As per case facts, the plaintiff filed a suit for declaration and injunction, which the trial court dismissed. The first appellate court, however, allowed the plaintiff's appeal, granting the reliefs. ...
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT
Reserved on : 11.12.2025
Pronounced on : 05.01.2026
CORAM
THE HON'BLE MR.JUSTICE K.MURALI SHANKAR
C.M.P.(MD)No.2862 of 2025
in
S.A(MD)No.SR 9518 of 2025
The State of Tamil Nadu rep.by
The District Collector,
Thoothukudi District. : Petitioner/Appellant
Vs.
Jothi Lakshmi : Respondent/Respondent
PRAYER in C.M.P(MD)No.2862 of 2025: Civil Miscellaneous Petition filed
under Order XLI, Rule 3(A) of C.P.C., to condone the delay of 4863 days in
filing the second appeal against the judgment and decree made in A.S.No.15
of 2007, dated 18.06.2008 on the file of the Additional District Court,
Thoothukudi, reversing the judgment and decree passed in O.S.No.9 of 2005
on the file of the Sub Court, Kovilpatti.
PRAYER in S.A (MD) SR No. 9518 of 2025 : Second Appeal filed under
Section 100 of C.P.C., against the judgment and decree, dated 18.06.2008 in
1/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
A.S.No.15 of 2007 on the file of the Additional District Court (Fast Track
Court No.II, Thoothukudi reversing the judgment and decree, dated
10.01.2006 in O.S.No.9 of 2005 on the file of the Sub Court, Kovilpatti.
For Petitioner : Mr.A.Ajmal Khan,
Additional Advocate General,
for Mr.D.Gandhiraj,
Special Government Pleader.
For Respondent : Mr.J.Barathan.
ORDER
The above application has been filed under Order XLI, Rule 3(A) of
C.P.C., to condone the delay of 4863 days in filing the second appeal,
challenging the judgment and decree made in A.S.No.15 of 2007, dated
18.06.2008 on the file of the Additional District Court, Thoothukudi, reversing
the judgment and decree passed in O.S.No.9 of 2005, dated 10.01.2006 on the
file of the Sub Court, Kovilpatti.
2.The respondent as plaintiff filed the suit in O.S.No.9 of 2005,
claiming the reliefs to declare that the suit properties are belonging to the
plaintiff and for consequential permanent injunction, restraining the defendant
and their men from in any manner interfering with the plaintiff's peaceful
possession and enjoyment of the suit property.
2/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
3.The petitioner/defendant filed a written statement and contested
the suit. The learned Subordinate Judge, Kovilpatti, after framing necessary
issues and after full trial, passed the judgment, dated 10.01.2006, dismissing
the suit. Aggrieved by the dismissal of the suit, the plaintiff filed an appeal in
A.S.No.15 of 2007 and the learned Additional District Judge, Thoothukudi,
upon considering the materials available on record and on hearing the
arguments of both the sides, passed the judgment and decree, dated
18.06.2008, allowing the appeal and thereby setting aside the judgment and
decree of the trial Court and granted the reliefs of declaration and permanent
injunction as prayed for by the plaintiff. Challenging the judgment and decree
of the first appellate Court, the defendant, who is the Government of Tamil
Nadu represented by the District Collector, Thoothukudi, filed the present
second appeal along with the above application to condone the delay of 4863
days in filing the second appeal.
4. The case of the petitioner canvassed in the delay condonation
petition is that after the disposal of the first appeal, the respondent/plaintiff
3/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
had initiated various proceedings before the Revenue authorities for grant of
patta; that the respondent has also filed number of writ petitions, seeking
directions to consider her representations claiming patta for the suit property
and that since the officials of the petitioner/defendant were grappling with
number proceedings before various authorities, they could not prefer the
second appeal within the stipulated time.
