0  02 Dec, 2025
Listen in mins | Read in 114:00 mins
EN
HI

Vedanta Limited Vs. The Nominated Authority, Ministry Of Coal

  Delhi High Court W.P.(C) 10686/2025 & CM APPL. 44163/2025
Link copied!

Case Background

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

W.P.(C) 10686/2025 Page 1 of 76

$~

* IN THE HIGH COURT OF DELHI AT NEW DELHI

Reserved on: 10

th

October, 2025

Pronounced on: 2

nd

December, 2025

+ W.P.(C) 10686/2025 & CM APPL. 44163/2025 (Directions for Stay

on the Operation of the Impugned Order)

VEDANTA LIMITED .....Petitioner

Through: Mr. Nidhesh Gupta with Mr. Prashanto

Chandra Sen, Senior Advocates, Mr.

Naveen Kumar, Mr. Bikram Dwivedi,

Mr. Ujjwal Kumar Rai, Mr. Rohit

Ghosh, Mr. Jimut Mohapatra, Mr.

Utkarsh Chandra, Mr. Prabhat Kumar

Rai, Mr. Aditya Goel and Mr. Lakshay

Singh, Advocates.

versus

THE NOMINATED AUTHORITY MINISTRY OF COAL

GOVERNMENT OF INDIA & ORS. .....Respondents

Through: Mr. Chetan Sharma, ASG with Mr.

Ankur Mittal, CGSC with Mr. Aviraj

Pandey, Ms. R. Jaiswal, Ms. Jutirani

Talakdar, Advocates for UOI.

CORAM:

HON'BLE MR. JUSTICE AMIT SHARMA

JUDGMENT

W.P.(C) 10686/2025 Page 2 of 76

AMIT SHARMA, J.

W.P.(C) 10686/2025

1. The present petition under Article 226 of the Constitution of India,

1950, has been filed seeking the following prayers: -

“In view of the foregoing facts and grounds, the Petitioner most

respectfully prays that this Hon’ble Court may be pleased to:

(a) Allow the present Writ Petition and issue appropriate writ, order or

directions to quash and set aside Impugned Order dated 21.07.2025

bearing file No. NA- 104/8/2020-NA (hereinafter referred as “Impugned

Order”) issued by the Respondent No. 1 I.e., Nominated Authority,

Ministry of Coal, Govt., of India; And/o

(b) Issue further appropriate orders or directions restraining the

Respondent No. 1 to give effect to appropriation order dated 21.07.2025

bearing file No. NA- 104/8/2020-NA issued by the Respondent No. 1

I.e., Nominated Authority, Ministry of Coal, Govt., of India and refund

any amount so appropriated; And/or

(c) Issue further appropriate writ, orders or directions directing the

Respondent No. 1 to grant an extension of milestone deadlines under the

Coal Mine Development and Production Agreement (CMDPA) dated

11.01.2021, executed in favour of the Petitioner with respect to the

Radhikapur (West) Coal Mine situated in Angul district, Odisha in terms

of the order dated 16.07.2025 filed by the Petitioner before the

Respondent No. 1; And/or

(d) Issue further order or directions to the Respondents to process the

applications of the Petitioner for grant of statutory clearances in a time

bound manner; And/or

(e) Pass such other or further orders as this Hon’ble Court may deem just

and proper in the facts and circumstances of the present case.

AND FOR THIS ACT OF KINDNESS, THE PETITIONER AS IN

DUTY BOUND SHALL EVER PRAY. ”

W.P.(C) 10686/2025 Page 3 of 76

FACTUAL BACKGROUND

2. Brief facts necessary for the adjudication of the present petition, as

stated by the petitioner in the present petition, are as under: -

i) On 18.06.2020, the Nominated Authority, Ministry of Coal,

Government of India, (respondent No.1) issued the Tender Document

for the 11

th

Tranche of Auction under the Coal Mines (Special

Provisions) Act, 2015

1

, for auctioning coal mines for commercial sale

including Radhikarpur (West) Coal Mine, which was subsequently

allotted to the petitioner. After conducting auction under the provisions

of CM (SP) Act, 2015, and associated Rules, on 28.12.2020, the

petitioner was declared ‘successful bidder’ for the Radhikapur (West)

Coal Mine

2

by respondent No.1 in accordance with the directions

issued by Govt. of India vide Office Memorandum dated 23.12.2020

and Rule 10 (10) of the CM (SP) Rules, 2014, pursuant to final offer of

21% of the revenue share for the Coal Mine submitted by the petitioner

(successful bidder).

ii) On 11.01.2021, Coal Mine Development and Production

Agreement (CMDPA) was executed between the President of India and

the Petitioner formalising the obligations and milestones to be adhered

to by the petitioner for operationalising the subject mine. After

execution of CMDPA, on 03.03.2021, respondent No.1 under Rule

1

Hereinafter referred to as “CM (SP) Act, 2015”

2

Hereinafter referred to as “Subject Mine”

W.P.(C) 10686/2025 Page 4 of 76

7(2)(b) and Rule 13(1) of the Coal Mines (Special Provisions) Rules,

2014 read with Section 6(3)(b) and Section 8(3) of the CM (SP) Act,

2015, issued a Vesting Order thereby, transferring all rights, title,

interest including the approved mine plan to the petitioner, enabling it

to undertake further steps toward development of the mine.

iii) On 17.02.2021, the petitioner submitted the Schedule-C Format

of the completion notice in terms of Clause 3.2.1 of the CMPDA and

furnished the 1

st

instalment of the upfront amount of Rs.24.76 Crores

along with a Performance Bank Guarantee

3

of Rs.263.17 Crores and a

fixed amount of Rs.7.69 Crores in terms of the Tender Document.

Further, on 05.04.2021, in furtherance of its obligations under

CMDPA, petitioner submitted the commencement plan for starting coal

mining operations at the allocated mine in terms of Clause 5.1 of the

Tender Agreement. On 08.04.2021, petitioner made an application in

Form-7 to the competent authority for transfer of the existing

Environment Clearance (EC) in its name which was issued on

10.01.2014 in favour of prior allottee in terms of the Clauses 1 (c) & 1

(d) of the Vesting Order.

iv) On 19.07.2021, respondent No.1 issued an Office Memorandum

granting relaxation in the timelines prescribed for achieving efficiency

parameters under CMDPA, in view of the nationwide lockdown owing

to the second wave of the COVID-19 pandemic. Vide this Office

Memorandum, 3 months relaxation was given for achieving efficiency

3

Hereinafter referred to as ‘PBG’

W.P.(C) 10686/2025 Page 5 of 76

parameters in both operational as well as non-operational coal mine by

respondent No.1. In the meanwhile, the request of the petitioner for

transfer of Environment Clearance (EC) and Forest Clearance (FC)

were forwarded to the Ministry of Environment, Forest and Climate

Change (MoEF & CC) for necessary action. On 26.11.2021, Forest

Advisory Committee (FAC) considered the proposal for transfer of

Forest Clearance (FC-I) submitted by the petitioner, however, the same

was deferred with direction for further inspection and clarifications.

v) On 07.12.2021, petitioner submitted a formal application before

Director of Mines, Govt. of Odisha, for grant of mining lease over an

area of 1048 hectares based on the vesting order issued by respondent

No.1. On 17.12.2021, Divisional Forest Officer (DFO), Angul, along

with DGIF(C), Bhubaneshwar, and Range Officer, Chhendipada,

conducted a field inspection of the proposed area and in the inspection

report dated 17.12.2021, it was noted that the location of the mine falls

within an area critical to elephant habitat and identified the site as a

high human-elephant conflict zone.

vi) On 23.12.2021, FAC in its 2

nd

meeting, recommended grant of

stage-I FC-I in favour of the petitioner, subject to certain conditions.

On 21.01.2022, the petitioner submitted all requisite documents to the

Office of the Director of Mines, Odisha, seeking further action for

execution of the Mining Lease in accordance with vesting order. On

04.02.2022, in a meeting held between respondent No.1, Central Mine

Planning & Design Institute Limited (CMPDI), petitioner and M/s

W.P.(C) 10686/2025 Page 6 of 76

EMMRL, issues arose regarding three different boundary coordinates

viz., Mining Plan, Vesting Order, recommendations of CMPDI.

vii) On 08.02.2022, petitioner received 1

st

Show Cause Notice (SCN-

I) for non-compliance of Milestone-2 (MS-2) pertaining to the

submission and approval of mining plan and on the same day, the

Nominated Authority issued a letter correcting the boundary

coordinates and directed revision based on Odisha Space Application

Centre (ORSAC) data. On 09.02.2022, petitioner wrote to CMPDI

informing them about revision of boundary coordinates for the subject

mine.

viii) On 21.02.2022, petitioner submitted its reply to SCN-I, citing

reasons including delays due to the COVID-19 pandemic and issues

with mine boundary coordinates. The explanation given by the

petitioner was accepted and SCN-I was dropped against the petitioner

based on the recommendation of Scrutiny Committee in its 18

th

meeting held on 23.08.2022 for providing relaxation by not

appropriating Performance Bank Guarantee for non-compliance with

the milestone (MS-2) and same was communicated to the petitioner by

respondent No.1 vide letter dated 18.01.2023.

ix) On 06.01.2022, MoEF & CC issued in-principle approval of

stage-I Forest Clearance and in view of the same petitioner applied for

grant of EC in its name. However, MoEF & CC raised Essential Details

Sought (EDS) on 10.01.2022 and directed the petitioner to apply afresh

W.P.(C) 10686/2025 Page 7 of 76

for Terms of Reference (ToR) as per provisions of EIA Notification

2006. On 08.09.2022, MoEF & CC issued ToR to the petitioner for

conducting a public hearing and preparing the Environment Impact

Assessment (EIA) and Environment Management Plan (EMP) for

obtaining Environmental Clearance. On 14.12.2022, Expert Appraisal

Committee (EAC) considered the EIA-EMP report submitted by the

petitioner and recommended the grant of Environment Clearance (EC).

On 23.01.2023, MoEF & CC issued final EC to the petitioner and the

same was allegedly, per respondent No.1, obtained after a delay of

more than 4 months as per the stipulated time period prescribed under

Schedule D- Efficiency Parameters. On 16.03.2024, Chief Secretary of

Odisha issued a notification enforcing the Model Code of Conduct in

view of upcoming General and Assembly Elections, and

simultaneously suspended all public hearing activities during this

period.

x) On 06.06.2024, petitioner received 2

nd

Show Cause Notice

(SCN-II) from respondent No.1 for alleged non-completion of MS-3

specifically regarding delay in obtaining stage-II Forest Clearance (FC-

II) and Environmental Clearance (EC). The petitioner submitted a

detailed reply to SCN-II on 20.06.2024 explaining that due to change in

land characteristics, re-initiation of clearance processes was necessary.

Reference was also made to the delays caused by boundary

discrepancies, new ToR/EC filings, elephant corridor issues and Model

Code of Conduct. On 08-09.08.2024, 24

th

Scrutiny Committee meeting

W.P.(C) 10686/2025 Page 8 of 76

was held in which deliberations were held on SCN-II issued to the

petitioner and the reply submitted by petitioner to the said SCN.

xi) On 12.08.2024, petitioner submitted an undertaking committing

to operationalise the mine in accordance with applicable laws and

clearances before the due date of 06.06.2025

4

. On 23.05.2025,

petitioner addressed a detailed representation to respondent No.1

invoking ‘Force Majeure’ in terms of Clause 25 of the CMDPA

thereby, seeking extension of time for achieving MS-4 & MS-5 under

CMDPA, in light of intervening circumstances which were beyond its

control.

xii) On 16.07.2025, the petitioner submitted a detailed representation

seeking revision of “Zero Date” under the CMDPA in view of the

revised forest area and consequential changes to the land schedule, as

per DFO’s directions. This representation was submitted highlighting

the reclassification and expansion of forest area which have triggered a

chain of legal consequences, including the need to restart the clearance

process afresh thereby constituting classic ‘Force Majeure’ scenario.

