As per case facts, the Delhi Development Authority (DDA) licensed a parking site to Kalwa on an 'as is where is' basis. Kalwa raised concerns about encroachments and lack of ...
FAO (COMM) 38/2026 Page 1 of 22
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Reserved on: 04.02.2026
Judgment pronounced on: 27.02.2026
Judgment uploaded on: As per digital signature~
+ FAO (COMM) 38/2026, CM APPL. 7629/2026, CM
APPL. 7630/2026, CM APPL. 7631/2026, CM APPL.
7632/2026
Delhi Development Authority ..... Appellant
Versus
Kalwa ..... Respondent
Advocates who appeared in this case
For the Appellant : Mr. Sanjay Vashishtha, Mr. Siddhartha
Goswami, Mr. Aditya Sachdeva and
Ms Geetanjali Reddy, Advocates
For the Respondent : Mr. Sunil Dutt Dixit and Ms Gauri
Dixit, Advocates
CORAM:
HON'BLE MR. JUSTICE DINESH MEHTA
HON'BLE MR. JUSTICE VINOD KUMAR
JUDGMENT
VINOD KUMAR, J.
1. This appeal under Section 37 of the Arbitration and
Conciliation Act, 1996 (hereinafter ‘the Act’) is directed against
a judgment dated 31.10.2025 passed by the learned District
Judge-02, Central District, Tis Hazari, Delhi (in short ‘District
Judge’) in ARBTN A.(Comm.)No.33/2019, vide which he
FAO (COMM) 38/2026 Page 2 of 22
dismissed the objections under Section 34 of the Act filed by the
appellant-DDA under Section 34 of the Act challenging the
Award dated 20.05.2014 adjudicated by the sole Arbitrator. For
the sake of convenience, the appellant would also be referred to
as ‘DDA’ and respondent would also be referred to as
‘Claimant’.
DISPUTE
2. The respondent is engaged in the business of running
parking sites at various places in NCT of Delhi. In a parking
tender process for Truck Parking site at Majnu ka Tila, Timarpur,
Delhi (hereinafter referred to as „the parking site‟), the
appellant-DDA declared the respondent as the highest bidder and
consequently issued an allotment letter bearing No.
F.99/11/2010/LPC/Parking/699 dated 26.03.2010 at a monthly
license fee of Rs.5,11,000/- for a contract period of three years
and directed the respondent to comply with the terms and
conditions in the aforesaid allotment letter. The respondent had
already deposited two months’ license fee as ‘earnest money’ at
the time of submitting tender. He communicated his acceptance
vide letter dated 29.03.2010 and also deposited advance license
fee of three months i.e. Rs.15,33,000/- adjustable only against the
last three months of the contract period as per the terms of the
allotment letter. The abovementioned acceptance letter is
reproduced as below:
FAO (COMM) 38/2026 Page 3 of 22
“To,
Dated 29.03.2010
The Assistant Director,
Delhi Development Authority,
Vikas Sadan, INA,
Delhi.
Subject:-Truck Parking Site Majnu Ka Tila.
Reference:- Your letter no: F 99(11)
2010/LPC/Parking/699
Dated 26.03.2010.
Sir,
With thanks, I am in receipt of your said letter no: F
99(11)2010/LPC/Parking/699 dated 26.03.2010 whereby
you have called upon to fulfill the following requirements.
Please find enclosed the following documents as required
by you in your above acceptance letter as under:-
1. Three months license fee of Rs. 15,33,000/- vide challan
no 6149 dt: 27.03.2010 deposited in SBI, Vikas Sadan,
New Delhi.
2. Acceptance of Terms and Conditions on Non-Judicial
stamp paper of Rs.10/- duly attested by Notary Public
bearing no: 33 AA 567730.
3. License deed on a non judicial stamp paper of Rs.100/-
duly attested by Notary Public for three years bearing no:
К 808327.
4. Four specimen signature duly attested by Gazzetted
officer.
