National Highway; Road Construction; Box Cut; Slope Stability; Landslide Risk; Public Safety; Writ Petition; Expert Opinion; NHIDCL; Jammu & Kashmir High Court
 12 Mar, 2026
Listen in 01:14 mins | Read in 48:00 mins
EN
HI

Petitioners Vs. Respondents

  Jammu & Kashmir High Court WP(C) No. 1243/2023
Link copied!

Case Background

As per case facts, petitioners filed a writ petition challenging the construction of deep box cuts on the NH-244, citing expert geological reports that recommended realignment or detouring due to ...

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

WP(C) No. 1243/2023

Page 1 of 32

IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH

AT JAMMU

Uploaded on: 12.03.2026

WP(C) No. 1243/2023

1. Surinder Singh, aged 44 years, S/o Sh. Trilok Singh, R/o

Village Bashat, Tehsil Chenani, District Udhampur.

2. Som Raj, aged 49 years, S/o Prithvi Gir, R/o Katwait,

Bachhal, Sudhmahadev, Udhampur.

3. Sharief Khan, aged 55 years, S/o Sh. Bashir Khan, R/o

Bashat, District Udhampur.

4. Sudesh Chander, aged 43 years, S/o Sh. Romal Chand,

R/o Sarar, Bap, Udhampur.

…..Petitioners

Through: Mr. Yasser Ejaz Tak, Advocate

Vs

1. Union of India,

Through Ministry for Service Transport and Highway Govt.

of India, New Delhi.

2. National Highway and Infrastructure,

Development Corporation Ltd.

Through its CMD, 3

rd Floor, PTI Building,

4- Parliament Street, New Delhi – 110001.

3. The Executive Director (P)

NHIDCL, H. No. 261, Sector-6,

Channi Himmat, Jammu.

4. General Manager (P),

PMU-Akhnoor,

NHIDCL, 333-F Shakti Nagar, Jammu – 180001.

5. Authority’s Engineer

TPF-Getinsa Euro Studios S.L. in association with

Segmental Consulting and Infrastructure Advisory Limited.

Project Office: Friends Colony Lane, Opp. BSF old Bridge,

Paloura, Jammu (J&K) 180001.

6. ECI-SRM Projects,

WP(C) No. 1243/2023

Page 2 of 32

Registered Office: 1-A, Hill View, Near Govt. H. S. S. Bahu

Fort, Jammu – 180006.

.….Respondents

Through: Mr. Sunny Mahajan, CGSC.

Mr. Rahul Pant, Sr. Advocate with

Mr. Anirudh Sharma, Advocate.

Mr. Basit Manzoor Keng, Advocate.

Coram : HON’BLE MR. JUSTICE RAHUL BHARTI , JUDGE

JUDGMENT

(12.03.2026)

01. This is a writ petition filed by four petitioners, all

claiming to be residents of different villages of district

Udhampur.

02. Before this Court comes to purported cause of action

leading the writ petitioners to join together and come up with

writ petition thereby seeking this Court to interject with

respect to an ongoing construction of a stretch of road falling

on Chenani – Sudhmahadev Section of NH-244 on the plea

that construction of High Gallas/Open Box Cut at three/four

locations of said stretch is against the

proposal/recommendations of the respondent No. 4 – General

Manager (P), PMU-Akhnoor and the respondent No. 5 –

Authority Engineer, TPF, warranting alternate alignments to

be resorted to, this Court needs first to refer to the Project

before coming to the stretches/sections with respect to which

originally approved and allotted course of construction is

alleged to be objectionable and vulnerable.

03. Chenani – Sudhmahadev is linked by NH -244 with

respect to the widening and upgradation of which a proposal

for 2-Lane with paved shoulder configuration and geometric

improvement from Km 0.000 to Km 16.990 on Chenani –

WP(C) No. 1243/2023

Page 3 of 32

Sudhmahadev Section of NH-244 in the then State of Jammu

& Kashmir was envisaged to be undertaken by the Ministry of

Road, Transport & Highways through the respondent No.2-

National Highways and Infrastructure Development

Corporation Limited (in short “NHIDCL”).

04. The respondent No. 2-NHIDCL came to allot said

project work’s contract to the respondent No. 6 – M/s ECI-

SRM Projects on 27.03.2018. The allotment of the project

was governed by the following schedule:-

Name of the Contractor M/s ECI-SRM Project

Letter of Award 27.03.2018

Contract Agreement 20.04.2018

Supplementary Agreement 22.11.2018

Contract Price 155.04 Cr

Length of the Project 16.990 Km

Revised date of Completion 31.03.2022

05. At the time of institution of present writ petition,

major road construction work is said to have been carried out

and completed except at four sections where road construction

work came to suffer road block. Said four sections are :-

Km 6 + 480 to Km 6 + 76

Km 11+300 to Km 11+580

Km 11+660 to KM 11+920

Km 13+200 to Km 13+460

06. At the aforesaid four sections, the nature of road

construction is meant to be that of a steep box cut road which

is form of a road construction technique used in hilly or

mountainous terrain where a deep, narrow, rectangular

shaped or U-shaped trench (the box) is excavated through a

WP(C) No. 1243/2023

Page 4 of 32

slope to create a road way. This type of road construction

method is employed often to create a direct, stable route while

minimizing the foot prints on the hilly side.

07. It would be serving the context to state here that there

are some design constraints relatable to such type of road

construction on account of the fact that because of cutting of

soil, through which road is to pass, the excavation of the

surface, the strengthening of the side slopes etc become a

matter of challenge and that requires measures to prevent

failures on steep, excavated slopes

08. During course of execution of the project work at

aforementioned locations of said road, issues of slope stability

factor relatable to the nature of the soil cropped up. The

reason for halting of the road construction at the aforesaid

three sections is said to be soil stability factor because of deep

excavation with prospect of perennial sliding tendency of stop

box cut construction at the aforesaid three sections..

