As per case facts, the Petitioner, a construction company, was awarded a railway work. An Original Application was filed before the NGT alleging illegal extraction of minor minerals from Government ...
Page 1
IN THE HIGH COURT OF ORISSA AT CUTTACK
W.P.(C) No.18697 of 2025
(In the matter of a petition under Articles 226 and 227 of the
Constitution of India, 1950).
M/S. Shanti Construction
Sambalpur Pvt. Ltd., Sambalpur
…. Petitioner(s)
-versus-
State of Odisha and Ors. …. Opposite Party (s)
Advocates appeared in the case throughHybrid Mode:
For Petitioner(s) : Mr. S.S. Padhy, Adv.
For Opposite Party (s) : Mr. Sonak Mishra, ASC
Mr. Shanti Prapaksh Mohanty, Adv.
CORAM:
DR. JUSTICE SANJEEB K PANIGRAHI
DATE OF HEARING:-09.01.2026
DATE OF JUDGMENT:-22.01.2026
Dr. Sanjeeb K Panigrahi, J.
1. In this Writ Petition, the petitioner seeks a direction from this Court to
quash the order dated 02.05.2025 passed by the National Green Tribunal,
Eastern Zone, Kolkata in O.A. No. 167/2023/EZ, and to restrain the
respondents from taking any coercive steps for recovery of
environmental compensation pursuant thereto.
I. FACTUAL MATRIX OF THE CASE:
2. The brief facts of the case are as follows:
(i) The petitioner is a company incorporated under the Companies Act and
is represented through its deponent, claiming residence within the
Page 2
territorial jurisdiction of the Orissa High Court and asserting that the
cause of action arose within such jurisdiction.
(ii) East Coast Railway, as Opposite Party No. 8, awarded the petitioner a
railway track laying work along with bridge work through Letter of
Acceptance dated 01.06.2022 followed by a formal contract agreement
dated 25.10.2022.
(iii) An Original Application being O.A. No. 167/2023/EZ was filed before the
National Green Tribunal, Eastern Zone Bench, Kolkata by certain persons
describing themselves as social workers and local villagers, alleging
illegal extraction of minor minerals such as earth and morrum by the
petitioner from Government land in Tangi-Choudwar Tahasil, District
Cuttack, for the railway work.
(iv) In the NGT proceedings, several public authorities including the State
Pollution Control Board, Collector Cuttack, Revenue Department and
Forest Department were arrayed as respondents on allegations of
inaction despite complaints.
(v) The NGT, by order dated 23.11.2023, constituted a Joint Committee
comprising senior scientist or officer of the State Pollution Control Board,
District Mining Officer Cuttack, Collector Cuttack or representative not
below ADM, and Divisional Forest Officer Cuttack, with the Board as the
nodal body for logistics and for filing the inspection report on affidavit,
and directions to recommend penalty, environmental compensation, and
remedial measures if violations were found.
(vi) Pursuant to the NGT order, the Committee visited the site on 18.12.2023
and noted excavation of morrum or laterite from alleged plots and
Page 3
surrounding areas, and also recorded that pits were water-filled, which
affected ascertainment of depth and quantification at that time.
(vii) The Committee requested the Mining Officer, being a member and
competent authority, to conduct a detailed scientific survey to assess the
actual quantity excavated from specified plots and surrounding areas,
and a report was thereafter prepared and filed before the NGT through
the Board’s affidavit.
(viii) The Joint Committee report recommended environmental compensation
and also compensation as per the Odisha Minor and Minerals
Compensation Rules, 2016, and the petitioner filed objections before the
NGT.
(ix) The NGT disposed of the Original Application by order dated 02.05.2025
directing the State respondents and the State Pollution Control Board,
Odisha to take action against the petitioner for recovery of environmental
compensation in accordance with law after giving full opportunity of
hearing, while stating it did not express any opinion on the merits of the
computation so as not to prejudice the petitioner’s defence before the
competent forum.
(x) After the NGT order dated 02.05.2025, the petitioner filed the present writ
petition before the High Court challenging that NGT order, while the
Pollution Control Board states that it had not yet taken steps to recover
the environmental compensation pursuant to the NGT directions.
