As per case facts, petitioners, Mechanical Engineers in GSI, sought higher pay scale benefits (NFJAG and NFU) based on pay commission recommendations. Their requests were initially denied, with respondents arguing ...
W.Ps.(C) 16769/2004 & 1541/2012 Page 1 of 24
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 17.12.2025
Pronounced on: 28.01.2026
+ W.P.(C) 16769/2004 & CM APPL. 5649/2011
UOI & ORS. .....Petitioners
Through: Mr. Vivek Goyal, SPC with
Mr.Gokul Sharma and
Mr.Aryan Aggarwal, Advs. for
UOI
versus
KANHAIYA SINGH & ANR. .....Respondents
Through: Mr. G. Natarajan and Mr.
Akshay, Advs. with
respondents in person.
+ W.P.(C) 1541/2012
KANHAIYA SINGH .....Petitioner
Through: Mr. G. Natarajan and Mr.
Akshay, Advs. with petitioner
in person.
versus
THE SECRETARY, MINISTRY OF MINES & ORS
.....Respondents
Through: Ms. Nidhi Raman, CGSC with
Mr. Akash Mishra and Mr.
Arnav Mittal, Advs. for UOI
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
HON'BLE MS. JUSTICE MADHU JAIN
J U D G M E N T
1. W.P.(C) 16769/2004 has been filed, challenging the Order dated
02.09.2003 passed by the learned Central Administrative Tribunal,
NAVIN CHAWLA, J.
W.Ps.(C) 16769/2004 & 1541/2012 Page 2 of 24
Principal Bench, New Delhi (hereinafter referred to as, the ‘Tribunal’)
in O.A. 2892/2002, titled Kanhaiya Singh & Anr. v. Union of India
& Ors., whereby learned Tribunal disposed of the said O.A.,
observing as under:
“7. It is clear from the observations that the
Engineering Cadre in GSI has also been
treated by the FCPC as one of the major
departments in which the Engineering
workforce is engaged and the recommendation
in para 50.45 clearly states that the
recommendation to grant functional JAG for
Executive Engineers is not confined to only
organised Group A Engineering Services but it
is made ot be given to all Engineering cadres
in the Government. In this background of the
matter, we have absolutely no hesitation in
holding that respondents have totally misread
the recommendation of FCPC which has
resulted in their conclusion to reject the claim
of the applicants. During the course of
arguments, counsel for the applicants has also
brought to our notice that Engineers similarly
placed with All India Radio and Doordarshan
under the Ministry of Information and
Broadcasting, who are also classified in the
category of GSC Group A, have been granted
non-functional Junior Administrative Grade.
Counsel for the respondents, when queried as
to why the Engineers in GSI be discriminated,
has no answer. Thus we find that the impugned
order has been passed on the basis of an
artificial and arbitrary classification, which
has no basis.
8. We accordingly quash the order and direct
the respondents to consider the case of the
applicants for the conferment of JAG non-
functional as recommended by FCPC at par
with their counterparts in the cadre of
Engineers in All India Radio and Doordarshan
who are similarly placed. This exercise should
be completed within a period of three months
W.Ps.(C) 16769/2004 & 1541/2012 Page 3 of 24
from the date of receipt of a copy of this
order.”
2. W.P.(C) 1541/2012 has been filed, challenging the Order dated
23.12.2011 passed by the learned Tribunal in O.A. 3919/2010, titled
Shri Kanhaiya Singh v. Union of India, whereby the learned Tribunal
dismissed the said O.A., observing as under:
“6. The respondents have clearly mentioned
that the Mechanical Engineering Service in the
Geological Survey of India is not an
‘Organised’ Group ‘A’ Services. The applicant
belongs to the said Mechanical Engineering
Service of GSI and cannot claim to have been
the member of the “Organised” Group ‘A’
Services. As per the extant guidelines and
decision of the Government of India, the NFU
is admissible only for the officers of
“Organised” Group ‘A’ Services. The
applicant has not given any proof to show that
his service belongs to one of the “Organised”
Group ‘A’ Services of Government of India. On
the other hand, the respondents have
demonstrated that the applicant belongs to the
Mechanical Engineering Service of GSI, which
is, as per the extant Recruitment Rules is not
“Organised” Group ‘A’ Service. Further, the
respondents have indicated in their counter
affidavit that the Recruitment Rules to declare
the Mechanical Engineering Service of GSI as
one of the “Organised” Group ‘A’ Services is
under consideration of the Government. As
and when the Government accepts the
proposal and declares the said service to be
“Organised”, the NFU would be admissible to
the Mechanical Engineers of the GSI and that
too only prospectively. No decision has been
taken by the Competent Authority on the said
proposal. Now, that the applicant has retired
from service, he would not be entitled to get
the benefits of the Government Office
Memorandum dated 24.04.2009 to grant him a
Non-Functional Upgradation under Pay Band -
W.Ps.(C) 16769/2004 & 1541/2012 Page 4 of 24
4. As such, no consequential benefits would
also accrue to the applicant.”