5.It is their further case that the property in question was used for
conducting sports events by the members of Adi-Dravidar Community and this
situation has escalated in sensitivity, placing the Revenue Authorities in a
precarious position due to potential for conflict; that the Adi-Dravidar
community has a history of organizing numerous sports events at the said
location, thereby establishing a pattern that may complicate property rights
and claims; that the officials have been compelled to invest considerable time
and resources into identifying a viable solution that addresses the competing
interests while mitigating the risk of law and order issues and this necessity for
intervention reflects the broader implications of property disputes in
community contexts, highlighting the need for a thorough examination of the
4/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
facts and circumstances surrounding the claims; that there is a delay of 4863
days in filing the second appeal and the said delay is neither wilful nor wanton
and due to the above said administrative reasons, Covid-19 and other natural
calamity, namely, flood in Thoothukudi and that the petitioner will be put to
irreparable loss and untold hardship, if the delay is not condoned.
6. It is the further case of the petitioner that the property in dispute
has been classified as 'Village Natham' or 'Sarkar Poramboke', which is
typically reserved for communal purposes; that the respondent/plaintiff, taking
advantage of the judgment and decree passed by the first appellate Court, is
taking coercive steps against the officials, but the officials are facing the wrath
of village people claiming right over the same property for conducting sports
events and that therefore, it is just and necessary to condone the delay of 4863
days in preferring the appeal.
7.The respondent/plaintiff filed a counter affidavit raising objections
and further stated that the above application is filed to condone an inordinate
and grossly unexplained delay of 6050 days (more than 16 years) in preferring
5/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
the second appeal and the same is wholly unsustainable and an abuse of
process of law; that the petitioner failed to provide any sufficient and bona
fide reasons for the extraordinary delay; that the petitioner's vague and general
excuses, such as administrative reasons, Covid-19 pandemic and natural
calamities lack any specificity or substantiation with proper records; that the
petitioner being a Government authority is expected to act diligently and
responsibly in legal matters, but the present petition reflects gross negligence,
deliberate inaction and complete lack of diligence for which, no justifiable
cause has been shown; that the petitioner has claimed that multiple
proceedings were initiated by her for patta and other reliefs, which clearly
shows that the petitioner was well aware of the respondent's claim all along
and despite such knowledge, the petitioner has not chosen to file second
appeal within the prescribed period and remained completely passive; that the
petitioner has deliberately suppressed the fact that the writ petition in
WP(MD)No.27872 of 2024 was filed against him, challenging his actions
concerning the subject property and the said writ petition came up for hearing
on 21.11.2024 and 07.01.2025 and this Court was pleased to grant a stay in
respondent's favour and immediately, after the writ petition was taken up and
6/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
interim stay was granted, the petitioner has rushed to file the second appeal
along with the above delay condonation petition and the same clearly indicates
that the petitioner has approached this Court only as a counter blast to the
adverse proceedings in the writ petition.
8. It is the further defence of the respondent that the Covid-19
pandemic excuses is wholly untenable as the pandemic occurred on
15.03.2020 to 28.02.2022, whereas the delay in filing the second appeal
started in 2008 itself; that the excuse of natural calamities in Thoothukudi is
equally baseless, as there is no specific evidence provided as to how any flood
or calamity prevented the filing of the appeal for more than a decade before
the pandemic even occurred; that though the petitioner claimed that the suit
property is sarkar poramboke land (Government land) and village natham,
they have failed to take any steps to establish their claim in Court for 16 years
and even the allegation that the suit property is a Sarkar Poramboke land and
Village Natham are contradictory to each other ; that the petitioner's reliance
on classification of land (such as 'Sarkar Poramboke' or Village Natham') is
irrelevant as the plaintiff had acquired valid title through sale deeds from legal
7/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
heirs and the first appellate Court had already adjudicated the issue in her
favour; that the petitioner failed to show that any substantial question of law
that would justify entertaining a second appeal after such a long delay; that the
petitioner has been enjoying the property lawfully since acquiring it through
registered sale deeds in the year 2004 and the first appellate Court has already
upheld her title in the year 2008 and that therefore, the second appeal as well
as the delay condonation petition are not maintainable and are liable to be
dismissed.
