Chatterjee Petrochem case, Haldia Petrochemicals judgment, Supreme Court corporate dispute
0  10 Dec, 2013
Listen in 1:28 mins | Read in 34:00 mins
EN
HI

Chatterjee Petrochem Co. & Anr Vs. Haldia Petrochemicals Ltd. & Ors.

  Supreme Court Of India Civil Appeal /10932 /2013
Link copied!

Case Background

The respondent HPL on the other hand, claims that the Arbitration Agreement contained in clause 15 of the Agreement dated 12th January, 2002 is void and/ or unenforceable and/or has become inoperative and/or incapable ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

Page 1 1

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO.10932 OF 2013

(Arising out of S.L.P.(C) No. 19951 OF 2013)

CHATTERJEE PETROCHEM CO. & ANR ………APPELLANTS

Vs.

HALDIA PETROCHEMICALS LTD.& ORS. ……… RESPONDENTS

J U D G M E N T

V. Gopala Gowda J.

On 21

st

March, 2012, the appellant Chatterjee

Petrochem (Mauritius) Company (hereinafter referred to

as ‘CPMC’) filed a request for arbitration in

International Chamber of Commerce (ICC), Paris in

relation to an agreement of restructuring which was

Page 2 C.A.@ slp(c)No.19951 of 2013

entered into between CPMC, Government of West Bengal,

West Bengal Industrial Development Corporation (in

short ‘WBIDC’) and Haldia Petrochemical Limited (in

short ‘HPL’) on 12

th

January, 2002. As per the

Agreement, the Government of West Bengal was to cause

WBIDC to transfer existing shareholding to CPMC to

ensure that CPMC holds 51% of the total paid up capital

of HPL. Clause 15 of the Agreement provides for

reference of all disputes, in any way relating to the

said Agreement or to the business of or affair of HPL

to the Rules of the ICC, Paris.

2.The respondent HPL on the other hand, claims that

the Arbitration Agreement contained in clause 15 of the

Agreement dated 12

th

January, 2002 is void and/ or

unenforceable and/or has become inoperative and/or

incapable of being performed.

3.A dispute arose between the parties regarding the

allotment of shares and the appellant filed Company

Petition No. 58 of 2009 before the Company Law Board

2

Page 3 C.A.@ slp(c)No.19951 of 2013

(in short ‘CLB’)on the grounds of oppression and

mismanagement. The appellant also sought transfer of

155 million shares in favour of Chatterjee Petrochem

(India) Pvt. Ltd. (in short “the CPIL”), the Indian

counterpart of CPMC as was decided in the Agreement.

4.The Company Petition was disposed of by the CLB by

upholding the decision of the Company to allot 155

million shares by Indian Oil Corporation (in short

‘IOC’). The transfer of 155 million shares to CPIL by

WBIDC was also confirmed. The CLB further directed the

Government of West Bengal and WBIDC to transfer 520

million shares held by them in HPL to Chatterjee

Groups.

5. The Government of West Bengal preferred an appeal

against the said Order before the High Court of

Judicature at Calcutta under the provisions of Section

10F of the Company’s Act, 1956. The High Court set

aside the Order of the CLB on the ground that CPIL was

not a member of HPL and the CLB could not have enforced

3

Page 4 C.A.@ slp(c)No.19951 of 2013

its right under private contract entered into between

CPIL and WBIDC for transfer of shares as the same could

not be the subject matter of a petition under Section

397 of the Companies Act.

6.Aggrieved by the same, the appellant preferred

appeal Nos. 5416-5419, 5420, 5437 and 5440 of 2008

before this Court. Vide judgment dated 30.09.2011,

this Court held that the claim of the appellant

transferring shares to IOC has changed the private

character of the Company and was not an act of

oppression on the part of the Company. According to

this Court, the transfer of shares to IOC was a result

of failure on the part of the appellant to infuse

adequate funds into the Company by way of equity as

promised and to participate in its rights issues. The

Company was therefore, constraint to induct IOC as a

member and the 155 million shares which was to be

transferred to the appellant was instead transferred to

4

Page 5 C.A.@ slp(c)No.19951 of 2013

the IOC. The relevant paragraph of the judgment reads

as under:

“103. The failure of WBIDC and GoWB to register

the 155 million shares transferred to CP(I)PL

could not, strictly speaking, be taken to be

failure on the part of the Company, but it was

the failure of one of the parties to a private

arrangement to abide by its commitments. The

remedy in such a case was not under

Section 397 of the Companies Act. It has been

submitted by both Mr. Nariman and Mr. Sarkar

that even if no acts of oppression had been

made out against the Company, it would still be

open to the learned Company Judge to grant

suitable relief under Section 402 of the Act to

iron out the differences that might appear from

time to time in the running of the affairs of

the Company. No doubt, in the Needle Industries

case, this Court had observed that the

behaviour and conduct complained of must be

held to be harsh and wrongful and in arriving

at such a finding, the Court ought not to

confine itself to a narrow legalistic view and

allow technical pleas to defeat the beneficial

provisions of the Section, and that in certain

situations the Court is not powerless to do

substantial justice between the parties, the

facts of this case do not merit such a course

of action to be taken. Such an argument is not

available to the Chatterjee Group, since the

alleged breach of the agreements referred to

hereinabove, was really in the nature of a

breach between two members of the Company and

not the Company itself. It is not on account of

any act on the part of the Company that the

shares transferred to CP(I)PL were not

registered in the name of the Chatterjee

5

Page 6 C.A.@ slp(c)No.19951 of 2013

Group. There was, therefore, no occasion for

the CLB to make any order either under

Section 397 or 402 of the aforesaid Act. If, as

was observed in M.S.D.C. Radharamanan's case

(supra), the CLB had given a finding that the

acts of oppression had not been established, it

would still be in a position to pass

appropriate orders under Section 402 of the

Act. That, however, is not the case in the

instant appeals.”

(emphasis laid by this Court)

7.On this decision given by this Court, the appellant

sought to invoke the arbitration clause contained in

the agreement dated 12

th

January, 2002 and made a

request for arbitration. The respondent no.1 on the

other hand, filed a suit before the High Court of

judicature at Calcutta praying that the arbitration

clause in the agreement be declared as void.

8. Learned senior counsel on behalf of the appellant

Dr. Abhishek Manu Singhvi relied upon Clause 15 of the

letter of agreement dated 12

th

January, 2002 to contend

that any dispute, difference or claims arising between

the parties relating to this letter of agreement dated

12

th

January, 2002, or any construction or

6

Page 7 C.A.@ slp(c)No.19951 of 2013

interpretation relating to the working of or the

business of the respondent no.1, shall first make an

endeavour to settle their disputes, differences etc. in

accordance with the Rules of Arbitration of the

International Chamber of Commerce. Therefore, the

learned senior counsel contended that the validity or

existence of the arbitration agreement is to be decided

by the Arbitration Tribunal in terms of Article 6 of

the ICC Rules, 1998 which is pari-materia to Section 16

of the Arbitration and Conciliation Act, 1996 (in short

‘A & C Act’)and the Civil Court has no jurisdiction to

decide on such issues. In support of this legal

contention, the learned senior counsel relied upon the

decision of this Court in Yograj Infrastructure Ltd. v.

Ssang Yong Engineering and Construction Co. Ltd .

1

wherein it was held that the arbitration shall be held

as is mentioned in the agreement which in the present

case, is at Paris.

1

(2011) 9 SCC 735

7

Page 8 C.A.@ slp(c)No.19951 of 2013

9.It is the further case of the appellant that the

agreement dated 12

th

January, 2002 between the parties

was not novated by the subsequent agreements.

According to the appellant, the agreement dated 12

th

January, 2002 is the principal agreement, which was

later followed by the supplemental agreements dated 8

th

March, 2002 and 30

th

July, 2004. The letter of agreement

dated 8

th

March, 2002 did not create any independent

legal right but was a mere direction from CPMC to

transfer 155 million shares to its nominee CPIL to

avoid delay. Therefore, according to the appellant, the

letter of agreement dated 8

th

March 2002 provided that

the terms and conditions of 12

th

January, 2002 agreement

would continue to remain valid and subsisting between

the parties. The relevant clauses will be mentioned in

the reasoning portion of the judgment.

10. The learned senior counsel relied upon Section 45

of the A & C Act to contend that the suit instituted by

the respondent No. 1 against the request of arbitration

8

Page 9 C.A.@ slp(c)No.19951 of 2013

by the appellant is not maintainable in law. He further

argued that the suit instituted by the respondent

No. 1 to restrain a foreign arbitration for resolution

of the disputes between the parties was in violation of

Section 5 of the A & C Act which limits judicial

authority’s intervention in arbitration and therefore

the impugned order of injunction passed by the High

Court of Judicature at Calcutta was contrary to law and

therefore, the same is liable to be set aside. In this

regard, the learned senior counsel relied upon the

three Judge Bench decision of this Court in Bhatia

International v. Bulk Trading S.A. and Anr.

