criminal appeal, evidence, conviction
0  24 Aug, 2022
Listen in 01:59 mins | Read in 25:00 mins
EN
HI

Pushpendra Kumar Sinha Vs. State of Jharkhand

  Supreme Court Of India Criminal Appeal /1333/2022
Link copied!

Case Background

As per the case facts, the appellant challenged an order that dismissed his application for discharge in a criminal case involving charges under the Indian Penal Code and the Prevention ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

REPORTABLE

IN THE SUPREME COURT OF INDIA

CRIMINAL APPELLATE JURISDICTION

CRIMINAL APPEAL NO.1333  OF 2022

[ARISING OUT OF SLP (CRL.) NO.3440 OF 2021 ]

PUSHPENDRA KUMAR SINHA     …..APPELLANT

VERSUS

STATE OF JHARKHAND      ..…RESPONDENT

J U D G M E N T

J.K. Maheshwari, J.

Leave granted. 

2.The   Appellant   has   assailed   the   final   judgment   dated

06.01.2020 passed by High Court of Jharkhand at Ranchi in

Criminal Revision No. 1057 of 2018, by which the order dated

04.07.2018 passed by learned Special Judge, Anti­Corruption

1

Bureau   dismissing   the   application   for   discharge   filed   by   the

Appellant under Section 239 of Code of Criminal Procedure, 1973

(for short “Cr.P.C.”) in connection with Special Case No. 02 of

2011 has been affirmed. The criminal case was registered against

the   Appellant   and   others   for   commission   of   offences   under

Sections 109, 409, 420, 467, 471, 477A and 120B of Indian

Penal Code (for short “IPC”) and Section 13(1)(c) and 13(1)(d) read

with 13(2) of Prevention of Corruption Act, 1988 (for short “PC

Act”).

3.The facts briefly put are that the Appellant was working as

an Executive Engineer (Electrical) (“EE”) in the Accelerated Power

Development Reforms Program (“ APDRP”) Wing  of  Jharkhand

State Electricity Board (in short “JSEB”) from 07.12.2004. During

his   tenure   as   EE,   one   Ramjee   Power   Construction   Limited

(hereinafter “RPCL”)   was   awarded   a   contract   of   work   under

APDRP vide work order dated 27.01.2005. On account of delay in

execution of the work and to resolve the said issue, the then

Chairman   JSEB,   Mr.   Shivendu,   convened   a   meeting   on

21.12.2006, wherein he orally instructed Mr. R.P. Agarwal, the

then Chief Engineer (“CE”), to place the agenda for next board

2

meeting for termination of the contract of M/s RPCL. Prior to

convening   of   the   next   Board   meeting,   Mr.   V.N.   Pandey   was

appointed as the new Chairman, JSEB on 04.01.2007. The new

Chairman called for a meeting on 06.02.2007/07.02.2007 for the

agenda   to   review   the   progress   of   RPCL’s   work.   In   the   said

meeting, other officers of JSEB including Mr. R.P. Agarwal, CE,

had participated. In the meeting, it was mutually agreed by JSEB

and   RPCL   that   full   effort   to   complete   the   work   within   the

extended   time,   i.e.   July,   2007   shall   be   made   by   RPCL.   In

furtherance of the decision taken in the aforesaid meeting, Mr.

R.P.   Agarwal,   CE,   made   various   correspondences   reminding

RPCL to complete the pending work. On retirement of Mr. R.P.

Agarwal,   Mr.   S.C.   Shrivastava   Superintending   Engineer

(Electrical) was made in charge in place of Mr. R.P. Agarwal.

Meanwhile, RPCL sent letters dated 16.05.2007, 18.05.2007 and

08.06.2007 requesting him for further extension of time. In the

said correspondences, it was said that RPCL had already invoked

the arbitration clause on 22.12.2006, in terms of the contract

and requested JSEB for appointment of an arbitrator. The said

letters were handed over to the Appellant, on which under the

instructions, the Appellant prepared a note dated 08.06.2007

3

and   placed   it   before   the   Chairman   on   the   issue   relating   to

appointment of an arbitrator and waiver of penalty, as advised by

learned   Advocate   General   (“AG”)   of   State   of   Jharkhand   in

similarly placed transmission lines projects. 

