As per case facts, the petitioner, M/s SK Electricals, secured a tender from RITES Ltd. for a construction project but claimed that multiple hindrances, attributable to the respondents, prevented the ...
2026:JHHC:26889-DB
1 | Page
IN THE HIGH COURT OF JHARKHAND AT RANCHI
W.P. (C) No. 2527 of 2026
---
M/s SK Electricals, a proprietorship firm, having its office at Bye
Pass Road, P.O. & P.S.-Daltonganj, Palamu, Jharkhand, represented
through its proprietor, Shri Santosh Kumar, S/o Pancham Saw, R/o
New Sahdeo Nagar, P.O. & P.S.-Hehal, Behind Colony of OTC
Ground, Ratu Pandra Road, near Chota Hanuman Mandir, P.O. &
P.S.-Hehal, District-Ranchi … … Petitioner
Versus
1. RITES Ltd., a Government of India enterprise and a company
registered under Companies Act, 1956, having its registered office
at SCOPE Minar, Laxmi Nagar, New Delhi, represented through its
Group General Manager (Civil) & PU-Head, ERPO, Kolkata, having
its office at Plot No. DJ/20, Action Area-1D, Street No. 326, New
Town, P.O. & P.S.-New Town, District-Kolkata
2. Group General Manager (Civil) & PU-Head, RITES Limited, ERPO,
Kolkata, Plot No. DJ/20, Action Area-1D, Street No. 326, P.O. & P.S.-
New Town, Kolkata
3. Neyveli Uttar Pradesh Power Limited (NUPPL), through its
Chairman, having its registered office at KH-419, G.N. Extension,
Gomti Nagar, P.O. & P.S.-Gomti Nagar, District-Lucknow (U.P.),
having its site office at near Village-Lahurimau-Kasimpur,
Ghatampur, Tehsil, P.O. & P.S.-Samuhi, District-Kanpur (U.P.)
…. .… Respondents
-----
CORAM: HON’BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE RAJESH SHANKAR
-----
For the Petitioner : Mr. Indrajit Sinha, Advocate
Mr. Vipul Poddar, Advocate
Mr. Pradyumna Poddar, Advocate
Ms. Sugandha Jaiswal Poddar, Advocate
For the Respondents: Mr. Srijit Choudhary, Advocate
Ms. Tanya Rai, Advocate
-----
Reserved on 31.08.2026 Pronounced on 07.09.2026
Per : Rajesh Shankar, J. :
1. The present writ petition has been filed making multiple prayers,
however, in course of argument, the learned counsel for the
petitioner confines the prayer to the following extent: -
f. For issuance of an appropriate writ(s), order(s) or
direction(s) for quashing and setting aside the order
contained in Serial No. RITES/PU -
2026:JHHC:26889-DB
2 | Page
KOL/OHE/NUPPL/2026/718 dated 22.04.2026 issued
under the signature of General Manager (Civil), PU
Head, Kolkata, whereby the respondent-department
has declared the petitioner as a 'Poor Performer' and
subsequently placed the petitioner in the 'Negative List
of Contractors'.
g. Upon quashing of the aforesaid order a further
writ(s), order(s) or direction(s) be issued declaring
that Clause 3(b) of the General Conditions of Contract
so far as it relates to declaration as Poor Performer
without giving appropriate opportunity of notice and
hearing is violative of the principles of natural justice
and thus is liable to struck down.
Submissions made by the learned counsel for the
petitioner:
2. Mr. Indrajit Sinha, the learned counsel appearing on behalf of the
petitioner submits that RITES Limited (respondent no.1) floated an
e-tender no. 09/OT/RITES/ERPO/PU -KOL/NUPPL-Kurwa/OHE-
General Electrical/2023 dated 31.10.2023 for the work-"Design,
Drawing, Supply, Erection, Testing & Commissioning of 25 KV OHE
system with SSP, Yard Illuminations & Electrification of Different
Buildings for Construction of new Railway Siding at NUPPL Dumka
Siding under Eastern Railway, Howrah Division for Pachwara South
Coal Block/ Neyveli Uttar Pradesh Power Limited (NUPPL) for
transportation of coal from Pachwara South Coal Block through
Indian Railway network." The said tender was issued by the
respondent no. 1 in the capacity of an agent/duly authorized
2026:JHHC:26889-DB
3 | Page
Power of Attorney Holder, acting for and on behalf of Neyveli Uttar
Pradesh Power Limited (NUPPL).
3. The petitioner participated in the said e- tender process and
emerged as the successful bidder. Thereafter, a Letter of
Acceptance dated 24.01.2024 was issued in its favour awarding
the work at a total contract price of Rs 6,40,10,551/- excluding
GST. Subsequently, Agreement No. RITES/PU - KOL/NUPPL-
OHE/RT760-00168/2024/637, dated 29.04.2024 was executed
between the petitioner and the respondent no. 1.
