As per case facts, a contract for road construction faced delays and cost revisions, leading to disputes, DRB recommendations, and arbitration. During arbitration, the appellant-JV submitted ledger entries under a ...
Page 1 of 52
HIGH COURT OF MEGHALAYA
AT SHILLONG
WA No.3/2026
Reserved on: 04.02.2026
Pronouncement on:19.02.2026
M/s BSCPL Infrastructure Ltd. through Mr. Bollineni
Krishnaiah, office at: 8-2-502/1/A, Jivi Towers, Road No.7,
Banjara Hills, Hyderabad-500034, Telangana.
..... Appellant
Vs.
Public Works Department (Roads) through its Chief Engineer
(National Highways), Government of Meghalaya.
..... Respondent
Coram:
Hon’ble Mrs. Justice Revati Mohite Dere, Chief Justice
Hon’ble Mr. Justice W. Diengdoh, Judge
Appearance:
For the Appellant : Mr. Jethmalani, Sr.Adv with
Mr. S. Chopra, Adv
Mr. K. Ch Gautam, Adv
Mr. R. Sharma, Adv
Mr. T. Tewari, Adv
Ms. S. Jethmalani, Adv
Ms. G.C. Marboh, Adv
For the Respondent : Mr. A. Kumar, Advocate General with
Mr. A.H. Kharwanlang, Addl.Sr.GA
Mr. A.S. Pandey, GA
Mrs. S. Laloo, GA
Ms. I. Syiemlieh, GA
i) Whether approved for reporting in Yes
Law journals etc.:
ii) Whether approved for publication
in press: Yes
Serial No.01
Supplementary List
2026:MLHC:85-DB
Page 2 of 52
JUDGMENT
Hon’ble, the Chief Justice:
By the aforesaid appeal, the appellant has impugned the
judgment and order dated 17
th
December, 2025, passed by
the learned Single Judge in Writ Petition (C) No.24 of 2025. By
the said judgment and order, the learned Single Judge
dismissed the appellant’s petition which sought quashing and
setting aside of the order dated 3
rd
December, 2024, passed
by the respondent, blacklisting/debarring the appellant for
five years from participating in any future tender/contract of
Public Works Department.
Brief facts:
In September, 2009, the Government of India, through
the Ministry of Road Transport and Highways, floated a tender
for the ‘2-laning of Nongstoin-Shillong Section of NH 44 and
Nongstoin-Rongjeng-Tura Road in the State of Meghalaya
under Phase ‘A’ of SARDP-Ne-NH-44E & SR-MG-PWD-2010-
11-172’. Accordingly, on 14
th
June, 2010, a Joint Venture
agreement was executed between M/s BSCPL and C&C 2026:MLHC:85-DB
Page 3 of 52
Construction for the purpose of bidding of the aforesaid two
specific projects, one in Nagaland and another in Meghalaya.
In the said Joint Venture agreement, M/s BSCPL (appellant)
was the lead partner of the said agreement.
2. On 15
th
June, 2010, Joint Venture, being BSC C&C JV
(hereinafter referred to as ‘JV’, submitted its bid before the
respondent.
3. On 31
st
January, 2011, a Letter of Acceptance was
issued in favour of the JV for the aforesaid 2-laning project.
On 21
st
February, 2011, the parties entered into an
agreement “contract” to execute the work of Ilvo Laning of
Shillong-Nongstoin Section of NH 44E and Nongstoin -
Rongjeng-Tura Road in the State of Meghalaya for contract
price of ₹1303.83 crores. The project was to be completed
within 36 months i.e., on or before 7
th
March, 2014.
4. It is not in dispute that the project could not be
completed within the stipulated period and hence, 2026:MLHC:85-DB
Page 4 of 52
supplementary agreements were entered into between the
parties and the timeline was extended. Admittedly, the revised
cost estimate was submitted on four occasions and the final
extension of time was approved by the respondent till 31
st
December, 2017. It appears that the Contract works were
completed on 15
th
December, 2017 and the completion
certificate for the project was issued on 13
th
March, 2018.
5. In the interregnum, during the aforesaid period i.e.,
2017-2018 disputes arose between the parties in terms of the
execution of the work under the contract. The appellant-JV
sent a notice in terms of Clause 24 of the Contract to the
respondent informing of its claims in relation to non-payment
of interest on delayed payments, non-payment of cost of extra
bitumen used in bituminous works and non-reimbursement of
labour cess. Accordingly, on 23
rd
April, 2015, the appellant-
JV sought appointment of Dispute Review Board-I (hereinafter
referred to as DRB-I) in terms of Clause 24 of the Contract.
2026:MLHC:85-DB
Page 5 of 52
6. Accordingly, on 1
st
June, 2016, DRB-I was constituted
for adjudication of the disputes for Claim-I, arising between
the parties. In May, 2016, Shri M. Phanbuh, Chief Engineer
(National Highway), denied the appellant’s claim as none of the
heads of claims were maintainable. On 2
nd
June, 2016, Shri
M.R. Sangma, Chief Engineer, admitted the claims of the
appellant-JV vide communication/letter sent by him. On 12
th
September, 2016, Mr. Sangma, Chief Engineer (National
Highway), submitted a letter of joint verification of claims with
the JV to DRB-I. On 25
th
September, 2016, DRB-I gave its
recommendation on the dispute and allowed Claim-I of the
appellant, i.e., ₹80 crore. On 19
th
February, 2017, DRB-I
revised its recommendation, i.e., passed an addendum to its
recommendation dated 25
th
September, 2016, and also
awarded interest to the appellant.
7. It appears that 3
rd
December, 2017, the Regional
Officer, MoRTH, forwarded the recommendation regarding
approval of RCE-IV (revised cost estimate). On 19
th
May, 2026:MLHC:85-DB
Page 6 of 52
2017, Mr. Sangma addressed a letter to DRB, communicating
that an amount of ₹16 crore has been processed towards
labour cess and the remaining claims were being processed to
be incorporated in RCE-IV.
8. Since the respondent failed to make the payment of
interest awarded by DRB-I, the appellant-JV sent a notice
dated 11
th
June, 2018, stating its intention to invoke
arbitration for the unpaid claims under DRB-I award. On 25
th
September, 2018, the appellant-JV applied to the DRB,
constituting the same members as the earlier DRB-I, for
adjudication of two sets of claims i.e., regarding additional
claims arising on account of delay, disruption and
prolongation of contract due to breaches by the respondent
during the execution of the contract (Claim-II), including loss
of profits. Accordingly, DRB-II was constituted. On 25
th
September, 2018, the DRB-II passed recommendation in
favour of the appellant-JV and awarded an amount of ₹220
(approx) crores/lakhs, towards delay, disruption and 2026:MLHC:85-DB
Page 7 of 52
prolongation, including loss of profits. On 16
th
October, 2025,
DRB-II further revised its recommendation.
9. On 16
th
January, 2019, the respondent also sent a
notice invoking arbitration and appointed Mr. K.K. Jalan as its
nominee arbitrator. On 1
st
January, 2019 in response to the
respondent’s notice of arbitration, appellant-JV appointed Mr.
R.K. Srivastava as its nominee arbitrator and sought for
consolidation of both, Claims-I and II before the learned
Arbitral Tribunal. On 13
th
March, 2019, the nominee
arbitrators of the appellant-JV and the respondent appointed
Hon’ble Mr. Justice (Retd) V.B. Gupta as the Presiding
Arbitrator and accordingly, the Arbitral Tribunal entered upon
reference in accordance with the Arbitration and Conciliation
Act, 1966 (hereinafter referred to as the ‘Act’) for adjudication
of both the claims allowed by DRB-I and DRB-II.