5. Four passport size photograph attested by Gazzelted
officer.
6. P/C of election I-Card duly attested by Gazzetted
Officer.
Sir, after visiting at parking site, I observed that there is
no in and out gate provided at the parking site for smooth
and proper exist and entrance of tine vehicles besides the
parking site is not been categorically demarcated and
fenced. No boundary wall constructed covering the
parking area and because of above reasons the safety of
vehicles parked in the parking area are at high risk and is
an open invitation for the anti-social elements who could
easily steal the vehicle, belongings etc. from the parking
zone.
It is further observed that the substantial area of the
parking are encroached by local shop keepers, Rehri
walas, hawkers who are operating illegally from the
parking sites besides that there is permanent sort of
FAO (COMM) 38/2026 Page 4 of 22
fixtures installed by food vendors, motor mechanics,
repairing works, mistries etc. also covered substantial
portion of the parking area: In addition to above, the
peoples residing in vicinity also occupied by the parking
site and using the parking site unauthorizedly and illegally
without payment for their vehicles and in this way,
approximately more than 40% area of the parking site are
under illegal and unlawful coverage by the unauthorized
persons. I put my bid for the parking site keeping in view
that the size of the area described to me could easily
utilized for parking above 700 and more truck vehicles but
in the present scenario, the available space is not more
than 400-450 vehicles.
In view of the above facts, I humbly request you to get the
entire area vacated from the unauthorized and illegal
occupancy and provide me 100% area allotted and
advertised for parking purposes, so that I could use the
100% area of the parking site.
You're prompt action would be highly appreciated.
Yours sincerely
Kawla
Parking Contractor”
3. The respondent in its aforementioned acceptance letter
requested for removal of all the unauthorised occupancy/
encroachments and other hurdles and for construction of
boundary wall and providing lights and handing over 100%
possession of the parking site. The case of the respondent is that
vide above reproduced letter, he had apprised DDA about the fact
that the parking site could only hold 400-450 trucks, whereas as
per the description provided to him, the parking site could be
easily utilised for 700 and more trucks. The respondent claims
that the parking site was handed over to the respondent on
05.04.2010 with the verbal assurance from the officials of DDA
of removing unauthorised and illegal occupancy so also carrying
out necessary repairs, light facility, raising boundary walls etc.
FAO (COMM) 38/2026 Page 5 of 22
4. Aggrieved by the non-action of DDA in removing of
encroachments etc., the respondent approached Vice Chairman of
DDA via letter dated 30.04.2010 and for the first time requested
appointment of Arbitrator in terms of the Agreement for
adjudication of dispute. Acknowledging the request of the
respondent, the appellant-DDA reverted via letter dated
01.05.2010, which is reproduced as below:
“OFFICE OF THE EXECUTIVE ENGINEER
NORTHERN DIVISION NO.III/DDA OPP: REM DEPT.
GTB NAGAR; DELHI, 9
F. 7 (10) AE (P) / ND-3/DDA/540
DT.1/5/2010
To
Shri Kalwa
Parking Contractor,
808, Karma Bangash
Chandani Mehal
Darya Ganj, Delhi
Sub; Allotment of Parking at Truck Parking, Tiram Pur
Ref: No: Nil dated 6.4.2010
Dear
With reference to your letter dt.4.4.2010, the parawise
reply is as under:-
As per parking area made by Delhi metro Corporation
and handed over to DDA. As per drawing only one No.
gate has been shown for entry and out. As per drawing
there is no, gate has been shown for entry and out. As par
drawing there is no space for out gate. So it is not possible
regarding boundary wall, the parking and could not be
covered with boundary wall because there are lot of shop
on both sides adjoining parking area and vehiclas can
take tum easily you have taken the parking tenders so
safety of vehiclas falls under you.
Regarding encroachment of parking area it has been seen
and found that there is no any encroachment in the
parking area. Some Khomcha people comes in the
FAO (COMM) 38/2026 Page 6 of 22
morning and goes in the evening. You observed that the
people residing in vicinity also occupied by the parking
site but it has been found that their vehicles are in the
service lane and you are also parking the vehiclas in this
s/L area.
