As per case facts, the Petitioner, a real estate developer, entered into a "Binding Heads of Terms" (HoT) with the Respondents, who are joint landowners, for a large-scale real estate ...
O.M.P.(I) (COMM.) 138/2026 Page 1 of 56
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment reserved on: 13.04.2026
Judgment pronounced on: 29.05.2026
+ O.M.P.(I) (COMM.) 138/2026
CONSCIENT INFRASTRUCTURE PVT. LTD.
.....Petitioner
Through: Mr. Dayan Krishnan, Senior
Advocate with Mr. Anirudh
Bakhru, Mr. Divyam Agarwal,
Mr. Ayush Puri, Mr. Ranvir
Singh Sisodia, Mr. Kanav
Madnani and Mr. Siddhant,
Advocates.
versus
MR. MAHESH KAPOOR & ANR.
.....Respondent
Through: Mr. Sandeep Sethi, Senior
Advocate with Mr. Manu Bajaj,
Ms. Parul, Mr. Krishna
Gambhir, Ms. Shreya Sethi and
Ms. Riya Kumar, Advocates.
CORAM:
HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
SHANKAR
JUDGMENT
HARISH VAIDYANATHAN SHANKAR, J.
1. The present Petition, filed by Conscient Infrastructure Pvt.
Ltd.
1
under Section 9 of the Arbitration and Conciliation Act, 1996
2
read with Section 151 of the Code of Civil Procedure, 1908
3
, seeks
certain ad interim reliefs and directions against Mr. Mahesh Kapoor
1
Petitioner
2
A&C Act
3
CPC
O.M.P.(I) (COMM.) 138/2026 Page 2 of 56
and Mrs. Usha Kapoor
4
.
2. The disputes between the parties are stated to arise out of an
arrangement termed as “Binding Heads of Terms of the Proposed
Collaboration for Development of the land situated in the revenue
estate of Village Aya Nagar, Mehrauli, Delhi (Jhankar Banquet)”
dated 17.05.2023
5
, executed in relation to the development of the
land admeasuring approximately 6.76 acres situated at Revenue
Estate Aya Nagar, Mehrauli, Delhi
6
.
3. By way of the present Petition, the principal relief sought is a
restraint against the Respondents, their employees, agents,
representatives, or any person acting on their behalf, from creating any
lien, charge, encumbrance, or third-party interest of any nature
whatsoever over the said Collaboration Land during the pendency of
the proceedings.
4. The Petitioner further seeks an order restraining the
Respondents from obstructing, interfering with, or otherwise impeding
the Petitioner in the performance of its obligations arising under the
Binding HoTs concerning the aforesaid Collaboration Land. In
addition thereto, the Petitioner has prayed for ad-interim ex parte
protection in terms of the aforementioned reliefs, with a further
direction that such interim protection be continued upon issuance of
notice to the Respondents.
5. With the consent of parties, this matter has been taken up for
final disposal.
FACTUAL MATRIX:
6. The Petitioner is a private limited company incorporated under
4
Respondents
5
Binding HoT
6
Collaboration Land
O.M.P.(I) (COMM.) 138/2026 Page 3 of 56
the provisions of the Companies Act, 1956 and is engaged in the
business of real estate development.
7. The Respondents, who are husband and wife, are the joint
owners of the Collaboration Land. Being desirous of developing the
said Collaboration Land, the Respondents approached the Petitioner
for undertaking development thereof.
8. Pursuant thereto, the parties entered into discussions and
negotiations in relation to the proposed development of the
Collaboration Land, culminating in the execution of the Binding HoT.
9. Under the Binding HoT, the Respondents agreed to contribute
the Collaboration Land, while the Petitioner was to undertake
development of a Residential Group Housing Project / Mixed Land
Use Project or any other permissible project as may be agreed between
the parties. The Petitioner was vested with the responsibility for
obtaining the requisite sanctions and approvals in relation to the
proposed development.
10. The parties agreed to the revenue-sharing arrangement whereby
42.3% of the distributable revenue was to accrue to the Respondents
and 57.7% to the Petitioner. Additionally, all project costs were to be
borne by the Petitioner.
11. The Binding HoT further contemplated execution of a
Definitive Collaboration Agreement upon receipt of sanctioned layout
plans, subject to a maximum outer limit of 14 months from the date of
the Binding HoT. Further, Clause R of the Binding HoT contained an
arbitration agreement providing for reference of disputes to arbitration
seated at Delhi.
12. The Respondents, while executing the Binding HoT,
represented, inter alia, that they possessed a clear, marketable, and
O.M.P.(I) (COMM.) 138/2026 Page 4 of 56
unencumbered title to the Collaboration Land and that, apart from a
disclosed dispute relating to the placement of an exit gate concerning
M/s Fountainhead Motels Pvt. Ltd., no material litigation affecting the
Collaboration Land subsisted.
13. Pursuant to the execution of the Binding HoT, it is the case of
the Petitioner that it proceeded to undertake steps towards
implementation of the proposed project, including preparation and
submission of layout plans before the concerned authorities. The
requisite fee for the same was deposited with the Municipal
Corporation of Delhi
7
and the layout plans, duly signed by the
Respondents, were submitted on 03.07.2023.
14. During the course of processing the approvals, certain
additional requirements emerged, including procurement of approvals
from the Airports Authority of India
8
and a No Objection Certificate
from the Ministry of Defence, owing to the proximity of the
Collaboration Land to an Air Force Station.
15. It further transpired that a substantial portion of the
Collaboration Land fell within a specified distance from the Air Force
Station. Consequently, the layout/building plans required revision and
were thereafter resubmitted on 29.02.2024.
16. The Petitioner also undertook demolition of the existing
structure operating under the name “Jhankar Banquet”, which,
according to the Petitioner, was necessary for facilitating inspection
and processing by the relevant authorities. The Petitioner alleges that
the said process was delayed on account of requests made by the
Respondents for the postponement of demolition.
7
MCD
8
AAI
O.M.P.(I) (COMM.) 138/2026 Page 5 of 56
17. The Petitioner further asserts that a pending dispute concerning
the Collaboration Land involving M/s Fountainhead Motels Pvt. Ltd.
also requires resolution during the subsistence of the Binding HoT. It
is stated that the Petitioner was constrained to facilitate an amicable
settlement, which was reached on 11.03.2024.
18. Subsequently, the parties executed a First Addendum dated
06.05.2024 extending the validity of the Binding HoT till 17.08.2024.
19. It is the case of the Petitioner that during the relevant period, the
Standing Committee of the MCD, whose approval was necessary for
sanction of the layout plans, remained non-existent for a substantial
duration.
20. The Petitioner further relies upon the imposition of the Model
Code of Conduct during various elections as having contributed to
delays in the approval process.
21. Despite these impediments, the Layout Scrutiny Committee,
MCD
9
, comprising representatives of all concerned MCD departments
and one representative of Delhi Development Authority
10
, agreed to
recommend the project proposal for development of the Collaboration
Land as a Group Housing Project to the Standing Committee. This in-
principle recommendation was made subject to the submission of a
reverification report concerning certain areas under the recreational
plan as per the Zonal Development Plan of Zone-J under MPD-2021.
22. On 18.05.2025, the parties executed a Second Addendum
extending the validity of the Binding HoT till 17.08.2025. Under the
said Addendum, the Petitioner made further payments to the
Respondents and also agreed to pay a sum of Rs. 25 lakhs per month
9
LOSC
10
DDA
O.M.P.(I) (COMM.) 138/2026 Page 6 of 56
during the extended period.
23. Thereafter, a Third Addendum dated 05.08.2025 came to be
executed, extending the validity of the Binding HoT till 17.12.2025 on
substantially similar terms.
24. It is the case of the Petitioner that on 20.10.2025, the
Respondents‟ representative and son, Mr. Virat Kapoor, for the first
time disclosed to the Petitioner the existence of two pending
litigations concerning the Collaboration Land, being appeals filed
under Section 185 of the Delhi Land Reforms Act, 1954. The said
appeals were ultimately dismissed vide Judgment dated 18.12.2025.
25. Since the Third Addendum was nearing expiry, the Petitioner
circulated a draft Fourth Addendum seeking further extension till
17.04.2026. According to the Petitioner, the Respondents suggested
modifications to the draft and continued to assure the Petitioner that
execution of the addendum was a mere formality.
26. It is the Petitioner‟s case that, notwithstanding non-execution of
the Fourth Addendum, both parties continued to act in furtherance of
the Binding HoT even after 17.12.2025. The Petitioner continued to
pursue approvals with statutory authorities, including MCD and AAI,
and claims to have kept the Respondents informed of such
developments from time to time.
27. On 10.02.2026, representatives of both parties are stated to have
jointly appeared before the Commissioner, MCD, in relation to the
pending approvals concerning the project.
28. According to the Petitioner, by February, 2026, the process for
sanction of the layout plans had substantially progressed and only
final approval of the Standing Committee remained pending.
29. On 10.03.2026, the Respondents addressed a communication to
O.M.P.(I) (COMM.) 138/2026 Page 7 of 56
the Petitioner asserting that the Binding HoT had elapsed on
17.12.2025 and calling upon the Petitioner to reconcile financial
aspects between the parties.
30. Thereafter, on 25.03.2026, the Respondents remitted an amount
of Rs. 2,80,00,000/- to the Petitioner and reiterated their position that
the Binding HoT had lapsed.
31. Apprehending the creation of third-party rights in respect of
the Collaboration Land, the Petitioner issued public notices and
thereafter addressed a detailed communication dated 27.03.2026,
asserting that the Binding HoT continued to subsist and calling upon
the Respondents not to deal with the Collaboration Land in derogation
of the Petitioner‟s rights.
32. The Petitioner states that it has paid, in aggregate, a sum of
approximately Rs. 8 Crores to the Respondents under the Binding
HoTs and Addendums, comprising upfront payments of Rs. 3.12
Crores, further payments of Rs. 2.75 Crores, and monthly payments of
Rs. 25 lakhs from 17.02.2025 to 17.03.2026, in addition to incurring
substantial expenditure on consultants, professional fees, surveys, and
approval costs over a period of approximately two and a half years.
33. In the aforesaid factual background, and in apprehension of
imminent adverse consequences likely to prejudice its rights and
interests, the present Petition under Section 9 of the A&C Act has
been instituted seeking the grant of interim measures pending
adjudication of the disputes between the parties.
SUBMISSIONS ON BEHAL F OF THE PARTIES:
34. At the outset, learned senior counsel appearing on behalf of the
Respondents would raise two broad preliminary objections to the
maintainability of the present Petition. Firstly, it would be contended
O.M.P.(I) (COMM.) 138/2026 Page 8 of 56
that the Binding HoT neither constitutes a concluded nor a specifically
enforceable contract in the eyes of the law. Secondly, it would be
submitted that, in the absence of any prima facie enforceable
contractual right, no interim protection as sought by the Petitioner can
be granted under Section 9 of the A&C Act.
35. In respect of the first contention, learned senior counsel for the
Respondents would contend that the Binding HoT does not constitute
a complete, final and concluded contract capable of specific
enforcement in law. It would be submitted that the Binding HoT
merely records a preliminary commercial understanding between the
parties while consciously contemplating execution of subsequent
definitive documentation, inter alia, the proposed Collaboration
Agreement.
36. It would be submitted that the structure, language and scheme
of the Binding HoT itself demonstrate that the parties did not intend
the said document to operate as the exhaustive repository of their
rights and obligations. Learned senior counsel would contend that
several material facets concerning implementation of the project,
operational modalities, reciprocal obligations, regulatory compliances
and commercial structuring were consciously left to be subsequently
negotiated, crystallised and incorporated in the contemplated
Collaboration Agreement.