2

to contend

that section 5 of the A & C Act provides that no

judicial authority shall intervene except where it is

provided. The relevant paragraph will be extracted in

the reasoning portion of the judgment.

11.Mr. Sudipto Sarkar, learned senior counsel also

appearing on behalf of the appellant further contended

that the maintainability of the arbitration of the

2

(2002) 4 SCC 105

9

Page 10 C.A.@ slp(c)No.19951 of 2013

disputes between the parties can be established by

relying on the decision of this Court in Venture Global

Engineering v. Satyam Computer Services Ltd. and Anr .

3

wherein it was held that Part I of the A & C Act will

be applicable to international arbitrations as well.

Therefore, Mr. Sarkar contended that the Arbitration

clause will be a bar for judicial intervention in the

present case in spite of the fact that it is an

international arbitration as per the principal

agreement which will be continued in force as per the

terms of the supplemental agreements.

12. On the other hand, it is the case of the respondent

HPL that the arbitration agreement dated 12

th

January,

2002 is rendered void in respect of the claim for

transfer of 155 million shares in favour of CPIL

inasmuch as the parties had contracted out of their

earlier agreement and the legal liability in respect

thereof was redefined in the subsequent 8

th

March, 2002

Agreement which provided for an exclusive jurisdiction

3

(2008) 4 SCC 190

10

Page 11 C.A.@ slp(c)No.19951 of 2013

to courts in Calcutta to decide dispute arising out of

the said agreement. Therefore, it was pleaded by

Mr. Ashok Desai, the learned senior counsel appearing

on behalf of the respondent no. 1-HPL that once a party

to an arbitration agreement seeks to adjudicate dispute

before another forum and such forum arrives at a

conclusive findings of fact in relation to the dispute

then, the subsequent effort on the part of the same

party to refer dispute for arbitration under ICC Rules

would be vexatious and abuse of law and it shall be

construed that the arbitration clause in the principal

agreement has been rendered inoperative by the conduct

of the party itself.

13. The learned senior counsel for the respondent no. 1

further claimed that Section 5 of the A & C Act can

come into play only when existence of a valid

arbitration agreement is established. Institution of

such a suit by the respondent no.1 would constitute an

“action pending before the judicial authority”

11

Page 12 C.A.@ slp(c)No.19951 of 2013

necessitating the invocation of Section 45 of the A & C

Act, if one of the parties makes a request to refer the

matter for arbitration. In such cases, the court must

see whether the arbitration agreement is valid,

operative and capable of being performed, before

referring the parties to arbitration.

14.It is the further case of respondent no.1 that the

subsequent agreement through letter dated 8

th

March

2002, in respect of transfer of 155 million shares of

HPL, new rights and liabilities were created by and

between the non- parties to the arbitration agreement.

The new agreement also provided for a different dispute

resolution mechanism among the parties, that is, the

courts in Calcutta. The relevant clause will be

extracted in the reasoning portion of the judgment.

15.The learned senior counsel, Mr. K.K. Venugopal,

appearing on behalf of Respondent no. 2, Govt. of West

Bengal, contended that the Arbitration and Conciliation

Act, 1996 does not apply to the present case. According

12

Page 13 C.A.@ slp(c)No.19951 of 2013

to the learned senior counsel, a party may purport to

appoint an arbitrator who may enter upon the

arbitration even when there is serious dispute as to

whether the arbitration clause exists. In spite of the

fact that no arbitration clause exists, if a party

resorts to arbitration, then neither section 8 nor

section 45 of the A & C Act in case of international

arbitration would provide for adjudication of the issue

as to whether the arbitration clause exists. It is only

where a suit has first been filed, in point of time, on

the substantive agreement or the underlying agreement,

either by way of specific performance or for

compensation for breach of contract, that section 8 or

section 45 of the A & C Act would come into play.

However, we are not inclined to comment on this

contention since it is not pertinent to the case.

16.The learned senior counsel for Respondent no. 2

also contended that when no arbitration clause exists

in the agreement, the matter cannot be adjudicated

13

Page 14 C.A.@ slp(c)No.19951 of 2013

either under Part I or Part II of the A & C Act rather,

the matter can be adjudicated only by an independent

suit seeking injunction against the party who had

initiated arbitration, from proceeding with the

arbitration.

