As per case facts, petitioners challenged land acquisition for National Highway No.50, alleging defective initiation due to improper description of the acquired land, particularly a portion of Gut No. 897. ...
wp-4786-2018.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 4786 OF 2018
Chandrabhan Sukdev Sangle and Others … Petitioners
vs.
The Competent Authority @ Dy. Collector
(Acquisition) Irrigation No.1, Nashik and Others… Respondents
Mr. Pramod Joshi a/w. Mr. Pratik Rahade, for petitioners.
Mr. O.A. Chandurkar a/w. Ms. M.S. Bane, AGP for the Respondent
Nos. 1, 4 and 7.
Mr. Rakesh Singh i/b. M.V. Kini & Co., for Respondent No. 2 -NHAI.
CORAM : MANISH PITALE &
SHREERAM V. SHIRSAT, JJ
RESERVED : 23
rd
MARCH, 2026
PRONOUNCED : 5
th
MAY, 2026
----------------
JUDGMENT (Per Manish Pitale, J.)
1. The petitioners approached this Court by filing this Writ
Petition, being aggrieved by the manner in which acquisition of their
lands was initiated in Gut No. 897 of village Pangarwadi (Shivar), Tal.
Sinnar, Dist. Nashik. The acquisition process culminated in the award
dated 25
th
November, 2011, but, in this Writ Petition filed in February,
2017, the petitioners claimed that the initiation of the acquisition
process itself was rendered defective because of lack of proper
description of the portion of land from Gut No. 897 that was acquired
Vishal Parekar ...1
VISHAL
SUBHASH
PAREKAR
Digitally signed by
VISHAL SUBHASH
PAREKAR
Date: 2026.05.05
15:14:25 +0530
wp-4786-2018.doc
for the purpose of National Highway No.50 between Pune and
Nashik.
2. At the point in time when the Writ Petition was filed, the
petitioners were still in possession of the subject land and it was
asserted that the petitioners and other villagers had been continuously
representing to the authorities that the alignment of the highway was
inappropriate whereby the portion of their land consisting of Wells was
being acquired instead of dry land and other grievances were also
raised. It was also the case of the petitioners that the defects regarding
improper measurement and identification of the portion of the lands
under acquisition was relevant with regard to the lands situated in Gut
Nos. 896, 897 and 908. It was alleged that in respect of the lands in
adjoining Gut Nos. 896 and 908 re-measurement was undertaken and
it was conceded by the authorities that there was defect requiring
rectification. The petitioners were discriminated against, as no such
exercise was undertaken for the petitioners, further alleging that the
land owners of the said adjoining Gut numbers were politically
influential persons.
3. During the pendency of the Writ Petition, on 24
th
May, 2017,
the possession of the lands of the petitioners was taken. According to
Vishal Parekar ...2
wp-4786-2018.doc
the petitioners, this was done in a clandestine manner and forcibly
while the petitioners were at the office of the Collector raising their
grievances in respect of the aforesaid defects in the acquisition process.
Even post dis-possession, the petitioners continued to agitate with
regard to the said grievances. The Writ Petition was amended to add a
prayer with regard to lapsing of acquisition under Section 24 of the
Right to Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013 (hereinafter referred to
“Act, 2013”). But, at the time of arguments, the said prayer was not
pressed on behalf of the petitioners.
4. The documents filed along with Writ Petition show that the
notifications under Sections 3A and 3D of National Highways Act,
1956 (“Act, 1956”) were issued stating that the land from aforesaid Gut
No. 897 was only being partly acquired. The notification recorded
acquisition from Gut No. 897(Part) to the extent of 0.88 R and the
land was simply described as “agricultural land- dry”. On the basis of
such description of the land proposed to be acquired, eventually, the
said award dated 25
th
November, 2011 was issued. The petitioners
refused to accept the compensation and protested, as according to the
them, the description of the land in the notification was defective and
deficient and that such an objection was raised on their behalf
Vishal Parekar ...3
wp-4786-2018.doc
immediately upon such notification being issued during the acquisition
process. Despite the objection, the process was completed, culminating
into the said award. It was further submitted that the respondent No. 2
National Highway Authority of India represented by the Executive
Engineer, National Highway, Division No. 9, Nashik failed to take
possession of the lands and did not commence any activity for
construction of the highway for a long period of time. It was stated that
the possession of the land was taken in May, 2017 during the pendency
of the Writ Petition. Although various prayers were made in the Writ
Petition at the stage of arguments much emphasis was placed on the
documents filed along with the rejoinder affidavit to claim that the
exercise of the measurement carried out demonstrated the actual area
of the land utilized for construction of the road was 0.93 R and not
0.88 R. Reliance was also placed on the fact that the respondents in the
year 2017 proceeded to grant compensation to similarly situated
individuals in the adjoining Gut No. 896 on the basis of private
negotiations under the Act, 2013, conceding that there was a defect in
the measurement and description of the land in the earlier notification.
