As per case facts, the appellant was awarded a contract for capital dredging, leading to an arbitral award in their favor for a substantial sum. The respondent challenged this award ...
2024 INSC 827 Page 1 of 11
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
Civil Appeal No 12097 of 2024
(Arising out of SLP(C) No 25369 of 2024)
International Seaport Dredging Pvt Ltd .... Appellant
Versus
Kamarajar Port Limited ....Respondent
J U D G M E N T
Dr Dhananjaya Y Chandrachud, J
1. Leave granted.
2. The appeal arises from an interim order dated 9 September 2024 of a Single
Judge of the High Court of Judicature at Madras in A No 4236 of 2024 in Arb OP
(Com Div) No 335 of 2024.
3. The respondent issued a Letter of Award for executing Capital Dredging Phase- III
at Kamarajar Port to the appellant for an approximate sum of Rs 274 crores. On
12 August 2015, the parties entered into a contract for the following work to be
conducted by the appellant:
a. Capital dredging of Container Berth and Multi Cargo Berths and their
approaches;
Page 2 of 11
b. Capital dredging of Coal Berth 3 & Coal Berth 4 and their approaches;
c. Removal of onshore boulders and transportation to the designated area;
d. Removal of offshore boulders and transportation to the designated area;
e. Removal of offshore identified debris/wrecks; and
f. Environmental monitoring.
4. These tasks were to be completed on or before 11 April 2017. Thereafter,
disputes arose between the parties . The appellant invoked the arbitration
agreement. The arbitral proceedings commenced and the three-member arbitral
tribunal made an award on 7 March 2024 directing the respondent to:
a. Pay the appellant a sum of Rs 21,07,66,621 towards the claims that were
allowed in its favour;
b. Pay the appellant interest on the amount awarded at the rate of nine per cent
per annum from 15 November 2017 until the date of the award if the payment
was made within three months, and, if not, at the rate of twelve per cent per
annum from the date of the award till the date of payment ; and
c. Pay the appellant Rs 3,20,86,405 by way of costs.
Page 3 of 11
5. Both parties filed applications under Section 33 of the Arbitration and Conciliation
Act 1996
1 for correction of the award and for additional arbitral awards. The
arbitral tribunal d ismissed the application filed by the respondent. It allowed the
application filed by the appellant only to the extent of increasing the costs awarded
to it by Rs 12,00,000 to reflect the fees paid to the arbitral tribunal subsequent to
the parties filing their memo of costs.
6. The respondent challenged the arbitral award under Section 34 of the Arbitration
Act and moved an application for stay of execution. The High Court, by its
impugned judgment and order dated 9 September 2024, granted a stay on the
execution of the award conditional on the respondent furnishing a bank guarantee
in the sum of Rs 21,07,66,621 within a period of eight weeks.
7. The judgment of the High Court has been assailed by the original claimant of the
arbitral proceeding (i.e., the appellant in this case) whose contention is that since
the award operates as a money decree under Section 36 of the Arbitration Act, the
High Court was not justified in directing merely the furnishing of a bank guarantee
in relation to the principal amount. The appellant contends that the respondent
ought to have instead been directed to deposit the amount awarded to i t as a
condition for the grant of a stay on the execution of the award.
8. Mr Shyam Divan, senior counsel appearing on behalf of the appellant, has urged
that: (i) A body of precedent has emerged from this Court in terms of which the
sanctity of arbitration must be preserved by requiring the deposit of the amount
1 “
Arbitration Act”
Page 4 of 11
awarded as a condition for the stay on the enforcement of the award; (ii) The
amended provisions of the Arbitration Act require that while considering an
application for stay of an award for the payment of money, due regard has to be
had to the provisions of the Code of Civil Procedure 1908
2; and (iii) The award of
Rs 21,07,66,621 covered ten claims of which three were awarded in full and seven
in part. The High Court while ordering a stay, has essentially furnished only two
reasons. The first reason pertains to the question of cess, while the only other
reason is that the respondent is not “a fly by operator”.
9. Mr C A Sundaram, senior counsel appearing on behalf of the respondent, submits
that: (i) The amended provisions of the statute incorporate provisions of the CPC
in regard to ordering a stay of an award which contains provisions for the payment
of money; (ii) Under Order XLI Rule 5 of the CPC, the requirement is for furnishing
of security and the deposit of money should not, therefore, be regarded as a
default option; (iii) The High Court had due regard to the fact that the respondent is
a statutory body and correctly held that security should be furnished in the form of
a bank guarantee; (iv) A s such the impugned judgment should not be interfered
with under Article 136 of the Constitution; and (v) The body of precedents which
Mr Divan relied on pertains to appeals under Section 37 of the Arbitration Act .
