As per case facts, the Petitioner, a Chief Manager at IOCL, was dismissed following a departmental inquiry into alleged irregularities in awarding a pre-commissioning work contract. The High Powered Committee ...
W.P.(C)-8888/2004 Page 1 of 32
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Reserved on: 26
th
May, 2026
Pronounced on: 7
th
September, 2026
Uploaded on: 7
th
September, 2026
# CNR No : DLHC010296812004
+ W.P.(C) 8888/2004
SHRI K.P. SHARMA
S/O SHRI PARMANAND SHARMA.
R/O H-32, SECTOR 39,
NOIDA-201 301, (U.P.) .....Petitioner
Through: Mr. Abhay Singh, Ms. Veena Singh,
Ms. Vindhya Singh and Mr. Prakash
Gautam, Advocates.
versus
M/S. INDIAN OIL CORPORATION LTD.
THROUGH ITS CHAIRMAN
SCOPE COMPLEX CORE -2.
7, INSTITUTIONAL AREA. LODHI ROAD.
NEW DELHI- 10003. .....Respondents
Through: Mr. V. N. Koura, Ms. Paramjeet Benipal,
Mr. Shaurya Dahiya and Mr. Aditya
Sharma, Advocates.
CORAM:
HON'BLE MS. JUSTICE NEENA BANSAL KRISHNA
J U D G M E N T
1. The Writ Petition has been filed under Article 226 of the Constitution
of India, by the petitioner, seeking the issuance of an appropriate writ, order
or direction for quashing and setting aside the impugned Order of Dismissal
W.P.(C)-8888/2004 Page 2 of 32
dated 27.04.2004, passed by Sh. M.S. Ramachandran, Chairman of the
Respondent, M/s Indian Oil Corporation Limited (hereinafter referred to as
"IOCL"), whereby the Petitioner has been dismissed from service with
immediate effect, and for the grant of all consequential service and
monetary benefits including full back wages, service benefits and
compensation.
2. The facts in brief are that the Petitioner, Sh. K.P. Sharma, was
employed with the Respondent Corporation as a Mechanical Engineer and
was, over the course of his service spanning approximately twenty years,
promoted to the post of Chief Manager in Grade 'F', vide Appointment
Letter No. P/65537 dated 13.04.1998 issued by Sh. A.K. Arora, Director
(Refineries), and posted as Chief Projects Manager at the Panipat Refinery,
of the Respondent Corporation.
3. The Respondent Corporation's Panipat Refinery comprised, inter alia,
of a Hydrocracker Unit (hereinafter referred to as "HCU") and a Hydrogen
Generation Unit (hereinafter referred to as "HGU"). The mechanical
completion of both Units was accomplished on 30.11.1998, whereafter pre-
commissioning activities commenced.
4. During the pre-commissioning stage, the Process Licensor, UOP-
USA, whose commissioning engineer was present at site, found that the
flange joints in the high-pressure section of the Hydrocracker plant, had
been boxed up with grease. This was a defect of a serious nature relating to
the safety of the plant, since the presence of grease between the flange joints
could form carbon at the operating conditions of the Hydrocracker plant,
which operated at 175 bar pressure and temperatures exceeding 650°C,
leading to the risk of fire and explosion. The Process Licensor accordingly
W.P.(C)-8888/2004 Page 3 of 32
recommended, on an urgent basis, that all flange joints in the high-pressure
section be opened, the damaged metallic ring gaskets replaced, and the
entire section re-boxed, prior to commissioning.
5. A High Powered Committee (hereinafter referred to as "HPC") was
constituted at the Panipat Refinery, comprising Sh. S.S. Saini, Executive
Director, Sh. H.K. Bakshi, General Manager (Projects), and Sh. R. Shankar,
Chief Finance Manager. The HPC exercised the financial powers of a
Director. Given the urgency of the work, which was further compounded by
the proposed visit of the Prime Minister to inaugurate the Refinery, the HPC
directed that available contractors at site be contacted to undertake the work
immediately.
6. Three contractors, namely M/s Dodsal, M/s L&T and M/s Petron,
were approached, but each expressed inability to take up the work on
account of pre-occupation with commissioning activities of other units. M/s
Gayatri Engineering Company (hereinafter referred to as "M/s GEC"), a
Vadodara-based engineering company which was already engaged in
catalyst-loading work at the Hydrogen Unit and whose performance was
stated to be satisfactory, agreed to mobilise and undertake the work
immediately.
7. Since finalisation of rates was likely to take time and the work was of
an urgent nature, M/s GEC was permitted to commence the work with effect
from 08.01.1999, on the basis of verbal approval of the HPC, which was
subsequently ratified by Process Note dated 07.01.1999. The Process Note
was signed by eight officers, namely Sh. Parimal Kumar, DM(ML), the
Petitioner Sh. K.P. Sharma, CPJM, Sh. A.K. Marchanda, DGM (Materials),
Sh. M.R. Verma, DGM (Technical Services), Sh. R. Shankar, CFM, the
W.P.(C)-8888/2004 Page 4 of 32
SM(PJ), Sh. H.K. Bakshi, GM (Projects), and Sh. S.S. Saini, Executive
Director.
8. An estimate of Rs.60.34 lakhs was prepared by Sh. A.K. Kulshreshtha,
Senior Mechanical Engineer (SMLE), on the basis of a fax copy of a
Purchase Order No. VCM/PVC:H2155:VMA dated 02.04.1996, purportedly
placed by M/s Finolex Industries Ltd., on M/s GEC for a similar job. The
estimate was checked by Sh. A.K. Marchanda, DGM (Materials), Sh. M.R.
Verma, DGM (Technical Services), Sh. R. Shankar, CFM, Sh. H.K. Bakshi,
GM (Projects), and approved by Sh. S.S. Saini, Executive Director, Panipat
Refinery.
9. On 03.03.1999, the HPC approved the proposal for award of the work
to M/s GEC for Rs.60,35,728/- on a single-tender post-facto basis, after
comparison and negotiation of the quoted rates, which were found to be
more or less matching with the estimate. A Fax of Acceptance was conveyed
to M/s GEC on 04.03.1999 by Sh. V.K. Rai, Chief Engineering Services
Manager. The Petitioner, Sh. K.P. Sharma, was designated as the
Engineer-in-Charge for the work.
