Developer, Trust, Arbitration Act, Section 34, Specific Performance, Termination Notice, PSCC Act, Arbitral Award, DCR Regulation
 06 Apr, 2026
Listen in 01:58 mins | Read in 45:00 mins
EN
HI

Developer Vs. Trust

  Bombay High Court CARBP.128.2023
Link copied!

Case Background

As per case facts, the Developer challenged an Arbitral Award under Section 34 of the Arbitration Act. The Arbitral Tribunal ruled that a Termination Notice by the Trust was illegal ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

CARBP.128.2023.Final.doc

canvassed by the Developer. The Learned Arbitral Tribunal has carefully

examined the pleadings of the Developer and has quoted chapter and

verse, how the Developer has, in its own affirmed pleadings, clearly

indicated that the Trust should be happy with a lower area, and how

delivery of less than the Agreed Area is justifiable. The justification flows

from the legitimacy of the fifth floor of the hostel building, that was

demolished, being in doubt. According to the Developer, the legitimacy of

the fifth floor is not borne out in the property records, and therefore, it is

not open for the Trust to claim performance of the delivery of the Agreed

Area. Even taken at its highest, this would mean that the agreement was

incapable of specific performance, which could at best, lead to a potential

claim in damages.

23. The Developer would contend that the very finding that the

Developer was not ready and willing to perform on the obligation to

deliver 32,000 square feet was perverse. This is untenable since the very

pleadings of the Developer in the arbitration proceedings indeed point to

how the obligation to deliver the Agreed Area was no longer valid. The

Developer indeed has contended that if certified by the municipal

authorities, and it gets additional incentive FSI under Regulation 33(7) of

the DCR, it would be open to delivering the Agreed Area. This would

indicate that there is no precision of a clear executable nature in the

Page 16 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

bargain sought to be enforced at the behest of the Developer as a matter

of specific relief.

24. The Developer had indeed pleaded that the Trust cannot seek any

area beyond what is approved and accepted by the planning authority.

Therefore, it is rightly contented by the Trust that when the pleadings are

read as a whole and the contemporaneous correspondence is examined,

the finding by the Learned Arbitral Tribunal that the Developer was never

ready and willing to provide a rehabilitated Hostel building of 32,000

square feet is not just a plausible and reasonable finding but an accurate

finding. Indeed, as contended by the Trust, the phrase “ready and

willing” is not a

mantra to be peppered into pleadings in a mechanical and

formulaic recitation without an actual and real depiction of how the actual

readiness and willingness to perform an agreement is discernible from the

record, and what precise obligation such party is ready and willing to

perform.

25. Indeed, this calls for comment on the parties moving away from

Regulation 33(7) to Regulation 33(6) as an interim measure to give the

Hostel its priority as agreed by the parties. Whether the project was

amenable to Regulation 33(7) at all and whether it was amenable to part

processing under Regulation 33(6) and subsequently by migration to

Regulation 33(7) is an issue that has remained at large. What the

Learned Arbitral Tribunal has done, and fairly so, is interpret the

Page 17 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

provisions of the agreement and the pleadings of the parties to examine

whether specific relief can be granted. There is not a whisper of a

provision or subsequent correspondence with the Trust having agreed to a

lower bargain – of taking less than the Agreed Area for such movement

across regulatory provisions under which the development would be

pursued. That being so, it would not have been possible for the Learned

Arbitral Tribunal to substitute the Agreed Area with the Reduced Area or

any other area and to uphold that as the basis of specific performance.

26. Even in the proceedings before this Court, a more novel argument

was made by the Developer, which only underlines the inchoate nature of

the bargain of which specific performance was sought. The Developer

would contend that the area allocated to the Temple may be added to the

Reduced Area, which would in turn show that the shortfall was just about

393 square feet. While the Trust would stridently oppose this submission

on the premise that this submission is being made for the very first time

in the Section 34 proceedings, it must be said that the Developer’s

contention, while attractive at first blush (particularly when seen in the

context of the consensual deviation from Regulation 33(7) of the DCR), it

would still not constitute that the parties had consensus

ad idem on what

revised area the Trust had settled for. The fact remains that the IOD is for

nearly 7,000 square feet lesser than the Agreed Area.

Page 18 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

27. The Learned Arbitral Tribunal has rightly held that oral evidence

and oral arguments have to be consistent with the pleadings. A holistic

reading of the pleadings has been rightly interpreted to indicate that the

Developer is not ready and willing to assuredly deliver the Agreed Area as

contracted. The right to get 32,000 square feet was never made

conditional on certification by any Planning Authority. Each party has

sought to explain how the evidence must be interpreted. It is not for this

Court to re-appreciate evidence. I must say that the reading of evidence as

canvassed by the Developer falls in the realm of re-appreciation of

evidence which this Court must not resort to. The overall reading of the

evidence and the contemporaneous correspondence by the Learned

Arbitral Tribunal would indicate that the finding of absence of readiness

and willingness to perform is an eminently plausible view that does not

call for interference.

