As per case facts, petitioners' land was taken by MTNL in 1989 without compensation, despite parallel proceedings under the ULC Act and LA Act. MTNL constructed buildings on the land ...
C-WP3702_05.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO.3702 OF 2005
Chirag Shashikant Shah and others … Petitioners
Vs.
State of Maharashtra and others … Respondents
WITH
INTERIM APPLICATION NO.15159 OF 2024
IN
WRIT PETITION NO.3702 OF 2005
---
Mr. Kailas Dewal a/w. Mr. Yash Dewal with Mr. Ashwin Kulkarni i/b. Mr. Kailas
Dewal for Petitioners.
Mr. O. A. Chandurkar, Additional GP with Ms. G. R. Raghuwanshi, AGP for
Respondent Nos.1 to 6-State.
Mr. Niranjan P. Shimpi for Respondent No.7.
CORAM : MANISH PITALE &
SHREERAM V. SHIRSAT, JJ.
Reserved on :AUGUST 07, 2026
Pronounced on:SEPTEMBER 07, 2026
JUDGEMENT : (Per Justice Manish Pitale)
. The petitioners herein seek directions against the respondents to
initiate proceedings for acquisition of 6900 sq.mtrs. land at CTS
No.1917 (Old Survey No.37), in Village Bhayander, Mumbai. It is an
admitted position that the said land is in possession of respondent No.7 -
Mahanagar Telephone Nigam Limited (MTNL) since the year 1989.
MTNL has constructed its building and it has been utilizing the said land
from the year 1989. The chronology of events narrated hereinbelow
would show two sets of proceedings concerning the subject land, one
under the Urban Land (Ceiling and Regulation) Act, 1976 (ULC Act)
and the other under the Land Acquisition Act, 1894 (LA Act). It is the
case of the petitioners that although the said land admeasuring 6900
1/27
C-WP3702_05.doc
sq.mtrs. has been utilized by respondent No.7 MTNL for all these years,
the petitioners have not been paid compensation and no acquisition
proceedings were undertaken in respect of the said land.
2. The writ petition was initially filed by Mrs. Evelyn Paul Pereira
and others. Due to passage of time, some of the original petitioners were
deleted and upon the demise of Mrs. Evelyn Paul Pereira, her legal
representatives were brought on record. Subsequently, the said
petitioners on record of this writ petition executed a registered deed of
transfer of actionable claims. On the basis of the said document, an
application was moved for substitution of the said original petitioners by
the present petitioners in whose favour the said document was executed.
By an order dated 20.02.2026, the said application was allowed.
Accordingly, the present petitioners came on record. Hence, reference to
petitioners in this judgment and order in the chronology of events at
relevant places is to be taken as reference to the predecessor of the
petitioners. The petitioners were owners of lands in Village Bhayander,
District Thane, including the said land admeasuring 6900 sq.mtrs. The
said lands were notified for acquisition in the year 1982. Notification
under Section 4 of the LA Act was issued on 10.11.1982 and Declaration
under Section 6 thereof was issued on 28.11.1985.
3. While these proceedings were undertaken parallelly, proceedings
under the ULC Act were also undertaken from the year 1976 onwards.
Accordingly, returns under Section 6(1) of the ULC Act were submitted
in respect of lands owned in Village Bhayander. On 26.10.1984, the
Deputy Collector and Competent Authority under the ULC Act passed
an order declaring land to the extent of 29,939 sq.mtrs. as surplus. A
revision proceeding was initiated before the State Government in that
regard.
4. In the meanwhile, suits were filed challenging the Notification
2/27
C-WP3702_05.doc
under Section 4 and Declaration under Section 6 of the LA Act. This
included Regular Civil Suit No.1050 of 1985 filed in respect of the lands
of the petitioners. In the said suit, written statement was filed on behalf
of the State authorities. The acquisition, inter alia, was for the benefit of
MTNL. Hence, in 1987, MTNL deposited an amount of Rs.9,13,996/-
with the Special Land Acquisition Officer (SLAO). In the said suit, an
order of status-quo was operating and therefore, in 1988, MTNL filed an
application for vacating the order of status-quo in respect of the subject
land admeasuring 6900 sq.mtrs. The petitioners placed their say on
record, stating that if acquisition was withdrawn from the remaining
portion, possession of 6900 sq.mtrs. land could be handed over to
MTNL. On 21.12.1988, the concerned Civil Court at Thane, considering
the said suit, vacated the order of status-quo in respect of 6900 sq.mtrs.
of land, which is subject matter of the present writ petition, in view of
undertaking given by the respondents i.e. the State authorities that they
would withdraw acquisition in respect of the remaining land notified for
acquisition.
5. In this backdrop, on 17.04.1989, the petitioners handed over
possession of the subject land admeasuring 6900 sq.mtrs. to MTNL.
There is no dispute about the said fact. In the proceedings under the
ULC Act, the revision proceeding was disposed of by the State
Government, taking note of the subsequent event of possession of 6900
sq.mtrs. of land being handed over to MTNL and thereupon, setting
aside the order dated 26.10.1984 to remand the matter back to the
competent authority under the ULC Act.
6. Upon remand, the competent authority under the provisions of the
ULC Act passed an order on 24.01.1990, declaring surplus land of
18,941 sq. mtrs. excluding 6900 sq.mtrs. i.e. the subject land from the
surplus land. The respondent State Government directed the competent
3/27
C-WP3702_05.doc
authority under Section 35 of the ULC Act to revise the said order dated
24.01.1990. Accordingly, on 20.08.1991, the competent authority passed
an order under Section 45 of the ULC Act reversing its own view taken
in the order dated 24.01.1990, to hold that the subject land admeasuring
6900 sq.mtrs. was part of the surplus land. Aggrieved by the said order,
one of the original owners filed an appeal under Section 33 of the ULC
Act. During this period, on 04.03.1992, the respondent No.5 Collector,
Thane informed respondent No.7 MTNL that the land acquisition
proposal stood cancelled due to declaration of the subject land as surplus
under the ULC Act.
