As per case facts, the Petitioner, a user fee collection agency, challenged the premature termination of its contract with NHAI for user fee collection at a fee plaza, along with ...
W.P.(C) 4817/2026 Page 1 of 18
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 17.04.2026
Judgment pronounced on: 20.04.2026
Judgment uploaded on: 20.04.2026
+ W.P.(C) 4817/2026, CM APPL. 23578/2026, CM APPL.
23579/2026, CM APPL. 23580/2026 and CM APPL.
24716/2026
MD. KARIMUNNISA .....Petitioner
Through: Mr. Sanjoy Ghose, Sr. Adv.
with Mr. Kaustubh Anshuraj,
Mr. Parmod Kalirana, Mr.
Manish Choudhary, Mr. Amaya
Vaid, Advs.
versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA
THROUGH ITS CHAIRMAN & ANR. .....Respondents
Through: Mr. N. Venkataraman, ASG
with Mr. Namit Saxena, Adv.
CORAM:
HON'BLE MR. JUSTICE ANIL KSHETARPAL
HON'BLE MR. JUSTICE AMIT MAHAJAN
J U D G M E N T
ANIL KSHETARPAL , J. :
1. Through the present Writ Petition under Article 226 of the
Constitution of India, the Petitioner assails the order dated 08.04.2026
[hereinafter referred to as the „Impugned Order‟], along with the show
cause notice dated 02.04.2026 [hereinafter referred to as the
„Impugned Show Cause Notice‟], whereby the Contract dated
26.05.2025 [hereinafter referred to as „Contract‟] executed between
W.P.(C) 4817/2026 Page 2 of 18
the Petitioner and the NHAI for collection of user fee at Pawangaon
Fee Plaza has been terminated prior to expiry of the contractual
period. The Petitioner has also challenged the fresh tender dated
02.04.2026 issued for engagement of a new user fee collecting agency
for three months for the said Fee Plaza.
2. The Petitioner contends that the termination of the Contract is
arbitrary, premeditated and contrary to the contractual stipulations,
particularly Clause 35(6) of the Contract [hereinafter referred to as
„Clause 35(6)‟], inasmuch as no circumstances warranting invocation
of the said clause existed. It is further urged that the impugned action
has been taken despite the contract remaining valid till 17.06.2026 and
without any breach attributable to the Petitioner.
3. In the aforesaid backdrop, the principal issues that arise for
consideration before this Court are:
i. Whether the Respondent Authority was justified in
terminating the Contract in exercise of its enabling powers under
Clauses 35(2) [hereinafter referred to as „Clause 35(2)‟] and
35(6); and
ii. Whether any interference is warranted in exercise of writ
jurisdiction with a contractual decision taken in the interest of
public exchequer by a public authority in matters relating to the
termination of a tender contract.
W.P.(C) 4817/2026 Page 3 of 18
FACTUAL MATRIX:
4. In order to appreciate the controversy involved in the present
case, the relevant facts, in brief, are required to be noticed.
5. The Petitioner had earlier operated as a User Fee Collection
Agency at the Pawangaon Fee Plaza situated at Km. 57+935 on NH-
353J in the State of Maharashtra for a period of two months during
April and May 2025. The Respondent No.1, namely the National
Highways Authority of India [hereinafter referred to as „NHAI‟],
invited bids through e-tender for engagement of a User Fee Collection
Agency at the said Pawangaon Fee Plaza, for a period of one year.
6. Pursuant to the competitive bidding process, in which multiple
bidders participated, the Petitioner was declared the successful bidder
with a daily remittance of Rs.2,62,430/- (Rs.2,58,737/- as per the
stand of the Respondents) for a period of one year and a Letter of
Award dated 13.05.2025 came to be issued in its favour. It is stated
that the Petitioner‟s quoted remittance was substantially higher than
the reserve price as well as the bid submitted by the second highest
bidder.