The A.E. concerned inspected the site and it has been
found that about 400 nos. vehicls were park in the parking
area No.1 to and other parking No.9, 10, and 11 were
vacant and it has also been found that you are using the
vacant land of DDA on parking in future DDA land may
not be used as parking.
Before you previous parking contractor has not raised any
observations neither he has forced any problems. However
safety of vehicles and to provide the security man for
watch and ward falls under your jurisdiction so DDA with
not be responsible for any theft. However, the tender for
C/o boundary wall and gate has been called and work
will start shortly.
Sd/-
(Executive Engineer
ND-3/DDA”
5. The respondent again wrote letters dated 05.05.2010 and
07.05.2010 reiterating his grievances alleging that he was
suffering a loss of Rs.12000/- per day due to appellant-DDA’s
failure to take remedial steps.
6. Meanwhile appellant-DDA invited fresh tender by means
of advertisement dated 27.02.2011 in respect of the parking site
in the mid of tenure with the respondent. Consequently, the
respondent moved to the High Court by filing a petition (O.M.P.
No. 235/2011) under Section 9 of the Act seeking interim relief
to prevent DDA from fresh allotment to third party. Vide order
dated 28.03.2011, learned Single Judge of this Court passed an
interim order directing postponement of the proposed auction of
FAO (COMM) 38/2026 Page 7 of 22
the parking site. Subsequently, by order dated 21.09.2011, the
learned Single Judge extended the said interim protection and
directed that the stay shall continue during the pendency of the
arbitral proceedings or until 04.04.2013, whichever event
occurred earlier so long as Claimant-Kalwa complied with court
direction of payment of monthly fee.
APPOINTMENT OF ARBITRATOR
7. The respondent preferred a petition (Arbitration Petition
No.80/2011) under Section 11 of the Act praying for appointment
of Arbitrator. A coordinate Bench of this court vide order dated
09.08.2011 directed the following:
“Strictly speaking, the respondent is correct in contending
that a petition under Section 11 would not be maintainable
in these circumstances, as the arbitration agreement
contains a named arbitrator. However, the matter does not
rest there. The petitioner invoked the arbitration
agreement as early as in May 2010 by addressing a notice
to the Vice Chairman, DDA, who is the named arbitrator.
Despite the said notice, the arbitrator has failed to enter
upon reference. It is a clear case where the arbitrator has
failed to lect without undue delay, as sufficient time has
gone by. Accordingly, the mandate of the learned
arbitrator stands terminated.
The present petition ought to have been styled as one
under Section 14 and 15 of the Act. However, in the facts
and circumstances of the case, I am inclined to treat the
present petition as one filed under Section 14 and 15 of
the Act. It is clear that disputes have indeed arisen
between the parties which are live and are to be resolved
through arbitration.
In view of the aforesaid facts and circumstances, I allow
the petition and appoint Mr. A.P.S. Gambhir, Advocate
(Mobile No.9999983935) as the sole arbitrator to
adjudicate all the claims and counter claims of the parties.
The fee of the learned arbitrator shall be paid in
accordance with the schedule of fee prescribed under the
FAO (COMM) 38/2026 Page 8 of 22
rules of the Delhi High Court Arbitration Centre.
Petition stands disposed”
In view of his order, the arbitration proceedings with the
appointed arbitrator commenced.
STATEMENT OF CLAIM
8. On the basis of facts already narrated, the respondent-
claimant raised the following claims before the Arbitrator:
A. Refund of license fee paid in excess
from 05.04.2010 to till date @ 40% as
the area is not operational and lying
under encroachments and obstructions
etc.
Rs.38,01,840/-
B. Compensation towards operational loss
@ Rs.12,000/- per day
Rs.61,56,000/-
C. Reimbursement of expenses incurred by
the claimant on creation of infrastructure
for running the parking site for the
agreed period of three years
Rs.1,00,000/-
D. Compensation for the mental
torture/agony and physical harassment
suffered by the claimant due to the
inaction of the respondent on his
bonafide requests.