10. On 09.08.1999, the Petitioner submitted his resignation to the
Respondent Corporation, giving three months' notice, as required under his
service conditions. The resignation was not accepted by IOCL and no
reason was assigned for the non-acceptance.
11. After expiry of the Notice period, the Petitioner informed the
Respondent Corporation by letter dated 30.11.1999 that it would not be
possible for him to continue with IOCL w.e.f. 01.12.1999. The Respondent
Corporation, by telegrams dated 11.09.1999 and 06.12.1999 and by
registered letters dated 29.12.1999 and 08.02.2000, directed the Petitioner to
W.P.(C)-8888/2004 Page 5 of 32
report for duty.
12. The Petitioner thereupon instituted Civil Writ Petition No. 725 of
2000 before this Court on 08.02.2000, asserting that his resignation had
automatically come into effect, on expiry of the notice period. The said Writ
Petition was admitted on 30.10.2000, and remained pending.
13. Meanwhile, a Vigilance Inquiry was conducted into the alleged
irregularities in the award of the contract to M/s GEC, culminating in a
Report dated 29.09.1999 submitted by the Chief Vigilance Officer of IOCL,
which recorded certain discrepancies and found the Petitioner primarily
responsible for the lapses.
14. On the basis of the said Report, the Respondent Corporation lodged a
complaint against the Petitioner, Sh. K.P. Sharma, and Sh. D.R. Patel, a
partner of M/s GEC, on 30.05.2000. FIR No. 147 under Sections 420, 467,
471 and 120-B of the Indian Penal Code, 1860 was registered on
19.06.2000, at Police Station Matlauda. The charge-sheet was filed on
30.04.2001 before the Judicial Magistrate, First Class, Panipat, additionally
invoking Sections 7, 12 and 13(d) of the Prevention of Corruption Act, 1988.
No FIR was lodged against the remaining seven officers involved in the
processing and approval of the award.
15. Departmental Charge-sheets dated 30.08.2000 were thereafter
issued against the remaining seven officers, namely Sh. S.S. Saini,
Executive Director, Sh. H.K. Bakshi, GM (Projects), Sh. R. Shankar, CFM,
Sh. A.K. Marchanda, DGM (Materials), Sh. M.R. Verma, DGM (Technical
Services), Sh. Parimal Kumar, DM(ML) and Sh. A.K. Kulshreshtha, SMLE.
16. On 02.12.2002, the Judicial Magistrate, First Class, Panipat returned
the criminal charge-sheet for presentation before the Special Court, for want
W.P.(C)-8888/2004 Page 6 of 32
of jurisdiction to try offences under the Prevention of Corruption Act, and
the matter was transferred to the Court of the Additional Sessions Judge,
Panipat. On 22.02.2003, the Ld. Public Prosecutor moved an Application
under Section 319 of the Code of Criminal Procedure, 1973, before the
Court of Sh. H.P. Singh, Ld. Additional Sessions Judge, Panipat, seeking to
summon the remaining seven officers as accused, on the ground that there
was sufficient evidence against them.
17. The Respondent Corporation thereupon, filed Criminal Misc. No.
10726 of 2003 under Section 482 Cr.P.C. before the High Court of Punjab
and Haryana on 10.03.2003 and obtained a stay of the proceedings, thereby
preventing the hearing of the said Application.
18. A departmental Charge-Sheet No. P/65537 dated 06.09.2000 was
issued against the Petitioner, alleging gross misconduct in connection with
the award of the work to M/s GEC for Rs.60,35,728/-, alleging inter alia
that the Petitioner had, at his directions, caused the preparation of an
estimate of Rs.44.78 lakhs in the first week of March 1999, but backdated to
06.01.1999; that a fresh estimate of Rs.60.34 lakhs was thereafter, prepared
on the basis of a forged fax of a Purchase Order dated 02.04.1996,
purportedly issued by M/s Finolex Industries Ltd. to M/s GEC; that the first
page of the proposal was substituted to reflect the enhanced estimate; that
the proposals for negotiation and award were likewise, backdated; and that
the Petitioner had unduly favoured M/s GEC with dishonest intention and
for personal gain, causing huge financial loss to the Corporation.
19. The Charge-sheet alleged violations of Rules 7(1), 7(2), 7(5), 7(9),
7(29) and 7(30), as well as Rule 6(1)(i), (ii) and (iii) of the Conduct,
Discipline & Appeal Rules, 1980 (hereinafter referred to as "the CDA
W.P.(C)-8888/2004 Page 7 of 32
Rules").
20. The Departmental Inquiry was conducted by the Inquiry Officer Sh.
Ashok Lokhanpal, Commissioner for Departmental Inquiries, nominated by
the Central Vigilance Commission. The Presenting Officer produced 48
prosecution documents PEX.1 to PEX.48 and examined 15 prosecution
witnesses PW.1 to PW.15. The Petitioner produced 9 defence documents
DEX.1 to DEX.9 and examined 5 defence witnesses, DW.1 to DW.5.
21. The Inquiry Officer submitted his Report, on 30.04.2003. The
findings of the Inquiry Officer, Sh. Ashok Lokhanpal, charge-wise, were as
follows:
(a) Charge 1 — that the work was awarded to M/s GEC at
exorbitant rates: the Inquiry Officer found that the
Petitioner had an active role and that over-enthusiasm in
the award was visible, but held the allegation only "partly
proved."
(b) Charge 2 — that the estimate of Rs.44.78 lakhs was
backdated: the backdating was found established. However,
the Inquiry Officer expressly recorded that "there are no
malafides attributable on account of such backdating." The
allegation was held "partly proved."
(c) Charge 3 — that the estimate was substituted from
Rs.44.78 lakhs to Rs.60.34 lakhs: the Inquiry Officer found
that the higher estimate had been prepared on the basis of
the forged fax received by the Petitioner, and his
involvement in procuring and relying upon the forged
document was found established. However, the Inquiry
W.P.(C)-8888/2004 Page 8 of 32
Officer expressly recorded that "regarding substitution of
the figure of Rs.44.78 lakhs by Rs.60.34 lakhs by Sh.
Kulshreshtha or the CO could not be proved as there was
no evidence to show clear involvement of these officials."