09. For dealing with the work stopping issues at said

sections, the Managing Director of the respondent No.2-

NHIDCL carried out a review meeting on 18.12.2019 which

was followed by involvement of all the concerned stakeholders.

In this meeting, it is said to have been decided to get the strata

geologically examined as per the site conditions and a feasible

slope stabilization proposal.

10. There is said to have taken place follow up inspection

by the officials of the respondents No. 2, 3 & 4 joined by the

respondent No. 5 – the Consultant of the respondent No. 2, the

respondent No. 6 and its representatives and its deputed

Geologist and Design Director on 16.06.2020.

WP(C) No. 1243/2023

Page 5 of 32

11. The purported inspection is said to have resulted in

the respondent No. 6 – M/s ECI-SRM Project’s engaged and

deputed Geologist-Mr. K. S. Jamwal (ex -Deputy Director

General, Geological Survey of India) coming up with a

purported report and putting up the following conclusions:-

“Conclusion

➢ After taking into considerations of all the prevailing

geological conditions and ground realities. It is

recommended that alignment of the proposed road

may be detoured for this section to avoid possibility

of threat to the road users and local populace. It

would be better if we opt for a tunnel in this

section.

➢ The proposal of tunnel should not be viewed from

prism of financial implications only, because it will

provide long term stability and safety. However,

the provision of detouring of this section, may also

be worked out for economical and reliable aspects.

Moreover, such a huge cutting of overburden to

form box-cut is not advisable because it will remain

constantly under safety threat. Even cut & cover

section does not seem favourable for this length

because for that also, we have to excavate first up

to a depth of 43 m which may cause serious

hazards and unfortunate human suffering before

we fill it with cover.

➢ Proposal for 120 m long tunnel, between CH

13+300 and CH 13+420 seems feasible and

permanent remedial measures for anticipated

serious hazards of landslides within this most

critical section where cutting of 43 m overburden is

involved. Moreover, excavation of proposed tunnel

will have similar favourable geological conditions

WP(C) No. 1243/2023

Page 6 of 32

like the CHENANI-NASHRI TUNNEL. In this case,

the intersection of the tunnel axis with geometry of

rocks is more favourable than that of CHENANI-

NASHRI TUNNEL.

➢ If such changes are feasible and possible at this

stage, then a balanced view of both situations may

be worked out from point of view of Techno -

economic feasibility to arrive at final decision. But

undersigned is of the opinion that option of the

detouring seems appropriate and technoeconomical

than all other options.

Final Conclusion:

1. Box Cut @ Ch 6+470 to 6+700: Detouring of this

site be tried through available natural gap near by

the present site. Else 100 M cut and cover method

can also be adopted to avoid the risk of slope

failure.

2. Box Cut @ Ch 11+340 to 11+540: Detouring of this

site be tried through available natural gap near by

the present site. Else 100 M Tunnel can also be

adopted, to avoid the risk of slope failure.

3. Box Cut @ Ch 11+700 to 11+960: Detouring of this

site be tried through available natural gap near by

the present site. Else 120 M Tunnel can also be

adopted, to avoid the risk of slope failure.

4. Box Cut @ Ch 13+220 to 13+460: Detouring of this

site be tried through available natural gap near by

the present site. Else 120 M Tunnel can also be

adopted, to avoid the risk of slope failure.”

12. The purported report of Mr. K. S. Jamwal (ex-Deputy

Director General, Geological Survey of India) annexed with the

WP(C) No. 1243/2023

Page 7 of 32

writ petition bears the signature of said Mr. K. S. Jamwal as

well as of Design Director, co-author to the said report while

bearing date 15.09.2020.

13. As against the aforesaid said report dated 15.09.2020

generated from the end of the respondent N0.6 , the

respondent No. 5, in its communication No. S-NHIDCL-SQS-

885 dated 03.10.2020 (Annexure-III, Page 56 to the writ

petition) addressed its own take to the respondent No. 4 –

General Manager (P), PMU-Akhnoor. In this communication of

the respondent No. 5, reference is being made to two

communications dated 10.07.2020 & 16.09.2020 from the

end of the respondent No. 6 - M/s ECI-SRM Projects.

14. In its above said communication dated 03.10.2020,

the respondent No. 5 refers to the discussion with the

respondent No. 6 and the Geologist . In this regard, the

proposal submitted by the respondent No. 6 came to be cited

which proposal is as under:-

S.

No.

Description

of

Option

Chainage Length

(in Mtr)

1 Realignment/

Detouring

Ch. 6+480 to 6+760 280 M

Ch. 11+300 to

11+540

240 M

Ch. 11+660 to

11+920

260 M

Ch. 13+200 to

13+460

260 M

Total 1040 M

2 Tunnel

Sections

Ch. 6+540 to 6+660 120 M

Ch. 11+380 to

11+480

100 M

Ch. 11+760 to

11+880

120 M

Ch. 13+300 to

13+420

120 M

Total 460 M

3 Cut & Cover Not Feasible as per -

WP(C) No. 1243/2023

Page 8 of 32

Sections contractor's

Proposal

15. It came to be conveyed by the respondent No. 5, in its

very said communication dated 03.10.2020 , that upon

examination by the respondent No.5’s Highway Design Expert,

the proposal of tunnels is not feasible in the given geological

conditions due to inadequate ground mass. Insofar as

proposal for realignment/detouring is concerned, the same is

said to be having the concurrence of the respondent No. 5 with

the following ramifications:

“The proposal involves an approximately 520 M

increase in length of the project highway in the affected

sections as per the details given below:-

S.

No.

Box Cut

Chainage

Original

Length

(m)

Maximum

Height

(in m)

Realignment

/ Detouring

Chainage

Revised

Length in

Detouring

(m)

Variation

in

Length

(m)

1 6+480 to

6+760

280 30.68 6+480 to

6+990

430 150

2 11+300

to

11+540

240 34.48 11+280 to

11+560

320 80

3 11+660

to

11+920

260 37 11+760 to

11+880

410 150

4 13+200

to

13+460

260 43 13+280 to

13+540

400 140

1040 Total 1560 520

Increase in length due to detouring was proposed

to be not involving any increase in total project cost as

the same could be adjusted out of saving in length of

project highway due to restricting scope of the package

upto 15+600 instead of 16+990 as per original scope of

contract.”

