As per case facts, the petitioner (Volleyball Federation) and respondent (sports marketing company) had an agreement for a pro-volleyball league. Disputes arose when the respondent reported a loss for the ...
Arb.O.P.(Com.Div.) No.175 of 2021
In the High Court of Judicature at Madras
Reserved on:
02.2.2026
Delivered on:
17.2.2026
Coram :
The Honourable Mr.Justice N.ANAND VENKATESH
Arbitration O.P.(Com.Div.) No.175 of 2021
Volleyball Federation of India,
rep.by Secretary General
Mr.Anil Choudry, Room No.72,
Jawaharlal Nehru Stadium,
Chennai-600003 ...Petitioner
Vs
Baseline Ventures (India) Pvt. Ltd.,
AWFIS Chemtex House, 6th Floor,
Chemtex Lane, Hiranandani Gardens,
Mumbai-400076. ...Respondent
PETITION under Section 34 of the Arbitration and Conciliation
Act, 1996 praying to set aside the award dated 21.11.2020 passed
by the learned Arbitrator.
For Petitioner : Mr.P.V.Balasubramanian
For Mr.P.Siddharth for
M/s.BFS Legal
For Respondent : Mrs.Elizabeth Seshadri &
Mr.H.Karthik Seshadri
1/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
ORDER
This petition has been filed assailing the award passed by the
learned Arbitrator dated 21.11.2020 under Section 34 of the
Arbitration and Conciliation Act, 1996 (for short, the Act).
2. Heard both.
3. The brief facts of the case are as follows:
(i) The respondent/claimant is a sports marketing and
promotion company. The petitioner federation is a registered society
and has been recognized as the Ministry of Youth Affairs,
Government of India. The petitioner federation is the sole governing
body of players of volleyball registered with it. The parties decided
to conduct a pro-volleyball league (PVL) and accordingly, they
entered into an agreement dated 21.2.2018 for a period of ten years
and the respondent/claimant agreed to conduct ten seasons of the
league. As per the agreement, the duration of the agreement, the
rights to hold, host, organize and operate the league were agreed
upon.
(ii) The petitioner federation agreed to be entitled to one time
2/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
payment fee of Rs.2.50 Crores for the entire term of the agreement
and in addition to the said one time payment fee, the petitioner
federation was also entitled to a minimum guarantee amount as set
out in the agreement and 50% of each season’s net profit. The first
season of the tournament was conducted between 02.2.2019 and
22.2.2019 at Kochi and Chennai.
(iii) Since the petitioner federation was entitled to 50% of the
profit, they sent a communication dated 18.6.2019 to the
respondent/claimant to furnish all the details of the statement of
accounts of the first season of the PVL. In turn, the respondent/
claimant sent a reply dated 04.7.2019 and submitted the auditor’s
report of its statement of accounts for the first season of the PVL. As
per the statement of accounts, the respondent/claimant showed a
loss to the tune of nearly Rs.1.66 Crores. This was construed by the
petitioner federation to have been deliberately done in order to
deprive them 50% of the net profit as per the agreement.
(iv) This trigger resulted in a dispute between the parties.
Apart from that, the respondent/claimant also attempted to file an
application before the Trade Mark Registry to register the name and
logo of the PVL in their name, which was also construed by the
3/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
petitioner federation as a breach of the terms of the contract. In
view of the above, the petitioner federation issued a notice dated
18.8.2019 to the respondent/claimant pointing out to various acts
and deeds, which constituted breach of the agreement committed by
the respondent/claimant. The petitioner federation nominated three
members to constitute an Audit Committee and called upon the
respondent/claimant to furnish all relevant documents before the
Audit Committee to be approved by the Governing Council and the
petitioner federation before organizing the second season of the
PVL.
(v) On receipt of the said notice, the respondent/claimant
gave a reply dated 26.8.2019. According to the petitioner, the
respondent/claimant tried to justify its action and also made certain
personal allegations against the Secretary General of the petitioner
federation and maligned their reputation.
