As per case facts, the claimant and petitioner entered a building contract for construction. Disputes arose over pending bills, retention amounts, and claims for extra work. The petitioner argued that ...
Arb O.P(COM.DIV.) No. 62 of
2021
IN THE HIGH COURT OF JUDICATURE AT MADRAS
ORDERS RESERVED ON : 09.02.2026
ORDERS PRONOUNCED ON : 17.02.2026
CORAM
THE HONOURABLE MR JUSTICE N. ANAND VENKATESH
Arb O.P(COM.DIV.) No. 62 of 2021
AND
EP SR. NO. 123007 OF 2023
M/s Annai Builders Real Estate
Pvt Ltd
Rep. by its Special Officer
K.Prabhakaran, 150-151, Alpha
Centre, North Usman Road,
T.Nagar, Chennai 600 017.
Petitioner (s)
Vs
G.B.Sarath Kumar
Kalpataru Apartments, H-3B,
Koyambedu, Chennai 600 107.
Respondent(s)
PRAYER
Petition filed under Section 34(2) of the Arbitration and Conciliation
Act, 1996 r/w Section 10 of the Commercial Courts Act, 2014 (Act
No.4 of 2016) praying to set aside the award dated 30.11.2020 passed
by the learned Sole Arbitrator Mr.G.M.Akbar Ali (Retd.,) in
A.F.No.195/2017 in the matter of dispute and differences between the https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
petitioner and the respondent and to direct the respondent to pay the
cost of the proceedings.
For Petitioner (s):Mr. K.Satheesh Kannan
Party in person
For
Respondent(s):
Mr.Avinash Wadhwani
ORDER
The petitioner has assailed the award passed by the Sole
Arbitrator dated 30.11.2020 by filing the present petition under
Section 34 of the Arbitration and Conciliation Act (for brevity
hereinafter referred to as the “Act”).
2.The brief facts of the case are the respondent / claimant
entered into a building contract agreement with the petitioner on
02.02.2011 for the construction of Plots, Smart Homes at
Anagaputhur containing 92 Plots. As per the contract, the Contractor
should construct in accordance with the detailed drawings given by
the owner which was appended as Annexure I to the agreement and
the specifications appended as Annexure II to the agreement. https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
3.During the execution of the Contract, the claimant raised
30 running bills, out of which 28 bills were cleared. However while
raising bill Nos.29 and 30, disputes arose between the parties and
according to the claimant, the amounts were not settled. Apart from
the above, the contract envisaged completion within a period of one
year. The provisional estimate, based on the working drawings was
calculated at approximately Rs.12.58 Crores. Out of every running
bill, 3% can be retained as retention amount and the same has to be
paid within three months of the completion of the contract. Thus, 3%
of the retention amount which was retained towards 28 bills which
were cleared, was also not released.
4.The further case of the claimant is that on 19.03.2012 due
to non payment of bills and pendency for over six months, a request
was made to clear the pending bills. It was also informed by the
contractor that due to non-availability of funds, the work on site is
affected. The bill that was raised towards minor alterations /
additions as required by the petitioner was raised on 28.05.2012 and
this amount also remained unpaid. https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
5.Since the amounts were not settled, the dispute was
referred to the sole arbitrator and the claimant raised the following
claims :-
a. Rs.48,03,763/- (Forty Eight Lakhs Three Thousand
and seven Sixty Three) towards outstanding
payment of Running Bill Nos.29 and 30.
(b) Rs.33,36,432/- (Thirty Three Lakhs, Thirty Six
Thousand and Four Hundred Thirty Two), being the
retention amount of 3% on the running bills paid.
(c) Rs.70,66,022/- (Seventy Lakhs Sixty Six Thousand
and Twenty Two) for the extra increase of the
basement height by two feet
(d) Rs.9,80,000/- (Nine Lakhs Eighty Thousand) to
the material at Site
(e) Rs.11,00,000/- (Eleven Lakhs) being outstanding
payments towards the extra work carried out at the
instance of the respondent.
(f)Rs.2,44,000/- (Two Lakhs and Forty Four
Thousand) for the purchase of grills made, to be
installed in the Windows. https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
Amounting to Rs.1,75.30,217/- (One Crore Seventy
Five Lakhs Thirty Thousand and two Hundred and
Seventeen) together with interest @ 24% p.a. until
date of payment. The payment of Rs.50,00,000/- (Fifty
Lakhs) as damages on account of loss of Business
account of the mental harassment and cost of
proceedings.
