0  17 May, 2024
Listen in mins | Read in 36:00 mins
EN
HI

M/S Sundew Properties Limited Vs. Telangana State Electricity Regulatory commission & Anr.

  Supreme Court Of India Civil Appeal /8978/2019
Link copied!

Case Background

This statutory appeal challenges a judgment by the Appellate Tribunal for Electricity (APTEL), which dismissed an appeal by the appellant against a decision by the Telangana State Electricity Regulatory Commission ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

2024 INSC 439

Page 1 of 24

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 8978/2019

M/S SUNDEW PROPERTIES LIMITED …APPELLANTS

VERSUS

TELANGANA STATE ELECTRICITY REGULATORY

COMMISSION & ANR. …RESPONDENTS

J U D G M E N T

DIPANKAR DATTA, J.

THE CHALLENGE

1. This is a statutory appeal before us under section 125 of the Indian

Electricity Act, 2003

1

. It registers a challenge to the judgment and order

dated 27

th

September, 2019 passed by the Appellate Tribunal for Electricity

2

1

Electricity Act

2

APTEL

Page 2 of 24

dismissing an appeal carried under section 111 of the Electricity Act by the

appellant from the judgment and order dated 15

th

February, 2016 passed

by the Telangana State Electricity Regulatory Commission

3

. Consequently,

the impugned judgment and order of the TSERC was upheld.

BRIEF FACTS

2. The basic facts giving rise to this appeal are not disputed. A brief

overview of the facts and the trajectory of proceedings, relevant for a

decision on the present appeal, are set out hereunder:

a) The appellant was notified by the Ministry of Commerce &

Industry (Department of Commerce), Government of India

4

as

a ‘Developer’, in terms of sections 3 and 4 of the Special

Economic Zones Act, 2005

5

, to establish a sector-specific

Special Economic Zone

6

unit for Information

Technology/Information Technology Enabled Services sector in

Madhapur, Ranga Reddy District, Hyderabad, in the former

State of Andhra Pradesh.

b) MoCI, vide a Notification bearing No.SO 528(E) dated 3

rd

March, 2010

7

introduced a proviso to section 14(b) of the

Electricity Act. The proviso accords upon the developer of a

SEZ, the status of a deemed distribution licensee under the

provisions of the Electricity Act.

3

TSERC

4

MoCI

5

SEZ Act

6

SEZ

7

2010 Notification

Page 3 of 24

c) Pursuant to the 2010 Notification, the appellant filed an

application

8

before the erstwhile Andhra Pradesh Electricity

Regulatory Commission seeking identification as a deemed

distribution licensee, in terms of the proviso to section 14(b) of

the Electricity Act read with regulation 13 and Schedule-2 of

the Andhra Pradesh Electricity Regulatory Commission

(Distribution Licence) Regulations, 2013

9

and section 49 of the

SEZ Act. Upon the Andhra Pradesh Reorganisation Act, 2014

coming into force, the application was transferred to the

TSERC.

d) By its aforesaid judgment and order dated 15

th

February, 2016,

the TSERC identified and accorded the status of a deemed

licensee to the appellant. However, this grant of status was

made conditional upon the appellant satisfying the

requirements stipulated in rule 3 of the Distribution of

Electricity Licence (Additional Requirements of Capital

Adequacy, Creditworthiness and Code of Conduct) Rules,

2005

10

, compliance whereof was mandatory per regulation 12

[which stipulates that an applicant for grant of distribution

licence shall, in addition to regulations 4 to 11, comply with the

2005 Rules] read with regulation 49 of the 2013 Regulations

[which stipulates that all the general conditions applicable to a

8

O.P. No. 10 of 2015

9

2013 Regulations

10

2005 Rules

Page 4 of 24

distribution licensee are also equally applicable to a deemed

licensee]. The appellant was, therefore, directed to infuse an

additional capital of Rs. 26.90 crore as equity share capital,

contributed by its promoters, into its power distribution

business via account payee cheques by 31

st

March, 2016. The

relevant part of the judgment and order of the TSERC is

extracted hereunder:

“16. […] On a close reading of the provisions of section 14,

we are of the view that the 'provisos' to section 14 are not

applicable to a deemed licensee. The status of a deemed

licence to a person under Section 14(b) of the Electricity

Act, 2003 emanates from the Notification give n under

Section 49(1) of the SEZ Act to a developer of SEZ provided

the deemed Licensee satisfies the other provisions of the

Act.