(vi) The issues were not amicably resolved between the
parties and the relationship between the parties was getting
strained. The Federation Internationale De Volleyball (FIVB)
convened a meeting on 31.10.2019 with an intention to amicably
settle the dispute between the petitioner federation and the
4/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
respondent/claimant. The FIVB suggested an addendum to the
agreement. Even thereafter, the dispute was not resolved between
the parties and the addendum was not finalised.
(vii) According to the petitioner, the respondent/claimant also
did not take any steps to cure the breaches caused by them. The
petitioner federation, on 18.11.2019, issued a press release
announcing termination of the agreement and by letter dated
19.11.2019, a notice of termination of agreement was issued by the
petitioner federation in line with Clause 6.4 of the agreement.
(viii) On receipt of the same, the respondent/claimant, through
communication dated 28.11.2019, refuted the allegations made and
called upon the petitioner federation to recall the termination letter
dated 19.11.2019, failing which, the respondent/claimant would be
constrained to initiate legal proceedings.
(ix) The dispute was referred to the learned Arbitrator and the
respondent/claimant filed a statement of claim and sought for the
relief of directing the petitioner federation to pay a sum of Rs.2.25
Crores along with interest from 18.12.2019 till the date of
realization and a further sum of Rs.6.28 Crores (approximately) as
damages in view of the wrongful and illegal termination of the
5/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
agreement dated 21.2.2018 along with interest from 19.11.2019 till
the date of realization.
(x) Before the learned Arbitrator, the petitioner federation
submitted a statement of defence denying the claim made by the
respondent/claimant and justifying termination of the agreement.
The petitioner federation also made counter claims for directing the
respondent/claimant to pay a sum of Rs.14.93 Crores representing
the loss on account of breach of the agreement by the respondent/
claimant, Rs.2.50 Crores towards damages for loss of reputation,
Rs.3,94,521/- towards interest on delayed payment of minimum
guarantee fee, to assign the petitioner federation all the trade mark
registrations/applications for the mark “PVL” and the logo, to injunct
the respondent/claimant from using the mark and for interest and
costs.
(xi) The learned Arbitrator, on considering the pleadings,
framed the following issues:
“1. Whether the termination of the
agreement dated 21.2.2018 through a notice
dated 19.11.2019 valid and justify?
2. Whether the failure to conduct the
league for the year 2018 constitute a breach of
6/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
the terms of the agreement?
3. Whether the expression of 10 season of
league matches for the period of operation of
agreement for 10 years mandate the setting up
at least one season for every year?
4. Whether the inability of Sony TV to
secure a window for telecast of matches of 2018
a justification for not conducting the league for
the year 2018?
5. Whether the permission accorded to the
claimant to conduct the league 2019 and
congratulatory messages of the President of the
respondent federation constitute a waiver on the
part of the respondent to complain of failure to
conduct league matches for 2018?
6. Whether the failure to conduct Women
Volleyball League and Beach Volleyball League
constitute a breach to support them as grounds,
among others for termination of the agreement?
7. Whether the claimant is guilty of
manipulation if accounts to return losses for
season 2019?
8. Whether the respondent could be
stated to be guilty of not setting up an audit
committee in the manner contemplated under
the agreement as soon as the respondent was
dissatisfied with the correctness of the account
shown by the claimant?
9. Whether details of expenses shown by
7/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
the claimant under various heads for conduct of
the 1st season exaggerated as contended by the
respondent?
10. Whether the claimant was entitled to
apply for registration of trademark "Pro
Volleyball League" as well as its logo unlawful
and violative of the terms of the agreement?
11. Whether the copyright for Pro
Volleyball League and the logo belong to the
respondent and consequently an application by
registration by the claimant is wrong and
unjustified?
12. Whether the claimant is entitled to
assessment of loss of profit to be claimed
against the respondent at Rs.4,00,00,000/- and
if not, to what amount?
13. Whether the claimant is entitled to
claim against the respondent the loss alleged to
have been incurred for season I and if so to what
amount?
14. Whether the claimant is entitled to
allege overhead expenses not included in the
auditor statement between April 2018 to October
2019 and if so to what amount?