6.The petitioner filed statement of defence and took a
specific stand that the respondent has paid much higher than the
actual work that was carried out at the site by the claimant.
According to the petitioner, the total value of the contract was
Rs.12,58,55,050/- and the total amount that was paid to the claimant
was Rs.10,83,44,952/-. This amount was 86% of the contract price
and whereas, the work carried out was only 60%. The petitioner took
a further stand that the claimant had stopped the work as early as
on 19.07.2012 and the claimant had also agreed to complete the work
only on payment of pending bills. The petitioner directed the
claimant to rectify several defects identified. However, the claimant
denies any defective work and was insisting for the payment of https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
nearly Rs.1.95 Crores.
7.The petitioner made a counter claim of Rs.97,24,495/-
towards excess payment with 12% interest from the date of
abandonment of work, penalty of a sum of Rs.1,38,44,155/- towards
delay, Rs.6,59,55,664/- towards completion of the construction
through another contractor and Rs.15,00,000/- towards damages
including mental agony and a cost of Rs.10,00,000/-.
8.The sole Arbitrator based on the pleadings framed the
following issues:-
1.Whether the claimant was forced to stop the
work by the actions of the respondent?
2. Whether the claimant has committed any breach
of contract?
3. Whether the claimant has caused delay in
execution of the contract?
4. Whether the claimant have submitted the last two
running bills 29 and 30?
5. Whether the respondent has paid excess payment
over the running bills of the claimant?
6. whether the claimant is entitled for a sum of
Rs.48,03,763/- towards outstanding payment towards https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
running bill Nos.29 and 30?
7. Whether the claimant is entitled for the return of
the retention amount of Rs.33,00,000/-?
8. Whether the claimant is entitled for a sum of
Rs.70,66,022/- towards extra increase of basement
height by 2 feet?
9. Whether the claimant is entitled for a sum of
Rs.11,00,000/- towards the extra work carried out at
the instance of the respondent?
10.Whether the claimant is entitled for a sum of
Rs.9,80,000/- towards the cost of materials left at site
and a sum of Rs.2,44,000/- for the grills made and
left at side?
11.Whether the claimant is entitled for a sum of
Rs.50,00,000/- towards damages on account of loss of
business and costs?
12. Whether the respondent is entitled for a sum of
Rs.97,24,495/- being the excess amount paid?
13. Whether the respondent is entitled for a sum of
Rs.1,38,44,155/- being the penalty for delay in
execution of the contract?
14. Whether the respondent is entitled for a sum of
Rs.6,59,55,664/- towards the cost incurred for the
completion of the construction?
15. Whether the respondent is entitled for any https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
damages at Rs.15,00,000/- and a cost of
Rs.10,00,000/-.
16. To what relief the parties are entitled to?
9.The claimant examined CW1 and CW2 and filed four
volume of documents. The petitioner relied upon three volumes of
documents. Apart from that, the valuers report and the objection
filed by the claimant was also taken on record.
10.The sole arbitrator on considering the facts and
circumstances of the case and on appreciation of evidence passed an
award dated 30.11.2020 directing the petitioner to pay to the
claimant a sum of Rs.1,10,07,441.80/- within three months from the
date of award failing which the same will become payable with
interest at the rate of 18% per annum from the date of award till the
date of payment.
11.Aggrieved by the above award, the present petition has
been filed before this Court.
12.The petitioner appeared in person and made his
submissions. The respondent is represented through a counsel and https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
the learned counsel made his submissions.
13. This Court has carefully considered the submissions made
on either and the materials available on record and also carefully
went through the award passed by the Sole Arbitrator.
14. The main ground that was raised by the petitioner was
that insofar as running bill Nos.29 and 30 are concerned, duplicate
claims have been made towards claims which had already been
settled earlier. To substantiate the same, the petitioner pointed out
instances where there was discrepancy in terms of the correct built
up area and works which were already completed and paid once
again claimed in these bills etc., The same has been explained in the
brief written statement that was filed on behalf of the petitioner.