9. The only point for consideration is whether the delay of 4863
days in filing the second appeal, challenging the judgment and decree made in
A.S.No.15 of 2007, dated 18.06.2008 on the file of the Additional District
Court, Thoothukudi, is liable to be condoned.?
10. Before proceeding further, it is necessary to refer the decision in
the case of Shankargir Vs. State of Madhya Pradesh and another passed in
Civil Appeal No.14613 of 2025, dated 05.12.2025, wherein the Hon'ble Apex
Court expressed dismay over the manner in which the High Court condoned
8/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
the delay of 1612 days on the mere asking of the State Government. The
Hon'ble Supreme Court reminded that the law is well-settled in terms
limitation and condoning delay that sufficient cause has to be looked into.
11. In the case of Thirunagalingam Vs. Lingeswaran and another
reported in 2025 Live Law SC 560, the Hon'ble Apex Court reiterated the
legal position that while considering the plea for condonation of delay, the
first and foremost duty of the court is to first ascertain the bona fides of the
explanation offered by the party seeking condonation rather than starting with
the merits of the main matter. Only when sufficient cause or reasons given for
the delay by the litigant and the opposition of the other side is equally
balanced or stand on equal footing, the court may consider the merits of the
main matter for the purpose of condoning the delay and the relevant portion is
extracted hereunder :
“Further, this Court has repeatedly emphasised in
several cases that delay should not be condoned merely as an act
of generosity. The pursuit of substantial justice must not come at
the cost of causing prejudice to the opposing party. In the present
9/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
case, the respondents/defendants have failed to demonstrate
reasonable grounds of delay in pursuing the matter, and this
crucial requirement for condoning the delay remains unmet.”
12. The learned counsel for the respondent would rely on the
decision of Hon'ble Supreme Court in State of Madhya Pradesh Vs.
Ramkumar Choudhary reported in 2024 SCC Online SC 3612, wherein its
earlier decision in Union of India Vs. Jahangir Byramiji Jeejeebhoy(D)
through his legal heir, reported in 2024 SCC Online SC 489, was referred
and the relevant passages are extracted hereunder :
5.1. In Union of India v. Jahangir Byramji Jeejeebhoy (D)
through his legal heir, wherein, one of us (J.B.Pardiwala, J) was a
member, after referring to various decisions on the issue, it was in
unequivocal terms observed by this Court that delay should not be
excused as a matter of generosity and rendering substantial justice
is not to cause prejudice to the opposite party. The relevant passage
of the same is profitably extracted below:
“24. In the aforesaid circumstances, we made it very
10/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
clear that we are not going to look into the merits of the matter as
long as we are not convinced that sufficient cause has been made
out for condonation of such a long and inordinate delay.
25. It hardly matters whether a litigant is a private party
or a State or Union of India when it comes to condoning the gross
delay of more than 12 years. If the litigant chooses to approach the
court long after the lapse of the time prescribed under the relevant
provisions of the law, then he cannot turn around and say that no
prejudice would be caused to either side by the delay being
condoned. This litigation between the parties started sometime in
1981. We are in 2024. Almost 43 years have elapsed. However, till
date the respondent has not been able to reap the fruits of his
decree. It would be a mockery of justice if we condone the delay of
12 years and 158 days and once again ask the respondent to
undergo the rigmarole of the legal proceedings.
26. The length of the delay is a relevant matter which the
court must take into consideration while considering whether the
delay should be condoned or not. From the tenor of the approach of
11/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
the appellants, it appears that they want to fix their own period of
limitation for instituting the proceedings for which law has
prescribed a period of limitation. Once it is held that a party has
lost his right to have the matter considered on merits because of his
own inaction for a long, it cannot be presumed to be non-deliberate
delay and in such circumstances of the case, he cannot be heard to
plead that the substantial justice deserves to be preferred as against
the technical considerations. While considering the plea for
condonation of delay, the court must not start with the merits of the
main matter. The court owes a duty to first ascertain the bona fides
of the explanation offered by the party seeking condonation. It is
only if the sufficient cause assigned by the litigant and the
opposition of the other side is equally balanced that the court may
bring into aid the merits of the matter for the purpose of condoning
the delay.