The allegation was held "partly proved."
(d) Charge 4 — that the negotiation proposal dated
15.02.1999 was backdated: held "proved."
(e) Charge 5 — that the award proposal dated 03.03.1999
was backdated: held "proved."
(f) Charge 6 — non-utilisation of the estimate prepared for
the M/s Technocrates Construction Services contract dated
12.11.1998 for Rs.11,27,616/-: the Inquiry Officer found
that the scope of work was different and held the allegation
"not proved."
(g) Charge 7 — that the Petitioner had procured the
unrealistic estimate with dishonest intent and for personal
gain, and had documents manipulated and backdated at his
direction: considered in three parts. On dishonest intent to
favour M/s GEC, held "partly proved" on the same basis as
Charge 3. On manipulation of documents at the Petitioner's
direction, held "not proved", since the senior officers had
signed "in their own right" and were "not prone to receive
any directions from him." On backdating at the Petitioner's
direction, held "not proved", the backdating being found a
collective exercise across the entire chain of officers rather
than one directed by the Petitioner alone.
W.P.(C)-8888/2004 Page 9 of 32
(h) Charge 8 — that the Petitioner had manipulated the
forged Purchase Order dated 02.04.1996 and thereby
caused huge financial loss: the Inquiry Officer found that
the fax was indeed forged, as established by PW.13, Sh.
M.S. Arora, but expressly recorded that "there is no direct
evidence provided by the prosecution to show such direct
complicity of the CO with M/s GEC." On financial loss, the
Inquiry Officer held that "the statement of financial loss to
IOC is considered purely hypothetical." The estimate,
though initiated at the Petitioner's instance, was routed
through and signed by five senior officers, none of whom
verified its basis, and "the CO cannot thus be held fully and
completely responsible for this lapse." The allegation was
held "partly proved."
22. The Inquiry Officer thereafter examined the statutory
misconduct provisions of the CDA Rules attracted on the above factual
findings on the Charges, and recorded the following:
(i) Rule 7(1) — fraud and dishonesty (arising from
Charges 3, 7 and 8): held "partly proved", since "the
prosecution has not provided any direct evidence to prove
fraud and dishonesty."
(ii) Rule 7(2) — illegal gratification (arising from Charge
7): held "not proved", as no documentary or oral evidence
established receipt of any bribe.
(iii) Rule 7(5) — conduct prejudicial to the interests of the
Corporation (arising from Charges 4, 5 and 8): held
W.P.(C)-8888/2004 Page 10 of 32
"proved."
(iv) Rule 7(9) — negligence in performance of duty
(arising from Charges 4, 5 and 8): held "proved."
(v) Rule 7(29) — acts subversive of discipline (arising from
Charge 7): held "not proved."
(vi) Rule 7(30) — abetment of misconduct (arising from
Charge 7): held "partly proved."
(vii) Rule 6(1)(i), (ii) and (iii) — the omnibus conduct rule
(covering the overall conduct): held "partly proved."
23. The Inquiry Officer observed that all officers, namely Sh. A.K.
Kulshreshtha, SMLE, and Sh. Parimal Kumar, DM(ML), the Petitioner, Sh.
A.K. Marchanda, Sh. M.R. Verma, Sh. R. Shankar, Sh. H.K. Bakshi, and
Sh. S.S. Saini, Executive Director, had signed the relevant documents in the
same backdates. The Inquiry Officer accordingly, held that the Petitioner's
conduct was "not thus viewed as a sole case of a conduct unbecoming of a
responsible officer" and that the charge stood "diluted" to the extent of
the shared institutional responsibility.
24. On 09.03.2004, the Competent Disciplinary Authority, Sh. M.S.
Ramachandran, Chairman of IOCL, forwarded the Inquiry Officer's
findings to the Petitioner and sought a written Representation, within ten
days. The Petitioner, Sh. K.P. Sharma, submitted his Representation on
12.04.2004, contending inter alia that his nearly twenty years of
unblemished service demonstrated his integrity; that he possessed no
financial power to award the contract; that the Fax had been obtained
pursuant to the HPC's own directions, as confirmed by Sh. R. Shankar, CFM
and Convener of the HPC; that the moment the forgery came to his notice,
W.P.(C)-8888/2004 Page 11 of 32
he had stopped all payments to M/s GEC; and that the Inquiry Officer's own
findings did not sustain the charges of fraud, dishonesty, financial loss or
sole responsibility. The Petitioner specifically identified the contradiction
between the Inquiry Officer's findings and the conclusions proposed to be
drawn from them.
25. In the impugned Order dated 27.04.2004, the Competent
Disciplinary Authority, Sh. M.S. Ramachandran, Chairman of IOCL,
observed as under:
“ORDER
This has reference to the Charge-sheet of even number
dated 6.9.2000 and the subsequent Departmental Inquiry
held in this connection against you. The Inquiry Officer has
submitted report vide letter dated 10.6.03 and the same was
forwarded to you vide letter of even reference dated 9.3.04.
Your representation dated 12.04.04 against the findings of
the Inquiry Officer is available on record.
I have carefully gone through the Report/Findings of the
Inquiry Officer along with the proceedings of the inquiry
and your representation dated 12.04.04. I find that you were
given full and fair opportunity for conducting your defence
by examining the witnesses in the Inquiry and the inquiry
was conducted by following the principles of natural justice.
From your representation, I find no new facts have been
brought out for my consideration.
Having applied my mind to the facts and circumstances of
the case, I agree with the findings of the Inquiry Officer and
find that:
1. You played an active role in award of the work to M/s
GEC at an exorbitant rate.
W.P.(C)-8888/2004 Page 12 of 32
2. The proposal dated 7.1.99 was actually prepared during
the first week of March 1999 but was signed in back date.
The proposal note dated 15.2.99 proposing price
negotiation and the proposal note dated 3.3.99 for award of
work to M/s GEC have also been signed in back date.
3. You were found to be involved in substituting the estimate
of Rs.44.78 lakh by Rs.60.34 lakh suggesting fraud &
dishonesty on your part. Moreover, this estimate was based
on a forged document and you relied on this document
without checking its veracity.
4. You had also not stated the reasons for non-availability /
non-applicability of the SOR in the instant case before
suggesting approval of the proposal dated 7.1.99 for award
of work in favour of M/s GEC.