7. Thereafter, the Contract was executed between the parties for
collection of user fee at the said Fee Plaza for the period commencing
from 17.06.2025 (08:00 hours) till 17.06.2026 (08:00 hours). The
Petitioner furnished performance security and commenced toll
collection operations in terms of the Contract.
W.P.(C) 4817/2026 Page 4 of 18
8. The Contract, inter alia, contained Clause 35 governing
termination of the contract. While Clause 35(2) enabled termination
upon issuance of seven days‟ notice without assigning reasons, Clause
35(6) provided for termination in case of “windfall gain” at new fee
plazas where the moving average of ETC and cash collections for the
preceding fifteen days exceeded forty percent of the existing
remittance being paid by the toll agency.
9. On 02.04.2026, the Respondents issued a show cause notice
cum seven days‟ termination notice invoking Clauses 35(2) and 35(6)
of the Contract, stating their intention to terminate the contract. The
notice alleged the occurrence of windfall gain and simultaneously
afforded an opportunity of personal hearing to the Petitioner. On the
same date, the Respondents also issued a fresh tender for engagement
of a new user fee-collecting agency for three months for the very same
Fee Plaza.
10. Subsequently, by order dated 08.04.2026, the Contract stood
terminated prior to expiry of its contractual tenure. Aggrieved thereby,
the Petitioner instituted the present Writ Petition under Article 226 of
the Constitution of India challenging the Impugned Show Cause
Notice, the Impugned Order and the fresh tender issued for
appointment of a new agency.
11. The principal contention of the Petitioner is that the invocation
of Clause 35(6) was wholly misconceived and impermissible,
inasmuch as the said provision relating to “windfall gain” is expressly
applicable only to new user fee plazas, whereas the Pawangaon Fee
W.P.(C) 4817/2026 Page 5 of 18
Plaza is an already operational and existing fee plaza. Further, the
premature termination of a subsisting contract, allegedly without
existence of any breach or default on its part, is arbitrary, pre-
determined, and violative of Article 14 of the Constitution of India.
12. During the course of hearing, the Respondents placed on record
a tabulated compilation reflecting a substantial and consistent increase
in toll collection at the Pawangaon Fee Plaza over successive months.
The said compilation, produced to demonstrate the financial trajectory
of collections vis-à-vis the contractual remittance, is extracted below
for ready reference:
Month ETC
Collectio
n
Annual
pass
Compensa
tion
amount
ETC
Collection
including
Compensation
Present
remittance
per day
Compari
son
Apr-25 2,31,734 0 2,31,734 2,58,737 10.44
May-25 3,38,228 0 3,38,228 2,58,737 30.72
June-25 4,50,264 0 4,50,264 2,58,737 74.02
Jul-25 4,81,012 0 4,81,012 2,58,737 85.91
Aug-25 5,19,804 2,716 5,22,521 2,58,737 101.95
Sep-25 6,41,192 5,150 6,46,341 2,58,737 149.81
Oct-25 6,21,503 8,682 6,30,185 2,58,737 143.56
Nov-25 7,79,651 12,915 7,92,566 2,58,737 206.32
Dec-25 8,72,630 17,590 8,90,220 2,58,737 244.06
Jan-26 8,64,490 18,933 8,83,422 2,58,737 241.44
Feb-26 9,37,590 20,970 9,58,560 2,58,737 270.48
Mar-26 8,92,866 19,780 9,12,646 2,58,737 252.73
13. A perusal of the aforesaid data indicates that the toll collection
substantially exceeded the 40% benchmark contemplated under
Clause 35(6) as early as June 2025 and thereafter demonstrated a
steady upward trajectory. According to the Respondents, continuation
W.P.(C) 4817/2026 Page 6 of 18
of the existing contractual arrangement despite such escalation in
collections resulted in a significant revenue imbalance, causing an
estimated loss of approximately Rs.7,50,000/- per day to the public
exchequer.