17.It is further the case of the learned senior

counsel, Mr. K.K. Venugopal that the facts of the

present case are extraordinary and that the matter has

been extensively litigated in the previous round both,

before the Company Law Board and the appellate

proceedings thereof. At no point in time did the

Chatterjee Group or any of its constituent affiliate,

saved or reserved their right to seek arbitration under

the alleged Arbitration Agreement which they now seek

to enforce. This Court has already declined the reliefs

on merit as well as on the point of jurisdiction.

Therefore, he submits that at this juncture, invoking

the arbitration clause from the principal agreement by

the Chatterjee Group disregarding the Agreement dated

14

Page 15 C.A.@ slp(c)No.19951 of 2013

8

th

March, 2002, is clearly vexatious and abuse of the

process of law. Therefore, the suit filed by respondent

no. 1 seeking injunction relief on arbitration is

maintainable in law.

18.It is further the case of the learned senior

counsel on behalf of Respondent no.2 that the matter

has been elaborately argued before this Court on

complicated issues of law which arise for determination

in the case. It is therefore, submitted by him that in

such an event this Court would not render findings on

questions of law while disposing an appeal against the

interlocutory order so as to give finality in such

findings. This approach of the Court is adopted in many

cases arising under the Intellectual Property law,

namely Bajaj Auto Ltd. v. TVS Motor Company Ltd.

4

,

Shree Vardhman Rice & General Mills v. Amar Singh

Chawalwala

5

, Milmet Oftho Industries & Ors. v.

Allergan Inc.

6

and Dhariwal Industries Ltd. & Anr. v.

4

(2009) 9 SCC 797 (para 5)

5

(2009) 10 SCC 257 (para 2)

6

(2004) 12 SCC 624 (paras 9 to 11)

15

Page 16 C.A.@ slp(c)No.19951 of 2013

M.S.S. Food Products

7

. We are inclined to mention at

this stage that in this appeal we are confined to

deciding upon the validity of the arbitration clause in

the principal agreement dated 12

th

January, 2002 only.

Hence, this contention does not require to be addressed

in this appeal.

19.The learned senior counsel for respondent No. 3

Mr. C.A. Sundaram contends that jurisdictional issue in

the present case, shall be decided as the threshold

issue in the present case. In relation to this, he

placed reliance upon the three Judge Bench decision of

this Court in Chloro Controls India Pvt. Ltd. v. Severn

Trent Water Purification Inc. and Ors .

8

20.In the light of the facts and circumstances

presented before us on the basis of admitted documents

on record, and also based on the legal contentions

urged by the learned senior counsel on behalf of both

7

(2005) 3 SCC 63 (para 20)

8

(2013) 1 SCC 641

16

Page 17 C.A.@ slp(c)No.19951 of 2013

the parties, the following issues would arise for

consideration of this Court in these proceedings:

1.Can the Arbitration clause under clause 15

of the letter of Agreement dated 12

th

January, 2002 be invoked by the appellants

and whether Clause 7.5 of the subsequent

Agreement dated 8

th

March, 2002 invoking the

exclusive jurisdiction of the courts of

Calcutta nullify the scope of arbitration

as mentioned in the previous agreement

dated 12

th

January, 2002?

2.Is the suit, filed by the respondents,

seeking injunction against arbitration of

disputes between the parties sought for by

the appellants as per Clause 15 of the

principal agreement referred to supra

maintainable in law?

3.What Order?

Answer to Point no.1

21.We are inclined to reject the submission made by

the learned senior counsel on behalf of the respondents

that the transfer of shares to CPIL instead of CPMC

substantially changes the legal rights and

responsibilities of the parties as per agreement

17

Page 18 C.A.@ slp(c)No.19951 of 2013

referred to supra thereby, resulting in novation of

contract.

22.It is nowhere mentioned in the letter dated 8

th

March, 2002 that transfer of shares to CPIL instead of

CPMC extinguishes the old agreement dated 12

th

January,

2002 to nullity. In fact, in the letter dated 8

th

March,

2002, CPMC has been constantly mentioned as a

guarantor. It is only to this extent the nature of

agreement has changed.

23.It is argued by the learned senior counsel Mr.