3. The issue in W.P.(C) 16769/2004 pertains to the grant of the
higher pay scale of Rs. 1200-16500 in the Non-Functional Junior
Administrative Grade (‘NFJAG’), while the issue in W.P.(C)
1541/2012 pertains to the grant of Non-Functional Upgradation
(‘NFU’). As the petitions involve common questions of law for
consideration, it is deemed appropriate to adjudicate upon them
together by way of this common Judgment. For the sake of
convenience, reference will be made to the applicants in the two O.As.
as the ‘petitioners’, and to the respondents in the two O.As. as the
‘respondents’ .
4. The brief facts giving rise to the present petitions are that the
petitioners were appointed in March 1981 as Mechanical Engineer
(Junior) in the Geological Survey of India (‘GSI’), under the
administrative control of the Ministry of Mines, through the
Combined Engineering Services Examination conducted by the Union
Public Service Commission (‘UPSC’). They joined in the then Pay
Scale of Rs. 700-1300 (now Pay Band-3 with Grade Pay of Rs. 5400)
and were subsequently promoted to the post of Mechanical Engineers
(Senior) in Pay Band-3 with Grade Pay of Rs. 6,600.
BRIEF FACTS:
5. The 5
th
Central Pay Commission (‘CPC’), while considering the
case of revision of the pay scales of the Engineering Services, recommended that the Non-Functional Selection Grade of Rs. 4500-
W.Ps.(C) 16769/2004 & 1541/2012 Page 5 of 24
5700 should be converted into a single Functional Scale of
Superintending Engineers, and the Scale of Rs. 3700-5000 should
instead be made the NFJAG for Executive Engineers. The promotion
to the said scale of Rs. 4500- 5700 was on the completion of 13 years
of service in Group ‘A’. It was also clarified that although these
recommendations were made in the context of the Central Public
Works Department (‘CPWD’), its dispensation would be available to
all Engineering cadres in the Government. These recommendations
were implemented and extended to all Organized Group ‘A’
Engineering Services vide O.Ms. dated 06.06.2000 and 20.12.2000,
issued by the Department of Personnel and Training (DoP&T).
6. Relying on these recommendations of the 5
th
CPC, the
petitioners sought grant of NFJAG and made several representations
to the Ministry of Mines. However, their representations did not
succeed. Aggrieved thereby, they filed O.A. No. 141/1999 before the
learned Central Administrative Tribunal, Jaipur Bench, praying for
grant of NFJAG scale of Rs.12000-16500. The said O.A. was
disposed of with the direction to the respondents to consider the
petitioners’ representations.
7. The petitioners, thereafter, preferred representations dated
10.09.2001 and 12.09.2001 seeking grant of NFJAG. However, the
said representations were again rejected by the respondents vide a
Speaking Order dated 02.05.2002, on the ground that the
recommendations of the 5
th
CPC were applicable only to the
Organized Group ‘A’ Engineering Services, and the petitioners
belonged to the General Central Service Group ‘A’.
W.Ps.(C) 16769/2004 & 1541/2012 Page 6 of 24
8. Aggrieved thereby, the petitioners filed O.A. 2892/2002 before
the learned Tribunal, seeking grant of NFJAG scale of Rs. 12000-
16500.
9. It is the case of the petitioners that though the recommendations
of the 5
th
CPC have been made in the context of the CPWD Engineers,
its benefits were dispensed to all Engineering Cadres in the
Government and were not confined only to Organized Group ‘A’
Engineering Services. Further the petitioners, like their counterparts in
CPWD, were recruited through the Combined Engineering Services
Examination conducted by the UPSC and therefore, they were equally
eligible for the grant of NFJAG, as per the recommendations of the 5
th
CPC.
10. The learned Tribunal, vide its Impugned Order dated
02.09.2003, disposed of the said O.A. with the above -quoted
observations and directed the respondents to consider the petitioners’
case for conferment of NFJAG at par with their counterparts.
11. It is the case of the respondents that, in compliance with the
said order dated 02.09.2003, the case of the petitioners was considered
in consultation with the Department of Expenditure, DoP&T and
Ministry of Law & Justice, however, it was found that it was not
possible to confer NFJAG upon the petitioners. Accordingly, vide
order dated 23.12.2003, the representations of the petitioners were
again rejected. The respondents found the petitioners ineligible for the
conferment of NFJAG on the grounds as under:
“(i) The recommendation of the Fifth Central
Pay Commission regarding extension of the
W.Ps.(C) 16769/2004 & 1541/2012 Page 7 of 24
non-functional JAG is applicable only to
Organized Group 'A' Engineering Service as
prescribed in Department of Personnel &
Training's Office Memorandum N0.22/1/2000-
CRD dated 6th June, 2000.