Rs.1,00,000/-
E. Litigation expenses incurred and to be
incurred
Rs.1,00,000/-
F. Refund of Security deposit amount and
advance amount towards license fee
lying in deposit
Rs.10,22,000/-
G. Pendente lite and future interest @ 18%
per annum on the claimed amount from
the date of filing of the arbitration
petition till the realization of the claim
-
FAO (COMM) 38/2026 Page 9 of 22
TOTAL Rs.1,12,79,840/-
STATEMENT OF DEFENCE
9. The DDA, in its Statement of Defence, averred that
possession of the site had been handed over to the claimant–
Kalwa on 05.04.2010 on an ‘as is where is’ basis as per Clause
17 of the agreement. It was thus contended that the claimant–
Kalwa was presumed to be aware of the condition of the parking
site for trucks as per the said clause. It was stated that
once possession was handed over to the Claimant–Kalwa, no
cause or dispute survived for appointment of an arbitrator under
Clause 24 of the agreement.
10. The DDA denied that its letter dated 01.05.2010 amounted
to any admission of problems at the parking site and asserted, on
the contrary, that there was no encroachment on the site, which
was lying vacant. It was further contended that it was the
responsibility of the claimant–Kalwa to check and safeguard
against the menace of theft before commencement of business
and that the DDA could not be held liable for the same.
ARBITRAL PROCEEDINGS AND THE AWARD
11. The Arbitrator after considering the pleadings of the
parties framed the following issues:
“Whether the claimant is entitled to:
FAO (COMM) 38/2026 Page 10 of 22
(i) Refund of excess license fee being Rs.38,01,840/-;
(ii) Compensation towards operational loss being
Rs.61,56,000/-;
(iii) Reimbursement of expenses incurred on creation of
infrastructure by the claimants being Rs.1,00,000/-;
(iv) Compensation for mental torture/agony and
physical harassment suffered by the claimant being
Rs. 1,00,000/-;
(v) Litigation expenses incurred by the claimant being
Rs.1,00,000/-;
(vi) Refund of security deposit being Rs.10,22,000/-;
(vii) Pendente-lite and future interest @18% on the
aforesaid claim;
(viii) Relief.”
12. The parties led their respective evidences before the
Arbitrator. After hearing the parties, the Arbitrator concluded that
photographic evidence showed the true circumstances of the
property site. Exhibit CW-1/19 (which contained 159
photographs of the situation at the parking site) and testimonies
of the witnesses proved the case of the Claimant regarding
encroachments on the site. Additionally, a conjoint reading of the
letters dated 01.05.2010 and 03.05.2010 proved that the DDA
was convinced that there were encroachments on the parking site
and had also promised to construct boundary wall and a gate at
parking site for the proper utilisation of the area of the parking
site. The learned Sole Arbitrator, upon appreciation of the
pleadings and evidence on record, held that owing to substantial
encroachment upon the parking site, the claimant was unable to
utilize the full capacity of the parking area. It was accordingly
held that the claimant was entitled to a proportionate refund of
licence fee. The Arbitrator determined that licence fee had been
FAO (COMM) 38/2026 Page 11 of 22
paid for a period of 18 months, i.e., from 05.04.2010 to
05.10.2011, amounting to Rs. 95,04,600/- and awarded 40
percent thereof, i.e., Rs. 38,01,840/-. The claim towards
operational loss was also partly allowed, awarding a sum of Rs.
32,88,000/-. Additionally, the Arbitrator awarded litigation
expenses of Rs.60,000/- and directed refund of the security
deposit of Rs.10,22,000/-. The awarded amounts were directed to
carry pendente lite and future interest at 9 percent per annum
from the date of filing of the claim petition until realization.
