As per case facts, Indian Railways sought open access to procure power for its traction substations but was denied connectivity and directed to clarify its status as a deemed distribution ...
2026 INSC 464 C.A. Nos. 4652-59/2024 Page 1 of 59
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 4652 OF 2024
INDIAN RAILWAYS ...APPELLANT(S)
VERSUS
WEST BENGAL STATE ELECTRICITY
DISTRIBUTION COMPANY
LIMITED & ORS. …RESPONDENT(S)
WITH
CIVIL APPEAL NOS. 4653-4659 OF 2024
J U D G M E N T
SATISH CHANDRA SHARMA, J.
1. This is a batch of statutory Appeals under Section 125 of the
Electricity Act, 2003 (for short, hereinafter referred to as, “The
Electricity Act”) assailing the common judgment and order dated
12.02.2024 passed by the Appellate Tribunal for Electricity at New
Delhi, (“APTEL”), in Appeal Nos. 276/2015, 320/2018, 114/2020,
73/2021, 213/2021, 170/2019, 343/2019 and 133/2020.
C.A. Nos. 4652-59/2024 Page 2 of 59
2. By the said judgment, APTEL has set aside the Order dated
05.11.2015 passed by the Central Electricity Regulatory
Commission (“CERC”) in Petition No. 197/MP/2015 along with
connected appeals arising from Orders passed by other State
Electricity Regulatory Commissions (“SERCs”).
3. The proceedings before APTEL were contested by multiple
Distribution Companies (DISCOMS) and SERCs, including the
West Bengal State Electricity Distribution Company Ltd.
(WBSEDCL), Odisha Electricity Regulatory Commission
(OERC), Kerala State Electricity Regulatory Commission
(KSERC), Madhya Pradesh Electricity Regulatory Commission
(MPERC), Rajasthan Electricity Regulatory Commission (RERC),
Maharashtra Electricity Regulatory Commission (MERC), Haryana
Electricity Regulation Commission (HERC), Punjab State
Electricity Regulatory Commission (PSERC), as against the Indian
Railways, the Appellant herein.
4. The controversy pertained to common issues: (i) whether
Indian Railways qualifies as a deemed distribution licensee (DDL)
under the third proviso to Section 14 of the Electricity Act; and (ii)
if so, whether it remains liable to pay Cross-Subsidy Surcharge to
different distribution licensees for availing open access in terms of
Section 42 of the Electricity Act. Five out of the eight State
Electricity Regulatory Commission (SERCs) had held that the
C.A. Nos. 4652-59/2024 Page 3 of 59
Indian Railways is not a DDL (“DDL”) in terms of the third proviso
to Section 14 of the Electricity Act.
Factual matrix
5. The facts in the case are undisputed and are succinctly
mentioned as under:
5.1. The Appellant, Indian Railways vide Letter dated
17.03.2015 to the Maharashtra State Electricity Transmission
Co. Ltd. (“MSETCL”) sought grant of connectivity for
procuring 100 MW power from Gujarat Urja Vikas Nigam
(“GUVNL”) for 16 traction substations of the Central and
Western railways through inter-state open access in terms of the
Electricity Act. MSETCL refused to grant connectivity and
directed the Indian Railways to obtain an appropriate order from
the competent commission regarding its status as a DDL.
5.2. The Appellant approached the CERC by way of a
petition, inter-alia seeking declaration that the Indian Railways
is entitled to the grant of open access for the power to be procured
from the Generating Station through the Inter-State Transmission
System (“ISTS”) of Central Transmission Utility and Intra-State
Transmission System of the States (viz. Maharashtra, Gujarat,
Jharkhand and West Bengal), to its facilities, i.e., traction points
and network of the Indian Railways, and direct that the Indian
Railways in its capacity as an authorised entity to distribute and
C.A. Nos. 4652-59/2024 Page 4 of 59
supply electricity is a separate participating entity, like any other
State entity notified by the Commission for the purposes of
scheduling and dispatch of electricity. The petition was filed
against the backdrop of the Letter No-25/19/2004-R&R dated
06.05.2014 issued by the Ministry of Power, Government of
India
1
which clarified that the Appellant i.e. the Indian Railways
is a deemed licensee under the third proviso to Section 14 of the
Electricity Act and for all purposes thereunder. It was urged by
the Appellant that:
(a) Firstly, it is a DDL under Section 14 of
Electricity Act, and that being a Department of the
Ministry of Railways, Government of India, the
Appellant qualifies as the “Appropriate Government”
and therefore has the deemed licensee status under the
third proviso to Section 14 of the Electricity Act.
Reliance was placed on Letter dated 06.05.2014 issued
by the Ministry of Power, Government of India that
clarified that “Railways is a deemed licensee under the
third proviso to Section 14 of the Electricity Act”. It
contended that the deeming fiction in the proviso
confers upon it, the status of a DDL and by virtue
thereof shall be subject to benefits and/or privileges
1
Letter No-25/19/2004-R&R dated 06.05.2014 issued by the Ministry of Power,
Government of India
C.A. Nos. 4652-59/2024 Page 5 of 59
emanating therefrom. It was their unilateral assertion
that as regards the grant of open access, a DDL shall be
granted non-discriminatory open access without the
obligation to pay Cross-Subsidy Surcharge and the
Additional Surcharge under the Electricity Act; and
(b) Secondly, it operates the rail systems in India as
per the provisions of the Railways Act (“Railways
Act”), which constitutes a complete code in itself and
overrides the provisions of the Electricity Act by virtue
of the non-obstante provision in Section 11 of the
Railways Act and Section 173 of the Electricity Act.
Therefore, its operations are independent of its status
under the Electricity Act, and it is entitled to distribute
and supply electricity under Section 11 of the Railways
Act.
5.3. The West Bengal State Electricity Distribution
Company Ltd. (“WBSEDCL”) impleaded as a party before the
CERC vide Order dated 12.10.2015, challenged the
maintainability of the Petition filed by the Appellant on the
grounds that, since no application for open access had been filed
in the respective States, and that the process for the grant of inter-
state open access as per the extant regulations had not been
necessarily complied with, therefore, the question of dispute with
respect to the open access did not arise.
C.A. Nos. 4652-59/2024 Page 6 of 59
5.4. The CERC vide Order dated 05.11.2015 observed that
Section 11(g) of the Railways Act authorizes the Railway
Administration “to erect, operate or repair any electric traction
equipment, power supply and distribution installation in
connection with the working of the railway.” It held that the use
of terms “power supply and distribution installations” indicates
that the Railway Administration is entrusted with the function of
establishing and operating a distribution network for supply of
power to the various railway installations. Placing reliance on the
judgment of General Manager, Northern Railways rep. by
Union of India v. Chairman, Uttar Pradesh State Electricity
Board & Ors.
2
and the Letter dated 06.05.2014 issued by the
Ministry of Power, it further held that Indian Railways was
authorised under the Railways Act to undertake transmission and
distribution activities with relation to its operations. Accordingly,
the CERC held:
(a) Indian Railways/Appellant is an authorised
entity under the Railways Act for carrying out
transmission and distribution activities for ensuring
supply of power in connection with the working of the
railways, without having to obtain a license from the
appropriate Commission.
2
[2012] 3 SCC 329
C.A. Nos. 4652-59/2024 Page 7 of 59
(b) Being an authorized entity, it shall be entitled for
grant of open access in connection with the working of
the Railways, as per provisions applicable to a
distribution licensee.
(c) It is a DDL under the third proviso to Section 14
of Act and is bound by the terms and conditions for a
licensee as specified under Section 16. Hence, no
separate declaration to this effect was required.
5.5. Aggrieved by the observations of the CERC, the
WBSEDCL filed Appeal no. 276/2015 before the Appellate
Tribunal. Subsequently, seven appeals as enlisted hereunder
were filed by the Appellant and relevant distribution companies
(DISCOMS), challenging Orders by the respective SERCs on
the identical issue. The following Appeals were heard together
by the APTEL:
WBSEDCL v. CERC
& Ors; Appeal No. 276/2015
CERC Order dated 05.11.2025
Held: Indian Railways is a DDL
under the third proviso to
Section 14 of the Electricity Act.
Indian Railways v. MERC
& Ors.; Appeal No. 343/2019
MERC Order dated: 05.04.2019.
Held: Indian Railways is a DDL.
Indian Railways v. Kerala State
Electricity Board Limited & Ors.;
Appeal No. 73 of 2021
KSERC Order dated: 12.12.2019.
Held: Indian Railways is a DDL and
was directed to pay charges
as applicable for open access.
C.A. Nos. 4652-59/2024 Page 8 of 59
Punjab State Power
Corporation Ltd v. PSERC
& Ors.; Appeal No. 320 of 2018
PSERC Order dated: 28.02.2018.
Held: Indian Railways is not a DDL.
Indian Railways v. Odhisa Power
Transmission Corporation Ltd &
Ors; Appeal No. 114 of 2020
OERC Order dated: 25.02.2020.
Held: Indian Railways is not a DDL.