7. On 23.03.1992, the appellate authority dismissed the appeal,
holding that the owners could claim compensation only under the ULC
Act and not under the LA Act. Aggrieved by the said order, the
petitioners filed Writ Petition No.3891 of 1992 before this Court to
challenge the said order passed by the appellate authority. In the said
pending Writ Petition No.3891 of 1992, the respondent No.7 MTNL,
which was also added as a party, moved an application bearing Civil
Application No.5510 of 1993 for a direction that its name should be
recorded in the property card. On 08.02.1994, this Court allowed the
application and accordingly, the name of MTNL was reflected in the
property card.
8. On 10.12.1999, the respondent SLAO informed MTNL that since
it was no longer necessary to acquire the subject land under the
provisions of the LA Act, the aforesaid amount deposited by MTNL was
refunded. Accordingly, Rs.9,08,784/- deposited by MTNL was refunded
to it after deducting amount of Rs.5,212/- towards government
establishment charges, joint measurement charges and newspaper
advertisement bills. The respondents in Writ Petition No.3891 of 1992
filed their affidavits and the writ petition was taken up for consideration.
4/27
C-WP3702_05.doc
9. By an order dated 04.02.2003, this Court allowed the said writ
petition and remanded the matter to the competent authority. It was
directed that order dated 20.08.1991 would be treated as notice. On
21.10.2003, the competent authority passed its order confirming the
order dated 24.01.1990, thereby excluding the subject land from surplus
land under the provisions of the ULC Act. Hence, on 03.04.2004, the
petitioner issued notice to the respondent to initiate land acquisition
proceedings concerning the subject land admeasuring 6900 sq.mtrs. or in
the alternative, to return the said land. In this backdrop, on 06.05.2005,
the present petition was filed. The petitioners prayed for direction to the
respondent Nos.1 to 6 to initiate acquisition proceedings under the LA
Act to acquire the subject land. In the alternative, the petitioners prayed
for a direction to the respondents to handover vacant and peaceful
possession of the subject land after demolishing the structures standing
thereon. The respondents filed their reply affidavits in the writ petition.
On 21.07.2006, this Court directed respondent No.7 MTNL to deposit an
amount of Rs.5 lakhs for the time being towards compensation for
acquisition of the subject land admeasuring 6900 sq.mtrs. The said
amount was indeed deposited by MTNL in this Court and it has been
earning interest. On 29.09.2006, this Court granted Rule in the writ
petition. As noted hereinabove, by order dated 20.02.2026, the present
petitioners substituted the original petitioners and they have pursued the
present writ petition.
10. Mr. Kailas Dewal, learned counsel appearing for the petitioners
submitted that this was a classic case of violation of right to property of
the petitioners guaranteed under Article 300A of the Constitution of
India. It was submitted that the Supreme Court in the cases of Kolkata
Municipal Corporation and another Vs. Bimal Kumar Shah and others,
(2024) 10 SCC 533 and Bernard Francis Joseph Vaz and others Vs.
Government of Karnataka, (2025) 7 SCC 580 recognized right to
5/27
C-WP3702_05.doc
property as a human right and seven valuable sub-rights were also
recognized therein. It was submitted that the approach of the
respondents, in the present case, demonstrates violation of such valuable
rights of the petitioners.
11. It was submitted that although possession of the subject land
admeasuring 6900 sq.mtrs. was taken as far back as on 17.04.1989, till
date, no compensation has been paid and no effort has been made to
acquire the said piece of land. It was submitted that the parallel
proceedings under the LA Act and the ULC Act undertaken by the
respondent authorities in respect of the subject land, had resulted in a
situation where the petitioners stood deprived of valuable land in lieu of
which no compensation has been paid till date. MTNL has utilized the
said land by making constructions and even earning substantial amounts
of money by giving out parts of the structures on rent and lease, while
the petitioners have been continuously deprived of their valuable rights.
12. Since the petitioners were pursuing their remedies under the ULC
Act diligently, which culminated in the said order dated 21.10.2003 and
they ultimately pursued their claim for payment of compensation by
acquisition of the subject land, it cannot be said that their claim is hit by
delay and / or laches. It was highlighted that although the respondents
claimed that an appeal had been filed against the said order dated
21.10.2003 of the competent authority under the ULC Act, no details
were forthcoming and the petitioners were never put to notice thereof. In
any case, upon repeal of the ULC Act in the State of Maharashtra from
29.11.2007, as per Section 3 of the Repealing Act, all pending
proceedings stood abated. On this basis, it was submitted that the order
dated 21.10.2003 passed by the competent authority under the ULC Act
in favour of the petitioners continued to operate, thereby indicating that
the petitioners are entitled to pursue their prayers made in the present
6/27
C-WP3702_05.doc
writ petition. In support of the aforesaid contentions, reliance was placed
on the judgement of the Supreme Court in the case of Vidya Devi Vs.
State of Himachal Pradesh and others, (2020) 2 SCC 569 and
judgement of this Court in the case of Voltas Limited and another Vs.
Additional Collector and Competent Authority, Thane and others, 2008
(5) ALL MR 537.