37. Learned senior counsel would further submit that the Binding
HoT neither transfers any present development rights nor creates any
vested proprietary or contractual interest in favour of the Petitioner.
Accordingly, the document merely contemplated a future
collaborative framework subject to execution of further agreements
and satisfaction of multiple contingencies.
O.M.P.(I) (COMM.) 138/2026 Page 9 of 56
38. In furtherance of the aforesaid submissions, learned senior
counsel for the Respondents would place reliance upon the Judgement
of this Court in Vijay Kumar vs. K.N. Chopra & Ors.
11
, to contend
that where the foundational document itself contemplates execution of
a subsequent Collaboration Agreement and leaves material
stipulations for future negotiation and crystallisation, no concluded
contract capable of specific performance comes into existence. A
similar reliance would be placed upon the Judgement of this Court in
Nikhil Kumar Anand vs. Hridey Vikram Bhatia & Ors.
12
.
39. In view of the foregoing submissions and the reliance placed, it
would be submitted that the Binding HoT, viewed in its entirety,
merely constituted a framework for future collaboration and not a
final, concluded and immediately enforceable development
agreement.
40. Learned senior counsel would, in this regard, specifically place
reliance upon Clauses C, D, E, F, G and J of the Binding HoT to
contend that crucial aspects concerning development obligations,
implementation modalities, commercial structuring, regulatory
compliances, timelines, approvals and operational responsibilities
were left to be comprehensively worked out subsequently under the
contemplated Collaboration Agreement.
41. Learned senior counsel would particularly emphasise upon
Clause O(b) of the Binding HoT to contend that even the pricing and
valuation mechanism concerning the apartments proposed to be
allotted or sold had not attained finality. According to the learned
senior counsel for the Respondents, certainty of consideration
11
2000 SCC OnLine Del 162
12
2026 SCC OnLine Del 1089
O.M.P.(I) (COMM.) 138/2026 Page 10 of 56
constitutes an essential ingredient of a concluded agreement relating to
immovable property and in the absence thereof, no enforceable
agreement can be said to exist.
42. Learned senior counsel appearing on behalf of the Respondents,
in furtherance of the aforesaid submissions, would place reliance upon
the Judgement of this Court in Aggarwal Hotels (P) Ltd. vs. Focus
Properties (P) Ltd
13
, to contend that where material and essential
terms such as consideration, parties, timelines and implementation
modalities remain uncertain or incomplete, no concluded agreement
capable of specific performance can be said to come into existence.
43. Learned senior counsel would additionally submit that the
continued circulation of draft addenda, proposed modifications and
negotiations regarding revised commercial terms itself demonstrates
the absence of consensus ad idem on several material aspects of the
proposed arrangement.
44. It would thus be contended that the Binding HoT falls within
the category of a mere “agreement to agree”, lacking certainty on
essential terms and consequently incapable of specific enforcement in
law.
45. Learned senior counsel appearing on behalf of the Respondents
would further contend that the present arrangement concerns a long-
term and technically complex real estate development project
involving continuous reciprocal obligations, procurement of statutory
approvals, coordination with multiple regulatory authorities,
construction obligations, commercial implementation and continuing
operational supervision.
46. It would therefore be submitted that enforcement of such an
13
1996 SCC OnLine Del 354
O.M.P.(I) (COMM.) 138/2026 Page 11 of 56
arrangement would necessarily require constant judicial supervision
and monitoring over an indefinite duration, thereby attracting the
prohibitions contemplated under Sections 14 and 41 of the Specific
Relief Act, 1963
14
.
47. In support of the aforesaid contention, learned senior counsel
for the Respondents would place reliance upon the Judgment of the
Hon‟ble Supreme Court in Vinod Seth vs. Devinder Bajaj and
Another
15
, to contend that arrangements involving continuing
obligations, uncertain or indeterminate terms, and acts dependent upon
future consensus between the parties are ordinarily not amenable to
specific enforcement. In furtherance of the said submission, reliance
would also be placed upon the Judgments of the Hon‟ble Supreme
Court in Gurbir Kaur vs. BDR Builders & Developers P. Ltd
16
, as
well as the decision of this Court in Davender Kumar Sharma vs.
Mohinder Singh & Ors.
17
.
48. To substantiate the further contention that agreements involving
continuous obligations and requiring constant or ongoing supervision
by the Court fall within the prohibitions contemplated under Sections
14(1)(b) and 14(1)(d) of the Specific Relief Act, learned senior
counsel for the Respondents additionally would rely upon the
Judgment of this Court in Prem Kumar Bansal vs. Ambrish Garg
18
,
as also the Judgment of the Hon‟ble Supreme Court in Her Highness
Maharani Shantidevi P. Gaikwad vs. Savjibhai Haribhai Patel &
Ors.
19
.
14
SRA
15
(2010) 8 SCC 1
16
2017 SCC OnLine Del 7737
17
2012 SCC OnLine Del 3688
18
2015 SCC OnLine Del 8758
19
(2001) 5 SCC 101
O.M.P.(I) (COMM.) 138/2026 Page 12 of 56
49. Learned senior counsel for the Respondents would further
contend that the subsequent conduct of the parties itself demonstrates
the absence of any concluded and enforceable contractual
arrangement. Reliance in this regard would be placed upon the
exchange of draft addenda, proposed modifications, negotiations
concerning revised terms and discussions relating to future
documentation, which, according to the Respondents, establish that
the parties themselves did not treat the Binding HoT as a complete and
final development agreement.
50. It would further be contended that the Respondents, vide
communication dated 25.03.2026, elected to treat the arrangement
between the parties as having come to an end and, in furtherance
thereof, proceeded to refund the amounts received under the Binding
HoT. According to the Respondents, such conduct clearly
demonstrates that no concluded and subsisting contractual relationship
survived between the parties, which could, in law, be made the subject
matter of specific enforcement.
51. In respect of the second aspect concerning the assertion that
interim relief under Section 9 of the A&C Act is not maintainable in
the facts of the present case, learned senior counsel for the
Respondents would submit that the present Petition under Section 9 of
the A&C Act is thoroughly misconceived and amounts to an indirect
attempt to secure specific performance of an alleged agreement which
is itself incapable of enforcement in law.
52. Learned senior counsel would submit that once the final relief
of specific performance itself is legally barred or seriously doubtful,
interim relief preserving such alleged rights cannot be granted and that
Section 9 of the A&C Act cannot be employed as a mechanism to
O.M.P.(I) (COMM.) 138/2026 Page 13 of 56
obtain, at an interlocutory stage, what would virtually amount to
enforcement of the alleged contract itself.
53. In support of the aforesaid submissions, reliance would be
placed upon the Judgement of the Hon‟ble Supreme Court in Arvind
Constructions Co. (P) Ltd. vs. Kalinga Mining Corporation & Ors.
20
,
wherein the Hon‟ble Supreme Court observed that exercise of powers
under Section 9 of the A&C Act remains governed by well-recognised
principles applicable to grant of interim injunctions and cannot be
exercised dehors the restrictions contained under the SRA. To support
this contention, further reliance would also be placed on the
Judgement of the Hon‟ble Supreme Court in Adhunik Steels Ltd. vs.
Orissa Manganese and Minerals (P) Ltd.
21
.
54. Learned senior counsel would further submit that the reliefs
sought by the Petitioner are squarely governed by settled principles
underlying Order XXXIX Rules 1 and 2 of the CPC and Order
XXXVIII Rule 5 of the CPC. It would be contended that the Petitioner
has failed to establish the triple test warranting the grant of an interim
injunction.
55. It would further be contended that the Petitioner is effectively
seeking a freezing order and protection akin to attachment before any
adjudication, without even satisfying the stringent requirements
governing such relief. Learned senior counsel would submit that there
is neither any pleading nor material demonstrating that the
Respondents are attempting to alienate assets dishonestly or defeat any
prospective arbitral award, and therefore no case under principles
analogous to Order XXXVIII Rule 5 CPC is made out.
20
(2007) 6 SCC 798
21
(2007) 7 SCC 125
O.M.P.(I) (COMM.) 138/2026 Page 14 of 56
56. Learned senior counsel appearing on behalf for the Respondents
would place reliance upon the Judgement of the Division Bench of
this Court in Ajay Singh vs. Kal Airways Pvt. Ltd. & Ors
22
, to contend
that while the powers under Section 9 of the A&C Act are broad, the
exercise thereof remains guided by well settled principles governing
interim injunctions and protective orders under the CPC, including
principles analogous to Order XXXVIII Rule 5 CPC.
57. Per contra, learned senior counsel appearing on behalf of the
Petitioner would vehemently contend that the Binding HoT constitutes
a “binding”, as the nomenclature itself suggests, and a concluded
commercial arrangement consciously entered into between
commercial entities with full knowledge of their respective obligations
and liabilities.
58. It would be submitted that the mere contemplation of the
execution of a rather elaborate additional Collaboration Agreement at
a subsequent stage does not dilute the binding nature of the
obligations already crystallised under the Binding HoT. Learned
senior counsel would contend that the law is well settled that where
parties intend to be bound and essential commercial terms stand
sufficiently settled, the contract does not become unenforceable
merely because a formal document remains to be executed.
59. Learned senior counsel for the Petitioner would further submit
that the Binding HoT specifically records the core commercial
understanding between the parties, including identification of the
Collaboration Land, the nature of the proposed development, the
financial obligations inter se the parties, security deposit
arrangements, exclusivity obligations, timelines and the overall
22
2017 SCC OnLine Del 8934
O.M.P.(I) (COMM.) 138/2026 Page 15 of 56
mechanism governing implementation of the project. It would
therefore be urged that all foundational and essential terms stood
sufficiently crystallised.
60. Learned senior counsel would further submit that Clauses C, D,
E, F, G and J relied upon by the Respondents merely contemplate
ancillary, procedural and implementation-related documentation
necessary for operationalisation of the project and cannot be construed
to mean that the foundational agreement itself was incomplete or non-
binding.
61. Learned senior counsel for the Petitioner would submit that
commercial arrangements, like the Binding HoT, involving large-scale
real estate development necessarily require subsequent technical
documentation, approvals, operational agreements and implementation
modalities, none of which dilute the binding nature of the principal
commercial arrangement already executed between the parties.
62. Insofar as Clause O(b) of the Binding HoT is concerned,
learned senior counsel would contend that the Respondents are
reading the said clause in isolation and dehors the overall scheme of
the Binding HoT.
63. According to the Petitioner, the consideration framework and
commercial mechanism between the parties stood sufficiently
identified and determinable under the terms of the Binding HoT itself
and therefore the agreement cannot be invalidated merely because
every component of pricing had not been numerically finalised at the
initial stage. It would also be submitted that in any real estate project
of such magnitude, such intricacies are always left open to be decided
in the future, closer to its completion and operation.
64. It would further be contended that even assuming certain
O.M.P.(I) (COMM.) 138/2026 Page 16 of 56
ancillary aspects remained to be operationalised subsequently, the
same would not render the entire arrangement void or unenforceable
where the essential commercial framework and reciprocal obligations
already stood concluded between the parties.
65. Learned senior counsel would additionally place considerable
reliance upon the subsequent conduct of the parties to demonstrate
that both sides consistently treated the Binding HoT as a valid,
operative and subsisting commercial arrangement.
66. In this regard, reliance would be placed upon the execution of
multiple addenda extending the validity and operation of the Binding
HoT from time to time, which, according to the Petitioner,
unequivocally establishes that the parties themselves proceeded on the
admitted footing that the arrangement was binding and enforceable.