Indian Railways v. MP Poorv
Kshetra Vidyut Vitran
Company Ltd & Ors.;
Appeal No. 213 of 2012
MPERC order dated: 05.05.2021.
Held: Indian Railways is not a DDL.
Indian Railways v. Jaipur Vidyut
Vitaran Nigam Ltd & Ors.;
Appeal No. 170 of 2019
RERC Order dated: 23.04.2019.
Held: Indian Railways is not a DDL.
Indian Railways v. Dakshin
Haryana BijliVitran Nigam
Ltd & Ors.;
Appeal No. 133 of 2020
HERC Order dated: 17.06.2020.
Held: Indian Railways is not a DDL.
5.6. At the outset, APTEL passed an interim Order dated
16.12.2015 in favour of the Appellant, whilst prima facie
observing that:
(a) By virtue of Section 11 of the Railways Act, the
Appellant appears to have full authority to undertake
distribution and supply of electricity. Section 11 cannot
be given a restricted meaning in light of the decision in
Northern Railways (supra);
(b) The power to erect, maintain and operate
traction equipment, lines, power supply and
C.A. Nos. 4652-59/2024 Page 9 of 59
distribution installation under the said provision
necessarily implies the use of such equipment to
distribute and supply electricity;
(c) The decision in Sesa Sterlite Limited v. Orissa
Electricity Regulatory Commission & Ors.
3
, which
laid an emphasis upon a distribution licensee to operate
and maintain a distribution system and supply power to
consumers, is not applicable to the Appellant herein as
Section 173 of the Electricity Act makes it clear that in
case of inconsistencies in the Railways Act, the latter
shall prevail over the Electricity Act;
(d) The relief sought by the Railways was for the
grant of open access through the Inter-State
Transmission Network of the Central Transmission
Utility, to which it is entitled on a non-discriminatory
basis. For this reason, the Petition before the CERC was
maintainable despite the absence of any independent
applications to State Transmission Utilities or
distribution licensees. The distribution licensees of
various States were also held to be not necessary or
proper parties to the said petition.
3
[2014] 8 SCC 444
C.A. Nos. 4652-59/2024 Page 10 of 59
5.7. Vide its Final Judgment and Order (“Impugned Judgment”)
dated 12.02.2024, however, APTEL rejected the claim of the
Appellant to be recognised as a deemed distribution licensee within
the ambit of the third proviso to Section 14 of the Electricity Act. It
further held that since the entire electricity received by the Railways
is consumed for its own use and its constituents, it is liable to pay
Cross-Subsidy Surcharge and Additional Surcharge to the respective
distribution licenses as any other consumer under Section 42 of the
Electricity Act. The following are the key observations by APTEL:
(a) Appellant cannot be held to be a DDL, insofar as it does
not distribute electricity. A distribution licensee defined under
Section 2(17) of the Electricity Act must (i) operate and
maintain a distribution system, and (ii) supply electricity to
consumers in its area of supply. The distribution installation
and electric traction of the Appellant is not a distribution
system within Section 2(19) of the Electricity Act, insofar as
a distribution system must connect the delivery point on a
transmission line to the point of connection or installation of
the consumer. Locomotives, signal equipment, and station
facilities are constituents of the Appellant itself and do not
qualify as consumers within the meaning of Section 2(15) of
the Electricity Act. Thus, the Appellant itself is a consumer. It
receives electricity at its traction sub-stations (TSSs) from
distribution licensees, supply authorities, and then conveys it
C.A. Nos. 4652-59/2024 Page 11 of 59
to locomotives, stations and other installations within its
operational domain. Conveyance of electricity within this
internal network is for the own consumption of the Appellant
and does not constitute distribution.
(b) The Clarificatory Letter dated 06.05.2014 issued by the
Ministry of Power, relied upon by the Appellant is an
administrative directive under Section 107 of the Electricity
Act, and is not mandatory in nature.
(c) The statutory powers granted to the Railways
administration under Section 11 of the Railways Act are
confined to the construction and maintenance of railway
works for running railway operations. Mere establishment of
distribution installation does not authorise the Appellant to
qualify as a DDL and supply electricity to consumers.
(d) In light of the decision in Sesa Sterlite (supra), even if
the Appellant was treated as a DDL or transmission licensee
and seeks to avail open access, it is still liable to pay Cross-
Subsidy Surcharge and additional surcharge as the electricity
procured by it, is for its own consumption and operation.
(e) The contents of the 31
st
Report of the Parliamentary
Standing Committee on Energy dated 19.12.2002 reflect that
the Appellant had sought exemption from the obligations of
distribution licensees under Sections 12, 42, and 47 of the
C.A. Nos. 4652-59/2024 Page 12 of 59
Electricity Act. The request by the Appellant seeking such an
exemption itself demonstrates that it was well aware that
Section 2(31)(c) read with Section 11(g) & (h) of the
Railways Act did not absolve it from obtaining a distribution
license and/or discharging the obligations of a distribution
licensee under the Electricity Act.
6. Aggrieved, the Appellant has approached this Court
challenging the legality and correctness of the Impugned Judgement
of APTEL dated 12.02.2024. The captioned Appeal was
accompanied by IA no. 80269/2024 seeking stay of the Judgment
under challenge passed by APTEL. Vide Order dated 06.05.2024,
this Court had directed that subject to the final adjudication of the
present Appeals, the Appellant shall not be required to pay either the
Cross-Subsidy Surcharge or Additional Surcharge to the
distribution licensees, and it was made clear that the open access
shall not be denied to the Appellant for that reason.
Submissions on behalf of Railways
7. Mr. M.G. Ramachandran, learned Senior Counsel for the
Appellant challenged the observations of APTEL as unsustainable
in law for the following reasons:
(a) It is the case of the Appellant that it is vested with the
statutory authority under Section 11 read with Section
2(31)(c) of the Railways Act, to lay down an electrical
system, including a transmission and distribution system
C.A. Nos. 4652-59/2024 Page 13 of 59
within its area of operation. The authority under the Railways
Act expressly includes executing all necessary works,
including laying down an electric distribution system over the
length and breadth of the country, and extends to the activities
of conveying electricity necessary for use at different places,
points, and purposes for the operations of the railways, which
cannot be interfered with by the operation of the Electricity
Act.
(b) Section 11 of the Railways Act begins with a non-
obstante clause, and the statutory power thereunder is
absolute in nature. Placing reliance on the decision of
Northern Railways (supra), it is contended that APTEL erred
in distinguishing that the authority under Section 11 was
confined only to transmission and not distribution. The
Appellant submits that Northern Railways (supra)
authoritatively laid down that the act of constructing its
transmission lines, and drawing power from external power
sources, falls within the statutory domain of the Railways Act.
(c) Section 11 has an overriding effect, and several High
Courts across the country have observed that the Railways
Act consolidates the law and is not a mere regulatory statute.
4
It is contended that enactments such as the Environment
4
Ganv Bhavancho Ekvott v. South Western Railways [2022] SCC Online Bom
7184
C.A. Nos. 4652-59/2024 Page 14 of 59
Protection Act have no application over works undertaken by
the Railways in exercise of the powers under Section 11 of
the Railways Act. Learned Senior Counsel submits that
APTEL made a fatal error in construing Section 11 and other
allied provisions of the Railways Act, with reference to the
Act.
(d) Reliance was passionately placed on Ganv Bhavancho
Ekvott v. South Western Railways
5
whereby the High Court
had held that the Southern Railway (SWR) and the Rail Vikas
Nigam Limited (RVL) were not under any statutory
compulsion to obtain environmental clearances or any
building permission from authorities and agencies under the
other legislations. It was held that the exemption for railway
administration to execute the works of construction and
maintenance of railway is conferred by the non-obstante
clause which has an overriding effect on all other laws except
for the Railways Act
6
and the legislation referred to in Section
11 itself. The Appellant herein submitted that power under
section 11 is thus unfettered and unqualified, and the status of
the Appellant under the Electricity Act is inconsequential,
insofar as the authority to distribute electricity is
5
Ganv Bhavancho Ekvott (supra)
6
Union of India (Western Railway) vs MCGM [2017] SCC Online Bom 9424; Goa
Foundation & Anr. vs Konkan Railway Corporation & Ors. [AIR] 1992 Bom 471;
Village Panchayat of Velsao vs Ministry of Railways [2022 SCC Online Bom 3526]
C.A. Nos. 4652-59/2024 Page 15 of 59
independently conferred under the Railways Act. The non-
obstante clause under Section 11 of the Railways Act implies
that the powers under the provision are exclusive. Section 173
of the Electricity Act further settles the dispute by providing
that, in the event of any inconsistencies, only the Railways
Act shall prevail.
(e) The Railways Act is a complete code in itself. The
statute expressly authorises the Appellant to lay down a
“distribution installation” for the operation of railways. By
their very nature, such installations are intended for the
purpose of distribution, thereby implying that the Appellant is
statutorily empowered to distribute electricity. Since this
power flows directly from the parent statute, no separate
authorization or license under any other law is required.