15. Whether the claimant suffered any
loss of reputation on account of termination of
the contract to be entitled to any compensation
and if so to what amount?
16. Whether the delay in payment of one
8/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
time fee and minimum guarantee amount as
stipulated under the agreement justified and if
not, what is the quantum of amount payable by
the claimant to the respondent?
17. Whether the claimant is liable to pay
loss of profits to the respondent in the event of
the finding that the termination of contract was
lawful to an amount of Ra.14,93,74,246/-and if
not, to what amount?
18. Whether the respondent has suffered
a loss of reputation by the conduct of the
claimant to merit a claim for Rs.2,50,00,000/- or
such amount that the Tribunal may determine?
19. Whether the claimant is entitled to
interest of Rs.3,94,521/- for delay payment of
minimum guarantee fee?
20. Whether the respondent is entitled to
seek for assignment of application of trademark
Pro Volleyball League and Logo or any other
name deceptively similar to it?
21. Whether the respondent is entitled to
relief of injunction against the claimant from in
any manner using the trademark Pro Volleyball
League or its Logo?
22. Whether the parties are entitled to
costs of one against the other?
23. Whether the claimant is entitled to
assessment of interest for the amount claimed
or as assessed and if so, what is the rate of
9/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
interest?
24. Whether the respondent is entitled to
assessment of interest for the amount claimed
or as assessed and if so, what is the rate of
interest?
25. To what other reliefs?”
(xii) The respondent/claimant examined C.W.1 and marked
Ex.C.1 to Ex.C.84. The petitioner federation examined R.W.1 and
marked Ex.R.1 to Ex.R.25.
(xiii) The learned Arbitrator, on considering the facts and
circumstances of the case and on appreciation of evidence, passed
the following award:
“79. In the result, in the line of findings
rendered under the above issues,
(1) The claimant is entitled to loss of
profits of Rs.4,00,00,000/- (Rupees four crores
only) against the respondent with interest at
12% from the date of commencement of arbitral
proceedings till the date of payment;
(ii) The claims for loss for season 1, claim
for overheads, expenses and loss of reputation
are dismissed;
(iii) The counter claim for
Rs.14,93,74,246/- made by the respondent
against the claimant is dismissed;
(iv) The damages for wrongful attempt for
10/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
registration of trademark and logo is assessed at
Rs.1,00,000/- (Rupees one lakh only) nominally
which the claimant is liable to pay the
respondent/counter claimant with interest at
12% from the commencement of arbitral
proceedings till the date of payment;
(v) There shall be a mandatory direction
against the claimant to transfer the application
for registration of copyright, trademark and logo
for Pro Volleyball League in favour of the
respondent/counter claimant;
(vi) There shall be an injunction
restraining the claimant from in any manner
using/infringing the copyright, trademark or logo
for any event that the claimant organizes in
future except with the permission of the
respondent;
(vii) The parties are at liberty to have a
due diligence to be conducted by a neutral
auditor for assessment of the account for season
I and any payment secured under this award will
not affect or be affected by the outcome of such
an exercise of audit;
(viii) The rights of franchisees of the 1st
season will be governed by the terms of
respective contracts and this award will not in
any way affect their rights and shall be
considered, with the first option of refusal, when
a competitive league is organized by the
11/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
respondent or its authorised representative; and
(ix) The claimant shall be entitled to costs
assessed at Rs.5,00,000/- (Rupees five lakhs
only) against the respondent.”
(xiv) Aggrieved by the above award, the petitioner federation
has approached this Court by filing this petition.
4. The learned counsel appearing on behalf of the petitioner
federation made the following submissions:
(a) The respondent/claimant committed breach of the
agreement by not conducting season-1 in the year 2018, not
conducting the Women’s League and the Beach Volleyball League,
neglected to pay the one time payment fee and minimum guarantee
amount as per the time line in the agreement, neglected to form the
Governing Council and the Audit Committee, unnecessarily involved
the FIVB in the dispute resolution, snatched the intellectual property
rights of the petitioner federation and indulged in manipulation of
accounts by showing loss thereby depriving 50% share of the
petitioner federation in the net profit.
