As per case facts, a company sought to enforce an arbitral award, but the payment was delayed due to disputes over interest and the deposit of funds in the court. ...
OMP (ENF.) (COMM.) 225/2018 Page 1 of 28
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Reserved on: 22
nd
December, 2025
Judgment Pronounced on: 12
th
January, 2026
+ OMP (ENF.) (COMM.) 225/2018, EX.APPL.(OS) 553/2019, I.A.
6421/2019 & EX.APPL.(OS) 2944/2022
SHENZHEN SHANDONG NUCLEAR POWER
CONSTRUCTION COMPANY LIMITED .....Decree Holder
Through: Mr. Gourab Banerji, Senior Advocate
with Mr. Anshuman Pande and Mr.
Abhishek Bhushan Singh, Advocates.
versus
VEDANTA LIMITED .....Judgement Debtor
Through: Mr. Dhruv Mehta, Senior Advocate
with Ms. Ranjana Roy Gawai, Ms.
Vasudha Sen, Mr. Vineet Wadhwa,
Mr. Keith Vargese and Mr. Shreyas
Mittal, Advocates.
CORAM:
HON'BLE MR. JUSTICE AMIT BANSAL
JUDGEMENT
AMIT BANSAL, J.
1. The present enforcement petition has been filed seeking enforcement
of the Arbitral Award dated 9
th
November 2017 (hereinafter the “Arbitral
Award”).
2. Brief factual background of the case is set out below:
2.1 On 18
th
April 2012, notice was issued on behalf of the claimant/ decree
holder invoking the arbitration clause. The statement of claim was filed on
behalf of the decree holder (claimant in the arbitration) on 17
th
October 2012.
OMP (ENF.) (COMM.) 225/2018 Page 2 of 28
2.2 On 12
th
December 2012, the Division Bench of Bombay High Court
passed an order in an appeal under Section 37 of the Arbitration and
Conciliation Act, 1996 (hereinafter ‘the Act’), arising out of a petition under
Section 9 of the Act, directing the judgment debtor to furnish a security in the
sum of Rs.187 crores to the decree holder. An SLP was filed against the said
order, which was dismissed in July, 2013.
2.3 On 14
th
August 2013, a bank guarantee was furnished on behalf of the
judgment debtor to the decree holder for a sum of Rs.187 crores, which
continued during the pendency of the arbitration proceedings.
2.4 The Arbitral Award was passed by the Arbitral Tribunal on 9
th
November 2017.
2.5 On 12
th
February 2018, a Single Judge of this Court dismissed the
petition under Section 34 of the Act filed on behalf of the judgment debtor.
2.6 The said decision was carried in appeal before the Division Bench by
the judgment debtor under Section 37 of the Act. On 5
th
March 2018, the
Division Bench directed the judgment debtor to deposit the entire amount as
per the Arbitral Award, including interest calculated at 9% per annum, with
the Registry of this Court. It was further directed that upon the deposit being
made, the bank guarantee given by the judgment debtor to the decree holder
would be returned.
2.7 On 23
rd
March 2018, at the request of the counsel appearing on behalf
of the judgment debtor, the Division Bench permitted the judgment debtor to
deposit a sum of Rs.152.22 crores in court during the course of the day, which
was done by the judgment debtor.
2.8 The Division Bench dismissed the appeal filed by the judgment debtor
on 30
th
August 2018.
OMP (ENF.) (COMM.) 225/2018 Page 3 of 28
2.9 On 14
th
September 2018, the present execution petition was filed by the
decree holder seeking enforcement of the Arbitral Award.
2.10 On 24
th
September 2018, this Court directed the Registry to release
Rs.60 crores to the decree holder with a caveat that decree holder will retain
the said money in its Indian Bank Account till the SLP filed by the judgment
debtor against the order of the Division Bench is listed.
2.11 On 11
th
October 2018, the Supreme Court disposed of the Special
Leave Petition by modifying the interest rate on the Euro component of the
Award from 9% per annum to London Interbank Offered Rate (LIBOR) plus
3%.
2.12 On 8
th
August 2019, the executing court directed the Registry to release
a sum of Rs.34,69,20,245/- to the decree holder.
2.13 On 6
th
January 2020, the executing court passed an order that the
amount deposited by the judgment debtor in this Court has to be adjusted
towards the interest first and thereafter towards the principal amount. The
Court also held that the Euro component of the Award would be converted
into Indian Rupees as per the exchange rate prevalent on the date of filing of
the claim petition i.e. 17
th
October 2012.
2.14 An appeal was filed by the decree holder against the judgment passed
by the executing court on 6
th
January 2020, which was dismissed by the
Division Bench on 27
th
April 2022.
2.15 On 18
th
May 2022, the judgment debtor filed an application under
Section 151 of the Code of Civil Procedure, 1908 (hereinafter ‘CPC’) to place
on record the judgment dated 27
th
April 2022 passed by the Division Bench
and sought refund of the excess amount deposited as security by the judgment
debtor along with interest.
OMP (ENF.) (COMM.) 225/2018 Page 4 of 28
2.16 On 2
nd
August 2022, the executing court recorded the statement of the
decree holder that it does not intend to challenge the judgment of the Division
Bench dated 27
th
April 2022 and the Award has to be enforced in terms of the
judgment passed by the executing court on 6
th
January 2020 and the judgment
of the Division Bench dated 27
th
April 2022.
2.17 On 12
th
September 2022, the decree holder filed its written submissions
stating that the decree holder is entitled to Rs. 210,95,49,778/-, calculating
interest up to 23
rd
November 2022.
2.18 On 17
th
October 2022, the judgment debtor filed its written submissions
stating that the decree holder is entitled to an amount of Rs.1,84,13,99,008/-
and the judgment debtor is entitled to a refund of excess security deposit of
Rs.82,31,44,320/-.
2.19 On 23
rd
November 2022, the executing court passed an order that the
judgment debtor will remit a sum of Rs.184.13 crores to the decree holder and
decree holder will hand over the original bank guarantee to the judgment
debtor. The Registry was also directed to return the excess amount to the
judgment debtor after retaining a sum of Rs.26 crores being the difference in
the amount claimed by the parties. The judgment debtor was also asked to
give an undertaking that in the event decree holder is found to be entitled to a
sum more than Rs.26 crores, the judgment debtor shall pay the said amount.