(f) Without prejudice, the Appellant is a DDL as per the
third proviso to Section 14 of the Electricity Act. Being an
entity of the Central Government, the Appellant is an
Appropriate Government within the definition of Section 2(5)
and is therefore exempt from obtaining a license in terms of
the third proviso to Section 14 of the Electricity Act. Further,
electric traction equipment, power supply systems, and
distribution installation used for the purposes of, or in
connection with a railway, fall within the statutory definition
of railways under Section 2(31) of the Railways Act. Thus,
C.A. Nos. 4652-59/2024 Page 16 of 59
distribution of electricity is an inherent function of the
Appellant.
(g) Although the term “distribution” is not defined under
the Railways Act or under the Electricity Act, in the ordinary
and natural sense, the term “distribute” means spreading of
goods anywhere by whatever means, and in the context of the
present case, it would mean any activity that involves the
conveyance of electricity from one point to another for use at
different locations. Accordingly, any activity involving the
conveyance of electricity from one source to another would
fall within the ambit of “distribution.” It is argued that in the
context of railways, the conveyance of electricity from
traction and non-traction substations through wires and
associated electrical systems to points of end use does not
merely amount to transmission or consumption in its area of
operation, but constitutes “distribution of electricity” within
the meaning and scope of the Electricity Act.
(h) Section 2(70) that defines “supply” as the sale of
electricity, is not a licensed activity under the Electricity Act.
Under the previous regime of the Indian Electricity Act, 1910,
its Section 3 specifically provided for the grant of a license to
a person for the supply of energy within a specified area,
along with the laying of electric supply lines for the
conveyance and transmission of energy.
C.A. Nos. 4652-59/2024 Page 17 of 59
(i) The statutory scheme of the Electricity Act consciously
departed from this position and distinguishes the two terms of
“distribution” and “supply”. The present statutory framework
under the Electricity Act reflects a deliberate legislative shift
by excluding “supply of electricity” as a licensed activity,
while retaining the licensing requirement for “distribution”,
thereby maintaining a clear distinction between the two
activities. It is submitted that the distinction has been
overlooked by APTEL, as it held that the Appellant cannot
claim the status of a DDL under Section 14 of the Act, as it is
not in the business of selling electricity to consumers, and is
only an end user of electricity. Being an entity of the Central
Government, it is an Appropriate Government and has the
status of a DDL as per the third proviso to Section 14 of the
Electricity Act. Section 2(5)(a) of the Electricity Act contains
no restriction that the reference to the Central Government
should be only with the references to the activities of other
agencies, supervised or regulated by the Central Government.
8. Ms. Aishwarya Bhati, learned ASG appearing for the Union
of India, submitted that:
(a) The Indian Railways is integrated with the Central
Government, and qualified as the “Appropriate Government”
under Section 2(5)(a)(ii), of insofar as:
C.A. Nos. 4652-59/2024 Page 18 of 59
(i) Railways is a union subject in terms of the
Seventh Schedule of the Constitution of India;
(ii) Rail Budget is part of the General Budget, and
its receipts and expenditure form part of the
Annual Financial Statement under Article 11;
(iii) Revenue generated by the Railways is credited
to the Consolidated Fund of India, confirming
its status as a departmentally run undertaking of
the Union.
(b) The Government of India (Allocation of Business),
Rules, 1961 and the Government of India (Transaction of
Business) Rules, 1961 further reflect the sovereign status of
the Ministries of the Government of India. It is argued that the
fiscal identity of the Ministry of Railways is inseparable from
the Union of India and the national exchequer. The status of
the Appellant flows from the sovereign executive power of
the Union under Article 73 of the Constitution.
9. Based on the aforesaid submissions, learned senior counsels
urged this Court to allow the Appeal and set aside the Impugned
Judgment of APTEL, and further grant non-discriminatory open
access to the Appellant, recognizing its status as a DDL in terms of
the third proviso to Section 14 of the Electricity Act.
C.A. Nos. 4652-59/2024 Page 19 of 59
Submissions on behalf of Respondents
10. Per contra, it has been asserted by the Respondents’
DISCOMS that the Indian Railways is not a DDL under the
Electricity Act. It is submitted that the Appellant is misconstruing
Section 11 read with Section 2(31) of the Railways Act to contend
that it is authorized to distribute electricity. As per the said
contention, the statutory framework under the Railways Act, only
empowers the Appellant to consume electricity for its own use, and
does not extend to the supply of electricity to consumer.
11. The DISCOMS were represented by learned Senior Counsels
Mr. C.A. Sundaram, Mr. Vaidyanathan, Mr. Maninder Singh, Mr. S.
Poovayya, Mr. Parag Tripathi, appearing on behalf of their
respective Respondents. The present submissions are common to all
the Respondents herein and are being advanced collectively under a
single head for the sake of brevity and convenience.
12. The submissions advanced on behalf of the Respondent-
DISCOMS collectively and individually are summarized as follows:
(a) Mr. Vaidyanathan, learned Senior Counsel for
WBSEDCL submitted that distribution is inextricably linked
with the supply by way of sale of electricity to consumers
within an area of supply, and that the levy of Cross-Subsidy
Surcharge and Additional Surcharge is a statutory
C.A. Nos. 4652-59/2024 Page 20 of 59
consequence of a consumer availing open access from a
source other than the distribution licensee within its area.
(b) Section 11(g) of the Railways Act is a provision
appearing under the Chapter titled “Construction and
Maintenance of Works”. It merely authorizes the Appellant to
erect, operate, maintain or repair any electric traction
equipment, power supply and distribution installation in
connection with the working of the railways. The non-
obstante provision therein would only be restricted to clauses
(a) to (h). Furthermore, there is no inconsistency between
Sections 14 and 42 of the Electricity Act and Section 11 of the
Railways Act in terms of Sections 173 of the Electricity Act.
Thus, the Electricity Act shall apply.
(c) Mr. S. Poovayya, learned Senior Counsel for various
TP Odisha DISCOMS, submitted that a system that does not
ultimately connect to the installation of a consumer is not a
distribution system at all under the Electricity Act as Section
2(19) of the Electricity Act defines “distribution system” as
under:
"distribution system" means the system of
wires and associated facilities between the
delivery points on the transmission lines or
the generating station connection and the
point of connection to the installation of the
consumers;
C.A. Nos. 4652-59/2024 Page 21 of 59
(d) He submitted that the definition itself indicates that a
distribution system is intended for connection to the
installation of the consumer or last-mile connectivity. In the
context of Railways, only if the system of wires and facilities
is connected to the end point of transmission lines or a
generator with the point of connection to a consumer, will it
fall within the specific definition of a distribution system
under the Electricity Act.
(e) Adverting to the activities of the Indian Railways, he
submitted that an installation laid down for the functioning of
the Railways, which does not ultimately connect to the
premises of a consumer cannot be considered a consumer
under the Electricity Act. For this reason alone, the Railways’
internal network and conveyance of electricity within its area
of operation, falls outside the scope of a distribution system
set up for the supply of electricity.
(f) He further submitted that “conveyance” of electricity
does not constitute “distribution” of electricity. Even if the
sub-station serves as the delivery point or the final point of
connection, it is only an additional point of internal
distribution installation, and the power procured by the
Railways continues to be consumed solely by itself.
(g) Mr. Maninder Singh, learned Senior Counsel appearing
on behalf of KSEBL submitted that the Petition O.P. No.
C.A. Nos. 4652-59/2024 Page 22 of 59
31/2019 filed by the Appellant before the KSERC had sought
the grant of open access to avail power supply from a
generating station in Bihar or any other source to the Railway
traction substations. It is argued that the nature of relief
sought by the Appellant was itself for its own consumption,
and not for the further distribution or supply to consumers.
Thus, the Appellant is a consumer as it procures electricity for
its own end-use and operations. Hence, KSERC vide Order
dated 12.12.2019 had directed that the DISCOM/KSEBL
shall issue a No-Objection Certificate in favour of the
Appellant to avail open access subject to the payment of
charges applicable to consumers.
(h) Mr. Singh further argued that the Appellant is not an
Appropriate Government in terms of the third proviso to
Section 14 as the definition is context dependent and does not
fulfil the statutory scheme of the Electricity Act. In particular,
Section 2(5)(ii) provides twin conditions that for the Central
Government to be the Appropriate Government there must be
any Inter-State generation, transmission, trading or sale with
respect to the Railways. None of the four activities are
undertaken by the Railways. Accordingly, it is not the
Appropriate Government.
(i) He further submitted that the electricity provided by the
Railways within its premises to its vendors, contractors or
C.A. Nos. 4652-59/2024 Page 23 of 59
agencies is not supply of electricity, as “supply” is defined
under Section 2(70) to mean sale of electricity to consumers.
In the present case, the Railways admittedly does not sell the
electricity to consumers, nor does it have any consumers. The
reliance on Northern Railways (supra) is misplaced as the
judgment dealt with the power of the Railways to construct
its own transmission lines, emphasising the non-obstante
provision in Section 11. It is nowhere held that while
consuming the electricity supplied directly by a Generating
Company, it would be treated as engaged in distribution of
electricity. In fact, the issue of distribution was never
considered or dealt with.