As per this representation, petitioner had requested respondent No.1

that CMPDI will conduct DGPS survey to ascertain the boundaries and

the petitioner is agreeable to bear the costs of reconducting the survey

and as per revised boundary coordinates, fresh allocation/vesting order

4

As per 24

th

Scrutiny Committee recommendations, undertaking to operationalize mine was before

03.06.2025; however, date mentioned in this letter is 06.06.2025

W.P.(C) 10686/2025 Page 9 of 76

may be issued, and the date of issuance of such order is to be

considered as fresh ‘Zero Date’ for achieving Efficiency Parameters.

xiii) Thereafter, on 21.07.2025, respondent No.1 in purported

compliance of Clause 10 and Schedule D of the CMDPA issued the

impugned Appropriation Order thereby, directing the appropriation of

Rs.29,23,55,117.68/- (Rupees Twenty-Nine Crore Twenty-Three Lakh

Fifty-Five Thousand One Hundred Seventeen and Sixty-Eight Paise

only) from the Performance Bank Guarantee of the Petitioner for

alleged non-compliance with MS-3 within the timeline stipulated in

Schedule D- Efficiency Parameters.

xiv) On 22.07.2025, petitioner submitted a letter to respondent No.1

protesting the unilateral appropriation of Performance Bank Guarantee

and requesting for withdrawal of the impugned appropriation order. On

22.07.2025 itself, the present petition has been filed assailing the

aforesaid Appropriation Order passed by respondent No.1 inter alia

seeking other prayers as noted hereinbefore.

SUBMISSIONS ON BEHALF OF THE PETITIONER

3. Learned Senior Counsels for the petitioner in support of the present

petition have made the following submissions: -

i) The impugned appropriation order has been passed arbitrarily

and without considering the representation of the petitioner seeking

W.P.(C) 10686/2025 Page 10 of 76

extension of the timelines for achieving the milestones and change of

‘Zero Date’ under CDMPA which was, at that time, pending before

respondent No.1. It is submitted that the sole ground on which the

Performance Bank Guarantee has been sought to be appropriated by

respondent No.1 is on account of delay in obtaining environment

clearance (EC) which, in turn, has resulted in delayed completion of

Milestone-3 (MS-3). It is submitted that, as per respondent No.1, MS-3

was due on 03.09.2022 and time limit to achieve the same was 18

months from the completion of previous MS (MS-2), however, it was

achieved on 23.01.2023, therefore, the same entitled respondent No.1

for appropriation of 10% of the Performance Bank Guarantee for delay

in completion of MS-3. It is the case of the petitioner that the alleged

delay of more than 4 months in completion of MS-3 is not solely

attributable to the latter as the same has occurred due to various other

factors such as Covid-19, disrupted administrative and field level

activities, grant of statutory clearances, regarding which respondent

No.1 was duly apprised by the petitioner and despite the same,

impugned order was passed without considering the case of the

petitioner. Learned Senior Counsels have submitted that the petitioner

had given repeated representations to the Nominated

Authority/respondent No.1 for seeking extension of time for

completion of Milestones under CDMPA and still without adverting or

sending any appropriate reply to the said representations, the impugned

order has been passed. Attention of this Court has been drawn towards

a letter/representation dated 16.07.2025 addressed to respondent No.1

by the petitioner for change in ‘Zero Date’ for subject Coal Mine on

W.P.(C) 10686/2025 Page 11 of 76

account of change of Land Schedule as per DFO, Angul, letter dated

11.07.2025 and also, a representation dated 23.05.2025 submitted by

the petitioner requesting extension of timelines to achieve the

Efficiency Parameters.

ii) Learned Senior Counsels have submitted that regarding the

alleged non-compliance of “Efficiency Parameters” mentioned in

CMDPA executed on 11.01.2021, i.e., delay in obtaining ‘Environment

Clearance’ (EC) on 23.01.2023 against the due date of 03.09.2022, a

show cause notice-2 was issued to the petitioner on 06.06.2024 and in

response to the said SCN-II, a detailed reply dated 20.06.2024 was

submitted by the petitioner. Attention of this Court has been drawn

towards the contents of the said SCN-II, and it is submitted that the said

SCN-II was issued in respect of delay in obtaining EC only. However,

it is submitted that in the impugned order in paragraph 7, respondent

No.1 has also taken into the consideration the recommendations made

by Scrutiny Committee in its 24

th

meeting held on 08-09.08.2024 and

the undertaking given on behalf of the petitioner to operationalise the

mine by 03.06.2025, which was a wholly extraneous and irrelevant

consideration for passing the impugned order. It is the case of the

petitioner that no prior SCN was given to the petitioner to explain the

said facts and respondent No.1 has, therefore, gone beyond the

contents/scope of SCN-II thereby, violating the principles of natural

justice. It is also the case of the petitioner that respondent No.1 had not

adjudicated on their representation on the issue of delay in achieving

Efficiency Parameters and has not taken into consideration the

W.P.(C) 10686/2025 Page 12 of 76

relaxations given in achieving the same on account of Covid-19

lockdown as well as the recommendation of the 18

th

Scrutiny

Committee meeting held on 23.08.2022.

iii) Learned Senior Counsels for the petitioner have further

submitted that the vesting order was issued in favour of the petitioner

on 03.03.2021 (vesting date: ‘Zero Date’) and as per the impugned

appropriation order as well as SCN-II dated 06.06.2024, due date for

completion of MS-3 was 03.09.2022 and time limit to complete the

same was 18 months from the completion of previous MS (MS-2). It is

further submitted that as per the vesting order, all statutory licences,

permits, permissions, approvals or consents as per rules, required to

undertake coal mining operations in the mine, if already issued by the

Central Government, to the prior allottee on the same terms and

conditions as were applicable to the prior allottee shall stand fully and

absolutely transferred and vested in the successful bidder. Attention of

this Court has been drawn towards the following covenants of the

vesting order: -

W.P.(C) 10686/2025 Page 13 of 76

It is, thus, argued that the Environment Clearance (EC) stood

vested, as per the vesting order dated 03.03.2021, in the petitioner on

W.P.(C) 10686/2025 Page 14 of 76

the said date itself; however, as per the direction of Ministry of

Environment, Forest and Climate Change (MoEF & CC), the petitioner

had to obtain fresh EC which with all efforts was done within the

prescribed timeline as per the Efficiency Parameters and the impugned

appropriation order has been passed on incorrect calculation of due date

and without taking into consideration the relaxation given by

respondent No.1 in achieving milestones and the dropping/waiving of

SCN-I.

iv) It is further submitted that respondent No.1 has calculated the

time limit/due date of 03.09.2022 for completion of MS-3 from the date

of issuance of vesting order and the same has been done arbitrarily and

on the basis of wrong calculation. Attention of this Court has been

drawn towards the ‘Schedule D- Efficiency Parameters’ wherein,

completion time for MS-2 (Approval of Mining Plan/Project Report

subject to the provisions of Clause 15) was 6 months from the

completion of previous MS (MS-1)/If MS-1 is not applicable, 6 months

from the date of allocation, and further, the completion time for

obtaining ‘Environment Clearance’ (EC) (MS-3) was 18 months from

the completion of previous MS (MS-2). It is, therefore, the case of the

petitioner that the calculation of due date of 03.09.2022 for completion

of MS-3 from the date of vesting is not correct as per Efficiency

Parameters. It has been argued by learned Senior Counsels for the

petitioner that the zero date was the date of vesting order (03.03.2021)

and from that date a period of 6 months was to be given for completion

of MS-2 which was due on 03.09.2021 and beyond the said date, a

W.P.(C) 10686/2025 Page 15 of 76

further 18 months was to be given for completion of MS-3 which was

due on 03.03.2023 and the petitioner has obtained the EC on

23.01.2023 which is well within the prescribed timeline for the

completion of Milestone-MS-3. For the sake of completeness, the said

“Schedule D- Efficiency Parameters” have been reproduced as under:

-

W.P.(C) 10686/2025 Page 16 of 76

v) It is further submitted that SCN-I was issued to the petitioner on

08.02.2022 for delay in filing the mining lease which was a part of MS-

W.P.(C) 10686/2025 Page 17 of 76

2 and for the reasons and justification for delay in submission of

application for mining lease put forth by the petitioner in its reply

submitted on 21.02.2024, the same were duly accepted by the Scrutiny

Committee in its 18

th

Scrutiny Committee meeting held on 23.08.2022

and SCN-I against the petitioner was waived/dropped for non-

compliance with the milestone (MS-2), i.e., Mining Lease Application.

Attention of this Court has also been drawn towards a letter dated

18.01.2023 issued by respondent No.1 to the CEO of the petitioner for

the dropping of SCN-I dated 08.02.2022. It is, therefore, the case of the

petitioner that SCN-II issued to it pursuant to which the impugned

appropriation order has been passed is, in fact, first SCN-I.

vi) Learned Senior Counsels for the petitioner have further

submitted that the delay in achieving the Milestone is also attributable

to a fundamental inconsistency in the demarcation of the mining lease

area as the coordinates notified in the vesting order and the mining plan

differed materially from those demarcated by the Odisha Space

Application Centre (ORSAC) necessitating formal correction only on

08.02.2022. It is the case of the petitioner that said discrepancy is a

failure on the part of public authorities and not attributable to it.

Attention of this Court has been drawn towards a letter dated

27.12.2021 written by Central Mine Planning & Design Institute

Limited (CMPDIL) to Deputy Secretary, Ministry of Coal, Government

of India, regarding the block boundary issue of Radhikapur East and

Radhikapur West Coal mines whereby, it was informed to the latter that

both the allottees have agreed for change in the black bounding

W.P.(C) 10686/2025 Page 18 of 76

coordinates of the subject mines/coal blocks and the same are required

to be revised with reference to ORSAC boundary and approved Mining

Plan boundary.

vii) It is further submitted that the boundary of the subject mines

were agreed to be revised on 04.02.2022 vide meeting held under the

Chairmanship of Additional Secretary & Nominated Authority

regarding boundary finalisation of the subject coal blocks vested in the

petitioner and M/s EMMRL. Attention of this Court has been drawn

towards the following minutes of meeting regarding Boundary of

Radhikapur West Coal Block: -

W.P.(C) 10686/2025 Page 19 of 76

W.P.(C) 10686/2025 Page 20 of 76

viii) It is pointed out that based on the aforesaid discussion, petitioner

addressed a letter dated 07.02.2022 to respondent No.1, proposing that

if the Mining Plan boundary coordinates are kept as it is on the three

sides, i.e., East, South and West, and if only, the north side is extended

further north to coincide with the new bounding coordinate line, it will

cover the entire mining boundary without creating too many changes as

per existing approved bounding coordinates and same will also cover

the ORSAC boundary. Learned Senior Counsels have submitted that

immediately after the issuing of vesting order, respondent No.1 was

informed that there was an area overlapping between the adjoining

Radhikapur East Coal Block requiring reconciliation and that mining

boundary coordinates differed as mentioned in the approved mining

plan, vesting order and recommendation given by CMPDIL. It is

further submitted that despite the revision of the boundary coordinates

in the aforesaid joint meeting held on 04.02.2022 and letter dated

07.02.2022 submitted to respondent No.1 by the petitioner, the

necessary revision in the vesting order along with revised boundary

coordinates for the Radhikapur West Coal Block (subject mine allotted

to the present petitioner) is still pending and despite repeated requests

by the petitioner, regarding the same, as it has created several

impediments in obtaining necessary clearances, the issue is still

unresolved. It is further the case of the petitioner that the aforesaid

developments have taken place after the issuance of vesting order in

favour of the petitioner thereby, resulting in 11 months of delay in

completion of milestones as elucidated in the Schedule D- Efficiency

W.P.(C) 10686/2025 Page 21 of 76

Parameters which have not been taken into consideration by respondent

No.1 while passing the impugned appropriation order.