(ii) The Engineers of the AIR and Doordarshan
belong to an organized Group 'A' Engineering
Service. Viz Indian Broadcasting Engineering
Service (as per the list of 49 organized
services indicated in para 8.53 read with
Annexure 8.1. of Fourth Central Pay
Commission's report) whereas the applicants
do not belong to any such organized service.
(iii) The Geological Survey of India is inter
alia, being catered by the major discipline of
Geology (having a strength of 1720 of Group
'A' Officer) which is treated as isolated cadre
(Unorganised service) even though they come
through the Geologists Examination conducted
by the UPSC. The Geologists are being
granted Non- functional Selection Grade as in
the case of applicant's disciplines at Direct
level after entering into 14th year of group 'A'
service in accordance with the provision
contained in the Department of Personnel &
Training Office Memorandum No.19/1/86- PP
dated the 14th August, 1987. When the major
discipline are not considered as organized
service in the Geological Survey of India, it
would be anomalous to consider a small
support service having total strength of 34
Group 'A' officers, as organized service.
Further, grant of Non- functional JAG to
Mechanical Engineers in accordance with the
provisions of the aforesaid Department of
Personnel & Training O.A. dated 6.6.2000 will
lead to discrimination vis-a-vis other
disciplines like Geology, Geophysics and
Geochemistry etc.
(iv) In case any group of Engineers have been
granted Non functional JAG in violation of the
provisions of aforesaid O.M. dated 6.6.2000
any other group of Engineers cannot seek
relief under equity clause and that the equality
clause enshrined under Article 14 of the
W.Ps.(C) 16769/2004 & 1541/2012 Page 8 of 24
Constitution of India can not be invoked where
its foundation is based on illegality. This is in
line with the decisions of the Hon'ble Supreme
Court report JT 2000(5) SC 389 (State of
Bihar Vs. Kameshwar Prasad Singh): 1997 (3)
SCC 3212 (State of Haryana & Ors. Vs. Ram
Kumar Mann) : 2003 (5) SCC 437 (UOI &
Ors. Vs. International Trading Company)
wherein the Apex Court has considered the
concept of negative equality in detail.”
12. Aggrieved thereby, the petitioners filed a Contempt Petition,
being C.P. 96/2004 in O.A. 2892/2002, before the learned Tribunal,
contending non- compliance of its order dated 02.09.2003.
13. Vide order dated 24.05.2004, the learned Tribunal found the
action of the respondents of rejecti ng the petitioners’ representations
vide the above order dated 23.12.2003, to be deliberate disobedience
and hence, it was held to be ‘clearly contemptuous’ . It was also
observed that, since the respondents did not challenge the order of the
learned Tribunal before a higher forum, it had attained finality.
Accordingly, three weeks’ time was granted to the respondents to
comply with the directions made in the said o rder of the learned
Tribunal.
14. Consequently, the respondents extended the recommendations
of the 5
th
CPC to the petitioners, subject to the final decision in the
Writ Petition, being W.P.(C) 16769/2004, which was filed by the
respondents in the meantime.
15. The Contempt Petition was, accordingly, disposed of vide order
dated 20.06.2004. However, the NFJAG benefit in the scale of
Rs.12000-16500 was extended to the petitioners, with effect from
W.Ps.(C) 16769/2004 & 1541/2012 Page 9 of 24
24.10.2000, and not with effect from 01.01.1996. In view of this, this
Court, vide interim order dated 12.12.2006 in W.P.(C) 16769/2004,
directed the respondents to grant the benefit of NFJAG to the
petitioners with effect from 01.01.1996, subject to the final outcome
of the petition.
16. Consequently, in compliance with the said Order, the petitioners
were granted the benefits of NFJAG with effect from 01.01.1996, vide
order dated 12.04.2007. The Special Leave Petition, being S.L.P(C)
no. 12030/2007, was filed by the respondents before the Supreme
Court against the said interim Order dated 12.12.2006, and the same
was also dismissed vide Order dated 08.02.2010 .
17. During the pendency of this petition and after his
superannuation on 31.08.2007, the petitioner no. 1, relying on the
DoP&T O.Ms. dated 24.04.2009, 21.05.2009, and 25.09.2009, filed
O.A. 3919/2010 before the learned Tribunal, seeking re-fixation of his
pay by grant of NFU in the Pay Band-4 and Grade Pay of Rs.8,000
with effect from 01.07.2006, and Grade Pay of Rs. 10,000 with effect
from 26.10.2009.