28. Indeed, the Trust had delivered an approval from the Government

of Maharashtra for development under Regulation 33(7) of the DCR,

which informed the basis of the bargain between the parties. The

Municipal Commissioner rejected this on the premise that the

department that gave the permission was the wrong one (Housing

Department instead of Urban Development Department), but then the

parties had entered into the arrangement with eyes open and the

Developer has also confirmed satisfaction with examination of all facets of

Page 19 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

the matter when entering into the bargain with the Trust. The hurdle

posed by the Municipal Commissioner rejecting the very basis of

Regulation 33(7) being applicable, even when taken as a facet outside the

scope of the parties’ expectations and control, it would undermine the

specific performance of the Development and not further the same.

Indeed, the departure into Regulation 33(6) could be said to fall within

the zone of consideration of acquiescence to the situation but it would still

not point to a sharp and precise revised bargain that is amenable to

specific performance.

29. The Learned Arbitral Tribunal has also examined the fact that there

is a pointer to the fifth floor being legitimate from the records obtained

under the law governing right to information. The Learned Arbitral

Tribunal has fairly held that the Developer was aware of the project it was

getting into and ought to have done its due diligence before executing a

contract of which it is seeking specific performance.

30. The Termination Notice was issued two years after the Trust is

contended to have lauded the Developer for managing to secure approvals

for the Hostel, and indeed the Learned Arbitral Tribunal has held that the

Termination Notice was illegal as being contrary to contract. However, to

grant specific relief, the Developer would still need to have demonstrated

readiness and willingness to perform on a precise, binding and committed

revised contract and that is not discernible from the record – in itself, a

Page 20 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

matter of adjudication and appreciation of evidence. Therefore, to my

mind, the finding that the Termination Notice is “illegal” would at worst

be a problematic finding but it is not a finding that presents a perversity

of such a magnitude that it would go to the root of the matter of specific

relief, for the Impugned Order to be interfered with.

31. I find that the Learned Arbitral Tribunal has instead adopted a

practical, commonsensical and commercially logical interpretation even

while holding that the Development Agreement was inca pable of

termination – that even the termination was not contractually envisaged

(indeed the Learned Arbitral Tribunal terms the termination “illegal” a

few times), the Development Agreement was not capable of specific

performance. Therefore, specific relief could not have been granted for

the asking in the teeth of the principles governing specific relief, which at

the least, requires a specific committed obligatory element that can be

enforced under supervision of the Court. That being the case, no fault can

be found with the finding that specific relief was not worthy of being

granted.

32. To reconcile the two positions, namely, that termination was illegal

and yet specific relief could not be granted, it is apparent to me that the

Learned Arbitral Tribunal has simply adopted the principle of restitution

to place the parties in the respective positions that they were in before

executing an apparently interminable contract that is incapable of specific

Page 21 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

performance. The Learned Arbitral Tribunal rejected the competing

claim for damages; directed that the Trust be put in possession; and

directed that the Trust must return the amount of Rs. 3.69 crores paid by

the Developer to the Trust, along with interest. The Learned Arbitral

Tribunal has indeed reconciled the two positions presented as being

inherently contradictory and to my mind there is no fatal contradiction or

inconsistency in the analysis that flows through this issue in the

Impugned Award.

33. The contention that the MCGM Order constitutes vital evidence

that has been ignored also does not appeal to me. Each party has made

submissions on how the MCGM Order helps its respective case, but

suffice it to say, the Section 34 Court must resist the temptation of being

drawn into interpreting the true import of this document and should

instead examine whether that document contains any vital evidence that

has been ignored. I find that the core elements and contents of the

MCGM Order have indeed been analysed in the Impugned Order to

factually arrive at a finding of a shortfall in the commitment of the

Developer to deliver the Agreed Area and therefore, it cannot be said that

any vital evidence has been ignored. At worst, the Developer could be

said to be unhappy with the interpretation of the evidence by the Learned

Arbitral Tribunal, but one cannot say that the Learned Arbitral Tribunal

Page 22 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

failed to appreciate vital evidence to render the Impugned Award patently

illegal.