[…]

18. We are of the view that the provisions contained in sub-

section (2), (3), (4), (5) & (6) of Section 15 of the Act are

not applicable to a deemed licensee. Moreover, [A.P.

Distribution Licence Regulations] contains the Rules

relating to procedure for granting of a distribution licensee

from Rules 4 to 11 […] The Rule 13 of the Regulation

stipulates that Rules contained in 4 to 11 are not applicable

to a deemed licensee and these Rules contain the

procedure for granting of a distribution licence to a person.

[…]

19. The Rule 13 of the [A.P. Distribution Licence

Regulations] stipulates that a deemed licensee shall make

an application in the form specified in Schedule - 2 to the

Commission to get identified as a deemed licensee and

rules 4 to 11 in the Regulations are not applicable to a

deemed licensee, Thus, the Rule 13 […] has excluded the

application of Rules laid down from Rules 4 to 11 […] As

observed earlier, the Rules 4 to 11 basically deal with the

procedure to be followed by a person for obtaining a licence

from the Commission. By implication, Rule 12 is applicable

to a deemed licensee also […]

20. We are not able to appreciate the argument of the

petitioner that Rule 12 is not applicable to a deemed

licensee. In our view, Rule 49 stipulates that all the general

Page 5 of 24

conditions applicable to a distribution licensee are also

equally applicable to a deemed licensee. Thus, in our view,

the Rule 12 is applicable to the petitioner.

21. The next issue that arises is whether the petitioner has

complied with the provisions of Rule 12? […] As a stand-

alone entity the petitioner does riot fulfil the. conditions laid

down in Rule 3 of the Capital Adequacy Rules. However,

the Rule 3(2) also stipulates that the net worth of the

promoters of the petitioner can be considered for the

purpose of computation of the Debt Equity ratio of 30:70

[…].

26(A). The [Commission], in exercise of the powers

conferred under Section 14 (b) of the Electricity Act, hereby

identifies and recognises M/s. Sundew Properties Ltd. […]

as a deemed licensee.

26(D). […] the promoters have to contribute 30% of the

total anticipated investment of Rs. 89.53 Crores which

works out to Rs.26.9 Crores on or before 31.03.2016.”

e) Aggrieved, the appellant carried an appeal

11

from the aforesaid

order of the TSERC to the APTEL. According to the appellant,

the directions of the TSERC were in excess of jurisdiction.

APTEL dismissed the appeal, as noticed above. It held that the

TSERC was justified in ordering infusion of additional equity by

the appellant to the tune of Rs.26.90 crore (being 30% of the

total anticipated investment of Rs.89.53 crore) as a pre -

condition for being identified as a deemed distribution licence.

The operative part of the judgment and order passed by the

APTEL reads as follows:

“8.14 […] while the Appellant is not required to apply for

grant of license but being a deemed distribution licensee

has to fulfil other technical and financial requirements as

per prevailing rules and regulations of the State

Commission which is mandated to reg ulate the Electricity

business in the state whether it is a DISCOM or any other

11

Appeal No.3 of 2017

Page 6 of 24

deemed distribution licensee as in the present case.

Accordingly, we are of the opinion that the State

Commission has passed the impugned order with careful

consideration and proper interpretation of the statute and

also considering the judgments passed by Hon'ble

Supreme Court in Sesa Sterilite [sic] case (supra) […]”

f) It is this judgment and final order that the appellant has

subjected to challenge in this statutory appeal by invoking the

appellate jurisdiction of this Court under section 125 of the

Electricity Act.

SUBMISSIONS

3. Mr. Singh, learned senior counsel appearing for the appellant,

challenged the validity of the orders of the TSERC and the APTEL by

advancing the following submissions:

a) The TSERC and the APTEL erred in failing to recognize that

under section 14(b) of the Electricity Act, a developer of an SEZ

is ipso facto and unconditionally deemed to be a distribution

licensee, thus eliminating the need for a separate licence

application. Recognition of the status of a deemed distribution

licensee is a ministerial act, effected automatically upon

fulfilment of conditions laid down in the SEZ Act, independent

of rule 3(2) of the 2005 Rules read with regulation 12 of the

2013 Regulations.

b) The status of deemed distribution licensee stands bestowed

upon the appellant by virtue of the 2010 Notification, requiring

Page 7 of 24

no further action. This position has been recognized and

approved by both the TSERC and the APTEL.