14. By order dated 16.04.2026, after hearing learned counsel for the
parties, this Court granted opportunity to the Petitioner to respond to
the compilation produced by the Respondents and directed the
Respondents to explain the delay in invoking Clause 35(6) of the
Contract, however, no satisfactory explanation has been furnished.
CONTENTIONS OF THE PARTIES:
15. Heard learned Counsel for the parties at length and perused the
record placed before the Court.
16. Learned Senior Counsel representing the Petitioner has made
the following submissions:
i. The termination of the Contract is arbitrary, pre-
determined and contrary to the contractual stipulations, inasmuch
as Clause 35(6) could not have been invoked since the
Pawangaon Fee Plaza is not a new user fee plaza and no
“windfall gain” situation existed.
ii. The contract was admittedly valid till 17.06.2026 and no
breach, deficiency, or contractual default has been attributed to
the Petitioner. Therefore, exercise of termination powers under
Clause 35(2) is mala fide and violative of Article 14 of the
Constitution of India.
W.P.(C) 4817/2026 Page 7 of 18
iii. The Impugned Show Cause Notice and the consequential
Impugned Order are non-speaking and were issued in a
mechanical manner, particularly as a fresh tender was floated on
the very same date, demonstrating a pre-decided intention to
terminate the contract.
iv. The reply dated 04.04.2026 submitted by the Petitioner
was neither considered nor dealt with prior to termination of the
Contract.
v. The policy circular dated 26.03.2025 governing
“overstay” situations has been wrongly applied during the
subsistence of the contractual period, thereby causing serious
financial prejudice.
17. Per contra, learned ASG appearing on behalf of the
Respondents has made the following submissions:
i. The Contract expressly confers upon the NHAI the power
to terminate the contract by issuance of notice under Clause
35(2), and such contractual power cannot be curtailed merely
because the contract period had not expired.
ii. Invocation of Clause 35(6), read with the applicable
policy circulars, is stated to be a policy and administrative
decision taken in public interest to safeguard public revenue and
ensure efficient toll operations.
iii. Judicial review in contractual matters is limited to
examining the decision-making process and does not extend to
W.P.(C) 4817/2026 Page 8 of 18
re-appreciation of commercial or policy decisions taken by a
public authority.
18. No other submissions were urged by learned Counsel
representing the parties.
ANALYSIS AND FINDINGS:
19. This Court has considered the submissions advanced by learned
Counsel for the parties and perused the material placed on record.
20. At the outset, it is necessary to delineate the scope of judicial
review exercisable in contractual and tender matters under Article 226
of the Constitution of India. It is now well-settled that when the State
or its instrumentalities act within the domain of commercial contracts,
the Court does not sit as an appellate authority over contractual
decisions. Interference is warranted only where the decision-making
process is shown to be arbitrary, mala fide, irrational, or in violation
of statutory or constitutional mandates.
21. The Supreme Court, in Tata Cellular v. Union of India
1
,
authoritatively held that judicial review in contractual matters is
confined to examining the decision-making process and not the merits
of the decision itself. The Court cannot substitute its own view for that
of the competent authority merely because another view is possible.
22. Similar principles have consistently been reiterated in Jagdish
Mandal v. State of Orissa
2
, wherein it was held that interference in
1
(1994) 6 SCC 651
2
(2007) 14 SCC 517
W.P.(C) 4817/2026 Page 9 of 18
tender matters is permissible only when the action is so arbitrary or
unreasonable that no responsible authority acting reasonably could
have arrived at such a decision, or when public interest is
demonstrably affected.
23. Recently, the Supreme Court in N.G. Projects Ltd. v. Vinod
Kumar Jain
3
cautioned that courts must exercise restraint in
contractual disputes involving State entities, as excessive judicial
intervention delays public projects and adversely impacts the public
exchequer.
24. Having delineated the settled contours governing judicial
review in contractual and tender matters, this Court now proceeds to
examine the controversy arising in the present case.