ix) Learned Senior Counsels for the petitioner have handed up in

Court, during the course of arguments, an Office Memorandum dated

31.01.2025 issued by Ministry of Coal, Govt. of India, in respect of

Guidelines for Preparation of Mining Plan and Mine Closure Plan for

Coal and Lignite blocks 2025 in Rule 2.7 envisaged in Chapter-II

‘Mining Plans’ providing for ‘Project Area’, it has been mentioned that,

‘For all coal blocks, the project boundary shall be delineated based on

the DGPS (Differential Global Positioning System) survey with

certification by CMPDIL and the certificate must be attached with the

Mining Plan along with the KML file’. In view of the same, it has been

contended that without there being a survey the discrepancy crept in the

boundary coordinates could not have been rectified as it required DGPS

survey along with certification by CMPDIL which was to be

undertaken by respondents and the same was also reflected in the letter

dated 27.12.2021 sent by CMPDIL to Ministry of Coal. It is also

pointed out that the petitioner and other allottee had requested the

respondents for conducting DGPS survey and delay in conducting the

same cannot be attributed to the petitioner. The said Guidelines have

been taken on record.

x) Learned Senior Counsels for the petitioner have submitted that as

per the vesting order approved Mine Plan & EC dated 10.01.2014

issued to the prior allottee stood vested in the petitioner. It is further

W.P.(C) 10686/2025 Page 22 of 76

submitted that the petitioner applied for transfer of EC to MoEF &CC;

however, same was denied without obtaining Forest Clearance-I over

the area. Subsequently, MoEF expedited the process for grant of FC

(Forest Clearance) and FC-1 was obtained on 06.01.2022. It is also the

case of the petitioner that with the revised boundary coordinates being

clarified after joint meeting held on 04.02.2022, there was no change in

the area and land schedule with change in boundary coordinates,

however, EC was again denied on the ground that, as per MoEF

guidelines, FC-1 had to be submitted within 18 months. It has been

argued that even after aforesaid intervening circumstances, and delay

fresh EC was granted on 23.01.2023, i.e., 23 months, as against the

allotted 24 months as per CMDPA including the period of 11 months

during which there was confusion of Boundary Coordinates and

effectiveness of the vested Mine Plan.

xi) Learned Senior Counsels have drawn attention of this Court

towards the clauses (c) & (d) of the vesting order dated 03.03.2021 and

it is submitted that the petitioner in terms of the said clauses applied for

transfer of EC on 08.04.2021 by submitting Form-7. It is further

submitted that respondent No.1 vide its Office Memorandum dated

04.10.2021 issued regarding the transfer of EC and FC of the subject

Coal Mine in favour of the petitioner forwarded the request letter of the

latter along with copy of undertaking for abiding by all the conditions

of EC & FC for further needful transfer of EC & FC (process till

consideration by FAC) in the name of the petitioner. However, despite

the same being forwarded on 04.10.2021, no EC & FC was transferred

W.P.(C) 10686/2025 Page 23 of 76

to the petitioner. But on 10.01.2022, MoEF &CC published on its

website that the proposal for transfer of EC cannot be executed in

absence any formal EC letter, which was not issued by this Ministry,

because as per extant rule of EIA, Notification, 2006, the applicant has

to apply afresh application for grant of TOR as per the provisions of

EIA, Notification, 2006 and the lapse of previous EC for the want of

FC-1 clearance. It is submitted that subsequent to the aforesaid

intimation published on 10.01.2022, the petitioner made a fresh

application for obtaining EC and the same was obtained on 23.01.2023.

xii) Further, learned Senior Counsels for the petitioner has drawn

attention of this Court towards the 24

th

Screening Committee meeting

held on 08.08.2024 and 09.08.2024 and particularly towards, the

observation and recommendations of the Committee in respect of the

Radhikapur (West) Coal Mine and SCN-II dated 06.06.2024 issued to

the petitioner for non-achievement of efficiency parameter within

stipulated time pertaining to Forest Clearance Stage-II, and

Environment Clearance, wherein the Committee has admitted that there

was delay in completion of this milestone (MS-3) due to initial

confusion about the boundary coordinates of the mine and

rearrangement of a part of CA (compensatory afforestation) land. The

Committee also took note of the fact that despite the delay in

achievement of this milestone (MS-3), the Allottee (petitioner herein)

has confirmed that the mine will be operationalised within 51 months’

timeline given in CMDPA, i.e., by 03.06.2025. It is submitted that

W.P.(C) 10686/2025 Page 24 of 76

despite the said explicit admission of delay in completion of milestone

on behalf of respondent No.1, the impugned order was passed.

xiii) Learned Senior Counsels for the petitioner have submitted that

vide letter dated 23.05.2025 addressed to respondent No.1, a

representation was made by the petitioner invoking “Force Majeure” in

terms of Clause 25 of the CMDPA and further, seeking appropriate

orders/directions for extension of timeline for achieving Milestones

under Schedule D of CMDPA due to the delay in completion of

Milestone 4 (Land Acquisition and R&R) primarily due to factors

beyond its control such as discrepancy in area proposed vis-à-vis area

demarcated as per ORSAC, which are intensified by the location of the

mine in an Elephant Zone and ecologically sensitive forest area, which

entitled the petitioner to benefit of force majeure clause. It is, therefore,

the case of the petitioner that respondent No.1 has not passed any order

on the said representation submitted by the petitioner nor on the other

representation dated 16.07.2025 submitted for the change in ‘Zero

Date’ for the subject mine on account of change of Land Schedule and

has arbitrarily passed the impugned appropriation order.

xiv) In view of the aforesaid submissions, it has been prayed that the

present petition be allowed and the impugned appropriation order be set

aside and respondent No.1/Nominated Authority be directed to grant

extension of milestone deadlines under CMDPA to the petitioner.

W.P.(C) 10686/2025 Page 25 of 76

SUBMISSIONS ON BEHALF OF THE RESPONDENTS

4. Learned Additional Solicitor General of India for the respondents,

while refuting the submissions made by learned Senior Counsels for the

petitioner, has made the following submissions: -

i) At the very outset, the respondents have raised preliminary issue

in respect of the maintainability of the present petition on the ground that

the petitioner has not availed alternate efficacious remedy under CM

(SP) Act, 2015, prior to the filing of the present petition before this Court

under Article 226 of the Constitution of India. It is submitted that it is a

well-established principle of law that writ jurisdiction ought not be

invoked without first exhausting the alternate efficacious remedy. It is

further submitted that as per Section 27 of the CM (SP) Act, 2015, which

provides for “Dispute settlement and Bar of Jurisdiction of civil

courts”, any proceedings arising from or in connection to the decision of

the Scrutiny Committee vide the impugned Appropriation Order is

subject to the jurisdiction of the Tribunal constituted under Coal Bearing

Areas (Acquisition and Development) Act, 1957, which is established

and situated at Talchar, Odisha. Attention of this Court has also been

drawn towards paragraph 16 of the impugned order wherein, it has been

noted as under: -

“16. Attention is invited to Section 27 of the Coal Mines

(Special Provisions) Act. 2015 providing for adjudication by the

Tribunal constituted under the Coal Bearing Areas (Acquisition

and Development) Act, 1957. For the instant Coal Mine the

Tribunal situated at Talcher, Odisha shall have jurisdiction.”

W.P.(C) 10686/2025 Page 26 of 76

In view of the aforesaid, it is contended that the petitioner has

deliberately ignored the aforesaid clause and has circumvented the

jurisdiction of the learned Tribunal at Talchar, Odisha, by filing the present

petition without first approaching the Tribunal. It is pointed out that there is

no averment in the present petition as to why the petitioner has not

approached the learned Tribunal constituted for the purpose of seeking

redressal of its grievance, if any, and has directly approached this Court in

writ jurisdiction. Reliance has been placed on Radha Krishan Industries v.

State of H.P.

5

, particularly on paragraph 27, to contend that the High Court

has discretion not to entertain a writ petition as one of the restrictions placed

on the exercise of power of the High Court under Article 226 of the

Constitution is where an effective alternate remedy is available to the

aggrieved person. Reliance has also been placed on Joshi Technologies

International Inc. v. Union of India

6

, particularly on paragraph 69, to

contend that the whenever a particular mode of settlement of dispute is

provided in the contract, the High Court would refuse to exercise its

discretion under Article 226 of the Constitution and relegate the party to the

said mode of settlement, particularly when settlement of disputes is to be

resorted to through the means of arbitration. Therefore, it is the case of the

respondents that the present petition ought to be dismissed as not

maintainable and the petitioner be relegated to seek appropriate remedy in

accordance with law before the Court of competent jurisdiction/appropriate

forum.

5

2021 SCC OnLine SC 334

6

(2015) 7 SCC 728

W.P.(C) 10686/2025 Page 27 of 76

ii) Learned ASG has drawn attention of this Court towards

Schedule D- ‘Efficiency Parameters’ to submit that completion time for

obtaining Environment Clearance (‘EC’) was 18 months from

completion of previous MS (MS-2). It is further pointed out that

completion time for ‘Approval of Mining Plan/Project Report subject to

the provisions of Clause 15’ was 6 months from the completion of

previous MS/If MS-1 is not applicable, 6 months from the date of

allocation. It is submitted that the case of the petitioner regarding non-

lapse of 18 months from the completion of previous milestone as

provided under Schedule D- ‘Efficiency Parameters’ is completely

misplaced and based on incorrect reading of the said schedule and

CMDPA. It is the case of the respondents that the petitioner was not

required to do anything to achieve MS-1 since the subject mine is a

fully explored mine. Insofar as MS-2 is concerned, it is contended that

for the purposes of ‘approval of mining plan/project report subject to

Clause 15’, the petitioner was not required to do anything in respect of

MS-2 as the vesting order dated 03.03.2021 itself records in Annexure-

2 thereof, that the approval of mining plan and mine closure plan has

already been granted by Ministry of Coal on 23.06.2011. Therefore, the

period of 18 months from the completion of previous milestone (MS-2)

for obtaining ‘Environmental Clearance’ would commence from the

date of vesting order, i.e., 03.03.2021, and the same was due on

03.09.2022 and EC was obtained by the petitioner on 23.01.2023

against the said due date, and therefore, the partial appropriation of

performance bank guarantee in terms of CMDPA rightly done by the

respondents.