II. SUBMISSIONS ON BEHALF OF THE PETITIONER:
3. Learned counsel for the Petitioner earnestly made the following
submissions in support of his contentions:
Page 4
(i) The impugned NGT order dated 02.05.2025 is alleged to violate
principles of natural justice because the petitioner claims it was not
issued notice of the Joint Committee site visit dated 18.12.2023 and the
inquiry was conducted behind its back, resulting in reliance on a report
procured without participation by the petitioner.
(ii) The NGT is alleged to have abdicated and outsourced its adjudicatory
function by mechanically following the Joint Committee report and
issuing directions based on committee findings rather than undertaking
independent adjudication on the objections and materials placed by the
petitioner.
(iii) The constitution of the Joint Committee is alleged to be vitiated by bias
because it comprised State authorities and regulatory bodies against
whom allegations of inaction were made in the Original Application,
attracting the principle nemo judex in causa sua and creating a conflict of
interest that undermines fairness and appearance of justice.
(iv) The petitioner challenges the NGT’s jurisdiction on the ground that
disputes relating to illegal extraction of minor minerals are governed by
the Mines and Minerals legal framework and the Odisha Minor Mineral
Concession Rules, 2016, and do not fall within the NGT’s statutory
jurisdiction confined to substantial questions relating to environment
arising out of enactments in Schedule I of the NGT Act, 2010.
(v) The petitioner contends the Joint Committee itself recorded that the site
was water-filled and quantification was not possible during the joint
visit, yet the inquiry was sub-delegated to the Mining Officer whose
independent report became the basis of the committee report, which is
Page 5
alleged to be improper and hit by the principle delegatus non
potestdelegare, and also raises transparency concerns.
(vi) The petitioner relies on MoEF and CC Notification S.O. 1224(E) dated
28.03.2020 inserting Item 6 of Appendix IX to the EIA Notification, 2006
to contend that prior environmental clearance is not required for
extraction or borrowing of ordinary earth for linear projects such as
roads, pipelines, and laying of railway lines, and asserts its activity falls
within this exemption.
(vii) The petitioner asserts it obtained necessary permissions from competent
authorities for execution of the railway project including utilisation of
earth, and claims it acted bona fide in reliance on statutory permissions
and railway authorisation for sourcing borrow material from specified
locations.
(viii) The petitioner contends the impugned order records no specific finding
of environmental damage, such as deforestation, pollution, or harm to
wildlife or habitats, and argues environmental compensation under the
Polluter Pays principle cannot be imposed merely for technical non-
compliance without demonstrated environmental harm or jurisdictional
facts.
(ix) The petitioner challenges the environmental compensation of Rs.
1,20,10,000 as arbitrary, disproportionate, and violative of Article 14, and
further argues that the CPCB methodology relied upon for assessing
environmental compensation does not cover the alleged acts in the
present case.
Page 6
III. SUBMISSIONS ON BEHALF OF THE OPPOSITE PARTIES:
4. The Learned Counsel for the Opposite Parties earnestly made the
following submissions in support of his contentions:
(i) The State Pollution Control Board contends the writ petition is premature
because, although the NGT directed recovery of environmental
compensation after giving the petitioner full opportunity of hearing, the
Board had not yet initiated any recovery steps when the petitioner
approached the High Court.
(ii) The Board contends the writ petition is not maintainable because the
NGT order is appealable under Section 22 of the NGT Act, 2010, and the
petitioner has an alternative statutory remedy which should be pursued
instead of invoking writ jurisdiction.
(iii) The Board contends the NGT passed the impugned order after
considering the expert committee report and after giving opportunity of
hearing to the petitioner, and the NGT expressly directed that recovery
be undertaken in accordance with law after giving full opportunity of
hearing, which safeguards due process at the stage of implementation.
(iv) The Board contends the MoEF and CC notification dated 28.03.2020
regarding exemption for ordinary earth is inapplicable because, on
inspection, the committee observed excavation of morrum or laterite, and
not merely ordinary earth, and the alleged activity involved extraction
without environmental clearance and without consent to establish and
consent to operate from the Board, which are stated to be mandatory
statutory requirements.