5. You got the estimates prepared by SMLE and DMMI by
changing the basis to the said forged document of M/s
Finolex faxed by M/s GEC, which amounts to encouraging
abetment of acts of omission and commission.
By the above acts of omission and commission, you have
failed to maintain absolute integrity and devotion to duty in
contravention of Rule 6(1) (i) & (ii) and acted in a manner
unbecoming of a public servant in contravention of Rule
6(1) (iii) of the CDA Rules, as OCL applicable to you. You
had also committed fraud & dishonesty in connection with
the business and property of the Corporation under Rule
7(1) and acted in a manner prejudicial to the interests of the
Corporation under Rule 7(5) of the CDA Rules. Further,
you had been negligent in performance of duties under Rule
7(9) and had also encouraged abetment of acts amounting
to misconduct under Rule 7(30) of the CDA Rules.
Taking into consideration the facts and circumstances of the
case, acts of omissions & commissions and the gravity of
proven charges and acts of misconduct, I impose the penalty
of “Dismissal” upon you with immediate effect.
W.P.(C)-8888/2004 Page 13 of 32
You are advised to collect your dues from Panipat Refinery
after obtaining necessary clearances.
(M.S. Ramachandra)
Chairman
Competent Disciplinary Authority”
26. The Disciplinary Authority, thus, imposed the penalty of dismissal
from service upon the Petitioner, with immediate effect.
27. The Petitioner has challenged the impugned Order on the
grounds that:
(i) the Disciplinary Authority, Sh. M.S. Ramachandran, while recording that he
agreed with the findings of the Inquiry Officer, proceeded to record findings
materially more adverse than those actually recorded by the Inquiry Officer,
Sh. Ashok Lokhanpal, on three separate charges, without recording reasons
for such departure and without affording the Petitioner an opportunity to
meet it, in violation of Rule 32(2) and Rule 34 of the CDA Rules;
(ii) that the Petitioner was the only officer dismissed out of eight charge-sheeted
for the very same transaction, while the remaining officers were either
promoted or given minor penalties;
(iii) that the Chairman, who under the Schedule to the CDA Rules is the
designated Appellate Authority for officers of the Petitioner's grade, passed
the impugned Order as the Disciplinary Authority, thereby extinguishing the
Petitioner's right of appeal since no new Appellate Authority was ever
notified;
(iv) that the penalty of dismissal is shockingly disproportionate to the
misconduct actually found proved, having regard to the Inquiry Officer's
W.P.(C)-8888/2004 Page 14 of 32
express findings that no direct evidence of fraud or dishonesty existed, that
illegal gratification was not proved, that the claim of financial loss was
purely hypothetical, and that the Petitioner could not be held fully and
completely responsible; and
(v) that the impugned Order is illegal, arbitrary, discriminatory and vitiated by
mala fide, in violation of Articles 14, 16 and 21 of the Constitution.
28. Per contra, the Respondent Corporation has stated in its Counter-
Affidavit, affirmed by Sh. N.K. Parmar, Chief Employee Relations
Manager, Refineries Division, that the present Writ Petition is misconceived
and not maintainable; the relationship between the Petitioner and the
Corporation being purely contractual. It is contended that IOCL is a
Company registered under the Companies Act, 1956, with no statutory
powers or functions, and that the CDA Rules are purely contractual in
character.
29. It is further contended that the Petitioner had suppressed material
facts, had taken employment abroad in Bahrain, had expressed no interest in
rejoining the Corporation, and had failed to exhaust the alternative remedy
of Appeal to the Board of Directors, under Rule 38 of the CDA Rules.
30. On merits, the Respondent submitted that the Petitioner, as Chief
Project Manager, held a position of trust and was responsible for overseeing
construction and commissioning; that the Petitioner had entered into an
arrangement with M/s GEC at exorbitant rates, ignoring prevailing site rates
on the basis of which the value of the work should not have exceeded
Rs.2,33,902/-; that the Petitioner had procured manipulated Regret Letters
from contractors, caused the proposals and estimates to be backdated and
W.P.(C)-8888/2004 Page 15 of 32
substituted, and placed the forged fax on record; and that this resulted in
an overpayment of approximately Rs.38.33 lakhs.
31. The Counter-Affidavit further alleged for the first time, that the
Petitioner had arranged to receive ten percent of the total contract
value as his personal share. This allegation did not form part of the
Charge-sheet dated 06.09.2000, was never investigated in the Departmental
Inquiry, and found no mention in the Inquiry Report dated 30.04.2003. The
Inquiry Officer had, to the contrary, expressly held the charge of illegal
gratification under Rule 7(2), as "not proved."
32. As to the treatment of the remaining seven officers, the Respondent
stated that all eight officers had been charge-sheeted, and that on the basis
of the Inquiry Report and in consultation with the CVC, major penalty was
imposed upon three officers and minor penalty upon the remaining four,
namely Sh. R. Shankar, Sh. M.R. Verma, Sh. Parimal Kumar and Sh. A.K.
Kulshreshtha, for procedural lapses. These four officers were subsequently
promoted, in the ordinary course. The Respondent submitted that no officer
had been exonerated and that the differential treatment disclosed no
selective victimisation.
33. The Petitioner, in his Rejoinder Affidavit, reiterated his averments
and specifically contested the preliminary objection as to maintainability,
contending that IOCL is a Public Sector Undertaking and an instrumentality
of the State, within the meaning of Article 12 of the Constitution.
34. On the alternative remedy, the Petitioner submitted that, as per the
Schedule to the CDA Rules, the Disciplinary Authority for Officers in Grade
D, E and F in the Refineries Division is the Director (Refineries), and the
Appellate Authority is the Chairman. Although Rule 35 was invoked to
W.P.(C)-8888/2004 Page 16 of 32
appoint the Chairman, Sh. M.S. Ramachandran, as Common Disciplinary
Authority for all eight charge-sheeted officers, the Respondent Corporation
failed to amend or notify a new Appellate Authority, in consequence. The
Petitioner was therefore, denied any effective right of Appeal, since the
same person who had passed the impugned Order of Dismissal was the one
designated to hear his appeal.