C.A. Sundaram, appearing on behalf of Respondent no.3

that the concurrent findings of facts on the prima

facie case by the learned single Judge and the

Division Bench of the High Court of Calcutta have held

that there has been a novation of agreement between

the parties to the principal agreement dated 12

th

January,2002 by the subsequent agreements dated 8

th

March, 2002 and 30

th

July, 2004.

18

Page 19 C.A.@ slp(c)No.19951 of 2013

24. It has been held by the learned single Judge of the

Calcutta High Court that:

“……This is a case, where by express words the

parties have altered their obligations by a new

agreement on 8

th

March, 2002 with a term that

the Courts in Kolkata ‘alone’ would have

jurisdictions. This was affirmed by the 30

th

July, 2004 agreement. This put an end to the

arbitration, once and for all. Therefore, the

arbitration clause in the 12

th

January, 2002

agreement was abrogated by the 8

th

March

agreement. Abrogation of an arbitration

agreement could not be made in clearer terms…”.

25.Further, the Division Bench of Calcutta High Court

vide impugned judgment dated 12

th

January 2012, made the

following observations:

a.) Agreement of 12

th

January 2002 was

substituted by agreements of March 8, 2002 and

July 30, 2004.

b.) Such a subsequent agreement completely

extinguished the rights existing under the

January 12, 2002 agreement and also destroyed

the arbitration clause.

c.) Remedy is under Agreement of March 8, 2002

which does not provide for Arbitration but

states that courts at Calcutta alone shall

have jurisdiction.

d.) Agreement of March 8, 2002 is not an

ancillary to agreement of January 12, 2002 but

materially alters the same. The principle laid

19

Page 20 C.A.@ slp(c)No.19951 of 2013

down in Chloro Controls Case (supra) does not

apply. Real intention of the parties in the

instant case was to substitute one agreement

with another.

26.Clause 1 of the supplementary agreement dated 30

th

July, 2004 reads as under:

“Pursuant to the said Principal Agreement GoWB

has caused WBIDC to transfer to Chatterjee

Petrochem (India) Private Limited (CPIL), an

affiliate of CPMC Rs. 155 crores of shares from

the shareholding of WBIDC existing on the date

of principal agreement…”

(emphasis laid by this Court)

The abovementioned clause goes to show that CPIL is an

affiliate of CPMC. This is to say, that by means of the

letter dated 8

th

March,2002 CPMC becomes a guarantor

whereas CPIL becomes the borrower. Therefore, the same

does not change the rights and responsibilities of the

parties under the agreement dated 12

th

January, 2002.

27. Further, the letter written by CPMC to WBIDC along

with the agreement dated 8

th

March, 2002 reads as

follows:

“…It is clarified that the aforesaid shall not

prejudice any of our rights under the said

20

Page 21 C.A.@ slp(c)No.19951 of 2013

Agreement dt. January 12, 2002 and all terms

and conditions thereof shall continue to remain

valid, binding and subsisting between the

parties to be acted upon sequentially”.

(emphasis laid by this Court)

The content of this letter goes to show that the

agreement dated 12

th

January, 2002 remains the principal

agreement while agreement dated 8

th

March 2002 remains a

supplementary agreement which was meant for

restructuring of HPL on urgency.

28.Further, and most importantly, the agreement

entered into between the parties dated 30

th

July, 2004

states as follows:

“WHEREAS the Parties hereto had entered into an

agreement dated January 12, 2002 (hereinafter

referred to as the principal agreement….”

Also, the Agreement dated 30

th

July, 2004 which is based

on shareholding issues, also notes through clause 6

that:

“6. The Parties hereby agree, record and

confirm that all other terms and conditions as

contained in the said Principal Agreement shall

21

Page 22 C.A.@ slp(c)No.19951 of 2013

remain binding, subsisting, effective,

enforceable and in force between the parties.”

(emphasis laid by this Court)

The abovementioned clauses of the subsequent Agreements

dated 8

th

March, 2002 and 30

th

July, 2004 go to show that

there has been no alteration in the nature of rights

and responsibilities of the parties involved in the

contract. Consequently, there has been no novation of

the contract.

