As per case facts, the Petitioner imported goods declared as "Bitumen," which were later identified as "Used Oil," a restricted item. The goods were seized, and adjudication proceedings commenced, which ...
W.P.(C) 7004/2026 Page 1 of 20
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 16.09.2026
Judgment pronounced on: 28.09.2026
Judgment uploaded on: 28.09.2026
# CNR No. DLHC010229892026
+ W.P.(C) 7004/2026 and CM APPL. 34395/2026
VISHAL OIL AND LUBRICANTS CO. .....Petitioner
Through: Mr. Rohit Kapur, Adv.
versus
THE COMMISSIONER OF CUSTOMS (IMPORT)
.....Respondent
Through: Mr. Piyush Beriwal, Ms.
Ruchita Srivastava, Mr. Sparsh
Jain, Advs.
CORAM:
HON'BLE MR. JUSTICE ANIL KSHETARPAL
HON'BLE MS. JUSTICE SHAIL JAIN
J U D G M E N T
ANIL KSHETARPAL , J.:
1. Through the present Petition, the Petitioner seeks a direction to
the Respondent to waive the interest/late charges reflected in the
Customs EDI System in respect of the aforesaid Bill of Entry.
2. The issue which arises for consideration in the present Petition
is whether the Petitioner can be saddled with the entire amount of
interest reflected in the Customs EDI System in respect of Bill of
Entry No. 9174780 dated 08.05.2015, including the period during
which the imported goods remained seized and the proceedings
W.P.(C) 7004/2026 Page 2 of 20
arising out of the Show Cause Notice dated 15.09.2015 remained
pending before the Customs authorities for nearly eight (08) long
years.
FACTUAL MATRIX :
3. In order to appreciate the controversy involved in the present
Petition, the relevant facts, in brief, are required to be noticed.
4. The Petitioner is a proprietorship concern of Mr. Dalip Singh
Rathore and is stated to be engaged in the business of import and sale
of petroleum products. On 08.05.2015, the Petitioner filed Bill of
Entry No. 9174780 at Inland Container Depot, Tughlakabad, New
Delhi, through its Customs Broker, declaring the imported goods as
“Bitumen” falling under Customs Tariff Heading 27132000. The
declared value of the goods was Rs.36,73,758/-.
5. The Bill of Entry was assessed on 08/09.05.2015 and customs
duty of Rs.9,22,210/- was assessed thereon. The consignment,
however, was put on hold by the SIIB (Import), ICD Tughlakabad for
physical examination. Upon examination conducted on 13.05.2015
and 14.05.2015, it was found that out of the 90 drums declared, 80
drums contained a black-coloured substance whereas 10 drums were
empty. Representative samples were drawn and forwarded to the
Central Revenue Control Laboratory, Pusa, New Delhi [„CRCL‟] for
examination.
6. The CRCL, vide test report dated 02.06.2015, reported the
samples to be “Used Oil” and not “Bitumen”. On the basis of the said
W.P.(C) 7004/2026 Page 3 of 20
report, the Customs authorities took the view that the imported goods
were “Used Oil” falling under Customs Tariff Heading 27101990 and
treated the same as a restricted item requiring the requisite
permissions/licence. The goods were consequently seized on
05.06.2015 under Section 110 of the Act.
7. Thereafter, the Petitioner was issued a summons under Section
108 of the Act and its statement was recorded on 06.07.2015.
According to the Petitioner, it had placed an order for “Bitumen” and
the goods described as “Used Oil” had been supplied by the overseas
supplier by mistake. The Petitioner also claims to have produced a
written communication from the overseas supplier acknowledging the
mistake.
8. On 19.08.2015, the Petitioner addressed a communication to the
Customs authorities seeking waiver of the Show Cause Notice and
early adjudication of the matter. Notwithstanding the said request, a
Show Cause Notice dated 15.09.2015 was issued by the Joint
Commissioner of Customs, proposing, inter alia, confiscation of the
goods under Section 111 of the Act and imposition of penalties under
Sections 112, 114A and 114AA of the Act.