W.P.(C) 10686/2025 Page 28 of 76

iii) It is further submitted that dispute in the present case is purely

contractual in nature, and thus, not amenable to present jurisdiction. It is

the case of the respondents that the penalty imposed on the petitioner is

in strict abidance with the provisions of CMDPA. Attention of this Court

has been drawn towards the following Clauses of the CMDPA which

read thus: -

“6.2 Events for appropriation of the Performances

Security

6.2.1. The Performance Security may be appropriated by the

Nominated Authority upon occurrence of any of the following

events (the "Appropriation Event"), to be determined by the

Nominated Authority in its sole discretion:

(a) failure of the Successful Bidder to provide the duly

acknowledged duplicate copy of the Vesting Order as required

under Clause 4.6;

(b) failure of the Successful Bidder to make payment of any of

the instalment of the Upfront Amount within the time specified

in Clause 3.1(6) and Clause 5.2;

(c) failure of submission of Commencement Plan within the time

specified in Clause 5.1.1;

(d) failure of the Successful Bidder to comply with the

Efficiency Parameters as required under Clause 10;

(e) any change in Control or transfer of right, title or interest in

the Coal Mine which is not in conformity with Clause 13;

(f) failure to make payment of the Monthly Payment in

accordance with this Agreement;

(g) any sale and/or utilisation of coal which is not in conformity

with Clause 8;

(h) failure to make payments of monthly revenue share for CBM

as per Clause 8.2.3;

(i) failure to pay revenue to the Government in case of shortfall

in coal production as per Clause 16.2.2;

W.P.(C) 10686/2025 Page 29 of 76

(j) cessation of coal mining operation exceeding a period of one

year continuously, or 18 months over a period of two years

without occurrence of any event of force majeure;

(k) surrender of the Coal Mine by the Successful Bidder or

termination of the Mining Lease granted to the Successful

Bidder before (a) the expiry of the period for which Mining

Lease (including renewed Mining Lease) has been granted or

will be granted, or (b) extractable reserves are remaining in the

Coal Mine, whichever is earlier;

(l) any other breach or non-compliance of any of the provisions

of this Agreement including in case of the Warranties being

untrue or misleading or incorrect in any manner whatsoever; or

(m) failure of the Successful Bidder to submit the revised

Performance Security in accordance with Clause 6.1.

6.2.2. Provided however that in the event an Appropriation

Event has occurred solely on account of an Event of Force

Majeure which could not have been mitigated by the Successful

Bidder through Good Industry Practice as provided in Clause 25,

then the Performance Security shall not be appropriated for such

specific Appropriation Event.

6.3. Manner of appropriation of the Performance Security

6.3.1. Upon occurrence of an Appropriation Event, to be

determined by the Nominated Authority, the Nominated

Authority shall have the unconditional right to appropriate the

Performance Security by providing a written notice to the

Successful Bidder in the following proportion:

# Appropriation

Event

Amount of the

Performance

Security to be

appropriated

1. Failure of the

Successful Bidder

to provide the duly

acknowledged

duplicate copy of

the Vesting Order

as required under

Clause 4.6

Entire

Performance

Security.

W.P.(C) 10686/2025 Page 30 of 76

2. Failure of the

Successful Bidder

to make payment

of any of the

instalment of the

Upfront Amount

within the time

specified in Clause

5.2

An amount

equal to the

first

instalment,

and/or second

instalment

and/or third

instalment

and/or fourth

instalment of

the Upfront

Amount

together with

12% per

annum simple

interest on

such amount

starting from

the date on

which such

amount was

due and until

the date of

appropriation

of the

Performance

Security.

3. Failure of

submission of

Commencement

Plan within the

time specified in

Clause 5.1.1

An amount

equal to 10%

of the

Performance

Security

4. Failure of the

Successful Bidder

to comply with the

Efficiency

Parameters as

required under

Clause 10

Such per cent

of the

Performance

Security for

each failure to

comply with

the Efficiency

Parameters as

W.P.(C) 10686/2025 Page 31 of 76

specified in

SCHEDULED.

5. Any change in

Control or transfer

of right, title or

interest in the Coal

Mine which is not

in conformity with

Clause 13

Entire

Performance

Security.

6. Any sale and/or

utilization of coal

which is not in

conformity with

Clause 8

Entire

Performance

Security.

7. Failure of the

Successful Bidder

to make payment

of the Monthly

Payment

The amount of

Monthly

Payment due

and payable,

along with a

simple interest

of twelve per

cent per annum

starting from

the date on

which such

amount was

due and until

the date of

appropriation

of the

Performance

Security.

8. Cessation of coal

mining operation

exceeding a period

of one year

continuously, or

18 months over a

period of two

years without

occurrence of any

Entire

Performance

Security.

W.P.(C) 10686/2025 Page 32 of 76

event of force

majeure

9. Surrender of the

Coal Mine by the

Successful Bidder

or termination of

the Mining Lease

granted to the

Successful Bidder

before (a) the

expiry of the

period for which

Mining Lease

(including

renewed Mining

Lease) has been

granted or will be

granted, or (b)

extractable

reserves are

remaining in the

coal Mine,

whichever is

earlier

Entire

Performance

Security

10

.

Any other breach

or non-compliance

with any of the

provision of this

Agreement,

including in case

of the Warranties

being untrue or

misleading or

incorrect in any

manner

whatsoever.

Such

proportion as

may be

determined by

the Nominated

Authority in its

sole discretion.

11

.

Failure of the

Successful Bidder

to submit the

revised

Performance

Entire

Performance

Security.

W.P.(C) 10686/2025 Page 33 of 76

Security in

accordance with

Clause 6.

12

.

Failure to make

payments of

monthly revenue

share for CBM as

per Clause 8.2.3

The amount of

revenue share

due and

payable, along

with a simple

interest of 12%

[twelve] per

cent per annum

starting from

the date on

which such

amount was

due and until

the date of

appropriation

of the

Performance

Security.

13

.

Failure to pay

revenue to the

Government in

case of shortfall in

coal production as

per Clause 16.2.2

The amount of

revenue share

due and

payable, along

with a simple

interest of 12%

[twelve] per

cent per annum

starting from

the date on

which such

amount was

due and until

the date of

appropriation

of the

Performance

Security.

W.P.(C) 10686/2025 Page 34 of 76

6.3.2. Any Appropriation Event resulting in appropriation of the

entire Performance Security shall be a Termination Event for the

purposes of Clause 26 (EFFECTIVE DATE, TERM AND

TERMINATION).

6.3.3. In the event of a part appropriation of the Performance

Security, the Successful Bidder shall be required to: (i) rectify

the Appropriation Event; and (ii) top-up the bank guarantee

constituting the Performance Security within fifteen Business

Days of receipt of a notice under Clause 6.3.1, failure to do so

shall be a Termination Event for the purposes of Clause 26

(EFFECTIVE DATE, TERM AND TERMINATION).

Appropriation Event except as mentioned in Clause 6.2.1 (d)

shall be rectified within seven Business Days of receipt of a

notice under Clause 6.3.1. Appropriation Event mentioned in

Clause 6.2. l (d) shall be rectified within the time specified in

SCHEDULED.

6.3.4. In the event that on account of one or more Appropriation

Events, an amount equal to hundred per cent of the Performance

Security is appropriated in aggregate in one or more instances,

the same shall be a Termination Event for the purposes of Clause

26 (EFFECTIVE DATE, TERM AND TERMINATION).”

iv) Learned ASG has further submitted that Clause 6 of the CMDPA

provided for performance security in the form of an irrevocable and

unconditional guarantee in the format provided in Schedule E of the

contract/CMDPA. Attention of this Court has been drawn towards the

following clauses/conditions of the Bank Guarantee furnished by the

petitioner in favour of the respondent No.1 in terms of CMDPA: -

“1. The Bank for the purpose hereof unconditionally and

irrevocably undertakes to pay to the Nominated Authority

without any demur, reservation, caveat, protest or recourse,

immediately on receipt of first written demand from the

Nominated Authority, a sum or sums (by way of one or more

W.P.(C) 10686/2025 Page 35 of 76

claims) not exceeding in the aggregate the amount of INR

[figures] (Indian Rupees [words]) without the Nominated

Authority needing to prove or to show to the Bank grounds or

reasons for such demand for the sum specified therein and

notwithstanding any dispute or difference between the

Nominated Authority and Successful Bidder on any matter

whatsoever. The Bank undertakes to pay to the Nominated

Authority any money so demanded notwithstanding any dispute

or disputes raised by the Successful Bidder in any suit or

proceeding pending before any court or tribunal relating thereto

the Bank’s liability under th.is present being absolute and

unequivocal.

2. The Bank acknowledges that any such demand by the

Nominated Authority of the amounts payable by the Bank to the

Nominated Authority shall be final, binding and conclusive

evidence in respect of the amounts payable by Successful Bidder

to the Nominated Authority under the Agreement.

3. The Bank hereby waives the necessity for the Nominated

Authority from demanding the aforesaid amount or any part

thereof from the Successful Bidder and also waives any right

that the Bank may have of first requiring the Nominated

Authority to pursue its legal remedies against the Successful

Bidder, before presenting any written demand to the Bank for

payment under this Guarantee.

4. The Bank further unconditionally agrees with the

Nominated Authority that the Nominated Authority shall be at

liberty, without the Bank's consent and without affecting in any

manner the Bank's obligation under this Guarantee, from time to

time to:

(i) vary and/or modify and of the terms and conditions of the

Agreement;

(ii) extend and / or postpone the time for performance of the

obligations of the Successful Bidder under the Agreement, or

(iii) forbear or enforce any of the rights exercisable by the

Nominated Authority against the Successful Bidder under the

terms and conditions of the Agreement.”

W.P.(C) 10686/2025 Page 36 of 76

It is therefore, submitted that the aforesaid bank guarantee

categorically provides that the same is unconditional in nature, with an

undertaking to pay to nominated authority (respondent No.1) without

any demur, reservation, caveat, protest, or recourse immediately upon

receipt of first written demand. Further, that respondent No.1 is not

required to prove or show to the bank any grounds or reasons for such

demand and the existence of any dispute between respondent

No.1/nominated authority and the petitioner on any matter will not be

ground for not honouring the bank guarantee.

v) It is also the case of the respondents that the invocation of bank

guarantee and its encashment cannot be injuncted merely because there

are disputes raised by the petitioner as to the validity of the impugned

order and the demand raised by respondent No.1. It has been argued

that the adjudication of such disputes has no corelation with the

encashment of bank guarantee which is an independent contract in

terms of the bank guarantee issued by the bank. Reliance has been

placed on the judgment of Hon’ble Supreme Court in BSES Ltd. v.

Fenner India Ltd.

7

, to contend that the appropriation of the part-

performance security cannot be deemed to be an irretrievable harm by

any stretch of imagination.

vi) Learned ASG has submitted that SCN-II dated 06.06.2024 was

issued by respondent No.1 for the deviations from achievement of

‘Efficiency Parameters’ noted in MS-3 within stipulated time pertaining

7

(2006) 2 SCC 728

W.P.(C) 10686/2025 Page 37 of 76

to Forest Clearance Stage-II and Environment Clearance to which the

petitioner had submitted a detailed reply on 20.06.2024 and same was

duly considered in a personal hearing given to the petitioner before 24

th

Scrutiny Committee meeting held on 08.08.2024 and 09.08.2024 and

based on the deliberation held, following observations and

recommendations were made by the Committee: -

“Based on the deliberations and the assurance of the Allottee, the

Committee made the following recommendations:-

1. The Allottee will give an undertaking in next 3 days to O/o

NA that they will operationalize the mine before the scheduled

timeline, i.e by 03.06.2025.

2. In the event the operationalization of the mine happens on or

before the due date, the matter will be put up to the Scrutiny

Committee for the final decision on the Show Cause Notice for

MS-3.

3. However, in the event the mine is not operationalized by

03.06.2025, the Committee recommended for imposition of

penalty in the form of appropriation of PBG as per the provision

of CMDPA.”