10. Section 36(2) of the Arbitration Act indicates that where an application to set aside
an arbitral award has been filed under Section 34, the filing of such an application
shall not, by itself, render that award unenforceable, unless the Court grants a stay
2 “
CPC”
Page 5 of 11
on the enforcement of the arbitral award in terms of sub- section (3). The provision
indicates that a separate application must be made for this purpose. Sub- section
(3) of Section 36 stipulates that where such an application has been filed, the
Court may, subject to such conditions as it may deem fit, grant stay of the
operation of the award for reasons to be recorded in writing. Following the
amendments brought about by the Arbitration and Conciliation (Amendment) Act
2015, the first proviso to sub- section (3) stipulates that the Court shall, while
considering an application for grant of stay in the case of an arbitral award for
payment of money, have due regard to the provisions related to the grant of stay
of a money decree under the CPC. The second proviso provides for a situation in
which the Court may grant unconditional stay. Section 36(3) and its provisos are
reproduced below:
“36. Enforcement –
…
(3) Upon filing of an application under sub- section (2)
for stay of the operation of the arbitral award, the Court
may, subject to such conditions as it may deem fit,
grant stay of the operation of such award for reasons
to be recorded in writing:
Provided that the Court shall, while considering
the application for grant of stay in the case of an
arbitral award for payment of money, have due
regard to the provisions for grant of stay of a
money decree under the provisions of the Code of
Civil Procedure, 1908 (5 of 1908).
Provided further that where the Court is satisfied that a
Prima facie case is made out that, –
Page 6 of 11
(a) the arbitration agreement or contract which is
the basis of the award; or
(b) the making of the award,
was induced or effected by fraud or corruption, it shall
stay the award unconditionally pending disposal of the
challenge under section 34 to the award.
Explanation.—For the removal of doubts, it is hereby
clarified that the above proviso shall apply to all court
cases arising out of or in relation to arbitral
proceedings, irrespective of whether the arbitral or
court proceedings were commenced prior to or after
the commencement of the Arbitration and Conciliation
(Amendment) Act, 2015 (3 of 2016).”
(emphasis supplied)
11. In the present case, there is an arbitral award to the tune of approximately Rs 21
crores in favour of the appellant. The High Court, while issuing a direction for
furnishing of a bank guarantee, dealt with only one of the claims which was
awarded by the arbitral tribunal, namely, that which pertained to the refund of the
cess under the Building and Other Construction Workers’ Welfare Cess Act 1996.
3
In this regard, the High Court observed that the Deputy Chief Labour
Commissioner, by its order dated 6 November 2019, held that the Cess Act was
not applicable to the appellant which was therefore not required to pay cess under
that statute. It noted that the arbitral tribunal had, however, rendered an award in
which it directed the respondent to pay the appellant this amount, which had
already been paid by the respondent to the appellant. It held that while the
substance of the claims of the parties could only be determined in the proceedings
under Section 34 of the Arbitration Act, it was prima facie satisfied that the arbitral
3
“Cess Act”
Page 7 of 11
tribunal had erred in not considering the claim of the respondent. Apart from
discussing this claim, which was in the amount of approximately Rs 3 crores, the
High Court did not address the other claims of the appellant which were allowed
by the arbitral tribunal. The amount awarded in relation to the remaining claims is
approximately Rs 18 crore.
12. The High Court granted a stay on the operation of the award subject to the
respondent furnishing a bank guarantee for the principal amount awarded to the
appellant, i.e. Rs 21,07,66,621. It held that it was not inclined to issue orders in
relation to the interest and the costs awarded to the appellant because “the
petitioner is not a fly-by operator and is a statutory undertaking. ” The law qua
arbitration proceedings, in our view, cannot be any different merely because of the
status of the respondent as a statutory undertaking.
13. In this regard, it is necessary to advert to a decision of a two- Judge Bench of this
Court in Pam Developments Private Limited v State of West Bengal
4 where it
was observed:
“20. In our view, in the present context, the phrase
used is “having regard to” the provisions of CPC and not
“in accordance with” the provisions of CPC. In the latter
case, it would have been mandatory, but in the form as
mentioned in Rule 36(3) of the Arbitration Act, it would
only be directory or as a guiding factor. Mere reference
to CPC in the said Section 36 cannot be construed in
such a manner that it takes away the power conferred in
the main statute (i.e. the Arbitration Act) itself. It is to be
taken as a general guideline, which will not make the
main provision of the Arbitration Act inapplicable. The
4
(2019) 8 SCC 112
Page 8 of 11
provisions of CPC are to be followed as a guidance,
whereas the provisions of the Arbitration Act are
essentially to be first applied. Since, the Arbitration Act
is a self-contained Act, the provisions of CPC will apply
only insofar as the same are not inconsistent with the
spirit and provisions of the Arbitration Act.”