25. The principal challenge mounted by the Petitioner essentially
relates to the validity of termination of the Contract, particularly the
invocation of Clause 35(6), contending that the Pawngaon Fee Plaza
was not a “New User Fee Plaza” and therefore the “windfall gain”
provision could not have been invoked.
26. Clause 35(6) envisages its invocation where the moving
average of electronic toll collection and cash collection for the
preceding fifteen days exceeds forty percent of the existing remittance
payable by the toll agency. In the present case, the material placed on
record indicates that toll collections crossed the said forty percent
threshold in the same month (June 2025) when the Petitioner took
over operations at the fee plaza under this contract.
3
(2022) 6 SCC 127
W.P.(C) 4817/2026 Page 10 of 18
27. Once the contract, viewed as a whole, provides adequate
safeguards to both contracting parties, it would not be appropriate to
strike down an individual clause as arbitrary. Considerable arguments
were advanced on the question whether the fee plaza constituted a
“new” fee plaza. However, once Clause 35(6) forms part of the
contractual framework accepted by the parties, the said controversy
loses much of its significance, particularly when it is the stand of the
Respondents that the fee plaza was less than one year old at the time
of award of contract and that the Petitioner itself had operated the
plaza for a limited period prior to execution of the Contract. In that
context, the Respondents have treated the plaza as a new fee plaza.
28. Clause 35(6) expressly contemplates termination upon
occurrence of specified financial contingencies relating to toll
collections. Once such a contractual power stand reserved in favour of
the NHAI, the contractor cannot claim an indefeasible right to
continue till expiry of the contractual tenure merely because the
Contract remained valid up to 17.06.2026. A commercial arrangement
governed by agreed contractual conditions necessarily remain subject
to termination in accordance with those very conditions, unless the
decision is established as arbitrary passed with mala fide intent or
biased.
29. Similarly, it has been consistently held that persons who enter
into contractual dealings with the State with open eyes must accept
both the advantages and the burdens flowing from such agreements. A
contractor participating in a competitive bidding process cannot
W.P.(C) 4817/2026 Page 11 of 18
subsequently challenge a mutually accepted termination mechanism
solely because its operation has resulted in commercial disadvantage.
30. The doctrine invalidating unfair contractual terms, as explained
in Central Inland Water Transport Corporation Ltd. v. Brojo Nath
Ganguly & Anr.
4
, applies primarily to situations involving gross
inequality of bargaining power, such as employer-employee
relationships. The present case, however, arises out of a commercial
tender between business entities operating in a competitive market
environment. The termination clause, forming part of the tender
conditions, cannot therefore be characterised as unconscionable or
oppressive.
31. It is pertinent to note that before declaring any particular clause
of a contract to be arbitrary, the Court is required to examine the
contract in its entirety. Testing a contractual stipulation on the
aforesaid basis becomes necessary, for a clause read in isolation may
lead to an incorrect conclusion. Selective reading of contractual terms
is fraught with inherent dangers and must therefore be avoided.
32. Clause 35(5) itself provides for premature termination of the
contract at the request of the contractor. Under sub-clause (a), the
contractor is at liberty to submit a written request to the NHAI seeking
premature termination within a period of thirty days of taking over the
fee plaza. Further, sub-clause (g) of Clause 35(5) contemplates
termination at the instance of the contractor in situations such as
farmer agitations or where the fee plaza is likely to remain closed for a
4
AIR 1986 SC 1571
W.P.(C) 4817/2026 Page 12 of 18
period exceeding thirty days. These provisions demonstrate that the
contractual framework incorporates safeguards operating in favour of
the contractor as well.
33. It is equally well settled that while State action in contractual
matters remains amenable to judicial review under Article 14 of the
Constitution of India, such review is confined to examining whether
the decision suffers from mala fides, arbitrariness, or colourable
exercise of power. Courts do not evaluate the commercial wisdom of
the Authority or substitute their own assessment for that of the
contracting agency managing public infrastructure.