(b) The learned Arbitrator went wrong in rendering a finding
that not commencing the league in the year 2018 and not
12/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
conducting the Women’s League and the Beach Volleyball League
did not constitute violation of the terms of agreement. Hence, just
because there was a failure on the part of the petitioner federation
to insist upon performance of the agreement, it would not be
deemed waiver of the provision. This finding went against terms of
the very agreement and the relevant materials that were placed
before the learned Arbitrator and therefore, this finding suffers from
perversity and patent illegality.
(c) The learned Arbitrator also went wrong in rendering a
finding that there was no manipulation of accounts on the part of
the respondent/ claimant and this finding would run against the
other findings rendered to the effect that the expenses shown and
some of the vouchers exhibited did not accord with the proper
detailing of expenses. The accounts required a third party audit and
those portions were construed as blemishes and not manipulation of
accounts. Hence, this finding also suffers from patent illegality.
(d) The learned Arbitrator further went wrong in rendering a
finding that there was no delay in the one time payment fee and the
minimum guarantee amount in spite of the fact that C.W.1 admitted
that the same had to be paid within a time frame. Therefore, this
13/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
finding requires the interference of this Court.
(e) The learned Arbitrator also went wrong in rendering a
finding that the termination notice was not in line with the
procedure contemplated under Clause 8 of the agreement without
noticing the fact that Ex.C.19 notice dated 18.8.2019 provided for
seven days to cure the defects and that ultimately, the termination
was done much beyond the period contemplated under the
agreement. Therefore, such a finding went against the substantial
compliance of the requirements by the petitioner federation under
the agreement. Even otherwise, mere procedural irregularities in the
termination does not, ipso facto, make the termination illegal.
Hence, the said finding also requires the interference of this Court.
(f) The learned Arbitrator once again went wrong in awarding
compensation towards the alleged loss of profit suffered by the
respondent/claimant without proper reasoning and rendered a
finding that Rs.4 Crores would be a reasonable loss of profit on mere
surmises.
(g) The learned Arbitrator went wrong in rejecting the counter
claims made by the petitioner federation towards damages for loss
of reputation and loss of profits.
14/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
5. Per contra, the learned counsel appearing for the
respondent/claimant submitted as follows:
The findings rendered by the learned Arbitrator were
reasonable since they were supported by sufficient reasons. Such
findings were rendered on appreciation of evidence and after
considering the terms of the agreement. Such a possible view taken
by the learned Arbitrator could not be interfered under Section 34 of
the Act. Accordingly, the learned counsel sought for dismissal of this
petition by confirming the award passed by the learned Arbitrator.
6. This Court has carefully considered the submissions of the
learned counsel on either side and perused the materials available
on record and more particularly the impugned award.
7. Before this Court goes into the various issues dealt with by
the learned Arbitrator and the submissions made on either side on
the findings rendered for the issues, the background, in which, the
petitioner federation entered into an agreement with the
respondent/claimant assumes some significance. Dealing with the
same briefly will lay a foundation to understand this case in its
15/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
proper context. It must also be borne in mind that it was the
respondent/claimant, which was bringing in funds, sponsors,
franchisees and was undertaking the entire work to conduct the
league and the petitioner was a mere facilitator.
8. Earlier, the petitioner federation made an attempt to
organize a national volleyball league in the year 2011. But, the
same was not successful due to the lacklustre response from the
general public. There were several internal squabbles in the
petitioner federation, which led to the suspension of the federation
by the Government of India in the year 2016 and it was
subsequently revoked only in the year 2017 after elections were
held and the Secretary General was chosen. The parties were
discussing with each other for conducting the league and ultimately,
it fructified in an agreement under Ex.C.2.
9. On the one hand, the petitioner federation was the
Authority for conducting sports activities relating to volleyball since
they were coming under the aegis of the Ministry of Youth Affairs
and Sports, Government of India and on the other hand, due to the
16/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
previous failure, they were also looking for parties to conduct events
and the presentation made by the respondent/claimant convinced
the petitioner federation and they entered into an agreement for
conducting the league, which involved national and international
players.