14. The Court also observed:
“26. Arbitration proceedings are essentially alternate
dispute redressal system meant for early/quick
resolution of disputes and in case a money decree —
award as passed by the arbitrator against the
Government is allowed to be automatically stayed, the
very purpose of quick resolution of dispute through
arbitration would be defeated as the decree- holder
would be fully deprived of the fruits of the award on
mere filing of objection under Section 34 of the
Arbitration Act. The Arbitration Act is a special Act which
provides for quick resolution of disputes between the
parties and Section 18 of the Act makes it clear that
the parties shall be treated with equality. Once the
Act mandates so, there cannot be any special
treatment given to the Government as a party. As
such, under the scheme of the Arbitration Act, no
distinction is made nor any differential treatment is
to be given to the Government, while considering an
application for grant of stay of a money decree in
proceedings under Section 34 of the Arbitration Act.
As we have already mentioned above, the reference to
CPC in Section 36 of the Arbitration Act is only to guide
the court as to what conditions can be imposed, and the
same have to be consistent with the provisions of the
Arbitration Act.
…
28. Section 36 of the Arbitration Act also does not
provide for any special treatment to the Government
while dealing with grant of stay in an application under
proceedings of Section 34 of the Arbitration Act.
Keeping the aforesaid in consideration and also the
provisions of Section 18 providing for equal treatment of
parties, it would, in our view, make it clear that there is
no exceptional treatment to be given to the
Government while considering the application for
Page 9 of 11
stay under Section 36 filed by the Government in
proceedings under Section 34 of the Arbitration
Act.”
(emphasis supplied)
15. Bearing in mind the above principles, we are of the view that the High Court was in
error in not even prima facie considering the fact that apart from the issue of cess,
there was an arbitral award in favour of the appellant in regard to other claims as
well. Further, the High Court ought not to have based its decision on the condition
for the grant of stay on the status of the respondent as a statutory authority. The
Arbitration Act is a self-contained code – it does not distinguish between
governmental and private entities. Hence, the decision of the Court cannot be
influenced by the position of the party before it and whether it is a fly -by-night
operator. Moreover, an assessment as to whether a party is reliable or trustworthy
is subjective. Many private entities, too, may rely on the size of their undertaking,
its success, public image, or other factors to argue that they are not fly-by-night
operators. In the absence of any provision of law in this regard, it would be
inappropriate for courts to apply this standard while adjudicating the conditions
upon which a stay of an award may be granted. Similarly, the form of security
required to be furnished should not depend on whether a party is a statutory or
other governmental body or a private entity. Governmental entities must be treated
in a similar fashion to private parties insofar as proceedings under the Arbitration
Act are concerned, except where otherwise indicated by law. This is because the
parties have entered into commercial transactions with full awareness of the
implications of compliance and non- compliance with the concerned contracts and
Page 10 of 11
the consequences which will visit them in law. Hence, the argument that the High
Court was correct in directing the respondent to furnish bank guarantees in
relation to the amount awarded because it is a statutory body is rejected.
16. In Toyo Engineering Corpn. v. Indian Oil Corpn. Ltd.,
5
this Court reiterated the
same principle in the following terms:
“3. This Court repeatedly having held that Order XLI
Rule 5 principles are to be followed in these cases, we
find that largely because public corporations are
involved, discretion continues to be exercised not on
principles under Order XLI Rule 5 but only because
large amounts exist and that Government Corporations
have to pay these amounts under Arbitral Awards.
Both these considerations are irrelevant, as has been
pointed out by us earlier.”
17. Under Order XLI Rule 5 of the CPC, the Court has the power to direct full or part
deposit and/or the furnishing of security in respect of the decretal amount. Bearing
in mind the principles which must guide the Court, we are of the view that the
order of the High Court requires modification. In modification of the direction of the
High Court in the impugned judgment dated 9 September 2024, we direct that:
(i) The respondent shall deposit an amount quantified at 75% of the decretal
amount, inclusive of interest, on or before 30 November 2024 before the
High Court; and
(ii) Conditional on the deposit of the aforesaid amount within the period
stipulated above, there shall be a stay on the enforcement of the arbitral
award.
5
2021 SCC OnLine SC 3455
Page 11 of 11
18. The impugned judgment of the High Court shall stand modified in the above terms.
The appeal is allowed accordingly.
19. Pending applications, if any, stand disposed of.
…..…..…....…........……………….…........CJI.
[Dr Dhananjaya Y Chandrachud]
……..…..…....…........……………….…........J.
[J B Pardiwala]
……..…..…....…........……………….…........J.
[Manoj Misra]
New Delhi;
October 24, 2024
-S-
Legal Notes
Add a Note....