10. On 1
st
February, 2019, the appellant-JV also invoked
arbitration proceedings in respect of both the Claims i.e.,
Claims- I and II. 2026:MLHC:85-DB
Page 8 of 52
11. On 30
th
May, 2019, the appellant-JV filed its statement
of claim for two claims based on DRB -I and DRB-II
recommendations. As far as Claim-I was concerned, it was
based on the admission of the officials of the respondent.
Along with the statement of claim, the appellant-JV also filed
an application under Section 31(6) of the Act, seeking an
interim award on claim-I allowed by the DRB-I, since it was an
admitted claim. It appears that the appellant-JV in the
statement of claims had filed 16 volumes of unindexed
documents running into more than 9500 pages. On 30
th
July,
2019, the respondent before filing its reply to the appellant’s
statement of claim, filed an application under Section 16 of
the Act, challenging the jurisdiction of the Arbitral Tribunal.
The Arbitral Tribunal vide order dated 21st March, 2020
dismissed the respondent’s application under Section 16 of
the Act.
12. It appears that on 10
th
November, 2020 , the
respondent tried to implead the Ministry of Road Transport 2026:MLHC:85-DB
Page 9 of 52
and Highways (MoRTH) in the arbitration, by filing an
application seeking impleadment of MoRTH, as a party
respondent to the arbitration proceeding. The respondent also
filed its statement of defence. On 18
th
December, 2020, the
appellant-JV filed its rejoinder to the statement of defence.
13. By two separate orders dated 27
th
July, 2021, the
Arbitral Tribunal rejected the impleadment application of the
respondent with costs and allowed the interim application
preferred by the appellant under Section 31(6) of the Act and
passed an interim award directing the respondent to pay the
appellant-JV a sum of ₹75 crore with interest pending detailed
calculation, as a part of the claims, arising out of Claim-I.
14. The respondent challenged the interim award under
Section 34 of the Act by filing a petition alongwith an
application for stay of the interim award dated 27
th
July,
2021. The said petition was filed before the Commercial
Court, Shillong. Vide order dated 29
th
October, 2021, the
Commercial Court, Shillong issued notice to the appellant-JV 2026:MLHC:85-DB
Page 10 of 52
and the Court granted ad-interim ex-parte stay on the interim
award passed by the Arbitral Award. On 17
th
November,
2021, the appellant-JV filed an application and sought
dismissal of the petition i.e., Commercial Misc. Case
No.24/2021, filed by the respondent on the premise that the
same was premature , as the Section 33 application was
pending before the Arbitral Tribunal. The Commercial Court,
Shillong vide order dated 17
th
November, 2021 modified its
stay on the interim award so as to allow continuation of the
Section 33 proceeding before the Arbitral Tribunal. On 21
st
December, 2021, the Arbitral Tribunal, rejected the said
application filed by the appellant-JV under Section 33 of the
Act.
15. On 19
th
January, 2021, the appellant-JV filed a
petition being Civil Revision Petition No.2 of 2022 in the High
Court of Meghalaya and sought quashing and setting aside of
the said orders passed by the Commercial Court, Shillong. The
High Court vide judgment and order dated 11
th
February, 2026:MLHC:85-DB
Page 11 of 52
2022 set aside the orders of the Commercial Court, Shillong
and directed the Commercial Court, Shillong to take up
Section 34 petition de novo in the light of the dismissal of
Section 33 application.
16. On 14
th
February, 2022, the Arbitral Tribunal framed
issues for adjudication. It appears that one of the issues
framed by the Arbitral Tribunal concerned Claim-I, which was
already the subject matter of the order dated 27
th
July, 2021.
On 6
th
April, 2022, the respondent filed a petition in this
Court challenging the Arbitral Tribunal’s order dated 14
th
February, 2022 framing issues and also prayed for stay of the
arbitral proceeding. Vide order dated 9
th
May, 2022, this
Court quashed the order of the Arbitral Tribunal dated 14
th
February, 2022 to the extent, that it related to issue No.1,
i.e., issue which concerned Section 31(6) application and
accordingly, arbitral proceedings were stayed vide order dated
25
th
April, 2022. Later, this Court vide order dated 9
th
May,
2022 quashed Issue No.1 and disposed of the petition. 2026:MLHC:85-DB
Page 12 of 52
17. Being aggrieved by the said order passed by the High
Court, the appellant-JV filed a Special Leave Petition before
the Apex Court. It appears that the arbitral proceeding was
stayed approximately for one year. In view of the stay, the
recording of evidence of the appellant-JV remained
incomplete. On 19
th
June, 2023, the Arbitration Appeal No.6
of 2023 preferred by the appellant-JV in this Court under
Section 37 of the Act challenging the judgment dated 17
th
May, 2023, passed by the Commercial Court, Shillong was
dismissed by the High Court with costs was decided against
the respondent and the Section 31(6) order of the Arbitral
Tribunal was upheld, i.e., interim award passed by the
Arbitral Tribunal was upheld. Pursuant thereto, the
respondent filed a Special Leave Petition in the Apex Court
against the said order dated 19
th
June, 2023, passed in
Arbitration Appeal No.6 of 2023. The said SLP was dismissed
by the Apex Court vide order dated 7
th
August, 2023. While
dismissing the Special Leave Petition Nos.14475 of 2022, the 2026:MLHC:85-DB
Page 13 of 52
Apex Court modified issue No.1 in the arbitration as well as
vacated the stay on the arbitration proceeding.
18. On 14
th
September, 2023, the arbitration proceedings
resumed after the stay was lifted by the Apex Court on 7
th
August, 2023. It appears that the respondent filed an
application on 17
th
September, 2024, under Section 16
contending that the dispute had become non-arbitrable before
the arbitrator, however, the same was dismissed with costs.
On 17
th
October, 2023, cross-examination of the appellant-
JV and evidence recording concluded. As the mandate of the
Arbitral Tribunal had expired on 30
th
November, 2023, the
same was renewed for further six months by the Commercial
Court, Shillong vide its order dated 4
th
July, 2024.
19. It appears that the Tribunal passed its final award with
the majority of 2:1, allowing Claim-I of the appellant-JV and
rejected the entire Claim-II of the appellant-JV.
2026:MLHC:85-DB
Page 14 of 52
20. It is the respondent’s case that on 3
rd
September,
2024, they unearth several ledger entries showing that the
appellant-JV had engaged, during the extensions granted in
execution of the contract, in giving illegal gratification to
government officials, including the Engineers of PWD, funding
of MoRTH officials and other officials. Accordingly, a complaint
was filed by the Chief Engineer (Roads), National Highway with
the Sardar Police Station, East Khasi Hills against the
appellant-JV and its partners including certain known and
unknown officials and representatives of the appellant -JV
alleging offences punishable under Sections 120B, 409, 420,
465, 468, 471, 477(a) IPC read with Section 13(2) of the
Prevention and Corruption Act, 1988. Pursuant to the
complaint, on 10
th
September, 2024, FIR bearing No.286(9)
of 2024 was registered with the Sardar Police Station, East
Khasi Hills, Shillong against the appellant-JV and its partners
and certain officials/representatives of the respondent and the
appellant.