15.Apart from that, the petitioner also pointed out that for
running bill Nos.1 to 28, the respondent had collected excess
payments more than the work that was actually completed in the
site. To establish this issue, the petitioner tabulated all the payments
made and for proper appreciation, the same is scanned and extracted
hereunder :- https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021 https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
16.The petitioner further stated that admittedly the
respondent had not completed the work and therefore, there is no
question of making the 100% payment since the payments are made
at different stages based on the percentage of the work completed. In
fact the petitioner had made excess payments for 86% and whereas
the claimant had completed only 60% of the work. The petitioner has
also raised a ground that the additional claim for the increase of the
basement height by two feet, which was allowed by the sole
arbitrator was not in accordance with the agreement and the usual
trade practice. The petitioner also pointed out to certain findings of
the sole Arbitrator which runs contrary to the evidence available on
record. Finally, the petitioner questioned the rejection of the counter
claim made by the petitioner and sought for the interference of the
award and to reject the claims made by the respondent/ claimant and
grant the counter claim sought for by the petitioner.
17.The learned counsel for respondent has taken a stand that
the Sole Arbitrator had taken into consideration the oral and
documentary evidence and has rendered findings which is certainly a https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
possible view taken by the Sole Arbitrator and that none of the
ingredients under Section 34 of the Act has been satisfied warranting
the interference of this Court.
18.This Court will first deal with the two running bill Nos.29
and 30 and also consider as to whether the petitioner had made
excess payments over and above the running bills raised by the
respondent/ claimant.
19.As per the agreement between the parties, Contractor
shall be paid at the rate of Rs.950 per Sq.ft inclusive of all taxes and
all other charges on the plinth area including balconies. As per
Annexure 3, the mode of payment was agreed upon and for proper
appreciation, the same is extracted hereunder:-
ANNEXURE III
Anagaputhur Provisional Estimate:-
Total plots - 92 Plots (6 Blocks)
Total Area - 1,32,479 x 950 = 12,58,55,050/-
[Rupees Twelve Crores
Fifty Eight Lakhs Fifty Five Thousand
and fifty only) https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
Advance - Rs.20,00,000
(Rupees Twenty Lakhs Only)
Contractor Payment Mode:-
Sl.No.Description Percentag
e %
1.Mobilisation Advance 1.5%
2.Completion of Foundation 5.5%
3.Completion of basement 8%
4.Completion of GF Roof
Slab
10%
5.Completion of GF Brick
Work
7%
6.Completion of GF
Plastering
8%
7.Completion of FF Roof
Slab
10%
8.Completion of Brick Work 7%
9.Completion of FF
Plastering
8%
10.Completion of External
Plaster
4%
11.Completion of Carpentry 5%
12.Completion of Electricity5%
13.Completion of Flooring 10%
14.Completion of Sanitary
Fixtures
5%
15.On Handing over 6%
Total 100%
Retention money will be deducted @ 3% on every bill,
payable 3 months after issuable of completion certificate. https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
20.From every bill, retention money will be deducted at 3%
payable three months after issuance of completion certificate. The
contractor’s final bills will be scrutinised for payment after
satisfactory completion and handing over the project and the same
will be paid within two weeks. The payments towards running bills
will be made after verification / certification. Keeping the above in
mind, this Court went through the entire materials and found that
insofar as running RA Bill Nos.1 to 28 are concerned, the same has
been raised by providing all the necessary particulars and supporting
documents which has also been verified and certified before the
payments was made for RA Bill Nos.1 to 28. While making this
payment, the retention charges of 3% has been deducted.
21.Insofar as RA Bill Nos.29 and 30 are concerned, even as
per the Sole Arbitrator, it has not been presented in the same
manner the earlier bills were presented. Admittedly, these bills were
not certified and the petitioner raised an objection that there is
duplication of claims since some of the claims were already made in
the previous bills and had also taken a stand that excess payments https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
have been made even towards the previous bills in terms of the work
that was actually completed and the actual payments that was made
in excess by the petitioner and the Sole Arbitrator has not gone into
the evidence and discussed about the same and has straight away
come to the conclusion that since these two bills were received by the
petitioner and the payment was not made, the petitioner is liable to
make the payments against bill Nos.29 and 30.
22.The above finding rendered by the Sole Arbitrator is bereft
of any reasons and unintelligible.
23.The Apex Court in [Dyna Technologies Pvt. Limited
Vs. Crompton Greaves Limited] reported in 2019 20 SCC Page 1
held that the mandate under Section 31(3) of the Act is to have
reasoning which is intelligible and adequate. Considering the fact
that the sole Arbitrator in this case is a legally trained mind,
compliance with this requirement becomes even more important. In
the case in hand, the abrupt finding that has been rendered by the
sole Arbitrator insofar as Bill Nos.29 and 30 by not even discussing
the grounds raised by the petitioner and the materials relied upon by https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
the petitioner, is unintelligible and the same would be equivalent to
not providing any reasons at all.