The findings of the learned Arbitrator on issue Nos.2 to 5:
10. These issues pertained to non conduct of the league
during the calendar year 2018 and the interpretation of the word
‘season’ in the agreement.
11. The specific case of the petitioner federation was that the
non conduct of the league season-1 in 2018 constituted breach of
the contract. The petitioner federation placed reliance on Ex.R.1 and
Ex.R.2, which provided for the commencement of season-1 in late
August 2018. Apart from that, Clause 1.1 of the agreement
stipulated that ‘season’ would mean matches to be played each
year.
12. The learned Arbitrator gave a finding that the contract did
17/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
not make out any specific stipulation that season-1 would be
conducted in 2018 itself. The learned Arbitrator further took into
consideration various formalities that were going on between the
parties and also took specific notice of the tripartite contracts with
the franchisees, which took place only between 10.10.2018 and
03.1.2019 under Ex.C.69. Apart from that, there was also a
novation of the tripartite agreement under Ex.C.45 on 12.1.2019.
The title sponsor namely ‘RuPay’ also came on board only on
25.1.2019 (Ex.C.37).
13. In view of the same, the learned Arbitrator came to the
conclusion that the petitioner federation was very well aware that
the first season was going to be held only in 2019. Therefore, the
learned Arbitrator rendered a finding that if at all the petitioner
federation construed that non commencing of season-1 of the
league constituted breach of the agreement, they ought to have
produced some material to show that they were insisting for the
commencement of the league from 2018. In the absence of the
same and in the light of the various developments that were taking
place upto 2019, in which, the petitioner federation was also a
18/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
party, the learned Arbitrator concluded that the non starting of
season-1 in the year 2018 did not constitute breach of the
agreement.
14. Apart from the above, the learned Arbitrator interpreted
the terms ‘league’, ‘season’ and ‘season year’ and came to the
conclusion that even though ‘ season year’ was treated as
synonymous to the calendar year, it should be reckoned only for the
tenure of the agreement as subsisting for ten years and that it was
not a mandate that for every calendar year, there should be one
league event and it was possible that one calendar year could have
even two league events to square off the responsibility of conducting
an event for one year when there was no event.
15. All the above findings rendered by the learned Arbitrator
are certainly possible views on interpretation of the terms of the
agreement and also the conduct of the petitioner, which was very
well aware that the first season was not going to commence in
2018. Hence, the findings of the learned Arbitrator do not
require the interference of this Court on these issues .
19/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
Issue No.6:
16. This issue pertained to non conduct of the Women’s
Volleyball League and the Beach Volleyball League, which, according
to the petitioner federation, constituted breach of the agreement.
17. The learned Arbitrator found that there were references
about the Women’s Volleyball League and the Beach Volleyball
League under the rights and responsibilities of the parties at Clause
2.1. The learned Arbitrator, on the basis of the various findings
rendered for issue Nos.2 to 5, dealt with this issue also. The learned
Arbitrator found that till the conclusion of the first season, there was
not even a single communication from the petitioner federation
insisting for conducting the Women’s Volleyball League and the
Beach Volleyball League.
18. The learned Arbitrator also found that there was no
specific mandate in the agreement for conducting the Women’s
Volleyball League and the Beach Volleyball League within any
stipulated period and that apart from that, it was the responsibility
of the petitioner federation to make available the players since they
20/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
were the sole Governing Body of Players of Volleyball registered and
associated with them. The learned Arbitrator took note of certain
communications addressed to the Services and the Railways wherein
it was found that the insistence was on men players and that there
were no steps taken to push the Women’s Volleyball League or the
Beach Volleyball League.
19. Under such circumstances, considering the conduct of the
petitioner federation, the learned Arbitrator found that there was no
breach of contract involved merely on the failure to conduct the
Women’s Volleyball League and the Beach Volleyball League during
season-1. This finding rendered by the learned Arbitrator is
certainly a plausible view on appreciation of evidence and
therefore, it does not require the interference of this Court .
