As per case facts, the Developer challenged an Arbitral Award under Section 34 of the Arbitration Act. The Arbitral Tribunal ruled that a Termination Notice by the Trust was illegal ...
CARBP.128.2023.Final.doc
canvassed by the Developer. The Learned Arbitral Tribunal has carefully
examined the pleadings of the Developer and has quoted chapter and
verse, how the Developer has, in its own affirmed pleadings, clearly
indicated that the Trust should be happy with a lower area, and how
delivery of less than the Agreed Area is justifiable. The justification flows
from the legitimacy of the fifth floor of the hostel building, that was
demolished, being in doubt. According to the Developer, the legitimacy of
the fifth floor is not borne out in the property records, and therefore, it is
not open for the Trust to claim performance of the delivery of the Agreed
Area. Even taken at its highest, this would mean that the agreement was
incapable of specific performance, which could at best, lead to a potential
claim in damages.
23. The Developer would contend that the very finding that the
Developer was not ready and willing to perform on the obligation to
deliver 32,000 square feet was perverse. This is untenable since the very
pleadings of the Developer in the arbitration proceedings indeed point to
how the obligation to deliver the Agreed Area was no longer valid. The
Developer indeed has contended that if certified by the municipal
authorities, and it gets additional incentive FSI under Regulation 33(7) of
the DCR, it would be open to delivering the Agreed Area. This would
indicate that there is no precision of a clear executable nature in the
Page 16 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
bargain sought to be enforced at the behest of the Developer as a matter
of specific relief.
24. The Developer had indeed pleaded that the Trust cannot seek any
area beyond what is approved and accepted by the planning authority.
Therefore, it is rightly contented by the Trust that when the pleadings are
read as a whole and the contemporaneous correspondence is examined,
the finding by the Learned Arbitral Tribunal that the Developer was never
ready and willing to provide a rehabilitated Hostel building of 32,000
square feet is not just a plausible and reasonable finding but an accurate
finding. Indeed, as contended by the Trust, the phrase “ready and
willing” is not a
mantra to be peppered into pleadings in a mechanical and
formulaic recitation without an actual and real depiction of how the actual
readiness and willingness to perform an agreement is discernible from the
record, and what precise obligation such party is ready and willing to
perform.
25. Indeed, this calls for comment on the parties moving away from
Regulation 33(7) to Regulation 33(6) as an interim measure to give the
Hostel its priority as agreed by the parties. Whether the project was
amenable to Regulation 33(7) at all and whether it was amenable to part
processing under Regulation 33(6) and subsequently by migration to
Regulation 33(7) is an issue that has remained at large. What the
Learned Arbitral Tribunal has done, and fairly so, is interpret the
Page 17 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
provisions of the agreement and the pleadings of the parties to examine
whether specific relief can be granted. There is not a whisper of a
provision or subsequent correspondence with the Trust having agreed to a
lower bargain – of taking less than the Agreed Area for such movement
across regulatory provisions under which the development would be
pursued. That being so, it would not have been possible for the Learned
Arbitral Tribunal to substitute the Agreed Area with the Reduced Area or
any other area and to uphold that as the basis of specific performance.
26. Even in the proceedings before this Court, a more novel argument
was made by the Developer, which only underlines the inchoate nature of
the bargain of which specific performance was sought. The Developer
would contend that the area allocated to the Temple may be added to the
Reduced Area, which would in turn show that the shortfall was just about
393 square feet. While the Trust would stridently oppose this submission
on the premise that this submission is being made for the very first time
in the Section 34 proceedings, it must be said that the Developer’s
contention, while attractive at first blush (particularly when seen in the
context of the consensual deviation from Regulation 33(7) of the DCR), it
would still not constitute that the parties had consensus
ad idem on what
revised area the Trust had settled for. The fact remains that the IOD is for
nearly 7,000 square feet lesser than the Agreed Area.
Page 18 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
27. The Learned Arbitral Tribunal has rightly held that oral evidence
and oral arguments have to be consistent with the pleadings. A holistic
reading of the pleadings has been rightly interpreted to indicate that the
Developer is not ready and willing to assuredly deliver the Agreed Area as
contracted. The right to get 32,000 square feet was never made
conditional on certification by any Planning Authority. Each party has
sought to explain how the evidence must be interpreted. It is not for this
Court to re-appreciate evidence. I must say that the reading of evidence as
canvassed by the Developer falls in the realm of re-appreciation of
evidence which this Court must not resort to. The overall reading of the
evidence and the contemporaneous correspondence by the Learned
Arbitral Tribunal would indicate that the finding of absence of readiness
and willingness to perform is an eminently plausible view that does not
call for interference.