34. In the present case, the NHAI issued prior notice, considered
the Petitioner‟s reply, afforded a personal hearing, and thereafter
proceeded to terminate the Contract. The decision-making process
thus satisfies the requirements of procedural fairness. No material has
been placed before this Court to indicate mala fides, bias, or manifest
arbitrariness in exercise of the contractual power under Clause 35(2).
35. Once the Contract itself reserves an express right of termination
upon notice, continuation of the contract till the last date of tenure
cannot be claimed as a vested or enforceable right in writ jurisdiction.
36. Further, the Petitioner, in its reply, has itself asserted that it has
been associated with the NHAI since the year 2020 and has
successfully operated more than 80 Fee Plazas across the country
without adverse remarks. The said assertion, rather than advancing the
Petitioner‟s case, demonstrates that the Petitioner is an experienced
and commercially sophisticated contractor, well acquainted with the
W.P.(C) 4817/2026 Page 13 of 18
operational, financial, and contractual framework governing toll plaza
agreements. Consequently, the Petitioner cannot be permitted to
contend that the implications or consequences flowing from Clause
35(6) were unforeseen or inequitable, the contractual stipulations
having been accepted with full knowledge and understanding of their
commercial ramifications.
37. Additionally, the Petitioner is estopped from challenging the
validity of Clause 35(6) at this stage after having availed benefits
under the Contract for nearly nine months out of the total contractual
duration of twelve months. Having enjoyed the contractual
arrangement for approximately eighty percent of its tenure, it would
be inappropriate to permit a challenge to the very clause forming part
of the agreed tender conditions.
38. In substance, the relief sought by the Petitioner amounts to
enforcement of a commercial contract in the nature of specific
performance while simultaneously assailing the validity of Clause
35(6). Under the scheme of the Specific Relief Act, 1963, contracts
requiring continuous supervision or day-to-day monitoring by the
Court are ordinarily not specifically enforceable, particularly where
compensation or damages constitute an adequate remedy. The
appropriate remedy, if any, available to the Petitioner would therefore
lie in seeking damages or compensation in accordance with law.
39. Consequently, viewed either from the standpoint of valid
invocation of Clause 35(6) or independently under Clause 35(2), the
impugned termination cannot be said to be legally unsustainable. The
W.P.(C) 4817/2026 Page 14 of 18
challenge raised by the Petitioner, therefore, essentially seeks
enforcement of contractual expectations rather than correction of any
constitutional or public law infirmity.
40. The Petitioner has further alleged that the Impugned Show
Cause Notice and the consequential Impugned Order were issued in a
mechanical manner and that the simultaneous issuance of a fresh
tender demonstrates a pre-determined decision to terminate the
Contract. This contention does not merit acceptance.
41. As noted above, a perusal of the record indicates that the
Petitioner was issued a seven days‟ notice, submitted a detailed reply
dated 04.04.2026, and was afforded an opportunity of personal
hearing on 06.04.2026. The Impugned Order records consideration of
the submissions advanced and reflects the satisfaction of the
Competent Authority that the explanation offered by the Petitioner
was not tenable. The requirement of natural justice does not obligate
an administrative authority to render a judgment akin to a judicial
decree. It is sufficient if the order discloses application of mind to the
material placed before it, which requirement stands duly satisfied in
the present case.
42. The mere fact that a fresh tender process was initiated
contemporaneously with the termination decision cannot, by itself,
establish mala fides or pre-determination. In matters relating to toll
collection on national highways, continuity of operations is directly
connected with safeguarding public revenue. Administrative
W.P.(C) 4817/2026 Page 15 of 18
preparedness to avoid disruption in user fee collection constitutes
prudent governance rather than evidence of arbitrariness.