5. The respondents filed their reply affidavits, alleging that the
petition suffers from delay and laches as the award was already passed
on 25
th
November, 2011, while the petition was filed in the year 2017.
Vishal Parekar ...4
wp-4786-2018.doc
It was submitted that since the petitioners refused to accept the
compensation, the same was deposited in a separate account, which the
petitioners could collect. It was further submitted that there was no
question of lapsing of acquisition of section 24(2) of the Act, 2013. It
wasalso submitted that the petitioners were not justified in staking
claim for enhanced compensation on alleged defective description of
the land acquired from Gut No. 897.
6. As noted here-in-above, apart form refuting the contentions of
the respondents in the rejoinder affidavit, the aforementioned
submissions were made on behalf of the petitioners and certain
documents were placed on record. It is in this backdrop that the rival
submissions were heard.
7. Mr. Pramod Joshi, learned counsel for the petitioners submitted
that when the Writ Petition was filed and possession of the subject land
was yet to be taken, the petitioners had placed on record sufficient
documents to indicate that even as per the office of respondent No. 6-
the Superintendent of Land Records, Nashik through its Dy.
Superintendent, there was indeed a defect in the joint measurement
conducted for all the three adjoining Gut Nos. 896, 897 and 908 of
the aforesaid village. Thereafter, rectification was made only in respect
Vishal Parekar ...5
wp-4786-2018.doc
of the joint measurement pertaining to Gut No. 896 and 908, for the
reason that the land owners were politically powerful persons, unlike
the petitioners in the present petition.
8. It was further submitted that the description of the land in
notification issued under section 3A of the Act, 1956, was
fundamentally defective and deficient as the land of the petitioners for
acquisition was merely stated to be 0.88 R from Gut No. 897(P)
further described as “agricultural land – dry”. Despite such description,
the respondents eventually took possession of that part of land from
Gut No. 897, which consisted of at least four Wells that were the only
source of water for the petitioners, who are farmers. This further
demonstrated the fact that the very initiation of the acquisition process
was rendered defective. In this context, the learned counsel for the
petitioners placed reliance on the judgment of the Supreme Court in
the case of Competent Authority vs. Barangore Jute Factory and
Others
1
. It was submitted that in a similar situation, the Supreme
Court held that such a defective notification deserves to be set aside,
which would pave the way for acquisition of the land afresh. But, the
Supreme Court finally held that the quashing of the notification may
lead to further complications and therefore, the respondent- authority
1
(2005) 13 Supreme Court Cases 477.
Vishal Parekar ...6
wp-4786-2018.doc
therein was directed to determine the compensation afresh by treating
the date of taking possession of the subject land as the relevant date for
determining the quantum of compensation. It was submitted that the
said judgment applies on all fours to the facts of the present case and
therefore similar reliefs ought to be granted.
9. It was alternatively submitted that since the petitioners in the
rejoinder affidavit had placed on record the joint measurement and
map drawn at the instance of the petitioners, showing obvious defects
in the description of the land under acquisition and the extent of the
land actually taken possession of, coupled with the fact that identically
situated land owners in the adjoining Gut No. 896 were granted
enhanced compensation by private negotiation under the Act, 2013,
this Court may consider granting quantum of compensation, identical
to the one granted to such land owners in the adjoining Gut number.