2026:MLHC:85-DB
Page 15 of 52
21. On 16
th
September, 2024, the respondent issued a
show cause notice to the appellant-JV and its partners in view
of the material found in the statement of claims, i.e., ledger
entries showing acts of corruption and bribery being
committed by the appellant-JV. Certain entries in the ledger
accounts were quoted in the show cause notice in support of
the same. On 30
th
September, 2024, the appellant-JV sent a
joint reply, including for C&C construction, to the show cause
notice stating therein that the expenses in the ledger account
were not by way of bribe or corruption.
22. On 3
rd
December, 2024, the respondent, after
considering their reply, blacklisted the appellant-JV and its
partners for a period of five years. It appears that almost
around this time, i.e., on 16
th
September, 2024, the
respondent also preferred an application under Section 2(3)
read with Section 16 of the Act, as according to the
respondent, the disputes had become inarbitrable due to
corruption and bribery. On 4
th
October, 2024, the appellant- 2026:MLHC:85-DB
Page 16 of 52
JV filed its reply to the Section 16 application filed by the
respondent before the Arbitral Tribunal, stating therein, that
the said entries relied upon by the respondent were records of
day-to-day expenses of the project incurred between 2014 -
2017.
23. Being aggrieved by the impugned order dated 3
rd
December, 2024 , blacklisting the appellant-JV and its
partners for five years, the appellant-JV preferred a Writ
Petition (C) No.24 of 2025, in this Court and sought quashing
of the order dated 3
rd
December, 2024, by which they were
blacklisted by the respondent for five years from participating
in any future tender/contract of Public Wors Department.
24. The learned Single Judge vide his judgment and order
dated 17
th
December, 2025, dismissed the said petition
essentially on the following counts:
(i) that the respondent was well within its authority to issue
show cause notice to the appellant-JV for blacklisting; 2026:MLHC:85-DB
Page 17 of 52
(ii) that the material relied upon for issuance of show cause
notice and subsequent blacklisting was not based on hearsay
or suspicion but on ledger accounts produced by the
appellant-JV themselves, which provided sufficient and
credible proof of illegal gratification and as such, the course of
action taken by the respondent was well within its right;
(iii) that the action resorted to by the respondent was neither
mala fide nor motivated nor without any basis, as the State
was obligated to put public interest over anything else in such
cases; and
(iv) there is no delay in taken action against the appellant-JV
and that the penalty imposed considering the nature of
allegations which reflects the conduct of the appellant-JV and
scale of public fund involved is neither disproportionate nor
excessive.
25. Hence, this appeal.
2026:MLHC:85-DB
Page 18 of 52
Submissions on behalf of the appellant:
Mr. Jethmalani, learned Senior Counsel appearing for
the appellant, assailed the order of blacklisting as well as the
impugned order passed by the learned Single Judge on the
following counts:
(i) that the show cause and the impugned order blacklisting
the appellant-JV, i.e., clauses 37 and clause 59.2(h) of the
conditions of contract, were inapplicable to the facts in hand.
(ii) that neither the show cause notice nor the impugned order
of blacklisting explicitly set out (a) the thing and value given to
the public official concerned; (b) what was the reciprocal
action of the public official, for the thing given, which was
meant to influence the public official concerned , in the
procurement process or in the contract execution; and (c) the
name of the public official who was sought to be influenced.
Thus, it is submitted that neither in the show cause notice nor
in the blacklisting order any such particulars are furnished. It
is further submitted that the show cause notice is also bereft
of vital particulars, rendering it void and illegal inasmuch as, 2026:MLHC:85-DB
Page 19 of 52
it does not put the appellant company to notice on the specific
factual particulars that he is supposed to meet vis-à-vis the
charge of corruption.
(iii) That the blacklisting order deals with much more
allegations, not referred to in the show cause notice and as
such, the impugned order cannot be sustained.
(iv) that the ledger entries which are admitted by the appellant
and relied upon by the respondent in the show cause notice
and in the blacklisting order do not disclose any payments
whatsoever to Mr. Sangma, Chief Engineer, for the alleged acts
performed by him or for any reason.
(v) that during the period of execution of the contract, there
were no complaints or allegations against the appellant-JV
regarding the quality of work, workmanship or progress of
work. It is submitted that due to the additional scope of works
and amounts, supplementary agreements were entered into
between the appellant-JV and the respondent under four
revised cost estimates on 30
th
July, 2013, 6
th
February,
2015, 7
th
July, 2015 and 30
th
May, 2017, which took the 2026:MLHC:85-DB
Page 20 of 52
project cost from ₹1303.83 crores to ₹2406.46 crores and that
these revisions were after following due procedure.
(vi) that at no stage of the arbitration proceeding, which was
delayed by the respondent, there were allegations of
bribery/corruption, either during recording of evidence or in
the statement of defence and that the allegations pertained
only to exaggeration of claims by the appellant-JV.
(vii) That the FIR lodged by the respondent, does not allege any
offence under the Prevention of Corruption Act; and that the
FIR alleges that the total value of property stolen was
₹2366.77 crore, which infact, is the entire sum awarded by the
Arbitral Tribunal to the appellant-JV, suggesting that no
amount was due and payable to the appellant company -JV at
all for the execution of the contract which execution of work,
spanned from 2011 to 2017 ; that the ledger entries of the
appellant company on which reliance is placed by the
respondent to blacklist the appellant-JV were annexed to the
statement of claim which was filed on 30
th
May, 2019, and
that the respondent despite knowing the same, lodged a police 2026:MLHC:85-DB
Page 21 of 52
complaint belatedly, only on 3
rd
September, 2024, after more
than five years and consequently, issued the impugned show
cause notice on 16
th
September, 2024, which ultimately
resulted in blacklisting the appellant-JV. It is submitted that
the explanation offered by the respondent for the delay in
filing the FIR/issuance of the show cause notice is, that they
waited till the cross-examination of the appellant-JV during
the trial of the arbitration petition, an explanation that defies
logic.
(viii) that the show cause notice and consequently , the
blacklisting order was passed by the respondent authorit y
with a mala fide intent only to deny the appellant-JV, its
legitimate financial dues arising out of an express contractual
obligation, which was accepted by the State PWD Department
and the nodal authority, MoRTH.
(ix) that the conduct of the respondent and the observations
made against the respondents in various proceedings, is
telling; 2026:MLHC:85-DB
Page 22 of 52
(x) that the FIR was registered show cause notice issued and
the impugned order was passed only to scuttle the arbitration
proceeding and prejudice the arbitrator; and
(xi) that the learned Single Judge failed to consider the
aforesaid.