Issue Nos.7 to 9, which pertain to manipulation of accounts:
20. The case of the petitioner federation was that there were
several inconsistencies in the invoices submitted by the respondent/
claimant and that there were discrepancies in the audit report.
21/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
21. Even the report submitted by the Deloitte, whose services
were engaged by the respondent/claimant, would show that the
expenses were inflated and false.
22. Therefore, it was contended on the side of the petitioner
federation that the revenue earned from advertisements on linear
and digital platforms were been reported in the audited profit and
loss statement, that the ticketing revenue was less than 76% of the
estimate, that there existed unexplained marketing expenses to the
tune of Rs.0.57 Crores, that there were discrepancies even in the
management fees and marketing expenses and that all those
manipulations were done by the respondent/claimant only to deprive
50% share in the net profit under the agreement.
23. The agreement itself contemplated formation of an Audit
Committee to look into the accounts where it was the petitioner
federation, which had to nominate three persons to the Audit
Committee. Such nomination was done through Ex.C.19.
Unfortunately, no meeting was convened with the respondent/
claimant regarding the audit committee and that there was no push
22/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
on the side of the petitioner federation to drive the Audit Committee
to scrutinize the accounts that were handed over by the respondent/
claimant.
24. The petitioner federation utilized the services of Price
Waterhouse Coopers Private Limited and the respondent/claimant
utilized the services of Deloitte. Both the reports were before the
learned Arbitrator. On considering both the reports, the learned
Arbitrator came to the conclusion that both the reports would have
to be kept aside on account of the fact that both the reports could
not be strictly construed as an audit since disclaimers in both the
reports were too sweeping and that many of the findings remained
as questions, which could be answered only by the other side.
Hence, the learned Arbitrator proceeded to deal with this issue on
the other available materials.
25. In the considered view of this Court, it was this issue
regarding sharing of net profit, which actually led to the entire
agreement reaching a stalemate. Therefore, this Court will closely
scrutinize the findings of the learned Arbitrator and see if they are
23/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
perverse or do suffer from patent illegality.
26. As observed supra, the respondent/claimant was running a
business and therefore, was the only contributor in so far as the
funds, sponsors and franchisees and all other dynamics for
conducting the league were concerned. On the other hand, the
petitioner was a facilitator and played an important role in terms of
being a powerful All India Body, which had the absolute control over
the volleyball sports and the players. In view of the same, as a
prudent businessman, the predominant motivation of the
respondent/claimant must be to earn profits.
27. Obviously, the responded/claimant is not getting into this
venture to suffer loss and in any case, if there is a loss, it is the
respondent/claimant, which will suffer the entire burden and not the
petitioner federation since the petitioner federation has been
guaranteed a minimum of Rs.1 Crore for a season with 10%
increment every year from seasons 2 to 10. A share from the net
profit will arise only when such 50% of the net profit is higher than
the minimum guarantee amount. Even in terms of expenses, it is
24/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
the respondent/claimant, which has to bear the cost of paying the
national and international players, referees, ground staff, cheer
leaders, refreshment of the petitioner’s core team (Ref. Clauses 3.4
and 3.5) and also to bear the cost of travel, lodging and food
(Clause 3.3). There is absolutely no outflow in terms of any
expenses for the petitioner federation and at the best, they will
always earn income and will never suffer a loss and the agreement
itself has been designed in that manner.
28. It must also be borne in mind that only season-1 was
complete and that all the steps were taken for commencing
season-2. Regular communications were happening between the
parties. However, the issue of share in the net profit seems to have
put spokes in proceeding further with the league. These facts must
be borne in mind by this Court while going into this issue.
29. The learned Arbitrator, on appreciation of evidence,
rendered a finding that some of the expenses shown and some of
the vouchers exhibited did not accord with proper detailing of
expenses. On considering the claim also, the learned Arbitrator
25/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
came to the conclusion that the petitioner federation was not
allowed any degree of control over the day to day functioning of the
respondent/claimant and its every item of expenditure.