2.20 Pursuant to the said order, the judgment debtor filed an undertaking on
14
th
December 2022. On the same day i.e. 14
th
December 2022, the decree
holder submitted before the Joint Registrar that it has received a sum of
Rs.184.13 crores. The judgment debtor also acknowledged that it has received
all the bank guarantees.
OMP (ENF.) (COMM.) 225/2018 Page 5 of 28
SUBMISSIONS ON BEHALF OF DECREE HOLDER
3. Mr. Gourab Banerji, senior counsel appearing on behalf of the decree
holder has made the following submissions:
3.1 Order XXI Rule 1 of the CPC recognizes a voluntary mode of payment
which does not require the decree holder to chase after the judgment debtor.
In terms of the Order XXI Rule 1 of the CPC as amended, the payment has to
be made by depositing in the executing court or directly to the decree holder.
Once payment has been made in the terms as mentioned above, the interest
liability shall cease to run. Reliance has been placed on a three-Judge Bench
decision of the Supreme Court in PSL Ramanathan Chettiar v. ORMPRM
Ramanathan Chettiar, (1968) 3 SCR 367, in support of its contention that
since the deposit made by the judgment debtor was not unconditional, and the
decree holder was not free to withdraw it, interest would continue to run on
the deposited amount. Reliance has also been placed upon judgment of the
Division Bench in DDA v. Bhai Sardar Singh, 2009 SCC OnLine Del 519.
3.2 Since bank guarantee is only a security and would not amount to
payment in Court, the interest would continue to run despite furnishing a bank
guarantee.
3.3 The judgment debtor failed to deposit entire decretal amount in terms
of the order passed by the Division Bench on 5
th
March 2018, and sought
adjustment from the bank guarantee amount of Rs.187 crores. Hence, there
was no payment of the decretal amount in terms of Order XXI Rule 1 of the
CPC. Since the sum of Rs.152 crores deposited by the judgment debtor in
proceedings under Section 37 of the Act could not be withdrawn by the decree
holder, the interest would continue to accrue on the deposited amount.
OMP (ENF.) (COMM.) 225/2018 Page 6 of 28
3.4 Even in the present execution petition filed on behalf of the decree
holder, a sum of Rs.60 crores was ordered to be released on 24
th
September
2018 and a further sum of Rs.34,69,20,245/- was directed to be released on
8
th
August 2019. Therefore, even after the appeal of the judgment debtor under
Section 37 of the Act had been dismissed, the decree holder could not get the
awarded amount in full.
3.5 In the calculation sheet filed by the judgment debtor along with its
affidavit on 17
th
January 2020, there is a categorical admission by the
judgment debtor that interest was due till 6
th
January 2020. However,
subsequently, in the calculation chart furnished by the judgment debtor, the
interest has been calculated only up to 23
rd
March 2018.
SUBMISSION ON BEHALF OF JUDGMENT DEBTOR
4. Mr. Dhruv Mehta, senior counsel appearing on behalf of the judgment
debtor has made the following submissions:
4.1 The “interest clock” stopped running on 23
rd
March 2018, the date on
which the entire awarded amount was deposited by the judgment debtor
before this Court. The judgment debtor deposited Rs.152.22 crores with the
Registry of this Court in compliance with the order passed by the Division
Bench on 5
th
March 2018. The sum of Rs.187 crores was admittedly available
with the decree holder for immediate encashment in the form of an
unconditional and irrevocable bank guarantee. Therefore, the deposit by the
judgment debtor on 23
rd
March 2018 amounts to payment as per Order XXI
Rule 1(1) of CPC and the interest would cease to run in terms of Order XXI
Rule 1(4) of CPC.
4.2 On 23
rd
March 2018, the decree holder was entitled, without any
hindrance, to access the entire awarded amount. It is the decree holder who
OMP (ENF.) (COMM.) 225/2018 Page 7 of 28
chose not to take any steps to do so. At the highest, interest could have run
only till 30
th
August 2018, when the Division Bench dismissed the appeal
under Section 37 of the Act and directed that the amount deposited with the
Registry be appropriated by the decree holder. It is the decree holder who
chose not to withdraw the deposited amount or encash the bank guarantee
because it wanted to receive the awarded amount partly in Euros and partly in
INR. The contention of the decree holder that it was entitled to partly receive
the amount in Euros was rejected by this Court vide judgment dated 6
th
January 2020 and the appeal therefrom was rejected by the Division Bench
on 27
th
April 2022.
4.3 The judgment debtor has consistently called upon the decree holder to
take the amounts deposited and encash the bank guarantee, which was lying
with the decree holder, however, the decree holder failed to do so.
4.4 On behalf of the judgment debtor, reliance has been placed on
Himachal Pradesh Housing and Urban Development Authority v. Ranjit
Singh Rana, (2012) 4 SCC 505, DDA v. Bhai Sardar Singh, (2023) 17 SCC
671, Cobra Instalaciones Y Servicios, S.A & M/s Shyam Indus Power
Solutions Pvt. Ltd. (JV) v. HVPNL, 2023 SCC Online Delhi 5439,
Ramacivil India Constructions Pvt. Ltd. v. Union of India, 2024 SCC
OnLine Del 4899, DLF Limited (Formely known as DLF Universal Limited)
v. Koncar Generators and Motors Limited, (2025) 1 SCC 343 and Bhadani
Associates v. Kamlini Dharamraj Ashar & Ors., 2017 (3) Mh. L.J. 437.
4.5 The stand of the decree holder that it could not access the amounts
deposited on account of a pre-condition contained in paragraph 133 of the
Arbitral Award as per which entire drawings and all other documents related
to the project were to be handed over by the decree holder to the judgment
OMP (ENF.) (COMM.) 225/2018 Page 8 of 28
debtor, is in the nature of an afterthought and inconsistent with the previous
stand taken by the decree holder.