28. Indeed, the Trust had delivered an approval from the Government
of Maharashtra for development under Regulation 33(7) of the DCR,
which informed the basis of the bargain between the parties. The
Municipal Commissioner rejected this on the premise that the
department that gave the permission was the wrong one (Housing
Department instead of Urban Development Department), but then the
parties had entered into the arrangement with eyes open and the
Developer has also confirmed satisfaction with examination of all facets of
Page 19 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
the matter when entering into the bargain with the Trust. The hurdle
posed by the Municipal Commissioner rejecting the very basis of
Regulation 33(7) being applicable, even when taken as a facet outside the
scope of the parties’ expectations and control, it would undermine the
specific performance of the Development and not further the same.
Indeed, the departure into Regulation 33(6) could be said to fall within
the zone of consideration of acquiescence to the situation but it would still
not point to a sharp and precise revised bargain that is amenable to
specific performance.
29. The Learned Arbitral Tribunal has also examined the fact that there
is a pointer to the fifth floor being legitimate from the records obtained
under the law governing right to information. The Learned Arbitral
Tribunal has fairly held that the Developer was aware of the project it was
getting into and ought to have done its due diligence before executing a
contract of which it is seeking specific performance.
30. The Termination Notice was issued two years after the Trust is
contended to have lauded the Developer for managing to secure approvals
for the Hostel, and indeed the Learned Arbitral Tribunal has held that the
Termination Notice was illegal as being contrary to contract. However, to
grant specific relief, the Developer would still need to have demonstrated
readiness and willingness to perform on a precise, binding and committed
revised contract and that is not discernible from the record – in itself, a
Page 20 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
matter of adjudication and appreciation of evidence. Therefore, to my
mind, the finding that the Termination Notice is “illegal” would at worst
be a problematic finding but it is not a finding that presents a perversity
of such a magnitude that it would go to the root of the matter of specific
relief, for the Impugned Order to be interfered with.
31. I find that the Learned Arbitral Tribunal has instead adopted a
practical, commonsensical and commercially logical interpretation even
while holding that the Development Agreement was inca pable of
termination – that even the termination was not contractually envisaged
(indeed the Learned Arbitral Tribunal terms the termination “illegal” a
few times), the Development Agreement was not capable of specific
performance. Therefore, specific relief could not have been granted for
the asking in the teeth of the principles governing specific relief, which at
the least, requires a specific committed obligatory element that can be
enforced under supervision of the Court. That being the case, no fault can
be found with the finding that specific relief was not worthy of being
granted.
32. To reconcile the two positions, namely, that termination was illegal
and yet specific relief could not be granted, it is apparent to me that the
Learned Arbitral Tribunal has simply adopted the principle of restitution
to place the parties in the respective positions that they were in before
executing an apparently interminable contract that is incapable of specific
Page 21 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
performance. The Learned Arbitral Tribunal rejected the competing
claim for damages; directed that the Trust be put in possession; and
directed that the Trust must return the amount of Rs. 3.69 crores paid by
the Developer to the Trust, along with interest. The Learned Arbitral
Tribunal has indeed reconciled the two positions presented as being
inherently contradictory and to my mind there is no fatal contradiction or
inconsistency in the analysis that flows through this issue in the
Impugned Award.
33. The contention that the MCGM Order constitutes vital evidence
that has been ignored also does not appeal to me. Each party has made
submissions on how the MCGM Order helps its respective case, but
suffice it to say, the Section 34 Court must resist the temptation of being
drawn into interpreting the true import of this document and should
instead examine whether that document contains any vital evidence that
has been ignored. I find that the core elements and contents of the
MCGM Order have indeed been analysed in the Impugned Order to
factually arrive at a finding of a shortfall in the commitment of the
Developer to deliver the Agreed Area and therefore, it cannot be said that
any vital evidence has been ignored. At worst, the Developer could be
said to be unhappy with the interpretation of the evidence by the Learned
Arbitral Tribunal, but one cannot say that the Learned Arbitral Tribunal
Page 22 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
failed to appreciate vital evidence to render the Impugned Award patently
illegal.
34. For the foregoing reasons, in my view, the interpretation of Clauses
28 and 29 of the Development Agreement is not in foundational conflict
with the finding that the core and essential term of the contract was
delivery of Agreed Area to the Trust. Therefore, whether or not the
Termination Notice is illegal, the finding that no case for specific relief
has been made out cannot be faulted. Presented with this seemingly
dilemmatic situation, the Learned Arbitral Tribunal has fairly and
reasonably held that the parties need to put back in their respective
positions, without any award of damages since both sides entered into the
bargain with eyes open and ran the risk of the costs and damages they
have respectively suffered. The Learned Arbitral Tribunal has fairly held
that neither party deserves to be saddled with damages for a contract
incapable of specific performance. Therefore, in my opinion, the
Impugned Award does present a wholesome outcome that is plausible,
logical and reasonable, and does not lend itself to interference under
Section 34 of the Act.