9. The Petitioner submitted its written reply to the Show Cause
Notice on 01.10.2015. The Petitioner disputed the allegation that the
“Used Oil” was a restricted or prohibited item and contended that the
goods were not hazardous waste. A personal hearing was thereafter
afforded on 08.12.2015, which was attended by the Petitioner's
counsel. The Petitioner states that, during the hearing, a request was
W.P.(C) 7004/2026 Page 4 of 20
again made for early adjudication.
10. No adjudication order was passed thereafter for a considerable
period. A further opportunity of personal hearing was afforded on
27.10.2016 by the succeeding adjudicating officer. The Petitioner did
not appear on the said date but, by a communication dated 27.10.2016,
informed the adjudicating authority that it had already submitted its
written reply and had availed the opportunity of personal hearing and,
therefore, did not wish to have any further personal hearing. The
Petitioner again requested that the matter be adjudicated
expeditiously, particularly as the consignment was lying uncleared.
11. The matter ultimately came up before the Additional
Commissioner of Customs, ACE, New Delhi, who afforded another
personal hearing on 31.01.2023. The Petitioner‟s representative
appeared at the hearing and reiterated the earlier submissions and
requested that the Show Cause Notice be adjudicated without any
further delay.
12. On 28.02.2023, the Additional Commissioner of Customs
passed Order-in-Original No. 11/SK/ADC/ACE/2023. The
adjudicating authority directed amendment of the description and
classification in Bill of Entry No. 9174780 from “Bitumen” falling
under CTH 27132000 to “Used Oil” falling under CTH 27101990.
The adjudicating authority further recorded that the “Used Oil” was
non-hazardous and held that no additional duty over and above the
duty already determined was payable. The declared transaction value
of Rs.36,73,758/- was accepted and the customs duty liability of
W.P.(C) 7004/2026 Page 5 of 20
Rs.9,22,210/- was confirmed, which, according to the order, had
already been paid and was accordingly appropriated.
13. The Order-in-Original further held the goods liable to
confiscation under Sections 111(l) and 111(m) of the Act. However,
an option was granted to the Petitioner to redeem the goods on
payment of redemption fine of Rs.1,83,000/- under Section 125 of the
Act. A penalty of Rs.5,000/- was imposed upon the Petitioner under
Section 112(a)(ii) of the Act and a further penalty of Rs.1,83,000/-
was imposed under Section 114AA of the Act. The proposed penalty
under Section 114A of the Act was dropped.
14. The Order-in-Original also records that the “Used Oil” was
non-hazardous and notices that similar non-hazardous used oil had
been cleared from Nhava Sheva Port. The adjudicating authority
accepted the declared transaction value and recorded that no
additional duty, over and above the duty already determined, was
payable. The order, thus, culminated the adjudication proceedings
arising out of the Show Cause Notice dated 15.09.2015.
15. It is not in dispute that the Bill of Entry was thereafter amended
and re-assessed on 29.08.2023 pursuant to the aforesaid Order-in-
Original. The description and classification of the goods were
accordingly changed from “Bitumen” to “Used Oil” and from CTH
27132000 to CTH 27101990.
16. According to the Petitioner, upon seeking clearance of the
goods pursuant to the adjudication order and the consequential re-
assessment, the Petitioner was required to deal with an amount
W.P.(C) 7004/2026 Page 6 of 20
described in the Customs EDI System as “interest charges”. The
Petitioner states that the amount reflected as interest was
approximately Rs.11,74,806/- on 16.11.2023. The Petitioner thereafter
made representations to the Customs authorities seeking removal of
the said interest liability.