34. For the foregoing reasons, in my view, the interpretation of Clauses

28 and 29 of the Development Agreement is not in foundational conflict

with the finding that the core and essential term of the contract was

delivery of Agreed Area to the Trust. Therefore, whether or not the

Termination Notice is illegal, the finding that no case for specific relief

has been made out cannot be faulted. Presented with this seemingly

dilemmatic situation, the Learned Arbitral Tribunal has fairly and

reasonably held that the parties need to put back in their respective

positions, without any award of damages since both sides entered into the

bargain with eyes open and ran the risk of the costs and damages they

have respectively suffered. The Learned Arbitral Tribunal has fairly held

that neither party deserves to be saddled with damages for a contract

incapable of specific performance. Therefore, in my opinion, the

Impugned Award does present a wholesome outcome that is plausible,

logical and reasonable, and does not lend itself to interference under

Section 34 of the Act.

35. This brings me to the contentions of the PSCC Act, namely, that the

Developer is a licensee and is a protectee of the statutory tenant-

protection provisions of that legislation and the ouster of forums other

than the Small Causes Court from adjudication of a licensee eviction. The

Page 23 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

Learned Arbitral Tribunal has examined this squarely, to return a finding

that the license or the right to enter upon the property is incidental and

inextricably linked to the right to develop the Subject Property. If the right

to specific performance of the obligation to permit the Developer to

develop the Subject Property is not found worthy of acceptance, it would

follow that the incidental right to enter upon the Subject Property and

develop it would come to an end.

36. In my view, the contention of the Developer that it is a statutory

protectee of the PSCC Act is extreme and unreasonable. Provisions of

beneficial and ameliorative legislation must be interpreted in the context

of the objectives of the legislation. It is well settled that if more than one

view is possible, the view that furthers the remedy and suppresses the

mischief in the objective of the legislation would need to be adopted. The

Developer is hardly a tenant or a licensee who has been given the right to

use the Subject Property for a license fee. On the contrary, the Developer

in the same breath claims an interest in the Subject Property with a right

to exploit it and sell units from the free sale component, which itself

stands undermined. The license to enter the Subject Property is an

incidental and ancillary right and can simply not be elevated to a tenancy-

protection right under the PSCC Act. No fault can be found with the

Learned Arbitral Tribunal’s analysis of this issue to reject the

jurisdictional challenge.

Page 24 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

37. Finally, the purported absence of permission from the Charity

Commissioner to litigate should be stated to be rejected. This is another

novel argument in the process of throwing the kitchen sink at the

problems the Impugned Award poses to the Developer. While this may

not have been raised before, it is evident from the record that the Charity

Commissioner is not unaware of the litigation that the parties have been

engaged in, and has postponed consideration of an extension of approval

for the redevelopment, to await the outcome of the arbitration. This

ground is based on the regulatory scheme relating to governance of

charities. This is of no avail for a contractual counterparty to place

reliance on, and that too after the arbitral proceedings have been

concluded, of course, the outcome being unsatisfactory to such

counterparty.

38. The Learned Arbitral Tribunal has also analysed the absence of

consent from 70% of the tenants. However, I do not think it necessary to

delve into the issue of tenants’ consents not having been obtained since

the Developer is not pressing anything related to this issue except in

defence of the contentions of the Trust that invokes this issue. The

analysis in this judgement, bearing in mind the scope of jurisdiction

under Section 34 of the Act, is restricted to the grounds on which the

Developer has assailed the Impugned Award.

Page 25 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

Some Relevant Case Law Extracts:

39. Before parting, a word about the scope of review under Section 34

would be in order. Without intending to undertake a prolix reproduction

from the numerous judgements that now well settle the standard, in the

context of incoherence and inherent inconsistency being alleged by the

Developer, the following extracts from Associate Builders

1

would be

appropriate (for ease of reference, the footnote in the judgement inserted

in the extracted paragraph is also set out in the extract below):

It must clearly be understood that when a court is applying the "public policy"

test to an arbitration award, it does not act as a court of appeal and con-

sequently errors of fact cannot be corrected. A possible view by the arbitrator

on facts has necessarily to pass muster as the arbitrator is the ultimate master of

the quantity and quality of evidence to be relied upon when he delivers his arbit-

ral award. Thus an award based on little evidence or on evidence which does

not measure up in quality to a trained legal mind would not be held to be invalid

on this score

[Inserted Footnote – extracted below:]

Very often an arbitrator is a lay person not necessarily trained in law. Lord

Mansfield, a famous English Judge, once advised a high military officer in Ja-

maica who needed to act as a Judge as follows:

" General, you have a sound head, and a good heart; take courage and

you will do very well, in your occupation, in a court of equity. My advice

is, to make your decrees as your head and your heart dictate, to hear

both sides patiently, to decide with firmness in the best manner you can;

but be careful not to assign your reasons, since your determination may

1 Associate Builders v. Delhi Development Authority – (2015) 3 SCC 49

Page 26 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

be substantially right, although your reasons may be very bad, or essen-

tially wrong".