c) Under the 2013 Regulations, there are two types of licensees:

first, those who apply for a distribution licen ce under

regulations 2(d) and 12, and secondly, those already deemed

licensees, seeking recognition of their status as such, under

regulations 2(h) and 13. The appellant belongs to the latter

category.

d) Regulation 12 of the 2013 Regulations applies to general

applicants seeking a distribution licence, mandating compliance

with both the 2005 Rules and the procedures prescribed in

regulations 4 to 11. It cannot apply to a deemed licensee under

regulation 13. The TSERC’s finding, as approved by the APTEL,

that the 2005 Rules are in-built into the 2013 Regulations and

therefore have to be satisfied by the appellant because of

implied application of regulation 12 to deemed licensees, is

contrary to the provisions of the Electricity Act and the very

scheme of the 2013 Regulations.

e) APTEL erred by agreeing with the TSERC’s reasoning that the

requirement to infuse Rs. 26.90 crore in equity was imposed

on the appellant under section 16 of the Electricity Act, despite

recognising the appellant as a deemed distribution licensee.

Conditions under section 16, whether general or specific, must

Page 8 of 24

be ‘specified’ by the Appropriate Commission through

regulations according to section 2(62) of the Electricity Act.

4. Resting on the aforesaid submissions, learned senior counsel

urged this Court to allow the appeal and set-aside the orders of the TSERC

and the APTEL to the extent requiring the appellant to comply with the

conditions stipulated in rule 3 of the 2005 Rules and infuse additional capital

to gain the status of a deemed licensee.

5. Per contra, Mr. Vaidyanathan, learned senior counsel appearing

for the second respondent (Southern Power Distribution Company of

Telangana Limited), joined by Mr. Goud, learned counsel appearing for

respondent no. 1 (TSERC), supported the impugned judgment and order

and advanced the following submissions:

a) No doubt, the appellant, a SEZ developer, may be granted the

status of a deemed licensee; however, the 2005 Rules and the

2013 Regulations will be applicable to the appellant as per the

law laid down by this Court in Sesa Sterlite Limited. v.

Orissa Electricity Regulatory Commission and others

12

.

b) The appellant cannot be deemed to be a distribution licensee

on its own without making an application under regulation 13.

c) There is a necessity to harmoniously interpret the SEZ Act and

the Electricity Act to uphold the provisions of both enactments.

12

(2014) 8 SCC 444

Page 9 of 24

The appellant cannot argue that the 2005 Rules and the 2013

Regulations do not apply to it, being a SEZ developer.

d) TSERC is empowered to impose general and specific conditions

at its discretion. The purpose of requiring the appellant to

infuse an additional capital under the 2005 Rules was to assess

the credit-worthiness of the appellant as it had accumulated

losses at the end of the financial year 2013-2014 and more

than 50% of its net-worth has been wiped-out, a fact which is

reflected from the Statutory Auditor’s report.

6. No case for interference having been set up by the appellant,

learned counsel for respondents prayed for dismissal of the appeal.

STATUTORY FRAMEWORK

7. Before proceeding further, it is imperative to refer to certain

statutory provisions.

8. Section 14 of the Electricity Act deals with the grant of a licence:

“14. Grant of Licence – The Appropriate Commission may, on

an application made to it under section 15, grant a licence to any

person –

(a) to transmit electricity as a transmission licensee; or

(b) to distribute electricity as a distribution licensee; or

(c) to undertake trading in electricity as an electricity trader,

in any area as may be specified in the licence:

Provided that any person engaged in the business of

transmission or supply of electricity under the provisions of the

repealed laws or any Act specified in the Schedule on or before

the appointed date shall be deemed to be a licensee under this Act

for such period as may be stipulated in the licence, clearance or

approval granted to him under the repealed laws or such Act

specified in the Schedule, and the provisions of the repealed laws

or such Act specified in the Schedule in respect of such licence

Page 10 of 24

shall apply for a period of one year from the date of

commencement of this Act or such earlier period as may be

specified, at the request of the licensee, by the Appropriate

Commission and thereafter the provisions of this Act shall apply

to such business:

Provided further that the Central Transmission Utility or the

State Transmission Utility shall be deemed to be a transmission

licensee under this Act:

Provided also that in case an Appropriate Government

transmits electricity or distributes electricity or undertakes trading

in electricity, whether before or after the commencement of this

Act, such Government shall be deemed to be a licensee under this

Act, but shall not be required to obtain a licence under this Act:

Provided also that the Damodar Valley Corporation,

established under sub-section (1) of section 3 of the Damodar

Valley Corporation Act, 1948, shall be deemed to be a licensee

under this Act but shall not be required to obtain a licence under

this Act and the provisions of the Damodar Valley Corporation Act,

1948, in so far as they are not inconsistent with the provisions of

this Act, shall continue to apply to that Corporation:

Provided also that the Government company or the

company referred to in sub-section (2) of section 131 of this Act

and the company or companies created in pursuance of the Acts

specified in the Schedule, shall be deemed to be a licensee under

this Act:

Provided also that the Appropriate Commission may grant

a licence to two or more persons for distribution of electricity

through their own distribution system within the same area,

subject to the conditions that the applicant for grant of licence

within the same area shall, without prejudice to the other

conditions or requirements under this Act, comply with the

additional requirements [relating to the capital adequacy, credit-

worthiness, or code of conduct] as may be prescribed by the

Central Government, and no such applicant, who complies with all

the requirements for grant of licence, shall be refused grant of

licence on the ground that there already exists a licensee in the

same area for the same purpose:

Provided also that in a case where a distribution licensee

proposes to undertake distribution of electricity for a specified

area within his area of supply through another person, that person

shall not be required to obtain any separate licence from the

concerned State Commission and such distribution licensee shall

be responsible for distribution of electricity in his area of supply:

Provided also that where a person intends to generate and

distribute electricity in a rural area to be notified by the State

Government, such person shall not require any licence for such

generation and distribution of electricity, but he shall comply with

Page 11 of 24

the measures which may be specified by the Authority under

section 53:

Provided also that a distribution licensee shall not require

a licence to undertake trading in electricity.”

9. To determine who qualifies as a deemed licensee under the

Electricity Act, we may refer to the 2013 Regulations.

10. Regulation 2(i)(h) of the 2013 Regulations defines “deemed

licensee” as follows:

“(h) ‘Deemed Licensee’ means a person authorised under sub -

section (b) of Section 14 and also under the first, second, third,

and fifth provisos to section 14 of the Act to operate and maintain

a distribution system for supply of electricity to the consumers in

his area of supply.”

11. Regulation 13 of the 2013 Regulations stipulates the procedure to

get identified as a deemed distribution licensee. It reads:

“13. The deemed licensees shall make application in the form

specified in Schedule- 2 to the Commission to get identified as the

deemed Licensee. Provided that nothing in Regulations 4 to 11

shall apply to deemed licensees.”

12. Insofar as a developer under the SEZ Act is concerned, a reference

may be made to the scheme of the SEZ Act to ascertain its status as deemed

distribution licensee.

13. The policy for SEZs was introduced with an objective to create a

competitive export environment and to attract foreign investment. It levels

the playing field for domestic businesses globally and introduces favourable

policies in investment, taxation, trade, customs, and labour regulations. In

line with this, for the purpose of ensuring consistent and high-quality power

supply to these SEZ units, the MoCI, vide the 2010 Notification [under

Page 12 of 24

clause (b) of sub-section (1) of section 49 of the SEZ Act] has specified that

the ‘developer’ of the SEZ shall be deemed to be a ‘distribution licensee’

under the provisions of the Electricity Act. The proviso inserted in clause (b)

of section 14 of the Electricity Act, vide the 2010 Notification, reads as

follows:

“Provided that the Developer of a Special Economic Zone notified

under sub-section (1) of Section 4 of the Special Economic Zones

Act, 2005, shall be deemed to be a licensee for the purpose of this

clause, with effect from the date of notification of such Special

Economic Zone.”

14. With the inclusion of the aforementioned proviso to section 14(b)

of the Electricity Act, it is evident that a SEZ developer is deemed to be a

distribution licensee.