13. The arbitrator also delved into the issue of interpretation of
‘as is where is’ clause, as encapsulated in clause 17 of the
agreement. It would be apposite to reproduce his opinion as
under:
“Though the learned counsel for the respondent
emphasised that the site was allotted on „as is where is‟
basis and also cited the judgments (supra) in favour of his
submissions. But the judgments cited by the learned
counsel for the respondent are distinguishable on facts.
First of all, the claimant was only a licencee with very
limited right to slow the parking of vehicles while in the
judgment cited, the respondent therein was a lessee of the
land having wider rights. Since, as a lessee could
approach different govt. departments for redressal of his
grievances like provisions for parking. lights, water,
sewage, roads etc. Moreover, parking, lights, water,
sewage, road etc. are additional facilities for the plot of
the respondent while the plot itself is intact. In the present
case, the biggest problem faced by the licencee (claimant)
was that the parking site allotted to him was not intact.
Even if, additional facilities were not provided was not a
question of much consequence in the present case.
Moreover, the respondent-DDA in the present case had
promised to construct a boundary wall and a gate and had
also promised to remove the encroachment as the conjoint
FAO (COMM) 38/2026 Page 12 of 22
reading of its letters dated 01.05.2010 and 03.05.2010
(Exhibit CW-1/8 & CW1/43) reveals. Therefore, the
judgment cited by the learned counsel for respondent do
not serve the desired purpose.”
14. The Arbitrator awarded the following relief as under:
(i) Refund of Licence fee paid in
excess
Rs. 38,01,840/-
(ii) Compensation for Operation Loss Rs. 32,88,000/-
(iii) Litigation Expense Rs. 60,000/-
(iv) Refund of Security Deposit
Amount
Rs. 10,22,000/-
Total: Rs. 81,71,840/-
The Arbitrator also awarded pendente lite and future interest at
the rate of 9 percent per annum on the aforesaid awarded amount
from the date of filing arbitration petition i.e. 03.11.2011 till
realization of the said amount.
IMPUGNED JUDGMENT
15. The DDA challenged the said award before learned
District Judge by filing objections under Section 34 of the Act.
While first dealing with the scope of Section 34 of the act, the
learned District Judge reiterated the settled position of law that
courts are not permitted to re-appreciate evidence or review
arbitral award on merits as the scope of judicial interference is
FAO (COMM) 38/2026 Page 13 of 22
narrow and confined to the grounds as illustrated in section
34(2) and 34(2A), which include jurisdictional errors, violation
of public policy, patent illegality apparent on the face of the
award, or perversity of such nature as to shock the conscience of
the Court. It was further opined that errors of fact, the existence
of alternative or possible interpretations, or mere dissatisfaction
with the reasoning adopted by the arbitral tribunal do not
constitute valid grounds for interference under Section 34 of the
Act.
16. On the issue of encroachment, the court found that there
were substantial encroachments upon the parking site. Learned
District Judge agreed with the Arbitrator on the issue of
encroachment and noted that the Respondent-Kalwa had also
placed photographs of the parking site on record. A letter dated
01.05.2010 by the appellant DDA was taken as admission of
encroachment and of promise by DDA that work for construction
of the wall would commence shortly. The Court noted that
the Appellant-DDA did not lead any evidence before the
arbitrator to rebut these facts. Consequently, the arbitrator’s
findings were held to be based on evidence, which could not be
characterised as perverse or arbitrary.
17. However, learned District Judge was quite cryptic while
dealing with the issue of ‘as is where is’ clause. Relevant portion
of impugned judgment is reproduced as under:
“37. Not only this, but it has also been contended that the
Ld. Arbitrator effectively changed the terms of the
FAO (COMM) 38/2026 Page 14 of 22
Contract while interpreting it and ordered the refund of
60% of the license fees on the grounds of operation loss
and granted compensation for loss of business. The
respondent was under an obligation to accept the parking
site on an „as is where it is‟ basis”, then so the Ld.
Arbitrator should have not given any compensation to the
respondent for alleged loss or encroachment.