Mr. Jethmalani, learned Senior Counsel appearing for
the appellant, relied on the following judgments in support of
his submissions:
(1) M/s Erusian Equipment & Chemicals Ltd. v. State of
West Bengal & anr: (1975) 1 SCC 70;
(2) Gorkha Security Services v. Government (NCT of Delhi)
& ors: (2014) 9 SCC 105;
(3) UMC Technologies Private Limited v. Food Corporation
of India & anr: (2021) 2 SCC 551;
(4) V-MARC India Limited v. State of Uttar Pradesh & ors:
2025 SCC OnLine All 379;
(5) Floral Electrical Pvt. Ltd. v. Haryana Vidyut Prasaran
Nigam Ltd. & anr: 2025 SCC OnLine P&H 2191 ;
(6) M/s Techno Prints v. Chhattisgarh Textbook
Corporation & anr: 2025 INSC 236: Civil Appeal No.2362
of 2025; and
2026:MLHC:85-DB
Page 23 of 52
(7) The Blue Dreamz Advertising Pvt. Ltd. v. Kolkata
Municipal Corporation & ors: 2024 INSC 589
Submissions on behalf of the respondent:
Mr. Kumar, learned Advocate General, opposed the
appeal on the following grounds:
(i) that the facts and the admitted ledger accounts which the
appellant-JV has admitted clearly reveals corrupt
practices/bribes made to public officials and that the action of
blacklisting the appellant-JV is justified, proportionate and in
larger public interest;
(ii) that there was no delay in issuing the show cause notice,
inasmuch as, there was a stay to the arbitral proceedings
pending before the Arbitral Tribunal for a sufficiently long
period; and that in any circumstance, actions of the appellant-
JV, who had indulged in corrupt practices cannot be
condoned, more particularly when the ledger entries have been
admitted by the appellant-JV. It is further submitted that the
ledger entries admitted by the appellant-JV clearly show that 2026:MLHC:85-DB
Page 24 of 52
the appellant-JV had indulged in corrupt practices and that
the argument, that the amount was small as compared to the
contract, is inconsequential, inasmuch as, corruption is
corruption;
(iii) that Clause 59.2(h) confers power on the respondent to
even otherwise, take appropriate action against the party
concerned, if it is found that the party has indulged in corrupt
practices. It is submitted that payment of monies to
government officials by way of wine bottles, laptops, mobiles,
costly gifts, hotel arrangements and donations to unknown
organisation cannot be trivialised;
(iv) that the ledger entries have been admitted by the
appellant-JV, although according to the appellant-JV, they
were given as gifts and as goodwill gestures, and not as bribes.
It is submitted that the appellant-JV is seeking to justify the
gifts, as legitimate business expenses, when infact, it is
nothing but bribery/corruption. He further submitted that the
appellant-JV had admitted the ledger entries submitted by
them, in the cross-examination before the Arbitral Tribunal. It 2026:MLHC:85-DB
Page 25 of 52
is further submitted that the ledger entries reveal the
underlying reasons for admission of claims made by the
Government officials in favour of the appellant -JV, thus
causing huge loss to the public exchequer;
(v) that both, the High Court and the Arbitral Tribunal had
passed critical observations vis-à-vis the ledger accounts
showing gifts given to government officials;
(vi) that sufficient details have been spelt out in the show
cause notice; that the principles of natural justice have been
duly complied with, as warranted and that thereafter, a
speaking order has been passed blacklisting the appellant-JV
for five years. Thus, according to the learned Advocate
General, due process has been followed to the hilt by the
respondent;
(vii) that in the FIR, Prevention of Corruption Act has been
invoked and the said FIR is being investigated; and that the
Enforcement Directorate has also issued summons to the
former Chief Engineer Mr. Almond M. Kharmawphlang under
the Prevention of Money Laundering Act; and 2026:MLHC:85-DB
Page 26 of 52
(viii) that the learned Single Judge, after going through the
record has rightly dismissed the appellant-JV’s petition by a
reasoned order and that no interference is warranted in the
same.
Mr. Kumar, learned Advocate General appearing for the
respondent, relied on the following judgments in support of his
submissions:
(1) Grosons Pharmaceuticals (P) Ltd. & anr v. State of U.P.
& ors: (2001) 8 SCC 604, para 2;
(2) Patel Engineering Limited v. Union of India & anr:
(2012) 11 SCC 257, paras 36 & 37;
(3) TPF Engineering Pvt. Ltd. & anr v. National Highways
Logistics Management Limited & anr: 2023 SCC OnLine
Del 7116, paras 24 to 28, 33 to 35, 43;
(4) ITD Cementation India Limited v. SSJV -ZVS Joint
Venture & ors: (2023) 2 High Court Cases (Del) 44: 2023
SCC OnLine Del 1391, paras 13 & 14;
(5) Asia Foundations & Constructions Ltd., Bombay & ors
v. State of Gujarat & anr: 1985 SCC OnLine Guj 93: AIR
1986 Guj 185: (1987) 2 GLH 510 , para 31;
2026:MLHC:85-DB
Page 27 of 52
(6) M/s Sabharwal Medicos Pvt. Ltd. through its Director
v. Union of India & ors: 2013 SCC OnLine Del 3839 , paras
12 to 15;
(7) Theme Engg. Service Pvt. Ltd. Assn. with Ishita Info
Sol. Thru. Their Auth. Rep. Sumeet Asthana v. National
Highway Authority of India Thru Chairman & anr : 2024
SCC OnLine All 6275, paras 35, 38;
(8) Riddhi Siddhi Associates v. National Highways
Authority of India & ors: 2024 SCC OnLine Del 5513,
paras 7 to 10;
(9) State of Odisha & ors v. Panda Infraproject Limited:
(2022) 4 SCC 393, paras 17, 18, 22, 24;
(10) Kulja Industries Limited v. Chief General Manager,
Western Telecom Project Bharat Sanchar Nigam Limited
& ors: (2014) 14 SCC 731, paras 17, 21, 25;
(11) State of Orrisa v. Madan Gopal Rungta: 1951 SCC
1024, para 15; and
(12) V. Punnen Thomas v. State of Kerala: 1968 SCC
OnLine Ker 110: AIR 1969 Ker 81 (FB): 1968 KLT 800 (FB),
paras 9 to 14.
26. Before we proceed to consider whether interference is
warranted in the impugned order dated 3
rd
December, 2024,
blacklisting the appellant-JV and the impugned judgment and
order dated 17
th
December, 2025, passed by the learned
Single Judge of this Court in WP (C) No.24 of 2025, it would 2026:MLHC:85-DB
Page 28 of 52
be apposite to deal with the law with respect to show cause
notice, in cases relating to blacklisting, which is no longer res-
integra.
27. In M/S Erusian Equipment and Chemicals Ltd v.
State of West Bengal & anr reported in (1975) 1 SCC 70,
the question that arose before the Apex Court was whether a
person who is put on the blacklist by the State Government is
entitled to a notice to be heard before the name is put on the
blacklist? The Apex Court in paras 15 to 17, 19 and 20 held as
under:
“15. The blacklisting order does not pertain to any
particular contract. The blacklisting order involves civil
consequences. It cast a slur. It creates a barrier between
the persons blacklisted and the Government in the matter
of transactions. The black lists are “instruments of
coercion”.
16. In passing an order of blacklisting the Government
department acts under what is described as a
standardised code. This is a code for internal instruction.
The Government departments make regular purchases.
They maintain list of approved suppliers after taking into
account the financial standard of the firm, their capacity
and their past performance. The removal from the list is
made for various reasons. The grounds on which
blacklisting may be ordered are if the proprietor of the firm
is convicted by court of law or security considerations to 2026:MLHC:85-DB
Page 29 of 52
warrant or if there is strong justification for believing that
the proprietor or employee of the firm has been guilty of
malpractices such as bribery, corruption, fraud, or if the
firm continuously refuses to return Government dues or if
the firm employs a Government servant, dismissed or
removed on account of corruption in a position where he
could corrupt Government servants. The petitioner was
blacklisted on the ground of justification for believing that
the firm has been guilty of malpractices such as bribery,
corruption, fraud. The petitioners were backlisted on the
ground that there were proceedings pending against the
petitioners for alleged violation of provisions under the
Foreign Exchange Regulations Act.
17. The Government is a Government of laws and not of
men. It is true that neither the petitioner nor the
respondent has any right to enter into a contract but they
are entitled to equal treatment with others who offer
tender or quotations for the purchase of the goods. This
privilege arises because it is the Government which is
trading with the public and the democratic form of
Government demands equality and absence of
arbitrariness and discrimination in such transactions.