17. The Petitioner states that the amount reflected as interest
continued to increase and was shown as Rs.12,10,874/- on 22.02.2024
and Rs.13,61,713/- on 28.03.2026. According to the Petitioner, the
amount had increased further to Rs.15,21,645/- as on 01.05.2026. The
Petitioner claims to have addressed representations dated 16.11.2023,
26.03.2025, 02.04.2025, 11.04.2025, 02.05.2025, 19.05.2025,
03.12.2025 and 28.03.2026 requesting that the said interest be
removed. No effective response was received, leading to the filing of
the present Petition.
CONTENTIONS OF THE PARTIES :
18. Contentions on behalf of the Petitioner:
18.1. It was submitted that the Petitioner cannot be made liable for
interest for the period during which the Bill of Entry could not be
finally processed on account of the seizure of the goods and the
pendency of adjudication proceedings before the Customs authorities.
It was submitted that the Bill of Entry was presented on 08.05.2015
and there is no allegation that the Bill of Entry itself was presented
belatedly.
18.2. It was further submitted that the Petitioner had continuously
W.P.(C) 7004/2026 Page 7 of 20
sought adjudication of the proceedings. The Petitioner had filed its
reply to the Show Cause Notice on 01.10.2015, appeared through
counsel at the personal hearing on 08.12.2015, and thereafter, by
communication dated 27.10.2016, specifically requested that the
matter be adjudicated expeditiously. Even when the matter was taken
up in 2023, the Petitioner appeared and again requested adjudication.
Thus, according to the Petitioner, the prolonged pendency of the
proceedings cannot be attributed to it.
18.3. It was further submitted that the provisions relating to late
presentation of a Bill of Entry under Section 46(3) of the Act have no
application to the present case. The Bill of Entry was admittedly
presented on 08.05.2015, shortly after the arrival of the goods, and
there is no case of the Respondent that the amount reflected in the EDI
System represents a charge for delayed presentation of the Bill of
Entry.
18.4. Reliance was placed upon the decisions of this Court in Swatch
Group India Pvt. Ltd. v. Union of India & Ors.
1
and Gala
International Pvt. Ltd. v. Additional Director General, Directorate of
Revenue Intelligence, Delhi & Ors.
2
, to contend that statutory
proceedings cannot be kept pending indefinitely and that departmental
delay cannot be permitted to operate to the prejudice of the importer.
18.5. It was submitted that the adjudication proceedings remained
pending from September, 2015 until February, 2023, i.e. for more than
seven (07) years. During this entire period, according to the Petitioner,
1
2023 SCC OnLine Del 4938
2
2023 SCC OnLine Del 6073
W.P.(C) 7004/2026 Page 8 of 20
the goods remained under the control of the Customs authorities and
the Petitioner had no occasion to obtain final clearance of the goods. It
was, therefore, contended that the Department cannot now seek to
recover interest calculated by treating the liability as having remained
outstanding from the original assessment in May, 2015.
18.6. It was further submitted that the Order-in-Original itself did not
sustain the Department‟s original apprehension in its entirety. The
adjudicating authority ultimately recorded that the imported “Used
Oil” was non-hazardous, accepted the declared transaction value and
held that no additional duty over and above the duty already
determined was payable. It was submitted that the Petitioner should
not be burdened with an interest liability for the prolonged period
during which the Department itself was seized of the matter.
19. Contentions on behalf of the Respondent:
19.1. Per contra, it was submitted that the present Petition is
misconceived. It was contended that the Petitioner has an efficacious
statutory appellate remedy against the Order-in-Original and that the
present Petition under Article 226 of the Constitution ought not to be
entertained
19.2. It was submitted that the Petitioner accepted the Order-in-
Original and exercised the option for redemption of the confiscated
goods. Having accepted the order and sought redemption, the
Petitioner cannot now dispute the statutory consequences flowing
from the said order.