13. It was further submitted that in the face of such admitted facts, the
respondents are not entitled to challenge the correctness and veracity of
the said order dated 21.10.2003 passed by the competent authority under
the ULC Act as the said order had become final and binding on all
parties. The respondents are not entitled to claim that the said order is
bad on merits or that, it is a nullity. In support of this contention, reliance
was placed on judgement of the Supreme Court in the case of V. S.
Charati Vs. Hussein Nhanu Jamadar (dead) by LRs, (1999) 1 SCC 273.
On this basis, it was submitted that the contentions raised on behalf of
the respondents in that regard do not deserve to be considered.
14. It was submitted that the respondents did not take any steps even
during pendency of the petition to initiate land acquisition proceedings,
while respondent No.7 MTNL continued to enjoy the said property. The
amount deposited by MTNL towards compensation for acquisition of the
subject land was also refunded by the respondent SLAO and therefore,
MTNL has enjoyed the land free of cost at the expense of the petitioners.
On this basis, it was submitted that the respondents ought to to be
directed to initiate acquisition proceedings in respect of the subject land
admeasuring 6900 sq.mtrs. It was submitted that the acquisition ought to
be undertaken under the Right to Fair Compensation and Transparency
in Land Acquisition, Rehabilitation and Resettlement Act 2013 (Act of
2013). It was further submitted that the petitioners need to be
compensated for being deprived of possession from 17.04.1989 onwards
7/27
C-WP3702_05.doc
in a suitable manner, in the interest of justice. It was also submitted that
alternatively, the subject land ought to be restored to the petitioners with
a direction to the respondents to demolish the structures constructed
thereon.
15. Mr. Chandurkar, learned Additional Government Pleader as also
Ms. Raghuwanshi, learned AGP appearing for respondent Nos.1 to 6-
State relied upon the reply affidavits filed on behalf of the said
respondents in this writ petition. It was submitted that the petitioners and
the respondent No.7 MTNL had mutually agreed as regards possession
of the subject land being handed over to MTNL during the pendency of
the said suit. This resulted in the land acquisition proposal itself being
withdrawn. It was emphasized that the said decision and actions were
not taken by the SLAO and the State authorities. On this basis, it was
submitted that if there is any liability to pay compensation to the
petitioners, it is squarely that of respondent No.7 MTNL. It was further
submitted that if a land acquisition proposal was submitted afresh, the
matter could be considered accordingly.
16. Mr. Shimpi, learned counsel appearing for respondent No.7
MTNL vehemently opposed the present petition. He raised objection of
gross delay and laches on the part of the petitioners. It was submitted
that when possession was handed over, as far back as on 17.04.1989,
filing of the present petition in May 2005 i.e. after 16 years,
demonstrates that the petitioners cannot be allowed to agitate their
grievances after such a long period of time. It was submitted that during
the interregnum, the petitioners never raised any grievance with regard
to compensation for the subject land admeasuring 6900 sq.mtrs. The
respondent No.7 MTNL has been in continued possession of the subject
land since April 1989, several structures have been constructed and a
number of third parties are in possession of such structures. In that light,
8/27
C-WP3702_05.doc
it was submitted that there was no question of returning the vacant
possession of the subject land to the petitioners.
17. It was further submitted that the present petition also raised
disputed questions of facts, which cannot be decided in writ jurisdiction.
According to the respondent No.7 MTNL, the disputed questions of
facts included the nature of out of court settlement between the
petitioners and MTNL with regard to the subject land admeasuring 6900
sq.mtrs. It was submitted that the contents of the application filed by
MTNL in the aforementioned suit wherein status-quo was operating, the
say of the petitioners therein and the order dated 21.12.1988 passed by
the concerned Civil Court, clearly indicate that there are number of
versions with regard to the nature of negotiations between the parties,
which ultimately led to possession of the subject land being handed over
to MTNL. In such a scenario, it was submitted that the petitioners cannot
be permitted to unsettle the status of the claim of the respondent MTNL
in the subject land. The writ petition itself was filed after more than 16
years of handing over of possession and today, after 37 years of the
possession having been handed over, no relief can be granted to the
petitioners. It was further submitted on behalf of the respondent No.7
MTNL that in such a scenario, the petitioners can be said to have waived
their rights, if any, in the subject land.
18. It was submitted that the petitioners cannot be permitted to take
advantage of the fortuitous circumstance of the ULC Act being repealed
during the pendency of the present petition. The petitioners can also not
be permitted to take advantage of the fact that the LA Act also stood
repealed during the pendency of the present writ petition and they cannot
be permitted to now invoke the Act of 2013 for seeking compensation in
respect of the subject land. It was submitted that in such a situation, the
writ petition deserved to be dismissed. If any relief is granted to the
9/27
C-WP3702_05.doc
petitioners, it would amount to dual benefit to them as the subject land
stood excluded from surplus land under the ULC Act and the petitioners
would end up enjoying compensation under the acquisition process. This
was an additional ground invoked on behalf of respondent No.7 to seek
dismissal of the petition.
19. Having considered the rival submissions, this Court finds that the
peculiar circumstances created by the turn of events in the present case,
have resulted in respondent No.7 MTNL retaining possession of the
subject land admeasuring 6900 sq.mtrs. from 17.04.1989 onwards, with
structures being constructed thereon and third parties also being in
possession of parts thereof. In such a situation, the alternative relief
sought by the petitioners of a direction to the respondents, particularly
respondent No.7 MTNL to handover vacant and peaceful possession of
the subject land after demolishing the structures standing thereon is
clearly impractical and hence does not deserve consideration. But, the
question as to whether the petitioners can be compensated and if so, in
what manner, certainly deserves consideration.