(j) Mr. Singh, also brought our attention to the Draft
Electricity Amendment Bill, 2025, and placed reliance on
Board of Control for Cricket in India v. Kochi Cricket Pvt.
Ltd. & Ors.
7
to assert that the proposed bill to amend a
provision demonstrates that the provision cannot be
interpreted in terms of the proposed amendment which has
not been passed, and buttress the submission of the Appellant
that the exemption in the proposed Electricity Amendment
Bill, 2025 shall be applicable to the Appellant even before the
enactment.
7
[2018] 6 SCC 287
C.A. Nos. 4652-59/2024 Page 24 of 59
(k) Mr. Parag Tripathi, learned Senior Counsel appearing
on behalf of PSPCL, while re-iterating the submission by
other Senior Counsels specifically brought our attention to the
Handbook on Power Supply Installation in Electric Traction
issued by the Indian Railway Engineering Institute which
provided that though the power supply and distribution
system is maintained by the Appellant, power is availed by
the Railways from the ‘supply authority’ either as a consumer
of a distribution licensee or through a bilateral transaction via
open access. This factum alone establishes that the Appellant
is a consumer under the Electricity Act.
(l) Mr. C.A. Sundaram, learned Senior Counsel for
SBPDCL reiterating the submissions made by the other
Counsels, has further vociferously argued that the Railways
is not the Appropriate Government for the purposes of the
third proviso to Section 14 of the Electricity Act. He
submitted that the mere fact that the Central Government is
running the Railways, it will not convert the activity of
carrying on of a business into an activity of the Central
Government as a sovereign body. It was urged that the
“appropriate Government” would necessarily mean the
Government in its sovereign capacity and not the Government
C.A. Nos. 4652-59/2024 Page 25 of 59
running its business and in exercise of its powers vested under
Article 298 of the Constitution
8
.
(m) Mr. Sundaram further brought our attention to the
definition of “railway administration” under section 2(32) of
the Railways Act, and that the mere fact that the Central
Government oversees the operations of the Railways does not
transform the Railways or the railway administration into the
Central Government itself. He further urged that the supply
of electricity by the Appellant to its entities due to a jural
relationship is not supply of electricity.
(n) He further submitted that the proposal of a Draft
Electricity Amendment Bill, 2025 seeks to amend Section
61(g) of the Electricity Act insofar as it aims to reduce and
eliminate the Cross-Subsidy Surcharge for railways within
five years. It is contended that the legislative proposal to
amend the existing legal framework and reduce the Cross-
Subsidy Surcharge for the Indian Railways, itself denotes that
no such provision or privilege exists under the current statute
that absolves the Appellant from payment of the Cross-
Subsidy Surcharge applicable to any consumer in terms of
Section 42 of the Electricity Act.
8
Union of India & Anr. v. Sri Ladulal Jain [1963 SCC Online SC 133]
C.A. Nos. 4652-59/2024 Page 26 of 59
13. Based on the aforesaid submissions, learned Senior Counsels
urged this Court to dismiss the Appeal and uphold the Impugned
Judgment of APTEL.
Issues
14. Based on the submissions of the parties, the specific issues
which arise for determination are:
(i) Whether the activities provided under Section 11(g) and
(h) of the Railways Act pass muster of “distribution” of
electricity, and whether such activities are a necessary
pre-requisite to qualify as a DDL under the Act?
(ii) Whether the Indian Railways, being an entity of the
Central Government, falls within the ambit of
“Appropriate Government” under Section 14 of the Act?
(iii) Whether the Indian Railways, even if held to be a DDL
under the Act, is exempt from the obligation to pay
Cross-Subsidy Surcharge or additional surcharge for the
grant of non-discriminatory open access as per Section
42 of the Act?
(iv) Whether a proposed legislation may be relied upon as an
aid to statutory interpretation for addressing gaps in the
existing framework, and to give effect to the
parliamentary intent to remedy defects thereunder?
C.A. Nos. 4652-59/2024 Page 27 of 59
Analysis
Issue (i): Whether the activities provided under Section 11(g) and
(h) of the Railways Act pass muster of “distribution” of electricity,
and whether such activities are a necessary pre-requisite to qualify
as a DDL under the Act?
15. Before examining whether the activities of the Appellant fall
within the purview of a distribution licensee (or a deemed
distribution licensee, as the case may be), it is crucial to examine the
statutory scheme of the Electricity Act to understand the framework
governing the grant of a license as well as obligations accrued to
such licensee.
16. The distribution of electricity under the Electricity Act is
subject to a strict licensed framework. Section 2(17) defines
“distribution licensee” as a licensee authorised to operate and
maintain a distribution system for supplying electricity to
consumers in its area of supply. The term “distribution system” is
separately defined under Section 2(19) as the system of wires and
associated facilities between delivery points on the transmission
lines or the generating station connection and the point of
connection to the installation of the consumers. A conjoint reading
of the two provisions makes it clear that any person or entity seeking
the grant of a distribution license under Section 14 of the Electricity
Act must mandatorily fulfil the twin requirements- (a) operating and
maintaining a distribution system for supply of electricity to
C.A. Nos. 4652-59/2024 Page 28 of 59
consumers and (b) supplying electricity to consumers within their
area of supply.
17. These twin requirements reiterated under Section 42(1) of the
Electricity Act and Sesa Sterlite (supra), mandate that it is the duty
of a distribution licensee to develop and maintain a distribution
system in his area of supply and to supply electricity in accordance
with the Electricity Act. The term “area of supply” defined under
Section 2(3) of the Act, means the area within which a distribution
licensee is authorised by his license to supply electricity. A bare
reading of the provision indicates that the mere operation and
maintenance of a distribution system is not the exclusive basis for
the grant of a licence for distribution of electricity. Such a system
must ultimately supply electricity and connect to the point of
connection of a consumer as its end-use.
18. A plain reading of the provisions mentioned hereinabove
makes it evident that the obligation of a distribution or a DDL to
supply electricity is mandatory in nature, and is a necessary
corollary of the interpretation of the current statute. For this reason,
the argument raised by the Appellant that ‘supply’ of electricity is
not a licensed activity under the current statutory regime of the
Electricity Act and was a feature only under the Indian Electricity
Act, 1910, is a semantic issue at best.
19. Be that as it may, the Appellant claims it is a DDL in terms of
the third proviso to Section 14 of the Electricity Act. It differentiates
C.A. Nos. 4652-59/2024 Page 29 of 59
between the two terms “distribute” and “supply”, and asserts that
the Railways Act statutorily empowers the Appellant to undertake
distribution of electricity. Section 11(g) of the Railways Act
authorises the Railway Administration to erect, operate, maintain or
repair electric power supply, and distribution in connection with the
working of the railway; and Section 11(h) authorises doing all other
acts necessary for making, maintaining, altering or repairing and
using the railway. Both provisions, empower the Railways to lay,
maintain and operate power supply infrastructure for its operations.
It is contended by the Appellant that the express use of the term
“distribution installation” in Section 11 is equivalent to the term
“distribution system” under the Electricity Act and constitutes an
independent legislative recognition that the Railways is statutorily
empowered to distribute electricity.
20. The submission of the Appellant is that there is no distinction
between a “distribution system” under the Electricity Act or a
“distribution installation” under the Railways Act. The term
“distribution installation” is not defined under either of the statutes,
whereas the term “distribution system” has been specifically defined
as a system of wires and associated facilities between delivery points
on the transmission lines or the generating station connection and
the point of connection to the installation of the consumers.
21. Even if we consider that the term “distribution installation” as
the term suggests, refers to a distribution or electric infrastructure
C.A. Nos. 4652-59/2024 Page 30 of 59
authorised to be set up by the Appellant to ensure power supply for
railway operations, it cannot be considered akin to a distribution
system. The definition of a distribution system is two pronged, it is
a system of wires and associated facilities between the delivery
points on transmission lines or generating companies, which
ultimately terminates at the installation of a consumer or the point
of last-mile connectivity. For this very reason, a distribution
installation which merely conveys electricity within the integrated
railway system, from the overhead equipment to the power
locomotives, communication systems, signals and station facilities,
for its own consumption and use, and does not translate into sale or
supply of electricity to a consumer
against consideration, cannot be
held to be within the meaning and scope of a distribution system
under the Electricity Act.
22. Additionally, a distribution system also extends to a definite
and specific area of supply. The term ‘area of supply’ defined under
Section 2(3) of the Electricity Act, refers to the area within which
the distribution licensee is authorised by his license to supply
electricity. The Appellant has contended that the area of supply
under the Electricity Act, would mean the same as the area of
operation used under the Railways Act.
23. At the outset, although, the parallels drawn by the Appellant
may prima-facie seem justiciable, the two terms area of supply and
area of operation cannot denote the same meaning. The area of
C.A. Nos. 4652-59/2024 Page 31 of 59
supply necessarily refers to a designated or authorised area, where a
distribution licensee has been granted the exclusive (or non-
exclusive) right to supply electricity. As such, the Respondent
DISCOMs hold licences granted by their respective State
Commissions demarcating precise territorial limits within which
they are authorised to distribute electricity.