W.P.(C) 7004/2026 Page 9 of 20
19.3. It was submitted that the amount reflected in the EDI System is
not a charge for delayed presentation of the Bill of Entry under
Section 46(3) of the Act. The Bill of Entry was indeed presented in
2015, but the goods were subsequently found to have been
misdeclared. The confiscation proceedings culminated in an order
permitting redemption under Section 125 of the Act and,
consequently, the Petitioner became liable to pay the duty and other
charges payable in respect of the goods.
19.4. Reliance was placed upon the judgment of the Supreme Court
in M/s Navayuga Engineering Co. Ltd. v. Union of India & Anr.
3
, to
submit that once confiscated goods are redeemed upon payment of
fine under Section 125 of the Act, the owner is liable to pay the duty
and charges payable in respect of the goods and the consequential
statutory interest on delayed payment of duty.
19.5. It was further submitted that the EDI System does not create the
liability but merely reflects the statutory liability arising under the
Act. According to the Respondent, the fact that the adjudication
proceedings remained pending for some time cannot, by itself,
extinguish a statutory liability. It was also submitted that the Petitioner
cannot rely upon alleged financial hardship, detention charges or
demurrage to seek waiver of statutory interest.
ANALYSIS & FINDINGS:
20. This Court has carefully considered the submissions advanced
on behalf of the parties and perused the material on record.
3
2024 INSC 547
W.P.(C) 7004/2026 Page 10 of 20
21. At the outset, it is necessary to delineate the precise controversy
which arises for consideration. The Petitioner has described the
amount reflected in the Customs EDI System as “interest charges” and
seeks waiver thereof. The Respondent, however, does not contend that
the said amount represents any charge on account of delayed
presentation of the Bill of Entry under Section 46(3) of the Customs
Act, 1962 [„the Act‟]. The Respondent‟s case is that the liability arises
as a consequence of the confiscation proceedings and the subsequent
redemption of the goods under Section 125 of the Act.
22. Thus, the question of delayed presentation of the Bill of Entry
under Section 46(3) of the Act is not really in issue. The Bill of Entry
was filed on 08.05.2015. There is no allegation that the Petitioner had
failed to present the Bill of Entry within the prescribed period. The
interest reflected in the EDI System is sought to be justified on an
entirely different basis.
23. The Respondent principally relies upon Section 125 of the Act
and the judgment of the Supreme Court in Navayuga Engineering
(supra). In the said case, the Supreme Court considered the liability to
pay customs duty in respect of goods which had been confiscated but
were subsequently redeemed upon payment of fine under Section 125
of the Act. The Supreme Court held that the owner of the goods
remains liable to pay customs duty even after redemption. At the same
time, the Supreme Court drew a distinction between the occasion on
which the liability under Section 125(2) arises and the statutory
machinery by which the duty liability is assessed and determined. The
Court held that, in confiscation proceedings, the obligation to pay duty
W.P.(C) 7004/2026 Page 11 of 20
and other charges under Section 125(2) arises when the owner
exercises the option to redeem the goods and the Department accepts
the same. The duty liability arising under Section 125(2) is thereafter
required to be assessed under Section 28. The Supreme Court further
held that once Section 28 applies for determination of the duty
liability, the statutory liability towards interest on delayed payment of
duty is attracted.
24. The aforesaid decision, therefore, makes two aspects clear.
First, the liability under Section 125(2) is a consequence of the
confiscation and redemption proceedings and is distinct from the
original assessment of the Bill of Entry. Second, once the liability is
required to be determined through the machinery of Section 28, the
statutory interest provision would follow in accordance with law.
25. Applying the aforesaid principle to the facts of the present case,
it is important to notice the chronology. The Bill of Entry was filed on
08.05.2015 and was initially assessed on the basis of the declaration
made by the Petitioner that the goods imported were “Bitumen”. The
goods were thereafter examined, found to be “Used Oil”, seized on
05.06.2015 and made the subject matter of confiscation proceedings.
26. The Show Cause Notice was issued on 15.09.2015. The
Petitioner submitted its reply on 01.10.2015 and a personal hearing
was afforded on 08.12.2015. Thereafter, although another hearing was
fixed on 27.10.2016, the proceedings were not brought to conclusion.