Page 7
(v) The Tahasildar, Tangi-Choudwar contends the writ petition is
misconceived and not maintainable and asserts that the NGT constituted
the committee by order dated 23.11.2023, the committee submitted its
report on 18.12.2023, and the report was filed before the NGT through an
affidavit of the Member Secretary of the Pollution Control Board on
09.02.2024.
(vi) The Tahasildar contends that during the committee visit, pits were found
and were water-filled, and therefore the Mining Officer was tasked to
conduct a detailed scientific survey to quantify extraction from specified
plots, and the allegation that this was improper is baseless.
(vii) The Tahasildar contends temporary permission had been granted to the
petitioner to lift and transport 2000 cum of ordinary earth or morrum
from specified plots subject to conditions, but during joint enquiry it was
found that the petitioner illegally lifted 1,00,000 cum from the scheduled
plots leading to imposition of penalty and royalty of Rs. 75,00,000, with
part deposit made and balance demanded.
(viii) The Tahasildar further contends that on subsequent inspection upon
public complaints, the petitioner was found to have illegally excavated
approximately 2,60,580 cum of ordinary earth or morrum from certain
plots recorded as jungle category land, and penalty and royalty
amounting to Rs. 1,60,71,320 was imposed on the petitioner’s firm
through a letter dated 10.07.2023, which remains unpaid.
(ix) The opposite parties contend, overall, that the petitioner engaged in
illegal mining or excavation beyond permissions and in violation of
Page 8
terms and conditions, and therefore the writ petition does not merit
consideration and is liable to be dismissed.
IV. JUDGMENT AND ANALYSIS :
5. Heard Learned Counsel for the parties and perused the documents
placed before this Court.
6. The writ petition challenges the NGT’s order of 02.05.2025 directing
recovery of environmental compensation without a hearing and on the
basis of a joint committee report. The main issues are the petition’s
maintainability despite the statutory right of appeal, and whether the
NGT committed jurisdictional error or violation of natural justice by
outsourcing adjudication to a committee and failing to hear the
petitioner.
7. The opposite parties contend that the petitioner must first appeal to the
Supreme Court under Section 22 of the NGT Act and that the writ is
premature. However, the availability of an alternate remedy does not
render a writ petition automatically non-maintainable. The Supreme
Court has consistently held that an alternative remedy is not an absolute
bar to relief under Article 226, especially where fundamental rights or
principles of natural justice are at stake or the order is wholly without
jurisdiction.
8. In fact, in the case of Whirlpool Corporation v. Registrar Trademarks,
Mumbai
1
, the Court emphasized that the High Court has discretion to
entertain a writ petition notwithstanding an alternate remedy, in at least
three contingencies: enforcement of fundamental rights, violation of
1
(1998) 8 SCC 1
Page 9
natural justice, or where the order is wholly without jurisdiction. The
Court held as follows:
“Under Article 226 of the Constitution, the High Court,
having regard to the facts of the case, has a discretion to
entertain or not to entertain a writ petition. But the High
Court has imposed upon itself certain restrictions one of
which is that if an effective and efficacious remedy is
available, the High Court would not normally exercise its
jurisdiction. But the alternative remedy has been
consistently held by this Court not to operate as a bar in at
least three contingencies, namely, where the writ petition
has been filed for the enforcement of any of the Fundamental
Rights or where there has been a violation of the principle of
natural justice or where the order or proceedings are wholly
without jurisdiction or the vires of an Act is challenged.
There is a plethora of case-law on this point but to cut down
this circle of forensic whirlpool, we would rely on some old
decisions of the evolutionary era of the constitutional law as
they still hold the field.”
9. These exceptions apply here. The petitioner raises serious allegations of
breach of natural justice and procedural infirmity by the NGT. In such
circumstances the High Court may exercise its writ jurisdiction even
though an appeal to the Supreme Court is theoretically available.
Accordingly, the writ petition is held maintainable and will be examined
on merits.