WP(C) No. 1243/2023

Page 9 of 32

16. The respondent No. 2 was, thus, urged to take a

suitable decision regarding disposal of ROW approximately

2.50 hectare already acquired at said box cut sections which

would be rendered surplus.

17. Thus, the respondent No. 5 extended its in-principle

approval for realignment/detouring of the subject highway in

the box cut sections as per the details set out hereinabove.

18. On 26

th

& 27

th

of September, 2020, there is said to

have taken place Special Project Monitor’s (SPM) visit to the

site to come up with an opinion that option of

realignment/detouring is feasible and economical. Mention of

this fact is found made in communication No. NHIDCL/PMU -

AKH/AE/C-S/2020-21/802 dated 20.10.2020 (annexure-IV,

page 59 to the writ petition) of the respondent No. 4 – General

Manager (P), NHIDCL, PMU -Akhnoor addressed to the

respondent No. 3 – Executive Director (P), NHIDCL, RO -

Jammu.

19. The respondent No. 4- General Manager (P), NHIDCL,

PMU-Akhnoor from his end through aforesaid communication

dated 20.10.2020 came up with his take and opinion that

option for realignment is not a sensible provision and that

construction of box cut after securing the slopes is feasible

and viable so as to continue with construction of open box cut

as planned. This opinion of the respondent No. 4- General

Manager (P), NHIDCL, PMU -Akhnoor was however relatable

to section 6+480 to 6+760 whereas with respect to other three

sections, the respondent No. 4 - General Manager (P),

NHIDCL, PMU -Akhnoor endorsed the proposal for

WP(C) No. 1243/2023

Page 10 of 32

realignment/ detouring as proposed and submitted by the

respondent No. 5 in his communication dated 03.10.2020.

20. From the aforesaid communication dated 20.10.2020

of the respondent No. 4- General Manager (P), NHIDCL, PMU -

Akhnoor, an inference is dished out as if the concern of the

petitioners with respect to the original plan of construction of

the national highway at the three sections/stretches is well

meaning and well placed.

21. There is said to have taken place a site visit of the

Managing Director of the respondent No. 2 – NHIDCL on

28.07.2021 as is finding mention in communication No.

NHIDCL/RO(Jammu)/JMU/C -S/2021-22/631 dated

03.08.2021( Annexure –X, Page 61 with the writ petition) from

end of the Deputy General Manager (P), NHIDCL , RO-

Jammu to the respondent No. 4 – General Manager (P),

NHIDCL, PMU-Akhnoor. In terms of said visit of the Managing

Director of the respondent No. 2 – NHIDCL on 28.07.2021,

the realignment was contemplated to be necessary in order to

bypass proposed box cuts at three locations while

simultaneously referring to carrying out of the work as per

approved scope at the location of the proposed box cuts. In

this regard, para 6 of this communication is worth

reproducing ………………................

………………………………………………

“6. As discussed during the site visit of MD

NHIDCL on 28.07.2021, re -alignment necessary

in order to bypass proposed box cuts at 03

locations and construction of Major Bridge No. 4

not to be included in the Change of Scope

proposal. Work is to be carried out as per

approved scope at the location of the proposed

WP(C) No. 1243/2023

Page 11 of 32

box cuts and the location of the Major Bridge No.

4. Authority Engineer in consultation with the

contractor is required to work out the revised

cost of the work considering only the Change of

Scope whose in principle approval was obtained

from NHIDCL HQ (namely re -alignment of Major

Bridge No. 2 and RRM Drain and Maintenance

work for 4.200 Kms) and the same may be

submitted to the Authority at the earliest.”

22. On the part of the respondent No. 4 – General Manger

(P), NHIDCL, PMU-Akhnoor, a communication No.

NHIDCL/PMU -AKH/AE/NH -244/CS/2021-22/591 dated

03.09.2021 came to be addressed to the respondent No. 5. In

this communication, the respondent No. 4- General Manager

(P), NHIDCL, PMU-Akhnoor is found to be referring to letter

No. ECI -SRM/J&K/CSD/2021 -22/401-402 dated

24.08.2021 of the respondent No. 6 on the issue of

requirement related to additional ROW for construction of a

box cut from Ch. 13+180 to 13+490 vis-à-vis Detour.

23. The said proposal of the respondent No. 6 is said to

have been diligently discussed to announce that the decision

was to go ahead with the present box cuts meaning thereby

originally conceived and planned road way construction is to

be carried out.

24. The respondent No. 4- General Manager (P), NHIDCL,

PMU-Akhnoor in his said communication dated 03.09.2021

proposed review of the case in the light of the points which are

set out herein below:-

a. There will be a need for a proper slope/angle of

repose which will have to be provided to cut faces

WP(C) No. 1243/2023

Page 12 of 32

of the box cuts for stability. To provide slope at

even minimum 60, an additional 30 meter wide

extra land along the box cut will be required to

be acquired as only total 24 meter wide land has

only been acquired as on today. This additional

land will be more or almost same if the box cut

with 42 meter height is avoided by taking a

detour. Moreover 42 meter high slope will never

be stable and safe. It will kept bleeding and

causing accidents.

b. The soil required to be dug for these three box

culverts with 43 meter height will cumulate to

almost 6 to 7 lakhs cubic meters which will

require a very huge area to stack the muck. The

land fill area is not available.

25. In his above said communication dated 03.09.2021,

the respondent No. 4 – General Manager (P), PMU-Akhnoor is

referring to a discussion during SPM’s visit and also during

the visit of MD of the respondent No. 2-NHIDCL by reference to

which it was decided to go ahead with present box cuts and,

accordingly, the respondent No. 6 was directed to proceed but

then the respondent No. 4 – General Manager (P), PMU -

Akhnoor brings in reference of severe rains bringing technical

problems for which review on the above mentioned points was

proposed.