4.Thereafter,   vide   JSEB   resolution   dated   28.06.2007,   a

committee   consisting   of   one   Mr.   GNS   Munda   (Member,

Technical), Mr. A. Banerjee (Finance) and Mr. A.K. Mishra (Law

Officer) was constituted, which on 09.08.2007 suggested three

names for appointment of an Arbitrator. Out of the three names

as   suggested,   Mr.   Ramayan   Pandey   was   appointed   as   the

arbitrator by consent. Arbitration proceedings commenced and

an interim award dated 25.11.2007 was passed in favour of

RPCL. Thereafter, an agenda accompanied with the aforesaid

award was put before Chairman, Mr. B.M. Verma prior to asking

for   an   opinion   from   the   AG,   State   of   Jharkhand,   regarding

enforceability of the award. Later, as per the opinion of the AG,

JSEB vide Board Resolution dated 05.04.2008 and 07.04.2008,

decided to implement the interim award. It is worthwhile to state

that,   Mr.   GNS   Munda   (Member,   Technical)   as   well   as   Smt.

4

Rajbala Verma (then Finance Secretary, State of Jharkhand) were

part of this Board meeting. 

5.It is pertinent to mention that, while giving effect to the

award,   JSEB   was   facing   shortage   of   funds.   However,   JSEB

decided to make internal enquiry into handling the work contract

given to RPCL. On the basis of the said enquiry, allegations of

malpractice and financial irregularity were levelled against the

Appellant and some others. The Secretary, JSEB vide letter dated

30.07.2010, made a request to the Director General of Vigilance

Bureau (“DGP”) to lodge an FIR against the Appellant and others

for offences punishable under Sections 109, 409, 420, 467, 471,

477A and 120B of IPC and Section 13(1)(c) and 13(1)(d) read with

13(2) of PC Act. Additionally, another letter dated 03.09.2010,

was issued by Smt. Rajbala Verma (then Vigilance Commissioner)

to   the   DGP,   recommending   the   same   action   against   the

Appellant. As already noted above, Smt. Rajbala Verma was also

a part of the Board meeting (being the then Finance Secretary,

State of Jharkhand) that had approved the implementation of the

arbitral   award.   In  the   said   facts,   FIR   dated   20.01.2011   was

lodged against the Appellant and other officers of the JSEB.

5

Investigation was carried out, chargesheet dated 08.01.2016 was

filed   and   cognizance   was   taken   by   the   Court   dealing   with

vigilance   cases   vide   order   dated   11.01.2016.   Thereafter,   the

Appellant moved a discharge petition under Section 239 of the

Cr.P.C.,   which  came   to  be   dismissed   by   the   learned   Special

Judge vide order dated 04.07.2018. The Court observed that

sufficient material exists to make out a prima­facie case against

the Appellant for framing of charges. 

6.Aggrieved by the same, the Appellant preferred a criminal

revision   assailing   the   aforesaid   order.   The   High   Court   vide

impugned order dismissed the revision and affirmed the order

passed   by   the   learned   Special   Judge.   The   High   Court   was

prima­facie  influenced by the fact that the previous chairman,

JSEB, Mr. Shivendu had orally instructed to put up the agenda

for termination of the contract of RPCL. On demitting the office

by the said Chairman, the Appellant had put the file noting

before   the   subsequent   Chairman   Mr.   V.N.   Pandey,   regarding

referral of the matter for arbitration without mentioning about

the instructions given by the previous Chairman, JSEB. The High

Court   found   fault   in   the   action   of   the   Appellant   of   having

6

proposed an agenda regarding wrongful implementation of the

award which was challenged belatedly. Thus, having found a

prima­facie case against the Appellant, the High Court dismissed

the revision petition.