10. Although extraction of minor minerals is primarily governed by mining
laws, the environmental impact of such extraction falls squarely within
the NGT’s remit. The NGT is an expert tribunal vested with broad
powers to adjudicate substantial questions of environment law arising
under the statutes listed in Schedule I of the NGT Act. Here, the
Page 10
complaints allege large-scale illegal excavation from government land
causing environmental degradation. Such extraction can lead to pollution
of land and water and damage to the ecosystem, engaging the
Environment (Protection) Act and related statutes under Schedule I.
11. The judicial precedents have reaffirmed that NGT’s jurisdiction cannot be
unduly narrowed and it is to be treated as an expert adjudicatory body
on environmental issues. The Supreme Court in Kantha Vibhag Yuva
Koli Samaj Parivartan Trust v. State of Gujarat
2
noted that the NGT’s
powers include providing relief, restitution and compensation in
environmental matters. The relevant excerpts are produced below:
“16. Section 14 and Section 15 entrust adjudicatory
functions to the NGT. The NGT is a specialized body
comprising of judicial and expert members. Judicial
members bring to bear their experience in adjudicating
cases. On the other hand, expert members bring into the
decision-making process scientific knowledge on issues
concerning the environment…”
12. There is no merit in the contention that the NGT had no jurisdiction
simply because the extraction involved minor minerals. By causing soil
erosion and water pollution, illegal mining raises “substantial questions
relating to environment” within the meaning of Section 14(1) of the NGT
Act. Hence the NGT was competent to entertain the original application
and constitute the joint committee. Even so, the manner in which it
discharged that function is subject to review as discussed below.
13. The core grievance is that the petitioner was never given notice of the
joint committee’s site inspection (18.12.2023) or an opportunity to be
2
2022 SCC OnLine SC 120
Page 11
heard on the committee’s report, which led to directions for recovery of
compensation. This is a fundamental breach of natural justice. The
Supreme Court in the case of Grasim Industries Limited v. State of
Madhya Pradesh
3
in this regard, has held as follows:
“A tribunal is required to arrive at its decision by fully
considering the facts and circumstances of the case before it.
It cannot outsource an opinion and base its decision on such
an opinion. A reliance in this respect should be placed on the
judgment of this Court in Kantha Vibhag Yuva Koli Samaj
Parivartan Trust and Others v. State of Gujarat and
Others.”
14. The Court in the abovementioned case condemned an NGT order passed
entirely on a committee’s findings without hearing the concerned party.
It noted that the NGT’s procedure was totally unknown to the settled
principles of natural justice, observing that “neither was any notice given by
the Joint Committee before giving an adverse report against the appellant nor the
NGT permitted impleadment” of the appellant. The Court held that such an
approach “smacks of condemning a person unheard”. This decision was set
aside and remanded because the NGT erred in proceeding ex parte.
15. In this case, exactly the same error is made. The Joint Committee’s report
was relied on to recommend heavy compensation, yet the petitioner had
no opportunity to contest its findings. The petitioner was not impleaded
in the NGT proceedings, nor was it given notice of the joint inspection.
The NGT Order itself even notes that the pits were water-filled and the
committee could not ascertain the full extent at the time. Instead of
permitting the petitioner to be heard on these findings, the NGT
3
2024 INSC 926
Page 12
mechanically issued directions to recover compensation. This procedure
violates the rule of audi alteram partem. An adjudicatory tribunal must
give the affected person a chance to be heard before reaching a decision.
16. Linked to the above, it is impermissible for the NGT to abdicate its
judicial role by simply rubber-stamping the committee’s report. The
Supreme Court has repeatedly held that the core adjudicatory function of
the NGT is non-delegable. In Kantha Vibhag (Supra), the Court declared
that while expert committees may assist by fact-finding, the NGT itself
must adjudicate the issues. It set aside an NGT order that required parties
to approach technical committees for relief, noting that the tribunal had
abdicated its jurisdiction and entrusted judicial functions to an
administrative expert committee, which is unsustainable as adjudication
is not a delegable function.
17. The same principle was reiterated in Grasim (Supra) the NGT “cannot
outsource” the decision by basing its order solely on a committee report.