26. On the part of the Deputy General Manager (P),

NHIDCL, RO -Jammu communication No. NHIDCL/

RO(Jammu)/JMU/C -S/2021-22/964 dated 20.09.2021

came to be addressed to the respondent No. 4 – General

Manager (P), PMU-Akhnoor by reference to review conducted

by the MD of the respondent No. 2 on 20.09.2021. In para 7

WP(C) No. 1243/2023

Page 13 of 32

of this communication, it came to be observed and recited that

during the site visit of MD of the respondent No. 2-NHIDCL on

28.07.2021 re-alignment being necessary in order to bypass

proposed box cuts at three locations and construction of major

bridge No. 4 not to be included in the change of scope proposal

as the work is to be carried out as per the approved scope at

the location of the proposed box cuts and the location of major

bridge No. 4.

27. The respondent No. 4 – General Manager (P), PMU-

Akhnoor came to address a communication

No. NHIDCL/PMU -AKH/AE/NH -244/C-S/2021-22/1077

dated 03.01.2022 to the respondent No. 3. In this

communication, the respondent No. 4 – General Manager (P),

PMU-Akhnoor in para 5 came up with the following take:-

5. Slope

protection

works for Box

cut locations:-

Since the

present

acquired ROW

was 24M

________.

As per MOM dated:

03.08.2021 of the review

meeting conducted at Jammu

under the Chairmanship of

Managing Director, NHIDCL

on 30.07.2021 after the site

visit on 28.07.2021 and

issued necessary directions as

listed below:-

Para 6 of MOM issued states

that “As discussed during the

site visit of MD NHIDCL on

28.07.2021, re-alignment is

necessary in order to bypass

proposed box cuts at 03

locations and construction of

Major Bridge No. 4 not to be

included in the Change of

Scope proposal. Work is to be

carried out as per approved

scope at the location of the

proposed box cuts and the

location of the Major Bridge

No. 4. Authority Engineer in

consultation with the

Contractor is required to work

WP(C) No. 1243/2023

Page 14 of 32

out the revised cost of the

work considering only the

Change of Scope whose in

principle approval was

obtained from NHIDCL HQ

(namely realignment of Major

Bridge No. 2 and RRM Drain

and Maintenance work for

4.200 Kms) and the same may

be submitted to the Authority

at the earliest.”

The SPM (Mr. S. K. Doon)

during site visit on 28.08.2021

while discussing the case of

Box cut Sections has

suggested that the area of

formation consists of soil

mixed with boulders and the

angle of repose is likely to be

approximately 60 degrees. As

per SPM remarks:-

a. Minimum required width

for box cut section from

Ch. 11+280 to Ch.

11+960 considering a

slope of 1H:2V shall be

(12 m + 37 m) 49 m at

the top. Approximate

quantity of excavation for

680 m long section is

likely to be more than 7

lac cum.

b. Minimum required width

for Box cut section from

Ch. 13+200 to Ch.

13+460 considering a

slope of 1H:2V shall be

(12 m + 43 m) 55 m at

the top. Approx quantity

of excavation for 260 m

long section is likely to

be more than 3 Lac cum.

The SPM in his inspection

Report dated 03.09.2021 has

suggested that either

additional land should be

acquired so that proper side

slopes are maintained to avoid

any landslides/accidents or

these sections should be

WP(C) No. 1243/2023

Page 15 of 32

developed on existing

alignment. SPM has also

suggested that same following

two options for consideration

of the Authority which were

reviewed by AE as per details

given below:-

a. OPTION-I:- Acquiring

additional land so that

proper side slopes are

maintained in deep box

cut sections to avoid any

landslides/accidents.

b. OPTION-II:- Developing

these sections on existing

alignment.

The above mentioned Options

(i.e. Option I & II) were

discussed during several

review meetings and as per

the directions of RO Jammu

vide letter No.

NHIDCL/RO(Jammu)/JMU/C -

S/2021-22/964 dated

20.09.2021. Option-I (i.e.

acquiring additional land so

that proper side slopes are

maintained in deep box cut

sections) has been considered

and included in the

Consolidated Change of Scope

proposal accordingly.

It is to be mentioned here that

the ROW width acquired at

these locations is only 24 M

but the average height of hill

cutting at these locations

requires additional width of

ROW to be acquired for proper

slope protections measures to

ensure the safety of road users

and any future landslides

obstructing the Project

highway.

Earthwork/formation cutting

for 24 m ROW has been

carried out by the contractor

(photographs enclosed) and

in-principle approval for slope

stability measures are

WP(C) No. 1243/2023

Page 16 of 32

required to proceed further.

28. Aforesaid communication came to be followed by

another communication No.NHIDCL/RO(Jammu)/AKH/ NH -

244/C-S/18(8)/2021-22/1830 dated 11.01.2022 from the

end of the respondent No. 3 to the General Manager (T),

NHIDCL HQ, New Delhi wherein in para 5(e) the following

situation came to be put up:-

5(e) Slope protection works for Box cut

locations:- Since the present acquired ROW

was 24M___________

PMU-Akhnoor &

AE's Comments

Comments/Recommendation

of RO-Jammu

As per MOM dated: -

03.08.2021 of the

review meeting

conducted at

Jammu under the

Chairmanship of

Managing Director,

NHIDCL on 30.07

2021 after the site

visit on 28.07.2021

and issued

necessary directions

as listed below:-

Para 6 of MOM

issued states that

"As discussed

during the site visit

of MD NHIDCL on

28.07 2021, re -

alignment is

necessary in order

to bypass proposed

box cuts at 03

locations and

construction of

Major Bridge No.4

The proposal for detouring at

04 Nos of Box Cut locations

was initially submitted by the

Contractor as the height of box

cuts at this location was found

to be very high between 28-45

m. However, at Km 6+480 to

Km 6+760, the said proposal

was not allowed as the work at

this location was already

initiated and the forest trees

were also cut. However, the

detouring at 03 Nos of location

was also discussed during the

visit of MD NHIDCL on 28.07

.2021 and owing to the fact

that, the detouring would

require additional land

acquisition which would lead

to the further delay in the

completion of the project under

PMDP-2015, which is already

lagging behind the scheduled

date of completion, instruction

was issued by MD NHIDCL to

drop the proposal for detouring

WP(C) No. 1243/2023

Page 17 of 32

not to be included in

the Change of Scope

proposal. Work is to

be carried out as per

approved scope at

the location of the

proposed box cuts

and the location of

the Major Bridge No.