ANALYSIS AND FINDINGS
5. In the aforesaid factual background, the issue that requires adjudication
is whether decree holder is entitled to recover a further amount of Rs. 26
crores towards the satisfaction of the Award or not. In other words, whether
decree holder is entitled to interest on the awarded amount till 23
rd
November
2022, as claimed by the decree holder or 23
rd
March 2018 and 30
th
August
2018, as claimed by the judgment debtor.
6. At the outset, a reference may be made to relevant provision of Order
XXI Rule 1 of CPC:
“1. Modes of paying money under decree.—(1) All money, payable under
a decree shall be paid as follows, namely:
(a) by deposit into the Court whose duty it is to execute the decree, or
sent to that Court by postal money order or through a bank; or
(b) out of Court, to the decree-holder by postal money order or through a
bank or by any other mode wherein payment is evidenced in writing; or
(c) otherwise, as the Court which made the decree, directs.
(2) Where any payment is made under clause (a) or clause (c) of sub-
rule (1), the judgment-debtor shall give notice thereof to the decree-
holder either through the Court or directly to him by registered post,
acknowledgment due.
(3) … …
…
(4) On any amount paid under clause (a) or clause (c) of sub-rule (1),
interest, if any, shall cease to run from the date of service of the notice
referred to in sub-rule (2).
(5) On any amount paid under clause (b) of sub-rule (1), interest, if any,
shall cease to run from the date of such payment:
Provided … … …”
[Emphasis supplied]
OMP (ENF.) (COMM.) 225/2018 Page 9 of 28
7. The scope of Order XXI Rule 1 of CPC was considered by a three-
Judge Bench judgment of the Supreme Court in Ramanathan Chettiar
(supra). The relevant paragraphs of the said judgment are set out below:
“12. On principle, it appears to us that the facts of a judgment-debtor's
depositing a sum in court to purchase peace by way of stay of execution
of the decree on terms that the decree-holder can draw it out on
furnishing security, does not pass title to the money to the decree-holder.
He can if he likes take the money out in terms of the order; but so long as
he does not do it, there is nothing to prevent the judgment debtor from
taking it out by furnishing other security, say, of immovable property, if
the court allows him to do so and on his losing the appeal putting the
decretal amount in court in terms of Order 21 Rule 1 CPC in satisfaction
of the decree.
13. The real effect of deposit of money in court as was done in this case is
to put the money beyond the reach of the parties pending the disposal of
the appeal. The decree-holder could only take it out on furnishing security
which means that the payment was not in satisfaction of the decree and the
security could be proceeded against by the judgment-debtor in case of his
success in the appeal. Pending The determination of the same, it was
beyond the reach of the judgment-debtor.
***
15. The last contention raised on behalf of the respondent was that at
any rate the decree-holder cannot claim any amount by way of interest
after the deposit of the money in court. There is no substance in this
point because the deposit in this case was not unconditional and the
decree-holder was not free to withdraw it whenever he liked even before
the disposal of the appeal. In case he wanted to do so, he had to give
security in terms of the order. The deposit was not in terms of Order 21
Rule 1 CPC and as such, there is no question of the stoppage of interest
after the deposit.”
[Emphasis supplied]
8. The Division Bench of this Court in DDA v. Bhai Sardar Singh
(supra), held that for a payment to fall within the ambit of Order XXI Rule 1
of the CPC, there must be an unconditional payment by the judgment debtor
OMP (ENF.) (COMM.) 225/2018 Page 10 of 28
to the decree holder either directly or through the executing court. Mere
deposit of the decretal amount in a court other than executing court can never
amount to payment. Paragraphs 16 and 17 of the said judgment are set out
below:
“16. Before adverting to the judgments relied upon by both the sides, it is
necessary to analyze a few relevant facts. To ward off a possible execution
of the decree that followed the dismissal of the objections to the Award by
the learned Single Judge on 2
nd
August, 2001, the appellant judgment
debtor deposited the decretal amount of Rs. 58,80,380/- in this Court in
terms of order dated 15th March, 2002 in CM No. 219/2002 in FAO(OS)
93/2002. This FAO(OS) 93/2002 was allowed, as aforesaid, on 20th April,
2004 reviving the objections of the appellant. Therefore, there was no
question of the amount deposited in the Court being available for
appropriation to the respondent decree holder after the judgment dated
20th April, 2004. Even when the fresh decree was passed on 15
th
July,
2005, the amount already lying deposited in the FAO(OS) 93/2002 did
not become available to the decree holder for appropriation
automatically. It is not the appellant's case that it communicated its
consent to the respondent for the withdrawal of the amount lying in
deposit in the disposed of FAO(OS) 93/2002 at any point of time within
a period of six weeks from the date of the passing of the decree dated
15th July, 2005. In fact, the appellant appears to have taken no steps
whatsoever to either tender the decretal amount with concessional rate
of interest within six weeks, or even otherwise to facilitate the withdrawal
of the amount deposited in the disposed of FAO(OS) 93/2002 by the
decree holder to the extent of the decretal amount. It was only after the
decree holder had preferred Execution Petition 168/2005 well after the
expiry of the six weeks period from 15th July, 2005, the appellant
judgment debtor for the first time gave its no objection to the decree
holder withdrawing the amount deposited in the aforesaid FAO(OS)
93/2002 on 14
th
December, 2005. Consequently, even if one were to
assume that the giving of the no objection by the judgment debtor to the
withdrawal of the decretal amount from the deposit lying in FAO(OS)
93/2002 amounted to making payment within the meaning of Order XXI
Rule 1 CPC, the said no objection came well after the expiry of the period
of six weeks from 15th July, 20.05.