4. It is submitted that from the very inception of the work, the
petitioner was prevented from executing the contractual
obligations on account of multiple hindrances attributable to the
respondents due to which the execution of the work could not be
commenced and/or proceeded with as per the contractual
schedule.
5. The General Manager (Civil), PU Head, Kolkata (respondent no. 2)
issued letter no. RITES/PU-KOL/OHE/NUPPL/2026/293 dated
16.02.2026 under Clause 3(iii) of GCC whereby the petitioner was
directed to take necessary action to accelerate the progress of
work within seven days of issuance of the said letter, failing which
a recommendation was to be made to the competent authority for
determination of the contract. It was mentioned in the said letter
that the performance guarantee as well as the security deposit
would also be forfeited by the employer. It was further warned in
the said letter that in the event of determination of the contract,
the petitioner would be declared as ‘poor performer’ in terms with
2026:JHHC:26889-DB
4 | Page
Clause 3(a)(i) of the General Conditions of Contract (in short
‘GCC’).
6. The petitioner replied the said letter of the respondent no. 2,
however vide letter no. RITES/PU-KOL/OHE/NUPPL/ 2026/378
dated 25.02.2026, the respondent no. 2 again issued a similar
direction with warning as was given to the petitioner in the letter
dated 16.02.2026. The petitioner replied the said letter on this
occasion also denying all the allegations made against it.
7. Finally, vide letter dated 16.03.2026 issued by the respondent no.
2, the contract of the petitioner was terminated alleging, inter alia,
that there was no concrete planning on the part of the petitioner
for procurement of copper materials, which were vital for
completion of the project. It was further alleged that the
petitioner's communications did not reflect any firm commitment
for timely completion of the work as well as there was no
assurance regarding completion of SSP work and other electrical
general works. It was also alleged that the petitioner had declined
to undertake certain additional works relating to providing 11 KV
local power supply to the proposed siding. Consequently, the
performance guarantee amounting to Rs. 32,00,528/- and the
security deposit of Rs. 13,50,491.66/- were forfeited.
8. Subsequently, the respondent no. 2, vide letter no. RITES/PU-
KOL/OHE/NUPPL/ 2026/718 dated 22.04.2026, declared the
petitioner as a 'Poor Performer'. It was also placed in the 'Negative
List of Contractors' and was debarred from participating in any
further tender to be invited by the respondent no. 1 for a period of
2026:JHHC:26889-DB
5 | Page
two years i.e., from 22.04.2026 to 21.04.2028.
9. Learned counsel for the petitioner contends that the legal position
on the subject of blacklisting has been settled in the cases of
Erusian Equipment & Chemicals Ltd. Vs. State of W.B. &
Another reported in (1975) 1 SCC 70, UMC Technologies (P)
Ltd. Vs. Food Corpn. of India & Another reported in (2021) 2
SCC 551, Techno Prints Vs. Chhattisgarh Textbook
Corporation and Another reported in 2025 SCC OnLine SC
343 and A.K.G Construction and Developers Pvt. Ltd. Vs.
State of Jharkhand & others reported in 2026 SCC OnLine
SC 520. The ratio culled out from the aforesaid judgments is that
the blacklisting has the effect of preventing a person from entering
into lawful relationship with the government for the purposes of
gains and as such the authority is required to give a fair hearing to
the concerned contractor before passing an order of blacklisting
against it.
10. It is submitted that the notices dated 16.02.2026 and 25.02.2026
were issued under Clause 3(iii) of GCC by way of warning that
upon determination of contract, the petitioner would be declared
as a ‘Poor performer’ in terms of clause 3(a)(i) and not under
Clause 3(b) of the GCC. The said notices cannot be said to have
been issued proposing the punishment of debarment.
11. It is further submitted that every action of the State or its
instrumentality, in exercise of its executive power, must be
supported by reason. An action uninformed by reasons may be
questioned as arbitrary in a proceeding under Article 226 of the
2026:JHHC:26889-DB
6 | Page
Constitution.
12. It is also contended that Clause 3(b) of the GCC, to the extent it
contemplates deemed and automatic declaration of a contractor as
"poor performer" and consequent debarment for a period up to
two years as per Clause 52.7 of the GCC, which is inevitable
consequence after determination of the contract under Clause
3(a), is manifestly unreasonable and arbitrary being violative of
the principles of natural justice. The said clause operates
mechanically and without any application of mind as it neither
envisages an independent inquiry regarding conduct of the
contractor, nor provides any opportunity of hearing to it before
imputing the stigma of a "poor performer" and imposing a
punishment of debarment.