18. It is the case of the petitioner no.1 that the 6
th
CPC
recommended grant of NFU to Organized Group ‘A’ Service Officers
and that such recommendations are applicable to the Group ‘A’
Engineering Cadres working in GSI. However, the learned Tribunal
dismissed his O.A. vide the Impugned Order dated 23.11.2011, with
the above quoted observations.
19. Aggrieved thereby, the petitioner no. 1 filed W.P.(C) 1541/2012,
seeking re-fixation of his pay by grant of NFU.
W.Ps.(C) 16769/2004 & 1541/2012 Page 10 of 24
20. The learned counsel for the petitioners submits that the
Engineers in All India Radio and Doordarshan, under the Ministry of
Information and Broadcasting, belong to an Organized Group ‘A’
Service and the petitioners are similarly placed. Therefore, the learned
Tribunal had rightly drawn similarity between the petitioners’ cadre
and the Engineers of All India Radio and Doordarshan, and directed
the respondents to consider the case of petitioners at par with their
counterparts.
SUBMISSIONS ON BEHALF OF THE PETITIONERS:
21. The learned counsel for the petitioners submits that the 5
th
CPC,
in paragraph 50.45, recommends the pay scale of Rs.4500-5700/ - for
Superintending Engineers and NFJAG to Executive Engineers, in the
context of CPWD engineers, however, it covers all Engineering
Cadres in the Government. Further, the grant of NFJAG is not
confined to Organized Group ‘A’ Services, but is extended to all
Engineering Cadres. The said paragraph reads as under:
“50.45 We would, however, like to make an
exception only in the case of Superintending
Engineers. It is a fact that the Second CPC
had already established a parity between
Superintending engineers and Conservators of
Forests by granting them both the scale of Rs.
1300-1800. This parity was cemented further
by the Third CPC, which observed that "For
the post of Conservators of forests we
recommend the scale which we have
recommended for the Superintending Engineer
grade of the Central Class I Engineering
Service VIZ. Rs.1800- 2000." For the selection
grade of Conservators of Forest, the same
Commission stated that "a selection grade of
W.Ps.(C) 16769/2004 & 1541/2012 Page 11 of 24
Rs.2000- 2250 should be introduced for the
Conservator of Forests, on the same principles
as recommended for the Selection Grade in the
Central Class I Engineering Service." Between
the Third and Fourth CPCs, there was an up-
gradation of the first grade for CFs to Rs.l800-
2000. Subsequently, the Fourth CPC merged
the scales of Rs. 1800- 2000 and the Selection
Grade of Rs.2000- 2250 and gave CFs the
single functional scale of Rs.4500- 5700. The
same treatment in spirit was unfortunately not
accorded to the SEs who were given a JAG of
Rs.3700- 5000 and an NFSG of Rs.4500- 5700.
Taking into account the significant role of
engineering services in the nation- building
process and the fact that the promotion
prospects in engineering cadres are rather
bleak, we recommend that the NFSG of
Rs.4500- 5700 should be converted into a
single functional scale for Superintending
Engineers and the scale of Rs.3700- 5000
should instead be the non- functional JAG for
Exe. Engineers. However, in order to avoid too
fast a rate of promotion in certain cadres to
this grade, it is further recommended that
promotions to the scale of Rs.4500- 5700 would
be permitted only on completion of 13 years of
service in Group 'A'. Although the above
recommendation is being made in the context
of CPWD engineers, it is clarified that this
dispenstion will be available to all
Engineering cadres in the Government. ”
22. The learned counsel, relying on the Department of Personnel
and Administrative Reforms O.M. dated 31.07.1982, submits that the
Guidelines for Introduction of Non-Functional Selection Grades for
Group ‘A’ Services shall be applicable to all Organized Group ‘A’
Services. Annexure-A of the said Guidelines provides a list of Central
Civil Services Group ‘A’ which includes GSI under the Ministry of
W.Ps.(C) 16769/2004 & 1541/2012 Page 12 of 24
Steel & Mines as Group ‘A’ Service . In this regard, he also makes
reference to the Central Civil Services (Revised Pay) Rules, 1997,
notified under Article 309 of the Constitution of India, to submit that
the upgraded pay scales were applicable to all E ngineering Cadres in
the Government with effect from 01.01.1996. The learned counsel
further submits that the provisions of the Central Civil Services
(Revised Pay) Rules, 1997 were notified under Article 309 of the
Constitution, therefore, they are of a statutory nature and cannot be
modified or restricted by an O.M. of the DoP&T.