43. The Petitioner has also relied extensively upon alleged financial
losses suffered at other fee plazas, blockage of performance securities,
and the assertion that the Pawangaon Fee Plaza constituted its sole
revenue-generating asset. In contractual matters, hardship or adverse
commercial impact cannot override the express terms voluntarily
agreed between the parties or justify exercise of writ jurisdiction in the
absence of arbitrariness, mala fides, or violation of statutory or
constitutional obligations.
44. It is well settled that writ jurisdiction under Article 226 cannot
be invoked to renegotiate commercial bargains or to grant equitable
protection against contractual consequences voluntarily undertaken. A
contractor participating in a competitive tender assumes both
commercial risks and contractual obligations, and subsequent financial
inconvenience does not render lawful contractual termination
arbitrary.
45. The material on record further indicates that the NHAI acted
with the objective of protecting public revenue and ensuring efficient
management of toll operations. Initiation of a fresh tender process and
interim operational arrangements demonstrate continuity planning in
discharge of statutory and public duties. Judicial interference in such
administrative decisions, absent demonstrable illegality, would
amount to substituting administrative discretion with judicial
preference, which is impermissible in exercise of writ jurisdiction.
W.P.(C) 4817/2026 Page 16 of 18
46. Ultimately, the controversy raised by the Petitioner pertains to
the applicability and exercise of contractual termination clauses, the
financial consequences arising therefrom, and competing
interpretations of contractual terms. Invocation of Article 226 cannot
transform a commercial disagreement into a constitutional cause of
action.
47. Before parting with the matter, this Court considers it necessary
to record certain observations arising from the subsequent
developments placed on record during the course of hearing.
48. The material produced before this Court, including the later
administrative orders relied upon by the parties, indicates that the
circumstances giving rise to alleged “windfall gain” were not acted
upon with promptitude by the NHAI. Delay in timely assessment and
invocation of contractual safeguards, particularly in contracts
involving collection of public revenue, has the potential to result in
avoidable loss to the public exchequer.
49. Public authorities entrusted with management of national
highway toll operations discharge functions closely connected with
public finance. Contractual clauses such as Clause 35(6) are
incorporated precisely to enable timely corrective intervention where
revenue projections undergo substantial variation. Any institutional
delay in monitoring or enforcement undermines the very purpose of
such contractual mechanisms.
50. During the course of hearing on 17.04.2026, learned Additional
Solicitor General appearing for the NHAI fairly submitted that there
W.P.(C) 4817/2026 Page 17 of 18
had been a significant delay in invoking Clause 35(6) of the Contract,
which, according to the Respondents, resulted in a loss of
approximately Rs.7.5 lakhs per day to the NHAI and consequently to
the public exchequer. It was further submitted that a senior official has
already been issued a show cause notice in this regard. Learned
Additional Solicitor General also informed the Court that steps are
being undertaken to introduce an automated technological
mechanism/software-based monitoring system to enable real-time
tracking of toll collections and early identification of “windfall gain”
situations so as to avoid recurrence of such lapses.
51. This Court appreciates the said statement and expects the NHAI
to expeditiously implement robust monitoring mechanisms ensuring
transparency, timely decision-making, and protection of public
revenue. Keeping in view the aforesaid position, the NHAI is directed
to place on record the ultimate decision taken pursuant to the said
show cause notice. The disciplinary proceedings against the concerned
officials shall be concluded, as far as practicable, within a period of
six months, and the outcome thereof shall be placed before this Court,
notwithstanding disposal of the present Writ Petition. These
observations and directions are issued in the larger public interest and
shall not be construed as affecting the legality of the impugned
termination upheld herein.
W.P.(C) 4817/2026 Page 18 of 18
CONCLUSION:
52. In view of the foregoing discussion, this Court is satisfied that
the present Writ Petition is devoid of merit and is, accordingly,
dismissed. All the pending applications also stand closed.
ANIL KSHETARPAL , J.
AMIT MAHAJAN, J.
APRIL 20, 2026
sp/sh
Legal Notes
Add a Note....