13. It is further argued that a contractor whose contract stands
determined, may have failed to proceed with the allotted work for
the reasons entirely beyond its control, or on account of a genuine
dispute with the employer, yet Clause 3(b) of GCC visits the
contractor with debarment as an automatic and inescapable
consequence, without distinction or discretion. Such a clause,
which conflates determination with debarment, strips the
contractor of any meaningful opportunity to demonstrate why the
graver consequence should not follow. It treats unequal situations
equally, which is contrary to the principles of natural justice being
violative of the fundamental right guaranteed under Article 14 of
the Constitution of India against arbitrary State action and is
contrary to the settled legal proposition.
2026:JHHC:26889-DB
7 | Page
14. It is also submitted that the respondents, being the
instrumentalities of the State, are bound to act fairly, reasonably,
and in a non-arbitrarily manner even in contractual matters. The
impugned termination has been issued in a mechanical manner,
ignoring the undisputed hindrances at the site and the petitioner's
repeated communications, thereby rendering the action arbitrary
and unconstitutional.
15. It is further submitted that mere alleged breach of contract should
not be a ground for blacklisting, rather for passing such an order,
the conduct of contractor must be so deviant or aberrant so as to
warrant a punitive measure of the said nature.
16. It is also urged that the petitioner was prevented from executing
the work due to non-availability of site, non-readiness of track
beds, absence of permissions, pending civil works and other
impediments attributable to the faults on the part of the
respondents for which the petitioner cannot be penalized.
Submissions on behalf of the respondents
17. Mr. Srijit Choudhary, Advocate, appearing on behalf of the
respondents at the outset submits that the present writ petition is
not maintainable in view of the fact that the petitioner has
expressly agreed under the contract that the city of jurisdiction of
Court would be “Kolkata” and as such it cannot now seek to invoke
the jurisdiction of this Court contrary to the agreed contractual
forum.
18. It is further submitted that the order declaring the petitioner as a
"Poor Performer” and placing it in the “Negative List of
2026:JHHC:26889-DB
8 | Page
Contractors” was not founded upon a solitary incident or an
unsubstantiated allegation, rather the respondents had issued
several notices to the petitioner with respect to its repeated acts of
breach of the contract. The petitioner kept on assuring the
respondents that the requisite materials would be procured and
supplied within the specified target dates, however despite
repeated assurances, the petitioner failed to procure and supply
the required copper materials within the contractual period. The
repeated failure to honour its own commitments constituted clear
and objective material suggesting that the petitioner had failed to
perform its contractual obligations. Thus, the respondents had
sufficient evidence before them to arrive at a conclusion that the
petitioner's performance was unsatisfactory and that it could not
be permitted to continue to deal with the respondents as a
contractor. Moreover, it had to face the consequences
contemplated under the contractual framework.
19. It is further submitted that the declaration of the petitioner as
‘Poor Performer’ was not an automatic consequence of
termination, rather before making such declaration, the
respondents considered the actual conduct and performance of the
petitioner, including its failure to arrange the essential materials
despite repeated assurances and opportunities. Thus, the present
case is significantly different from the judgments relied upon by
the petitioner where the contractors were automatically blacklisted
merely because their contracts were terminated without any
independent consideration of their conduct and without any
2026:JHHC:26889-DB
9 | Page
foundational facts.
20. It is also contended that the petitioner has placed much reliance
on the judgments of the Hon’ble Supreme Court rendered in the
cases of A.K.G Construction (Supra.) and UMC Technologies
(Supra.), however, the said judgments are not applicable in the
facts and circumstance of the present case. The correct
proposition emerging from the aforesaid judgments is that the
blacklisting must be supported by sufficient material, application of
mind and procedural fairness. In the present case, the
respondents were repeatedly confronted with the petitioner
defaults and had provided several opportunities to it to rectify the
same. The petitioner was also asked on numerous occasions to
demonstrate its ability to supply the requisite materials, including
copper, however, it failed to perform its contractual obligations
even after giving repeated assurances.
Finding of the Court:
Finding Qua Maintainability:
21. Respondents' have raised the issue of maintainability of the
present writ petition asserting that in view of Clause 46.17
mentioned under the heading “Clauses of Contract” in the Section
4 (Proforma of Schedules) of Part-1 (Technical Bid) relating to the
tender and contract document, the city of Jurisdiction of Court is
‘Kolkata’ and hence the said clause completely oust the jurisdiction
of this Court to hear the matter.
22. In support of the said contention, the learned counsel for the
respondents places reliance on the judgment of the Hon’ble
2026:JHHC:26889-DB
10 | Page
Supreme Court rendered in the case of M/s Swastik Gases (P)
Ltd. Vs. Indian Oil Corpn. Ltd. reported in (2013) 9 SCC 32.