7.Learned counsel for the Appellant, Mr. Prashant Bhushan

strenuously urged as under: 

(i)the   Appellant   was   not   having   decision­making   power   or

financial authority to carry out the contract and the award

passed. The nature of duty assigned to the Appellant was

confined to follow instructions of his superiors and by no

stretch of imagination he can be said to have the power to

refer the matter for arbitration in a case where the dispute

is arising out of a work contract between JSEB and RPCL; 

(ii)there is no concealment of the instruction of the previous

Chairman   pertaining   to   termination   of   the   contract   as

substantiated by noting dated 08.06.2007 on page no. 48 of

the APDRP file which was the next page of noting of the CE

on page no. 47, under instructions from the Chairman; 

(iii)the prosecution has concealed that the verbal instruction

for termination of contract given by the previous Chairman

7

in   the   meeting   dated   21.12.2006,   had   been   overturned

within two months by the new Chairman, Mr. V.N. Pandey

in   the   JSEB   tripartite   meeting   held   on   06.02.2007   and

07.02.2007, in which the Appellant was not a member;

(iv)the questionable noting dated 08.06.2007 of the Appellant

was based on facts and documents forming part of the

APDRP file endorsed to him by his controlling officer; 

(v)the Appellant is being prosecuted on a wrong premise from

the stage of granting time to complete the work, reference

made to arbitration and till further directions for making the

payment for the interim award passed against JSEB, in

favour of the RPCL. He was not a part of the decision­

making process or of taking further steps to implement the

said   award.   Thus,   culpability   as   alleged   against   the

Appellant, on the pretext of not putting up the agenda for

cancellation of the contract amounts to abuse of the power

and prima­facie, no case to prosecute him is made out;

(vi)there is no allegation of illegal gratification, undue benefit or

disproportionate assets qua the Appellant  in the FIR or

charge­sheet which is also backed by the income tax records

of the Appellant; 

8

(vii)prosecution has failed to establish any nexus between the

Appellant and RPCL to whom the benefit is alleged to have

been made; 

(viii)while   granting   bail   to   the   Appellant   on   merits,   it   was

categorically observed by the High Court that the Appellant

had   put   up   the   matter   before   higher   authorities   for

instructions   before   proceeding   further   and   did   not   act

unilaterally;

(ix)except for the Director of Finance, none of the decision­

making authorities namely, members of Central Purchase

Committee and the Board of JSEB have been made accused

in this case;              

8.Per contra, learned counsel for the Respondent­State has

argued in support of the concurrent findings of both the Courts

and contended that the entire factual gamut of the instant appeal

stems  around   the   pleadings  of   defence   including  reliance  on

documents which cannot be permitted to be raised at this stage.

It is further urged that at the stage of framing of charge, the

scope of interference is limited, and the Court is not required to

see as to whether there are sufficient grounds for conviction. The

9

Court has to only see the material collected during investigation

and on consideration of the same, a prima facie case is made out

or not. 

9.After having heard learned counsel for the parties and on

perusal of the record, which reveals that after the board meeting

dated 21.12.2006, the then Chairman Mr. Shivendu had orally

instructed the then CE, Mr. R.P. Agarwal to place the agenda for

termination of the contract of RPCL. As per the said instructions,

the agenda was proposed and placed on 27.12.2006 by Mr. R.P.

Agarwal. On the said proposed agenda, Member Technical put up

a note on 19.01.2007, recording “please discuss”. Thereafter, the

meeting of the JSEB was held on 06.02.2007 and 07.02.2007,

which was presided over by the new Chairman Mr. V.N. Pandey

and Mr. R.P. Agarwal, CE, was a member of the said meeting.

Either at the stage of the proposed agenda or in the meeting of

the JESB held on 06.02.2007 and 07.02.2007, the Appellant had

not participated in the decision­making process. The minutes of

the aforesaid meeting is relevant and reproduced as under: 

“MINUTES OF THE MEETING HELD ON 06.02.2007 &

07.02.2007 AT JSEB HQR.

The following officer, consultant & contractors were present in

the meeting:­

10

1.  Shri V.N. Pandey Chairman

2. Shri R.P. Agarwal Chief Engineer (APDRP)

3.  Shri P. Ranjan                               General Manager­cum­      

        Chief Engineer/Jamshedpur

   4. Shri Niranjan Rai        Director (Finance)

5. Shri Madhup Kumar       Director (RE/Plan)

6. Shri P. Raghu       RITES Ltd.

7. Shri Y.P. Singh          do

8. Shri A.K. Singh RPCL

9. Shri T.K. Bhattacharya    do

The issue of M/s RPCL was discussed in length. Work of

Jamshedpur town under APDRP has been awarded to M/s RPCL

vide W.O. Nos. 28 & 29 dated 27.01.2005. The progress was

reviewed   and   found   that   progress   is   very­very   slow.   After

discussion, JSEB & M/s RPCL mutually agreed on the following

points:­

1.M/s RPCL will submit photo copy of all orders placed by them

for   procurement   of   materials   for   the   APDRP   work   of

Jamshedpur to Chief Engineer/APDRP & m/s RITES Ltd., the

consultant.