67. Learned senior counsel would further submit that the Petitioner
continuously acted upon the arrangement and discharged its
obligations thereunder, including making substantial payments and
pursuing approvals and clearances for development of the
Collaboration Land over a prolonged period extending nearly thirty
months.
68. It would further be submitted that even immediately prior to
expiry of the third addendum, a draft fourth addendum for further
extension was exchanged between the parties and assurances were
extended on behalf of the Respondents that execution of the formal
addendum was merely procedural in nature.
69. Learned senior counsel would further contend that the
Respondents themselves continuously acted in furtherance of the
Binding HoT till as late as February, 2026, by participating in
meetings with authorities, signing documents submitted before
O.M.P.(I) (COMM.) 138/2026 Page 17 of 56
statutory authorities and negotiating terms of the proposed fourth
addendum, thereby unequivocally acknowledging the continued
subsistence and binding nature of the arrangement.
70. Learned senior counsel for the Petitioner would place particular
reliance upon the Respondents‟ own communication dated
25.03.2026, wherein the Respondents themselves expressly
acknowledged:
(i) The Heads of Terms dated 17.05.2023;
(ii) The extensions granted through multiple addenda;
(iii) The subsisting arrangement between the parties over an
extended duration; and
(iv) Refund of the security deposit in terms of the Heads of Terms
itself.
71. Learned senior counsel would therefore submit that the
Respondents, having consciously acted upon the Binding HoT over a
substantial duration, having derived benefits thereunder and having
permitted the Petitioner to incur substantial expenditure and undertake
extensive development-related activities, cannot now be permitted to
approbate and reprobate by contending that the arrangement was non-
binding or incomplete.
72. It would further be contended that the Respondents‟ plea
regarding uncertainty of terms is clearly an afterthought, raised only
after substantial performance had already taken place on both sides,
and the project had reached an advanced stage of approvals and
implementation.
73. Learned senior counsel appearing on behalf of the Petitioner
would further submit that the Binding HoT was not a mere
exploratory commercial understanding, but in fact created and
O.M.P.(I) (COMM.) 138/2026 Page 18 of 56
transferred valuable and enforceable commercial and development
rights in favour of the Petitioner, although falling short of formal
conveyance of title.
74. Learned senior counsel would further contend that the mere fact
that legal title in the property was not immediately conveyed does not
denude the Binding HoT of enforceability. It would further be
submitted that development and collaboration arrangements frequently
operate upon conferment of valuable development and commercial
rights without immediate transfer of ownership/title and are routinely
recognised as specifically enforceable.
75. In support of the aforesaid submissions, learned senior counsel
for the Petitioner would place heavy reliance upon the Judgement of
this Court in Grovy India Ltd. v. Balbir Singh
23
, to contend that
where a development agreement creates valuable rights in favour of
the developer in the property or constructed area, such arrangements
are capable of specific enforcement. It would further be submitted that
where an owner parts with valuable incidents of ownership and
confers substantive development rights upon a developer, it would be
difficult to hold that such an agreement is incapable of specific
performance.
76. It would additionally be argued that the Binding HoT expressly
contemplated execution of further definitive documents only in
furtherance and implementation of rights already created thereunder
and not as a condition precedent to creation of such rights.
77. Learned senior counsel would therefore submit that the Binding
HoT created valuable proprietary and commercial interests in favour
of the Petitioner capable of protection and enforcement in law and
23
2021 SCC OnLine Del 4783
O.M.P.(I) (COMM.) 138/2026 Page 19 of 56
consequently constitutes a valid and enforceable substratum for the
grant of interim protection under Section 9 of the A&C Act.
78. Learned senior counsel would further contend that the
Respondents‟ objections founded upon Sections 14 and 41 of the SRA
are wholly misconceived and proceed upon a restrictive pre-
amendment understanding of the law.
79. It would be submitted that, after the enactment of the Specific
Relief (Amendment) Act, 2018, the legislative scheme substantially
tilts in favour of the enforcement of commercial contracts and limits
the refusal of specific performance to narrowly construed statutory
exceptions.
80. In support of the aforesaid submissions, learned senior counsel
appearing on behalf of the Petitioner would place reliance upon the
Judgement of the Division Bench of this Court in Global Music
Junction Pvt. Ltd. v. Shatrughan Kumar @ Khesari Lal Yadav
24
, to
contend that the legislative intent post-2018 fundamentally favours
enforcement of consciously negotiated commercial obligations and
contractual certainty.
81. Learned senior counsel, placing reliance upon the said
judgment, would submit that, prior to the amendment, damages
constituted the ordinary rule while specific performance was treated as
an exception; however, the amended statutory framework reverses the
said position by substantially tilting the law in favour of specific
enforcement, subject only to limited statutory exceptions.
82. It would be contended that after deletion of the unamended
Section 14(1)(a) of the SRA, the mere availability of monetary
compensation can no longer constitute a standalone ground to refuse
24
2023 SCC OnLine Del 5479
O.M.P.(I) (COMM.) 138/2026 Page 20 of 56
specific performance and therefore, the Respondents‟ submission that
the Petitioner may be relegated to damages is contrary to the post-
amendment statutory framework recognised in the aforesaid
Judgement.
83. Learned senior counsel would additionally submit that the
present dispute concerns valuable development rights in immovable
property and a unique commercial opportunity incapable of adequate
monetary compensation and therefore preservation of the contractual
arrangement becomes necessary pending adjudication through
arbitration.
84. Learned senior counsel would thus contend that the Binding
HoT is fully capable of specific enforcement and consequently
constitutes a valid substratum for the grant of interim protection under
Section 9 of the A&C Act. It would be contended that the jurisdiction
conferred under Section 9 of the A&C Act is broad, equitable and
intended to preserve the efficacy of arbitral proceedings by
safeguarding the subject matter of dispute pending adjudication before
the learned Arbitral Tribunal.
85. Learned senior counsel would submit that Section 9 of the A&C
Act expressly empowers the Court to grant such interim measures as
may appear “just and convenient” and therefore the provision is
intended to secure the ends of justice and preserve the substratum of
arbitration. It would be contended that once a bona fide arbitral
dispute and a prima facie contractual relationship are demonstrated,
the Court possesses ample jurisdiction to grant protective reliefs
necessary to prevent the frustration of arbitral proceedings.
86. It would further be contended that the Court, while exercising
jurisdiction under Section 9 of the A&C Act, is not finally
O.M.P.(I) (COMM.) 138/2026 Page 21 of 56
adjudicating the maintainability of a claim for specific performance or
conclusively determining the enforceability of the underlying contract,
all of which properly fall within the domain of the learned Arbitral
Tribunal.
87. The Petitioner would further contend that the existence of
disputes regarding completeness, enforceability or interpretation of the
Binding HoT cannot by itself disentitle a party from seeking interim
protection under Section 9 of the A&C Act, particularly where refusal
of protection would result in frustration of arbitral proceedings or
irreversible alteration of the subject matter.
88. Learned senior counsel would additionally submit that the
Respondents are incorrectly seeking to equate the present proceedings
with a prayer for attachment before judgment under Order XXXVIII
Rule 5 CPC. It would be contended that the present Petition
fundamentally seeks preservation of the contractual and commercial
substratum forming the subject matter of arbitration and not recovery
of a money claim simpliciter.
89. Learned senior counsel would further submit that while the
Court may be guided by the underlying principles governing Orders
XXXVIII and XXXIX CPC, the powers under Section 9 of the A&C
Act are not constricted by rigid technical limitations applicable to
ordinary civil proceedings.
90. To fortify the aforesaid submissions, learned senior counsel for
the Petitioner placed heavy reliance upon the recent pronouncement of
this Court in GTL Infrastructure Ltd. v. S.C. Wadhwa and Sons
(HUF)
25
, contending that the powers under Section 9 of the A&C Act
are inherently broad and expressly encompass such orders as are
25
2025 SCC OnLine Del 2081
O.M.P.(I) (COMM.) 138/2026 Page 22 of 56
necessary to preserve and protect the subject matter of arbitration.
91. It would further be contended that denial of interim protection
at this stage would render the arbitral proceedings nugatory and
irreversibly prejudice the Petitioner, whereas the grant of interim
protection would merely preserve the subject matter pending
adjudication by the learned Arbitral Tribunal.
92. Learned senior counsel appearing on behalf of the Petitioner
would submit that time was never intended to constitute the essence of
the Binding HoT executed between the parties. It would be contended
that the nature of the transaction, the conduct of the parties and the
subsequent exchanges inter se the parties clearly demonstrate that the
timelines contemplated under the Binding HoT were merely
facilitative and directory in nature and not intended to automatically
extinguish rights upon expiry thereof.
93. It would further be contended that the execution of successive
addenda extending the validity and operation of the Binding HoT
itself constitutes a clear indication that strict adherence to timelines
had consciously been waived by the parties. Learned senior counsel
would submit that had time truly been intended to be of the essence,
there would have been no occasion for repeated extensions, continuing
negotiations or further performance after expiry of the original
timelines.
94. It would further be contended that the Respondents themselves
continued acting in furtherance of the Binding HoT even beyond the
original timelines, including participating in meetings with statutory
authorities, negotiating further extensions and exchanging draft
documentation. Learned senior counsel would therefore submit that
the Respondents, by their own conduct, unequivocally acknowledged
O.M.P.(I) (COMM.) 138/2026 Page 23 of 56
the continued subsistence of the arrangement and are consequently
precluded from contending that the Binding HoT stood extinguished
merely by efflux of time.
95. In support of the aforesaid submissions, learned senior counsel
appearing on behalf of the Petitioner would place reliance upon the
Judgment of the Hon‟ble Supreme Court in Hind Construction
Contractors v. State of Maharashtra
26
to contend that the question
whether time constitutes the essence of a contract is fundamentally
one of intention to be gathered from the contract as a whole and the
conduct of the parties.
96. Learned senior counsel would further place reliance upon the
Judgment of the Hon‟ble Supreme Court in N. Srinivasa v.
Kuttukaran Machine Tools Ltd
27
to contend that in agreements
concerning immovable property and allied development arrangements,
time is ordinarily not regarded as the essence of the contract unless
expressly and unequivocally stipulated otherwise.
97. Learned senior counsel would therefore submit that the
Respondents are precluded, both in law and equity, from contending
that the Binding HoT stood frustrated, extinguished or rendered
unenforceable merely upon expiry of timelines, particularly when the
Respondents themselves continued acting in furtherance of the
arrangement over a prolonged period of time.
98. In rebuttal to the submissions made by the learned counsel for
the Petitioner, learned senior counsel appearing for the Respondents
would submit that the timelines stipulated under the Binding HoT
constituted an integral and commercially fundamental component of
26
(1979) 2 SCC 70
27
(2009) 5 SCC 182
O.M.P.(I) (COMM.) 138/2026 Page 24 of 56
the arrangement and, therefore, time was clearly intended to be of the
essence of the contract.
99. It would be contended that the Binding HoT itself contemplated
execution of definitive agreements, fulfilment of reciprocal
obligations and achievement of specified milestones within stipulated
periods. According to the Respondents, the very incorporation of
successive timelines and validity periods demonstrates that the parties
intended expeditious culmination of the transaction and not an
indefinite or open-ended commercial arrangement.
100. Learned senior counsel would further submit that the necessity
of repeated extensions and addenda itself establishes that adherence to
timelines was treated as material by the parties. It would be argued
that had time not been significant, there would have been no occasion
for repeated formal extensions of the Binding HoT from time to time.
101. It would additionally be contended that the transaction concerns
a large-scale commercial real estate development involving substantial
financial exposure, market fluctuations, regulatory compliance, and
evolving third-party interests, where commercial certainty and timely
performance constitute the very substratum of the arrangement. In
support of the aforesaid submissions, learned senior counsel appearing
on behalf of the Respondents would place reliance upon the Judgment
of the Hon‟ble Supreme Court in Desh Raj & Ors. vs. Rohtash
Singh
28
.