35. This brings me to the contentions of the PSCC Act, namely, that the
Developer is a licensee and is a protectee of the statutory tenant-
protection provisions of that legislation and the ouster of forums other
than the Small Causes Court from adjudication of a licensee eviction. The
Page 23 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
Learned Arbitral Tribunal has examined this squarely, to return a finding
that the license or the right to enter upon the property is incidental and
inextricably linked to the right to develop the Subject Property. If the right
to specific performance of the obligation to permit the Developer to
develop the Subject Property is not found worthy of acceptance, it would
follow that the incidental right to enter upon the Subject Property and
develop it would come to an end.
36. In my view, the contention of the Developer that it is a statutory
protectee of the PSCC Act is extreme and unreasonable. Provisions of
beneficial and ameliorative legislation must be interpreted in the context
of the objectives of the legislation. It is well settled that if more than one
view is possible, the view that furthers the remedy and suppresses the
mischief in the objective of the legislation would need to be adopted. The
Developer is hardly a tenant or a licensee who has been given the right to
use the Subject Property for a license fee. On the contrary, the Developer
in the same breath claims an interest in the Subject Property with a right
to exploit it and sell units from the free sale component, which itself
stands undermined. The license to enter the Subject Property is an
incidental and ancillary right and can simply not be elevated to a tenancy-
protection right under the PSCC Act. No fault can be found with the
Learned Arbitral Tribunal’s analysis of this issue to reject the
jurisdictional challenge.
Page 24 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
37. Finally, the purported absence of permission from the Charity
Commissioner to litigate should be stated to be rejected. This is another
novel argument in the process of throwing the kitchen sink at the
problems the Impugned Award poses to the Developer. While this may
not have been raised before, it is evident from the record that the Charity
Commissioner is not unaware of the litigation that the parties have been
engaged in, and has postponed consideration of an extension of approval
for the redevelopment, to await the outcome of the arbitration. This
ground is based on the regulatory scheme relating to governance of
charities. This is of no avail for a contractual counterparty to place
reliance on, and that too after the arbitral proceedings have been
concluded, of course, the outcome being unsatisfactory to such
counterparty.
38. The Learned Arbitral Tribunal has also analysed the absence of
consent from 70% of the tenants. However, I do not think it necessary to
delve into the issue of tenants’ consents not having been obtained since
the Developer is not pressing anything related to this issue except in
defence of the contentions of the Trust that invokes this issue. The
analysis in this judgement, bearing in mind the scope of jurisdiction
under Section 34 of the Act, is restricted to the grounds on which the
Developer has assailed the Impugned Award.
Page 25 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
Some Relevant Case Law Extracts:
39. Before parting, a word about the scope of review under Section 34
would be in order. Without intending to undertake a prolix reproduction
from the numerous judgements that now well settle the standard, in the
context of incoherence and inherent inconsistency being alleged by the
Developer, the following extracts from Associate Builders
1
would be
appropriate (for ease of reference, the footnote in the judgement inserted
in the extracted paragraph is also set out in the extract below):
It must clearly be understood that when a court is applying the "public policy"
test to an arbitration award, it does not act as a court of appeal and con-
sequently errors of fact cannot be corrected. A possible view by the arbitrator
on facts has necessarily to pass muster as the arbitrator is the ultimate master of
the quantity and quality of evidence to be relied upon when he delivers his arbit-
ral award. Thus an award based on little evidence or on evidence which does
not measure up in quality to a trained legal mind would not be held to be invalid
on this score
[Inserted Footnote – extracted below:]
Very often an arbitrator is a lay person not necessarily trained in law. Lord
Mansfield, a famous English Judge, once advised a high military officer in Ja-
maica who needed to act as a Judge as follows:
" General, you have a sound head, and a good heart; take courage and
you will do very well, in your occupation, in a court of equity. My advice
is, to make your decrees as your head and your heart dictate, to hear
both sides patiently, to decide with firmness in the best manner you can;
but be careful not to assign your reasons, since your determination may
1 Associate Builders v. Delhi Development Authority – (2015) 3 SCC 49
Page 26 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
be substantially right, although your reasons may be very bad, or essen-
tially wrong".
It is very important to bear this in mind when awards of lay arbitrators are chal-
lenged.