The matter was ultimately taken up by the Additional Commissioner
of Customs only in January, 2023 and the Order-in-Original came to
W.P.(C) 7004/2026 Page 12 of 20
be passed on 28.02.2023.
27. Thus, the proceedings arising out of the Show Cause Notice
dated 15.09.2015 remained pending for more than seven (07) years
before the liability arising from the confiscation proceedings was
finally determined by the adjudicating authority.
28. The significance of the date of determination cannot be
overlooked. Prior to the adjudication of the Show Cause Notice, the
Petitioner was faced with proceedings in which the very nature,
description and classification of the imported goods were in dispute.
The goods had been seized and were not available to the Petitioner for
clearance. The question whether the goods were liable to confiscation
and, if so, whether they could be redeemed upon payment of fine, was
itself yet to be adjudicated.
29. It was only by the Order-in-Original dated 28.02.2023 that the
adjudicating authority determined the consequences of the
confiscation proceedings. The authority directed amendment of the
description and classification of the goods from “Bitumen” under
CTH 27132000 to “Used Oil” under CTH 27101990; confirmed the
customs duty liability of Rs.9,22,210/-; recorded that the said duty had
already been paid and appropriated; imposed redemption fine of
Rs.1,83,000/-; and imposed penalties of Rs.5,000/- under Section
112(a)(ii) and Rs.1,83,000/- under Section 114AA of the Act.
30. The Order-in-Original further recorded that the “Used Oil” was
non-hazardous and that no additional duty over and above the duty
already determined was payable. Consequently, it is only upon the
W.P.(C) 7004/2026 Page 13 of 20
passing of the Order-in-Original dated 28.02.2023 that the
consequences flowing from the confiscation proceedings stood
determined.
31. In these circumstances, the Respondent cannot, in this Court‟s
view, proceed on the basis that the statutory interest liability arising
from the redemption proceedings commenced from the date of the
original assessment of the Bill of Entry in May, 2015.
32. The original assessment in May, 2015 was an assessment based
upon the declaration of the goods as “Bitumen”. That assessment was
followed almost immediately by physical examination, seizure and
initiation of confiscation proceedings. The subsequent adjudication
altered the description and classification of the goods and determined
the consequences of the confiscation proceedings. The liability arising
from such proceedings, therefore, cannot be retrospectively treated as
having remained payable from the date of the original assessment
merely for the purpose of calculating interest.
33. The judgment in Navayuga Engineering (supra) supports this
distinction. The Supreme Court has specifically held that the
obligation to pay duty and charges under Section 125(2) arises in the
context of the exercise and acceptance of the redemption option, while
the assessment and determination of the duty liability is undertaken
through the machinery provided under Section 28. It is upon such
determination that the statutory interest provision becomes attracted.
34. In the present case, the amount/liability arising from the
adjudication proceedings was determined by the Order-in-Original
W.P.(C) 7004/2026 Page 14 of 20
dated 28.02.2023. Therefore, the period prior thereto, during which
the confiscation proceedings themselves remained pending and the
amount payable pursuant thereto had not been finally determined,
cannot be treated as a period of delayed payment of the amount
determined under the said proceedings.
35. This Court is conscious that the original Bill of Entry did
contain an assessment of customs duty of Rs.9,22,210/-. However, the
Respondent itself does not contend that the present interest demand is
merely interest on an unpaid amount arising from that original
assessment. Its case is founded upon the liability consequential to
confiscation and redemption under Section 125. Once the Respondent
chooses to sustain the interest demand on that basis, the date on which
the liability arising from the confiscation proceedings was determined
assumes significance.