30. Apart from that, the respondent/claimant was not
expected to submit the accounts of their day to day activities and
what was focussed by the learned Arbitrator was as to whether the
discrepancies that were found in terms of incurring expenses by the
respondent/claimant could be construed as manipulation of
accounts.
31. Unfortunately, in this case, the constitution of the Audit
Committee did not progress and at some stage, it became non
starter except for exchange of details, notes, etc. Many of the
answers that have been rendered by C.W.1 during the cross
examination did not form part of any of the communications that
took place between the parties.
32. The learned Arbitrator found that there was need for a
third party audit considering the scale of operation of the size of the
26/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
league involved. However, the discrepancies that were shown did
not satisfy the learned Arbitrator to conclude that there was
manipulation of accounts. Hence, the learned Arbitrator rightly
rendered a finding that if the petitioner federation was of the firm
belief that the accounts were manipulated and the share of profit
was not duly accounted for, there could have been no bar for the
petitioner to seek for the relief of rendering the accounts during the
proceedings by appointing an independent auditor or auditor firm. In
the absence of the same, the learned Arbitrator was not able to
expand the scope of inquiry.
33. The copious reasons given by the learned Arbitrator are
certainly possible views and just because this Court will be able to
take a different view based on the same set of materials, that will
not be a ground to interfere under Section 34 of the Act as the law
on this issue is too well settled. In view of the same, the findings
rendered by the learned Arbitrator on these issues do not
require the interference of this Court.
Issue Nos.16 and 19:
27/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
34. These issues pertained to delay in the one time payment
fees and the minimum guarantee amount and also the claim for
interest made by the petitioner federation.
35. The case of the petitioner federation was that the learned
Arbitrator erred in rendering a finding that there was no delay in the
one time payment fees and that the petitioner federation was
entitled to payment of interest.
36. The learned Arbitrator took into consideration the fact that
there was an obligation on the part of the petitioner federation to
raise invoices, that despite repeated requests made by the
respondent/claimant, the petitioner did not raise invoices and that
once the invoices were raised, payment was made promptly. The
learned Arbitrator also took into consideration the fact that the
invoices were needed for claiming GST refund. The learned
Arbitrator found that the obligation under Clause 3.3 of the
agreement has been complied with.
37. The finding of the learned Arbitrator is based on
28/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
appreciation of evidence and the relevant clauses and it does
not suffer from any perversity or patent illegality warranting
the interference of this Court.
Issue Nos.15, 18 and 17:
38. The above issues pertained to loss of reputation arising
from the termination of contract and damages/loss of profit claimed
by the petitioner federation.
39. The learned Arbitrator found that the loss of reputation
was in the realm of tort and not in contracts. Apart from that, there
was no loss of reputation involved in this case by virtue of the
termination of contract. Therefore, the claim made by both the
parties under this head was rejected.
40. In the considered view of this Court, this finding
rendered by the learned Arbitrator is perfectly in accordance
with law.
41. In so far as the damages and loss of profit claimed by the
petitioner federation were concerned, the learned Arbitrator rightly
29/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
found that the petitioner federation killed the goose that laid golden
eggs. The petitioner federation also had in their pocket Rs.2.5
Crores, which was the initial one time payment fee and Rs.1 Crore
as the minimum guarantee amount. Hence, the petitioner does not
suffer any loss and if at all there is any loss/damages, it is only
attributable to the attempt made by the respondent/claimant to
register their trademark and the logo in their favour. For that, a
notional damage of Rs.1 Crore was awarded apart from the relief of
injunction.
42. Therefore, the finding rendered by the learned
Arbitrator on these issues is also not liable to be interfered
by this Court.
Issue No.1:
43. This issue pertained to the validity of termination of the
contract effected by the petitioner federation.
44. The learned Arbitrator had already rendered a finding that
the non conduct of the league in 2018 including the Women’s
30/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
Volleyball League and the Beach Volleyball League did not constitute
breach of agreement. The agreement contemplated a particular
procedure under Clause 6.3 of the agreement for termination of the
agreement. The learned Arbitrator found that 15 days’ prior notice
was not given when Ex.C.19 notice was issued since only 7 days’
notice was given for rectifying the alleged breach.