In view of the aforesaid recommendation made by the Scrutiny

Committee in paragraph 3 thereof, penalty in the form of appropriation

of Performance Bank Guarantee has been imposed for failure in

completion of MS-3 within the scheduled timeline. Learned ASG has

also drawn attention of this Court towards a letter dated 12.08.2024 with

subject ‘Reply to SCN dated 06.06.2024’ sent by petitioner to

respondent No.1/Nominated Authority post the issuance of SCN-II

whereby, the petitioner had given undertaking as per the aforesaid

W.P.(C) 10686/2025 Page 38 of 76

recommendation to operationalise the subject mine before the due date

of 06.06.2025

8

. It is pointed out by learned ASG that in terms of the said

undertaking, the subject mine has still not been operationalised by the

petitioner. It is further the case of the respondents that vide minutes of

24

th

Scrutiny Committee meeting held on 08.08.2024 and 09.08.2024,

petitioner was not given any clean chit and the Scrutiny Committee had

deferred the exercise of its right to appropriate the proportionate

performance security as per CMDPA. It is further submitted that perusal

of the deliberations happened in the said meeting would reveal that the

Committee did not accept the reasons given by the petitioner and it was

recommended that only in the event, if the petitioner was able to

operationalise the mine on or before 03.06.2025, the matter was required

to be put before Scrutiny Committee again for taking decision on SCN-

II. It is further pointed out that post the submission of response to SCN-

II on 20.06.2024, the petitioner gave the above undertaking and

therefore, all the issues pertaining to SCN-II stood subsumed and it is on

account of said undertaking given by the petitioner, respondents did not

impose any penalty at the relevant point in time; however, as the subject

mine was not operationalised till date, the impugned order for part-

appropriation of the Performance Bank Guarantee was passed. It is also

the case of the respondents that the reasons elucidated in representation

dated 23.05.2025 seeking an extension of time to achieve milestones

were already in knowledge of the petitioner when the aforesaid

undertaking was made by it. It is further submitted that the impugned

8

As per 24

th

Scrutiny Committee recommendations, undertaking to operationalize mine was before

03.06.2025; however, date mentioned in this letter is 06.06.2025

W.P.(C) 10686/2025 Page 39 of 76

order has been passed after providing an opportunity of hearing to the

petitioner and under due intimation to it, and thus, the contention of the

petitioner that the impugned order has been passed in violation of

principles of natural justice is incorrect.

vii) Regarding the contention of the petitioner that EC stood vested

in favour of the petitioner on 03.03.2021 from the date of vesting order

itself, learned ASG has drawn attention of this Court towards Annexure-

5 of the Vesting Order dated 03.03.2021 wherein, it has been mentioned

that, “The Successful Bidder does not intend to adopt and continue with

any of the contracts of the Prior Allottee”. It is, therefore, submitted that

the petitioner has itself agreed to not continue with the earlier EC issued

by Central Government on 10.01.2014 to the prior allotee and therefore,

now they cannot contend that respondent No.1 had forced them to obtain

fresh EC arbitrarily as fresh EC has to be obtained as earlier EC was

discontinued.

viii) Regarding the 1

st

Forest Clearance, learned ASG has drawn

attention of this Court towards a letter dated 06.01.2022 whereby,

Central Government had accorded approval for transfer of process of

seeking approval under Forest (Conservation) Act, 1980, to the petitioner

subject to certain conditions which need to be complied prior to handing

over of forest land. It is submitted that said conditions were to be

complied prior to Stage-II approval; however, same have not been

complied with by the allottee/petitioner till date and in view of the same,

W.P.(C) 10686/2025 Page 40 of 76

the Forest Clearance is still pending. The relevant conditions enlisted in

the said letter reads as under: -

“A. Conditions which need to be complied prior to handing over

of forest land by the State Forest Department and compliance is

to be submitted prior to Stage-II approval

1. Compensatory Afforestation:

i. The Compensatory afforestation over equivalent non-forest

land, shall be raised shall be raised by the State Forest Department at

the project cost. At least 1000 saplings per ha shall be planted over

admissible CA land. If this this not possible to plant these many

seedlings in the identified NFL, the balance seedlings will be planted

in degraded forest land as per the prescription of the Working Plan at

the cost of the User Agency. In such cases CA cost will be revised and

duly approved by he competent authority and deposited online in the

CAF managed by the CAMPA;

ii. 25% of the CA cost additionally will be spent towards soil and

moisture conservation activities in the proposed CA area as per site

requirement and deposited in CAF;

iii. The cost of compensatory afforestation at the prevailing wage

rates as per compensatory afforestation scheme and the cost of survey,

demarcation and erection of permanent pillars, if required on the CA

land, shall be deposited in advance with the Forest Department by the

user agency. The CA will be maintained for 10 years. The scheme

may include afforestation of indigenous species with appropriate

provision for anticipated cost increase for works scheduled for

subsequent years;

iv. The non-forest land identified for CA shall be transferred and

mutated in favour of the State Forest Department and subsequently

notified by the State Government as RF under Section - 4 or PF under

Section-29 of the Indian Forest Act, 1927 or under the relevant

Section(s) of the local Forest Act before Stage-II approval. A copy of

the final Notification shall be submitted along with the compliance of

Stage-I approval;

**** **** ****

14. Wildlife Management Plan:

W.P.(C) 10686/2025 Page 41 of 76

i. It is reported that the area comes under elephant zone and human

wildlife conflict area. The elephant habitat may be fragmented due to

Radhikarpur (East) and Radhikapur (West) Coal Blocks on one side

and Railway line traversing the forest area on another side, which

need to be addressed. User Agency should submit a comprehensive

site-specific Wildlife Conservation Plan approved by the Chief

Wildlife Warden encompassing suitable measures to address Wildlife

conservation and Human Wildlife conflicts. Comments of the Project

Elephant Division of the MoEF&CC shall be obtained and addressed

in the said Plan and a copy of approved Plan shall be submitted to the

Ministry along with the compliance of Stage-I approval;

ii. Cost of implementation of the provisions of the Wildlife

Management Plan, on pro rata basis, shall be deposited into the

account of CAMPA of the State;”

ix) Insofar as the issue of mismatch in the Mining Plan (mining

lease area) along with Mine Closure Plan and the issue of revision of

boundary coordinates of the subject mine are concerned, it is submitted

that in terms of the meeting held under the chairmanship of Additional

Secretary and respondent No.1/Nominated Authority on 04.02.2022

(minutes of which were issued on 08.02.2022) regarding boundary of

subject mine, the petitioner/allottee was to submit the proposal for their

request that the bounding coordinate of subject mine should be changed

in a way that no revision in the Mining Plan is required and the same will

not have impact of clearances already vested to them and timelines for

development of coal block. It is further submitted that the petitioner on

09.02.2022 submitted the request proposing that, ‘the Mining Plan

bounding coordinates are kept as it is on three side, i.e., East, South and

West side and if only the north side is extended further North to coincide

with the new bounding coordinate line, it will cover the entire mining

boundary without creating too many changes as per existing approved

W.P.(C) 10686/2025 Page 42 of 76

bounding coordinates and the same will also cover the ORSAC

boundary’ and in view of the same, request was made for needful action.

As per respondents, the change in bounding coordinates was proposed by

the petitioner itself on the touchstone that Odisha Govt. generally

transfers the land as per boundaries decided by ORSAC. It is, therefore,

submitted that the mis-match of boundary coordinate stood resolved in

view of the letter sent by the petitioner on 09.02.2022 as the change in

bounding coordinates as per the specific requirement of the petitioner

(though not mandated under CMDPA or otherwise) would not have any

impact either on the clearances of timelines for development of coal

mines. Learned ASG has submitted that, even otherwise, the concept of

“boundary of a coal mine” is different from “bounding coordinates” and

there is no dispute with respect to the boundary of the coal mine in the

present case and the petitioner, if at all, only wanted a slight change in

the bounding coordinates of the subject mine. Attention of this Court has

been drawn towards the representation dated 23.05.2025 submitted by

the petitioner invoking “force majeure” and further seeking appropriate

orders/directions for extension of timeline for achieving Milestones

under Schedule D of CMDPA, to show that the petitioner has now taken

a stand that it had no clarity on the Mining Boundary Coordinates ever

since the issuance of Vesting Order till 08.02.2022, when they received a

letter from respondent No.1 finally correcting the Bounding Latitude and

Longitude thereby, clarifying that the Bounding Coordinates were to be

revised as per ORSAC without any changes in the mining plan.

W.P.(C) 10686/2025 Page 43 of 76

x) Regarding elephant corridor passage, it is submitted that FAC in

its second meeting on 23.12.2021 had granted Stage-I FC approval

which was recommended on 06.01.2022 with certain conditions as

pointed out hereinabove, which have not been complied by the

petitioner. It is further submitted that the issue of Elephant corridor had

emerged on 17.12.2021, when the file inspection was done by DFO and

the petitioner had ample opportunity from the said date to take

appropriate steps to obtain requisite permits.

xi) It is further submitted that Essential Details Sought (EDS) for

Compensatory Afforestation (CA) were sought from the petitioner on

08.08.2022 and it was requested to comply with the conditions imposed

by MoEF & CC. It is pointed out that the natural growth of Sal trees over

approximately 36 acres of land resulting in a change in the legal nature

and over the extent of government land was observed during the

inspection of site on 14.02.2023; however, by that time EC was already

obtained by the petitioner on 23.01.2023. Therefore, it is submitted that

same cannot be taken into consideration as it was an event which had

occurred post obtaining EC and, the petitioner had ample time and

opportunity to take appropriate steps to ensure timely operationalisation

of the mine. Learned ASG has thus, submitted the failure to

operationalise the mine has occurred due to the petitioner failing to

obtain requisite FC, EC and Land Acquisition and Possession of Land in

a timely manner and the said issues were already in the knowledge of the

petitioner when the aforesaid undertaking to operationalise the subject

mine was given. Attention of this Court has also been drawn towards a

W.P.(C) 10686/2025 Page 44 of 76

letter dated 29.05.2024 sent by petitioner seeking clarification to show

that the issue with respect to the Elephant Corridor and CA were raised

by the petitioner without specifying the impact of the same as to how

they were creating hindrance in obtaining any particular permit from the

concerned department.

xii) Insofar as the dropping of SCN-I dated 08.02.2022 issued for

non-compliance with ‘Efficiency Parameter’ is concerned, it is submitted

that the said SCN was dropped in view of the reply submitted by the

petitioner on 21.02.2022 and the fact that the petitioner had complied

with the requirements of Clause 15 for MS-2 and in view of the same, no

penalty was imposed on the petitioner.

xiii) Learned ASG has submitted that the letter dated 11.07.2025 was

issued by DFO, Angul, for filing of FC application for additional

lookalike forest land to the stage-I approval for subject mine, however,

the same will have no bearing in the present case as EC was obtained on

23.01.2023 against the due date of 03.09.2022 and therefore, the same

cannot now be a ground to assail the impugned order, after a lapse of two

years, which has been passed for non-completion of MS-3 within the

stipulated time period in terms of Schedule D- Efficiency Parameters. It

is further submitted that the said letter has been issued independent of

the impugned appropriation order. It is also the case of the respondents

that this letter cannot come to the aid of the petitioner as they have

W.P.(C) 10686/2025 Page 45 of 76

defaulted in making good of their own undertaking given for

operationalising the subject mine by 03.06.2025

9

.

xiv) It is, thus, prayed that the impugned appropriation order need not

be interfered and the present petition be dismissed.

REJOINDER SUBMISSIONS ON BEHALF OF THE PETITIONER

5. Learned Senior Counsels for the petitioner have made the following

rejoinder submissions: -

i) Firstly, regarding the preliminary issue of maintainability of the

present petition, learned Senior Counsel has submitted that power to

issue prerogative writs under Article 226 of the Constitution is plenary

in nature and is not limited by any other provision of Constitution.

Further, availability of alternative remedy cannot operate as an absolute

bar in cases where the writ petition has been filed for the enforcement

of Fundamental Rights or where there has been a violation of the

principle of natural justice or where the order or proceedings are wholly

without jurisdiction or the vires of an Act is challenged. It is further

submitted that the existence of an adequate or suitable alternative

remedy available to the litigant is merely a factor which the Court

entertaining a petition under Article 226 of the Constitution will

consider for exercising the discretion to issue writ in said jurisdiction;

however, the same does not impinge upon the jurisdiction of the High

9

The date mentioned in the letter dated 12.08.2024 is 06.06.2025

W.P.(C) 10686/2025 Page 46 of 76

Court to deal with the matter itself when it is in position to do so on the

basis of the affidavits filed. Reliance has been placed on the judgments

of Hon’ble Supreme Court in Whirlpool Corpn. v. Registrar of

Trade Marks

10

, S.J.S. Business Enterprises (P) Ltd. v. State of

Bihar

11

, Union of India v. Tantia Construction (P) Ltd.