35. The Petitioner further alleged that after his resignation and
commencement of employment with M/s Lurgi India Ltd., New Delhi, as
Deputy General Manager (Projects), Mr. Thomas Antony, DGM (HR),
Headquarters, IOCL, wrote a letter dated 31.01.2000 to Sh. Onkar Gupta,
Director, M/s Lurgi India, stating that the Petitioner had been "absconding
from his duties from 23rd December, 1999" and that "some vigilance
enquiries are going on against Shri K.P. Sharma in connection with some
purported fraud." The Petitioner contended that on the date of this Letter,
the Vigilance Inquiry Report had already been submitted on 29.09.1999, and
that the Letter contained false information, which caused him to lose his
employment at Lurgi India, forcing his resignation on 08.02.2000.
36. The Petitioner further contended that the Disciplinary Authority had
adopted findings which were directly contradicted by the Inquiry Officer's
own Report, and that the impugned Order had been passed with a pre-
determined mind, in violation of Rule 32(2) and Rule 34 of the CDA Rules
and the principles of natural justice.
37. Learned counsel for the Petitioner, in his Written Submissions, has
asserted that the impugned Order dated 27.04.2004 is illegal, arbitrary,
discriminatory and passed with mala fide intentions; that the Petitioner had
no say or role in awarding the contract as neither did he possess the financial
W.P.(C)-8888/2004 Page 17 of 32
power nor did he award the contract to M/s GEC; that the Inquiry Officer
himself concluded that no loss had been caused to IOCL and that the forged
fax originated from M/s GEC without any proven direct complicity of the
Petitioner; and that the Petitioner is a law-abiding senior citizen with no
gratuity or pension, having twice suffered heart attacks in 2010 and 2019.
Reliance was placed on Articles 14, 16 and 21 of the Constitution.
38. In the Additional Written Submissions dated 21.12.2023, the
Petitioner supplemented his case with the submission that the rectification
work was to be borne by the Process Licensor, UOP-USA, and not by IOCL,
and that the costs were in any event recovered from the Process Licensor;
that the M/s Petron contract for similar work on the same Hydrocracker
Plant, awarded through independent tendering by the Contract Cell, was at a
rate 16.70% higher than the M/s GEC awarded rate; and that the Petitioner
had not been paid since 01.12.1999, although the Order of Dismissal was
passed only on 27.04.2004.
39. Per contra, the learned counsel for the Respondent, in his Written
Submissions, has contended that the Writ Petition is not maintainable for
enforcement of contractual rights. Reliance is placed on Bareilly
Development Authority v. Ajai Pal Singh, (1989) 2 SCC 116; State of U.P. v.
Bridge & Roof Co., (1996) 6 SCC 22; Kerala State Electricity Board v.
Kurien E. Kalathil, (2000) 6 SCC 293; and National Highways Authority of
India v. Ganga Enterprises, (2003) 7 SCC 410. It is further submitted,
relying on the Constitution Bench judgment in Sirsi Municipality v. Cecelia
Kom Francis Tellis, AIR 1973 SC 855, that Article 226 cannot enforce a
contract of employment, except where Article 311 is contravened, a
mandatory statutory obligation is breached, or the principles of natural
W.P.(C)-8888/2004 Page 18 of 32
justice are violated.
40. On interference with findings, reliance is placed upon Indian Oil
Corporation Ltd. v. Ashok Kumar Arora, JT 1997(2) SC 367 and Apparel
Export Promotion Council v. A.K. Chopra, JT 1999(1) SC 61.
41. On proportionality, reliance is placed upon Union of India v. Ex.
Constable Ram Karan, (2022) 1 SCC 373 and Indian Oil Corporation Ltd.
v. Rajendra D. Harmalkar, 2022 SCC OnLine SC 486, to contend that the
Court will not interfere with the punishment, unless it shocks the conscience
of the Court.
Submissions heard and record perused.
42. Briefly stated, the Petitioner, Sh. K.P. Sharma, then serving as Chief
Project Manager in Grade 'F' at the Panipat Refinery, was charge-sheeted
along with seven other officers, for irregularities in the award of pre-
commissioning work to M/s GEC for Rs.60,35,728/-.
43. The Inquiry Officer, Sh. Ashok Lokhanpal, of the eight factual
Charges, held two "proved" (Charges 4 and 5, both relating to backdating),
five "partly proved" (Charges 1, 2, 3, 7 and 8) and one "not proved"
(Charge 6). As a legal consequence of these factual findings, under the
statutory misconduct provisions of the CDA Rules, Rule 7(5) (conduct
prejudicial to the Corporation) and Rule 7(9) (negligence in performance of
duty) were held "proved"; Rules 7(1) (fraud and dishonesty) and 7(30)
(abetment of misconduct) were held "partly proved", and Rules 7(2) (illegal
gratification) and 7(29) (acts subversive of discipline) were held as "not
proved."
44. The Disciplinary Authority, Sh. M.S. Ramachandran, Chairman of
W.P.(C)-8888/2004 Page 19 of 32
IOCL, recorded that he agreed with the Inquiry Officer's findings and
imposed the penalty of dismissal from service.
I. Whether the Respondent-IOCL is an instrumentality of the State and
whether the present Writ Petition is maintainable:
45. The first question that arises is whether this Writ Petition is
maintainable. Learned counsel for the Respondent has urged that the
relationship between the Petitioner and the Respondent Corporation is
purely contractual, that the CDA Rules are not statutory in character, and
that the Petitioner's remedy lies in a civil suit.
46. This submission does not withstand scrutiny. The Petitioner does not
seek enforcement of the terms of his contract of employment or damages for
breach of it. He seeks quashing of the Order of Dismissal on the ground of
violation of natural justice and of Articles 14, 16 and 21 of the Constitution.
47. The Respondent Corporation is a Public Sector Undertaking and has
been expressly recognised by the Supreme Court as an "organ of the State"
or an "instrumentality of the State" within the meaning of Article 12 of the
Constitution. In Mahabir Auto Stores & Ors. v. Indian Oil Corporation &
Ors., (1990) 3 SCC 752, the Supreme Court specifically held that, in the
facts and circumstances of that case, the respondent-company, Indian Oil
Corporation, was an organ of the State or an instrumentality of the State, as
contemplated under Article 12 of the Constitution. The Supreme Court
further held that the action of such a State instrumentality is amenable to
scrutiny under Article 14 and must satisfy the requirements of
reasonableness and non-arbitrariness.