29. It has been further argued by the learned senior

counsel for the respondents that Section 5 of the A & C

Act, which bars intervention by judicial authority in

Arbitration Agreement will not be applicable to

International Agreements such as the present case. We

are inclined to reject this contention by placing

reliance upon the legal principle laid down by this

Court in Venture Global Engineering case (supra), the

relevant paragraph of which reads as under:

“25. …… In order to find out an answer to the

first and prime issue and whether the decision

in Bhatia International (supra) is an answer to

22

Page 23 C.A.@ slp(c)No.19951 of 2013

the same, let us go into the details regarding

the suit filed by the appellant as well as the

relevant provisions of the Act. The appellant

-VGE filed O.S. No. 80 of 2006 on the file of

the Ist Additional District Court,

Secunderabad, for a declaration that the Award

dated 3.4.2006 is invalid, unenforceable and to

set aside the same. Section 5 of the Act makes

it clear that in matters governed by Part I, no

judicial authority shall intervene except where

so provided. Section 5 which falls in Part I,

specifies that no judicial authority shall

intervene except where so provided. The Scheme

of the Act is such that the general provisions

of Part I, including Section 5 , will apply to

all Chapters or Parts of the Act. ”

(emphasis laid by this Court)

30. Further, it is pertinent to read Clause 7.5 of the

Agreement dated 8

th

March, 2002 carefully. Clause 7.5

reads thus:

“Jurisdiction: Courts at Calcutta alone shall

have jurisdiction in all matters relating to

this Agreement.”

The phrase ‘this agreement’ means the Agreement dated

8

th

March, 2002 which is essentially a supplementary

Agreement and does not, by any mean, make the Principal

Agreement dated 12

th

January, 2002 subject to the

jurisdiction of the Court.

23

Page 24 C.A.@ slp(c)No.19951 of 2013

31. Therefore, we are of the opinion that both the

learned single Judge and the Division Bench erred in

arriving at the conclusion mentioned above and their

findings are liable to be set aside. In the light of

the case mentioned above and also on the basis of the

clauses of the Principal Agreement dated 12

th

January

2002 and subsequent Agreements dated 8

th

March 2002 and

30

th

July, 2004, read with section 5 of the A&C Act, we

are inclined to observe that the Arbitration clause in

the Principal Agreement continued to be valid in view

of clause no. 6 of the Agreement dated 30

th

July, 2004

and also by virtue of its mention in different parts of

both the supplementary agreements dated 8

th

March, 2002

and 30

th

July, 2004. Therefore, the arbitration clause

mentioned in Clause 15 of the Arbitration agreement

dated January 12, 2002 is valid and the appellant is

entitled to invoke the arbitration clause for settling

their disputes. We, therefore, answer the point no.1 in

favour of the appellant.

24

Page 25 C.A.@ slp(c)No.19951 of 2013

Answer to Point nos.2 and 3

32. We answer point nos. 2 and 3 together since they

are interrelated.

It is the claim of the respondent no.3 that the

suit was filed by Respondent no. 1 under section 9 of

CPC and not section 45 of the A&C Act. Respondent no.3

further placed reliance upon the decision of this Court

in Ganga Bai v. Vijay Kumar & Ors.

9

to hold that:

“15. … There is an inherent right in every

person to bring suit of a civil nature and

unless the suit is barred by statute one may,

at ones peril, bring a suit of one's choice. It

is no answer to a suit, howsoever frivolous the

claim, that the law confers no such right to

sue. A suit for its maintainability requires no

authority of law and it is enough that no

statute bars the suit. But the position in

regard to appeals is quite the opposite. The

right of appeal inheres in no one and therefore

an appeal for its maintainability must have the

clear authority of law. That explains why the

right of appeal is described as a creature of

statute.”

(emphasis supplied by this Court)

Therefore, the learned senior counsel appearing on

behalf of respondent no. 3 places reliance upon this

9

(1974) 2 SCC 393

25

Page 26 C.A.@ slp(c)No.19951 of 2013

decision to contend that the Calcutta High Court

(exercising its ordinary original jurisdiction) has

the jurisdiction (territorial as well as pecuniary) to

entertain the present suit under section 9 of CPC and

grant of such interim injunctive relief as it deems

fit under Order 39 Rules 1 and 2 of the CPC is

permissible in law.

33.We are inclined to reject this contention raised

by the learned senior counsel appearing on behalf of

Respondent no. 3. A careful reading of the decision

leaves no doubt in the mind as has been held in

Ganga Bai’s case (supra) that:

“15. … There is an inherent right in

every person to bring suit of a civil

nature and unless the suit is barred

by statute one may, at ones peril,

bring a suit of one's choice……”

(emphasis laid by this Court)

34. The learned senior counsel for respondent no. 3

further places reliance upon the Constitution Bench

26

Page 27 C.A.@ slp(c)No.19951 of 2013

decision of seven Judges in SBP & Co. v. Patel

Engineering Ltd. & Anr.