2.JSEB will help Ms RPCL for procurement of materials.

3.JSEB will be make payment immediately (probably within a

week) after submission of bills by M/s RPCL.

4.Approval of additional B.O.Q. and items shall be given by

JSEB immediately.

5.M/s RPCL will submit fresh inspection call of materials to

Electrical   Superintending   Engineer­cum­CEO/General

Manager­cum­Chief   Engineer,   Jamshedpur   for   getting

inspecting officer deputed.

6.M/s RPCL will contract Chief Engineer (APDRP) if here is any

delay in issuing Road permits by Chief Engineer (S&P).

7.M/s RPCL agreed that they will apply their full efforts to

complete   the   project   so   that   it   may   be   completed   within

extended completion period i.e. July’ 07 instead of going for

Arbitration/Court of Law.

8.JSEB will review the matter of L.D. clause after completion of

the project work.

Sd/­

11

(R.P. Agrawal)

Chief Engineer (APDRP)

Memo No.  ­­­­­       

Dated­­­­­­­­

Copy forwarded to all concerned officers/M/s RITES Ltd./ M/s 

RPCL for information and necessary action.

Fax – 2543986”

10.The   perusal  of   the   aforesaid   minutes   and  the   proposed

agenda dated 27.12.2006 prepared by Mr. R.P. Agarwal, CE,

reveals that the oral recommendation of the then Chairman, Mr.

Shivendu, was drawn in the proposed agenda but it was not

acted upon as per the noting dated 19.01.2007 made by the

Member Technical who made an endorsement  “Please discuss”.

Thereafter, what was the agenda that was put forth in the next

JSEB   meeting,   is   not   on   record.   The   minutes   of   the   Board

meeting  reflect  that  Mr.  R.P. Agarwal  who had  prepared  the

agenda dated 27.12.2006, was a part of the said meeting. The

decisions were taken in the said meeting with the mutual consent

of the parties. The Appellant was not a part of the decision­

making process. In the said meeting as per clause (7), it was

decided that  “M/s RPCL agreed that they will apply their full

efforts to complete the project so that it may be completed within

extended completion period, i.e., July’ 07, instead of going for

12

Arbitration/Court of Law.”  Correspondences further reflect that

prior to demitting the office, Mr. R.P. Agarwal, CE, wrote three

letters, of which two were dated 05.04.2007 and one was dated

25.04.2007, requesting RPCL for implementation of the contract

as per the decision of JSEB. The said correspondence also does

not   show   any   involvement   of   the   Appellant.   As   alleged,   the

agenda dated 08.06.2007 was prepared by the Appellant, wherein

the following instructions were required to be obtained:

“…….Hence instruction may be obtained on:

(i)Appointment of an arbitrator in light of the advice of the

AG Jharkhand.

(ii)Waiver   of   penalty   in   light   of   the   advice   of   the   AG,

Jharkhand, and

(iii)Putting the agenda for further time extension incorporating

the condition of approval of revised BQO which could not

be given till date.”

11.On perusal of the JSEB Board meeting dated 06.02.2007

and 07.02.2007, it is clear that extension was granted up to July

2007 instead of going in for arbitration or approaching the Court

of Law. The JSEB and its members were not inclined to cancel

the contract and the decision was taken by mutual consent.

Therefore, the instructions sought by the Appellant as per the

agenda dated 08.06.2007, were either based on the advice of the

learned   AG   of   Jharkhand   or   in   furtherance   of   the   previous

13

decision of the Board. Later, it was directed that JSEB, Member

Technical may constitute a committee consisting of officers from

‘Technical’, ‘Finance’ and ‘Law’ to suggest the names to appoint

an   Arbitrator,   after   approval   of   the   Chairman.   The   Member

Technical proceeded in the matter of appointment of Arbitrator

and three names were proposed on 09.08.2007, out of which, Mr.

Ramayan Pandey, Ex­Law Secretary, State of Jharkhand was

appointed as an arbitrator. The Arbitrator passed an interim

award on 25.11.2007, in favour of RPCL. 