23. The learned counsel places reliance on the O.M. dated
02.08.1989 issued by the DoP&T, to submit that in terms of the
DoP&T O.M. dated 14.08.1987, the Non-Functional Selection Grade
was admissible to officers of Organized Group ‘A’ Service, however,
the benefit was extended to all seven scientific and technical streams
of GSI as they have all the characteristics of an O rganized Service.
24. He submits that the above position has been recognized by the
GSI in various documents and mere delay in framing the Rules would
not take away the status of the Mechanical Engineering Service in the
GSI as an Organized Group ‘A’ Service. In support of his arguments,
the learned counsel places reliance on the j udgments of the Supreme
Court in Union of India & Ors. v. Sri Harananda & Ors., (2019) 14
SCC 126, State of Mizoram & Anr. v. Mizoram Engineering Service
Association & Anr., (2004) 6 SCC 218, and Union of India & Ors. v.
Sudipta Lahiri, 2024 SCC Online SC 5718; of this Court in G.J.
Singh & Ors. v. Union of India & Ors., 2015:DHC:7281-DB, and Dr.
Subodh Jha & Ors. v Union of India & Ors., 2025:DHC4960-DB;
W.Ps.(C) 16769/2004 & 1541/2012 Page 13 of 24
and of the Karnataka High Court in Union of India & Ors. v. M.N.
Ramachandra Rao, 2014 SCC OnLine Kar 4054.
25. The learned counsel for the respondents submits that the
Impugned Order dated 02.09.2003 passed by the learned Tribunal, is
bad in law, and therefore, is liable to be set aside. He submits that the
matter of fitment of officers in a particular group should be left to the
discretion and expertise of Special Commissions and the same is
undertaken by specialised agencies after detailed examination of the
nature of the posts and duties. Therefore, it should not be decided by
Courts and Tribunals.
SUBMISSIONS ON BEHALF OF THE RESPONDENTS
26. The learned c ounsel submits that the learned Tribunal has
wrongly equated the petitioners with the engineers of the AIR and
Doordarshan, and held them to be Organized Group ‘A’ Services
Engineers. He submits that the learned Tribunal has also erred in
deciding upon the applicability of different pay scales to different
employees of the Government. While the engineers of AIR and
Doordarshan belong to Organized Group ‘A’ Engineering Services, the
petitioners belong to the General Central Service Group ‘A’. He
submits that the equality clause under Article 14 of the Constitution of
India would apply only if the persons are similarly placed, and not
when there exists a valid classification based on reasonable
differentia. Therefore, in the present case, the petitioners have been
erroneously granted the benefits of Organized Group ‘A’ Services.
W.Ps.(C) 16769/2004 & 1541/2012 Page 14 of 24
27. He further submits that the learned Tribunal has failed to
appreciate the Speaking Order dated 23.12.2003, passed by the
respondents, whereby the representations of the petitioners were duly
considered and rejected with reasons recorded in support thereof.
28. On the issue of re-fixation of pay of petitioner no. 1 by grant of
NFU, the learned counsel for the respondents reiterates that the
petitioner did not belong to the Organized Group ‘A’ Service , so as to
be entitled to NFU in ter ms of the DoP&T O.M. dated 24.04.2009. He
submits that the petitioner fell within the Mechanical Stream, which in
fact, belonged to the General Central Service Category. In support
thereof, he placed reliance on DoP&T O.M. dated 19/20.11.2009
which provides the attributes of Organized Group ‘A’ Central
Services. He submits that the petitioner’s service does not qualify as
Organized Group ‘A’ Services in terms of the said O.M., as it fails to
meet the requirements set out in clauses (iv) to (vi) thereof. The said
clauses are reproduced as under:
“(iv) All the vacancies above JTS and upto
SAG level in such services are filled up by
promotion from the next lower grade;
(v) While a service may comprise one or more
distinct cadre(s), all such cadres should be
governed by composite Service Rules
facilitating horizontal and vertical movement
of officers of a particular cadre at least upto
SAG level. The cadre posts of an Organized
Service expressly belong to that service. The
posts not belonging to any service are
classified as General Central Service and,
therefore, an Organised Group ‘A’ Service
cannot have posts/grades classified as General
Central Service; and
W.Ps.(C) 16769/2004 & 1541/2012 Page 15 of 24
(vi) Such a service consists of two distinct
components, namely Regular Duty Posts and
Reserves. The Reserves are generally of four
types, viz (i) Probationary Reserves, (ii) Leave
Reserve, (iii) Training Reserve and (iv)
Deputation Reserve. The various types of
reserves are usually created and accounted for
in the Junior Time Scale.”