24. On the other hand, an area of operation refers to the operative
dimensions of an entity. In the context of Railways, it would mean
the integrated railway system spread across the length and breadth
of the country, however only limited to operational use and limit of
the railway network. The Appellant’s contention that boundaries,
fences or gates earmarked by the Central Government under Section
18 of the Railways Act, defines the area of supply for the Appellant
is wholly misconceived. To accept this submission of the Appellant
would be to hold that the pan-India operational footprint of the
Indian Railways, constitutes a single area of supply under the
Electricity Act. This is wholly absurd and inconsistent with the
scheme of the Act, insofar as the term “area of supply” is clearly
defined as a subject of the licensing obligations of a distribution
licensee and not an area of operation.
25. Notably, under certain sub-delegated legislations issued by
the respective State Commissions, the area of supply is also referred
as the area of distribution. In the context that the terms “distribution”
and “supply” have been used interchangeably save as otherwise
C.A. Nos. 4652-59/2024 Page 32 of 59
provided, they refer to the salient act of sale of electricity to a
consumer. In context thereof, it appears that the Appellant has taken
refuge under the two terms of ‘distribution installation’ and ‘area of
operation’ under the Railways Act to suggest that it distributes
electricity and, hence, is a DDL under the Electricity Act.
26. Furthermore, the submission of the Appellant that the non-
obstante clause under Section 11 of the Railways shall override the
licensing requirements of the Electricity Act, is premature and
untenable. It is settled that Section 11 of the Railways Act cannot be
given a restrictive meaning, however it cannot be read so
expansively as to dispense with the mandatory licensing framework
under Section 12 and 14 of the Electricity Act. A non-obstante
clause operates only in the event of a direct and irreconcilable
inconsistency and cannot function as a blanket dispensation from
the applicability of a subsequent and special regulatory statutory
framework qua a specific subject matter. This Court in Central
Bank of India v. State of Kerala & Ors.
9
had clearly opined that the
mere introduction of a non-obstante clause in the legislation is not
sufficient to clothe a provision with an overriding effect, and what
must further be established is that the two provisions are so
inconsistent that they cannot stand together. The Appellant in the
present case has failed to demonstrate that there is a irreconcilable
conflict between the Railways Act and the Electricity Act. There is
9
[2009] 4 SCC 94
C.A. Nos. 4652-59/2024 Page 33 of 59
neither any provision under the Railways Act that prohibits
obtaining a license, nor any provision of the Electricity Act exempts
the railways from being a DDL in terms of section 14. The Appellant
can exercise their operational powers under section 11, while
simultaneously comply with the licensing framework under the
Electricity Act. It is a cardinal principle of statutory interpretation
that when two statutes are capable of being read harmoniously, the
judicial endeavour must be to read them together.
10
27. We further deem it appropriate to also clarify that the reliance
of the Appellant on Ganv Bhavancho Ekvott (supra) is
misconceived. The import and independence of section 11
recognised therein was limited to the exemption to the Railways
from procedural permissions including general environmental
clearances, and local body legislations. The exemption can in no
manner be construed as a blanket immunity from regulatory,
procedural and legislative requirements as noticed in the cited
decision itself. The judgment is distinguishable both on facts, and
on the nature of the conflicting statute, and offers no authority for
the proposition that the Appellant is exempted from the regulatory
framework under the Electricity Act. Additionally, the authority
vested in the Appellant to distribute electricity within its operational
domain cannot be said to be unfettered insofar as it has to meet the
10
Sri Venkataramana Devaru & Ors. v. State of Mysore &Ors. [1957 SCC
OnLine SC 138]
C.A. Nos. 4652-59/2024 Page 34 of 59
fundamental requirements of distribution of electricity, within the
meaning and scope of the Electricity Act. Section 11 on the facts and
circumstances of the present case, cannot be read as a provision of
unlimited sweep, and it is therefore incorrect to contend that Section
11 of the Railways Act operates as an absolute and unrestricted
shield guarding the appellant from its obligations.
28. We are also of the considered view that the omission of the
words “distribution” or “supply” of electricity in Sections 11(g) and
(h) is deliberate and intentional. The legislature while framing these
provisions certainly intended to empower the Appellant solely to
erect and operate a distribution infrastructure necessary for railway
operations. The language clearly confines the purpose of these
installations to the operational use of Railways and does not extend
any authority to the Appellant to undertake a commercial
distribution or supply of electricity, beyond the railway’s internal
domain.
29. We further agree with the observation of APTEL and the
submissions made by the Respondents that the reliance of the
Appellant on the decision of General Manager, Northern Railways
(supra) is misplaced. The decision in the said case expressly dealt
with the power of the Railways to construct transmission lines for
the purpose of its operations, and described the expansive scope of
the non-obstante clause under Section 11 of the Railways Act. The
said decision however, did not construe the scope of Section 11 as
C.A. Nos. 4652-59/2024 Page 35 of 59
being so expansive that it justifies an act that the Railways is not
inherently empowered to do. The erection of transmission lines or
distribution lines as argued by the Appellant, cannot bestow upon
the Appellant the authorisation to carry out supply of electricity that
is procured by it, to third party consumers.
30. At this juncture, we deem it appropriate to also observe that
the submission of the Appellant that it is a deemed distribution
licensee, lacks any substantial basis. The statutory regime under the
Electricity Act regulates the commercial supply of electricity to
consumer through a licensed distribution network.
31. The Appellant, operates a closed and self-contained
electricity network which is for the purposes of meeting the
operational requirements of the railway system, including traction,
signalling, stations. It is only when electricity is sold or provided to
consumers outside the operational domain of the railway, that the
activities undertaken by the Appellant could intersect with the
obligation of a distribution licensee.
32. Further, the purpose of a status of a distribution licensee,
whether obtained vide an application or is extended to the entity
through a deemed fiction, is to supply electricity against
consideration. The term ‘consideration’ for distribution licensees
with generators would mean tariff, and as consumers payable to
licensees would mean additional surcharge/Cross-Subsidy
Surcharge. In the present case, the Railways is procuring electricity
C.A. Nos. 4652-59/2024 Page 36 of 59
from the Respondent DISCOMs in various states for its own use and
for consumption to its constituents.
33. The judgment in K.C. Ninan v. Kerala State Electricity
Board & Ors.
11
has authoritatively re-iterated that supply of
electricity is a primary and defining function of a distribution
licensee. The regulatory regime under the Indian Electricity Act,
1910 also posed an obligation on every licensee to supply energy to
every person within the area of supply. Hence, the statutory
regime/regulatory regime under the Electricity Act has been
consistent. Additionally, electricity is a movable good
12
under the
Sale of Goods Act, 1930. The charges paid by the consumer to the
distribution licensee is essentially the price paid for goods supplied
and consumed. The consumption of electricity by a consumer is
always effected through equipment or appliances installed within
the premises.
34. The tenuous claim of the Appellant is merely based on a thin-
iced assertion that being an entity of the Central Government, the
deeming fiction of an Appropriate Government, as meant to be
under the third proviso to Section 14 of the Electricity Act would
ipso facto devolve upon them without much effort.
11
[2023] 14 SCC 431
12
Commissioner of Sales Tax vs Madhya Pradesh Electricity Board [1961] 1 SCC
200
C.A. Nos. 4652-59/2024 Page 37 of 59
35. More-so, the arguments made by the Appellant are more in
the nature of asserting this misplaced notion than being rooted in the
conviction that the activities carried out by it pass muster for a
distribution license in the first place. Hence, the claim of the
Appellant that it is a DDL is not borne from the activities or
functions performed by the railways, but is aimed at the recognition
of being a distribution licensee under the Act, insofar as it is entitled
to non-discriminatory open access from inter-state transmission
utilities and other distribution licensees, without the payment of
Cross-Subsidy Surcharge or additional surcharge.
36. In light thereof, it is pertinent to reflect on the submissions
made by the Appellant whereby it asserts that it is not claiming the
right to do any other activity outside the purpose of the Railways
operations or unconnected with the workings of the Railways,
including the right to supply electricity to third parties beyond the
network of Railways or enter into any business or trade of
distributing or using the electricity outside its area of operation. This
stated position, in fact, answers the controversy, and underscores
that the Appellant does not seek to assume the scope of functions
associated with a distribution licensee. In effect, the Appellant does
not seek to assume, nor does it accept, the role and obligations of a
distribution licensee under the Electricity Act, 2003 and instead
selectively relies on such status only to the extent it is beneficial.
C.A. Nos. 4652-59/2024 Page 38 of 59
37. This conduct further substantiates the apprehension of the
Respondents that the Appellant’s claim to be treated as a DDL is to
merely circumvent the obligation of payment of the Cross-Subsidy
Surcharge and to evade the corresponding statutory and regulatory
obligations qua a distribution licensee.
Issue No. (ii) Whether the Indian Railways, being an entity of the
Central Government, falls within the ambit of “Appropriate
Government” under section 14 of the Electricity Act, 2003?
