ‘any dispute’ in Clause 4 of the Work Order
is wide enough to include all disputes relating to the
said Work Order. Therefore, when a party raises a
dispute for non-payment of money after completion of
the work, which is denied by the other party, such a
dispute would come within the meaning of ‘arbitration
agreement’ between the parties. Clause 4 of the Work
Order also clearly provides that any dispute between
the department and the contractor shall be referred to
the Superintending Engineer, Hydel Circle No. 1,
Chandigarh for orders. The word ‘orders’ would
indicate some expression of opinion, which is to be
carried out, on enforced and which is to be carried out,
or enforced and which is a conclusion of a body (in this
case Superintending Engineer, Hydel Cirlce No. 1,
Chandigarh). Then again the conclusion and decision of
the Superintending Engineer will be final and binding
on both he parties. This being the position in the
present case and in view of the fact that Clause 4 of the
Work Order is not under challenge before us, the
decision that would be arrived at by Superintending
Engineer, Hydel Circle No 1, Chandigarh must also be
binding on the parties as a result whereof Clause-4
must be held to be binding arbitration agreement.”
32. The Bench distinguished the judgment in State of Orissa v. Damodar
Das by making the following observations : (Dina Nath case, SCC
pp. 35-36 para 17)
17. “From a plain reading of this clause in Damodar Das it
is evident that the powers of the Public Health Engineer
were essentially to supervise and inspect. His powers were
limited to the questions relating to the meaning of the
specifications, drawings and instructions, quality of
workmanship or materials used on the work, or as to any
other question, claim, right, matter, drawings,
specifications, estimates, instructions, orders or these
conditions, or otherwise concerning the works or the
execution or failure to execute the same. However, in the
case before us, the Superintending Engineer was given full
26
power to resolve any dispute arising between the parties
which power in our view is wide enough to cover any
nature of dispute raised by the parties. The clause in the
instant case categorically mentions the word ‘dispute’
which would be referred to him and states ‘his decision
would be final and acceptable/binding on both the
parties.”
33. In our opinion, neither of the judgments relied upon by Shri
Mukherjee help the cause of his client. In Mallikarjun case this Court
noted that the Superintending Engineer, Gulbarga Circle, Gulbarga
was not an officer of the University and he did not have any
authority or jurisdiction either to supervise the construction work or
issue any direction to be contractor in relation to the project. The
Court also emphasised that the parties had agreed that any dispute
arising from the contract would be referred to the decision of the
Superintending Engineer. These factors are missing in the instant
case. Likewise, Clause 4 of the Work Order which came up for
interpretation in Punjab State v. Dina Nath contemplated resolution
by the Superintending Engineer of any dispute arising between the
department and the contractor. Therefore, the relevant clause of the
Work Order was rightly treated as an arbitration agreement.”
27. Ultimately, the Hon’ble Supreme court in (2014) 1 SCC 516 found
that the agreement involved in the said case was not an arbitration
agreement.
28. Applying the same test as has been considered by the Hon’ble
supreme court, this court finds, that clause 23 of the agreement
involved in this case clearly uses the term “any dispute” and
provides that the decision of the Superintending engineer of the
circle shall be final, conclusive and binding upon all the parties; the
jurisdiction to decide the dispute by the said authority has been
derived as per the agreement executed with the consent of the
parties; the Agreement contemplates that the Superintending
Engineer shall determine substantive rights of parties as the Clause
encompasses all varieties of disputes that may arise between the
parties and does not restrict the jurisdiction of the Superintending
Engineer to specific issues only AND the agreement of the parties
to refer their disputes to the decision of the Superintending
Engineer is intended to be enforceable in law as it is binding in
27
nature.
Accordingly, this court finds that clause 23 of the agreement
involved in this case, upon its bare perusal, is certainly an
arbitration agreement when seen in the light of the ratio of
aforesaid judgment passed by Hon’ble Supreme Court.
29. This court further finds that number of judgments has been relied
upon by the respondent as mentioned above wherein matters have
been referred to the Arbitrator resorting to the similar clause-23 of
the F 2 agreement. The counsel for the appellants in response to this
statement of the respondent has tried to draw the distinction
between the clause which were under consideration by this court in
other judgments and clause 23 involved in this case by submitting
that Arbitration and Conciliation Act, 1996 was specifically
mentioned in the arbitration clause involved in the other judgment,
but in the instant case, there is no such reference. This court finds
that reference or non reference of Arbitration and Conciliation Act,
1996 in the arbitration clause itself has no bearing and it is the
clause as such which is to be examined to see as to whether there is
any provision for getting the dispute resolved through arbitration.
Accordingly, the distinction which has been sought to be drawn by
the counsel appearing on behalf of the appellants has no merits and
accordingly such argument is hereby rejected.
30. This court finds that learned court below has passed a detailed
judgment considering all the points raised by the appellants and
every point has been rejected while considering the ground for
setting aside of the award as mentioned in the application under
Section 34 of the Arbitration and Conciliation Act, 1996 and has
taken note of the fact that the appellants never participated in the
proceedings before the learned Arbitrator and it was not open to
them to raise such point now. Further the learned court below has
also considered that challenge to award is permissible on the
grounds under Section 34 of the Arbitration and Conciliation Act,
1996 and the court does not sit in appeal over the award. Learned
court below also held that appropriate reasoning has been assigned
in deciding the claim. Although the appellants did not appear
before the learned Arbitrator, even then due care was taken while
28
deciding the claim. The learned court below also held that the
appellants had failed to prove that any element of public policy is
involved in this case so as to assail the award passed by the learned
Arbitrator.
31. This court finds that the impugned order passed by the learned
court below is itself well reasoned order dealing with all the points
raised by the appellant before the learned court. The scope of
Section 34 of the Arbitration and Conciliation Act, 1996 is very
limited and the court does not sit in appeal against the award
passed by the learned Arbitrator.
32. This court finds that none of the grounds as pointed out by the
appellants call for any interference in the award passed by the
learned Arbitrator or in the impugned order passed by the learned
court below. Accordingly, this appeal is hereby dismissed.
33. Pending I.A., if any, stands dismissed as not pressed.
(Anubha Rawat Choudhary, J.)
Binit/A.F.R.
Legal Notes
Add a Note....