OMP (ENF.) (COMM.) 225/2018 Page 11 of 28
17. In our view, the act of making payment to the decree holder under
Rule 1 of Order XXI CPC would require a positive act on the part of the
judgment debtor of either depositing “into the Court whose duty it is to
execute the decree” or to make payment out of court to the decree holder
through a postal money or through a bank or by any other mode
“wherein payment is evidenced in writing”, unless the Court which made
the decree otherwise directs. The payment made under a decree, to fall
within the ambit of Order XXI Rule 1 CPC has therefore, necessarily, to
be an unconditional payment by the judgment debtor to the decree holder
either directly, or indirectly through the medium of the Court whose duty
is to execute the decree. Mere deposit of the decretal amount in a Court,
other than an executing Court can never amount to “payment” and even
where the decretal amount is deposited in the executing court, the
judgment debtors liability to pay interest does not cease until notice
contemplated by sub-rule(2) of Rule 1 of Order XXI is given. This is
evident from sub-rule(4) above. Order XXI Rule 1 CPC does not
contemplate the decree holder having to chase the judgment debtor to
realize the decretal amount by seeking attachment of one or the other
accounts of the judgment debtor or the properties of the judgment debtor.
If resort to the execution process of the Court is required to be made by
the decree holder, and the decretal amount is recovered in pursuance of
the order of attachment of the accounts of the judgment debtor, and/or sale
of assets of the judgment debtor, such realization of the decretal amount
would not amount to payment of the decretal amount under Rule 1 of Order
XXI.”
[Emphasis supplied]
9. In DDA v. Bhai Sardar Singh (supra), what weighed with the Division
Bench was the aspect whether the decree holder could have withdrawn the
amount deposited by the judgment debtor in Court. In the facts of the said
case, the Division Bench noted that even though the judgment debtor had
deposited the Award amount in Court, the said amount was not available to
the decree holder for appropriation. There was no consent by the judgment
debtor to the decree holder for withdrawal of the amount lying deposited with
the Court in appeal under Section 37 of the Act. The Division Bench further
OMP (ENF.) (COMM.) 225/2018 Page 12 of 28
observed that if the decree holder still had to resort to the execution process
to recover the amount, the deposit would not amount to payment of the
decretal amount under Order XXI Rule 1 of CPC.
10. The aforesaid judgment was carried in appeal to the Supreme Court by
the judgment debtor therein. The Supreme Court
1
partly allowed the appeal
and modified the interest rate awarded by the Division Bench from 18% p.a.
to 12% p.a. The relevant observations of the Supreme Court as relied upon by
the judgment debtor are set out below:
“19. A reading of the aforesaid sub-rules clarifies that when money is
paid under a decree, the interest, if any, shall cease to run either from
the date of direct payment or from the date of service of notice to the
decree-holder, wherever applicable. Sub-rules (4) and (5) do not
stipulate that the interest would stop running only and only when the
entire amount as per the decree shall stand paid. This Court, as will be
seen below, has held that money even when paid in part towards the
decree would cease to accrue interest to the extent of the amount paid.”
[Emphasis supplied]
11. From a reading of the aforesaid paragraph, what emerges is that even if
part payment towards the decree has been paid, then interest would cease to
accrue to the extent of the amount paid. Significantly, the Supreme Court did
not interfere with the aforesaid observations of the Division Bench as
extracted above.
12. In Himachal Pradesh Housing (supra), the amount under the Arbitral
Award was deposited by the judgment debtor in proceedings under Section
34 of the Act. It was in the context of Section 31 (7) (b) of the Arbitration and
Conciliation Act that it was held the deposit of Award amount into the Court
would amount to payment to the credit of the decree holder. The judgment in
1
DDA v. Bhai Sardar Singh, (2023) 17 SCC 671.
OMP (ENF.) (COMM.) 225/2018 Page 13 of 28
Himachal Pradesh Housing (supra) did not deal with the issue whether the
deposit made in Court in the appeal under Section 34 of the Act could have
been withdrawn by the decree holder or not without any hindrance from the
Court in which the amount was deposited. Hence, the said judgment would
not be applicable in the present case.
13. In the judgment of the Coordinate Bench in Cobra (supra), the
judgment debtor deposited the entire amount in proceedings under Section 36
of the Act in order to avoid facing any coercive action. Ultimately, the
objections filed by the judgment debtor under Section 34 were dismissed and
the decree holder sought release of the deposited amount along with interest
till the date of dismissal of the objections under Section 34 of the Act. It was
held that the decree holder was never denied access to the Award amount and
could have withdrawn the aforesaid deposit, subject to the condition of
returning the same if the Award was set aside. The decree holder waited to
withdraw the amount after the objections of the judgment debtor were
dismissed. In these circumstances, it was held once the judgment debtor has
intimated the decree holder with a notice of the deposit and the Award amount
is available for withdrawal to the decree holder unconditionally, the liability
of the judgment debtor would cease on the date of the deposit.
14. Similar view was taken by another Coordinate Bench in Ramacivil
(supra).
15. In the latest judgment of the Supreme Court in Koncar Generators and
Motors (supra), it has been observed as under:
“38. It is important to appreciate the consequence and effect of deposit
during the pendency of proceedings to understand the need to convert this
amount on that date. Through a deposit, the award debtor parts with the
money on that date and provides the benefit of that amount to the award-
OMP (ENF.) (COMM.) 225/2018 Page 14 of 28
holder. Provided that the award-holder is permitted to withdraw this
amount, it can convert, utilise, and benefit from the same at that point in
time. Considering that the deposited amount inures to the benefit of the
award-holder, it would be inequitable and unjust to hold that the amount
does not stand converted on the date of its deposit.
***
43. Here, the Court in Nepa case [Nepa Ltd. v. Manoj Kumar Agrawal,
(2023) 17 SCC 659 : 2022 SCC OnLine SC 1736] also differentiated P.S.L.
Ramanathan Chettiar [P.S.L. Ramanathan Chettiar v. O.R.M.P.R.M.
Ramanathan Chettiar, 1968 SCC OnLine SC 28 : (1968) 3 SCR 367 : AIR
1968 SC 1047] , which has also been relied on by the respondent in the
present matter, and another decision by this Court in DDA v. Bhai Sardar
Singh & Sons [DDA v. Bhai Sardar Singh & Sons, (2023) 17 SCC 671 :
2020 SCC OnLine SC 1450] . P.S.L. Ramanathan Chettiar [P.S.L.
Ramanathan Chettiar v. O.R.M.P.R.M. Ramanathan Chettiar, 1968
SCC OnLine SC 28 : (1968) 3 SCR 367 : AIR 1968 SC 1047] holds that
a deposit is only a way to obtain a stay on execution and does not pass
title to the decree-holder, and hence, is not in satisfaction of a decree.