48. The objection that the Petitioner's relationship with the Respondent is
W.P.(C)-8888/2004 Page 20 of 32
contractual, therefore, cannot by itself conclude the question of
maintainability. The Supreme Court in ABL International Ltd. v. Export
Credit Guarantee Corporation of India Ltd., (2004) 3 SCC 553, has
recognised that the mere existence of a contractual relationship does not
constitute an absolute bar to the exercise of writ jurisdiction against an
instrumentality of the State where the impugned action is amenable to
judicial review on public law grounds.
49. In the present case, the Petitioner is not seeking enforcement of a
purely contractual term; he assails an order of dismissal passed in
disciplinary proceedings on the grounds of violation of the prescribed
procedure, principles of natural justice and the constitutional requirement of
non-arbitrariness.
50. The preliminary objection to maintainability is, accordingly,
rejected.
II. Whether the Petitioner had an efficacious alternative remedy of Appeal
under Rule 38 of the CDA Rules:
51. The next question is whether the Petitioner ought to have been
relegated to the appellate remedy, under Rule 38 of the CDA Rules.
52. Rule 38 provides:
"38. (i) An employee may appeal against an order imposing
upon him any of the penalties specified in Rule 29 or
against the order of suspension referred to in Rule 26. The
appeal shall lie to the authority specified in the schedule.
(ii) An appeal shall be preferred within 60 days from the
date of communication of the order appealed against. The
appeal shall be addressed to the Appellate Authority
W.P.(C)-8888/2004 Page 21 of 32
specified in the schedule and submitted to the authority
whose order is appealed against."
53. Under the Schedule to the CDA Rules, for Officers in Grade D, E and
F in the Refineries and Pipelines Division, the authorities are specified as
follows:
Category of Employees Disciplinary Authority Appellate Authority
Officers in Grade D, E
and F
Director Chairman
54. From the Rules, it emerges that for the Officers for whom the
Disciplinary Authority, is the Chairman, the Appellate Authority is the
Board of Directors. The Petitioner, Sh. K.P. Sharma, was an officer in
Grade 'F'. Under the Schedule, the Disciplinary Authority for him was the
Director and the Appellate Authority was the Chairman. Rule 42 of the
CDA Rules addresses this question. It reads as under:
"42. The authorities specified in the schedule shall be
prescribed and notified, as may be required from time to
time, with the approval of Director/Chairman."
55. Rule 42 CDA Rules contemplates that the authorities specified in the
Schedule, are to be prescribed and notified, from time to time.
56. The however, was passed by the Chairman, Sh. M.S. Ramachandran,
who acted as Disciplinary Authority and the impugned Order dated
27.04.2004 was made, in exercise of disciplinary jurisdiction, in terms of
Rule 35.
57. The basis on which the Chairman Sh. M.S. Ramachandran assumed
W.P.(C)-8888/2004 Page 22 of 32
the role of Disciplinary Authority, is Rule 35 of the CDA Rules, which
provides for common proceedings and reads as under:
"35. Where two or more employees are concerned in a case,
the disciplinary authority, or an authority higher than it,
who is competent to impose a penalty on such employees
may make an order directing that disciplinary proceedings
against all of them may be taken in a common proceedings
and specified authority may function as the disciplinary
authority for the purpose of such common proceedings."
58. Since all eight officers were charge-sheeted in the same case, Rule 35
was invoked to appoint the Chairman as the Common Disciplinary
Authority, for the purpose of proceedings. Accepting that Rule 35 validly
conferred the powers of the Disciplinary Authority upon the Chairman, the
consequence must be noted. The Chairman, who under the Schedule is
designated as the Appellate Authority for officers of the Petitioner's grade,
has passed the impugned Order of Dismissal, as Disciplinary Authority. The
question that arises is, what then happens to the Petitioner's right of Appeal.
59. In the present case, however, no material has been placed on record to
show that consequent upon the Chairman being appointed as the Common
Disciplinary Authority under Rule 35, any other authority was prescribed or
notified as the Appellate Authority, as contemplated under Rule 38. The
Schedule designate the Chairman as the Appellate Authority for officers in
Grade D, E and F. Thus, on the material placed before this Court, there was
no separately designated Appellate Authority to whom the Petitioner could
have preferred an Appeal against the Order, passed by the Chairman
himself.
60. The result is that, in terms of Rule 38, an Appeal against the
W.P.(C)-8888/2004 Page 23 of 32
impugned Order would have been addressed to the Chairman as the
Appellate Authority, as specified in the Schedule, whose Order was under
challenge. The same person cannot be the deciding Authority as well as the
Appellate Authority The same authority would thus, be also the Appellate
Authority, which is against the tenets of Service Jurisprudence..
61. In the absence of any material on record showing that an Appellate
Authority was designated before whom the Petitioner could file an Appeal,
it cannot be held that there was any effective appellate remedy, in terms of
Rule 38, was available to the Petitioner.
62. Additionally, the rule excluding writ jurisdiction where an alternative
remedy exists, is a rule of discretion and not one of compulsion. The
Supreme Court in Harbanslal Sahnia v. Indian Oil Corporation Ltd., (2003)
2 SCC 107, following Whirlpool Corporation v. Registrar of Trademarks,
(1998) 8 SCC 1, held that the High Court may exercise its writ jurisdiction
notwithstanding the availability of an alternative remedy, inter alia, where
the petition raises a question involving violation of the principles of natural
justice.
63. The present case involves such a challenge to the decision-making
process, in addition to the fact that the efficacious appellate remedy itself
has not been shown to be not available.
64. The objection is accordingly, rejected.
III . Scope of Judicial Review:
65. Before turning to the impugned Order, it is necessary to state the
scope within which this Court exercises its power of judicial review. The
Supreme Court in B.C. Chaturvedi v. Union of India, (1995) 6 SCC 749,
W.P.(C)-8888/2004 Page 24 of 32
held that judicial review is not an Appeal from a decision, but a Review of
the manner in which the decision was made. The Court does not sit as an
appellate authority over the findings of the Disciplinary Authority and does
not reappreciate evidence. The Court is concerned to see whether the inquiry
was held by a competent authority; whether the rules of natural justice were
complied, and whether the findings are based on some evidence.