24.The above finding of this Court is further substantiated by
the fact that the sole Arbitrator while dealing with the claim made by
the respondent towards extra work, cost of materials left at site etc.,
has concluded that the bills raised by the claimant has not been
verified or certified and therefore, the claimant is not entitled for any
uncertified or unverified bill amounts. This finding completely
contradicts the finding rendered by the sole Arbitrator while allowing
Bill Nos.29 and 30 which also admittedly was not verified or certified.
This glaring contradictions also makes this Court to come to the
conclusion that the finding rendered by the Sole Arbitrator is
unintelligible.
25.There is yet another glaring illegality in the award passed
by the sole arbitrator. The specific case of the petitioner is that the
claimant had completed only 60% of the work and whereas, excess
payments have been made for 86%. In order to ascertain the actual
work that was completed on the site, an expert was appointed who https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
submitted a report which runs to nearly 242 pages. In this report, it
talks about the actual work that was completed. If admittedly only
80% of the work was completed even according to the claimant,
there is no question of settling the entire final bill and there is also
no question of releasing the retention amount since the retention
amount retained can be returned only if the entire work is completed
to the satisfaction of the petitioner. Even this issue has not been
property appreciated and dealt with by the Sole Arbitrator.
26.The Sole Arbitrator does not go into the report and deal
with the same and straight away discarded the entire report with an
observation that an expert opinion is only meant to assist the Court
and it cannot be considered as a conclusive proof. It is quite
unfortunate that the Sole Arbitrator even without dealing with the
detailed report submitted by the expert choose not to even make a
reference to it. It is true that the report of the expert may not be a
conclusive proof. But, however, it is a very relevant fact which will
have a bearing while dealing with the issue of the alleged excess
payments said to have been made by the petitioner. Thus, the
material evidence that was available was not considered by the Sole https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
Arbitrator and it was rejected on the ground that already bill Nos.1
to 28 have already been verified and certified and paid and therefore,
there is no need to consider this report. This finding was rendered
inspite of detailed materials placed by the petitioner to establish
that work was actually completed only to the tune of about 60% and
whereas payments made towards the same were to the tune of about
86%.
27.There is another claim pertaining to extra work said to
have been done by the claimant to increase the basement height by
two feet. The specific stand taken by the petitioner is that it forms
part of the basement work and it cannot be construed as an
additional work. However, the sole arbitrator considered the same as
extra work and awarded a sum of Rs.28.67 lakhs.
28.The counter claims made by the petitioner has been
rejected. https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
29.Considering the manner in which the Sole Arbitrator has
proceeded in this case while dealing with the main issues, this Court
finds that it is difficult to separate / severe the valid portion of the
award from the invalid portion. Hence, this Court is not inclined to
go into the counter claims made by the petitioner since the above
findings rendered by the Sole Arbitrator will have a bearing while
deciding the counter claims also.
30.On an overall reading of the award passed by the Sole
Arbitrator, this Court finds that the findings rendered for the main
issues are unintelligible and it was given in complete disregard to
the evidence available on record and the findings are also mutally
contradictory. Hence, this Court is inclined to interfere with the
entire award on the ground of perversity and patent illegality. It will
be left open to the parties to refer the dispute afresh to the new
Arbitrator in accordance with law.
https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
31.In the result, the award passed by the Sole Arbitrator
dated 30.11.2020 is hereby set-aside and this petition stands allowed.
No costs. Consequently, the EP D No.123007 of 2023 is closed.
17-02-2026
rka
Index:Yes/No
Speaking/Non-speaking order
Internet:Yes
Neutral Citation:Yes/No
To
G.B.Sarath Kumar
Kalpataru Apartments, H-3B,
Koyambedu, Chennai 600 107.
https://www.mhc.tn.gov.in/judis
Arb O.P(COM.DIV.) No. 62 of
2021
N.ANAND VENKATESH J.
rka
Arb O.P(COM.DIV.) No. 62 of
2021
EP SR. NO. 123007 OF 2023
17-02-2026 https://www.mhc.tn.gov.in/judis
Legal Notes
Add a Note....