10. In this context, attention of this Court was invited to a letter
dated 20
th
November, 2017 issued by respondent No. 2 – Executive
Engineer, National Highway, Division No. 9, Nashik, conceding that
there was a defect in the intended acquisition initiated as per the same
notification which pertains to the land of the petitioners also and
offered compensation @ Rs. 4,240/- per sq. mtr. It was emphasized
Vishal Parekar ...7
wp-4786-2018.doc
that surprisingly on the very next day on 21
st
November, 2017, Sale
Deeds were executed with such identically situated land owners.
Therefore, the petitioners had instructed their counsel in this petition
to make a statement that they would be satisfied if compensation for
acquisition of their lands is granted at the same rate of Rs. 4,240/- per
sq. mtr. to put an end to the controversy. On this basis, the learned
counsel for the petitioners submitted that the Writ Petition could be
allowed by granting such enhanced rate of compensation.
11. Mr. Chandurkar, learned AGP appearing on behalf of
respondent Nos. 1, 4 and 7 submitted that the petition suffers from
delay and laches. It was too late in the day for the petitioners to claim
enhanced compensation, particularly when they had not chosen to take
recourse to the remedy available under the Act, 1956, by approaching
the Arbitrator for enhanced compensation. It was further submitted
that the petitioners cannot take advantage of the aforesaid judgment of
the Supreme Court in the case of Barangore Jute Factory and Ors.
(supra) for the reason that the facts are distinguishable. It was further
submitted that the land owners in the adjoining Gut No. 896 were
offered compensation, because it was found as a matter of fact that
there was defect in joint measurement and additional area of 0.53 R
was utilized for construction of the National Highway, justifying the
Vishal Parekar ...8
wp-4786-2018.doc
offer made in the year 2017. It was submitted that there was absolutely
no ground for claiming lapsing of acquisition under section 24(2) of
the Act, 2013. On this basis, it was submitted that the Writ Petition
deserved to be dismissed.
12. Mr. Rakesh Singh, learned counsel appearing for respondent
No. 2 representing NHAI supported the contentions of the learned
AGP. He further submitted that the petitioners cannot raise ground of
discrimination, for the reason that the land owners of Gut No. 896
were not similarly situated like the petitioners. In any case, it was
submitted that the petitioners did not raise any objection for long
period of six years and therefore, the Writ Petition cannot be
entertained for the relief of setting aside of the land acquisition award
and/or for any relief pertaining to enhanced mandatory compensation.
It was submitted that the work pertaining to National Highway was
completed in the year 2022 itself and therefore the Writ Petition
deserved to be dismissed.
13. Having heard the learned counsel for the rival parties, we find,
that, at the point in time the Writ Petition was filed, the petitioners
were still in possession of the subject land. It was during the pendency
of the petition that in May, 2017, they stood dispossessed. The
Vishal Parekar ...9
wp-4786-2018.doc
documents on record show that the petitioners had been sending
representations to the respondents, particularly the officers concerned
with the acquisition process, raising specific grounds with regard to
lack of proper identification of the portion of land belonging to them
in Gut No. 897, which was made subject matter of acquisition. The
record shows such representations sent from the year 2012 onwards.
Even though, the award was issued on 25
th
November, 2011, it is found
that even during the acquisition process, the petitioners had raised
strong objection about the portion of land from Gut No. 897 being
acquired by the respondents. The petitioners claimed that the
alignment of acquisition had been deliberately changed to favour
certain politically powerful individuals and in the process their land
consisting of Wells full of water was sought to be taken under
acquisition, instead of dry land located within the said Gut No. 897.
14. It is a matter of record that although the land acquisition award
was issued on 25
th
November, 2011, the actual possession of the land
was not taken till May, 2017. In the interregnum, the land owners,
similarly situated like the petitioners from adjoining Gut Nos. 896 and
908 had also made representations and protested with regard to the
manner in which the acquisition had been undertaken. The documents
on record show that meetings were held in the office of the Collector to
Vishal Parekar ...10
wp-4786-2018.doc
resolve the disputes.
15. In this backdrop, the document at Exhibit A assumes
significance. It is a letter dated 2
nd
August, 2016 sent by the Dy.