27. We are of the view that the question of limitation is
not merely a technical consideration. The rules of limitation are
based on the principles of sound public policy and principles of
12/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
equity. We should not keep the ‘Sword of Damocles’ hanging over
the head of the respondent for indefinite period of time to be
determined at the whims and fancies of the appellants.
xxx xxx xxx
34. In view of the aforesaid, we have reached to the
conclusion that the High Court committed no error much less any
error of law in passing the impugned order. Even otherwise, the
High Court was exercising its supervisory jurisdiction under Article
227 of the Constitution of India.
35. In a plethora of decisions of this Court, it has been
said that delay should not be excused as a matter of generosity.
Rendering substantial justice is not to cause prejudice to the
opposite party. The appellants have failed to prove that they were
reasonably diligent in prosecuting the matter and this vital test for
condoning the delay is not satisfied in this case.
36. For all the foregoing reasons, this appeal fails and is
hereby dismissed. There shall be no order as to costs.”
13/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
After referring to the above said decision, the Hon'ble Apex Court
observed,
'Applying the above legal proposition to the facts of the
present case, we are of the opinion that the High Court correctly
refused to condone the delay and dismissed the appeal by
observing that such inordinate delay was not explained
satisfactorily, no sufficient cause was shown for the same, and no
plausible reason was put forth by the State. Therefore, we are
inclined to reject this petition at the threshold.'
6. At the same time, we cannot simply brush aside the
delay occurred in preferring the second appeal, due to callous
and lackadaisical attitude on the part of the officials functioning
in the State machinery. Though the Government adopts
systematic approach in handling the legal issues and preferring
the petitions/applications/appeals well within the time, due to the
fault on the part of the officials in merely communicating the
information on time, huge revenue loss will be caused to the
Government exchequer. The present case is one such case,
wherein, enormous delay of 1788 days occasioned in preferring
14/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
the second appeal due to the lapses on the part of the officials
functioning under the State, though valuable Government lands
were involved. Therefore, we direct the State to streamline the
machinery touching the legal issues, offering legal opinion, filing
of cases before the Tribunal / Courts, etc., fix the responsibility on
the officer(s) concerned, and penalize the officer(s), who is/are
responsible for delay, deviation, lapses, etc., if any, to the value of
the loss caused to the Government. Such direction will have to be
followed by all the States scrupulously.
13. Bearing the above position in mind, let us consider the case on hand.
As already pointed out, the reasons canvassed for the delay are Covid-19 and
other natural calamity ie., flood in Thoothukudi apart from administrative
reasons.
14.As rightly pointed out by the learned counsel for the respondent,
Covid-19 impacted the limitation period only between March 2020 and
February 2022. But in the case on hand, the first appellate Court disposed of
the appeal on 18.06.2008 ie., 12 years before the Covid-19 pandemic.
Regarding the flood in Thoothukudi, the petitioner has not elaborated anything
further.
15/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
15. Now turning to the administrative reasons, according to the
petitioner, the respondent after, dismissal of the first appeal, initiated various
proceedings before the Revenue Authorities for grant of patta and also filed
number of writ petitions, seeking directions to consider the petitioner's
representation claiming patta for the suit property and that since the officials
of the petitioner were grappling with the above proceedings, they could not
prefer the appeal within the stipulated time.
16.Though it has been averred that various proceedings were initiated
before the Revenue Authorities and number of writ petitions were filed before
the High Court, the petitioner has not chosen to mention the same. The learned
counsel for the respondent would submit that the respondent filed a writ
petition in W.P(MD)No.27872 of 2024 against the petitioner challenging his
actions concerning the subject property and the said writ petition was taken up
for hearing on 21.11.2024 and 07.01.2025 and the High Court has granted stay
in favour of the respondent and only thereafter, the petitioner has filed the
present appeal along with the delay condonation petition as a counter blast to
the writ proceedings.