36. There is yet another circumstance which supports the aforesaid
conclusion. The record demonstrates that the Petitioner did not remain
inactive during the pendency of the adjudication proceedings. The
Petitioner filed its reply to the Show Cause Notice, appeared through
counsel at the hearing held on 08.12.2015 and, thereafter, by
communication dated 27.10.2016, specifically informed the
adjudicating authority that it did not seek any further personal hearing
and requested that the matter be adjudicated expeditiously. The
Petitioner again appeared before the adjudicating authority on
31.01.2023 and requested that the proceedings be concluded.
37. This Court is not holding that departmental delay, by itself,
W.P.(C) 7004/2026 Page 15 of 20
extinguishes a statutory liability to pay interest. Such a proposition
would not be consistent with the statutory scheme or the judgment of
the Supreme Court in Navayuga Engineering (supra). What is being
held is narrower: “interest cannot be calculated for a period during
which the liability sought to be subjected to interest had itself not been
determined”.
38. The distinction is material. If an amount has been determined
and has thereafter remained unpaid, the statutory consequences of
delayed payment may follow in accordance with law. However, where
the amount itself is determined only upon culmination of the
confiscation proceedings, the period anterior to such determination
cannot automatically be treated as a period of delayed payment of that
subsequently determined liability.
39. The Respondent has relied upon the finality of the Order-in-
Original and the Petitioner‟s exercise of the option of redemption.
There is no dispute that the Petitioner has not challenged the Order-in-
Original dated 28.02.2023 in the present proceedings. This Court is
also not examining the correctness of the findings relating to
classification, confiscation, redemption fine or penalty. Those aspects
have attained finality and shall remain undisturbed.
40. However, acceptance of the Order-in-Original cannot mean that
every amount subsequently reflected in the EDI System is immune
from examination by this Court. The present Petition does not seek to
reopen the adjudication order. The limited grievance is as to the period
for which the consequential interest has been computed.
W.P.(C) 7004/2026 Page 16 of 20
41. The Respondent has also submitted that the EDI System merely
reflects the statutory liability and does not itself create such liability.
There can be no quarrel with the proposition. The EDI System cannot
create a liability which is otherwise not authorised by the Act.
Conversely, an amount which is statutorily payable cannot be avoided
merely because it is reflected in the EDI System. The question,
therefore, is one of correct computation in accordance with the
statutory provisions.
42. In this regard, the amount reflected in the EDI System, as stated
by the Petitioner, had reached Rs.11,74,806/- on 16.11.2023 and
continued to increase thereafter. The fact that the amount continued to
increase is itself indicative of the computation being made by
reference to an earlier date. If the computation has proceeded from the
original assessment in May, 2015, the same would necessarily require
correction in view of the legal position discussed hereinabove.
43. This Court, therefore, holds that the Respondent was not
justified in computing the interest liability arising from the
confiscation and redemption proceedings from the date of the original
assessment in May, 2015. The period prior to 28.02.2023, the date of
determination of the amount pursuant to the adjudication proceedings
cannot be subjected to interest on the premise that the amount
determined under the Order-in-Original was in delayed payment from
May, 2015.
44. At the same time, the Petitioner cannot be granted a blanket
waiver of interest for the period subsequent to determination of the
W.P.(C) 7004/2026 Page 17 of 20
liability. Once the amount became determined pursuant to the Order-
in-Original dated 28.02.2023 and became subject to the statutory
consequences applicable to delayed payment, the liability, if otherwise
attracted under the Act, would have to be worked out in accordance
with law.
45. The precise amount payable, therefore, requires recalculation by
the Respondent. Such recalculation shall commence from the date on
which the amount was determined pursuant to the Order-in-Original
dated 28.02.2023 and shall be made in accordance with the applicable
statutory provisions governing interest. The Respondent shall also
take into account the subsequent re-assessment of the Bill of Entry on
29.08.2023 and all payments or appropriations already made.
46. In particular, the Respondent shall not compute interest for the
period from 08/09.05.2015 till 28.02.2023 merely on the ground that
the original Bill of Entry had been assessed in May, 2015. The
interest, if otherwise payable, shall be determined with reference to
the liability as determined in the adjudication proceedings and the
statutory provisions applicable thereto.