10

wherein it was held that:

“19…..When the defendant to an action

before a judicial authority raises the

plea that there is an arbitration

agreement and the subject matter of

the claim is covered by the agreement

and the plaintiff or the person who

has approached the judicial authority

for relief, disputes the same, the

judicial authority, in the absence of

any restriction in the Act , has

necessarily to decide whether, in

fact, there is in existence a valid

arbitration agreement and whether the

dispute that is sought to be raised

before it, is covered by the

arbitration clause….”

(emphasis laid by this Court)

35.We have already held that the Principal Agreement

dated 12

th

January, 2002 continues to be in force with

its arbitration clause in place. We have also

mentioned, while answering point no. 1, that section 5

of the A&C act will be applicable to Part II of the

Act as well. The Agreement dated 12

th

January, 2002

remains valid and the arbitration clause, with all

fours, will be applicable to the parties concerned to

10

(2005) 8 SCC 618

27

Page 28 C.A.@ slp(c)No.19951 of 2013

get their disputes arbitrated and resolved in the

Arbitration as per the Rules of ICC. The contention

raised by the learned senior counsel for Respondent

no.2, Mr. K.K. Venugopal regarding the maintainability

of the suit while examining the interlocutory order in

the appeals, is therefore, untenable in law.

36. The fact that CPIL, which initially was a non-

signatory to the Agreement does not jeopardize the

arbitration clause in any manner. In this connection,

we are inclined to record an observation made in the

three Judge Bench decision of this Court in Chloro

Controls India Pvt. Ltd. (supra), wherein it was held

as under:

“107. If one analyses the above cases

and the authors' views, it becomes

abundantly clear that reference of

even non-signatory parties to

arbitration agreement can be made. It

may be the result of implied or

specific consent or judicial

determination. Normally, the parties

to the arbitration agreement calling

for arbitral reference should be the

same as those to the an action. But

this general concept is subject to

28

Page 29 C.A.@ slp(c)No.19951 of 2013

exceptions which are that when a

third party, i.e. non-signatory

party, is claiming or issued as being

directly affected through a party to

the arbitration agreement and there

are principal and subsidiary

agreements , and such third party is

signatory to a

subsidiary agreement and not to the

mother or principal agreement which

contains the arbitration clause, then

depending upon the facts and

circumstances of the given case, it

may be possible to say that even such

third party can be referred

to arbitration .”

(Emphasis laid by this Court)

37. The respondent no.1 has filed a suit seeking two

remedies against the appellants: firstly, that the

Arbitration Agreement contained in Clause 15 of the

Agreement dated January 12, 2002 is void and/or

unenforceable and/or has become inoperative and/or

incapable of being performed, and secondly, the

respondent no.1 sought permanent injunction

restraining the appellant herein from initiating and/

or continuing with the impugned Arbitration

proceedings bearing case no. 18582/ARP pursuant to the

29

Page 30 C.A.@ slp(c)No.19951 of 2013

Impugned Arbitration Agreement contained in clause 15

of the Agreement dated January 12, 2002 and the

Request for Arbitration dated March 21, 2012 and the

communication dated April 02, 2012 issued by defendant

no. 8 in the Arbitration proceedings connected

therewith and incidental thereto.

Since, we have already held that the arbitration

clause is valid, suit filed by the respondent no.1 for

declaration and permanent injunction is unsustainable

in law and the suit is liable to be dismissed.

38. In view of the above, we direct the parties to

resolve their disputes through arbitration as

mentioned in clause 15 of the letter of Agreement

dated 12

th

January, 2002 in accordance with the Rules

of ICC. We have also seen from the written submission

of the appellants counsel that the appellants have

already initiated an arbitration proceeding. In such

case, the parties shall continue with the arbitration

proceeding since the suit filed for permanent

30

Page 31 C.A.@ slp(c)No.19951 of 2013

injunction against the arbitration proceeding is

dismissed by setting aside the impugned judgment and

final order in A.P.O. No. 13 of 2013 passed by the

High Court of judicature at Calcutta on 04.06.2013.

Accordingly, the appeal is allowed, but no costs.

…………………………………………………J.

[G.S. SINGHVI]

…………………………………………………… J.

[V. GOPALA GOWDA]

New Delhi,

December 10, 2013

31

Reference cases

Description

Legal Notes

Add a Note....