The decree-holder in DDA [DDA v. Bhai Sardar Singh & Sons, (2023)
17 SCC 671 : 2020 SCC OnLine SC 1450] was not permitted to withdraw
the deposited amount and hence, interest was calculated on the same.
The Court in Nepa [Nepa Ltd. v. Manoj Kumar Agrawal, (2023) 17 SCC
659 : 2022 SCC OnLine SC 1736] however held that these cases do not
apply in its facts as the respondent here was permitted to withdraw the
deposited sum and did so. Hence, the Court instead relied on the ability
of the respondent to use the deposited money as it deems fit.
44. These cases demonstrate that once there is a deposit by the award
debtor and the award-holder is permitted to withdraw the same, even if
such withdrawal is conditional and subject to the final decision in the
matter, the court must consider that the award-holder could access and
benefit from such deposit. It is then the burden of the award-holder to
furnish security, as required by the court's orders, to utilise the amount
or to make an application for modification of the condition if it is unable
to fulfil the same.
45. In furtherance of the above, we therefore reiterate that the deposit of
Rs 7.5 crores must be converted as on the date of such deposit i.e. 22-10-
OMP (ENF.) (COMM.) 225/2018 Page 15 of 28
2010, when the rate of exchange as submitted by the appellants was 1 euro
= Rs 59.17.
46. The second deposit of Rs 50 lakhs pursuant to the High Court order
dated 3-6-2011 stands on a different footing from the first deposit. This
order did not permit the respondent to withdraw this amount till the
completion of the proceedings. Hence, the amount cannot be converted as
on the date of deposit as the respondent could not have benefitted from the
same. This amount could be withdrawn only in 2016, pursuant to the
executing court's order dated 24-8-2016. The respondent withdrew the
entire deposit of Rs 8 crores, along with the interest that accrued on this
amount, on 10-10-2016.”
[Emphasis supplied]
16. The legal position that emerges from a reading of the aforesaid
judgments is that if the amount deposited by the decree holder in Court is
available for withdrawal to the decree holder, the liability of the judgment
debtor would cease on the date of the deposit and no interest would run on the
amount deposited. However, if there is an embargo on the decree holder to
withdraw the deposited amount, the interest would continue to run on the
Award amount. If the deposit is made only to secure a stay in the execution
proceedings, then such deposit is not in satisfaction of the decree. Therefore,
it has to be seen whether the decree holder can benefit from the deposited
amount even if the withdrawal of such amount is conditional.
17. Now I proceed to apply the aforesaid legal principles to the facts and
circumstances of the present case.
18. At the outset, reference may be made to the operative part of the
Arbitral Award dated 9
th
November 2017, which is set out below:
“134. Thus, in light of the aforesaid the following amount are awarded in
favour of the Claimant and the Respondent is liable to pay the same to the
Claimant within a period of 120 days from the date of this award:
I. Under the First Claim:
OMP (ENF.) (COMM.) 225/2018 Page 16 of 28
a) Rs. 46,71,41,942/- and Euro 23,717,437; and
b) Rs.12,19,69,047/-: and
II. Under the Second claim:
a) Rs. 25,47,325/-; and
b) Rs.6,06,707/-
c) Rs. 1,31,10,990/-
135. The aforesaid amount shall be payable along with interest at the rate
of 9% from the date of institution of the present arbitration proceedings
provided the amount is paid/ deposited within 120 days of the award.
136. In case the respondent fails to pay the aforesaid amounts within 120
days from the date of the Award, the claimant shall be entitled to further
interest at the rate of 15% till the date of realization of the amount.
137. Considering the overall facts and circumstances of the case and the
expenditure incurred in the arbitration proceedings, we consider it
appropriate to award Rs.50,00,000.00/- (Rupees Fifty Lakh) towards costs
and legal expenses to the claimant, which according to us would meet the
ends of justice. The claim of payment of cost of the Respondent is
rejected.”
19. The challenge to the aforesaid Award under Section 34 of the Act by
the judgment debtor was dismissed on 12
th
February 2018. In the appeal filed
by the judgment debtor under Section 37 of the Act, the Division Bench vide
order dated 5
th
March 2018 directed the judgment debtor to deposit the entire
awarded amount along with the interest calculated @ 9% per annum with the
Registry of this Court. Upon the said deposit being made, the bank guarantee
given by the decree holder was directed to be returned. The relevant
paragraphs of the said order dated 5
th
March 2018 are set out below:
“Issue notice.
Having heard learned counsel for the appellant and counsel for the
respondent, it is directed that the appellant would deposit the entire
amount as per the award dated 9
th
November, 2017, including interest
calculated @ 9% per annum with the Registrar General of this Court.
The said amount, it is stated, would be deposited within three weeks. The
OMP (ENF.) (COMM.) 225/2018 Page 17 of 28
said deposit once made will be converted into an FDR to earn interest
and will abide by further orders of this Court.
On the deposit being made, the bank guarantee given by the appellant to
the respondent, would be returned.”
[Emphasis supplied]
20. On 23
rd
March 2018, the judgment debtor moved an application before
the Division Bench seeking modification of the order dated 5
th
March 2018.
The order passed by the Court on 23
rd
March 2018 is set out below:
“It is stated by learned senior counsel appearing for the appellant that
the sum of Rs.152.22 crores would be deposited during the course of the
day.
Issue notice.
Mr. Ranjit Prakash, learned counsel for the respondent accepts notice.
List on 03.05.2018, the date already fixed.”
21. Since the full amount was not deposited by the judgment debtor in
terms of the order passed on 5
th
March 2018, the bank guarantee could not be
returned.
22. After the order was passed by the Division Bench on 23
rd
March 2018,
judgment was reserved in the appeal under Section 37 of the Act on the very
next date, i.e., 3
rd
May 2018. The judgment was pronounced on 30
th
August
2018 dismissing the appeal.