102. Learned senior counsel appearing on behalf of the Respondents
would further place reliance upon the Judgement of the Hon‟ble
Supreme Court in Saradamani Kandappan vs. S. Rajalakshmi &
28
(2023) 3 SCC 714,
O.M.P.(I) (COMM.) 138/2026 Page 25 of 56
Ors.
29
, to contend that the traditional presumption that time is not
ordinarily of the essence in immovable property transactions stands
considerably diluted in modern commercial transactions involving
escalating property values and commercial certainty.
103. Learned senior counsel would submit that despite repeated
extensions and opportunities, the Petitioner failed to fulfil material
obligations contemplated under the Binding HoT, including
finalisation of definitive documentation and compliance with
commercial obligations within the agreed timelines. According to the
Respondents, a party repeatedly failing to adhere to agreed timelines
cannot subsequently seek equitable protection under Section 9 of the
Act.
104. It would further be contended that the Binding HoT itself
contemplated execution of a definitive Collaboration Agreement and
related documentation within stipulated periods and, therefore, the
arrangement remained contingent upon successful crystallisation of
the contemplated transaction within the agreed timeframe. Upon
failure thereof, no enforceable right survived in favour of the
Petitioner.
ANALYSIS:
105. This Court has heard the learned senior counsel appearing on
behalf of the parties and, with their able assistance, perused the
material placed on record and the Judicial precedents passed across
the Bar.
106. At the outset, this Court notes that it is conscious of the limited
compass of its jurisdiction under Section 9 of the A&C Act. The
29
(2011) 12 SCC 18
O.M.P.(I) (COMM.) 138/2026 Page 26 of 56
power conferred thereunder is interim and protective in nature,
intended to preserve the subject matter of the arbitration and to
safeguard the efficacy of the arbitral process. At this stage, the Court
is required only to examine whether the well-settled parameters
governing the grant of interim relief, namely, the existence of a prima
facie case, the balance of convenience, and the likelihood of
irreparable injury, stand satisfied for the purposes contemplated under
Section 9 of the A&C Act. In ArcelorMittal Nippon Steel (India) Ltd.
v. Essar Bulk Terminal Ltd.
30
, the Hon‟ble Supreme Court has
expounded upon the contours of such jurisdiction in the following
terms:
“88. Applications for interim relief are inherently applications
which are required to be disposed of urgently. Interim relief is
granted in aid of final relief. The object is to ensure protection of
the property being the subject-matter of arbitration and/or
otherwise ensure that the arbitration proceedings do not become
infructuous and the arbitral award does not become an award on
paper, of no real value.
89. The principles for grant of interim relief are (i) good prima
facie case, (ii) balance of convenience in favour of grant of interim
relief and (iii) irreparable injury or loss to the applicant for interim
relief. Unless applications for interim measures are decided
expeditiously, irreparable injury or prejudice may be caused to the
party seeking interim relief.
90. It could, therefore, never have been the legislative intent that
even after an application under Section 9 is finally heard, relief
would have to be declined and the parties be remitted to their
remedy under Section 17.
91. When an application has already been taken up for
consideration and is in the process of consideration or has already
been considered, the question of examining whether remedy under
Section 17 is efficacious or not would not arise. The requirement to
conduct the exercise arises only when the application is being
entertained and/or taken up for consideration. As observed above,
there could be numerous reasons which render the remedy under
Section 17 inefficacious. To cite an example, the different
arbitrators constituting an Arbitral Tribunal could be located at far
away places and not in a position to assemble immediately. In such
30
(2022) 1 SCC 712.
O.M.P.(I) (COMM.) 138/2026 Page 27 of 56
a case, an application for urgent interim relief may have to be
entertained by the Court under Section 9(1).”
(emphasis supplied)
107. This Court is not presently called upon to render a final
adjudication on the enforceability of the Binding HoT, nor to
conclusively determine whether the Petitioner would ultimately be
entitled to a decree of specific performance, as such issues would
appropriately fall within the exclusive domain of the learned Arbitral
Tribunal. The scope of the present examination is, therefore, confined
to assessing whether, upon application of the settled triple test
governing grant of interim measures, an arguable and bona fide
arbitral claim exists warranting preservation of the subject matter
pending adjudication of the disputes through arbitration.
108. The principal objection raised on behalf of the Respondents is
that the Binding HoT is neither a concluded nor specifically
enforceable contract and consequently cannot constitute the
substratum for the grant of interim protection. This Court is, however,
unable to accept the aforesaid submission.
109. A perusal of Clauses B, C, D, E, F, G and J of the Binding HoT
prima facie demonstrates that the parties had consciously identified
the Collaboration Land, recorded the broad development framework,
stipulated reciprocal obligations, financial commitments, security
deposit arrangements, exclusivity obligations and implementation
structure governing the project. The Binding HoT, therefore, cannot at
this stage be reduced to a mere exploratory arrangement or
unenforceable expression of future intent.
110. The contention of the Respondents that the Binding HoT merely
contemplated execution of a future Collaboration Agreement and
therefore lacked contractual finality also does not commend
O.M.P.(I) (COMM.) 138/2026 Page 28 of 56
acceptance at this stage. Commercial transactions of the present
nature, particularly large-scale real estate development arrangements,
frequently contemplate subsequent technical and operational
documentation. The mere existence of a contemplated future
Collaboration Agreement does not, ipso facto, obliterate obligations
already crystallised inter se the parties. The contemplated
Collaboration Agreement appears intended to operationalise and
elaborate the commercial framework already agreed upon under the
Binding HoT rather than create obligations for the first time.
111. In this context, reference may be made to the decision of the
Supreme Court in Trimex International FZE Ltd. Dubai v. Vedanta
Aluminium Ltd., India
31
, wherein the Hon‟ble Supreme Court
recognised that even in commercial transactions contemplating
execution of further formal documentation, a binding and enforceable
contractual arrangement may nevertheless emerge if the essential
commercial terms stand crystallised and the conduct of parties
demonstrates consensus ad idem. The Hon‟ble Supreme Court
observed that the mere fact that a formal contract remained to be
executed would not, by itself, negate the existence of a concluded
arrangement.
112. The Hon‟ble Supreme Court, in the said decision, further
observed that commercial parties may consciously agree to be bound
immediately while deferring certain ancillary or implementation
aspects for later formalisation and that a contract cannot be treated as
non-binding merely because a subsequent detailed agreement was
contemplated.
113. The principles enunciated in Trimex International (supra) lend
31
(2010) 3 SCC 1
O.M.P.(I) (COMM.) 138/2026 Page 29 of 56
support to the Petitioner‟s contention that the Binding HoT constituted
a binding commercial arrangement notwithstanding contemplation of
a subsequent Collaboration Agreement. The relevant paragraphs
thereof read as follows:
“49. In the light of the details which have been extracted in the
earlier paragraphs, I am unable to accept the stand of the
respondent. It is clear that if the intention of the parties was to
arbitrate any dispute which arose in relation to the offer of 15-10-
2007 and the acceptance of 16-10-2007, the dispute is to be settled
through arbitration. Once the contract is concluded orally or in
writing, the mere fact that a formal contract has to be prepared and
initialled by the parties would not affect either the acceptance of
the contract so entered into or implementation thereof, even if the
formal contract has never been initialled.
***
52. The Court of Appeal in Pagnan S.p.A. v. Feed Products
Ltd. [(1987) 2 Lloyd's Rep 601 (CA)] , Lloyd's Law Reports at p.
619 observed as follows:
“It is sometimes said that the parties must agree on the
essential terms and that it is only matters of detail which
can be left over. This may be misleading, since the word
„essential‟ in that context is ambiguous. If by „essential‟
one means a term without which the contract cannot be
enforced then the statement is true : the law cannot enforce
an incomplete contract. If by „essential‟ one means a term
which the parties have agreed to be essential for the
formation of a binding contract, then the statement is
tautologous. If by „essential‟ one means only a term which
the Court regards as important as opposed to a term which
the Court regards as less important or a matter of detail,
the statement is untrue. It is for the parties to decide
whether they wish to be bound and, if so, by what terms,
whether important or unimportant. It is the parties who
are, in the memorable phrase coined by the Judge, „the
masters of their contractual fate‟. Of course, the more
important the term is the less likely it is that the parties
will have left it for future decision. But there is no legal
obstacle which stands in the way of the parties agreeing to
be bound now while deferring important matters to be
agreed later. It happens every day when parties enter into
so-called „heads of agreement‟.”
The above principle has been consistently followed by the English
courts in Mamidoil-Jetoil Greek Petroleum Co. SA v. Okta Crude
Oil Refinery AD, (2001) 2 All ER (Comm) 193, Lloyd's Law
O.M.P.(I) (COMM.) 138/2026 Page 30 of 56
Reports at p. 89; Wilson Smithett & Cape (Sugar)
Ltd. v. Bangladesh Sugar and Food Industries Corpn. [(1986) 1
Lloyd's Rep 378], Lloyd's Law Reports at p. 386. In addition,
Indian law has not evolved a contrary position. The celebrated
judgment of Lord Du Parcq in Shankarlal Narayandas
Mundade v. New Mofussil Co. Ltd. [AIR 1946 PC 97] makes it
clear that unless an inference can be drawn from the facts that the
parties intended to be bound only when a formal agreement had
been executed, the validity of the agreement would not be affected
by its lack of formality.”
(emphasis supplied)
114. The aforesaid conclusion is further reinforced by the subsequent
conduct of the parties themselves. The material placed before this
Court reflects that multiple addenda/extensions were admittedly
executed, extending the operation of the Binding HoT over a
substantial duration. Significant payments were admittedly made by
the Petitioner. Meetings were held with statutory authorities.
Documents and draft addenda continued to be exchanged inter se the
parties even proximate to the alleged termination communication
dated 25.03.2026, which itself acknowledges the Binding HoT, the
extensions granted thereunder and the subsisting commercial
arrangement between the parties over an extended period.
115. In particular, the addenda executed between the parties reflect
repeated extensions of the Binding HoT coupled with continuing
financial obligations undertaken by the Petitioner. The material placed
on record further prima facie demonstrates that substantial payments,
including payments of Rs. 1 Crore, Rs. 1.75 Crores and continuing
monthly payments, were admittedly made by the Petitioner under the
arrangement. The record additionally reflects continuing meetings and
interactions with statutory authorities, including MCD, DDA and
AAI, in furtherance of the proposed development project. Prima facie,
such prolonged and consistent conduct is difficult to reconcile with the
O.M.P.(I) (COMM.) 138/2026 Page 31 of 56
Respondents‟ present contention that the arrangement was merely
exploratory or non-binding in nature.
116. The conduct of the parties, therefore, militates against the
Respondents‟ present contention that the arrangement was merely
tentative or non-binding.
117. Further, the reliance placed by the Respondents upon the
decisions in Vinod Seth (supra), Gurbir Kaur (supra), Vijay Kumar
(supra), Prem Kumar Bansal (supra), Davender Kumar Sharma
(supra) and similar authorities also does not persuade this Court to
decline protection at this interlocutory stage. These decisions
principally arose in materially distinguishable factual contexts where
the agreements under consideration were found to be vague,
incomplete, lacking in consensus on essential contractual terms, or
otherwise incapable of implementation owing to the absence of clarity
regarding the nature of obligations undertaken by parties, or where the
specific performance would require continuous supervision of the
Court.
118. Prima facie, the present case stands on an entirely different
footing. The Collaboration Land herein stands specifically identified.