It is very important to bear this in mind when awards of lay arbitrators are chal-

lenged.

[Emphasis Supplied]

40. Indeed, the Sole Arbitrator manning the Learned Arbitral Tribunal

is not a lay man and is a former Chief Justice of a High Court. However, I

felt the need to extract the foregoing not because the Impugned Award

reads like one by a layman but for emphasising the principle involved –

where the reasons for two separate findings are logical and reasonable,

and the two can be reconciled in a manner that does not make the

findings mutually repugnant, if the outcome is just, logical and

commonsensical, the arbitral award need not be interfered with. The

reasons for which the Learned Arbitral Tribunal has held the Termination

Notice to be “illegal” and the allusions to the Development Agreement

subsisting to some extent may make the denial of specific relief illogical,

but one cannot lose sight of the fact that the reconciliation of the two

seemingly conflicting positions is quite commonsensical and logical. I

have already given my reasons as to how the two positions are not

inherently conflicting. Even if this reconciliation is contended as not

being explicitly and expressly set out in the Impugned Award, it is also

well settled that even implied reasons that are discernible and are capable

of being inferred to support a just and fair outcome in arbitral awards

Page 27 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

would make it appropriate not to interfere with arbitral awards. In this

regard, the following extract from the decision of the Supreme Court in

Dyna Technologies

2

would be appropriate:

24. There is no dispute that Section 34 of the Arbitration Act limits a chal-

lenge to an award only on the grounds provided therein or as interpreted by

various courts. We need to be cognizant of the fact that arbitral awards should

not be interfered with in a casual and cavalier manner, unless the court comes to

a conclusion that the perversity of the award goes to the root of the matter

without there being a possibility of alternative interpretation which may sustain

the arbitral award. Section 34 is different in its approach and cannot be equated

with a normal appellate jurisdiction. The mandate under Section 34 is to respect

the finality of the arbitral award and the party autonomy to get their dispute ad-

judicated by an alternative forum as provided under the law. If the courts were

to interfere with the arbitral award in the usual course on factual aspects, then

the commercial wisdom behind opting for alternate dispute resolution would

stand frustrated.

25. Moreover, umpteen number of judgments of this Court have categorically

held that the courts should not interfere with an award merely because an al-

ternative view on facts and interpretation of contract exists. The courts need to

be cautious and should defer to the view taken by the Arbitral Tribunal even if

the reasoning provided in the award is implied unless such award portrays per-

versity unpardonable under Section 34 of the Arbitration Act .

[Emphasis Supplied]

Summary of Conclusions:

41. In the result, the points determined by me may be summarised

thus:

2 Dyna Technologies Private Limited v. Crompton Greaves Limited – (2019) 20 SCC 1

Page 28 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

A] The finding that the Termination Notice is illegal for not

being supported by Clauses 28 and 29 of the Developm ent

Agreement is plausible and falls within the realm of interpretation

that the Learned Arbitral Tribunal is entitled to make;

B] Such interpretation on legality of termination is not

inherently and necessarily inconsistent with the refusal to grant

specific relief to the Developer in view of the other logical,

reasonable and plausible finding that the obligation to deliver the

Agreed Area of 32,000 square feet of redeveloped area is an

essential term of the agreement between the parties;

C] The Learned Arbitral Tribunal has rightly found that there

has been no revised area that had been agreed between the parties,

for a Court-supervised enforcement of specific relief to be possible;

D] The refusal to grant specific relief is not irreconcilable with

the finding that the Termination Notice was “illegal”;

E] The objection on arbitrability on the ground of exclusive

jurisdiction under the PSCC Act is untenable since the license

granted to the Developer was incidental to the development rights

conferred on the Developer. Once such development rights are not

held as being amenable to enforcement by way of specific relief, the

license would also become irrelevant. The Learned Arbitral

Page 29 of 30

APRIL 6 , 2026

Aarti Palkar

CARBP.128.2023.Final.doc

Tribunal’s findings that the statutory tenancy protection provisions

in the PSCC Act have no relevance to the Development Agreement

cannot be faulted;

F] The objection on the ground of lack of approval for litigation

by the Charity Commissioner is untenable for the reasons set out

above. The Charity Commissioner has been aware of the litigation

and even if regulatory action were to be contemplated, it would not

have a foundational and jurisdictional basis to undermine the

Impugned Award.

42. In the result, the Section 34 Petition is finally disposed of without

any interference with the Impugned Award.

43. All actions required to be taken pursuant to this order shall be

taken upon receipt of a downloaded copy as available on this Court’s

website.

[SOMASEKHAR SUNDARESAN, J.]

Page 30 of 30

APRIL 6 , 2026

Aarti Palkar

Reference cases

Description

Legal Notes

Add a Note....