23. The judgment debtor claims that since the aforesaid sum was deposited
by it with the Registry of this Court on 23
rd
March 2018, the “interest clock”
would stop running from the said date. It is further submitted that since the
balance amount of Rs.187 crores was already available with the decree holder
for immediate encashment in the form of an unconditional bank guarantee,
the interest would cease to run in terms of Order XXI Rule 1(4) of the CPC.
24. I cannot agree with the contention of the judgment debtor that the
“interest clock” would stop running on 23
rd
March 2018, when the deposit of
OMP (ENF.) (COMM.) 225/2018 Page 18 of 28
Rs.152.22 crores was made in Court as the amount deposited could not be
withdrawn by the decree holder on the said date.
25. The deposit of Rs.152.22 crores was made by the judgment debtor in
terms of the order passed by the Division Bench on 5
th
March 2018. The said
deposit would amount to “depositing a sum in Court to purchase peace by way
of stay of execution of the decree”, in terms of the judgment of the Supreme
Court in Ramanathan Chettiar (supra).
26. Therefore, in my considered view, the decree holder did not have access
to the awarded amount on 23
rd
March 2018. The decree holder could also not
have withdrawn the part deposit made by the judgment debtor on 23
rd
March
2018 as the same was subject to further orders of the Court. This is not a case
where there was a self-imposed embargo by the decree holder on itself.
Therefore, there was no occasion or opportunity for the decree holder to seek
withdrawal of the money so deposited.
27. The judgment debtor failed to comply with the order passed on 5
th
March 2018 by not making the complete deposit of the Arbitral Award
including interest @ 9% p.a. The judgment made a partial deposit of
Rs.152.22 crores in Court and sought to adjust the bank guarantee amount of
Rs.187 crores. Admittedly, the bank guarantee of Rs.187 crores was furnished
by the judgment debtor to the decree holder in the proceedings arising out of
Section 9 of the Act. The said bank guarantee continued up to 31
st
December
2022, even after the challenge to the Arbitral Award attained finality.
28. In my considered view, bank guarantee cannot be taken to be a deposit
in terms of Order XXI Rule 1 of the CPC. The bank guarantee only serves as
a form of security to secure the amounts that may be due to a party. The decree
holder cannot enjoy the benefit of the money which is secured by the bank
OMP (ENF.) (COMM.) 225/2018 Page 19 of 28
guarantee. The decree holder could not have invoked the bank guarantee on
23
rd
March 2018. The bank guarantee, as per its terms, was payable upon
enforcement of the Arbitral Award in favour of the decree holder, which stage
had not yet arisen as the matter was still pending adjudication. It is also not
the case of the judgment debtor that it conveyed its consent for the invocation
of the bank guarantee on 23
rd
March 2018.
29. In the judgment in Bhadani Associates (supra) relied upon by the
judgment debtor, a Single Bench of the Bombay High Court took the view
that giving a bank guarantee would amount to payment of money in the Court.
It was held that a bank guarantee would not amount to a security as it could
be invoked. In the said case, the bank guarantee could not be encashed as the
decree holder had challenged the Award which was pending. The said
judgment was based on its own peculiar facts and would not be applicable to
the facts of the present case. Even otherwise, I am unable to subscribe to the
view taken by the Bombay High Court that amount secured by way of a bank
guarantee can be taken to be a deposit in Court in terms of Order XXI Rule 1
of the CPC.
30. Next, it is contended on behalf of the judgment debtor that the decree
holder would be entitled to withdraw the amount so deposited at the very least
on 30
th
August 2018, when the Division Bench dismissed the appeal filed by
the judgment debtor. While dismissing the appeal, the order of the Division
Bench stated that all interim orders stand vacated and the amount deposited
would be appropriated by the decree holder. The operative part of the
aforesaid judgment passed by the Division Bench is set out below:
“30. The award and the impugned judgment do not disclose any patent
illegality, for the above reason; they also do not reveal that the tribunal
adopted a procedure, that shocks the conscience of this court, or arrived
OMP (ENF.) (COMM.) 225/2018 Page 20 of 28
at findings that no reasonable person, placed in the situation of an arbitral
tribunal, given the material that was before it, would have rendered. The
appeal consequently has to fail; it is dismissed without order on costs. All
interim orders stand vacated; the amount deposited shall be appropriated
by the succeeding party i.e. the respondent.”
31. In the facts of the present case, I cannot agree with the aforesaid
submission. Immediately after the appeal under Section 37 of the Act was
dismissed by the Division Bench on 30
th
August 2018, the decree holder filed
the present execution petition on 14
th
September 2018 and the same came up
for hearing on 24
th
September 2018. On the said date, counsel appeared on
behalf of the judgment debtor and submitted that the judgment debtor has
approached the Supreme Court by filing an SLP against the judgment of the
Division Bench dated 30
th
August 2018. Taking note of the aforesaid
submission, the executing court permitted release of sum of Rs.60 crores to
the decree holder. To be noted, decree holder is not claiming any interest on
the aforesaid amount of Rs.60 crores.
32. On the said date, there was no consent given by the judgment debtor
with regard to the release of the amount deposited in Court or for the
invocation of bank guarantee. On the other hand, the judgment debtor resisted
the release by stating that it is in the process of filing an SLP. Therefore, the
aforesaid date of 30
th
August 2018 would also not be relevant for the purposes
of stopping the ‘interest clock’.
33. The appeal filed by the judgment debtor against the judgment of the
Division Bench dated 30
th
August 2018 was disposed of by the Supreme Court
on 11
th
October 2018, modifying the interest awarded by the Arbitral
Tribunal. Paragraph 23 of the judgment of the Supreme Court is set out below:
“23. In light of the above-mentioned discussion, the Interest awarded by
the arbitral tribunal is modified only to the extent mentioned hereinbelow:-
OMP (ENF.) (COMM.) 225/2018 Page 21 of 28
(i) The Interest rate of 15% post 120 days granted on the entire sum
awarded stands deleted. A uniform rate of Interest @9% will be
applicable for the INR component in entirety till the date of
realization.
(ii) The Interest payable on the EUR component of the Award will
be as per LIBOR + 3 percentage points on the date of Award,
till the date of realization.”