38. The Appellant’s claim to be treated as a deemed distribution
licensee under the third proviso to Section 14 of the Electricity Act,
2003 hinges upon whether it is squarely covered by the definition of
‘Appropriate Government’ defined under section 2(5) of the Act,
2003, which reads as under:
“(5) Appropriate Government” means-
(a) the Central Government-
(i) in respect of a generating company wholly or
partly owned by it;
(ii) in relation to any inter-State generation,
transmission, trading or supply of electricity and
with respect to any mines, oil-fields, railways,
national highways, airports, telegraphs,
broadcasting stations and any works of defence,
dockyard, nuclear power installations;
(iii) in respect of the National Load Despatch
Centre and Regional Load Despatch Centre;
C.A. Nos. 4652-59/2024 Page 39 of 59
(iv) in relation to any works or electric installation
belong to it or under its control;
(b) in any other case, the State Government having
jurisdiction under this Act.”
39. The Appellant contends that it is entitled to the status of a
deemed distribution licensee by operation of law, on the ground that
it qualifies as an appropriate Government being an instrumentality
of the State under Article 12 of the Constitution. In contrast, the rival
contention of the Respondent argues that section 2(5) of the
Electricity Act restricts the scope of “Appropriate Government”, and
that an entity can fall within the statutory domain only if it satisfies
the conditions laid down under section 2(5)(a), particularly clause
(ii), having regard to the nature and functions of the entity in
question.
40. Before we advert to the functional test, a plain reading of
section 2(5)(a)(ii) makes it evident that the subject of the definition
is the Central Government, and the term “railways” appears only as
a relative reference, and a subject-matter that triggers the application
of the Central Government. Insofar as the provision does not extend
that the Railways itself is the Appropriate Government, it only
expands the scope of the term to include the Central Government in
matters relating to railways.
C.A. Nos. 4652-59/2024 Page 40 of 59
41. This distinction at the very outset is critical to the
identification of an entity claiming to be clothed with governmental
authority. In arguendo, if the term “railways” in section 2(5)(a)(ii)
were read as conferring the status of an “Appropriate Government”
to the Appellant, the deeming fiction shall extend to all other
authorities mentioned in the provision including mines, oil-fields,
airports, dockyards and nuclear installations. This clearly does not
reflect the legislative intent of this provision. The categories of
functionaries mentioned in section 2(5)(a)(ii) merely reflect a class
of activities, and not stand-alone entities that can be conferred the
status of an “appropriate Government” for the purposes of the
statute.
42. It is also a well-settled principle of law that the mere
classification of an instrumentality or agency as “State” under
Article 12 of the Constitution of India does not automatically render
it as an “Appropriate Government”. This position was
authoritatively settled by this Court in the Steel Authority of India
Ltd. & Ors. v. National Union Waterfront Workers & Ors.
13
This
Court distilling from its earlier decisions in Sukhdev Singh & Ors.
v. Bhagatram Sardar Singh Raghuvanshi & Anr.
14
and Ajay Hasia
& Ors. v. Khalid Mujib Sehravardi & Ors.
15
, laid down a functional
test holding that the determinative criterion is whether the industry
13
(2001) 7 SCC 1
14
(1975) 1 SCC 421
15
(1981) 1 SCC 722
C.A. Nos. 4652-59/2024 Page 41 of 59
is carried on under the authority of the Central Government, and not
merely whether the entity qualifies as “State” under Article 12 of the
Constitution. The relevant extract of the judgment reads as under:
“38.From the above discussion, it follows that the
fact of being an instrumentality of a Central/State
Government or being ‘State’ within the meaning of
Article 12 of the Constitution cannot be
determinative of the question as to whether an
industry carried on by a company/corporation or an
instrumentality of the Government is by or under the
authority of the Central Government for the
purpose of or within the meaning of the definition of
‘appropriate Government’ in the CLRA
Act….Further, the definition of establishment in the
CLRA Act takes in it fold purely private
undertakings which cannot be brought within the
meaning of Article 12 of the Constitution. In such a
case, how is ‘appropriate Government’ determined
for the purposes of the CLRA Act or the Industrial
Disputes Act? In our view, the test which is
determinative is: whether the industry carried on by
the establishment in question is under the authority
of the Central Government. Obviously, there cannot
be one test for one part of the definition of
‘establishment’ and another test for another part.
Thus, it is clear that the criterion is whether an
undertaking/instrumentality of the Government and
not whether the undertaking is an instrumentality or
agency of the Government for purposes of Article
12 of the Constitution, be it of the Central
Government or the State Government.”
C.A. Nos. 4652-59/2024 Page 42 of 59
43. Upon applying the aforesaid test, it is evident that the
Appellant operates as a functionary of the Central Government.
Although, the mention of ‘railways’ in Para 38 of the Court in SAIL
(supra) is cursory and illustrative in nature, the statutory scheme of
the Railways Act and the Statement of Objects and Reason
thereunder confirm that the entire railway system has become part
of the Government of India. The Railway Board constituted under
the Act, functions as an extended arm of the Central Government,
with the powers delegated to it by the Government itself. It is no
doubt that the Central Government has an authoritative control over
the Railways.
44. A fortiori, the Central Government exercises control over the
Appellant insofar as the electric installations comprising traction
sub-stations, the overheard catenary systems, high voltage
transmission lines, the 25 kV and 1.5 kV alternating current systems
etc., are owned by the Central Government. The construction and
maintenance work of these equipments are carried out from public
funds appropriated by the Parliament from the Consolidated Fund
of India.
45. It is thus evident that the nominal, pervasive, administrative
as well as fiscal control of the Appellant lies in the clutches of the
Central Government. The submission of the Respondents to draw a
distinction between the ‘Central Government’ and ‘railway
administration’ is therefore untenable, as such a distinction does not
C.A. Nos. 4652-59/2024 Page 43 of 59
dilute the overarching control exercised by the Central Government
and borders on technicality.
46. We agree with the observation made by APTEL that the
submission urged on behalf of the Respondent merits rejection.
However, we cannot assert enough that even if the Appellant is held
as falling within the ambit of Appropriate Government, under
section 2(5)(a), the benefit of being treated as a deemed distribution
licensee cannot be extended to it. The scheme of the Electricity Act
makes it clear that a distribution licensee is under the statutory
obligation to supply electricity to its consumers within its area of
supply.
47. Notably, the Appellant’s electrical infrastructure including
traction sub-stations, overhead catenary systems, and 25kV
alternating current systems, exists entirely for captive self-
consumption for traction purposes and not for supply to third party
consumers. The case of the Appellant cannot be held in equivalence
with the Military Engineering Services (MES) which is a recognized
deemed distribution licensee and equally operates under the
authority of the Central Government as much as the Appellant. The
distinction between the two entities is apparent such that MES
supplies electricity to consumers which include residents, personnel
and establishment within the defined cantonment and defense areas,
unlike the Appellant. As a matter of fact, it is the own admission on
behalf of the Appellant that it is not claiming the right to give supply
C.A. Nos. 4652-59/2024 Page 44 of 59
or provide electricity to third parties unconnected with the working
of the railways or outside the area of operation of the Railways or
enter into any business or trade of distributing electricity or using
electricity outside its area of operations.
48. Therefore, the deemed status attached to the MES is not by
virtue of it being a government entity, but it is a governmental entity
that actually performs the function of distribution within the
meaning and scope of the Electricity Act. It is apparent on the face
of record that the Appellant has no such analogous relationship with
any consumer, and its claim to the deemed distribution licensee
status fails at the very threshold.
49. At this juncture, we deem it appropriate to clarify that the
Letters dated 06.05.2014 and 03.04.2023 issued by the Ministry of
Power, are not authoritative in nature, and carry no binding legal
force. They are no more than executive communications that neither
amend nor override the statutory provisions under the Act, and
certainly cannot be relied upon to confer or negate jurisdiction. It is
rather unfortunate that the Appellant has pursued this lis for over 10
years based solely on the tenuous claim that, as a Central
Government entity, it automatically qualifies as the “Appropriate
Government” under the third proviso to section 14 of the Electricity
Act. This argument is more a reliance on a misplaced notion than a
demonstration that the Appellant’s activities satisfy the criteria for a
distribution licensee.
C.A. Nos. 4652-59/2024 Page 45 of 59
50. For the reasons mentioned hereinabove and for the limited
purpose of this analysis, the Appellant is regarded as falling within
the ambit of “Appropriate Government” under section 2(5)(a) of the
Act, but the observation carries no determinative consequence for
the relief sought by the Appellant. Nominal virtue, however firmly
established, cannot substitute for the substantive functions that the
statute demands.
Issue No. (iii) Whether the Indian Railways, even if held to be a
deemed distribution licensee under the Act, is exempt from the
obligation to pay Cross-Subsidy Surcharge or Additional Surcharge
for the grant of non-discriminatory open access as per section 42 of
the Act?