In the said case, the question for consideration before the Hon’ble
Supreme Court was as to whether in view of Clause 18 of the
consignment agency agreement, the Calcutta High Court had the
exclusive jurisdiction in respect of the application made by the
appellant under Section 11 of the Arbitration and Conciliation Act,
1996. Moreover, though the appellant did not dispute that the
agreement was amenable to the jurisdiction of the Courts at
Kolkata, however, it claimed that part of the cause of action had
also arisen at Jaipur and, therefore, the Chief Justice of the
Rajasthan High Court or the designate Judge had the territorial
jurisdiction to consider the appellant’s application seeking
appointment of an arbitrator under Section 11. In the said case,
Their Lordships held that by having Clause 18 in the agreement,
the intention of the parties were clear and unambiguous that the
courts at Kolkata alone had the jurisdiction. It was further held
that to construe the jurisdiction clause like Clause 18 of the
agreement, the maxim expressio unius est exclusio alterius comes
into play which means that expression of one is the exclusion of
another. Where the contract agreement specifies the jurisdiction of
the courts at a particular place and such courts have the
jurisdiction to deal with the matter, an inference may be drawn
that parties intended to exclude all other courts.
23. We have also perused the judgment of the Hon’ble Supreme Court
rendered in the case of Indus Mobile Distribution (P) Ltd. v.
2026:JHHC:26889-DB
11 | Page
Datawind Innovations (P) Ltd. & Others reported in (2017)
7 SCC 678. In the said case, the question was as to whether,
when the seat of arbitration was at Mumbai, an exclusive
jurisdiction clause stating that the courts at Mumbai alone would
have jurisdiction in respect of the disputes arising under the
agreement, would oust all other courts including the High Court of
Delhi, whose judgment was appealed against. In the said case,
Their Lordships followed the judgment of M/S Swastik Gases
(P) Ltd. (Supra.) and other similar judgments holding that the
Mumbai Courts alone had the jurisdiction to the exclusion of all
other courts in the country, as the juridical seat of arbitration was
at Mumbai.
24. In both the aforesaid judgments, the matter was relating to fixing
of jurisdictional seat of arbitration by the parties under the Act,
1996 to one court excluding all other courts in the country. In the
said cases, there was no issue as to whether the parties to a
private contract can oust jurisdiction of the High Court under
Article 226 of the Constitution of India by a private agreement.
Thus, the facts and circumstances involved in the cases relied
upon by the learned counsel for the respondents is quite
distinguishable from the facts of the present case.
25. We have also perused the judgment of the Hon’ble Supreme Court
rendered in the case of Maharashtra Chess Association Vs.
Union of India & Others reported in (2020) 13 SCC 285 as
has been relied by the learned counsel for the petitioner. In the
said case, the issue was as to whether a private agreement
2026:JHHC:26889-DB
12 | Page
entered into between the appellant and the second respondent
(the All India Chess Federation) in the form of the constitution and
bye-laws of the latter, by conferring exclusive jurisdiction on the
courts at Chennai, can oust the writ jurisdiction of the Bombay
High Court under Article 226 of the Constitution.
26. In the said case, Their Lordships have held that there is a marked
distinction between the jurisdiction of a civil court and the writ
jurisdiction of a High Court under Article 226 of the Constitution of
India. The parties to a contract can agree to submit their disputes
to only one amongst several courts having jurisdiction so as to
exclude of all other courts, however, the contractual exclusion
clause cannot ipso facto exclude jurisdiction of a writ court. The
writ jurisdiction of the High Court is fundamentally discretionary
and even the existence of an alternate adequate remedy is merely
an additional factor to be taken into consideration by the High
Court in deciding whether or not to exercise its writ jurisdiction. In
exercising its discretion to entertain a particular case under Article
226, the High Court may take into consideration various factors
including the nature of injustice alleged by the petitioner, whether
or not an alternate remedy exists, or whether the facts raise a
question of constitutional interpretation. The High Court must take
a holistic view of the facts as presented in the writ petition and
make a determination on the facts and circumstances of each
unique case.
27. The Hon’ble Supreme Court has further held that the Bombay High
Court relied solely on Clause 21 of the constitution and bye-laws of
2026:JHHC:26889-DB
13 | Page
the All India Chess Federation to hold that its own writ jurisdiction
was ousted. The Bombay High Court however failed to examine
the case holistically and made a considered determination as to
whether or not it should, in its discretion, exercise its powers
under Article 226. The scrutiny to be applied by the High Court to
every writ petition under Article 226 of the Constitution is a crucial
safeguard of the rule of law. It is not open to a High Court to
abdicate this responsibility merely due to the existence of a
privately negotiated document ousting its jurisdiction.
28. Thus, it is no more res integra that jurisdiction of the High Court
under Article 226 of the Constitution of India cannot be taken
away by a private agreement between the parties to a contract. It
is upon the High Court itself to decide as to whether the facts and
circumstances of a particular case is fit one to exercise the
extraordinary writ jurisdiction.