66. This Court has, accordingly, not to go into the sufficiency of the
evidence before the Inquiry Officer, Sh. Ashok Lokhanpal. The questions
which fall for examination are:
(i) whether the Disciplinary Authority, Sh. M.S. Ramachandran,
in recording findings on three separate charges that were
materially more adverse than the conclusions actually
reached by the Inquiry Officer, complied with the
requirements of Rule 32(2) and Rule 34 of the CDA Rules;
(ii) whether the impugned Order relies upon any matter that was
not part of the Departmental Charge-sheet dated
06.09.2000 or the Inquiry record; and
(iii) whether the penalty of dismissal is proportionate to the
misconduct actually found established."
(i). Whether the Disciplinary Authority departed from the findings of the
Inquiry Officer without following the prescribed procedure:
67. Turning now to the impugned Order dated 27.04.2004 and its co-
relation with the findings recorded in the Inquiry Report dated 30.04.2003,
three critical departures are evident, which are set out in seriatim below.
W.P.(C)-8888/2004 Page 25 of 32
Sr. No. Subject Inquiry Officer's Finding
Disciplinary Authority's
Finding in the Impugned
Order
1.
Substitution of the
estimate from
Rs.44.78 lakhs to
Rs.60.34 lakhs
"regarding substitution of the figure
of Rs.44.78 lakhs by Rs.60.34 lakhs
by Sh. Kulshreshtha or the CO
could not be proved as there was no
evidence to show clear involvement
of these officials."
"was found to be involved in
substituting the estimate of
Rs.44.78 lacs by Rs.60.34
lacs suggesting fraud and
dishonesty on your part."
2.
Fraud and
dishonesty under
Rule 7(1)
"the prosecution has not provided
any direct evidence to prove fraud
and dishonesty" — charge held only
"partly proved."
"had also committed fraud
and dishonesty in connection
with the business and
property of the Corporation
under Rule 7(1)."
3.
Abetment under
Rule 7(30)
"could be partially construed as
misconduct" — charge held only
"partly proved."
"encouraged abetment of
acts of omission and
commission."
68. In each of the three matters set out above, an allegation which the
Inquiry Officer had either found not established for want of evidence or held
W.P.(C)-8888/2004 Page 26 of 32
only "partly proved" with express caveats, was treated by the Disciplinary
Authority as fully established against the Petitioner. In none of the three
allegations, did the Disciplinary Authority record any disagreement with the
Inquiry Officer's finding, furnish reasons for the departure, or afford the
Petitioner an opportunity to meet the proposed departure.
69. Equally significant is the findings of the Inquiry Officer, which
the impugned Order does not address.
70. The Inquiry Officer, at paragraph 5.16 of his Report, held that the
claim of financial loss to the Corporation was "purely hypothetical." The
impugned Order does not address this finding at all, notwithstanding that it
bears directly on the gravity of the misconduct and the proportionality of the
penalty.
71. It bears emphasis that the Petitioner, Sh. K.P. Sharma, placed these
very contradictions before the Disciplinary Authority, in his statutory
Representation dated 12.04.2004, quoting the specific findings of the
Inquiry Report and pointing out that those findings did not support the
conclusions the Disciplinary Authority proposed to draw. The impugned
Order responds to that Representation only with the general recital that "no
new facts have been brought out for my consideration."
72. A Representation that identifies with precision, findings the
Disciplinary Authority, cannot be brushed aside by merely stating that the
Representation raised nothing new, when the legal infirmities in the
reasoning process itself, had been specifically highlighted.
73. Rule 32(2) and Rule 34 of the CDA Rules are central to the
determination of this question. Rule 32(2) reads as under:
W.P.(C)-8888/2004 Page 27 of 32
"32. (2) The disciplinary authority shall if it disagrees with
the findings of the inquiring authority on any charge, record
its reasons for such disagreement and record its own
findings on such charge, if the evidence on record is
sufficient for the purpose."
74. Rule 34, the corresponding provision governing communication of
orders, provides:
"34. Orders made by the disciplinary authority under Rule
31 or Rule 33 with regard to its findings on each charge
shall be communicated to the employee concerned who shall
also be supplied with a copy of the inquiry report, if any.
Explanation: Where an inquiry is held by an inquiring
authority appointed by the disciplinary authority and the
disciplinary authority disagrees with any or all the
findings of the inquiring authority on each of the charges,
orders of the disciplinary authority will also state the
reasons for his disagreement with the finding of the
inquiring authority."
75. The requirement embodied in these provisions, was recognised as a
principle of natural justice, in Punjab National Bank v. Kunj Behari Misra,
(1998) 7 SCC 84, where the Supreme Court held that a Disciplinary
Authority proposing to disagree with an Inquiring Authority's findings, must
give the delinquent employee a further opportunity to represent against the
proposed departure.
76. The Disciplinary Authority, Sh. M.S. Ramachandran, did not record
that he disagreed with the Inquiry Officer's findings. He recorded that he
agreed, but recorded the findings which were materially different from
those that were actually reached the Inquiry Officer. This is not a case of a
Disciplinary Authority openly disagreeing and recording reasons, which
W.P.(C)-8888/2004 Page 28 of 32
Rule 32(2) permits. This is a case of a Disciplinary Authority claiming to
agree, recorded contradictory findings, which apparently is misreading of
the conclusions of the findings of the Inquiry officer, which forecloses even
the procedural safeguard that Rule 32(2) provides.
77. The impugned Order is accordingly, vitiated for non-compliance
with Rule 32(2) and Rule 34.
(ii) Whether the impugned Order relies upon any matter that was not part
of the Departmental Charge-sheet dated 06.09.2000 or the Inquiry
Record:
78. Further, the Respondent Corporation in its Counter-Affidavit alleged
for the first time, that the Petitioner had arranged to receive ten percent of
the total contract value, as his personal share. This allegation did not form
part of the Charge-sheet dated 06.09.2000, was never investigated in the
departmental inquiry, was never put to the Petitioner, and found no mention
in the Inquiry Report dated 30.04.2003. The Inquiry Officer had, to the
contrary, expressly held the charge of illegal gratification under Rule 7(2) as
"not proved."