[Emphasis Supplied]
40. Indeed, the Sole Arbitrator manning the Learned Arbitral Tribunal
is not a lay man and is a former Chief Justice of a High Court. However, I
felt the need to extract the foregoing not because the Impugned Award
reads like one by a layman but for emphasising the principle involved –
where the reasons for two separate findings are logical and reasonable,
and the two can be reconciled in a manner that does not make the
findings mutually repugnant, if the outcome is just, logical and
commonsensical, the arbitral award need not be interfered with. The
reasons for which the Learned Arbitral Tribunal has held the Termination
Notice to be “illegal” and the allusions to the Development Agreement
subsisting to some extent may make the denial of specific relief illogical,
but one cannot lose sight of the fact that the reconciliation of the two
seemingly conflicting positions is quite commonsensical and logical. I
have already given my reasons as to how the two positions are not
inherently conflicting. Even if this reconciliation is contended as not
being explicitly and expressly set out in the Impugned Award, it is also
well settled that even implied reasons that are discernible and are capable
of being inferred to support a just and fair outcome in arbitral awards
Page 27 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
would make it appropriate not to interfere with arbitral awards. In this
regard, the following extract from the decision of the Supreme Court in
Dyna Technologies
2
would be appropriate:
24. There is no dispute that Section 34 of the Arbitration Act limits a chal-
lenge to an award only on the grounds provided therein or as interpreted by
various courts. We need to be cognizant of the fact that arbitral awards should
not be interfered with in a casual and cavalier manner, unless the court comes to
a conclusion that the perversity of the award goes to the root of the matter
without there being a possibility of alternative interpretation which may sustain
the arbitral award. Section 34 is different in its approach and cannot be equated
with a normal appellate jurisdiction. The mandate under Section 34 is to respect
the finality of the arbitral award and the party autonomy to get their dispute ad-
judicated by an alternative forum as provided under the law. If the courts were
to interfere with the arbitral award in the usual course on factual aspects, then
the commercial wisdom behind opting for alternate dispute resolution would
stand frustrated.
25. Moreover, umpteen number of judgments of this Court have categorically
held that the courts should not interfere with an award merely because an al-
ternative view on facts and interpretation of contract exists. The courts need to
be cautious and should defer to the view taken by the Arbitral Tribunal even if
the reasoning provided in the award is implied unless such award portrays per-
versity unpardonable under Section 34 of the Arbitration Act .
[Emphasis Supplied]
Summary of Conclusions:
41. In the result, the points determined by me may be summarised
thus:
2 Dyna Technologies Private Limited v. Crompton Greaves Limited – (2019) 20 SCC 1
Page 28 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
A] The finding that the Termination Notice is illegal for not
being supported by Clauses 28 and 29 of the Developm ent
Agreement is plausible and falls within the realm of interpretation
that the Learned Arbitral Tribunal is entitled to make;
B] Such interpretation on legality of termination is not
inherently and necessarily inconsistent with the refusal to grant
specific relief to the Developer in view of the other logical,
reasonable and plausible finding that the obligation to deliver the
Agreed Area of 32,000 square feet of redeveloped area is an
essential term of the agreement between the parties;
C] The Learned Arbitral Tribunal has rightly found that there
has been no revised area that had been agreed between the parties,
for a Court-supervised enforcement of specific relief to be possible;
D] The refusal to grant specific relief is not irreconcilable with
the finding that the Termination Notice was “illegal”;
E] The objection on arbitrability on the ground of exclusive
jurisdiction under the PSCC Act is untenable since the license
granted to the Developer was incidental to the development rights
conferred on the Developer. Once such development rights are not
held as being amenable to enforcement by way of specific relief, the
license would also become irrelevant. The Learned Arbitral
Page 29 of 30
APRIL 6 , 2026
Aarti Palkar
CARBP.128.2023.Final.doc
Tribunal’s findings that the statutory tenancy protection provisions
in the PSCC Act have no relevance to the Development Agreement
cannot be faulted;
F] The objection on the ground of lack of approval for litigation
by the Charity Commissioner is untenable for the reasons set out
above. The Charity Commissioner has been aware of the litigation
and even if regulatory action were to be contemplated, it would not
have a foundational and jurisdictional basis to undermine the
Impugned Award.
42. In the result, the Section 34 Petition is finally disposed of without
any interference with the Impugned Award.
43. All actions required to be taken pursuant to this order shall be
taken upon receipt of a downloaded copy as available on this Court’s
website.
[SOMASEKHAR SUNDARESAN, J.]
Page 30 of 30
APRIL 6 , 2026
Aarti Palkar
Legal Notes
Add a Note....