34. It is contended on behalf of the judgment debtor that after the dismissal
of the SLP by the Supreme Court, the decree holder was free to withdraw the
deposited amount and encash the bank guarantee. However, this was not done
as the decree holder insisted that the Euro component of the Arbitral Award
should be paid in Euros. In the alternative, it was contended on behalf of the
decree holder that in the event the Euro component was to be converted into
INR, the date of conversion should be the date of actual payment and not the
date of filing of the claim petition. In support of this contention, the judgment
debtor has placed reliance on the following:
i. Paragraph 13 and Prayer clause 19 a. of the present Petition.
ii. Paragraphs 4 and 5 of the Order dated 24.09.2018.
iii. Paragraphs 2 and 3 of the Order dated 08.08.2019.
iv. Paragraphs 3 to 8 and 11.1 to 11.7, 15 and Prayer clause of
the Rejoinder filed by the Decree Holder.
v. Paragraphs 7 and 8 of the Order dated 06.01.2020.
The aforesaid contention of the decree holder was rejected by the
order passed by the executing court on 6
th
January 2020 and upheld by
the Division Bench on 27
th
April 2022.
35. It was only on 2
nd
August 2022, the decree holder made a statement
before the executing court that it is accepting the judgment of the executing
OMP (ENF.) (COMM.) 225/2018 Page 22 of 28
court of 6
th
January 2020 as upheld by the Division Bench on 27
th
April 2022.
Therefore, the decree holder acknowledged the position that Euro component
would be converted into INR and the applicable conversion date would be the
date of filing of the claim i.e. 17
th
October 2012.
36. As per the decree holder, the issue with regard to the Euro component
of the Arbitral Award became relevant and was pressed by the decree holder
after the judgment was passed by the Supreme Court on 11
th
October 2018,
reducing the interest rate on the Euro component.
37. It was further contended on behalf of the decree holder that if it was the
case of the judgment debtor that the date of conversion/ claim was 17
th
October 2012, then the judgment debtor should have deposited the entire
amount in INR as per the said conversion rate.
38. In this context, it may be relevant to make a reference to the order
passed by the executing court on 8
th
August 2019. The relevant extracts of the
said order are set out below:
“1 Mr. Dhruv Mehta, learned senior counsel, on instructions, says that
the judgment debtor has already paid a sum of Rs.60 crores to the decree
holder. Besides this, Mr. Mehta says that a bank guarantee in the sum of
Rs.187 crores is available with the decree holder.
1.1 It is also Mr. Mehta’s submission that a sum of Rs.92 crores along
with accrued interest is available with the Registry of this Court.
1.2 It is, therefore, Mr. Mehta’s stand that a further sum of Rs.40 crores
can be remitted to the decree holder out of the amount lying with the
Registry of this Court.
1.3 This apart, Mr. Mehta says that the decree holder can encash the
bank guarantee in the sum of Rs.187 crores towards the satisfaction of
the decretal debt.
2 On the other hand, Ms. Arora says that the subject award directs
payments to be made to the decree holder in INR as well as in foreign
currency. Insofar as the INR component is concerned, which remains to
OMP (ENF.) (COMM.) 225/2018 Page 23 of 28
be satisfied, the judgment debtor owes a further sum amounting to
Rs.38,96,77,793/- .
2.1 Ms. Arora says that insofar INR component is concerned, it is the stand
of the judgment debtor, though erroneous, that it owes a sum of
Rs.34,69,20,245/- .
2.2 Ms. Arora, thus says, that for the moment, without prejudice to rights
and contentions of the decree holder, the INR component amount as
quantified by the judgment debtor be released to the decree holder.
3. It is also the submission of Ms. Arora that the balance amount payable
towards satisfaction of the subject award is required to be paid by the
judgment debtor in Euros.
3.1 Mr. Mehta contends to the contrary. According to Mr. Mehta, the
judgment debtor is not required to remit any sum awarded in favour in
favour of the decree holder in Euros. For this purpose, Mr. Mehta has
drawn my attention to paragraph 91 of the award dated 09.11.2017
(“award”).
4. Prima facie, I am of the view that Mr. Mehta is correct. The reason
why I say so is that paragraph 91 of the award adverts to the date when
foreign currency component of the award is to be converted to INR.
Since Ms. Arora contends to the contrary, I am open to hearing further
arguments for her and being persuaded to the contrary.
5. Given these circumstances, the Registry will release, for the time being,
a sum of Rs.34,69,20,245/- to the decree holder.
6. There is another aspect of the matter, which is, as to whether the
amounts to be paid by the judgment debtor under the award are subject to
the pre-condition contained in paragraph 133 of the award. Ms. Arora
says that release of payments to the decree holder cannot be made subject
to fulfilment of purported conditions alluded to in paragraph 133 of the
award.
6.1 Ms. Arora buttresses her argument by contending that if the judgment
debtor insists that observations made in paragraph 133 are a condition
precedent for release of payments, then, the judgment debtor would have
to prefer its own enforcement petition.”
[Emphasis supplied]
OMP (ENF.) (COMM.) 225/2018 Page 24 of 28
39. The said order records the submission of senior counsel for the
judgment debtor to the following effect:
i. Bank guarantee of Rs.187 crores is available with the decree
holder.
ii. Sum of Rs.92 crores along with accrued interest is available with
the Registry of this Court.
iii. The decree holder can encash the bank guarantee of Rs.187
crores towards satisfaction of the decretal debt and a further sum
of Rs.40 crores can be remitted to the decree holder out of the
amount lying with the Registry of the Court.
40. Submission on behalf of the senior counsel for the decree holder were
also noted in the said order to the following effect:
i. Insofar as the INR component of the award is concerned,
judgment debtor owes a further sum of Rs.38,96,77,793/-.
ii. The balance amount payable towards the satisfaction of the
Award is required to be paid by the judgment debtor in Euros.
41. A reading of the aforesaid order manifests that since the decree holder
insisted on receiving the awarded amount other than Rs.38,96,77,793/- in
Euros, the Court directed the Registry to release the sum of Rs.34,69,20,345/-
being the INR component of the award, which was admitted by the judgment
debtor.