15. The main contention of the parties that whether the TSERC

imposed condition to infuse additional capital per rule 3(2) of the 2005 Rules

read with regulation 12 of the 2013 Regulations is justifiable or extraneous

is deliberated at length in a later part of this judgment. Regulation 12

provides that a person applying for a grant of a distribution licence shall, in

addition to regulations 4 to 11, comply with the 2005 Rules. Regulation 12

is extracted below:

“12. Application for grant of Distribution Licence in the area

of supply of an existing Distribution Licensee – A person

applying for grant of a licence for distribution of electricity through

his own distribution system within the same area of supply of an

existing Distribution Licensee shall, in addition to the provisions of

Regulation 4 to 11, comply with “Distribution of Electricity Licence

(additional requirements of Capital Adequacy, Creditworthiness

and Code of Conduct) Ru les, 2005” issued by the Central

Government.”

16. Rule 3 is extracted hereunder:

Page 13 of 24

“3. Requirements of capital adequacy and

creditworthiness. –

(1) The Appropriate Commission shall, upon receipt of an

application for grant of licence for distribution of electricity under

sub-section (1) of section 15 of the Electricity Act, 2003, decide

the requirement of capital investment for distribution network

after hearing the applicant and keeping in view the size of the area

of supply and the service obligation within that area in terms of

section 43.

(2) The applicant for grant of licence shall be required to satisfy

the Appropriate Commission that on a norm of 30% equity on cost

of investment as determined under sub-rule (1), he including the

promoters, in case the applicant is a company, would be in a

position to make available resources for such equity of the project

on the basis of net worth and generation of internal resources of

his business including of promoters in the preceding three years

after excluding his other committed investments.”

ISSUES

17. Having noticed the relevant statutory framework, we are now

tasked with deciding two short issues:

a) Whether the designation of an entity as a SEZ developer by the

MoCI ipso facto qualifies the entity to be a deemed distribution

licensee, obviating the need for an application under section 14

of the Electricity Act?

b) Whether regulation 12 of the 2013 Regulations, and by

implication rule 3(2) of the 2005 Rules, are applicable to a SEZ

developer recognised as a deemed distribution licensee under

the proviso to section 14(b) of the Electricity Act read with

regulation 13 of the 2013 Regulations?

Page 14 of 24

ANALYSIS

18. We have considered the submissions advanced by learned counsel

for the parties and have also perused the materials on record.

Issue (a)

19. It would not be inapt to be reminded of what was stated by a

Bench of two Hon’ble Judges of this Court in State of Bombay v.

Pandurang Vinayak Chaphalkar

13

nearly seventy years ago:

“11. […] When a statute enacts that something shall be deemed

to have been done, which in fact and truth was not done, the court

is entitled and bound to ascertain for what purposes and between

what persons the statutory fiction is to be resorted to and full

effect must be given to the statutory fiction and it should be

carried to its logical conclusion.”

20. In view of the existing facts, we are inclined to the view that the

very purpose of the deeming fiction in the proviso to section 14(b) of the

Electricity Act is to confer upon an entity like the appellant a status which

is otherwise available in accordance with the Electricity Act. In other words,

as an effect of the 2010 Notification inserting the proviso to section 14(b),

the appellant is entitled to the privilege of being acknowledged as a

(deemed) distribution licensee under the Electricity Act for supply of power

within its SEZ area. Once the appellant is a (deemed) distribution licensee,

certain benefits and/or privileges do enure in its favour.

21. The respondents have heavily relied on Sesa Sterlite Limited

(supra) to assert that there has to be a harmonious construction of both

13

(1953) 1 SCC 425

Page 15 of 24

the SEZ Act and the Electricity Act to give effect to the provisions of both

the enactments, so long as they are not inconsistent with each other.

22. A Bench of two Hon’ble Judges of this Court in Sesa Sterlite

Limited (supra) held:

“43. The reading of Section 49 of the SEZ Act would reveal that

the Central Government has got the authority to direct that any

of the provisions of a Central Act and the rules and regulations

made thereunder would not apply or to declare that some of the

provisions of the Central Acts shall apply with exceptions,

modifications and adaptation to the special economic zone. So,

under the scheme of the Special Economic Zones Act, the Central

Government has to first notify as to what extent the provision of

the other Acts are to be made applicable or applicable with

modification or not applicable for the special economic zone area.

It is in furtherance thereto, the Government of India, Ministry of

Commerce and Industry through its Notification dated 21-3-2012,

with regard to power generation in special economic zone, has

declared that all the provisions of the Electricity Act, 2003 and the

Electricity Rules, 2005 shall be applicable to the generation,

transmission and distribution of power, whether stand-alone or

captive power. This notification would clarify that there is no

inconsistency between the Special Economic Zones Act, 2005 and

the Electricity Act, 2003.