………………………………”
18. After noting the submissions of ‘as is where is’ as raised
by DDA, learned District Judge, instead of dealing it, read the
judgment of Associated Builders vs. DDA (2015) 3 SCC 49 to
emphasize that the arbitrator is the sole judge of the quantity and
quality of evidence. Once it is shown that the arbitrator has
considered the material on record and adopted a reasoned view,
the Court cannot interfere merely because another view is
possible. Accordingly, the petition under Section 34 was
dismissed and the arbitral award was upheld in its entirety.
ANALYSIS OF SUBMISSIONS OF PARTIES IN THIS
APPEAL UNDER SECTION 37
19. Aggrieved by the impugned award and the impugned
judgment, DDA preferred this appeal under Section 37 of the
Act. The primary submission of the Learned counsel for
appellant-DDA is that the license was admittedly granted on ‘as
is where is basis’. Clause 17 of the Agreement expressly
mentions the obligation of the respondent-claimant to have
inspected the site and satisfied himself as to all prevailing
conditions prior to submission of the bid.
FAO (COMM) 38/2026 Page 15 of 22
20. The learned counsel for appellant-DDA further contended
that neither the Notice Inviting Tender (NIT) nor the Agreement
specified any minimum parking capacity or number of vehicles.
The respondent-claimant’s assertion that the site ought to
accommodate approximately 700 vehicles was wholly unilateral
and unsupported by any contractual representation. While
assailing the impugned award, the learned counsel for the
respondent argued that while raising the objections of
encroachment, the respondent-claimant still accepted the
allotment via acceptance letter dated 29.03.2010. Moreover, he
deposited the requisite amounts, executed the Agreement, and
took physical possession of the site on 05.04.2010.
21. The learned counsel for the appellant-DDA submitted that
having done so after inspection and with full knowledge of the
site conditions, the respondent-claimant cannot raise any claim
on the ground of encroachment or capacity of the parking site.
22. Learned Counsel for the appellant argued that the term ‘as
is where is’ means the status of the plot in respect of condition
and amenities of the plot and that the issues of encroachment and
boundary wall, single door entry were not part of terms of the
contract. It was argued that when the respondent had accepted
and taken the possession of the site, it would not matter in what
condition the parking site lay.
FAO (COMM) 38/2026 Page 16 of 22
23. Per contra, it is argued by the learned Counsel for the
respondent that had the respondent got complete vacant plot, he
had no right to complain about condition of such a plot and
therefore any claim of respondent for encroachment, boundary
and lack of amenities like road, water, street light etc. would have
been barred under Clause 17. But here the situation is that DDA
did not deliver completely vacant plot. This is the reason that
while accepting the terms and conditions, the respondent raised
the issue of encroachment with DDA vide letter dated
29.03.2020. It is submitted that infact it was orally assured that
DDA would remove such encroachments and raise boundary wall
and open up one more gate so that the respondent is able to use
the parking site efficiently.
24. It is further argued by learned Counsel for respondent that
Sh. Naresh Maheshwari, employee-Manager of the company, in
his evidence as CW2, has testified to this effect in para 6 of his
evidence affidavit before the Arbitrator where that the claimant
had accepted possession of parking site on verbal assurance of
officials to remove unauthorised and illegal occupation at parking
site. It is submitted that this version is corroborated by letter
dated 01.05.2020 of DDA addressed to respondent, which
reflects that DDA owed a responsibility to remove
encroachments and raise boundary walls. Therefore, it is
submitted that clause 17 ‘as is where is’ basis means that the
status of plot after removing the encroachment. Accordingly the
FAO (COMM) 38/2026 Page 17 of 22
learned Counsel for the respondent supported the impugned
award and the view of the Arbitrator on this issue.
25. We have considered the rival submissions. The only issue
which required our consideration is as to whether the view of the
Arbitrator and the learned District Judge on ‘as is where is’
clause 17 is perverse and suffers from patent illegality.
