As per case facts, Petitioner, a registered contractor, was awarded four road construction and five-year maintenance projects under the PMGSY Scheme. The petitioner completed both the construction and maintenance works ...
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.461 of 2023
======================================================
M/s Ghanshyam Lal through its partner Sanjeev Kumar Madhogaria, Aged
about- 43 years, Gender- Male, Son of Ghanshyam Lal Madhogaria, Resident
of Simrahi Bazar, P.S.- Raghopur, District- Supaul.
... ... Petitioner/s
Versus
1.The State of Bihar through the Chief Secretary, Government of Bihar, Old
Secretariat, Patna.
2.The Secretary, Rural Works Department, Visheshwaraiya Bhawan, Bailey
Road, Patna.
3.The Additional Chief Executive Officer-cum- Secretary, Bihar, Rural Road,
Bihar, Patna.
4.The Engineer-in- Chief, Rural Works Department, Visheshwaraiya Bhawan,
Bailey Road, Patna.
5.The Chief Engineer-2, Rural Works Department, Visheshwaraiya Bhawan,
Bailey Road, Patna.
6.The Superintending Engineer, Rural Works Department, Works Circle,
Madhepura.
7.The Executive Engineer, Rural Works Department, Works Division, Birpur.
... ... Respondent/s
======================================================
Appearance :
For the Petitioner/s: Mr. Lal Babu Singh, Advocate
For the Respondent/s: Mr. Kumar Alok ( SC 7 )
======================================================
CORAM: HONOURABLE JUSTICE SMT. G. ANUPAMA CHAKRAVARTHY
ORAL JUDGMENT
Date : 24-07-2026
1. The petitioner has filed the instant
application for the following reliefs:
“(i) For a direction to the
Respondents to make payment of
admitted dues to the petitioner for
maintenance works under PMGSY
Scheme in connection with: - (a)
Package No. BR-35R021; from Shiv
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
2/17
Nagar to Kataiya Road, (b) Package No.
BR-35R-028; from Chhitahi Kanal to
Gopalpur Road (19th KM Koshi Bandhi),
(c) Package No.BR-35R-033, from
Shreepur to Mansapur Road and (d)
Package No. BR-35R-035; from
Souranjan to Thalha Road.
(ii) For a further direction to
the Respondents to pay interest at
Commercial rate to the petitioner on
illegal withholding of admitted dues for
the maintenance works completed by
the petitioner.
(iii) For a declaration that
the action of the respondents of
withholding of admitted dues amounts
to unjust enrichment.
(iv) For any other relief(s) or
consequential relief(s) to which the
petitioner may be found entitled to in
the facts and circumstances of this
case."
2. The brief facts culled out of the Writ
petition is that the petitioner is a partnership firm
represented through its partner, Shri Sanjeev
Kumar Madhogaria. The petitioner is a registered
contractor in the respondent department and is
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
3/17
engaged in carrying out construction and
maintenance works under the respondent
department and other works departments in the
State of Bihar.
3. The respondent department issued
Notice Inviting Tender for construction and
maintenance of four road projects, namely,
Package Nos. BR-35R-021, BR-35R-028, BR-35R-
033 and BR-35R-035. The petitioner participated in
the tender process and, being the lowest and most
responsive bidder, was awarded all the four works.
Consequently, agreements were executed between
the parties.
4. Each agreement comprised two
components, namely, execution of the construction
work and maintenance of the road for a period of
five years. The petitioner completed the
construction work, in accordance with the terms of
the agreements and there was no complaint
whatsoever regarding the quality or quantity of the
work executed. Thereafter, the petitioner also
carried out the maintenance work during the
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
4/17
stipulated period and completed the same to the
satisfaction of the respondent authorities.
5. It is the case of the petitioner that
although the maintenance work was duly
completed, verified through site inspection and
found satisfactory by the departmental authorities,
the payment towards the maintenance work has
not been released. According to the petitioner, the
respondents have admitted the dues payable
towards the maintenance work, but have withheld
payment solely on the ground of non-allotment of
funds by the Government.
6. It has further been pleaded that,
after the creation of the Birpur Works Division, the
four works in question were transferred from the
Works Division, Supaul to the newly constituted
Works Division, Birpur. The Executive Engineer of
the Birpur Division addressed communications
dated 09.06.2018 and 08.10.2020 to the
Government requesting for allotment of funds
towards payment of maintenance works under the
PMGSY Scheme, wherein the petitioner's works
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
5/17
were specifically included in the requisition.
Despite of repeated requests made by the
petitioner and the recommendations of the
departmental authorities, no payment has been
released till date.
7. According to the petitioner, the
amount claimed is an admitted contractual liability
and the continued withholding of payment has
caused him substantial financial hardship. It is the
petitioner's case that non-payment of the admitted
dues is arbitrary, unreasonable and amounts to
unjust enrichment on the part of the respondents
and violates the petitioner's legal and
constitutional rights. Having no other efficacious
alternative remedy, the petitioner has preferred
the present Writ petition.