20. The parallel proceedings under the ULC Act and the LA Act
initiated in respect of the subject land has led to a situation where the
petitioners stood deprived of enjoyment of the subject land from
17.04.1989 onwards. The admitted facts in the present case indeed
indicate that the exercise of determining quantum of compensation and
payment thereof to the petitioners was not undertaken. Such admitted
facts include initiation of land acquisition for larger pieces of land in
Village Bhayander, District Thane belonging to the petitioners, which
stood challenged before the Civil Court wherein an order of status-quo
had the effect of possession of the lands, including the subject land,
being retained by the petitioners. Respondent No.7 MTNL was
interested in the subject land admeasuring 6900 sq.mtrs. and therefore, it
10/27
C-WP3702_05.doc
had deposited an amount of Rs.9,13,996/- with the respondent SLAO.
As a result of the order dated 21.12.1988 passed by the said Civil Court
in Regular Civil Suit No.1050 of 1985, possession of the subject land
was handed over to the respondent No.7 MTNL while in the backdrop,
the proceedings under the ULC Act continued. Eventually, the
acquisition proceeding itself was withdrawn by the SLAO and
accordingly, on 10.12.1999, the aforesaid amount deposited by MTNL
was refunded to it. Thus, MTNL has continued to remain in possession
of the subject land without payment of any amount towards
compensation to the petitioners.
21. It is also an admitted position on facts that although the order
dated 24.01.1990 passed by the competent authority under the ULC Act,
excluding the subject land admeasuring 6900 sq.mtrs. from the surplus
land, was set aside by the Revising Authority and the appeal there
against was dismissed, such orders were set aside by this Court by order
dated 04.02.2003, allowing Writ Petition No.3891 of 1992 filed by the
petitioners. Upon remand, the competent authority, by its order dated
21.10.2003, confirmed the earlier order dated 24.01.1990, as a
consequence of which, the subject land stood excluded from surplus land
under the ULC Act. This is a crucial fact in the present case. Although
the respondents claim that an appeal against the said order dated
21.10.2003 passed by the competent authority under the ULC Act was
filed, the said appeal remained pending without any orders thereon.
22. We find substance in the petitioners placing reliance on the
judgement of this Court in the case of Voltas Limited and another Vs.
Additional Collector and Competent Authority, Thane and others
(supra), wherein it was held that upon the Repealing Act having its
effect from 29.11.2007 in Maharashtra, whereby the ULC Act stood
repealed, by operation of Section 3 of the Repealing Act, all pending
11/27
C-WP3702_05.doc
proceedings under the ULC Act stood abated. Therefore, the order dated
21.10.2003 passed by the competent authority, confirming the earlier
order dated 24.01.1990 excluding the subject land from surplus land,
stood undisturbed and the benefit thereof must accrue to the petitioners.
23. The respondents, particularly respondent No.7 MTNL, have
raised a serious objection with regard to gross delay and laches on the
part of the petitioners as also the aspect of waiver of rights with efflux of
time. It is claimed that with passage of time and gross delay on the part
of the petitioners to seek relief in an appropriate manner, the possession
of MTNL acquired legitimacy.
24. The admitted position on facts recorded in the form of
chronological sequence of events hereinabove shows that after the
competent authority had passed its order dated 21.10.2003 upon remand
from this Court, the earlier order dated 24.01.1990, excluding the subject
land admeasuring 6900 sq.mtrs. from the surplus land, stood confirmed.
Till such time that the said order was passed, the matter was in a state of
flux for the petitioners. The appeal filed on their behalf had been
dismissed by the appellate authority and the subject land was
categorized as ‘surplus’ under the ULC Act. So long as the aforesaid
status remained, the petitioners could not have agitated their claim for
compensation under the LA Act with regard to the possession of the
subject land being handed over to MTNL on 17.04.1989. The order
dated 21.10.2003 passed by the Competent Authority re-confirmed the
status of the subject land as not being surplus. It is a matter of record
that within reasonable time from the order dated 21.10.2003 i.e. on
03.04.2004, the petitioners sent a legal notice through their advocate to
the respondents calling upon them to compute and pay compensation for
the subject land, failing which, the respondents were called upon to
handover vacant and peaceful possession of the subject land after
12/27
C-WP3702_05.doc
demolishing the structures constructed thereon.
25. Thereafter, on 06.05.2005, the petitioners filed the present writ
petition claiming the aforesaid reliefs in the context of the subject land.
Considering the sequence of events, which is not disputed by the
respondents, it becomes clear that the petitioners pursued the remedies
available to them under the ULC Act and also as regards their claim for
payment of compensation in the light of the possession of the subject
land being handed over to MTNL on 17.04.1989. In the facts of the
present case, it cannot be said that the claim of the petitioners agitated in
the present writ petition suffers from delay and / or laches. It can also
not be said that the petitioners waived their rights because of the fact that
they filed the present writ petition in the year 2005. The fact that the
present writ petition filed as far back as in the year 2005, wherein Rule
was issued as far back as on 29.09.2006, could not be taken up for
consideration and final disposal for 21 years, cannot be a ground to
deprive relief to the petitioners, if they have otherwise made out the case
in their favour. Hence, the arguments of the respondents pertaining to
delay and laches as also waiver are rejected.
26. Although the right to property is no longer a fundamental right
and it is a constitutional right under Article 300A of the Constitution of
India, the Supreme Court in a number of judgements, including in the
cases of Kolkata Municipal Corporation and another Vs. Bimal
Kumar Shah and others (supra) and Bernard Francis Joseph Vaz
and others Vs. Government of Karnataka (supra), has held that the
said right is a human right, which cannot be casually denied to the
owners of the land. In the case of Kolkata Municipal Corporation and
another Vs. Bimal Kumar Shah and others (supra), the Supreme
Court has recognized seven sub-rights in the right to property, which
include the right to notice, the right to be heard, the right to a reasoned
13/27
C-WP3702_05.doc
decision, duty to acquire only for public purpose, the right of restitution
or fair compensation, the right to an efficient and expeditious process
and the right of conclusion.