26. The Supreme Court of India had the opportunity to
consider ‘as is where is basis’ clause in the judgment of K.C.
Ninan vs Kerela State Electricity Board ,
MANU/SC/0604/2023, while observing that:
“138. Thus, the implication of the expression „as is where
is‟ or "as is what is basis" or "as is where is, whatever
there is and without recourse basis" is not limited to the
physical condition of the property, but extends to the
condition of the title of the property and the extent and
state of whatever claims, rights and dues affect the
property, unless stated otherwise in the contract. The
implication of the expression is that every intending bidder
is put on notice that the seller does not undertake any
responsibility to procure permission in respect of the
property offered for sale or any liability for the payment of
dues, like water/service charges, electricity dues for power
connection and taxes of the local authorities, among
others.
xxxxxxx
141. To conclude, all prospective auction purchasers are
put on notice of the liability to pay the pending dues when
an appropriate „as is where is‟ clause is incorporated in
the auction sale agreement. It is for the intending auction
purchaser to satisfy themselves in all respects about
circumstances such as title, encumbrances and pending
statutory dues in respect of the property they propose to
FAO (COMM) 38/2026 Page 18 of 22
purchase. In a public auction sale, auction purchasers
have the opportunity to inspect the premises and ascertain
the facilities available, including whether electricity is
supplied to the premises. Information about the
disconnection of power is easily discoverable with due
diligence, which puts a prudent auction purchaser on a
reasonable enquiry about the reasons for the
disconnection. When electricity supply to a premises has
been disconnected, it would be impossible for the
purchaser to assert that they were oblivious of the
existence of outstanding electricity dues.
142. In terms of the legal doctrine of caveat emptor, it
becomes the duty of the buyer to exercise due diligence. A
seller is not under an obligation to disclose patent defects
of which a buyer has actual or constructive notice in terms
of Section 3 of the Transfer of Property Act, 1882.
However, in terms of Section 55(1)(a), in the absence of a
contract to the contrary, the seller is under an obligation
to disclose material defects in the property or in the
seller‟s title thereto of which he is aware and which a
buyer could not with ordinary care discover for himself.
143. While examining the effect of an „as is where is‟
clause, the facts and circumstances of each case
individually, along with the terminology of the clauses
governing the auction sales must be taken into
consideration, to arrive at an equitable decision.”
27. The spirit of the above judgment is that when a tender
process is initiated, the contractor has the opportunity to inspect
the condition of the land/property and only after inspecting it,
they are required to make a bid.
28. We would also like to refer to a judgment of this Court in
S.K. Pandey Vs. MCD and Ors , MANU/DE/0143/2012,
wherein a similar dispute was under consideration. The Parking
FAO (COMM) 38/2026 Page 19 of 22
site was allotted to the tenderer on ‘as is where is’ basis by MCD.
The tenderer alleged that there was 60 percent encroachment on
the total area of parking space allotted to him. It was held that:
“15. The parking site in question in commercial site and
the petitioner accepted the terms and conditions of the
letter of offer. The terms and conditions of the contract
agreement stipulated that the parking site has been given
an “As is where is basis”. Thus, no dispute can be raised
by the petitioner with regard to any loss or damage as the
other was accepted by the petitioner with open eyes”
29. Now let us apply the ratio of the aforesaid judgments to the
facts of this case. For this purpose, we deem it necessary to
reproduce Clause 17 of the Agreement executed between the
parties as under:
“The parking site is being tendered on "As is where is
Basis". It is presumed that the intending tenderer has
inspected the parking site and familiarized himself/herself
with the prevailing conditions in all respect before
submitting the tender. No claim/dispute above
condition/capacity of the parking site shall be entertained
by DDA. The tenderer cannot put any condition with
his/her tender.”
30. This clause itself makes it clear that the intending tenderer
had not only the duty of inspecting the site but also familiarizing
himself/herself with prevailing conditions in all respects. In
this respect we would like to refer to the evidence of CW1
tendered as below:
“Question: There is a condition in the license deed 1(vii),
which states that when you file a tender, before that you
need to inspect that area and then on that basis quote your
bid. So did you do that and inspect the site?