12.In view of the discussion made hereinabove, it is apparent

that at the time of taking a decision by the JSEB on 06.02.2007

and 07.02.2007, the Appellant was neither involved nor was part

in the proposal or the decision­making process. He had prepared

the   proposed   agenda   for   instructions   on   08.06.2007,   in

furtherance of clause (7) of the aforesaid Board meeting, and

based on the advice of the learned AG, State of Jharkhand in the

matter of appointment of an Arbitrator and waiver of penalty, as

suggested. Even after the proposed agenda for termination of the

contract dated 27.12.2006, prepared by the then CE Mr. R.P.

Agarwal, it was not acted upon because Member Technical on

14

19.01.2007, had put up a note “Please discuss”. Later, the Board

took a decision on 06.02.2007 and 07.02.2007. Thus, it is clear

that the question of termination of contract in the opinion of the

Board was dropped and the recourse to complete the work within

the   extended   time   was   agreed   in   place   of   going   in   for

arbitration/Court of Law. The same has also been observed by

the High Court in its order dated 02.05.2016, while granting bail

to the Appellant on merit. In the said facts, merely preparing a

subsequent agenda dated 08.06.2007, seeking instructions for

appointment   of   an   Arbitrator   would   not   bring   the   Appellant

within the purview of culpability for commission of the alleged

offences. This Court has reason to believe that the decisions, if

any, taken by the JSEB and other higher officials were after

perusal of the complete noting in the file. After implementation of

the   said   decision,   arbitral   proceedings   were   commenced   and

award   dated   25.11.2007   was   passed.   Thereafter,   the   agenda

regarding implementation of the award was put up before the

Chairman, Mr. B.M. Verma who vide noting dated 27.01.2008,

made   a   request   to   the   AG   to   give   legal   opinion   about   the

maintainability and enforceability issues relating to the interim

award. The learned AG responded by letter dated 31.01.2008,

15

opining that the award did not suffer from any illegality and

should   be   implemented.   Accordingly,   the   Board   of   JSEB

approved   the   interim   arbitral   award   vide   resolution   dated

05.04.2008 and 07.04.2008. In the said meeting, Smt. Rajbala

Verma (then Finance Secretary to the State of Jharkhand) also

participated and duly approved the resolution.

13.The   perusal   of   material   indicates   that   because   it   was

difficult for the JSEB to implement the award due to financial

difficulty,   a   roving   and   fishing   enquiry   was   conducted,   in

consequence   of   which,   Secretary,   JSEB   vide   letter   dated

30.07.2010   and   Smt.   Rajbala   Verma   (then   Vigilance

Commissioner) vide letter dated 03.09.2010, requested the DGP,

Vigilance Bureau to register an FIR against the Appellant. We fail

to understand as to why the same person, who had approved the

implementation of award as a member of the Board, had later as

Vigilance Commissioner, recommended initiation of prosecution

against the Appellant, who had merely prepared the agenda for

appointment of an arbitrator and had nothing to do with the

approval of the award and payment of money. In view of the

aforesaid, if at all any culpability had to be assigned, it should

16

have been assigned after examining the role of senior authorities

who were involved in the decision­making process. Astonishingly,

most   of   the   senior   officials,   who   approved   various   decisions

regarding   extension   of   time,   appointment   of   arbitrator   and

implementation of arbitration award and consequent payment to

RPCL have not been arrayed as accused. In our considered view,

prima­facie  there   is   nothing   which   affixes   culpability   or

constitutes commission of offence including mens­rea on the part

of the Appellant. It seems that an attempt has been made to

implicate the Appellant for the decisions in which prima­facie, he

did not have any role to play, nor do his acts establish any

culpability regarding the alleged offences.

14.If at all there were issues with respect to the maintainability

of the award due to the provisions of the contract, particularly as

per the contended negative covenant, the same should have been

highlighted by the learned AG, especially when his opinion was

expressly sought. We find it difficult to accept that the opinion of

the learned AG was prejudiced merely because he was not made

aware of the negative covenant pertaining to price variation by an

engineer of the JSEB who has limited exposure in the domain of

17

law. We have no hesitation in stating that AG being the highest

law officer of a State, is competent to advise the State on legal

matters after due diligence, taking into consideration all relevant

factors and material. Therefore, the Appellant cannot be said to

influence or impact the opinion of the learned AG which had

resulted in approval of JSEB to implement the award. Hence, in

our considered view, it cannot be inferred that the Appellant led

the AG and the JSEB to implement the award with fraudulent or

dishonest intention to cause loss to JSEB and benefit to RPCL. 