29. In the present case, the place of work was at ‘Dumka’-a district in
the State of Jharkhand and as such the same is within the
territorial jurisdiction of this court. Even the alleged default has
been committed by the petitioner within the State of Jharkhand
and therefore major part of the cause of action qua the debarment
of the petitioner has arisen within the territorial jurisdiction of this
Court. Thus, it would not be in the interest of justice to relegate
the petitioner to the jurisdiction of a Court at ‘Kolkata’ that too
when the petitioner has confined its prayer with respect to
challenging the order dated 22.04.2026 whereby it has been
declared as a ‘Poor Performer’ and has been placed in the
2026:JHHC:26889-DB
14 | Page
‘Negative List of Contractors’ also debarring it for a period of two
years from 22.04.2026 to 21.04.2028 making it ineligible to
participate in future tenders of the respondent no. 1.
30. It is a well settled principle of law that the order of blacklisting
amounts to civil death of a contractor and as such the same is
amenable to judicial review on the touchstone of natural justice. In
the case of Techno Prints (Supra.), the Hon'ble Supreme Court
has observed that once a blacklisting order is passed, the
contractor is left with no other option but to take recourse before
the High Court invoking writ jurisdiction under Article 226 of the
Constitution. Thus, the writ court is the only forum where the
order of blacklisting can be challenged and therefore the petitioner
has no other alternative/efficacious remedy except filing of the
present writ petition.
31. Even otherwise, the respondents have challenged the
maintainability of the present writ petition by relying on the
printed terms and conditions of the contract wherein the city of
jurisdiction of court is mentioned as ‘Kolkata’. In the case of
Godrej Projects Development Ltd. Vs. Anil Karlekar &
Others; reported in (2025) 4 SCC 259 as has been relied upon
by the learned counsel for the petitioner, the Hon’ble Supreme
Court has held that keeping in view the principle enshrined in
Article 14 of the Constitution, the courts should not enforce an
unfair and unreasonable contract or any such clause in a contract
entered into between the parties who are not equal in bargaining
powers, rather the Courts should strike down such clause in a
2026:JHHC:26889-DB
15 | Page
contract. In the said case, Their Lordships have further referred
few illustrations regarding inequality of bargaining power and out
of those illustrations, one is that the aforesaid principle of equality
before law will apply where a person has no choice, or rather no
meaningful choice, but to give his assent to a contract or to sign
on the dotted lines in a prescribed or standard form or to accept a
set of rules as part of the contract, however unfair, unreasonable
and unconscionable a clause in that contract or form or rules may
be.
32. In the present case also, though, the said contract was signed by
the petitioner as well as the representative of the respondent no.1,
at the time of signing of the said contract, the bargaining powers
of the parties were not the same. The petitioner had no choice to
deny the said term of the contract or to demand for change of the
same. Thus, the petitioner was the weaker party in the said
contract. Under the said circumstance, the writ petition is not liable
to be dismissed merely on the ground that in the tender
document, the place of jurisdiction of the Court has been shown to
be at Kolkata.
33. For the reasons as aforesaid, the objection regarding
maintainability of the present writ petition raised by the learned
counsel for the respondents is not liable to be sustained and is
rejected.
Finding on the issue of declaring the petitioner as ‘poor
performer’ and placing it in the negative list of contractors
and thereby debarring it from participating in further
2026:JHHC:26889-DB
16 | Page
tender process to be floated by the respondent no. 1 for a
period of two years:
34. On perusal of the GCC, it is evident that one of the consequences
of determination of contract has been detailed under clause Cause
3(b) of GCC which provides that the contractor shall be deemed to
be declared a ‘Poor Performer’ as per Clause 52.7 of GCC and shall
not be eligible for a period up to two years, to participate in
tenders of other works which may be invited by the respondent
no. 1. Further, Clause 52.7 of GCC provides that the Engineer-in-
Chief without prejudice to the other rights against the contractor,
may declare the contractor to be a ‘poor performer’ after giving
him written notice of seven days in any of the following cases: -
“i. The contractor abandons the work for 30
days or more without valid reasons.
ii. Progress on the work is behind schedule
by 25% or more of the stipulated contract period
for reasons solely attributable to the contractor.
iii. Completion of work is delayed by 25% or
more of the stipulated contract period for reasons
solely attributable to the contractor.
iv. The contractor repeatedly (twice or more)
makes claims on frivolous grounds or goes to court
or seeks arbitration for such claims.
v. The contractor repeatedly (twice or more)
seeks extra-contractual financial support from
RITES for completing the work.
vi. If there are more than two instances of
financial failure of contractor in making timely
payments to his labour or sub-contractors or to
suppliers of materials.”