4. Authority

Engineer in

consultation with

the Contactor is

required to work out

the revised cost of

the work

considering only the

Change of Scope

whose in principle

approval was

obtained from

NHIDCL HQ (namely

realignment of Major

Bridge No. 2 and

RRM Drain and

Maintenance work

for 4.200 Kms) and

the same may be

submitted to th e

Authority at the

earliest."

The SPM (Mr. S. K.

Doon) during site

visit on 28.08.2021

while discussing the

case of Box cut

Sections has

suggested that the

area of formation

consists of soil

mixed with boulders

and the angle of

repose is likely to be

approximately 60

degrees. As per SPM

at these locations and carry

out the work as per the

Schedule-B of Contract

Agreement with requisite slope

protection works.

Accordingly, this office has

directed the Contractor to

carry out the work at these

locations as per Schedule-B,

however, it may also be noted

that the ROW acquired at

these locations is only 24 m

and since the overburden at

these locations were in the

range of 28-45 m, hence, as

highlighted by SPM, Shri SK

Doon in his inspection report

that considering a slope of

1H:2V, the minimum width

required for box cut sections at

Ch 11+280 to Km 1l+960 is 49

m at the top and requires

additional land and

accordingly at Ch.13+200 to

13+460, the minimum width

required at the top for BOX

Cut was determined as 55 m,

with a requirement of

additional land. The SPM

suggested two options as

indicated by PMU-Akhnoor viz.

(i) Acquiring additional land so

that proper side slopes are

maintained in deep box cut

sections & (ii) developing these

sections in existing road. The

same has been discussed

several times at this office and

as per the directions issued by

this office vide letter dated 20

09 2021, the option-l has been

considered by AE & GM(P),

PMu-Akhnoor for

consideration considered

WP(C) No. 1243/2023

Page 18 of 32

remarks: Minimum

required width for

box cut section from

Ch. 11 +280 to Ch.

11+960 considering

a slope of 'lH:2V

shall be (12 m + 37

m) 49 m at the top.

Approximate

quantity of

excavation for 680

m long section is

likely to be more

than 7 lac cum.

a. Minimum

required width

for Box cut

section from

Ch.13+200 to

Ch. 13+460

considering a

slope of lH:2V

shall be (12 m

+43 m) 55m at

the top. Approx

quantity of

excavation for

260 m long

section is likely

to be more

than 3 Lac

cum.

The SPM in his

inspection Report

dated 03.09.2021

has suggested that

either additional

land should be

acquired so that

proper side slopes

are maintained to

avoid any

landslides/accidents

or these sections

should be developed

under clause 13 1.3 (iii).

In this context, the COS

proposal has been examined in

this office and it has been

observed that instead of 04

locations, the contractor has

submitted the proposal for 06

locations and the additional 02

box-cut locations involves

acquisition of Forest land. The

box cut proposed at Ch 6+020

to Ch.6+250, involves Private

land on LHS and Forest land

on RHS, Further, the box cut

at Ch. 6+500 to Ch.6+700

involves Forest land at both

LHS and RHS. The EPC

Contractor and AE has

previously been directed by

this office, that COS regarding

slope protection requiring

additional acquisition of Forest

land shall not be considered

since the whole process is time

taking and shall delay the

completion of the project.

Therefore, this office is of

opinion that the proposal for

COS for slope protection works

viz. catchment drain, chute

drain, matting and hydro

seeding as well as additional

excavation work at these

locations for maintaining the

requisite slope is

recommended for 04 locations

only as per Annexure-G for

according in-principle approval

and issuing of Change of Scope

order as per clause 13.2.4 of

Contract Agreement.

WP(C) No. 1243/2023

Page 19 of 32

on existing

alignment. SPM has

also suggested the

same following two

options for

consideration of the

Authority which

were reviewed by AE

as per details given

below:

a. OPTION-I:-

Acquiring

additional land

so that proper

side slopes are

maintained in

deep box cut

sections to

avoid any

landslides/

accidents.

b. OPTION-Il: -

Developing

these sections

on existing

alignment.

The above

mentioned Options

(i.e. Option I & II)

were discussed

during several

review meetings and

as per the directions

of RO Jammu vide

letter No.

NHIDCL/RO

(Jammu)/JMU/C -

S/2O21-22/964

dated:- 20.09.2021,

Option-l (i.e.

acquiring additional

land so that proper

side slopes are

maintained in deep

box cut sections)

has been considered

WP(C) No. 1243/2023

Page 20 of 32

and included in the

Consolidated

Change of Scope

proposal

accordingly.

It is to be mentioned

here that the ROW

width acquired at

these locations is

only 24 M but the

average height of hill

cutting at these

locations requires

additional width of

ROW to be acquired

for proper slope

protections

measures to ensure

the safety of road

users and any

future landslides

obstructing the

Project highway.

Earthwork/

formation cutting for

24 m ROW has been

carried out by the

contractor

(photographs

enclosed) and in-

principle approval

for slope stability

measures are

required to proceed

further.

29. On the other hand, the Sub -Divisional Magistrate,

Chenani by virtue of his communication No. SDM/C/2021 -

22/1629-35 dated 04.02.2022 addressed to the Deputy

Commissioner, Udhampur came to adv ert to the issue of road

blockade at the aforesaid stretches stating therein that the box

cutting at eight locations have been done in an unplanned way

WP(C) No. 1243/2023

Page 21 of 32

as the land cuts are vertical despite the soil being very loose

extremely prone to slides and threat to public life and property

for which NHIDCL needs to take immediate preventive and

corrective measures. So much so, the box cuts falling in the

section in Village Chullyar are said to have caused huge losses

to public/private land and other properties.