Hohfeld treats privileges as a form of liberty as opposed to
a duty. The activities of the Government have a public
element and, therefore, there should be fairness and
equality. The State need not enter into any contract with
any one but if it does so, it must do so fairly without
discrimination and without unfair procedure. Reputation is
a part of a person’s character and personality. Blacklisting
tarnishes one's reputation.
19. Where the State is dealing with individuals in
transactions of sales and purchase of goods, the two
important factors are that an individual is entitled to trade
with the Government and an individual is entitled to a fair
and equal treatment with others. A duty to act fairly can
be interpreted as meaning a duty to observe certain 2026:MLHC:85-DB
Page 30 of 52
aspects of rules of natural justice. A body may be under a
duty to give fair consideration to the facts and to consider
the representations but not to disclose to those persons
details of information in its possession. Sometimes duty to
act fairly can also be sustained without providing
opportunity for an oral hearing. It will depend upon the
nature of the interest to be affected, the circumstances in
which a power is exercised and the nature of sanctions
involved therein.
20. Blacklisting has the effect of preventing a person from
the privilege and advantage of entering into lawful
relationship with the Government for purposes of gains.
The fact that a disability is created by the order of
blacklisting in decades that the relevant authority is to
have an objective satisfaction. Fundamentals of fair play
require that the person concerned should be given an
opportunity to represent his case before he is put on the
blacklist.”
28. In Gorkha Security Services v. Government (NCT of
Delhi) & ors reported in (2014) 9 SCC 105, the Apex Court
was called upon to consider the form and content of show
cause notice that is required to be served before deciding,
whether the noticee is to be blacklisted or not? and whether it
was a mandatory requirement that there should be a
stipulation contained in the show cause notice that action of
blacklisting is proposed? The Apex Court in paras 21, 22 and
29 held as under: 2026:MLHC:85-DB
Page 31 of 52
“21. The central issue, however, pertains to the
requirement of stating the action which is proposed to be
taken. The fundamental purpose behind the serving of
show-cause notice is to make the noticee understand the
precise case set up against him which he has to meet. This
would require the statement of imputations detailing out
the alleged breaches and defaults he has committed, so
that he gets an opportunity to rebut the same. Another
requirement, according to us, is the nature of action which
is proposed to be taken for such a breach. That should
also be stated so that the noticee is able to point out that
proposed action is not warranted in the given case, even if
the defaults/breaches complained of are not satisfactorily
explained. When it comes to blacklisting, this requirement
becomes all the more imperative, having regard to the fact
that it is harshest possible action.
22. The High Court has simply stated that the purpose of
show-cause notice is primarily to enable the noticee to
meet the grounds on which the action is proposed against
him. No doubt, the High Court is justified to this extent.
However, it is equally important to mention as to what
would be the consequence if the noticee does not
satisfactorily meet the grounds on which an action is
proposed. To put it otherwise, we are of the opinion that in
order to fulfil the requirements of principles of natural
justice, a show-cause notice should meet the following two
requirements viz:
(i) The material/grounds to be stated which
according to the department necessitates an action;
(ii) Particular penalty/action which is proposed
to be taken. It is this second requirement which the
High Court has failed to omit.
We may hasten to add that even if it is not specifically
mentioned in the show-cause notice but it can clearly and 2026:MLHC:85-DB
Page 32 of 52
safely be discerned from the reading thereof, that would
be sufficient to meet this requirement.
29. No doubt, rules of natural justice are not embodied
rules nor can they be lifted to the position of fundamental
rights. However, their aim is to secure justice and to
prevent miscarriage of justice. It is now well-established
proposition of law that unless a statutory provision either
specifically or by necessary implication excludes the
application of any rules of natural justice, in exercise of
power prejudicially affecting another must be in conformity
with the rules of natural justice.”
29. In UMC Technologies Private Ltd v. Food Corporation
of India & anr reported in (2021) 2 SCC 551, the Apex
Court held in paras 14 and 21 as under:
“14. Specifically, in the context of blacklisting of a person
or an entity by the State or a State Corporation, the
requirement of a valid, particularised and unambiguous
show-cause notice is particularly crucial due to the severe
consequences of blacklisting and the stigmatisation that
accrues to the person/entity being blacklisted. Here, it
may be gainful to describe the concept of blacklisting and
the graveness of the consequences occasioned by it.
Blacklisting has the effect of denying a person or an entity
the privileged opportunity of entering into government
contracts. This privilege arises because it is the State who
is the counterparty in government contracts and as such,
every eligible person is to be afforded an equal opportunity
to participate in such contracts, without arbitrariness and
discrimination. Not only does blacklisting take away this
privilege, it also tarnishes the blacklisted person's
reputation and brings the person's character into question. 2026:MLHC:85-DB
Page 33 of 52
Blacklisting also has long-lasting civil consequences for
the future business prospects of the blacklisted person.
21. Thus, from the above discussion, a clear legal position
emerges that for a show-cause notice to constitute the
valid basis of a blacklisting order, such notice must spell
out clearly, or its contents be such that it can be clearly
inferred therefrom, that there is intention on the part of the
issuer of the notice to blacklist the noticee. Such a clear
notice is essential for ensuring that the person against
whom the penalty of blacklisting is intended to be
imposed, has an adequate, informed and meaningful
opportunity to show cause against his possible
blacklisting.”
30. In Kulja Industries Ltd v. Chief General Manager
Western Telecom Project Bharat Sanchar Nigam Limited
& ors reported in (2014) 14 SCC 731, the Apex Court held as
under:
“21. The legal position governing blacklisting of suppliers
in USA and UK is no different. In USA instead of using the
expression “blacklisting” the term “debarring” is used by
the statutes and the courts. The Federal Government
considers “suspension and debarment” as a powerful tool
for protecting taxpayer resources and maintaining integrity
of the processes for federal acquisitions. Comprehensive
guidelines are, therefore, issued by the Government for
protecting public interest from those contractors and
recipients who are non-responsible, lack business integrity
or engage in dishonest or illegal conduct or are otherwise
unable to perform satisfactorily. These guidelines 2026:MLHC:85-DB
Page 34 of 52
prescribe the following among other grounds for
debarment:
(a) Conviction of or civil judgment for.—
(1) Commission of fraud or a criminal offense in
connection with obtaining, attempting to obtain, or
performing a public or private agreement or transaction;
(2) Violation of Federal or State antitrust statutes,
including those proscribing price fixing between
competitors, allocation of customers between competitors,
and bid rigging;
(3) Commission of embezzlement, theft, forgery,
bribery, falsification or destruction of records, making
false statements, tax evasion, receiving stolen property,
making false claims, or obstruction of justice; or
(4) Commission of any other offense indicating a lack
of business integrity or business honesty that seriously
and directly affects your present responsibility;
(b) Violation of the terms of a public agreement or
transaction so serious as to affect the integrity of an
agency program, such as.—
(1) A wilful failure to perform in accordance with the
terms of one or more public agreements or transactions;
(2) A history of failure to perform or of unsatisfactory
performance of one or more public agreements or
transactions; or
(3) A wilful violation of a statutory or regulatory
provision or requirement applicable to a public agreement
or transaction;
(c) * * *
(d) Any other cause of so serious or compelling a
nature that it affects your present responsibility. 2026:MLHC:85-DB
Page 35 of 52
25. Suffice it to say that “debarment” is recognised and
often used as an effective method for disciplining deviant
suppliers/contractors who may have committed acts of
omission and commission or frauds including
misrepresentations, falsification of records and other
breaches of the regulations under which such contracts
were allotted. What is notable is that the “debarment” is
never permanent and the period of debarment would
invariably depend upon the nature of the offence
committed by the erring contractor.”