35. The said clause further provides that upon declaration of a
contractor as ‘poor performer’, his name will be placed in the
2026:JHHC:26889-DB
17 | Page
RITES ‘Negative List of Contractors’ and will not be eligible for a
period up to two years, to participate in tenders of other works
which may be invited by the RITES.
36. The learned counsel for the respondents puts much stress on the
notices dated 16.02.2026 and 25.02.2026 contending that the
petitioner was provided reasonable opportunity of hearing before
putting it in the ‘Negative List of Contractors’ and debarring it for a
period of two years from participating in the tenders of other
works of the respondent no. 1.
37. To appreciate the said contentions of the learned counsel for the
respondent no. 1, we have perused both the aforesaid letters
which were issued to the petitioner under Clause 3(iii) of GCC. In
the said letters, it was alleged against the petitioner that it had
failed to execute and complete the contract as per its commitment.
The petitioner was further advised to accelerate the progress of
work within seven days of issuance of the said notice, otherwise a
recommendation was to be made to the competent authority to
determine the contract and in such event, the bank guarantee as
well as security deposit were to be forfeited. In the said letters, it
was further mentioned that in the event of determination of
contract in terms with clause 3(iii) of contract, the petitioner would
also be declared a ‘poor performer’ as per clause 3(a)(i) of the
contract. In the said letters, it was however not specifically
mentioned that the petitioner would be put in the ‘Negative List of
the Contractors’ and would be debarred from participating in the
future tenders to be invited by the respondent no. 1 for a period
2026:JHHC:26889-DB
18 | Page
up to two years.
38. In the case of Erusian Equipment & Chemicals Ltd. (Supra.),
the Hon’ble Supreme Court has held that the order of blacklisting
involves civil consequences. It casts a slur. It creates a barrier
between the persons blacklisted and the Government in the matter
of transactions. The blacklists are “instruments of coercion”.
Blacklisting has the effect of preventing a person from the privilege
and advantage of entering into lawful relationship with the
Government for purposes of gains. Moreover, the fundamentals of
fair play require that the person concerned should be given an
opportunity to represent his case before he is put on the blacklist.
39. In the case of UMC Technologies (P) Ltd. (Supra.), the
Hon’ble Supreme Court has held that a person against whom any
action is sought to be taken or whose right or interests are being
affected, should be given a reasonable opportunity to defend
himself. The basic factor of the principles of natural justice is that
before an adjudication starts, the authority should issue notice to
the concerned party disclosing the precise reason for drawing the
proceeding against him so that he can defend himself. Such notice
should specifically and unambiguously mention the grounds
necessitating action and the proposed penalty/action. An order
travelling beyond the bounds of notice is impermissible and
without jurisdiction to that extent. It has further been held that in
the context of blacklisting of a person or an entity by the State or
its instrumentality, the requirement of a valid, particularised and
unambiguous show-cause notice is crucial particularly due to the
2026:JHHC:26889-DB
19 | Page
severe consequences of blacklisting and the stigmatisation that
accrues to the person/entity being blacklisted.
40. In the case of Techno Prints (Supra.), the ratio laid down in the
judgment of the Hon’ble Supreme Court rendered in the case of
Erusian Equipment & Chemicals Ltd. (Supra.) has been
followed holding that there have to be strong, independent and
overwhelming materials to resort to the power of blacklisting
which has the drastic consequences on a contractor. It has further
been held that the power to blacklist cannot be resorted to when
the grounds for the same are only breach or violation of the term
or condition of a particular contract and when legal redress is
available to both parties. If a contractor is to be visited with the
punitive measure of blacklisting on account of an allegation that it
has committed a breach of contract, the nature of its conduct must
be so deviant or aberrant so as to warrant such a punitive
measure.
41. In the case of A.K.G Construction and Developers Pvt. Ltd.
(Supra.), the Hon’ble Supreme Court has held that while
exercising judicial review over administrative actions of the State
or its instrumentalities in relation to contracts provisioning clauses
and rules relating to termination and/or blacklisting, the Courts
must apply distinct standards of legality, rationality and
proportionality. Such an approach is compelling since the
conditions for imposing such measures, as also the consequences
of such actions, have differing gravity. It has further been held that
the contractual conditions governing termination vis-à-vis those
2026:JHHC:26889-DB
20 | Page
relating to blacklisting are distinct and are to be exercised
independently. A decision of blacklisting is not automatic and
certainly not a logical consequence of a decision of termination.
Even after the department decides to terminate the contract, there
is still a choice of exercising the power of blacklisting. These
decisions operate in two dimensions - past and subsisting for
termination and future for blacklisting. In view of the serious
consequences, it is necessary for the department to issue a
specific notice proposing blacklisting of a contractor and call for an
explanation as to why an order of blacklisting should not be
passed.