Superintendent of Land Records, Sinnar, Dist. Nashik to the Sub
Divisional Officer, National Highway, Sub Division- II, Nashik. This
letter specifically pertained to Gut Nos. 896, 897 and 908, from which
lands were acquired for construction of the said National Highway. In
this letter, it was specifically stated that the joint measurement
undertaken at the time of initiating acquisition was done in a hurried
manner under police protection and specific boundary lines were not
identified at the time when the measurement was undertaken. It was
further stated that there was request for proper joint measurement in
the said Gut numbers and therefore if the boundary lines and areas of
the land actually acquired for the purpose of National Highway were
identified, it would help in resolving the controversy. Thereafter, the
said Dy. Superintendent, Land Records, Sinnar sent a further
communication dated 8
th
July, 2016 to the said competent authority,
which is at page 33 of the petition. On this occasion, a reference was
made only to lands in Gut Nos. 896 and 908. It was stated that a joint
measurement in respect of the said land was undertaken and it was
found that there were deficiencies and inaccuracies. These were
Vishal Parekar ...11
wp-4786-2018.doc
corrected and a report pertaining to such joint measurement along with
the map were annexed to the said letter.
16. Thereafter on 20
th
November, 2017, the respondent No. 2
Executive Engineer, National Highways, Nashik sent a letter to the
land owners similarly situated like the petitioners having land in Gut
No. 896. In this letter, reference was made to the aforementioned two
letters sent by the Dy. Superintendent of Land Records and it was
stated that upon correction of the deficiency or inaccuracy in joint
measurement, it was found as regards the said land owner that instead
of 0.28 R of land, 0.81 R land from Gut No. 896 had been utilized for
construction of the said National Highway, thereby indicating that an
additional area of 0.53 R was required to be taken into consideration
for the purposes of compensation. Thereupon, respondent No. 2
offered compensation @ Rs. 4,240/- per sq. mtr. to the said land
owner. This was based on an earlier letter dated 29
th
September, 2017
sent by the Competent Authority and Dy. Collector (Land
Acquisition) to the respondent No.2, referring to the said defect being
cured and the offer for enhanced compensation being made. It is also a
matter of record that immediately on 21
st
November, 2017, Sale Deeds
were executed in favour of the said land owners granting them
compensation/consideration @ Rs. 4,240/- per sq. mtr.
Vishal Parekar ...12
wp-4786-2018.doc
17. We find substance in the contention raised on behalf of the
petitioners that the inherent defect in the joint measurement and
consequent depiction of the area of land under acquisition for
construction of the National Highway, pertain to such lands that were
the subject matter of the notification issued under section 3A of the
Act, 1956. The defect pertained to adjoining Gut numbers i.e. 896,
897 and 908. This is evident from the said letter dated 2
nd
August,
2016 sent by the Dy. Superintendent, Land Records, Sinnar to
respondent No. 2. We also find substance in the contention raised on
behalf of the petitioners that having found such a defect, running
through the said adjoining Gut numbers, the rectification was done
only in respect of the lands in Gut Nos. 896 and 908, thereby
discriminating against the petitioners whose lands were located in Gut
No. 897. The documents on record show that the petitioners had been
repeatedly approaching the respondent- authorities with an identical
grievance and yet relief appears to have been granted to a chosen few
land owners in the adjoining Gut numbers.
18. The documents on record also show that the land that was
eventually taken possession of by the respondents consisted of Wells,
which were the source of water for the petitioners who are
agriculturists, despite the fact that the description of the land given in
Vishal Parekar ...13
wp-4786-2018.doc
the notification under section 3A of the Act, 1956, stated that they
were dry agricultural lands.
19. This brings us to the specific contentions raised on behalf of the
petitioners on the basis of the judgment of the Supreme Court in the
case of Barangore Jute Factory and Ors. (supra). In the said case, the
Supreme Court considered the provisions of the Act, 1956, and the
necessity of describing the lands proposed to be acquired, in a proper
manner in the notification issued under section 3A of the Act, 1956,
when only part of land from a Gut number was being acquired. Since
the said judgment covers the arguments made by the rival parties in
this petition also, the relevant portion of the said judgment is required
to be appreciated. The said portion from the judgment of the Supreme
Court in the case of Barangore Jute Factory and Ors. (supra) reads as
follows:-
4] ….. ….The appendix contains a long list of various portions
of lands sought to be acquired. The list runs into more than 10 pages
in the paper book. We have chosen to reproduce only a small portion
of the appendix in order to appreciate the rival contentions of the
learned counsel for the parties. The learned counsel for the writ
petitioners submitted that the purpose of giving a brief description
of the land sought to be acquired is that the person whose land is to
be taken away, should at least know what he is being deprived of.