30. The respondent No. 5 was required to consult the

respondent No. 6 to work out the revised cost of the work

considering the change of scope which might become

necessary for slope construction work at the location of the

box culverts as per requirement at the site.

31. It seems that it is at this stage of the situation that the

intervention from the end of the petitioner No. 4 – Sudesh

Chander came up with a representation addressed to the

Deputy Commissioner, Land Acquisition Udhampur and the

respondents No. 3 to 6 wherein the respondent No. 4 by

reference to letter dated 20.10.2020 of the respondent No. 4 –

General Manager (P), PMU -Akhnoor came to exploit the

recommendation that detouring/realignment needs to be done

because of slope stabilization issues which would always be

prone to risk rendering maintenance of national highway on

the locations very expensive. The petitioner No. 4 – Sudesh

Chander in his representation objected that the course of

action on the part of the respondent No. 3 on his own to

acquire more land for increasing the road width at the

aforesaid locations was in disregard to the recommendations

on the issue.

32. The respondent No. 4 – General Manager (P), PMU-

Akhnoor from his end came to address communication No.

WP(C) No. 1243/2023

Page 22 of 32

NHIDCL/PMU -AKH/C-S/R&P.G/2022-23/738 dated

09.11.2022 in response to the petitioner No. 4’s e-mail dated

03.11.2022. The respondent No. 4 – General Manager (P),

PMU-Akhnoor in his said communication dated 09.11.2022

meant to object to the petitioner No. 4 as to how he came to

acquire the official correspondence related to NHIDCL and its

officials.

33. The petitioner No. 4 from his end by virtue of his letter

dated 15.11.2022 addressed to the respondent No. 4 –

General Manager (P), PMU-Akhnoor came to refer that the

communications related to the subject are there in the public

domain through the reference of the respondent No. 5 as well

as the respondent No. 6. The petitioner No. 4 came to impress

upon the respondent No. 4 – General Manager (P), PMU-

Akhnoor to came to allege that the respondent No. 4 – General

Manager (P), PMU-Akhnoor was in hand in globe with the

respondent No. 6.

34. As per the petitioners, their concern was brought to

the notice of Member Parliament - Shri Jugal Kishore Sharma

and other concerned public authorities for revisiting the

original plan of construction of the road at the aforesaid three

locations/sections.

35. The petitioners at this stage had come forward with

the institution of the present writ petition on 15.05.2023

along with the photographs of the site in reference attached for

the five sections showing box cut No. 1.

36. In their writ petition, the petitioners in para 22 came

forward with the grounds of challenge addressed against the

casual approach of the respondents with respect to

WP(C) No. 1243/2023

Page 23 of 32

construction of the road in the form of High Gallas/Open Box

Cut at three locations i.e., Ch. 11+300 to 11+540, 11+660 to

11+920 & 13+200 to 13+460 stating the same to be against

the proposal and recommendations of the respondent No. 4 –

General Manager (P), PMU-Akhnoor and the respondent No. 5.

37. The petitioners in the grounds of challenge pleaded

that proposed alignment of road with Deep Gallas/ Box Cut is

not viable in the area as per the expert Geologist and despite

his report and recommendations endorsed by the officials of

NHIDCL, the respondent No. 2 is not accepting the same

which action of the respondent No. 2 is, thus, said to be

arbitrary and unfair lacking bona fide. Thus, much emphasis

has been placed upon so-called expert report of Geologist-Mr.

S. K. Jamwal nominated by none else than the contractor-

respondent No. 6 whose report then came to be endorsed and

recommended by the respondent No. 4 – General Manager (P),

PMU-Akhnoor joined by the respondent No. 5. The petitioners,

thus, asked for the following prayers:-

“Writ petition under Article 226 of the Constitution of

India for the issuance of an appropriate writ, direction

or orders commanding the respondent No.2 to 4 to

execute the work of widening and upgradation on

Chenani- Sudhmahadev Section of NH -244 by

accepting the proposal/ recommendation of the

Authority's Engineer (Respondent No. 5) dated

O3.1O.2O2O forwarded to respondent No. 4 for

realignment/ detouring option at 03 Locations i.e.

Ch.11+30O to 11+540, 11+660 to l7+92O and 13+200

to 13+460 which is based upon the report of Geological

Expert Sh. K.S. Jamwal (Retd. Deputy Director,

Geological Survey of India) instead of the construction

WP(C) No. 1243/2023

Page 24 of 32

of High Gallas/ Box Cut which being unstable shall be

prone to landslides and shooting stones leading to risk

of loss of lives not only of the residents of the area but

also the commuters plying through the said sections of

the NH-244;

With further writ direction or order commanding the

respondent No. 2 and 3 to accept the proposal/

recommendations dated 20.lO.2O2O of the respondent

No. 4 for realignment/ detouring option at 03 Locations

i.e., Ch.11+3OO to l1+540, 11+660 to 11+920 and

13+200 to 13+460 having being recommended for in

principal approval, which is not only based upon the

Expert opinion of the Authority's Engineer but also the

Special Project Monitor;

With further issuance of appropriate writ direction or

order restraining the respondent No.2 to 6 to execute

the work at 03 Locations i.e., Ch.11+300 to 11+540,

11+660 to l7+92O and 13+2OO to 13+460 by

construction of High Gallas/ Open Box Cut being not

only against the expert recommendations but being

prone to collapse of side slopes which could lead to

man-made disaster in the area of the petitioners.

With further issuance of appropriate writ direction or

order which this Hon'ble Court may deem fit and proper

in the facts and circumstances of the writ petition.”

38. In response to the writ petition, this Court, by virtue

of an order dated 19.05.2023, came to place status-quo

direction as a result whereof situation came to be held up.