12

, T.N.

Cements Corpn. Ltd. v. Unicon Engineers

13

, India Glycols Ltd. v.

S.R. Technologies

14

, in support of this contention. Learned Senior

Counsels have drawn attention of this Court towards Section 27(4) of

the CM (SP) Act, 2015, to submit that the jurisdiction of the High

Court is not affected by Section 27 of the said Act and this Court is

entitled to exercise jurisdiction, powers or authority in relation to

matters connected with the Act. It is further submitted that the plea of

alternate efficacious remedy before the learned Tribunal is

misconceived as the said Tribunal is not fully functional, and in fact, no

case is being heard as it has been recently constituted and has not

started fully functioning due to the lack of supporting staff and required

infrastructures. It is further submitted that the said Tribunal has been

established for the purpose of dealing with the cases relating to the land

acquisition issued relating to coal bearing areas and for adjudicating on

the disputes pertaining to land acquisition/compensation and thus,

given the nature of the dispute arising in the present case, the same

cannot be subject to the jurisdiction of the said Tribunal.

10

(1998) 8 SCC 1, particularly on paragraphs 14 & 15 at page 9

11

(2004) 7 SCC 166

12

(2011) 5 SCC 697: (2011) 3 SCC (Civ) 117 at page 708

13

(2025) 4 SCC 1: SCC OnLine SC 127 at page 14

14

(2025) 5 SCC 780

W.P.(C) 10686/2025 Page 47 of 76

ii) It is further submitted that the impugned order is contrary to the

express terms of CMDPA wherein, it has been mentioned that the

Performance Bank Guarantee/security will be appropriated only when

there is failure on the part of the petitioner. It is the case of the

petitioner, based on the facts already pointed out hereinbefore, that

since the delay in obtaining EC for achieving MS-3 is not solely

attributable to the petitioner the appropriation of the bank guarantee by

respondent No.1 is therefore, based on incorrect construction of facts.

Attention of this Court has been drawn towards Clause 6.3 of the

CMDPA which provides for ‘Manner of appropriation of the

performance security’ and it is submitted that conditions mentioned for

the appropriation of the Performance Bank Guarantee are not fulfilled

in the present case.

iii) It is further submitted that as per the impugned order, the

direction for appropriation of the Performance Bank Guarantee was

given for non-completion of MS-3 and particularly, for not obtaining

Environment Clearance within the time limit prescribed in Schedule D

– Efficiency Parameters; however, the computation of due date for MS-

3 by respondent No.1 is wholly arbitrary and based on incorrect

construction of facts/timelines. It is submitted that as per SCN-II dated

06.06.2024, the petitioner was to obtain EC within 18 months from the

completion of previous MS (MS-2) and respondent No.1 has erred in

calculating the due of 03.09.2022 for completion of MS-3 from the date

of vesting order, i.e., 03.03.2021, and the same was not be calculated

from 03.09.2021 as for completion of MS-2, the time limit as per

W.P.(C) 10686/2025 Page 48 of 76

Schedule D was 6 months from the completion of previous MS (MS-1)

or if MS-1 is not applicable, 6 months from the date of allocation.

Therefore, it is pointed out that respondent No.1 has not

considered/added the said period of 6 months while calculating the

completion time for MS-3 and if, 18 months from completion of MS-2

is calculated from 03.09.2021 then, the EC obtained on 23.01.2023 is

well within the stipulated time limit. It is further submitted that

respondent No.1 vide letter dated 18.01.2023 issued to the petitioner, in

view of the recommendation of 18

th

Scrutiny Committee meeting held

on 23.08.2022, had dropped/waived off SCN-I dated 08.02.2022.

Attention of this Court has also been drawn towards SCN-I to show

that respondent No.1 while issuing said SCN for non-compliance with

Efficiency Parameters for MS-2 had calculated the due date as

03.09.2021 and whereas in SCN-II, respondent No.1 had considered

due date as 03.09.2022. In view of the same, it is contended that the

said due date of 03.09.2022 has been incorrectly calculated because as

per Efficiency Parameters, MS-3 was to be completed within 18

months from the completion of MS-2 and the due date for completion

of MS-3 should have been 03.03.2023 and the same was to be 18

months from the due date for completion of MS-2, i.e., 03.09.2021.

Thus, the EC obtained on 23.01.2023 is within the stipulated time as

per Efficiency Parameters.

iv) It is further submitted that as SCN-I was waived off based on

recommendation of 18

th

Scrutiny Committee meeting held on

23.08.2022 and therefore, the said period of delay stood condoned and

W.P.(C) 10686/2025 Page 49 of 76

the same cannot be counted towards calculating due date for

completion time for MS-3. Attention has been drawn towards the

following recommendation of 18

th

Scrutiny Committee meeting held on

23.08.2022: -

“Observation &Recommendation: -

The committee observed that there was delay of only 3 months in

achievement of given milestone and sincere efforts were made by

the Allottee for completion of milestone within given timeline.

The committee also agreed with the explanation given by the

Allottee and concluded that the delay cannot be attributed to them.

The committee recommended that penalty should not be imposed

through appropriation of PBG and Show Cause notice be waived

off.”

In view of the above, it has been contended on behalf of the

petitioner that the aforesaid recommendation confirms that the due date

for MS-3 must be computed from 03.09.2021 after taking into

consideration the aforesaid relaxation given by Scrutiny Committee by

waiving off SCN-I.

v) Learned Senior Counsels have drawn attention of this Court

towards Annexures-3 & 4 of the vesting order dated 03.03.2021 to

show that statutory licences, permits, permissions, approvals or

consents issued by Central Government to prior allottee were to be

transferred on the same terms and conditions to the present petitioner

(successful bidder) on application by the latter which has not been done

and the petitioner had to apply afresh for obtaining EC. It is submitted

that the petitioner had moved an application for transfer of EC on

W.P.(C) 10686/2025 Page 50 of 76

08.04.2021 and further that, respondent No.1 vide Office Memorandum

dated 04.10.2021 had forwarded the request letter of the petitioner for

transfer of EC issued to the prior allotee. It is further submitted that the

petitioner got to know that it has to apply afresh application for grant of

TOR as per provision of EIA Notification, 2006, on 10.01.2022 and

even if, period of 18 months in terms of Efficiency Parameters is

calculated from 10.01.2022 then, also the EC obtained on 23.01.2023 is

well within the stipulated time period.

vi) Learned Senior Counsels have further drawn attention of this

Court towards an order dated 20.06.2025 passed by a Coordinate Bench

of this Court in W.P.(C) 8484/2025 titled as “M/S JSW Cement

Limited v. Union of India & Ors.”, to show that the said petition was

filed by a successful bidder of Marwatola VI Coal Mine and the

Coordinate Bench while issuing notice had also stayed the

appropriation of Bank Guarantee subject to the same being kept alive.

It is the case of the petitioner that the latter stands on a better position

in comparison to the petitioner in the aforesaid petition as there MS-3

was yet to be achieved and Scrutiny Committee therein, had deferred

the imposition of penalty in the form of appropriation of PBG as per

CMDPA till MS-3 is completed; however, in the present case, MS-3

has been completed and the impugned order has been passed based on

incorrect calculation of the due date as pointed out hereinbefore.

vii) Lastly, it is the case of the petitioner that the Tribunal under

Section 27 of the Act is non-functional and therefore, the alternate

W.P.(C) 10686/2025 Page 51 of 76

efficacious remedy could not be effectively exercised by the petitioner.

Attention of this Court has been drawn towards Clause 6.2.2 of the

CMDPA to show that the appropriation of PBG could not have been

sought in case the appropriation event has occurred solely on account

of a ‘Force Majeure’ which could not have been mitigated by the

successful bidder.

viii) It is therefore, submitted that the present petition be allowed and

the respondents be directed to grant extension of milestone deadlines

and to process the applications of the petitioner for grant of statutory

clearances in a time bound manner.

6. During the course of hearing, learned ASG has handed over an order

dated 09.05.2025 passed by learned Tribunal constituted under Coal Bearing

Areas (Acquisition and Development) Act, 1957, established and situated at

Talchar, Odisha, to show that the said Tribunal is functional and the petitioner

can exercise their alternate efficacious remedy before the said Tribunal. It has

further been pointed out that by learned ASG that, during the pendency of the

present petition, respondent No.1 had rejected the representation dated

16.07.2025 filed on behalf of the petitioner requesting a change in “Zero

Date” for the subject mine and, it was observed that all the issues cited by the

petitioner in their representation were already within its knowledge at the time

of vesting order and the same have also been deliberated in various forums

including the Scrutiny Committee and accordingly, the request for change in

“Zero Date” was rejected and the petitioner has been advised to ensure full

compliance with the conditions stipulated in Schedule D-Efficiency

W.P.(C) 10686/2025 Page 52 of 76

Parameters and operationalise the mine in accordance with CMDPA

provisions.

7. Heard learned Senior Counsels for the petitioner as well as learned

ASG for the respondents and perused the records.

ANALYSIS AND FINDINGS

8. For the adjudication of the present petition, following dates and events

are relevant: -

Date Event

11.01.2021 Coal Mine Development and Production Agreement (CMDPA)

was executed between the Petitioner and the President of India

03.03.2021 Respondent No.1 under Rule 7(2)(b) and Rule 13(1) of the Coal

Mines (Special Provisions) Rules, 2014 read with Section

6(3)(b) and Section 8(3) of the Coal Mines (Special Provisions)