45. In any case, Ex.C.19, by itself, did not bring about a
potential threat of termination of the agreement. Even
thereafter, various discussions were held and in fact, there
was a FIVB mediated meeting where even a draft addendum
had been drawn out and the commencement date for season
- 2 was also announced. Hence, Ex.C.19, at the best, can only
be construed as yet another communication that took place
between the parties and it cannot be certainly treated as a
notice of termination.
46. A curious ground was raised on the side of the petitioner
federation as if the involvement of the FIVB would also constitute
breach of Clause 8.
31/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
47. The learned Arbitrator rightly discarded this attempt
by rendering a finding that the FIVB was only attempting to
resolve the disputes in order to proceed to conduct season-2
of the league.
48. In so far as the trademark issue was concerned, the
learned Arbitrator rightly rendered a finding that Ex.C.19
would not come to the aid of the petitioner federation since it
was not in line with Clause 6.3.
49. As rightly contended on the side of the respondent/
claimant, there was ambiguity in the interpretation of the clauses
contained in the contract and even the learned Arbitrator used the
test of assessing for the so-called mischief in terms of trade mark
and copyright by claiming the ownership and found that this would
have had relevance only at the conclusion of all seasons. The
respondent/claimant was marketing and promoting the league and
was giving an interpretation that it included the name and logo that
were designed for conducting the league.
32/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
50. Therefore, the learned Arbitrator, by applying legal
precedents, found that there was no danger of the trade mark to be
misused or sold to any third party and the respondent/claimant was
not, in fact, trying to run away from the scene so as to cause any
damage to the petitioner, which could be construed as a breach of
the agreement.
51. In the light of the above discussions, this Court
holds that the finding rendered by the learned Arbitrator on
this issue does not suffer from any perversity or patent
illegality warranting the interference of this Court.
Issue Nos.12 to 14:
52. These issues pertained to assessing of loss of profit by
unlawful termination.
53. The learned Arbitrator already rendered a finding that the
termination of contract was not justified. Therefore, the learned
Arbitrator went into the issue of fixing the loss of profit due to
unlawful termination. Thereafter, the learned Arbitrator took into
33/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
consideration Ex.C.40 and gave the detailed estimate as to how the
projection of future revenue was made with the actual figures. While
undertaking this exercise, Ex.C.34 to Ex.C.39 were taken into
consideration. The learned Arbitrator, on appreciation of all the
materials, came to the conclusion that fixing a sum of Rs.4 Crores
under this head would be highly reasonable.
54. In so far as the loss of profit was concerned, I have held in
in the decision in M/s.State Industries Promotion Corporation
of Tamil Nadu Limited Vs. M/s.RPP Infra Projects Limited
[O.P.No.494 of 2018 dated 06.10.2025] that the Arbitrators are
permitted a leaway to employ an honest guesswork and a rough and
ready method for quantifying the damages. Proof of actual loss will
arise only where a claim is made for loss of profitability.
55. The learned Arbitrator rightly employed the correct
test by doing an honest guesswork based on the materials
while assessing the loss and the same does not require the
interference of this Court.
34/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
56. In so far as the interest component and costs were
concerned, the same have been properly granted while
dealing with issue Nos.22 to 24 and they do not require the
interference of this Court.
57. The upshot of the above discussions leads to the only
conclusion that the award dated 21.11.2020 passed by the learned
Arbitrator does not require the interference of this Court.
58. Accordingly, the above original petition stands dismissed
with costs of Rs.2,50,000/- (Rupees two lakhs and fifty
thousand only) payable by the petitioner to the respondent.
17.2.2026
RS
35/36 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.) No.175 of 2021
N.ANAND VENKATESH,J
RS
Arb.O.P.(Com.Div.) No.175 of 2021
17.2.2026
36/36 https://www.mhc.tn.gov.in/judis
Legal Notes
Add a Note....