29. He further makes reference to the Ministry of Mines’ Note for
the Cabinet dated 04.10.2011 on Restructuring of the GSI, proposed to
declare the Engineering Stream of the GSI as an Organized Service,
after suitable restructuring. He also makes reference to the Ministry of
Mines Notification dated 17.05.2013, declaring the Engineering
stream of GSI as a Central Organized Service with effect from the date
of the said Notification. The said Notification provides as under:
“3. Constitution of the Geological Survey of
India Engineering Service Group 'A' In
Geological Survey of India.- (1) On and from
the commencement of these rules the
Engineering stream of GSI is hereby
constituted as Geological Survey of India
Engineering Service Group 'A' in Geological
Survey of India as a Central Organised
Service.”
30. The learned counsel submits that a Central Group Service
cannot become Organised Group ‘A’ Service unless the Cadre
Controlling Authority consciously constitutes it. In view of this, the
Engineering Services of GSI became an Organized Service only with
effect from the issuance of the Ministry of Mines’ Notification dated
17.05.2013. Since the demand for g rant of NFU from a date when the
service itself was not an Organized Service is not tenable in law,
W.Ps.(C) 16769/2004 & 1541/2012 Page 16 of 24
therefore, the prayer of the petitioner no. 1 seeking grant of NFU from
a back date is not tenable.
31. From the above narration of facts and the submissions made by
the learned counsels for the parties, the common question that needs to
be answered in the present petitions is whether the Mechanical
Engineering Branch of the GSI is an Organized Group ‘A’ Central
Service, thereby entitling the petitioners to the benefit of the NFJAG,
in terms of the recommendations of the 5
th
CPC, and the NFU, in
terms of the recommendations of the 6
th
CPC.
ANALYSIS AND CONCLUSION
32. Before we answer the above issue, we would again take note of
the fact that the petitioners succeeded in their claim for the NFJAG
before the learned Tribunal, and the said order has also been
implemented by the respondents, subject to the orders to be passed in
W.P.(C) 16769/2004. The petitioners have, however, failed in their
claim for the grant of the NFU before the learned Tribunal, resulting
in the filing of W.P.(C) 1541/2012.
33. As regards the core question of whether the Mechanical
Engineering Branch in the GSI is an O rganized Group ‘A’ Central
Service, we would start by taking note of the O.M. dated 31.07.1982,
by which the Department of Personnel and Administrative Reforms,
while laying down the guidelines for introduction of Non-Functional
Selection Grade in Group ‘A’ Central Services, gave a list of
Organized Group ‘A’ Central Services, which inter alia, included the
GSI under the Ministry of Steel and Mines (Department of Mines) at
W.Ps.(C) 16769/2004 & 1541/2012 Page 17 of 24
Serial No. 23 of the Annexure-A thereof. We would further take note
of the O.M. dated 16.07.1990, issued by the DoP&T, which again
gave a list of services/cadres to which N on-Functional Selection
Grade is applicable. In Annexure-A thereto, GSI under the
Department of Mines is reflected as a Group ‘A’ Service to which the
recommendations of the 4
th
CPC regarding selection grade would
apply.
34. Much reliance has been placed by the respondents on the O.M.
dated 19/20.11.2009 of the DoP&T to state that out of the six
attributes of Organized Group ‘A’ Services mentioned by the DoP&T
in the said O.M., at least three attributes appearing at serial nos. (iv)
and (vi) thereof, are not met by the E ngineering Cadre of the GSI.
However, that is not of much support to the respondents as paragraph
2 thereof specifically states that what has been stated therein are
certain basic attributes of an Organized Group ‘A’ Service, and that an
Organized Group ‘A’ Service is one which is constituted consciously
as such by the Cadre-Controlling Authorities through an established
procedure. Taking note of the same, the Supreme Court in Sri
Harananda (supra) held as under:
“23.5 So far as the submission made on behalf
of the appellants that CAPFs are not an
Organized Group A Services as they do not
satisfy two attributes out of six attributes is
concerned, it is required to be noted that the
OM dated 19- 11-2009 specifically notes that
there may be certain "minor deviations" from
the attributes listed therein and also to the
extent wherein it states that even if the listed
criteria are fulfilled, the same would not
automatically confer the status of an
W.Ps.(C) 16769/2004 & 1541/2012 Page 18 of 24
Organized Group A Service. Thus, as rightly
observed by the High Court in the impugned
judgment and order, fulfilling/compliance of
the attributes shall not be given too weightage
while deciding on the status of CAPFs.”
35. The above submission of the respondents, therefore, does not
hold much water, especially in light of the consistent stand that the
GSI is an Organized Group ‘A’ Central Service.