[…]

46. To recapitulate briefly, in the present case no doubt by virtue

of the status of a developer in the SEZ area, the appellant is also

treated as deemed distribution licensee. However with this, it only

gets exemption from specifically applying for licence under Section

14 of the Act.”

23. The question in Sesa Sterlite Limited (supra), was whether the

appellant - a deemed distribution licensee, being a developer of Special

Economic Zone (SEZ) and having a unit in the SEZ, is liable to pay Cross-

Subsidy Surcharge (CSS). It was held that the appellant would be liable to

pay CSS for several reasons, including on the facts that it was using

dedicated transmission lines belonging to the distribution licensee for the

Page 16 of 24

area in question. This Court interpreted the expression 'open access' and

the rationale behind CSS and additional surcharge to observe that the

former was payable by a distribution licensee and the latter was to meet

the fixed cost of the distribution licensee of the area. The provision of open

access, it is observed, balances the right of the consumers to purchase from

a source of their choice. The rationale and the ratio of the decision,

therefore, is that a deemed distribution licensee is treated at par and not

different from a distribution licensee. Accordingly, if CSS is payable by a

distribution licensee, the deemed distribution licensee is equally liable to

pay the same. This decision, in other words, equates deemed distribution

licensee with the distribution licensee for the purpose of supply of electricity

to the consumers. Sesa Sterlite Limited (supra) is not a decision for the

proposition that deemed distribution licensee, to qualify as a deemed

distribution licensee, must meet the criteria, includ ing the capital

requirements as applicable by regulations to a distribution licensee.

24. Further, the provisos to section 14 of the Electricity Act distinguish

between entities that are ipso facto deemed distribution licensees and those

that are merely declared as deemed licensees without clarity on the

necessity of making an application to obtain a licence. For instance, the

third and fourth provisos to section 14 not only confer the status of deemed

licensees to the State Government and the Damodar Valley Corporation,

respectively, but also explicitly exempt them from the requirement to obtain

a licence. Entities not covered by these specific provisos would, therefore,

be required to obtain a licence. The requirement of obtaining a license has

to be read into the other provisos to section 14 since, for instance, the

Page 17 of 24

second and fifth provisos to section 14 grant deemed licensee status to

Central/State Transmission Utility and a government company ,

respectively, but neither specifies the requirement to obtain a license nor

exempts them from obtaining license.

25. As far as the 2010 Notification is concerned, the proviso to section

14(b) introduced by the said Notification, confers deemed licensee status

on SEZ developers. However, such conferment does not explicitly exclude

the requirement of obtaining a licence. This lack of specificity, especially

when compared with the clear provisions for other entities, suggests that

the legislative intent was not to ipso facto grant SEZ developers the status

of deemed distribution licensees, thereby obliging them to obtain a licence

by making an application in terms of regulation 13. TSERC is, therefore,

empowered to scrutinise such applications in accordance with law, however,

only limited to the provisions which are applicable to deemed licensees.

Verification and acceptance recognise their status as deemed licensees.

Issue (b):

26. Issue (b) revolves around rule 3(2) of the 2005 Rules, which per

the TSERC and the APTEL, the appellant is bound to adhere by infusing

additional capital in order to qualify as a deemed licensee. While the

appellant contends that the 2010 Notification, by necessary consequence,

grants upon the appellant the status of a deemed licensee, the respondents

submit that the identification of the appellant as a deemed distribution

licensee is conditional upon the appellant satisfying the other requirements

of the Electricity Act, specifically the sixth proviso to section 14 of the

Page 18 of 24

Electricity Act which provides for compliance with additional requirements

like capital adequacy which as per the respondents includes rule 3 of the

2005 Rules read with regulation 12 of the 2013 Regulations.

27. It is contended by the respondents that the application of 2005

Rules to the appellant, a SEZ developer, stems from the sixth proviso to

section 14 read with regulation 12 of the 2013 Regulations.

28. Let us now deal with the provisos to section 14. Upon a bare

reading of the provision, it becomes crystal clear that not only does the

sixth proviso, but none of the nine provisos to section 14, apply to the

appellant, a SEZ developer. Even the TSERC and the APTEL are ad idem

with this view. The status of a SEZ developer as a deemed licensee

emanates from the 2010 Notification, which introduced the proviso to

section 14(b), conferring deemed licensee status to SEZ developers.