27. In the present case, these rights have to be construed in the
backdrop of the fact that possession of the subject land admeasuring
6900 sq.mtrs. was taken as far back as on 17.04.1989. The beneficiary of
the said land i.e. respondent No.7 MTNL had deposited amount of
Rs.9,13,996/- towards compensation payable to the claimants with the
SLAO. In the affidavit in reply dated 24.09.2002 filed by the SLAO in
the aforementioned Writ Petition No.3891 of 1992, it was specifically
stated that the said amount was towards 80% of the compensation
amount. In the very same affidavit, the SLAO stated that by a demand
draft dated 10.12.1999, amount of Rs.9,08,784/- was refunded to MTNL
after deducting amount of Rs.5,212/- towards government establishment
charges, joint measurement charges and newspaper advertisement bills.
Thus, payment of compensation in lieu of utilization of the subject land
admeasuring 6900 sq.mtrs. was always recognized and contemplated by
the respondents themselves.
28. The exercise of withdrawing from acquisition was undertaken by
the SLAO by stating that it was no longer necessary to acquire the land
under the LA Act. This was perhaps because the proceedings under the
ULC Act, at the relevant time i.e. in the year 1999, were at the stage of
challenge raised by the petitioners in Writ Petition No.3891 of 1992 to
the order of the appellate authority dismissing the appeal and confirming
the order of the competent authority, including the subject land
admeasuring 6900 sq.mtrs. in surplus land. But, the order passed by this
Court on 04.02.2003 in Writ Petition No.3891 of 1992 changed the
picture as the said order of the competent authority was set aside and the
matter was remanded for consideration afresh. The subsequent order of
14/27
C-WP3702_05.doc
the competent authority dated 21.10.2003 was in favour of the
petitioners as the original order dated 24.01.1990, excluding the subject
land admeasuring 6900 sq.mtrs. from surplus land, stood confirmed.
29. As noted hereinabove, the petitioners moved with alacrity, issued
a legal notice to the respondents and promptly filed the present writ
petition in May 2005 for the aforesaid relief. Thus, there is no
impediment in considering the claim of the petitioners on merits as
regards their entitlement to be compensated for utilization of the subject
land and if the said compensation is denied then their right towards
restoration of the land in their favour. We find substance in reliance
placed on behalf of the petitioners on the judgement of the Supreme
Court in the case of V. S. Charati Vs. Hussein Nhanu Jamadar (dead)
by LRs (supra), wherein it was held that a decision rendered by tribunal
or a court becomes final and binding on the parties when it is not
challenged and even if the decision is wrong, it does not amount to a
nullity.
30. In the present case, though respondent No.7 MTNL, in its
affidavit in reply in the present petition, claimed that the respondents had
challenged the said order dated 21.10.2003 passed by the competent
authority in favour of the petitioners, no further details were
forthcoming. In any case, by operation of Section 3 of the Repealing
Act, which repealed the ULC Act in Maharashtra with effect from
29.11.2007, a proceeding, if any, to challenge the said order of the
competent authority, stood abated. Thus, the order dated 21.10.2003
attained finality and the respondents cannot be permitted to claim that it
was a nullity, even if for the sake of arguments, it could be said to be
wrong. Thus, the petitioners have successfully made out their case for
claiming compensation for the subject land utilized by respondent No.7
MTNL. We find that the alternative prayer made on behalf of the
15/27
C-WP3702_05.doc
petitioners for restoration of possession of the said land with structures
standing thereon being demolished, would lead to grave inconvenience
and it would be impractical. Therefore, the only relief that can be
considered is an appropriate direction for determination and payment of
compensation for the subject land admeasuring 6900 sq.mtrs.
31. We find support in the judgements of the Supreme Court rendered
in similar circumstances, where granting relief of restoration of land to
the claimants, was found to be impractical, as the subject land already
stood utilized for public purpose. In the case of Competent Authority vs.
Barangore Jute Factory and others, (2005) 13 SCC 477, the Supreme
Court found that the impugned notification was liable to be quashed, the
consequence of which would be restoration of land to the claimants. But,
upon finding that the subject land was already utilized for public purpose
of construction of a national highway, the Supreme Court found that no
useful purpose would be served by considering the consequential relief
of restoration of possession of the land to the claimants. In that light, the
Supreme Court proceeded to direct the authorities to determine
compensation from a future date, so that justice was done to the
claimants/land owners.
32. In a recent judgement rendered in the case of Bernard Francis
Joseph Vaz and others vs. Government of Karnataka (supra), the
Supreme Court adopted a similar approach. After referring to the said
judgement in the case of Competent Authority vs. Barangore Jute
Factory and others (supra), the Supreme Court further took note of a
series of judgements, recognizing the right to property under Article
300A of the Constitution as a human right. In the said judgment, the
Supreme Court also referred to the judgements concerning the question
of delay and laches, including judgement of the Supreme Court in the
case of Vidya Devi vs. State of Himachal Pradesh and others (supra).
16/27
C-WP3702_05.doc
33. After referring to a number of judgements on the nature of right
under Article 300A of the Constitution of India, in the case of Bernard
Francis Joseph Vaz and others vs. Government of Karnataka
(supra), the Supreme Court observed as follows:
“43. Right to property ceased to be a fundamental right by
the Constitution (Forty-fourth Amendment) Act,
1978, however, it continues to be a human right in a
welfare State, and a constitutional right under Article
300-A of the Constitution.