This becomes all the more necessary when only a part of the land
out of a bigger chunk of land is sought to be acquired. A reference to
the Tables forming part of the appendix, which according to the
acquiring Authority contain brief description of the land, will show
that under various heads, only part of bigger chunks of land is being
acquired. If the entire land falling in a particular survey is acquired,
there cannot be any problem of identi�cation of land. But when only
a part of land out of larger tract of land is sought to be acquired, the
question arises which part is going to be acquired. For instance in
Vishal Parekar ...14
wp-4786-2018.doc
the �rst Table full area of land in Dag No.1448 at Serial No.3 is 17
acres as per column 5. Column 7 indicates that only a part of the said
17 acres is being acquired and as per Column 8, the part which is
sought to be acquired is 2.7500 acres. This means out of 17 acres
only 2.7500 acres is being acquired. The question will arise as to
which side this part which is sought to be acquired is falling, it could
be anywhere on the northern, southern, western, eastern sides or in
the centre. How is one to know which part is under acquisition?
Similar position emerges with reference to other serial numbers
where only part of larger chunks of land is being acquired. Such
cases are several when we look at the entire Appendix and the
Tables forming part of it. According to the learned counsel for the
writ petitioners, the absence of information as to which part of the
land is being acquired makes the description insu�cient, rather
vague. The owners are not in a position to identify the land under
acquisition. It also renders it impossible to make claim regarding
compensation for the land under acquisition because it is a matter of
common knowledge that in bigger tracts of land, certain areas on a
particular side are more valuable than the others. The absence of
proper description of land makes it impossible to �le objection
against acquisition. For all these reasons it is argued on behalf of the
land owners that the statutory requirement of a brief description of
land is not ful�lled. According to the Writ Petitioners non-
compliance of sub- section (2) of Section 3A renders the
Noti�cation invalid and the same is therefore, liable to be quashed.
5] ….. ……… So far as the question whether the impugned
Noti�cation meets the requirement of Section 3A(1) of the Act
regarding giving brief description of land is concerned, we have
already shown that even though plot numbers of land in respect of
each mouza are given, di�erent pieces of land are acquired either as
whole or in part. Wherever the acquisition is of a portion of a bigger
piece of land, there is no description as to which portion was being
acquired. Unless it is known as to which portion was to be acquired,
the petitioners would be unable to understand the impact of
acquisition or to raise any objection about user of the acquired land
for the purposes speci�ed under the Act or to make a claim for
compensation. It is settled law that where a statute requires a
particular act to be done in a particular manner, the act has to be
done in that manner alone. Every word of the statute has to be given
its due meaning. In our view, the impugned noti�cation fails to meet
the statutory mandate. It is vague. The least that is required in such
cases is that the acquisition noti�cation should let the person whose
land is sought to be acquired know what he is going to lose. The
impugned noti�cation in this case is, therefore, not in accordance
with the law.
6] While dealing with the question of brief description of land in the
acquisition noti�cations, reference was made to some judgments of
this Court where acquisition Noti�cations under Section 4 of the
Land Acquisition Act had come up for consideration on account of
challenge being leveled on ground of vagueness of the Noti�cations.
In most of these cases, Plan of the area under acquisition was made
Vishal Parekar ...15
wp-4786-2018.doc
part of the noti�cations to show that the requirement of description
of land was met. This lead us to inquire whether there was any site
plan forming part of the impugned Noti�cation.
7] The availability of a Plan would have made all the di�erence. If
there is a Plan, the area under acquisition becomes identi�able
immediately. The question whether the impugned Noti�cation
meets the requirement of brief description of land under Section
3A(2) goes to the root of the matter. The High Court rightly
observed : "…..It is just not possible to proceed to determine the
necessity of acquisition of a particular plot of land without
preparation of a proper Plan." The appendix to the impugned
noti�cation shows that in many cases small parts of larger chunks of
land have been noti�ed for acquisition. This is not possible without
preparing a Plan. But where is the Plan? The Noti�cation in
question makes no reference to any Plan. Our attention was drawn to
averments in pleadings by Writ Petitioners and replies thereto of the
acquiring authority. The Writ Petitioners have pleaded that there
was no Plan. Replies are vague and by way of rolled up answers.