8. The Learned counsel for the
petitioner submits that there is no dispute with
regard to the execution and completion of the
maintenance work. The respondents themselves
have verified the work through site inspection,
found it satisfactory and admitted the petitioner's
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
6/17
entitlement to payment.
9. It is submitted that the only reason
assigned by the respondents for withholding
payment is non-allotment of funds by the
Government. Learned counsel for the petitioner
contends that paucity of funds cannot be a valid
ground to deny payment for work duly executed,
accepted and certified by the department.
10. It is further submitted that the
Executive Engineer, on more than one occasion,
requested the Government to allot maintenance
funds and specifically included the petitioner's
claims in the requisition, which clearly establishes
that the respondents have acknowledged the
liability.
11. The Learned counsel further
submits that once the work has been completed,
accepted and the liability has been admitted, the
respondents are under a legal obligation to release
the admitted dues within a reasonable time. The
continued non-payment is arbitrary, unreasonable
and violative of Article 14 of the Constitution of
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
7/17
India and also amounts to unjust enrichment, as
the respondents have enjoyed the benefit of the
work without making payment.
12. Accordingly, it is prayed that this
Court may direct the respondents to release the
admitted amount payable towards the
maintenance work under the four agreements
along with all consequential benefits and such
other reliefs as may be deemed fit and proper in
the facts and circumstances of the case.
13. A counter affidavit was filed on
behalf of the respondents. The Learned counsel
appearing for the respondents, while relying upon
the counter affidavit filed on behalf of the
Executive Engineer, submits that the petitioner
was awarded the four road projects under the
PMGSY Scheme pursuant to a valid tender process
and the agreement were duly executed between
the parties.
14. It is contended that the
construction works were completed and the
maintenance period commenced from the
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
8/17
respective dates of physical completion of the
works. According to the respondents, under
Clauses 38.2 and 39.4 of the Standard Bidding
Document (PMGSY), payment towards
maintenance work is required to be made on the
basis of monthly bills submitted by the contractor
and after certification of satisfactory maintenance
by the Engineer.
15. The Learned counsel for the
respondents further contended that although
requisitions for allotment of maintenance funds
were sent to the Government by the Executive
Engineer vide letters dated 09.06.2018 and
08.10.2020, it was subsequently noticed that the
entries relating to the maintenance work had been
made in the Measurement Book in a consolidated
manner at the end of the five-year maintenance
period instead of being recorded periodically in
accordance with the contractual provisions.
16. It is contended that, in view of the
aforesaid irregularity, the competent authority
initiated a preliminary enquiry and show-cause
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
9/17
notices were issued to the concerned officers to
ascertain whether the maintenance work had been
carried out in accordance with the agreement and
whether the entries made in the Measurement
Book were genuine and in conformity with the
prescribed procedure.
17. The Learned counsel for
respondents contends that the claim of the
petitioner is presently under examination by the
department and, if upon verification the claim is
found to be genuine and admissible, the payment
shall be released in accordance with law. It is,
therefore, submitted that as the verification
process is still continuing and the liability has not
yet attained finality, the petitioner cannot claim
that there are admitted dues payable by the
respondents.
18. A rejoinder to the counter affidavit
was filed on behalf of the petitioner. In reply, the
Learned counsel for the petitioner submits that the
stand taken by the respondents in the counter
affidavit, in fact, fortifies the case of the petitioner.
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
10/17
It is submitted that the respondents have
categorically admitted that the petitioner was
awarded the works, completed the construction as
well as the maintenance work and that requisitions
were forwarded by the Executive Engineer to the
higher authorities for allotment of funds towards
payment of the maintenance dues.
19. The Learned counsel for the
petitioner contends that there is no allegation
whatsoever regarding the quality or quantity of the
maintenance work executed by the petitioner. On
the contrary, the work stood verified by the
departmental authorities and the respondents
themselves treated the petitioner's claim as
payable by forwarding requisitions for release of
funds. It is, therefore, contended that the liability
of the respondents stood admitted and the only
reason assigned earlier for non-payment was non-
allotment of funds.
20. It is further contended that the plea
now sought to be raised regarding alleged
irregularities in the entries made in the
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
11/17
Measurement Book is wholly misconceived and is
an afterthought. According to the petitioner, the
Measurement Book is prepared and maintained by
the departmental officers and the petitioner has no
control over the manner in which entries are
recorded therein. Even assuming that there was
any procedural irregularity in the Measurement
Book, the same cannot be attributed to the
petitioner nor can it defeat the petitioner's claim
for payment of work admittedly executed and
accepted by the department.
21. The Learned counsel for the
petitioner also contends that the maintenance
period expired in the years 2016 and 2017 and the
respondents, after having admitted the petitioner's
entitlement and sought allotment of funds, cannot,
after several years, withhold payment on the
pretext of a departmental enquiry. Such a stand is
arbitrary and cannot deprive the petitioner of the
admitted contractual dues.