31. In Patel Engineering Ltd v. Union of India & anr
reported in (2012) 11 SCC 257 , the Apex Court held as
under:
“36. We cannot say the reasoning adopted by the second
respondent is either irrational or perverse. The dereliction,
such as the one indulged in by the petitioner, if not
handled firmly, is likely to result in recurrence of such
activity not only on the part of the petitioner, but others
also, who deal with public bodies, such as the second
respondent giving scope for unwholesome practices. No
doubt, the fact that the petitioner is blacklisted (for some
period) by the second respondent is likely to have some
adverse effect on its business prospects, but, as pointed
out by this Court in Jagdish Mandal v. State of Orissa
[(2007) 14 SCC 517] :(SCC p.518) “Power of judicial review
will not be invoked to protect private interest at the cost of
public interest, or to decide contractual disputes.”
2026:MLHC:85-DB
Page 36 of 52
32. The aforesaid legal position is well settled and
undisputed and there can be no escape from the said settled
legal principles. The question that arises for consideration
before us, is whether there is breach of any of the said
principles enunciated, by the Apex Court in the facts of the
present case.
33. Keeping in mind the settled position of law and the facts
in hand, we are of the opinion that no interference is
warranted in the order blacklisting the appellant-JV and the
impugned judgment and order dated 17
th
December, 2025
passed in WP (C) No.24 of 2025, by which the appellant’s writ
petition, challenging the order blacklisting them for five years
from participating in any future tender/contract of the PWD
was dismissed, for the reasons that follow.
34. At the outset, we may note certain admitted facts; (a)
that a contract was entered into between the appellant-JV and
the respondent on 21
st
February, 2011, for the period of 36
months w.e.f. 7
th
March, 2011, i.e., till 6
th
March, 2014; (b) 2026:MLHC:85-DB
Page 37 of 52
that the contract amount was ₹1303.83 crore; (c) that the
contract period was extended from time to time; (d) that the
appellant-JV completed the work on 15
th
December, 2017;
and (e) that the final completion certificate was issued on 13
th
March, 2018. It appears that during the extension granted to
complete the contract, the comprehensive contract value was
revised from ₹1303.83 crores to ₹2406.46 crores. It is also not
disputed that there were two proceedings initiated by the
appellant-JV, i.e., DRB-I and DRB-II, and that arbitration
proceeding were also initiated by the appellant-JV and the
respondent.
35. It is also not in dispute that in the arbitration
proceeding, the appellant-JV had submitted statement of
claims, i.e., ledger accounts in support of its claim. The
ledgers concerned Claim-II. It is this ledger account, which
has been relied upon by the respondent to issue show cause
notice to the appellant-JV. The statement of claim dated 30
th
May, 2019, filed by the appellant-JV before the Arbitral 2026:MLHC:85-DB
Page 38 of 52
Tribunal, alongwith the ledger account under the head of
‘business promotion account ’, reflects payment s of
cash/expenditure/cheque payments made to various
officials/authorities. The statement of claim under the head of
‘business promotion account’ shows the following ledger
entries;
“13.1 Cash being paid for purchase of gift
items for Govt. officials;
13.2 Cash being paid for tour from Shillong to
Guwahati to-fro charges (for IOCL officials) and
sweets- for seeking extension of time in clearing
dues.
13.3 Cash being paid for gift articles purchased
and given to local administrators (watch from
HELOIS-Titan Company);
13.4 Cash being paid at Hotel Polo Towers for
celebration of Engineers Day of PWD Department
Staff as per instruction of Higher Management;
13.5 Cash being paid towards purchase of W.
Bottles (B Dog) 3nos@ 1600/- for officials;
13.6 Cash being paid towards amount at
Bamboo Hut Restaurant for farewell party with
PWD Staff;
13.7 Cash being paid towards expenses at City
Hut Family Dhaba for Govt. officials;
2026:MLHC:85-DB
Page 39 of 52
13.8 Cash being paid for purchase of Whisky
Bottles for officials;
13.9 Expenditure in favour of Highland Studio
against purchase of gift (Samsung Tab) items for
officials in the Christmas Festival;
13.10 Expenditure incurred in favour of MX Tech
against purchase of gift items (Samsung Galaxy
Core 2 Prime) for officials in the event of
Christmas Festival);
13.11 Cash being paid towards purchase of Titan
Watch 3 Nos from Meghatraders for officials;
13.12 Cash being paid towards purchase of
Whisky Bottles towards Govt. officials;
13.13 Expenditure incurred for purchase of gift
items for event of New Year 2015;
13.14 Cash being paid for purchase of sweets for
IOCL officials;
13.15 Cheque of Rs 5,00,000/ - paid to
NONGKHNUM WE CARE SOCIETY as per
instructions of Higer Management;
13.16 Cash being paid towards purchase of gift
items for officials of local administration purpose;
13.17 Cash being paid for purchase of Samsung
Mobile Phone 1 nos for official purpose.”
36. It is submitted on behalf of the appellant -JV that
reliance placed on these ledger entries in the impugned show 2026:MLHC:85-DB
Page 40 of 52
cause notice or the order blacklisting the appellant-JV is
misconceived inasmuch as, it does not show what was the
thing, its value and how it influenced the officials, in the
execution of the contract. It is further submitted that there is
no name of any public official mentioned but only designation
and that the show cause notice, which places reliance on the
ledger entries, does not in any way show quid pro quo by any
government official to the appellant-JV. It is further submitted
by the learned Senior Counsel for the appellant-JV that at the
highest, it can be said that it was a goodwill gesture by the
appellant-JV to the bureaucracy but does not show that the
appellant-JV got anything in return or that there was any quid
pro quo.
37. In this context, at this stage, it would be relevant to
reproduce Clause 37 of the ‘Instruction to bidders’ and 59.2(h)
of the General Conditions of Contract, respectively.
“37. Corrupt or Fraudulent Practice
37.1 The employer will reject a proposal for award if it
determines that the bidder for award has engaged in 2026:MLHC:85-DB
Page 41 of 52
corrupt or fraudulent practices is competing for the
contract in question will declare the form in eligible, either
indefinitely or for a stated period of time, to be awarded a
contract with National Highway Authority of India/State
P.W.D. and any other agencies, if at any time determines
that the firm has engaged in corrupt or fraudulent
practices in competing for the contractor, or in execution.
59. Termination
59.1. The Employer or the Contractor may terminate the
other party causes a fundamental breach of the Contract.
59.2. Fundamental breaches of Contract include, but shall
not be limited to the following:
a) the Contractor stops work for 28 days when no
stoppage of work is shown on the current Programme
and the stoppage has not been authorized by the
Engineer;
b) The Engineer instructs the Contractor to delay the
progress of the works and the instruction is not
withdrawn within 28 days;
c) The Employer or the Contractor is made bankrupt
or goes into liquidation other than for a reconstruction
or amalgamation;
h) If the Contractor, in the judgment of the
Employer has engaged in corrupt or fraudulent
practices in competing for or executing the
contract.
For the purpose of this paragraph: “corrupt practice”
means the offering, giving, receiving or soliciting of
anything of value to influence the action of a public 2026:MLHC:85-DB
Page 42 of 52
official in procurement process or in contract
execution.
Fundamental practice “means misrepresentation of
facts in order to influence a procurement process or
the execution of a contract to the detriment of the
Borrower and includes collusive practice among
Bidders (prior to or after bid submission) designed to
establish bid prices at artificial non-competitive levels
and to deprive the Borrower of the benefits of free
and open competition.