Reading anything beyond this would defeat the very purpose of the proviso

and the concept of the deemed licence. The sixth proviso does not pertain

to deemed licensees and, therefore, the 2005 Rules are not applicable to

the appellant.

29. Upon closer examination of regulation 12, it becomes apparent

that its application does not extend to applicants who are otherwise deemed

licensees. The interpretation of regulation 12 as requiring additional capital

infusion for an applicant for acceptance of a deemed licensee status appears

to be at odds with the language and intent of the 2013 Regulations itself.

TSERC has, in essence, interpreted regulation 12 by reading it up to mean

Page 19 of 24

that it also applies to a person who is a deemed licensee, and in doing so,

the TSERC has aimed to achieve indirectly what it could not directly.

30. Reading down and reading up are two principles often discussed

in legal contexts, particularly in the realm of statutory interpretation.

Reading down, which has been firmly ingrained in our jurisprudence, refers

to the practice of interpreting a statute narrowly, limiting its scope or

application to specific situations or individuals. This approach is commonly

employed when the language of a statute is ambiguous or when there is a

need to avoid potential conflicts with other laws or constitutional provisions.

For example, if a law is unclear about whether it applies to certain types of

businesses, a court may choose to read down the statute to only include

those businesses explicitly mentioned in the text. On the other hand,

reading up involves interpreting a statute broadly, extending its scope or

application beyond what is expressly stated in the text. Reading up is a

concept that is invoked with great caution within our legal framework

because it can lead to judicial activism or judicial overreach, where courts

expand the reach of laws beyond what the legislature intended.

31. A Constitution Bench of this Court in B.R. Kapur v. State of

Tamil Nadu

14

, while stating that reading up of a statute is not permissible,

held thus:

“39. Section 8(4) opens with the words ‘notwithstanding anything

in sub-section (1), sub-section (2) or sub-section (3)’, and it

applies only to sitting members of Legislatures. There is no

challenge to it on the basis that it violates Article 14. If there were,

it might be tenable to contend that legislators stand in a class

apart from non-legislators, but we need to express no final

14

(2001) 7 SCC 231

Page 20 of 24

opinion. In any case, if it were found to be violative of Article 14,

it would be struck down in its entirety. There would be, and is no

question of so reading it that its provisions apply to all, legislators

and non-legislators, and that, therefore, in all cases the

disqualification must await affirmation of the conviction and

sentence by a final court. That would be ‘reading up’ the provision,

not ‘reading down’, and that is not known to the law.”

32. The literal rule of interpreting a statute empowers courts to iron

out the creases within legislation but without altering the very fabric of

which it is made. The practice of reading up a provision can only be justified

when it aligns with legislative intent, maintains the fundamental character

of the law, and ensures that the resulting interpretation remains consistent

with the original context to which the law applies. This holds especially true

for subordinate legislation, which require greater scrutiny in this regard.

Reading up a provision of subordinate legislation in a manner that it

militates against the primary legislation is not permissible.

33. The authority to craft subordinate legislation is derived from the

enabling/primary legislation and it is imperative that such legislation

harmonizes with the provisions outlined in the enabling/primary legislation.

The Electricity Act has conferred power on the Central Government to make

Rules [see section 175], and on the Central Electricity Authority and the

Central Commission to make Regulations [see sections 176 and 177,

respectively]. All such rules/regulations are to be made consistent with the

Electricity Act. Section 181 of the Electricity Act confers power on the State

Commissions to make Regulations but such regulations too must be

consistent with the provisions of the primary enactment and the rules

framed thereunder generally. Rules and Regulations are enacted to

Page 21 of 24

supplement the main provision, not to supplant it. They serve the crucial

role of bridging potential gaps within the primary legislation, yet, their

function is not to create webs and voids merely to clog and hamper their

implementation. Any gaps addressed by Rules and Regulations must be

discernible within the framework of the primary legislation.