22. It is lastly submitted that the
respondents have enjoyed the benefit of the work
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
12/17
executed by the petitioner without making
payment for nearly eight years. The continued
withholding of the admitted dues is wholly
unjustified, amounts to unjust enrichment and has
caused serious financial hardship to the petitioner.
It is, therefore, prayed that the respondents be
directed to release the admitted dues together
with appropriate interest within a time to be fixed
by this Court.
23. Heard the Learned counsel for the
petitioner as well as the Learned counsel for the
respondents.
24. Upon consideration of the rival
submissions and the material available on record,
this Court finds that there is no dispute with regard
to the fact that the petitioner was awarded the
works in question, completed the construction
work and thereafter carried out the maintenance
work in terms of the agreements. The respondents
have also not alleged any deficiency with regard to
the quality or quantity of the maintenance work
executed by the petitioner.
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
13/17
25. What assumes significance is the
categorical stand taken by the respondents in
paragraph 14 of the counter affidavit, wherein it
has been admitted that the Executive Engineer,
Rural Works Department, Works Division, Birpur,
vide Letter No. 781 dated 09.06.2018 and
thereafter by reminder vide Letter No. 1270 dated
08.10.2020, forwarded requisitions to the higher
authorities seeking allotment of funds for payment
of the maintenance works. The said letters
correspond to Annexure-3 and Annexure-4 to the
Writ petition and have also been brought on record
by the respondents as Annexure C-1 and Annexure
C-2 to the counter affidavit. The aforesaid conduct
of the respondents clearly establishes that the
petitioner's claim towards maintenance charges
had already been scrutinized by the department
and the liability to make payment was duly
acknowledged by the competent authority. Had
there been any dispute regarding execution of the
maintenance work or the petitioner's entitlement,
there would have been no occasion for the
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
14/17
Executive Engineer to forward requisitions
recommending allotment of funds for payment of
the petitioner's dues.
26. The subsequent plea taken by the
respondents regarding alleged irregularities in the
entries made in the Measurement Book and the
pendency of a departmental enquiry cannot, in the
facts of the present case, defeat the petitioner's
legitimate claim. The Measurement Book is a
departmental record maintained by the officials of
the respondents, and any procedural lapse or
irregularity therein cannot be made a ground to
deny payment for work which has already been
executed, verified and accepted by the
department. An internal administrative or
procedural issue within the department cannot
prejudice the rights of a contractor whose work
stands accepted and whose entitlement has
already been recognized by the department itself.
27. This Court is, therefore, of the
considered view that the petitioner cannot be
denied payment of the admitted contractual dues
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
15/17
on account of any internal or technical issue in the
functioning of the respondent department. The
obligation to make payment for the maintenance
work duly executed by the petitioner rests squarely
upon the respondent authorities.
28. Once the respondents themselves
had acknowledged the petitioner's entitlement by
forwarding requisitions for allotment of funds,
there remained no justifiable reason to withhold
the payment for such a prolonged period that too
for 8 long years. The continued non-payment of
the admitted dues is arbitrary, unreasonable and
wholly unjustified.
29. Accordingly, the present Writ
petition deserves to be allowed. The respondent
Executive Engineer, Rural Works Department,
Works Division, Birpur, is directed to take all
consequential steps and ensure release of the
admitted dues payable to the petitioner towards
the maintenance works executed under the PMGSY
Scheme in connection with (i) Package No. BR-35R-
021, from Shiv Nagar to Kataiya Road; (ii) Package
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
16/17
No. BR-35R-028, from Chhitahi Kanal to Gopalpur
Road (19th KM Koshi Bandhi); (iii) Package No. BR-
35R-033, from Shreepur to Mansapur Road; and
(iv) Package No. BR-35R-035, from Souranjan to
Thalha Road, as reflected in the requisitions
forwarded vide Letter No. 781 dated 09.06.2018
and Letter No. 1270 dated 08.10.2020, which form
Annexure-3 and Annexure-4 to the Writ petition
and Annexure C-1 and Annexure C-2 to the counter
affidavit, respectively.
30. The aforesaid exercise shall be
completed and the admitted amount payable to
the petitioner shall be released within a period of
two months from the date of receipt/production of
a copy of this order. In the event any further
administrative approval or allotment of funds is
required, the respondent Executive Engineer shall
immediately pursue the matter with the competent
authority so as to ensure compliance with the
directions contained in this order within the
stipulated period.
31. With the aforesaid observations,
Patna High Court CWJC No.461 of 2023 dt.24-07-2026
17/17
the writ petition stands allowed.
32. Interlocutory Application, if any,
shall stands disposed of.
Spd/-
(G. Anupama Chakravarthy, J)
AFR/NAFR NAFR
CAV DATE NA
Uploading Date 24.07.2026
Transmission Date
Legal Notes
Add a Note....