51. Section 42 of the Electricity Act mandates the distribution
licensees to develop and maintain an efficient, co-ordinated and
economical distribution system in the area of supply, and to supply
electricity to any consumer, who demands it. To foster competition
and consumer choice, the Electricity Act enables consumers to
procure electricity either from the distribution licensee in their area
of supply or from alternative sources through open access. Section
2(47) defines “open access” as follows:
“(47) “open access” means the non-discriminatory
provision for the use of transmission lines or
distribution system or associated facilities with such
lines or system by any licensee or consumer or a
person engaged in generation in accordance with
C.A. Nos. 4652-59/2024 Page 46 of 59
the regulations specified by the Appropriate
Commission”
52. Where any consumer avails electricity through open access,
two distinct surcharges arise under the Electricity Act. Section 42(2)
levies a Cross-Subsidy Surcharge to meet the requirements of the
current level of cross-subsidy within the area of supply, while
section 42(4) levies an Additional Surcharge to meet the fixed costs
of the distribution licensee arising out of its obligation to supply.
53. Distribution licensees are mandated, as a matter of social
policy, to supply electricity at concessional tariffs to certain
categories of consumers, such as agricultural users and low-income
households. These subsidised tariffs ensure equitable access to
electricity, which is essential to the very existence of citizens, as
held in Anuj Kumar Agarwal v. Registrar of Cooperative Societies
& Ors.
16
54. Cross-Subsidy Surcharge is levied on open-access consumers
to off-set the revenue shortfall experienced by distribution licensees
in providing these subsidised tariffs. Thereby, the financial burden
is equitably shared across different consumer categories instead of
burdening the existing consumer base. Additional Surcharge
operates on a distinct footing and is levied to mitigate the potential
financial losses incurred by distribution licensees due to stranded
16
2024 SCC OnLine Del 5087
C.A. Nos. 4652-59/2024 Page 47 of 59
costs. When high-volume, high-revenue consumers such as the
Indian Railways choose to procure electricity through open-access,
distribution licensees may be left with underutilised infrastructure
and power purchase commitments, leading to financial strain. The
National Tariff Policy, 2016 specifically provides that Additional
Surcharge becomes applicable only upon the conclusive
demonstration that a licensee’s existing power purchase obligations
in the capacity of a licensee, has generated precisely such stranded
costs for the distribution licensees in whose areas its traction
installations are located.
55. Thus, the Cross-Subsidy Surcharge and the Additional
Surcharge are critical for maintaining the financial health and
operational capacity of the distribution sector, enabling it to invest
in infrastructure upgrades, ensure reliable service, and continue to
meet its obligations to all consumer categories.
56. The rationale underlying Cross-Subsidy Surcharge and
Additional Surcharge has been authoritatively articulated in Sesa
Sterlite as follows:
“(3) Cross-Subsidy Surcharge (CSS)—Its rationale
27. The issue of open access surcharge is very
crucial and implementation of the provision of open
access depends on judicious determination of
surcharge by the State Commissions. There are two
aspects to the concept of surcharge — one, the
cross-subsidy surcharge i.e. the surcharge meant to
take care of the requirements of current levels of
C.A. Nos. 4652-59/2024 Page 48 of 59
cross-subsidy, and the other, the additional
surcharge to meet the fixed cost of the distribution
licensee arising out of his obligation to supply. The
presumption, normally is that generally the bulk
consumers would avail of open access, who also
pay at relatively higher rates. As such, their exit
would necessarily have adverse effect on the
finances of the existing licensee, primarily on two
counts — one, on its ability to cross-subsidise the
vulnerable sections of society and the other, in terms
of recovery of the fixed cost such licensee might
have incurred as part of his obligation to supply
electricity to that consumer on demand (stranded
costs). The mechanism of surcharge is meant to
compensate the licensee for both these aspects.
28. Through this provision of open access, the law
thus balances the right of the consumers to procure
power from a source of his choice and the legitimate
claims/interests of the existing licensees. Apart from
ensuring freedom to the consumers, the provision of
open access is expected to encourage competition
amongst the suppliers and also to put pressure on
the existing utilities to improve their performance in
terms of quality and price of supply so as to ensure
that the consumers do not go out of their fold to get
supply from some other source.
29. With this open access policy, the consumer is
given a choice to take electricity from any
distribution licensee. However, at the same time the
Act makes provision of surcharge for taking care of
the current level of cross-subsidy. Thus, the State
Electricity Regulatory Commissions are authorised
to frame open access in distribution in phases with
surcharge for:
C.A. Nos. 4652-59/2024 Page 49 of 59
4. (vi)(a) current level of cross-subsidy to be
gradually phased out along with cross-subsidies;
and
(b) obligation to supply.”
30. Therefore, in the aforesaid circumstances
though CSS is payable by the consumer to the
distribution licensee of the area in question when it
decides not to take supply from that company but to
avail it from another distribution licensee. In a
nutshell, CSS is a compensation to the distribution
licensee irrespective of the fact whether its line is
used or not, in view of the fact that, but for the open
access the consumer would pay tariff applicable for
supply which would include an element of cross-
subsidy surcharge on certain other categories of
consumers. What is important is that a consumer
situated in an area is bound to contribute to
subsidising a low end consumer if he falls in the
category of subsidising consumer. Once a cross-
subsidy surcharge is fixed for an area it is liable to
be paid and such payment will be used for meeting
the current levels of cross-subsidy within the area.
A fortiori, even a licensee which purchases
electricity for its own consumption either through a
“dedicated transmission line” or through “open
access” would be liable to pay cross-subsidy
surcharge under the Act. Thus, cross-subsidy
surcharge, broadly speaking, is the charge payable
by a consumer who opt to avail power supply
through open access from someone other than such
distribution licensee in whose area it is situated.
Such surcharge is meant to compensate such
distribution licensee from the loss of cross-subsidy
that such distribution licensee would suffer by
C.A. Nos. 4652-59/2024 Page 50 of 59
reason of the consumer taking supply from someone
other than such distribution licensee.”
57. The legal chain that flows from the foregoing is direct and
clear. As established in Issues (i) and (ii), the Appellant is a
consumer within the meaning and scope of section 2(15) of the
Electricity Act. It purchases electricity exclusively for its own use
and supplies it to no one but its own constituents. Thus, like any
other consumer, Cross-Subsidy Surcharge and Additional
Surcharge are applicable to the Appellant.
58. In arguendo, even if the Railways is treated as a deemed
distribution licensee (DDL), its procurement of electricity through
open access exclusively for its own consumption renders it a
consumer for that purpose. Sesa Sterlite adopted a functionality test
and held that an entity which has been accorded the status of a DDL,
but which utilises the entire quantum of electricity for its own
consumption and does not have any customers, could not be a
distribution licensee under the Electricity Act and would itself be a
consumer. Thus, a functionality test was adopted, and the operations
of a distribution licensee as a consumer were recognised.
Accordingly, such an entity, like the Railways in the present case,
would be liable to pay Cross-Subsidy Surcharge and Additional
Surcharge if it procures electricity through open access.
C.A. Nos. 4652-59/2024 Page 51 of 59
59. The Appellant cannot escape this conclusion by inverting the
argument and contending that as a deemed distribution licensee, it
is free from any payment obligations applicable to any consumer. In
this respect, the Appellant is claiming a privileged treatment as
compared to other consumers, which is impermissible in law.
Issue No. (iv) Whether a proposed legislation may be relied upon
as an aid to statutory interpretation for addressing gaps in the
existing framework, and to give effect to the parliamentary intent to
remedy defects thereunder?
60. The use of legislative history as an aid to statutory
construction is no longer res integra
17
. This Court, in a catena of
decisions
has held that in understanding the legislative intent and
scheme of a statute, recourse to legislative material is permissible.
In the present case, reliance is placed on a legislative proposal which
seeks to substantially alter the statutory scheme of the Electricity
Act. We are conscious that a legislative proposal does not have a
binding force on the interpretation of the existing statute, but a
careful perusal of the proposed enactment may aid in resolving
apparent incongruencies and identifying perceived gaps in the
existing framework.
61. In the present case, the legislative history of the Electricity
Act reflects that previous proposals
in 2014 and 2018 had sought to
17
Kalpana Mehta vs Union of India [2018] 7 SCC 1
C.A. Nos. 4652-59/2024 Page 52 of 59
confer the statutory status of a licensee in favour of the Appellant,
seeking to save it from the binding statutory obligations of paying
Cross-Subsidy Surcharge and additional surcharge. Insofar as,
Section 9 of the Electricity (Amendment) Bill, 2014 sought to
clarify that the Railways shall be a DDL by adding the following
proviso after the present third proviso to Section 14:
“Provided also that the Railways as defined under
the Indian Railways Act and the Metro Rail
Corporation established under the Metro Railways
(Operation and Maintenance) Act, 2002 be deemed
to be a licensee under this Act, and shall not be
required to obtain a licence under this Act”
Be that as it may, this provision of the 2014 Amendment Bill was
rejected and not passed by the Parliament, showing the legislative
intent that the Railways does not constitute a licensee in terms of
Section 14 of the Electricity Act.