Here too, by directing recovery based on the joint committee without an
independent evaluation of the petitioner’s case, the NGT has effectively
delegated its judgment to the committee. This is contrary to Kantha and
Grasim. The NGT must review objections, apply its judicial mind and
render an order; it cannot abdicate that responsibility.
18. The petitioner also points out that the Joint Committee was constituted of
officials (State Pollution Control Board, District Mining Officer,
Collector/ADM, Divisional Forest Officer) who were themselves
respondents or alleged defaulting authorities in the original application.
This raises a potential conflict under the maxim nemo judex in causa sua.
Page 13
While no specific precedent is cited for committee composition, the
combined effect of no notice plus possible bias underscores the
unfairness. In any event, the Supreme Court’s rulings in Grasim (Supra)
and Kantha (Supra) render this moot: the NGT should not have relied on
such a committee’s findings without hearing the petitioner, regardless of
membership.
19. The petitioner invokes the MoEF&CC notification of 28.03.2020 (Item 6,
Appendix IX of the EIA Notification, 2006), which exempts extraction of
ordinary earth for linear projects (roads, railways, pipelines) from prior
environmental clearance. It is contended that its excavations fall within
this exemption and that it also obtained local permissions to source earth.
The respondents counter that the material excavated was laterite/morrum
(not mere “ordinary earth”) and that no valid consents or clearances
(CTE/CTO) were in place.
20. On this record, no environmental clearance was obtained for the mining
activity. Whether or not the exemption technically applies (which would
require scrutiny of the material and purpose), the petitioners’ failure to
obtain any clearances or consents is a statutory breach under the EPA
and Water Acts. However, the question of permits and exemptions is
primarily one of facts and merits for the competent forum. Crucially, the
NGT did not finally adjudicate those points, it merely directed
compensation. If this Court were to reach the exemption issue, it would
note that even if the MoEF notification excused prior EC, the absence of
prescribed consents would still render the extraction unauthorized. That
Page 14
said, given the NGT’s quashing on procedural grounds, these factual and
regulatory aspects need not be fully resolved here.
21. The petitioner argues that the compensation of ₹1,20,10,000 (as computed
by the State Board) is arbitrary and disproportionate, and that the CPCB
guidelines do not cover excavation of earth. Even if the petitioners had
illegally excavated, compensation under the “polluter pays” principle
must have a basis in law and a nexus to actual harm. The Supreme Court
has warned against using turnover or arbitrary formulas.
22. In Benzo Chem Industrial (P) Ltd. v. Arvind Mahajan
4
, the Court
invalidated an NGT penalty that bore no relation to the pollution,
holding that generation of revenue has no nexus with the amount of
penalty, and that the rule of law does not permit the State to extract a
pound of flesh. The relevant excerpt:
“In any case, the generation of revenue would have no
nexus with the amount of penalty to be ascertained for
environmental damages. It is further to be noted that the
learned NGT found the appellant to be guilty of violations,
the least that was expected from the NGT is to give a notice
to the appellant before imposing such a heavy penalty.”
23. The CPCB’s compensation guidelines are not binding law unless enacted
by Parliament. Here the NGT expressly refrained from endorsing the
computation, leaving details for “competent authority”. In short, any
calculation of damages must await an adversarial hearing.
V. CONCLUSION AND DIRECTION:
24. In sum, the Writ Petition discloses a clear case of procedural illegality.
The NGT’s order of 02.05.2025 is vitiated by breach of natural justice and
4
2024 SCC OnLine SC 3543
Page 15
by unlawful delegation of its judicial function to the joint committee
without affording the petitioner a hearing. The alternative remedy of
appeal does not preclude relief, since the order is tainted by fundamental
unfairness.
25. For the abovementioned reasons, the Writ Petition is allowed and the
impugned NGT order is quashed and set aside. The parties are left to
pursue their rights before the appropriate authority or forum consistent
with law, and the petitioner shall not be prejudiced in any manner
pending such proceedings.
26. Interim order, if any, passed earlier stands vacated.
(Dr. Sanjeeb K Panigrahi)
Judge
Orissa High Court, Cuttack,
Dated 22
nd
Jan., 2026/
Legal Notes
Add a Note....