There is no speci�c reply. It is obvious that there was no Plan and
therefore none was referred to in pleadings nor any thing was
produced before Court at the hearing. Learned counsel for the
Competent Authority tried to submit before us that there was a Plan
at the time of issue of the noti�cation and the Writ Petitioners ought
to have inspected it if they so desired. He further submitted that the
Plan was produced before the High Court. We �nd that both these
submissions are not sustainable as they are not correct. A reference
to the impugned Noti�cation shows that there is no mention of any
Plan. Without this how can anybody know that there was a Plan
which could be inspected and inspected where? We are inclined to
accept that there was no Plan accompanying the impugned
Noti�cation. During the course of hearing we were shown a Plan
which we are unable to link with the impugned Noti�cation. This
was a 1996 P.W.D.Plan. The P.W.D. is a department of the State
Government. The impugned Noti�cation is by the Central
Government. The NHAI is established under a Central Act. The
Competent Authority under Section 3 of the Act is appointed by the
Central Government. Therefore, this State Government Plan of
1996 (the impugned Noti�cation is of 1998) is of no assistance. The
impugned judgment of the High Court emphasises the need for a
Plan. It is clear from the judgment of the High Court that no Plan
was produced before it. The absence of any reference to a Plan in the
impugned Noti�cation and in fact non-availability of any Plan linked
to the Noti�cation, forti�es the argument that the description of the
land under acquisition in the impugned Noti�cation fails to meet the
legal requirement of a brief description of the land which renders
the Noti�cation invalid.
8] The absence of plan also renders the right to �le objections under
Section 3C(1) nugatory. In the absence of a Plan, it is impossible to
ascertain or know which part of acquired land was to be used and in
what manner. Without this knowledge no objections regarding use of
land could be �led. Since the objection regarding use of the land had
Vishal Parekar ...16
wp-4786-2018.doc
been given up by the writ petitioners, we need not go any further in
this aspect. We would, however, like to add that unlike Section 5A of
the Land Acquisition Act,1894 which confers a general right to
object to acquisition of land under Section 4 of the said Act, Section
3C(1) of the National Highways Act gives a very limited right to
object. The objection can be only to the use of the land under
acquisition for purposes other than those under sub-section 3A(1).
The Act confers no right to object to acquisition as such. This
answers the argument advanced by the learned counsel for the
NHAI that failure to �le objections disentitles Writ Petitioners to
object to the acquisition. The Act confers no general right to object,
therefore, failure to object becomes irrelevant. The learned counsel
relied on the judgment of this court in Delhi Administration vs.
Gurdip Singh Uban & Others [(1999) 7 SCC 44]. In our view, this
judgment has no application in the facts of the present case where
right to object is a very limited right. The case cited is a case under
the Land Acquisition Act, 1894 which confers a general right to
object to acquisition of land under Section 5A. Failure to exercise
that right could be said to be acquiescence. The National Highways
Act confers no such right. Under this Act there is no right to object
to acquisition of land except on the question of its user. Therefore,
the present objection has to be decided independently of the right to
�le objections. De hors the right to �le objection, the validity of the
Noti�cation has to be considered. Failure to �le objection to the
noti�cation under Section 3C, therefore, cannot non-suit the Writ
Petitioners in this case.
9] The learned counsel supporting the acquisition submitted that
the delay in �ling the Writ Petition is fatal to the case of land
owners. It is true that 11th June, 1998 Noti�cation was challenged
only in September, 2001 by �ling the Writ Petition. But if the
Noti�cation violates the very statute from which it derives its force,
will delay in challenging it clothe it with legitimacy? The Act
requires the Noti�cation to be issued in a particular manner with
brief particulars of land being acquired. The Noti�cation in this case
fails to meet this requirement. We have held it to be bad in law. It has
no legs to stand. The conduct of the opposite party cannot be used
to make it stand. Moreover, the Writ Petitioners have explained the
reasons for the delay in �ling the Writ Petition. The Company which
owns the lands had been de-registered. It is a Company registered in
the U.K. It had to be revived. Revival came in mid-2001 whereafter
the action was taken. Thus we �nd no merit in the argument about
delay in challenging the Noti�cation rendering the challenge liable
to be rejected.