The Binding HoT records the broad development framework, revenue-
sharing arrangement, reciprocal obligations, financial commitments,
exclusivity stipulations and implementation structure governing the
project. More importantly, the material placed on record prima facie
demonstrates prolonged and consistent performance of the
arrangement by both sides through execution of multiple addenda,
admitted payments running into several crores, continued engagement
with statutory authorities, exchange of draft Collaboration Agreements
and continuing negotiations over an extended duration. Therefore, this
O.M.P.(I) (COMM.) 138/2026 Page 32 of 56
is not a case involving a wholly indeterminate, uncertain or non-
existent arrangement incapable of arbitral enforcement.
119. Further, whether the Binding HoT ultimately satisfies all
requirements necessary for the grant of final relief of specific
performance is itself a matter requiring fuller examination before the
learned Arbitral Tribunal. At the present stage, this Court is only
required to examine whether the Petitioner has disclosed a bona fide
and arbitral claim warranting preservation of the subject matter
pending adjudication.
120. This Court is of the considered view that the Binding HoT
herein cannot, at this stage, be said to be so uncertain, nebulous or
unworkable as to render the Petitioner‟s claim ex facie frivolous or
incapable of arbitral consideration. The project land, being the
Collaboration Land, stands identified. The commercial relationship
between the parties stands admitted. Payments under the arrangement
are admitted. The parties admittedly acted upon the arrangement over
a prolonged period. Therefore, this is not a case where the Petitioner
seeks enforcement of a wholly inchoate or non-existent understanding.
121. Further, this Court cannot overlook the significant legislative
shift brought about by the Specific Relief (Amendment) Act, 2018,
which fundamentally altered the jurisprudential approach governing
the enforcement of commercial contracts. As noticed by the Division
Bench of this Court in Global Music (supra), the amended statutory
framework now substantially tilts in favour of enforcement of
contractual obligations, subject only to limited and narrowly construed
statutory exceptions.
122. The pre-amendment position, wherein specific performance was
viewed as an exceptional and discretionary remedy while damages
O.M.P.(I) (COMM.) 138/2026 Page 33 of 56
constituted the ordinary rule, has undergone substantial dilution
pursuant to the 2018-Amendment. The legislative intent underlying
the amendment unmistakably reflects a conscious policy shift towards
strengthening contractual sanctity, ensuring commercial certainty, and
promoting greater confidence in the enforceability of agreements,
particularly in the context of modern commercial and infrastructure
transactions. The relevant portion of the said judgment reads as
follows:
“AMENDMENT ACT, 2018 HAS MADE SPECIFIC
PERFORMANCE OF A CONTRACT A GENERAL RULE
RATHER THAN AN EXCEPTION. THE LEGIS LATIVE SHIFT IS
TOWARDS STRONGER ENFORCEMENT OF CONTRACTS.
29. Specific performance is an equitable relief given by the Court
to enforce against a defendant the duty of doing what he agreed by
the contract to do. It was in the process of a search for effective
remedial action that Specific Relief emanated from the Equity
Courts in England. Sir Edward Fry in his, A Treatise on the
Specific Performance of Contracts, 6
th
Edn. states “The only
remedy at common law for the non-performance of a contract was
in damages…. The common law treats as universal a proposition
which is for the most part, but not universally true, namely, that
money is a measure of every loss. The defeat of justice which arose
from this universality of the common law principle was met and
remedied in certain cases by the jurisdiction of Courts of Equity to
compel specific performance.”
30. The principles built up by successive Chancellors of England in
this branch of law were borrowed by the Indian Courts and served
to enrich the Indian Law. The Specific Relief Act of 1877 was
modelled on the draft New York Civil Code of 1862 and embodied
in it the relevant doctrines evolved by the Courts of Equity in
England. The Act of 1877 was not exhaustive. For decades this Act
was subjected to judicial interpretations which revealed many
deficiencies and lacunae.
31. On the recommendations of the Law Commission's Ninth
Report, the Specific Relief Act, 1963 was brought into force. The
Act, 1963 as originally enacted, conferred wide discretionary
powers upon the Courts to decree specific performance and to
refuse injunction etc. As a result of wide discretionary powers, the
Courts in majority of cases awarded damages as a general rule and
granted specific performance as an exception.
O.M.P.(I) (COMM.) 138/2026 Page 34 of 56
32. However, it was recently felt that the Act, 1963 is not in tune
with the rapid economic growth happening in our country and the
expansion of infrastructure activities that were needed for the
overall development of the country. India also did not fare well in
the international rankings in „Enforcement of Contracts‟ and „Ease
of Doing Business‟. The World Bank in its „Ease of Doing
Business‟ 2018 report ranked India at 100 out of 190 countries. In
„Enforcement of Contracts‟, India was ranked at 164 out of 190
countries as per World Bank Doing Business indicators.
33. Accordingly, with the intent of promoting public interest, „Ease
of Doing Business‟ and to provide an effective remedy to parties
who have suffered loss due to breach or non fulfilment of a
contract, the Government of India appointed an Expert Committee
under the Chairmanship of Mr. Anand Desai.
34. Acting on the recommendations of the said Committee, the
Government of India decided to amend the Act, 1963 prospectively
(See: Katta Sujatha Reddy v. Siddamsetty Infra Projects Private
Limited, (2023) 1 SCC 355). The Statement of Objects and
Reasons of the Specific Relief (Amendment) Act, 2018 (hereinafter
be referred to as „Amendment Act, 2018‟) is reproduced
hereinbelow:—
“STATEMENT OF OBJECTS AND REASONS
The Specific Relief Act, 1963 was enacted to define and
amend the law relating to certain kinds of specific relief. It
contains provisions, inter alia, specific performance of
contracts, contracts not specifically enforceable, parties
who may obtain and against whom specific performance
may be obtained, etc. It also confers wide discretionary
powers upon the courts to decree specific performance and
to refuse injunction, etc. As a result of wide discretionary
powers, the courts in majority of cases award damages as
a general rule and grant specific performance as an
exception.
2. The tremendous economic development since the
enactment of the Act have brought in enormous
commercial activities in India including foreign direct
investments, public private partnerships, public utilities
infrastructure developments, etc.; which have prompted
extensive reforms in the related laws to facilitate
enforcement of contracts, settlement of disputes in speedy
manner. It has been felt that the Act is not in tune with the
rapid economic growth happening in our country and the
expansion of infrastructure activities that are needed for
the overall development of the country.
3. In view of the above, it is proposed to do away with the
wider discretion of courts to grant specific performance
and to make specific performance of contract a general
O.M.P.(I) (COMM.) 138/2026 Page 35 of 56
rule than exception subject to certain limited grounds.
Further, it is proposed to provide for substituted
performance of contracts, where a contract is broken, the
party who suffers would be entitled to get the contract
performed by a third party or by his own agency and to
recover expenses and costs, including compensation from
the party who failed to perform his part of contract. This
would be an alternative remedy at the option of the party
who suffers the broken contract. It is also proposed to
enable the courts to engage experts on specific issues and
to secure their attendance, etc.
4. A new section 20A is proposed for infrastructure project
contracts which provides that the court shall not grant
injunction in any suit, where it appears to it that granting
injunction would cause hindrance or delay in the
continuance or completion of the infrastructure project.
The Department of Economic Affairs is the nodal agency
for specifying various categories of projects and
infrastructure sub-sectors, which is provided as Schedule
to the Bill and it is proposed that the said Department may
amend the Schedule relating to any such category or sub-
sectors.
5. Special courts are proposed to be designated to try suits
in respect of contracts relating to infrastructure projects
and to dispose of such suits within a period of twelve
months from the date of service of summons to the
defendant and also to extend the said period for another
six months in aggregate, after recordings reasons therefor.
The Bill seeks to achieve the above objectives…”
35. It is settled law that a speech made by a mover of the bill
explaining the reasons for introducing the bill can certainly be
referred to for ascertaining the mischief sought to be remedied and
the object and the purpose of the legislation in question.
In Kalpana Mehta v. Union of India, (2018) 7 SCC 1, the
Supreme Court has held as under:—
“125. In K.P. Varghese v. CIT, (1981) 4 SCC 173 : 1981
SCC (Tax) 293, the Court, while referring to the Budget
Speech of the Minister, ruled that speeches made by
Members of legislatures on the floor of the House where a
Bill for enacting a statutory provision is being debated are
inadmissible for the purpose of interpreting the statutory
provision. But the Court made it clear that the speech
made by the mover of the Bill explaining the reasons for
introducing the Bill can certainly be referred to for
ascertaining the mischief sought to be remedied and the
object and the purpose of the legislation in question. Such
a view, as per the Court, was in consonance with the
juristic thought not only in the western countries but also
O.M.P.(I) (COMM.) 138/2026 Page 36 of 56
in India as in the exercise of interpretation of a statute,
everything which is logically relevant should be admitted.
Thereafter, the Court acknowledged a few decisions of
this Court where speeches made by the Finance Minister
were relied upon by the Court for the purpose of
ascertaining the reason for introducing a particular clause.
xxx xxx xxx
134. From the aforesaid, it clear as day that the Court can
take aid of the report of the Parliamentary Committee for
the purpose of appreciating the historical background of
the statutory provisions and it can also refer to committee
report or the speech of the Minister on the floor of the
House of Parliament if there is any kind of ambiguity or
incongruity in a provision of an enactment.
xxx xxx xxx
144. It is worthy to note here that there is an intrinsic
difference between parliamentary proceedings which are
in the nature of statement of a Minister or of a Mover of a
Bill made in Parliament for highlighting the purpose of an
enactment or, for that matter, a Parliamentary Committee
report that had come into existence prior to the enactment
of a law and a contestable/conflicting matter of “fact”
stated in the Parliamentary Committee report. It is the
parliamentary proceedings falling within the former
category of which courts are enjoined under Section 57,
clause (4) to take judicial notice of, whereas, for the latter
category of parliamentary proceedings, the truthfulness of
the contestable matter of fact stated during such
proceedings has to be proved in the manner known to
law.”
36. The then Minister of Law and Justice and the Minister of
Electronics and Information Technology, Sh. Ravi Shankar Prasad
while moving the Amendment Act, 2018 explained its rationale as
under:-
“Shri Ravi Shankar Prasad : Sir, may I just explain the
rationale for this Bill? The Specific Relief Act was
enacted in the year 1963. And, the Act clearly stated that
damages and monetary compensation shall be the norm
and a specific relief shall be an exception. So much so that
under Section 41 of the Act, no injunction could be
granted in the event an errant party tries to run away. You
take damages. Now, Sir, with the passage of time,
infrastructure has become a big issue in India. A lot of
money is coming and investment is coming. And, many of
them ultimately partake of the contracts which are relevant
as far as the Specific Relief Act is concerned. Now, Sir, in
many cases, errant parties or deviant parties, they are
creating problems. Whenever the parties used to go to the
O.M.P.(I) (COMM.) 138/2026 Page 37 of 56
court, they say, “No specific performance, you take
money”. It was also impacting our standing in the Ease of
the Doing Business. Therefore, ultimately, it was thought
that this matter requires to be addressed. And, ultimately, a
three-member Committee of eminent people was formed
and that Committee recommended - there were people
from the law firms; there were people from the industry -
that this requires proper amendment. And, therefore, we
came with an amendment. What is the purport of the
amendment which we are seeking to move today? It is
basically threefold. First and foremost, now, a specific
performance shall be the rule and damages has been
exception. So, we have reversed the entire focus of the Bill
from 1963 to 2017-18….”
37. From the aforesaid, it is apparent that the primary intent behind
the Amendment Act, 2018 is to introduce greater certainty in the
enforcement of contracts and consequently improve India's ranking
in „Enforcement of Contracts‟ and „Ease of Doing Business‟.