The above said act of corrupt practice in
execution of the project are duly covered under
the heading “fraudulent practice” and moreover
the employer has a right even independent of
contract to initiate blacklisting/debarment
procedure for indulging in corrupt and
fraudulent practices.”
(emphasis supplied)
38. It is pertinent to note, that Clause 37 applies not only at
the time of completion of the contract, but also in its
execution. According to the respondent, the facts reveal
corrupt practice by the appellant-JV, during the execution of
the contract. Clause 59.2(h) as reproduced hereinabove spells
out the scope of what is ‘corrupt practice’. The said Clause
59.2(h) reveals that there is a power vested in the respondent
to take appropriate action, even though it was concluded 2026:MLHC:85-DB
Page 43 of 52
contract. Clause 59.2(h) also reveals, that the respondent, in
addition, even in the absence of the said provision in the
contract, had an inherent power to blacklist/debar the
appellant-JV, for indulging in corrupt and fraudulent
practices.
39. The Apex Court in Kulja Industries Limited v. Chief
General Manager Telecom Project B harat Sanchar Nigam
Limited & ors: (2014) 14 SCC 731 has in para 17 held as
under:
“17. That apart, the power to blacklist a contractor
whether the contract be for supply of material or
equipment or for the execution of any other work
whatsoever is in our opinion inherent in the party allotting
the contract. There is no need for any such power being
specifically conferred by statute or reserved by contractor.
That is because "blacklisting" simply signifies a business
decision by which the party affected by the breach decides
not to enter into any contractual relationship with the
party committing the breach. Between two private parties
the right to take any such decision is absolute and
untrammelled by any constraints whatsoever. The
freedom to contract or not to contract is unqualified in the
case of private parties. But any such decision is subject to
judicial review when the same is taken by the State or any
of its instrumentalities. This implies that any such decision
will be open to scrutiny not only on the touchstone of the 2026:MLHC:85-DB
Page 44 of 52
principles of natural justice but also on the doctrine of
proportionality. A fair hearing to the party being
blacklisted thus becomes an essential precondition for a
proper exercise of the power and a valid order of
blacklisting made pursuant thereto. The order itself being
reasonable, fair and proportionate to the gravity of the
offence is similarly examinable by a writ court.”
40. As noted earlier in the ‘business promotion account’,
i.e., ledger account, the details of expenses have been
mentioned i.e., expenses incurred for purchasing alcohol,
personal gifts etc. for government officials. The said business
promotion account/ledger account has been filed with the
statement of claim and admittedly, has not been denied by the
appellant-JV. Eg. entry dated 31
st
December, 2015, shows
purchase of HP laptop for PWD, Junior Engineer; entry dated
18
th
June, 2015, cash paid to Mr. K. Chakradhar towards
purchase of gift items (family watch set 1 No.) for government
official purpose; amounts spent for costly gifts such as
mobiles, cameras; entries regarding monthly payments to the
police station; donation of ₹4 lakhs made to the Police Officers
Wives Association, donation of ₹5 lakhs made to Nongkhnum 2026:MLHC:85-DB
Page 45 of 52
We Care Society and so on; entries of gifts to officers of Public
Works Department, to MoRTH officers, DRB members etc.
41. It is pertinent to note that based on the aforesaid ledger
entries, which were submitted with the statement of claim
dated 30
th
May, 2019, the respondent had issued the
impugned show cause notice dated 16
th
September, 2024.
Admittedly, the appellant-JV has not denied the said entries
given with the statement of claim. The explanation offered by
the appellant-JV is, that the same was not given as bribes,
and that some of the mon ies were given to charitable
organisations, and that the said entries do not in any way
reflect that the said amounts were given by way of corrupt
practice or bribe to any official; and that at the highest, one
can say that the statement of claim submitted by the
appellant-JV, with respect to the said entries was wrongfully
claimed and that the same could not have been claimed by the
appellant-JV, is clearly an afterthought.
2026:MLHC:85-DB
Page 46 of 52
42. Infact, a perusal of the show cause notice dated 16
th
September, 2024, would show that the same clearly sets out
the instances of alleged corrupt practice directly attributable
to the appellant-JV. It may be noted, that the appellant-JV in
its reply thereto dated 30
th
September, 2024 has not
specifically denied the entries but have explained the same as
expenses validity incurred and were not acts of alleged
bribery/corruption. Thus, despite opportunity being given,
appellant-JV failed to satisfactorily explain the allegations on
which blacklisting was proposed. In this context, it would be
apposite to reproduce para 2 of the judgment of the Apex
Court in Grosons Pharmaceuticals (P) Ltd. v. State of U.P.
& ors: (2001) 8 SCC 604, which reads thus:
“2. ..... It is true that an order blacklisting an approved
contractor results in civil consequences and in such a
situation in the absence of statutory rules, the only
requirement of law while passing such an order was to
observe the principle of audi alteram partem which is one
of the facet of the principles of natural justice. The
contention that it was incumbent upon the respondent to
have supplied the material on the basis of which the
charges against the appellant were based was not the
requirement of principle of audi alteram partem. It was 2026:MLHC:85-DB
Page 47 of 52
sufficient requirement of law that an opportunity of show
cause was given to the appellant before it was blacklisted.
It is not disputed that in the present case, the appellant
was given an opportunity to show cause and he did reply
to the show cause which was duly considered by the State
Government. We are, therefore, of the view that that the
procedure adopted by the respondent while blacklisting
the appellant was in conformity with the principles of
natural justice.”
43. It is also evident from the aforesaid clauses 37 and
59.2(h), that it was permissible for the respondent to blacklist
or debar the contractor even independent of the contract,
inasmuch as, the respondent had an inherent right to choose
with whom to do business with and to debar entities that
indulge in corrupt and fraudulent activities. The allegations in
the show cause notice pertain to the execution of the contract,
during the period 2015 to 2017.
44. Thus, from the aforesaid clauses, it is evident that the
respondent was well within its power to issue show cause
notice to the appellant-JV for backlisting and consequently, on 2026:MLHC:85-DB
Page 48 of 52
consideration of appellant-JV’s reply, to take appropriate
action for blacklisting the appellant-JV.
45. We may also note from a perusal of the show cause
notice, the reply of the appellant-JV and the impugned order
dated 3
rd
December, 2024, that the material relied upon for
issuance of show cause notice and subsequently, passing the
blacklisting order, was based on the admitted ledgers
produced by the appellant-JV and admitted to , by the
appellant-JV in the cross-examination before the Arbitral
Tribunal. The admitted entries, albeit sought to explain, form
the basis of illegal gratification to government officials. In
these circumstances, we do not find the action of the
respondent to be vitiated by mala fides or motivated. The State
is under an obligation to put public interest over everything
else. After all, the monies utilised is public money, which
cannot be lost sight of.
46. On the question of delay as vehemently argued by Mr.
Jethmalani, learned Senior Counsel for the appellant-JV, we 2026:MLHC:85-DB
Page 49 of 52
are of the opinion that in the facts, no delay was occasioned
warranting quashing of the order of blacklisting on the said
count. As noted above, the statement of claim was filed on
30
th
September, 2019, and that during the period from 25
th
April, 2022 to 9th May, 2022, the proceeding before the
Arbitral Tribunal was stayed. It is also evident that the cross-
examination of the appellant-JV commenced only on 11
th
July, 2022, after the stay was vacated, after which on 3
rd
September, 2024, a complaint was filed, pursuant to which
an FIR was registered at the behest of the respondent. The FIR
is based on the statement of claims/ledger accounts
submitted by the appellant-JV before the Arbitral Tribunal.