44. Article 300-A of the Constitution provides that no
person shall be deprived of his property save by
authority of law. The State cannot dispossess a citizen
of his property except in accordance with the
procedure established by law.
45. This Court in the aforesaid case of Vidya Devi
[(2020) 2 SCC 569 : (2020) 1 SCC (Civ) 799]
observed that in a democratic polity governed by the
rule of law, the State could not have deprived a
citizen of their property without the sanction of law. It
was further observed that the State being a welfare
State governed by the rule of law cannot arrogate to
itself a status beyond what is provided by the
Constitution.
46. Recently, this Court in the aforesaid case of Ultra-
Tech Cement Ltd. v. Mast Ram, [(2025) 1 SCC 798 :
(2025) 1 SCC (Civ) 379 : (2025) 253 Comp Cas 1]
observed that the Government as a welfare State
ought to have proactively intervened in the matter
with a view to ensure that the requisite amount
towards compensation is paid at the earliest. It was
further observed that the State cannot abdicate its
constitutional and statutory responsibility of payment
of compensation by arguing that its role was limited
to initiating acquisition proceedings. It was, therefore,
observed that the delay in the payment of
compensation, in accordance with law, to the
landowners after taking away ownership of the
subject land from them is in contravention to the
spirit of the constitutional scheme of Article 300-A
and the idea of a welfare State.
47. In the aforesaid case of Ultra-Tech Cement, this Court
further observed that acquisition of land for public
17/27
C-WP3702_05.doc
purpose is undertaken under the power of eminent
domain of the Government much against the wishes
of the owners of the land which gets acquired. It was,
therefore, observed that when such a power is
exercised, it is coupled with a bounden duty and
obligation on the part of the government body to
ensure that the owners whose lands get acquired are
paid compensation/awarded amount as declared by
the statutory award at the earliest.
48. It will also be appropriate for the purpose of the
present discussion to refer to the judgment of this
Court in K. Krishna Reddy v. Collector (LA) [(1988)
4 SCC 163] , specifically in para 12, it was observed
thus: (SCC pp. 166-67)
‘12. We can very well appreciate the anxiety and
need of claimants to get compensation here
and now. No matter what it is. The lands
were acquired as far back in 1977. One
decade has already passed. Now the remand
means another round of litigation. There
would be further delay in getting the
compensation. After all money is what
money buys. What the claimants could have
bought with the compensation in 1977
cannot do in 1988. Perhaps, not even one
half of it. It is a common experience that the
purchasing power of rupee is dwindling.
With rising inflation, the delayed payment
may lose all charms and utility of the
compensation. In some cases, the delay may
be detrimental to the interests of claimants.
The Indian agriculturists generally have no
avocation. They totally depend upon land. If
uprooted, they will find themselves nowhere.
They are left high and dry. They have no
savings to draw. They have nothing to fall
back upon. They know no other work. They
may even face starvation unless
rehabilitated. In all such cases, it is of utmost
importance that the award should be made
without delay. The enhanced compensation
must be determined without loss of time. The
appellate power of remand, at any rate ought
not to be exercised lightly. It shall not be
resorted to unless the award is wholly
unintelligible. It shall not be exercised unless
18/27
C-WP3702_05.doc
there is total lack of evidence. If remand is
imperative, and if the claim for enhanced
compensation is tenable, it would be proper
for the appellate court to do modest best to
mitigate hardships. The appellate court may
direct some interim payment to claimants
subject to adjustment in the eventual award.’
49. It cannot be gainsaid that the appellants herein have
been deprived of their legitimate dues for almost 22
years ago. It can also not be controverted that money
is what money buys. The value of money is based on
the idea that money can be invested to earn a return,
and that the purchasing power of money decreases
over time due to inflation. What the appellants herein
could have bought with the compensation in 2003
cannot do in 2025. It is, therefore, of utmost
importance that the determination of the award and
disbursal of compensation in case of acquisition of
land should be made with promptitude.”
34. In the light of the said position of law clarified and reiterated by
the Supreme Court in a number of judgements, we find that in the facts
of the present case, the petitioners have made out a case for appropriate
directions to the respondents to determine and pay compensation to the
petitioners for utilization of the subject land admeasuring 6900 sq.mtrs.
It is undisputed that the said land has been utilized by respondent No.7
MTNL and that possession of the land was handed over to the said
respondent as far back as on 17.04.1989. The said respondent
constructed buildings on the subject land and utilized the same for its
purpose. Parts of the constructed portions have been let out on rent/lease
by the said respondent, thereby showing that it has utilized and enjoyed
the subject property from the year 1989 onwards.
35. On the other hand, the petitioners have been deprived of
enjoyment of the subject land from the year 1989 and till date, nothing
has been paid towards compensation. Amongst the seven sub-rights
recognized by the Supreme Court in the case of Kolkata Municipal
19/27
C-WP3702_05.doc
Corporation and another vs. Bimal Kumar Shah and others (supra),
the petitioners have been deprived of the right to fair compensation, the
right to an efficient and expeditious process for determination and
payment of compensation and the right to conclusion. Thus, we find that
the right of the petitioners under Article 300A of the Constitution, has
been violated in the facts and circumstances of the present case.