79. It is a foundational principle of administrative law, stated in Mohinder
Singh Gill v. Chief Election Commissioner, (1978) 1 SCC 405, that the
validity of an Order must ordinarily be tested on the reasons contained in the
Order itself and cannot be supplemented in judicial proceedings by reasons
which did not form part of the decision-making process.
80. The basis for such allegation, may be the Criminal Charge-Sheet that
came to be filed against the petitioner. However, an allegation of this
W.P.(C)-8888/2004 Page 29 of 32
gravity, which was never put to the delinquent officer and never tested,
cannot be relied upon to sustain the impugned Order or to aggravate the
misconduct for the purpose of determining proportionality. Pertinently, the
criminal trial is still pending with no final decision.
81. This allegation can therefore, be not taken into consideration for any
purpose, in the present Writ Petition.
(iii). Whether the penalty of dismissal is disproportionate:
82. The question that next arises is whether the penalty of dismissal, is
proportionate to the misconduct actually found established.
83. Rule 29 of the CDA Rules provides a graded scale of penalties,
divided into two categories. The Minor Penalties, at clauses (a) to (e), range
from Censure at the lightest end to Reduction to a lower stage in the time-
scale of pay for a limited period at the heavier end. The Major Penalties, at
clauses (f) to (i), range from Reduction to a lower stage for a specified
period, through Reduction to a lower grade or post and Removal from
service, up to Dismissal at clause (i), which is the ultimate penalty in the
scale. The Petitioner was visited with the most severe penalty of Dismissal,
under clause (i).
84. The standard which governs interference with the quantum of
punishment is not whether the Court would itself have imposed the same
penalty, but whether the penalty is so disproportionate as to shock the
conscience of the Court, a standard developed in Ranjit Thakur v. Union of
India, (1987) 4 SCC 611.
85. The findings of the Inquiry Officer in respect of Charges, was that the
W.P.(C)-8888/2004 Page 30 of 32
allegation of illegal gratification and the alleged substitution of the estimate
from Rs.44.78 lakhs to Rs.60.34 lakhs was not proved for want of any
documentary or oral evidence. The non-utilisation of the earlier M/s TCS
estimate was not proved, as the scope of work being found different. The
alleged substitution of the estimate from Rs.44.78 lakhs to Rs.60.34 lakhs
"could not be proved as there was no evidence to show clear involvement"
of the Petitioner. The claim of financial loss to the Corporation was held
"purely hypothetical." The allegation of manipulation of documents at the
Petitioner's direction, was held "not proved", the charged officers having
signed "in their own right" and being "not prone to receive any directions
from him."
86. What stood established against the Petitioner, the backdating of the
negotiation proposal dated 15.02.1999 and the award proposal dated
03.03.1999, and the failure to verify the forged Finolex fax, which were held
"proved."
87. The Inquiry Officer did not, however, find the Petitioner to be the sole
author of the irregularities. The negligence in not verifying the forged
document was also not attributable to the Petitioner alone. The estimate
received through Finolex fax, was routed through and signed by the same
five senior officers without independent verification, and the Inquiry Officer
expressly held, thus "the CO cannot thus, be held fully and completely
responsible for this lapse." The Petitioner's conduct was "not thus viewed
as a sole case of a conduct unbecoming of a responsible officer", and the
charge under Rule 6(1) was held "diluted" to the extent of the shared
institutional responsibility.
88. Therefore, the only allegations proved against the Petitioner, was the
W.P.(C)-8888/2004 Page 31 of 32
shared negligence and institutional responsibility. No allegation of bribe or
illegal gratification, has been proved.
89. It is well settled that the punishment must correspond to the
misconduct actually established in the disciplinary proceedings, and cannot
be sustained by relying upon allegations which were not proved in the
inquiry or by attributing to the Petitioner a degree of responsibility which
the Inquiry Officer expressly declined to attribute to him.
90. The significant aspect in the present case, is that in respect of the
same transaction, four of the remaining seven officers, namely Sh. R.
Shankar, Sh. M.R. Verma, Sh. Parimal Kumar and Sh. A.K. Kulshreshtha,
who also were sharing the same charges of procedural lapses, as shared
negligence and the institutional responsibility, in handling the Project and
were characterised by the Respondent as having committed procedural
lapses, were visited with minor penalties and were subsequently, promoted
in the ordinary course.
91. The decision of the Supreme Court in Punjab & Sind Bank v. Raj
Kumar, 2026 INSC 313 also explained the principle that differential
punishment among co-delinquents does not, by itself, amount to
discrimination, particularly where their rank, responsibility or individual
role differs.
92. The question here is not whether the Petitioner was necessarily
required to receive the same punishment as the other officers, but what
emerges from the aforesaid discussion is the discriminatory and
unwarranted extreme punishment of Dismissal, merely because he was the
junior most in the hierarchy of the Charged officers who were held
guilty of the same misconduct. The penalty of dismissal from service had
W.P.(C)-8888/2004 Page 32 of 32
no rational and proportionate relationship to the gravity of that misconduct
actually found proved against the petitioner. It is grossly disproportionate
to the misconduct established on the record.
Conclusion:
93. In view of the foregoing discussion, the impugned Order of Dismissal
dated 27.04.2004 cannot be sustained and is, accordingly, set aside. Having
regard to the nature and extent of the misconduct proved against the
Petitioner, the finding of shared institutional responsibility, and the penalty
imposed upon the co-officers involved in the same transaction for the
procedural lapses found against them, the penalty of dismissal imposed
upon the Petitioner is substituted with the minor penalty under Rule 29 of
the CDA Rules.
94. The Respondent Corporation shall give effect to the substituted
penalty and carry out the consequential pay fixation and computation of the
service and retiral benefits that become due to the Petitioner consequent
upon such substitution and according to law. The Petitioner shall, however,
not be entitled to any back wages for the intervening period.
95. The aforesaid consequential benefits shall be computed and released
by the Respondent Corporation within a period of three months from the
date of receipt of a copy of this judgment.
96. The Writ Petition is allowed, in the above terms. Pending
applications, if any, are disposed of accordingly.
(NEENA BANSAL KRISHNA)
JUDGE
SEPTEMBER 7, 2026/va/RS
Legal Notes
Add a Note....