Post registration of the FIR, show cause notice dated 16
th
September, 2024 was issued to the appellant-JV. Hence, in
the facts, we do not find that the delay is such, warranting
quashing of the impugned order blacklisting the appellant-JV.
47. As far as the submission of Mr. Jethmalani, learned
Senior Counsel, that the show cause notice is vague and 2026:MLHC:85-DB
Page 50 of 52
devoid of particulars, we find no merit in the same. We find
that the show cause notice details the particulars, including
setting out the entries in the ledger account showing
payments made to the officials, and as such, the said show
cause notice cannot be quashed and set aside on the ground
of vagueness and being devoid of particulars. We also find that
principles of natural justice have been duly complied with and
that the impugned order blacklisting the appellant-JV has
been passed after considering the material on record and as
such, no interference is warranted in the same.
48. As far as the delay in registration of the FIR and the
non-inclusion of the Prevention of Corruption Act is
concerned, it is pertinent to note that the said FIR is under
investigation. The question, whether or not an offence is made
out will be considered by the Court in the petition filed by
some of the persons seeking quashing of the FIR, and as such
cannot be gone into in the present appeal.
2026:MLHC:85-DB
Page 51 of 52
49. As far as the findings/observations made by the
Tribunal and the High Court in their orders, both learned
Senior Counsel for the appellant-JV and the learned Advocate
General vehemently relied on the same, to point out the
damning observations so made by the Tribunal/Court. It
appears that the Arbitral Tribunal’s order has been challenged
under Section 34 of the Act, before the appropriate forum. Mr.
Jethmalani relied on certain observations and scathing
remarks made by the Tribunal/High Court against the
respondent, including imposition of costs on the respondent,
whereas, Mr. Kumar, learned Advocate General, also relied on
the damning observations made by the Arbitral Tribunal and
the High Court with respect to the ledger entries submitted by
the appellant-JV in the arbitration proceeding, to show how
the Tribunal and the High Court had dealt with the ledger
entries and had made scathing remarks against the appellant-
JV. As stated aforesaid, we will not go into the merits of the
same, since the question before us is, whether the show cause
notice and consequently, the blacklisting order suffers from 2026:MLHC:85-DB
Page 52 of 52
any infirmities and is bad in law; and whether the impugned
judgment and order passed by the learned Single Judge
suffers from any infirmities, warranting interference in the
same.
50. Suffice to state, that in the facts as stated above and
having regard to the judicial pronouncements, we find that no
interference is warranted either in the order dated 3
rd
December, 2024, blacklisting the appellant-JV or in the order
impugned dated 17
th
December, 2025, passed by the learned
Single Judge in WP (C) No.24 of 2025.
51. In terms of the aforesaid, the w rit appeal stands
dismissed.
(W. Diengdoh) (Revati Mohite Dere)
Judge Chief Justice
2026:MLHC:85-DB
In the landmark ruling of BSCPL Infrastructure Ltd. v. Public Works Department (Roads), the Meghalaya High Court addressed critical questions regarding Government Blacklisting and the boundaries of Judicial Review under Article 226 . This comprehensive analysis, now featured on CaseOn, explores how the judiciary balances administrative discretion with the principles of natural justice.
The core legal questions addressed by the Meghalaya High Court in this matter include:
Whether the State’s decision to blacklist the contractor for five years was legally sustainable and supported by adequate material?
Whether the show cause notice and the subsequent blacklisting complied with the principle of natural justice?
Whether alleged ledger entries indicating corrupt practices could justify such severe civil consequences?
The case clarifies a very important question: “Can a government authority lawfully blacklist a contractor for alleged corrupt practices, and to what extent can the High Court interfere with that decision under writ jurisdiction (Articles 226)?”
The court relied on the following legal frameworks and principles:
Principles of Natural Justice: Specifically regarding the adequacy of show-cause notices and procedural fairness.
Clause 59.2(h): A specific contractual provision conferring power on the respondent to take appropriate action against a party indulged in corrupt practices.
Doctrine of Proportionality: Assessing whether the five-year debarment was justified and in the larger public interest.
On 21 February 2011, the parties entered into a contract for the construction of two specific projects. In the said Joint venture agreement, M/s BSCPL (appellant) was the lead partner of the said agreement. The terms of the contract were that it had to be completed within 36 months or before 7 March 2014, but later it was extended to 31 December 2017. On 15 December 2017, the appellant completed the construction project.
During the period 2017-2018, disputes arose between the parties in terms of the execution of the work under the contract. Later, the appellant-JV sent a notice to the respondent informing of its claims in relation to non-payment of interest on delayed payments and non-reimbursement of labour cess. Consequently, DRB-I & DRB-II (Dispute Review Board) were constituted for the adjudication of the disputes for claims-I and II. On 13 March 2019, the nominee arbitrators of the appellant-JV and the respondent appointed the presiding arbitrator for the adjudication of both the claims allowed by DRBs.
During the arbitration, the appellant-JV submitted ledger entries under a ‘business promotion account’ and it was found that the appellant-JV had engaged in giving illegal gratification to government officials showing acts of corruption and bribery. The respondent then sent a show cause notice and, after considering the reply, blacklisted the appellant and its partners for five years.
Professional Note: Understanding complex evidentiary disputes is made easier with CaseOn’s 2-minute audio briefs, which help legal professionals quickly analyze the nuances of rulings like this one while on the go.
The Meghalaya High Court evaluated the following contentions:
| Appellant's Argument |
Respondent's Counterargument |
| The show cause notice was vague and bereft of vital particulars as it does not put the specific factual particulars, rendering it void and illegal. | The material relied upon for blacklisting was based on the ledger accounts produced by the opposite party which provide sufficient proof of illegal gratification. |
| The ledger entries have been admitted by the appellant-JV, although according to him, they were given as gifts and as goodwill gestures, and not as bribes. |
Clause 59.2(h) confers power on the respondent to take appropriate action against the party indulged in corrupt practices. It has submitted that payment of monies to government officials by way of expensive gifts, hotel arrangements, and donations clearly shows the intent to influence the contract. |
| The show cause notice and the blacklisting is with a malafide intent only to deny the legitimate financial dues arising out of an express contractual obligation. | The admitted ledger accounts reveal corrupt practices and the action of blacklisting is justified, proportionate, and in larger public interest. |
The Meghalaya High Court, exercising its jurisdiction under Article 226 of the Indian Constitution, upheld the State’s five-year blacklisting order against the appellant and dismissed the appeal. The Court carefully examined the precedents on Natural Justice and held that the show-cause notice satisfied principles of natural justice, the decision was supported by material on record, and no interference was warranted under writ jurisdiction.
This ruling in BSCPL Infrastructure Ltd .v. Public Works Department is significant because it consolidates and clarifies the legal principles governing blacklisting, administrative discretion, and judicial review in public contract matters.
For Practitioners: It functions as a strategic guide—clarifying how to draft or challenge show-cause notices, assess evidentiary sufficiency, and frame arguments within the confined scope of constitutional review.
Core Takeaway: It underscores that while the state possesses the authority to debar contractors in the larger public interest, such power must be exercised in conformity with natural justice and procedural fairness.
About the Author
Shreya Sharma is a B.Sc. LL.B. student at NLIU Bhopal. This analysis aims to simplify complex judicial pronouncements for the benefit of law students and young professionals. Curated by CaseOn Editorial Team.
Note: This case study is for educational purposes only and does not constitute legal advice.
Legal Notes
Add a Note....