36. The only question which remains to be addressed is the manner in
which the petitioners are to be compensated for violation of the aforesaid
right. The chronology of events noted hereinabove shows that while
respondent No.7 MTNL had deposited an amount of Rs.9,13,996/- with
the SLAO in July 1987, specifically for the purpose of the subject land
admeasuring 6900 sq.mtrs., the said amount was never paid to the
petitioners. Instead, in December 1999, the SLAO refunded an amount
of Rs.9,08,784/- to the said respondent, after deducting a smaller amount
towards expenses, as it was found that acquisition of the subject land
was not necessary. Thus, from the very beginning, the respondent
authorities as well as respondent No.7 MTNL were aware about the fact
that if the petitioners were to be deprived of the subject land, they
deserved to be adequately compensated, in accordance with law.
37. But, till date, the petitioners have not been paid any amount
towards compensation, despite the fact that they stood deprived of
possession of the subject land as far back as on 17.04.1989. We are of
the opinion that in such circumstances, the petitioners deserve fair
compensation by recognizing their right under Article 300A of the
Constitution. While determining the specific date as reference point and
basis for determination of quantum of compensation, the chequered
history and chronology of events of the present case, need to be
considered.
38. On 17.04.1989, when possession of the subject land admeasuring
20/27
C-WP3702_05.doc
6900 sq.mtrs. was taken by MTNL, during pendency of Regular Civil
Suit No.1050 of 1985, as per order of the competent authority, under
ULC Act dated 26.10.1984, the subject land was included in surplus land
of the petitioners. Subsequently, when the State Government remanded
the matter to the competent authority under ULC, by the aforesaid order
dated 24.01.1990, the competent authority excluded the subject land
admeasuring 6900 sq.mtrs. from surplus land of the petitioners. But, by
this time, possession of the same was already taken by the MTNL.
39. Thereafter, the proceedings under the ULC Act continued, as the
order dated 24.01.1990 was revised and on 20.08.1991, the competent
authority reversed its own order and held the subject land again as part
of the surplus land of the petitioners under the ULC Act. The said order
was challenged in appeal, which was dismissed on 23.03.1992 and the
order of the appellate authority was challenged in the said Writ Petition
No.3891 of 1992. Eventually, on 04.02.2003, this Court partly allowed
the writ petition, set aside the orders of the competent authority, revising
its earlier order, as also the order of the appellate authority and remanded
the matter back to the competent authority for consideration afresh.
40. On 21.10.2003, the competent authority passed its order,
confirming its own earlier order dated 24.01.1990, whereby the said land
was excluded from surplus land. As noted hereinabove, even though
MTNL claims that the respondents had challenged the said order, in the
light of the Repeal Act, which repealed the ULC Act in the State of
Maharashtra with effect from 29.11.2007, the challenge, if any, raised to
the order of the competent authority dated 21.10.2003, abated. As noted
hereinabove, the petitioners, in this backdrop, issued a legal notice to the
respondents, claiming reliefs and eventually, on 06.05.2005, they filed
the present writ petition before this Court.
41. This Court is of the opinion that till the proceedings under the
21/27
C-WP3702_05.doc
ULC Act culminated in the order dated 21.10.2003 passed by the
competent authority, confirming its earlier order dated 24.01.1990,
excluding the surplus land of the petitioners, the question as to whether
the petitioners continued to have rights in the subject land, was in a flux.
Till the order dated 21.10.2003 was passed by the competent authority
under the ULC Act, which led to the filing of the present writ petition on
06.05.2005, it could be said that the petitioners would have found it
difficult to assert their right of compensation for deprivation of
enjoyment of the subject land. Therefore, we are of the opinion that if a
specific date is to be ascertained for determination of market value
payable towards compensation to the petitioners in a just and fair
manner, by balancing the interests of all the parties to this litigation, it
would be appropriate that the date of filing of this petition i.e.
06.05.2005, is fixed as the date for determination of market value for
payment of compensation to the petitioners.
42. In the case of Bernard Francis Joseph Vaz and others vs.
Government of Karnataka (supra), the Supreme Court, while referring
to earlier precedents, has recognized power in the High Court under
Article 226 of the Constitution of India, to shift or postpone the date of
preliminary notification for acquisition to a later date. Although in the
present case, the SLAO concluded in the year 1999 that acquisition of
the subject land was not necessary and refunded the amount deposited
by MTNL, we find that the said action was undertaken at a point in time
when challenge to the order of the competent authority under the ULC
Act, holding the subject land as part of surplus land, was still in vogue. It
cannot be ignored that notification under Section 4 of the LA Act for
acquisition of large pieces of land of the petitioners including the said
land, was issued as far back as on 10.11.1982 and that declaration under
Section 6 of the LA Act was issued on 28.11.1985. It appears that the
said notifications did not survive, in the light of the sequence of events,
22/27
C-WP3702_05.doc
including filing of Regular Civil Suit No.1050 of 1985 and the approach
adopted by the parties, leading to possession of the subject land
admeasuring 6900 sq.mtrs. being handed over to MTNL on 17.04.1989.
43. The relevant portion of the judgement of the Supreme Court in the
case of Bernard Francis Joseph Vaz and others vs. Government of
Karnataka (supra), reads as follows:
“15. It can thus be seen that the learned Single Judge of the
High Court, upon appreciation of the material placed on
record, was of the view that insofar as the opinion of the
learned Advocate General with regard to shifting of the
date of the preliminary notification to a later date is
concerned, the said opinion was beyond the scope and
ambit of the query put forth to him and consequently, the
said opinion could not have been made the basis by the
SLAO to pass the award. It is further to be seen that the
learned Single Judge of the High Court after considering
the provisions of the 1894 LA Act, the KIAD Act and
various decisions of this Court, observed that the market
value of the acquired land has to be taken as on the date
of the preliminary notification as contemplated under
Section 11 of the 1894 LA Act. Further, the learned
Single Judge of the High Court observed that only in
exceptional circumstances, where either this Court or the
High Court comes to the conclusion that the acquisition
proceedings themselves were liable to be quashed on
account of certain illegalities or infirmities in the
acquisition process/procedure, it was permissible only for
this Court in exercise of its powers under Article 32/142
or the High Courts under Article 226 of the Constitution
of India to shift the date to a later/subsequent date. It was
further observed that this power to shift the date is
available only to either this Court or the High Courts and
not definitely/certainly to the SLAOs or the State
Government.