39. From the end of the respondents No. 1 to 4, reply cum

objections to the writ petition came to be submitted on

WP(C) No. 1243/2023

Page 25 of 32

02.08.2023 accompanied with an application for vacation of

status-quo direction as set out in the order dated 19.05.2023

by this Court.

40. The reply/objections on behalf of the respondents No.

1 to 4 was signed by the respondent No. 4 – General Manager

(P), PMU-Akhnoor supported by an affidavit of incumbent Shri.

S. P. Singh Sangwan.

41. Along with their reply/objections, the answering

respondents No. 1 to 4 came up with set of supporting

communications as annexures to assert that the writ petition

is based not on true facts and without any locus-standi on the

part of the petitioners.

42. In their reply/objections, the answering respondents

No. 1 to 4 came to submit that the MD of the respondent No. 2

on the basis of his visit on 28.07.2021 had directed that the

upgradation of the road shall be carried out as per the original

alignment including the Deep Box Cuts for which purpose the

SPM in his report dated 03.09.2021 suggested additional land

to be acquired for proper site slopes maintenance to avoid any

landslide/accidents.

43. In the reply/objections, the respondent No. 4 –

General Manager (P), PMU-Akhnoor came to submit that the

respondent No. 6 was directed to go ahead with the

construction of box culverts and the respondent No. 5 was

directed to propose slope protection measures which are

necessary as per the site conditions along with protection to

work out the additional land acquired as per site conditions so

as to maintain stable slope after proposing slope protection

measures.

WP(C) No. 1243/2023

Page 26 of 32

44. By reference to a communication dated 20.09.2021, a

direction for carrying out the work as per the original

alignment was emphasized.

45. By reference to deliberations of a meeting held on

04.10.2022 under the Chairmanship of MD of the respondent

No. 2, the directions issued to the respondent No. 6 to execute

the work as per the provisions of the contract without any

additional financial implications due to require d slope

protection has been reiterated with an observ ation that

additional land at the box cut locations to be provided by the

respondent No. 5 to the respondent No. 6 for which additional

required land is said to have been acquired to the extent of

1.86 Hectares.

46. From the end of the petitioner No. 1 – Surinder Singh,

a Supplementary Affidavit dated 01.04.2024 came to be

submitted in order to counter the factual assertions made in

their reply/objections on behalf of the respondents No. 1 to 4.

47. In his Supplementary Affidavit, the petitioner No. 1 –

Surinder Singh came up with emphasis that the respondents

No. 1 to 4 have neglected the report of the Geologist appointed

by the respondent No. 6 in which it is clearly mentioned that

detouring of the road in issue should be tried/attempted to

avoid the risk of slope failure and in the alternative, the

recommendation for 100 M cut and cover method instead of

box cuts. The Geologist’s report is said to have received no

consideration at all. In the supplementary affidavit, the

petitioner No. 1 came to reiterate that Special Project Monitor’s

(SPM) report dated 01.10.2020 being contrary to its second

report dated 03.09.2021 in the context of which realignment

WP(C) No. 1243/2023

Page 27 of 32

option is the better option reiterated by the respondent No. 5

as well.

48. On behalf of the respondent No. 5, reply to the writ

petition came to be filed on 14.03.2024. In his objections, the

respondent No. 5 came forward with a statement that on the

basis of visit of MD of the respondent No. 2 – NHIDCL on

28.07.2021, the direction was to carry out the upgradation of

the road as per the original alignment including the deep box

cut. In his reply, the respondent No. 5 comes to state that

while discussing the case of box cut sections, the Special

Project Monitor (SDM) in his report dated 03.09.2021 has

come to suggest that additional land should be required for

proper side slopes to be maintained to avoid any

landslide/accidents, on the basis whereof the respondent No.

6 came to be directed to go ahead with the construction of box

culverts and the respondent No. 5 was directed to propose

slope protection measures necessary as per the site conditions

besides direction for working out additional land acquired as

per site conditions so as to maintain stable slopes after

proposing slope protection measures.

49. On behalf of the respondent No. 6, reply/objections to

the writ petition came to be filed on 22.04.2024. In its reply,

the respondent No. 6 has come to place reliance upon

Geologist – Shri K. S. Jamwal’s report to say that if road

construction is to be carried out as per the original layout then

it may lead to geological disturbances in the soil/rock mass in

the affected sections besides an environmental damage which

shall adversely affect safety of the local public and the road

users travelling on these highway sections.

WP(C) No. 1243/2023

Page 28 of 32

50. The respondent No. 6, in its reply has emphasized

that the geological study report along with its various technical

proposals submitted by the Geological Expert – Shri S. K.

Jamwal should be considered in the large interest of stability

of the highway project and for the sake of public safety. The

respondent No. 6 along with its reply has annexed a technical

report from the end of the Design Director of the respondent

No. 6. In this technical report, emphasis has been again

referred to that of Geologist-Shri K. S. Jamwal’s report and

recommendations and the consideration received from the end

of the respondents No. 4 & 5.

51. The direction of MD of the respondent No. 2 – NHIDCL

on 28.07.2021’s visit to go ahead with the original plan of

construction for open box cut sections with suitable slope

protection/stabilization measures was referred to be

technically neither in line with the measures recommended by

the Geology domain expert nor in line with the respondent No.

5’s recommendation in the matter. In this regard reference has

been made to the provisions of clause 7.9.3 of IRC:SP;48-1998

with respect to deep box cuts which is reproduced herein

under:-

“Box cut: At steep and narrow spurs, box cut or

through cuts may be provided. These reduce the length

of the road and also improve the radius of curves. Such

cuts, however, have their own problems. During

excavation, the cutting and disposal of spoils take more

time and efforts as compared to hill side cut. Drainage

of road surface and surrounding areas is difficult. Sub-

surface springs get activated on the formation during

wet weather. If the soil is unstable box cuts become

trouble spots due to frequent slides and blockage of

road requiring expensive protective works like breast

walls, sub-soil drains, catch water drains etc. A careful

study and comparative cost analysis of reduction in

WP(C) No. 1243/2023

Page 29 of 32

length vis-a-vis provision of additional protective works

should be made before taking a decision on providing

box cuts. A typical cross section of box cut is shown in

Fig. 7.12.”