36. We must herein also take note of the fact that by an O.M. dated
15.05.1990, the DoP&T had also clarified that while the technical
streams of the GSI, which would include the Mechanical Engineering
Cadre, is a Group ‘A’ Service, the Financial and Administrative
Streams are not so, and, therefore, they cannot be treated as an
Organized Group ‘A’ Service. Further, by an O.M. dated 02.08.1989
issued by the DoP&T, it had again been stated that the benefit of the
NFU had been extended to all seven S cientific and T echnical Streams
of the GSI, as they all have the characteristics of an organized service,
which criterion is not fulfilled by the A dministrative and F inancial
Streams of the GSI. Therefore, consistently there had been no dispute
that the Mechanical Engineering stream of the GSI is an O rganized
Group ‘A’ Central Service.
37. In fact, the above has also been the consistent view of the
learned Tribunal as also of different Courts. In M.N. Ramachandra
Rao (supra), the Bangalore Bench of the learned Tribunal, by its order
dated 19.03.2012, had found the contention of the respondent that the
post of Director, GSI, is not an Organized Group ‘A’ Service, to be
“very strange”. It had placed reliance, inter alia, on the O.M. dated
W.Ps.(C) 16769/2004 & 1541/2012 Page 19 of 24
31.07.1982, which we have referred to hereinabove. The said decision
was partly approved by the Karnataka High Court vide its judgment in
M.N. Ramachandra Rao (supra), and we quote from the same as
under:
“10. Since all the points are interlinked with
one another, we will deal with the points
together as hereunder. The learned Additional
Solicitor General is not disputing that Official
Memorandum vide Annexure-A1 is dated 31- 7-
1982. On a perusal of Annexure-A1 and
schedule thereto, the post of the respondent is
found at SI No 23, which is characterized as
organized group. When the Union of India has
recognized the post held by the respondent as
organized group in the year 1982, it cannot
now go back from its own official
memorandum. Therefore, we are of the view
that the tribunal is justified in holding that the
post held by the respondent would also carry
30% of the duty post
11. The contention of the learned Additional
Solicitor General that though the official
memorandum was issued in the year 1982, the
same has not been given effect to and that
there was no demand by the respondent,
cannot be a ground to hold the post held by the
respondent a nonorganized group category.
When we hold that the post held by the
respondent is an organized group, as on the
date of issue of Annexure-A1 in the year 1982,
15% of the duty post was reserved for the
benefit of the post held by the respondent. It is
also not in dispute that subsequently, 15% has
been enhanced to 30%. The said amendment
would always enure to the benefit of the
respondent. Therefore, we do not find any fault
with the order of the tribunal in directing the
petitioners herein to consider the case of the
respondent on merit to extend 30% duty post
for the post held by the respondent.”
W.Ps.(C) 16769/2004 & 1541/2012 Page 20 of 24
38. The Special Leave Petition against the said judgment of the
Karnataka High Court, that is, SLP (C) 16461/2014, was dismissed by
the Supreme Court vide its order dated 17.10.2014.
39. Relying on the above O rder, the High Court of Meghalaya in
Union of India & Ors. v. Dr. Umesh Kumar Mishra, 2022 SCC
OnLine Megh 56, observed as under:
“5. It is submitted on behalf of the
respondent herein that the view taken by the
Tribunal is supported by a Karnataka High
Court judgment rendered on April 21, 2014 in
WP No. 45591 of 2012 (Union of India vs.
M.N. Ramachandra Rao). The respondent also
asserts that the relevant judgment in MN.
Ramachandra Rao has been left undisturbed
by the Supreme Court following a petition for
special leave to appeal against the order of
April 21, 2014 passed by the Karnataka High
Court. The respondent submits that there can
now be no denial of the dues of the respondent
in terms of such order of the Karnataka High
Court.
“6. Accordingly, and since adequate
reasons have been given in the relevant order
passed by the Central Administrative Tribunal,
no interference is called for. However, it is
made clear that the relief the respondent
herein will be entitled to will be confined to
the legal position as indicated in the
Karnataka judgment, and not beyond.”
40. In Sudipa Lahiri (supra), the High Court of Meghalaya had
again disposed of a petition based on the above order of the Bangalore
Bench of the learned Tribunal and the judgment of the Karnataka High
Court. The Supreme Court dismissed Special Leave Petition, being
SLP (C) 20026/2022, in challenge thereto, by observing as under:
“3. We have further perused the order dated
W.Ps.(C) 16769/2004 & 1541/2012 Page 21 of 24
14
th
March, 2022 and we find that the present
matter was disposed of in the same terms as in
the order dated 14
th
March 2022. There was
no occasion or, justification for the Union of
India to have challenged the said order by way
of this Special Leave Petition.