*****
39. This Court is of the view that by virtue of the changes brought
about by the Amendment Act, 2018, the Courts will now grant
specific performance unless the claim for relief is barred under
limited grounds prescribed in the statute. This change is aimed at
providing greater protection of contractual expectations by
ensuring that a non-defaulting party can obtain the performance it
bargained for. The Amendment Act, 2018 intends to discourage
errant parties who may deem it more viable to breach a contract
than perform it, as the cost of damages may still be less than the
cost of the performance.
40. The Amendment Act, 2018 has also brought the Indian Specific
Performance Act in line with the UNIDROIT Principles of
International Commercial Contracts, as it aspires to achieve
harmonization in international law governing commercial
contracts.
*****
42. Consequently, the Amendment Act, 2018 has changed the
nature of specific relief from an equitable, discretionary remedy to
a statutory remedy. It has made specific performance of a contract
a general rule rather than an exception.”
(emphasis supplied)
123. This Court also takes note of the Report dated 26.05.2016
submitted by the Expert Committee constituted under the
Chairmanship of Mr. Anand Desai, which formed the foundational
O.M.P.(I) (COMM.) 138/2026 Page 38 of 56
basis for the 2018 Amendment to the SRA.
124. The Committee emphatically underscored that enforcement of
contractual obligations ought to be treated as the general rule, and
refusal of specific performance or injunctive relief should remain
confined only to limited and specifically enumerated exceptions. The
Committee specifically recommended that specific performance and
injunctions should no longer be treated as exceptional remedies, but
ought ordinarily to be made available to a promisee seeking
enforcement of contractual rights, whether before courts, tribunals, or
arbitral forums.
125. The said Report further emphasized that judicial interference
through discretionary refusal of such reliefs should remain minimal
and restricted to clearly identifiable statutory grounds. Significantly,
the Committee also recognized that where a party seeks specific
performance, its contractual interests ought not to be defeated merely
by passage of time during adjudicatory proceedings, and therefore
appropriate interim protections should be available to preserve the
subject matter pending final adjudication. The relevant portion of the
said report reads as follows:
“11.6 Changes suggested
It is therefore necessary to explore whether specific performance
and injunction should be available as normal, routine and usual
remedies to a promisee who seeks to have them. It is also necessary
to explore in what manner can a promisee be assured of the benefit
of performance to the extent that he has been promised under his
contract.
Three major changes are suggested:-
(i) Specific performance and injunction should no longer be an
exceptional remedy, but should be available to any promisee
who seeks these reliefs, whether through courts,tribunals, or in
arbitration. Interference with these remedy in exercise of
discretionary powers of the court should be minimal, and on
specific grounds only.
O.M.P.(I) (COMM.) 138/2026 Page 39 of 56
(ii) If the promisor refuses or fails to perform his promise, the
promisee should be entitled get the performance completed
through a third party, at the cost of the promisor.
(iii) Where a promisee seeks specific performance, his interests
should not be prejudiced by passage of time during litigation.
His interests should be protected by appropriate interim orders.
11.7 Amendments proposed
The amendments proposed are broadly as given below, and are
dealt with in detail later:
(i) Both remedies of specific performance and Injunction when
sought for breach of contract, will no longer be exceptional
remedies. Section 10 to be amended accordingly.
(ii) A court can refuse these remedies only on the stated grounds.
Such grounds in the current Sections 14 and 20 are merged into
one section, l.e. Section 14. It is expressly stated that these
remedies shall not be refused on any other grounds. These
remedies shall no longer be discretionary.
(iii) A new relief of 'compensation pursuant to substituted
performance' is created in new section 20A.
(iv) Title of Chapter II to be changed to 'Enforcement of
Contracts' to accommodate all these remedies, and other
consequential amendments.”
126. In the backdrop of the legislative history and the underlying
object of the 2018-SRA amendment, this Court is of the considered
opinion that the enforcement of contracts now constitutes the general
rule rather than the exception. Consequently, the submission advanced
on behalf of the Respondents that the Binding HoT is ex facie
unenforceable under Sections 14 and 41 of the SRA cannot, at this
prima facie stage, be accepted in absolute terms.
127. Whether the nature of the obligations contemplated under the
Binding HoT attracts the prohibitions contained under Section 14(b)
of the SRA, or whether the relief sought is barred under Section 41(h)
of the SRA, are issues which would necessarily require a detailed
factual examination and evidentiary appreciation, an exercise more
appropriately undertaken in arbitral proceedings and not within the
O.M.P.(I) (COMM.) 138/2026 Page 40 of 56
limited jurisdiction presently being exercised under Section 9 of the
A&C Act.
128. This court is of the considered opinion that once the statutory
framework itself favours enforcement of contractual obligations, the
exceptions restraining such enforcement cannot be expansively
construed at the threshold stage so as to defeat the very subject matter
of arbitration. Mere invocation of Sections 14 or 41 of the SRA,
without a clear and unimpeachable demonstration that the case
squarely falls within the statutory prohibitions, cannot by itself compel
the Court, at a prima facie stage, to decline protective interim
measures. The Court, while exercising jurisdiction under Section 9 of
the A&C Act, is only required to undertake a limited and tentative
examination to ascertain whether an arguable arbitral claim exists,
warranting preservation of the subject matter pending adjudication.
129. In the facts and circumstances of the present case, this Court
does not, at this stage, find such overwhelming or absolute weight in
favour of the Respondents‟ contention so as to conclusively hold that
Sections 14 and 41 of the SRA completely bar enforcement of an
agreement of the present nature. The Respondents‟ objections, though
raising issues requiring consideration, are matters which remain open
for a detailed adjudication before the learned Arbitral Tribunal. At this
interim stage, this Court is therefore unable to hold that the Binding
HoT is so manifestly unenforceable in law that no interim protection
whatsoever can be granted for safeguarding the subject matter of the
arbitral proceedings pending final adjudication.
130. As is well established, at the stage of considering a Petition
under Section 9 of the A&C Act, the Court is not required to finally
determine the ultimate enforceability of the underlying contract or
O.M.P.(I) (COMM.) 138/2026 Page 41 of 56
conclusively adjudicate the entitlement of parties to specific
performance. It is sufficient if the material placed on record discloses
a bona fide and substantial arbitral claim requiring preservation
pending adjudication before the learned Arbitral Tribunal. Whether
the Petitioner ultimately succeeds in obtaining specific performance or
any other substantive relief would necessarily fall for determination in
arbitral proceedings upon appreciation of evidence and contractual
material.
131. Equally unpersuasive is the Respondents‟ submission that the
Petition effectively seeks final relief at the interim stage. The relief
sought by the Petitioner is essentially preservative in nature. The
Petitioner seeks maintenance of the contractual and commercial
substratum pending adjudication before the learned Arbitral Tribunal.
The same cannot, in the facts of the present case, be equated with the
grant of a final decree of specific performance.
132. The decisions in Adhunik Steels Ltd. (supra), Arvind
Constructions (supra) and Ajay Singh (supra), in fact, recognise the
broad and equitable nature of jurisdiction under Section 9 of the A&C
Act, albeit guided by settled principles governing interim reliefs.
There can be no quarrel with the proposition that the Court must test
the matter on the touchstone of a prima facie case, balance of
convenience and irreparable injury. However, those very principles,
in the considered view of this Court, operate in favour of the Petitioner
in the peculiar facts of the present matter.
133. In this regard, reference may also be made to the decision of the
Supreme Court in Essar House Private Limited v. Arcellor Mittal
O.M.P.(I) (COMM.) 138/2026 Page 42 of 56
Nippon Steel India Ltd
32
, wherein the Hon‟ble Supreme Court
reiterated that while exercising jurisdiction under Section 9 of the
A&C Act, the Court is not strictly constrained by the rigours of the
CPC and possesses broad equitable powers to secure the efficacy of
arbitral proceedings and preserve the subject matter of arbitration.
134. The Hon‟ble Supreme Court further observed that the Court
exercising jurisdiction under Section 9 of the A&C Act ought not to
refuse interim protection merely on technicalities and that the Court
must adopt a course which advances the ends of justice and safeguards
the efficacy of arbitral proceedings. The relevant observations, as
made in the said judgment, read as follows:
“38. In deciding a petition under Section 9 of the Arbitration Act,
the Court cannot ignore the basic principles of CPC. At the same
time, the power of the Court to grant relief is not curtailed by the
rigours of every procedural provision in CPC. In exercise of its
powers to grant interim relief under Section 9 of the Arbitration
Act, the Court is not strictly bound by the provisions of CPC.
***
44. In Jagdish Ahuja v. Cupino Ltd., 2020 SCC OnLine Bom
849, the Bombay High Court correctly summarised the law in para
6 extracted hereinbelow : (SCC OnLine Bom)
“6. As far as Section 9 of the Act is concerned, it cannot
be said that this Court, while considering a relief
thereunder, is strictly bound by the provisions of Order 38
Rule 5. As held by our Courts, the scope of Section 9 of
the Act is very broad; the court has a discretion to grant
thereunder a wide range of interim measures of protection
“as may appear to the court to be just and convenient”,
though such discretion has to be exercised judiciously and
not arbitrarily. The court is, no doubt, guided by the
principles which civil courts ordinarily employ for
considering interim relief, particularly, Order 39 Rules 1
and 2 and Order 38 Rule 5; the court, however, is not
unduly bound by their texts. As this Court held in Nimbus
Communications Ltd. v. BCCI, 2012 SCC OnLine Bom
287 (per D.Y. Chandrachud, J.), as the learned Judge then
was), the court, whilst exercising power under Section 9,
32
(2022) 20 SCC 178
O.M.P.(I) (COMM.) 138/2026 Page 43 of 56
„must have due regard to the underlying purpose of the
conferment of the power under the court which is to
promote the efficacy of arbitration as a form of dispute
resolution‟. The learned Judge further observed as follows
: (SCC OnLine Bom para 24)
„24. … Just as on the one hand the exercise of the power
under Section 9 cannot be carried out in an uncharted
territory ignoring the basic principles of procedural law
contained in the Code of Civil Procedure, 1908, the
rigours of every procedural provision in the Code of Civil
Procedure, 1908 cannot be put into place to defeat the
grant of relief which would subserve the paramount
interests of justice. A balance has to be drawn between the
two considerations in the facts of each case.‟ ”
***
48. If a strong prima facie case is made out and the balance of
convenience is in favour of interim relief being granted, the Court
exercising power under Section 9 of the Arbitration Act should not
withhold relief on the mere technicality of absence of averments,
incorporating the grounds for attachment before judgment under
Order 38 Rule 5 CPC.”
135. The aforesaid principles, when applied to the facts of the
present case, prima facie justify preservation of the contractual and
commercial substratum pending arbitral adjudication. The Petitioner
has demonstrated the existence of a substantial and bona fide arbitral
dispute arising from a commercial arrangement acted upon over a
prolonged duration. In such circumstances, this Court would be failing
in its duty under Section 9 of the A&C Act if, pending arbitral
adjudication, irreversible third-party rights are permitted to be created
so as to render the arbitral proceedings infructuous or ineffectual.
136. Insofar as the issue regarding time being of the essence is
concerned, this Court is also unable, prima facie, to accept the
Respondents‟ submission that the Binding HoT automatically stood
extinguished upon expiry of the stipulated timelines.
137. Undoubtedly, the decisions in Saradamani Kandappan (supra)
and Desh Raj (supra) emphasise that courts must accord due
O.M.P.(I) (COMM.) 138/2026 Page 44 of 56
significance to timelines in modern commercial transactions involving
immovable property. There can be no dispute with the said
proposition. However, the said Judgements themselves recognise that
the question remains one of contractual intention gathered from the
entirety of the arrangement and the conduct of the parties.