15.On a perusal of the FIR, we find that it is alleged against

Umesh   Kumar,   Financial   Controller   –   III   and   the   present

Appellant,   CE   (APDRP),   that   they   made   payment   of

Rs.4,89,24,788/­ against the gross value of Rs. 7,89,84,826/­, as

per   the   arbitral   award   without   approval   of   the   competent

authority. Mr. Umesh Kumar had filed quashment petition being

‘Cr. M.P. No. 2136/2015’ before the High Court wherein the

Court   on   the   allegation   of   payment   without   approval   of   the

competent   authority   (as   alleged   against   Appellant   also)   has

observed as under:

“1.Having heard learned counsel for the parties and on perusal

of the records, I do find that nothing is there against the

18

petitioner   with   respect   to   appointment   of   M/s   RPCL   nor

anything   is   there   in   the   matter   of   appointment   of   an

Arbitrator. Only when award was given by the Arbitrator, the

petitioner did make payment of the amount which had been

awarded not from the working fund but from the loan fund.

This   has   been   taken   by   the   Vigilance   to   be   illegal   as

according to it the payment should not have been made from

the existing loan amount, as the loan had never been taken

for the purpose of making payment of the amount awarded

by   the   Arbitrator.   This   accusation   cannot   be   the   subject

matter of the prosecution in absence of anything being placed

that there was restriction on the part of the authority of the

Board to make payment of the amount covered under the

award passed against the Board from the loan account. It is

opinion   of   the   Vigilance   not   based   on   any   circular   or

guideline  that the payment should have  been made after

having a fresh loan from the Power Finance Corporation. It

be stated that the petitioner is to act according to his own

wisdom and not as per the wishes of others and if nothing is

there showing any culpability in the matter of payment of the

amount, the petitioner cannot be said to have committed any

wrong.

2.Coming   further,   it   be   stated   that   the   petitioner   passed

release   order   with   respect   to   payment   of   a   sum   of   Rs.

4,89,24,788/­ but that release order was passed without

having any approval of the Chairman though such post facto

approval according to the petitioner has been granted by the

Chairman   not   on   the   file   but   on   separate   sheet   which

according to the Vigilance is bad but even if this irregularity

is there in the matter of payment of the said amount, his

culpability can only be found when something is more there

showing his connivance or conspiracy with the  contractor

though the Vigilance has tried to establish that the file moved

so fast but that never indicates about the culpability of the

petitioner, as there may be conspiracy of other officials with

the contractor on account of which the file moved so fast.

Furthermore, it has never been the case of the vigilance that

the aforesaid payments were made without the materials

being supplied or short supplied.

19

3.Further, it be stated that the ingredients of the offence of

criminal conspiracy are that there should be an agreement

between the persons who are alleged to conspire and the

said agreement should be for doing of an illegal act or for

doing, by illegal means, an act which by itself may not be

illegal. In other words, the essence of criminal conspiracy is

an agreement to do an illegal act and such an agreement can

be   proved   either   by   direct   evidence   or   by   circumstantial

evidence or by both and it is a matter of common experience

that direct evidence to prove conspiracy is rarely available.

Accordingly, the circumstances proved before and after the

occurrence   have   to   be   considered   to   decide   about   the

complicity of the accused. Even, if some acts are proved to

have been committed, it must be clear that they were so

committed in pursuance of an agreement made between the

accused persons who were parties to the alleged conspiracy.

Inferences   from   such   proved   circumstances   regarding   the

guilt   may   be   drawn   only   when   such   circumstances   are

incapable   of   any   other   reasonable   explanation.   In   other

words, an offence of conspiracy cannot be deemed to have

been   established   on   mere   suspicion   and   surmises   or

inference which are not supported by cogent and acceptable

evidence. This proposition of law has been laid down by the

Hon’ble   Supreme   Court   in   a   case   of   Central   Bureau   of

Investigation,   Hyderabad   Vs.   K.  Narayana   Rao   {(2012)   9

SCC 512}. Here in the instant case, nothing appears to be

there for showing connivance or conspiracy except aforesaid

two facts which have been dealt with hereinabove regarding

payment of the amount to the contractor.”