Act, 2015, issued a Vesting Order thereby, transferring all

rights, title, interest including the approved mine plan to the

petitioner

05.04.2021 Petitioner submitted the commencement plan for starting coal

mining operations in the subject coal mine in terms of Clause

5.1 of CMDPA

W.P.(C) 10686/2025 Page 53 of 76

08.02.2022 Show Cause Notice (SCN-I) was issued by respondent No.1 for

alleged non-compliance with Efficiency Parameters for delay in

achieving MS-2, i.e., Mining Lease Application. The said SCN-I

issued to the petitioner reads thus: -

W.P.(C) 10686/2025 Page 54 of 76

W.P.(C) 10686/2025 Page 55 of 76

23.08.2022 Scrutiny Committee in its 18

th

meeting accepted the explanation

given by the petitioner and concluded that delay in achievement

of MS-2 cannot be attributed to the petitioner. The committee

recommended that penalty should not be imposed through

appropriation of Performance Bank Guarantee and show cause

notice be waived off. The relevant minutes of meeting of 18

th

Scrutiny Committee reads as under: -

W.P.(C) 10686/2025 Page 56 of 76

06.06.2024 Petitioner received SCN-II for delay in achievement of MS-3,

i.e., Forest Clearance stage-2 and Environment Clearance. SCN-

II reads as under: -

W.P.(C) 10686/2025 Page 57 of 76

W.P.(C) 10686/2025 Page 58 of 76

08.09.2024

&

09.09.2024

Scrutiny Committee in its 24

th

meeting considered the

petitioner’s reply to SCN-II and recommended that the

petitioner will give an undertaking in next three days that the

mine will be operational by 03.06.2025 and in the event of non-

happening of same, recommendation was made for imposition

of penalty in the form of appropriation of Performance Bank

Guarantee as per CMDPA. It was also recommended that if the

mine is operational by 03.06.2025, the matter will be before

screening committee for final decision on SCN-II. The relevant

W.P.(C) 10686/2025 Page 59 of 76

minutes of meeting of 24

th

Scrutiny Committee reads as under: -

W.P.(C) 10686/2025 Page 60 of 76

12.08.2024 Petitioner, in terms of the recommendations of 24

th

Scrutiny

Committee meeting, submitted its undertaking to operationalise

the subject mine before the due date of 03.06.2025. The said

letter of submission of undertaking reads thus: -

W.P.(C) 10686/2025 Page 61 of 76

W.P.(C) 10686/2025 Page 62 of 76

September

2024 to

May 2025

It was stated that the petitioner was in discussion with the local

authorities to seek clarifications regarding the issues pertaining

to FC compliances, Elephant Corridor, Compensatory

Afforestation and for conducting GPS (DGPS) survey

23.05.2025 Petitioner made a representation to respondent No.1 invoking

“force majeure” in terms of Clause 25 of CMDPA and further

seeking appropriate directions for extension of timeline for

achieving milestones under Schedule D-Efficiency Parameters

of CMDPA

20.06.2025 Petitioner was informed by Nominated Authority/respondent

No.1 that an opportunity of personal hearing would be provided

to it on 18.07.2025

11.07.2025 Petitioner submitted a representation before Nominated

Authority/respondent No.1 seeking extension of timeline for

achieving milestones under CMDPA

18.07.2025 Personal hearing was provided to the petitioner by Nominated

Authority/respondent No.1

21.07.2025 Respondent No.1 issued the impugned appropriation order for

invocation of 10% of the Performance Bank Guarantee for non-

completion of MS-3 especially for delay in obtaining

W.P.(C) 10686/2025 Page 63 of 76

Environment Clearance. The relevant portion of the impugned

appropriation order reads thus: -

W.P.(C) 10686/2025 Page 64 of 76

9. At this stage, it is apposite to refer to the principles for grant or refusal

to grant of injunction to restrain enforcement of a bank guarantee. The

Hon’ble Supreme Court in Himadri Chemicals Industries Ltd. v. Coal Tar

Refining Co.

15

, while elucidating the principles for grant or refusal to grant of

injunction to restrain enforcement of a bank guarantee, had observed and held

as under: -

“14. From the discussions made hereinabove relating to the principles for

grant or refusal to grant of injunction to restrain enforcement of a bank

guarantee or a letter of credit, we find that the following principles

should be noted in the matter of injunction to restrain the encashment of

a bank guarantee or a letter of credit:

(i) While dealing with an application for injunction in the course of

commercial dealings, and when an unconditional bank guarantee or

letter of credit is given or accepted, the beneficiary is entitled to realise

such a bank guarantee or a letter of credit in terms thereof irrespective

of any pending disputes relating to the terms of the contract.

(ii) The bank giving such guarantee is bound to honour it as per its

terms irrespective of any dispute raised by its customer.

(iii) The courts should be slow in granting an order of injunction to

restrain the realisation of a bank guarantee or a letter of credit.

(iv) Since a bank guarantee or a letter of credit is an independent and a

separate contract and is absolute in nature, the existence of any dispute

between the parties to the contract is not a ground for issuing an order

of injunction to restrain enforcement of bank guarantees or letters of

credit.

(v) Fraud of an egregious nature which would vitiate the very

foundation of such a bank guarantee or letter of credit and the

beneficiary seeks to take advantage of the situation.

15

(2007) 8 SCC 110

W.P.(C) 10686/2025 Page 65 of 76

(vi) Allowing encashment of an unconditional bank guarantee or a letter

of credit would result in irretrievable harm or injustice to one of the

parties concerned.”

10. The Hon’ble Supreme Court in Standard Chartered Bank v. Heavy

Engineering Corporation Ltd. & Anr.

16

, with respect to encashment of

bank guarantee, has observed and held as under: -

“23. The settled position in law that emerges from the precedents of

this Court is that the bank guarantee is an independent contract between

bank and the beneficiary and the bank is always obliged to honour its

guarantee as long as it is an unconditional and irrevocable one. The

dispute between the beneficiary and the party at whose instance the

bank has given the guarantee is immaterial and is of no consequence.

There are, however, exceptions to this rule when there is a clear case of

fraud, irretrievable injustice or special equities. The Court ordinarily

should not interfere with the invocation or encashment of the bank

guarantee so long as the invocation is in terms of the bank guarantee.

**** **** ****

26. In our considered view, once the demand was made in due

compliance with bank guarantees, it was not open for the appellant

Bank to determine as to whether the invocation of the bank guarantee

was justified so long as the invocation was in terms of the bank

guarantee. The demand once made would oblige the bank to pay under

the terms of the bank guarantee and it is not the case of the appellant

Bank that its defence falls in any of the exception to the rule of case of

fraud, irretrievable injustice and special equities. In absence thereof, it

is not even open for the Court to interfere with the invocation and

encashment of the bank guarantee so long as the invocation was in

terms of the bank guarantee and this is what has been observed by the

Division Bench of the High Court in the impugned judgment [Heavy

Engg. Corpn. Ltd. v. Standard Chartered Bank, 2019 SCC OnLine Cal

16

(2020) 13 SCC 574

W.P.(C) 10686/2025 Page 66 of 76

617 : (2019) 3 Cal LT 133] and that reflected the correct legal

position.”

11. Recently, the Hon’ble Supreme Court in Jindal Steel and Power Ltd.

& Anr. v. Bansal Infra Projects Pvt. Ltd. & Ors.

17

, while emphasising that

bank guarantees serve as the backbone of commercial transactions and same

must be honoured in accordance with their terms, has observed and held as

under: -

“11. We are aware of the established legal principle that the Courts

should refrain from interfering with the invocation of a bank guarantee

except in cases of fraud of an egregious nature or in cases where

allowing encashment would result in irretrievable injustice. This Court

in Hindustan Construction Co. Ltd. v. State of Bihar

5

, emphasized that

bank guarantees serve as the backbone of commercial transactions and

must be honoured in accordance with their terms. The following

paragraphs are pertinent in this regard:

“8. Now, a bank guarantee is the common mode of securing

payment of money in commercial dealings as the beneficiary, under

the guarantee, is entitled to realise the whole of the amount under

that guarantee in terms thereof irrespective of any pending dispute

between the person on whose behalf the guarantee was given and

the beneficiary. In contracts awarded to private individuals by the

Government, which involve huge expenditure, as, for example,

construction contracts, bank guarantees are usually required to be

furnished in favour of the Government to secure payments made to

the contractor as “advance” from time to time during the course of

the contract as also to secure performance of the work entrusted

under the contract. Such guarantees are encashable in terms

thereof on the lapse of the contractor either in the performance of

the work or in paying back to the Government “advance”, the

guarantee is invoked and the amount is recovered from the bank. It

is for this reason that the courts are reluctant in granting an

17

2025 SCC OnLine SC 1041

W.P.(C) 10686/2025 Page 67 of 76

injunction against the invocation of bank guarantee, except in the

case of fraud, which should be an established fraud, or where

irretrievable injury was likely to be caused to the guarantor. This

was the principle laid down by this Court in various decisions.

In U.P. Coop. Federation Ltd. v. Singh Consultants & Engineers (P)

Ltd.

6

, the law laid down in Bolivinter Oil SA v. Chase Manhattan

Bank

7

was approved and it was held that an unconditional bank

guarantee could be invoked in terms thereof by the person in whose

favour the bank guarantee was given and the courts would not

grant any injunction restraining the invocation except in the case of

fraud or irretrievable injury. In Svenska Handelsbanken v. Indian

Charge Chrome

8

, Larsen & Toubro Ltd. v. Maharashtra SEB

9

,

Hindustan Steel Works Construction Ltd. v. G.S. Atwal & Co.

(Engineers) (P) Ltd.

10

, National Thermal Power Corporation

Ltd. v. Flowmore (P) Ltd.

11

, State of Maharashtra v. National

Construction Co.

12

, Hindustan Steel Works Construction

Ltd. v. Tarapore & Co.

13

as also in U.P. State Sugar

Corporation v. Sumac International Ltd.

14

, the same principle has

been laid down and reiterated.

9. What is important, therefore, is that the bank guarantee

should be in unequivocal terms, unconditional and recite that the

amount would be paid without demur or objection and irrespective

of any dispute that might have cropped up or might have been

pending between the beneficiary under the bank guarantee or the

person on whose behalf the guarantee was furnished. The terms of

the bank guarantee are, therefore, extremely material. Since the

bank guarantee represents an independent contract between the

bank and the beneficiary, both the parties would be bound by the

terms thereof. The invocation, therefore, will have to be in

accordance with the terms of the bank guarantee; or else, the

invocation itself would be bad.””

12. In view of the aforesaid principles, it is incumbent on the petitioner to

show that their case falls within any of exceptions, i.e., fraud, irretrievable

injustice, and special equities. The Nominated Authority/respondent No.1 has

passed the impugned appropriation order primarily based on the failure of the

petitioner to operationalise the subject mine by 03.06.2025 in terms of their

W.P.(C) 10686/2025 Page 68 of 76

own undertaking submitted vide letter dated 12.08.2024 in pursuance of the

recommendations of 24

th

Scrutiny Committee meeting held on 08-09.08.2024.

Perusal of the letter dated 12.08.2024, as reproduced hereinbefore, shows that

the petitioner, despite claiming time loss for the reasons beyond its control,

chose to submit the undertaking to operationalise the subject mine before the

due date of 03.06.2025. It is also pertinent to note that the said undertaking

was not given under protest to the recommendations of the 24

th

Scrutiny

Committee meeting nor it is the case of the petitioner that they had taken

recourse to the remedies as permissible in law to assail the recommendations

of the 24

th

Scrutiny Committee meeting. The said recommendations were

given after considering the reply of the petitioner to SCN-II submitted on

06.06.2024 wherein, similar issues were raised which were allegedly

prevailing and were within the knowledge of the petitioner. Perusal of the

deliberations of 24

th

Scrutiny Committee shows that the issues of

discrepancies in boundary coordinates and transfer of EC had been agitated in

response to SCN-II dated 06.06.2024 and it was observed by the Committee

that no request for revision of ‘Zero Date’ was made on behalf of the

petitioner till that day. As already noted, that the said findings of the

Committee were never assailed by the petitioner. Thus, in the considered

opinion of this Court, the case of the petitioner, prima facie, does not fall

within any of the exceptions as noted hereinbefore.

13. It is the case of the petitioner that after submission of the aforesaid

undertaking to operationalise the mine vide letter dated 12.08.2024, petitioner

was in discussion with the local authorities to seek clarifications regarding the

issues pertaining to FC compliances, Elephant Corridor, Compensatory

W.P.(C) 10686/2025 Page 69 of 76

Afforestation and for conducting GPS (DGPS) survey; however, it is pertinent

to note that these issues were well within petitioner’s knowledge at the time

of giving the said undertaking.

14. Even otherwise, this Court is not inclined to exercise its jurisdiction

under Article 226 of the Constitution of India as the petitioner has an alternate

efficacious statutory remedy as provided under Section 27 of the CM (SP)

Act, 2015, which reads as under: -

“27. Dispute settlement and Bar of Jurisdiction of civil courts.––(1)

Any dispute arising out of any action of the Central Government,

nominated authority or Commissioner of payment or designated

custodian, or any dispute between the successful bidder or allottee and

prior allottee arising out of any issue connected with the Act shall be

adjudicated by the Tribunal constituted under the Coal Bearing Areas

(Acquisition and Development) Act, 1957 (20 of 1957).

(2) Where the Central Government is of the opinion that any

dispute arising out of any issue connected with the Act exists or is

apprehended and the dispute should be adjudicated by the Tribunal

referred to in sub-section (1), then, the Central Government may by order

in writing, refer the dispute or any matter appearing to be connected

with, or relevant to, the dispute, to the Tribunal for adjudication.