16/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
17. Admittedly, the petitioner has nowhere whispered about the writ
petition in WP(MD)No.27872 of 2024, filed by the respondent and granting of
stay by this Court. Even assuming for argument sake that the respondent
initiated various revenue proceedings and filed several writ petitions, that by
itself is not a ground or reason for not filing the second appeal.
18. The learned Additional Advocate General appearing for the
petitioner would submit that the suit property has been classified as Sarkar
Poramboke or Village Natham indicating that it is a Government owned and
designated for public or community use. He would further submit that since
the land in dispute is the Government land, the same cannot be allowed to be
grabbed by the respondent and that is why the petitioner has preferred the
present appeal challenging the judgment and decree of the first appellate
Court, which are erroneous factually and legally.
19. The learned counsel for the respondent would submit that the
petitioner/Government had taken some pleas before the first appellate Court,
17/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
but the same came to be rejected; that the Government failed to take any steps
to establish their claim for 16 years, that the very allegation of the Government
that the suit properties are Sarkar Proramboke or Village Natham are
contradictory to each other and that the Government reliance on classification
of land as Sarkar Proramboke or Village Natham is totally irrelevant as the
respondent had acquired valid title through sale, which came to be accepted by
the first appellate Court.
20. As per settled legal position referred above, the Courts while
considering the plea of condonation of delay must not start with merits of the
matter, but can consider the merits for the purpose of condoning the delay only
if the sufficient cause given by the litigant and the opposition of the other side
is equally balanced or stand on equal footing.
21. As already pointed out, the reasons canvassed, by no stretch of
imagination can be taken as sufficient cause or reason and moreover, the
reasons canvassed were also not proved. It is settled law that administrative
reason cannot be taken as a sufficient cause so as to attract Section 5 of
18/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
Limitation Act or Order 41 Rule 3A of C.P.C. No doubt, though the
respondent has alleged that there occurred delay of 6050 days, the Registry
has calculated the delay at 4863 days. The petitioner has sought to condone
the delay of more than 13 years in filing the second appeal.
22. When the matter was taken up for enquiry, the learned counsel for
the respondent would submit that the respondent is in possession and
enjoyment of the suit property. The learned Additional Advocate General, on
instructions, would admit the same. Moreover, the second appeal is not an
automatic right and it is a discretionary appeal granted by the Constitution
requiring the High Court's satisfaction that the case involves a substantial
question of law. It is not just a matter of facts; the core requirement is a
substantial question of law as defined in Section 100 C.P.C. Hence, the
contention of the petitioner that they should be given an opportunity to
prosecute the second appeal cannot be countenanced.
23. Considering the above, this Court has no hesitation in holding that
the petitioner has not shown any sufficient cause for the inordinate delay of
19/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
4863 days in filing the second appeal and as such, this Court concludes that
the petition is devoid of merits and is liable to be dismissed.
24. In the result, the Civil Miscellaneous Petition is dismissed.
Consequently, the Second Appeal is rejected at the SR stage itself.
05.01.2026
NCC : Yes /No
Index : Yes / No
Internet : Yes / No
das
To
1.The Additional District Court, Thoothukudi.
2.The Sub Court, Kovilpatti.
2.The Record Keeper,
Vernacular Section,
Madurai Bench of Madras High Court,
Madurai.
20/21 https://www.mhc.tn.gov.in/judis
C.M.P.(MD)No.2862 of 2025
in S.A(MD)No.SR 9518 of 2025
K.MURALI SHANKAR,J.
das
Pre-delivery order made in
C.M.P.(MD)No.2862 of 2025
in
S.A(MD)No.SR 9518 of 2025
Dated: 05.01.2026
21/21 https://www.mhc.tn.gov.in/judis
Legal Notes
Add a Note....