4. The present petitions are sheer abuse of the
process of law. The petitioners are cautioned
not to file such frivolous petitions in future.”
41. The Supreme Court, in fact, imposed costs on the respondents
for continuing to re-agitate the same stale issues in different
proceedings.
42. Therefore, we fail to appreciate how the respondents still
maintain that the Mechanical Engineering Cadre of the GSI is not an
Organized Group ‘A’ service.
43. The learned counsel for the respondents has further submitted
that the Recruitment Rules ( in short, ‘RRs’) for the Mechanical
Engineering Cadre were notified by the Ministry of Mines only on
17.05.2013 and, inter alia, provide that the Engineering cadre will be
an Organized Group ‘A’ Service. He submits that the said RRs are
effective only from the date of the notification, therefore, the
Mechanical Engineering Cadre of the GSI was not an O rganized
Group ‘A’ Service prior to the notification.
44. We are not impressed with the above submission.
45. As noted hereinabove, since 1982, it had been recognised that
GSI is an Organized Group ‘A’ Service. The only exception sought to
be carved out from the same was in respect of the Administrative and
Financial Cadres of GSI. A recognition of this fact by way of the RRs
dated 17.05.2013, therefore, would not mean that the Mechanical
W.Ps.(C) 16769/2004 & 1541/2012 Page 22 of 24
Engineering Cadre will become an Organized Group ‘A’ Service only
from that date. In fact, we would also take note of the RRs titled
‘Geological Survey of India (Group A and Group B posts) (Second
Amendment) Rules, 1984’, which provide that the posts of Director
(Mechanical Engineering), Mechanical Engineer (Senior), and
Mechanical Engineer (Junior) are General Central Service Group ‘A’
Gazetted posts.
46. In this regard, we may also make a reference to the judgment of
the Supreme Court in Mizoram Engineering Service Association
(supra), wherein the Supreme Court rejected a similar plea by
observing as under:
“6. Great stress was laid on the fact that
Engineering Service in the State was not an
organised service and therefore, it did not
have categorisation by way of entrance-level
and senior-level posts and for that reason the
higher scale of Rs 5900- 6700 which was
admissible for senior-level posts could not be
given in the Engineering Service. The main
reason for dubbing Engineering Service as an
unorganised service in the State is absence of
recruitment rules for the service. Who is
responsible for not framing the recruitment
rules? Are the members of the Engineering
Service responsible for it? The answer is
clearly "No". For failure of the State
Government to frame recruitment rules and
bring Engineering Service within the
framework of organised service, the engineers
cannot be made to suffer. Apart from the
reason of absence of recruitment rules for the
Engineering Service, we see hardly any
difference in organised and unorganised
service so far as government service is
concerned. In government service such a
distinction does not appear to have any
W.Ps.(C) 16769/2004 & 1541/2012 Page 23 of 24
relevance. Civil service is not trade unionism.
We fail to appreciate what is sought to be
conveyed by use of the words "organised
service" and "unorganised service". Nothing
has been pointed out in this behalf. The
argument is wholly misconceived.”
47. For the above reasons, and following the judgment of the
Karnataka High Court, as approved by the Supreme Court in M.N.
Ramachandra Rao (supra), and the other judgments referred by us
herein above, we hold that the Mechanical Engineering Cadre of the
respondent is an Organised Group ‘A’ Service and that the petitioners
were entitled to the NFJAG as also the NFU benefits under the 5
th
and
the 6
th
CPC, respectively.
48. The Order dated 02.09.2003 of the learned Tribunal is,
therefore, approved, and the W.P.(C) No. 16769/2004 is hereby
dismissed. At the same time, the Impugned Order dated 23.12.2011 of
the learned Tribunal is hereby set aside, and the W.P.(C) No.
1541/2012 is allowed.
49. The petitioner no. 1 is held entitled to grant of the NFU in terms
of the O.M. dated 24.04.2009 read with the O.M. dated 25.09.2007 of
the DoP&T. The consequential benefits of the same shall be released
by the respondents to the petitioner within a period of eight weeks
from today, along with interest at the rate of 6% per annum.
50. We find that, in spite of the O rder dated 22.04.2024 passed by
the Supreme Court, imposing costs on the respondents for re -agitating
issues which already stood settled, the same arguments were reiterated
before us with full vehemence. We, therefore, impose costs on the
W.Ps.(C) 16769/2004 & 1541/2012 Page 24 of 24
respondents of Rs.25,000/-, to be paid to each of the petitioners within
a period of eight weeks from today.
51. The petitions, along with the pending application, are disposed
of in the above terms.
NAVIN CHAWLA, J.
MADHU JAIN, J.
JANUARY 28, 2026 /rv/Yg
Legal Notes
Add a Note....