.. ……
14] Having held that the impugned noti�cation regarding acquisition
of land is invalid because it fails to meet the statutory requirements
and also having found that taking possession of the land of the writ
petitioners in the present case in pursuance of the said noti�cation
was not in accordance with law, the question arises as to what relief
can be granted to the petitioners. The High Court rightly observed
Vishal Parekar ...17
wp-4786-2018.doc
that the acquisition of land in the present case was for a project of
great national importance, i.e. the construction of a national
highway. The construction of national highway on the acquired land
has already been completed as informed to us during the course of
hearing. No useful purpose will be served by quashing the impugned
noti�cation at this stage. We cannot be unmindful of the legal
position that the acquiring authority can always issue a fresh
noti�cation for acquisition of the land in the event of the impugned
noti�cation being quashed. The consequence of this will only be that
keeping in view the rising trend in prices of land, the amount of
compensation payable to the land owners may be more. Therefore,
the ultimate question will be about the quantum of compensation
payable to the land owners. Quashing of the noti�cation at this stage
will give rise to several di�culties and practical problems. Balancing
the rights of the petitioners as against the problems involved in
quashing the impugned noti�cation, we are of the view that a better
course will be to compensate the land owners, that is, writ
petitioners appropriately for what they have been deprived of.
Interests of justice persuade us to adopt this course of action.
15] Normally, compensation is determined as per the market price of
land on the date of issuance of the noti�cation regarding acquisition
of land. There are precedents by way of judgments of this Court
where in similar situations instead of quashing the impugned
noti�cation, this Court shifted the date of the noti�cation so that the
land owners are adequately compensated. Reference may be made to
(a) Ujjain Vikas Pradhikaran v. Rajkumar Johri and
others [1992 (1)SCC 328]
(b) Gauri Shankar Gaur & Ors. v. State of UP &
Ors. [1994 (1) SCC 92]
(c) Haji Saeed Khan & Ors. v. State of UP & Ors.
[2001 (9) SCC 513]
In that direction the next step is what should be the crucial date
in the facts of the present case for determining the quantum of
compensation. We feel that the relevant date in the present case
ought to be the date when possession of the land was taken by the
respondents from the writ petitioners. This date admittedly is 19-
02-2003. We, therefore, direct that compensation payable to the
writ petitioners be determined as on 19-02-2003, the date on which
they were deprived of possession of their lands. We do not quash
the impugned noti�cation in order not to disturb what has already
taken place by way of use of the acquired land for construction of
the national highway. We direct that the compensation for the
acquired land be determined as on 19-02-2003 expeditiously and
within ten weeks from today and the amount of compensation so
determined, be paid to the writ petitioners after adjusting the
amount already paid by way of compensation within eight weeks
thereafter. The claim of interest on the amount of compensation so
determined is to be decided in accordance with law by the
appropriate authority. We express no opinion about other statutory
rights, if any, available to the parties in this behalf and the parties
will be free to exercise the same, if available. The compensation as
determined by us under this order along with other bene�ts, which
Vishal Parekar ...18
wp-4786-2018.doc
the respondents give to parties whose lands are acquired under the
Act should be given to the writ petitioners along with what has been
directed by us in this judgment.
20. A perusal of the above quoted portion of the said judgment of
the Supreme Court shows that when the brief description of the land
proposed to be acquired, is not properly stated in the notification
under section 3A of the Act, 1956, particularly when only a part of the
land out of a larger part of land is sought to be acquired, the
notification itself is liable to be quashed. Once this happens, the entire
acquisition proceedings, including the land acquisition award is liable
to be quashed. We find that the Supreme Court in the said case was
dealing with facts that were similar to the facts arising in the present
petition.