62. The Respondents' DISCOMS brought our attention to the
Fourth Report of the Standing Committee on Energy dated
07.05.2015, which recorded the unequivocal admission by the
Appellant that it is not a DDL under the scheme of the Electricity
Act. APTEL had also placed reliance on the 31
st
Report of the
Parliamentary Standing Committee, which recorded that the
Appellant had sought exemption from the obligations of distribution
licensees under Section 12, 42, and 47 of the Electricity Act. The
request for exemption from the applicability of the Electricity Act
C.A. Nos. 4652-59/2024 Page 53 of 59
was neither acceded to by the Parliamentary Standing Committee
nor accepted by the Parliament.
63. The latest Draft Electricity (Amendment) Bill, 2025,
particularly seeks to amend Section 61(g) of the existing statutory
regime under the Act, to progressively reduce and ultimately
eliminate the Cross-Subsidy Surcharge and Additional Surcharge
for the Appellant.. The proposed provision under Section 12 reads
as under:
“(g) that the tariff reflects the cost of supply of
electricity and also, progressively reduces cross-
subsidies in the manner specified by the
Appropriate Commission;
Provided that cross-subsidy with respect to
Railways, Metro Railways and Manufacturing
Enterprises shall be fully eliminated within five
years from the date of commencement of the
Electricity (Amendment) Act, 2025.”
64. The Explanatory Note on the proposed Amendment Bill
makes a specific mention that the Indian Railways and
metro/monorail systems are currently burdened by cross-subsidies
and surcharges, and proposes to exempt the Appellant from cross-
subsidy within five years. A bare reading of the Note confirms that
under the extant regime, the Appellant is treated like any other
consumer. It reads as under:
“2.2. Reducing Logistics and Mass Transit
Cost: Electricity tariffs for Indian Railways and
Metro/Mono Rail systems are currently burdened by
C.A. Nos. 4652-59/2024 Page 54 of 59
cross-subsidies and surcharges, which increase
costs of transporting goods and people. These
higher costs ultimately raise the price of goods and
services across the economy. To alleviate this
burden, it is proposed to exempt Manufacturing
Enterprises, Railways, and Metro Railways from
cross-subsidy within five years. This measure will
help lower transport and logistics costs, improve
efficiency, and enhance India’s competitiveness in
global markets.”
Further, the Comparative Statement to the Draft Electricity
(Amendment) Bill, 2025, in contrast with the current Act as it
stands, states the following:
“13. Cross Subsidy and Surcharges on
manufacturing and clean/public transport: State
Commissions impose substantial cross-subsidies
and surcharges on industrial consumers. Industrial
electricity tariffs in India remain considerably
higher than those in developed countries such as the
United States and emerging economies like China,
Vietnam, and Indonesia. This practice significantly
undermines the global competitiveness of Indian
manufacturers by inflating electricity
costs. Elevated electricity costs not only hinder
industrial growth but also stunt employment
generation, and deter foreign
investments. Simultaneously, there is a need to
create significant number of job opportunities in the
manufacturing sector. Micro, Small, and Medium
Enterprises (MSMEs) have a high job creation
potential in the manufacturing sector. Reducing
industrial electricity tariffs can significantly
accelerate the growth of the manufacturing sector
C.A. Nos. 4652-59/2024 Page 55 of 59
MSMEs and enable absorption of the large
agricultural workforce. Access to affordable
power would lower production costs, enhance
competitiveness of Indian manufactured goods, and
facilitate their scale-up from micro to small or
medium enterprises. This, in turn, would strengthen
their contribution to employment generation and
gross value added (GVA), supporting the national
goal of achieving “Viksit Bharat @
2047”. Addressing the high industrial tariff
handicap is crucial to enhancing India’s global
industrial competitiveness, and driving economic
growth. The logistics cost in India constitutes
nearly 14 percent of GDP as opposed to about 8
percent in most major economies. There is a need
to reduce this cost in line with the National Logistics
Policy and make Indian industry cost
competitive. Despite being energy efficient and
running on electricity, Indian Railways and
Metro/Mono rail systems across the country are
subjected to elevated electricity tariffs owing to the
imposition of cross-subsidies and surcharges. This
does not align with the goal of electrifying the
transport sector as part of India’s energy transition
and increasing the rate of energy efficiency
improvement. The higher tariffs result in higher
transportation and logistics costs besides
discouraging goods and passenger modal
shifts. Public transport costs, particularly in urban
and semi-urban areas, impact the wage rates and
standards of living of working classes. The
proposed amendment seeks to address these
challenges by exempting Indian Railways, Metro
rail and manufacturing industries, from payment of
cross-subsidy and surcharges, not later than five
years. This reform aligns with the vision of “Viksit
C.A. Nos. 4652-59/2024 Page 56 of 59
Bharat @ 2047”. It will help in fostering industrial
expansion, attracting investments, and generating
employment opportunities. It reduces the transport
costs for urban commuters and promotes
sustainable economic growth.”
65. On a prima-facie view itself, the nature of the proposed
amendment under the Draft Electricity (Amendment) Bill, 2025 is
remedial in nature. The language used is clear and simple, to address
the existing burden of Cross-Subsidy Surcharge payable by the
Appellant by exempting them from payment of cross-subsidy and
surcharges, within the next five years. By this very objective, an
inference can be made that there was a gap or deficiency that needed
to be filled by legislative action and the shift in the statutory regime
would not have been warranted if the existing statute already
provided for such exemption.
66. As already dealt with hereinabove, it is clear that the
Appellant is a consumer and that it procures electricity for its own
consumption and use. In terms of the Act, open access shall be
granted by the distribution licensee subject to the payment of cross-
subsidy and surcharges as decided by the appropriate Commission.
67. This Court, in Vodafone International Holdings BV v. Union
of India & Anr.
18
, had held that a legislative proposal introducing a
specific provision or exemption is indicative that such provision,
18
(2012) 6 SCC 757
C.A. Nos. 4652-59/2024 Page 57 of 59
exemption, or privilege was not covered by the existing framework.
In the present case as well, the very fact that such legislative actions
to exempt the Appellant from payment of Cross-Subsidy Surcharges
have been proposed to be taken, indicate a coherent, consistent, and
current legislative intent about the absence of such exemption under
the prevailing statute. This absence further implies that even by
adopting a purposive construction to the prevailing statute, such an
exemption cannot be read into the statute.
68. It was urged by the Appellant that since the proposed
amendment grants an exemption from payment of Cross-Subsidy
Surcharge and AS, the same should be read into a liberal and
purposive interpretation in its favour. Otherwise, an interpretation to
impose Cross-Subsidy Surcharge and Additional Surcharge under
the current regime would render the proposed amendment otiose.
We are unable to accept this approach.
69. It is a settled canon of statutory interpretation that a legislative
casus omissus cannot be supplied by a judicial interpretative
process. Be that as it may, the proposed legislative framework in the
present case explicates that the legislative intent of the Parliament
under the Electricity Act was not to exempt the Appellant from the
obligations under the Electricity Act. More so, it puts the
controversy to rest as the Appellant, procuring electricity for its own
use and consumption, is an industrial consumer and for availing
C.A. Nos. 4652-59/2024 Page 58 of 59
open access, it is liable to pay Cross-Subsidy Surcharge and
additional surcharge, like any other consumer.
70. Although we are conscious that the proposed legislation is
only a draft amendment bill which has not been enacted by the
Parliament, and lacks any force of law as of today, reliance
thereupon has been crucial to determine the legislative intent of the
Government. Further, the Appellant stands bound by the principle of
estoppel. Being an entity of the Central Government, the Appellant
cannot be permitted to approbate and reprobate or blow hot and cold,
by advancing contentions contrary to the position adopted under the
proposed statutory scheme.
CONCLUSION
71. It is clear, for the reasons elaborated hereinabove, that the
Appellant does not pass muster as a deemed distribution licensee
under the Act, and it can in no circumstances escape the liability
from payment of cross-subsidy surcharge and additional surcharge
as a consumer of electricity through open access.
72. The Respondents are accordingly directed to compute and
issue a detailed calculation of the Cross-Subsidy Surcharge and
Additional Surcharge amounts outstanding qua the Appellant,
disaggregated by the area of supply and the period of availing such
open access. The Appellant shall be afforded a reasonable
opportunity to respond to the said calculations, and be granted time
C.A. Nos. 4652-59/2024 Page 59 of 59
to furnish and respond to such outstanding amount at the discretion
of the respective distribution licensees/companies, subject to the
judicial scrutiny of the Appropriate Commission. Ordered
accordingly.
73. Consequently, all the Appeals are dismissed and the common
judgment and order dated 12.02.2024 passed by the Appellate
Tribunal for Electricity at New Delhi (“APTEL”) in Appeal Nos.
276/2015, 320/2018, 114/2020, 73/2021, 213/2021, 170/2019,
343/2019 and 133/2020 is upheld. Pending application(s), if any,
shall also stand disposed of.
74. No order as to costs.
...…………………………………J.
[DIPANKAR DATTA]
...…………………………………J.
[SATISH CHANDRA SHARMA]
New Delhi
May 08, 2026.
Legal Notes
Add a Note....