42. In the present case, before putting the petitioner in the ‘Negative
List of Contractors’ and debarring it from participating in future
tenders of the respondent no. 1 for a period of two years, no
specific show cause notice was issued to it stating the grounds of
action and the proposed penalty/action, so as to afford an
opportunity to the petitioner to defend the same. Even in the order
dated 22.04.2026, no ground has been mentioned on which the
order of debarment of the petitioner from participating in future
tenders invited by the respondent no. 1, has been passed. It
merely discloses that the contract awarded to the petitioner has
been determined and it has been declared as ‘Poor Performer’ and
in view of the said reason, it has been placed in the ‘Negative List
of the Contractors’ as well as has been debarred from participating
in the future tenders of the respondent no. 1 for a period of two
years.
2026:JHHC:26889-DB
21 | Page
43. It transpires from the conduct of the respondents particularly the
respondent no. 2 that the order of debarment was passed
mechanically without any application of mind. Thus, the action of
the debarment was taken against the petitioner as an automatic
consequence of determination of the awarded contract. In the
case of Techno Prints (Supra.), it has been specifically held by
the Hon’ble Supreme Court that the order of debarment of a
contractor cannot be automatic after determination of contract on
the ground of failure to fulfill the terms and conditions of the
contract. The order of debarment or blacklisting cannot be passed
unless the conduct of the contractor is shown to be so deviant that
warrants punitive action.
44. Even if the petitioner may not have much to say regarding
termination of the contract, however this does not mean that it
has nothing to say against the action of debarment. An order of
debarment cannot be passed merely for violation of the terms and
conditions of the contract, unless it is found that the nature of the
conduct of the petitioner is so deviant or aberrant which warrants
the punitive measure.
45. Under the said circumstance, we are of the considered view that
the letters dated 16.02.2026 and 25.02.2026 on which much stress
has been given by the respondents, do not fulfill the requirement
of issuance of show cause notice for blacklisting. The said letters
merely contain warning to the petitioner for not expediting the
progress of work and those cannot to be said to be the show
cause notices in true sense.
2026:JHHC:26889-DB
22 | Page
46. For the reasons as aforesaid, the impugned letter dated
22.04.2026 to the extent of placing the petitioner in the ‘Negative
List of Contractors’ for a period of two years from 22.04.2026 to
21.04.2028 and debarring it from participating in the tenders to be
invited by the respondent no. 1 for the said period, is hereby
quashed and set aside.
47. So far as, the other actions of the respondents relating to the said
contract including that of the petitioner being declared as a ‘Poor
Performer’ is concerned, the same do not warrant interference by
this Court under its extraordinary writ jurisdiction. The petitioner is
however at liberty to challenge the same in accordance with law.
The respondents will also have the liberty, if so advised, to initiate
fresh proceeding for debarment against the petitioner and pass
appropriate order after following due process of law.
48. The writ petition is, accordingly, disposed of with the aforesaid
observations.
49. Pending interlocutory application, if any, also stands disposed
of.
(M.S. Sonak, C.J.)
(Rajesh Shankar, J.)
07.09.2026
Vikas/A.F.R.
Uploaded on 07.09.2026
In a significant decision, the Jharkhand High Court recently addressed the critical issues surrounding contractor blacklisting and the fundamental principles of natural justice. The ruling in M/s SK Electricals vs. RITES Ltd. & Ors., W.P. (C) No. 2527 of 2026, underscores the judiciary's role in safeguarding fair administrative action, even in contractual disputes. This judgment, detailing critical aspects of contractor blacklisting and natural justice principles, is now available on CaseOn, offering essential insights for legal professionals and students alike.
The petitioner, M/s SK Electricals, a proprietorship firm, successfully bid for a tender floated by RITES Ltd. (respondent no.1) as an agent for Neyveli Uttar Pradesh Power Limited (NUPPL). A contract was executed for the design, drawing, supply, erection, testing, and commissioning of an OHE system for a new railway siding. However, the petitioner contended that hindrances attributable to the respondents prevented the commencement and progress of work.
Subsequently, RITES Ltd. issued letters warning the petitioner about slow progress and the potential determination of the contract, forfeiture of performance guarantees, and declaration as a 'poor performer'. Following these warnings, the contract was terminated, citing a lack of concrete planning and commitment from the petitioner. Crucially, RITES Ltd. then declared M/s SK Electricals a 'Poor Performer' and placed it in the 'Negative List of Contractors,' debarring it from participating in future tenders for two years.
Could the High Court of Jharkhand exercise its writ jurisdiction under Article 226 of the Constitution of India, even though the contract specified 'Kolkata' as the city of jurisdiction for disputes?
Was the declaration of the petitioner as a 'Poor Performer' and subsequent blacklisting valid, given that no specific show-cause notice proposing blacklisting or debarment was issued, but only warning letters regarding contract determination?