42. The contention of the decree holder regarding the date of conversion of
the Euro component was rejected by an order passed by the executing court
on 6
th
January 2020. The relevant observations made in the said order are set
out below:
OMP (ENF.) (COMM.) 225/2018 Page 25 of 28
“31. The decree holder is claiming the exchange rate of EURO 23,717,737
on the date of the payment whereas according to the judgment debtor, the
exchange rate has to be on the date of the filing of claim petition in terms
of Para 91 of the award.
32. The Arbitral Tribunal has given a clear finding that the amount of
EURO 23,717,437 would be of the value of exchange rate as prevalent on
the date of filing of the claim petition. This finding was not interfered by
the Supreme Court and has attained finality. This Court cannot go behind
the award.
33. There is merit in the contentions urged by the learned senior counsel
for the judgment debtor. There is a clear unequivocal finding of the
Arbitral Tribunal that the amount of EURO 23,717,437 would be of the
value of exchange rate as prevalent on the date of filing of the claim
petition.”
43. The judgment debtor challenged the aforesaid order by way of an
appeal, which was dismissed by the Division Bench vide judgment dated 27
th
April 2022.
44. Post the dismissal of EFA(OS)(COMM) 5/2020 on 27
th
April 2022, the
issue with regard to the Euro component of the decretal amount was settled,
i.e., the Euro component of the decretal amount would be converted to INR
on the exchange rate prevailing on filing of the claim petition.
45. It was only thereafter that a statement was made on behalf of the decree
holder on 2
nd
August 2022 that the Award had to be enforced in terms of the
judgment dated 6
th
January 2020 and the judgment dated 27
th
April 2022.
46. Pursuant to the order passed on 2
nd
August 2022, both sides filed their
written submissions along with a calculation sheet showing the amounts due.
In terms of the written submissions filed on behalf of the decree holder, a sum
of Rs.210,95,49,778/- (including interest till 23
rd
November 2022) is due
whereas, in terms of the written submissions filed on behalf of the judgment
OMP (ENF.) (COMM.) 225/2018 Page 26 of 28
debtor, the decree holder is entitled to a sum of Rs.1,84,13,99,008/- (including
interest till 23
rd
March 2018) and the judgment debtor is entitled to refund of
excess security deposit amounting to Rs. 82,31,44,320/-.
47. When the matter came up before the executing court on 23
rd
November
2022, following directions were passed:
“A. The judgment debtor will remit the aforesaid sum of ₹184.13 crores
by a cheque in favour of the decree holder. The cheque will be handed over
by learned counsel on record for the judgment debtor to learned counsel
on record for the decree holder.
B. At the same time, learned counsel for the decree holder will hand over
the original bank guarantee furnished by the judgment debtor pursuant
to the order of the Bombay High Court to learned counsel for the judgment
debtor, as the security will no longer be required.
C. Learned counsel for the parties will coordinate amongst themselves to
ensure that directions (A) and (B) above are complied with as
expeditiously as possible, and no later than two weeks from today.
D. The difference between the amount claimed by the decree holder and
the amount computed by the judgment debtor is approximately ₹26
crores. After learned counsel for both parties certify compliance with
directions (A) & (B) above, the Registry is directed to return the excess
amount deposited by the judgment debtor in FAO(OS)(COMM) 35/2018
to the judgment debtor. It is made clear that an amount of ₹26 crores will
be retained, and the balance will be released to the judgment debtor. The
aforesaid amount of ₹26 crores will be kept in an interest bearing fixed
deposit. The return of the excess amount by the Registry is also subject to
an undertaking by the judgment debtor that, in the event the decree holder
is ultimately found to be entitled to more than the aforesaid sum of ₹26
crores, the same will be paid by the judgment debtor forthwith.”
[Emphasis supplied]
48. In these circumstances, I cannot persuade myself to accept the
submission of the decree holder that the ‘interest clock’ would continue to run
till 7
th
December 2022 when the final amount was received by the decree
holder. On 8
th
August 2019, for the first time the judgment debtor consented
to the fact that the decree holder can encash the bank guarantee of Rs. 187
OMP (ENF.) (COMM.) 225/2018 Page 27 of 28
crores towards satisfaction of the decretal amount in addition to a further sum
of Rs. 40 crores from the amount deposited. However, the decree holder
insisted on receiving the Euro component of the Award in Euros, which
contention was eventually rejected. In my view, if the decree holder had
accepted the submission of the judgment debtor on the said date, the entire
decretal amount would have been received and the decree would have been
satisfied. In fact, in the said order, the Court has expressed its prima facie
view that the contention of the judgment debtor with regard to the Euro
component of the award is correct. Nevertheless, the decree holder chose to
contest this issue and the issue was ultimately resolved on 2
nd
August 2022,
when the decree holder made a statement that it does not propose to challenge
the judgment dated 27
th
April 2022.
49. An oral submission was made on behalf of the decree holder before me
that the amounts could not be released to the decree holder also on account of
the objections taken by the judgment debtor with regard to non-fulfilment of
conditions in paragraph 133 of the Arbitral Award.
50. I am unable to accept the aforesaid submission of the decree holder that
it could not access the amounts deposited on account of aforesaid objection
of the judgment debtor. There is no pleading in the petition to this effect and
this submission clearly appears to be in the nature of an afterthought.
51. In my considered view, the amounts under the Award could not be
released to the decree holder from 8
th
August 2019 till 7
th
December 2022 on
account of factors attributable to the decree holder. Therefore, in my
considered view, the ‘interest clock’ would stop running from 8
th
August
2019.
OMP (ENF.) (COMM.) 225/2018 Page 28 of 28
52. Based on the above, the judgment debtor shall file its revised
calculation of the amounts due to the decree holder within four (4) weeks from
today. Further, the amounts due to the decree holder in terms of the revised
calculation shall be paid out of the sums deposited with the Registry of this
Court within six (6) weeks from today. The balance amount shall be returned
to the judgment debtor along with accrued interest.
53. The present enforcement petition is disposed of with the aforesaid
direction.
54. All pending applications stand disposed of.
55. List before the Registrar on 9
th
March, 2026 for compliance.
AMIT BANSAL
(JUDGE)
JANUARY 12, 2026
at
Legal Notes
Add a Note....