34. In the present case, the TSERC, in paragraph 19, asserted that

regulation 12 applies implicitly to a deemed licensee as well. We do not

agree with this reasoning, mainly for two reasons . First, the primary

legislation, the Electricity Act, through the proviso inserted in section 14(b),

confers deemed licensee status upon SEZ developers without imposing any

specific conditions. Secondly, the 2013 Regulations make a clear distinction

between an applicant seeking a licence [as defined under regulation 2(d)]

and a deemed distribution licensee seeking recognition as such [as defined

under regulation 2(h)]. Regulation 2(d) defines an “applicant” as “a person

who has submitted an application to the Commission for the grant of a

distribution licence”. In contrast, regulation 2(h) defines a “deemed

licensee” as “a person authorized under sub-section (b) of Section 14, and

also under the first, second, third, and fifth provisos to section 14 of the

Act, to operate and maintain a distribution system for supplying electricity

to consumers in their area of supply”. The 2013 Regulations clearly

delineate distinct categories of licensees. Regulation 12 pertains solely to

regular distribution licensees as defined under regulation 2(h), not to

deemed licensees. ‘Reading up’ regulation 12 so as to expand its ambit to

include within it deemed licensees, especially when the Electricity Act does

not stipulate any such inclusion, runs counter to the subsequently inserted

Page 22 of 24

proviso to clause (b) of section 14 of the Electricity Act—an exercise which

is impermissible and which we cannot approve. Therefore, the recognition

of the status of a deemed distribution licensee cannot hinge on compliance

with rule 3(2) of the 2005 Rules read with regulation 12 of the 2013

Regulations.

35. The language of regulation 12 merits careful scrutiny. It states

that an applicant shall, “in addition to the provisions of Regulation 4 to 11”,

comply with the provisions of the 2005 Rules. It is evident that it is a normal

applicant [as defined under regulation 2(d)], which is tasked with complying

with regulations 4 to 11, that has to comply with the 2005 Rules. However,

the appellant herein, as discussed previously, is not a regular applicant but

a deemed distribution licensee [as defined under regulation 2(h)], and is

governed by regulation 13, the proviso to which specifically states that

nothing in regulations 4 to 11 would apply to deemed licensees. Having thus

been statutorily exempted from complying with regulations 4 to 11, we are

of the opinion that the appellant, being a deemed licensee, would also be

exempt from the concomitant obligation of complying with regulation 12, in

view of the language of the provision, which imposes the burden of

complying with regulation 12 only on those applicants who come within the

purview of regulations 4 to 11. The appellant falling outside the scope of

the latter, would thus necessarily fall outside the scope of the former too.

36. TSERC’s reliance on regulation 49 of the 2013 Regulations to

enforce the applicability of regulation 12 also appears to be flawed.

Regulation 49, situated within Chapter-4 [General Conditions of Distribution

Licence] of the 2013 Regulations, specifies that “these general conditions

Page 23 of 24

shall apply to distribution licensees and to all deemed distribution

licensees”. A straightforward reading reveals that the term ‘general

conditions’ in regulation 49 pertains exclusively to the general conditions

outlined in Chapter-4. By no stretch of imagination could the scope of this

provision be widened so as to include within its ambit regulation 12, which

forms part of Chapter-3 [Procedure for Grant of Distribution Licence] of the

2013 Regulations.

CONCLUSION

37. To sum up, being a SEZ developer in terms of the 2010 Notification

does not ipso facto confer upon the appellant the status of a deemed

licensee without any scrutiny and without being under any requirement to

apply; it is required to make an application in accordance with the 2013

Regulations. We have been apprised that this condition has been fulfilled as

the status of the appellant as a deemed licensee has already been upheld

pursuant to the application made in accordance with rule 13 of the 2013

Regulations. The first issue is answered accordingly. As far as the second

issue is concerned, the condition stipulated in rule 3(2) of the 2005 Rules,

as imposed by the TSERC with a direction to infuse an additional capital of

Rs. 26.90 crore is not justified and contrary to the statutory scheme as

discussed aforesaid. The judgments and orders of the TSERC and the APTEL

are set aside to this extent. The order of the TSERC, which grants the status

of a deemed licensee to the appellant, however, subject to the condition

that its promoters infuse additional capital is accordingly modified to the

extent of excluding such condition.

Page 24 of 24

38. The appeal is partly allowed in the aforesaid terms. No costs.

………………………………J

(SANJIV KHANNA )

………………………………J

(DIPANKAR DATTA)

New Delhi;

17

th

May, 2024.

Reference cases

Description

Legal Notes

Add a Note....