47. This Court also deems it appropriate to clarify that the reference
to the Order-in-Original dated 28.02.2023 as the date of determination
is confined to the liability arising from the confiscation proceedings
which is the subject matter of the present dispute. This Court is not
expressing any opinion on any independent statutory liability which
may otherwise arise under the Act on account of a separate and legally
recognised default.
W.P.(C) 7004/2026 Page 18 of 20
48. The reliance placed by the Petitioner on the decisions in Swatch
Group India (supra) and Gala International (supra) is therefore not
required to be examined for the purpose of granting a complete
waiver. The relief which follows in the present case flows principally
from the statutory scheme of Sections 125 and 28 of the Act, as
explained by the Supreme Court in Navayuga Engineering (supra).
49. The contention regarding availability of an alternate statutory
remedy also does not warrant dismissal of the present Petition. The
Petitioner is not seeking, in these proceedings, adjudication of the
correctness of the confiscation, classification or penalties imposed
under the Order-in-Original. The limited question concerns the
computation of consequential interest and, in particular, the period
from which such interest can validly be computed. Since the material
facts are undisputed and the issue turns upon the application of the
statutory scheme to the admitted chronology, the present Petition can
be disposed of by issuing a limited direction for recomputation.
50. Accordingly, the challenge to the entire interest liability cannot
be accepted. However, the computation of interest for the period prior
to determination of the amount pursuant to the Order-in-Original
dated 28.02.2023 cannot be sustained.
CONCLUSION:
51. In view of the aforesaid discussion, the present Petition is partly
allowed in the following terms:
i. The Respondent shall recompute the interest liability in respect
W.P.(C) 7004/2026 Page 19 of 20
of Bill of Entry No. 9174780 dated 08.05.2015 in accordance with the
observations made in Paragraph 43 herein, the Customs Act, 1962 and
the applicable statutory provisions;
ii. while undertaking the aforesaid computation, the Respondent
shall exclude the period from the date of the original assessment in
May, 2015 up to 28.02.2023, being the date on which the liability
arising from the adjudication proceedings was determined by the
Order-in-Original;
iii. the Respondent shall, thereafter, determine the interest, if any,
payable for the period subsequent to 28.02.2023 strictly in accordance
with the applicable statutory provisions and the liability determined
under the Order-in-Original;
iv. the Respondent shall take into account the subsequent re-
assessment of the Bill of Entry on 29.08.2023 and shall give due credit
for all amounts already paid or appropriated towards customs duty,
redemption fine and penalties;
v. the Respondent shall issue a fresh computation to the Petitioner
within four (04) weeks from the date of receipt of a copy of this
judgment; and
vi. upon receipt of the fresh computation, the Petitioner shall be
liable to discharge the amount, if any, found payable in accordance
with law.
52. The computation of interest reflected in the Customs EDI
System, to the extent that it proceeds by treating the period prior to
W.P.(C) 7004/2026 Page 20 of 20
28.02.2023 as a period of delayed payment of the liability determined
in the confiscation proceedings, is accordingly set aside.
53. It is clarified that this Court has not interfered with or expressed
any opinion upon the findings contained in Order-in-Original No.
11/SK/ADC/ACE/2023 dated 28.02.2023 relating to the description or
classification of the goods, confiscation, redemption fine, penalty or
any other finding contained therein. The said order shall remain
undisturbed.
54. The Petitioner shall, however, be entitled to the benefit of the
fresh computation in terms of this judgment and shall be liable to pay
only such amount as may be found payable after undertaking the
aforesaid exercise.
55. The Petition, along with the pending application, is disposed of
in the aforesaid terms.
ANIL KSHETARPAL , J.
SHAIL JAIN, J.
SEPTEMBER 28, 2026
jai/pal
Legal Notes
Add a Note....