138. In the present case, the repeated execution of
addenda/extensions, the admitted continuation of negotiations, the
continued participation of both sides in pursuing approvals and the
exchange of further drafts even after expiry of earlier timelines prima
facie demonstrate that the parties themselves never treated the
arrangement as automatically extinguished upon expiry of the original
periods.
139. Significantly, the material placed before this Court reflects that
negotiations, exchanges of draft addenda and discussions concerning
continuation of the project admittedly continued even after expiry of
earlier timelines. Prima facie, such conduct evidences that the parties
themselves treated the timelines as extendable and the arrangement as
subsisting notwithstanding expiry of earlier periods contemplated
under the Binding HoT. Significantly, the Binding HoT does not
appear, ex facie, to contain any automatic termination or forfeiture
mechanism extinguishing rights immediately upon expiry of timelines.
140. At this stage, therefore, whether time ultimately constituted the
essence of the contract is a matter requiring fuller examination before
the learned Arbitral Tribunal and cannot be conclusively determined
against the Petitioner in proceedings under Section 9 of the A&C Act.
141. Reference may also be made to the decision of the Supreme
O.M.P.(I) (COMM.) 138/2026 Page 45 of 56
Court in B. Santoshamma v. D. Sarala
33
, wherein the Hon‟ble
Supreme Court, while considering the scope of specific enforcement
of agreements concerning immovable property, reiterated the
significant shift brought about by the 2018-SRA amendment and
emphasised that courts must adopt a purposive and meaningful
interpretation so as to prevent a defaulting party from defeating
contractual rights by its own wrongful conduct. The Hon‟ble Supreme
Court further recognised that agreements concerning immovable
property create valuable enforceable rights and that a contracting party
cannot be permitted to frustrate the agreement by creating third-party
complications during the subsistence of contractual obligations. The
relevant observations read as follows:
“70. After the amendment of Section 10 of the SRA, the words
“specific performance of any contract may, in the discretion of the
court, be enforced” have been substituted with the words “specific
performance of a contract shall be enforced subject to …”. The
court is, now obliged to enforce the specific performance of a
contract, subject to the provisions of sub-section (2) of Section 11,
Section 14 and Section 16 of the SRA. Relief of specific
performance of a contract is no longer discretionary, after the
amendment.
71. An agreement to sell immovable property, generally creates a
right in personam in favour of the vendee. [[Ed. : The Supreme
Court in V.K. Sreedharan v. Chandramaath Balakrishnan, (1990)
3 SCC 291, on a harmonious construction of Section 40 Part II and
Section 54 TPA and Section 91 of the Trusts Act, 1882, held that
the vendee under an antecedent agreement to sell gets a good title
in equity despite subsequent attachment of the seller's property, and
this equitable proprietary interest created by the antecedent
agreement to sell can be enforced in priority over the rights of a
subsequent judgment-creditor. The ruling in V.K. Sreedharan
case has been followed by the Supreme Court in Rajender
Singh v. Ramdhar Singh, (2001) 6 SCC 213. The equitable
property right created by an agreement for sale binds the seller and
other third persons, except bona fide transferees without notice of
the prior agreement for sale. This principle is statutorily recognised
in Section 19(b) of the Specific Relief Act, 1963.In fact, the
33
(2020) 19 SCC 80
O.M.P.(I) (COMM.) 138/2026 Page 46 of 56
Transfer of Property Act, 1882 itself envisages a dual structure of
property at law and in equity, as can be seen from Section 5
thereof. Section 5 TPA inter alia provides that a “transfer of
property” means “an act by which a living person conveys property
… to himself”. This express possibility of a transfer to oneself was
brought about by the 1929 Amendment to the TPA. This
amendment seems to make it clear that the TPA itself contemplates
a dual structure of property and ownership in India being the same
as that in England: of legal estates and equitable estates. This is
because it is only in the case of a trust that the concept of transfer
of property to oneself makes any sense, for in case of a trust, where
the settlor appoints himself the sole trustee, he, in his capacity as
the settlor, transfers the legal ownership of the trust property to
himself in his capacity as the sole trustee and transfers equitable or
beneficial ownership to the beneficiaries of the trust. This is
because a “transfer to oneself” is only possible if one transfers the
legal estate to oneself, and the beneficial or equitable estate to
another. It has been so held by a three-Judge Bench of the Supreme
Court in Tulsidas Kilachand v. CIT, (1961) 3 SCR 351. In respect
of an agreement to sell, Section 91 of the Trusts Act, 1882 read
with the definition of “trust” in Section 2(c) of the Specific Relief
Act, 1963, appears to create a constructive trust in respect of the
property which is the subject-matter of(Ed. note contd.)the
agreement to sell, with the seller/subsequent transferees as
constructive trustee holding the legal estate in the sale property on
trust for the vendee who is the cestui que of such trust. The vendee
is the holder of the beneficial estate in equity in the sale property
under such trust. When it is stated that “an agreement to sell
immovable property, generally creates a right in personam in
favour of the vendee”, it would appear that this pertains to the
nature of obligations owed by the trustee holding the legal title to
the property, to the beneficiary who holds the beneficial estate in
equity. It is often said that “equity acts in personam”: this probably
is with reference to the nature of the obligation owed by the trustee
to the beneficiary. However, the beneficial estate created by an
agreement to sell, as explained in V.K.
Sreedharan v. Chandramaath Balakrishnan, (1990) 3 SCC 291
and Rajender Singh v. Ramdhar Singh, (2001) 6 SCC 213, does
exhibit a proprietary character, though in equity.This equitable
proprietary character of the rights created by an agreement to sell is
further evidenced in the following cases. In Hill
Properties v. Union Bank of India, (2014) 1 SCC 635, a share
certificate in a housing company being the equivalent of a contract
for sale, was held to create a “species of property” or “species of
interest”, which was further held to be a mortgageable interest.
In Lakshmi v. E. Jayaram, (2013) 9 SCC 311, the lessee of the
vendee under a contract for sale, thus in fact a lessee in equity with
no legal title, was held to have the right to maintain an action for a
perpetual injunction against the transferor/legal title holder of the
O.M.P.(I) (COMM.) 138/2026 Page 47 of 56
property from interfering with the possession of the lessee in
equity. In CIT v. Podar Cement, (1997) 5 SCC 482, it was held
that a vendee under an agreement to sell was liable to pay capital
gains tax on his interest as the same was proprietary in nature.
In Saraswati Devi v. DDA, (2013) 3 SCC 571, the interest of the
highest bidder in auction of immovable property but before sale
had been executed i.e. at the stage of a contract for sale, was held
to be an interest in property susceptible to acquisition by the
State.The above cases appear to establish that the rights of a
vendee exhibit an equitable proprietary character i.e. a near
complete in rem character. There is one key difference between
legal property rights, estates or interests and equitable property
rights, estates or interests. Legal property rights exhibit a complete
or total in rem character without exception i.e. they bind the whole
world or third parties or subsequent transferees without exception
regardless of notice, knowledge or consent. Equitable property
rights mirror legal property rights, but exhibit a near complete in
rem character i.e. with an exception: equitable property rights bind
the whole world or third parties or subsequent transferees except
bona fide transferees for consideration without notice of the prior
equitable proprietary interests. For a more detailed analysis see the
Editorial note in Venigalla Koteswaramma v. Malampati
Suryamba, (2021) 4 SCC 246, at pp. 252-256.]] The vendee
acquires a legitimate right to enforce specific performance of the
agreement.
***
87. Section 12 of the SRA is to be construed and interpreted in a
purposive and meaningful manner to empower the Court to direct
specific performance by the defaulting party, of so much of the
contract, as can be performed, in a case like this. To hold otherwise
would permit a party to a contract for sale of land, to deliberately
frustrate the entire contract by transferring a part of the suit
property and creating third-party interests over the same.
88. Section 12 has to be construed in a liberal, purposive manner
that is fair and promotes justice. A contractee who frustrates a
contract deliberately by his own wrongful acts cannot be permitted
to escape scot-free.
***
89. After having entered into an agreement for sale of 300 sq yd of
land, with her eyes open, and accepted a major part of the
consideration (Rs 45,000 out of Rs 75,000) it does not lie in the
mouth of the vendor to contend that the contract should not have
specifically been enforced in part, in respect of the balance 200 sq
yd meters of the suit land which the vendor still owned. It is
patently obvious that the vendor did not disclose any earlier
agreement to the vendee, as discussed above. The agreement in
O.M.P.(I) (COMM.) 138/2026 Page 48 of 56
writing dated 21-3-1984, does not bear reference to any earlier
agreement, as noted above.”
142. This Court also finds merit in the submission advanced on
behalf of the Petitioner that the Binding HoT prima facie created
valuable commercial and development rights. The arrangement was
not a mere construction contract simpliciter. The Petitioner was to
derive identifiable commercial entitlements linked to the development
of the project. The decision in Grovy India (supra) prima facie
supports the proposition that development arrangements conferring
valuable commercial entitlements and incidents of ownership may
constitute specifically enforceable rights. The relevant portion of the
said judgment reads as follows:
“4. The dispute relates to a Property Development Agreement
(“PDA”), dated 14
th
January, 2020, executed between the plaintiff
and the defendant. The defendant has admitted this document….
***
17. The plaintiff has, in this suit, sought specific performance of
the PDA and thereby a direction to the defendant to hand over
peaceful possession of the suit property to the plaintiff, produce the
original property papers, handover all the executed documents, and
further execute all such other necessary documents to fulfil the
contemplated terms of the PDA. Additionally, a direction to the
defendant, to have the mortgage, in respect of the suit property,
redeemed, has also been sought.
***
69. The Court was, therefore, in Vinod Seth
2
, dealing with a
vague, imprecise and oral agreement. A reading of the decision
makes it clear that the difficulty which, in the opinion of the Court,
would arise in attempting specific performance of such an
undocumented agreement was one of the main considerations
which compelled the Supreme Court to agree with the view of this
Court that the agreement was incapable of specific performance.
70. In appreciating the law enunciated in Vinod Seth
2
, the Court
cannot, in my view, proceed unmindful of the nature of the
controversy, and, especially, the agreement, which was before the
Supreme Court. Judgements of courts, including the Supreme
Court, it is trite, are not to be treated as analogous to Euclid's
O.M.P.(I) (COMM.) 138/2026 Page 49 of 56
theorems, and followed blindly, without appreciating the fact-
situation in which they came to be rendered.
71. Sushil Kumar Agarwal:
72. As against this, Sushil Kumar Agarwal, also by a Bench of
two Hon'ble Judges of the Supreme Court, involved a suit for
specific performance of a written development agreement. It is
unnecessary to delve into the specifics of the disputes in that case.
Suffice it to reproduce paras 18, 19 and 24.3 of the report, which
read as under:
“18. When a pure construction contract is entered into, the
contractor has no interest in either the land or the
construction which is carried out. But in various other
categories of development agreements, the developer may
have acquired a valuable right either in the property or in
the constructed area. The terms of the agreement are
crucial in determining whether any interest has been
created in the land or in respect of rights in the land in
favour of the developer and if so, the nature and extent of
the rights.
19. In a construction contract, the contractor has no
interest in either the land or the construction carried out on
the land. But, in other species of development agreements,
the developer may have acquired a valuable right either in
the property or the constructed area. There are various
incidents of ownership in respect of an immovable
property. Primarily, ownership imports the right of
exclusive possession and the enjoyment of the thing
owned. The owner in possession of the thing has the right
to exclude all others from its possession and enjoyment.