Are contractual clauses that contemplate automatic declaration of a contractor as a 'poor performer' and consequent debarment upon contract determination, without an independent inquiry or opportunity of hearing, violative of natural justice and Article 14 of the Constitution?
The High Court's writ jurisdiction is fundamentally discretionary and cannot be ousted by a private agreement between parties to a contract. The court must consider the facts holistically, including the nature of injustice and the cause of action's situs (Maharashtra Chess Association Vs. Union of India & Others, 2020).
Blacklisting, having severe civil consequences and stigmatizing effects, necessitates a fair hearing. A specific, unambiguous show-cause notice, detailing the grounds for action and the proposed penalty, is crucial before blacklisting (Erusian Equipment & Chemicals Ltd. Vs. State of W.B. & Another, 1975; UMC Technologies (P) Ltd. Vs. Food Corpn. of India & Another, 2021; Techno Prints Vs. Chhattisgarh Textbook Corporation and Another, 2025; A.K.G Construction and Developers Pvt. Ltd. Vs. State of Jharkhand & others, 2026).
Courts should not enforce unfair or unreasonable contractual clauses, especially when entered into between parties with unequal bargaining powers. Such clauses, if unconscionable, can be struck down (Godrej Projects Development Ltd. Vs. Anil Karlekar & Others, 2025).
The Court first addressed the respondents' challenge to maintainability. While acknowledging precedents like M/s Swastik Gases (P) Ltd. Vs. Indian Oil Corpn. Ltd. (2013) and Indus Mobile Distribution (P) Ltd. v. Datawind Innovations (P) Ltd. & Others (2017), which dealt with exclusive jurisdiction for arbitration, the High Court distinguished these from the constitutional writ jurisdiction under Article 226. Relying on Maharashtra Chess Association (2020), the Court affirmed that a private contractual clause cannot oust the writ jurisdiction of a High Court. Given that the work site was in 'Dumka,' Jharkhand, and the alleged default occurred within the state, a major part of the cause of action arose within the Court's territorial jurisdiction. Therefore, it rejected the objection to maintainability.
Furthermore, citing Godrej Projects Development Ltd. (2025), the Court noted the inequality of bargaining power between the parties. The petitioner, as the weaker party, had no choice but to accept the contractual terms, including the jurisdiction clause. Consequently, dismissing the writ petition solely on this ground would be unjust.
The Court meticulously examined the declaration of the petitioner as a 'Poor Performer' and its placement in the 'Negative List of Contractors'. It referenced several Supreme Court judgments, including Erusian Equipment (1975), UMC Technologies (2021), Techno Prints (2025), and A.K.G Construction (2026). These precedents firmly establish that blacklisting has severe civil consequences and must adhere to natural justice principles, particularly the issuance of a specific show-cause notice.
The Court found that the warning letters dated 16.02.2026 and 25.02.2026, which merely warned about potential 'poor performer' status upon contract determination, did not fulfill the requirement of a specific show-cause notice for blacklisting. These letters primarily focused on expediting work progress, not on proposing the punitive measure of debarment with detailed grounds. The final debarment order itself also lacked specific grounds, merely stating that the petitioner was declared a 'Poor Performer' due to contract determination.
Crucially, the Court emphasized that a decision of blacklisting is not automatic and certainly not a logical consequence of a contract termination. These are distinct actions requiring independent consideration and due process. Blacklisting can only be resorted to when the contractor's conduct is so deviant or aberrant as to warrant such a punitive measure, not merely for breach of contract.
For busy legal professionals, CaseOn.in offers 2-minute audio briefs that concisely analyze crucial rulings like this, providing rapid insights into complex judicial pronouncements and their practical implications.
The Court also considered the argument against Clause 3(b) of the GCC, which contemplated automatic declaration as a 'poor performer' and subsequent debarment. It found such a clause to be manifestly unreasonable and arbitrary, violating natural justice principles. It operates mechanically, without considering the reasons for contract failure or providing an opportunity for the contractor to explain. This constitutes an unequal treatment of situations and is contrary to Article 14 of the Constitution, particularly given the unequal bargaining power between the state instrumentality and the contractor.
The Jharkhand High Court quashed and set aside the impugned part of the letter dated 22.04.2026, which placed the petitioner in the 'Negative List of Contractors' and debarred it from participating in future tenders for two years. The Court clarified that its interference did not extend to the 'Poor Performer' declaration itself or other actions related to contract termination, allowing the petitioner to challenge those in accordance with law. The respondents were also granted liberty to initiate fresh debarment proceedings against the petitioner, provided they follow due process of law by issuing a specific show-cause notice and affording a fair hearing.
This article provides a simplified analysis of the High Court's judgment for informational purposes only. It is not intended as, and should not be relied upon as, legal advice. Readers should consult with a qualified legal professional for advice pertaining to their specific circumstances.
Legal Notes
Add a Note....