16. We are in agreement with the findings of the learned
Single Judge of the High Court, inasmuch as the SLAO
cannot shift/postpone the date of preliminary notification.
In case, upon appreciation of the material placed on
record if this Court or the High Court, in exceptional
circumstances, came to the conclusion that the
acquisition proceedings themselves were liable to be
quashed only then by exercising inherent powers this
23/27
C-WP3702_05.doc
Court under Article 32/142 or the High Courts under
Article 226 of the Constitution of India, respectively, can
shift/postpone the date of preliminary notification to a
later date. In our considered opinion, therefore, the
learned Single Judge of the High Court rightly came to
the conclusion that the award dated 22-4-2019 be
quashed and set aside and ordered accordingly.”
44. We are of the opinion that following the position of law laid down
by the Supreme Court in the aforementioned judgements, while
exercising power under Section 226 of the Constitution, this Court can
fix a specific date for determination of market value, which would then
be the basis for payment of compensation to the petitioners. In the facts
and circumstances of the present case, we are not inclined to grant the
relief of restoration of possession of the subject land to the petitioners
and therefore, the only exercise that can be carried out is the
determination of quantum of compensation, which would amount to just,
fair and reasonable compensation in recognition of the right of
petitioners under Article 300A of the Constitution. To that extent, we are
inclined to treat this as a case where acquisition was initiated under the
LA Act, but no award was made.
45. In this context, we make a reference to Section 24(1)(a) of the Act
of 2013, to apply the provisions of the said Act insofar as they relate to
determination of quantum of compensation. In that light, the date of
filing of this writ petition i.e. 06.05.2005, is fixed as the date for
determining the market value of the subject land admeasuring 6900
sq.mtrs. Thereupon, the quantum of compensation shall be determined,
by applying the provisions of the Act of 2013 and all statutory benefits
payable under the said Act, shall be paid to the petitioners. Since the
petitioners have been deprived of possession of the subject land for the
period between 17.04.1989 and 05.05.2005, the respondents shall pay
rental compensation to the petitioners as per policy of the State. Since
24/27
C-WP3702_05.doc
MTNL has been enjoying the said property, the financial burden of the
reliefs being granted to the petitioners in this petition, shall be borne by
the MTNL. The amount of Rs.5 lakhs deposited in this Court in terms of
order dated 21.07.2006, shall be disbursed to the petitioners along with
accrued interest and it shall be adjusted in the quantum of compensation
that shall be determined, in terms of directions being issued in the
present writ petition. We find that such directions would meet the ends
of justice, in the facts and circumstances of the present case.
46. In view of the above, the writ petition is allowed in the following
terms:
(a) The respondent No.6 – Special Land Acquisition Officer is
directed to forthwith initiate the exercise of determination
of quantum of compensation payable to the petitioners by
fixing the date 06.05.2005 as the date for determination of
market value of the subject land admeasuring 6900
sq.mtrs.;
(b) the quantum of compensation shall be determined under
the provisions of the Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and
Resettlement Act 2013;
(c) the said compensation shall include all statutory benefits
payable under the provisions of the Right to Fair
Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act 2013;
(d) the said exercise of determination of quantum of
compensation shall be initiated forthwith by respondent
No.6 – Special Land Acquisition Officer, without waiting
for deposit of any amount by respondent No.7 – MTNL
25/27
C-WP3702_05.doc
and the same shall be completed within a period of six
months from the date of this order;
(e) thereupon, within one week of determination of such
quantum of compensation, the said respondent shall
intimate respondent No.7 – MTNL, who shall deposit such
amount of compensation with SLAO within two weeks of
receipt of intimation. Respondent No.6 – SLAO in turn,
shall disburse the amount to the petitioners within one
week of receiving the same from MTNL;
(f) the amount of Rs.5 lakhs deposited in this Court in terms
of order dated 21.07.2006 along with accrued interest,
shall be disbursed to the petitioners within two weeks of
the date of this order. The Registry to take necessary steps
accordingly;
(g) the aforesaid amount disbursed by the Registry to the
petitioners, shall be adjusted at the time of payment of
compensation to the petitioners, to be determined in terms
of the directions given hereinabove;
(h) the respondent No.5 – Collector is directed to forthwith
initiate the exercise of determination of rental
compensation payable to the petitioners for the period
between 17.04.1989 and 05.05.2005, in terms of the policy
of respondent – State. The said exercise shall be completed
within a period of eight weeks from the date of this order
and the amount so determined, shall be intimated to
respondent No.7 – MTNL within one week. Thereupon,
MTNL shall disburse the said amount to the petitioners
within two weeks.
26/27
C-WP3702_05.doc
47. In the light of the directions given hereinabove, Interim
Application No.15159 of 2024 is disposed of.
48. Rule is made absolute in above terms.
(SHREERAM V. SHIRSAT, J.) (MANISH PITALE, J.)
27/27
Minal / Priya
MINAL
SANDIP
PARAB
Digitally signed by
MINAL SANDIP
PARAB
Date: 2026.09.07
15:21:00 +0530
Legal Notes
Add a Note....