Answer: Yes, I filed the tender only after the inspection of
the site.
FAO (COMM) 38/2026 Page 20 of 22
Question: There is another condition in the licence deed
which is condition no.18 stating that the sites are given in
„as is where is basis‟, it will be handed over in the exact
position, were you aware of such a condition?
Answer: Yes. I was aware of the terms and conditions.”
31. We are fully cognizant of the fact that the courts cannot
appreciate or re-appreciate the evidence. But when the question
of patent illegality and perversity has been raised, the courts are
fully entitled to look into such evidence, of course, without
interpreting and analysing the same. The aforesaid portion of
evidence is enough to show that before tendering the bid, the
respondent was very much aware of encroachments on the
parking site.
32. If the view of the Arbitrator on the ‘as is where is’ clause,
which has already been reproduced, is accepted, it would be
highly prejudicial to those persons who refrained themselves
from raising the bid on seeing the encroachments on the site. The
evidence of respondent to the effect that he was assured by some
officials of DDA and that they would remove the encroachments
cannot be accepted as there is nothing in the contract to that
effect. In the matters of tenders, no oral assurance can be read
into unless it is specifically mentioned in the contract. Such
exercise would seriously and adversely affect the interest of the
contractors who refrained from bidding in the view of existing
condition of the parking site. Had they known of any such
assurance, they could also have considered the option of raising a
FAO (COMM) 38/2026 Page 21 of 22
bid. Such assurance would actually result in change in terms and
conditions of the contract.
33. Such change of conditions of tender, after its acceptance, is
in conflict with public policy of law because it would adversely
prejudice the rights of those who would have made a bid, had
some assurance of removal of encroachments been in their
knowledge. Therefore, the interpretation of ‘as is where is’ clause
by the Arbitrator is absolutely perverse and suffers from patent
illegality. Accordingly, the award of refund of excess license fee
and compensation on account of operation loss against Claims
‘A’ and ‘B’ respectively, which is based upon patently illegal
interpretation of ‘as is where is’ clause, is hereby set aside.
34. The Arbitrator has directed refund of security deposit
amounting to Rs.10,22,000/- against Claim ‘F’. Though the grant
of security deposit has also been challenged, but during
arguments nothing was brought to the notice of this court
showing that the respondent was not entitled to its refund. Hence,
this part of Award is upheld.
35. The appellant has challenged the grant of interest on the
ground that it was awarded without reference to contractual
stipulations or governing principles. Perusal of the statement of
claims shows that respondent made Claim ‘G’ for pendente lite
and future interest at the rate of 18 percent per annum from the
date of filing of arbitration petition i.e. 03.11.2011 till the
realisation. We find that Arbitrator has awarded reasonable
FAO (COMM) 38/2026 Page 22 of 22
interest at the rate of 9 percent from the date of filing of
arbitration petition till realisation. We are of the opinion that
there is no patent illegality or perversity in the same, though such
interest has to be awarded only on the award of security deposit
amount of Rs.10,22,000/- and the litigation fee of Rs.60,000/-
which has now been upheld by this court as above. The issue of
grant of litigation fee as awarded by the Arbitrator against Claim
‘E’ remains unchallenged. We also find no infirmity in the same
being reasonable.
36. Consequently, we hold that the respondent is only entitled
to claim of security deposit of Rs.10,22,000/- as well as litigation
expenses amounting to Rs.60,000/- along with interest at the rate
of 9 percent per annum from 03.11.2011 till realisation.
37. Accordingly, we set aside the impugned award and
impugned judgment to the extent as discussed above.
38. Appeal is accordingly partly allowed.
39. Pending applications stand disposed of.
VINOD KUMAR, J
DINESH MEHTA, J
FEBRUARY 27, 2026
vb
Legal Notes
Add a Note....