52. It is in aforesaid backdrop of chronology of facts and

circumstances that the petitioners are seeking issuance of an

appropriate writ, direction or order thereby commanding the

respondents No. 2 to 4 to execute the work of widening and

upgradation of Chenani-Sudhmahadev Road Section of NH -

244 by accepting the proposal/ recommendation of the

respondent No. 5 in terms of communication dated

03.10.2020 forwarded to the respondent No. 4 – General

Manager (P), PMU - Akhnoor, NHIDCL for

realignment/detouring option at three locations based upon

report of Geological Expert – K. S. Jamwal instead of going

ahead with the construction of High Gallas/ Box Cut which is

claimed to be unstable and prone to landslides and shooting

stones leading to the risk of loss of lives of the residents of the

area but also the users of Chenani-Sudhmahadev NH -244 at

aforesaid sections.

53. The petitioners also seek an appropriate writ direction

or order commanding the respondent No. 2 – NHIDCL and the

respondent No. 3 – Executive Engineer (P), NHIDCL for

accepting proposal/recommendations of the respondent No. 4

– General Manager (P), PMU -Akhnoor for

realignment/detouring option at three given locations having

been recommended and accepted in principle based not only

upon expert opinion of the respondent No. 5 but also of the

Special Project Manager (SPM).

54. Thus, in a way, this Court is being called upon by the

petitioners to prohibit the respondents from going ahead with

WP(C) No. 1243/2023

Page 30 of 32

the original plan of construction of the Chenani-Sudhmahadev

NH-244 by reference to the three/four locations in reference

said to be problematic in terms of construction of the road to

pass through said three/four locations.

55. Before this Court examines its competence to issue so

called expert like direction/order unto the respondent No. 2 in

particular i.e., NHIDCL to abandon the original scheme of

things in the construction of NH-244 at aforesaid three

locations, this Court needs to bear in mind the mandate of the

Hon’ble Supreme Court of India providing scope for indulgence

in such like situations/cases, which is set out in the

judgments in the following cases:-

1) 1991 (2) SCC 539: Dahanu Taluka

Environment Protection Group and another

Vs. Bombay Suburban Electricity Supply

Company Limited and others.

2) 1999 (1) SCC 492 : Raunaq International

Ltd. v. I.V.R. Construction Ltd. & Ors.

3) 2000 (10) SCC 664: Narmada Bachao

Andolan vs Union of India And Others

4) 2016 (6) SCC 408 : Centre For Public

Interest Litigation vs U.O.I.& Ors.

5) 2001 (3) SCC 572 : The Project Director,

Project Implementation Unit Vs P. V.

Krishnamoorthy & others.

6) 2022 (11) SCC 1: Rajiv Suri Vs D elhi

Development Authority.

7) 2022 (6) SCC 127: N.G. Projects Limited v.

Vinod Kumar Jain.

8) 2024 (1) SCC 716 : Delhi International

Airport Vs Union of India and others.

WP(C) No. 1243/2023

Page 31 of 32

9) 2025 SC 2901 : Bindu Kapurea Vs

Subhashish Panda & Ors.

56. This Court has no iota of doubt that the present writ

petition has a taint of being a sponsored litigation and that too

prompted by and at the end of the respondents No. 5 to 6.

57. To put it more simply, the respondents No. 5 to 6

seem to have self invited this writ petition from the end of the

four petitioners who otherwise cannot be assumed to have

such a passionate indulgence in the matter of tracking the

development project of Chenani -Sudhmahadev NH -244

construction project to the extent of knowing each and every in

and out project related nuisances.

58. This Court has not come across with any averment

from the end of the petitioners in the entire writ petition as to

how they were able to get all the purported requisite interest

and information forming subject matter of the writ petition as

surely not by exercise of their right to information under the

Right to Information Act, 2005.

59. Even if this Court were to make concession for the

bona fide of the petitioners that as being proactive residents of

the area being concerned with the ongoing construction of

Chenani-Sudhmahadev NH-244, still this Court would not be

in a position to assume the driver seat by substituting the

respondent No. 2 – NHIDCL to direct as to how the

construction of the road at three sections/stretches is to be

carried out or ought to be carried out.

60. Factually gathering from the standpoint of the

respondent No. 2 – NHIDCL, this Court cannot do fault finding

with the final decision of the respondent No. 2- NHIDCL in

WP(C) No. 1243/2023

Page 32 of 32

terms whereof the construction of the road at three

sections/stretches has been asked to be carried out as

originally conceived with all safety provisions having been

resorted to by the respondent No. 2- NHIDCL at its end.

61. In case the Chenani-Sudhmahadev NH -244 would

ever suffer any mishap at the aforesaid three sections as

apprehended by the petitioners, then surely the culpability

and accountability of the respondent No. 2- NHIDCL would be

there to attend the delinquence and deficiency of the

respondent No. 2 – NHIDCL but as on date when the writ

petition came to be filed and the case has been heard, this

Court cannot assume that the respondent No. 2 – NHIDCL is

adamant to undertake road construction at three

sections/stretches on a risk and vulnerable note.

62. Therefore, this Court finds lack of bona fide at the end

of the petitioners as well as lack of cause of action at their

disposal to come up with the present writ petition which is

held to be misconceived and, accordingly, dismissed.

63. Any interim direction operating in the present writ

petition shall also stand dismissed.

64. The detailed judgment is following the order dated

25.09.2024 vide which the petition was ordered to be

dismissed as is hereby being done.

(Rahul Bharti)

Judge

Jammu

12.03.2026

Muneesh

Whether the judgment is speaking : Yes / No

Whether the judgment is reportable : Yes / No

Description

Legal Notes

Add a Note....