16.The High Court quashed the criminal proceedings against

Umesh Kumar with the above said observations. Assailing the

same, Special Leave Petition (Criminal) No. 4062 of 2017, was

filed by the State of Jharkhand, which was dismissed by this

Court vide order dated 05.02.2020, after condoning the delay. As

20

per the FIR allegations, it is alleged that Umesh Kumar and the

present Appellant had made the payment of Rs.4,89,24,788/­

against the gross value of Rs.7,89,84,826/­ without approval of

the competent authority. In this regard, the allegation against the

Appellant is that he suggested that part payment of the arbitral

award   may   be   made   to   RPCL   from   the   working   fund,   on

refundable basis since there was no fund available in the Power

Finance   Corporation   Account.   It   is   not   the   case   of   the

prosecution that the Appellant had made payment to the agency.

However, it can be inferred that the Appellant has suggested the

possible mode of payment in furtherance of the Board’s office

order no. 243 dated 16.03.2006, after passing of the arbitral

award which was required to be paid alongwith interest, but to

satisfy the award by noting, the said suggestion was made. In our

view, this itself is not sufficient to implicate the Appellant. In

addition   thereto,   it   is   most   pertinent   that   even   on   such   a

suggestion, the payments were not made from the working fund,

rather, part payment of the award was made from the loan taken

from   Power   Finance   Corporation   on   the   recommendation   of

Umesh Kumar, against whom criminal proceedings have been

21

quashed as indicated hereinabove and the said order has not

been interfered with by this Court. 

17.It   is   also   worthwhile   to   mention   that   during   the

investigation,   no   incriminating   material   or   money   was   seized

from the house of the Appellant. Further, it is not a case where

allegations of illegal gratification or disproportionate assets have

been successfully found by prosecution against the Appellant. On

the contrary, when the Income Tax Department had assessed the

block   income   tax   return   for   seven   years,   the   Department

recorded   a   refund   Rs.8843   to   the   Appellant   after   detailed

scrutiny of the records. 

18.It is a well settled law that at the time of framing of the

charges, the probative value of the material on record cannot be

gone into but before framing of charge the Court must apply it’s

judicial mind on the material placed on record and must be

satisfied that the commission of offence by the accused was

possible. Indeed, the Court has limited scope of enquiry and has

to see whether any prima­facie case against the accused is made

out or not. At the same time, the Court is also not expected to

mirror   the   prosecution   story,   but   to   consider   the   broad

22

probabilities   of   the   case,   weight   of   prima­facie   evidence,

documents produced and any basic infirmities etc. In this regard

the judgment of “Union of India Vs. Prafulla Kumar Samal,

(1979) 3 SCC 4” can be profitably referred for ready reference.

Having due regard to the documents placed before us and in the

light of the submissions and discussion made above, we are of

the   considered   view   that   sufficient   grounds   casting   a   grave

suspicion on the Appellant, do not exist. It is observed that the

ingredients of alleged offences cannot be prima­facie established

against the Appellant as neither had he been entrusted with

funds of JSEB nor he had fraudulently or dishonestly deceived

senior officials of the JSEB to cause any benefit to RPCL or any

wrongful loss to JSEB and no evidence of illegal gratification or

disproportionate assets has been found against the Appellant.  

19.In view of the foregoing discussion, we are of the considered

opinion that the High Court erred in refusing to exercise the

revisional powers vested in it under Sections 397 and 401 of the

Cr.P.C. and dismissing the criminal revision preferred by the

Appellant.   In   the   facts   and   circumstances   of   the   case   as

discussed, the inescapable conclusion that can be drawn in this

23

case that ingredients of the alleged offences are not prima­facie

made out against the Appellant. Therefore, we deem it fit to allow

the   instant   appeal   and   set­aside   the   impugned   order.

Consequently,   the   Appellant   is   discharged   in   the   criminal

proceedings arising out of Special Case No.02 of 2011.

……………………..CJI.

[N.V. Ramana]

………………………..J.

[J.K. Maheshwari]

………………………..J.

[Hima Kohli]

New Delhi;

August 24, 2022

24

Reference cases

Description

Legal Notes

Add a Note....