(3) The Tribunal referred to in sub-section (1) shall, after hearing

the parties to the dispute, make an award in writing within a period of

ninety days from the institution or reference of the dispute.

(4) On and from the commencement of the Act, no court or other

authority, except the Supreme Court and a High Court, shall have, or be

entitled to exercise, any jurisdiction, powers or authority, in relation to

matters connected with the Act.”

W.P.(C) 10686/2025 Page 70 of 76

15. In this regard, it is apposite to refer to a judgment of learned Division

Bench of this Court in Trimula Industries Limited v. Union of India,

Ministry of Coal and Others

18

, wherein, learned Division Bench was

dealing with a challenge to an order passed by learned Coordinate Bench of

this Court whereby, the appellant therein, was directed to approach the

Authority as provided for under Section 27 of the CM (SP) Act, 2015, for

assailing the similar appropriation order issued to the said appellant for non-

compliance with the efficiency parameters. The relevant facts of the aforesaid

judgment are as under: -

“8. The vesting order dated 22nd April, 2015 was, thereafter, issued by

Respondent No. 1 in favour of the Appellant, which indicated that the

Coal Mine allocated to the Appellant does not have forest area. However,

it is the case of the Appellant that vide letter dated 12th March, 2016

issued by the Respondent No. 3, for the first time, it came to light that

land allocated for mining to the Appellant also includes forest land of

around 74 hectares. The Appellant contends that there was no mention of

any forest area in the contents of the summary, which was uploaded on

the website portal of Metal Scrap Trade Corporation Limited (MSTC)

and therefore the Appellant verily believed that it has available a total

mining lease area of 949.87 hectares and this does not include any forest

area. The Appellant contends that non-disclosure of existence of forest

area is a gross misrepresentation by Respondent No. 1.

9. However, disputes arose as a Show Cause Notice (SCN) dated 25th

May, 2023 was issued by the Nominated Authority of Respondent No. 1

to the Appellant for non-compliance with the efficiency parameters.

10. The Nominated Authority of Respondent No. 1 thereafter passed

[first] appropriation order on 02nd August, 2023 and directed

appropriation of amount of Rs. 42,34,29,600/- against the performance

Bank Guarantee for non-compliance of efficiency parameters. This

appropriation order was challenged by the Appellant before the learned

Single Judge in a separate writ petition i.e., WP(C) 10453/2023. The

18

2024 SCC OnLine Del 3350

W.P.(C) 10686/2025 Page 71 of 76

learned Single Judge vide interim order dated 08th August, 2023 stayed

the encashment of bank guarantee primarily in view of the dispute

pertaining to disclosure/non-disclosure of the forest area.

11. Subsequently, vide minutes of the 21st meeting of the Scrutiny

Committee held on 10th January, 2024, the Respondent No. 1

recommended for [further] appropriation of performance Bank Guarantee

to the tune of Rs. 3,93,88,800/-, citing failure of Appellant in

advancement of milestone within given timeline. In pursuance to the said

recommendation, [second] appropriation order dated 06th March, 2024

was issued by the Nominated Authority of Respondent No. 1.

12. The [second] appropriation order dated 06th March, 2024 passed by

the Nominated Authority of Respondent No. 1 was challenged by the

Appellant before the learned Single Judge in the underlying writ petition

i.e., WP(C) 3789 of 2024. This writ petition has been disposed of by the

impugned judgment dated 14th March, 2024 and order dated 02nd April,

2024 with a direction to the Appellant to avail the statutory remedy of

appeal against the second appropriation order.”

In the aforesaid facts, after hearing learned counsel for the parties and

perusing the record, learned Division Bench had observed and held as under: -

“17. The primary contention of the Appellant is that the impugned

judgment dated 14th March, 2024 and impugned order dated 02nd April,

2024 declining to entertain the writ petition are inconsistent, inasmuch

as, the learned Single Judge has entertained W.P. (C) No. 10453/2023

pertaining to the first appropriation order, arising from the same CMDPA

and pertaining to the same performance Bank Guarantee.

18. The Appellant does not dispute the existence of alternate remedy

under Section 27 of the Act of 2015, especially after perusing the

compilation of the orders of the Tribunal filed by Respondent No. 1

during the course of the hearing. It, however, assails the direction to avail

the same on the ground that since the facts in issue are admitted, the

same can be adjudicated in the underlying writ petition.

19. The Supreme Court in Radha Krishan Industries v. State of Himachal

Pradesh

1

summarised the principles with respect to maintainability of a

W.P.(C) 10686/2025 Page 72 of 76

writ petition when the aggrieved person has an effective alternate remedy

in law and held as under:

“27. The principles of law which emerge are that:

27.1. The power under Article 226 of the Constitution to issue writs

can be exercised not only for the enforcement of fundamental

rights, but for any other purpose as well.

27.2. The High Court has the discretion not to entertain a writ

petition. One of the restrictions placed on the power of the High

Court is where an effective alternate remedy is available to the

aggrieved person.

27.3. Exceptions to the rule of alternate remedy arise where : (a)

the writ petition has been filed for the enforcement of a

fundamental right protected by Part III of the Constitution; (b)

there has been a violation of the principles of natural justice; (c)

the order or proceedings are wholly without jurisdiction; or (d) the

vires of a legislation is challenged.

27.4. An alternate remedy by itself does not divest the High Court

of its powers under Article 226 of the Constitution in an

appropriate case though ordinarily, a writ petition should not be

entertained when an efficacious alternate remedy is provided by

law.

27.5. When a right is created by a statute, which itself prescribes

the remedy or procedure for enforcing the right or liability, resort

must be had to that particular statutory remedy before invoking

the discretionary remedy under Article 226 of the Constitution.

This rule of exhaustion of statutory remedies is a rule of policy,

convenience and discretion.

27.6. In cases where there are disputed questions of fact, the High

Court may decide to decline jurisdiction in a writ petition.

However, if the High Court is objectively of the view that the

nature of the controversy requires the exercise of its writ

jurisdiction, such a view would not readily be interfered with.”

(Emphasis supplied)

20. The principle laid down by the Supreme Court in paragraph 27.5

is attracted in the facts of this case and therefore, we find no

infirmity in the impugned judgment directing the Appellant to avail

its statutory remedy of appeal. The issues of fact agitated by the

Appellant including non-declaration of forest land in the NIT are

issues which the Appellate Authority is competent to decide.

W.P.(C) 10686/2025 Page 73 of 76

21. Further, in our opinion, the passing of the interim order dated

08th August 2023 by the learned Single Judge in WP(C) 10453/2023

cannot act as a bar to the Court relegating a party to avail its

statutory remedy of appeal. In fact, the impugned judgment/order is

in consonance with the law laid down by the Supreme Court on this

issue. The compilation of orders shown by Respondents No. 1 and 2

also evidence that the Court has in similar matters consistently

directed the writ petitioner to assail the appellate remedy against the

orders passed by the Nominated Authority.

22. The learned Single Judge vide orders dated 14th March, 2024 and

02nd April, 2024 granted interim protection to the Appellant in the

application of stay by the Appellate Authority and directed the Appellant

herein to approach the Appellate Authority on or before 30th April, 2024.

We, hereby, extend the time for the Appellant to approach the Appellate

Authority till 30th May, 2024 on the same terms and conditions.

23. The Appellant is, however, directed to extend the validity of the Bank

Guarantee for a period of six months, within one week from today.

24. The Appellate Authority is directed to hear and decide the appeal

expeditiously preferably within two months from the first date of

hearing.

25. The contention of the Appellant that the learned Single Judge ought

to have entertained the underlying writ petition as the other writ petition

i.e., W.P. (C) 10453/2023 remains pending, is without any merit. In our

opinion, the Appellant ought to have challenged the first appropriation

order dated 02

nd

August, 2023 also before the Appellate Authority under

Section 27 of the Act of 2015. We, therefore, direct the Registry to list

W.P. (C) 10453/2023 before the learned Single Judge on 08

th

May, 2024

for directions. The parties are directed to remain present before the

learned Single Judge on the said date.”

(emphasis supplied)

16. The aforesaid judgment passed by learned Division Bench of this

Court in similar factual context is in relation to availability of statutory

W.P.(C) 10686/2025 Page 74 of 76

remedy under Section 27 of CM (SP) Act, 2015, and is binding on this Court.

The issues raised by the petitioner in the present case have been disputed by

the respondents. The contentions raised by the petitioner pertains to disputed

questions of fact in respect of provisions of CMPDA over which learned

Tribunal established under Section 27 of the CM (SP) Act, 2015, has

jurisdiction/authority to adjudicate upon. Even otherwise, said disputed facts

cannot be decided by this Court in the present jurisdiction.

17. Reliance has been placed by learned Senior Counsels for the petitioner

on Whirlpool Corpn. v. Registrar of Trade Marks

19

, S.J.S. Business

Enterprises (P) Ltd. v. State of Bihar

20

, Union of India v. Tantia

Construction (P) Ltd.

21

, T.N. Cements Corpn. Ltd. v. Unicon Engineers

22

,

India Glycols Ltd. v. S.R. Technologies

23

, to contend that the existence of

an adequate or suitable alternative remedy available to the litigant is merely a

factor which the Court entertaining a petition under Article 226 of the

Constitution will consider for exercising the discretion to issue writ in said

jurisdiction; however, the same does not impinge upon the jurisdiction of the

High Court to deal with the matter itself when it is in position to do so on the

basis of the affidavits filed. The aforesaid legal position is not disputed;

however, the present case is squarely covered by the decision of learned

Division Bench in Trimula Industries Limited (supra).

19

(1998) 8 SCC 1, particularly on paragraphs 14 & 15 at page 9

20

(2004) 7 SCC 166

21

(2011) 5 SCC 697: (2011) 3 SCC (Civ) 117 at page 708

22

(2025) 4 SCC 1: SCC OnLine SC 127 at page 14

23

(2025) 5 SCC 780

W.P.(C) 10686/2025 Page 75 of 76

18. Similarly, reliance placed by learned Senior Counsels for the petitioner

on order dated 20.06.2025 passed by Coordinate Bench in W.P.(C) 8484/2025

titled as “M/s JSW Cement Limited v. Union of India & Ors.” will not

benefit the petitioner, in view of the aforesaid judgment of the learned

Division Bench of this Court in Trimula Industries Limited (supra) which

pertains to Section 27 of the CM (SP) Act, 2015, and is binding on this Court.

19. In view of the aforesaid discussion and in facts and circumstances of

the present case, the present petition is disposed of with liberty to the

petitioner to avail its alternate efficacious remedy in accordance with Section

27 of the CM (SP) Act, 2015, before the concerned learned Tribunal situated

at Talchar, Odisha, within a period of 10 days from today.

20. It is further directed, till that time, interim order dated 23.07.2025

passed by this Court directing maintenance of status quo with respect to

Performance Bank Guarantee No. 1637622BG0000209 dated 15.06.2022

(amended on 25.09.2025) shall continue to operate. It is clarified that this

extension of interim order is for ten days or till the time the petitioner

approaches learned Tribunal under the aforesaid provision, whichever is

earlier. It is further directed that the Bank Guarantee should be kept alive.

21. Needless to state that, nothing stated hereinabove, should be construed

as an expression of opinion (prima facie or otherwise) as to the merits of the

dispute. All rights and contentions of the parties are reserved.

22. Pending applications, if any, also stand disposed of accordingly.

W.P.(C) 10686/2025 Page 76 of 76

23. Judgment be uploaded on the website of this Court, forthwith.

AMIT SHARMA

(JUDGE)

DECEMBER 02, 2025/bsr/ns

Reference cases

Description

Legal Notes

Add a Note....