21. A perusal of the notification under Section 3A of the Act, 1956,
in the present case shows that in so far as the land belonging to the
petitioners is concerned the only description was that land from Gut
No. 897 (P) was being acquired to the extent of 0.88 R, with the land
being stated as “agricultural land- dry”. The petitioners have placed on
record 7/12 extract i.e. the revenue record to show that Gut No. 897
consisted of 8H and 35R land. The aforesaid description in the
notification under Section 3A of the Act, 1956, is found to be woefully
inadequate to demonstrate as to which portion admeasuring 0.88 R
Vishal Parekar ...19
wp-4786-2018.doc
from 8H and 35 R of Gut No. 897 was proposed to be acquired. Such
defective brief description clearly denied the petitioners a fair
opportunity to raise their objections and to place their case before the
authorities. This is exactly what the Supreme Court held in the case of
Barangore Jute Factory and Ors. (supra) as a defect going to the root of
the matter, necessitating quashing of the notification itself.
22. On the question of delay, in the said judgment in paragraph 9
quoted here-in-above, the Supreme Court found that delay in
challenging would not clothe the act of the authorities with legitimacy
if it suffers from a fundamental defect regarding the notification itself.
We find that the petitioners in the present case have placed on record
sufficient documents to show that, at the stage of acquisition before the
award was issued on 25
th
November, 2011 and even immediately
thereafter, they had been pursuing the authorities on the aforesaid
fundamental defect in identification of the exact portion admeasuring
0.88 R in Gut No. 897, that was made subject matter of the
acquisition. It is a matter of record that till the Writ Petition was filed,
the petitioners continued to be in possession. It was only during the
pendency of the petition that the respondent-authorities took
possession of the land and the Highway was eventually completed in
the year 2022. Therefore, the respondents cannot escape responding to
Vishal Parekar ...20
wp-4786-2018.doc
the issues raised by the petitioners in the petition by taking shelter of
the argument of delay and laches.
23. Apart from this, as noted here-in-above, we find that the
petitioners appear to have been discriminated against, as land owners
similarly situated like them in the adjoining Gut Nos. 896 and 908
were granted the relief of rectification of joint measurement and
consequential modification of area under acquisition, leading to grant
of compensation, under the Act, 2013. On this ground also, we find
that the petitioners have made out a case in their favour.
24. If the principle laid down in the judgment of Barangore Jute
Factory and Ors. (supra) is followed and applied to the facts of this
case, the notification itself would stand quashed leading to the entire
acquisition proceeding as also the award being set aside. But even the
Supreme Court in the said judgment did not proceed to quash the
notification, recognizing several difficulties and practical problems that
would arise. In that backdrop, the Supreme Court balanced the rights
of the petitioners therein by taking a different course of action. It was
held that the petitioners therein would be entitled to determination
and payment of compensation from a different date and in that context
the crucial date was identified as the date on which the petitioners
Vishal Parekar ...21
wp-4786-2018.doc
therein were actually dispossessed. On that basis, directions were issued
for determination of compensation.
25. If we were to follow the said course of action, the relevant date
in the facts of the present case would be 24
th
May, 2017 when the
petitioners were dispossessed during the pendency of this Writ
Petition. The respondents would have to calculate the quantum of
compensation under the Act, 2013, treating the relevant date as 24
th
May, 2017. Such directions could have been issued, but for the fact of
the learned counsel for the petitioners on specific instructions from the
petitioners and in line with their representation dated 8
th
September,
2020, submitted that the petitioners would be satisfied if they are also
granted compensation @ Rs. 4,240/- per sq. mtr. as was granted to the
similarly situated land owners in adjoining Gut No. 896.
26. We are of the opinion that if such a direction is issued, it would
balance the interests of the rival parties, as the other option of quashing
the notification itself following the law laid down by the Supreme
Court in the case of Barangore Jute Factory and Ors. (supra), would
lead to unnecessary problems and complications for all the stake
holders.
Vishal Parekar ...22
wp-4786-2018.doc
27. In view of the above, we partly allow the Writ Petition by
directing that the respondents shall pay compensation to the
petitioners @ Rs. 4,240/- per sq. mtr. for the extent of their land
acquired and utilized for construction of the aforesaid Highway.
28. The amount shall be calculated and paid to the petitioners
within a period of eight weeks from today.
29. Pending applications, if any, also stand disposed of.
(SHREERAM V. SHIRSAT, J) (MANISH PITALE, J.)
Vishal Parekar ...23
Legal Notes
Add a Note....