The right to ownership of a property carries with it the
right to its enjoyment, right to its access and to other
beneficial enjoyments incidental to it. [ B.
Gangadhar v. B.G. Rajalingam, (1995) 5 SCC 238, para
6]. Ownership denotes the relationship between a person
and an object forming the subject-matter of the ownership.
It consists of a complex of rights, all of which are rights in
rem, being good against the world and not merely against
specific persons. There are various rights or incidents of
ownership all of which need not necessarily be present in
every case. They may include a right to possess, use and
enjoy the thing owned; and a right to consume, destroy or
alienate it. [Swadesh Ranjan Sinhav. Haradeb
Banerjee, (1991) 4 SCC 572]. An essential incident of
ownership of land is the right to exploit the development,
potential to construct and to deal with the constructed area.
In some situations, under a development agreement, an
owner may part with such rights to a developer. This in
O.M.P.(I) (COMM.) 138/2026 Page 50 of 56
essence is a parting of some of the incidents of ownership
of the immovable property. There could be situations
where pursuant to the grant of such rights, the developer
has incurred a substantial investment, altered the state of
the property and even created third-party rights in the
property or the construction to be carried out. There could
be situations where it is the developer who by his efforts
has rendered a property developable by taking steps in
law. In development agreements of this nature, where an
interest is created in the land or in the development in
favour of the developer, it may be difficult to hold that the
agreement is not capable of being specifically
performed. For example, the developer may have evicted
or settled with occupants, got land which was agricultural
converted into non-agricultural use, carried out a partial
development of the property and pursuant to the rights
conferred under the agreement, created third-party rights
in favour of flat purchasers in the proposed building. In
such a situation, if for no fault of the developer, the owner
seeks to resile from the agreement and terminates the
development agreement, it may be difficult to hold that the
developer is not entitled to enforce his rights. This of
course is dependent on the terms of the agreement in each
case. There cannot be a uniform formula for determining
whether an agreement granting development rights can be
specifically enforced and it would depend on the nature of
the agreement in each case and the rights created under it.
*****
24.3. In order to determine the exact nature of the
agreement signed between the parties, the intent of the
parties has to be construed by reading the agreement as a
whole in order to determine whether it is an agreement
simpliciter for construction or an agreement that also
creates an interest for the builder in the property. Where
under a development agreement, the developer has an
interest in land, it would be difficult to hold that such an
agreement is not capable of being specifically enforced.”
(Italics and underscoring supplied)
73. Where, therefore, as in the present case, the agreement is not
merely for development or construction on the property, but also
envisages valuable rights enuring, in favour of the developer, in the
constructed edifice, the Supreme Court itself holds, unequivocally,
that it would be difficult to treat the agreement as incapable of
specific performance.
74. The requirement of precision, in the construction contract, as a
pre-condition for its enforceability, is relatable to the erstwhile
Section 14(3)(c)(iii) of the Specific Relief Act. That requirement
no longer figures on the statute book, after the amendment of
O.M.P.(I) (COMM.) 138/2026 Page 51 of 56
Section 14 by the 2018 Amendment Act. In my prima
facie opinion, lack of precision in the construction agreement can
no longer be regarded, by itself, as a sufficient disqualification to
its enforceability by specific performance. Else, it would be re-
introducing, by a side wind, the consideration in the erstwhile
Section 14(3)(c)(iii), which the legislature has consciously
removed from the statute. Such an exercise is necessarily to be
eschewed, as it would militate against the legislative intent.
75. The sequitur would, therefore, be that a construction contract
can no longer be regarded as incapable of specific performance
merely because its terms are imprecise or vague. If, however,
owing to such imprecision or vagueness, any direction for specific
performance would require continuous supervision by the Court,
that would, even now, render the agreement incapable of specific
performance by virtue of Section 14(b). For that, however, the
Court would have to arrive at a finding that, owing to the
imprecision of the agreement, or for any other reason, any direction
for specific performance would require continuous supervision by
the Court. In the scenario of Section 14 as it exists today, and
without the support of the erstwhile Section 14(3)(c) and its
various clauses, this would, in almost every case, be arguable at the
very least.
76. Prima facie, in view of the above legal position, I am unable to
convince myself to hold, prima facie, that the defendant has been
able to make out a case of the PDA being incapable of specific
performance, by operation of Section 14(b) of the Specific Relief
Act, as would justify vacation of the interim direction to
maintain status quo in respect of the suit property.”
143. For the reasons already recorded hereinabove, this Court is
satisfied that the Petitioner has succeeded in establishing a strong
prima facie arbitral claim warranting protection and preservation
pending adjudication of disputes before the learned Arbitral Tribunal.
The existence of the Binding HoT, the repeated extensions granted
thereto, the admitted payments exchanged between the parties, the
continuing negotiations, and the overall contemporaneous conduct of
the parties collectively indicate that serious and substantial triable
disputes arise for adjudication in arbitration. At this stage, the material
placed on record discloses the existence of a bona fide and arguable
contractual dispute which cannot be summarily rejected in
O.M.P.(I) (COMM.) 138/2026 Page 52 of 56
proceedings under Section 9 of the A&C Act.
144. The claims asserted by the Petitioner cannot, at the present
stage, be characterised as illusory, speculative, vexatious, or wholly
devoid of an enforceable legal substratum. On the contrary, the
material presently available prima facie demonstrates that the disputes
raised by the Petitioner are neither sham nor frivolous, but involve
substantive questions requiring fuller examination on facts and law
before the learned Arbitral Tribunal. This Court, while exercising its
limited jurisdiction at the interim stage, is therefore unable to hold that
the Petitioner‟s claims are ex facie untenable so as to deny protective
relief altogether.
145. This Court is further of the considered view that if interim
protection is declined at this stage and the Respondents are permitted
to create irreversible third-party rights, alienate interests, or
fundamentally alter the commercial nature and character of the project
during the pendency of arbitral proceedings, the arbitral process itself
may stand seriously prejudiced and frustrated. In such an eventuality,
any award that may ultimately be rendered in favour of the Petitioner
could be rendered ineffective, illusory, or incapable of meaningful
enforcement. Conversely, the grant of interim protection at this stage
merely serves to preserve the existing state of affairs and safeguard the
subject matter of arbitration pending final adjudication. Such
protection neither results in a final determination of rights nor causes
irretrievable prejudice to the Respondents, whose rights and
contentions shall remain open to be adjudicated before the learned
Arbitral Tribunal in accordance with law.
146. In this context, reference may also be made to the decision of
the Supreme Court in Maharwal Khewaji Trust (Regd.), Faridkot v.
O.M.P.(I) (COMM.) 138/2026 Page 53 of 56
Baldev Dass
34
, wherein the Hon‟ble Supreme Court emphasised that
ordinarily, during pendency of proceedings, courts ought to preserve
the existing status of immovable property and should not permit
alteration of the nature of the property or creation of complications
capable of frustrating the ultimate adjudicatory process. The Apex
Court observed that unless exceptional circumstances are made out,
the nature and status of the property ought to be preserved so as to
avoid multiplicity of proceedings and irreversible prejudice to the
party ultimately found entitled thereto. The relevant observations, as
made in the said judgment, read as under:
“10. Be that as it may, Mr Sachar is right in contending that unless
and until a case of irreparable loss or damage is made out by a
party to the suit, the court should not permit the nature of the
property being changed which also includes alienation or transfer
of the property which may lead to loss or damage being caused to
the party who may ultimately succeed and may further lead to
multiplicity of proceedings. In the instant case no such case of
irreparable loss is made out except contending that the legal
proceedings are likely to take a long time, therefore, the respondent
should be permitted to put the scheduled property to better use. We
do not think in the facts and circumstances of this case, the lower
appellate court and the High Court were justified in permitting the
respondent to change the nature of the property by putting up
construction as also by permitting the alienation of the property,
whatever may be the conditions on which the same is done. In the
event of the appellant's claim being found baseless ultimately, it is
always open to the respondent to claim damages or, in an
appropriate case, the court may itself award damages for the loss
suffered, if any, in this regard. Since the facts of this case do not
make out any extraordinary ground for permitting the respondent to
put up construction and alienate the same, we think both the courts
below, namely, the lower appellate court and the High Court erred
in making the impugned orders. The said orders are set aside and
the order of the trial court is restored.”
147. The Court is also guided by the principle recognised in GTL
Infrastructure (supra) that Section 9 of the A&C Act is intended to
preserve the efficacy of arbitral proceedings and the Court must adopt
34
(2004) 8 SCC 488
O.M.P.(I) (COMM.) 138/2026 Page 54 of 56
the course carrying the lower risk of injustice. The relevant portion of
the said judgment reads as follows:
“17. It is apparent from the above that the powers of the court to
order interim measures of protection under Section 9 of the A&C
Act are wide and are not confined solely to orders that can be
passed under Order XXXIX Rules 1&2 of the Civil Procedure
Code, 1908. However, the court would be guided by the principles
underlying the said Code. Clearly, such orders would also extend
to granting the relief, if such relief is admissible on admitted facts.”
148. The disputes arising between the parties concern valuable
development rights in relation to immovable property and a unique
commercial opportunity which, by its very nature, may not be capable
of exact or complete restitution through monetary compensation alone.
The subject matter of the dispute possesses distinct commercial and
proprietary attributes, and any irreversible alteration thereto, or
creation of third-party rights during the pendency of arbitral
proceedings, may result in consequences incapable of being
adequately remedied merely by an award of damages. In such
circumstances, even if the Petitioner were ultimately to succeed before
the learned Arbitral Tribunal, the prejudice occasioned by a
fundamental change in the character of the project or alienation of
rights therein may render the eventual arbitral award ineffective or
incapable of meaningful enforcement.
149. Conversely, this Court is of the considered view that the
interests of the Respondents can be sufficiently protected and balanced
by imposing appropriate safeguards and conditions aimed at
preserving the equities between the parties during the pendency of the
arbitration. Grant of interim protection, therefore, would not result in
irreparable injustice to the Respondents, particularly when suitable
conditions can be moulded by the learned Arbitral Tribunal at the
O.M.P.(I) (COMM.) 138/2026 Page 55 of 56
relevant stage, if necessary, to ensure that neither party derives an
undue advantage pending final adjudication of their respective rights
and claims before the learned Arbitral Tribunal.
DECISION:
150. Accordingly, having regard to the peculiar facts and
circumstances of the present case, this Court is of the considered
opinion that interim protection deserves to be granted in favour of the
Petitioner so as to preserve the subject matter pending adjudication of
disputes through arbitration.
151. Accordingly, the Respondents are restrained from creating any
third-party rights, alienating, encumbering, transferring, or otherwise
dealing with the Collaboration Land in any manner prejudicial to the
rights and interests claimed by the Petitioner under the Binding HoT,
till such stage as may be considered appropriate upon an application
being moved by either of the parties before the learned Arbitral
Tribunal in accordance with law.
152. It is clarified that all observations recorded herein are purely
prima facie in nature and have been made solely for the purposes of
adjudication of the present petition under Section 9 of the A&C Act.
Nothing contained herein shall be construed as an expression on the
merits of the disputes between the parties, nor shall the same prejudice
the rights, claims, defences, or contentions of either party before the
learned Arbitral Tribunal, which shall adjudicate the disputes
independently and uninfluenced by any observations made
hereinabove.
153. The present Petition, along with pending Application(s), if any,
stands disposed of in the above terms.
O.M.P.(I) (COMM.) 138/2026 Page 56 of 56
154. No order as to costs.
HARISH VAIDYANATHAN SHANKAR, J.
MAY 29, 2026/sm/DJ
Legal Notes
Add a Note....